711 Hogben Pty Ltd v Anthony Tadros [2022] NSWSC 1259
Catchwords: LANDLORD AND TENANT – breach by landlord of lease by failing to carry out landlord’s works to render the premises fit for use as a childcare centre – DAMAGES – assessment of value of commercial opportunity to trade which opportunity the tenants lost as a consequence of the landlord’s breach
Supreme Court
New South Wales
Medium Neutral Citation:
711 Hogben Pty Ltd v Anthony Tadros [2022] NSWSC 1259
Hearing dates:
29, 30, 31 August and 1 September 2022
Decision date:
19 September 2022
Jurisdiction:
Equity - Commercial List
Before:
Hammerschlag CJ in Eq
Decision:
Verdict for damages for $730,000.
Catchwords:
LANDLORD AND TENANT – breach by landlord of lease by failing to carry out landlord’s works to render the premises fit for use as a childcare centre – DAMAGES – assessment of value of commercial opportunity to trade which opportunity the tenants lost
as a consequence of
the landlord’s breach
Legislation Cited:
Children (Education and Services) National Law 2010 (NSW)
Education and Care Services National Regulations 2011 (NSW)
Environmental Planning and Assessment Act 1979
(NSW)
Environmental Planning and Assessment Regulation 2021 (NSW)
Cases Cited:
711 Hogben Pty Ltd v Tadros [2016] NSWSC 697
711 Hogben Pty Ltd v Tadros [2016] NSWCA 244
711 Hogben Pty Ltd v Tadros
[2016] NSWSC 1238
711 Hogben Pty Ltd v Tadros [2016] NSWSC 1683
711 Hogben Pty Ltd v Anthony Tadros [2018] NSWSC 628
711 Hogben Pty Ltd v Anthony Tadros [2021] NSWSC 1463
711 Hogben Pty Ltd v Tadros [2022] NSWSC 1085
Badenach
v Calvert (2016) 257 CLR 440
Commonwealth v Amann Aviation Pty Ltd (1991) 174 CLR 64
Daniels v Anderson (1995) 37 NSWLR 438
Kizbeau
Pty Ltd v WG & B Pty Ltd (1995) 184 CLR 281
Luna Park (NSW) Ltd v Tramways Advertising Pty Ltd (1938) 61 CLR 286
Malec
v JC Hutton Pty Ltd (1990) 169 CLR 638
March v E & MH
Stramare
Pty Ltd (1991) 171 CLR 506
Sellars v Adelaide Petroleum NL &
Ors
(1994) 179 CLR 332
Silverbrook
Research Pty Ltd v Lindley [2010] NSWCA 357
Tabet
v
Gett
(2010) 240 CLR 537
Wenham v Ella (1972) 127 CLR 454
Category:
Principal judgment
Parties:
Anthony Tadros - First Defendant/Second Cross Claimant
Sharon Tadros - Second Defendant/Third Cross Claimant
George Tadros - Third Defendant/First Cross Claimant
711 Hogben Pty Ltd ACN 157911745 - Plaintiff/ Third Cross Defendant
Representation:
Counsel:
M W Young SC - Defendants/Cross Claimants
J E Lazarus SC, M Sheldon - Plaintiff/Third Cross Defendant
Solicitors:
Finn Roache Lawyers - Defendants/Cross Claimants
One Group Legal - Plaintiff/Third Cross Defendant
File Number(s):
2015/330101
JUDGMENT
HIS HONOUR:
This is yet another chapter , regrettably probably not the last,
in this long running dispute between a landlord and its tenants. The lengthy history of the proceedings is attributable
largely
to the
obdurate
default of the landlord , who does not dispute that it was in continuous breach of the lease from 2015 to 8 October 2020 .
This is the hearing of the tenants ’
claim for damages for
that
breach.
Only quantum is
in issue .
The proceedings have spawned no less than
seven
judgments of the Court, all of which have been adverse to the landlord: see
711 Hogben Pty Ltd v Tadros
[2016] NSWSC 697
(Stevenson J);
711 Hogben Pty Ltd v Tadros
[2016] NSWCA 244 (Meagher and Leeming JJA);
711 Hogben Pty Ltd v Tadros
[2016] NSWSC 1238 (Stevenson J);
711 Hogben Pty Ltd v Tadros
[2016] NSWSC 1683 (Beech-Jones J
–
as his Honour then was);
711 Hogben Pty Ltd v Anthony Tadros
[2018] NSWSC 628
(Hammerschlag J);
711 Hogben Pty Ltd v Anthony Tadros
[2021] NSWSC 1463 (Stevenson J);
711 Hogben Pty Ltd v Tadros
[2022] NSWSC 1085
(Stevenson
J).
The proceedings
concern a
Deed of A greement for
L ease (
the
AFL
)
dated 11 April 2014 between
the plaintiff (
Hogben
or
the Landlord
) and the first and second defendants (
the tenants
) for premises (
the
P
remises
)
owned by
Hogben
at
levels
one
and
two , 7-11 Hogben Street, Kogarah, which is in the southern suburbs of Sydney. The tenants ’
obligations were guaranteed by their father, George Tadros, the third defendant , who has represented them in m any
of the ir
dealings
with Hogben .
I shall refer to him as
George
, with no disrespect intended.
The tenants
intended
(and apparently still
do,
but probably with less enthusiasm )
to operate a childcare centre
called St George Baby Dragons Academy
(
the
C
entre
)
from the
P remises .
Two observations should be made at the outset. First, t he lawful operation by a
“ provider ”
of a
childcare
centre requires approval or certification ( referred to as
Service Approval
)
from the Department of Children and Education (
t
he Department
)
under the
Children (Education and Services) National Law 2010
(NSW ) (
the
Act
) and
the
regulations made under it , namely the
Education and Care Services National Regulations 2011
(NSW)
(
the Regulations
).
A person who is to be the
“ Approved Provider ”
must be identified.
Second, the
P remises are
on
levels
one and two
of
an
eight -storey
building .
This means
that
the
P remises , not being
on
the ground floor,
have
no
actual , conventional
outdoor play area , which
may be thought to be
somewhat unusual for
a
childcare centre .
The first floor
has
what is described as a simulated outdoor area and the second floor has an area which is outdoors ,
in the sense that it is uncovered ,
although, obviously, it is walled in.
These two
aspects
play a role in this dispute.
Under the
AFL ,
Hogben
agreed to grant , and the tenants
agreed
to take, a
ten-year
lease of the
P remises ,
with two ten-year options,
with
the lease to
commenc e
“ on the Opening Date , or the date the tenant begins trading ” . Opening Date is
defined in the AFL as the later of the Landlord obtaining an Occupation Certificate
(
OC
)
in accordance with s 109C of the
Environmental Planning and Assessment Act 1979
(NSW) (
the EPA Act
) ,
[1]
or
the end of the Fitting Out period, which was a period of 20 weeks.
T o date,
as appears below,
t he
tenants
have n ot
traded
from the
P remises .
I suspect they never will.
Under cl 3.1
of the AFL
, the Landlord was obliged to use its reasonable endeavours to complete certain building work
(defined as
Landlord’s Works
) in accordance with a plan described as CD1231
(
the Plan
)
by the Handover Date, which was specified as 30 April 2014 .
For their part, the tenants agreed to fit out the
P remises
during a period of 20 weeks after the Handover Date
(
the
T
enants’
W
orks
).
Under cl
12 of the AFL , the tenants were
required to provide security for the performance of their obligations under the lease in the form of three payments ,
each of $27,940 ,
on specified dates.
T he first of these
was
paid.
At the time
of the
AFL,
Hogben
held
two Development
Consents (
DC
)
from the Kogarah City Council
(
the Council
)
( now subsumed by the
larger
Georges River Council ) . It had one
DC
for
the construction of the
building as a whole
(issued on 30
M ay 2011) ,
and another for the use of levels one and two as a childcare centre ,
which I will refer
to
as
the Childcare D
C
( originally issued o n 6 February 2013
and modified on
5 May 2015 ) .
Condition (1) of t he Childcare D C
includes
requires
the development
to
be implemented in accordance
with the Plan. It also includes , relevantly,
the following conditions:
(12)
Hours – Outdoor Play Areas
Outdoor play hours should not exceed a total of 2 hours any day and not before 7am and the external doors to the outdoor play area remain shut before 7am.
…
(13)
Number of Children – Outdoor Play Areas
During outdoor play no more than 12 children are to be outdoors on
each floor level at any one time.
(14)
No cooking of food without Council Approval
No cooking of food shall be undertaken within the premises without the prior written consent of Kogarah City Council.
On 16 July 2013, the Council issued a
C onstruction
C ertificate
(
CC
)
for
the intended eight storey building. It required construction to follow the plans and specifications which had been approved, which in the case of levels one and two ,
was the Plan.
In early January 2015, the tenants held an open day for the
C entre.
George gave evidence that parents who attended
the
o pen
d ay
commented on the fact that the simulated outdoor area was far too hot for their children, but nevertheless many registered their children, and some paid a registration fee
plus two weeks ’
care fees.
George
considered that the proposed centre would be able to accommodate 72 children, being 16 babies
(up to 2 years), 20 toddlers (2-3 years), and 36 kinder
children
(3-6 years). He says that by the end of January
2015 ,
all places had been filled and a waiting list was formed. There is in evidence a list of parents who, at or after the open day, registered their children and paid. There were apparently some who registered but did not pay, and some who expressed interest but neither registered nor paid. The list records that those who registered and paid (59) required a total of 169 care
days
per week
for their children .
Ultimately, the moneys had to be repaid because the
C entre did not open as anticipated.
On 12 February 2015, the Council issued an
interim
OC
to Hogben.
It did not
authorise the occupation of the
C entre, which at the time had not been completed. The
OC
stated that use and fit
out of the
C entre was subject to a separate
DC
and
CC .
Hogben took the position, which the tenants disputed, that the issue of this certificate was sufficient to bring about the arrival of the Opening Date, with the consequence that the lease had begun
(I draw no distinction between the equitable lease to which the AFL gave rise and the formal
lease
which was to be ex ecuted , because nothing turns on it).
On 18 May 2015, the Council issued to George an
interim OC
for the Centre
and certified that, subject to compliance with a list of outstanding matters, the building was suitable for use as a childcare centre under the
Building Code of Australia
(
BCA
) . The tenants took the position that this certificate caused the arrival of the Opening Date.
The
AFL
contains a dispute resolution provision (cl 14), under which the
parties
agreed that any disputes would be referred to an expert for determination.
The parties fell into dispute about the date
on which
the lease
had
commenced. George
took the stance
(correctly)
that
Hogben had not constructed
the
P remises
according to
the Plan , amongst others,
because , as built,
they had
floor to ceiling window frames, which
he
considered would prevent the
P remises from obtaining Service Approval , as
t here are child safety issues with floor to ceiling windows.
Nevertheless,
and no doubt because they were keen to start trading,
the tenants proceeded with the
T enants ’
W orks.
The
fit out
also deviated from
the Plan.
The dispute was referred to an experienced solicitor, who determined that the commencing date of the lease was 18 May 2015.
Hogben
challenged the expert determination and failed:
711 Hogben Pty Ltd v Tadros
[2016] NSWSC 697
(Stevenson J , 1/6/2016 ) .
Hogben sought leave to appeal . Leave
was refused:
711 Hogben Pty Ltd v Tadros
[2016] NSWCA 244
(Meagher and Leeming JJA , 1/9/2016 ) .
On 2 September 2016, Hogben sought to have Stevenson J disqualify himself from hearing the balance of the proceedings on the basis that comments which his Honour
had
made during the hearing of the challenge to the expert determination revealed apprehended bias. His Honour
(in m y
respectful
view
entirely correctly)
declined to disqualify himself and referred the matter for allocation of a hearing date:
711 Hogben Pty Ltd v Tadros; Tadros v 711 Hogben Pty Ltd
[2016] NSWSC 1238 (Stevenson J , 2/9/2016 ).
Hogben
brought another
challenge
to
the expert determination
and failed:
711 Hogben Pty Ltd v Tadros
[2016] NSWSC 1683 (Beech-Jones J
–
as his Honour then was
–
30/11/2016 ) .
In breach of the AFL, Hogben failed to construct according to the Plan.
Consequently , the tenants instituted proceedings seeking specific performance
by
Hogben
of its
obligation to carry out the work necessary to bring the
P remises into conformity with the Plan ,
and damages. The specific performance
and damages
proceedings became the tenants ’
cross claim in these proceedings.
Still, Hogben refused to build.
The matter was listed for hearing before me in April 2018.
Hogben took the position, as it does now, that Service Approval would not be given.
I considered that I should determine the tenants ’
claim for specific performance before determining their claim for damages, because
I considered that
the quantum of
any
damages would turn largely on the date (if any) from which they could trade as a childcare centre from the
P remises, and this would be known once the
P remises were completed
( if a decree for specific performance was mad e)
and
Service Approval
had been
obtained
(or not , as the case may be ) .
I expected that there would be certainty on that issue
in the near future .
My
expectation proved unrealistic.
On 10 May 2018, I delivered judgment :
711 Hogben Pty Ltd v Anthony Tadros
[2018] NSWSC 628
(
the first judgment
) .
It was not in dispute that the Landlord was, and at that time remained, in breach of the
AFL.
I found that it had refused to alter the
P remises
so as to
bring them into conformity with the Plan, and it remained steadfast in that refusal: see the first judgment at [14].
Hogben did not appeal.
O n 18 May 2018, I made the following orders:
Dismissal of proceedings
1. Proceedings against the First and Second Cross Defendants be dismissed.
2. First Cross Claimant's proceedings against the First, Second and Third Cross Defendants be dismissed.
Specific Performance
3. The Cross Claimants shall forthwith and in any event within 21 days of these orders, lodge an Application for Approval of such modified or amended development consent 313/2011/3, determined by Kogarah Council on 5 May 2015, as is necessary to permit Third Cross Defendant to construct the exterior walls and external structures of that part of the premises known as Level 1 7-11 Hogben Street, Kogarah ("the Premises"), as depicted in plan numbered CD1231, drawing number DA 01, dated July 2011, prepared by Cornerstone Design ("the Plan") as elaborated with necessary details agreed among the parties on or before close of business on 23 May 2018. The Third Cross Defendant shall endorse such Application immediately upon having received it from the Cross Claimants.
4. Within 48 hours of receiving Council approval referred to in Order 3 above, the Cross Claimants are to notify the Third Cross Defendant and provide a copy of that approval to it.
5.
In the event that
a Construction Certificate is required by Council, the Cross Defendant shall prepare drawings and submit them to the Cross Claimant for
lodgment
with Council with 14 days of that requirement being communicated to the Cross Defendant.
6. Within 48 hours of receiving Council Construction Certificate referred to in Order 5 above, the Cross Claimants are to notify the Third Cross Defendant and provide a copy of that certificate to it.
7. On or before the expiration of 90 days after the later of the date on which Council approval referred to in Order 3 is given, or the issue of a Construction Certificate described in Order 5, if required by Council, is obtained, the Third Cross Defendant is to do all things necessary to build the exterior walls and external structures of the Premises in accordance with the Plan (the "Building Works"), and is to restore the Premises otherwise to the condition existing immediately prior to commencement of the Building Works.
8. The Third Cross Defendant shall notify the Cross Claimants when the Building Works are complete and shall obtain certification of completion from an independent certifier. Within 14 days of service of the certification of completion, the Cross Claimants shall apply for the issuance of a Final Occupation Certificate by Georges River Council, and within 7 days from the issuance of the final occupation certificate the Second and Third Cross Claimants (or either of them) shall lodge an application for a Services Approval for:
a. a long day care for 36 children aged between 0-35 months on level 1 of the
Premises;
and
b. a long day care for 36 children aged between 36 months to pre - school age on level 2 of the Premises.
9.
Whether or not
the Cross Claimants obtain the Service Approval described in Order within 135 days of the date for the making of such Application for Approval, the
econd
and Third Cross Claimants claim against the Third Cross Defendant be listed for directions on or about the expiration of that period.
Costs
10. Costs of the Second and Third Cross Claimants, and the First Cross Defendant, which are not the subject of Orders made on 17 June 2016 (Hammerschlag J); 8 December 2016 (Beech-Jones J); and 20 April 2018 (Hammerschlag J), are reserved.
11. Liberty to apply with 3 days' written notice.
Hogben is referred to as the Third Cross
Defendant in the orders.
T he tenants ( the c ross
c laimants) did not comply with order 3 by lodging an application for a modified or amended Development Approval
within the time specified .
On 7 September 2018, I made the following orders:
1. I make the orders in the document entitled SHORT MINUTES OF ORDER which I have initialled, dated today's
date
and placed with the papers. These orders take the place of the orders made on 18th May 2018.
2. The proceedings are stood over to the directions list on 8th February 2019.
3. Parties have liberty to apply on three days' notice.
SHORT MINUTES OF ORDER:
Dismissal of proceedings:
1. Proceedings against the First and Second Cross Defendants be dismissed.
2. First Cross Claimant's proceedings against the First, Second and Third Cross Defendants be dismissed.
Specific Performance:
3. The Cross Claimants shall forthwith and in any event within 21 days of these orders, lodge an Application for Approval of such modified or amended development consent 313/2011/3, determined by Kogarah Council on 5 May 2015, as is necessary to permit Third Cross Defendant to construct the exterior walls and external structures of that part of the premises known as Level 1 7-11 Hogben Street, Kogarah ("the Premises"), as depicted in plan numbered CD1231, drawing number DA 01, dated July 2011, prepared by Cornerstone Design ("the Plan") as elaborated with necessary details agreed among the parties on or before close of business on 23 May 2018. The Third Cross Defendant shall endorse such Application immediately upon having received it from the Cross Claimants.
4. Within 48 hours of receiving Council approval referred to in Order 3 above, the Cross Claimants are to notify the Third Cross Defendant and provide a copy of that approval to it.
5.
In the event that
a Construction Certificate is required by Council, the Cross Defendant shall prepare drawings and submit them to the Cross Claimant for
lodgment
with Council with 14 days of that requirement being communicated to the Cross Defendant.
6. Within 48 hours of receiving Council Construction Certificate referred to in Order 5 above, the Cross Claimants are to notify the Third Cross Defendant and provide a copy of that certificate to it.
7. On or before the expiration of 90 days after the later of the date on which Council approval referred to in Order 3 is given, or the issue of a Construction Certificate described in Order 5, if required by Council, is obtained, the Third Cross Defendant is to do all things necessary to build the exterior walls and external structures of the Premises in accordance with the Plan (the "Building Works"), and is to restore the Premises otherwise to the condition existing immediately prior to commencement of the Building Works.
8. The Third Cross Defendant shall notify the Cross Claimants when the Building Works are complete and shall obtain certification of completion from an independent certifier. Within 14 days of service of the certification of completion, the Cross Claimants shall apply for the issuance of a Final Occupation Certificate by Georges River Council, and within 7 days from the issuance of the Final Occupation Certificate, the Second and Third Cross Claimants (or either of them) shall lodge an application for a Services Approval for:
(a) a long day care for 36 children aged between 0-35 months on level 1 of the
Premises;
and
(b) a long day care for 36 children aged between 36 months to pre - school age on level 2 of the Premises.
9.
Whether or not
the Cross Claimants obtain the Service Approval described in Order 8 within 135 days of the date for the making of such Application for Approval, the Second and Third Cross Claimants claim against the Third Cross Defendant be listed for directions on or about the expiration of that period.
9a. These orders take the place of the orders made on 18 May 2018.
Costs:
10. Costs are reserved.
11. Liberty to apply within 3 days' written notice.
The decree for specific performance required the
t enants to lodge a modification application for the Childcare D C .
On 25 October 2018, the
tenants
asked
Hogben
to sign a
m odification
a pplication.
On 8 February 2019, the
t enants relisted the matter because
Hogben
had not complied with the Court ’ s
o rders.
Orders were made that
Hogben
endorse and return to the tenants the
m odification
application
by 12 February 2019, together with a series of ancillary orders directed at
e nsuring completion of the building works necessary to conform with the Plan and achieving the issue of the necessary certificates and the lodgement of a Service Approval application.
On 12 February 2019,
Hogben
endorsed
the
m odification
a pplication, and it was lodged with the Council on 15 March 2019. However, on 16 August 2019,
Hogben
revoked its consent, although it provided it again on 13 September 2019. The Council approved the
m odification
a pplication on
7
November 2019
and notified George on 14 November 2019 .
It is not necessary for present purposes to recount the
detail of the
complex and meandering series of events which unfolded from that time until 8 October 2020 .
It suffices to say that o n
8 October 2020 ,
the Council issue d
Hogben
an
OC
for the Landlord ’ s
W orks which
had been carried out to bring the
P remises into conformity with the
P lan.
As
at
8 October 2020, there were still some works outstanding which were necessary
to be finished
before the Council would issue a
OC
for the fit out of the Premises. These were identified in a letter dated 1 December 2020 from the Council to George. Most of these were the responsibility of the tenants. Two items were, however, the responsibility of Hogben. They were
a requirement to strengthen balustrades to the outdoor play area on level two and provide an engineer ’ s certificate for the structural adequacy
and
a requirement to
provide
“ floor waste ”
( i.e.
a drain)
to the front balcony.
The OC for the fit out of the Premises
was provided by
Hogben
on 4 February 2021. The front balcony is not part of the tenancy.
The balcony
did have a floor waste, but this had apparently been covered over by the tenants.
Other
requirements by the Council were the tenants ’
responsibility.
T he outstanding
item s did not inhibit the tenants from applying for Service Approval , which they did by an application lodged on 12 October 2020. Nor did they inhibit Hogben
from
applying for a final
OC
for the fit out of the Premises, which it did on 15 November 2020.
Although
there were some things still to be done by Hogben, the tenants
concede
that Hogben had assuaged its breach by 8 October 2020.
On 1 December 2020, the Council
notified
Hogben , copying in George, that a series of different certificates needed to be provided and various items of outstanding works needed to be completed before a final
OC
could be issued for the fit
out of the
P remises.
The certificates
required
included
the
certificate of compliance for
“ critical radiant flux of the vinyl floor and synthetic grass ” . It is not in dispute that the tenants have not yet provided this certificate. The outstanding works are mostly of minor nature. In some cases, they turned out not to be necessary, and the remaining ones appear all to be minor and capable of ready completion. But they have not been completed.
The Council inspected the Premises on or about 1 February 2021. On 15 April 2021, the Council issued a list of 18 items that remained to be completed before the final
OC
could be issued. They are all the responsibility of the tenants.
George deals with these matters i n
his
affidavit sworn on 5 October 2021. Most, if not all,
items
appear to have been complied with
or satisfied .
On 12 August 2021,
Hogben ’ s solicitors wrote to the
t enants ’
solicitors asserting that the
t enants were in breach of their obligation to pay rent, which
began on 8 October 2020.
Hogben
claimed
that ,
as
at
8 August 2021, the outstanding rental would total $323,901.20.
On 10 September 2021,
Hogben
terminated the lease
and took possession of the Premises .
The
tenants
ac cept
that the lease has been terminated.
They may
seek relief against forfeiture
depending on the outcome of their damages claim ,
which may put them in a financial position to be able to carry on .
T he tenants accept
that the y
are
liable
for
rent from 8 October 2020
to 10 September 2021
(apart from
any further obligations under the lease, which may ne ed
to be discharged if relief against forfeiture is to be a possibility) .
On 9 November 2021, the tenants applied for leave to amend their cross claim, which leave was unsuccessfully opposed by Hogben:
711 Hogben Pty Ltd v Anthony Tadros
[2021] NSWSC 1463 (Stevenson J , 15/10/2021 ) .
Despite
termination of the lease, there has apparently been some measure of cooperation between the
parties , including
Hogben giving the tenants limited
access to the
P remises .
N o doubt
both sides
are
seeking to preserve
their
tactical position
in light of
these proceedings , including the possibility that there may be relief against forfeiture.
As recently as 2 August 2022,
the
Council notified
Hogben
of a list of outstanding items to be done prior to
the
issue of a final
OC . They include a certificate of compliance for the critical radiant flux of newly installed black floor tiles in the play area on the second level.
George gave evidence of being
“ entangled in a legal battle ”
with
Hogben
for almost seven years and of health difficulties he has encountered. He says that
all of
his savings and borrowed moneys have been spent on legal fees in these proceedings , a proposition I have no difficulty in accepting.
He asserts that his financial situation is directly attributable to
Hogben .
The evidence does not extend to disclosing the
actual
financial position of the tena nts
themselves ,
although there is nothing to suggest that they are in a better financial position than George, who is their guarantor.
By 10 December 2021, the tenants had not obtained an
OC
for the Premises, nor had they obtained Service Approval.
On that date, the matter came before Ball J who fixed the tenants ’
claim for damages before me to commence on 20 June 2022 .
No doubt his Honour contemplated that this would leave more than enough time for the tenants to achieve Service Approval
(or not) .
There were still some interlocutory steps to be completed. On 1 April 2022, his Honour heard a motion by George to vacate the hearing. His Honour vacated the hearing date and fixed it to commence on 25 July 2022. On 7 April 2022, I varied the hearing date to 29 August 2022.
On 10 August 2022, Hogben moved an application before Stevenson J for a freezing order restraining George from dealing with the proceeds of a property owned by him as joint tenant with his wife. The application failed. His Honour ordered that the costs of 10 August 2022 be paid by Hogben on the indemnity basis:
711 Hogben Pty Ltd v Tadros
[2022] NSWSC 1085 (Stevenson J).
This Hearing
The hearing
before me
took
three
and a half days.
The Court Book runs to over 2,600 pages.
George gave evidence ,
as did Mr Peter
Pan o poulos , who is the son of Hogben ’ s director. Both were cross examined.
There was something of an attack on George ’ s credit, but m y impression was that
he was
making an effort
to give
honest evidence , as was
Panopoulos ,
despite the fact that their relationship is very tense .
Each side called an expert in the field of the provision of childcare services.
The y gave
evidence in concurrent session.
The tenants called Mr John Wall
(
Mr Wall
) , who ,
as appears from the first judgment ,
gave evidence at the hearing before me in 2018.
He has many years ’
practical
experience in managing new start long
day-care
centres.
I considered him then to be impressive and my view has not changed .
He is undoubtedly passionate about his work.
Hogben called Ms Lynda Campbell
(
Ms Campbell
) ,
an early childhood education and care consultant. She too is
impressive.
She is more understated.
The
experts
produced a joint report.
Hogben also called :
Mr Benedict Jun- Hae
Youn ,
a forensic accountant, who was cross
examined
briefly ;
Mr Kim Jones,
an architect, whose
unchallenged
evidence included the results of a survey which establishes that the tenants did not construct the fit out in accordance with the Plan ;
and
Mr Allan Harriman, a fire safety engineer and building regulations consultant ,
who gave evidence about the state of the Premises and what is required to be done to put them in a proper state.
At the suggestion of
senior
counsel for Hogben , which was not opposed by
senior counsel for
the tenants, I visited the Premises in the presence of the parties on 7 September 2022.
The Law
At this point, it is appropriate to provide a brief statement of the applicable legal principles which apply to the tenants ’
claim for damages.
A plaintiff claiming to have suffered loss by reason of a defendant ’ s breach of contract bears the onus of proving the extent of that loss or damage:
Luna Park (NSW) Ltd v Tramways Advertising Pty Ltd
(1938) 61 CLR 286.
The general principle is that when assessing damages for breach of contract, the plaintiff is to be put in the position that he or she would have been in but for the breach, that is, the position if the contract had been performed:
Wenham v Ella
(1972) 127 CLR 454.
An opportunity may be lost because a party fails, in breach of its contractual obligations, to take steps which it is obliged to take. In such a case,
in order to
discharge its onus on the issue of causation, the plaintiff must establish (on the probabilities) that had there been no breach, the steps concerned would have been taken ,
and that the opportunity to gain a financial benefit (or avoid a financial detriment) was thereby lost:
Daniels v Anderson
(1995) 37 NSWLR 438 ,
529.
Whether the breach caused loss is to be approached in a practical or common-sense way:
March v E & MH
Stramare
Pty Ltd
(1991) 171 CLR 506.
The assessment of damages for a loss which depends on future chances or possibility of benefit may be fraught with difficulty and attended by uncertainty, but the mere fact that damages cannot be assessed without difficulty and uncertainty does not relieve a Court from the responsibility of attempting to assess them as best it can.
Where there has been an actual loss of some sort ,
the common law does not permit difficulties in estimating the loss in monetary terms to defeat an award of damages :
Kizbeau
Pty Ltd v WG & B Pty Ltd
(1995) 184 CLR 281.
A lost commercial advantage or opportunity is a compensable loss even where there is a less than 50 per cent likelihood that the commercial advantage will be realised.
Damages are to be assessed by reference to the probabilities or possibilities of what would have happened:
Commonwealth v Amann Aviation Pty Ltd
(1991) 174 CLR 64 ,
125 ;
Sellars v Adelaide Petroleum NL &
Ors
(1994) 179 CLR 332 ,
349 .
Where future or hypothetical events must be taken account of in assessing damages and proof of them is necessarily unattainable, the Court assesses the degree of probability that an event would have occurred, or might occur, and adjusts its award of damages to reflect that degree of probability:
Malec
v JC Hutton Pty Ltd
(1990) 169 CLR 638 ,
643;
Sellars v Adelaide Petroleum NL &
Ors
(1994) 179 CLR 332 ,
350.
Different standards apply to proof of damage from those that are involved in the assessment of damages.
The general standard of proof applies with respect
to the issue of causation and whether a party has suffered loss or damage:
Tabet
v
Gett
(2010) 240 CLR 537 , 585 .
In relation to the assessment of damages,
“ the hypothetical may be conjectured ” :
Malec
v JC Hutton Pty Ltd
(1990) 169 CLR 638 ,
643 .
See also:
Badenach
v Calvert
(2016) 257 CLR 440 at [38]-[41].
In
Tabet
v
Gett
at 587,
Kiefel
J said,
“ [r] esort
to the language of
‘ chance ’
cannot displace the analysis necessary for the determination of the issue of causation of damage ” .
Th e
T enants’
C ase
The tenants
say
that had
Hogben
buil t
in accordance with the Plan,
they would have commenced trading
at
the Centre by July 2015.
For this to have happened, they would have needed Service Approval, which they claim would have been
obtained .
They argue that the damages
they have suffered by Hogben ’ s breach
are:
their lost profits for the entire period from May 2015 to date on the basis that
the
breach
caused them to be
unable to trade throughout the
period;
their
rental
liability
from 8 October 2020 (when rent first became payable) to
10 September 2021 on the
footing
that Hogben ’ s breach rendered them unable to use the Premises .
They accept, however that their rental liability (from 2015) is to be
taken into account
in calculating their
lost profits ;
and
their liability for rent after 10 September 2021, which they accept will be the subject of an entitlement by Hogben to set-off against its liability to them for damages
(and which must in any event be effectively paid for them to achieve relief against forfeiture).
Their claim
for lost profit
(or, more accurately, for loss of the opportunity to make a profit)
is set out in the following table
(Figure 1) (13469, xlsx) .
The Landlord’s
Answers
First,
Hogben
disputes
that
the
t enants have suffered loss by
its
breach
because , it says,
they
have not proved that Service Approval would have been given.
To the extent that it is relevant, they say that Service Approval would not be given now.
Second, Hogben argues
even if
the
tenants
had
achieved
Service Approval in 2015
(or were to get it now) ,
they
would have
traded (or
will
trade)
at a loss .
Third ,
Hogben argues that even if the tenants lost an opportunity to earn profits,
their
claimed
loss
should be heavily discounted
to
take into account
the vicissitudes that might adversely
have
affected their prospects of making profits , which
Hogben argues should
include the possibility that they would not have achieved Service Approval.
Finally, Hogben argues that ,
for two periods,
it did not cause
the
delay in the tenants being able to trade. These
are the
periods between 24 April 2019 ,
the
last day for the approval of the modification application ,
and 16 August 2019 ,
when George first took steps to follow it up (114 days) ,
and between 8 October 2020 and the present date, given that the tenants have not obtained an
OC
and
S ervice
A pproval. I observe that
Hogben articulated the issues for determination
in its comprehensive written closing submissions. It did not identify a failure by the tenants to mitigate
as an issue , although in the body of the submissions it did submit in the alternative that for these periods the tenants ’
failure to take certain steps broke the chain of causation between its breach and them suffering loss
based on the same facts.
The tenants did not
favour
the Court with written closing submissions.
Consideration
Where the damage suffered is loss of a commercial opportunity, t he line between things which need to be proved as being causative of damage and things which are merely factors relevant to the evaluation of
the
opportunity may not always be bright :
cf
Silverbrook
Research Pty Ltd v Lindley
[2010] NSWCA 357.
This is a case in point. It is common cause that without Service Approval the tenants could not lawfully trade.
On one view, the lease itself provided the commercial opportunity to trade, the value of which was dependant amongst others on obtaining Service Approval, the prospect of which is just one of the multiple factors to be assessed in evaluating the commercial opportunity.
This approach would not require the tenants to prove on the balance of probabilities that they would have obtained Service Approval. In my view, this approach might
in
t his case
be described as resorting to the language of chance and displacing the analysis necessary for the determination of the issue of causation or damage: see
Daniels v Anderson
(1995) 37 NSWLR 438 at 529;
Tabet
v
Gett
(2010) 240 CLR 537 .
Hence, the approach I have taken,
which I consider to be more in accordance with the approach taken by the High Court in
Tabet
v
Gett
,
is that
obtaining
Service Approval is a step which the tenants must show they would have taken to discharge the onus of proving loss, to which the balance of probabilities applies as opposed to the evaluation of the opportunity to trade which they had ,
provided they achieved Service Approval.
I record that on the former approach the result would
not
be any different because had I assessed the opportunity on the basis that it included an evaluation of the
tenants ’
prospects of obtaining Service Approval, I would have adopted the same percentage I have adopted in assessing the damage they have suffered.
There is a third possible approach ,
which was urged upon me by
Hogben , namely ,
to require the tenants to prove on the probabilities that they would have got Service Approval, and then
to
evaluate the commercial opportunity by including a discount attributable to the possibility that they would not have obtained Service Approval. I consider this to be
circular,
incorrect
and not in accordance with the authorities.
Service Approval
Two questions
require answers :
w ould the tenants have obtained Service Approval and started trading in 2015?
w ill
the tenants obtain Service Approval ?
As I have said,
t o establish that Hogben ’ s breach caused them loss, the tenants must prove on the probabilities that the answer to the first question is in the affirmative.
For the reasons which follow, I am
persuaded
that it is more probable than not
that the tenants would have obtained Service Approval in 2015
and started trading
in 2015, although later than July . However,
I am not satisfied that it is
more probable than not
that they would now obtain
Service Approval .
I consider it to be unlikely that they will.
It is common cause that it is a prerequisite for the grant of Service Approval that there be an
OC
for the Premises.
The EPA Act and the
Environmental Planning and Assessment Regulation 2021
(NSW) (
EPA
Regulations
)
govern the issue of
DCs ,
CCs and OCs . The
EPA Regulations
prescribe
that it must be a
condition o f
a
DC
that building works must be carried out in accordance with the
BCA . A
CC
must be issued before building work under a
DC
is carried out.
Upon
the satisfactory completion of all works, an
OC is
issued by a Principal Certifying Authority (this can be the Council or an accredited certifier) which states that the building is suitable for use in accordance with its classification under the BCA.
It is not in dispute that the Council cannot lawfully issue an
OC
for building work
which was carried out other than in accordance with a
CC . However,
such construction may be the subject of a Building Information Certificate (
BIC
) under which, in effect, the Council certifies that it does not intend to
take action
with respect to the non-compliance.
Division 6.7 of the EPA Act makes provision for the issue of a BIC.
A BIC operates to prevent a council from
taking action
for 7 years
in relation to the non-compliance. It is difficult to imagine that if the Council issued a BIC in this case, it would not issue another one, or that it would then
take action .
It is not in issue that
if all other requirements were satisfied,
an
CC
in relation to the fit out
could be given if the Council also gave a BIC.
Hogben ’ s primary submission is that
S ervice
A pproval cannot be granted
for the Centre
because the tenants constructed the fit out other than in accordance with the Plan
( read with the BCA )
so
that an
OC
cannot be issued ,
with the consequence that Service Approval cannot be obtained.
M r Harriman
identified
a number of
non-compliances
of the Premises,
including that the ceiling height is less than that required by the BCA and the layout of each floor is
“ vastly different ”
to the Plan. He observed that the ceiling panels
in the outdoor area are designed for internal spaces and are likely to collapse over time. He opined that the defects/divergences need to be rectified, a modified
DC
is needed because of changes to the floor layout ,
and that it will take 15
to
21 weeks for the tenants to obtain
a
modified
DC ,
a
BIC
and
a CC ,
which includes carrying out all of the building works necessary to rectify the
P remises.
As appears later, a period should be factored into the assessment of when they would have started to trade.
Mr Harriman was not available to be cross
examined at the hearing. I was informed that counsel for both sides
had
agreed that no submission
would
be made that anything turned on the tenants ’
failure to cross
examine.
Mr Harriman ’ s
own
evidence
undermines Hogben ’ s
position . Mr Harriman did not suggest that a BIC cannot be
(or would not have been)
obtained. Indeed, it is implicit in his evidence that it can
and would
have been
obtained .
Consistent with this
conclusion, it is to be observed that as late as 2 August
2022 ,
the Council informed Hogben that it would require a BIC application to be lodged and that application to be determined prior to the issue of an OC. The tenants lodged a BIC application with Hogben ’ s authority shortly thereafter. There is no suggestion that the application w ould not succeed .
At the hearing in 2018, Mr Wall gave evidence that
had the Premises been constructed in accordance with the Plan,
Service Approval would have been obtained so that the tenants would have been able to trade by July 2015.
There is every reason to conclude that had it been evident in 2015 that the steps identified by Mr Harriman were necessary to obtain Service Approval, the tenants would have taken them (Mr Harriman did not cost the steps). The tenants were already invested in the Centre, and George had not spent all his money on
needless
court cases.
At that hearing,
Hogben called
its own
expert,
Dr Abbey, whose opinion was that there would be issues to be resolved
but , importantly,
Dr Abbey did not
hold the view that Service Approval would not be given, even if certain requirements of the Department needed to be the subject of a waiver :
see
711 Hogben Pty Ltd v Anthony Tadros
[2018] NSWSC 628
at [26]. Sections 87 and 90 of the Act make provision for the grant of waivers.
One respect
on
which
Dr Abbey
and Mr Wall agreed
was
that
the
natural elements in the simulated outdoor space on level one and the outdoor space on level two did not meet the requirements of the
R egulations ,
because the children would not have opportunities to explore and experience the natural environment ( e.g.
plants, water, natural elements and vegetation).
This is a reference
to
reg
113, which provides:
113 Outdoor
space
—natural environment
The approved provider of a centre-based service must ensure that the outdoor spaces provided at the education and care service premises allow children to explore and experience the natural environment.
However, Mr Wall gave evidence that in his experience it is the interpretation of the visiting inspector from the Department
which counts ,
that
inspectors would provide recommendations on improvements to meet regulation s
and standards ,
and that this inadequacy would easily be fixed. He gave evidence that in his experience inspectors would provide direction and support and are always please d
to help the success of a new application.
I preferred Mr Wall ’ s evidence to that of Dr Abbey ’ s
on the question of whether Service Approval would have been achieved in 2015 .
Ms Campbell was asked to opine whether the Premises in their present configuration would have been likely to have received Service Approval under the
R egulations as they were
at
20 January 2015 ,
when an application for Service Approval was first lodged.
In her report dated 15 July 2022, her
view
is
that the Premises would not have been likely to be approved because
the
R egulations
were the same then as they are now and the Premises would have been non-compliant with respect to three of them, being
regs
97,
108
and
113 .
I observe that her opinion assume s
an
81-place
operation ,
but I infer
that
her view would remain the same
for a 61-place operation .
Regulation 113 has been referred to above.
Regulation 97(1) requires an operator to have specified emergency and evacuation procedures. This re quirement
can immediately be put to one side because nothing stood in the way of the tenants having the necessary emergency and evacuation procedures in place, which I am confident they would have
had
at that time
(and will do if they get relief against forfeiture and intend to trade) .
Regulation 108(2)
of the Regulations
provides:
108 Space requirements—outdoor space
…
(2) The approved provider of an education and care service must ensure that, for each child being educated and cared for by the service, the education and care service premises has at least 7 square metres of unencumbered outdoor space.
With respect to the present, Mr Wall and Ms Campbell agree that :
there are significant building faults that need to be rectified including the provision of more natural elements in the outdoor play areas; repair of all fixtures and consideration of lines of sight from the manager office and between play areas before another service approval application is made.
current configuration of the proposed outdoor area on level one would need a waiver by the Department of Education to be able to be considered as unencumbered outdoor space.
the service would need to consider impact of neighbouring units, above the outdoor play area, on safety and privacy of children playing outdoors on level 2 which the Department of Education (the NSW Regulatory Authority) would check during the service approval process.
t he service would also need to obtain
age appropriate
equipment to be used in the case of an emergency evacuation before a service approval would be considered.
t he current state of repair of the premises and child play resources/equipment is not of high quality, having been at the site for at least 5 years, especially the
outdoor play equipment on level two, and currently poses a risk to child health and safety.
Ms Campbell t akes
the view that the provision of fixtures and equipment was done as cheaply as possible, for example the cots were second-hand. She agree s
with Mr Harriman ’ s views of what repairs
are
needed.
Mr Wall and Ms Campbell
agree that a substantial amount of money ,
in the order of $350,000 ,
is required to be spent by the approved provider before a Service Approval c an
be lodged.
According to George, he does not have the money to meet this expense. His only source will be out of any verdict he might obtain in this case.
Mr Wall maintain s
his opinion that all matters which will stop a Service Approval being granted can be repaired,
renovated
or replaced and meet all regulations and
N ational
Q uality
S tandards for the purpose of a Service Approval being granted.
He somewhat forcefully expressed the view that the Centre would, if the said sum of money were spent, be able to meet these requirements and be a top-class facility. Ms Campbell disagreed.
Ms Campbell
place s
emphasis on the
lack of
outdoor space
and natural elements of
the Premises. She dr ew
attention to a publication by the NSW Government called Childcare Planning Guideline September 2021 (first published in August 2017)
(
the Guideline
) . The
G uideline contains the following in relation to simulated outdoor environments
(which applies to level one) :
Simulated outdoor environments
Proponents should aim to provide the requisite amount of unencumbered outdoor space in all development applications.
A service approval will only be granted in exceptional circumstances when outdoor space requirements are not met. For an exemption to be granted, the preferred alternate solution is that indoor space be designed as a simulated outdoor environment.
Simulated outdoor space must be provided in addition to indoor space and cannot be counted twice when calculating areas.
Simulated outdoor environments are internal spaces that have all the features and experiences and qualities of an outdoor space. They should promote the same learning outcomes that are developed during outdoor play. Simulated outdoor environments should have:
•
more access to natural light and ventilation than required for an internal space through large windows, glass doors and panels to enable views of trees, views of the sky and clouds and movement outside the facility
•
skylights to give a sense of the external climate
•
a combination of different floor types and textures, including wooden decking, pebbles, mounds, ridges, grass,
bark
and artificial grass, to mimic the uneven surfaces of an outdoor environment
•
sand pits and water play areas
•
furniture made of logs and stepping logs
•
dense indoor planting and green vegetated walls
•
climbing frames, walking and/or bike tracks
•
vegetable gardens and gardening tubs.
She drew attention to the fact that the
G uideline describes a simulated outdoor play area as having all the features and
experience
of an outdoor
space ,
including waterplay areas and vegetable gardens ,
and that only
in
exceptional circumstances will Service Approval be granted where these requirements are not met.
Ms Campbell
place s
emphasis on the
restrictions imposed by the
C hildcare DC on
the number of children and times for outdoor play hours. She expressed the opinion that the
D epartment would consider there to be insufficient time for physical activity ,
which would further limit the number of children it would approve to attend the
C entre at any one time.
I interpolate that Mr Wall agree s
that in this respect the Premises are far from ideal.
Ms Campbell
drew attention to the limitation in the
C hildcare DC that there be no cooking of food without Council approval. I interpolate that Mr Wall agree s
that this would need to be addressed.
I prefer Mr Wall ’ s evidence to that of Ms Campbell when it comes to 2015, but I prefer Ms Campbell ’ s evidence when it comes to the present.
T his is predominantly because the climate for obtaining Service Approval in 2015 was far more benign than it is now. There has been profound change.
Coupled with this, there has been
an
increase in the supply of childcare places since then.
In their joint report, Mr Wall and Ms Campbell agreed that since 2016
to
2017:
a lot of best practices in relation to protection around children have been updated. For example, the supervision of children coming out of a lift is different and a lot of the doors at the premises do not meet a now applicable standard that a director’s office
have
a full glass window.
Mr Wall gave oral evidence that practices have changed.
He
gave evidence (which I accept) that 2015 was a completely different environment to the present. He says he was delivering 20 to 30 childcare centres a year in 2015, project managing them through to successful Service Approval, whereas last year he did only five, and this year he might do five or six
(this aspect plays a part later in connection with the question of the demand for childcare centres in Kogarah) .
The interpretation of
the
National Quality Standards
have
changed. Since 2015, from a design point of view, practices in relation to baby change areas, door s , visibility,
supervision
and the way that childcare centres are managed, including walking from room to room and from one activity to another, have changed.
Mr Wall
gave evidence that d epartments are a lot
“ more stricter ” . There is
now
a greater emphasis on child safety.
He
gave evidence that what they were doing in 2014
and
2015
with outdoor playgrounds
was nowhere near what they were doing now.
In my view, the open day revealed substantial demand in 2015 for the
C entre , a factor which would have enhanced the prospects of getting Service Approval .
It is beyond doubt that obtaining Service Approval in 2015 would have bee n much
easier than it is now. This
adds
weight to Ms Campbell ’ s opinion that Service Approval is unlikely to be granted now with respect to the Premises.
It is to be emphasised that this does not mean that it is not possible.
In their joint report, Mr Wall and Ms Campbell agree that the current configuration of the outdoor area on level one would need a waiver by the
D epartment to be able to be considered unencumbered outdoor space. They differ on whether a waiver would be given now. Mr Wall says it would be. Ms Campbell says it would not be.
One
consequence of the
finding that the tenants would have achieved Service Approval in 2015 but are unlikely to do so now is that they have proved that
Hogben ’ s breach caused them to lose the opportunity to earn a profit
for the whole period over which they claim they would have traded .
A
second
consequence is that
no
issue
arises in connection with
the tenants ’
alleged failure
(about which I make no finding)
to take steps between 24 April
and
16 August 2019 ,
and 8
October 2020
to date ,
because those steps, even if taken, would not have resulted in a Service Approval .
Hogben
took the point
that currently neither the tenants nor George are an Approved Provider, and the tenants have no t
identified any that could operate a childcare centre. However, George ’ s daughter had a provider approval ,
which was issued
on 1 September
2009
and
which was apparently current in 2015 . This issue does not impact the position in 2015.
Lost Profit
I turn to the question of the value of the lost opportunity.
It is an exercise fraught with difficulty ,
attended by uncertainty ,
and
that
requires the hypothetical to be conjectured , but these difficulties
are not permitted to defeat the estimation of the tenants ’
loss in monetary terms.
Whilst
I have taken
all of
the arguments into account , I have not restated them. Whilst I have had regard to
all of
the evidence, I have not attempted to restate it.
The
tenants
were not prepared to
accept
that there should be any allowance for vicissitudes or risks associated with trading
which might adversely have
affected profitability .
They plumped for their full claim and nothing else.
I reject their approach.
For the reasons which follow, their full claim
is to be substantially
discounted.
Plainly, there will always be a relationship between price and demand.
One would expect the tenants acting rationally to reduce prices if there
wa s insufficient demand. On their claim, there is scope to do this and
still remain
profitable.
The tenants relied on Mr Wall ’ s evidence.
Hogben relied on Ms Campbell ’ s and Mr
Youn ’ s
evidence.
Mr
Youn
produced calculations based on assumptions supported by Ms Campbell.
I regard Mr Wall ’ s
opinions
as somewhat optimistic, and Ms Campbell ’ s as somewhat pessimistic.
Whilst i t is
no doubt
possible that the tenants could achieve Mr Wall ’ s projections, I consider that th at
possibility
should be subject to a
large
discount to reflect the
possibilities
that
his daily fees
may not be achieved, the occupancy rates may be lower than
h e predicts,
and the
expenses may be higher , and to take account of other vicissitudes which may impact adversely on profitable trading .
There will inevitably be some non-recovery of fees payable.
The integers in the tenants ’
calculation of profit (see Figure 1) which are
heavily
in dispute are:
daily fee; and
occupancy rate.
There
are
other differences.
The tenants ’
calculations
a re based on the
C entre being open five days a week, 52 weeks a year. Ms Campbell ’ s view is that
most centres close over the Christmas period and parents are not charged.
Mr Wall had a different view.
According to him, he did not have a shutdown period for his own centres.
I think
it is more probable that the tenants would use every trading day available (especially given the high rent they would be paying
–
this is referred to later).
There
appeared to be initial
disagreement about
the
staffing levels
which Mr Wall assumed, but during their evidence in concurrent session
he and Ms Campbell
appeared to reach consensus that Mr Wall ’ s assumption on staff levels was justified , perhaps with the caveat that Ms Campbell thought a higher staff level might be required to make the offering high-end .
The discount will recognise the possibility than an additional teacher
might
be required.
There
is
disagreement on
how long it would have taken to get the
C entre off the ground. The handover date was 26 May 2014, and a fitting out period of 20 weeks was provided for.
Hogben argued that after 8 October 2020, the tenants acted without any haste and the tenants ’
work remained incomplete and uncertified, and that the Court should find that the tenants would only have been in a position to trade at 20 February 2017, being the sum of the days from 8 October 2020 to the end of the hearing (693 days), 144 days required to rectify the Premises in accordance with Mr Harriman ’ s evidence, 14 days to make a service approval application, 90 days for the Department to deal with a service approval application, and a lead time of 60 days to hire staff.
I do not accept Hogben ’ s position.
The delay to 8 October 2020 was almost exclusively that of Hogben. A potentially valuable period of trading had been lost due to its conduct, and George had spent
lots
of money, amongst others, fighting
this case.
But it is a fact that the tenants have constructed the fit out not in accordance with the Plan, and to have fixed this would have taken between 15 and 21 weeks. I think it is fair to assume that, had their application for
S ervice
A pproval required this work to be done , the tenant s
would have attempted to have had it
done expeditiously.
I think it is fair to adopt a date somewhere around the middle
of Mr Harriman ’ s estimate . I consider that the calculation should be done on the footing that the tenants would
have commenced trading by 18 November 2015 , being after 18 weeks , rather than the middle of July .
The same period could have been used as lead time , hiring staff, etc .
Mr Wall varied his calculations just before the hearing to reduce the number of places to 61 from 72, which he originally assumed, to
take into account
that rent would increase from year to year under the lease and the increase in staff costs. He was criticised for the lateness of these adjustments, but nothing, in my opinion, turns on it.
Various other criticisms were directed at Mr Wall, such as an earlier reluctance to make concessions. I consider none of them to be justified.
If a waiver of reg 108
of the Regulations
is not obtained ,
the maximum number of places would be 34 and only level two could operate. It is not in dispute that if only 34 places were available, the tenants would suffer no loss. As I have held earlier, I consider that a waiver would have been obtained in 2015 but would
likely
not now be obtained. I consider the assumption of 61 places to be justified.
Mr Wall support s
the following daily fees
for the financial years each ending on 30 June
the following year , except for 2023 where the calculations end on 31 December
2023 :
2016
2017
2018
2019
2020
2021
2022
2023
to 31 December
$115
$121
$126
$131
$136
$141
$146
$151
Mr Wall ’ s fees do not distinguish between fees that would apply to the different age groups catered for.
Ms Campbell takes issue with Mr Wall ’ s fees. She distinguishes between age groups. In her view, the
C entre would have been capable of generating the following daily fees. The fees which she supports for 2 – 3 year
olds
are about halfway between those she supports for 0-2 year
olds
and 3-5 year
olds . I consider the differences to be immaterial. The following table is the fees for the
2-3 year
olds .
2016
2017
2018
2019
2020
2021
2022
2023
to 31 December
$78
$80
$85
$97.50
$105
$112.50
$120
No figure provided
Mr Wall relied on a
Child care
N eeds
A ssessment
(
NA
)
produced by Business Geographics, an
organisation
which describes itself as a specialist in childcare location services.
The NA includes a supply analysis for long care day centres in the Kogarah catchment area which supplies 1,177 long day care places
at 24 centres . Current fees range from $98 per day to $147 per day.
The average is $118 per day.
Added to this, s ince 2016, there has been an increase of 63.7% in the supply of childcare places
(although there also has been an increase in demand, but not quite to this level).
N egative features of the Premises include :
t hey are
in a mixed-use apartment building surrounded on all four sides by other buildings with no real outdoor environment . As parents at the open day remarked, the level one simulated outdoor area is hot (although that was by all accounts in mid-summer).
there is some risk of hazard from falling items.
privacy is not optimal.
the
restrictions on the numbers of children permitted to play in the
“ outdoor areas ” , with no actual outdoor area on level one (where the under three-year- olds
would be).
t ravel between the two levels is by lift, there being no internal staircase.
But then again, the Premises are in the vicinity of a major hospital , and in a bustling part of Sydney .
The ceilings give the impression of being low. This may be a function of the fact that their height does not comply with the BCA, but this issue can be resolved.
It will be readily observed that for the 2023 Financial Year, the fees Mr Wall supports are more than the most expensive charged in the whole catchment area. His support for these fees is based on his opinion that, if it operated, the Centre would be of such quality as to attract a premium fee ,
and that there is high demand in the area.
I think it is appropriate to move, then, to Mr Wall ’ s daily rates for 2022 and 2023, which are $146 and $151 respectively.
The discount to be applied will need to recognise that the consumers may not consider fees at this rate to
be a reflection of
the quality
and amenities of the Premises even if additional work
i s done , as well as the possibility that these rates may negatively affect demand . One of the examples of a high-end childcare centre in Kogarah is Rise and Shine Early Learning Centre, an impressive place going by the photograph in evidence.
I consider it unlikely that the
C entre will be able to match this facility
so as to
attract its highest rate .
Ms Campbell ’ s daily rate for 2022 is $120. I think this rate errs on the modest side.
It is common cause that it will necessitate the tenants spending about $350,000 on the Premises before a
potentially successful
Service Approval application could be lodged.
As mentioned earlier, Ms Campbell ’ s view is that the fixtures and equipment are cheap. It is reasonable to assume that
between 2015 and the end of 2022, expenditure of this order would have been necessary to keep the
C entre operating at the level
approaching that
postulated by Mr Wall.
The amount
should be added to the
expenses
column in the tenants ’
profit calculations.
Mr Wall assumes a $5 increase
in fees
every year. Ms Campbell ’ s rates of increase are in fact higher.
Mr Wall ’ s rate of increase may be confidently adopted.
Mr Wall and Ms Campbell
also
differed on the achievable occupancy rate.
Mr Wall ’ s assumed
occupancy
rates are:
2016
2017
2018
2019
2020
2021
2022
2023
to 31 December
67.08
89.50
89.50
89.50
89.50
89.50
89.50
94.33
Ms Campbell ’ s
assumed occupancy
rates ar e much
lower:
2016
2017
2018
2019
2020
2021
2022
2023
to 31 December
60
70
70
70
63
50
65
-
I consider
Mr Wall ’ s rates to be optimistic, and Ms Campbell ’ s to be pessimistic . T he discount must recognise the distinct possibility that Mr Wall ’ s occupancy rates will not be achieved, particularly at the daily rates he postulates.
The experts agreed that the restrictions on cooking
will have to be addressed. If food
has to
be brought in, expenses will increase.
It is not necessary to consider whether there is any substantive difference between
“ cooking ”
and food preparation. Either way, t he discount should recognise he possibility, albeit in my view a slim one, that condition 14 of the Childcare DC will not be changed.
I observe that Mr
Youn
extracted information from a report published by IBISWorld, an industry research organisation, entitled
“ Childcare Services in Australia ” ,
which indicates that over the period of 2017 to 2023 the various integers (expressed as a percentage to revenue) and profit conclusion in
Mr
Wall ’ s calculations
bear the following relationship to the industry average:
Integer
Tenants
IBISWorld
Staff costs
52.72%
52.00%
Rent
18.26%
9.38%
Purchases
4.86%
6.39%
Other costs
7.07%
19.75%
Profit
17.10%
7.75%
It will be observed that there is
a material
differential on some of the integers,
in particular with
respect to the rent, which is the
tenants ’
only fixed cost.
The rent payable under the lease is much higher than the industry average.
Senior counsel for Hogben described the rent as
“ way above the odds in this industry ”
and agreed with the description of the lease as a
bad bargain
for tenants .
This is a factor which I consider should contribute to the discount because it is a constant which the tenants w ould
not
have been
able to improve.
In its closing written outline, Hogben submitted that if the Court did not reject the entirety of the tenants ’
loss of chance case there should be a very substantial discount to any damages,
“ and certainly not less than 50 per cent (and likely closer to 80 or 90 per cent) ” ,
on the basis that the Court can have no satisfaction that the tenants are likely to achieve (and ever would have achieved) an OC and Service Approval, and it is most unlikely the Centre will, or would have ever, operated profitably.
In my view,
recognising that precision is impossible,
the discount that should be applied is 50 per cent ,
which
is
hefty,
but which
reflects the Court ’ s view
of
the tenants ’
chance s
of making the profit s
they claim they have lost.
If I had approached the matter by including ,
in the assessment of their percentage chance of making the profits they could have made, the
tenants ’
prospects obtaining approval in 2015, I would still have applied the same percentage.
The calculation is to be done
on the basis that the starting day is 18 November 2015, but with rent liability to commence from 15 July 2015.
The
following numbers are rounded down in favour of Hogben, and to
make due
allowance for inaccuracies caused by my arithmetical
inadequacies and the complexities involved in adapting
the
spreadsheet s
provided by the experts .
A djusting the starting date
to 18 November 2015 ,
but leaving rent being paid from 15 July 2015,
total revenue on Figure 1 is reduced to
the order of
$13,35 0 , 000 , which yields a profit of $2,16 0,000 , of which 50 per cent is $1,08 0,000 .
In my opinion, the
commercial
opportunity which the tenants lost
by reason of Hogben ’ s breach
should be assessed at $1,0 8 0,000, less $350,000 , that is at $730,000 .
As
a
rough safety check, adopting
the
start date of 18 November 2015
and the top fee charged by
Rise and Shine Early Learning Centre
in 2023
of $140
(reducing it by $5 for each preceding year) ,
and reducing Mr Wall ’ s occupancy rate of 94.33 per cent for 2023 to 89.5 per cent (being the rate adopted by him from 2017 and 2022) ,
revenue
is
of the order of
$12,20 0 , 000 , with
profit of $1,02 0 , 000 .
As another
rough safety check , adopting
the
start date of 18 November 2015
and
revenue of $13,35 0 , 000
yields $1,030,000 if
the industry
wide
rate of revenue to profit of 7.75 per cent is applied.
Conclusion
There will be a verdict for the
tenants (the
second and third cross claimants )
against
Hogben ( the third cross defendant )
for $ 730 ,000.
I will hear the parties on costs if necessary. If after ten days the parties have not reached agreement on costs, they are to exchange position papers setting out their position s
on costs, with brief reasons, and to send them to my Associate.
I will stand the matter over to a convenient date to give the
parties
an opportunity to draw to my attention any issues that remain to be dealt with, including any application for relief against forfeiture
and, if necessary, to deal with costs.
Endnote
1.
Now covered by ss 6.3, 6.4 and 6.16 of the EPA Act.
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Decision last updated:
19 September 2022
Official source: https://www.caselaw.nsw.gov.au/decision/183536d0341e5a08567b261e