A & M Telecommunications Pty Ltd trading as SAWWA ACN 146873289 v WCED Pty Ltd [2025] NSWDC 7
Catchwords: BUILDING AND CONSTRUCTION – Building and Construction Industry Security of Payment Act 1999 – application for summary judgment
District Court
New South Wales
Medium Neutral Citation:
A & M Telecommunications Pty Ltd trading as SAWWA ACN 146873289 v WCED Pty Ltd [2025] NSWDC 7
Hearing dates:
1 November 2024
Date of orders:
07 February 2025
Decision date:
07 February 2025
Jurisdiction:
Civil
Before:
Cole DCJ
Decision:
(1) The
plaintiff ’ s Notice of Motion filed
on
26 July 2024 is dismissed.
(2) This matter is to proceed by way of pleadings.
(3) The plaintiff is to pay the
defendant ’ s
costs of
and incidental to the Notice of Motion within 14 days of the date of this order.
(4) The matter is listed for directions before the Judicial Registrar on 21 February 2025.
Catchwords:
BUILDING AND CONSTRUCTION
–
Building and Construction Industry Security of Payment Act 1999
– application for summary
judgment
Legislation Cited:
Australian Consumer Law
Building and Construction Industry Security of Payment Act 1999 (NSW)
Uniform Civil Procedure Rules 2005
Cases Cited:
Agius v New South Wales [2001] NSWCA 371
Dualcorp Pty Ltd v Remo Constructions Pty Ltd [2009] NSWCA 69
Fancourt v Mercantile Credits Ltd (1983) 154 CLR 87
General Steel Industries Inc v Commissioner for Railways (NSW) (1964) 112 CLR 125
Kitchen Xchange v Formacon Building Services [2014] NSWSC 1602
Spencer v Commonwealth of Australia (2010) 241 CLR 118
Steve Karamihos and Aristea Karamihos v Bendigo and Adelaide Bank Limited, Bendigo and Adelaide Bank Limited v Steve Karamihos and Aristea Karamihos [2013] NSWSC 172
Witron Australia Pty Ltd v Turnkey Innovative Engineering Pty Ltd [2023] NSWCA 305
Category:
Procedural rulings
Parties:
A&M Telecommunications Pty Ltd trading as SAWWA (Plaintiff)
WCED Pty Ltd (Defendant)
Representation:
Counsel:
P Bambagiotti (Plaintiff)
J Polese (Defendant)
Solicitors:
Redenbach Legal (Plaintiff)
CVC Law (Defendant)
File Number(s):
2024/275308
Publication restriction:
Nil
JUDGMENT
By Notice of Motion filed on 26 July 2024, the plaintiff seeks the following orders:
Pursuant to section 15 of the
Building and Construction Industry Security of Payment Act 1999
(NSW), an order for summary judgment be made against the defendant for the full amount claimed in the proceedings in the sum of $143,135.85.
The defendant pays the plaintiff the costs of the notice of motion.
Background
The factual background to the matter is set out in the affidavit of Mr Ross
Iannello
dated 26 July 2024 and filed in the plaintiff ’ s case, and the affidavit of Mr Naeem
Hindaoui , a director of the defendant.
On 29 April 2024,
Kabling
Solutions wrote to the defendant submitting a fee proposal
on behalf of the plaintiff
for the Demolition Consultancy Services required for demolition at 111 Crown Street,
Wollongong .
The proposal included a scope of works at Attachment A and a schedule of rates at Attachment B.
On 7 May 2024, the defendant raised Purchase Order ENG2404-02.
Both parties
say that a contract came into existence on 7 May 2024 in which the plaintiff was engaged by the defendant
to perform construction works and services between 6 May 2024 and 17 June 2024 .
On 9 July 2024, the plaintiff prepared a payment claim for $139,309.50, inclusive of GST ( ‘ the payment claim ’ ). The payment
claim
cited reference number SW_W2425
and gave a due date of 23 July 2024. Timesheets for Robert Brady from 6 May
2024 to
4 June 2024 and for
Ondrej
Krpalek
from 6 May 2024 to 17 June 2024 were attached to the payment claim. The payment
claim is a
one page
document with annexures, and the last line of the page, under the signature, says:
This is a payment claim under the Building & Construction Industry Security of Payment Act 1999 (NSW).
The payment claim was served on the defendant on 10 July 2024.
On 17 July 2024, an email was sent from the defendant to Mr Abdul Ali, the signatory to the payment claim.
A series of time sheets and invoices from the plaintiff were annexed to the
email , and it is stated, in the email, that these have been sent to
Mr Ali on a previous occasion.
The time sheets and invoices have been marked in red to indicate the
defendant ’ s position as to what is due to the plaintiff .
Some of the
time sheets
have
an explanation for the deletion of an item, such as
“
we didn’t request 2 persons to be on site, we required 1 supervisor only
”
(Saturday 26/6/24).
Beside t he
figures on the invoices
which have been deleted,
the
defendant ’ s
assertion as to what is payable ,
expressed numerically ,
has been added
(see the annexure to the affidavit of Mr
Hindaoui
of 4 September 2024) .
The
email says:
Dear Abdul
Hope this finds you well.
We received an invoice from yourself by express post with a time sheet attach to it.
Kindly find attached again all corrected invoices and time sheet.
Should you have any enquiries please don’t hesitate to contact
me
thank you.
Kind
Regards,
Omar Hassan
Estimating.
On 25 July 2024, the plaintiff issued a letter of demand to the defendant, seeking payment in full of the amount of the payment claim. No payment was forthcoming.
Summary Judgment
The
Uniform Civil Procedure Rules 2005
( ‘ the UCPR ’ )
give the Court power to give summary judgment in rule 13.1:
13.1
Summary judgment
(1) If, on application by the plaintiff in relation to the plaintiff’s claim for relief or any part of the plaintiff’s claim for relief—
(a) there is evidence of the facts on which the claim or part of the claim is based, and
(b) there is evidence, given by the plaintiff or by some responsible person, that, in the belief of the person giving the evidence, the defendant has no defence to the claim or part of the claim, or no defence except as to the amount of any damages claimed,
the court may give such judgment for the
plaintiff, or
make such order on the claim or that part of the claim, as the case requires.
(2) Without limiting subrule (1), the court may give judgment for the plaintiff for damages to be assessed.
(3) In this rule, a reference to
damages
includes a reference to the value of goods.
I t is well established that the test for the
obtain ing of
summary judgment
is that
the plaintiff must show
that the defendant ’ s defence to the action is ,
in the words of Barwick J in
General Steel Industries Inc v Commissioner for Railways (NSW)
(1964) 112 CLR 12 5
at [8]:
…"so obviously untenable that it cannot possibly succeed"; "manifestly groundless"; "so manifestly faulty that it does not admit of argument"; "discloses a case which the Court is satisfied cannot succeed"; "under no possibility can there be a good cause of action"; "be manifest that to allow them" (the pleadings) "to stand would involve useless expense".
In
Fancourt
v Mercantile Credit
s Ltd
(1983) 154 CLR 87 at [27 ] the High Court said:
…The power to order summary or final judgment is one that should be exercised with great care and should never be exercised unless it is clear that there is no real question to be tried: see Clarke v. Union Bank of Australia Ltd.
[1917] HCA 19; (1917) 23 CLR
5 ;
Jones v. Stone (1894) AC 122 ; Jacobs v. Booth's Distillery Co. (1901) 85 LT 262.
The Plaintiff’s argument
T he plaintiff stressed the
strictness of the requirements of the
Building and Construction Industry Security of Payment Act 1999
( ‘ the Act ’ ). The plaintiff argued,
( to summarise it briefly ) , that
the
payment claim
served by it upon the defendant on 10 July 2024
was compliant with the requirements of
s 13 of
the Act .
Further,
it was argued
that the defendant had failed to
provide a payments schedule to the plaintiff
under s 14 of the Act , and had thus become liable to pay the claimed amount on the due date specified in the payment claim ,
and
the claimed amount could
therefore be
recovered
in this action
by the plaintiff from the defend a nt as a debt under s 15(2) of the Act .
The plaintiff argued that the email sent
by Mr Hassan to Mr Ali
on 17 July 2024 could not be characterised as a payment schedule .
Mr
Bambagiotti
acknowledged the flexibility given
in the exercise of
characterisation, and
said that t hree
characteris tics are critical. Firstly, the email (in this matter) must identify the payment claim to which it relates
(s
14(2)(a)) . Secondly, the email
must indicate
what portion
of the claim
the defendant
proposes to
pay
(s 14(2)(b)) .
Thirdly ,
in the event that
the
email indicates that
the defendant proposes
to pay less than the amount claimed, a reason or reasons
must be given in the email
as to why
the defendant
has formed that intention
(s 14(3)) .
Mr
Bambagiotti
argued that
each of the requirements
must be present
for the email to be a payment schedule.
Compliance with s 14(3)
would not be sufficient if the requirements of s 14(2)(a) and (b)
of the Act had not been fulfilled.
As to the first requirement, t he plaintiff argued that the email did not
identify the payment claim to which it relates.
There is reference in the email to receipt of
the 10 July 2024 document, but
there is no
acknowledge ment
that
the 10 July 2024 document
is a payment claim under the Act.
As to the second requirement, the plaintiff argued that the email did not indicate
the amount of the payment that the defendant
proposed
to make.
It was argued that the amendments in red to the time sheets and the invoices were akin to a
“ formula ”
for working out what the defendant says is payable, and do not amount to an indication of what the defendant agrees to pay. It was
properly
conceded , however,
that it was possible to calculate , from the red markings and figures, what the defendant proposed to pay.
The plaintiff argued that, in the absence of a clear statement as to what the defendant
proposed
to pay,
no
“ scheduled amount ”
emerged, as contemplated by s 14(2)(b) of the Act.
The plaintiff further argued that
the defendant could not
succeed in
a defence of res judicata or issue estoppel
based upon
Dualcor
p
Pty Ltd v Remo Constructions Pty Ltd
[2009] NSWCA 69
( ‘ Dualcorp ’ ) ,
because
the
statements in the
judgment s
in that matter
on that topic are
confined to payment claims which ha ve
been the subject of adjudication under the Act, and the payment claim in this matter has not been the subject of an adjudication or any judicial determination.
As to the possibility of a defence of
misleading and deceptive conduct under the Australian Consumer Law, the plaintiff agreed that such a defence
is not precluded by s
15(4)( b) of the Act. The plaintiff argued that
such a defence would have to relate to misleading and deceptive conduct which goes to the effectiveness of the payment claim
as a payment claim under the Act .
The plaintiff relied upon
the following statement by
Macfarlan
J in
Dualcorp
at [41]:
41. …The defence may thus be raised, as may one that service of a payment claim was not effective because it involved misleading or deceptive conduct (
Bitannia
Pty Ltd v
Parkline
Constructions Pty Ltd
(2006) 67 NSWLR 9 especially at [96] per
Basten
JA).
The Defendant’s argument
The defendant argued that summary judgment
should not be given.
The defendant argued that
the Court could not
find that there is no real
question to be tried, or that the defence was untenable or manifestly groundless.
In its submissions, the defendant said:
28.
The Defendant has, respectfully, met the relevant tests to resist the application for summary judgment because the above submissions and its evidence have proven or met:
(a)
The threshold to establish a reasonable cause of action is a low one, where it has been held that reasonable prospects of success
means
more than “Fanciful prospects”
Spencer v Commonwealth
(2010) 241 CLR 118; 84 ALJR 612; [2010] HCA 28 at 128 – 132, per French CJ and
Gummow
J. The Defendant’s defences are reasonable causes of action.
(b)
The assessment of these tests
are
to be made by taking the case at its highes t, in which there should be acceptance of the truth of the allegations in the pleading or the evidence, as an order can be made on the pleadings alon e.
Agius
v New South Wales
[2002] Aust Tort Reports 81-656: [2001] NSWCA 371 at 24; and
(c)
There is a clear public interest in allowing this case to be fully heard on its merits. If consumer protection is avoided,
ignored
or not considered then there can be no true balancing of rights and protections of the parties.
Steve
Karamihos
v
Aristea
Karamihos
v Bendigo and Adelaide Bank Limited, Bendigo and Adelaide Bank Limited v Stave
Karamihos
and
Aristea
Karamihos
[2013] NSWSC 172, per Pembroke J at [37]-[42]. The Defendant raises valid arguments under the
ACL
and they should be entitled to be heard on those claims.
The defendant relied upon s 1 3(5) of the Act, which says:
(5)
Except as otherwise provided for in the construction contract, a claimant may only serve one payment claim in any
particular named
month for construction work carried out or undertaken to be carried out (or for related goods and services supplied or undertaken to be supplied) in that month.
The defendant argued that the invoices
interspersed with time sheets
at pp 24
-
56
of the affidavit of Mr
H indaoui
overlap with the payment claim and, themselves, constitute payment claims
and are therefore in breach of s 13(5) of the Act.
It was pointed out that most of those
invoices
state on their face that they are
payment claims under the Act.
It was argued that the payment claim is therefore invalid.
It was further argued that no supporting statement
was
served with the payment claim on 10 July 202 4. The defendant argued that, although this does not invalidate the payment claim, it invalidates service
or renders service ineffective
(see
Kitch
e
n Xchange v
Formacon
Building Services
[2014] NSWSC 1602
at [36]-[46], [49]-[50]).
In the alternative, the defendant argued that, if the payment claim is valid, then a payment schedule has been
served in response to it
within the
10 day
time limit provided for in s
14(4)(b)(ii)
of
the Act, being the email of 17 July 2024
together with its attachments .
It was argued that the
email
complied
with s 14(2) and (3) of the Act.
It identified the payment claim to which it related by referring to
having received
“ an invoice from yourself by express post with a time sheet attach
to it ” .
On the invoices attached to it, marked in red , were the amounts
the defendant proposed to pay in response to the payment claim. Arriving at the total figure require s
simple addition.
A previous email of 8 July 2024
to Mr Ali
set out the total.
The reasons
were clear by inference from the red markings on the time sheets and were made express in red writing on
some of those time sheets .
The plaintiff relied upon
Wit
r
on
Australia Pty Ltd v Turnkey Innovative Engineering Pty Ltd
[2023]
NSWCA 305
at
[40], where Kirk JA, with whom Leeming JA and Payne JA agree d ,
rejected the argument that a payment schedule must
“ identify
some
particular numeric figure ” .
The
defendant referred to its defence, filed on 17 October 2024 , which sets out ,
in some detail ,
defences under s 18 and s 21 of the Australian Consumer Law.
Consideration
The question to be decided
on this application is whether the plaintiff has shown that the defence is obviously untenable or manifestly groundless, or whether , to the contrary, it is apparent that there is a question to be tried.
I am s atisfied,
on the basis of
the
material
before me ,
and having regard to the arguments on both sides summarised above,
th at the matters raised by the defendant
are all arguable to , at least, the extent necessary to
defeat the application for summary judgment.
I need not assess the relative strengths of the different
issues or make any findings in relation to them. All that is necessary is that it be
apparent
that they are
not obviously untenable or manifestly
groundless, and that threshold has been reached or exceeded in
relation to
each
issue.
Orders
The following orders will issue:
The
plaintiff ’ s Notice of Motion filed
on
26 July 2024 is dismissed.
This matter is to proceed by way of pleadings.
The plaintiff is to pay the
defendant ’ s
costs of
and incidental to the Notice of Motion within 14 days of the date of this order.
The matter is listed for directions before the Judicial Registrar on 21 February 2025.
**********
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.