OLIVER HUME PROPERTY FUNDS (HACKHAM) PTY LTD v YAS PROPERTY AND DEVELOPMENT PTY LTD [2026] SASC 95
Applicant: OLIVER HUME PROPERTY FUNDS (HACKHAM) PTY LTD Counsel: MR D
WHITINGTON KC WITH MR L WICKS AND MR N DAY - Solicitor: JOHNSON WINTER SLATTERY
Respondents: YAS PROPERTY AND DEVELOPMENT PTY LTD Counsel: MR T DUGGAN KC
AND MR I ROBERTSON-CLARKE SC WITH MS E KEYNES - Solicitor: COWELL CLARKE
Hearing Date/s: 04/06/2026, 05/06/2026, 11/06/2026, 15/06/2026
File No/s: CIV-26-006365
B
SUPREME COURT OF SOUTH AUSTRALIA
(Civil: Application)
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply
to this judgment. The onus remains on any person using material in the judgment to ensure that the intended use of that material does not breach
any such order or provision. Further enquiries may be directed to the Registry of the Court in which it was generated.
OLIVER HUME PROPERTY FUNDS (HACKHAM) PTY LTD v
YAS PROPERTY AND DEVELOPMENT PTY LTD
[2026] SASC 95
Decision of the Honourable Justice Gray
22 June 2026
EQUITY - EQUITABLE REMEDIES - INJUNCTIONS - INTERLOCUTORY
INJUNCTIONS
EQUITY - EQUITABLE REMEDIES - INJUNCTIONS - INTERLOCUTORY
INJUNCTIONS - RELEVANT CONSIDERATIONS - BALANCE OF
CONVENIENCE GENERALLY
EQUITY - EQUITABLE REMEDIES - INJUNCTIONS - INTERLOCUTORY
INJUNCTIONS - SERIOUS QUESTION TO BE TRIED - GENERALLY
The applicant and first respondent entered into an agreement in respect of a large residential
subdivision at Onkaparinga Heights. The respondents, as owner of relevant land, was to procure and
hold the development land and the applicant, as developer, was responsible for managing and
delivering the project, including planning, construction and sales.
By a notice of termination dated 29 April 2026, the first respondent purported to terminate the
agreement on the basis that the applicant had engaged in fraudulent conduct, including
misrepresentations in feasibility studies and budgets, misuse of the casting vote within the Project
Control Group, improper handling of project funds, or otherwise engaged in a fraud on a power. By
a further notice dated 2 June 2026, the first respondent advanced an alternative basis for termination
contending that the applicant did not satisfy the contractual conditions precedent alleging a fraud on
a power and a further right of immediate termination.
The applicant disputes the validity of the termination and seeks interlocutory injunctive relief to
restrain the respondent from acting upon the notices of termination pending trial. The applicant
contends that the allegations of fraud are in substance commercial disagreements that fall to be
resolved under the contractual dispute resolution procedure pursuant to the agreement. The applicant
states that all conditions precedent have been satisfied, and that, absent an injunction preserving the
-- 1 of 41 --
status quo, its contractual rights, securities and entitlement to profit participation will be irreparably
prejudiced.
Held, dismissing the application for injunctive relief:
(1) There is a strong prima facie case for the claim to declaratory relief in respect of the validity
of the termination notices alleging fraudulent conduct, and also in relation to the alternative
basis for termination concerning fraud upon the power and failure to satisfy a condition
precedent. [142]
(2) In respect of each ground upon which the respondents rely to justify the termination, there is
a strong prima facie case or a strong serious question to be tried that the termination was
invalid. The applicant has established that the strength of their case, considered overall, is
such that it does diminish the weight to be placed on other balance of convenience factors.
[142]-[143]
(3) Significant considerations in reaching the finding that the balance of convenience factors do
not favour the grant of injunctive relief are that there is no identified financier to fund the
project governed by the agreement, and the relationship of trust and confidence between the
parties has irretrievably broken down. If the parties were to be required to work together, the
Court considers there would be ongoing disputes, and further and continued litigation. The
inability of the parties to work together would be a strong discretionary factor against the
grant of any remedy of specific performance at the end of a trial. [144]-[145]
(4) In relation to the balance of convenience, particular regard has been had to the financial
implications for the parties concerning the grant or refusal to grant injunctive relief. To the
extent that the applicant has an interest in some of the land that interest is protected by caveats.
The applicant has not demonstrated at this interlocutory stage that damages are not an
adequate remedy in respect of the other potential loss asserted. Considering these matters
together and weighting these matters and all the balance of convenience factors referred to by
the parties, together with the strength of the serious question to be tried, the Court finds that
the interlocutory relief sought should not be granted. [146]
Australian Broadcasting Corporation v O’Neill (2006) 227 CLR 57; Bradto Pty Ltd v Victoria (2006)
15 VR 65; Derry v Peek (1889) 14 App Cas 337; Hancock v Rinehart [2015] NSWSC 646; JC
Williamson Ltd v Lukey (1931) 45 CLR 282; Dexus Sahmri2 Pty Ltd v South Australian Health and
Medical Research Institute Ltd [2025] SASC 61; Nadinic v Drinkwater (2017) 94 NSWLR 518;
Patrick Stevedores Operations No 2 Pty Ltd v Maritime Union of Australia (1998) 195 CLR 1;
Samsung Electronics Co Ltd v Apple Inc (2011) 217 FCR 238; [2011] FCAFC 156, applied.
Bingham v 7-11 Stores [2003] QCA 402; Castlemaine Tooheys Ltd v South Australia (1986) 161
CLR 148; Jones v Dunkel (1959) 101 CLR 298, considered.
-- 2 of 41 --
OLIVER HUME PROPERTY FUNDS (HACKHAM) PTY LTD v YAS
PROPERTY AND DEVELOPMENT PTY LTD
[2026] SASC 95
Civil: Interlocutory Application
GRAY J:
1 This matter concerns a dispute arising out of a Development Management
Agreement dated 31 August 20211 between the applicant, Oliver Hume Property
Funds (Hackham) Pty Ltd,2 and the first respondent, YAS Property &
Development Pty Ltd.3 The Agreement concerns a large residential subdivision
project at Onkaparinga Heights.4 The respondents to the proceedings are YAS and
various other companies associated with YAS.5
2 Both parties accept the existence of the Agreement and broadly the division
of responsibilities. YAS was to procure and hold the development land, while
Oliver Hume, as developer, was responsible for managing and delivering the
project, including planning, funding arrangements, construction, and sales.6 The
central controversy concerns YAS’s purported termination of the Agreement on
29 April 2026.7
3 Oliver Hume contends that this termination is invalid and seeks by
interlocutory injunction to restrain the termination. YAS maintains the validity of
the termination of the Agreement pursuant to the notice of termination issued on
29 April 2026 (‘the first Notice of Termination’) or on the alternative basis of
termination set out on 2 June 2026 (‘the second Notice of Termination’). YAS
opposes the grant of injunctive relief sought by Oliver Hume.8
4 The issue in dispute in these proceedings is whether YAS validly terminated
the Agreement for “fraud” by Oliver Hume, or whether there is another basis upon
which the Agreement may be terminated. Oliver Hume characterises the
termination as opportunistic and unsupported, arguing that the allegations of fraud
are in substance commercial disagreements concerning development strategy,
project financing, and cost allocation. Oliver Hume contends that these matters
fall to be considered within the contractual dispute resolution procedure,9 and do
1 Referred to as ‘DMA’ or ‘the Agreement’.
2 ‘Oliver Hume’ or ‘the Developer’.
3 ‘YAS’ or ‘the Owner’.
4 ‘the Onkaparinga Heights Development’.
5 Together ‘the respondents’.
6 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [2]-[4]; Summary of Argument
of the Respondents filed on 2 June 2026 (FDN 25) at [1]-[3].
7 Exhibit A2: Affidavit of Eve Danielle Thomson dated 16 May 2026 (FDN 2); Exhibit EDT-1, at p 14-
183 (EDT-1).
8 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [1], [23]; Summary of Argument
of the Respondents dated 2 June 2026 (FDN 25) at [5], [9].
9 See clause 11 of the Agreement.
-- 3 of 41 --
[2026] SASC 95 Gray J
2
not give rise to a right to terminate the Agreement.10 Oliver Hume asserts that the
contractual conditions precedent to subsequent project performance were satisfied.
5 By contrast, YAS alleges that Oliver Hume engaged in fraudulent or
improper conduct, including misrepresentations in feasibility studies and budgets,
misuse of its casting vote within the Project Control Group (‘PCG’), and improper
handling of project funds. YAS further contends that approvals central to the
project, including the feasibility study and project budget, were adopted in a
manner which breached the requirements of the DMA.11 YAS asserts that the
contractual conditions precedent to subsequent project performance remain unmet
due to defects in the approval process.12
6 The issue that I must determine is whether interlocutory relief should be
granted. Oliver Hume contends that, absent an injunction preserving the status
quo, its rights under the DMA will be irreparably prejudiced, particularly given the
advanced stage of the project and the risk that transfers of land or restructuring of
ownership may undermine the security Oliver Hume holds in relevant land,13 and
Oliver Hume’s entitlement to profit participation.14 Oliver Hume contends that the
funding difficulties associated with the financier calling in the obligations under
the loan are matters of YAS’s own making.15
7 YAS, as the Owner, was required to fund the development project. It did so
through a finance facility entered into on 25 May 2023, in the name of OVAFS
Pty Ltd,16 being a holding company for the entities holding the land.1718 MCH
Agency Services Pty Ltd as Agency and Security Trustee (‘Metrics’) provided the
finance. Oliver Hume submits that YAS should not be able to avoid the obligations
imposed by the DMA, due to the actions of the financier which Oliver Hume
contends were precipitated by YAS’s actions.19
8 YAS submits that the grant of an injunction would be impractical and unjust.
YAS relies upon the breakdown of the relationship between the parties and the
asserted commercial unviability of the project under Oliver Hume’s management.20
YAS asserts that there are financial pressures, including default under the relevant
10 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [36].
11 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [59], [75].
12 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [10], [58]-[59].
13 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [33]; Exhibit A5: Third Affidavit
of David James Rogers dated 01 June 2026 (FDN 23) at [75].
14 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [54], [63]; Exhibit A5: Third
Affidavit of David James Rogers dated 01 June 2026 (FDN 23) at [16].
15 Transcript of Proceedings, Oliver Hume Property Funds (Hackham) Pty Ltd v Yas Property &
Development Pty Ltd (Supreme Court of South Australia, Gray J, 04 June 2026) at T50.33-51.10, 72.21-
72.38 (‘T’).
16 ‘OVAFS’.
17 The ‘Metrics Loan Facility’.
18 Summary of Argument of the Respondents filed on 2 June 2026 (FDN 25) at [3]. I note at this point
that undertakings were also given in this matter by OVAFS.
19 T 40.38 – 41.30.
20 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [91].
-- 4 of 41 --
[2026] SASC 95 Gray J
3
loan facility and the project financier requiring repayment, giving rise to a risk of
receivership.21 YAS contends that in order for the project to continue it must
proceed independently of Oliver Hume with alternative financing which has been
arranged and other development arrangements.22
Background
9 In or about 2014, Mr Hatem Shahin (‘Mr Shahin’), the sole director of YAS,
began discussions with the relevant landowners whose property formed the land
in the Hackham area (now known as Onkaparinga Heights), for the purpose of a
large-scale residential subdivision.23
10 Mr Hatem Shahin is the sole director and shareholder of YAS (AUS) Pty Ltd,
which is the sole owner of the shares in YAS.24
11 At the time of entry into the Agreement, YAS had secured rights to acquire
the relevant parcels of land through options contracts or land sale contracts,
thereby establishing the foundation for the proposed development.25
12 On 31 August 2021, YAS and Oliver Hume entered into the DMA relating
to the development for subdivision of the land at Hackham into suburban
allotments.26 Under the Agreement, YAS assumed responsibility for procuring, re-
zoning and committing the land to the development.27 Oliver Hume was appointed
as development manager and assumed responsibility for delivering the
development, including planning, financing arrangements, and overall project
management.28
13 The acquisition of the development land was structured through nominee or
related entities associated with YAS, which progressively acquired individual
parcels for incorporation into the overall development.29 The first tranche of these
land acquisitions settled in September 2021.30
14 A key early step in the project was the rezoning of the land for residential
development. That rezoning was achieved during 2022–2023, with the land
21 T 151.
22 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [11]–[15], [18], [78]–[88].
23 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [19]; Exhibit R4: First
Affidavit of Hatem Shahin dated 19 May 2026 (FDN 10) at [5].
24 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [6].
25 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [2], [21].
26 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [2]; Summary of Argument of
the Respondents dated 2 June 2026 (FDN 25) at [22]; Exhibit R4: First Affidavit of Hatem Shahin dated
19 May 2026 (FDN 10) at [4].
27 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [2], [8]-[11]; Summary of
Argument of the Respondents dated 2 June 2026 (FDN 25) at [2], [22], [26].
28 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [9]-[10], [12]; Summary of
Argument of the Respondents dated 2 June 2026 (FDN 25) at [2], [26].
29 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [4]-[5]; Summary of Argument
of the Respondents dated 2 June 2026 (FDN 25) at [2], [19]-[21].
30 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [5].
-- 5 of 41 --
[2026] SASC 95 Gray J
4
ultimately being redesignated as part of the suburb of Onkaparinga Heights,
thereby enabling the proposed development to proceed.31 Around that time, the
Project Control Group approved nominee entities to take transfers of the land.32
15 To fund the acquisition and development of the land, the Metrics loan facility
was entered into on 25 May 2023.33 This facility underpinned the project’s
financial structure and was subsequently increased in stages.34 Further parcels of
land were acquired, including settlements in May 2023 and November 2024.35
16 By late 2025, a draft feasibility study and a project budget were prepared and
then approved by the Project Control Group.36 The applicant contends that all
conditions precedent were thereby satisfied.37 The respondents contend those
approvals did not comply with the DMA.38 In December 2025, the finance facility
was increased to approximately $38,250,000.39
17 In early 2026, further disagreements emerged between the parties in relation
to project strategy, financial modelling, and project progress.40 On 29 April 2026,
YAS purported to terminate the DMA on the basis that Oliver Hume had acted
fraudulently in the course of the development.41 Under the Metrics Loan Facility,
the termination date of the facility was 19 May 2026, and the financier ultimately
required repayment.42 On 18 May 2026, Oliver Hume commenced proceedings
seeking interlocutory and final relief to restrain YAS from acting on the
termination of the DMA.43 In late May 2026, the final tranche of land acquisitions
settled, completing the acquisition phase.44 This is referred to as the Tranche 3
land. It is not in dispute that this land is important to the success of the
Onkaparinga Heights development.45
31 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [14], [25]; Summary of
Argument of the Respondents dated 2 June 2026 (FDN 25) at [24].
32 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [25].
33 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [3], [27]; Exhibit R5: Second
Affidavit of Hatem Shahin dated 21 May 2026 (FDN 14) at [30].
34 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [27].
35 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [4]-[5]; Summary of Argument
of the Respondents dated 2 June 2026 (FDN 25) at [2], [27].
36 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [25]; Summary of Argument of
the Respondents dated 2 June 2026 (FDN 25) at [52]-[53]; Affidavit of David James Rogers dated 20
May 2026 (FDN 6), Exhibit DJR-1 (FDN 12) at p 968.
37 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [25]-[26]; Affidavit of David
James Rogers dated 20 May 2026 (FDN 6) at [41]-[43].
38 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [10], [59].
39 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [3], [27]; Affidavit of David
James Rogers dated 19 May 2026 (FDN 6) at [60].
40 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [45]; Summary of Argument of
the Respondents dated 2 June 2026 (FDN 25) at [52]-[53].
41 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [5], [28].
42 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [4], [6]–[7], [31]; Exhibit
A3: First Affidavit of David James Rogers dated 19 May 2026 (FDN 6), Exhibit DJR-1 (FDN 12) at p
1090.
43 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [6], [8].
44 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [5].
45 Exhibit A2: Affidavit of Eve Danielle Thomson dated 16 May 2026 (FDN 2) at [21].
-- 6 of 41 --
[2026] SASC 95 Gray J
5
The parties submissions
The applicant’s case
18 In substance, the applicant’s case is that:
1. the termination of the DMA by YAS constitutes an opportunistic attempt
to seize the benefit of the project;46
2. the allegations of fraud are legally unsustainable and factually
unparticularised;
3. the dispute is one that should have been resolved under the contract’s
dispute resolution process; and
4. injunctive relief is required to preserve the contractual relationship and
prevent irreparable prejudice pending trial.
The termination was wrongful and opportunistic
19 The applicant contends that the purported termination of the Agreement by
YAS on 29 April 2026 was wrongful, without merit, and opportunistic.47 The
termination is said to have occurred at a critical stage in the project’s development,
immediately prior to relevant land settlements and in circumstances where the
project had already advanced significantly under Oliver Hume’s management.48
20 The applicant contends that Oliver Hume had carriage of the development
for approximately five years and had undertaken the substantive work necessary
to bring the Onkaparinga Heights development to its current position, including
progressing the planning, financing, and acquisition stages.49 The applicant
contends that the timing and circumstances of the termination demonstrate that the
termination was a strategic step taken by YAS to remove Oliver Hume and obtain
for itself the value created in the project.50
The allegations of fraud are unfounded and mischaracterised
21 A central plank of the applicant’s case is that the allegations of fraud relied
upon by YAS are without factual or legal foundation.51 The applicant contends
that the matters relied upon do not involve dishonesty, but instead concern:
• feasibility modelling and financial projections;
• project sequencing and development strategy; and
46 T 40.13-41.12.
47 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [1].
48 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [23]; Affidavit of David James
Rogers dated 19 May 2026 (FDN 6) at [79].
49 Affidavit of David James Rogers dated 20 May 2026 (FDN 13) at [17]-[18].
50 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [26]-[27].
51 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [36].
-- 7 of 41 --
[2026] SASC 95 Gray J
6
• commercial disagreements as to assumptions and timing.52
22 The applicant indicates that feasibility studies and project budgets are
inherently forward-looking documents based on estimates, assumptions, and
information obtained from third parties, which are necessarily revised over time as
the project develops.53 The applicant contends that no relevant representation of
fact was falsely made, and that there is no evidence of any knowing or reckless
falsity.54 Accordingly, the applicant submits that the allegations of “fraud” are
merely a label applied to ordinary commercial disputes arising in the course of a
complex development, and are incapable of satisfying any legal standard of
fraudulent conduct.55
The disputes fall within the contractual dispute resolution mechanism
23 The applicant contends that the present application falls within the exception
in cl 11.7(b) of the Agreement permitting a party to seek urgent injunctive relief,
and that the validity of the purported termination is a matter properly to be
determined by the Court rather than through the contractual expert process.56
24 The applicant also contends that the matters relied upon by YAS to justify
the termination should have been raised within the dispute resolution regime
provided for in the DMA. Oliver Hume issued a formal Notice of Dispute on 2
April 2026.57 Oliver Hume proposed that the disputes raised by that notice should
be resolved by independent expert determination, and the contractual dispute
resolution process was actively on foot at the time of the purported termination.58
Further, the applicant contends that YAS did not issue a notice of default in
accordance with the contract, as Oliver Hume contends that YAS was required to
do as the matters that YAS seeks to raise are commercial disagreements.59 The
allegations of fraud made by YAS are said by Oliver Hume to be a deliberate
attempt by YAS to bypass the contractual procedures and obtain an immediate
termination of the DMA without complying with the agreed dispute resolution
framework.60
The conditions precedent had been satisfied and the project had progressed
25 The applicant contends that all contractual conditions precedent had been
satisfied prior to termination, including, rezoning approval for the project land
52 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [99], [107]–[108].
53 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [83]–[86].
54 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [94]–[97].
55 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [36].
56 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [23]; The applicant relies on the
reasons of B Doyle J in Dexus Sahmri2 Pty Ltd v South Australian Health and Medical Research
Institute Ltd [2025] SASC 61 at [126]-[133].
57 Exhibit A3: First Affidavit of David James Rogers dated 19 May 2026 (FDN 2) at [134], and Exhibit
DJR-1 (FDN 12) at pp 1037-1046, 1076.
58 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [134]–[135].
59 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [66]–[68].
60 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [36].
-- 8 of 41 --
[2026] SASC 95 Gray J
7
which was completed around February 2023; and approval of nominee entities by
the Project Control Group (December 2022).
26 The applicant also relies upon the approval of the Project Budget and
Feasibility Study at the PCG meeting of 2 December 2025 as well as an earlier
approval in February 2022.61 The applicant contends that the feasibility study and
budget were prepared in accordance with the contractual framework, presented to
the PCG, and approved using the agreed voting mechanism including the casting
vote provision.62 The applicant contends that this approval satisfied the final
condition precedent and that, thereafter, the DMA was fully operative and required
continued performance.63
Oliver Hume has substantially performed and contributed to the project
27 The applicant contends that it has substantially performed its obligations
under the DMA and has been the primary driver of the project’s progress.64 In this
regard, Oliver Hume relies upon its actions in relation to the following matters:
• Oliver Hume’s funding of initial land acquisitions prior to the
establishment of external financing;65
• Oliver Hume’s arrangement and negotiation of the Metrics finance
facility and subsequent variations;66
• Oliver Hume’s management of the development process, including
planning approvals, engineering coordination, contractor engagement,
and construction oversight; and
• Oliver Hume’s ongoing responsibility for day-to-day project
management.67
28 Oliver Hume contends that it had operational involvement in the project,
including regular engagement with consultants, strategy, procurement, site
supervision, and regulatory processes.68 The applicant contends that the progress,
structure, and value of the Onkaparinga Heights Development are directly
attributable to these efforts.69
61 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [40]–[44]; Exhibit A6: Fourth Affidavit
of David James Rogers dated 09 June 2026 (FDN 36) at [11.1].
62 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [95]–[96].
63 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [40]–[44].
64 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [24]–[26].
65 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [69]–[70].
66 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [53]–[56].
67 Affidavit of David James Rogers dated 20 May 2026 (FDN 13) at [20].
68 Affidavit of David James Rogers dated 20 May 2026 (FDN 13) at [20].
69 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [24]–[26].
-- 9 of 41 --
[2026] SASC 95 Gray J
8
There is a strong prima facie case (serious issue to be tried)
29 The applicant contends that it has established a strong prima facie case that:
• no fraud has occurred;
• the contractual grounds for termination were not available; and
• the purported termination is invalid and ineffective.70
30 The matters upon which Oliver Hume rely include that all decisions
complained of were taken within the governance structure of the PCG. Further,
Oliver Hume contends that financial arrangements and project decisions were
transparently documented and communicated. Oliver Hume also states that the
allegations of fraud made by YAS were not made prior to the Notice of
Termination.71
The balance of convenience favours maintaining the agreement
31 The applicant contends that the balance of convenience strongly favours
preserving the existing contractual position.72 The applicant relies upon evidence
that Oliver Hume has the resources, expertise, and personnel necessary to continue
the project. Further, Oliver Hume contends that the project has established
operational systems and relationships critical to delivery of the development; and
disruption of those arrangements would cause inefficiency, delay, and further
cost.73
32 The applicant further states that, if the injunction is not granted and the Notice
of Termination remains operative then, it may be practically impossible to restore
Oliver Hume to its role within the project, particularly if third parties are engaged
or project structures are altered.74 The applicant contends that YAS should be held
to the agreement reached with Oliver Hume reflected in the DMA. The applicant
submits that the respondents should not be permitted to avoid their contractual
obligations due to a situation brought about by the respondents’ actions.
Preservation of the status quo is necessary
33 The applicant emphasises that interlocutory relief is required to preserve the
subject matter of the dispute.75 The applicant contends that there is a real risk that,
absent injunctive relief being granted, land may be transferred to entities outside
the DMA framework and that Oliver Hume’s security and contractual rights will
be diminished. It is contended that the project structure will be irreversibly
70 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [28].
71 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [131].
72 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [33], [58].
73 Exhibit A4: Second Affidavit of David James Rogers dated 20 May 2026 (FDN 13) at [18]–[20].
74 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [174].
75 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [33], [63].
-- 10 of 41 --
[2026] SASC 95 Gray J
9
altered.76 The applicant contends that such steps would undermine its ability to
obtain meaningful final relief.
The termination threatens the viability of the entire project
34 The applicant contends that the termination places the viability of the project
at immediate risk.77 The applicant referred to the Tranche 3 land acquisitions, with
a total purchase price of approximately $6.75 million, which were due to settle on
29 May 202678 and contended that those parcels are critical to future development
stages; and without them, the project’s staging and marketability will be materially
impaired.79 As noted below, ultimately those settlements proceeded.
The termination has triggered financing consequences
35 The applicant contends that the purported termination has caused immediate
and significant financing consequences.80 These matters include the project
financier Metrics issuing a notice of default and requiring repayment of the facility
and declining to extend the facility given the existence of the dispute between the
parties to this proceeding.81 The applicant contends that funding would likely
become available again if the injunction is granted, and Oliver Hume remains as
the developer.82
There is a risk of irreparable prejudice
36 Finally, the applicant contends that it faces irreparable prejudice if
interlocutory relief is not granted.83 This prejudice includes exclusion from a
project in which Oliver Hume has invested substantial time, expertise, and capital.
There would also be a loss of anticipated profits which Oliver Hume estimates at
approximately $35 million.84 Oliver Hume contends that there is a risk that
damages will not be recoverable, given YAS’s limited asset position; and there
would be ongoing reputational harm and disruption to the commercial relationship
of the parties.85 Further, as noted previously, the applicant contends that, if land
and assets are transferred outside the contractual framework, Oliver Hume’s rights
will be more difficult to protect.86
76 However, as discussed below caveats have been lodged: see further, Affidavit of David James Rogers
dated 19 May 2026 (FDN 6) at [161]–[164].
77 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [138]–[141].
78 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [138]–[141].
79 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [141]-[144].
80 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [150].
81 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [150].
82 Affidavit of David James Rogers dated 20 May 2026 (FDN 13) at [12].
83 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [166]–[167], [175].
84 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [166]–[167], [175].
85 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [166]–[167], [175].
86 Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [161]–[164].
-- 11 of 41 --
[2026] SASC 95 Gray J
10
The respondents case
Whether the DMA was validly terminated
37 The respondents contend that termination of the DMA on 29 April 2026 was
lawful and effective,87 and they rely on an express contractual entitlement to
terminate for fraud.88 In the alternative, the respondents assert that termination was
justified by the failure to complete contractual conditions precedent in accordance
with the requirement of the DMA within the required timeframe.89
38 The respondents acknowledge, for the purposes of this application, the
existence of a serious question to be tried, but contend that the applicant has not
established a strong prima facie case, and that the evidence discloses multiple
instances of unsatisfactory conduct on the applicant’s part.90
Whether the applicant engaged in fraudulent or misleading conduct and breached
its contractual obligations
39 The respondents contend that the applicant provided misleading feasibility
studies and financial modelling; failed to disclose critical assumptions and risks;
and misrepresented the financial position and viability of the project.91 The
affidavits of Mr Shahin identify concerns about the reliability of feasibility models,
uncertainty in financial assumptions, and discrepancies in projected outcomes.92
The respondents contend that the applicant failed to perform its obligations as
developer.93
40 The respondents contend that notwithstanding rezoning being achieved, the
project did not progress in a timely manner, and there were delays in subdivision,
and civil works being conducted.94 It is alleged that significant delays accrued and
key milestones were not met, with little meaningful advancement following
rezoning.95 The respondents also contends that the applicant failed to comply with
its obligations of transparency and reporting.96
41 The respondents contend that the applicant failed to provide requested
financial and project information; did not disclose feasibility models and
underlying assumptions; and excluded Mr Shahin from communications with
consultants and project stakeholders.97 Mr Shahin in his affidavits refers to repeated
87 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [5]–[6].
88 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [35]–[40].
89 Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [8].
90 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [73], [75].
91 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [44]–[52].
92 Exhibit R4: First Affidavit of Hatem Shahin dated 19 May 2026 (FDN 10); Exhibit R6 Third Affidavit
of Hatem Shahin dated 29 May 2026 (FDN 21).
93 See Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [24]–[26] as to the
obligations which the respondents contend the applicant has failed to perform.
94 Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21), Exhibit HS-12 at p 48.
95 Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21), Exhibit HS-12 at pp 48-49.
96 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [52]–[60].
97 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [52]–[60].
-- 12 of 41 --
[2026] SASC 95 Gray J
11
requests for information which were not adequately met and ongoing concerns
regarding lack of access to project data.98
42 The respondents also allege deficiencies in the financial management of the
project.99 These allegations include, variation and expansion of loan facilities
without proper disclosure; movement and allocation of funds without adequate
explanation; and reimbursement of costs in a manner said to benefit the
applicant.100 Mr Shahin refers to issues arising from the Metrics loan facility,
including increases in funding and the application of funds, as well as concerns
regarding transparency in financial reporting.101
43 The respondents contend that the parties had also entered into a separate
development management agreement at Golden Grove on identical terms,102 which
YAS terminated on 6 November 2025 under an equivalent provision to that
contained in cl 2.5(c) of the DMA.103
44 YAS contends that as a consequence of Mr Shahin acting to terminate the
DMA concerning the Golden Grove project, Oliver Hume took action to avoid that
consequence in respect of the Onkaparinga Heights project. The respondents
contend that, within a month of termination of the Golden Grove DMA, the
applicant altered its approach in respect of the Onkaparinga Heights project and
caused the Project Control Group to adopt the draft Project Budget and draft
Feasibility Study at the December 2025 meeting in order to deny YAS the
opportunity to terminate the DMA on the same basis that the Golden Grove DMA
had been terminated.104
45 The respondents contend that the applicant insisted upon commencing the
Onkaparinga Heights development from a parcel of land located at the centre of
the project, notwithstanding the absence of water and sewerage connections to that
area. This is said to have resulted in years of delay awaiting the delivery of services
by SA Water, incurring substantial wasted expenditure including on engineering
fees, and the continued accrual of interest under the Metrics facility.105 The
respondents further contend that this deferred the point at which the project would
become self-funding, thereby prolonging the applicant’s retention of the casting
vote on the PCG.106
98 See, for example, Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21), Exhibit
HS-11 at pp 46-47.
99 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [52]–[60].
100 Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [14]-[20].
101 Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [62]-[67].
102 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [23]; Exhibit R6: Third
Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [6.4].
103 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [50]; Exhibit R6: Third
Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [6.4.4].
104 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [75.2.5].
105 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [41]; Exhibit R6: Third
Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [9.9], [9.9.1]-[9.9.2].
106 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [60].
-- 13 of 41 --
[2026] SASC 95 Gray J
12
46 The respondents allege that the applicant opened and held sole control of the
project bank account in breach of the DMA and used that control to reimburse
itself for ‘project soft costs’ before it was entitled to do so.107 The respondents
contend that Oliver Hume directed the Metrics loan funds into accounts Oliver
Hume solely controlled; that it falsely represented that documents had been
provided to YAS through a shared OneDrive folder; and that it incorporated a
company and lodged a tax return without YAS’s approval.108
The breakdown of the contractual relationship and issues of serious financial
prejudice
47 The respondents contend that the relationship between the parties has
irretrievably broken down.109 This is said to arise from ongoing disputes within the
Project Control Group; repeated disagreements regarding strategy, finance, and
project execution; and a fundamental loss of trust and confidence by Mr Shahin in
the applicant.110
Whether the respondents face serious financial prejudice
48 The respondents contend that the project is subject to urgent financial
pressure.111 Mr Shahin refers to the Metrics loan facility being called in; the refusal
of Metrics to extend financing; and ongoing liabilities, including interest and
development costs.112
49 The respondents assert that they are able to proceed with the project
independently of the applicant.113 The respondents contend that alternative
financing has been identified, and that funding was able to be obtained such that
on 26 May 2026, 27 May 2026 and 29 May 2026, the final tranche of land
acquisitions settled.114 The respondents contend that the project can progress
outside the existing development structure,115 as the alternative financier is
prepared to fund the development on the basis of Mr Shahin’s proposal which
involves the development of smaller allotments, and the development of the
western part of the land first.116
107 Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [7.3], [17]-[18].
108 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [36.4]–[36.7]; Exhibit R6:
Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [9.3], [9.5], [9.6], [9.8].
109 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [11]–[18].
110 Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [77]-[82].
111 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [11]–[14].
112 Exhibit R4: First Affidavit of Hatem Shahin dated 19 May 2026 (FDN 10); Exhibit R6: Third Affidavit
of Hatem Shahin dated 29 May 2026 (FDN 21) at [48], [68.17], [71]-[72], [81], [83]-[84].
113 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [17]–[18].
114 Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [4]-[5]; Summary of Argument
of the Respondents dated 2 June 2026 (FDN 25) at [2], [27].
115 Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [80].
116 T 108.23-27.
-- 14 of 41 --
[2026] SASC 95 Gray J
13
Where the balance of convenience lies
50 The respondents contend that the balance of convenience favours refusal of
interlocutory relief.117 They submit that maintaining restraints by granting the
injunction will increase financial exposure as it would force the respondents to
continue with the DMA which concerns a project from which the financier has
withdrawn. There is said to be an irreparable breakdown in the relationship of trust
and confidence between the parties to the DMA. The respondents contend that the
consequence of those matters, is that there is a real risk of project failure if the
injunction sought is granted as the injunction is mandatory in nature and it would
force the parties to continue with a project without finance.118
51 The respondents contend that the project, as managed by the applicant, is
commercially unviable. They point to the applicant’s own financial modelling,
which they say applied a hurdle rate of 15% and yielded a negative net present
value of approximately $9.2 million, required peak indebtedness of some $82
million, with the final sale of allotments not being contemplated until about mid-
2033. Further, the respondents refer to a disclosed projected profit of
approximately $19 million attributable only to anticipated GST credits rather than
to gross sales.119
Relevant legal principles
52 The principles governing interlocutory injunctions are relatively well settled.
An interlocutory injunction generally operates as a protective measure. The
purpose of such an injunction is to maintain the integrity of the rights of the parties
pending final adjudication. The function of an interlocutory injunction is not to
determine ultimate rights but seeks to minimise the risk of injustice.
53 As a consequence, for the purposes of this matter, I need only deal
provisionally with the facts and the law.120 I must “exercise a discretion” aimed at
selecting the course that will cause “the least injustice if it is later shown to have
been wrong.”121 The nature of the interlocutory relief to be considered in this case
is inherently anticipatory and risk-based, rather than determinative.
54 The relief sought if granted is to be granted “in aid of the final relief” to
protect the legal or equitable rights asserted by the applicant.122 The relevant
question to be determined may be considered by reference the two factors being,
whether there is a serious question to be tried and where the balance of
convenience lies.123 There is a question arising from the case law as to whether the
117 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [78]-[88].
118 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [80]–[88].
119 Summary of Argument of the Respondents dated 2 June 2026 (FDN 25) at [15], [56]:
120 Beecham Group Ltd v Bristol Laboratories Pty Ltd (1968) 118 CLR 618 at 622.
121 Beecham Group Ltd v Bristol Laboratories Pty Ltd (1968) 118 CLR 618; Kolback Securities Ltd v Epoch
Mining NL (1987) 8 NSWLR 533, 535-539 (McLelland J).
122 Australian Broadcasting Corporation v Lenah Game Meats Pty Ltd (2001) 208 CLR 199 at [15]–[16].
123 Australian Broadcasting Corporation v O’Neill [2006] HCA 46; (2006) 227 CLR 57 at [65]-[72]
(Gummow and Hayne JJ).
-- 15 of 41 --
[2026] SASC 95 Gray J
14
requirement that damages is not an adequate remedy is a separate and distinct
matter or is one of the balance of convenience factors.124 However, for the reasons
discussed below this distinction is not determinative in this case125 and the parties
both accept that damages being an adequate remedy is not a bar to relief, and this
is a matter to be weighed with the balance of convenience considerations.126
55 In the context of a serious question to be tried, as Gummow and Hayne JJ
held in Australian Broadcasting Corporation v O’Neill:127
…it is sufficient that the plaintiff show a sufficient likelihood of success to justify in the
circumstances the preservation of the status quo pending the trial.
56 This formulation reflects a low threshold, requiring neither proof of probable
success nor a final determination of rights.
57 In determining the balance of convenience as the Court held in Bradto Pty
Ltd v State of Victoria:128
the Court should take whichever course appears to carry the lower risk of injustice if it
should turn out to have been ‘wrong’ in the sense of granting an injunction to a party who
fails to establish his right at the trial, or in failing to grant an injunction to a party who
succeeds at trial.
58 The task in considering the balance of convenience is to conduct a
comparative assessment of risks, considering the consequences of error. It follows
that matters which may be destructive of the subject matter of the action, and of a
parties defence to a claim need to be carefully weighed.129 It is important to
consider, for example, whether refusal of relief would render final relief nugatory,
such that the balance may strongly favour preservation of the status quo. The two
limbs of the test identified above are interdependent, and the stronger the
applicant’s case, the less the balance of convenience need favour the grant of the
injunction, and vice versa.130
59 A central consideration in the balance of convenience is whether damages
would provide an adequate remedy. Relevant matters in this context include,
whether damages are sufficient, or whether damages may be inherently inadequate
as future profits and complex commercial outcomes are such that damages may be
difficult to quantify. The adequacy of damages may be considered as part of the
balancing exercise rather than as a threshold requirement, however, the relevance
124 T42.29-44.12. Australian Broadcasting Corporation v O’Neill (2006) 227 CLR 57, at [19] (Gleeson and
Crennan JJ), [65]-[72] (Gummow and Hayne JJ).
125 Ultimately whether damages is an adequate remedy is considered separately or as part of the balance of
conveniences facts the same conclusion is to be reached: Australian Broadcasting Corporation v O’Neill
(2006) 227 CLR 57; Samsung Electronics Co Ltd v Apple Inc [2011] FCAFC 156; (2011) 217 FCR 238.
126 T207.1-7.
127 Australian Broadcasting Corporation v O’Neill [2006] HCA 46; (2006) 227 CLR 57 at [65] (Gummow
and Hayne JJ).
128 Bradto Pty Ltd v State of Victoria [2006] VSCA 89; 15 VR 65 at [35].
129 Cooper v Moloney (No 6) [2012] SASC 212 at [75].
130 Samsung Electronics Co Ltd v Apple Inc [2011] FCAFC 156; (2011) 217 FCR 238 at [67].
-- 16 of 41 --
[2026] SASC 95 Gray J
15
of this matter will be context specific. Whilst the applicant may show that it will
suffer irreparable injury for which damages will not be adequate compensation,
this consideration may be subsumed within the broader balancing exercise.131
60 The relief sought in this case is effectively a form of mandatory injunction
akin to specific performance. As a consequence, caution should be exercised in
considering the suitability of such relief. As Dixon J held in JC Williamson Ltd v
Lukey: 132
Specific performance, in the proper sense, is a remedy to compel the execution in specie of
a contract which requires some definite thing to be done… the remedy is not available
unless complete relief can be given… Specific performance is inapplicable when the
continued supervision of the Court is necessary… It is not a form of relief which can be
granted if the contract involves the performance by one party of services to the other or
requires their continual co-operation.
61 Further, His Honour went on to state:133
Probably the true rule is that an injunction should not be granted which compels, in
substance, the defendant to perform his side of the agreement when the continuance of his
obligation… depends upon the future conduct of the plaintiff… If the contract is one the
execution of which the Court cannot superintend, it does not seem… in accordance with
principle to bind one party to performance in specie…
62 However, compared to the approach set out in JC Williamson,134 the
requirement of judicial supervision may no longer now be such a significant barrier
to relief being granted as it was at the time JC Williamson was decided. Rather,
the potential future need for the exercise of the Court’s supervisory jurisdiction is
a matter to be weighed in the context of the importance of parties being bound to
the contractual terms that they have agreed.135 As a consequence the breakdown of
a commercial relationship will not necessarily operate as a bar to injunctive relief,
and may be dependent on the circumstances be a matter to be weighed in the
balance.
63 The other legal principles relevant to this matter, and to be considered in the
context of the termination of the agreement are the legal principles concerning
fraud. The applicant relies in this case upon “fraud” bearing its common law
meaning, requiring dishonesty. The common law meaning of fraud was considered
in Derry v Peek, to be:136
a false statement of fact which is made… knowingly, or without belief in its truth or
recklessly without caring whether it be true or false, with the intent that it should be acted
upon… and which was in fact so acted upon.
131 Australian Broadcasting Corporation v O’Neill (2006) 227 CLR 57.
132 JC Williamson Ltd v Lukey (1931) 45 CLR 282 at 297–298 (Dixon J).
133 JC Williamson Ltd v Lukey (1931) 45 CLR 282 at 299.
134 (1931) 45 CLR 282 (‘JC Williamson’).
135 Bircan v Portakaldali [2008] NSWSC 791 at [12].
136 Derry v Peek (1889) 14 App Cas 337 at 374.
-- 17 of 41 --
[2026] SASC 95 Gray J
16
64 This reflects the orthodox position that fraud requires conscious dishonesty
or recklessness, not mere error or breach. Fraud must be specifically pleaded with
particularity, including particularity as to the alleged dishonesty.137
65 The respondents also rely upon the equitable doctrine of fraud on the power.
This is said to arise in the context of the assertion that the contractual conditions
precedent to subsequent project performance remain unmet due to defects in the
approval process. As was held in Hancock v Rinehart,138 this doctrine provides
that a power must be exercised: 139
in good faith for the purpose for which it was given and not for any ulterior or extraneous
purpose.
66 Further, as Brereton J went on to hold:140
Fraud in this context does not require dishonesty or immoral conduct, nor an intent to
deceive.
67 In this way, “fraud on a power” is conceptually distinct from common law
fraud. It concerns improper purpose, not dishonesty.141
Consideration
68 I have considered the submissions advanced by the parties both in the written
submissions and at the hearings of this matter.142 I have also considered the detailed
affidavit evidence relied upon by the parties.143 I have had regard to the
undertakings offered by the applicant and to the terms of the open offer made by
the respondents, and the other documents received during the course of the
hearing.144 I would not find on the evidence before me that the undertaking offered
by the applicant was insufficient.
137 Nadinic v Drinkwater (2017) 94 NSWLR 518 at [45].
138 Hancock v Rinehart [2015] NSWSC 646 at [57].
139 Hancock v Rinehart [2015] NSWSC 646 at [57].
140 Hancock v Rinehart [2015] NSWSC 646 at [57].
141 See further, McKerlie v Drillsearch Energy Ltd [2009] NSWSC 488 at [30].
142 Summary of Argument of the Applicant for hearing on 20 May 2026 dated 19 May 2026 (FDN 7),
Summary of Argument of the Respondents filed on 21 May 2026 (FDN 15), Summary of Argument of
the Applicant dated 2 June 2026 (FDN 24), Summary of Argument of the Respondents filed on 2 June
2026 (FDN 25), Submissions in Reply of the Applicant for hearing on 11 June 2026 dated 9 June 2026
(FDN 37) and Submissions in Reply of the Applicant dated 14 June 2026 (FDN 41).
143 Exhibit A2: Affidavit of Eve Danielle Thomson dated 16 May 2026 (FDN 2); Exhibit A3: First Affidavit
of David James Rogers dated 19 May 2026 (FDN 6) and Exhibit DJR-1 (FDN 12); Exhibit A4: Second
Affidavit of David James Rogers dated 20 May 2026 (FDN 13), Exhibit A5: Third Affidavit of David
James Rogers dated 01 June 2026 (FDN 23), Exhibit A6: Fourth Affidavit of David James Rogers dated
09 June 2026 (FDN 36), Exhibit R3: First Affidavit of Andrew Nicholas Wesley Bullock dated 19 May
2026 (FDN 8), Exhibit R4: First Affidavit of Hatem Shahin dated 19 May 2026 (FDN 10), Exhibit R5:
Second Affidavit of Hatem Shahin dated 21 May 2026 (FDN 14), Exhibit R6: Third Affidavit of Hatem
Shahin dated 29 May 2026 (FDN 21), Exhibit R7: Paragraphs [2], [5], [8] and [9]-[13] of the Fourth
Affidavit of Hatem Shahin dated 02 June 2026 (FDN 27), and Exhibit R8: Second Affidavit of Andrew
Nicholas Wesley Bullock dated 11 June 2026 (FDN 39).
144 See further, MFI-R2: Open Offer/Draft Undertaking as to damages dated 5 June 2026.
-- 18 of 41 --
[2026] SASC 95 Gray J
17
69 As I note above, this matter concerns an application for urgent injunctive
relief. The findings that I make below are relevantly interlocutory findings and are
made on that basis.145 Where I have made findings on the evidence before me these
are interlocutory findings.
70 Both parties to this proceeding emphasised the need for expedient
determination,146 due to the commercial considerations which I set out below.147 In
this context, whilst I have had regard to the detail of the submissions advanced by
the parties and to the extensive affidavit material filed, and I have weighed the
relevant matters, I set out below the matters of central significance as raised by the
parties and the matters of significant relevance to my determination.
71 I must consider the matters raised by the parties by reference to the question
of whether the grant of injunctive relief would maintain the integrity of the rights
of the parties pending final adjudication, and whether granting or refusing relief
would minimise the risk of injustice arising following determination of the
substantive claim.148 I must consider whether there is a serious question to be tried,
the strength of the case for primary relief, and where the balance of convenience
lies.149 I must consider whether the applicant has established that damages are not
an adequate remedy.150 The adequacy of damages may be considered as one of the
matters to be weighed in the balance. Even if the applicant has not established that
damages are not an adequate remedy this is not a bar to injunctive relief.151
Serious question to be tried
72 The applicant asserts that it has a strong prima facie case for an interlocutory
injunction to restrain the respondents from giving effect to or acting upon its
purported termination notices in support of its claim to declaratory relief. The final
relief sought is a declaration that the purported termination notices are invalid and
that the DMA remains operative and binding on the parties.152
73 The respondents accept that there is a serious question to be tried as to
whether the termination notices were validly issued and whether the respondent
had a right to terminate the contract.153 However, the respondents dispute that there
is a strong prima facie case.
145 Beecham Group Ltd v Bristol Laboratories Pty Ltd (1968) 118 CLR 618; see also T 175.
146 T21, T39.
147 Applicants Summary of Argument filed 19 May 2026 at [9], [14]-[17], [32]-[35].
148 Bradto Pty Ltd v State of Victoria (2006) 15 VR 65 at [35]; Cooper v Moloney (No 6) [2012] SASC 212
at [75].
149 Australian Broadcasting Corporation v O’Neill [2006] HCA 46; (2006) 227 CLR 57 at [65] (Gummow
and Hayne JJ).
150 Castlemaine Tooheys Ltd v South Australia (1986) 161 CLR 148 at 153 (Mason ACJ); see Gleeson CJ
and Crennan J at [19] in Australian Broadcasting Corporation v O’Neill (2006) 227 CLR 57).
151 Samsung Electronics Co. Limited v Apple Inc. [2011] FCAFC 156 at [61]-[66]; Hyde v Hyde [2026]
SASCA 13.
152 See Oliver Hume Property Funds (Hackham) Pty Ltd, ‘Originating Application’, 18 May 2026, CIV-
26-006365 (FDN 1), order 3.
153 T 169.6-11, T 177.4-7.
-- 19 of 41 --
[2026] SASC 95 Gray J
18
74 The primary case of the applicant for injunctive relief centres on both the first
notice of termination and the second notice of termination being invalid. Invalidity
is advanced on the basis that the respondents will not establish fraudulent conduct
or otherwise establish a right to terminate. As a consequence the applicant
contends that the respondents should be required to comply with the dispute
resolution mechanisms in the DMA. The terms of the DMA contemplate that most
disagreements between the parties to the DMA will be resolved in accordance with
the dispute resolution procedure provided for in clause 11, subject to the limited
exceptions provided for in clause 12. The limited exception upon which the
respondents rely concern what is said to be fraudulent acts in the performance by
the Developer of its obligations under the Agreement.
75 Clause 11 provides for a dispute resolution procedure. The clause provides
for cooperation between the parties and for the parties to meet and “conduct in
good faith discussions and negotiations as may be necessary or desirable to
amicably resolve any Dispute which may from time to time arise”.154 The clause
provides for the issuing of a dispute notice,155 and for the conducting of a meeting
to resolve the dispute pursuant to that notice.156 Failing those matters resolving the
dispute within 14 days after receipt of the dispute notice, the next step in the
dispute resolution process is governed by cl 11.4. Clause 11.4 directs the dispute
to an independent determination (see cl 11.5) or a mediation (cl 11.6).
76 Clause 11.4 of the DMA provides:
11.4 Failure to resolve
If a Dispute is not resolved within 14 days after receipt of the Dispute Notice and the
Dispute relates to (as specified in the Dispute Notice):
(a) in the Owner’s opinion, the Developer’s performance being contrary to
clause 4.1 or contrary to promises and representations made by the
Developer to the Owner or contrary to or not in accordance with the spirit
and intent of this Agreement, clause 11.6 will apply at the election of the
Owner (failing which clause 11.5 will apply); or
(b) any other dispute arising under or in connection with the Agreement, clause
11.5 will apply.
77 Where the matter falls within cl 11.6, being referral for mediation, at any time
after the end of 20 business days from the time of the appointment of a mediator a
party may stop seeking to resolve the dispute through mediation and refer the
matter to determination by an independent expert.157
78 In general terms, the effect of cl 11 is to provide for a process of notification,
meetings, mediation, and then, subsequent to mediation (or in some circumstances
154 Clause 11.1.
155 Clause 11.2.
156 Clause 11.3.
157 See clause 11.6(d) DMA.
-- 20 of 41 --
[2026] SASC 95 Gray J
19
directly pursuant to cl 11.4(b)), the dispute is referred to expert determination to
resolve the matter.
79 Clause 12 of the DMA provides for termination in the context of “Material
Event of Default.” A Material Event of Default is defined as follows:158
Material Event of Default occurs with respect to:
(a) the Developer, where the Developer;
(i) fails to perform any obligation under this Agreement and that failure amounts
to a material breach of this Agreement; or
(ii) commits any wilful misconduct, fraudulent act or gross negligence in the
performance of its obligations under the Agreement;
(b) the Owner, where the Owner:
(i) fails to perform any obligation under this Agreement and that failure amounts
to a material breach of this Agreement; or
(ii) commits any wilful misconduct, fraudulent act or gross negligence in the
performance of its obligations under the Agreement.
80 It follows that fraudulent conduct on the part of one party confers a right upon
the other party to terminate the Agreement without needing to comply with the
dispute resolution procedure referred to in cl 11.159
81 The termination notice issued on 29 April 2026, by the first respondent,
provides, inter alia, as follows:160
NOTICE OF TERMINATION
TO: Oliver Hume Property Funds (Hackham) Pty Ltd
of: Level 2, 4 Riverside Quay,
Southbank VIC 3006
By email: Attention: Michael Duster
[email protected]
RECITALS
A. YAS Property and Development Pty Ltd (the “Owner”) and Oliver Hume Property
Funds (Hackham) Pty Ltd (“the Developer”) are the parties to the agreement styled
as the ‘Development Management Agreement – Hackham’, dated 31 August 2021
(“the DMA”).
158 See clause 1.1 of the DMA.
159 See sub-cl 12.1(a)(ii).
160 Exhibit A2: Affidavit of Eve Danielle Thomson dated 16 May 2026 (FDN 2), Exhibit EDT-1 at pp 14-
183.
-- 21 of 41 --
[2026] SASC 95 Gray J
20
B. This Notice uses terms as defined in the DMA (italicised when first appearing).
C. The Owner is the purchaser under the Land Contracts, being the form of agreement
described in Schedule 4 to the DMA as the basis for the acquisition of the Land.
D. Entities related to the Owner are the nominees of the Land Contracts and are, or are
contracted to become, the registered proprietors of the Land.
E. By the DMA the Owner appointed the Developer as the development manager of the
Hackham Project on the terms and conditions set out in the DMA.
F. The Owner contends that the Developer has fraudulently committed one or more
Material Events of Default, which entitle the Owner to immediately terminate the
DMA.
NOW TAKE NOTICE that:
1. The Developer, in the course of the purported performance of the Developer’s
obligations under the DMA, has committed one or more acts or omissions as set out
in the attached Schedule A that, alone or cumulatively, are Material Event(s) of
Default.
2. The acts or omissions are each, or collectively with one or more other act or
omission:
2.1 fraudulent;
2.2 a material breach of the DMA; and
2.3 not capable of being remedied.
3. The Owner hereby gives the Developer notice pursuant to clause 12.1(a)(ii) of the
DMA, the Owner terminates the DMA with immediate effect.
4. The Owner reserves all its rights against the Developer (including by the
commencement of legal proceedings).
Dated:
Executed by YAS Property and Development Pty Ltd
Hatem Shain
Sole director/Secretary
29/4/2026
82 The acts or omissions referred to in Schedule A of the termination notice,
referred to four general matters. The first concerns an allegation of fraudulent
misrepresentation in relation to the draft project budget and feasibility study which
-- 22 of 41 --
[2026] SASC 95 Gray J
21
was presented at the PCG meeting in December 2025.161 The second matter
concerns what is said to be a deliberate misrepresentation by the Developer to the
Owner that the purpose of obtaining a loan from Metrics in the amount of $5
million was to obtain working capital for the Onkaparinga Heights development.
It is alleged that the Developer knew, or was indifferent to the truth of, these
representations because the purpose of the loan was to enable the Developer to use
the majority of the loan to reimburse itself for amounts it had paid on account of
‘project soft costs’.162 The third matter concerns an allegation of fraudulent
misrepresentation in relation to a feasibility study. It is said that at the PCG
meetings in January and March 2026, and subsequently following the March
meeting, the Developer deliberately misrepresented to the Owner that the
information contained in four different versions of a feasibility study was accurate.
The fourth matter concerns an allegation of a fraud on the power. That is an
allegation that the Developer, by its representative, the Chairperson of the PCG,
deliberately and intentionally misused its casting vote to control the Onkaparinga
Heights development in a manner intended to disadvantage the Owner, and to
advantage the Developer. It is alleged that this was done in disregard of the
Developer’s obligation of good faith under the DMA or the best interests of the
Onkaparinga Heights development.
83 The applicant alleges that each of the matters raised in the notice of
termination had been raised prior to the service of the termination notice by Mr
Shahin.163 The applicant contends the matters raised in the termination notice are
matters which fall within the dispute resolution processes provided for in the
DMA,164 and that these matters should have been dealt with pursuant to the dispute
resolution procedure provided for in cl 11 of the DMA.165 I consider that to be a
strongly arguable proposition. I find that the currently available evidence indicates
there is a serious dispute between the parties concerning the factual substratum
underlying the allegations of fraud set out in the termination notice. I find that the
currently available evidence does not, clearly indicate fraudulent conduct
involving dishonesty.
84 As was set out in Derry v Peek,166 fraud requires conscious dishonesty, being
a false statement of fact which is made knowingly or without belief as to its truth
or recklessly without caring whether it be true or false, with the intent that it should
be acted on. Mere error or breach of a contractual obligation will not amount to
fraudulent conduct. Fraud must be specifically pleaded with particularity,
including particularity as to the alleged dishonesty.167 The currently available
161 Exhibit A2: Affidavit of Eve Danielle Thomson dated 16 May 2026 (FDN 2), Exhibit EDT-1 at pp 14-
183.
162 Exhibit A3: First Affidavit of David James Rogers dated 19 May 2026 (FDN 6), Exhibit DJR-1 (FDN
12) at p 223.
163 Exhibit A3: First Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [132]-[136].
164 T19.
165 Exhibit A3: First Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [132]-[136];
Summary of Argument of the Applicant dated 2 June 2026 (FDN 24) at [36].
166 Derry v Peek (1889) 14 App Cas 337 at 374.
167 Nadinic v Drinkwater (2017) 94 NSWLR 518 at [45].
-- 23 of 41 --
[2026] SASC 95 Gray J
22
evidence before me, considered on an interlocutory basis, does not clearly indicate
fraudulent conduct and readily identifiable dishonesty.168 On the evidence before
me, considered at this interlocutory stage, I find that there is a strong prima facie
case for declaratory relief concerning the invalidity of the notice of termination to
the extent that that notice alleges fraudulent conduct.169
85 In respect of the alternative basis upon which the respondents allege in the
notice of termination that they were justified in terminating the DMA, these
matters suggest there is a ‘fraud on the power’. The respondents contend that these
matters fall within cl 12 of the DMA and give rise to an immediate right of
termination. The respondents also contend in respect of the allegation of fraud on
a power and the consequent alternative basis for termination set out in the letter of
2 June 2026 concerning a failure to satisfy a condition precedent, that there is an
additional right of termination contained in cl 2.5 which gives rise to an immediate
right of termination. In response to this submission the applicant places emphasis
upon the alleged failure to satisfy the third condition precedent being expressed in
the first purported termination notice by reference to the fraud exception in cl
12.1(a)(ii).170
86 The alternative basis upon which the respondents allege that the agreement
may be terminated is set out in a letter of 2 June 2026.171 The 2 June 2026 letter,
inter alia, provides:
In our client’s termination of the DMA by way of its termination notice dated 29 April
2026 (“Termination Notice”), it referred to a number of matters arising from your client’s
purported draft Feasibility Study and proposed Project Budget (see paragraphs 1, 4 -6, 7
8).
Clause 2.5(a)(iii) provides as a condition precedent that the Developer is required to be
“satisfied as to the Project Budget and the Feasibility Study”. We note that clause 2.5(b) of
the DMA expressly provides that the conditions precedent under clause 2.5(a) are for the
benefit of both parties and can only be waived or varied by agreement.
Before the Developer could be “satisfied as to the Project Budget and the Feasibility Study”
within the meaning of clause 2.5(a)(iii), the Developer was required to comply with the
requirements of clause 6.1(a), which clause required the Developer to “with the assistance
of the Owner prepare a draft Feasibility Studt and a proposed Project Budget”.
Notwithstanding repeated requests made by the Owner, at no stage did the Developer take
any serious steps to obtain the assistance of the Owner in the preparation of a draft
Feasibility Study and/or a proposed Project Budget. Indeed, from at least 28 July 2025, the
Owner was, by formal notice, seeking a copy of any draft Feasibility Study and proposed
Project Budget.
168 Nadinic v Drinkwater (2017) 94 NSWLR 518 at [45].
169 That is, fraudulent conduct in the common law sense as set out under the first three headings referred to
in Schedule A of the Notice of Termination.
170 Submissions in Reply of the Applicant dated 14 June 2026 (FDN 41); T39.15-40.37.
171 Exhibit A6: Fourth Affidavit of Hatem Shahin dated 2 June 2026 (FDN 27), Exhibit HS-21 at p 25.
-- 24 of 41 --
[2026] SASC 95 Gray J
23
The documents that the Developer provided in an email to the Owner on 2 December 2025
(being the documents which the Developer caused the chairperson to use its casting vote to
approve as the Project Budget and Feasibility Study at the PCG meeting on 2 December
2025, some 2 hours after the draft documents were provided to the Owner) was a PDF
entitled “Onkaparinga Heights – Project Budget & Feasibility Study (December 2005)”
and was not a draft Project Budget or a draft Feasibility Study within the meaning of the
DMA.
The Owner subsequently became aware in March 2026 that the Developer had an actual
draft Project Budget and draft Feasibility Study (which contained the data behind the PDF
provided by the Developer) which had not been provided to the Owner by the Developer
despite the data being available to the Developer. This included the failure to provide the
cash flow (which was required to be provided – see reference to the cash flow in Schedule
1, 1(d)(ii)) and the Net Present Value of the project, based on a discount rate of 15%, which
was stated to be - $9.2m.
The December meeting of the PCG occurred on 2 December 2025, some 2 hours after the
Developer’s email providing the PDF to the Owner. Plainly this was insufficient time to
enable the Owner to consider and thereby it was plainly insufficient for the PCG to consider
the document. As is apparent from Mr Hatem Shahin’s subsequent conduct, had he been
aware of the actual documents and had he been provided with an accurate statement of the
feasibility and project budget (and has he been given a reasonable time to consider the
documents before the scheduled PCG to approve them ) he would have terminated the
DMA prior to any such meeting pursuant to clause 2.5(c).
As the minutes of the PCG meeting in December 2025 record, Mr Hatem Shain at the PCG
meeting “objected to the timing, lack of detail, and absence of supporting assumptions” in
the PDF document and did not support the “feasibility (the more accurate statement is that
Mr Shahin opposed the PCG approving the “feasibility”).
Pursuant to clause 6.1(b)(ii), “the parties must act reasonably when deciding whether to
approve or not approve a draft Project Budget at the PCG”. Plainly the Developer did not
act reasonably by acting as set out above and by forcing the vote at the PCG meeting, 2
hours after providing the PDF to the Owner.
Further, there was no proper basis for the cash flow to predict cash inflows from the sale
of Lots in January 2026, given the state of the project, and noting that the cash flow had
not been provided to the Owner.
In the circumstances, the purported approval by the PCG of a “draft Project Budget and a
draft Project Feasibility” was void and of no effect and by reason of the conduct of the
Developer, the approval by the PCG cannot be relied upon and/or the Developer is estopped
from relying upon it.
The actions of the Developer in putting forward the PDF as the “draft Project Budget and
a draft Project Feasibility” in the circumstances surrounding the December PCG meeting
also amounted to a clear breach by the Developer of its obligation to act in good faith and
in the best interests of the Project.
For the above reasons, the Developer never satisfied the Conditions Precedent under the
DMA.
As such, without resiling from the fact that our client has already terminated the DMA by
way of its Termination Notice, the Owner hereby provides your client with notice that, in
-- 25 of 41 --
[2026] SASC 95 Gray J
24
the event that the Termination Notice is for whatever reason invalid or ineffective (which
is denied), it terminates the DMA pursuant to clause 2.5(c).
87 The respondents assert that the contractual conditions precedent to
subsequent project performance remain unmet due to defects in the approval
process concerning the Project Budget, which are referred to in the 2 June 2026
letter cited above. These matters are said to be a fraud on the power.172
88 The equitable doctrine of fraud on a power is distinguishable from common
law fraud. The doctrine has application including when a power has been exercised
other than in good faith for the purposes for which it was given. The doctrine may
have application where a power is exercised for an ulterior or extraneous
purpose.173 Considering the matter on an interlocutory basis, I have some doubt
that cl 12 is to be construed to include the equitable doctrine of a fraud on the
power.
89 That said, the respondents contend that cl 2.5(a)(iii) gives rise to an
independent basis upon which the DMA could be terminated. Considering the
matter on an interlocutory basis there is some force in that argument, and there is
evidence which supports the respondents’ claim that the manner in which the
Developer is to be “satisfied”, for the purposes of clause 2.5(a)(iii), did not comply
with the terms of the Agreement, including the requirements of cl 6.1.
90 Against these matters, the applicant contends that cl 2.5(a)(iii) is dependent
only upon the Developer being satisfied as to the Project budget and the feasibility
study and thus is independent of cl 6.1 of the DMA.174 Further, it is asserted that
the reliance on cl 6.1, in the context of the late notice to Mr Shahin of the feasibility
study and project budget shortly prior to the PCG meeting on 2 December 2025,
cannot be seen as a fraud on the power, nor is it precipitated by the termination of
the Golden Grove DMA as the relevant expiry date was 31 December 2025.175
Further, the applicant refers to the unchallenged evidence of Mr Rogers176 that the
condition precedent had been satisfied in February 2022 and that Mr Rogers had
overlooked the record in circumstances where Mr Tuck had left Oliver Hume in
November 2024.177
91 Considering the matter on an interlocutory basis, I have some difficulty in
accepting that cl 2.5(a)(iii) operates independently of cl 6.1. I accept that cl
2.5(a)(iii) concerns a matter of which the Developer must be satisfied. That said,
I have more difficulty in accepting that the Developer could act unreasonably in
172 T165.19-38; Submissions in Reply of the Applicant for hearing on 11 June 2026 dated 9 June 2026
(FDN 37); Summary of Argument of the Applicant dated 2 June 2026 (FDN 24).
173 Hancock v Rinehart [2015] NSWSC 646 at [57].
174 T17.35-19.4; Submissions in Reply of the Applicant for hearing on 11 June 2026 dated 9 June 2026
(FDN 37) at [4]-[6].
175 Submissions in Reply of the Applicant for hearing on 11 June 2026 dated 9 June 2026 (FDN 37).
176 Exhibit A6: Fourth Affidavit of David James Rogers dated 09 June 2026 (FDN 36) at [11.1].
177 See further, Exhibit R3: First Affidavit of Andrew Nicholas Wesley Bullock dated 19 May 2026 (FDN
8) at [11]; Submissions in Reply of the Applicant for hearing on 11 June 2026 dated 9 June 2026 (FDN
37) at [71].
-- 26 of 41 --
[2026] SASC 95 Gray J
25
reaching such a view. Considering the matter on an interlocutory basis, the concept
of reasonableness embodied in cl 6.1 of the DMA may include a requirement to
act reasonably having regard to the rights and interests of the other contracting
party, or, at the least, to consider and evaluate the interests of the other contracting
party.
92 Considering the matters advanced in respect of the alternative basis for the
termination, I consider that there is strength in the contention advanced by the
respondents that there is an independent right of termination in cl 2.5(a)(iii). I also
consider that the respondents contentions on the issue of a fraud on the power
conferred upon the applicant pursuant to cl 2.5(a)(iii) and cl 6.1, in respect of the
applicant’s conduct concerning the draft Project Budget at the PCG and by reason
of non-compliance of the applicant with the requirement to act reasonably as
stipulated in cl 6.1, are reasonably arguable. However, I do not consider that the
respondents have provided significant evidence concerning the more recent
evidence of Mr Rogers in relation to the condition precedent being satisfied in
February 2022.178
93 I find there is a strong prima facie case for the claim to declaratory relief
based upon the invalidity of the first Notice of Termination and the allegations of
fraudulent conduct, and the other matters raised concerning fraud on a power. In
respect of the alternative basis for termination, set out in the second Notice of
Termination I also find that there is a prima facie case. I find that there is force in
that case as the respondent has not produced significant evidence concerning the
alleged earlier satisfaction of the condition precedent in February 2022. Thus, in
considering this matter, I consider there is a strong prima facie case for the claim
to declaratory relief.
94 In finding that there is a strong, serious question to be tried or a strong prima
facie I have considered each of the grounds for termination advanced by the
respondents. I have also considered the answers of the applicant to each of these
grounds. These are matters to be weighed together with the balance of
convenience factors. I have had regard to declaratory relief being discretionary
remedy. It is relevant to consider that for the applicant to succeed in its claim for
primary declaratory relief the applicant is likely to need to establish that each and
every basis upon which the respondent seeks to rely to justify the termination by
reason the Notice of Termination dated 29 April 2026 are not made out. The
applicant by reason of the nature of the declaratory relief sought179 would also need
to establish that the DMA remains on foot. For this reason, the validity of the
grounds for termination set out in the second Notice of Termination dated 2 June
178 See further, Exhibit A6: Fourth Affidavit of David James Rogers dated 09 June 2026 (FDN 36) at [11.1];
Submissions in Reply of the Applicant dated 14 June 2026 (FDN 41) at [11]; Submissions in Reply of
the Applicant for hearing on 11 June 2026 dated 9 June 2026 (FDN 37) at [71].
179 The applicant seeks, inter alia, a declaration that the First Respondent’s purported termination of the
Development Agreement by its Notice of Termination dated 29 April 2026 was invalid and that the
Development Agreement remains on foot; see Oliver Hume Property Funds (Hackham) Pty Ltd,
‘Originating Application’, 18 May 2026, CIV-26-006365 (FDN 1), order 3.
-- 27 of 41 --
[2026] SASC 95 Gray J
26
2026 are also relevant, and to obtain the declaratory relief sought the applicant
would need to establish that the grounds of termination put forward in the second
notice of termination are not made out.
Balance of convenience factors including whether damages are an adequate
remedy
95 Central to the submissions of the parties concerning the balance of
convenience factors are the financial implications for each party and for the
Onkaparinga Heights development which will follow from the grant or refusal of
injunctive relief. Another significant factor concerns the breakdown of the
relationship between the parties. As indicated above, the parties took different
positions in relation to these matters and also in relation to the question of whether
damages are an adequate remedy. The parties accepted that the question of
whether damages are an adequate remedy is a matter to be weighed together with
other balance of convenience factors.180 Further, as the applicant submitted the fact
that damages may be an adequate remedy does not operate as a bar to injunctive
relief.181 Rather, this is a matter to be weighed in the balance.
Financial implications of the grant of injunctive relief
96 In relation to the question of balance of convenience, central to the dispute
between the parties is the question of the finance available in respect of the project.
97 The background of the financial arrangements is that YAS, as the Owner,
was required to fund the development project. It did so through a finance facility
entered into on 25 May 2023, in the name of OVAFS Pty Ltd (‘OVAFS’), being a
holding company for the entities holding the land (the ‘Metrics Loan Facility’).182
MCH Agency Services Pty Ltd as Agency and Security Trustee (‘Metrics’)
provided the finance. The original debt was $17,730,000,183 this was increased to
$32,674,950 on 29 November 2024 and then, in December 2025, by $5 million to
$38,250,000.184 Under the Metrics Loan Facility, the termination date of the
facility was 19 May 2026, by which time OVAFS was required to pay all
outstanding amounts together with all accrued unpaid interests and fees due and
payable. As indicated above, YAS sought to terminate the DMA on 29 April 2026.
The originating application seeking interlocutory and final relief was filed some
19 days later on 18 May 2026. This was the day before the Metrics Loan Facility
was due to expire. A week prior to that on 7 May 2026, Metrics had written to
both the respondents and Oliver Hume informing them that, due to the dispute
between the parties, there was no appetite to consider an extension of the Metrics
Loan Facility. Metrics also stated that it required the repayment of the outstanding
180 Samsung Electronics Co. Limited v Apple Inc. [2011] FCAFC 156, at [61]-[66]; Hyde v Hyde [2026]
SASCA 13.
181 Castlemaine Tooheys Ltd v South Australia (1986) 161 CLR 148 at 153 (Mason ACJ).
182 Summary of Argument of the Respondents filed on 2 June 2026 (FDN 25) at [3].
183 Exhibit R5: Second Affidavit of Hatem Shahin dated 21 May 2026 (FDN 14) at [30].
184 Exhibit A3: First Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [60]; see further,
Summary of Argument of the Respondents filed on 2 June 2026 (FDN 25).
-- 28 of 41 --
[2026] SASC 95 Gray J
27
funds of $38.25 million on 19 May 2026.185 Metrics then sent a notice of default
and demand on 1 June 2026, which was expressed as a final notice.
98 The respondents contend that finance will not be available for the
development if the DMA remains on foot with Oliver Hume as the developer as
the relationship between Mr Shahin and Oliver Hume has irretrievably broken
down. On that basis, the respondents submit that the Owner will only be able to
proceed with obtaining finance with another financier if there is a developer other
than Oliver Hume. Mr Shahin indicates that he has already engaged another
developer.186
99 The evidence put forward by the respondents and in particular the evidence
contained in the third affidavit of Mr Shahin187 indicates that Labarssa Capital (the
‘Owner’s financier’) has agreed to advance funds for the totality of the project in
three stages. The evidence put forward by the respondents asserts that the
proposed funding agreement is conditional on the project being carried out using
the Owner’s development methodology. It is said that the proposed stages are
firstly to settle on the third tranche of land (which settlement was ultimately
finalised on 26 and 29 May 2026). The second stage is to discharge the Metrics
facility, and the third stage is to provide the project with a construction facility
from early July 2026.188 If the Owner is prevented from continuing the
development using the Owner’s development methodology by reason of an
injunction being granted, the respondents contend that the Owner’s financier will
view this as an event of default or some other breach by the Owner and it is likely
that the Owner’s financier will demand immediate repayment of the funds that the
Owner’s financier has advanced. These funds are currently secured over the
Tranche 3 land. Given the importance of the Tranche 3 land, this consequence is
said to materially impede the development potential of the Owner’s land. It is said
to also require significant amendments to the staging and layout of the
development. These matters are said to come at further cost and delay and may
prevent further development of the land by the Owner.189
100 A further consequence is said to be that the Owner’s financier will not
advance the Owner funds to refinance the Metrics Loan Facility which will mean
that Metrics will likely seek to enforce its security and sell the Owner’s land and
the consequences of this will deprive the Owner of the efforts made in relation to
that land over the course of the last 10 years.190
101 Against these matters, the applicant contends that the respondents have not
put on evidence of how much debt the respondents will take on, on what terms
185 Exhibit A3: First Affidavit of David James Rogers dated 19 May 2026 (FDN 6), Exhibit DJR-1 (FDN
12) at p 223, p 1090.
186 Exhibit R5: Second Affidavit of Hatem Shahin dated 21 May 2026 (FDN 14) at [63.6]; Exhibit R6:
Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [82].
187 Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21), see in particular [80]-[81].
188 Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [80].
189 Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [81.1].
190 Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [81.2].
-- 29 of 41 --
[2026] SASC 95 Gray J
28
debt will be taken on, and in what time frame. The applicant contends that these
matters are necessary so as to enable an assessment of whether there will be
sufficient equity in the project at the time of judgment to satisfy an award of
damages.
102 The applicant also challenges the evidence of the respondents to the extent
that the respondents assert that only the respondents can continue with the project.
The applicant points to there being no evidence of the respondents having obtained
finance to fund the balance of the development or the terms of any finance.
Further, the applicant submits there is no evidence in the nature of a feasibility
study or budget as to the respondents’ proposed development and there is no
evidence of the structure of the respondents’ proposed development and further,
there is no evidence of the respondent having engaged a developer. The applicant
refers to Mr Shahin’s assertions as to these matters as being inconsistent and
unsupported by the documents.191
103 The applicant contends that the only reason the project is currently suffering
financial difficulties is that the respondents sought to sabotage the Metrics Loan
Facility.192 On the applicant’s case, this was a calculated and engineered situation
brought about by Mr Shahin so the respondents could force the Court’s hand on an
application to restrain termination by setting up the submission that it now makes
about the lack of finance available for the project to continue under the
development agreement.193 The applicant contends that it has the capacity and
relationships so as to enable the rectification of the project’s finance problems
which Oliver Hume suggests Mr Shahin has brought about.194
104 The applicant submits that it should be afforded the opportunity in the face
of a purported termination which is entirely without merit to seek to obtain the
necessary finance given, and that the difficulties with finance have, on the
applicant’s case, been brought about entirely by the conduct of Mr Shahin. The
applicant also relies on evidence195 which indicates that Oliver Hume has already
been able to obtain a letter of comfort from a new financier in the time available
and has access to some $8 million to continue funding the project pending the
Developer’s proposed financier’s approval.196
191 In particular the applicant refer inter alia to Exhibit R4: First Affidavit of Hatem Shahin dated 19 May
2026 (FDN 10) at [9]; Exhibit R5: Second Affidavit of Hatem Shahin dated 21 May 2026 (FDN 14) at
[63.6]; Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [75]-[80]-[82];
Exhibit R7: Fourth Affidavit of Hatem Shahin dated 02 June 2026 (FDN 27) at [2], [5], [8] and [9]-[13].
192 Exhibit A3: First Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at 223, at [147]-[152].
193 Submissions in Reply of the Applicant filed 10 June 2026 (FDN 37) at [60].
194 Exhibit A3: First Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [2]-[4], [153]-[154];
Exhibit A4: Second Affidavit of David James Rogers dated 20 May 2026 (FDN 13) at [14]-[16]; Exhibit
A5: Third Affidavit of David James Rogers dated 01 June 2026 (FDN 23) at [19]-[39], [57], [63], [71],
[77] and [89].
195 Exhibit A6: Fourth Affidavit of David James Rogers dated 09 June 2026 (FDN 36) at [18].
196 Submissions in Reply of the Applicant filed 10 June 2026 (FDN 37) at [60].
-- 30 of 41 --
[2026] SASC 95 Gray J
29
105 The effect of the applicant’s submissions197 is also that if the injunction is
granted and the development agreement continues in force then Metrics may
continue to fund the Onkaparinga Heights development,198 or the applicant may
find another funder, as Oliver Hume is experienced in obtaining finance. In
contrast, the applicant asserts that the proposal put forward by the respondents is
“effectively destructive” of the applicant’s ultimate claim to enforce the
development agreement and to have the benefit of the agreement that Oliver Hume
suggests was fairly struck between the parties on commercial terms.199
106 The applicant relies upon an email from Metrics dated 7 May 2026 which
inter alia provides as follows:200
It is apparent to us, from the Notice of Termination and communications we have had from
both parties in relation to it, that there is material dispute between the parties to the
Development Agreement. We do not comment on the merit of either side’s position in
respect of that dispute nor do we wish to engage in any further communication in respect
of it. Our position is that, in light of the dispute, we have no appetite to consider an
extension of the Maturity Date, or any period of forbearance and, as such, we require
repayment of the Secure Money in full by no later than 19 May 2026. We expressly reserve
all rights of the Finance Parties under the Finance Documents in connection with the
Default that will occur if the Secured Money is not repaid in full on that date.
107 On 19 May 2026, YAS contacted Metrics to provide an update on refinancing
and to request Metrics to provide a forbearance for a further four weeks. Mr
Shahin indicates in his affidavit that no response to that communication has been
received.201 The respondents accordingly remain in default of the Metrics Loan
Facility and assert that penalty interest has been charged since 4 May 2026, at the
rate of $4000 per day.202
108 Mr Shahin indicates that he has entered into a new facility with a new
financier and that the new financier has provided finance of part of that new facility
of over $7.5 million for the settlement of the Tranche 3 land contracts.203 Two of
those land contracts settled on 26 and 27 May 2026 and one settled on 29 May
2026. The Owner’s Financier now has security over the Tranche 3 land pursuant
to the new facility.204
109 I accept that the information and details of the finance available with the
Owner’s financier is limited. I accept the validity of a number of the criticisms
197 See in particular, submissions on 04 June 2026 at T58.29-59.31. See also, T60.4-61.6.
198 Exhibit A4: Second Affidavit of David James Rogers dated 20 May 2026 (FDN 13) at [14].
199 See in particular T60.38-61.6.
200 Exhibit A3: First Affidavit of David James Rogers dated 19 May 2026 (FDN 6), Exhibit DJR-1 (FDN
12) at p 1090.
201 Exhibit R5: Second Affidavit of Hatem Shahin dated 21 May 2026 (FDN 14) at [48].
202 Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [72]. Penalty interest of
$4000 per day since 4 May 2026 is also found in the Summary of Argument of the Respondents filed
on 2 June 2026 (FDN 25) at [32], [85]. The Metrics facility figures and dates at para [95], see also FDN
25 at [3], [27], [31].
203 Summary of Argument of the Respondents filed on 2 June 2026 (FDN 25) at [33].
204 Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [17.3].
-- 31 of 41 --
[2026] SASC 95 Gray J
30
advanced by the applicant concerning the lack of detail in respect of that evidence.
However, my task on this urgent interlocutory application is not to make final
factual findings as to the finance available but rather to make an appropriate
assessment of risk and to make a comparative assessment of the risk considering
the consequence of error based upon the evidence before me and drawing any
appropriate inference from that evidence or the lack of evidence.205 Matters which
may be destructive of the subject matter of the action and of parties’ defence to a
claim need to be weighed. It is relevant for me to question whether a refusal of
injunctive relief would render final relief nugatory such that the balance may
strongly favour the preservation of the status quo. I would not find on the evidence
before me that the applicant has insufficient prospects of financial recovery of
damages if successful at trial.
110 Whilst there is a lack of detail in relation to the finance that is available to
the Owner from the Owner’s financier, this is a matter that needs to be weighed in
the balance in the context of the risk to both parties if an injunction is granted and
the parties are required to continue under the DMA. The previous financier of the
Onkaparinga Heights development, Metrics, has refused to further fund the
development and states amongst other things that there is a material dispute
between the parties to the Agreement.206 The terms of the email from Metrics dated
7 May 2026 does not demonstrate an appetite to continue funding the Onkaparinga
Heights development under the DMA between the parties.207
111 The Owner’s financier has already funded the further purchase of land to the
sum of some $7.5 million. The applicant’s evidence considered at its highest in
relation to further financing relies upon the potential for Metrics to continue to
finance or refinance the development should the injunction be granted and to the
letter of comfort that has been provided from the proposed Developer financier,
and to the potential for another financier to be obtained.208
112 Considering the question of the financial arrangements overall and having
regard to the potential implications of the caveats upon those financial
arrangements, none of the arrangements put forward by the parties suggest that
there will be a completely satisfactory resolution to the financial difficulties facing
the Onkaparinga Heights development whether the injunction is granted or not.
There is a lack of detail provided concerning the respondents proposed financial
arrangements. Further, the arrangements offered by the respondents may well be
affected by the caveats and the mortgages held by Oliver Hume. That said, the
Owner has engaged an alternative financier who has funded the purchase of the
205 Jones v Dunkel [1959] HCA 8; (1959) 101 CLR 298.
206 Exhibit A3: First Affidavit of David James Rogers dated 19 May 2026 (FDN 6), Exhibit DJR-1 (FDN
12) at p 1090.
207 See however, Exhibit A4: Second Affidavit of David James Rogers dated 20 May 2026 (FDN 13) at
[14].
208 Exhibit A6: Fourth Affidavit of David James Rogers dated 09 June 2026 (FDN 36), Exhibit DJR-5 at p
108.
-- 32 of 41 --
[2026] SASC 95 Gray J
31
Tranche 3 land. Oliver Hume has a letter of comfort, and the potential of other
financing. Oliver Hume has not engaged an alternative financier.
113 I consider that in weighing the balance of convenience factors that to grant
the injunction and require the parties to continue under the DMA would be to
require the parties to continue in an agreement which currently has no engaged
financier to fund the project the DMA.
114 The risk of injustice is something I must consider even though evidence is in
a number of respects incomplete. I find there would be difficulty with requiring
parties to continue in a relationship for the development of land under an
agreement that currently has no financier. On balance, considering the matters at
this interlocutory stage, I consider that the respective financial arrangements
somewhat favour the refusal of interlocutory relief. Given that both the position
of the applicant and the position of the respondents concerning financial
arrangements do not offer a solution that would see the Onkaparinga Heights
development securely funded, I do not place significant weight on this matter but
rather consider that it is a matter to be weighed in the balance together with the
other balance of convenience considerations, which must be considered in the
context of the strength of the applicant’s claim for primary relief.
Irretrievable breakdown of the relationship between the Owner and the Developer
115 It is not in dispute between the parties that the effect of a grant of an
interlocutory injunction would be to require the parties to continue in their
contractual relationship notwithstanding that there has been a degree of breakdown
in that relationship. The respondents point to decisions such as JC Williamson,209
that to grant the injunction would be to require the parties to specially perform their
obligations under the DMA and that this may require a degree of supervision by
the Court. I accept as the respondents contend and for the reasons set out in JC
Williamson that in circumstances where the continued supervision of the Court is
likely to be necessary, a grant of injunctive relief may be undesirable.210 However,
I also accept that, as the applicant contends relying upon the more recent decisions
that where the grant of injunctive relief may involve a degree of supervision by the
Court arising out of the maintenance of the relationship between the parties, this is
no longer necessarily to be regarded as such a strong factor against the grant of
interlocutory relief.211 Whilst the consequence of a breakdown of a commercial
relationship will not necessarily operate as a bar to injunctive relief, the
appropriateness of injunctive relief is dependent, upon the specific circumstances
of the matter and is a matter to be weighed in the balance.
209 (1931) 45 CLR 282.
210 JC Williamson Ltd v Lukey (1931) 45 CLR 282 at 299.
211 That is, in comparison to the principles set out in JC Williamson. See Submissions in Reply of the
Applicant for hearing on 11 June 2026 dated 9 June 2026 (FDN 37) at [11]. See further, Bingham v 7-
11 Stores [2003] QCA 402, at [10] (Williams JA); Patrick Stevedores Operations No 2 Pty Ltd v
Maritime Union of Australia (1998) 195 CLR 1 at 46-47 (Brennan CJ, McHugh, Gummow, Kirby and
Hayne JJ).
-- 33 of 41 --
[2026] SASC 95 Gray J
32
116 The respondents submit that the breakdown of the relationship is
irretrievable. The respondents further submit that requiring two parties to continue
to work together on a development on which is, on the documents before this
Court, likely to continue for a number of additional years in circumstances where
the parties cannot agree on fundamental issues impacting the development will
cause ongoing conflict.212 Further, the respondents contend that the availability of
dispute resolution process under the DMA will not ensure the effective resolution
of the parties difficulties and the respondents submit that to suggest that these
dispute resolution processes will assist shows a complete disconnect from the
reality of the situation between the parties. Further, the numerous allegations of
fraudulent conduct made by the respondents against the applicant is indicative of
a complete breakdown of trust between the parties.
117 The applicant refers to the fact that the parties may have locked horns in the
past, and that Mr Shahin has seen fit to make unmeritorious allegations against
Oliver Hume involving dishonesty as being no bar to the parties being required to
continue to work together within the structures of the DMA.213 However, even on
the submissions of the applicant, it is accepted that requiring the parties to work
together under the current DMA in the context of the current breakdown of the
relationship would be something that would need to be compelled through the
grant of an injunction and compelled in circumstances where there is no currently
available financier for the project.
118 Mr Shahin’s attempt to link the timing of the PCG meeting on 2 December
2025, to a notice given by him on 6 November 2025 in respect of the purported
determination of a different project at Golden Grove for a different reason is said
by the applicant to be “mere speculation infected by an unnatural suspicion”.214
This submission is indicative of the nature of the breakdown in the relationship of
trust and confidence between the parties.
119 The evidence before the Court already indicates that one financier who was
funding the project and was invested in the project by reason of that funding had
no appetite to extend the funding in circumstances where there was a breakdown
in the relationship. The applicant accepted in submissions that if the injunction
were to be granted requiring the parties to work together and no further funding
was forthcoming, then the parties could come back to Court. However, that
submission exemplifies in some ways the anticipated difficulty with the grant of
injunctive relief given the nature of the breakdown in the relationship between the
parties combined with the lack of finance.215 It is already the case that,
notwithstanding that the application for injunctive relief will be determined, the
parties foreshadowed during the hearing of these proceedings further Court
212 Summary of Argument of the Respondents filed on 2 June 2026 (FDN 25) at [91].
213 Summary of Argument of the Applicant filed on 2 June 2026 (FDN 24) at [62]; Exhibit A5: Third
Affidavit of David James Rogers dated 01 June 2026 (FDN 23) at [72].
214 Summary of Argument of the Applicant filed 9 June 2026 (FDN 37) at [11].
215 T64.33-65.07.
-- 34 of 41 --
[2026] SASC 95 Gray J
33
proceedings between them concerning the caveats that have been lodged on the
land.216
120 Whilst there is force in the submission advanced by the applicant that parties
should be continue to be bound to the terms of the contract that they have agreed
and that they should not readily be released from those obligations due a
breakdown in a relationship, that is matter which in the context of this litigation
needs to be weighed in the balance with other matters. These other matters include,
inter alia, the already anticipated further litigation between these parties whether
the injunction is granted or not.217
121 I accept the validity of a number of the criticisms that the applicant makes of
the respondents submission that YAS should not be forced to remain yoked to
Oliver Hume under the DMA because YAS does not agree with Oliver Hume’s
methodology and seeks now to pursue its own methodology, and does not wish to
become indebted to the extent anticipated under the current projected
indebtedness. These criticisms are based upon the lack of detail contained in the
alternative methodology put forward by YAS which does not contain significant
detail of the alternative extent of indebtedness. That said, however, the continued
fractured and litigious nature of the relationship between the two parties currently
before the Court needs to be assessed and weighed in the balance.
122 I consider based upon a consideration of a number of the matters emerging
from the evidence that neither party offers a satisfactory commercial resolution
whereby the relationship will be terminated without the need for ongoing disputes
should the injunction not be granted. Similarly, I consider that the likelihood of
ongoing and increasing disputation between the parties is likely to occur should
the parties be required to continue in a commercial relationship under a
Development Management Agreement when there is a clear breakdown in the
relationship of trust and confidence between the parties and there is a complete
lack of a financier being ready and willing and able to fund the Development under
the DMA.
123 The undisputed evidence before the Court is that the previous financier
Metrics, had no appetite to continue as financier in the context of the material
dispute between the parties.218 The matter for me to weigh in the balance is which
of these two alternative scenarios, neither which is desirable, is less likely to cause
injustice having regard to the potential outcome of the substantive dispute, and the
other balance of convenience factors. I find that there is limited prospects of these
parties being able to work together. The relationship of trust and confidence has
broken down. This has occurred in a context where pursuant to the DMA, the
Developer was to act in some ways as an agent for the Owner concerning the
216 Those proceedings have now been brought: see matter CIV-26-007673.
217 Accepting of course that should an injunction be granted requiring the parties to work together, Oliver
Hume may reconsider its position in relation to the caveats. However, on that scenario there remains the
issue of further proceedings if financing cannot be obtained.
218 Exhibit A3: First Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at p 1090.
-- 35 of 41 --
[2026] SASC 95 Gray J
34
relevant land. I place significant weight upon the likely inability of the parties to
work together in considering the balance of convenience. As I discuss further
below this difficulty is compounded by the decision of Metrics to not continue
funding.
Whether damages are an adequate remedy
124 The respondents contend that Oliver Hume has provided no evidence or
satisfactory reason as to why damages are not an adequate remedy should Oliver
Hume be successful in obtaining final relief.219 The respondents assert that Oliver
Hume has already given an estimate of its damages claim being in the amount of
$35 million.220 The respondents assert that this amount is the amount put forward
by Oliver Hume as representing what Oliver Hume says is its share of the projected
profit from the project.221 The respondents claim that this projected profit is
inconsistent with the estimate of the previous projected profit figures for the
project which were some $20 million, of which Oliver Hume was to receive 50 per
cent. However, the respondents rely upon these figures as indicating that if the
Court was to determine at the final hearing that specific performance was not
available to Oliver Hume, but that Oliver Hume was entitled to relief, Oliver Hume
could be compensated by a way of damages. The respondents assert that relief in
the form of damages will be the appropriate type of relief at a final hearing as the
parties to this matter are unable to work together.222
125 Against these matters the applicant asserts that the reliance placed upon the
projection of profits presents difficulty as these matters are based on feasibility
studies which are in effect only projections and that assessing profits at this stage
of the proceedings can be “fraught and speculative”.223 Further, the applicants
point to the lack of information put forward by YAS concerning YAS’s assessment
of its likely profit.224 Oliver Hume contends that as the respondent have not put on
evidence of how much debt the respondents will, under their proposal be taking on
and on what terms and in what time frame, it is not possible to make an assessment
as to whether there will be sufficient equity in the project by the time of judgment
to satisfy any award of damages.225 Oliver Hume also points to the significant
contribution Oliver Hume has made to the Onkaparinga Heights development.226
126 I accept the position put forward by both parties that whether damages are an
adequate remedy may be considered as part of the balancing exercise rather than
219 Summary of Argument the Respondents filed 2 June 2026 (FDN 25) at [76.1].
220 Summary of Argument of the Respondents filed on 2 June 2026 (FDN 25) at [76.1], [77]; see also,
Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [166]–[167], [175].
221 Summary of Argument of the Respondents filed on 2 June 2026 (FDN 25) at [77].
222 See further, Summary of Argument of the Respondents filed on 2 June 2026 (FDN 25) at [77].
223 Exhibit A3: First Affidavit of David James Rogers dated 19 May 2026 (FDN 6) at [82]-[108]. See
further, Submissions in Reply of the Applicant for hearing on 11 June 2026 dated 9 June 2026 (FDN
37) at [47].
224 Summary of Argument of Applicant filed on 9 June 2026 (FDN 37) at [48].
225 Submissions in Reply of the Applicant for hearing on 11 June 2026 dated 9 June 2026 (FDN 37) at [50].
226 Exhibit A5: Third Affidavit of David James Rogers dated 01 June 2026 (FDN 23) at [8], [20], [21] and
[26]-[28].
-- 36 of 41 --
[2026] SASC 95 Gray J
35
as a threshold requirement.227 The adequacy of damages as a remedy needs to be
considered in the context of the applicant’s primary position that it seeks
restoration of its position pursuant to the DMA and restoration of the contractual
relationship under the DMA, so that it may continue as the Developer in respect of
the Onkaparinga Heights development.
127 I accept that the assessment of damages will be complex as if Oliver Hume
were successful in the claim for final relief, an assessment of damages would need
to consider projected profits. However, I do not consider that Oliver Hume has
established that damages are not an adequate remedy for financial loss. If Oliver
Hume establishes an interest in relevant land this will be protected by the caveats
lodged. I accept that this finding does not bar injunctive relief and that it is a matter
to be weighed together with the other factors.
128 In reaching this conclusion I note, as was accepted by Oliver Hume at the
hearing,228 that as Oliver Hume has issued caveats over the land other than in
respect of the Tranche 3 land and also hold mortgages. As a consequence, Oliver
Hume presently holds some security to protect its position in respect of that land.
229 Any caveatable interest in the relevant land and any valid mortgages will protect
Oliver Hume’s interest in the land. In respect of their other interests, including in
maintaining their position under the DMA I accept that if Oliver Hume were
successful in obtaining the primary relief they seek in the substantive proceedings
and were to seek specific performance, then given the change in position by that
time it is unlikely that they would be restored to their position of Developer under
the DMA. However, even considering all these matters, I find that Oliver Hume
has not established that damages are not an adequate remedy in that respect of the
relevant loss they are likely to claim.230
Other balance of convenience matters
129 The applicant submits that the way to ensure that the agreement under the
DMA and the Onkaparinga Heights development proceeds is to enjoin the
respondents from resiling from the DMA on what is said to be spurious grounds
and to allow funding to be found which accommodates the DMA and is acceptable
to Oliver Hume having regard to the security which Oliver Hume says it is entitled,
under the mortgages and charges and which form the basis of the caveats which
227 Submissions in Reply of the Applicant for hearing on 11 June 2026 dated 9 June 2026 (FDN 37), at
[45]; See further, Samsung Electronics Co Ltd v Apple Inc [2011] FCAFC 156; (2011) 217 FCR 238 at
[67] (Dowsett, Foster and Yates JJ).
228 T 187.20-189.37.
229 I note that the respondents have challenged the position put forward by Oliver Hume and suggest that
Oliver Hume does not have a caveatable interest. Neither party has sought at this urgent injunctive
hearing to make detailed submissions concerning the nature of the caveatable interest, although, the
caveats have been put in evidence before this Court. Neither party sought at the hearing of this matter
to have the validity of the caveats determined in advance of the determination of the injunction
application: at T 225.26-226.2. A separate application was brought and urgent hearing sought in respect
of the caveats after this matter was reserved.
230 Summary of Argument of the Respondents filed on 2 June 2026 (FDN 25) at [92]–[93], that is the loss,
other than the claimed interest in the land.
-- 37 of 41 --
[2026] SASC 95 Gray J
36
Oliver Hume indicates are validly lodged in respect of the land other than the
Tranche 3 land.231
130 The applicant rejects the claims that Oliver Hume’s actions in protecting its
securities and lodging the caveats “blows up from a commercial perspective the
ability to refinance”.232 Oliver Hume submits that this submission should be
ignored in circumstances where it was within the power of the respondents to
produce details of alternate development proposals and financing and that the
respondents have failed to do so.
131 The applicants submit that the respondents have not thought through its
purported termination of the DMA and that the respondent must have thought it
could sabotage the Metrics Loan Facility and then put in place other arrangements,
such that the project could only proceed by way of an alternate proposed
development and that the balance of convenience would favour the respondents no
matter how spurious its ground for termination. The applicant submits that that
strategy is fundamentally flawed in light of Oliver Hume’s security position.
132 The applicant submits that the only way forward for the project is for the
DMA to continue on its terms and an injunction to be granted pending trial to
facilitate that happening. The applicant also contends that the respondents have
not obtained any approvals from council, state government or utilities and
infrastructure bodies and further the respondents have no way to obtain finance
without Oliver Hume’s co-operation under its nominee charges.233 The applicant
submits that there is no reason to diminish the value of the several undertakings it
has offered.234 I have regard to those matters and the undertakings offered.
133 The respondents contend that it is progressing the Development since
termination of the DMA, including:
1. Fundamentally changing the design by increasing the allotments in the
northern parcel of the Development, resulting in changes to the pricing, size,
design, and entrance to the Development;235
2. Engaging with third parties to undertake revisions to the staging of the
Development including to arrange the changes listed above;236
231 See further Submissions in Reply of the Applicant dated 14 June 2026 (FDN 41) at [18].
232 T 180.
233 See further, Submissions in Reply of the Applicant for hearing on 11 June 2026 dated 9 June 2026 (FDN
37) at [58].
234 The respondents further submit that the applicant’s undertaking as to damages is inadequate, the Oliver
Hume group having profitability of around $2 million and no substantial landholding: Submissions in
Reply of the Applicant for hearing on 11 June 2026 dated 9 June 2026 (FDN 37) at [57])
235 Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [74.1]; Summary of
Argument of the Respondents filed on 2 June 2026 (FDN 25) at [34.1]–[34.7].
236 Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [74.2]; Summary of
Argument of the Respondents filed on 2 June 2026 (FDN 25) at [34.1]–[34.7]
-- 38 of 41 --
[2026] SASC 95 Gray J
37
3. Lodging and presenting an application with the relevant council for
development approval.237 Any previous applications have been cancelled;238
4. Engaging with consultants to undertake the new masterplan design,239 with
$600,000 of fees incurred to date paid to these consultants to progress the
new development;240
5. Events have been scheduled to launch the development with council, builders
and members of the public in July, August, and September 2026;241
6. A website is being created and marketing updates have been posted;242
7. YAS has engaged in discussions with two developers in respect of the
Development who had expressed their interest in becoming involved and has
appointed a developer.243
134 The further matters raised by the applicants and the respondents are matters
to be weighed in the balance together with the other matters advanced by the
parties.
Conclusion
135 I have considered the detail of the matters raised by the parties and the detail
of the submissions advanced by the parties and the extensive affidavit material
filed. I have weighed the relevant matters and set out above my findings on central
issues in contention.
136 Neither party to this proceeding has on my assessment of the balance of
convenience factors put forward a satisfactory basis upon which the Onkaparinga
Heights development could properly proceed. The difficulty with seeking to
balance the relative risk of injustice to each party considering the matter at this
interlocutory stage is that the interest of neither party will be served by a receiver
being appointed and the Onkaparinga Heights development failing. Yet neither
party offers a satisfactory resolution.
137 If an injunction were to be granted and the parties forced to continue under
the Development Management Agreement, I consider assessing the matter at this
stage that it is highly likely that the parties will continue in litigation and will
simply not be able to work together.
237 Exhibit R4: First Affidavit of Hatem Shahin dated 19 May 2026 (FDN 10) at [9].
238 Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [74.2].
239 Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) and Exhibits HS-5 to HS-
17 at [74.3].
240 Exhibit R4: First Affidavit of Hatem Shahin dated 19 May 2026 (FDN 10) at [9].
241 Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [74.5].
242 Exhibit R6: Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [74.5].
243 Exhibit R5: Second Affidavit of Hatem Shahin dated 21 May 2026 (FDN 14) at [63.6]; Exhibit R6:
Third Affidavit of Hatem Shahin dated 29 May 2026 (FDN 21) at [75] and [82].
-- 39 of 41 --
[2026] SASC 95 Gray J
38
138 I do not accept the applicant’s submission that granting the injunction is the
only way the project can proceed. I consider that it is likely that no financier would
have an appetite to fund the development under the current DMA between the
parties given the irreconcilable differences between the parties and the likely
disputes that will arise between the parties as to the suitability of any proffered
finance. That is, even if there was a financier who was willing to make an offer of
finance, it is unlikely that both parties would agree upon the terms of that finance
and their respective obligations.
139 Whilst, I have considered carefully the applicant’s submission that if an
injunction was granted and the parties were unable to obtain finance the parties
could come back to Court, I consider that that approach would likely lead to further
litigation. YAS, as the Owner is required to fund the development project. I do
not consider it likely that Mr Shahin would be able to reach an agreement
concerning finance acceptable to both Mr Shahin and the applicant. Alternatively,
if the injunction is refused, I accept there is likely to be difficulty in the respondents
obtaining finance given the current existence of the caveats over the relevant land
other than the Tranche 3 land and there is already further proceedings which have
been brought concerning those caveats.
140 In short, having regard to the relevant considerations which I have set out
above and to the detailed submissions advanced by the parties and to the extensive
affidavit material filed, whilst I consider there is no entirely satisfactory
commercial outcome from either the grant or refusal of injunctive relief, I must
determine which approach would minimise the risk of injustice arising following
determination of the substantive claim, having regard to the balance of
convenience factors.
141 I consider based upon the evidence before me that there is very limited
prospect of the parties ever resuming a satisfactory commercial relationship that
would not be characterised by ongoing litigation and further disputes. I do not
consider that the grant of injunctive relief would maintain the integrity of the rights
of parties pending final adjudication. Rather, I consider that the grant of injunctive
relief would simply result in further litigation and disputes between the parties. I
consider that the applicant has not established that damages are not an adequate
remedy to protect Oliver Hume’s interest outside of any interest Oliver Hume may
have in the land. I acknowledge that the refusal of the grant of injunctive relief is
likely to mean that the applicant, even if successful at trial is unlikely to be restored
to the position that it held under the DMA prior to the termination of that
Agreement by the respondents. However, balancing the relevant matters, I
consider the refusal to grant injunctive relief is appropriate.
142 I find as set out above, there is a strong prima facie case for the claim to
declaratory relief in respect of the invalidity of the termination based on allegations
of fraudulent conduct, and also in relation to the alternative basis for termination
concerning a fraud upon the power. I accept that there is an interrelationship
between the strength of the case to be tried and the balance of convenience factors.
-- 40 of 41 --
[2026] SASC 95 Gray J
39
I accept that the balance of convenience factors needs to be considered in the
context of the findings I have made concerning the strength of the serious question
to be tried.244
143 I have found considering this matter at this interlocutory stage that in respect
of each and every ground upon which the respondents rely to justify the
termination that there is a strong prima facie case or a strong serious question to
be tried that the termination was invalid. I consider that the applicant has
established that the strength of the applicant’s case is such that it diminishes the
weight to be placed on other balance of convenience factors.
144 I have considered the matters advanced by the parties concerning the balance
of convenience. I have had particular regard to the financial implications for the
parties concerning the grant or refusal to grant injunctive relief. I have also had
regard to the applicant not having demonstrated at this interlocutory stage that
damages are not an adequate remedy. Considering these matters together and
weighting these matters and all the balance of convenience factors referred to by
the parties together with the strength of the serious question to be tried, I find that
the interlocutory relief sought should not be granted.
145 I consider that the balance of convenience factors do not favour the grant of
interlocutory relief. Significant considerations in reaching this finding are that
there is no identified financier to fund the project governed by the DMA, and the
relationship of trust and confidence between the parties has irretrievably broken
down. If the parties were to be required to work together, I consider there would
be ongoing disputes and further and continued litigation. This would be a strong
discretionary factor against not only the grant of interlocutory relief but also
against the grant of any remedy of specific performance at the end of a trial in the
event Oliver Hume were to be successful.
146 I consider that to the extent that the applicant has a caveatable interest in land
its interest will be protected by the caveats and any relevant mortgage. In respect
of the applicant’s other financial interest arising from the DMA the applicant has
not established on this interlocutory application that damages are not an adequate
remedy.
147 It follows that I would dismiss the application for injunctive relief to restrain
the first respondent until trial or further order from acting upon its purported
termination of the DMA.
148 I will hear the parties as to any other or further orders.
244 Australian Broadcasting Corporation v O’Neill [2006] HCA 46; (2006) 227 CLR 57 at [65] (Gummow
and Hayne JJ).
-- 41 of 41 --