A-Civil Aust Pty Ltd v Meso Solutions Pty Ltd [2023] NSWSC 372
Catchwords: BUILDING AND CONSTRUCTION – Building and Construction Industry Security of Payment Act 1999 ( NSW) (“the Act”) – adjudication determination – whether s 17 (2) notice valid – whether clause requiring certain documents to be attached to payment claim in contract is void pursuant to s 34 of the Act CONSUMER LAW — m isleading or deceptive conduct — whether representations were made
Supreme Court
New South Wales
Medium Neutral Citation:
A-Civil Aust Pty Ltd v Meso Solutions Pty Ltd [2023] NSWSC 372
Hearing dates:
5-6 December 2022, 8 February 2023
Date of orders:
17 April 2023
Decision date:
17 April 2023
Jurisdiction:
Equity - Commercial List
Before:
Richmond J
Decision:
Application challenging the decision of the adjudicator dismissed. Claim for misleading or deceptive conduct under the ACL also dismissed, as no relevant
misrepresentation was
made.
Catchwords:
BUILDING AND CONSTRUCTION –
Building and Construction Industry Security of Payment Act 1999
( NSW)
(“the Act”) – adjudication determination – whether
s 17 (2) notice valid
– whether clause requiring certain documents to be attached to payment claim in contract is void pursuant to s 34 of the Act
CONSUMER LAW —
m isleading or deceptive conduct —
whether representations were made
Legislation Cited:
Building and Construction Industry Security of Payment Act 1999
(NSW), ss 8, 9, 11, 13, 17, 34
Competition and Consumer Act 2010
(Cth), Sch 2
(Australian Consumer Law), ss 18, 20, 21, 232, 236
Building and Construction Industry Security of Payment Amendment Bill 2013
Cases Cited:
All Season Air Pty Ltd v Regal Consulting Services Pty Ltd
[2017] NSWCA 289
Blue v Ashley
[2017] EWHC 1928 (Comm)
Briginshaw
v
Briginshaw
(1938) 60 CLR 336; [1938] HCA 34
Clyne v Deputy Commissioner of Taxation
(1981)
150 CLR 1 ; [1981] HCA 40
Edelbrand
Pty Ltd v H M Australia Holdings Pty Ltd
[2012] NSWCA 31
Et-China.com International Holdings Ltd v Cheung
[2021] NSWCA 24 ; 388 ALR 128
Griffin Energy Group Pty Ltd v ICICI Bank Ltd
[2015] NSWCA 29;
317 ALR 395
Helou
v PD Mulligan Pty Ltd
(2003) 57 NSWLR 74;
[2003] NSWCA 92
John Holland Pty Ltd v Roads and Traffic Authority of New South Wales
[2007] NSWCA 19 ; 23 BCL 205
Jones v Dunkel
(1959) 101 CLR 298; [1959] HCA 8
Kallin
Pty Ltd v ACN 107 851 847 Pty Ltd
[2018] NSWSC 124
Plaza West Pty Ltd v Simon’s Earthworks
(NSW) Pty Ltd
[2008] NSWCA 279
Probuild
Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd
(2018) 264 CLR 1; [2018] HCA 4
Quickway
Constructions Pty Ltd v Electrical Energy Pty Ltd
[2017] NSWSC 1140
Watson v Foxman
(1995) 49 NSWLR 315
Category:
Principal judgment
Parties:
A-Civil Aust Pty Ltd (Plaintiff)
MESO Solutions Pty Ltd (First Defendant)
Navid King (Second Defendant)
Adjudicate Today Pty Ltd (Third Defendant)
Representation:
Counsel:
Mr J Foley (Plaintiff)
Mr D Weinberger (First Defendant)
Solicitors:
M&A Lawyers (Plaintiff)
HBA Legal (First Defendant)
IHS Law (Second Defendant and Third Defendant)
File Number(s):
2022/00251664
JUDGMENT
In these
proceedings
the plaintiff,
A-Civil
Aust Pty Ltd (
A-Civil
) ,
challenges the validity of
a payment claim issued by the
f irst
d efendant,
Meso
Solutions Pty Ltd (
Meso
) ,
under the
Building and Construction Industry Security of Payment Act 1999
(NSW) (
the Act
)
on 30 May 2022 (
Claim 16
)
and an adjudication determination made by the second defendant on 12 August 2022 in respect of that payment claim (
Determination
) .
A-Civil
contends
that
Meso
made representations to A-Civil to the effect that A ‑ Civil
could ignore Claim 16, A-Civil
did not
need to respond to it with a payment schedule and that
Meso
would not proceed to the adjudication of
Claim 16
under the Act . A-Civil contends that
by taking steps to proceed to an adjudication of Claim 16 contrary to those representations,
Meso
engaged in
misleading and deceptive conduct in contravention of s 18 of the Australian Consumer
L aw
(
ACL
), or a lternatively,
unconscionable conduct
in contravention of s 20 and
s
21 of the ACL . A-Civil seeks injunctive relief under s 23 2
of the ACL, or alternatively damages under s 236 of the ACL. A ‑ Civil originally put an alternative claim in estoppel based on the
making of the
alleged representations but accepted at the
final
hearing
(correctly in my view)
that
this claim did not add anything to its claim under the ACL and did not press it.
A- Civil ’ s
alternative case is that the Determination is affected by jurisdictional error
because
a t
the time of the notice purportedly issued by
Meso
under s
17(2) of the Act the
amounts the subject of Claim 16 had
not
become due and payable under the
construction
contract and consequently
the Determination
is invali d
and should be quashed.
The
s econd
d efendant and
t hird
d efendant did not take any active part in the proceedings.
Evidence was given on behalf of A-Civil by Nasser Matta, the chief executive officer of A-Civil (
Mr Matta
) and Chaudhury
Mostafiz , the project manager of A ‑ Civil (
Mr
Mostafiz
), and
on behalf of
Meso
by Timothy Orr, the managing
director of
Meso
(
Mr Orr
) and Edward
Bobek , the technical director of
Meso
(
Mr
Bobek
). Each of them was cross examined.
Background
In 2020 A-Civil was engaged by Paynter Dixon Constructions Pty Ltd
(
Paynter Dixon
)
to undertake work for the construction of a car park for the Parramatta RSL Club located at 2 Macquarie Street, Parramatta
(
the Site
) , and they
entered into
a formal contract for this work on 20 November 2020.
On 24 March 2020,
Meso
sent a letter
of offer
to A-Civil containing
the
proposed terms
on which
Meso
would undertake
sheet piling, anchoring, dewatering and permanent basement wall works
for
A-Civil at the Site (
the Project
) .
Following this, there
were discussions between A-Civil and
Meso
regarding pricing of the work to be undertaken by
Meso . While the formal contract was not entered into until 28 June 2021, A-Civil and
Meso
had reached a broad consensus as to the pricing and nature of the work to be performed by
Meso
by December 2020 because
Meso
ordered sheet piles in November 2020 which were delivered to the
S ite on 1 December 2020 and
Meso
commenced works on the
S ite on 17
December 2020.
On 30 March 2021, A-Civil sent
to
Meso
by
email
the proposed
contract
to be entered into by A-Civil and
Meso
for the Project . In late May 2021 Mr
Bobek
sent
emails to A-Civil giving detailed comments on the
draft
contract.
On 23
June 2021 Mr Orr and Mr Matta had a meeting at which they discussed the alterations to be made to the
draft
contract following which Mr
Mostafiz
sent
by email
a revised version of the contract to Mr
Bobek
for signature.
On 28 June 2021, A-Civil and
Meso
entered into
the
contract
under which
Meso
undertook to perform foundation piling works at the Site for a lump sum of $1,406,745 (ex GST)
(
Contract
) . The Contract
contained
an attachment entitled
“ General Conditions of Agreement ”
(
General Conditions
) .
C lause 8.3
of the General Conditions required
that all payment claims should be accompanied by certain documents .
Clause 8.3 is set out later in these reasons.
It is not in dispute that in none of the emails or discussions before the final version of the
C ontract was sent to A-Civil on
around
2 3
June 2021 did Mr
Bobek
or Mr Orr raise any concern with A-Civil as to cl 8.3 of the
General Conditions . However, Mr
Bobek
gave evidence that he
had a telephone conversation with Mr
Mostafiz
on 28 June 2021
before
Meso
executed the Contract
during which he raised a concern that the
requirement s
for payment claims under cl
8.3 were onerous or too hard to comply with and Mr
Mostafiz
said words to the effect that
Meso
could
“ just keep on doing what you are doing ” .
Mr
Mostafiz
accepts that he had a conversation with Mr
Bobek
that day in which he advised Mr
Bobek
that he had emailed him
the Contract
and
requested
that he sign the Contract , but he denies saying the words attributed to him by Mr
Bobek .
Prior to
entering into
the Contract, between 23 November 2020 and 25 June 2021 (inclusive),
Meso
issued 9 payment claims to A-Civil.
Payment Claim 9, issued on 25 June 2021, indicated that $429,881.70 was outstanding prior to
entering into
the Contract.
A further 6 payment claims were issued
in the period from when
the Contract was entered into
and the issue of Claim 16 on 30 May 2022
in respect of which
A-Civil did not issue any payment schedules, nor did
Meso
issue any s 17(2) notice s
or lodge any adjudication application s .
A-Civil made payments to
Meso
amounting to $714,621.56 from 15
December 2020 to 23 December 2021
but no further payments after that time.
B etween December 2021 and May 2022, Mr Orr and Mr
Bobek
made repeated attempts to follow up the outstanding amounts with A- Civil ’ s
representatives Mr
Matt a , his son Mr George Matt a
and Mr
Mostafiz .
It is clear that
Meso
understood that A- Civil ’ s
delay in making payments to
Meso
was due in large part to the failure of Paynter
Dixon
to pay amounts outstanding by it to A-Civil.
On 28 January 2022, Mr
Bobek
sent an email to Mr Matta, copying in Mr Orr, which stated :
Attached are our claim 14 for Parramatta. Do you require us to prepare any documents for any legal action or meeting with Paynter's to force them to pay the outstanding amount?
If it helps force the issue, we can lodge an adjudication application and withdraw it before it is assigned to an adjudicator.
We are more than happy to attend a meeting with you and Paynter's to sort this out.
I tried calling you to discuss tactics Can you call me or Tim please Having this large amount of outstanding money is affecting our suppliers.
Also, the
Monavale
Surf Club Invoice still hasn't been paid. Our understanding as a favour to you we placed the sheets on short notice at a discounted rate, to be paid as soon as the job was completed.
O n
4 February 2022, Mr
Bobek
sent the following email to Mr Matta:
I understand that
Paynters
have sent A-Civil a back charging document and that you advised
Tim
you would email it to us.
Could you arrange/instruct your accounts department to forward the documents thanks, to prepare the response for our scope thanks?
On
7
February 2022, Mr
Mostafiz
responded by email to Mr Orr as follows:
Please find the attached back charges related to RC wall works. We need your assistance to
reply back
to PDC by COB tomorrow. Please see below drop box link for details.
The drop box contained
a large number of
documents relating to Paynter Dixon ’ s claim against A-Civil for back charges which
apparently included
work performed by
Meso
under the Contract. Mr Orr replied by email
to Mr
Mostafiz
on the same day
that it was not possible to respond by close of business on the following day, and instead a meeting was arranged with Paynter Dixon in early March to discuss the matter.
T his meeting took
place
but
it appears that
Meso ’ s
attendance was short and
inconclusive
(see [ 40 (3)] below) .
On 1 April 2022, Mr
Bobek
sent an email to Mr Matta seeking to progress further discussions on how to deal with the Paynter Dixon back
charges claim which included the following:
A few weeks back I called
George
and he informed me you were away and would call when you were back.
I trust you are well and will call Tim to discuss. We need to get the ball rolling on this as the window for using the payments act is closing.
The payments act is a relatively cheap way to proceed. If we wait and are forced to use the credit act, it will run into a $50,000.00 legal bill.
The longer we leave it, the more difficult it will become to prepare the adjudication application, as this will need to be very detailed in this situation.
Mr Orr later that day sent a follow up email to Mr Matta as follows:
Can you give me a call as soon as
you
are able so that we can progress this please? If you can provide us with the information that Eddie has
requested
I think we should be able to develop a reasonably strong argument for the payment of the remaining monies and we are fairly owed. We do need to bring this to a conclusion as it really has caused us some harm.
O n
1 May 2022, Mr
Bobek
sent an email to Mr Matta attaching a further payment claim:
Attached are our claim 15 for Parramatta. Tim and I have made numerous attempts to first to arrive at a figure for
Meso’s
outstanding monies and then to understand the strategy A-Civil is undertaking to recover our money from Paynter’s.
Again, we can only ask what is Paynter’s argument that they have not paid us at least the shoring scope immediately. They could not possibly have an argument that can stand up.
We have also calculated a fair price for the basement walls on past emails from Paynter’s and their form worker. We would like to discuss
this
scope with you to understand Paynter’s position on this scope.
If Paynter’s does not come to a fair agreed amount during this payment period, we will be considering all our options.
The
Monavale
Surf Club Invoice still hasn’t been paid, $15,000.00 plus GST. As a favour to you, we placed the sheets on short notice at a discounted rate, to be paid as soon as the job was completed. Fair is fair Nasser, why are they not paying could you send me the contact number of the builder so that I can call them to discuss it.
Has there been any word about what is happening with the Camila job? There is $77,719.93 plus GST outstanding for this job as well.
Again, we arranged for sheets on short notice as a favour to you. Why is the client not paying. Can you please provide their number to discuss thanks.
When you add these three jobs up A-Civil has a debt to
Meso
of $566,000.00 plus GST. You as an intelligent businessman understand what that sort of unpaid debt does to a business’s cash flow and means to keep up with payments to suppliers.
On 7 May 2022, Mr
Bobek
sent two emails to Mr Matta indicating
need to progress the matter urgently,
including the following:
Nasser I cannot emphasise enough, time is running out on using
the payments act we need to get going on this, otherwise it will cost both of us a lot more to seek restitution under the credit act.
On 30 May 2022
Mr
Bobek
sent an email to Mr Matta attaching
C laim 1 6
in the sum of $366,813.79 .
It is undisputed that Claim 16
was not accompanied by the
documents
required by cl 8.3 of the General Conditions.
Mr
Bobek ’ s
email
stat ed :
Attached is our claim 16 for the Parramatta RSL. Tim and I have made numerous attempts to first to arrive at a figure for
Meso’s
outstanding monies and then to understand the
strategy
A-Civil is undertaking to recover our money from Paynter’s. As
always
our door is open to discuss and work this out.
With that in mind, we have provided a claim that reflects our understanding and position of the situation.
…
As
always
our door is open for discussion and the formation of a strategy to obtain the outstanding amount from Paynter’s.
A-Civil
submitted that Claim 16 had several errors including that it understated the amount paid by A-Civil to
Meso
by approximately $70,000 and overstated the amount owing by A-Civil to
Meso
by approximately $70,000 . This was conceded by Mr Orr in cross-examination.
A-Civil also submitted that Claim 16 had an error as it
misdescribed the construction contract as
“ Formal Instruction of Agreement dated 20 August 2018 ” . However, it was not suggested that anything turned on this because the Project was correctly
identified
and the parties accepted that Claim 16 met the requirements of s
13(2) of the Act.
Mr
Matta
gave evidence
that
on or about 2 June 2022
he had the following
telephone
conversation
with Mr Orr :
Matta :
“ Why are you still sending us (A-Civil) payment claims? You know Paynter Dixon are
backcharging
for your incomplete contract works and is charging for materials they had to supply for your contract works. You know supplies were paid for by A-Civil for
Meso's
contract works, and A-Civil hasn't been paid for your contract works. You sent payment claims 14, 15 and 16 but haven't sent the documents and ITPs and responses to the
backcharges ."
Orr: "Just disregard payment claim 16. Eddie will give you a response for A ‑ Civil to send to Paynter Dixon so that A-Civil can get paid for any outstanding contract money,
and also
so that Paynter Dixon will not sue for the back charges. We won't be going to adjudication. I will prepare another claim and provide
all of
the backup documents to then have you submit to Paynter Dixon. Our relationship has been good for a long time. Eddie's father died and
this is why
the documents have not been provided.
Don't worry about claim 16, you don't need to reply with a payment schedule.
Matta :
“Then can you please retract payment claim 16?”
Orr: “I’ve told you, ignore payment claim 16 because Eddie will arrange to get that work done so that A-Civil can get paid from Paynter Dixon.”
A-Civil alleges that
th is
conversation amounted to a representation by
Meso
by its managing director
that
A-Civil should disregard Claim 16 ,
Meso
would not be proceeding with an adjudication of Claim 16 and A-Civil did not need to respond to Claim 16 by issuing a payment schedule
(together, the
2 June Representation
).
Mr Orr denies that
th e
conversation
described at [24] above
took place
and
denies
that
he ever said words to that effect to Mr Matta.
On 15 July 2022,
Mr
Bobek ,
sent an email to Mr Matta
and also
to his son, George ,
attaching
a notice
to A-Civil
under s 17(2) of the
Act , which stated :
Notice under Section 17(2) of the
Building and Construction Industry Security of Payment Act 1999 NSW
.
In response to this Company’s payment claim dated 30 May 2021 for $366,813.79 including GST your Company failed to provide a payment schedule within the time allowed by the
Building and Construction Industry Security of Payment Act 1999 NSW
.
As a consequence , your Company became liable to pay the whole amount of claim 16 on the due date. No amounts have been paid. Our Company has elected to apply for adjudication of the payment claim. Your Company has 5 business days in which to serve a payment schedule or pay payment claim 16
amount
in full immediately.
If, within that time, your Company fails to pay these amounts, this company will proceed to adjudication. If your company also fails to serve a payment schedule, your Company will be barred from lodging an adjudication response [see Section 20(2A) of the Act].
Mr
Matta
gave evidence
that on or about
18
July
2022 he had the following conversation by telephone with Mr Orr :
Matta : “Why are you sending this when you said not to provide a payment schedule? You said you were going to provide all the documents and get all the evidence and ITPs as discussed before."
Orr:
"Don't worry about it, ignore it, I told you we're not going to adjudication, our relationship is strong. We will provide all the documents as discussed before."
Matta:
“Tell
me if I need to reply with a payment schedule because I'm not going to leave my business vulnerable or exposed because I am responsible to Paynter Dixon. Paynter Dixon is asking for a deed of release to be signed, which I haven't committed to because I'm waiting for your documents.
Meso
must sign a deed of release at the same time for the project, I am not leaving
A-Civil
exposed to
backcharges.
Do you want me to respond to
this 17(2) notice
with a payment schedule?
You told me not to provide a payment schedule.
You owe A - Civil money, you have not provided documents to defend any claims and to back up your claims. Do you want A-Civil to provide a payment schedule?"
Orr:
"No, I'll get Eddie to get all documents, I promise we won't be going to adjudication, and we will work together to get the money from Paynter Dixon. Our relationship goes back a long way.
Eddie will prepare all
the documents that you've ask [sic] for and sit with
Mostafiz
to prepare the claim."
A-Civil alleges that
this conversation amounted to a representation by
Meso
to A-Civil that A-Civil should ignore Claim 16, that
Meso
would not be proceeding with an adjudication of Claim 16, and that A-Civil did not need to respond to Claim 16 by issuing a payment schedule
(together, the
18 July Representation
).
M r Orr
denies that
the conversation described at
[2 8 ]
above
took place and denies
that he ever said words to that effect to Mr Matta.
Mr
Bobek
advised Mr Matta by email on 4 August 2022 at 2:04pm that
Meso
had
lodged an
a djudication
a pplication (
Application
)
with
the
third defendant, Adjudicate Today,
in respect of Claim 16.
On 5 August 2022, Mr
Bobek
sent an email to Paynter Dixon serving a payment withholding request on it under s 26A of the Act, requiring Paynter Dixon to withhold the amount of $366,813.79 (incl GST) from moneys owed to A-Civil.
Mr Matta and Mr Orr gave evidence that they had one telephone conversation regarding the
A pplication after it was lodged by
Meso
but disagreed as to what was said.
Mr Matta ’ s
evidence
was
that on or about 5 August 2022 he had the following conversation by telephone with Mr Orr regarding the
A pplication:
Matta :
" You
said you were not going to adjudication, and I did not need to
provide a payment schedule.
You said Eddie was going to give me
documents and backup to claims to defend against Paynter Dixon.
You've done nothing, now you're going to adjudication to play the
game, and your
[sic]
being sneaky.
Why did you only send the payment
claim to me and why didn't you cc in
Mostafiz , George and everyone
else?
You knew that my mother passed away.
You told me that you
would never go to
adjudication
and I didn't need to put on a payment
schedule."
Orr: "I'II speak to Eddie and make sure he withdraws the adjudication
application.
I promised you that I would not go to adjudication, and that
Eddie would provide the documents.
I promise you that we are not
trying to be sneaky. We are not like that."
Mr Orr ’ s version of the conversation
(which he said occurred shortly after the
A pplication was served and resulted from a call made to him by Mr
Matta)
is as follows:
Matta: “Are you going to withdraw the adjudication application?”
Orr: “No. We have not been paid by A-Civil since the end of last year. We have given you enough time and have tried to work with you to come to an
agreement
but you have not provided us with a payment schedule and you refuse to provide evidence of the payment schedules sent by A-Civil by Paynter Dixon.”
Matta: “I am not going to show you those. I am directing you not to make any contact with Paynter Dixon in relation to this matter. Are you going to withdraw the application?”
Orr: “No. We needed to take this
step in
order to protect ourselves because we are not getting paid and nothing else has worked.”
Matta: “If you maintain this application, I’ll file an injunction in the Supreme Court.”
On 8 August 2022, the
third defendant, Adjudicate Today,
accepted the
Application
and nominated the second defendant, Mr
Navid
King (
Adjudicator
), to adjudicate the
A pplication.
On the same day
Mr
Bobek
telephoned Adjudicate Today and asked what was required to withdraw the
A pplication and what costs would be involved in doing so, and
a representative from
Adjudicate Today
emailed Mr
Bobek
(with a copy to A ‑ Civil) stating:
Dear Mr
Bobek ,
As per our phone discussion if you want to withdraw the matter you have to put this in writing and include the Respondent.
M r Matta
also
gave evidence that on 9 August 2022
he had the following conversation by telephone with Mr
Bobek
regarding the
A pplication :
Matta:
"Tim agreed to withdraw the adjudication and also said for us not to put a payment schedule in. He said that you would provide all of the documents and
ITPs
and everything needed to defend the
backcharges
from Paynter Dixon and to make the claim to Pay nter
Dixon.
Bobek : "Yeah, Tim advised me to do this, the lawyers are not in the office today, they will be withdrawing the application either late this afternoon or tomorrow morning."
Mr
Bobek ’ s
version of the conversation is as follows:
Matta: “What are you doing with this adjudication application? Tim has already agreed to withdraw it.”
Bobek : “No he hasn’t. We have not been paid by A-Civil since last year. You keep saying the reason for this is because Paynter Dixon is
backcharging
you
but you refuse to show me their payment schedules and you don’t want me to help you go back to them. Nor did you ever want to come to an amicable resolution of the moneys owing to
Meso.”
Matta: “Ok, so you will withdraw the application, yes?”
Bobek: “No. We have lawyers retained and they have given us strong advice not to withdraw the application, so we won’t be doing that. But again, I want to try to help you deal with Paynter Dixon so that you can get paid and then we can try to resolve our dispute. I will come to your office at 8:30am tomorrow to go through the Paynter Dixon material and assist you with formulating a response.”
Matta: “If you don’t withdraw it, we will sue you in the Supreme Court.”
A-Civil alleges that the conversations Mr Matta had with Mr Orr and Mr
Bobek
on 5 and 9 August respectively amounted to a representation by
Meso
that it would withdraw the
A pplication (
Withdrawal Representation
).
The conflict in the evidence as to the conversations which Mr Matta says he had with
each of
Mr Orr and Mr
Bobek
in August 2022
needs to be considered
in light of
the
emails
which passed between them on 8,
9 and 10 August 202 2
regarding the withdrawal of the adjudication application , which are as follows:
At 12 : 42pm on Monday, 8 August 2022, Mr
Bobek
sent the following email to Mr
Mostafiz
(emphasis added) :
Following our conversation on 5
August,
2022 at 12 : 40pm as advised, I will speak to
Nasser
anytime between 6am-10pm any day, including weekends.
We have never had an issue with helping A-Civil. There must be at least a dozen emails where Tim and I have made representations to help A-Civil with their claim against
Paynter’s ,
which A-Civil never took up.
As well as countless calls that Tim and I have made to various people within A-Civil, including Nasser, to have this matter resolved.
We were always directed to deal with Nasser.
To date, we haven’t received a call or email
.
If I don’t answer Nasser’s call immediately, I’ll be in a meeting and call within 1-2 hours.
Th e bold words
suggest that Mr
Bobek
and Mr Orr
did not speak
to Mr
Matta
in the previous week.
At 12 : 59pm that day, Mr Matta responded to Mr
Bobek
by email as follows:
I have personally tried calling you and Tim, even in the last 10min, and in your email below you say you were helping A-Civil, that is incorrect as you know Paynter’s are back charging for
Meso
incomplete work from your contract works on the job at Parramatta RSL.
Meso
have all the information as Tim was at the meeting with A-Civil and Paynter’s, they stated all Back Charges and were not paying A-Civil for
Meso
incomplete works.
You state you were helping A-Civil, that’s not the case as we had to
p urchase all materials that are in
Meso
contract to purchase, so I state A-Civil was helping
Meso
as we didn’t have to pay for the material as you have all receipts for the material.
Significantly, in this email Mr Matta makes no reference to having spoken to Mr Orr on 5 August or t o
Mr Orr ’ s agreement
to withdraw the
A pplication. The words
“ you state you were helping A ‑ Civil ”
in Mr Matta ’ s email pick up a comment in the second paragraph of Mr
Bobek ’ s
email of 12 : 42pm.
At 4 : 39 pm , Mr
Bobek
respond ed
by email to Mr Matta, including the following
(emphasis added) :
Up until your call at 1: 58pm today, I haven’t missed a call from you. Even though Tim is extremely busy, I was surprised he was able to take your call. Besides, I’m the one dealing with this matter, have a better understanding of the Adjudication Application process, and have complete authority to act on behalf of
Meso . Tim has explained our model to you on many occasions. Each of us has our areas of responsibility, and part of mine is
matter
such as this.
…
You missed the meeting mentioned in your earlier email and sent
Mostafiz . Tim attended as you had requested him to. Paynter’s questioned what Tim was doing there, as the issues were much larger than the “minor issue of
Meso’s
scope”. Paynter’s words, not ours. As you know, under those circumstances, he left as it was inappropriate for him to be in attendance, l e aving
Mostafiz
to deal with Paynter’s.
In your conversation with Tim, you mentioned it was sneaky that I only sent emails to you
. I was merely following your instruction; you rang me one day and directed me that I was not to include others in emails. I was merely following your instructions. I did include George for the 17.2 notice and added
info@a-civil
for the adjudication emails, as I felt it warranted it.
How can we help you when you have rejected all our attempts to help? On many occasions, I’ve offered to come to your offices to help and go through the situation with
Mostafiz
or send me the documents Paynter has provided, namely payment schedules and emails stating why they are not paying. Then I can review and work out how to respond. This is my
domain
of responsibility within
Meso , not Tim’s and remains the offer I have been making for months. The offer still stands. I’m more than happy to come to your offices this week and go through it all with
Mostafiz.
Regarding the current and in-play Adjudication Application and Withholding Notice to Paynter’s. Paynter’s not having paid you means that you currently haven’t been put out of pocket apart
from the non-payment by
Paynters. This means they are legally bound to hold the amount we have stated in our notice. Once we go through the process and if the amount requires adjusting, we will have a lawyer issue a Deed stating the adjusted amount’s parameters. In don’t see why Paynter should be let off the hook; both of us should apply maximum pressure. Why should they get away with the back charging wall when you weren’t notified in time and other items we can find in the process? Nasser, as I’ve told you before I’m good at this. Let me help you. But I can’t do without knowing the complete picture.
The first paragraph suggest s
that Mr Matta and Mr Orr had a telephone conversation on 8 August 2022 between the time these two emails were sent. The
emphasised
statement in the third paragraph
( “ in your conversation with
Tim
you mentioned it was sneaky that I only sent emails to you ” )
is consistent with part of the conversation w hich
Mr Matta says he had with Mr Orr set out at [ 3 4 ]
above, but the remainder of the email is not consistent with Mr Orr having said that the
A pplication
would be withdrawn.
At 1 : 21pm on 9 August 2022
Mr
Bobek
sent the following email to Mr
Matta and Mr
Mostafiz
(with a copy to Mr Orr):
Attached is the email you were referring to in our phone conversation.
Unfortunately, this doesn’t tell me much.
All companies, Paynter Dixon included, will inflate their back-charging to give themselves negotiating room. We based our claim on the information contained in it and emails on rates from Paynter’s.
I need to see the payment schedules Paynter Dixon sent A-Civil and their backup documents justifying the amount of back charging.
Also, you have seen our last claim. What is A-Civil’s
assessment of that claim? You don’t have to send a payment schedule. I've prepared a spreadsheet which is attached. Just fill in the column marked A-Civil assessment. We may not be as far apart as perceived and arguing about nothing. It may not be worth going to war with Paynter’s, and it becomes a commercial decision.
Also, please confirm that we are on the same page with payments received.
Tim has agreed to withdraw the Adjudication Application once we review their position and formulate a response to Paynter Dixon, accepting the abovementioned paragraph.
The email referred to in the first paragraph is
the
email of 7 February 2022 referred to
at [16] above
which attached material concerning Paynter Dixon’s position on
backcharges
for work done by A-Civil which A-Civil was disputing (and had in that earlier email sought
Meso’s
assistance in framing its response to Paynter Dixon).
The last paragraph appears to be a summary of Mr
Bobek’s
understanding of what Mr Orr “agreed” to do in his conversation with Mr Matta which is not consistent with Mr Matta’s version of the conversation.
At 1 : 46pm that day, Mr Orr sent the following email to Mr
Bobek
with a copy to Mr Matta and Mr
Mo s tafiz :
It sounds like PD are holding onto a lot of money including for
earthworks, and
piling as well as the RC walls from what Nasser tells me. We can reconstruct what they are arguing about by simply reviewing each of their payment schedules for the series of months. That way we can determine exactly what the argument is about between A-Civil and
Meso
on one side and PD on the other.
I think we have calculated
pretty closely
the value of the works we did and deducted supply costs etc.
At 4 : 25pm that day, Mr
Bobek
sent an email to Mr Matta and Mr
Mostafiz
(with a copy to Mr Orr) stating:
I’m tied up in meetings for the next couple of hours. I can be at your office at 8:30am in the morning to start going through this.
A t 4:29pm
that day , Mr Matta
responded by an email to
Mr
Bobek
stating :
As agreed,
Meso
will be withdrawing the Adjudication today, I haven’t received anything
as yet
and as to the withdrawing from the Adjudication.
Can you confirm this will be done today by 5pm thanks.
A t 5:03pm
that day , Mr
Bobek
replied stating :
I called our lawyer's office and advised what we wanted to do.
He was tied up with another matter and his assistant has advised him.
He will get to it when he can either today or tomorrow.
In any case, the adjudicator has ten days to respond.
If you feel you must get your lawyers to place the start the legal action, that's fine I’ll still work with you guys to work this out.
I cancelled meetings to be at your offices at 8.30 tomorrow and working late to fit you
guys
in.
A t 5:23pm
that day , Mr Matta replied
stating:
Ok Eddie,
Thanks for the commitment for the withdrawing the Adjudication and will see you soon.
On 10 August 2022 at 1:17pm, Mr
Bobek
sent an email to Mr Matta stating :
Our lawyer finally got back to us a few moments ago.
He has strongly recommended we not withdraw the adjudication application until we have a better idea of the information that A Civil is willing to share with us
in order to
pursue a successful joint claim against Paynter Dixon.
He also advised we have 10 days from yesterday to come to a resolution, in any case, it won't be realised until we pay for it.
I came to your offices this morning as I said I would establish the baseline of what PD has agreed with each of our claims which will then formulate the response to their back charging claims.
After
Mostafiz's
no-show this morning and A-Civil reluctance to share PD information we will not be withdrawing the adjudication application. As always, we are open to willing to work together to come to a resolution but require the PD information.
Mr
Bobek
sent further emails to Mr Matta on 16 and 17 August 2022 stating that
Meso
needed to see Paynter Dixon ’ s payment schedules and other specified documents before it would withdraw the adjudication application.
It is clear that A-Civil
did not respond .
On 17 August 2022
at 4 : 38pm ,
Adjudicate Today sent an email to A-Civil and
Meso
attaching the
D etermination
which
determin ed
the adjudicated amount to be $366,813.76 .
On 24 August 2022, these proceedings were commenced by A-Civil by way of summons.
C lause 8.3 of the
General Conditions
Clause 8.3
of the General Conditions
provides relevantly:
8.3 Payment Claim & Payment Certificate
…
(b)
At the times stated in Annexure A, item 11, and upon the times set out in Clauses 8.15 and 8.17, the Subcontractor may submit a Payment Claim to A-Civil, or as directed in writing by A-Civil. Notwithstanding the formalities of Clauses 8.15 and 8.17, a Payment Claim must include the value, quantities and description of work carried out by the Subcontractor in the performance of this Agreement to the permissible Reference Date together with the information set out in Clause 8.3(c), (g), (h) and (i) (“
Payment Claim
”).
(c)
A Payment Claim must contain and show the Subcontractor’s assessment of:
(i)
the value of the Works completed (excluding Variations, but allowing for Variation omissions) since any earlier, if any, Payment Claim, pursuant to this Agreement and valued (as shown in Annexure A, item 8) in accordance with Clause 8.3(b) and Clauses 8.5, and/or 8.6 and/or 8.7 at the Reference
Date;
(ii)
the value of work completed for Variations at the Reference Date, valued in accordance with Clause
7;
(iii)
the total amount determined under Clauses 8.3(c)(i ) and 8.3(c)(ii), less the amount previously paid to the
Subcontractor;
(iv)
the deduction of any Retention Moneys to be retained by A-Civil pursuant to this
Agreement;
(v)
any other amounts to which the Subcontractor is then entitled under this Agreement at the Reference
Date;
(vi)
GST in the form of a tax invoice; and
(vii)
plans, drawings, schedules marked and containing accurate and current information to
support the quantities or weight claimed in the Payment Claim.
…
(g)
A-Civil is not obliged to make a Progress Payment referred to in Clause 8.8 to the Subcontractor unless each Payment Claim made for each Reference Date to the satisfaction of A-Civil:
(i)
complies with Clauses 8.3(c) and (d);
(ii)
complies with Clause
8.3(g);
(iii)
complies with Clause
9;
(iv)
is accompanied with a “Subcontractor’s Statement” in the form as provided in Annexure C of this Agreement regarding workers compensation, payroll tax and remuneration, which is to be signed by the Subcontractor or its authorised representative as required under the Relevant Legislation and any other relevant
laws;
(v)
is accompanied with a Statutory Declaration in the form as provided in Annexure F of this Agreement which is to be signed by the Subcontractor or its authorised representative and duly witnessed by a person legally authorised to administer an oath under the
Oaths Act 1900
(NSW), or as required under the Relevant Legislation and any other relevant
laws;
(vi)
is accompanied with accurate and current documentary evidence in the form of itemised reports and receipts showing comprehensive details about the Subcontractor’s employees and/or Persons’ names and amounts due,
payable
and paid for the period referable to the Payment Claim showing that the Subcontractor’s obligations for:
(A)
Superannuation;
(B)
Redundancy;
(C)
Accident insurance
cover;
(D)
Long Service Leave; and
(E)
EHS,
have been fulfilled (including paid) by the Subcontractor in accordance this Agreement (see Annexure K), with Relevant Legislation, any other applicable law, awards, industrial
requirements
and instruments.
(vii)
is accompanied with accurate and current documentary evidence in the form of certificates of currency for current,
paid
and compliant insurance policies having regard to Clause 10 for the period referable to the Payment Claim showing that the Subcontractor’s obligations for:
(A)
Contract
Works;
(B)
Public and Products
Liability;
(C)
Workers Compensation or Workcover
NSW;
(D)
Professional
Indemnity;
(E)
Motor Vehicle Third
Party;
(F)
Asbestos Liability; and
(G)
All-Risk Liability,
have been fulfilled (including premiums paid) by the Subcontractor in accordance with this Agreement, Relevant Legislation, any other applicable law, awards, industrial
requirements
and instruments.
(viii)
is accompanied with accurate and current documentary evidence in the form of itemised reports, statements (including for integrated client accounts,
income
and activity statements (BASs)), returns and receipts showing comprehensive details about the Subcontractor’s employees and/or Persons’ names and amounts due, payable and paid for the period referable to the Payment Claim showing that the Subcontractor’s obligations for:
(A)
PAYG
Tax;
(B)
Income
Tax;
(C)
Fringe
Benefits;
(D)
GST;
(E)
Payroll Tax; and
(F)
Duty,
have been fulfilled (including paid) by the Subcontractor in accordance with this Agreement, Relevant Legislation, any other applicable law, awards, industrial
requirements
and instruments.
(ix)
have returned to A-Civil two copies of this Agreement duly executed on behalf of the Subcontractor, unless, without affecting any of A-Civil’s
rights under this Agreement, this Agreement has been accepted pursuant to the Formal Instrument of Agreement and/or Clause 2.2( hh) of this Agreement.
(h)
Without limiting the effect of Clause 8.3(g), A-Civil is also not obliged to make a Progress Payment referred to in Clause 8.8 to the Subcontractor until the Subcontractor
has delivered,
to the satisfaction of A-Civil, the following:
(i)
completed Director(s) Guarantee and Parent Company
Guarantee;
(ii)
details of the Subcontractor’s quality, industrial, environmental, health and safety systems, policies and
agreements;
(iii)
a list of all Secondary Subcontractors, labour hire firms and suppliers engaged by the Subcontractor in connection with the Works; and
(iv)
if the Payment Claim is the Substantial Completion Payment Claim under Clause 8.15, an executed deed of settlement and release substantially in the form of the deed in Annexure E,
as requested by A-Civil or in accordance with this Agreement, Relevant Legislation, any other applicable law, awards, industrial
requirements
and instruments.
…
(k)
If the Subcontractor fails to comply with some or all of the requirements of Clauses 8.3(b), (c) and (d), 8.3(g), (h) and (i) within the time by which A-Civil is obliged to provide a Payment Certificate, either, at A-Civil’s
sole discretion, the relevant Payment Claim is void, or if not void, A-Civil is entitled to issue a Payment Certificate for either $Nil or for the Certified Amount, but A -Civil is not obliged to make any Progress Payment until 20 Days after A-Civil is satisfied that the Subcontractor has complied with the totality of Clauses 8.3(b), (c) and (d), and 8.3(g), (h) and (i).
Issues
T he issues in dispute
are :
Whether A ‑ Civil has established that
Meso
made
representations on 2
June 2022 ,
18 July 2022 or
in early August 2022 that
Meso
would withdraw the Application and, thus, that A-Civil was not required to issue a payment schedule .
Whether
non-compliance with cl 8.3
of the General Conditions
by
Meso
oust ed
the jurisdiction of the Adjudicator .
Whether A-Civil waived compliance with cl 8.3 of the General Conditions.
Claims under sections 18, 20 and 21 of the ACL
Section 18(1) of the ACL provides:
A person must not, in trade or commerce, engage in conduct that is misleading or deceptive or is likely to mislead or deceive.
Section 20 of the ACL provides:
(1)
A person must not, in trade or commerce, engage in conduct that is unconscionable, within the meaning of the unwritten law from time to time.
(2)
This section does not apply to conduct that is prohibited by section 21.
Section 21 of the ACL provides:
(1)
A person must not, in trade or commerce, in connection with:
(a)
lease or supply or possible supply of goods or services to a person; or
(b)
the acquisition or possible acquisition of goods or services from a
person;
engage in conduct that is, in all the circumstances, unconscionable.
A- Civil ’ s
primary case was that each of the 2 June Representation and 18
July Representation contravened s 18 of the ACL. It also submitted that
Meso
would engage in unconscionable conduct within the meaning of s 20 of the ACL or in the alternative s 21 of the ACL if it was permitted to obtain and enforce an adjudication certificate and judgment with respect to the Determination as this would be conduct contrary to the
r epresentations.
The parties
were in agreement
that
the central issue on which the application of s 18, 20 or 21 of the ACL turned was whether A-Civil had established, as a matter of fact, that
Meso
made each of the alleged representations.
In
Kallin
Pty Ltd v ACN 107 851 847 Pty Ltd
[2018] NSWSC 124 at [42], Hammerschlag J (as his Honour then was) said:
Where a party seeks to rely upon spoken words as a foundation for a cause of action, including a cause of action based on a contract, the conversation must be proved to the reasonable satisfaction of the Court, which means that the Court must feel an actual persuasion of its occurrence or its existence. In the absence of some reliable contemporaneous record or other satisfactory corroboration, a party may face serious difficulties of proof. Such reasonable satisfaction is not a state of mind that is obtained or established independently of the nature and consequences of the fact or facts to be proved. The seriousness of an allegation made, inherent unlikelihood of an occurrence of a given description, or the gravity of the consequences flowing from a particular finding are considerations which must affect the answer to the question of whether the issue has been proved to the reasonable satisfaction of the Court. Reasonable satisfaction should not be produced by inexact proofs, indefinite testimony,
or indirect inferences: see
Briginshaw
v
Briginshaw
(1938) 60 CLR 336 at 362
, [1938] HCA 34 ;
Helton v Allen
(1940) 63 CLR 691 at 712;
Rejfek
v McElroy
(1965) 112 CLR 517 at 521;
Watson v Foxman
(1995) 49 NSWLR 315 at 319.
In
Briginshaw
v
Briginshaw
(1938) 60 CLR 336 ; [1938] HCA 34 ,
Dixon J emphasised that when the law requires the proof of any fact the Court must feel an actual persuasion of its occurrence or existence before it can be found, and
“ it cannot be found as a result of a mere mechanical comparison of probabilities independently of any belief in its reality ” .
In
Watson v Foxman
(1995) 49 NSWLR 315,
McLelland
CJ in Eq made the following well known observations regarding the fallibility of human memory
( at 319):
… human memory of what was said in a
conversation is fallible for a variety of reasons, and ordinarily the degree of
fallibility increases with the passage of time, particularly where disputes or
litigation intervene, and the processes of memory are overlaid, often subconsciously, by perceptions or self-interest as well as conscious consider ­ ation of what should have been said or could have been said. All too often what
is
actually remembered
is little more than an impression from which plausible
details are then, again often subconsciously, constructed. All this is a matter of
ordinary human experience.
See also the observations of Leggatt J
(as his Honour then was)
as to the fallibility of human memory
to similar effect
in
Blue
v Ashley
[2017] EWHC 1928
(Comm)
at [66]-[69].
Hence, in commercial disputes the contemporaneous documents, objectively established facts and the apparent logic of events are likely to be the most reliable sources of evidence:
Et-China.com International Holdings Ltd v Cheung
[2021] NSWCA 24 ; 388 ALR 128
at [25]-[29] (and cases there cited).
Whether the 2 June and 18 July Representations
were made
Based
on all the evidence
I do not have an actual persuasion
that Mr Orr made either the 2 June Representation or the 18 July Representation, for the following reasons.
First,
A-Civil has not proved that
any conversation occurred between
Mr
Matta and Mr Orr
on
or about
either 2 June 2022 or 18 July 2022 . Mr Matta was aware at the time he prepared his second affidavit of 23 November 2022
that M r
Orr disputed that he spoke to Mr Matta on or around either of those dates. Mr Matta
could
have
but did not put on evidence as to his mobile phone records to show that he either made or received a call from Mr Orr on each of those days. It is significant that in his second affidavit of 23 November 2022 he included his mobile telephone log for 9 August 2022 to establish the calls he made to Mr
Bobek
on that day. That telephone log shows that he made three calls to Mr Orr ’ s mobile phone on
9 August 2022 . There is no explanation as to why Mr Matta did not address the question of whether he made
a call
to
or received a call from Mr
Orr on 2 June 2022 or 18 July 2022 in the same way. In these circumstances I draw the inference that Mr Matta ’ s telephone log would not have assisted in establishing that telephone conversations between them occurred on
or around 2 June 2022 and 18 July 2022 :
Jones v Dunkel
(1959) 101 CLR 298 at 320-321 ; [1959] HCA 8 .
Second,
Meso
tendered Mr Orr ’ s telephone log for his mobile phone
for the period from 31 May to 4 August 2022 . This showed that no call was made
by Mr Orr on that mobile phone to Mr Matta or vice versa
at any time during that period . Mr Orr ’ s evidence was that he makes and receives all his business calls on his mobile phone. Further, it is clear from Mr Matta ’ s mobile phone log for 9 August 2022 that he
telephoned
Mr Orr on his mobile phone
3 times on that
day
and it may be inferred that this is the likely
telephone
number he would have used had he called Mr Orr on 2 June or 18 July 2022 .
Third, the email correspondence in the period from 2 June to 17 August 2022 (when
the parties were notified
by Adjudicate Today
that
the Determination
had
been
made) contains no reference to the making of any representation in the nature of the 2 June Representation or the 18 July Representation. In particular, the evidence clearly establishes that there were discussions on 8 to 10 August 2022 regarding the withdraw al
of the
A pplication, including several emails by Mr Matta to Mr
Bobek
and Mr Orr on that subject. In none of these emails does Mr Matta refer to the 2 June or 18 July Representations. Had the 2 June or 18 July Representations been made, one would expect Mr
Matta to have reminded Mr Orr of this fact and to have pressed him to act consistently with them.
Fourth, it is inherently improbable that Mr Orr would have made the 2 June or 18 July Representations given the large amount owing by A-Civil to
Meso
at that time, and the fact that Mr Orr and Mr
Bobek
had been chasing A-Civil for payment of
Meso ’ s
outstanding payment claims for the
P roject since the last payment was received from A-Civil on 23 December 2021.
Fifth, Mr Matta ’ s evidence in cross-examination was that at the time A-Civil received all payment claims made after the Contract was entered into (including Claim 16) he was of the view that they were not valid payment claims under the Act due to non-compliance with cl 8.3 of the General Conditions :
Q. When you received, for example, payment claims 11 to 15, it was obvious to you that MESO had not complied with general condition 8.3; correct?
A. Correct.
Q. And when you received payment claim 16, it was obvious to you that MESO had not complied with general condition 8.3; correct?
A. Correct.
Q. And when you received those claims, that is, 10 to 15 and 16, it was your view that those payment claims are invalid; correct, because they did not comply with general condition 8.3?
A. Well, payment claim 16 was only sent to me. I was – I was not ‑‑
Q. When it was sent to you, upon receiving payment claims 10 to 16, you formed the view that they were invalid because they did not comply with general condition 8.3; correct?
A. Correct.
Later he was asked further questions about payment claim 9 at page 917 of the Court Book, and the following exchange occurred:
Q. The document at 917, did you, at the time when you received it, understand it to be a claim under the Security of Payment Act or not?
A. Yes.
Q. Did you think
in order for
it to be a valid payment claim under the Security of Payment Act MESO had to comply with general condition 8.3?
A. Yes.
Q. And you formed the view in June 2021 that it wasn’t a valid payment claim under the Act because the document at 917 did not comply with general condition 8.3; correct?
A. Yes.
Q. And the same can be said about payment claims 10 to 15; correct?
A. Yes.
Q. And the same can be said about payment claim 16; correct?
A. Yes.
Mr Matta ’ s view that
Claim
16 was invalid
is the likely explanation for why no payment schedule was issued for Claim 16 and makes it highly unlikely that Mr
Matta saw any need to obtain an undertaking from
Meso
that A-Civil did not need to put on a payment schedule or that it would not proceed to adjudication. This is because if Claim 16 was invalid, the adjudication would be unsuccessful.
Whether t his
view is correct is the subject of
the jurisdiction claim dealt with later in these reasons.
Sixth, having observed both Mr Matta and Mr Orr give evidence in cross-examination, I am not persuaded that Mr Matta ’ s recollection of the alleged conversations with Mr Orr is reliable.
Seventh , none of the matters raised by
counsel for A-Civil
as reasons why I should accept Mr Matta ’ s evidence
are
persuasive.
It was
submitte d
that Mr Orr and Mr
Bobek
had given false evidence regarding conversations relating to the inclusion of cl 8.3 and the
W ithdrawal
R epresentation. I put to one side Mr
Bobek ’ s
evidence regarding cl 8.3 and the
W ithdrawal
R epresentation because he is not the person said to have made the 2 June or 18 July Representations. In so far as Mr Orr is concerned, I do not accept that he gave false evidence regarding cl 8.3 or the
W ithdrawal
R epresentation.
I t was submitted that because
Meso
had offered to A-Civil
o n
28
January 2022 to lodge an adjudication application against A-Civil and then to subsequently withdraw it, to enable
A-Civil to press for payment of monies owed to A-Civil by Paynter Dixon, this made it
“ entirely believable ”
that
Meso
would lodge an adjudication application with no intention of pursuing it to an adjudication and would say as much to A ‑ Civil. I do not regard the email of 28 January 2022 as having any bearing on the question whether the 2 June or 18 July Representations were made. There is no suggestion in the evidence that A-Civil ever took up the suggestion
in the email of 28 January 2022
that this was a worthwhile strategy to adopt.
I t was submitted that the
W ithdrawal
R epresentation w as
consistent with the 2 June and 18 July Representations. For reasons explained below, I do not accept that the
W ithdrawal
R epresentation w as
made but in any event of more significance is the fact that in the email correspondence occurring in August 2022 regarding the
A pplication, Mr
Matta made no reference to the fact that Mr Orr had made the 2 June and 18 July Representations.
I t was submitted that the contemporaneous emails indicate that Claim 16 and the subsequent adjudication application were assisting A-Civil to obtain payment from Paynter Dixon and to put pressure on Paynter Dixon. In my view, this is not correct. Rather, the contemporaneous
emails
from
Meso
indicate that the purpose of Claim 16 was to recover the amount which
Meso
claimed it was owed by A-Civil. The repeated statements by
Meso
that it wished to assist A-Civil to obtain payment from Paynter Dixon which is found in the email attaching Claim 16 (as well as emails before and after that time) are clearly explicable on the basis that
Meso
was offering to assist A-Civil to recover amounts owing to it by Paynter Dixon as this would make it easier for A-Civil to fund the payment to be made by it to
Meso
for the large amount outstanding since 23 December 2021.
I t was submitted that the email correspondence on 9 and 10 August 2022 indicated that
Meso
only decided to pursue the adjudication after it received advice from its lawyers on 10 August 2022. I reject this submission. The emails of 8, 9 and 10 August 2022 indicate that
Meso
had decided on the strategy of pursuing adjudication
in order to
recover the amounts which it
considered to be owing
by A-Civil and while it considered
A- Civil ’ s
request that it withdraw the
A pplication, ultimately it decided not to do so.
I t was submitted that there was no rational explanation as to why A ‑ Civil would not have issued a payment schedule with respect to Claim 16, particularly upon receiving the s 17(2) notice on 15 July 2022. Rather, it was said that the most plausible explanation as to why A-Civil did not issue a payment schedule regarding Claim 16 is because Mr Matta was told that he did not have to worry about it. I reject this submission.
It is clear that A-Civil
had not issued a payment schedule for any of the other 15 payment claims
which preceded Claim 16 . While the giving of the s
17(2) notice on 15 July 2022 exposed A ‑ Civil to the risk that it would lose its entitlement to lodge an adjudication response unless it served a payment schedule within 5 business days after receipt of the notice, this
was drawn to the attention of A-Civil by Mr
Bobek . Had the 2 June
and 18 July
2022 Representation s
been made, one would expect that Mr
Matta would have sent an email to Mr
Bobek
reminding him that Mr
Orr had made the
r epresentation s
and requiring the
s 17(2)
notice to be withdrawn. Mr Matta did not do so and indeed there were no written communications from A-Civil to
Meso
regarding Claim 16 until 8 August 2022, after the
A pplication had been
lodged . The more plausible explanation in my view
is that A-Civil took the view that Claim 16 had no legal effect due to non-compliance with cl 8.3 of the General Conditions .
I t was submitted that the errors on the face of Claim 16 indicate that
Meso
was less concerned with correctly calculating the amount owing to it and more concerned with issuing a payment claim to assist A-Civil in pursuing
Paynter
Dixon. I reject this submission as it is contradicted by the email correspondence from Mr
Bobek
to A-Civil at the time Claim 16 was issued.
Whether the
W ithdrawal
Representation was made
I do not accept Mr Matta ’ s evidence regarding the conversations he had with Mr Orr and Mr
Bobek
after the
A pplication was lodged.
The starting point is Mr Matta ’ s telephone log for 9 August 2022 (which he put into evidence) which establishes two important matters. The first is that Mr
Matta had a telephone conversation with Mr
Bobek
at 11 : 18am
on that day
which lasted for 9 minutes and 41 seconds. The telephone log
records
no other call to Mr
Bobek ’ s
mobile phone lasting more than a few seconds that day except for one he made to Mr
Bobek ’ s
mobile phone at 4 : 02pm which lasted for 7 seconds. There is a text message which Mr
Bobek
left on Mr Matta ’ s mobile phone at 4 : 02pm which states:
“ Sorry, I can ’ t talk right now. ”
I infer from this that the 7 second call at 4 : 02pm most likely involved Mr Matta leaving a short voicemail message for Mr
Bobek
and that they did not actually speak at that time. Hence, the conversation between Mr Matta and Mr
Bobek
referred to at [ 3 7 ]
and [3 8 ]
above most likely occurred at 11 : 18am on 9 August 2022,
ie ,
before the email Mr
Bobek
sent to Mr Matta at 1 : 21pm set out at [ 40 (4) ] above.
This is confirmed by the opening paragraph of the email which says:
“ Attached is the email you were referring to in our phone conversation ” . The
“ phone conversation ”
is most likely the one he has just had at 11 : 18am that morning.
The significance of this timing is that Mr
Bobek ’ s
email sent at 1 : 21pm concludes with
the
statement
“ Tim has agreed to withdraw the adjudication application once we review their position and formulate a response to Paynter Dixon,
…” . The tenor of the email, including particularly the last paragraph, is more consistent with Mr
Bobek ’ s
version of the conversation set out at [ 3 8 ] above rather than Mr Matta ’ s version.
The second important matter established by Mr Matta ’ s mobile phone log is that he called Mr Orr ’ s mobile phone at 1 : 48pm on 9 August 2022 and had a conversation which lasted for
just over
13 minutes.
It may be
that the last
paragraph of Mr
Bobek ’ s
email sent at 1 : 21pm that day prompted Mr Matta to call Mr Orr.
But
there is
no evidence as to what was said
in th e
conversation
at 1 : 48pm
and
given the length of the call, the Court
can
have no confidence that either version
of the conversation at [ 3 4 ] and
[3 5 ] above reflects what
was said
by them in a call
on 9 August 2022.
The email correspondence on 8 August 2022 suggests that
the conversation
between Mr Matta and Mr Orr above
about
which they each gave evidence at [ 3 4 ] and [ 3 5 ] above occurred on
8
August 2022. Importantly, this is before Mr
Bobek ’ s
email of 9 August 2022 at 1 : 21pm which records what Mr Orr had
“ agreed ”
regarding withdrawal of the adjudication application.
Having placed the conversation between Mr Matta and Mr Orr in context, I think it is more likely that Mr Orr ’ s version of the conversation is correct. Mr
Orr and Mr
Bobek
had consistently maintained the position that they needed to see the payment schedules
and other documents
provided by Paynter Dixon to A-Civil to understand the nature of
Paynter
Dixon ’ s claim against A-Civil.
Having not received that information,
Meso
had now proceeded to the next stage of enforcing its rights under the Act to recover the significant sum which it regarded as owing by A-Civil to it and was in a position of strength.
It makes
no sense for Mr Orr to have changed his approach in the conversation with Mr
Matta on
either 8 or
9 August 2022 when Mr Matta was clearly not offering to change his approach regarding the provision of the Paynter Dixon payment schedules
or to provide any benefit to
Meso
for giving up its position of strength . The two emails sent by Mr Matta to Mr
Bobek
in the afternoon of 9 August 2022 (the first at 4 : 29pm and the second at 5 : 23pm) have the flavour of Mr Matta seeking to put pressure on Mr
Bobek
to withdraw the adjudication application.
In addition to the documentary record, I have also
taken into account
the evidence given by each of Mr Matta, Mr Orr and Mr
Bobek
in cross-examination in concluding that Mr Matta ’ s version of each conversation with Mr Orr and Mr
Bobek
is not reliable.
Conclusion
For the above reasons, I do not accept that any of the
alleged
representations were made by
Meso
to A-Civil and accordingly the claims under s 18, s 20 and s 21 of the ACL cannot succeed.
Jurisdictional claim
A- Civil ’ s
pleaded case is that the s 17(2) notice was invalid because
Claim 16
was not accompanied by the documents required by cl 8.3 of the General Conditions ( in particular those
referred to in
cll
8.3(g)(iv), (v), (vi), (vii) and (viii)) with the result that A-Civil had no obligation to pay the amount stated in Claim 16. By virtue of cl 8.3(k) of the General Conditions,
Claim
16 was void and only fell due for payment 20 days after
Meso
had complied with the totality of the obligations in cl 8.3(g) of the General Conditions (which never occurred).
Relevant provisions of the Act
The following are the provisions of the Act relevant to this issue.
8 Right
to progress payments
A person who, under a construction contract, has undertaken to carry out construction work or to supply related goods and services is entitled to receive a progress payment.
9 Amount
of progress payment
The amount of a progress payment to which a person is entitled in respect of a construction contract is to be—
(a)
the amount calculated in accordance with the terms of the contract, or
(b)
if the contract makes no express provision with respect to the matter, the amount calculated
on the basis of
the value of construction work carried out or undertaken to be carried out by the person (or of related goods and services supplied or undertaken to be supplied by the person) under the contract.
…
11 Due
date for payment
(1)
Subject to this section and any other law, a progress payment to be made under a construction contract is payable in accordance with the applicable terms of the contract.
…
(1B)
A progress payment to be made to a subcontractor under a construction contract (other than an exempt residential construction contract) becomes due and payable on
(a)
the date occurring 20 business days after a payment claim is made under Part 3 in relation to the payment, except to the extent paragraph (b) applies, or
(b)
an earlier date as provided in accordance with the terms of the contract.
…
(8)
A provision in a construction contract has no effect to the extent it allows for payment of a progress payment later than the relevant date it becomes due and payable under subsection (1A) or (1B).
…
13 Payment
claims
(1)
A person referred to in section 8 who is or who claims to be entitled to a progress payment (the
claimant
) may serve a payment claim on the person who, under the construction contract concerned, is or may be liable to make the payment.
(1A)
A payment claim may be served on and from the last day of the named month in which the construction work was first carried out (or the related
goods and services were first supplied) under the contract and on and from the last day of each subsequent named month.
(1B)
However, if the construction contract concerned makes provision for an earlier date for the serving of a payment claim in any
particular named
month, the claim may be served on and from that date instead of on and from the last day of that month.
(1C)
In the case of a construction contract that has been terminated, a payment claim may be served on and from the date of termination.
(2)
A payment claim
-
(a)
must identify the construction work (or related goods and services) to which the progress payment relates, and
(b)
must indicate the amount of the progress payment that the claimant claims to be due (the
claimed amount
), and
(c)
must state that it is made under this Act.
(3)
The claimed amount may include any amount
-
(a)
that the respondent is liable to pay the claimant under section 27(2A), or
(b)
that is held under the construction contract by the respondent and that the claimant claims
is
due for release.
(4)
A payment claim may be served only within
-
(a)
the period determined by or in accordance with the terms of the construction contract, or
(b)
the period of 12 months after the construction work to which the claim relates was last carried out (or the related goods and services to which the claim relates were last supplied),
whichever is the later.
…
17
Adjudication
applications
(1)
A claimant may apply for adjudication of a payment claim (an
adjudication application
) if
-
(a)
the respondent provides a payment schedule under Division 1 but
(i)
the scheduled amount indicated in the payment schedule is less than the claimed amount indicated in the payment claim, or
(ii)
the respondent fails to pay the whole or any part of the scheduled amount to the claimant by the due date for payment of the amount, or
(b)
the respondent fails to provide a payment schedule to the claimant under Division 1 and fails to pay the whole or any part of the claimed amount by the due date for payment of the amount.
(2)
An adjudication application to which subsection (1)(b) applies cannot be made unless
-
(a)
the claimant has served written notice on the respondent, within the period of 20 business days immediately following the due date for payment, of the claimant’s intention to apply for adjudication of the payment claim, and
(b)
the respondent has been given an opportunity to provide a payment schedule to the claimant within 5 business days after receiving the claimant’s notice.
…
34
No
contracting out
(1)
The provisions of this Act have effect despite any provision to the contrary in any contract.
(2)
A provision of any agreement (whether in writing or not)
(a)
under which the operation of this Act is, or is purported to be, excluded,
modified
or restricted (or that has the effect of excluding, modifying or restricting the operation of this Act), or
(b)
that may reasonably be construed as an attempt to deter a person from
taking action
under this Act,
is void.
A-Civil’s
contentions
In the present case, the
A pplication was made by
Meso
in reliance on s 17(1)(b) of the Act. A-Civil contends that the s 17(2) notice which
Meso
served on A ‑ Civil on 15 July 2022 did not comply with s 17(1)(b) because
Meso
did not supply with Claim 16 the documents required by cl 8.3(g) of the General Conditions, and consequently
by the operation of cl 8.3 (k) of the General Conditions , no amount ever fell due for payment under Claim 16.
The correctness of this contention turns on two questions: first, whether the due date for payment of the amount claimed under a payment claim is determined
by the provision of the contract such as cl 8.3 which makes
the
payment obligation contingent on the provision of certain documents; and second, if so, whether the provision of the contract which has that effect is void under s 34 of the Act.
Consideration
The scheme of ss 8, 9, 11 and 13 of the Act is as follows:
Sections 8 and 9 confer a statutory entitlement o n a person who under a construction contract has undertaken to carry out construction work or supply related goods and services to receive a
“ progress payment ”
in an amount
“ calculated in accordance with the terms of the contract ”
(where, as here, the contract makes express provision as to the amount payable).
Section 11(1) states that the amount of the progress payment is payable in accordance with the applicable terms of the contract subject to the operation of the succeeding provisions of s 11.
In the present case, the operation of s 11(1) is qualified by s 11(1B) which states, relevantly, that a progress payment
“ becomes due and payable ”
on the date 20 business days after the payment claim was made under s 13.
The primacy of the date for payment stated in s 11(1B) is indicated by s
11(8) which states that a provision of a contract which allows for payment of a progress payment
at a later time
than provided under s
11(1B) has
“ no effect ” .
Section 13 sets out the procedure for making a claim for a progress payment (referred to as a
“ payment claim ” ) and sets out certain matters which must be set out in the payment claim in s 13(2).
It is clear that
while
the statutory entitlement under s 8 is predicated on the existence of a construction
contract , the entitlement and the means available for its enforcement stand apart from the parties ’
rights under the Contract:
Probuild
Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd
(2018) 264 CLR 1; [2018] HCA 4 at [38];
All Seasons Air Pty Ltd v Regal Consulting Services Pty Ltd
[2017] NSWCA 289 at [8].
Section 9 provides that the amount of a progress payment to which a person is entitled under s 8 is to be “calculated in accordance with the terms of the contract”. In
John Holland Pty Ltd v Roads and Traffic Authority of New South Wales
[2007] NSWCA 19
; 23 BCL 205
at [38] ,
Hodgson JA (with whom Beazley JA agreed) said that “calculated in accordance with the terms of the contract” means calculated on the criteria established by the
contract, and
does not mean reached according to mechanisms provided by the contract. This observation was referred to with evident approval by Bathurst CJ in
Edelbrand
Pty Ltd v H M Australia Holdings Pty Ltd
[2012] NSWCA 31 at [79].
Later, in
Plaza West Pty Ltd v Simon’s Earthworks (NSW) Pty Ltd
[2008] NSWCA
279, Hodgson
JA explained what he meant by his earlier observation in
John Holland
when
he said at [54]
:
This means that contractors are not deprived of entitlement to payment under the Act because a condition precedent, such as the obtaining of a superintendent’s certificate, has not been satisfied; and it means equally that contractors are not ipso facto entitled to payment because of the operation of a deeming provision such as cl 37(2) of the contract in this case.
Section 11 deals with the time at which the progress payment is payable. The relevant provision of s 11 in the present case is s 11(1B) which makes the progress payment “due and payable” on the date which is the earlier of the two dates specified in paragraphs (a) and (b) of the sub-section (which is this case is 20 business days after the payment claim was made). The expression “due and payable” in its ordinary meaning denotes an amount which is presently payable as opposed to an amount due but not yet payable. The word “due” used on its own is ambiguous as it can mean owing although not payable until a future date or it can mean presently payable; the compound phrase “due and payable” makes it clear that the relevant amount is required to be immediately
or presently paid:
Clyne v Deputy Commissioner of Taxation
(1981)
150 CLR 1
at 8
and 15
,
[1981] HCA 40 ;
Helou
v PD Mulligan Pty Ltd
(2003) 57 NSWLR 74;
[2003] NSWCA 92 at [26(3)];
Griffin Energy Group Pty Ltd v ICICI Bank Ltd
[2015] NSWCA 29 ;
317 ALR 395
at [53]-[54] .
The reference in s 11(1B) to a progress payment is to the statutory entitlement conferred by s 8 of the Act. While the statutory entitlement
under s 8
is calculated in accordance with the terms of the contract (s 9(c)), the date on which it becomes due and payable is determined by s 11(1B) and not the terms of the contract
(such as a provision like cl 8.3 (g)
of the General Conditions) . While s 11(1B) describes the progress payment as being one made
“ under a construction contract ” , all this does is identify the construction contract which is the precondition for the statutory right to progress payments:
Quickway
Constructions Pty Ltd v Electrical Energy Pty Ltd
[2017] NSWSC 1140 at [27].
The method of enforcement of a progress payment as a debt due to the claimant turns on whether a payment schedule is served, whether there is an adjudication application and, if so, whether it goes to adjudication: see s 14, 15, 16 and 25 of the Act. However, these provisions all proceed on the basis that the statutory entitlement under s 8 is an obligation which is immediately due for payment on the date specified in s 11(1B) (where that provision applies).
It is clear from the Second Reading Speech for the Building and Construction Industry Security of Payment Amendment Bill 2013 which introduced
s 11(1B) into the Act that this is how
s 11(1B)
is intended to operate. The Minister said:
I turn now to the prompt payment provisions set out in section 11 of the Act. New section 11(1) of the bill provides that subject to this section and any other law, a progress payment to be made under a construction contract is payable in accordance with the application terms of the contract. This ensures that parties to a contract may continue to negotiate terms that apply to the process of assessing a payment claim made under a construction contract. New section 11(1A) of the bill stipulates that a progress payment to be made by a principal to a head contractor becomes due and payable on the date occurring 15 business days after a payment claim is made under part 3 of the Act. New section 11(1B) of the bill stipulates that a progress payment to be made to a subcontractor becomes due and payable on the date occurring 30 business days after a payment claim is made under part 3 of the Act. This provision
applies to contracts between a head contractor and subcontractor as well as contracts between subcontractors, and subcontractors and suppliers.
These maximum payment periods are the safety net for both head contractors and subcontractors. A construction contract may of course provide for payment on an earlier date than these maximum payment periods. These prompt payment provisions are designed to start the faster flow of cash from the top of the contracting chain. Consistent with the exemption I have already described, new section 11(1C) of the bill retains the existing due and payable provisions for construction contracts connected to an exempt residential contract. There are no changes in this bill to part 3 of the Act, which sets out the procedure for recovering progress payments, including how a payment claim is to be made. New section 11(8) of the bill voids any provision in a construction contract that provides for payment of a progress payment later than the maximum payment periods set out in subsections (1A) and (1B).
In my opinion, s 11(1B) has the effect that the progress payment claimed by
Meso
under Claim 16 became due and payable 20 business days after that payment claim was made (30 May 2022) notwithstanding that the documents required under cl 8.3(g)
of the General Conditions
did not accompany Claim 16. Clause 8.3(g) allows A ‑ Civil to make a progress payment
at a later time
than provided under s
11(1B) because it permits A-Civil to defer making the payment until such time as the documents listed in cl 8.3(g) are provided by
Meso , and hence is to be disregarded for the purposes of s 11 (1B)
by
s 11(8).
If I am wrong in the conclusion that cl 8.3 (g)
is inapplicable, then I would find that it is void under s 34(2)(a) of the Act. Clause
8.3(g)
would, if it applied to a progress payment under s
8,
operate to exclude,
modify
or restrict the operation of s 11(1B) because
it would
prevent the progress payment from being due and payable unless certain documents are provided to A-Civil.
A-Civil submitted that cl 8.3(g) does not offend s 11 because it does not extend the time for payment of a claim under the
C ontract beyond the period of 20 business days after the payment claim is made, but rather makes the payment obligation conditional on the provision of certain documents. It was submitted that s 11 is directed only at provisions which attempt to defer the time for payment and not provisions such as cl 8.3(g) which make the payment obligation
conditional or
contingent on some matter or event. It was submitted that this contention
i s supported by s 12 which treat s
a
“ pay when paid ”
provision as of no effect. A
“ pay when paid ”
provision is one which, essentially,
makes the liability to pay money owing or the time for payment contingent on a payment being made under ,
or the operation of ,
another contract.
In my view, this submission overlooks the words
“ progress payment
…
becomes due and payable ”
in s 11(1B) which indicate that, by force of that subsection, the statutory entitlement to a progress payment arising under s 8 is both owing and payable on the specified date. It is irrelevant that under the construction contract the obligation may be contingent on certain documents being provided with the progress claim : see the observation of Hodgson JA set out at [79] above . Nor is it relevant to the construction of s 11 that s 12 renders ineffective provisions in a construction contract making the obligation to make a payment for construction work contingent or conditional on certain matters. Section 12 was
present in the Act when enacted
to deal with a particular kind of term in a construction contract (referred to as a
“ pay when paid ”
provision) and s 11(1B) was introduced
in 2013
to deal with a different mischief.
Whether A-Civil waived compliance with cl 8.3
Meso
raised in its defence a contention that in a conversation between Mr
Mostafiz
and Mr
Bobek
on 28 June 2022, Mr
Mostafiz
told Mr
Bobek
that
Meso
need not comply with cl 8.3.
Meso
accepted that if it was successful on the first two issues, it was not necessary to deal with this waiver issue.
While this issue does not arise given my conclusions on the first two issues, I will make the following brief observations
about it .
I t is clear from the evidence that Mr
Mostafiz
and Mr
Bobek
did have a conversation on 28
June 2021 regarding the
C ontract. Mr
Mostafiz
could not recall in cross-examination whether he discussed cl 8.3 of the General Conditions with Mr
Bobek
during that conversation. Mr
Bobek
said in cross-examination that he recalls saying to Mr
Mostafiz
that cl 8.3 was onerous and that Mr
Mostafiz
said to him words to the effect
“ Don ’ t worry about [it], just keep on doing what [ Meso ] are doing ” . Accepting for the moment that words to this effect were said, it falls short of a waiver of cl 8.3 for
a number of
reasons.
First, the claim of waiver or estoppel was based on Mr
Mostafiz
having made a representation that
Meso
was not required to strictly comply with the provisions of cl 8.3(g). However, the conversation relied on is not sufficiently precise to form the basis of any meaningful representation by
Meso
as clearly
a number of
the subparagraphs of cl 8.3
apart from cl 8.3(g)
were necessary for the operation of the progress payment regime
under the Contract . Second, it is not clear how the alleged representation sits with the very extensive
“ entire agreement ”
clause contained in the
C ontract which was signed later that day. Third, it is not clear that Mr
Mostafiz
had authority to bind A-Civil as he was not a director of A-Civil but merely an employee.
None of these matters w as
dealt with in submissions,
reflecting the fact that this issue was touched on only briefly by the parties.
Conclusion
For the above reasons,
the proceedings should be dismissed with costs .
I direct the parties within 7 days to bring in Short Minutes of Order to give effect to these reasons .
**********
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Decision last updated:
18 April 2023
Official source: https://www.caselaw.nsw.gov.au/decision/1877d45d44ae072b4bf3d95b