A-Civil Aust Pty Ltd v Ceerose Pty Ltd [2024] NSWCA 7
Catchwords: BUILDING AND CONSTRUCTION — adjudication — whether adjudication determination was affected by jurisdictional error — whether adjudicator denied respondent to adjudication procedural fairness — whether basis of adjudicator’s determination regarding retention monies was in issue on the adjudication — whether respondent could reasonably anticipate basis of determination regarding retention monies — denial of procedural fairness material
Court of Appeal
Supreme Court
New South Wales
Summary available
Medium Neutral Citation:
A-Civil Aust Pty Ltd v Ceerose Pty Ltd [2024] NSWCA 7
Hearing dates:
15 November 2023
Date of orders:
1 February 2024
Decision date:
01 February 2024
Before:
Leeming JA at [1]
White JA at [5]
Mitchelmore JA at [6]
Decision:
(1)
The appeal is dismissed.
(2)
The appellant is to pay the first
respondent’s costs of the appeal.
Catchwords:
BUILDING AND CONSTRUCTION — adjudication — whether adjudication determination was affected by jurisdictional error — whether adjudicator denied respondent to adjudication procedural fairness — whether basis of adjudicator’s determination regarding retention monies was
in issue on the adjudication
—
whether respondent could reasonably anticipate basis of determination regarding retention monies
—
denial of procedural fairness
material
Legislation Cited:
Building and Construction Industry Security of Payment Act 1999
(NSW)
Construction Contracts (Security of Payments) Act
(NT)
Cases Cited:
Ausenco Operations Pty Ltd v Ferretti International Ottoway Pty Ltd
[2020] SASC 46
Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd
(2010) 78 NSWLR 393; [2010] NSWCA 190
Commissioner for ACT Revenue v
Alphaone
(1994) 49 FCR 576
Demex
Pty Ltd v McNab Building Services Pty Ltd
[2023] NSWCA 261
Downer Construction (Australia) Pty Ltd v Energy Australia
(2007) 69 NSWLR 72; [2007] NSWCA 49
JKC Australia LNG Pty Ltd v INPEX Operations Australia Pty Ltd
(2018) 41 NTLR 149; [2018] NTCA 6
Minister for Immigration and Border Protection v SZMTA
(2019) 264 CLR 421; [2019] HCA 3
Minister for Immigration and Border Protection v SZSSJ
(2016) 259 CLR 180; [2016] HCA 29
Multiplex Constructions Pty Ltd v
Luikens
[2003] NSWSC 1140
MZAPC v Minister for Immigration and Border Protection
(2021) 273 CLR 506; [2021] HCA 17
Probuild
Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd
(2018) 264 CLR 1; [2018] HCA 4
Category:
Principal judgment
Parties:
A-Civil Aust Pty Ltd (Appellant)
Ceerose Pty Ltd (First Respondent)
Paul Roberts (Second Respondent)
ABC Dispute Resolution Service (Third Respondent)
Representation:
Counsel:
L Gor (Appellant)
D Hume (First Respondent)
Solicitors:
Shaba & Thomas Lawyers (Appellant)
Salim Rutherford Lawyers (First Respondent)
File Number(s):
2023/00169019
Publication restriction:
Nil
Decision under appeal
Court or tribunal:
Supreme Court of New South Wales
Jurisdiction:
Equity
Citation:
[2023] NSWSC 345; [2023] NSWSC 999
Date of Decision:
6 April 2023; 21 August 2023
Before:
Richmond J
File Number(s):
2022/307139
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
HEADNOTE
[This headnote is not to be read as part of the judgment]
On 2 March 2022, Ceerose Pty Ltd (Ceerose) and A-Civil Aust Pty Ltd (A-Civil)
entered into
a subcontract for excavation work on a site in Sydney; Ceerose was the main contractor and A-Civil was the subcontractor. On 1 July 2022, Ceerose terminated the subcontract and A-Civil left the site. On 29 July 2022, A-Civil served its final payment claim on Ceerose pursuant to s 13 of the
Building and Construction Industry Security of Payment Act 1999
(NSW) (Security of Payment Act) for $709,940.74, which included the release of retention monies of $115,577.79 (ex GST).
On 12 August 2022, Ceerose provided a payment schedule to A-Civil in which Ceerose asserted that A-Civil was not entitled to the retention monies. Ceerose submitted that A-Civil had not satisfied the preconditions for making a claim in cl 5.4 of the General Conditions of the subcontract and, alternatively, Ceerose had recourse to the retention monies in part satisfaction of its claim for amounts A-Civil owed to it for breach of the subcontract under cl 5.2 of the General Conditions.
On 26 August 2022, A-Civil submitted an adjudication application under the Security of Payment Act. In relation to the retention monies, A-Civil submitted that it had complied with
Ceerose’s
directions, and any delays were the result of
Ceerose’s
poor management. Further, A-Civil submitted that Ceerose had wrongfully terminated the subcontract and deprived it of the opportunity to carry out its obligations. In its adjudication response of 6 September 2022, Ceerose reiterated that A-Civil had no right to the retention monies under cl 5.4 and that it had exercised its right to recourse under cl 5.2. It denied any wrongful termination of the subcontract.
On 27 September 2022, the adjudicator
made a determination
under s 22 of the Security of Payment Act, concluding, relevantly to the appeal, that Ceerose owed A-Civil the full amount of the retention monies claimed. In his reasons, the adjudicator decided that the subcontract had been terminated and that A-Civil was therefore entitled to the release of the retention monies.
The primary judge held that the adjudicator’s conclusion regarding the retention monies was affected by jurisdictional error, namely, a material denial of procedural fairness. His Honour concluded that the adjudicator had decided the claim for the retention monies on a basis for which neither party had contended and without putting the parties on notice and giving them an opportunity to be heard. His Honour declared that the part of the adjudication
determination
involving
the claim for retention monies
was
invalid.
The central issue on the appeal was whether his Honour erred in finding that there was a material denial of procedural fairness. A-Civil contended that the primary judge had mischaracterised the basis of the adjudicator’s determination and had erred in concluding that it was not in issue or “on the table”. Alternatively, A-Civil contended that the primary judge erred in concluding that Ceerose could not have reasonably anticipated that the adjudicator would decide the retention monies claim in the manner he did.
The Court
(Leeming JA,
White JA
and Mitchelmore JA
), dismissing the appeal, held:
Per Leeming JA (White JA and Mitchelmore JA agreeing):
(1)
The primary judge was correct to conclude that the adjudicator’s reasons were so far removed from the parties’ submissions that it resulted in a substantial breach of the obligation to accord procedural fairness: [4].
Only rarely will there be a basis for quashing an adjudication certificate for want of procedural fairness; this appeal turned on its very particular facts: [1].
Per Mitchelmore JA (Leeming JA and White JA agreeing):
(2)
The primary judge did not err in characterising the reasoning of the adjudicator and the issue to which the reasoning gave rise, namely, whether the clause governing
retention monies provided by a subcontractor ceased to apply upon termination of the subcontract: [32].
His Honour’s reasons in this regard
did not involve impermissible merits review: [31].
(3)
There was no error in his Honour’s conclusion that the basis of the adjudicator’s determination regarding retention monies was not in issue or “on the table”. Although Ceerose put in issue A-Civil’s
entitlement to the retention monies, it was
on the basis of
the operation of cl 5.4 or cl 5.2. By contrast, the adjudicator’s reasoning could only be premised on cl 5.4 and cl 5.2 having no operation upon termination: [37]. A-Civil did not raise the issue in its adjudication application, instead contending that the subcontract had been wrongfully terminated: [43].
Demex
Pty Ltd v McNab Building Services Pty Ltd
[2023] NSWCA 261;
Ausenco Operations Pty Ltd v Ferretti International Ottoway Pty Ltd
[2020] SASC 46 considered.
(4)
The
primary judge did not err in concluding that Ceerose could not have anticipated the adjudicator’s conclusion .
Although it was apparent that A-Civil was claiming the retention monies, it did not articulate any basis for that claim in the payment claim; and its position in the adjudication application was inconsistent with the subcontract being at an end: [47].
Demex
Pty Ltd v McNab Building Services Pty Ltd
[2023] NSWCA 261;
Multiplex Constructions Pty Ltd v
Luikens
[2003] NSWSC 1140 considered;
JKC Australia LNG Pty Ltd v INPEX Operations Australia Pty Ltd
(2018) 41 NTLR 149; [2018] NTCA 6 distinguished.
(5)
The primary judge was correct to find a material denial of procedural fairness. The denial of procedural fairness was substantial and material in the sense that there was a realistic possibility that the decision could have been different but for the denial of procedural fairness: [51]. Ceerose was not given the opportunity submit on the reasoning ultimately adopted by the adjudicator: [52].
Demex
Pty Ltd v McNab Building Services Pty Ltd
[2023] NSWCA 261;
Minister for Immigration and Border Protection v SZMTA
(2019) 264 CLR 241; [2019] HCA
3 ;
MZAPC v Minister for Immigration and Border Protection
(2021) 273 CLR 506; [2021] HCA 17 applied.
Downer Construction (Australia) Pty Ltd v Energy
(2007) 69 NSWLR 72 distinguished.
JUDGMENT
LEEMING JA
: I agree with Mitchelmore JA that this appeal should be dismissed, for the reasons given by her Honour. I add the following by way of emphasis and to explain why this appeal turns on its very particular facts. It may be expected that only rarely will there be a basis for quashing an adjudication certificate for want of procedural fairness by reason of the dispute being determined in a way which could not have been anticipated by the loser and as to which the loser was entitled to be heard.
This Court ’ s decision in
Demex
Pty Ltd v McNab Building Services Pty Ltd
[2023] NSWCA 261 at [16]-[33], which post-dated that of the primary judge, emphasised that an adjudicator determining a dispute under the
Building and Construction Industry Security of Payment Act 1999
(NSW) is required to accord procedural fairness to the parties, even though the determination does not (speaking generally) affect their rights under the construction contract (s
32), and even though the adjudicator need not be legally qualified and is generally confined to considering the contract, the payment claim and payment schedule and the parties ’
submissions (s 22(2)). There is no right to an oral hearing, and there is an obligation to determine the dispute as expeditiously as possible and in any event within the tight time constraints imposed by s 21(3). Matters which, if not flagged by a court determining the same dispute would amount to a denial of procedural fairness, will not necessarily amount to a procedurally unfair approach when adopted by an adjudicator. Further, it is to be borne steadily in mind that the adjudicator ’ s determination may be replete with errors of law on its face, but even so it remains immune from judicial review until and unless jurisdictional error be established:
Probuild
Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd
(2018) 264 CLR 1; [2018] HCA 4. To be clear, that does not for a moment mean that the parties are bound in any final way by a decision which is legally incorrect. That is the point of the adjudicator ’ s determination not affecting the parties ’
rights, which they are entitled to have determined in accordance with law by a court accompanied by the usual incidents of curial determination including oral hearing and entitlement to appeal.
Claims of a denial of procedural fairness of the nature advanced by Ceerose give rise to a peculiarity. If a party advances a submission which is
wrong as a matter of law , and which is refuted by the other side but accepted by the adjudicator, then without more there will be no right of review. Judicial review is not available for error of law on the face of the record. However, if the adjudicator off his or her own bat determines a dispute on the same legally
incorrect
basis, then there is not only an error of law on the face of the record but also a denial of procedural fairness, with the latter (but not the former) vitiating the determination.
This is not a consideration which favours grounds such as those advanced by Ceerose being widely available.
The question in such cases is whether the party has been given a fair opportunity to be heard. That will turn on an evaluative judgment of
“ what is in play ” , to use the parties ’
metaphor. I respectfully agree with Kirk JA ’ s observation in
Demex
at [33] that a reviewing court should view sceptically arguments involving high degrees of specificity in this regard. The parties are often (as they were in the present case) sophisticated, and it is not necessary to spell out every aspect of their dispute. The issues in most disputes are familiar, and only rarely will there be scope for an adjudicator to determine them in a way which could not be anticipated thereby amounting to procedural unfairness. However, as Mitchelmore JA explains, in this
particular case , the reasons given by the adjudicator for determining that A-Civil was entitled to the retention monies were so far removed from the submissions advanced by both of them that this is a rare case where there has been a substantial breach of the obligation to accord procedural fairness. The primary judge was correct so to conclude.
WHITE JA:
I agree with Mitchelmore JA and with the additional reasons of Leeming JA.
MITCHELMORE JA:
This is an appeal
from
a decision
of
Richmond J
i n which
his Honour declared that
an adjudication determination under the
Building and Construction Industry Security of Payment Act 1999
(NSW) ( Security of Payment Act )
was invalid
in part :
Ceerose Pty Ltd v A-Civil Aust Pty Ltd (No 2)
[2023] NSWSC 345.
The adjudicator
had
relevantly
determined
that the
first
respondent
to
the appeal,
Ceerose Pty Ltd (Ceerose) ,
was
to pay
the appellant,
A-Civil Aus t
Pty Ltd (A-Civil)
retention monies
of $115,577 . 79.
The primary judge
concluded
that in so
determining , the adjudicator denied Ceerose procedural fairness .
The primary issue on the appeal is whether his Honour erred in reaching that conclusion.
For the reasons that
follow ,
the appeal should be dismissed.
Background
to the appeal
As there was no dispute
as between A-Civil and Ceerose
about the background to the
appeal ,
I have
largely
adopted
the primary judge ’ s
summary .
I note for completeness that a submitting appearance was filed
in the appeal
on behalf of the second
respondent (the adjudicator, Mr
Paul Roberts)
and
the
third respondent
( ABC Dispute Resolution Service ) .
On 2 March 2022, Ceerose and A-Civil
entered into
a subcontract for works at 163-167 McEvoy Street, Alexandria ;
Ceerose was the main contractor and A-Civil was the subcontractor : at [3] .
T he
s ubcontract
required
A-Civil to perform excavation work
on the site
for a
contract
sum of $2,840,210 : at [3] .
The
subcontract incorporated the
General Conditions
contained in the
“ Subcontract conditions for design and construct ”
(AS4903-2000) . C lause
5
of the General Condition s , which was headed
“ Security ” ,
provided as follows :
“
5.1
Provision
Security
shall be provided in accordance with
Item
19 or 20. All delivered
security
, other than cash or retention monies, shall be transferred in escrow.
Except for any security provided in respect of unfixed plant or material, the total value of all
security
held by the
Main Contractor
shall not exceed:
(a)
Prior to
practical completion
of the head contract – 5% of the
subcontract sum
; and
(b)
After
practical completion
of the head contract – 2.5% of the
subcontract sum
.
5.2
Recourse
A party may have recourse to
security
:
(a)
Where the amount due to that party under the
Subcontract
or otherwise remains unpaid after the time for payment; and
(b)
In respect of any
Claim
to payment (liquidated or otherwise) that party may have against the other under the
Subcontract
or otherwise,
On the giving of written notice to the other party.
5.3
Change of
security
At any time, a party providing retention monies or cash
security
may substitute, with the written consent of the other in its absolute discretion, form of
security
. To the extent that another form of
security
is provided, the other party shall not deduct, and shall promptly release and return, retention moneys and cash
security
.
5.4
Reduction and release
Upon the issue of the
certificate of practical completion
under the head contract, a party’s entitlement to
security
(other than in
Item
19(e)) shall be reduced by the percentage or amount in
Item
19(f) or 20(d) as applicable, and the reduction shall be released and returned within 28 days to the other party.
A party’s entitlement otherwise to
security
shall cease 28 days after
final certificate is issued under the head contract
.
Upon a party’s entitlement to
security
ceasing, that party shall release and return forthwith the
security
to the other party.
5.5
Trusts and interest
Except where held by a government department or agency or a municipal, public or statutory authority, any portion of
security
which is cash or retention monies, shall be held in trust for the parties in accordance with the terms of this agreement."
The term
“ security ”
was defined in cl
1 of the General Conditions to include cash or retention monies . The term
“ claim ”
was
also
defined
in cl
1
to
include
“ any
Claim
, action, demand
or damages … including but not limited to at law, in tort (including negligence), under statute, in equity including quantum mer it [sic] or restitution based on unjust enrichment, for rectification, frustration or for any other legal or equitable remedy ” .
Item
19 of
Part A of the
Annexure to the General Conditions, which was referred to in cl
5.1,
dealt with security to be
provided
by the subcontractor, being A-Civil. Item
19
provided
that the security would take the form of retention monies in the amount of 10
per cent
of each progress certificate .
Consistently with cl
5.4,
read with Item 19,
50
per cent
of the retention sum
was
required to be
returned to A-Civil within 28
days
of practical completion , and
the
balance
was
returnable to A-Civil 28 days after the final certificate
was
issued under the head contract : at
[7] .
Clause 39 of the General Conditions dealt with the consequences of default, and relevantly provided:
“
39.1 Preservation of other rights
If a party breaches (including repudiates) the
Subcontract
, nothing in this clause shall prejudice the right of the other party to recover damages or exercise any other right or remedy.
39.2
Subcontractor’s
default
If the
Subcontractor
commits a substantial breach of the
Subcontract
, the
Main Contractor
may give the
Subcontractor
a written notice to show cause.
Substantial breaches include, but are
not
limited to:
(a) Failing to:
i . Perform properly the
Subcontractor’s
design
obligations
;
ii. Provide
security
;
iii. Provide evidence of
insurance;
iv. Comply with clause 34.1 or
31;
v. Comply with clause
29.3
vi. Comply with a
direction
of the
Subcontract Superintendent
; or
vii. Use the materials or standards of
work
required by the
Subcontract
;
viii. comply
with any clause of this contract.
(b) Wrongful suspension of
work
;
(c) Substantial departure from a
construction program
without reasonable
cause;
(d) Failing to proceed with due expedition and without delay; and
(e) In respect of clause 38, knowingly providing documentary evidence containing an untrue statement.
39.3
Main Contractor’s
notice to show
cause
A notice under subclause 39.2 shall state:
(a) That it is a notice under clause 39 of these
Subcontract
Conditions;
(b) The alleged substantial
breach;
(c) That the
Subcontractor
is required to show cause in writing why the
Main Contractor
should not exercise a right referred to in subclause
39.4;
(d) The date and time by which the
Subcontractor
must show cause (which shall not be less than 5 business days after the notice is received by the
Subcontractor
); and
(e) The place at which cause must be shown.
39.4
Main Contractor’s
rights
If the
Subcontractor
fails to show reasonable cause by the stated date and time, the
Main Contractor
may by written notice to the
Subcontractor
:
(a) Take out of the
Subcontractor’s
hands the whole or part of the
work
remaining to be completed and suspend payment until it becomes due and payable pursuant to clause 39.6; or
(b) Terminate the
Subcontract
.
…
39.10 Termination
If the
Subcontract
is terminated pursuant to subclause 39.4(b) … the parties’ remedies, rights and liabilities shall be the same as they would have been under the law governing the
Subcontract
had the defaulting party repudiated the
Subcontract
and the other party elected to treat the
Subcontract
as at an end and recover damages.
…”
On 1 July 2022, Ceerose terminated the
s ubcontract and A-Civil left the site :
at
[9] .
On 29 July 2022, A-Civil
served
an
eighth
and final payment claim
on Ceerose ,
pursuant to s
13 of the
Security of Payment Act . A-Civil
made a claim for
$70 9 , 940 .74 ( ex
GST) , which included
the release of retention monies of $115,577 . 79
(ex GST) .
A- Civil ’ s
payment claim did not
provide any
detail
as to
the
basis on which
it
sought the
retention
monies , but
included
the amount as a line item in the
schedule to the
payment claim .
On 12 August 2022, Ceerose provided a payment schedule to A-Civil
pursuant to s
14 of the
Security of Payment
Act ,
in which it asserted that
the amount
it
owed
under the payment claim
was
“ $N il ” :
at
[11] .
In that document,
Ceerose
advanced two
bases on which
A-Civil was not entitled to
the retention
monies .
The first
basis
was that
A-Civil had not satisfied the preconditions
in cl
5.4 of the General Conditions for
making a claim for the retention monies ,
and thus
did not have an entitlement to submit a claim for those monies :
at
[11].
The second, alternative ,
basis
was
that
Ceerose
had , and would have, recourse
to the retention monies
pursuant to
cl
5.2 ,
in part
satisf action of
its claim for amounts A-Civil
owed to it
for breach
of the
s ubcontract :
at
[12] .
As to the amount owing
to it ,
Ceerose stated :
“23.
Ceerose is entitled to an amount
in excess of
$3,221,374.40 from A Civil resulting from deductions and loss and damage suffered by Ceerose due to A
Civil’s
acts, default and omissions.
24.
Ceerose applies the monies held on retention against the amount of $3,221,374.40 owed by A Civil to Ceerose. On this basis,
Ceerose assess the Purported Payment Claim as $Nil. Notwithstanding the recourse to retention monies, monies remain owed by A Civil to Ceerose.”
On 26 August 2022, A-Civil made an application for adjudication of its payment claim under s 17 of the
Security of Payment Act : [13].
In
its
submissions in support of the
adjudication application ,
A-Civil disputed
Ceerose ’ s
claim
that
it had not
satisfied
the precondition s
in cl 5.4
to
release the retention monies .
A-Civil
submitted
that it had complied with
Ceerose ’ s
directions and instructions ,
and
that
any delays were a result of
Ceerose ’ s
poor management.
Further,
A-Civil
submitted that
Ceerose
had
deprived
it
of the opportunity to carry out its obligations under the
s ubcontract by wrongfully terminating
it :
at
[13] .
In answer to
Ceerose ’ s
alternative
contention that it had exercised its right
of
recourse
to the retention monies
under cl
5.2, A-Civil
reiterated its submission
that
Ceerose ’ s
termination of the
s ubcontract was
“ intentional and wrong ” :
at
[14] .
On 6 September 2022, Ceerose provided its adjudication response under s 20 of the
Security of Payment Act :
at
[15] .
Ceerose
reiterated
its argument s
that A-Civil had no right to the retention monies under cl
5.4 and
that it had exercised
its right
of
recourse under cl
5.2 :
at
[17].
Ceerose denied that
it had wrongfully terminated the
s ubcontract
and submitted that
even if it
had ,
A- Civil ’ s
claim
would be one
for damages ,
which was
not a claim that
could
be brought under the
Security of Payment Act .
O n 20
September 2022, the adjudicator issued a
“ request for further submissions ”
to A-Civil, with the requested information to be provided by 12pm on 21
September 2022 and any responsive comment from Ceerose to be provided by 5pm on 21
September 2022. By this time, the parties had already agreed to a request by the adjudicator to extend the statutory time for his decision
to 27
September 2022 .
The statutory
time period
of 10 business days would otherwise have expired on
20
September 2022
(see s
21(3)(a) of the Security of Payment Act) .
The
a djudicator’s determination
On 27 September 2022, the
a djudicator
made a
d etermination
under s
22
of the
Security of Payment Act
that the adjudicated amount w a s
$167,970.87 (inc luding
GST) , the date on which the amount became payable was
16
August 2022, and
his
fees were to be apportioned between the parties equally:
at
[18].
T he adjudicated amount
included the full amount of the retention monies
that A-Civil
claimed, being
$115,577 . 79 (ex GST).
Section
22(3)(b) of the
Security of Payment Act
requires that the adjudicator ’ s determination include
the reasons for the determination.
In the
Background and Preliminary Issues section
of the reasons , the adjudicator
summarised the parties ’
respective positions
regarding
the subcontract , including
Ceerose ’ s
position that it had
lawfully
terminated the subcontract on 1
July 2022
and that in accordance with its terms, it was entitled to set off and/or otherwise deduct amounts
that were
payable to A-Civil.
In [9] of the determination, the adjudicator set out what he considered to be the parties ’
rights regarding the payment claim , which relevantly included the following:
“a.
Under section 13(1C) of the Act, [A-Civil] is entitled to serve a payment claim on and from the date of
termination;
b.
Under Clause 39.4 – Main Contractor’s rights: if the Subcontractor fails to show reasonable cause, the Main Contractor may by written notice:
39.4(a) – Take out of the Subcontractor’s hands the whole or part of the work remaining to be completed and suspend payment until it becomes due and payable pursuant to clause 39.6; or
39.4(b) – Terminate the Subcontract.
c.
…
d.
…
e.
Under clause 39.10 – Termination, if the Subcontract is terminated pursuant to subclause 39.4(b), the parties’ remedies , rights and liabilities shall be the same as they would have been under the law governing the Subcontract had the defaulting party repudiated the Subcontract
and the other party elected to treat the Subcontract as at an end and recover damages.
f.
….”
The adjudicator then stated, at [10]:
“Accordingly, if the Subcontract is terminated, pursuant to subclause 39.4(b), payment shall [be] as per the Subcontract.”
Although the adjudicator formulated
[10]
contingently,
he u ltimately
decided
that the subcontract
had been
terminated . The adjudicator ’ s reasons
regarding
the implications of termination
for
A- Civil ’ s
claim for the retention monies
commenced at [107].
Given the issues that arise on the appeal it is useful
to set
those
reasons
out
in full :
“
Claim for Retention Release
107.
In the payment claim, the Claimant claims $115,577.79 for release of its retention.
108.
In the payment schedule, the Respondent assesses this item as $0.00 for the following reasons:
a.
There is no right or entitlement under the
Subcontract;
b.
The Claimant has not satisfied the Subcontract pre-conditions to an entitlement to claim retention
money;
c.
It has an express right under the Subcontract to have recourse to retention
money;
d.
The Claimant is indebted to the Respondent “
for an amount enormously in excess of the retention money
”; and
e.
When the Subcontract was terminated, the Claimant did not accrue any right to retention money and cannot satisfy the contractual rights to claim its retention.
109.
In the adjudication application, the Claimant states:
a.
It did not abandon the site and complied with its obligations under the
Subcontract;
b.
A Notice of Delay was submitted by A-Civil on 1 July 2022, requesting an Extension of Time for the delay caused by inclement weather in reaching practical
completion;
c.
The Respondent sent it the termination letter on 1 July 2022 without providing any reasons as to why the project was terminated; and
d.
The Respondent deprived it of the opportunity to carry out its obligations under the Contract by wrongfully terminating the Contract which was intentional.
110.
In the adjudication response, the Respondent states:
a.
There is no basis to claim retention monies under the contract or under the
Act;
b.
The Respondent is entitled under the Subcontract to have recourse to the retention money and alternatively, any claim for retention monies is a claim for damages and cannot be made under the
Act;
c.
It repeats and relies on the reasons in its Payment
Schedule;
d.
The payment claim is not a claim for construction work or related goods or services and is therefore not a payment claim for the purposes of the Act; and
e.
There is no right or entitlement under the Subcontract for the Claimant to claim its retention. In accordance with section 10 of the Act, the Adjudicator must have regard to the terms of the Subcontract and the terms of the Subcontract do not give rise to an entitlement for the Claimant to make this claim.
111.
Pursuant to Clause 5.4, the Subcontractor’s entitlement to security is:
a.
reduced by 50% upon practical completion of the head contract with the reduction released within 28 days; and
b.
the balance released 28 days after the final certificate is issued under the head contract.
112.
Clause 5.4 of the Subcontract links the Subcontractor’s entitlement to security to practical completion and issue of the final certificate under the head contract which I find is void for contracting out of the Act. Notwithstanding, the Subcontract has been terminated and, therefore, the Claimant is entitled to the release of its security.
113.
Therefore, I value the claim for retention at
$115,577.79
.”
(Footnotes omitted.)
In respect of deductions
for which
Ceerose
advanced a
claim
in
its
payment schedule, the
a djudicator
found in its favour on
one item, being a deduction of $6,000
for
a
Council
fine :
at
[24] .
The largest item
that
Ceerose
had
claimed was $2,694,506 for the cost to complete the works
under
the
s ubcontract.
In relation to this item, the
a djudicator concluded that A-Civil could not be
“ back charged ”
for the cost to complete
for two reasons :
Ceerose had not deducted the value of subcontract works remaining
( so as
to calculate the
“ extra over cost of completing the works ” ),
and
Ceerose
“ [ had ]
not incurred the cost to complete which is based on a quotation and estimates ” .
On 28 September 2022, the
a djudicator issued an invoice for his fees and expenses, which were to be split between A-Civil and Ceerose.
A-Civil paid the full amount, and claimed from Ceerose its proportion of $18,791.22, which has not been paid :
at
[27]-[28] .
On 11 October 222, an adjudication certificate was issued
for the amount of
$ 189,095.53
and
j udgment was entered in the District Court
for
that
sum
(plus the filing fee) : [29] . O n
12 October 2022 ,
the
District
Court made
a garnishee order :
at
[ 29 ] .
On 14 October 2022, Ceerose commenced proceedings
by way of a Summons filed in court
before the
Equity
d uty
j udge.
An interim stay was granted
with respect to
A-Civil enforcing the judgment and
the bank acting on the garnishee order.
On 17 October 2022, Ceerose paid the amount of
the
judgment
sum
into
c ourt :
at
[30]-[31] .
On 2 November 2022, Rees J
lifted the interim stay and
made an order that the amount paid into
c ourt be paid out to A-Civil: see
Ceerose Pty Ltd v A-Civil Aust Pty Ltd
[2022] NSWSC 1487 .
The reasons of the primary judge
The focus of
Ceerose ’ s
procedural fairness complaint was
the second sentence of [112] of the determination. In its Amended Technology & Construction List
Statement at [18]-[19], Ceerose contended that neither party had sought the conclusion that the adjudicator reached in that sentence, and the adjudicator had not given any notice that he was contemplating adopting that reasoning.
The primary judge accepted that
the
reasoning for
the adjudicator ’ s decision
about
the retention monies
was
confined to
the second sentence
of [112] , which referred to the subcontract having been terminated: at [33].
After setting out
a number of
provisions of the
Security of Payment Act
relevant to the
process by which
progress payments may be recovered under the Act , and the
principles
relevant to considering an
alleg ed
denial of
procedural fairnes s,
the primary judge turned to identifying
what issues were
“ on the table ”
in the
adjudication.
To that end,
his Honour had regard to the terms of the payment claim, the payment schedule, the adjudication
application
and the adjudication response , stating
at [67] :
“It is clear from the adjudication application that A-Civil claimed to be entitled to the retention monies because Ceerose had wrongfully terminated the Contract: see adjudication application at [57] and [58]. This statement of the basis for its claim needs to be read in the context of what A-Civil knew was
Ceerose’s
position, which was stated clearly in the payment schedule as being that there was no right to the retention monies for two alternative and independent reasons: first, because cl 5.4 applied to restrict release of the retention monies until the certificates referred to in that clause had been issued, and second, that it had exercised its right to have recourse to the retention monies under cl 5.2. A-Civil did not respond to these contentions by a contention that neither cl 5.2 nor cl 5.4 applied because there had been a termination of the Contract. Rather, A-Civil responded by contending that these provisions did not apply because
Ceerose’s
termination was wrongful ( i.e.
not permitted by the contract). ”
His
Honour had earlier found at [33]
by reference to [112] of the adjudicator ’ s r e asons,
that
the adjudicator
did not conclude
that A-Civil was entitled to the retention monies
because
Ceerose had wrongfully terminated the subcontract.
Rather, as his Honour said of
the second
sentence
of [112]
(at
[68] ) :
“The issue raised by this
sentence
is whether cl 5
ceases to apply
following termination of the Contract
for whatever reason, so that from
that
time
there is
nothing to prevent A-Civil from claiming the retention monies.
In my view, it cannot be said that Ceerose should have reasonably anticipated that this issue was raised by the
payment claim or the
adjudication application.
Ceerose was not given prior notice that this was an issue that it had to deal with, and it was entitled to be given
such notice and an opportunity to make submissions on it.”
The primary judge
found
that
this
denial of
the opportunity to make submissions was material , accepting
Ceerose ’ s
submission that
“ it
could have put to the
a djudicator that cl 5.2 was a complete answer to the issue raised by the second sentence of [112] of the
d etermination ”
in circumstances where
(at [69]) :
there was no express term in the
s ubcontract that the right to have recourse to the retention monies under cl 5.2 cease d
on
termination ;
cl ause
5.2 permit ted
Ceerose to have recourse to security
“ in respect
of
any
C
laim
to payment
(liquid or otherwise)
that it may have against A-Civil
under the subcontract or otherwise ” , and
“ Claim ”
was broadly
defined ;
there
was
a
” respectable
argument ”
that s
34
of the
Security of Payment Act
did
not apply to cl 5.2
because
the clause did
not, and
did
not purport to, exclude ,
modify or restrict the operation of the Ac t; and
the
a djudicator did not record in [1]-[10] ,
[108] or [110] of the
d etermination that Ceerose had exercised its right
of
recourse under cl
5.2 ;
and
as
Ceerose had exercised its right
of
recourse
to the retention monies , the submission now contemplated
was
one the
a djudicator had not previously
addressed
and
it
could not
be assumed that he would reject it .
I t was common ground
before the primary judge
that if his Honour found th at the adjudicator
had
denied
Ceerose procedural fairness in relation to the retention monies,
the
declaration of invalidity should relate only to
that part of the determination.
Section 32 A( 1) of the
Security of Payment
Act
relevantly
provides that if the Supreme Court makes a finding that jurisdictional error has occurred in relation to an adjudicator ’ s determination, the Court may make an order setting aside the whole or any part of the determination.
A-Civil’s
appeal
By
its
A mended
N otice of
A ppeal,
A-Civil
appeal ed
from
that part of the
primary judge ’ s
decision
by
which
his Honour found that
the adjudicator
made
a
material
jurisdictional error
affecting his determination
regarding
the retention monies .
A-Civil
advanced
ten
grounds
of appeal, nine of which alleged
various
errors
attending
the
primary judge ’ s conclusion that the adjudicator had denied Ceerose procedural fairness ,
while
ground 10
set out
various
conclusions that his Honour should
instead
have reached .
Thus, in
grounds 1 to 9 ,
A-Civil alleged
that
the primary judge made
the following errors :
f inding that
the
a djudicator ’ s decision to include the retention monies claim in the adjudication amount was affected by jurisdictional error, being a material denial of procedural fairness
(ground 1 ) ;
framing the issue
for decision by the adjudicator
as whether
A-Civil
was entitled to the retention monies on the basis of wrongful termination ,
contrary to his
Honour ’ s
statement of principle that
the
issues for decision were determined by reference to the payment claim,
payment
schedule ,
adjudication application and
adjudication
response
(ground 2 ) ;
finding
that
it was not open to the
a djudicator to decide
A- Civil ’ s
claim for the retention monies on the basis that the
s ubcontract had been terminated by
Ceerose
because
this was not the basis of
A- Civil ’ s
claim
(ground 3 ) ;
finding that
the
issue raised by the second sentence of [112] of the
d etermination was whether cl 5 of the
s ubcontract ceased to apply following termination
( such that there was nothing preventing
it
from claiming the retention monies ), because no such issue was raised in the second sentence of [112] (ground 4 ) ;
engaging in impermissible merits review
by
formulating
the
issue
in [112]
of the adjudicator ’ s reasons
in a manner from which
the only available
conclusion
was
that the adjudicator had decided an issue
of which the
parties were not
on
notice
and which was not
within their reasonable
anticipation
(ground 5) ;
alternatively to
ground 5 ,
finding that
Ceerose
could not have reasonably anticipated that the
a djudicator might decide that
A-Civil
was entitled to the retention monies
following
Ceerose ’ s
termination of the subcontract
and reject
Ceerose ’ s
claim to have had recourse to the retention monies ,
because
Ceerose
could have anticipated that
the adjudicator would not accept
its interpretation of cl 5.2 and/or it would not succeed on the claimed deductions and set-offs
(ground 6) ;
finding that the issues
“
on the table
”
for decision by the
a djudicator did not extend
to
A- Civil ’ s
entitlement to the retention monies
following termination of the subcontract
and
Ceerose ’ s
recourse to those monies , in circumstances where Ceerose addressed those
issues
and the adjudicator decided them (ground 7) ;
finding , in
[23]
of the primary judgment ,
that the
a djudicator made no reference to
Ceerose
purporting to exercise its rights under cl 5.2
of the subcontract (ground
8) ; and
finding , in [25]
of the primary judgment ,
that it was of any consequence that the declin ed
deduction of $2,694,506 for the cost of completing the construction works was not linked to the claim for retention monies
(ground 9) .
During
the hearing
of the appeal , counsel for A-Civil
accepted
that
success on
grounds 8 and 9
alone would not
relevantly affect
the correctness of the primary judge ’ s decision .
The critical grounds of appeal were
grounds 1 to 7
and
[67]-[69] of the reasons of the primary judge . In the written and oral submissions,
A-Civil
took
a global
approach
to
those paragraphs and
the
grounds.
Ceerose , on th e
other hand,
made
submissions on each of the grounds , addressing
A- Civil ’ s
broader complaints
in the process .
I have
evaluated
A- Civil ’ s
arguments by reference to its
broader approach ,
assisted by
the focus
that
Ceerose
brought to the individual grounds .
A-Civil also prepared ,
at the time of
its
reply
submissions,
a
detailed
schedule of the arguments
that the parties respectively
advanced and the reasoning and conclusion of the adjudicator ,
to which I have had regard .
Was there a denial of procedural fairness?
Preliminary issue: characterisation of the adjudicator’s reasons
A-Civil
first
submitted that the
primary judge
mischaracterised
the
import of
the second sentence of
[112] of
the adjudicator ’ s
reasons , wrongly
read ing
the
sentence as raising
the issue of
the proper or correct interpretation of
cl
5 when that was
not
the
adjudicator ’ s
reasoning or
his
conclusion , much less
an
issue
that
the adjudicator identified
or raised .
A-Civil contended that in
so
construing
that
sentence,
his Honour
had impermissibly
supplemented the
adjudicator ’ s
reasons ,
dr awing
inferences that did not appear
on the face of that
sentence.
In oral
argument , counsel for A-Civil
submitted that
the adjudicator
had
concluded
that
A-Civil was entitled to release of the
retention monies
because the
subcontract had been terminated , without
attribut ing
that
conclusion
to
cl
5 or any other
provision of the subcontract .
A- Civil ’ s
encapsulation of the adjudicator ’ s conclusion
about the retention monies
served to
highlight
the
concern that the
primary judge
expressed in [68] .
T he adjudicator decided that
it
followed from
termination of the subcontract ,
without more
,
that
A-Civil
was entitled
to
the
release of the retention monies .
That conclusion necessarily
involved
a
further,
albeit
unexpressed ,
conclusion,
namely
that
cl
5.4 and
cl
5.2
of the subcontract ,
on which
Ceerose relied,
ceased
to operate up on termination.
W hat
his Honour direct ed
attention to
in [68]
was
the
issue
that underpinned
the
adjudicator ’ s conclusion .
That his Honour
referred to cl
5 as opposed to
the specific clauses is of no moment.
A-Civil described the alleged error of the primary judge
in [68]
as
involving
impermissible merits review , in the sense that h is Honour identified an issue
as he saw it ,
and
then addressed
how
the adjudicator
should have
resolved it .
Properly understood,
that is not what his Honour did.
In any event, his
Honour
did not make
the
error
of characterisation
for
which A-Civil contended .
Grounds 2, 4 and 5
of the Amended Notice of Appeal
related to
this issue .
T hey
should be dismissed.
Before moving to A- Civil ’ s
arguments regarding procedural fairness, it is necessary to
address
a
further
submission that A-Civil made regarding
the second sentence of
[112] of the adjudicator ’ s reasons , namely, that
it
also resolved the application
of the retention monies
against, or recourse to those monies for,
the various
deductions and set-offs that Ceerose had raised.
I do not accept that submission .
A s
counsel for Ceerose submitted during the hearing,
the adjudicator did not reason
from
his
conclusion regarding
Ceerose ’ s
claim for
deductions and
set-offs
to
his
conclusion regarding
the retention monies .
T he
second sentence of [112]
does not
contemplate or
accommodate
such a
process of
reasoning .
Did the adjudicator deny
Ceerose procedural fairness?
In
Demex
Pty Ltd v McNab Building Services Pty Ltd
[2023] NSWCA 261 ( “
Demex
” ),
which post-dated the decision of the primary judge
in this case ,
Kirk
JA (Mitchelmore and Adamson
J JA agreeing) considered
the
scope and content of the
requirement for procedural fairness under the
Security of Payment Act .
Without repeating his Honour ’ s careful
review
of
the applicable principles
and
the
provisions of the
Security of Payment Act
(as to which see [ 10 ] to [ 34 ] ) ,
it is useful to
refer to some of
what
his Honour
said by reference to
a number of
authorit ies regarding procedural fairness
generally and
in the context of the Security of Payment Act :
A statute conferring a power the exercise of which is apt to affect an interest of an individual is presumed to confer that power on condition that the power is exercised in a manner
that affords procedural fairness to that individual,
with that presumption operating unless it is clearly displaced by the particular statutory scheme : at [11], citing
Minister for Immigration and Border Protection
v
SZSS
J
(2016) 259 CLR 180; [2016] HCA 29 at [75].
Procedural fairness generally requires that those liable to be affected by a decision be given the opportunity of first being heard . That opportunity
“ would
ordinarily
require
the party affected to be
given the opportunity
of ascertaining the relevant issues and to be informed of the nature and content of adverse material ” , and
“ extends to
require the decision-maker to identify to the person affected any issue critical to the decision which is not apparent from its nature or the terms of the statute under which it is made ” :
at [12], quoting
Commissioner for ACT Revenue v
Alphaone
(1994) 49 FCR 576 at 590-591 ,
591-592 .
The general attributes of the doctrine must then accommodate
to the terms and structure of the statutory scheme in
question: at [15].
Specifically
in
relation to the Security of Payment Act, Kirk JA
referred
to :
the close delineation under the Act of the boundaries of a dispute, having regard to the limited material to which an adjudicator may have regard in determining an adjudication application, in s
22(2) (at
[16]- [17] );
the
tight
timeframe
for raising and resolving claims under the Act , as can be seen in
the provisions
for
serving a payment schedule (s
14), an adjudication application (s
17),
and
a response to an adjudication application (s
20) ,
the time for
the adjudicator ’ s determination
in
s
21
( subject to extensions by agreement )
(at
[18] ), and the fact that an adjudicator may
require
further submissions ,
under s
21(4),
but that does not lead to any automatic extension of time
(at [19]) ;
the interim nature of the adjudicator ’ s decision ,
which ,
noting
s
3(4) and s
32
of the
Security of Payment
Act , does not affect any rights the parties have under the construction contract (at [22] , citing
Probuild
Constructions (Aust) Pty Ltd v Shade
Systems Pty Ltd
(2018)
264 CLR 1; [2018] HCA 4
at [39]-[40] ) ;
and
the selection criteria for
adjudicators
in s
18 of the Act,
which do not
include legal
qualifications
and
which contemplate that adjudicators may be expected to bring their
experience and expertise to bear in making determinations (at [23]-[24]) .
The purpose of
the scheme
for which the Security of Payment Act makes provision
“ is best served by restricting the scope of intervention by the courts ”
(at [27],
quoting
Chase Oyster Bar
Pty Ltd v Hamo Industries Pty Ltd
(2010) 78 NSWLR 393; [2010] NSWCA 190
at [55]).
“ [ T ] he general requirement of procedural fairness that might ordinarily be applied by a decision - maker exercising statutory power is attenuated
in the context of the Act ” :
at [30].
O nly
a substantial denial of procedural fairness by an adjudicator in determining an adjudication application will
be a jurisdictional error under the
Security of Payment
Act: at [32].
W hat this means in practice will depend on the
particular circumstances
of cases , but
“ generally a conclusion of invalidity would only be reached if there was a significant departure from what would ordinarily be the requirements of procedural fairness for a person exercising a statutory power, and where that departure could be characterised as leading to substantial practical injustice in all the circumstances ” : at [32].
A-C i vil
alleg ed
error
on the part of the primary judge
regarding
procedural fairness
on two
bases .
First,
it contended that t he
basis
on
which the adjudicator determined the claim for retention monies was
in issue ,
or
“ on the table ” ,
by reason of submissions that
the parties
made
in the course of
the procedure under the
Security of Payment Act .
Second,
even if
the basis on which the adjudicator determined the claim was not
“ on the table ” ,
A-Civil contended that
Ceerose should have
anticipated that
the adjudicator
would
need to
decide the question
of
whether the retention money should remain with Ceerose or be released . It could not be said in those circumstances that there had been substantial practical injustice .
(1) Was the basis on which the adjudicator determined the claim for retention monies in issue or
“on the table”?
As Kirk JA observed in
Demex
(at [33]) , by reference to
Ausenco Operations Pty Ltd v Ferretti International Ottoway Pty Ltd
[2020] SASC 46 at
[61]
(Doyle
J) , whether an adjudicator has determined a matter on a basis for which the parties did not contend will often depend on the level of abstraction or specificity at which one articulates the issue in dispute.
His Honour further observed,
again by reference to
Ausenco
( at [62] ) ,
that beyond extremes
“ it is difficult to generalise as to the level of abstraction or specificity at which the obligation to afford procedural fairness must be addressed in a particular case ” .
A-Civil contended that the primary judge ’ s
conception of
what was on the table for decision
by the adjudicator
was too narrow .
It submitted that
Ceerose ’ s
submissions
raised the question of
entitlement to the retention sum as a matter of contractual interpretation, including pursuant to
cl l
5.2 and 5.4.
A-Civil
relied
in this regard
on
Ceerose ’ s
submission
that
it
had
lawfully terminated the subcontract , and
its further submission
that
A-Civil
was not entitled to the retention monies
on a proper construction of the subcontract .
Those
two
submissions
were
sufficient , in its submission,
to
raise
as an issue
the basis on which the adjudicator
ultimately
determined
A- Civil ’ s
claim for retention monies ,
which entailed acceptance of the first submission
and
rejection of the second .
This argument was the subject of ground 7 of the Amended Notice of Appeal.
As I noted above at [
33
], the adjudicator
reason ed
because
the contract had been terminated ,
A-Civil was entitled to release of the retention monies .
Ceerose
unquestionably
put in issue A- Civil ’ s
entitlement to the retention monies ,
but on the basis
that
cl
5.4
and/ or cl
5.2 of the subcontract
continued to operate .
By contrast ,
the
adjudicator ’ s
reason ing
in [112]
could only have been premised on
those clauses
having no
operation
beyond
termination of the subcontract.
The primary judge was correct to conclude that
Ceerose’s
submissions did not raise
as an issue
the
path of reasoning
and
conclusion
that
the adjudicator ultimately adopted .
A-Civil relied
additionally
on
the
statement in
Ceerose ’ s
payment schedule that A-Civil had
“ no right or entitlement to claim its retention under the Subcontract
or otherwise
”
( at [121],
emphasis added ; Ceerose made a similar statement
at
[123] ) .
The
words
“ or otherwise ”
do not have the effect for which A-Civil contends, of broadening the scope of
Ceerose ’ s
response to
the
claim for the retention monies
so as to
accommodate
the basis on
which the adjudicator
ultimately
determined that claim.
As counsel for Ceerose submitted,
s
20(2 B ) of the
Security of Payment Act
provided
one
explanation for
its inclusion
of those words , as
that
provision
prohibit s
a respondent to an adjudication application
from
including ,
in its response ,
a ny reasons for withholding payment unless those reasons have already been included in the payment schedule provided to the claimant.
Additionally,
and
as counsel for Ceerose further submitted,
the use of
“ or otherwise ”
would not reasonably be construed as
operating to
put
on the table
every
issue that could conceiv ably fall within its terms.
A-Civil
next
submitted that
it
had
raised ,
in
its
adjudication application,
what was to be done
with the retention
monies
in the event that
t he
adjudicator
decided that
Ceerose :
( i )
had lawfully terminated
the subcontract for breach ,
but (ii)
was not entitled to have recourse to
the retention
monies .
This argument was the subject of ground 3 of the Amended Notice of Appeal.
A-Civil
relied on
[44]-[52] of its
adjudication application .
Accepting that its primary submission to the adjudicator was that Ceerose had wrongfully terminated the subcontract ,
A-Civil argued that
it
had also submitted that
its right to
the
progress payment
(which
includ ed
the retention
monies)
was unaffected by termination.
A-Civil contended that although
his Honour
had stated, correctly, that
it was necessary to have regard to the adjudication documents to understand
the
issues for determination , his Honour had
overlooked this aspect of its submissions.
The section of the adjudication
application
on which A-Civil relied
was
headed
“ Ceerose ’ s
Claims have no Prospects of Success ” . The focus of that section of its application was
what
Ceerose
had
advanced ,
in
the payment schedule ,
in the way of
set-offs , deductions and costs to complete,
on the basis of
which
Ceerose
contend ed
that it did not owe A-Civil
any money .
T he section is not
lengthy
and
it is useful to set it out :
“(44)
Ceerose spuriously pursues negative valuations, purported setoffs and deductions and costs to complete in the [payment schedule (PS)], summarised at paragraph 6 of the PS.
(45)
Ceerose’s
allegations are untrue and misleading.
(46)
A-Civil
denies paragraphs 4 and 5 of the PS.
(47)
Ceerose contends that A-Civil was in substantial breach of the Contract, that A-Civil repudiated the Contract, to
[sic]
which Ceerose accepted and terminated the Contract. This is not true, A - Civil was
not in breach of the Contract and did not repudiate the Contract.
(48)
A-Civil submits that Ceerose wrongfully terminated the Contract. Ceerose was not justified in terminating the Contract and A-Civil relies upon its response to
Ceerose’s
purported show cause notice dated 7 June 2022
… .
(49)
A-Civil’s
right to a progress payment is not affected by termination of the Contract. The Court of Appeal in
Brodyn Pty Ltd (t/as Time Cost & Quality) v Davenport
[2004] NSWCA
394 at [62] to [66] decided that s 8(2) of the Act does not provide that reference dates cease on the termination of a contract or cessation of work.
(50)
A-Civil has an accrued right to a progress payment under the Act.
…
(51)
A-Civil’s
view is that
Ceerose is not entitled to set off any of its claimed amounts under any circumstances because the amounts claimed are unliquidated and not amounts due but amounts claimed to be due.
(52)
Ceerose has failed to demonstrate with its setoffs
to:
(a)
identify any express or implied provisions of the Contract at
[sic]
which it alleges to have been breached or which it relies upon for its
entitlement;
(b)
identify the act of omission of A-Civil that constitutes an alleged
breach;
(c)
demonstrate any causal nexus between the alleged breach of the Contract and the alleged loss and damage
suffered,
and;
(d)
identify the quantum of its loss or damage claimed in respect of each alleged breach.
(53)
Further or in the alternative,
Ceerose’s
setoffs are damages and are not able to be valued or considered by the Adjudicator in this
particular forum . As was distinguished in
Quasar Constructions v
Demtech
Pty Ltd
[2004] NSWSC 116,
the relevant concepts do not
extend to damages for breach of contract.”
(Footnotes omitted.)
I n the written submissions
on the appeal ,
A-Civil emphasised [49]-[50]
and [52]
in
the above extract .
Those
first
two paragraphs
address ed the statutory basis of
A- Civil ’ s
right to a progress payment ,
as opposed to the
contra ct ual
basis
of
A- Civil ’ s
right
or entitlement
to
the
retention
monies .
In oral submissions,
c ounsel for
A-Civil
emphasised
[ 52 (c) ]
and
[52 (d)]
of the adjudication application,
submitting that
because
those subpa r a graph s
assumed
lawful termination
of the subcontract
they
rais ed
as an
issue ,
admittedly
“ faintly ” ,
what was to be done with the retention monies
in the event that
the
adjudicator found the
contract was terminated
but
rejected
Ceerose ’ s
claims
for deductions and setoffs .
C onsistently with the balance of this section of
A- Civil ’ s
adjudication
application,
the focus of
[52], including (c) and (d),
was
Ceerose ’ s
claim ed
deductions ,
setoffs
and cost s
to complete .
Neither the paragraph nor any other part of this section of the application
said anything about
A- Civil ’ s
claim to retention monies.
Rather, that
issue was the
subject
of
the
immediately following
section of the
adjudication
application , in which
A-Civil
specifically
responded to
Ceerose ’ s
submissions
and ,
in that context :
r elied
on what it alleged was
Ceerose ’ s
wrongful termination of the subcontract
( at [57]-[58] ) ; and
did not advance
a ny
submission
in support of its entitlement
to the retention
monies ,
let alone
submit
that it was entitled to
those monies
if
the adjudicator
were
to find
that
the subcontract was terminated and
that
Ceerose ’ s
claims
for
deductions and setoffs
were
un substantiated.
It follows that
I would dismiss
g round s
3
and 7 of the
Amended Notice of Appeal .
(2) Should Ceerose have foreseen, or anticipated, that
the adjudicator would
reach the
conclusion
in the second sentence of [112] ?
A-Civil
next
submit ted
that
both parties
should
have
anticipated that
the adjudicator
might conclude that A-Civil had a right to the retention monies notwithstanding
Ceerose ’ s
termination of the
s ubcontract.
I f
the adjudicator
accept ed
that the subcontract was
terminated ,
but
reject ed
Ceerose ’ s
alternative
argument s
regarding
cl l
5.4 and 5.2 ,
the adjudicator would
still
have
to decide
whether
A-Civil was entitled to the retention monies, as a matter of
contractual interpretation or under the
Security of Payment Act .
Ceerose was legally represented
and
should have anticipated that possibility .
A-Civil
relied
on
the decision of
JKC
Australia LNG Pty Ltd v
I
NPEX
Operations Australia Pty Ltd
(2018) 41 NTLR 149 ;
[2018] NTCA 6
( “
JKC
” )
as instructive in this context .
In
Multiplex Constructions Pty Ltd v
Luikens
[2003] NSWSC 1140,
Palmer J said at [76] that a
“ payment
claim
and a payment schedule are, in many cases, given and received by parties
who are experienced ” .
After quoting this statement in
Demex
at [84],
Kirk JA
stated
that
“ [ g ] iven
experienced parties, and the tight timeframes
under the legislative scheme,
there is no requirement that every step in a payment
claim
or adjudication application must be spelt out in express words ” .
Ceerose accepted that
it
w as
a sophisticated party with legal
representation
and
it
should have anticipated that the adjudicator
might decide that it did not have a right of recourse to the retention monies.
H owever,
it
submitted that it
should
not
have anticipated
the conclusion
that A-Civil was entitled to those monies
merely
because
the subcontract had been terminated , noting that
A-Civil
was
represented
and had
advanced no such contention.
It
was apparent from the payment claim that A-Civil was
claiming
the
retention monies , but it did not
articulate
a ny
basis
for that
claim
in that document .
Then, in
its
adjudication application,
A-Civil
adopted
a position that
was inconsistent with the
subcontract
being
at an end , relying on
Ceerose ’ s
purportedly wrongful termination of the subcontract.
Having regard to the
matters
on which the parties joined issue
in the documents
that the adjudicator is
limited to
considering ,
I do not accept
A- Civil ’ s
submission
that
Ceerose
should have anticipated
that the adjudicator would decide
that
A-Civil was entitled to
the retention monies
on the basis that he did .
Contrary to
A- Civil ’ s
reliance
on
JKC
,
the facts of that case
provide a useful counterpoint to
the present .
The
a djudicator
decided
that
a
provision
of the
Construction Contracts (Security of Payments) Act
(NT)
regarding
the
importation
of
certain
provisions of the Act into deficient contracts
(s
20)
should
apply
because
the
contract
in issue
was deficient
in a relevant respect.
T he
practical
consequence
was
that the notice of dispute
was served out of time : at [14] .
The adjudicator
had invited the parties to make submissions on this issue
in advance of his decision ,
and
they
had
each
responded to the effect that
there was no basis for
s
20 to operate : at [11]-[12 ].
The
denial of procedural fairness alleged was
that the adjudicator had not foreshadowed that he would decide that the parties ’
submissions on the issue
were wrong
and that the notice of dispute was served out of time .
In
allowing the appeal from the trial judge ’ s conclusion that there was a denial of procedural fairness,
the
Northern Territory
Court of Appeal
observed that
“ once
the
A djudicator
sought submissions on whether cl
6 was to be implied into the [contract ]
the possibility of a finding that no notice of dispute was given within 14 days was clearly flagged ” : at [49].
Further,
the consequence of a finding in those terms
“ would inevitably be that INPEX would be obliged to pay the whole sum in dispute to JKC unless there was some compelling reason why that should not be so ” : at [50].
By contrast, in
the present case, the
a djudicator gave no indication of
the issue
on the basis of
which he
concluded that A-Civil was entitled to
the retention monies ; and
the proposition that
those monies
had to
be released
upon termination
of the subcontract
was
not
inevitable.
A- Civil ’ s
contention that
Ceerose
should have anticipated the argument that the adjudicator ultimately found to be decisive was the subject of ground 6. It should be dismissed.
The primary judge ’s conclusion was
correct
Ground 1 of the Amended Notice of Appeal took issue with the primary judge ’ s general conclusion
that there was a material denial of procedural fairness . As I have noted above,
consistently with authority it is necessary for the denial of procedural fairness to be substantial , with s atisfaction of
that
requirement turns on
whether
the error
was substantial :
Demex
at
[ 32 ] .
I agree with the conclusion of the primary judge that
the
error
in the present case
met that description .
The
denial of procedural fairness
was also material ,
in the sense
that
there was a realistic possibility that the decision could have been different but for the denial of procedural fairness :
Minister for Immigration and Border Protection v SZMTA
(2019) 264 CLR 4 2 1; [2019] HCA 3 at [45] ;
MZAPC v Minister for Immigration and Border Protection
(2021 )
273 CLR 506 ; [2021] HCA
17
at [2], [85] .
I have referred
above to the
primary judge ’ s identification of the
arguments that
Ceerose was precluded from putting to the adjudicator
on the issue
he found
to be determinative
(see [
28
] above) .
A-Civil
contended
on the appeal
that
those
arguments were
no more than
refinements
of
Ceerose ’ s
recourse arguments ,
referring to
Downer Construction (Australia) Pty Ltd v Energy
Australia
(2007) 69 NSWLR 72 ; [2007] NSWCA 49
("
Downer
” ) .
The reasoning of
Giles JA
in
Downer
at [91] ,
on which A-Civil relied, was
that there is no denial of
procedural fairness if
a party
could have put its arguments in a different or better way .
In my view, that
reasoning does not apply
to
the arguments that
Ceerose could have
put
to
the adjudicator
if he
had
given
Ceerose
the opportunity
to
make submissions on the reasoning that he ultimately adopted as determinative .
A-Civil
submit ted
that
as a consequence of
the primary judge ’ s reasoning ,
a djudicator s would have
to
make decisions
in terms
closely reflecting the arguments
the
parties
advanced ,
or
submit their own views for further submissions . It submitted that
such an approach
was
inconsistent with the
tight timeframe s
for which
the
Security of Payment Act
makes provision
( to which I have referred above ) .
Th e
submission misunderstands
the
nature of the
denial of procedural fairness
that the primary judge found and that I would uphold ,
namely, that the
adjudicator
made a decision
on a basis that no one put
and that was not
properly
anticipated .
It
turns on
its particular facts .
The additional reasons of Leeming JA , with which I agree,
are also relevant in this regard.
Ground 1 should be dismissed.
It follows that it is unnecessary to consider grounds 8 and 9, noting
the submission of counsel for A-Civil to which I referred at [
31
] above , and they should also be dismissed.
Conclusion
I propose the following orders:
The appeal is dismissed.
The appellant is to pay the
first
respondent ’ s costs of the appeal.
**********
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Decision last updated:
01 February 2024
Official source: https://www.caselaw.nsw.gov.au/decision/18d5d507483ceac05aba5a23