AGY Global Wealth Pty Ltd v Gillies [2023] NSWCATAP 85
Catchwords: APPEAL – Notice of Appeal – filed outside of the prescribed time – whether extension of time should be granted – no sound recording or transcript of the Tribunal’s oral reasons for decision filed - extension of time refused .
Civil and Administrative Tribunal
New South Wales
Medium Neutral Citation:
AGY Global Wealth Pty Ltd v Gillies [2023] NSWCATAP 85
Hearing dates:
2 March 2023
Date of orders:
27 March 2023
Decision date:
27 March 2023
Jurisdiction:
Appeal Panel
Before:
S Thode, Principal Member
M Deane, Senior Member
Decision:
1.
The application for an extension of time to lodge
the
Notice of Appeal is refused.
2.
Appeal dismissed.
Catchwords:
APPEAL – Notice of Appeal – filed outside of the prescribed time – whether extension of time should be
granted
– no sound recording or transcript of the Tribunal’s oral reasons for decision filed - extension of time refused .
Legislation Cited:
Civil and Administrative Tribunal Act 2013
(NSW)
Civil and Administrative Tribunal Rules 2014
(NSW)
Home Building Act 1989
(NSW)
Cases Cited:
Jackson v NSW Land and Housing Corporation [2015] NSWCATAP 281
Kelly v Szatow [2020] NSWSC 407
Texts Cited:
None cited
Category:
Principal judgment
Parties:
AGY Global Wealth Pty Ltd (Appellant)
Belen Gillies (Respondent)
Representation:
Husseini Solicitors
Wiggins Legal (Respondent)
File Number(s):
2023/00007933
Publication restriction:
Nil
Decision under appeal
Court or tribunal:
NSW Civil and Administrative Tribunal
Jurisdiction:
Commercial and Consumer Division
Citation:
N/A
Date of Decision:
07 October 2022
Before:
J Searson, General Member
File Number(s):
HB 22/32700
REASONS FOR DECISION
Background
The appeal concerns proceedings arising out of a contract to do residential building work , namely the installation of
a
10 Kw
solar panel system
with 36 solar panels and
an inverter
at a property in Rockdale, NSW. The contract was
entered into on or about
18 December 2018
between the own er Belen Alina Gillies , and the builder
Skylight Energy
trading as
AGY Global Wealth
Pty Ltd
for a contract price of
$9000 . For convenience we shall refer to the parties as the owner and the builder respectively.
The installation
was completed in or around
18 December 2018
and
the owner noted
about
one year later that the system was not functioning correctly.
On 13 December 2020 the owner commenced proceedings in the Consumer and Commercial Division of the Tribunal
claiming an amount of $10,000, being the replacement cost
of the entire system, plus out of pocket expenses .
The matter was originally heard on 23 April 2021 and orders were made in the owner ’ s
favour on
7 July 2021. The
builder was ordered to
replace the defective inverter
and the owner was given leave to Renew the proceedings, in the event that the order is not carried out or carried out defectively (the Work Order ) .
The builder sought
and was granted an extension of time to comply with the Work Order.
The builder failed to comply with
the
extended
Work Order and on
20 July 2022 the owner commenced Renewal proceedings HB
22/32700
seeking an order for payment of the sum of $10,000. The Renewal proceedings were heard on
7 October 2022 and
orders were made in favour of the owner .
The builder did not attend the hearing and was
ordered to pay
$10,835 for the cost of replacement and rectification of the
system . The Tribunal ’ s orders note that
o ral
r easons were given at the beginning of the hearing.
The builder filed a Set Aside application HB 22/46246
on the basis that a medical certificate that he claimed to have submitted excusing his absence from
the hearing on 7 October 2022 had not been considered by the Tribunal.
O n 21 November 202 2 the Tribunal dismissed the builder ’ s set aside application
and lifted the stay
of
the orders.
The builder
filed
a Notice of Appeal dated
9 January 2023. In
the Notice of Appeal the
builder
contend s
that the Appeal Panel should
set aside
the orders
made on 7 October 2022
and
dismiss the owner ’ s Renewal application.
On
25 January 2023
directions were made
in
the
a ppeal
proceedings , which included
orders for the
builder
to provide by 8 February 2023 :
All the evidence given to the Tribunal at first instance on which it was intended to rely;
Any evidence not provided to the T r ibunal at first instance in making the decision under appeal, on which it was intended to seek leave to rely;
The
builder ’ s written submissions in support of the appeal; and
As oral reasons were given a typed transcript of the relevant parts of the hearing, together with the sound recording of the entire hearing .
On 27 February 2023 the
builder
lodged submissions which did not include a sound recording or
transcript of the oral reasons.
The matter was heard by the Appeal Panel on 2 March 2023. At that hearing, the
builder
was represented by
c ounsel, who clarified that
it was the
money order
of 7 October 2022 for which review was being sought, not the decision to dismiss the set aside application.
Contrary to the contentions made in the Notice of Appeal,
c ounsel for the
builder
acknowledged that the Notice of Appeal had been lodged
out of time
and sought an extension of time in which to lodge the Notice of Appeal .
The
owner
opposed the application for an extension of time.
Time limits and extensions of time in the Appeal Panel
The decision of the Tribunal below is an internally appealable decision and an appeal can be made from that decision as of right on a question of law, or with the leave of the Appeal Panel on any other grounds: see
Civil and Administrative Tribunal Act 2013
(NSW) (NCAT Act), s 80(1) and (2)(b) and see
Jackson v NSW Land and Housing Corporation
[2015] NSWCATAP 281 at [14]-[15].
Where leave to appeal is sought and the decision the subject of appeal is a decision of the Tribunal in the Consumer and Commercial Division, the Appeal Panel may only grant leave to appeal where it is satisfied the appellant may have suffered a substantial miscarriage of justice because:
“(a)
the decision of the Tribunal under appeal was not fair and equitable, or
(b) the decision of the Tribunal under appeal was against the weight of evidence, or
(c) significant new evidence has arisen (being evidence that was not reasonably available at the time the proceedings under appeal were being dealt with).
(see NCAT Act, Sch 4, cl 12)
Clause
25(4) of the
Civil and Administrative Tribunal Rules 2014
(NSW) (NCAT Rules) prescribes the time within which an appeal from an internally appealable decision of the Tribunal is to be lodged, unless time is extended under s 41 of the NCAT Act.
In the present case , the prescribed time for lodging
an
appeal was
within 28 days from the day on which the appellant was notified of the
decision to be appealed or
first
given reasons for the decision , whether orally or in writing
(whichever is the la ter) : NCAT Rules, cl 25(4)( c )
and
25(4A).
The orders appealed against were published on 7 October 2022 and the Notice of Appeal was not lodged until
9 January 2023. The appeal was therefore lodged
more than
three
months out of time.
Extension of time
Section 41 of the NCAT Act gives the Tribunal a wide discretion to
“ extend the period of time for doing anything under any legislation in respect of which the Tribunal has jurisdiction despite anything to the contrary under that legislation ” .
The general principles which apply in considering whether leave to extend time to appeal should be granted were considered in
Kelly v Szatow
[2020] NSWSC 407 at [31]-[32]. Relevant considerations include: the length of the delay and any associated reasons for such, the strength of the plaintiff's case and consideration of whether the defendants would be prejudiced by a granting of the application: see
Jackamarra v Krakouer
(1998) 195 CLR 516 at [3]-[5];
Tomko v Palasty
(No 2) [2007] NSWCA 369 (Tomko) at [55].
The relevant considerations for an extension of time application in the Appeal Panel were set out in
Jackson v NSW Land and Housing Corporation
[2014] NSWCATAP 22 at [22]:
22.
The considerations that will generally be relevant to the Appeal Panel's consideration of whether to grant an extension of time in which to lodge a Notice of Appeal include:
(1)The discretion can only be exercised in favour of an applicant upon proof that strict compliance with the rules will work an injustice upon the appellant -
Gallo v Dawson
[1990] HCA 30, 93 ALR 479 at [2],
Nanschild v Pratt
[2011] NSWCA 85 at [38];
(2)The discretion is to be exercised in the light of the fact that the respondent (to the appeal) has already obtained a decision in its favour and, once the period for appeal has expired, can be thought of as having a "vested right" to retain the benefit of that decision -
Jackamarra v Krakouer
(1998) 195 CLR 516 at [4],
Nanschild v Pratt
[2011] NSWCA 85 at [39] and, in particular, where the right of appeal has gone (because of the expiration of the appeal period) the time for appealing should not be extended unless the proposed appeal has some prospects of success -
Jackamarra
at [7];
(3)Generally, in an application for an extension of time to appeal the Appeal Panel will be required to consider:
(a)The length of the delay;
(b)The reason for the delay;
(c)The appellant's prospects of success, that is usually whether the applicant has a fairly arguable case; and
(d)The extent of any prejudice suffered by the respondent (to the appeal),
-
Tomko v Palasty (No 2)
(2007) 71 NSWLR 61at [55] (per Basten JA) but note also [14],
Nanschild v Pratt
[2011] NSWCA 85 at [39] to [42]; and
(4)It may be appropriate to go further into the merits of an appeal if the explanation for the delay is less than satisfactory or if the opponent has a substantial case of prejudice and, in such a case, it may be relevant whether the appellant seeking an extension of time can show that his or her case has more substantial merit than merely being fairly arguable -
Tomko v Palasty (No 2)
(2007) 71 NSWLR 61 at [14] (per Hodgson JA, Ipp JA agreeing at [17]) and
Molyneux v Chief Commissioner of State Revenue
[2012] NSWADTAP 53 at [58] - [59].
Length of delay and reason for delay
Oral reasons for the
decision under appeal
were given to the parties on 7 October 2022.
Although
the Notice of Appeal
stated
that the
appeal
documents had been sent on
28 December 2022,
the Notice of Appeal
was not stamped as received by the
Appeal Panel Registry
until 9 January 2023.
The
Notice of Appeal was received significantly later than 28 days after reasons had been given.
At the hearing,
c ounsel for the
builder
submitted that
the
builder
was a small business ,
the director was involved in a number of cases and
had
found it difficult to proceed. Counsel for the
builder
acknowledged that this was probably
not a sufficient excuse
to commence proceedings significantly out of time
and the
builder
should have engaged legal representation but there had been financial
constraints .
These submissions were made
“ from the bar table ”
and no evidence was filed to support the contention.
The
builder ’ s circumstances are not unu sual.
All
appellants
are subject to the same requirements in lodging a Notice of Appeal
in time
and the
builder
has not made out any particular hardship.
We are of the view that t he reasons for the delay are not compelling.
The appellant’s prospects for success
The onus is on the
builder
to
show
a reasonably arguable case if time is extended to lodge
the
appeal ; that is ,
to show a reasonably arguable case that the Tribunal erred
on a question of
in law
or that the
builder
suffered a substantial miscarriage of justice on the grounds prescribed in cl 12 of Sch 4 of the NCAT Act.
The Tribunal gave oral reasons at the conclusion of the hearing
on 7 October 2022
to award a money order . The
builder
did not apply for written reasons and did not provide us with a sound recording or transcript of the oral reasons. Therefore, we are unaware what
findings the Tribunal made or the
reasons the Tribunal gave for its decision.
In the written submissions, the
builder
contended
that :
The award of $10835 was not fair and equitable because the
owner ’ s evidence had not justified the additional costs . The total cost of the goods supplied and installed by the
builder
was less than the amount claimed by the
owner ,
and the cost of a brand new replacement inverter was only $2493.00
The claim was a warranty claim and not the
builder ’ s duty to cover;
The
owner
had not given the
builder
access to install the new inverter;
The
owner
had not returned the products and the
builder
had been subjected to a miscarriage of justice
due to a current and potential financial loss
from
the excessive cost of orders and products and opportunity costs for future projects .
Counsel for the
builder
contended
that there had been both a miscarriage of justice and that the decision made by the Tribunal was not fair and equitable . Counsel for the
builder
acknowledged that the
builder
had not provided a
transcript or recording of the oral reasons, but
submitted that the decision on its face was unfair and had an element of miscarriage of justice .
It was further submitted
that the decision was unfair and unjust because the Tribunal had failed to consider s 48MA to the
Home Building Act 19
89
and no order had been made for the return of the faulty equipment to the
builder , resulting in unjust enrichment
to the
owner .
Whether the Tribunal
did take
s 48MA
into account or whether it was considered relevant on renewal is unclear in circumstances where the Appeal Panel
has not been provided with a transcript or sound recording of the
findings and
reasons on which the
builder
is seeking to rely
in order to establish some demonstrable error . The failure to provide a transcript or sound recording of the reasons on which the builder is seeking to rely
is also
contrary to the
directions
made on
25 January 2023 .
Nor did the
builder
request written reasons for decision, which
it
was entitled to do: NCAT Act, s 62.
Hence, in the absence of the
builder
filing and serving a copy of the sound recording of the hearing
or a transcript of the oral reasons , we are unable to identify any error in the decision of the Tribunal below . On
this basis, there can be no real prospect of the
builder
succeeding in
the
appeal or
in the
application for leave to appeal.
Prejudice
Counsel for the
builder
contended that the
owner
would not be disadvantaged by the extension of time.
In spite of the finding above that the
builder
has no real prospect of success, it is also worth noting the
owner ’ s submissions regarding prejudice if the extension of time were granted.
In the Reply to
Appeal, the
owner
noted that the matter had been determined by the Tribunal and the
owner
to the appeal had to lodge two renewal applications as a result of the
builder ’ s failure to comply with the orders.
The
owner
submitted that the
builder
was using the appeals process as a means of de lay.
The
owner
submitted that the
builder
had already had two opportunities
to put its case prior to the hearing on 7 October 2022, being the date of the original hearing on
23 July
2021 , following which
written reasons
and a work order were delivered on 7 July 2021 . After that decision was made, renewal proceedings were
commenced
on 20 December 2021 and the work order was confirmed on 11 March 2022 . The
builder
failed to comply with the work order and the matter was relisted on 18 August 2022 following which a money order was made at the hearing on 7 October 2022 at which the director of the
builder
failed to appear.
The
owner
further noted that the
builder
appeared to have abandoned the appeal by failing to comply with the orders of
25 January 2023 and failing to provide a
transcript .
(The
builder
subsequently provided submissions on
27 February 2023).
At the hearing the
owner
submitted that
she had already relied on the money order and bought a new inverter.
In our view, there is considerable prejudice to the
owner
if time were extended.
The
owner
was successful in
her
claim , both on the work order and the money order on renewal.
Two years after filing the initial application, she
has
now
relied on the money order
and replaced the faulty equipment
and would be significantly disadvantaged if the
extension of time were granted .
Conclusion
on
extension of time
The
builder
has not made out compelling reasons for the delay in filing the Notice of Appeal and has not shown
a reasonably arguable case that
that the appeal
might succeed.
Without a recording or transcript of the oral reasons, we are unable to ascertain what the reasons were for making the order
that the
builder
seeks to overturn. As a result,
the
builder
is unable to demonstrate that those reasons raise a question of law
upon which there would be a right of
appeal or
a substantial miscarriage of justice
for which leave to appeal could be sought. Additionally, we are satisfied that the
owner
would suffer considerable prejudice were an extension of time in which to appeal granted.
For the reasons set out above, we find that it is not appropriate to make an order under s 41 of the NCAT Act
granting an extension of
time
for the
builder
to lodge the Notice of Appeal .
Conclusion and Orders
As we have refused the
builder ’ s application for an extension of time within which to lodge
the
Notice of Appeal, this also disposes of
the
appeal and application for leave to appeal.
We make the following orders:
The application for
an extension of
time to lodge
the
Notice of Appeal is refused .
Appeal dismissed.
I hereby certify that this is a true and accurate record of the reasons for
decision of the Civil and Administrative Tribunal of New South Wales.
Registrar
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Decision last updated:
27 March 2023
Official source: https://www.caselaw.nsw.gov.au/decision/18711597096618ac2b5ca31f