ADN Resource Management Pty Ltd v The Council of Camden [2025] NSWLEC 1312
Catchwords: DEVELOPMENT APPLICATION: – conciliation conference – agreement between parties - orders
Land and Environment Court
New South Wales
Medium Neutral Citation:
ADN Resource Management Pty Ltd v The Council of Camden [2025] NSWLEC 1312
Hearing dates:
Conciliation conference on 29 April 2025
Date of orders:
08 May 2025
Decision date:
08 May 2025
Jurisdiction:
Class 1
Before:
Coetzee AC
Decision:
The Court orders that:
(1) The Appeal is upheld.
(2) Development consent is granted to Development Application No. DA/2024/537/1 (as amended) for the construction and use of a landscape material supply facility with associated works, on land legally described as Lot 25 in Deposited Plan 1222679 and known as 1110 The Northern Road, Bringelly NSW, subject to the conditions at Annexure A.
(3) The Applicant is to pay the Respondent's costs thrown away pursuant to s
8.15(3) of the
Environmental Planning and Assessment Act 1979
in the
agreed
sum of
( $3,500 ) , payable within 14 days.
Catchwords:
DEVELOPMENT
APPLICATION: –
conciliation conference – agreement between parties - orders
Legislation Cited:
Environmental Planning and Assessment Act 1979 , ss 4.16,
8.7, 8.15 ,
Div 4.8
Land and Environment Court Act 1979 , s 34 ,
Water Management Act 2000 , s
91
Camden
Local Environmental Plan 20 10 cll 2.3, 2.7, 4.3, 5.21, 6.2, 7.4
Environmental Planning and Assessment Regulation 2021, ss
38
State Environmental Planning Policy (Biodiversity and Conservation) 2021,
Ch 6
State Environmental Planning Policy (Resilience and Hazards) 2021,
ss 4.6
State Environmental Planning Policy (Transport and Infrastructure) 2021, s
2.119
Texts Cited:
Camden Council’s Community Participation Plan 2021
Category:
Principal judgment
Parties:
ADN Resource Management Pty Ltd (Applicant)
Council of Camden (Respondent)
Representation:
Counsel:
P Smith (Applicant)
K Huxley (Solicitor) (Respondent)
Solicitors:
Miller Prince (Applicant)
Holding Redlich (Respondent)
File Number(s):
2024/00481450
Publication restriction:
Nil
Judgment
COMMISSIONER
: This class 1 appeal is brought under s 8.7 of the
Environmental Planning and Assessment Act 1979
(EPA Act)
following the deemed refusal by
the
Council
of Camden
of development application DA /2024/537/1
(the DA)
seeking consent for
the construction and use of a landscape material supply facility with associated works, on land legally described as Lot 25 in Deposited Plan 1222679 and known as 1110 The Northern Road, Bringelly NSW .
The Court arranged a conciliation conference under s 34(1) of the
Land and Environment Court Act 1979
(LEC Act) between the parties, at which I presided on
29 April 2025 .
Prior to the
conciliation conference, the parties reached agreement .
This
agreement between the parties involves
the Court upholding the appeal and granting development consent to the development application subject to
those agreed
conditions
of consent.
A signed agreement prepared in accordance with s 34 (10) of the LEC Act was filed with the Court on 2 9 April 2025 .
The Respondent, as the relevant consent authority, has approved under s 38(1) of the
Environmental Planning and Assessment Regulation 2021 , to the Applicant amending Development Application DA/2024/537/1 in accordance with the following amended plans
(Amended Development Application Documents):
Drawing No and Revision
Title
Prepared by
Date
Architectural Plans
1.
Drawing No. 01, Revision F
Site Plan
AJ Design & Draft
15 April 2025
Drawing No. 02, Revision F
Floor Plan
Drawing No. 03, Revision F
Elevations
Drawing No. 04, Revision F
Section A-A
Landscape Plans
2.
Drawing No. 24083 DA 1 - 2, Revision C
Legend/Details/Plant Schedule
Vision Dynamics Pty Ltd
22 April 2025
Drawing No. 24083 DA 2 - 2, Revision C
Landscape Concept Plan – Ground Floor
Engineering Plans
3.
Drawing No. D00, Revision E
Cover Sheet, Legend & Drawing Schedule
Amity Engineers
19 April 2025
Drawing No. D01, Revision E
General Notes
Drawing No. D05, Revision E
Cut and Fill Plan
Drawing No. D10, Revision E
Stormwater Drainage Plan – Ground Floor
Drawing No. D12, Revision E
Site Catchment Plan – Pre vs Post Development
Drawing No. D20, Revision E
Stormwater Drainage Details
Wastewater Plans
4.
Drawing No. 3964-WW, Revision A-04
On-Site Wastewater Management Plan
Broadcrest Environmental Pty Ltd
17 April 2025
Reports
5.
Traffic Letter of Response
McLaren Traffic Engineering
16 April 2025
6.
On-site Wastewater Report
Broadcrest Environmental Pty Ltd
17 April 2025
7.
Flood Risk Management
Amity Engineers
19 April 2025
8.
Arboricultural Letter of Response
Urban Forestry Australia
22 April 2025
9.
Detailed Site Investigation
Foundation Earth Sciences
10 February 2025
10.
Tuflow Flood Model
Amity Engineers
-
The parties ask me to approve their decision as set out in the s34 agreement before the Court. In general terms, the agreement approves the development subject to amended plans that were prepared by the
Applicant and
the agreed conditions of development consent annexed to the s34 agreement.
Under s 34(3) of the LEC Act, I must dispose of the proceedings in accordance with the parties ’
decision if the parties ’
decision is a decision that the Court could have made in the proper exercise of its functions. The parties ’
decision involves the Court exercising power under s 4.16 of the EPA Act. In this case, there are jurisdictional prerequisites that must be satisfied before this function can be exercised. The parties explained to me during the conference as to how the jurisdictional prerequisites have been satisfied in order to allow the Court to
make the agreed orders at [ 20 ] .
Jurisdictional
pre requisites
The site is owned by the Applicant.
The Court notes
that the DA was lodged by Ammar Group Pty Limited, on 25 October 2024, however as a result of a change of company name from Ammar Group Pty Limited on 30 September 2024, this company is now called ADN Resource Management Pty Limited (Applicant).
The DA was notified in accordance with the Camden Council ’ s Community Participation Plan 2021 (CCPP) between 30 October 2024 and 3 December 2024. No submissions were received during the notification period.
The Respondent does not consider that the Application as amended requires renotification under part 3.3 of the CCPP.
Camden Local Environmental Plan 2010
The site is zoned
RU4 Primary Production Small Lots under the Camden Local Environmental Plan 2010 (CLEP). The DA seeks consent for the construction and use of a landscape material supply facility which is permissible with consent use on RU4 Primary
Production
Small Lots ,
and
in accordance with
c l 2.3
of the CLEP ,
I have had regard ed
the objectives of the zone .
The parties agree and I accept that the following applicable provisions
under the CLEP
are met:
Cl ause
2.7 demolition works are permissible with consent
Cl ause
4.3
Height of Buildings
prescribes a maximum permitted height of building limit of 9.5m for the Site . The proposed development has a maximum height of approximately 7.7m and complies with this development standard.
Cl ause
5.2 1 Flood Planning applies to the site
is identified as being within a flood planning area. A Flood Risk Management Plan has been provided by the Applicant by Amity
Engineers dated 19 April 2025.
Pursuant to Cl 5.21(2) (a) to (e) ,
the parties agree that
proposed development complies.
Cl ause
6.2 Public Utility Infrastructure
the parties confirm that the
public utility infrastructure that is essential for the proposed development is available.
Cl ause
7.4 Earthworks is applicable to the site
and is outlined in
Engineering
Plan
Cut to Fill
Drawing No. D05
( Revision E , prepared by Amity Engineers, Dated 19 April 2025 ) . The parties agree
the proposed development will not adversely affect or disrupt drainage and flood patterns, flood storage or soil stability in the area based noted in Stormwater Plans
(Drawing No. D10, Revision E, dated 19 April 2025)
and Flood Risk Management Plan
( D ated 19 April 2025)
prepared by Amity Engineers .
Excavated material is to be managed in accordance with the Conditions of Consent in Annexure A.
Water Management Act 2000
The DA
was lodged
a s
I ntegrated
D evelopment
pursuant to
Div 4.8 of the EPA Act , requiring an approval under
s 91 of
the
Water Management Act 2000
(WM Act) .
The
Respondent referred to the DA to the Department of Planning and Environment – Water (DPE Water) on 29 January 2025. On 14 April 2025, DPE Water indicated that for the purposes of the WM Act, a controlled activity approval is not required for the proposed works and ‘no further assessment by this agency is necessary’.
On 9 April 2025, Water NSW confirmed that for the purposes of the
WM Act, no further
investigation is required .
State Environmental Planning Policy (Resilience and Hazards) 2021
The provisions of
s 4.6 pf the
State Environmental Planning Policy ( Resilience and Hazards ) 2021
(RH SEPP)
applies to the site.
The Court notes that the
site was
the subject of previous clean up notices by the NSW Environment Protection Authority (EPA). The Court
has sighted
the EPA letter to the Council of Camden
(Dated 26 November 2024, Reference: DOC24/957209)
that the clean up actions are now completed.
The DA is supported by a Preliminary Site Investigation
(PSI)
of
a kind
required by s 4.6 of the RH SEPP , prepared by
Foundation Earth Sciences Pty Ltd dated 10 February 2025 .
I accept the conclusion of the PSI
that the site is suitable for the proposed development, and I note
the recommendations contained in the PSI are incorporated in the agreed conditions of consent
2.2(8) and 2.3(1 3 ) .
State Environmental Planning Policy (Biodiversity and Conservation) 2021
Chapter 6
Water Catchments
of the State Environmental Planning Policy (Biodiversity and Conservation) 2021 (BC SEPP)
is applicable as th e site is
located
within the
Hawkesbury-Nepean
Catchment .
The
DA
(as amended)
is accompanied
by Stormwater
Management Plans prepared by Amity Engineers ( Drawing No. D10, Revision E, Drawing No. D12, Revision E, and Drawing No. D20, Revision E,
Dated 19 April 2025 ) , a
Flood Risk Management Report prepared by Amity Engineers (Dated 19 April 2025) and a Wastewater Diagram (Drawing No. 3964-WW, Revision A-04) and Report prepared by Broadcrest Consultants Pty Ltd dated 17 April 2025 .
With regard to these documents, and
Conditions
of Consent:
2.1(7), 2.1(12), and 2.2(4)
which
provide additional
controls
to ensure
there is
no
adverse effect
on the water quality and river flows of the Hawkesbury-Nepean River and its tributaries , the parties
agree,
and I accept that the
provisions of the BC SEPP are met.
State Environmental Planning Policy (Transport and Infrastructure) 2021
Pursuant
to
c l 2.119 of
the
State Environmental Planning Policy (Transport and Infrastructure) 2021 , t he address of the site
has frontage to the Northern Road
which is a classified road . However
the parties advised that
as the
access to the site is proposed of f
Bent Street, which is a Local Road,
this clause is satisfied .
Conclusion
As the parties ’
decision is a decision that the Court could have made in the proper exercise of its functions, I am required under s 34(3) of the LEC Act to dispose of the proceedings in accordance with the parties ’
decision.
In making the orders to give effect to the agreement between the parties, I was not required to, and have not, made any merit assessment of the issues that were originally in dispute between the parties.
The Court notes that:
The Respondent, as the relevant consent authority, has approved under section 38(1) of the
Environmental Planning and Assessment Regulation 2021 ,
to the Applicant amending Development Application DA/2024/537/1 in accordance with the amended plans listed in Annexure A.
The
Applicant
has
filed the plans and documents in
Annexure
A
with the Court on
29 April 2025 .
Orders
The Court orders that:
The Appeal is upheld.
Development consent is granted to Development Application No. DA/2024/537/1 (as amended) for the construction and use of a landscape material supply facility with associated works, on land legally described as Lot 25 in Deposited Plan 1222679 and known as 1110 The Northern Road, Bringelly NSW, subject to the conditions at
Annexure A.
The Applicant is to pay the Respondent's costs thrown away pursuant to s
8.15(3) of the
Environmental Planning and Assessment Act 1979
in the agreed sum of
( $3,500 ) , payable within 14 days.
L Coetzee
Acting
Commissioner of the Court
Annexure A (251 KB, pdf)
**********
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Decision last updated:
08 May 2025
Official source: https://www.caselaw.nsw.gov.au/decision/1969e29d2c8977a4954120f6