2 Phillip Rise Pty Ltd v Kempsey Shire Council [2023] NSWLEC 28
Catchwords: APPEAL - Appeal against the refusal of application for a construction certificate ‑ Acting Commissioner holds that development consent proposed to found the construction certificate had lapsed ‑ Applicant challenges Acting Commissioner ’s conclusion as wrong at law ‑ Acting Commissioner concluded that contamination testing did not satisfy a condition of the development consent because the testing had not been carried out by the then owner of the site for the purposes of satisfying the development consent - carrying out contamination testing in satisfaction of the condition of the development consent relied upon by the Applicant as demonstrating the development consent had not lapsed ‑ condition required that contamination testing be undertaken ‑ purpose for which the relevant contamination testing was carried out ‑ carrying out of contamination testing which complied with the terms of the development consent condition as a matter of fact, in its scope sufficient to satisfy the condition no matter by whom and why that testing was carried out - appeal upheld ‑ directions given to permit construction certificate to be uploaded to the Planning Portal and the making of orders to finalise the proceedings COSTS ‑ costs in s 56A appeals follow the event - Respondent ordered to pay the Applicant's costs of the appeal
Land and Environment Court
New South Wales
Medium Neutral Citation:
2 Phillip Rise Pty Ltd v Kempsey Shire Council [2023] NSWLEC 28
Hearing dates:
12 December 2022
Decision date:
22 March 2023
Jurisdiction:
Class 1
Before:
Moore J
Decision:
See
directions
at [
73]
Catchwords:
APPEAL - Appeal against the refusal of application for a
construction certificate
‑
Acting Commissioner
holds that
development consent
proposed to found the
construction certificate
had lapsed ‑ Applicant challenges
Acting Commissioner ’s conclusion as wrong at law ‑
Acting Commissioner
concluded that contamination testing did not satisfy a condition of the
development consent
because the testing had not been carried out by the then owner of the site for the purposes of satisfying the
development consent
-
carrying out contamination testing in satisfaction of the condition of the
development consent
relied upon by the Applicant
as demonstrating the
development consent
had not lapsed ‑
condition required that contamination testing be undertaken
‑
purpose for which the relevant contamination testing was carried out
‑ carrying out of contamination testing which complied with the terms of the
development consent
condition as a matter of fact, in its scope sufficient to satisfy the condition no matter by whom and why that testing was carried out
-
appeal upheld ‑ directions
given to permit
construction certificate
to be uploaded to the
Planning Portal
and the making of orders to finalise the proceedings
COSTS
‑
costs
in
s
56A appeals follow the event
-
Respondent ordered to pay the Applicant's costs of the appeal
Legislation Cited:
Environmental Planning and Assessment Act 1979
, s 99
Land and Environment Court Act 1979
, s 56A
Cases Cited:
2 Phillip Rise
Pty Ltd v
Kempsey Shire Council
[2022]
NSWLEC 1107
Hunter Development Brokerage Pty Ltd v Cessnock City Council;
Tovedale
Pty Ltd v Shoalhaven City Council
(2005)
63 NSWLR 124;
[2005]
NSWCA 169
Project Blue Sky Inc v Australian Broadcasting Authority
(1998) 194
CLR 355; [1998] HCA 28
Taylor v The Owners of Strata Plan 11564 and Others
(2014) 253
CLR 531; [2014] HCA 9
Category:
Principal judgment
Parties:
2 Phillip Rise Pty Ltd (Applicant)
Kempsey Shire Council (Respondent)
Representation:
Counsel:
Mr R Lancaster SC (Applicant)
Mr M Seymour, barrister (Respondent)
Solicitors:
Norton Rose Fulbright Australia (Applicant)
Local Government Legal (Respondent)
File Number(s):
88745 of 2022
Publication restriction:
No
TABLE OF CONTENTS
Introduction
The Summons commencing the appeal
Relevant statutory provisions
Representation
The hearing
The evidence
The 1993 development consent
The evidence before the Acting Commissioner and his decision
The position advanced by the Company
The position advanced for the Council
Consideration
Costs
Return of exhibits
Directions to give effect to my conclusion
Judgment
Introduction
On 22
December
2021 (with subsequently provided written submissions),
Bradbury
AC
heard an appeal by
2
Phillip
Rise
Pty Ltd (the Company) against a deemed refusal by
Kempsey
Shire
Council
(the Council) of the Company's application to be issued a
construction
certificate
for a development comprising
site
clearing
and preparatory works for a resort complex comprising 180
residential units ,
together with
a
commercial and administration complex
to be located
at
2
Phillip
Drive ,
South
West
Rocks
(the site) .
Development
consent
had been granted for the Company's proposed development in 1993 .
The basis of the Council's opposition to the granting of the
construction
certificate ,
during the hearing before the
Acting
Commissioner ,
was that the
1993
development
consent
had lapsed and,
as a consequence , there was no basis upon which the
Acting
Commissioner
could found a determination to order the issuing of a
construction
certificate
to
the Company.
On 1
March
2022, the
Acting
Commissioner
handed down his decision (
2 Phillip Rise
Pty Ltd v
Kempsey Shire Council
[2022]
NSWLEC
1107 ) .
He determined that the Company ’ s appeal should be dismissed and the Company ’ s application for a
construction
certificate
refused .
The
Acting
Commissioner ’ s orders were:
1
The appeal is dismissed.
2
Construction certificate
Application CFT-78801 to undertake
site clearing
works in accordance with
Development consent
T4-91-195 in respect of Lot 2 DP 1091323 known as 1 Phillip Drive,
South West Rocks
is determined by refusal.
3
The exhibits are returned other than exhibits A and B.
On
28
March
2022 , the Company commenced an appeal pursuant to
s
56A of the
Land a
nd Environment
Court Act
1979
(the
Court
Act ) against the
Acting
Commissioner 's decision .
Such appeals are confined to being ones on questions of law .
The terms of
s
56A of the
Court
Act
are later reproduced.
The Summons commencing the appeal
The Summons commencing the Company ’ s appeal is in the following terms:
DETAILS OF APPEAL
1
Pursuant to
s 56A of the Land and Environment
Court Act
1979, the Appellant appeals from the whole of the decision below.
ORDERS SOUGHT
1
Appeal allowed.
2
The Orders of the Court below on 1 March 2022 be set aside.
3
The application for
construction certificate
CFT-78801 is approved and a
construction certificate
is issued in relation to part of the development
2 Phillip Drive ,
South West Rocks
NSW 2431, being
site clearing
and preparatory works approved under
development consent
T4-91-95 for the establishment of a resort complex comprising 180 residential units together with commercial and administration complex.
4
The respondent to pay the applicant’s costs of this appeal.
5
Such other orders as the Court deems appropriate.
APPEAL GROUNDS
1
Given his findings that:
a.
acid sulphate
soil testing was required by condition
38,
b.
acid sulphate
soil testing was engineering work (Work) (at [47] and [52]), and
c.
the Work was carried out before the relevant date,
the Commissioner should have found that the Work related to the development for which the consent had been granted and thus the consent had not lapsed.
2
The Commissioner erred in law in imposing an additional test not found in the statutory provision (at [52]) that it was necessary to find that the entity carrying out the
acid sulphate
soil testing had as its purpose that of complying with condition 38 of that consent before finding that those works related to the development for which
development consent
was granted.
Relevant statutory provision s
It is necessary to set out the element of the
Court
Act
which provides the basis for the Company's appeal .
The Company's appeal is, as earlier indicated, founded on
s
56A of the
Court
Act .
This provision is in the following terms:
56A
Class 1, 2, 3 and 8 proceedings—appeals to the Court against decisions of Commissioners
(1)
A party to proceedings in Class 1, 2, 3 or 8 of the Court’s jurisdiction may appeal to the Court against an order or a decision of the Court on a question of law, being an order or a decision made by a
Commissioner
or Commissioners.
(2)
On the hearing of an appeal under subsection (1), the Court shall—
(a)
remit the matter to the Commissioner or Commissioners for determination by the Commissioner or Commissioners in accordance with the decision of the Court, or
(b)
make such other order in relation to the appeal as seems fit.
(3)
Notwithstanding subsection (1), an appeal shall not lie to the Court under that subsection in respect of a question of law that has been referred to, and determined by, a Judge pursuant to
section 36.
As can be seen, such appeals are confined to ones on questions of law .
Issues that were addressed in the decision of a primary
decision ‑ maker
(here
Bradbury
AC ) concerning questions of fact ,
or mixed questions of fact and law ,
cannot provide a basis for such an appeal (unless such a decision is
“ legally
unreasonable ”
so as to
give rise to a question of law) .
This distinction between matters capable of founding an appeal and matters incapable of doing so is engaged for this appeal as it comprises, in part, the basis upon which the Council proposes that the Company's appeal should be dismissed.
In addition to the above provision of the
Court
Act , one provision of the
Environmental Planning a
nd Assessment Act 1979
(the
EPA
Act ), as in operation as at the date of the Council granting its
development
consent
on 24
February
1993 ,
is also engaged .
The provision,
s
99 of the
EPA
Act , as at that date ,
was in, relevantly, the following terms:
99
Lapsing of consent
(1)
A
development consent
lapses:
(a)
5 years after the date from which it operates, except as provided by paragraph (b), or
(b)
…
(2)
…
(3)
…
(4)
Development consent
for:
(a)
…, or
(b)
…, or
(c)
the carrying out of a work,
does not lapse if building,
engineering
or construction work relating to the building, subdivision or work is physically commenced on the land to which the consent applies before the date on which the consent would otherwise lapse under this section.
(4A)-(11)
…
Representation
The Company was represented by
Mr
R
Lancaster
SC ,
with the Council being represented by
Mr
M
Seymour , barrister .
Concise written submissions were provided on behalf of the parties .
It will be necessary, later, to refer to, and/or quote from, those written submissions.
The hearing
The hearing of the Company's appeal was held on 12
December
2022 .
It was conducted efficiently, being completed in half a day.
The evidence
The evidence for the Company comprised its
Appeal
Book
( Exhibit
A ) and a chronology covering the period from the date of granting the
1993
development
consent
(24
February
1993) to 28
March
2022
( the date of the
Summons
commencing this appeal being filed ( Exhibit
B ) ) .
The only other relevant date to be noted is that the
borehole
drilling ,
to which later reference is made ,
had been completed by 29
October
1994.
The evidence on behalf the Council comprised its
Appeal
Book
( Exhibit
1 ) and a marked-up air photo plan of the site ( Exhibit
2 ).
The
1993
development
consent
For the purposes of this appeal, two aspects of the
1993
development
consent
required to be noted .
The first is that the
1993
development
consent ’ s notice of determination included, amongst the conditions of consent forming part of the determination,
condition
38 .
Condition
38 is in the following terms:
Further testing for the presence of
acid sulphate
soils shall be undertaken prior to the release of the building application and appropriate measures identified and implemented to obviate and [any] impact.
The question of
whether or not
this condition has been satisfied is critical to the present appeal.
Second, t he conditions also contained
a number of
requirements that mandated that further information be provided to the Council before the consent could be acted upon ‑
these conditions, although needing to be addressed later, did not
provide any basis upon which it could be concluded that the
1993
development
consent
might have lapsed.
It is to be noted that the testing undertaken in
January
1995 (following the
borehole
drilling ,
which was completed in late
October
1994) disclosed, relevantly, no presence of
acid
sulphate
soil or potential
acid
sulphate
soil on the site and thus, subject to the legal issues decided by the
Acting
Commissioner
and forming the subject of this appeal, the requirement to prevent lapsing would have been satisfied .
This was because the borehole
drilling
and testing of the material extracted from the borehole constituted engineering work for the purposes of
s
99(4) of the
EPA
Act
as earlier set out (
Hunter Development Brokerage Pty Ltd v Cessnock City Council;
Tovedale
Pty Ltd v Shoalhaven City Council
(2005)
63
NSWLR
124 ;
[2005]
NSWCA
169 ).
Setting aside the matters here requiring consideration, the
1993
development
consent
would therefore not have lapsed pursuant to the then applicable
s
99(1)(a)( i ) of the
EPA
Act .
The
evidence before the
Acting
Commissioner
and hi s decision
It is next appropriate to set out how the
Acting
Commissioner
approached the issues in contest in the hearing before him.
The
Acting
Commissioner
considered that he was required to determine
whether or not
the
1993
development
consent
had lapsed .
He was of the view that it was
a necessary prerequisite
to upholding the Company's appeal and determining that a
construction
certificate
was appropriate to be issued for the building works for which the Company sought approval
needed to
be based on a
development
consent
which validly subsisted to provide a foundation for such
construction
certificate .
For this purpose, the
Acting
Commissioner
considered whether testing for (relevantly) the presence of
acid
sulphate
soils across a wider area than the site (but including a borehole for such testing purposes on the site) satisfied
t he terms of
condition
38 of the
1993
development
consent .
The
acid
sulphate
soil testing had been carried out
for
an oil company, Caltex
Petroleum
Pty Ltd
(Caltex), the
former
owner
of
a
larg er area
of land
which included the Company's site .
The testing undertaken by environmental consultants engaged by Caltex was required to be undertaken as a consequence of a groundwater contamination plume across the site travelling down gradient toward
Salt
Water
Creek .
The plume was located, in part, under the
westerly
portion of the site .
Caltex was required to remediate the contamination caused by the plume using a remediation technique known as
“ air
spar ging ” .
Caltex required access to the Company ’ s site
in order to
undertake the EPA ‑ mandated testing regime across the wider area for which it was required
by that bo d y .
By letter dated 7
June
1994 ( prior to entry into the deed discussed below ), the legal representatives of the then owner wrote to the solicitors representing Caltex .
This letter is also in evidence as part of the papers behind
Tab
6 of
Exhibit
A
before me .
It was also in evidence before the
Acting
Commissioner ,
comprising portion of the Applicant's
Tender
Bundle
( Exhibit
B ) in the proceedings below .
The relevant paragraph of that letter was in the following terms:
Could you please provide, in detail, the methods, procedures and protocols (including testing sites) to be used in the confirmatory testing specifically proposed for Lot 504 to determine
whether or not
there are
acid sulphate
soils or potential
acid sulphate
soils in or on the relevant part of Lot 504.
The then owner of the Company's site,
Chrisbeck
Pty Ltd ( Chrisbeck
-
the
former
owner ) , and Caltex
entered into
a deed which granted Caltex access to
the Company's site in order to undertake testing on the site as part of the broader suite of testing Caltex was mandated to undertake .
The deed between
the
former
owner
and Caltex was dated
30
September
1994 .
A number of
elements of the deed require consideration in this appeal .
First, it is appropriate to set out the terms of the recital to the deed .
This
recital
reads:
Chrisbeck
has the benefit
of, and
intends to develop Lot 504 in accordance with the Lot 504
Development consent, and has agreed to permit Caltex to enter the Land, and Caltex has agreed to enter the Land, on the terms and conditions of this Deed.
The
development
consent
mentioned in the recital to the deed set out immediately above is the
development
consent
which has been the subject of the
Acting
Commissioner ’ s consideration in the appeal dealt with by him .
It is to be noted that
cl
2 of the deed
provided that
Caltex was to pay the
former
owner
an access fee of $140,000 for the right to access the site and to carry out the testing permitted by the deed.
The definitions in
cl
2 of the deed defines the term
“ Works ”
as meaning
“ the works referred to in
cl
3.1 ” .
N ext, it is appropriate to set out what the deed defines, relevantly, as the activities which Caltex
was
permitted to undertake on the site .
Th ese works were
set out , relevantly,
in
cl
3.1
of the deed in the following terms:
Chrisbeck
hereby grants Caltex and any contractor or consultant engaged by Caltex to carry out the works (including without limitation
Groundwater Technology Australia
Pty Ltd), a non-exclusive license to enter the land by the access points for the purposes of carrying out the following works:
•
investigation to ascertain the extent and nature of any
acid sulphate
soils or potential
acid sulphate
soils in or on the
land;
•
irrelevant;
•
irrelevant;
•
irrelevant;
•
conducting on the land transect drilling to an approximate average depth of 10 m at locations generally indicated on the transect drilling
plan;
•
taking and testing samples from the transect drilling to ascertain the extent and nature (if any) of any
acid sulphate
soils or potential
acid sulphate
soils
…;
•
irrelevant;
•
irrelevant.
Finally, the deed contains a confidentiality clause restricting
the
former
owner
as to the circumstances under which
the
former
owner
might be permitted to disclose information concerning the outcome of the testing to be undertaken by Caltex's consultants.
The deed also provided, in
cl
4.1 , that a copy of the report which would result from the testing to be undertaken on behalf of Caltex would be provided to
the
former
owner .
Environmental consultants,
Groundwater
Technology
Australia , carried out the testing on behalf of Caltex and produced a report dated
January
1995 .
Mr
Malcolm
Dale ,
a
senior employee of
Groundwater
Technology
Australia ,
supervised the carrying out of the testing that was undertaken for Caltex .
Mr
Dale
gave evidence before the
Acting
Commissioner
and a copy of his expert report forms part of the material behind
Tab
6
of the
Exhibit
A
in these proceedings .
It is appropriate to set out what
Mr
Dale
said at
Sections
7.2.2 and
7.2.3 of his expert report .
These were in the following terms:
7.2.2.
Acid sulphate soil testing consistent with clause 38
Acid sulphate soil testing undertaken by GTA was in accordance with the deed of access between Caltex Oil and
Chrisbeck
Pty Ltd communicated to GTA via a letter WE910114.DRH:
11, dated 5 October 1994.
GTA was not aware of the reasoning behind the
acid sulphate
testing request.
7.2.3.
Acid sulphate soil testing
As part of the access agreement for lot 504 communicated to GTA, only one borehole (DMW17) was proposed to be assessed for ASS . Another borehole (BMW 22) was also assessed for ASS in the
CaLM
land as per section 7.2.1
One borehole was considered sufficient at the time to assist the presence of ASS or PASS .
The borehole would be sampled and tested at multiple levels to determine the depth of any potential ASS and would be a good indicator of the presence or absence of actual or potential ASS .
If ASS or PASS was detected in the borehole, further sampling may have been required to determine the extent of any ASS or PASS .
Previous testing by e.g .
I of the former terminal land and number 64 Phillip Drive and mentioned in the procedures, suggested that acid forming soils were unlikely to be present on Lot 504.
Testing for ASS and PASS by contaminated land consultants in the mid-1990s was not mainstream, however,
acid sulphate
risk soil mapping was published by the NSW Department of land and water conservation (including the soil conservation service) in 1995, and comprehensive guidance on
acid sulphate
soils was issued in 1998 entitled:
acid sulphate
soils assessment and guidelines NSW,
acid sulphate
soils management advisory committee, August 1998.
Testing for ASS and PASS is now routine part of any environmental assessment may still only include sampling from one or two boreholes from the broader site sampling plan .
Should ASS or PASS be identified an Acid Sulphate Management Plan would be required for any works program in accordance with the 1998 guidelines.
It is not in dispute that the borehole on what is now the Company's site was tested for
acid
sulphate
soils and that this testing revealed no presence of
acid
sulphate
soils or potential
acid
sulphate
soils at the borehole that was sampled .
The report disclosing this position was in evidence before the
Acting
Commissioner
and was in evidence before me.
The transcript before the
Acting
Commissioner
shows that the above matters were addressed by
Dr
Brunton
who was representing the Company before the
Acting
Commissioner .
He submitted (Transcript 22
December
2021 , page
44 , line
28 to page
45 , line
1):
Mr Dale
has pointed out in his evidence, the mere fact that there was one well on the subject land was consistent with the practice in
1993 and 1995 of identifying and assessing the likelihood of the presence of acid phosphate soils .
His opinion is that not only was it consistent with the practice in 1993, but it would also be the practice today . He says in section 2.7.2.3 of his report behind
Tab
21
Exhibit B :
“T esting for acid
…
1998 guidelines ”.
So we would submit that not only was he, in carrying out the testing in
1993 it was testing carried out as required by
condition
3.1(a) of the access deed and that testing was required by the landowner, with respect, for the purpose of satisfying this consent condition and that is underscored by the letter of the landowner solicitor dated 7 June
1994 behind
Tab
20, with a landowner sought from Caltex the detail of members (numbers) procedures and protocols, including testing sites to be used in the confirmatory testing specifically proposed for Lot 504 to determine whether or not any
acid sulphate
soils or potential
acid sulphate
soils in the relevant (not transcriber wall).
So
we would say the legal test has been met from the facts in this particular matter, and the contention of Council that there is not enough evidence to be satisfied that the works carried out by GTA related to the development cannot be sustained. Because that showed the works for
acid sulphate
soil testing at the forefront of the landowner's mind as it is proven by the correspondence; it's referred to in the title of the deed and is an express clause in the deed for requiring Caltex to do the very testing.
It is to be noted that, by letter
in
2007, the Company's legal representatives provided a copy of this report to the Council in response to a request from the Council for further information
a s to whether
condition
38
of the
1993
development
consent
had been satisfied in a fashion which would have prevented that consent from lapsing.
There is no direct evidence of consent being granted by Caltex pursuant to
cl
14 .1 ( b ) of the deed for this purpose, but the necessary inference (accepted by the parties for the purposes of the proceedings before the
Acting
Commissioner
and before me) is that such consent had been granted to the Company .
The
Acting
Commissioner
formed the view that, before he could contemplate deciding
whether
to order the issuing of a
construction
certificate
to the Company, he needed to be satisfied that the
1993
development
consent
had not lapsed .
He invited the parties to address him on this point .
His conclusion, that
the
1993
developmen t
consent
had lapsed because
condition
38 had not been satisfied, was based on his analysis of the circumstances surrounding the testing which had been undertaken by
Groundwater
Technology
Australia
for
Caltex and whether it could be
relied upon
for the purpose of satisfying
condition
38 of the
development
consent .
In this context, he explained his reasoning for concluding that
condition
38 had not been satisfied
at
[ 51 ] to
[ 54 ] of his judgement .
It is appropriate, although somewhat lengthy, to set out these paragraphs in full,
as they explain his reason s
for reaching that conclusion
- ones
founded on why he considered
condition
38
ha d not been
satisfied
had led to the lapsing
of the
1993
development
consent .
The paragraphs are in the following terms:
51
The evidence clearly establishes that the acid sulphate soil testing carried out by GTA was carried out on the instruction of Caltex for the purpose of determining the presence of acid sulphate soils, as these would impact on the proposed method of remediating hydrocarbon contamination in the land.
52
I accept that acid sulphate soil testing is relevantly engineering work that
is capable of constituting
the physical commencement of development for the purposes of s 99(4) of the EPA Act. It is also well established that such work can relate to the development even if it serves more than one purpose:
Hunter
at [115]. However, I am not satisfied that the acid sulphate soil testing in this appeal was carried out for the purpose of complying with condition 38 of the Consent, and thus “relates to” the development the subject of the Consent. My reasons for coming to this conclusion are as follows:
(1)
Chrisbeck
had no involvement
in the design of the acid sulphate sampling protocol devised by GTA. If the testing was being done in part to satisfy
Chrisbeck’s
obligations under condition 38, one might reasonably have expected that
Chrisbeck would have indicated what its, or the Council’s, requirements were in relation to that testing.
(2)
The Deed allowed Caltex, for a fee, to access
Chrisbeck’s
land for the purpose of carrying out the acid sulphate soil testing but did not impose any obligation on Caltex to do any sampling or testing. Again, If the testing was being done in part to satisfy
Chrisbeck’s
obligations under condition 38, one might reasonably have expected that it would have required Caltex to carry out the testing required for that purpose.
(3)
Chrisbeck
did not provide the results of the testing to the Council until 2007, some 12 or 13 years after the testing had been done.
(4)
While the Deed
makes reference
to the existence of the Consent, it does not recite that the Consent required testing for acid sulphate soils or that the results of the testing to be done by Caltex would be relied on by
Chrisbeck
for the purpose of satisfying condition 38.
(5)
The confidentiality provision in the Deed meant that
Chrisbeck
could not provide the results of the acid sulphate soil testing to the Council except with the further agreement of Caltex. If
Chrisbeck
had intended to provide the acid sulphate soil test results to the Council to satisfy its obligations under condition 38, one might reasonably have expected to see its ability to do so, without the need for any further approval from
Caltx, reflected in the terms of the Deed.
(6)
The only bore hole and well established by Caltex on the Site for the purpose of testing for acid sulphate soils, is located outside the area proposed to be developed under the Consent. This is a strong indicator, in my view, that the testing was done solely for Caltex’s purposes and not also for the purpose of satisfying the requirements of condition 38.
53
Returning to the principles established in
Hunter , in my view the Applicant has not demonstrated:
(1)
a “real nexus” between the acid sulphate soils testing carried out by GTA for Caltex and the additional testing required by condition 38 of the
Consent;
(2)
that there is more than a merely notional or equivocal connection between the testing carried out by GTA and the testing required by condition 38 of the
Consent;
(3)
a real relationship or connection between the testing carried out by GTA and the testing required by condition 38 of the
Consent;
(4)
that the testing carried out by GTA was of the type required to satisfy the requirements of condition 38 of the Consent.
54
I have therefore concluded that the acid sulphate soils testing did not relate to the Consent. Accordingly, I find that the Consent lapsed on 24 February 1998. This finding is sufficient to refuse the construction certificate and dismiss the appeal. However, as the remaining jurisdictional pre-requisites were the subject of evidence and submissions, I will briefly set out my findings relevant to those matters.
Having concluded that
condition
38 had not been satisfied, the
Acting
Commissioner
then also proceeded to consider the further contention of the Council that had been advanced to him as a basis why a
construction
certificate
should not be issued because the Company had failed
to provide a range of information which was otherwise required to have been provided to the Council to permit this to happen.
It is sufficient, for present purposes, that this contention was dealt with by the
Acting
Commissioner .
It is not necessary to set out his analysis on these points .
It is
also
sufficient to note that he concluded that, had he been satisfied that the consent had not lapsed because of the failure to satisfy
condition
38, he would have concluded that this second contention would not have prevented him from ordering the issuing of a
construction
certificate
to the Company.
The position advanced by the Company
The position advanced by
Mr
Lancaster
for the Company concerning the required satisfaction of
condition
38 within the relevant
time period
by the testing undertaken on behalf of Caltex was a comparatively simple one.
First, he noted that there was no dispute that the testing had been undertaken for Caltex in a timely fashion
- thus
not raising any issues of lapsing in this regard .
In this context, it is to be noted that, although the results of the testing were first notified to the Council by letter from the Company's legal representatives to the Council
in
2007,
condition
38, in terms, did not mandate that the testing information needed to be provided to the Council - merely that the testing was required to have been undertaken.
The
Acting
Commissioner
had formed the view that, for him to be satisfied that
condition
38 was satisfied, the testing commissioned by Caltex and undertaken by
Groundwater
Technology
Australia
was undertaken for the purpose of satisfying the condition.
By approaching the matter in the above fashion,
Mr
Lancaster
submitted, the
Acting
Commissioner
had misdirected himself as to how he should understand the concept of purpose for the appropriate analysis of
whether or not
condition
38 had been satisfied .
The
Acting
Commissioner
had, he submitted, understood
“ purpose ”
to mean the reason why the testing was undertaken .
The Acting
Commissioner ’ s consideration of the
“ purpose ”
in the fashion undertaken by him misunderstood how he was to approach the question of compliance with condition
38 and, thus, the potential for lapsing of the 1993
consent.
The extent of the testing, both as to the substances encompassed by the laboratory testing of the samples that were taken by Groundwater
Technology
Australia and the location of the various boreholes sunk across the wider area than the Company ’ s site encompassed by the Caltex testing scope was shown in the report provided to the Council in 2007.
The report included the results from a relevant borehole on the Company ’ s site.
Mr
Lancaster
submitted that the correct approach to the concept of
“ purpose ”
was not to ascertain why the testing had been undertaken, but to ask what had been sought to be achieved, relevantly, by the scope of the testing
and the results from it .
Considering the question of
“ purpose ”
on the
“ what ”
rather than the
“ why ”
basis meant, he submitted, that the results
from
the
borehole
within the Company site
w ere
what was relevant for the purposes of satisfaction of condition
38 .
Mr Lancaster submitted that the critical point was that, as a matter of fact, one borehole on the Company ’ s site had been tested for acid sulphate soils and none were found.
In this context, the fact that this
borehole
had been drilled on the Company ’ s
site
and acid
sulphate soils testing undertaken
at a location consiste nt
with the
expected or known extent of the contamination which Caltex would be required to remediate ,
was sufficient, as a matter of scientific fact, to demonstrate that
condition
38 had been satisfied ,
Mr
Lancaster
proposed .
This conclusion arose,
Mr
Lancaster
submitted, because the
“ purpose ”
for which the testing commissioned by Caltex had been undertaken was to ascertain the extent of contamination at the locations where boreholes were sunk and determining, by laboratory analysis, what was or was not the presence of various potential contaminants (here relevant, the presence of
acid
sulphate
soils or potential
acid
sulphate
soils on the Company ’ s site as required by
condition
38).
Viewing the
“ purpose ”
of the testing commissioned by Caltex in this context, what motivated the commissioning of the testing (as had been considered by the
Acting
Commissioner in his analysis of the
“ purpose ”
of the testing as he construed it) was irrelevant .
On this basis, he submitted that
condition
38 had been satisfied, and that
not only should the appeal be upheld, but I should order that a
construction
certificate
be issued to the Company
in order to
permit i t
undertake the range of building works proposed as they were within the scope of the
1993
development
consent
which continued to subsist.
The position advanced for the Council
Mr
Seymour
advanced two bases upon which he submitted that the
Acting
Commissioner 's decision should be
sustained
and the appeal dismissed .
The two bases upon which he founded his submissions were significantly different .
The first of them was founded on a somewhat complex structure of submissions as to broader matters of statutory construction
on
what
Mr
Seymour
proposed
was the necessary mandated process governing applications for the issuing of
construction
certificate s.
The second basis for sustaining the
Acting
Commissioner 's decision was that the
Acting
Commissioner
had been correct in how he had approached the issue of
whether or not
condition
38 had been satisfied.
I advanced the proposition to
Mr
Seymour
that, if I was satisfied that the Company's position concerning how the testing undertaken by Caltex should be approached for the purposes of determining whether
condition
38 had been satisfied was correct, such a conclusion rendered it unnecessary to consider the first basis for his submissions . Mr
Seymour
indicated that he accepted the validity of that proposition .
Although
Mr
Seymour
comprehensively took me through the relevant elements of the
Groundwater
Technology
Australia
report and the deed between
the
former
owner
and Caltex which permitted the testing to be undertaken, it is unnecessary for me to address any of that detail .
He did so for the purpose of demonstrating to me, in his submission, that the approach which had been taken by the
Acting
Commissioner
to understanding how the testing which had been undertaken by Caltex's consultants should be seen for the purposes of determining
whether or not
the testing satisfied
condition
38 and, therefore, engaged
s
99(4) of the
EPA
Act
as at the relevant date .
He submitted that doing so in the fashion he advanced demonstrated the correctness of the
Acting
Commissioner ’ s approach.
Given that I have rejected his propositions and am satisfied that the
“ purpose ”
for which the testing was undertaken, relevantly, was to determine
whether or not
acid
sulphate
soils and/or potential
acid
sulphate
soils were present in
the
borehole
that was located on the Company ’ s site , such an analysis is unnecessary.
Given that, for reasons later explained, I am satisfied that the Company ’ s position now advanced concerning
the satisfaction of
condition
38 is correct and that there are no other impediments arising from the terms of the
1993
consent acting as a barrier to the issuing of a
construction
certificate
to the Company, there is no need to consider whether or not
Mr
Seymour 's
first line of
submissions based on matters of statutory construction are valid or not.
It is, therefore, not necessary to set out the detail of this more general basis advanced in support of the
Acting
Commissioner 's decision, because it is rendered irrelevant by my finding that the
1993
development
consent
has not lapsed
(as
Mr
Seymour
had
submitted ,
as earlier noted, would be the position) .
Consideration
The submissions made by
Mr Lancaster
to the effect that it is the scope of that which is carried out as potentially being capable of satisfying
condition
38 rather than who carried out that activity and what, if anything, is to be understood of the reason why that activity was carried out are correct .
The
consideration of what was required by
condition
38
was clearly one to be approached
on the basis of
conventional statutory interpretation (
Project Blue Sky Inc v Australian Broadcasting Authority
(1998) 194
CLR
355; [1998]
HCA
28) without any need to read additional words into the provision as might otherwise have been permitted if necessary (
Taylor v The Owners of Strata Plan 11564 and Others
(2014) 253
CLR
531; [2014]
HCA
9) .
Taking the narrow approach adopted by the
Acting Commissioner
that, in effect, any activity which would fall within the scope of
s
99(4) of the
EPA Act
would be required to be carried out by, or directly on behalf of, the beneficiary of the consent at the time such activity took place is a position which involves, in my assessment, an impermissibly narrow interpretation of
s
99(4) .
Indeed, to reach such a conclusion would have necessitated
read
ing
additional
and unnecessary
words into the provision .
On this basis, I am satisfied that the Company's appeal should be upheld.
In these circumstances, it is unnecessary to consider whether the
Acting Commissioner
should have addressed the question of what inference should be drawn from the paragraph in the letter from the legal representatives of the
former owner
to the legal representatives of Caltex
during the course of
the negotiation for the deed that permitted Caltex to undertake the testing
‑
a paragraph earlier set out
at [
22 ].
However, that the Company's case before me was not advanced
on the basis of
what should be inferred (if anything) from this correspondence
also
renders it unnecessary for me to consider it.
It is to be noted that the deed between Caltex and
the
former
owner
which permitted Caltex to undertake the testing on the Company ’ s site as part of Caltex's testing across a wider area, the fact that the owner was identified as
Chrisbeck
is irrelevant for present purposes .
This is because, if the
1993
development
consent
remains valid, it runs with the land and the benefit of relying upon it is currently held by the Company for the purposes of these proceedings.
It is here appropriate to note that, as the relief sought by the Company in its appeal was that I should order the issuing of the requested
construction
certificate
to the Company ,
utilising the power to do so given by
s
56A(2)(b) of the
Court
Act ,
if I concluded that
condition
38 had been satisfied
and the appeal should be upheld , I needed to also be satisfied that there was no other impediment to doing so .
For this purpose, should it arise, I indicated to
Mr
Seymour
that I would need to know
whether or not
the
“ insufficient
information ”
contention that had been pleaded before the
Acting
Commissioner
was now accepted by the Council as no longer standing as a barrier to the ordering of a
construction
certificate
because the required additional information had been supplied to the Council .
Mr
Seymour
indicated he that he would need to have relevant Council officers contacted
in order to
determine what the current position with respect to those matters was .
I directed that that information be obtained as soon as was practicable .
After I reserved my decision, I was advised by the Council's solicitor (by e ‑ mail to my Associate) that:
Council has now instructed that it has received the information of the kind in conditions 5 and 17 of the Consent .
Accordingly
Council would accept His Honour can issue a
Construction certificate
if he was otherwise to find the error.
As I have concluded that
condition
38 was satisfied by the testing undertaken by
Groundwater
Technology
Australia
(even though undertaken pursuant to the deed between the
former
owner
and Caltex) resulting in the
1993
development
consent
not lapsing, there now remains no impediment to me exercising the discretion available pursuant to
s
56A(2)(b) of the
Court
Act
and ordering that the appeal
be
upheld and that a
construction
certificate
be issued to the Company.
Costs
Costs in appeals pursuant to
s
56A of the
Court Act
ordinarily follow the event
.
There is nothing in these proceedings which would cause me to depart from that position .
It is therefore appropriate to order that the Council is to pay the Company's costs of the appeal , t he orders for which I have made provision in the directions ,
at [
7 3 ]
below ,
are to include an order to give effect to this
costs
outcome.
Return of exhibits
The orders for which I have made provision in the directions ,
at [
7 3 ]
below ,
are also to provide for the return of the exhibits to the party which tende re d the exhibit.
Directions to give effect to my conclusion
As I understand the position, it is necessary
that
the terms of the
construction
certificate
to be issued
are
made available
through
the NSW
Planning
Portal .
In order to
give effect to this as reflecting the outcome of this appeal, it is appropriate to direct that the parties confer and settle the terms of the orders necessary to
achieve
this outcome .
I therefore give the following directions:
The parties are to confer and, if agreed, provide settled orders to my Associate, in Microsoft Word format, to give effect to the conclusion that the appeal
is to
be upheld and a
construction
certificate
as sought by the Company is to be issued to the
Company;
Any settled orders are to be provided electronically to my Associate by the close of business on
29
March
2023;
If settled orders are provided to my Associate pursuant to
(2), I will make orders in chambers to finalise the appeal ;
and
If the parties are unable to agree on the terms of orders to give effect to the outcome of these present proceedings as provided for in
(1) and
(2), the matter is listed for mention before me at
8.30
am
on
3 0
March
2023
to permit me to resolve any matters remaining in dispute .
**********
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Decision last updated:
22 March 2023
Official source: https://www.caselaw.nsw.gov.au/decision/187018dbed39185082c8d312