A.N.T. Building Pty Ltd v Vibe Electrical Pty Ltd [2023] NSWSC 615
Catchwords: CIV IL PROCEDURE – whether proceedings should be dismissed for want of prosecution with due dispatch
Supreme Court
New South Wales
Medium Neutral Citation:
A.N.T. Building Pty Ltd v Vibe Electrical Pty Ltd [2023] NSWSC 615
Hearing dates:
8 June 2023
Date of orders:
8 June 2023
Decision date:
08 June 2023
Jurisdiction:
Equity - Technology and Construction List
Before:
Stevenson J
Decision:
Application to dismiss proceedings to be dismissed; plaintiff to pay the costs of the application on an indemnity basis and
by 28 July 2023 ; such costs to be assessed as a global figure; proceedings to be dismissed if those costs not paid
Catchwords:
CIV IL PROCEDURE – whether proceedings should be dismissed for want of prosecution with due dispatch
Legislation Cited:
Building and Construction Industry Security of Payment Act 1999 (NSW)
Civil Procedure Act 2005
(NSW)
Uniform Civil Procedure Rules 2005
(NSW)
Cases Cited:
Hoser
v
Hartcher
[1999] NSWSC 527
Category:
Procedural rulings
Parties:
A.N.T. Building Pty Ltd (Plaintiff)
Vibe Electrical Pty Ltd (Defendant)
Representation:
Counsel:
B Le Plastrier (Plaintiff)
B Lloyd (Defendant)
Solicitors:
Flame Tree Legal (Plaintiff)
Brander Smith McKnight Lawyers (Defendant)
File Number(s):
2021/284342
EX TEMPORE JUDGMENT (REVISED)
The plaintiff ("the
Builder ") brings these proceedings against the defendant ("the
Contractor "). The claim relates to contracts between the
Builder
and the
Contractor
in June
2015 and April
2016 arising from developments at Manly and Woollahra. The claim made by the
Builder
against the
Contractor
relates to alleged incomplete and defective work and delay.
The matter before me today is the defendant's
N otice of
M otion of 12
April
2023 seeking an order under
Uniform Civil Procedure Rules
2005
(NSW) ,
r
12.7(1) ,
that the proceedings be dismissed for, in effect, want of diligent prosecution.
In
April
2019 ,
the
Builder
commenced proceedings in the District Court of New South Wales against the
Contractor
making the same claims for incomplete and defective work and delay as are being made in these proceedings. The
Builder
prosecuted those proceedings so
unsatisfactorily
that
in April
2020
the
Contractor
sought
and obtained an order that those proceedings
be dismissed for want of prosecution.
The
Builder
commenced
these
proceedings on 6
October
2021 seeking, as I say, the same relief arising from the same matters as were made in the District Court proceedings.
In these proceedings, o n 2
July
2022, by consent,
an order
was made that the
Builder
serve its lay and expert evidence by 14
October
2022. No evidence was served.
The matter was
before the Court on 3
February
2023, on which occasion the
Builder
proposed that
the
time to serve its lay evidence be extended to 28
February
2023 and the time to serve its expert evidence be extended to 6
April
2023.
Recognising the position that it was in, the
Builder
proposed that those orders be subject to a guillotine order .
I ndeed, in his affidavit made on 3
February
2023, the sole director of the
Builder , Mr
Gleeson, deposed that, "I understand that this means unless I comply with the order
it is likely I will not be able to file any further evidence in the proceedings".
The solicitor for the
Builder
deposes he spent much time in February
2023 working with Mr
Gleeson to prepare Mr
Gleeson's affidavit including, Mr
Wells said, working with Mr
Gleeson for 15
hours on 27
February and 19
hours on 28
February
2023.
The affidavit was served in the early hours of 1
March
2023 . N othing turns on that slight delay.
However, the affidavit referred to an exhibit
containing 1534 pages. That exhibit
was not served with the affidavit due to, apparently, difficulties uploading its bulk into Mr
Wells' email system. It was not served until early May. The "explanation" given for that is that there was "pagination" and "cross-referencing" (or similar) problems. It is hard to understand
how this
could have caused such a delay.
Mr
Wells also has deposed
that , despite all the work he did in February
2023, he did not have an opportunity to "review" the affidavit as he would "usually do" let alone have counsel cast his or her eye over the document.
Ultimately, late in March
2023, Mr
Wells got instructions to brief counsel.
It was in that circumstance that the
Contractor
filed its motion of 12
April
2023 seeking to have the proceedings dismissed for want of prosecution.
Despite the consent guillotine order
of 3
February
2023 that the
Builder
serve its expert evidence by 6
April
2023, the relevant expert, Mr
Adrian Jamieson,
a
quantity surveyor, was not retained until 12
May
2023. Again, no sensible explanation has been given for that delay.
The position now is that the
Builder
has foreshadowed serving a further affidavit of Mr
Gleeson today . This is
s aid to be in the final stages of preparation ,
despite the fact that
Mr
Wells deposed on 12
May
2023 that Mr
Gleeson's supplementary affidavit was "well advanced".
Mr
Wells has
also
deposed :
“Generally, the supplementary affidavit is required to rectify various admissibility issues and rectify the exhibit (that is, replace black and white photographs with colour photographs, A4 pages with A3 pages and replace incomplete documents with complete documents). The supplementary affidavit will include evidence as to the time and date photographs were taken. It will also provide foundation for conclusions and include more precise details with respect to various aspects of Mr Gleeson’s evidence so that they plaintiff’s case can be better understood by experts, the
defendant
and the Court.”
Mr
Le
Plastrier , who appears today for the
Builder , informed me that as well as dealing with the matter to which Mr
Wells deposed, the new affidavit will deal with some matters of substance.
Mr
Jamieson has sworn an affidavit confirming that he has been
retained, and
foreshadowing that he expects to be in a position to be able to produce a report by 28
June.
Before me today also is the
Builder 's notice of motion of 2
June seeking leave to rely upon "further lay evidence" and "expert evidence" in these proceedings. The leave that will be sought is to rely on Mr
Gleeson's
further affidavit
and Mr
Jamieson's report once they are to hand.
T he circumstances in which a court will dismiss proceedings for want of prosecution
are
well-established, and
include, as Simpson J (as her Honou r
then was) stated in
Hoser
v
Hartcher
:
[1]
(a) t he ultimate question is whether, on balancing the prejudice to the respective parties by making or not making an order, justice demands that the action be
dismissed;
(b)
the discretion should be exercised only in a clear case where it is manifestly warranted
… as is generally the case with discretionary decisions, each case depends upon its own
facts;
(c) any explanation offered by the plaintiff for the delay in proceeding must be
considered;
(d)
personal blamelessness on the part of a plaintiff
(as distinct from any tardiness or other fault on the part of his/her/its legal representative) is relevant. (Footnotes omitted.)
This is a case where I have given serious consideration to taking the drastic step of dismissing the proceedings.
I am
however
persuaded that notwithstanding the
manner in which
the
Builder
has been vexed by the way these proceedings have been conducted, it would not be in the interests of justice to shut the plaintiff out from pursuing a claim which may well have merit.
Accordingly, I propose to give what the
Builder
should understand to be one last chance to get its house in order, and to
diligently
prosecute these proceedings to their conclusion. The
Builder
should understand that no further procedural delinquency of any kind, let alone of the kind that I have described in these reasons, will be tolerated.
Accordingly, I propose to dismiss the
Contractor 's notice of motion.
Mr
Le
Plastrier , in his
written
submissions, somewhat ambitiously I thought, suggested the motion should be dismissed with costs. I do not propose to do that. I propose to order
that, notwithstanding the fact that the motion is to be dismissed, the
Builder
pay the
Contractor 's costs of the motion on an indemnity basis. I propose to assess those costs on an indemnity basis under section 98(4) of the
Civil Procedure Act
2005
(NSW) . I
propose
then order
that that figure be paid within 14 days, and order
that if that amount is not paid, for that reason alone, the proceedings will stand dismiss ed .
I propose to defer considering whether the
Builder
should have leave to rely upon Mr
Gleeson's further affidavit, and Mr
Jamieson's foreshadowed report,
and also
defer the question of whether, how and what terms, the
Builder
should pay any costs of the
Contractor
that will be thrown away should leave be granted.
[The Court adjourned to enable the parties to consider His Honour’s reasons]
Since giving the above judgment earlier today, the Builder has adduced evidence from Mr
Gleeson to the effect that it issues payment claims under the
Building and Construction Industry Security of Payment Act 1999
(NSW)
at the end of each month and usually receives payment s
in response to those building claims around the middle of the following month.
The moneys to be received in respect of the payment claims served at the end of May 2023 have been, Mr
Gleeson says, "wholly allocated to pay staff wages, trade subcontractors and suppliers".
Mr
Gleeson deposes that the Builder anticipates serving payment claims at the end of June and to receive funds in respect of those payment claims around the middle of July. In those circumstances, Mr
Gleeson deposes that ,
were the Builder obliged to pay a sum on account of the costs of the Contractor's motion prior to that, it would "need to pay that in priority to trades and suppliers and this will have adverse consequences on [the
B uilder] carrying out and complying with its contract obligations to its clients".
It appears to me that it is not in the interests of either party that the Builder's ability to continue trading be jeopardised .
I n those circumstances I am persuaded that I should vary what I said this morning and order that if the Builder does not pay the sum I propose to fix as the Contractor's costs of its motion by 28
July 2023, then the proceedings will stand dismissed.
As to what the gross sum costs order should be, I have received evidence from the Contractor's solicitor
to the effect that the actual costs sustained by the Contractor is
$19.594 ,
comprising solicitors' fees of $6,300, counsel's fees of $10,300 and the motion filing fee of $1,334.
That total figure obviously represents the total of the costs actually incurred by the Contractor. I foreshadowed this morning that I would make an order that costs be on
an
indemnity basis. It may be that the total of $19,594 is marginally above the costs that the Contractor would recover on an indemnity basis.
However,
I see no reason to discount that figure for today's purpose.
The parties should b r ing in short minutes to give effect to these reasons.
**********
Endnote
1.
[1999] NSWSC 527 at [20]-[23].
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Decision last updated:
08 June 2023
Official source: https://www.caselaw.nsw.gov.au/decision/1889965f792fede4292d70b8