123 259 932 Pty Ltd v Cessnock City Council [2023] NSWCA 21
Catchwords: CONTRACTS – Remedies – Damages – Reliance Damages – Presumption referred to in McRae v Commonwealth Disposals Commission and The Commonwealth v Amann Aviation – Whether primary judge erred in finding that the presumption did not arise – Presumption arises where expenditure is incurred by a plaintiff in reliance on a contractual promise made by the defendant and “wasted” because of non-performance by the defendant – No precondition that the plaintiff first establish it is “impossible” to prove expectation damages – Plaintiff proved conditions for presumption – Ground of Appeal upheld. CONTRACTS – Remedies – Damages – Reliance Damages – Presumption referred to in McRae v Commonwealth Disposals Commission and The Commonwealth v Amann Aviation – Whether primary judge erred in finding presumption rebutted – Presumption rebutted where defendant demonstrates plaintiff would not have recouped expenditure – Contractual and non-contractual potential benefits of plaintiff to be considered in expenditure inquiry – Plaintiff rejected inferior offer of defendant – Innocent party to a contract entitled to insist on contractual rights rather than accept inferior proposal – Rejection of offer could not form reasonable basis for inference defendant would not have recouped expenditure – Presumption not rebutted – Ground of appeal upheld. CONTRACTS – Remedies – Damages – Remoteness of damage – Whether primary judge erred in finding recovery was precluded by the rule in Hadley v Baxendale – Loss incurred by plaintiff reasonably can be supposed to have been in the contemplation of both parties when contract was made – Damages fall within the second limb of Hadley v Baxendale – Ground of appeal upheld.
Court of Appeal
Supreme Court
New South Wales
Summary available
Medium Neutral Citation:
123 259 932 Pty Ltd v Cessnock City Council [2023] NSWCA 21
Hearing dates:
25 August 2022
Date of orders:
20 February 2023
Decision date:
20 February 2023
Before:
Macfarlan JA at [1];
Brereton JA at [2];
Mitchelmore JA at [171].
Decision:
Parties directed to bring in short minutes, including calculation of interest , providing
for:
(a) The appeal to be
allowed;
(b)
The judgment
below to be set
aside;
(c)
In
lieu thereof ,
judgment for
appellant/plaintiff
for $3,697,234.41 and
interest;
(d) The
Respondent to pay
the appellant’s
costs of the proceedings at first instance and on appeal.
Catchwords:
CONTRACTS – Remedies – Damages – Reliance Damages – Presumption referred to in
McRae v Commonwealth Disposals Commission
and The
Commonwealth v Amann Aviation
– Whether primary judge erred in finding that the presumption did not arise – Presumption arises where expenditure is incurred by a plaintiff in reliance on a contractual promise made by the defendant and “wasted” because of non-performance by the defendant – No precondition that the plaintiff first establish it is “impossible” to prove expectation damages – Plaintiff proved conditions for presumption – Ground of Appeal upheld.
CONTRACTS – Remedies – Damages – Reliance Damages – Presumption referred to in
McRae v Commonwealth Disposals Commission
and
The Commonwealth v Amann Aviation
– Whether primary judge erred in finding presumption rebutted – Presumption rebutted where defendant demonstrates plaintiff would not have recouped expenditure – Contractual and non-contractual potential benefits of plaintiff to be considered in expenditure inquiry – Plaintiff rejected inferior offer of defendant – Innocent party to a contract entitled to insist on contractual rights rather than accept inferior proposal – Rejection of offer could not form reasonable basis for inference defendant would not have recouped expenditure – Presumption not rebutted – Ground of appeal upheld.
CONTRACTS – Remedies – Damages – Remoteness of damage – Whether primary judge erred in finding recovery was precluded by the rule in
Hadley v Baxendale
– Loss incurred by plaintiff reasonably can be supposed to have been in the contemplation of both parties when contract was made – Damages fall within the second limb of
Hadley v Baxendale
– Ground of appeal upheld.
Legislation Cited:
Corporations Act 2001
(Cth),
s 601 AD(2)
Environmental Planning and Assessment Act 1979
(NSW), s 72
Cases Cited:
Anglia Television Ltd v Reed
[1972] 1 QB 60
Berry v CCL Secure Pty Ltd
(2020) 271 CLR 151; [2020] HCA 27
Commonwealth v Amann Aviation Pty Ltd
(1991) 174 CLR 64; [1991] HCA 54
Cory & Son v Wingate Investments
(1981) 17 BLR 104
Foaminol Laboratories Ltd. v. British Ortid Plastics Ltd
[1941] 2 All ER 393
Hadley v Baxendale
(1854) 9 Exch 341; 156 ER 145
Johnson v Perez
(1988) 166 CLR 351; [1988] HCA 64
McRae v Commonwealth Disposals Commission
(1951) 84 CLR 377; [1951] HCA 79
McIntosh v Williams
[1979] 2 NSWLR 543
Meetfresh Franchising Pty Ltd v Ivanman Pty Ltd
[2020] NSWCA 234
Nikolaou v Papasavas, Phillips & Co
(1989) 166 CLR 394; [1989] HCA 11
Renown Corporation Pty Ltd v SEMF Pty Ltd
[2022] NSWCA 233
Robinson v Harman
(1848) 1 Exch 850; 154 ER 363
Scott v Ennis-Oakes
[2020] NSWCA 239
Tabcorp Holdings Ltd v Bowen Investments Pty Ltd
(2009) 236 CLR 272; [2009] HCA 8
Wenham v Ella
(1972) 127 CLR 454 ; [1972] HCA 43
Williamson v John I. Thornycroft
And
Company, Limited
[1940] 2 KB 658
Willis v Commonwealth
(1946) 73 CLR 105; [1946] HCA 22
Texts Cited:
Fuller, LL and Perdue WR, “The Reliance Interest in Contract Damages”, (1936) 46
Yale Law Journal
52
Category:
Principal judgment
Parties:
123 259 932 Pty Limited,
ACN 123259932 (Appellant)
Cessnock City Council (Respondent)
Representation:
Counsel:
D L Williams SC w B D Kaplan (Appellant)
D L Cook SC w G Ng (Respondent)
Solicitors:
Dentons Australia Pty Ltd (Appellant)
Holding Redlich (Respondent)
File Number(s):
2021/320994
Publication restriction:
N/A
Decision under appeal
Court or tribunal:
Supreme Court
Jurisdiction:
Common Law Division
Citation:
[2021] NSWSC 1329
Date of Decision:
18 October 2021
Before:
Adamson J
File Number(s):
2017/295180
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
HEADNOTE
[This headnote is not to be read as part of the judgment]
T he respondent (“the Council”)
agreed
to grant to the appellant (“Cutty Sark”) a lease of a part of Cessnock Airport (“the airport”), on
which
Cutty Sark was constructing an aircraft hangar from
where
it intended to operate a business conducting joy flights and advanced flight aerobatic training . The relevant land
was to become one lot of a proposed 25 lot subdivision,
and the proposed lease would be for
a term of thirty years from the registration of the plan of subdivision. The Council – which was not only the applicant but also the relevant consent authority for approval of the subdivision – also promised to take all reasonable action to apply for and register the
subdivision p lan by 30 September 2011 (“Sunset Date”), and in the meantime granted Cutty Sark a licence
of
proposed Lot 104. The Council repudiated that obligation, notifying Cutty Sark that it would not
commit
the funding
required
to
proceed , with the consequence that the Plan was not
registered by the Sunset Date, or at all,
and the
p roposed
l ease was not granted. In the meantime, Cutty Sark had proceeded to construct the hangar, at a cost
in excess
of $3 million. Cutty Sark was later deregistered and as a result the Council terminated the
Agreement and
purchased the hangar for $ 1, as contemplated by the Agreement.
Cutty Sark was reinstated and commenced proceedings claiming damages for breach of contract by the Council. The primary judge held that the Council had breached the Agreement by failing to take all reasonable action to apply for and obtain registration of the Plan, but that Cutty Sark was entitled only to nominal damages in the sum of $1. Cutty Sark appeals, contending that it should have been awarded substantial reliance damages, representing the amount that it had expended in
c onstructing the hangar.
Held, per Brereton JA;
Macfarlan and Mitchelmore JJA agreeing
([1], [171
]), allowing the appeal:
Whether the presumption in
Amann Aviation
arose
As to the formulation of the presumption:
1. A plaintiff who is
unable
or does not undertake to
demonstrate whether or to what extent the performance of a contract would have resulted in a profit may
claim
its wasted expenditure.
In such a case, expenditure incurred by a plaintiff in reliance on a contractual promise made by the defendant and
“ wasted ”
because of non-performance by the defendant is recoverable ,
except to the extent that the defendant shows that the plaintiff would not have recouped its expenditure had the contract been performed:
[73], [161].
2. Relevant expenditure is not confined to expenditure under or required by the
contract, but
extends (subject to the rule in
Hadley v Baxendale
(1854) 9 Exch 341)
to any detrimental change of position by the promisee in reliance upon the defendant ’ s promise. The value of the reliance interest is the quantum of the net
detriment.
Such expenditure is regarded as
“ wasted ”
if the promise in reliance on which it was made is not performed, except to the extent that it is shown that the plaintiff has received some offsetting benefit, whether under or dehors the contract.
It suffices to enliven the presumption that
expenditure has been incurred in reliance on a defendant’s contractual promise which the defendant has failed to perform:
[73], [161].
3. It is not a precondition to the presumption
arising that the plaintiff first establish that it is
“ impossible ”
to prove expectation damages, let alone that it be impossible to prove that it would not have recouped its expenditure :
[96]-[97]; [162].
Commonwealth v Amann Aviation
(1991) 174 CLR 64;
McRae v Commonwealth Disposals Commission
(1951) 84 CLR 377, applied.
Meetfresh Franchising Pty Ltd v Ivanman Pty Ltd
[2020] NSWCA 234, followed.
Berry v CCL Secure Pty Ltd
(2020) 271 CLR 151, considered.
As to whether the contract excluded the Council’s liability for reliance damages
4. The provision in the Agreement excluding or releasing the Council from liability do es
not preclude Cutty Sark ’ s claim for reliance damages.
The provision has no direct application: [100]. Generic reference to
“ commercial risk ”
obscures that the Agreement delineates between risks that Cutty Sark accepted and risks which it did not accept. Cutty Sark did
not
accept the risk that eventuated
–
that the Council repudiated its obligations to take all reasonable steps to procure registration of the Plan: [101]-[103]; [164].
As to the impact of the Council having no obligation to develop the airport
5. The claim for reliance damages does not proceed on the basis that the Council was contractually obliged to implement the commercial development of the airport, but on expenditure incurred in reliance on the Council performing the obligation of taking all reasonable action to procure registration of the Plan. The fact that the Council did not promise to develop the airport does not mean that Cutty Sark did not incur expenditure on construction of the hangar in reliance on Council ’ s promise to take all reasonable steps to procure registration of the plan: [102].
Conclusion: the presumption arose
6. In the present case, the presumption arose;
Cutty Sark prov e d
that it had incurred expenditure in reliance on the Council ’ s performance of its obligation to take all reasonable steps to procure registration of the Plan: [121]-[124]; [166].
Whether the presumption was rebutted
As to Council’s obligation not extending to developing the airport
7. The
fact that there was no promise to develop the airport does not mean that the potentiality of its development is irrelevant when considering whether the Council
had discharged its onus of rebutting the presumption, by showing that Cutty Sark would not recoup its expenditure. In considering whether a plaintiff has been shown to be unable to recoup its expenditure, a court is not confined to the contractual entitlements of the plaintiff; it is permissible to have regard also to potential benefits that might have accrued to the plaintiff, although they are not contractual entitlements, if they may reasonably be supposed to have been in the contemplation of the parties: [126]-[130].
Commonwealth v Amann Aviation
(1991) 174 CLR 64
As to Cutty Sark’s businesses having been unsuccessful
8. Losses in the early stages of the businesses and their discontinuation prior to the Sunset Date does not significantly inform the prospects of resuming operations
and recouping expenditure over the ensuing period of 30 years in the different circumstances that would or might have prevailed had the Plan been registered and the Lease granted, particularly given that with a subdivision there was a prospect of surrounding commercial development and a more conducive commercial environment: [131].
As to Cutty Sark’s rejection of an alternative offer
9. Cutty
Sark as the innocent party was entitled to insist on its contractual rights, or damages for breach, rather than accepting some inferior proposal advanced by the Council. The rejection provides no reasonable basis for an inference that Cutty Sark would not have resumed operations and ultimately recouped its expenditure, had it been granted
the proposed lease: [132].
Conclusion: the presumption is not rebutted
10. It is impossible to be satisfied that by the end of the term of the proposed lease, Cutty Sark would not have recouped its expenditure.
In circumstances where what would have transpired had
the
Council performed its obligations was speculative ,
but there was a high degree of likelihood (given that Council was also the consent authority) that the Plan would be registered, and at least a prospect of further development of the airport producing a more conducive commercial environment for Cutty Sark ’ s business operations, if not immediately then sometime over the ensuing thirty years of the lease to which Cutty Sark was entitled, the Council could not and did not show that Cutty Sark would not over a 30-year lease have recouped its expenditure : [135]-[140].
Whether recovery
was precluded by the remoteness of damages
11. I t was, or ought to have been, plain to both parties, had they turned their minds to the question when the contract was made, that non-performance by the Council of its relevant obligation would result in Cutty Sark wasting the expenditure it had incurred and was going to incur in constructing the hangar. The loss incurred is therefore reasonably to be supposed to have been in the contemplation of both parties when the contract was made .
The damages fall
within the second limb of
Hadley v Baxendale
(1854) 9 Exch 341 .
The matters relied on by the primary judge
–
that the parties contemplated that no lease might be granted without breach, that the hangar would eventually be transferred to the Council for nominal consideration, and that whether and when the Plan would be registered was uncertain
–
are not inconsistent
with that conclusion :
[149].
Judgment
MACFARLAN JA
:
I agree with Brereton JA .
BRERETON JA:
The respondent Cessnock City Council
( “ the Council ” )
is the registered proprietor of land near
Pokolbin on which is located the Cessnock
Airport ,
also known as Hunter Valley
A irport
( “ the
a irport ” ) . By an agreement for lease
bearing the
date 16
January 2008
but made
on or about
26
July 2007
( “ the
A greement ” ),
the Council
promised
to
grant to the appellant 123
259
932 Pty Limited
–
formerly, Cutty Sark Holdings Pty Limited ( “ Cutty Sark ” )
–
a
lease
( “ Proposed Lease ” )
of
a part of the
a irport ,
on which Cutty Sark
intended to
construct an aircraft hangar from which it
would
operate a business conducting joy flights and advanced flight aerobatic training,
which was to become
Lot 104
in a proposed 25 lot subdivision,
for a term of thirty years
from the registration
of the plan of subdivision ( “ the Plan ” ).
The Council
–
which was not only the applicant but also the relevant consent authority for approval of the
subdivision
–
promised
to
take all reasonable action to apply for and register
the
P lan by 30
September 2011
( “ Sunset Date ” ) , and in the meantime granted Cutty Sark a licence
to occupy
proposed Lot 104 .
Cutty Sark proceeded to construct the hangar , at a cost of
in
excess of
$ 3 million.
The
Council ’ s obligation to take all reasonable action to apply for and obtain registration of the
P lan required it to take all reasonable action to fulfil the conditions of the development consent,
including
that the proposed lots be connected to Hunter Water Corporation ’ s
r eticulated
s ewerage
s ystem . The
Council
did not comply with that condition, asserting that it
did not have
and could not reasonably obtain the $1.3 million
required
to do so .
C onsequen tly ,
the P lan was not registered by the
S unset
D ate , or at all , and the Proposed Lease was not granted .
Prior to the Sunset Date ,
Cutty Sark
had ceased to operate businesses from the h a ngar , as they were not successful .
A fter the Sunset Date, by mid-2012 ,
Cutty Sark
vacated
proposed Lot 104 and the hangar on it.
Cutty Sark was deregistered by the Australian Securities and Investments Commission
(ASIC)
on
7
September
2015 . The Council terminated the Agreement
and ,
o n 11
May 2016, paid ASIC $1 for the acquisition of the hangar, in
reliance on
a provision
of the
P roposed L ease which entitled the Council to acquire the hangar for $1 upon termination for any reason . O n
6
December 2016, Council
granted
a lease of the hangar
to
a new tenant
for a term
of five years.
Cutty Sark was reinstated by order
of the
Supreme Court of South Australia on 5
June 2017. It commenced these proceedings
against the Council
claiming damages for breach of contract on 29
September 2017.
The primary judge held that the Council had breached the Agreement by failing to take all reasonable action to apply for and obtain registration of the
P lan
by the Sunset Date
in accordance with
its contractual obligation to do so ,
[1]
but that Cutty Sark was entitled only to nominal damages in the sum of $1. Cutty Sark appeals, contending that it should have been awarded substantial reliance damages, representing the amount that it had
expended
in constructing the hangar.
Background
Council embraces a c oncept for development
of
the airport
In 1998, the Council called for expressions of interest for the development and management of the airport.
[2]
The
request
for expressions of interest
included a development plan which
contemplate d the lengthening of the runway to accommodate larger aircraft, and the subdivision of lots
within the airport .
[3]
O n about 17
November 1998 ,
Peter Roberts, of Aviation & Leisure Corporation Pty Limited ( “ ALC ” ) ,
lodged an expression
of interest.
His proposals included the erection of hangars with attached residences for aircraft owners
–
a
concept
known elsewhere as
“ hangar homes ” , which
“ was attractive to the Council as Mr Roberts
re presented it as a way of producing an income stream for the Council which would help pay for the airport ”
following
its
eventual development.
[4]
The Council awarded him a tender on 2
June 1999.
[5]
In July 2002, the Council resolved to
lease parts of the airport to ALC ,
with a view to its future development ,
[6]
and in March 2004 t he Council entered into a lease and a management agreement
with ALC ,
[7]
which
provided that if the plan of subdivision was registered by 30
June 2011, the Council would grant ALC a 25-year lease.
[8]
On 12 December 2003, the Council lodged a development application ( “ DA ” ) for
(a)
the consolidation of the land comprising the airport into proposed lot s 1 and
2 , and
(b)
the
subsequent subdivision
of lot 2
into 25 lots, one of which would be proposed
Lot 104 .
[9]
The exhibited plan
depicte d f i ve
subdivided lots (10 3
to
107) to the east of the runway ,
accessible from Main Road ;
the runway and environs (108) ;
and
19
lots to its
west ,
accessible from De Beyers Road
( 109 to 127) .
On 7 July 2004, the Council adopted a development control plan ( “ DCP ” ) under s 72 of the
Environmental Planning and Assessment Act 1979
(NSW) for the airport, the purpose s
of which included
“ to permit development that will capitalise on the advantages of the site and its strategic location ” ;
“ to encourage moderate growth in the standard of infrastructure available and in the use of the
airport ” ; and to
“ encourage appropriate ancillary development, related to the
airport ” .
[10]
The DCP
described
the Council ’ s vision for the airport as
an
“ aerodrome facility managed in a manner which attracts new and
environmentally responsible
economic
development
opportunities
to the Cessnock region ” . On 30
September 2004, the Council issued an internal
memorandum which described the purpose of the proposed subdivision of the airport as
“ to enable the long-term development of the aerodrome in accordance with Council ’ s development vision ” .
By November 2004, an independent consultant planner, Leanne Saccaro, had prepared a report recommending that the proposed subdivision be approved, subject to conditions. She reported that the proposed subdivision
“ represents an opportunity for Council to further develop the aerodrome in line with the vision adopted by the Council ” ,
and
recommended that the DA be approved
“ subject to conditions
…
and that a determination notice be issued accordingly ” .
Council granted development consent on 17 November 2004, subject to conditions which included that the proposed lots be
“ connected to Hunter Water Corporation ’ s reticulated sewerage system ”
(Condition 23).
[11]
The
consent described the development as
“ Twenty five
(25) Lot Subdivision
Cessnock Aerodrome Site (Hangar Sites) ” .
On 7 November 2005, DP1064825 was registered, consolidating the airport land into lot 2.
[12]
However, as will appear, the contemplated
further
subdivision of lot 2 into 25 lots , including Lot 104,
was never registered.
Cutty Sark
and the Agreement for Lease
Meanwhile, o n 21 April 2004,
Mr James Gordon Johnston, who in due course would become the principal of Cutty Sark, and his business partner
Mr
Phil Unicomb, met with Council ’ s then Corporate and Community Services Manager
Mr
Peter Gogarty ,
to discuss a suitable site for a hangar to house aircraft that Mr Johnston and related entities had acquired.
[13]
Mr Johnston ’ s vision was that the hangar could incorporate an aviation museum ,
and an entertainment venue.
[14]
I n April
2005, a solicitor acting in Mr Johnston ’ s interests
(Mr Dockrill )
submitted a DA for the proposed hangar on proposed
Lot 104 , and
the Council granted
development consent
for it
on 28
July 2006 .
[15]
Between August 2005 and April
2007, Mr Dockrill and Council ’ s solicitors negotiated the terms of the contractual arrangements between the Council and Cutty Sark, which was incorporated on 27
December 2006.
[16]
The se negotiations culminated in the execution
by the Council ,
on or about 26
July 2007, of the
Agreement ,
[17]
by
which the Council promised ,
s ubject to registration of the Plan, to grant Cutty Sark a 30-year lease of proposed Lot 104. Clause
3.1 of the
Agreement
provided:
“(a)
The Lessor agrees to grant, and the Lessee agrees to accept, the grant of the Lease from and including the Commencing Date.
(b)
In addition to the terms and conditions contained in this Deed the terms and conditions of the Lease will apply as if the Lease were in force. If any provisions of this Agreement for Lease with the provisions of the Lease, then the provisions of this Deed will prevail.”
The
“ Commencing Date ”
was defined to mean
“ the day after the registration date of the Plan and the Instrument ” .
“ Plan ”
was defined to mean
“ the proposed plan of subdivision of Land a copy of which is annexed to this Deed marked
‘ C ’
and if the proposed Plan is modified under clause
4.3 means that Plan as modified ” ,
and
“ Instrument ”
as
a proposed instrument creating
easements and /or restrictions under s
88B of the
Conveyancing Act 1919
(NSW).
The primary judge recorded that, although annexure
‘ C ’
was not itself in evidence, it was common ground that it referred to the development of the airport, including
of
the areas to the west and east of the runway.
[18]
“ Lease ”
was defined to mean
“ the Lease of the Land forming Annexure A, as completed under clause
3.3 ” , and
“ Land ”
was defined as
“ the land and any improvements on the land
described
in Item
1. ”
[19]
Item 1 specified the Land as being
“ Folio Identifier
2/1064825 part being proposed Lot 104 in DP ” , and the annexed proposed lease provided for a term of 30 years.
While the obligation to grant the Lease was subject to registration of the Plan,
the Council
promised to take all reasonable action to apply for and
obtain
regist ration of
the
P lan by
the
S unset
D ate . I f the
P lan was not approved and registered
by
the Sunset Date,
then each party
had a right of rescission, and in that event , then (subject to clause
13.3) neither
could
make any claim for damages against the other.
Clause
4 provided
as follows :
“
4.1 Registration of Plan
The Lessor’s obligations to
enter into
the Lease are subject to and conditional on the registration by the LPI-NSW of the Plan as a plan of subdivision and the Instrument.
4.2 Approval and Registration
(a)
The Lessor must take all reasonable action to apply for and obtain:
(1)
the approval of the Plan by the Relevant Authority to the Plan and the Instrument;
(2)
the registration by the LPI of the Plan and the Instrument;
on or before the Sunset Date.
(b)
The Lessee:
(1)
may not object to any applications made by the Lessor in its capacity as Lessor or as the Relevant Consent Authority in respect of the Plan; and
(2)
must provide any consents requested by the Lessor necessary to procure registration of the Plan.
4.3 Modifications
The Lessee acknowledges having inspected the Plan and the Instrument, the Lessee may not make any claim against the Lessor or rescind or terminate this Deed in respect of a modification to the Plan or the Instrument.
4.4 Rescission
If the Plan is not:
(a)
approved by the Lessor on terms reasonably acceptable to the Lessor; and
(b)
registered by the LPI-NSW, on or before the Sunset Date, then before the registration of the Plan and providing the Lessor has not given the Lessee notice of the date the Plan will be registered, the Lessor or the Lessee may rescind this Deed by giving notice to the other.
4.5 No compensation
Subject to clause 13.3 if the Agreement for Lease is terminated pursuant to clause 4.4 then neither the Lessor nor the Lessee may make any Claim for Damages against the other.”
C lause 13 relevantly provided:
“
13.1 Lessor’s right to terminate
The Lessor may terminate this Deed by giving the Lessee notice if the Lessee:
(a) repudiates its obligations under this Deed; or
…
(c) is a corporation that:
(1) undergoes a Winding Up;
…
13.3 Consequences of termination
…
(c) Termination of this Deed does not affect:
(1) a party’s rights in respect of a breach of this Deed by another party before then; or
(2) the Lessee’s obligations to make payments under this Deed for periods before then.”
“ Winding Up ”
was defined to include
“ compromise or scheme of arrangement with creditors, amalgamation, reconstruction, reorganisation, administration, dissolution, liquidation, bankruptcy, merger, consolidation, any analogous procedure (whether formal or informal) and death ” ; a s the primary judge held,
that
included deregistration.
[20]
Pending the
Commenc ing
Date, t he Council granted Cutty Sark a licence
“ to enter the Land during the Licence Period for the Permitted Use on the terms of this Licence ” ,
in consideration of payment of
a
“ Licence Fee ” .
[21]
The
“ Licence Period ”
was defined in cl
1.1 to mean, in effect, the period from the date on
which the
Council
first gave
Cutty Sark
or its employees access to the Land, to the Commencing Date.
“ Permitted Use ”
was defined to mean
“ the use of the Land as an aircraft hangar for joy flights and advance [sic] flight-aerobatic training. ”
The
terms of the
licence w ere
the same as
those
of the Proposed Lease , and the
rent under the Proposed Lease reflected the indexed licence fee.
Clause
5.2 provided:
“(a)
The Licence granted under clause 5.1 is on the same terms and conditions set out in the Lease as if the word ‘
lease
’ was replaced with the word ‘
licence
’ where it appears in the Lease and the Lease provisions (with the necessary changes being made) were set out in full in this Licence as agreed to between the Lessor and the Lessee.
(b)
The terms of this Licence will prevail in the event there is an inconsistency between the Licence provisions and the Lease provisions.”
[Emphasis in original.]
Clause 5.3 provided:
“The Lessor does not intend to create a lease or tenancy of the Land or any other estate or interest in the Land by giving a Licence under clause 5.1.”
Clause 12.3 of the Agreement relevantly provided:
“
12.3
Release
The Lessee releases the Lessor from, and agrees the Lessor is not liable for, all liability or loss arising from, and costs incurred in connection with:
…
(b)
anything the Lessor is permitted or required to do under this Lease;
(c)
a Service being unavailable, being interrupted or not working properly;
(d)
the Aerodrome or Aerodrome Infrastructure Facilities not being available for use by the Lessee;
(e)
loss of the Lessee’s profits; and
(f)
any liability for damage to the Land or the Lessee’s property or for any other loss (however that loss was caused or arose), including but not limited to:
(1)
financial or economic loss to the Lessee or to any other person;
(2)
loss of goodwill in relation to the business being carried on by the Lessee;
(3)
indirect or consequential loss;
(4)
loss resulting from:
…
(C)
any change in the flow of members of the public in or around the Land or Aerodrome for any reason”.
“ Aerodrome ”
was defined to mean
“ the Cessnock Aerodrome adjacent to the Land ” , and
“ Aerodrome Infrastructure Facilities ”
was defined to mean:
“… all existing and future improvements comprising the Aerodrome and includes without limitation, buildings, runways, movement areas, taxiways, terminals, aprons, roads, dams, visual aids provided by aerodromes such as markings, markers, signals, signs, visual aids provided for lighting and any communication facilities, plant,
machinery, fittings, civil works, signalling systems, equipment, nodes, conduits, ducting, and other plant, equipment, buildings or facilities owned or leased by the Lessor.”
The Agreement made extensive provision for and in respect of the “Lessee’s Works”, which were defined as
“the works to be carried out by the Lessee as set out in Annex
ure
D”
,
including provision for submission of plans for the consent of the Lessor,
and specific reference to the erection of a hangar.
Annexure D was not itself in evidence,
but there can be no doubt that
the parties had in contemplation the
expensive
and iconic
hangar
which was
ultimately
constructed .
As has been noted, the Council had already,
on 28 July 2006
, granted development consent for the hangar.
Moreover ,
communications between the parties expressly referred to
Cutty Sark’s
intention to spend millions of dollars on the construction of an “iconic” hangar designed by a
renowned
architect. According to Mr Johnston, in October 2004 he told
Mr Gogarty :
“I will need a decent tenure as I will
be
spending between 2 to 3 million on a Peter Stutchbury building”
.
[22]
On 8 September 2006, Mr Dockrill
wrote to
the solicitors then acting for the Council,
Sparke Helmore , pressing for a
lease
term of 35 years :
[23]
“As your client is aware our client is spending conside
rable capital costs in constructing the
h angar at
$1.8m
and additional costs of aircraft and other set up items of another
$
2.2m
meani ng a total outlay of
$4m
.”
On 18 October 2006, Mr Dockrill wrote to Sparke Helmore :
[24]
“I t is
noted
that the
P lans for the
Hangar
have been prepared by an award-winning
architect , the design
is
of a
very high
standard and the iconic hangar once completed will be very worthwhile
visual and working hangar situated on this very important part of Cessnock
Airport .
It can be appreciated that our client could have submitted a
D evelopment
Application
for a more modest building which would cost
approximately
one half of the cost to build the hangar as approved and which
would
make the proposed
business to be run from the
building
more
economically
viable
. However our client decided that the hangar as designed and consented to by Council is a much more appealing building for the future of the airport and a worthwhile addition to the tourist landscape
for
the airport and the
adjoining Pokolbin
area
.”
Clause 16.8 of the
P roposed
L ease
annexed to the Agreement
provided that on expiry or termination of the
L ease, the hangar would be transferred to the Council unencumbered for $1:
“(a) Subject to clause 17, notwithstanding any other provision in this Lease, the Lessee and the Lessor agree that any improvements erected on the Land by the Lessee including but not limited to any building or aircraft hangars will, on the expiry, determination or surrender of this Lease be transferred to the Lessor free of any Security Interests, at the cost of $1.00 at which time the Lessor will become the sole and absolute owner of the Lessee’s improvements.
(b) The Lessee covenants with the Lessor not to make any Claim by way of compensation or otherwise, in relation to any improvements made to or on the Land by the Lessee, which become the absolute property of the Lessor by virtue of this clause.”
Cutty Sark builds and operates from the hangar
Between May 2007 and November 2010, Cutty Sark constructed the hangar on proposed Lot 104.
[25]
Services were connected in March
2009.
[26]
Cutty Sark operated three businesses from the hangar: an adventure flight business between July and November
2009, an aircraft museum between September
2009 and February
2010, and a corporate venue hire business from
August
2009 to June
2011.
[27]
The primary judge found that each of these businesses
“ proved to be unprofitable prior to the sunset date ” .
[28]
Mr Johnston gave evidence that they were not sustainable in circumstances where it was difficult to attract business when the airport had not been subdivided and developed.
[29]
He elaborated in cross - examination,
“ if I ’ d been given my tenure I would probably say I think I can make it work. But Council would have had to develop the airport that was also promised ” .
[30]
In 2010 and 2011,
Mr Johnston attempted to sell the hangar and received an offer of $2,375,000, but the primary judge did not consider that or any other offer to be credible or genuine.
[31]
The Council repudiates
On 29 June 2011
–
one day before the
end
date of
the Agreement
between the Council and ALC
–
Mr Roberts of ALC attended a m eeting
with Alan Revell
( a consultant engaged by ALC )
and the Council, including its then General Manager Lea Rosser ,
at which
Ms Rosser said that the Council
“ won ’ t be proceeding with the subdivision of the land at the airport ” , as it had
“ no intention of spending about a million dollars fixing the sewerage ” .
[32]
On 13 September 2011, Ms Rosser wrote to
Cutty Sark ’ s
solicitor
Mr Dockrill, noting that the Council had
“ been unable to achieve the registration of the plan of subdivision within the timeframe anticipated in the agreement for lease ” , and offering Cutty Sark
“ an exclusive licence for a term of twenty-five years with virtually identical terms to the draft lease attached to
the
a greement
for lease or a number of successive leases for terms of five years or less ” .
[33]
This of course was not the thirty-year lease of
Lot 104
in a twenty-five lot subdivision for which Cutty Sark had bargained.
On 20
December 2011
Mr Dockrill ,
observing that Cutty Sark had spent
“ over $2.7 million ”
on the hangar venue,
[34]
rejected the Council ’ s offer .
[35]
At about the same time, the Council terminated its a rrange ments with ALC, and resumed management of the airport.
[36]
Neither the Council nor Cutty Sark
purported to
exercise a right of rescission pursuant to clause
4.4 when ,
on 30
September 2011 ,
the Sunset Date passed without the
P lan being registered ; given that
the failure was attributable to the Council ’ s own failure to take all reasonable steps, it may be doubted that the Council would have been entitled to
rescind under that provision .
The Council did not
thereafter
pursue
any
action to apply for and obtain registration of the
P lan .
On 18
January 2012,
it
convened a
“ leadership group ”
briefing in relation to Cutty Sark. Notes prepared by Bronwyn Rumbel, the Council ’ s Integrated Planning and Strategic Property Manager, recorded that
“ Council has not considered carrying out the subdivision of this lot
[104]
separately
–
because there does not appear, at this stage, to be any benefit to Council in subdividing the airport at all ” .
[37]
In a conversation with Ms Rumbel on 13
March 2012, Mr Johnston said that
he
“ would like security of tenure ” .
[38]
Cutty Sark
ceases occupation
Cutty Sark
ceased occupation of
proposed
Lot 104
and the hangar on it
in mid-2012.
On 6
September 2013, it disconnected the power to the hangar, as it could not afford to pay the electricity bills.
[39]
O n 15 August 2012, the Council resolved to endorse the nomination of the airport as a major infrastructure project under the Hunter Infrastructure and Investment Funds Grant Programme, and on 22
August 2012, the Council applied to the Hunter Infrastructure and Investment Fund for funding in the sum of $2
million to purchase and refurbish the hangar.
[40]
A report to the Council
meeting
of that date stated that the
Council
had
“ received around twelve requests for both hangar space and office space from businesses looking to establish or expand at Cessnock Airport and, at present,
Council
is unable to satisfy this demand ” .
[41]
In January
2014, the
Council
published its
“ Cessnock Airport Strategic Plan ” , describing its vision
of
a
“ well-planned and serviced aerodrome facility managed in a manner that attracts environmentally responsible economic development opportunities to the Cessnock region ” .
[42]
On 14
August 2014, the
Council
lodged an expression of interest with Restart NSW Resources for Regions, seeking $6.95 million to upgrade the airport
“ to realise the community ’ s vision of it being a well-plann ed
and serviced facility that attracts environmentally responsible economic development opportunities to the Cessnock region ” .
[43]
Deregistration and reinstatement
As has been noted, Cutty Sark was deregistered
by
ASIC
on 7
September 2015, for non-payment of fees .
[44]
Its property thereupon vested in ASIC.
[45]
On 9
September 2015, the Council ’ s solicitors wrote to ASIC, noting that Cutty Sark had been deregistered and asserting that the Council proposed to secure and insure the premises.
[46]
ASIC responded on 14
September 2015, noting that all non-trust property of Cutty Sark belonged to ASIC, which generally was the only party legally able to deal with its property, but that it had no objection to the Council
“ terminating the licence and taking possession of the premises ” .
[47]
On 18
September 2015, Council ’ s solicitors wrote to ASIC that the Council
“ regard s
the Agreement as now having come to an end ”
for several reasons .
[48]
ASIC responded on 22
September 2015, stating that it had no intention of taking any action in relation to the matter.
[49]
On 11
May 2016, Council ’ s solicitors paid ASIC $1 for the acquisition of the hangar, as contemplated by clause
16.8
of
the
proposed
Lease.
[50]
On 6
December 2016, Council
granted
a lease of the hangar
to
a new tenant, Onyx Aviation Pty Ltd,
[51]
for a
term
of five years ,
entitling Onyx to occupy proposed
Lot 104
“ for conducting an aviation related business ” .
[52]
Cutty Sark was reinstated by order
of t he Supreme Court of South Australia on 5
June 2017 ,
[53]
and
commenced these proceedings on 29
September 2017.
In 2020, the Council produced
a nother
“ Cessnock Airport
S trategic
P lan ” .
T he Mayor ’ s Foreword
included :
“ This plan articulates the main
priorities, and
sets
clear objectives
to achieve an improved position for the Cessnock Airport to ensure it remains a strong public asset, and reflects well on
Cessnock
Council overall vision to
be
a cohesive and welcoming community living in an attractive and sustainable rural environment with a diversity of business and employment opportunities supported by accessible infrastructure and services which effectively meet
community needs.”
The Executive Su mmary
stated :
“Cessnock Airport is a vibrant hub and an integral component to the Hunter community.
This Strategic Plan identifies ways in which the Airport can further develop as an
aerodrome business hub that works with and contributes to the economic growth of the
region.
The success of this Airport lies in the fact it already has a point of difference in the
market
place
due to its central location to the vineyards of the Hunter Valley and the current
varied user base, and this should be developed.
The key Principles upon which this Plan is based are;
����
Implement a safe, secure and environmentally suitable airport;
����
Construct a well-planned airport;
����
Develop sound asset management and business practices;
����
Ensure strong financial viability and sustainability factors; and,
����
Focus on branding and marketing.
There are
a number of
key objectives that can be immediately implemented, and which
are detailed along with specified actions that will result in the development of a dynamic,
financially viable asset for the community.
Future development and growth should be investigated as funding opportunities arise,
and a review of this plan is recommended every five years to determine whether market
forces have
changed
or business opportunities have arisen that could benefit this Airport
facility.”
The plan
included a
precinct master plan
providing
for additional
private
hangars ,
an historical museum area
and the extension
of the runway
in precinct 2, and an area for commercial business
opportunities in precinct 3.
It also included
a
business plan ,
which
under
the
heading
“ B usiness
O pportunities ”
stated :
"Concepts to be investigated include;
����
Investigating whether gliders could be handled within the current facilities;
����
Development of a Historical aviation museum area; and
����
Development of aligned businesses including maintenance companies, light plane
manufacturers, and even caravan park/ accommodation operators.
Bathurst Airport currently operates as a larger regional facility however, they also allow
gliders to launch from their airport via a grass strip located within the airport precinct.
There is ample opportunity for this to also occur at Cessnock Airport.
The inclusion of a historical or museum area into Precinct 2 would help attract new
businesses that deal in that section of the
market place. There is also the opportunity to
cross sell to tourism, through visitations to the museum, and increase utilisation of the
airport through joy flights.
The concept of developing land within Precinct 3 to include a caravan park opens the
opportunity for increased caravan stays, accommodation for training, and potential for
consideration of accommodation hangars. Infrastructure (sewer and water) will need to be
upgraded or a suitable alternative environmental option resolved. "
Th e Business Plan
also stated :
“This report considers that there is real opportunity within the current market to take the
airport forward through both
short and medium term
actions which are considered the
most appropriate and financially prudent approach to grow the Airport business.
The table below highlights the priority for each action, as
follows:”
The
table identified
“ High Priority ”
items to
be completed
by
May 2021 ,
“ Medium Priority ”
items to be completed by
June
2021 ,
and
“ Ongoing A nnual ”
items
–
which bespeaks
an
assessment that
all
this could be a chieved
within a period of
less than
two years.
The primary judgment
and the appeal
At
the trial , Cutty Sark
did not claim
“ loss of bargain ”
damages,
but, invoking
the
judgments of the High Court in
McRae v Commonwealth Disposals Commission
[54]
and in
Commonwealth v Amann Aviation Pty Ltd
,
[55]
and the judgment of this Court in
Meetfresh Franchising Pty Ltd v Ivanman Pty Ltd,
[56]
claimed “reliance damages”, on the basis
that it had incurred
wasted
expenditure in reliance upon the Council performing its obligation to take “all reasonable action” to a
pply for and obtain
registration of the Plan.
The primary judge, who accepted that the Council was in breach of its obligation to take all reasonable action to procure registration of the Plan, characterised Cutty Sark’s claim for damages as being propounded on “a single basis”, namely “that it was entitled to recoup the whole of its expenditure on constructing the hangar (costs of construction, overhead expenses and miscellaneous expenses) because the defendant’s breach had rendered it impossible for it to prove that it would have recouped that expenditure during the 30-year lease and therefore, in accordance with
Amann
, it was entitled to a presumption that it would have done so”.
[57]
Cutty Sark’s case
was that:
it had incurred expenditure (of $3,697,234.41) in reliance upon the Council’s promise that it would take all reasonable action to apply for and obtain registration of the
P lan;
that expenditure was wasted because
the Council
did not perform
that promise;
in accordance with the aforementioned authorities, it was
to be presumed
that, had the Council performed its contractual obligations,
Cutty Sark
would
at least
have recouped its expenditure on the
hangar;
the Council had not shown – and could not show – that Cutty Sark would not at least have recouped its expenditure had the promise been performed, so the presumption was not rebutted; and
Cutty Sark was therefore entitled to recover
the amount of its
wasted expenditure.
Her Honour rejected that argument ,
holding that the case was not one in which the presumption arose, and that if it did, it had been rebutted:
[58]
“For the reasons given above, I do not consider the present to be a case where the presumption arises that the plaintiff would have recouped its expenditure if the AFL had not been breached by the defendant. However, even if such a presumption had arisen, I consider that the defendant has discharged the onus of rebutting it by showing that the cost of the hangar would not have been recouped. Indeed, the businesses conducted by the plaintiff were, so far as the evidence revealed, insufficient to meet the (relatively modest) licence fees for the period from which they became payable on 19 October 2007 (6 months from the Handover Date) until the date on which the defendant validly terminated the AFL (18 September 2015).”
As an additional basis for refusing
to award substantive
da mages, her Honour held that
the damages claimed by
Cutty Sark
would not fall within either the first or the second limb of
Hadley v Baxendale
.
[59]
Having reached that conclusion, her Honour did not resolve a dispute as to the quantum of Cutty Sark ’ s expenditure. Cutty Sark had adduced evidence to support a contention that it had spent $3,697,234.41, which although not
challenged in cross-examination of Cutty Sark ’ s principal Mr Johnston, was disputed in the Council ’ s closing written submissions at first instance .
Cutty Sark ’ s grounds of appeal were, in substance, that the primary judge erred :
in failing to find that the principles in
McRae
and
Amann Aviation
extended beyond damages claims where it was impossible to prove damages, and encompassed a case where damages for lost profits were
difficult to prove or where a plaintiff elected to prove only
“ reliance ”
damages ;
in finding that the presumption that
Cutty Sark
would at least have recovered its expenditure in relation to the construction of a
hangar had the
Council
complied with clause
4.2 of the Agreement did not arise ;
in finding that clauses
12.3(d)
and
12.3(f)(4)(C) of the Agreement were relevant to the assessment of
“ reliance ”
damages in respect of the hangar or that they had the effect that the
presumption in
Amann Aviation
was not engaged ;
in finding that the costs of constructing the
hangar were not recoverable pursuant to either of the two limbs in
Hadley v
Baxendale
;
in finding that, even if the presumption in
Amann
Aviation
had arisen, the
Council
discharged its onus of rebutting it by showing
that the cost of the hangar would not have been recouped by
Cutty Sark ; and
in declining to make a finding as to the amount incurred by
Cutty Sark
in constructing the hangar ;
t he primary judge should have found that
Cutty Sark
incurred $3,697,234.41 in
constructing the hangar.
The
issues in the appeal may conveniently be stated and arranged as follows :
Did
the presumption referred to in
McRae
and
Amann Aviation
arise
(Grounds 1, 2 and 3) ;
If so, was it rebutted
(Ground 5) ;
W as recovery precluded in any event by the rule in
Hadley v Baxendale
(Ground 4) ;
and
What was the quantum of Cutty Sark ’ s expenditure
(Ground 6 ) .
Did
the presumption arise?
(Grounds 1, 2 and 3)
The
McRae/ Amann Aviation
presumption
Damages for breach of contract are awarded to place the injured party in the position in which it would have been had the contract been performed, so far as money can do so.
[60]
Typically, this involves compensating the plaintiff for the
contractual benefits which it would have received had the contractual promise been performed ; these are referred to as
“ loss of bargain ”
or
“ expectation ”
damages.
However, a
plaintiff
who
is unable
to demonstrate whether or to what extent the performance of a contract would have resulted in a profit
may
seek , instead of
lost profits under the contract ,
to recoup
its
wasted expenditure .
[61]
In such a case,
“ the law
assumes
that a plaintiff would at least have recovered his or her expenditure had the contract been fully performed ” , but
“ i t will still be open to a defendant, however, to argue that, notwithstanding the fact that it is impossible to assess what profits, if any, the plaintiff would have made had the contract been fully performed, the expenditure claimed by a plaintiff would nevertheless not have been recovered even if ”
the defendant had performed its ob l igation s.
[62]
The presumption
–
and that the defendant
bears the onus of
rebut ting
it
–
was explained in
Amann Aviation
by Mason
CJ and Dawson
J
as follows (emphasis added):
[63]
“…
McRae
illustrates the proposition that a plaintiff has a prima facie case for recovery of wasted expenditure
once it is established that the expense was incurred in reliance on the promise of the party in breach, there being a failure of performance by that party
. By reason of its facts, the reasoning in
McRae
does not depend upon the presumption that an innocent party would not have
entered into
the contract unless it would at least have recovered its reliance expenditure under the contract had it been performed. But the reasoning is not inconsistent with the application, in appropriate cases, of that presumption which, in our view, has much to commend it.
Indeed, it is just and fair that the repudiating party should bear the onus of showing that the party not in breach would have made a loss on the contract
.”
Deane
J
said:
[64]
“In a case where a plaintiff has incurred expenditure either in procuring the contract or in its performance but it is impossible or difficult to establish the value of any benefits which the plaintiff would have derived from performance by the defendant, considerations of justice dictate that the plaintiff may rely on a presumption that the value of those benefits would have been at least equal to the total detriment which has been or would have been sustained by the plaintiff in doing whatever was reasonably necessary to procure and perform the contract (see, eg,
McRae
, at 414;
Holt v United Security Life Ins & Trust Co
(1909) 72 Atlantic Reporter 301 at 305–6;
L Albert & Son v Armstrong Rubber Co
(1949) 178 F 2 at 188– 9). In my view, the rational basis of that presumption is that that total detriment represents what would reasonably have been in the contemplation of the parties themselves as the cost to the plaintiff of full performance by the defendant and constitutes some evidence, in proceedings between them, of the value of the total benefits which would have been derived by the plaintiff from such performance. It follows from it that, at least in a case where proof of value is impossible or difficult, it is presumed in the plaintiff
’
s favour that the future net benefits (ie excess of future benefit over future detriment) which would have been derived from performance of the contract would have been of a value sufficient to recoup the past net expenditure reasonably incurred in procuring or performing it. Where that presumption is operative, it enables the recovery by a plaintiff of what are commonly referred to as “reliance damages”
, that is to say, damages
equivalent to the wasted expenditure which has been reasonably incurred in reliance upon the assumption that the contractual promises of the defendant would be honoured. The presumption will be rebutted if it be self-evident or established that the plaintiff would have derived no financial or other benefit from performance of the contract or that any financial or other benefit which would have been derived from future performance would not have been sufficient in value to counterbalance the past expenditure. The presumption will not, however, be displaced merely by the circumstance that the benefits which the plaintiff would have obtained from performance by the defendant included the chance of some more remote benefit and it is a matter of speculation whether that ultimate benefit would have in fact been obtained or by the circumstance that the perceived “benefit” which the plaintiff sought and for which she incurred the past expenditure is something which is of value only to the plaintiff or which, for some other reason, is not capable of being objectively valued in monetary terms (see, eg,
McRae
, at 414;
Fink v Fink,
at 134–5, 143 ). If it be established that the plaintiff would not, in any event, have derived the “benefit” which she sought from performance by the defendant or that any “benefit” which would have been derived is capable of being valued in monetary terms and would, when so valued, have been inadequate to recoup the expenditure, the plaintiff
’ s recovery will be limited to the extent (if at all) to which it has not been established that that expenditure would not have been recouped (see, eg,
Bowlay Logging Ltd v Domtar Ltd
(1978) 87 DLR (3d) 325 at 332–5 affd 135 DLR (3d) 179) . Even in a case where it is established that the plaintiff would have incurred a loss if the contract had been fully performed, reliance damages can be recovered in respect of wasted expenditure to the extent (if at all) that the past net expenditure exceeds that ultimate loss since, to that extent, the expenditure would have been recouped if there had been no breach (see, eg,
Sunshine Vacation Villas Ltd v The Bay
(1984) 13 DLR (4th) 93 at 102–3 ).”
The
principle that emerges from the
judgments of Mason
CJ and Dawson
J
and of Deane
J
is
that
a plaintiff who does not prove expectation damages may recover
expenditure incurred in reliance on a contractual promise
made
by the defendant and
“ wasted ”
because of non-performance by the defendant ( “ the presumption ” ), except to the extent that the defendant shows that the plaintiff would not have recouped its expenditure had the contract been performed ( “ the rebuttal ” ) .
Toohey
J and Gaudron
J recognised a similar presumption, but one which cast only an evidentiary as distinct from a legal onus on the defendant, holding that where it is not possible to predict a plaintiff ’ s position if the contract had been fully performed, in the absence of evidence to the contrary the law assumes that the plaintiff would at least have recovered its expenditure, and it was entitled to recover such expenditure as was reasonably incurred in reliance on the defendant ’ s promise .
[65]
The judgment of Brennan
J
proceeds on a somewhat different basis, making the reversal of the onus conditional upon it being established that the defendant ’ s breach denied, prevented or precluded the existence of circumstances which would have determined the value of the plaintiff ’ s contractual benefits.
His Honour
said
(emphasis added):
[66]
“
The sufficient and necessary justification for shifting the onus to the party in breach in the assessment of damages for wasted expenditure incurred in reliance on the defendant’s promise before rescission for breach is that the breach of the contract itself makes it impossible to undertake an assessment on the ordinary basis
…
A plaintiff’ s inability to quantify his lost benefits is no justification by itself for casting on the defendant an onus to prove that the plaintiff would not have recouped reliance damages had the contract been performed.
What justifies
the reversal of the onus is the defendant’s repudiation or breach which denies, prevents or precludes the existence of circumstances which would have determined the value of the plaintiff’s contractual benefits
. Thus, in
McRae’s
case, where the breach assigned was that there was no oil tanker on Jourmaund Reef where the contract of sale warranted a tanker to be, the salvager purchasers who had wasted expenditure in reliance on the defendant
’
s promise recovered reliance damages. …
The point of distinction between the method of assessment of expectation damages and the method of assessment of reliance damages is the reversal in the case of reliance damages of the onus of proof of the net value of the plaintiff ’ s contractual benefits.
There can be no duplication of reliance damages and expectation damages. The compensable losses in reliance damages do not include possible lost profits but both cover expenditure reasonably incurred in preparing to perform and in performing the contract within the limits prescribed by
Robinson v Harman
. The measure of damages prescribed by
Robinson v Harman
governs each method of assessment.
Where justification for reversing the onus exists, reliance damages may be recovered; absent that justification, the plaintiff must recover expectation damages, if any, by proof of the value of benefits and the cost of performance; that is, by proof that $B − $y is greater than $x. These are alternative methods of assessing damages, but the plaintiff does not have an election as to the method. The plaintiff who seeks recovery of reliance damages must show that justification for reversing the onus of proof exists. Otherwise, he must endeavour to prove his damages on the ordinary basis.”
N o such precondition is to be found in the judgment of Mason
CJ and Dawson
J, nor in that of Deane
J.
Although the
obiter
remarks of
Bell, Keane and Nettle
JJ
in
Berry v CCL Secure Pty Ltd
[67]
apparently
embrac e the approach
of Brennan J,
that was
for the purpose
of illustrating the more general proposition that
a
wrongdoer’s conduct
may
sometimes shift
the burden,
rather than
of rejecting the approach of Mason CJ and Dawson J:
[68]
“ While a claimant bears the legal burden of establishing the amount of its loss or damage, the nature and circumstances of the wrongdoer’s conduct may support an inference or presumption that shifts the evidentiary burden. That accords with the principle encapsulated in
Armory v Delamirie
that, where a wrongdoer has destroyed or failed to produce evidence which the innocent party requires to show how much he or she has lost, it is just that the wrongdoer should suffer the resulting uncertainty. Hence, in that case, since the defendant by his wrongful conversion of the plaintiff’s stones, and failure to produce them at trial, had made it impossible for the plaintiff to prove the quality of them, the stones were presumed to be of the highest quality and value. One relevant modern application of that principle is reflected in this Court’s decision in
Amann Aviation
, in which it was held that where, upon acceptance of the Commonwealth’s repudiation of a contract, Amann claimed damages for loss of the contract, Amann was entitled to recover “reliance damages” assessed on the basis of a rebuttable presumption that the net benefits to which Amann would have been entitled under the contract (if the contract had not been rescinded) would have been sufficient to cover the expenditure which Amann incurred pursuant to the contract. As Brennan
J
explained, because the Commonwealth had repudiated the contract and thereby deprived Amann of the ability to establish that the contract would have returned sufficient to recoup Amann’s contractual expenses, it was to be presumed that Amann would not have incurred its expenditure in reliance on the contract without a reasonable expectation that its performance of the contract would have returned it sufficient to recoup its expenses, and thus it was just that the Commonwealth should bear the ultimate onus of proving at least a prospect that Amann’s returns under the contract would not have been sufficient to recoup that expenditure. By contrast, as Brennan
J
observed, if a claimant seeks “expectation damages” for the loss of a chance that, had an agreement run to term, it may have been renewed or extended, the onus is on the claimant to establish those facts, although, even then, since the existence and degree of such an hypothetical possibility is, by reason of the wrongful termination of the contract, incapable of proof on the balance of probabilities, it is considered just that the wrongdoer should suffer the resulting uncertainty to the extent that proof to the level of a real (more than negligible) possibility is regarded as enough. The worth of the chance is then valued by a process of informed estimation.”
However, the judgment of this Court in
Meetfresh
adopt s
the approach of Mason
CJ and Dawson
J.
Macfarlan
JA (with whom Bell
P , as his Honour
the Chief Justice
then was,
and Meagher
JA ,
agreed) said, in respect of a claim for damages for wasted expenditure or reliance damages:
[69]
“The decision in
Amann Aviation
established that, in respect of such a claim, ‘the law
assumes
that a plaintiff would at least have recovered his or her expenditure had the contract been fully performed’, with the consequence that the onus of proof rests on the party breaching the contract to establish ‘that the reliance expenditure would have been wasted even if the contract had been performed’ (at 86–90 per Mason CJ and Dawson J).”
Thus, t he dominant rationale for the presumption is that it may be presumed that a party would not enter into a contract unless it would at least have recovered its reliance expenditure had
the contract
been performed.
[70]
This rationale underlies
the explanation, provided by Mason
CJ and Dawson
J
in
Amann Aviation,
that
reliance damages are not a
discrete and
alternative
measure
to expec tation damages
involvin g an
election, but
a manifestation of the central principle enunciated in
Robinson v Harman
:
[71]
“ A further example of the application of
Robinson v Harman
which will result in a plaintiff being entitled to claim damages for wasted expenditure is in a contract for services such as that between a solicitor and a client. Where a solicitor has breached his or her contractual duty of care, the measure of damages to which a client will be entitled will be such an amount as would put the client in the position he or she would have been in had the contract of retainer been performed without negligence. In cases where, had nonnegligent advice been given, the client would
not
have entered into a subsequent transaction, for example a purchase of real property, then, in conformity with
Robinson v Harman
, the client will be entitled to recover as damages expenditure wasted on account of the negligent advice, less anything subsequently recovered and given reasonable acts of mitigation [
Hayes v Dodd
[1990] 2 All ER 815 at 820, per Staughton LJ]. The amount of wasted expenditure will be the appropriate measure of damages in such a situation because, it
having
been established that the client would not have entered into the subsequent contract if proper advice had been given, it is not sensible to speak of loss of profits.
Hayes v Dodd
is a useful illustration of the statement that the expressions ‘expectation damages’, ‘damages for loss of profits’, ‘reliance damages’ and ‘damages for wasted expenditure’ are simply manifestations of the central principle enunciated in
Robinson v Harman
rather than discrete and truly alternative measures of damages which a party not in breach may elect to claim.
”
Reliance damages are
thus
compensation for loss of contractual benefits,
allowed
on the basis that expenditure less benefits received
may be regarded as equivalent to
the minimum net contractual benefits that the innocent party would have received
ha d
the contractual
promise been performed , subject to the defendant proving that the expenditure would not have been recouped.
In other words,
net wasted expenditure
serves as a proxy for the minimum contractual benefits that the innocent party would have derived, except to the extent that the defendant shows that it would not have been recouped .
The
respondent
submitted that the reliance damages contemplated by
Amann
Aviation
encompassed only:
expenditure incurred by the plaintiff in preparing for or performing
obligations under the contract
, with a corresponding expectation of receipt of a
benefit under the contract
which would allow the plaintiff to
at least recoup its expenditure.
Amann
Aviation
itself
was said to be an exemplification of
this,
in that
the benefit was receipt of payment by the Commonwealth for surveillance services,
in order to
obtain
which Amann spent money fitting out aircraft with surveillance equipment . The respondent called these
“
Amann
damages ” ; and
loss incurred in the expectation that a promise would be fulfilled. In
Amann
Aviation
,
the example was given of a client who, relying on his or her solicitors ’
performance of
their
contractual obligation to use reasonable care,
enters into
a transaction with a third party and thereby incurs a loss, so that the client has been put to additional expense which would not have been incurred had the contractual obligation been performed.
The respondent called these
“ true reliance damages ” .
There is clearly
a
distinction between the two categories , but it is not the distinction for which the respondent contends. T he first
category
(of which
the damages claimed in
Amann Aviation
and in
McRae
are
both
examples) ,
concerns expenditure incurred in reliance upon the defendant ’ s promise
in anticipation
of performance
of it , whereas
the
second
concern s expenditure incurred
after and
because of the
defendant ’ s
breach of contract
on the (incorrect) assumption that the defendant had performed it
( eg by the plaintiff
entering into a loss-making transaction which
it
would not have entered into had the solicitor used reasonable care) .
In the first, there is a change of position
by the plaintiff
on the faith of the defendant ’ s promise of
future
performance; in the second, there is a change of position
caused by
and after
the defendant ’ s breach.
That distinction enables it
immediately
to be recognised that the second
c ategory i s of no application here.
The Council submitted that the first
class was
con fined to
the costs of procuring or performing the contract ,
to be distinguished from money expended on the faith that the contract would be performed.
This was to found the submission that in
this case the expenditure on the hangar did not engage the doctrine, because Cutty Sark was not contractually obliged to build the hangar, there was no expectation of a benefit under the contract (as the Council was not obliged
to confer any benefit on Cutty Sark), and the expenditure on construction costs was not in expectation of
obtain ing
any benefit
under the
Agreement,
but in the
mere
hope that the airport would be developed, which was never a contractual obligation of the Council.
However,
in
Amann Aviation
,
the relevant expenditure was not incurred pursuant to a ny
contractual obligation,
though
it was incurred
to position the plaintiff to perform and derive benefit from the contract.
The type of expenditure
that would be recoverable
was
describ ed
variously as
“ expenditure justifiably incurred for the purpose of discharging contractual obligations ” ,
[72]
“ expenditure thrown away ” ,
[73]
“ expenditure
reasonably
incurred under a contract ” ,
[74]
“ such expenditure as is reasonably incurred in reliance on the defendant ’ s promise ” ,
[75]
“ the amount which a plaintiff has reasonably expended in reliance on the defendant ’ s promise and which is wasted by reason of the defendant ’ s breach of his promise ”
[76]
,
“ expenditure incurred in reliance on the defendant ’ s promise ”
[77]
, or
“ expenditure incurred in obtaining the contract and in performance of it on its part ” .
[78]
But w hile
a range of expressions were used to describe the relevant expenditure
,
the predominant description was no more specific than to the effect of
“ expenditure reasonably incurred in reliance on the defendant ’ s promise ” .
[79]
T he scope of the expenditure
that engaged the presumption was not an issue in
Amann Aviation.
The
more specific
descriptors should not be regarded as definitive of that scope, but as instances of the more general proposition that a plaintiff has a
“ reliance interest ”
arising from expenditure reasonably incurred in reliance upon the defendant ’ s performance of its contractual obligations.
In Australian law,
the progenitor of this doctrine is
the judgment of
Dixon and Fullagar
JJ ,
with whom McTiernan
J
agreed,
in
McRae
(emphasis added):
[80]
“ There is, however, more in this case than that, and the truth is that to regard this case as a simple case of breach of contract by non-delivery of goods would be to take an unreal and misleading view of it. The practical substance of the case lies in these three factors—(1) the Commission promised that there was a tanker at or near to the specified place; (2)
in reliance on that promise the plaintiffs expended considerable sums of money
; (3) there was in fact no tanker at or anywhere near to the specified place. In the waste of their considerable expenditure seems to lie the real and understandable grievance of the plaintiffs, and the ultimate question in the case (apart from any question of quantum) is whether the plaintiffs can recover the amount of this wasted expenditure or any part of it as damages for breach of the Commission’ s contract that there was a tanker in existence. In the opinion of
Webb
J. it would have been reasonable, and within the proper contemplation of the Commission, that the plaintiffs should take steps, but should do no more than take steps, to see whether there was a tanker in the locality given, and, if so, whether any and what things should be done to turn her to account. And his Honour estimated the reasonable cost of taking such steps at the sum of £500.
This view, however, seems to assume that the plaintiffs would be, or ought to be, in doubt as to whether they really had succeeded in buying a tanker.
But they were clearly entitled to assume that there was a tanker in the locality given
.
The Commission had not, of course, contracted that she or her cargo was capable of being salved, but it does not follow that the plaintiffs’
conduct in making preparations for salvage operations was unreasonable, or that the Commission ought not to have contemplated that the course in fact adopted would be adopted in reliance on their promise. It would be wrong, we think, to say that the course which the plaintiffs took was unreasonable, and it seems to us to be the very course which the Commission would naturally expect them to take
. There was evidence that salvage operations at the locality given would not have presented formidable difficulties in fair weather.
The plaintiffs were, of course, taking a risk, but it might very naturally seem to them, as
business men, that the probability of successful salvage was such as to make the substantial expense of a preliminary inspection unwarranted
. It was a matter of business, of weighing one consideration with another, a matter of which
business men
are likely to be the best judges.
So far as the purpose of the expenditure is concerned, the case seems to fall within what is known as the second rule
in
Hadley v. Baxendale
[(1854) 9 Ex. 341 [156 E.R. 145]]. A
fairly close
analogy may be found in a case in which there is a contract for the sale of sheep, and the buyer sends a drover to take delivery. There are no sheep at the point of delivery. Sheep have not risen in price, and the buyer has suffered no loss through non-delivery as such. But he will be entitled to recover the expense which he has incurred in sending the drover to take delivery: cf.
Pollock v. Mackenzie
[(1866) 1 Q.S.C.R. 156 ], and
see also
Foaminol Laboratories Ltd. v. British Ortid Plastics Ltd
[(1941) 2 All E.R. 393, esp. at p. 397]. ”
Rejecting as fallacious an argument that the alleged damage did not flow from the breach because the expenditure might equally have been wasted had there been a tanker at the specified location, their Honours said (emphasis added):
[81]
“ The argument is far from being negligible. But it is really, we think, fallacious. If we regard the case as a simple and normal case of breach by non-delivery, the plaintiffs have no
starting-point . The burden of proof is on them, and they cannot establish that they have suffered any damage unless they can show that a tanker delivered in performance of the contract would have had some value, and this they cannot show. But when the contract alleged is a contract that there was a tanker in a particular place, and the breach assigned is that there was no tanker there, and the damages claimed are measured by expenditure incurred on the faith of the promise that there was a tanker in that place, the plaintiffs are in a very different position. They have now a
starting-point .
They can say: (1) this expense was incurred; (2) it was incurred because you promised us that there was a tanker; (3) the fact that there was no tanker made it certain that this expense would be wasted
. The plaintiffs have in this way a
starting-point . They make a prima-facie case.
The fact that the expense was wasted flowed prima facie from the fact that there was no tanker; and the first fact is damage, and the second fact is breach of contract. The burden is now thrown on the Commission of establishing that, if there had been a tanker, the expense incurred would equally have been wasted
. This, of course, the Commission cannot establish. The fact is that the impossibility of assessing damages
on the basis of
a comparison between what was promised and what was delivered arises not because what was promised was valueless but because it is impossible to value a non-existent thing. It is the breach of contract itself which makes it impossible even to undertake an assessment on that basis. It is not impossible, however, to undertake an assessment on another basis, and, in so far as the Commission ’s breach of contract itself reduces the possibility of an accurate assessment, it is not for the Commission to complain.
For these reasons we are of opinion that the plaintiffs were entitled to recover damages in this case for breach of contract, and that
their damages are to be measured by reference to expenditure incurred and wasted in reliance on the Commission’
s promise
that a tanker existed at the place specified.
Thus, the plaintiffs ’
entitlement to recover reliance damages arose from expenditure reasonably incurred in reliance on the defendant ’ s contractual promise. It did not depend on the expenditure being pursuant to a contractual obligation, or required to perform the contract
–
and in
McRae
it was not; it did not matter that the plaintiff s
assumed the risk that salvage might not be possible ,
in which case they would not only have made no profit but incurred a loss; and it fell within the second limb of
Hadley v Baxendale,
because it was expenditure incurred for a purpose which the defendant ought to have
anticipated. T he essential components of the claim were identified as: (1) expense was incurred; (2) in reliance on the defendant ’ s contractual promise (that there was a tanker); (3) the breach of
which
rendered certain that the expense would be wasted (even though it might have been wasted in any event); (4) th us casting on
the defendant the burden of showing that it would have been wasted regardless.
There is no reason to confine the notion of expenditure incurred
“ in reliance on the defendant ’ s contractual promise ”
to expenditure under or required by the contract.
The notion that one would incur expenses only if it were reasonable to suppose that they would at least be recouped applies equally to moneys expended in reliance on a contractual promise as to those expended in
performing or
preparing
to perform
the contract.
The relevant expenditure in
McRae
was not incurred in performance of, or in preparing to perform, any contractual obligation : t he plaintiff ’ s only contractual obligation was to pay the purchase price ; i t was not obliged to salvage the tanker.
The expenditure
was incurred so that the plaintiff could derive benefit from the contract.
There is no relevant difference between the expenditure of the venturers in
McRae
to position themselves to derive benefit from the contract for sale, and that of a prospective lessee who in anticipation of being granted a lease fits out the premises
–
which is
analogous to
what occurred in the present case.
Fuller and Perdue , in their seminal and influential article,
[82]
referred to by Mason
CJ and Dawson
J
in
Amann Aviation,
[83]
described the
“ reliance interest ”
as follows:
“
Secondly,
the plaintiff has in reliance on the promise of the defendant changed his position. For example, the buyer under a contract for the sale of land has incurred expense in the investigation of the seller’s
title, or
has neglected the opportunity to enter other contracts. We may award damages to the plaintiff for the purpose of undoing the harm which his reliance on the defendant’s promise has caused him. Our object is to put him in as good a position as he was in before the promise was made. The interest protected in this case may be called the
reliance interest.
”
The authors elaborated:
“On the other hand, the promisee who has actually relied on the promise, even though he may not thereby have enriched the promisor, certainly presents a more pressing case for relief than the promisee
who merely demands satisfaction for his disappointment in not getting what
was
promised him. In passing from compensation for change of position to compensation for loss of expectancy we pass, to use Aristotle’s terms again, from the realm of corrective justice to that of distributive justice. The law no longer seeks merely to heal a disturbed status quo, but to bring into being a new situation. ”
In my opinion, the reliance interest
is not confined to
expenditure
required
by the
contract, or
required
to
enable the plaintiff to perform its contractual obligations, but
extends to any
reasonable
detrimental change of position by the promisee in reliance upon the defendant ’ s promise.
It extends to any expenditure reasonably incurred in reliance
on
the defendant ’ s contractual promise.
The references
in
Amann Aviation
to expenditure in preparation for or in performance of a contract
do not confine the doctrine
to such expenditure :
while
such a description sufficed to capture the relevant expenditure
in
Amann Aviation,
it
would not capture that
in
McRae
, where the plaintiff ’ s only obligation was to pay the purchase price , and the expenditure was incurred to
enable the plaintiff to exploit
the property it acquired under the contract .
Although I have referred to expenditure
“ reasonably incurred ” , and
qualifications to that effect are to be found in the
above references
in
McRae
and in
Amann Aviation
to expenditure
“ justifiably ”
or
“ reasonably ”
incurred ,
[84]
this is
really an expression of the rule in
Hadley v Baxendale.
There can be no question
as to
reasonable reliance
: a promise e
is entitled to rely on a contractual promise. Indeed, this was the was the essential point on which ,
in
McRae
,
Dixon
and Fullagar
JJ differed from
the primary judge
Webb
J,
in stating:
[85]
“This view, however, seems to assume that the plaintiffs would be, or ought to be, in doubt as to whether they really had succeeded in buying a tanker. But they were clearly entitled to assume that there was a tanker in the locality given.”
The question whether expenditure is
reasonably incurred
turns on whether it was the type of expenditure as might naturally be incurred in preparing for, performing or exploiting the benefit of the contract, or is or ought to have been contemplated by the defendant. Thus in
McRae
,
although the defendant had not
promised that the ship or cargo was salvageable:
“…
it does not follow that the plaintiffs ’
conduct in making preparations for salvage operations was unreasonable, or that the Commission ought not to have contemplated that the course in fact adopted would be adopted in reliance on their promise. It would be wrong, we think, to say that the course which the plaintiffs took was unreasonable, and it seems to us to be the very course which the Commission would naturally expect them to take. ”
The value of the
reliance
interest is the quantum of the net detriment.
Insofar as the plaintiff
is shown to have
derived some benefit from its expenditure,
including benefits
dehors
the contract,
it must give credit: thus, in
Amann Aviation,
credit was given for the residual value of the aircraft which Amann had purchased.
[86]
But u nless the value of th e benefit received
equals or exceeds the reliant expenditure, the difference is nonetheless wasted .
This is what Deane
J
described as the
“ wasted net expenditure ” .
[87]
Such expenditure is regarded as
“ wasted ”
if the promise in reliance on which it was made is not performed, except to the extent that it is shown that the plaintiff has received some offsetting benefit, whether under or
dehors
the contract.
“ Wasted
net
expenditure ”
is shorthand for expenditure incurred in reliance upon a contractual promise
that is not performed,
to the extent it is not offset by a benefit.
It was a central theme of the respondent ’ s submissions
that
the plaintiff
had
to establish that
the expenditure was wasted
as a consequence of
the defendant’s breach
.
[88]
However, if
the expenditure was incurred in reliance on the defendant ’ s contractual promise, then it is regarded as wasted in the relevant sense if the promise is not performed, except to the extent that an offsetting benefit is shown.
It suffices to enliven the presumption that
expenditure has been incurred in reliance on a defendant’s contractual promise which the
defendant has failed to perform.
[89]
If, regardless of the defendant ’ s breach, the expenditure would have been wasted in any event, then the rule casts on the defendant the onus of so demonstrating.
I f
the respondent ’ s submission is intended to introduce some
additional
causative r equirement , it would
subvert the presumption .
To sum up:
a
plaintiff who is unable
or does not undertake
to demonstrate whether or to what extent the performance of a contract would have resulted in a profit may
claim
its wasted expenditure. In such a case, expenditure incurred by a plaintiff in reliance on a contractual promise made by the defendant and
“ wasted ”
because of non-performance by the defendant is recoverable, except to the extent that the defendant shows that the plaintiff would not have recouped its expenditure had the contract been performed. Relevant expenditure is not confined to expenditure under or required by the
contract, but
extends (subject to the rule in
Hadley v Baxendale
)
to any detrimental change of position by the promisee in reliance upon the defendant ’ s promise.
Such expenditure is regarded as
“ wasted ”
if the promise in reliance on which it was made is not performed, except to the extent that it is shown that the plaintiff has received some offsetting benefit, whether under or
dehors
the contract.
The value of the reliance interest is the quantum of the net detriment , after allowing for any
offsetting
benefit accruing to the plaintiff from the expenditure .
It suffices to enliven the presumption that
the
expenditure has been incurred in reliance on a defendant’s contractual promise which the defendant has failed to perform.
The primary judge’s reasoning
The
reasoning
that culminates in th e primary judge ’ s conclusion
set out above
[90]
that the presumption did not arise but that if it did
it was rebutted
does not
distinguish
the
reasons for holding that the presumption does not arise from
th os e for holding that it was rebutted, and
consideration s which on any view are relevant only to the latter (such as, that Cutty Sark ’ s businesses were unprofitable) are interspersed with
consideration s
relevant to the former.
However, t hose
potentially
relevant to
whether the presumption arose were
as follows .
First ,
h er Honour
consider ed that
Amann
Aviation
was confined
to cases where the nature of the breach rendered assessment of damages on the usual basis impossible , and
added that damages were recoverable only
if within the
rule in
Hadley v Baxendale
:
[91]
“If read without sufficient regard to its facts,
Amann
could be read as standing for the surprising and unorthodox proposition that there is no obligation on an injured party to prove loss since the wrongful party will, in any event, be liable for wasted expenditure. However, the effect of
Amann
is not to turn the wrongful party into the insurer of the injured party. Rather,
Amann
is another example of that category of case to which
McRae
belongs,
where the nature of the breach renders assessment of damages on the usual basis (a comparison between the injured party’s position following breach and its position following performance without breach) impossible. In such cases, the court will not permit the wrongful party to take advantage of its own wrong. However, the loss suffered by the injured party
as a result of
the breach will only be recoverable if it falls within one or other of the two limbs in
Hadley v Baxendale
. In both
McRae
and
Amann
, the claim for damages assessed by reference to wasted expenditure was found to fall within the second limb of
Hadley v Baxendale
.”
Secondly, her Honour observed that the claim was not one for misrepresentation.
[92]
That is so, but that is so in every claim for reliance damages for breach of contract ; i t says nothing as to whether the conditions that engage the presumption are satisfied
(or for that matter whether any presumption is rebutted).
Thirdly , her Honour emphasised that
the Council
was not contractually bound
to develop the airport
:
[93]
“It is important, at the outset, to identify the relevant breach, which was to fail to take reasonable action to register the Plan and the Instrument by the Sunset Date. This breach occurred on 30 September 2011. The consequences of the breach were twofold: first, the plaintiff was not entitled to a 30-year lease;
and,
second, because the plan of subdivision was not registered, proposed Lot 104 and the other lots in the subdivision were not registered. It is important to note that the defendant did not
promise
to develop the airport along the lines of the subdivision, although such development was the ultimate purpose of the subdivision. Whether or not the airport was, in fact, developed, depended on external factors outside the control of the parties, such as demand for
particular lots
and demand for hangar homes. The evidence, such as it was, showed that there was little demand at that location. As far as the evidence reveals, there was little interest beyond the plaintiff’s, in the further development of the airport. Although one of the aircraft acquired by Cutty Sark HK had been purchased from someone who housed aircraft on the western side of the runway at the airport, the evidence did not reveal the details of this arrangement.”
Fourthly , her Honour distinguished
Amann
Aviation
and
McRae
.
As to
Amann Aviation
,
this was
on the basis that in that case,
although the
Commonwealth
was not contractually bound to renew the contract,
the successful tenderer would have a significant competitive advantage in gaining a renewal, and
the income to be gained from the contract was, since the Commonwealth was the party responsible for payment, both known in advance and assured :
[94]
“The present case is, in this (and other) respects, to be distinguished from
Amann
. Although the initial coastal surveillance contract in
Amann
was for a limited term (which was found to be insufficient to recoup the expenditure incurred by Amann in refitting aircraft to perform the contract), it could reasonably, at the time of entry into the contract, be assumed that the Commonwealth would continue to require coastal surveillance services in the future and that it would, as it had in the past, select a contractor through a tendering process. As aircraft needed to be refitted to the specification required by the Commonwealth, the sitting contractor had a significant competitive advantage over other tenderers since it
had,
on that hypothesis, already incurred the cost of modifying aircraft to comply with the specification. Further, the income to be gained from the contract was, since the Commonwealth was the party responsible for payment, both known in advance and assured.”
As to
McRae
,
the distinction
was
on the basis that in that case, the non-existence of the subject matter of the contract rendere d it impossible for McRae to prove that it would have recouped its expenditure :
[95]
“
McRae
, too, is to be distinguished from the present case. Because there was no wreck, and the Commonwealth Disposals Commission was held to have promised that there would be a wreck, there was nothing to flesh out the counterfactual to show what the wreck would have been worth had it existed. Thus, in
McRae
, the nature of the breach was such as to render it impossible for McRae to prove that it would have recouped its expenditure and impossible for the Commonwealth Disposals Commission to prove that it would
not
have.”
Her Honour then
explain ed:
[96]
“In the present case, unlike in
Amann
, there was no guaranteed income; the defendant was not responsible for paying the plaintiff anything; the defendant’s obligation, once the Plan and Instrument were registered, was, in substance, to allow the plaintiff quiet enjoyment of Lot 104 for the term of the lease, so that the plaintiff could make whatever money it could from the businesses it had identified which were permitted uses of Lot 104 under the lease. The difference the development,
if and when
it occurred, might have made, was unknown. Whether the development proceeded depended on external factors, such as whether there was a demand for the lots.
Unlike in
McRae
, there was a real site (proposed Lot 104) from which the very businesses which the plaintiff proposed to conduct after the Plan and Instrument were registered could be conducted pursuant to the licence. The businesses proved to be unprofitable and were abandoned.”
Finally, her Honour said that clauses
12.3(d) and
(f)(4)(C) of the
Agreement
excluded any claim for loss arising from the “Aerodrome Infrastructure Facilities” and from “any change in the flow of members of the public in or around the Land or Aerodrome for any reason” respectively, so as to make clear that the risk of the future development occurring or not was to be borne by Cutty Sark and not by the Council:
[97]
“Further, cl 12.3(d) specifically excluded any claim for loss arising from the ‘Aerodrome Infrastructure Facilities’ (which, as referred to above, was defined as including future developments of the site) not being available for use by the plaintiff and cl 12.3(f)(4)(C) specifically excluded any liability for any loss resulting from ‘any change in the flow of members of the public in or around the Land or Aerodrome for any reason’. These sub-clauses made it clear that the risk of the future development occurring (or not) was to be borne by the plaintiff and not the defendant. The plaintiff, in effect, took proposed Lot 104 in its then current state in the hope that the area around it might make proposed Lot 104 more conducive to profit (if it remained in possession) and more valuable, in the event of assignment, to third parties if it wished to relinquish possession. The surrounding circumstances and the terms of the AFL (including cl 16.8 of the proposed lease, which, as indicated by the precontractual negotiations, was relevant to the amount of the licence fee) show that the commercial risk was the plaintiff’s and not the
defendant’s.”
Her Honour also referred in this context to the circumstances that all the businesses which Cutty Sark had intended to conduct from proposed Lot 104 had proved to be unprofitable ;
[98]
and that having abandoned the businesses ,
the only methods to recover even part of the costs of the hangar were to obtain freehold or persuade the Council to pay compensation.
[99]
However, while arguably relevant to whether the Council rebutted the presumption, th ose matters
say nothing as to whether the presumption arose.
Her Honour also said that it was relevant that Cutty Sark had refused an offer of five consecutive five-year leases,
[100]
because this indicated that Cutty Sark was better off without its obligations under the deed ( which
includ ed
paying licensing fees for the next 30 years for a site from which it had been unable to operate any business profitably).
However,
that Cutty Sark refused an offer inferior to its contractual entitlements
c ould not
inform whether the presumption arose , even if it were relevant to whether it was rebutted
-
which ,
for reasons advanced below ,
it was not.
[101]
Two relevant themes can be seen in t he
reasoning
in support
of the proposition that the presumption did not arise .
The first is that
the presumption arises only where the defendant ’ s breach renders it
impossible
for the plaintiff
to prove that it would have recouped its expenditure, and this was not such a case.
[102]
If correct, that is
plainly a reason why the
presumption
would not arise.
The basis on which her Honour distinguished
McRae
was relevant to that issue, because
it
was that
“ in
McRae
, the nature of the breach was such as to render it impossible for McRae to prove that it would have recouped its expenditure and impossible for the Commonwealth Disposals Commission to prove that it would
not
have ” .
[103]
However, the basis
of her Honour ’ s distinction of
Amann Aviation
is not
relevant to that issue :
the matters referred to by her Honour
in that context
–
essentially,
that
the incumbent contractor would have a commercial advantage in the renewal process
–
are
relevant only
to
the likelihood of expenditure being recouped (and thus arguably
to
rebuttal of the presumption) , but not
to whether
the presumption arose .
Her Honour referred also to the contractual remuneration being known in advance and assured; but it is not
apparent how that is relevant to whether the presumption arose, although it might relate to the prospects of recoupment.
The second
theme
is that
although development of the airport was the ultimate purpose of the subdivision,
the Council had not promised to develop the airport,
and
the risk of the future development occurring or not was to be borne by Cutty Sark and not by the Council.
[104]
In so far as that is relevant to remoteness under
Hadley v Baxendale,
it is addressed under that heading below.
[105]
Otherwise, in so far as it
is a reason why
the presumption
would not arise ,
it appears to go to the issue of whether it was reasonable for Cutty Sark to incur expenditure
in reliance on the contract
–
in other words,
it involved a view that Cutty Sark did not , or was not entitled to,
rely
on
the
Council ’ s performance of the relevant obligation in incurring its expenditure, because
of the manner in which the contract allocated risk, and the limited nature of the
Council ’ s
obligations under it.
An impossibility
prerequisite?
(Ground 1)
The first
basis for not applying
Amann
Aviation
to hold
t hat the presumption was engaged (leaving for the moment to one side the question whether any such presumption was rebutted)
that
emerges from her Honour ’ s judgment
is that
the case was not one in which the Council ’ s breach of contract was such as to render it
impossible
for Cutty Sark to prove that it would have recouped its expenditure .
As has been noted, her Honour
said that
Amann
Aviation
and
McRae
were cases
“ w here the nature of the breach renders assessment of damages on the usual basis
…
impossible ” .
[106]
Notwithstanding
the primary judge’s
characteris
ation of
Cutty Sark
’s claim
in the manner summarised
above,
[107]
Cutty Sark’s case did not involve the proposition that it was “
impossible
for it to prove that it would have recouped” its expenditure, or that
the
Council’s breach had rendered it so
; the contention
was simply that
the
Council had not
discharged its onus of proving
that
Cutty Sark
would not have recouped its expenditure. Thus arises the question whether it is a precondition to the application of the presumption referred to in
Amann
Aviation
that it be
impossible
for the plaintiff to prove that it would have recouped its expenditure.
Although there are
passages in the
judgments in
Amann Aviation
where terminology such as
“ not possible ”
is used ,
in my opinion they do not support the proposition that
the
presumption can be invoked only where it is
im possible to work out lost profits or expectation damages.
The
context is important.
Thus when
Mason
CJ and Dawson
J
said:
[108]
“Similarly, where it is not possible for a plaintiff to demonstrate whether or to what extent the performance of a contract would have resulted in a profit for the plaintiff, it will be open to a plaintiff to seek to recoup expenses incurred, damages in such a case being described as reliance damages or damages for wasted expenditure.”
that was not a statement that impossibility of assessment of lost profits is a precondition to claiming reliance damages, as is clear from their Honours’ later explanation that reliance damages were not an alternative to loss of bargain damages in the sense of involving an election,
as all were but manifestations of the central principle enunciated in
Robinson v Harman
, rather than discrete and truly alternative measures of damages which a party not in breach may elect to claim.
[109]
And
as their Honours further explained (emphasis added):
[110]
“Naturally, the categories of case in which a plaintiff is likely to make a claim for the recovery of expenditure incurred are those in which the plaintiff has not suffered a loss of profits and those in which it is impossible to assess what would have been the outcome had the contract been performed or those in which that outcome is otherwise uncertain. So much is acknowledged by Lord Denning in the passage from
Anglia Television
already cited. The
manner in which
a plaintiff frames his or her claim for damages will be dictated not so much by a choice of alternatives giving rise to an election but simply according to whether the contract, if fully performed, would have been and could be shown to have been profitable (even if the actual amount of profit is not readily ascertainable).
If this can be demonstrated, a plaintiff’
s expectation of a profit, objectively made out, will be protected by the award of damages. Otherwise, subject to it being demonstrated that a plaintiff would not even have recovered any or
all of
his or her reasonable expenses, a plaintiff
’s objectively determined expectation of recoupment of expenses incurred will be protected by the award of damages
.”
Deane
J
referred to
“ a case where a plaintiff has incurred expenditure either in procuring the contract or in its performance but it is impossible
or difficult
(emphasis added)
to establish the value of any benefits which the plaintiff would have derived from performance by the defendant ” .
[111]
That does not support the proposition that it must be “impossible” to prove an expectation loss before the presumption arises, let alone that the impossibility be attributable to the defendant’s breach.
Similarly,
Toohey J
characterised
reliance damages
as
(empha
sis added)
“
a means of compensating the plaintiff where there has been no loss of profits or, more likely,
where the plaintiff cannot prove loss of profits with any certainty
”
and said that
damages
we re most appropriately assessed by reference to expenditure incurred where profits
are difficult
or impossible to quantify
or where the outcome of the contract is not predictable
.
[112]
Gaudron J
quoted the observation of Lord Denning M
R
in
Anglia Television Ltd v Reed
that “if [a plaintiff] has not suffered any loss of profits —
or if he cannot prove what his profits would have been
— he can claim in the alternative the expenditure which has been thrown away, that is, wasted, by reason of the breach”
,
[113]
and said
:
[114]
“ The present case is
one in which the uncertainties are such that it is not possible to make any reliable estimate of the value of Amann's contractual rights
. Thus, it is one in which the assessment of damages might properly be approached having regard to Amann's wasted expenditure.”
What emerges from the passages discussed in the preceding paragraphs is that
reliance damages may be recovered
where
a plaintiff does not prove an expectation of a profit.
None of those
expositions of the circumstances in which reliance damages may be claimed , properly understood,
requir e s
that it is a
precondition to their recoverability
that it first be established that it has been rendered “impossible” to prove an expectation loss.
On the other hand,
i n
Brennan J ’ s approach , it was
the defendant ’ s breach
having the effect of
den
ying
, prevent
ing
, or preclud
ing
the existence of circumstances which would have determined the value of the plaintiff ’ s contractual benefits
tha t
cast the onus on the defendant to prove that the plaintiff would not have recouped
its
expenditure.
[115]
And
the dissenting judgment of McHugh J
also
supports
the proposition that reliance damages are recoverable only if the
plaintiff first proves that the defendant ’ s breach has made it impossible to prove the outcome of the contract.
[116]
However,
the above analysis demonstrates that the
pre dominant
view in
Amann Aviation
is that the recoverability of reliance damages does not depend
upon it being proved that the defendant ’ s breach has rendered it
impossible
for
the plaintiff
to
prove
expectation damages.
Moreover, i n
Meetfresh
, Macfarlan
JA (with whom Bell
P
and Meagher
JA agreed)
explicitly
rejected the submission that damages for wasted expenditure were recoverable only where it
wa s impossible to quantify expectation damages:
[117]
“[30]
In support of these grounds of appeal, the appellant submitted that damages for wasted expenditure are only awarded where it is impossible to quantify expectation damages. It then contended that this was not such a case because it was possible to quantify Ivanman’s loss of profits, that being zero because its business had been performing poorly.
[31]
This approach is not supported by
Amann Aviation
or other authority. The effect of
Amann Aviation
is that the Court may award reliance damages where the evidence does not establish any loss of profits. Where, as here, a claimant does not seek to prove that the revenue it would have been likely to earn would have exceeded expenditure, such that profits would have been earned, it remains open to that party to claim that the prospective revenue would at least have been sufficient to recoup identified expenses.”
Meetfresh
thus stands as clear authority of this Court that reliance damages may be recovered not only where it is impossible to quantify expectation
damages, but
also
where
the plaintiff does not undertake to
prove, or
the evidence does not establish
,
any loss of profits.
For the reasons stated above , that position is a correct understanding of
the dominant
reasoning in
Amann Aviation.
Moreover, it would be quite illogical that a presumption casting the onus on the defendant to prove that the plaintiff would not have recouped its expenditure would arise only where the plaintiff
first established that it
could not possibly prove the opposite.
While the practical effect
of this
may be that a plaintiff who chooses not to undertake to prove an expectation loss can ,
by
claiming “reliance loss”
,
cast a burden on the defendant, t
his does not involve
any “
surprising and unorthodox proposition that there is no obligation on an injured party to prove loss since the wrongful party will, in any event, be liable for wasted expenditure ” ; nor does it make the wrongful party the insurer of the injured party.
First ,
the plaintiff will always have to prove that it incurred the expenditure, in reliance on
the defendant performing its relevant contractual obligation.
That is , of itself,
prima facie
proof of loss.
Secondly,
as Mason
CJ and Dawson
J
explained in
Amann Aviation,
such an approach is
in complete conformity with the principle that an award of damages for breach of contract should place a plaintiff in the same
(but no better)
position as if the contract had been performed, because
it permits the defendant to show that the injured party would not have recovered all or any of its wasted expenditure, in which
case the plaintiff is not entitled
t o
compensation for wasted expenditure
to the extent to
w hich it would not have been recouped :
[118]
“ The corollary of the principle in
Robinson v Harman
is that a plaintiff is not entitled, by the award of damages upon breach, to be placed in a superior position to that which he or she would have been in had the contract been performed. In
L Albert and Son v Armstrong Rubber Co
[(1949) 178 F 2d 182 (at 189)Chief Judge
L earned Hand said:
‘[O]n those occasions in which the performance would not have covered the promisee
’s outlay, such a result imposes the risk of the promisee's contract upon the promisor. We cannot agree that the promisor's default in performance should under this guise make him an insurer of the promisee’
s venture’.
Chief Judge Learned Hand went on [ibid at 191] to approve the statement made by Fuller and Perdue in their celebrated article, ‘
The Reliance Interest in Contract Damages’
, Yale Law Journal Vol 46 (1936) 52 at p79:
‘We will not in a suit for reimbursement for losses incurred in reliance on a contract knowingly put the plaintiff in a better position than he would have occupied had the contract been fully performed.’
In similar vein, the
Restatement of the Law: Contracts
, [2nd ed. (1981) ¶349
]
states:
‘As an alternative to the measure of damages stated in ¶347 [expectation damages], the injured party has a right to damages based on his reliance interest, including expenditures made in preparation for performance or in performance, less any loss that the party in breach can prove with reasonable certainty the injured party would have suffered had the contract been performed.’
According to the comment, the plaintiff may choose to sue for damages based on his reliance interest ‘if he cannot prove his profit with reasonable certainty. He may also choose to do this in the case of a losing contract, one under which he would have had a loss rather than a profit.’
To the same effect is
Corbin on Contracts
, [vol 5 (1964), ¶1031]. Corbin says:
‘The fact that profits are too uncertain for recovery does not prevent a judgment in favor of the plaintiff
for the amount of
his expenditures.’
After referring to Canadian cases to similar effect, t heir Honours
concluded
(emphasis added) :
[119]
“Thus, if a plaintiff’ s expenditure would not have been fully recouped had the contract been performed, then full compensation for the wasted expenditure would not be awarded. A plaintiff is only entitled to damages for an amount equivalent to that which would have been earned had the contract been fully performed.
In this way, the award of damages assessed by reference to a plaintiff’s expenditure is in complete conformity with the principle that an award of damages for breach of contract should place a plaintiff in the same position as if the contract had been performed
.”
Accordingly ,
the effect of
Amann
Aviation
and
McRae
is that where a plaintiff
does not prove
“ expectation damages ”
but
claims
“ reliance damages ”
for wasted expenditure, it will upon proof of
its
expenditure
incurred
in reliance on
the defen dant ’ s promise to
perform the relevant contractual obligation
have the benefit of a rebuttable presumption that it would at least have recovered that expenditure had the
promise
been performed.
It is not a precondition to
that
presumption arising that the plaintiff
first
establish that it is
“ impossible ”
to prove
expectation damages, let alone that
it be impossible to prove that it would not have recouped its expenditure.
These case s
do not constitute a category of case which depends on the nature of the breach rendering assessment of damages on the usual basis
“ impossible ” ; they apply whe never
the
plaintiff does not
claim
or the
evidence does not establish any loss of profits.
Although the
respondent ’ s submissions
seek to pass it off as a
“ false issue ” ,
[120]
the requirement for
“ impossibility ”
of proof of expectation damages was
the
chief
basis
for
her Honour ’ s conclusion
as a matter of principle that
the
Amann
presumption did not arise.
[121]
Ground 1 succeeds.
Risk and reliance
(Ground 3)
The second
theme
that emerges
from
the primary judge’s reasoning in this respect
is
that the Council should not be liable for the construction costs
of the hangar
because it was not contractually bound to develop the
airport
. That reasoning was also supported by the proposition that
clauses
12.3(d) and (f)(4)(C) of the
Agreement
excluded any claim for loss arising from the “Aerodrome Infrastructure Facilities”
not being available,
and from “any change in the flow of members of the public in or around the Land or Aerodrome for any reason” respectively, so as to make clear that the risk of the future development occurring or not was to be borne by Cutty Sark and not by the Council
.
As explained above, insofar as this is
relevant
to whether the presumption arose
, it would be because Cutty Sark did not, or could not reasonably, have
relied on the contract in incurring construction costs when there was no
promise
to develop the airport.
It may also be relevant to
remoteness under
Hadley v
Baxendale,
which is considered later.
C lause 12.3 of the Agreement
has been set out above;
[122]
relevantly, it had the effect that Cutty Sark released the Council from, and agreed that the Council
was not liable for,
all liability or loss arising from
the Aerodrome or Aerodrome
Infrastructure Facilities not being available for use by
Cutty Sark, and
for any loss resulting from
any change in the flow of members of the public in or around the Land or Aerodrome for any reason.
Plainly, clause 12.3 has no direct application:
Cutty Sark is not claiming in respect of
loss arising from the “aerodrome infrastructure facilities not being available” for its use, nor in respect of loss from “any change in the flow of members of the public in or around the land or aerodrome for any reason”.
Rather, it is claiming to recover loss being money which
it expended
in reliance on the Council’s
contractual promise to take all reasonable action to
procure registration of
the
P lan.
T
he primary judge’s reasoning
in this respect
[123]
was to the effect that
although the claim might not have been caught by clause
12.3,
it was not reasonable for Cutty Sark to incur the expenditure it did
in reliance on Council performing that obligation , as the
commercial
risk associated with the construction of the hangar was to be born e
not by the Council but by Cutty Sark
–
in
the light of
the provisions of that clause ,
the fact that Council was not contractually obliged to develop the airport,
and the presence
in the
P roposed Lease annexed to the
Agreement
of clause
16.8, which provided
for
the hangar to be
transferred
to the Council
unencumbered
for $1 upon termination of the Lease for any reason.
However,
reference to
“ commercial risk ”
generically, and even to the
“ risk of the future development occurring (or not) ” ,
obscures that the
Agreement
clearly delineates
risks which
Cutty Sark accepted , from other risks which it did not accept.
Because the Council did not promise to develop the airport, Cutty Sark assumed the commercial risk of any loss from the future (non) development of the airport.
Cutty Sark
also
accepted
the risk that the
Aerodrome Infrastructure Facilities might not be available for its use ,
and
that the flow of
the
public
might
be disrupted, and that the hangar as a fixture would revert to the lessor on expiry of the lease
–
that is,
after a term of 30 years in which Cutty Sark would have an opportunity to recoup its expenditure .
However, it
accepted
those risks and outcomes in circumstances where
the
Council had promised to take all
reasonable
action
to procure registration of the
P lan ,
where
the
Council was also the
relevant
consent authority, and where
Cutty Sark
would have 30 years in which to turn its investment to profit.
The
one risk that Cutty Sark did
not
accept was
tha t the Council would not take all reasonable action to procure registration of the
P lan .
In respect of
development of the airport ,
the risk it
assumed was that the development might not proceed,
and it might not recover its expenditure on the hangar,
notwithstanding that the Council took all reasonable steps to procure registration of the plan
.
However, i t did not
accept the risk that development would be rendered impossible
because the Council did not
take all reasonable steps to procure registration of the
P
lan
, which was a
necessary
precondition to it .
Although it is undoubtedly correct
that the Council was not contractually obliged to implement the commercial development of the airport , the Council is not being sued for breach of any such promise.
The claim for reliance damages does not proceed on the basis that it was so
bound, and
involves no hypothesis that the Council must have developed the airport
.
Rather,
the claim depends on expenditure incurred in reliance on the Council performing the obligation which it indisputably had, of taking all reasonable
action
to procure registration of the
P lan.
The fact that
the
Council did not promise to develop the airport does not mean that Cutty Sark did not incur expenditure on construction of the hangar in reliance on
the
Council ’ s promise to take all reasonable steps to procure registration of the
P lan.
It cannot be said that Cutty Sark was not entitled to rely on the Council performing its contractual obligations.
The fact that the Council did not promise to develop the airport is
beside the point. The one risk that matters is that which eventuated
–
that
the
Council
repudiated
its obligations
to take all reasonable action to procure registration of the Plan
–
and that risk was one which Cutty Sark did not accept.
The
reliance damages claim does not ask the
Council to bear the risk either of future development occurring or not occurring, or of any events that might affect the extent to which members of the public might visit the airport.
The risk which it is being asked to bear is that resulting from its
own
failure to take all reasonable action to procure registration of the
P lan , in breach
of its contractual obligation to do so.
Insofar as the primary judge held that
the presumption did not arise because the contractual allocation of risk meant that Cutty Sark did not or
could
not
reasonably rely on the Council ’ s promise to
take all reasonable steps
to
procure
registration of the
P lan,
Ground
3 succeeds.
No termination prerequisite
The respondent
submitted that expectation loss was not recoverable
except upon termination by the innocent party,
because
until then
the other party could remedy any breach. Reference was made to
Scott v Ennis-Oakes
,
[124]
in which it was held that a right to claim loss of bargain damages arises upon termination of the contract by the innocent party, and
that
until the contract is terminated by the innocent party, it remains on foot and no right to loss of bargain damages arises.
[125]
First,
t his submission was founded on the misconception that this was a claim in the supposed second category of reliance damages, in which case considerations applicable to expectation damages were said to apply. It has been explained above that this claim was not in that category.
[126]
In any event,
Scott v Ennis-Oakes
was concerned with
“ loss of bargain ”
damages: that is, a claim for damages for the difference between
what the innocent party
had to pay or was entitled to receive under the contract, and
the greater amount it would have to pay
for an equivalent property ,
or the lesser amount it would realise if
the subject property
were resold.
There are many circumstances in which expectation damages are recoverable without termination by the innocent party: for example, damages for breach of a warranty as to quality
in a sale of goods. The claim in the present case is not one for loss of bargain
damages.
Scott v Ennis-Oakes
is irrelevant.
Secondly, a s the
respondent
accept ed ,
[127]
termination
of the contract is not a necessary precondition to the award of
reliance damages.
McRae
is an
illustration of a case
in which termination
does not appear to have been considered relevant .
S o ,
for that matter ,
is the solicitor example
given
in
Amann Aviation
:
there would be no requirement for the plaintiff to terminate the retainer before suing for damages
resulting from the entry into the disadvantageous transaction.
One reason for this is that expenditure can be incurred in reliance upon
one contractual promise which is not performed,
even
though the contract remains on foot and is otherwise performed.
It was
also
submitted that, following the
Council ’ s
breach, Cutty Sark did not terminate the Agreement, which therefore remained on foot;
that
Cutty Sark then defaulted (by becoming deregistered) ;
the Council terminated, and the loss of bargain was due to Cutty Sark ’ s default ;
if, before termination of the Agreement by the Council, Cutty Sark was not entitled to recover its expenditure, then there is no reason why the termination by the Council in reliance on Cutty Sark ’ s default should affect that position.
The primary judge held that the Council had validly terminated the Agreement.
[128]
Although it may be doubted whether, having repudiated its essential and fundamental obligation under the Agreement,
the
Council was entitled to terminate for breach by Cutty Sark, this holding was not challenged on appeal. If Cutty Sark had sued before that termination, the position would have been that the Council had repudiated, and Cutty Sark had vacated the premises. In circumstances where the Sunset Date had passed, and the Council had no intention of seeking registration of the Plan, there would have been no difficulty in assessing damages on the basis that Council ’ s breach had foreclosed any possibility of Cutty Sark deriving the benefit of the promise. By refusing to take reasonable action to procure registration of the Plan and stating that it did not intend to do so, the Council plainly engaged in repudiatory conduct; and there was a continuing repudiatory breach so long as the Council failed to take the reasonable steps required to procure registration. In vacating the premises, Cutty Sark had accepted the repudiation and thereby terminated the Agreement. That is a different concept from rescission without breach,
under clause 4.4. But if that be incorrect, and the absence of a formal acceptance of the repudiation meant that the contract remained on foot with the theoretical possibility that the Council might yet, albeit belatedly, remedy its breach by taking steps to procure registration of the Plan, it put it beyond its capacity to do so when it terminated in 2015, whereupon Cutty Sark ’ s claim for reliance damages crystallised, if it had not already done so. These questions do not appear to have been explored at the trial, presumably because Cutty Sark ’ s right to claim damages for Council ’ s breach was in any event preserved. Clause
13.3 of the Agreement had the effect that Cutty Sark ’ s rights in respect of a breach by the Council before termination were not affected by termination. Cutty Sark ’ s right to claim to recover its expenditure incurred in reliance on the Council ’ s promise to take all reasonable steps to procure registration of the Plan, which the Council had repudiated, was thus preserved. It is not to the point to argue, as the respondent does, that Cutty Sark lost the bargain because of its own breach resulting in the Council ’ s termination, because it is not suing for loss of bargain damages; it is suing for damages for the Council ’ s breach of its obligation to take all reasonable action to procure registration of the Plan.
Conclusion: the presumption is engaged
(Ground 2)
Cutty Sark
incurred
expenditure in reliance
on the Agreement
There was evidence that Cutty Sark built the hangar in reliance on Council’s promise to take all reasonable action to register the plan of subdivision.
[129]
The primary judge referred to Mr Johnston’s evidence that had he known that Cutty Sark would ultimately not be provided with a 30-year lease in respect of Lot 104, he would not have caused the company to spend money on the construction of the hangar.
[130]
While her Honour
pointed out that such an allegation would be relevant to a claim for damages
for misrepresentation, it is also relevant to a claim to have expended
money in reliance on the promise that the Council would
grant
a lease.
Indeed, one might think it self-evident that absent a promise by the landowner who was also the consent authority to take
all reasonable action to procure the subdivision, a mere temporary licensee would not have incurred such expenditure to erect such improvements.
The reasonableness of
its
doing so is accentuated by the fact that in respect of the DA the Council was the consent authority as well as the applicant, which provided a high degree of confidence that if Council performed its obligations the Plan would be registered.
In my view, it is plain enough that the expenditure was incurred in reliance on the Council’s contractual promises, including
in particular the
promise to take all reasonable action to procure registration of the Plan. Even if it embarked on the exercise before the contract was made, i
t is unrealistic to suppose that Cutty Sark would have proceeded to complete construction of the hangar without the comfort that the Council ’ s relevant promise provided.
That
promise
was the Council’s key obligation under the Agreement. It was the essential promise for which Cutty Sark bargained. It is beside the point that the Council did not promise to develop the airport, so long as Cutty Sark relied on its promise to take all reasonable action to procure registration of the Plan.
The respondent submitted
that expenditure was incurred
before
the
contract was made and thus could not have been incurred in reliance on a
promise
contained i n it.
Mr Johnston engaged architects to design the hangar in January
2005 (before Cutty Sark was incorporated);
and
the development application for the construction of the hangar was lodged in April
2005 . Mr Johnston ’ s evidence was that he signed the Agreement in or around April
2007 ;
[131]
indeed ,
it seems that Cutty Sark had
executed
it by
23
March 2007 .
[132]
H e executed
the construction contract in or around May
2007 ,
[133]
and c onstruction of the hangar commenced in
that month . The Council executed the Agreement
on 26
July 2007 , though it
did
not
date and return
an executed copy
until 16
January
2008 .
[134]
C onstruction of the hangar
continued until about
November
2010 , when an occupation certificate was
issued .
[135]
The damages claim
was confined to costs of construction, and did not
include the earlier
costs of the design and DA .
Even if
some
construction expenditure
was
incurred before
the
Agreement
was executed,
most
of the construction work occurred
after the contract was made in July
2007 .
It is
entirely uncommercial
and unrealistic
to suppose that Cutty Sark would have continued to incur those construction costs if it knew that
there was no prospect of
it s
obtaining a lease of a lot in a subdivision
on which the hangar was erected.
The continued incurring of expenditure
after the contract was made is sufficient to establish reliance
upon the Council ’ s promise to take all reasonable
action
to procure registration of the Plan.
O nce that is established, the claim for wasted expenditure extends to that
reasonably incurred in the expectation that there would be a contract.
The expenditure recoverable as reliance damages includes
expenditure
incurred prior
to contract , if when the contract
wa s made it was reasonably in the contemplation of the parties as likely to be wasted if the contract were broken .
In
Anglia Television
v Reed
,
[136]
the defendant was a well-known actor who had contracted with the plaintiffs to play the leading man ’ s part in a television play which they were producing.
A few days after making the contract, the defendant repudiated it. The plaintiffs were unable to find a substitute, accepted his repudiation, and abandoned the production. The plaintiffs claimed as damages their total wasted expenditure of
£2,750.
In response to t he defendant ’ s contention
that they could only recover their expenditure
incurred
after the contract was concluded
( £854 ), the Court of Appeal
held that,
having elected to claim their wasted expenditure instead of their loss of profits,
the plaintiffs
were not limited to the expenditure incurred after the contract ,
but could claim the expenditure incurred before the contract provided it was reasonably in the contemplation of the parties as likely to be wasted if the
contract were broken , and so
in the circumstances were entitled to recover the
£2,750.
Lord Denning
MR, with whom
Phillimore
LJ and Megaw
LJ agreed, said:
[137]
“If the plaintiff claims the wasted expenditure, he is not limited to the expenditure incurred
after
the contract was concluded. He can claim also the expenditure incurred
before
the contract,
provided that
it was such as would reasonably be in the contemplation of the parties as likely to be wasted if the contract was broken. Applying that principle here , it is plain that, when
Mr. Reed entered into this contract, he must have known perfectly well that much expenditure had already been incurred on director's fees and the like. He must have contemplated — or, at any rate, it is reasonably to be imputed to him — that if he broke his contract, all that expenditure would be wasted,
whether or not
it was incurred before or after the contract. He must pay damages for all the expenditure so wasted and thrown away. This view is supported by the recent decision of Brightman J. in
Lloyd v. Stanbury
[1971]
1
W.L.R.
535. There was a contract for the sale of land. In anticipation of the contract — and before it was concluded — the purchaser went to much expense in moving a caravan to the site and in getting his furniture there. The seller afterwards
entered into
a contract to sell the land to the purchaser, but afterwards broke his contract. The land had not increased in value, so the purchaser could not claim for any loss of profit. But Brightman J. held, at p. 547, that he could recover the cost of moving the caravan and furniture, because it was “within the contemplation of the parties when the contract was signed.” That decision is in accord with the correct principle, namely, that wasted expenditure can be recovered when it is wasted by reason of the defendant ’ s breach of contract. It is true that, if the defendant had never entered into the contract, he would not be liable, and the expenditure would have been incurred by the plaintiff without redress;
but,
the defendant having made his contract and broken it, it does not lie in his mouth to say he is not liable, when it was because of his breach that the expenditure has been wasted.”
In
Amann Aviation,
Gaudron
J
said:
[138]
“Once it is appreciated that damages assessed by reference to wasted expenditure are awarded to compensate for the loss of contractual rights or for loss of profits, it is apparent that what is involved is an assumption (referred to in
McRae
, at 414, as “a starting-point”) that the loss is no less
than that which has been outlaid and wasted by reason of repudiation or breach. An assumption to that effect is no more than the recognition of the ordinary expectations of the world of commerce that the value of a contract will be no less than the cost of its performance. That assumption necessarily contemplates
that damages
will include preliminary expenses, as was held in
Anglia Television
.”
Here,
when the contract was made,
it was manifest that Cutty Sark was
preparing
and proceeding
to
construct
the hangar. Even if some of the costs of doing so were incurred before the contract was made,
so that the Council would not have been liable for them if no contract was made,
they were reasonably incurred in the expectation that there would be such a contract, given that Mr Johnston had in April
already
executed the document drafted and submitted to him by the Council.
It was also manifest that, if the Council did not perform its contractual obligation,
that expenditure would be thrown away.
T he presumption that
Cutty Sark would have derived contractual benefits no less than its expenditure takes into account its precontractual as well as its post-contractual expenditure.
The expenditure was wasted
Council
repudiated its obligation to take all reasonable action to procure registration of the Plan.
Its
breach was not merely failing to have the subdivision registered by 30
September 2011
–
a mere failure to procure registration, without fault, was not a breach; the breach was in not even trying to do so, and it was not as if it merely deferred doing so : it
expressly declared it had no intention of proceeding.
A s has already been noted,
a t the heart of the respondent ’ s case was the proposition that
Cutty Sark ’ s
relevant expenditure was not wasted
as a consequence of
the defendant’s breach.
[139]
This submission
involved
two
limbs :
It was submitted that Cutty Sark ’ s adventure flight business had failed by November
2009, and that by October
2010 Cutty Sark was trying to sell the entire hangar and its aircraft; by June
2011, the last vestige of the business, the venue hire, had also been abandoned, before the Sunset Date. In the context
that
the Council ’ s only breach was in failing to have the Plan registered by 30
September 2011, it was submitted that, if one were to ask whether or not on the Sunset Date, Cutty Sark had wasted $3
million building a hangar, it was immediately apparent that
whether or not the subdivision plan was lodged on 30
September
2011 made no difference: Cutty Sark had already incurred the expenditure, and attempted to run various business from it, all of which had failed. In substance, this was a submission that the Council ’ s breach was not causative, because the expenditure w ould have been
wasted in any event , because Cutty Sark ’ s business model was flawed;
I t was
submitted that the relevant expenditure
was
incurred to operate
particular types
of business from the hangar, and
notwithstanding
the breach
it remained possible
for Cutty Sark
to do.
S ince Cutty Sark did not rescind consequent upon th e
breach, it continued thereafter to enjoy a licence in relation to the proposed lot on the same terms and conditions, and to occupy the proposed lot and to use the hangar and enjoy the fruits of its expenses, until the
Agreement
was terminated by reason of its own breach.
The re
was no substantive difference between the lease for which Cutty Sark bargained, and the licence which it received in lieu
in
respect of the same land.
The sums expended in constructing the hangar were not wasted in the relevant sense in circumstances where Cutty Sark continued to enjoy rights under the
Agreement
( be ing
rights that substantially reflected those in the lease).
In substance, this was a submission
that Cutty Sark received benefits that
substantially
corresponded to its contractual rights.
First,
as a whole the
submission proceeds on the incorrect assumption that it was for Cutty Sark to establish
some causative element beyond that the contractual promise ,
in reliance upon
which
the expenditure was incurred ,
was not performed.
Secondly,
t h e first
limb
is redolent of the
argument
that was rejected in
McRae
as
“ fallacious ” ,
albeit
“ far from being negligible ” .
[140]
The
key
benefit for which Cutty Sark bargained was for Council to take all reasonable steps to procure registration of a plan of subdivision which would result in it having a lease for
30 years of one lot in the context of a 25-lot subdivision, with the prospect of surrounding commercial development.
E xpenditure was incurred ,
in reliance on
that
promise.
As has been explained, it understates the quality of the Council ’ s breach to characterise it as
“ only
…
in failing to have the Plan registered by 30
September 2011 ” .
Here, as in
McRae,
the Council ’ s breach of its promise rendered certain that Cutty Sarks ’
expenditure would be wasted, in the relevant sense
–
namely that Cutty Sark would not receive the benefits for which it bargained
and in the expectation of which it incurred expenditure .
It might be said that the present case is di fferen t, in that Cutty Sark ’ s businesses had ceased to trade before the Council ’ s breach had been committed. However, Cutty Sark had not at that stage abandoned the site, and it remained open to it to resume business at least until it did so, which was only after the Council had repudiated. Moreover, the fact that Cutty Sark ’ s businesses were unsuccessful
and it abandoned the site, in circumstances different from those which would have obtained had the contract been performed (namely, a 30-year lease of a subdivided lot in a 25 - lot subdivision, with the prospect of surrounding commercial development), does not negate the conclusion that it s expenditure was
incurred in reliance on a promise which was not performed ,
so that it did not receive the contractual benefits to which it was entitled , a nd
was thus wasted in the relevant sense (except to the extent there was some offsetting benefit) .
Save insofar as the Council can establish that Cutty Sark would not have recouped its expenditure regardless, it is beside the point that the contractual benefits might not have proved profitable for Cutty Sark.
Thirdly, as
to the second
limb ,
again,
the
promise in reliance upon which
Cutty Sark
incurred its expenditure
was
that the
Council
would
take all reasonable steps to procure registration of a plan of subdivision which would result in it having a lease for 30 years of one lot in the context of a 25-lot subdivision, with the prospect of surrounding commercial development. It did not incur the expenditure on the faith of having a mere licence over an isolated site not separately titled with no other lots created in the vicinity for
potential
commercial
development .
The offsetting
“ benefit ”
of the licence that Cutty Sark obtained was not even substantially comparable to what it bargained for under the contract. A lease confers rights and an interest in land, which a licence does
not. More significantly, Cutty Sark bargained for a 30-year lease of a subdivided lot in a 25-lot subdivision, which would have provided an environment for surrounding commercial development. Thus Cutty Sark
sh ould have
had
a thirty-year lease of a lot in a subdivision from which to conduct its business and recoup its expenditure, not
an
opportunity to do so from an isolated hangar in an unsubdivided airport.
True, any offsetting benefits must be brought to account, but it was not shown that the offsetting benefit of a licence
of the unsubdivided proposed lot
in those circumstances had any value , and on that issue
the Council bore the onus:
as Bre nnan
J
said in
Amann Aviation
:
[141]
“The point of distinction between the method of assessment of expectation damages and the method of assessment of reliance damages is the reversal in the case of reliance damages of the onus of proof of the net value of the plaintiff’s contractual benefits.”
Conclusion
Cutty Sark having
incurred expenditure in reliance on the
Council’s
promise
to take all reasonable steps to procure registration of the Plan
, and the
Council
having
repudiat ed
that obligatio
n
so as to
render it impossible
for Cutty Sark
to
receive the
contractual
benefits for which it had
bargain ed
, Cutty Sark’s expenditure
w as
wasted
in the relevant sense
.
That
sufficed to engage th
e presumption .
Moreo ver, even if Brennan
J’s
view
that the
presumption arises only if t he defendant ’ s breach
“d
enies, prevents or precludes the existence of circumstances which would have determined the value of the plaintiff ’ s contractual benefits
” be
preferred, that requirement was satisfied here.
In
Amann Aviation,
Brennan
J
found that although the contract did not include a right of renewal, performance would have resulted in Amann acquiring a substantial commercial advantage in tendering for the next contract,
[142]
and repudiation by the Commonwealth caused Amann to lose that advantage, the valuation of which was
“ a speculative exercise ”
such that it
“ cannot be
quantified with any degree of accuracy ” ,
[143]
such
that the Commonwealth ’ s repudiation of the contract thus
“ preclude[d] the occurrence of the events which would have permitted in due time a true assessment of the value of the commercial advantage lost by reason of the repudiation ” ,
[144]
th ereby
casting
on the Commonwealth the onus of showing that had the contract been performed ,
the plaintiff would not have recouped its wasted expenditure .
[145]
B ecause the Commonwealth had
“ not shown that the advantage was valueless or was of insufficient value when added to the contractual remuneration to provide sufficient net benefits to cover the expenditure incurred by Amann prior to rescission ” ,
[146]
that onus was not discharged.
Like
Amann Aviation
, th e present
is a case in which the Council ’ s non-performance of clause
4.2
“ precluded the occurrence of the events which would have permitted in due time a true assessment of the value of the commercial advantage lost by reason of repudiation ” .
Because the Council did not
try to procure registration of the
P lan,
it cannot be known what would have happened had it done so (although there must be a high degree of probability , given that it was also the consent authority,
that
the Plan
would have been registered, and the 30- year
lease granted) . And it cannot be known whether, if the
P lan had
been registered, the
commercial development
would have proceeded,
and what impact that would have had on the profitability of Cutty Sark ’ s businesses .
Still less can it be known
whether
commercial
development might have
ensu ed at some later time during the currency of the 30-year lease, and what opportunities that would have presented for Cutty Sark to recoup
its expenditure.
The Council ’ s breach rendered
impossible
a true assessment of
the probable outcome of performance of the contract
and whether it would have
enabled
Cutty Sark
at least to recoup its expenditure .
On either view of
Amann Aviation,
therefore, the presumption arose.
It was not shown that the licence of the unsubdivided proposed lot had any offsetting value to be brought to account. The Council bore the burden of proving, if it
could, that Cutty Sark’s expenditure would not have been recouped had the Council performed its promise.
Ground 2
therefore
succeeds.
Was the presumption rebutted?
(Ground 5)
The next question is whether, as the primary judge found, the Council discharged
the
onus of showing that the expenditure incurred by Cutty Sark in constructing the hangar would not have been recouped in whole or in part, if
the Council
had complied with clause
4.2 of the Agreement and taken all reasonable action to procure registration of the
P lan.
The primary judge ’ s reasoning on this issue
proceeded
as follows:
t he Council did not
contractually
promise to develop the airport along the lines of the subdivision, although such development was the ultimate purpose of the subdivision;
[147]
w hether or not the airport was in fact developed depended on external factors outside the control of the parties ,
such as demand for
particular lots
and demand for hangar homes, and the evidence indicated that there was little such demand;
[148]
e ach of the three businesses which
Cutty Sark
intended to conduct and did in fact conduct from proposed Lot 104 proved to be unprofitable ;
[149]
t he possibility that
Cutty Sark
might have been in a better position to operate profitably had the development proceeded
wa s no more than speculative ,
and it was not part of
the
bargain
that
the Council would do any more than take all reasonable action to register the
P lan, the Council ’ s promise not extending to developing the airport;
[150]
t hat Cutty Sark had abandoned the businesses prior to the
S unset
D ate, and the site altogether not long afterwards, told against the assumption
that it would have but for the breach remained on Lot 104 for the period of the lease
to
recoup the cost of the hangar ,
and support ed
the Council ’ s
submission that the hangar was a white elephant;
[151]
that Cutty Sark refused
the Council ’ s
offer of five consecutive five-year leases made on 13
September 2011
provides some indication that it did not intend to stay on proposed Lot 104 and conduct its businesses in the long term and is consistent with the Council ’ s hypothesis that Cutty Sark was better off without the obligations under the Agreement ,
which would have committed it to pay license fees for the next 30 years.
[152]
One theme in that reasoning is that the
Council ’ s promise did not extend to developing the airport.
As has already been explained, t he contractual benefits to which Cutty Sark was entitled under the Agreement w ere, in substance,
a 30-year lease of Lot 104 in a 25-lot subdivision of part of the airport.
However,
the fact that there was no promise to develop the airport does not mean that the potentiality of its development
i s irrelevant
when
considering whether the Council had shown that Cutty Sark would not recoup its expenditure.
That is because,
in considering whether
a plaintiff has been
shown to be unable
to recoup its expenditure,
a
court is not confined to the contractual
entitlements of the plaintiff ;
it is permissible to have regard
also
to
potential benefits that
might have accrued to the plaintiff, although
they are not
contractual
entitlements, if they
may reasonably be supposed to have been in the contemplation of the parties .
[153]
In
Amann Aviation
,
Mason
CJ and Dawson
J
accepted that the Commonwealth did not promise to renew its contract with the plaintiff and was not liable in damages for non-fulfilment of that promise,
[154]
but held that the loss of the prospect of securing a renewal of the contract was within the contemplation of the parties (for the purposes of the second limb of the rule in
Hadley v Baxendale
) as a probable result of the breach, so that Amann was
entitled to compensation which took into account the value of the loss of th at
pro spect :
[155]
“However, in the present case, the application of the rule in
Hadley v Baxendale
turns not on the degree of knowledge possessed by the defendant but on what may reasonably be supposed to have been in the contemplation of the parties as the probable result of the breach. If it be right to suppose that the loss of the prospect of securing a renewal of the contract was within the contemplation of the parties as a probable result of the breach, then, notwithstanding the principle established by
Abrahams
and
Lavarack
, Amann is entitled to compensation which takes into account the value of the loss of the prospect of securing a renewal of the contract.
What was in the contemplation of the parties depends upon a consideration of the terms of the contract in the light of the matrix of circumstances in which it was made. As we have seen, performance of the contract by Amann would have placed it in an advantageous position to secure a renewal of the contract with the benefits that would entail. The prospect of renewal was a distinct commercial benefit, inevitably contemplated by the parties as enuring to the advantage of Amann on, and by reason of, its performance of the contract. It was not an advantage which would accrue to Amann independently of performance of the contract or incidentally. The corollary is that the parties necessarily contemplated the loss of that prospect as the probable result of a repudiation or fundamental breach of the contract on the part of the Commonwealth.”
To similar effect,
Deane
J
said that the presumption
“ will not
…
be displaced merely by the circumstance that the benefits which the plaintiff would have obtained from performance by the defendant included the chance of some more remote benefit and it is a matter of speculation whether that ultimate benefit would have in fact been obtained or by the circumstance that the perceived
‘ benefit ’
which the plaintiff sought and for which she incurred the past expenditure is something
…
which
…
is not capable of being objectively valued in monetary terms ” .
[156]
His Honour said:
[157]
“It is impossible to do more than speculate about either the value to Amann of the chance of a further contract which would have existed at the end of the contract period or the price it would have obtained for its equipment if the contract had been fully performed by the Commonwealth. It follows from the earlier discussion of relevant principles that, in these circumstances, Amann
is entitled to
found
its claim for damages upon the presumption that the value of the contractual benefits which it would have derived from full performance by
the Commonwealth would have at least equalled the expenditure incurred in obtaining the contract and in performance of it on its part.”
His Honour added that the difficulty of assessing the value of the chance of a further contract made it impossible for the Commonwealth to rebut the presumption.
[158]
Thus, even though the defendant did not promise and was not bound to renew
the contract ,
“ the value of the prospect of a renewal of the contract was a matter to be taken into account in determining whether
Amann would or would not have recouped its expenditure ” , and the onus was on the Commonwealth to demonstrate that
“ the value to Amann of the prospect of renewal of the contract when combined with [its] expenses that would have been recovered by way of gross receipts was less than the total expenses to be incurred by Amann in the performance of its contractual obligations ” .
[159]
Although the plaintiff would not have recouped its expenditure in the initial term of the contract, and although it had no right to a further term, its prospects of obtaining a renewed term were sufficient that it could not be said that it was established that it would not ultimately recoup its expenditure.
Here, commercial development of the airport was admittedly the ultimate purpose of the promised subdivision.
To adapt the
words
of Mason
CJ and Dawson
J
extracted above , i t was a
“ a distinct commercial benefit ” , inevitably contemplated by the parties as enuring to the advantage of Cutty Sark
from
performance of the contract , and one which would not
accrue to
Cutty Sark
independently of performance of the contract or incidentally ; t he corollary is that the parties necessarily contemplated the loss of that prospect as the probable result of
the Council rep udiating its obligation to take all reasonable action to procure registration of the Plan . That the Council
did not
promise
to develop the airport is
no more significant than
was
the fact that
in
Amann
the Commonwealth
did not promise to renew
Amann ’ s
contract .
A second theme is that Cutty Sark ’ s endeavours to operate a business from proposed Lot 104 prior to the
Sunset Date
were unsuccessful ;
the businesses had failed ;
Cutty Sark had departed
the site ;
thus it would never
h ave recouped its expenditure
even
if the
Plan had been registered and the Lease granted.
However ,
although Cutty Sark had discontinued its then businesses before the Sunset Date, at a time when it did not know
whether or not
the subdivision would proceed, it had not then abandoned the premises; it took that step only later, after the Council had made clear that it had no intention of spending the money required to obtain registration of the Plan. At least until that point, had the Plan been registered, Cutty Sark would have had thirty years in which to resume operations from the hangar
–
whether the same or different businesses
–
in a potentially more conducive commercial environment.
Proof of losses in the early stages of a business or enterprise that
wa s to run for many years does not establish that, over the term of the Lease, Cutty Sark would not have earnt sufficient revenue to recoup its costs, particularly when there was a prospect that over that term the commercial environment would become more favourable with development of the airport.
[160]
The discontinuation of
its
business es
prior to the Sunset Date
does not significantly
i lluminate
the prospects of resuming operations
and
recouping expenditure over the
ensuing period of
30 years
in the different circumstances that would or might have prevailed
had the
Plan
been registered and
the
Proposed
L ease granted, particularly given that with a subdivision there was a prospect of
surrounding
commercial development and a more conducive commercial environment
–
the
prospect of which still appears to be
firmly
in the Council ’ s mind
today,
when
there would remain
20 years of the 30-year lease
yet
to run .
A third theme in the reasoning is that Cutty Sark rejected offers
which if accepted might have given it
the ability to conduct business from the hangar , with rights
not
significantl y
different
from
the rights which it would have had under the
Proposed
Lease . Cutty Sark ’ s
declining of those offers and that opportunity
is said to indicate that had the
P roposed Lease been granted it would not likely have resumed
operations.
With respect, this reasoning
impermissi b ly draws inferences from
Cutty Sark ’ s
declining
proposals from the Council that were inferior to its contractual entitlements.
Cutty Sark as the innocent party was entitled to insist on its contractual rights, or damages for breach, rather than accept ing
some inferior proposal advanced by the Council.
The
rejection of an offer of a 25-year licence, or 5 consecutive leases of 5 years, of
isolated
premises which did not comprise a subdivided
title d
lot
in
a 25-lot subdivision, provides no reasonable basis for an inference that Cutty Sark would not have
resumed operations and ultimately
recouped its expenditure , had it been granted
a
30-year lease of Lot 104 in a 25-lot subdivision , which was the likely result if the Council had performed its contractual obligation .
The offer s were
plainly inferior to Cutty Sark ’ s contractual entitlement ,
not only in that
they were not of
a 30-year lease, but also that
they
did not involve registration of the
P lan.
Even if Cutty Sark ’ s rejection of th ese
offer s
–
after the Sunset Date
–
“ provides some indication that it did not intend to stay on the proposed Lot 104 and conduct its businesses in the long-term ” ,
[161]
that was in circumstances
where Council
had
repudiated its obligations , as a result of which any prospect of a more conducive commercial environment was
precluded, and was offering an inferior solution , which Cutty Sark was entitled to reject ; it provides no basis for inferring that
Cutty Sark
would have had the same intention had Council not repudiated its contractual obligations.
As to her Honour ’ s observation
that it was
“ consistent with the defendant ’ s hypothesis that the plaintiff was better off without the obligations under the A greement , which would have committed it to pay licence fees for the next 30 years on a site, the surrounds of which might not have been developed during that period, and from which it had been unable to operate any business profitably ” , that would be so only
if Cutty Sark ’ s departure be treated as an acceptance by it of Council ’ s repudiation, thus bringing to an end its obligations under the Agreement
to pay
the licence fee
–
a
position it was entitled to adopt in the light of Council ’ s repudiation hav ing
precluded the prospect of commercial development. It says nothing as to
whether, had Council performed its obligations, Cutty Sark
c ould have recouped its expenditure over the ensuing
thirty years , during which the surrounds might have been developed
and it might have been able
to operate a business profitably .
Similarly, t he fact that Cutty Sark sought to extricate itself by one means or another from
the
predicament
created by the
Council ’ s
repudiat ion of
its obligations, without waiting to see whether the Council would belatedly do what it had promised to do
but
then expressly stated that it would not do , provides no basis for concluding that had Council performed its obligations, Cutty Sark
w ould not over the ensuing 30 years have recovered its expenditure.
It does not follow, from the circumstance t hat ,
after the Council had repudiated its obligations,
[162]
Cutty Sark
sought
to obtain freehold title to Lot 104
in order to
recover its costs ,
that it could not have recovered them had it been given a lease of a lot in a 25-lot subdivision, with 30 years in which to do so.
It is true that there was a prospect that the subdivision would not
have
proceed ed
without any breach on the part of the Council,
though
the prospects of that appear remote ,
given that Council
w as also the consent authority. There
wa s also
most certainly
a prospect that had the subdivision proceeded, the commercial development of the airport might not have , and if it did not,
it might have been
very
difficult for Cutty Sark to generate a sufficient return to recoup its expenditure. On the other hand, had the
P lan been registered, there was at least a prospect that
commercial
development would
fol low, if not immediately then later . It was submitted that if the Council did not have the money to complete the sewerage connection (which was the obstacle to registration of the Plan), it was most unlikely that it would have implemented the development. However,
the primary judge ’ s findings that the Council ’ s breach of clause 4.2 was by its failure to commit
“ funds to connect the proposed lots to sewerage ” ,
[163]
that while as at 2010 it was expected that the cost of doing that work
“ would eventually be offset (and notionally paid for) by income from the airport development ” ,
that
“ it was plain that the income would not be forthcoming at that level for some considerable time (if at all) ” ,
[164]
and that
“ when compared
with the other demands on the Council ’ s budget (including maintenance of roads and bridges) the development of the airport was not of sufficient priority to obtain the requisite funds ” ,
[165]
address only the short term, and not the prospects
of development
over the 30-year term of the
Proposed
L ease that ought to have been granted.
A 30-year lease from 1
October 2011 would not have expired until 30 September 2041 ;
the evidence revealed a significant possibility of expansion and development of the airport, with Council documents over
the decade from 2011 to 202 0
consistently referring to the increased demand for hangarage and the Council ’ s ambitions
for development of the airport ; and
had the Plan been registered,
there would
still remain
today
another 19 years
until 2041
for that to occur .
In those circumstances, i t is impossible to
be satisfied
that by 2041, Cutty Sark would not have recouped its expenditure. No doubt whether it would have done so is speculative, but that is because non-performance by the Council of its obligations under clause
4.2 has rendered it impossible to tell.
The fact that such a prospect
is
speculative, in circumstances where the Council bears the onus of showing that Cutty Sark would not have recovered its expenditure, does not assist the Council .
As the presumption is not displaced merely by the circumstance that the benefits which the plaintiff would have obtained from performance by the defendant included the chance of some remote benefit and it is a matter of speculation whether it would have in fact arisen, the speculative nature of the benefit to Cutty Sark renders it impossible for the Commonwealth to rebut the
Amann
presumption.
[166]
The Council submitted that Cutty Sark could not recover damages that had regard to the prospect of redevelop ment of the
airport unless it were established that such a prospect would have existed at the date of the breach, namely 30
September 2011. It was said that as damages are normally measured by reference to the circumstances at the date of breach of contract,
[167]
if the primary judge could not be satisfied that there would have been
as at
30
September 2011
some prospect of the airport being developed if clause 4.2 were complied with, then there could be no loss either
of
that prospect or
of
the prospect of Cutty Sark deriving profits after development of the airport ; and that only if
the
prospect
existed
as at 30
September 2011
could Cutty Sark cast any onus
on the Council to prove that it would not have recouped its expenditure had the Council fully performed its contractual obligations.
[168]
T h is submission is misconceived. First,
as explained above, net wasted expenditure serves as a proxy for the minimum contractual benefits that the innocent party would have derived, unless the defendant shows that it would not have been recouped ; i n considering whether the defendant has discharged that onus, regard is had not just to what the defendant has promised, but to other matters reasonably supposed to have been in the contemplation of the parties ,
when they made the contract ,
as probable result s
of a breach .
I n this case,
one such matter was the prospect that there would be commercial development of the airport.
The
evaluation of that prospect is
not a binary decision . In this respect there is no such distinction as the Council suggested, between a speculative prospect, and
its
speculative value. The value of a prospect (or a
“ chance ” ) is inherently intertwined with its likelihood
–
or the extent to which it is
“ speculative ” . That there is no such dichotomy is also indicated by the observation of Deane
J
in
Amann Aviation
that
“ the presumption will not
…
be displaced merely by the circumstance that the benefits which the plaintiff would have obtained from performance by the defendant included the chance of some more remote benefit and it is a matter of speculation whether that ultimate benefit would have in fact been obtained ” ,
[169]
with any speculation as to the value of the chance of the benefit being a difficulty to be confronted by the wrongdoer and not the innocent party.
[170]
Thus e ven if redevelopment of the airport was not
likely in the short term ,
it was necessary to consider
whether there was a prospect of redevelopment
sometime
during the
30 year
term of the lease
that would facilitate
recoupment. The fact that
the
Council had decided against
proceeding
in 2011 ,
and that
development
might not have been an immediate prospect as
at
30
September 2011 ,
does not mean that there was not then
some
prospect of redevelopment
during the 30-year term , or that it was so remote that it could be concluded that Cutty Sark would not, over that period,
ultimately
recoup its expenditure.
Secondly, the
“ rule ”
that damages are assessed as at the date of breach is
in any event
nowadays but a guide, yielding
“ if, in the particular circumstances, some other date is necessary to provide adequate compensation ” .
[171]
More
relevantly,
even where it applies, a court is not precluded from having regard to subsequent events in evaluating the position as at the relevant date.
[172]
In this case, the evidence of the Council ’ s ongoing support for redevelopment of the airport between 2012 and 202 0
shows that, as at 30 September 2011, there was very much a prospect of it occurring sometime before 20 41.
Thirdly,
it is not correct that it is only if Cutty Sark established that such a prospect would have existed
as
at
30
September 2011
that it could cast any onus upon the Council to prove that it would not have recouped the expenses that it incurred in reliance on the Agreement.
As has been explained, o nce Cutty Sark established it incurred expenditure on the faith of the promise that was not performed, the onus shifted to the Council to show that it would not have recouped its expenditure.
In circumstances where what would have transpired had
the
Council performed its obligations was speculative but there was a high degree of likelihood
( given that
the
Council was also the consent authority) that the
P lan would be registered, and at least a prospect of further development of the airport
producing a more conducive commercial environment for Cutty Sark ’ s business operations, if
not
immediately then sometime over the ensuing thirty years of the lease to which Cutty Sark was entitled, the Council could not and did not show that Cutty Sark would not ,
over a 30-year lease ,
have recouped its expenditure.
Ground 5 succeeds.
Was recovery
precluded by the r ule in
Hadley v Baxendale
?
(Ground 4)
An a dditional
basis for her Honour ’ s
rejection of the claim for substantial damages was the rule in
Hadley v Baxendale
,
which
limits damages recoverable for breach of contract to losses which may
“ fairly and reasonably be considered either arising naturally
…
from such breach of contract itself, or such as may reasonably be supposed to have been in the contemplation of both parties at the time they made the contract, as the probable result of the breach of it ” .
[173]
The primary judge held that the reliance damages claimed by Cutty Sark w ere
not recoverable under either limb :
[174]
“[222]
For completeness, it is necessary to address whether the damages claimed by the plaintiff would fall within either the first or the second limb of
Hadley v Baxendale
. Mr Williams submitted that they fell within both limbs since the loss of such costs arose naturally from the breach and may reasonably be supposed to have been in the contemplation of both parties, at the time they made the contract, as the probable result of a breach. Mr Williams submitted that the actual amount spent on the construction of the hangar was not to the point. He relied on the statement in
Alexander v Cambridge Credit Corporation Ltd
(1987) 9 NSWLR 310 at 365 (McHugh JA) that the parties need not contemplate the degree or extent of the loss or damage suffered for the purposes of the second limb of
Hadley v Baxendale
. Thus, he submitted that it was immaterial that the figure stipulated in the development application for the hangar was $560,000 and the actual figure (claimed as damages) was approximately six times that amount.
223. The terms of the AFL were such that it was within the reasonable contemplation of the parties that no lease would be
granted
and the AFL would be terminated, without breach, on or after the Sunset Date because the Plan and Instrument had not been able to be registered. Thus, the hangar was erected at the plaintiff’s risk. Because the plaintiff chose to erect a nondemountable hangar (having undertaken to the defendant that it would be
‘cost-prohibitive’
to do so as noted by Mr Gogarty in his pre-contractual communication to Mr Dockrill extracted above), the defendant made express provision, in cl 16.8 of the lease, for the hangar to become its property on payment of one dollar when the agreement was terminated by either party or by effluxion of time. This was a clear indication that the parties intended that the plaintiff bear the risk of the hangar being transferred to the defendant for nominal consideration at any time between the entry into the AFL and the expiry of the 30-year lease. The plaintiff could have had no reasonable expectation when it chose to expend, on its case, in the order of $3.5m on the hangar, that it would be permitted to amortise the cost over a period of 30 years from the day after the date of registration of the Plan and Instrument, since that event was uncertain, both as to timing and eventuality, and as both parties had a right to terminate if the deadline was not met (except if a party was in breach).
224. It is understandable that Mr Johnston consistently agitated for an option to purchase the proposed Lot 104. As a matter of commercial reality, had the plaintiff owned (or had an option to purchase) the freehold of the land on which the hangar had been constructed, it would have been entitled to retain it, either because it was a fixture or because it was located on land which it owned. Thus, the plaintiff would have had an asset which could be
sold
and which was, at least, potentially valuable (since, on that hypothesis, the lease would have come to an end because the freehold and leasehold interests would have merged with the plaintiff ’ s acquisition of the freehold title). However, this did not
occur
and the defendant steadfastly refused to grant any such interest to the plaintiff, which was stuck with the terms of the AFL, including cl 16.8 of the proposed lease.
225.
In these circumstances, I am not satisfied that the cost of the hangar would be recoverable under either of the two limbs in
Hadley v Baxendale
. For these reasons, as referred to above, the dispute as to the total amount spent to construct the hangar does not need to be resolved. I note that there is no claim for restitution and no admissible evidence as to the value of the hangar.”
Th e reasoning disclosed by the above
passage
i s to the effect that:
i t was within the reasonable contemplation of the parties that no lease would be
granted
and
the Agreement
would be terminated without breach on or after the
Sunset Date ;
t he hangar was thus erected at Cutty Sark ’ s risk , and
in particular at
the risk
that it would be transferred to the Council for nominal consideration
at any time between the making of the Agreement and
the expiry of the Lease;
and
Cutty Sark could have had no reasonable expectation when it chose to incur expenditure on the hangar
that it
would be permitted to amortise
the cost over a period of 30 years from registration of the Plan, since that event was uncertain, both as to timing and eventuality .
However, the relevant question was
not
whether Cutty Sark could
reasonably have expected
when it chose to incur expenditure on the hangar that it would be permitted to amortise the cost over a period of 30 years ,
or whether the hangar was erected at Cutty Sark ’ s risk,
but
whether
when the contract was made the parties ought to have
recognised that
expenditure
had been and/or
w ould be
incurred in respect of the hangar
in rel iance on the Council ’ s promise to take all reasonable action to procure registration of the Plan , which
would be wasted
if the Council did not
do so .
In
McRae,
Dixon and Fullagar
J J
said:
[175]
“So far as the purpose of the expenditure is concerned, the case seems to fall within what is known as the second rule
in
Hadley v. Baxendale
[(1854) 9 Ex. 341 [156 E.R. 145]]. A
fairly close
analogy may be found in a case in which there is a contract for the sale of sheep, and the buyer sends a drover to take delivery. There are no sheep at the point of delivery. Sheep have not risen in price, and the buyer has suffered no loss through non-delivery as such. But he will be entitled to recover the expense which he has incurred in sending the drover to take delivery: cf.
Pollock v. Mackenzie
[(1866) 1 Q.S.C.R. 156 ], and
see also
Foaminol Laboratories Ltd. v. British Ortid Plastics Ltd
[(1941) 2 All E.R. 393, esp. at p. 397].”
Hallett
J
considered
the question
of remoteness in
a claim in respect of wasted expenditure
in
Foaminol Laboratories Ltd. v. British Ortid Plastics Ltd
(emphasis added):
[176]
“I now come to the expenditure by the plaintiffs in connection with their sales campaign. They had certain advertisements inserted, and they incurred certain other expenses in
preparation
for the intended sales campaign, and I am quite satisfied that in fact they sustained a pecuniary loss to the extent of those items by reason of the defendants ’
failure to supply the containers necessary to proceed with the sales. The defendants knew perfectly well that these containers were wanted for the packing of a new summer cream which was going to be introduced by the plaintiffs to the public, and that,
in order to
introduce to the public a new product of this kind of cosmetics, advertising of some kind would have to take place. The defendants also knew that there would be certain other minor expenses incurred in the way of preparation for sale, such as labels, which form a small item of the claim. Furthermore, they knew perfectly well that it was essential that, when the demand had been created, a supply should be available. The two things go together. If the supply is not available when the demand has been created, then, from the point of view of the seller, his work in creating the demand is thrown away.
Therefore, it seems to me to be quite plain that, at the time when the defendants made the contract, they must have known, or ought to have known if they had stopped to think about it, that, if, through their default, the supply was not available to meet the demand, then the expenditure on advertising in creating the demand would be thrown away, and they must have known that that expenditure was going to take place.
I slightly modified what I had already said by saying that they would have known if they had paused to think about it, because both
counsel
reminded me that in actual fact, when two people are making a contract, they are not usually thinking about what the consequences will be to one or the other if there is a breach. What they are both thinking about at the time is that, when they make a contract, it will be carried out, and, in a sense, it is undoubtedly artificial to talk of their contemplating the consequences of a breach. What that really amounts to, however, is that the law implies that each of them would have realised the consequences if he had stopped to think about them. In my view, therefore, it cannot be said that the expenditure on advertising and upon one or two other small matters, such as the cellophane to go over the containers, and the waxed discs, and the artist ’s drawings, which fall into the same category is too remote in point of law to be established.”
From that passage ,
and from
McRae,
it is
plain that the
proper application of
Hadley v Baxendale
as a control on remoteness of damage in a claim for wasted expenditure
is whether, when the contract was made, it was within the reasonable
contemplation of the parties that the relevant expenditure would be incurred and, i f the contract were breached
in the relevant manner,
wasted.
In
Amann Aviation
, the rule in
Hadley v Baxendale
played a rather different role : its
second limb was
reli ed
on to show that a defendant ’ s
liab ility
could extend
beyond damages for not doing that which he or she was contractually bound
to do.
Thus, Mason
CJ and Dawson
J
said that:
“The rule that the defendant is not liable in damages for not doing that which he or she has not promised to do is necessarily subject to the rule in
Hadley v Baxendale
. According to Alderson B’s renowned formulation, the plaintiff is entitled to recover such damages as arise naturally, that is, according to the usual course of things, from the breach, or such as may reasonably be supposed to have been in the contemplation of both parties at the time they made the contract as the probable result of the breach. It is now accepted that this is the statement of a single principle and that its application may depend on the degree of relevant knowledge possessed by the defendant in the
particular case.
However, in the present case, the application of the rule in
Hadley v. Baxendale
turns not on the degree of knowledge possessed by the defendant but on what may reasonably be supposed to have been in the contemplation of the parties as the probable result of the breach. If it be right to suppose that the loss of the prospect of securing a renewal of the contract was within the contemplation of the parties as a probable result of the breach, then… Amann is entitled to
compensation which takes into account the value of the loss of the prospect of securing a renewal of the contract.”
[177]
In that way, it enabled
the prospect of renewal to be taken into account in considering whether the plaintiff would not have recouped its expenditure.
Similarly, in this case it permits the prospect of commercial development to be taken into account in considering that same question.
But that is a different question from whether
damages in respect of wasted expenditure
on the hangar are too remote
to be recoverable
under the rule.
In this case,
it was plainly in the contemplation of the parties when the Agreement was made that Cutty Sark would incur substantial expenditure in erecting the hangar. T he Agreement was made in circumstances where the characteristics of the hangar featured in the parties ’
negotiations ;
the Council had granted development consent for the hangar ;
the Agreement made provision in respect of
“ the Lessee ’ s works ” , which could only have been the hangar;
preliminary works on its construction had commenced, and (as the primary judge found),
“ the [Council] was aware that [Cutty Sark] was constructing a hangar at substantial expense on proposed Lot 104 ” .
[178]
And had they turned their mind to it,
it would have been obvious that that expenditure would be wasted
if
the
Council did not take all reasonable action to register the plan.
While undoubtedly Cutty Sark assumed an element of risk, it did not assume the risk that the Council would not take all reasonable action to procure registration of the plan.
The matters relied on by the primary judge
–
that the parties contemplated that no lease might be granted without breach, that the hangar would eventually be transferred to the Council for nominal consideration, and that whether and when the Plan would be registered was uncertain
–
are
not at all in consistent with the parties also recognising that if the Council did not take all reasonable steps to procure registration of the Plan, Cutty Sark ’ s expenditure would be wasted . In this case it was, or ought to have been, plain to both parties, had they turned their minds to the question when the contract was made, that non-performance by the Council of its relevant
obligation would result in Cutty Sark wasting the expenditure it had incurred and was going to incur in constructing the hangar.
The loss incurred
is therefore
reasonably
to
be supposed to have been in the contemplation of both parties when the contract was made, within the second limb
of
Hadley v Baxendale
.
Ground 4 succeeds.
Quantum (Ground 6)
Cutty Sark claimed that it had expended $3,697,234.41 on the construction of the hangar (including overheads and miscellaneous expenses) ,
as follows:
Construction Costs
Amount (incl GST)
Builder (Babic Construction)
$2,404,187.75
Architecture fees
$546,644.62
Trades
$549,905.27
TOTAL construction costs
$3,500,737.64
Overheads
$175,126.68
Miscellaneous costs
$21,370.09
TOTAL
$3,697,234.41
The
Council
disputed $438,228.26 of th
at
total, on the basis that the relevant i
nvoices
were addressed to an entity other than Cutty Sark, and no evidence was given of any arrangement between that entity and Cutty Sark. Her Honour did not resolve that dispute
,
observing that it
“
was not fully explored in the evidence”.
[179]
The
relevant
evidence
was in short compass.
In his affidavit of 20
September 2021, Mr Johnston
exhibited an
“ Updated Expenditure Schedule ”
of Cutty Sark ’ s
expenses in relation to the construction of the
hangar , and
explained that it included
amounts paid to the build er
(Babic) , amounts paid to the architect (Stut c h bu ry), amounts paid to trades , overhead costs directly relating
to the project, and miscellaneous costs . The effect of this evidence was
that the expenses listed in
the
“ U pdated
E xpenditure
S chedule ”
were expenditure by Cutty Sark in relation to the construction of the hangar on proposed Lot 104.
[180]
In his evidence in chief, Mr Johnston was
shown
a copy of
the
“
U pdated
E xpenditure
S
chedule”
, from which some deletions had been made,
which showed
the
grand total of $3,697,234.41, of which he
said
“
that’s exactly right
” .
[181]
He was
then
asked:
[182]
“Q. Have you satisfied yourself that the items that you wish to identify as items to be deleted from the schedule have in fact been deleted from this schedule?
A. Yes, they have.
Q. Does that updated expenditure schedule with those deletions, together with the invoices to which it refers, constitute the expenditure that Cutty Sark made on the hangar?
A. Yes, on the hangar alone. That’s correct.”
The
document
was tendered ,
and
ad mitted without objection , although c ounsel for the
Council
said:
[183]
“COOK: I should, just by way of clarity, indicate that my position is based upon what Mr Williams said earlier that it’s a summary of all the invoices. Given that we’ve received the updated schedule this morning, if we add up the invoices and it comes to a different figure to that in the document, your Honour won’t preclude me from making submissions that the amount is a different amount, I trust?
HER HONOUR: No, I won’t. Your position is preserved. Thank you, Mr Cook.”
The cross - examination of Mr Johnston did not touch upon this topic. However, in the
Council ’ s closing written submissions, it disputed $438,228.26 of the total claimed , submitting :
[184]
“178. It is one of the more curious features of this case that the total of the expenses allegedly incurred by Cutty Sark in constructing the Hangar continued to increase well after that construction had completed. On 6 February 2011, Mr Dockrill wrote to the General Manager of the Council, saying, amongst other things, that ‘our client has spent approximately $2.5m in constructing his hangar on the property’. Thereafter, on 20 December 2011, Mr Dockrill asserted in correspondence that the ‘[t]he current amount spent on the hangar venue by our client is over $2.7 million’.182 This was in circumstances where, on Mr Johnston’s own evidence, the Hangar was completed in November 2010. The total costs associated with the construction of the Hangar are now said to approach $3.7 million. While some account may be taken of the perils of embarking upon an arithmetic exercise in real time, less explicable is the fact that several of the invoices on which Cutty Sark now relies in quantifying its alleged losses were addressed, not to Cutty Sark itself, but to other persons or entities, most prominently Cutty Sark Investments (Hong Kong) Ltd, Air Action Pty Ltd and Mr Johnston personally. Annexed to these submissions is a schedule identifying these invoices.
179. Cutty Sark has led no evidence of any arrangement pursuant to which it assumed liability under these invoices. Nor has it otherwise assayed an explanation for why the liabilities recorded in these invoices should be seen as forming part of its asserted loss. At the very least, these invoices should be excluded from Cutty Sark’s claim.”
The annexure identified invoices totall ing
$438,228.26.
Mr Johnston ’ s evidence set out above was not the subject of challenge.
The respondent submitted that the matter was not one which had to be put in cross - examination .
I am prepared to accept that the Council was not precluded
from
relying on the fact that various invoices were addressed to persons or entities other than Cutty Sark ,
but the absence of any challenge to Mr Johnson
in this respect makes it easier to accept
his
evidence, general ised assertion
as it was,
to the effect that the schedule represented expenditure incurred by Cutty Sark
in constructing the hangar .
Moreover, e xamination of the annexure listing the
disputed
invoices
reveals
that many were issued by the architects who
supervised
construct ion of
the
hangar, or trades who worked on it, sometimes to Mr Johnston personally
and sometimes to
other related entities. No suggestion has been made that they were not referrable to the construction of the hangar , and it is clear enough from their content s
that they were . No suggestion has been made that they were not incurred. Some appear to be subcontractor costs addressed to head contractors. No suggestion was made that they were not passed onto and
ultimately
incurred by Cutty Sark. I f
costs referrable to the construction of the hangar were invoiced to associated entities of Cutty Sark, it is readily to be inferred that, if Cutty Sark did not itself then pay them, it became liable to reimburse the associated entity which advanced the funds for its benefit.
In those circumstances, and in the light of Mr Johnson ’ s
broad-brush
but
unchallenged
evidence on the question
and the conduct of the trial,
the proper finding is that Cutty Sark incurred expenditure of $3,697,234.41 on construction of the hangar.
Ground 6 succeeds.
Conclusion
My conclusions may be summarised as follows:
A plaintiff who is unable
or does not undertake
to demonstrate whether or to what extent the performance of a contract would have resulted in a profit may
claim
to recoup its wasted expenditure. In such a case, expenditure incurred by a plaintiff in reliance on a contractual promise made by the defendant and
“ wasted ”
because of non-performance by the defendant is recoverable ,
except to the extent that the defendant shows that the plaintiff would not have recouped its expenditure had the contract been performed. Relevant expenditure is not confined to expenditure under or required by the
contract, but
extends (subject to the rule in
Hadley v Baxendale
)
to any detrimental change of position by the promisee in reliance upon the defendant ’ s promise. Such expenditure is regarded as
“ wasted ”
if the promise in reliance on which it was made is not performed, except to the extent that it is shown that the plaintiff has received some offsetting benefit, whether under or dehors the contract.
The value of the reliance interest is the quantum of the net detriment , after allowing for any
offsetting benefit accruing to the plaintiff from the expenditure .
It suffices to enliven the presumption that
expenditure has been incurred in reliance on a defendant’s contractual promise which the defendant has failed to perform.
Amann Aviation
and
McRae
do not constitute a category of case which depends on the nature of the breach rendering assessment of damages on the usual basis
“ impossible ” ; they apply when the plaintiff does not
claim
or the evidence does not establish any loss of profits.
It is not a precondition to that presumption arising that the plaintiff first establish that it is
“ impossible ”
to prove expectation damages.
Ground 1 succeeds.
The fact s
that the Council did not promise to develop the airport , and that the con t ract allocated significant risks to Cutty Sark ,
are
beside the point. The one risk that matters is that which eventuated
–
that Council repudiated its obligations to take all reasonable action to procure registration of the Plan
–
and that risk was one which Cutty Sark did not accept.
Cutty Sark was entitled to rely on the Council performing its contractual obligations.
Insofar as the primary judge held that the presumption did not arise because the contractual allocation of risk meant that Cutty Sark did not or could not reasonably rely on the Council ’ s promise to take all reasonable steps to procure registration of the plan,
Ground 3 succeeds .
Termination of the contract
by the innocent party
is not invariably a precondition to recovery of reliance damages.
In any event , c lause 13.3 of the Agreement had the effect that Cutty Sark ’ s rights in respect of a breach by the Council before termination were not affected by termination , and
Cutty Sark ’ s right to claim to recover its expenditure incurred in reliance on the Council ’ s promise to take all reasonable steps to procure registration of the Plan, which the Council had repudiated, was thus preserved.
Cutty Sark incurred substantial expenditure in
constructing the hangar on proposed Lot 104 in
reliance upon the Council ’ s promise to take all reasonable action to procure registration of the Plan. Even if some of the construction expenditure was incurred before the Agreement was made, it is recoverable as
it was plain when the contract was made that it would be wasted if the promise was not performed.
Th e presumption arose. C
utty Sark, although it did not prove (nor endeavour to prove) that it had incurred any expectation loss, did prove that it had incurred expenditure in reliance on the Council’s performance of its obligation to take all reasonable steps to procure registration of the Plan. Council’s repudiation of that obligation rendered certain that Cutty Sark would not receive the benefits for which it had contracted, and that its expenditure would be wasted in the relevant sense. That sufficed to engage the presumption
,
so
as to
cast on the
Council t
he onus of showing
the value of any offsetting benefit received by Cutty Sark, and/or that its expenditure would not have been recouped had the contract been performed.
Moreover, e ven if the
presumption arises only if the defendant ’
s breach “denies, prevents or precludes the existence of circumstances which would have determined the value of the plaintiff
’
s contractual benefits”, that requirement was satisfied here
:
t he Council ’ s breach rendered impossible a true assessment of the probable outcome of performance of the contract and whether it would have enabled Cutty Sark at least to recoup its expenditure.
Ground 2 succeeds.
The presumption was not rebutted.
In circumstances where what would have transpired had
the
Council performed its obligations was speculative ,
but there was a high degree of likelihood (given that
the
Council was also the consent authority) that the Plan would be registered, and
there was
at least a prospect of further development of the airport producing a more conducive commercial environment for Cutty Sark ’ s business operations, if not immediately then sometime over the ensuing thirty years of the lease to which Cutty Sark w ould have been
entitled, the Council could not and did not show that Cutty Sark would not over a 30-year lease have recouped its expenditure. The primary judge erred in concluding otherwise.
Ground
5 succeeds.
It was plainly in the contemplation of the parties when the Agreement was made that Cutty Sark would incur substantial expenditure in erecting the hangar ; an d
it was, or ought to have been, plain to both parties, had they turned their minds
to the question when the contract was made, that non-performance by the Council of its relevant obligation would result in Cutty Sark wasting the expenditure it had incurred and was going to incur in constructing the hangar.
The loss incurred
in the nature of wasted
expenditure
is therefore reasonably to be supposed to have been in the contemplation of both parties when the contract was made, within the second limb
of
Hadley v Baxendale
, and
the primary judge
erred in holding otherwise .
Ground 4 succeeds.
In the light of Mr Johnson ’ s broad-brush
but
unchallenged
evidence on the question ,
and the conduct of the trial, the proper finding is that Cutty Sark incurred expenditure of $3,697,234.41 on construction of the hangar.
Ground 6 succeeds.
The appeal should be allowed. The judgment below should be set aside and in lieu thereof there should be
judgment
for
Cutty Sark for $3,697,234.41 and interest. The Council must pay Cutty Sark ’ s costs of the proceedings at first instance and on appeal. The parties should be directed to bring in short minutes, including calculation of interest, to give effect to this judgment.
MITCHELMORE JA:
I agree with Brereton JA.
**********
Endnotes
1.
123 259 932 Pty Ltd v Cessnock City Council (No 2) [2021] NSWSC 1329 (“Primary judgment”) at [179].
2.
Primary judgment at [10].
3.
Primary judgment at [10].
4.
Primary judgment at [13].
5.
Primary judgment at [11]-[12].
6.
Primary judgment at [12].
7.
Primary judgment at [21].
8.
Primary judgment at [21].
9.
Primary judgment at [16].
10.
Primary judgment at [22].
11.
Primary judgment at [24].
12.
Primary judgment at [31].
13.
Primary judgment at [19].
14.
Primary judgment at [18].
15.
Primary judgment at [38].
16.
Primary judgment at [32]-[45].
17.
Primary judgment at [52]. It had already been executed by Mr Johnston on behalf of Cutty Sark. However, it was ultimately dated 16 January 2008, when the Council returned the executed Agreement to Cutty Sark.
18.
Primary judgment at [138].
19.
The definitions are contained in clause 1.1 of the Agreement for Lease.
20.
Primary judgment at [150].
21.
Clause 5.1 of the Agreement.
22.
Affidavit, James Gordon Johnston, 6 March 2019 at [23].
23.
Letter from Dockrill to Sparke Helmore of 8 September 2006; Primary judgment at [40].
24.
Letter from Dockrill to Sparke Helmore of 18 October 2006.
25.
Primary judgment at [39]; Affidavit, James Gordon Johnston, 6 March 2019 at [68].
26.
Primary judgment at [45].
27.
Primary judgment at [57]-[60].
28.
Primary judgment at [62].
29.
Affidavit, James Gordon Johnston, 6 March 2019 at [172], [188].
30.
Tcpt, 5 October 2021, p 74(34)-(36). Although her Honour regarded that prognostication with scepticism, as will appear Cutty Sark did not bear the onus on that issue.
31.
Primary judgment at [78].
32.
Primary judgment at [84].
33.
Primary judgment at [88].
34.
Primary judgment at [92].
35.
Primary judgment at [92].
36.
Primary judgment at [85].
37.
Primary judgment at [95].
38.
Primary judgment at [98].
39.
Primary judgment at [108].
40.
Primary judgment at [103].
41.
Affidavit, Bronwyn Ann Rumbel, 7 November 2019, Exhibit BAR-1, p 262.
42.
Affidavit, Bronwyn Ann Rumbel, 7 November 2019, Exhibit BAR-1, p 311.
43.
Affidavit, Bronwyn Ann Rumbel, 7 November 2019, Exhibit BAR-1, p 298.
44.
Primary judgment at [119].
45.
Corporations Act 2001 (Cth), s 601AD(2).
46.
Primary judgment at [122]; Affidavit, James Gordon Johnstone, 6 March 2019 at [122].
47.
Primary judgment at [123]; Affidavit, Bronwyn Ann Rumbel, 7 November 2019 at [70].
48.
Primary judgment at [124]; Letter, Holding Redlich to ASIC, 18 September 2015.
49.
Primary judgment at [125].
50.
Primary judgment at [127].
51.
Primary judgment at [128].
52.
Affidavit, Bronwyn Ann Rumbel, 7 November 2019, Exhibit BAR-1, pp 542-559.
53.
Primary judgment at [130].
54.
(1951) 84 CLR 377; [1951] HCA 79 (“McRae”).
55.
(1991) 174 CLR 64; [1991] HCA 54 (“Amann Aviation”).
56.
[2020] NSWCA 234 (“Meetfresh”).
57.
Primary judgment at [210].
58.
Primary judgment at [221].
59.
(1854) 9 Exch 341; 156 ER 145.
60.
Robinson v Harman (1848) 1 Exch 850; 154 ER 363 (Parke B); Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009) 236 CLR 272; [2009] HCA 8 at [13] (French CJ, Gummow, Heydon, Crennan and Kiefel JJ).
61.
Amann Aviation at 81.
62.
Amann Aviation at 86.
63.
Amann Aviation at 89.
64.
Amann Aviation at 126-127.
65.
Amann Aviation at 142-143 (Toohey J), 155-157 (Gaudron J).
66.
Amann Aviation at 106-18.
67.
(2020) 271 CLR 151; [2020] HCA 27.
68.
(2020) 271 CLR 151; [2020] HCA 27 at [29]. That this was entirely obiter is apparent from [30], where their Honours stated that it was unnecessary to invoke either of the presumptions considered in Amann Aviation.
69.
[2020] NSWCA 234 at [29].
70.
Amann Aviation at 89, 96 (Mason CJ and Dawson J); 126-7 (Deane J); Meetfresh at [29].
71.
Amann Aviation at 85.
72.
Amann Aviation at 81 (Mason CJ and Dawson J).
73.
Amann Aviation at 84 (Mason CJ and Dawson J), referring to Anglia Television Ltd v Reed [1972] 1 QB 60 (Lord Denning MR).
74.
Amann Aviation at 85 (Mason CJ and Dawson J).
75.
Amann Aviation at 86 (Mason CJ and Dawson J).
76.
Amann Aviation at 104 (Brennan J).
77.
Amann Aviation at 106 (Brennan J).
78.
Amann Aviation at 131 (Deane J); see also at 126 where his Honour refers to expenditure “either in procuring the contract or in its performance”.
79.
Amann Aviation at 86.3, 88.9, 89.1, 89.4 (Mason CJ and Dawson J); 104.7-9, 105.1, 105.3, 106.1, 107.1 (Brennan J); 127.1, 129.5 (Deane J); 139.7-8, 140.9 (Toohey J); 154.4, 158.7 (Gaudron J); 161.6 166.9-167.1 (McHugh J).
80.
McRae at 412-413 (Dixon and Fullagar JJ).
81.
McRae at 414-415 (Dixon and Fullagar JJ).
82.
“The Reliance Interest in Contract Damages”, (1936) 46 Yale Law Journal 52 at 54.
83.
“The Reliance Interest in Contract Damages”, (1936) 46 Yale Law Journal 52 at 56.
84.
Above at [61].
85.
McRae at 412-413 (Dixon and Fullagar JJ).
86.
Amann Aviation at 79 (Mason CJ and Dawson J).
87.
Amann Aviation at 127-128.
88.
Respondent’s written submissions at [6], [14], [21].
89.
Amann Aviation at 89 (Mason CJ and Dawson J).
90.
Primary judgment at [221]; above at [45].
91.
Primary judgment at [207].
92.
Primary judgment at [208]-[209].
93.
Primary judgment at [211].
94.
Primary judgment at [215].
95.
Primary judgment at [216].
96.
Primary judgment at [217]-[218].
97.
Primary judgment at [220].
98.
Primary judgment at [212].
99.
Primary judgment at [214].
100.
Primary judgment at [219].
101.
See below at [132]-[133].
102.
Primary judgment at [207], [215]-[218]; see above at [75], [78]-[80].
103.
Primary judgment at [216].
104.
Primary judgment at [211], [220]; see above at [77], [81].
105.
See below at [143]-[149].
106.
Primary judgment at [207], above at [75].
107.
Primary judgment at [210]; see above at [43].
108.
Amann Aviation at 81.
109.
Amann Aviation at 85; see above at [56].
110.
Amann Aviation at 85.
111.
Amann Aviation at 126.
112.
Amann Aviation at 142-143.
113.
[1972] 1 QB 60 at 64.
114.
Amann Aviation at 155-157.
115.
Amann Aviation at 106-107.
116.
Amann Aviation at 166-167 (McHugh J).
117.
[2020] NSWCA 234 at [30]-[31].
118.
Amann Aviation at 82-3 (Mason CJ and Dawson J).
119.
Amann Aviation at 84 (Mason CJ and Dawson J).
120.
Council’s written submissions at [21], [29]-[32].
121.
Primary judgment at [207].
122.
Above at [22].
123.
Primary judgment at [220], [223].
124.
[2020] NSWCA 239.
125.
[2020] NSWCA 239 at [37]-[44] (Bathurst CJ, Bell P and Gleeson JA agreeing).
126.
Above at [59].
127.
Respondent’s written submissions at [13].
128.
Primary judgment at [221].
129.
Affidavit, James Gordon Johnston, 6 March 2019 at [26]; Affidavit, Bronwyn Ann Rumbel, 7 November 2019, Exhibit BAR-1, p 186; Tcpt, 6 October 2021, p 114(16)-(19).
130.
Primary judgment at [208].
131.
Affidavit, James Gordon Johnston, 6 March 2019 at [72].
132.
Letter from Mr Dockrill to Sparke Helmore, 23 March 2007.
133.
Affidavit, James Gordon Johnston, 6 March 2019 at [62].
134.
Primary judgment at [52]; Affidavit, James Gordon Johnston, 6 March 2019 at [73].
135.
Affidavit, James Gordon Johnston, 6 March 2019 at [66]-[68].
136.
Anglia Television Ltd v Reed [1972] 1 QB 60 (“Anglia Television”).
137.
Anglia Television at 64.
138.
Amann Aviation at 155-156.
139.
Respondent’s written submissions at [21].
140.
McRae at 414-415; above at [63].
141.
Amann Aviation at 107.
142.
Amann Aviation at 111-112.
143.
Amann Aviation at 112.
144.
Amann Aviation at 113.
145.
Amann Aviation at 113.
146.
Amann Aviation at 115.
147.
Primary judgment at [211].
148.
Primary judgment at [211].
149.
Primary judgment at [212].
150.
Primary judgment at [213].
151.
Primary judgment at [214].
152.
Primary judgment at [219].
153.
Amann Aviation at 90-92 (Mason CJ and Dawson J).
154.
Amann Aviation at 91.
155.
Amann Aviation at 92.
156.
Amann Aviation at 127.
157.
Amann Aviation at 130-131.
158.
Amann Aviation at 131.
159.
Amann Aviation at 94.
160.
Cf Meetfresh at [35].
161.
Primary judgment at [219].
162.
That this occurred only after the Sunset Date, and not before the Council had repudiated, appears from the Primary Judgment at [92], [94], [100]-[102].
163.
Primary judgment at [178].
164.
Primary judgment at [67].
165.
Primary judgment at [162].
166.
Cf Amann Aviation at 127, 130-131 (Deane J).
167.
Citing Wenham v Ella (1972) 127 CLR 454 at 473; [1972] HCA 43.
168.
Respondent’s written submissions at [47].
169.
Amann Aviation at 127.
170.
Amann Aviation at 130-131.
171.
Johnson v Perez (1988) 166 CLR 351 at 367 (Wilson, Toohey and Gaudron JJ); [1988] HCA 64; see also Cory & Son v Wingate Investments (1981) 17 BLR 104 at 118 (Walton J), 121-123 (Ormrod LJ); quoted in Renown Corporation Pty Ltd v SEMF Pty Ltd [2022] NSWCA 233 at [17]-[18] (Brereton JA).
172.
Williamson v John I. Thornycroft And Company, Limited [1940] 2 KB 658 at 659 (Scott LJ, with whom Clauson LJ agreed), 660-661 (Du Parcq LJ); Willis v Commonwealth (1946) 73 CLR 105 at 109 (Latham CJ), 116 (Dixon J); [1946] HCA 22; McIntosh v Williams [1979] 2 NSWLR 543 at 550-551 (Moffitt P and Samuels JA)); Johnson v Perez (1988) 166 CLR 351 at 368-9 (Wilson, Toohey and Gaudron JJ); [1988] HCA 64; Nikolaou v Papasavas, Phillips & Co (1989) 166 CLR 394 at 405-6; [1989] HCA 11 (Wilson, Dawson, Toohey and Gaudron JJ).
173.
Hadley v Baxendale (1854) 9 Exch 341 at 354; 156 ER 145.
174.
Primary judgment at [222]-[225].
175.
McRae at 413.
176.
[1941] 2 All E.R. 393 at 397.
177.
Amann Aviation at 91-92 (Mason CJ and Dawson J).
178.
Primary judgment at [237].
179.
Primary judgment at [56].
180.
Affidavit, James Gordon Johnston, 20 September 2021 at [8] (definition of “project”) [12] (“I, on behalf of the company”) [13] (costs claimed by Babic during the project), [16] (Stutchbury’s costs during the project), [19] (costs claimed by trades), [26] (overhead costs directly relating to the project), [31] (miscellaneous costs), and [15], [18], [29] and [33] (Mr Johnston’s practice as the authorised representative of Cutty Sark to authorise payments). .
181.
Tcpt, 5 October 2021, p 58(44).
182.
Tcpt, 5 October 2021, pp 58(46) – 59(03).
183.
Tcpt, 5 October 2021, p 59(26)-(33).
184.
Defendant’s closing submissions of 7 October 2021 at [178]-[179].
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Decision last updated:
20 February 2023
Official source: https://www.caselaw.nsw.gov.au/decision/1865dcfaa9ebfb5d9e06af19