CHEHADE & SONS CONSTRUCTIONS PTY LTD In Person v LAWRDO SUPER PTY LTD In Person [2026] SADC 3
First Applicant: CHEHADE & SONS CONSTRUCTIONS PTY LTD In Person Counsel: MR A
LAZAREVICH - Solicitor: FLETCHER & LAWSON
Second Applicant: PROPERTY PARTNERS PTY LTD In Person Counsel: MR A LAZAREVICH -
Solicitor: FLETCHER & LAWSON
First Respondent: LAWRDO SUPER PTY LTD In Person Counsel: MR E BELPERIO - Solicitor: WRP
LEGAL
Second Respondent: LAWRDO INVESTMENTS PTY LTD In Person Counsel: MR E BELPERIO -
Solicitor: WRP LEGAL
Hearing Date/s: 14/08/2024 to 16/08/2024, 19/08/2024 to 21/08/2024, 23/08/2024, 09/10/2024
File No/s: CIV-22-002846
B
DISTRICT COURT OF SOUTH AUSTRALIA
(Civil)
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply
to this judgment. The onus remains on any person using material in the judgment to ensure that the intended use of that material does not breach
any such order or provision. Further enquiries may be directed to the Registry of the Court in which it was generated.
CHEHADE & SONS CONSTRUCTIONS PTY LTD & ANOR v
LAWRDO SUPER PTY LTD & ANOR (No 2)
[2026] SADC 3
Judgment of her Honour Judge Thomas
27 January 2026
CONTRACTS - GENERAL CONTRACTUAL PRINCIPLES - FORMATION OF
CONTRACTUAL RELATIONS
CONTRACTS - GENERAL CONTRACTUAL PRINCIPLES - DISCHARGE,
BREACH AND DEFENCES TO ACTION FOR BREACH
EQUITY - GENERAL PRINCIPLES - FIDUCIARY OBLIGATIONS -
PARTICULAR CASES - JOINT VENTURER
DAMAGES - ASSESSMENT OF DAMAGES IN ACTIONS FOR BREACH OF
CONTRACT - GENERALLY
The parties were involved in residential property developments established as joint ventures for mutual
profit. This proceeding concerns disputed claims for four joint ventures.
The first applicant seeks damages for its alleged contractual entitlement to be the builder for the
residential property development known as O’Connell Street. It also seeks payment of six unpaid
invoices for O’Connell Street and two other residential property developments known as Radar Street
and Upton Street/Chicklade Street.
The second applicant seeks compensation for the respondents’ breaches of alleged contractual and
fiduciary duties in failing to account for its 50% profit share from the developments known as Radar
-- 1 of 105 --
Street, Upton Street/Chicklade Street and O’Connell Street. It also seeks payment of three unpaid
invoices for the Radar Street, Connie Street and O’Connell Street developments.
The applicants further seek declarations, ancillary relief, interest and costs.
At trial, the respondents conceded that two unpaid invoices were properly payable.
Otherwise, the respondents deny the applicants are entitled to the relief sought on grounds that the
parties’ joint venture arrangements were initially governed by the terms of a written Project Manager
Services Agreement, thereby disputing the initial terms upon which interest was to be calculated in
determining joint venture profit, which terms were then allegedly varied. They further contend that in
early 2020 the parties’ principals agreed to end profit sharing. Accordingly, the respondents’ principal
was entitled to and lawfully ended the applicants’ participation in the O’Connell Street development.
In the circumstances they contended for, the respondents deny a fiduciary relationship existed between
them and the second applicant.
There are also questions as to whether any estoppels arise in the absence of the Court finding the parties’
existing agreement for any joint venture was varied as alleged by the respondents and a minor question
about set off for GST allegedly paid by the respondents on their very first joint venture.
Held:
1. There is no overarching joint venture agreement between the parties that governs all of the
developments. A series of joint venture agreements was made and each was property specific.
2. The first applicant was not a party to any joint venture agreement on terms entitling it to carry
out the building works required for subsequent joint ventures. However, there was a binding
agreement for the first applicant to be the builder for the O’Connell Street joint venture.
3. No agreement was made in early 2020 to end the second applicant’s existing entitlement to
share profits equally for any of the disputed joint ventures.
4. There was no agreement for the terms of the draft Project Manager Services Agreement to
apply to the parties’ property development joint ventures going forward, and therefore no
agreement to vary the parties’ existing agreement for calculating interest in determining joint
venture profit for the disputed joint ventures.
5. There was also no agreement made in July 2019 to vary the parties’ existing agreement for
calculating interest in determining joint venture profit for any of the disputed joint ventures.
6. Accordingly, in determining profit for the disputed joint ventures, interest as a project cost is
to be calculated on 80% of the purchase price at an interest rate of 6.5%, the rate agreed in
February 2018.
7. The first applicant is entitled to contractual damages in the amount of $502,700 including GST
for the O’Connell Street joint venture.
8. The first applicant is entitled to judgment against the second respondent in the following
amounts:
1. $440 including GST for its invoice no. 0107 dated 17 December 2020;
2. $16,233.30 including GST for its invoice no. 0122 dated 24 March 2021;
3. $32,870 including GST for its invoice no. 0126 dated 20 May 2021;
4. $617 including GST for its invoice no. 0118 dated 28 May 2021;
5. $7,810 including GST for its invoice no. 0140 dated 11 August 2021.
-- 2 of 105 --
9. The second applicant is entitled to judgment against the first respondent in the following
amounts:
1. $10,000 including GST for its unpaid invoice no. 0009-1 dated 27 February 2020 for
reimbursement of marketing commission for Connie Street.
2. $600 (no GST) for its unpaid invoice no. 0009-2 dated 27 February 2020 for the
reimbursement of wages paid for the O’Connell Street joint venture.
10. The second applicant is entitled to share the profits of the Radar Street, Upton Street/Chicklade
Street and O’Connell Street joint ventures in equal proportion with each of the respondents (as
the case may be).
11. The second applicant is entitled to an order for payment out of the Lynch Meyer trust account
of an amount representing its 50% profit share for the Radar Street joint venture that is to be
calculated by adjusting the profit split calculation for interest. Interest as a project cost is to
be calculated on the basis of 80% of the purchase price of the Radar Street property at an
interest rate of 6.5%.
12. The second applicant is entitled to an order against the second respondent for payment of an
amount representing its equal profit share for the Upton Street/Chicklade Street joint venture
that is to be calculated by adjusting the profit split calculation for interest. Interest as a project
cost is to be calculated on the basis of 80% of the purchase price of the Upton Street/Chicklade
Street property at an interest rate of 6.5%.
13. In determining joint venture profit for the O’Connell Street joint venture, no amount is to be
allowed for any amount paid to or invoiced by Adelaide Building Consulting, or for any costs
incurred in making a second application for subdivision, or for project management or sales
consultancy services, but any buyer’s agent commission paid should be allowed as a project
cost.
14. The second applicant is entitled to an equitable interest in the net sale proceeds of the 13
allotments comprising the whole of the land comprised in CT Volume 5397 Folio 273 to the
extent of its 50% profit share for the O’Connell Street joint venture by reason of the
respondents’ breaches of fiduciary duties.
15. The second applicant is entitled to an order against the respondents for payment of an amount
representing its 50% profit share for the O’Connell Street joint venture that is to be calculated
by adjusting the profit calculation made by Mr McPharlin for interest and sales commission as
identified in the reasons for judgment.
16. As regards the second applicant’s claim for breach of fiduciary obligations, it is entitled to the
declaration and orders sought for an account of profits or equitable damages at its election.
17. The applicants’ claims for payment of two invoices for Radar Street are dismissed.
18. The respondents’ defences of estoppel and set off for GST fail.
Agricultural Rural Finance Pty Ltd v Gardiner (2008) 238 CLR 570; Allen v Carbone (1975) 132
CLR 528; Ancient Order of Foresters in Victoria Friendly Society Ltd v Lifeplan Australia Friendly
Society Ltd [2018] HCA 43; (2018) 265 CLR 1; Australian Broadcasting Corporation v XIVth
Commonwealth Games Ltd (1988) 18 NSWLR 540; Bellgrove v Eldridge (1954) 90 CLR 613; Blythe
v Northwood [2005] NSWCA 221; (2005) 63 NSWLR 531; Breen v Williams (1996) 186 CLR 71;
Built Environs Pty Ltd v Tali Engineering Pty Ltd [2013] SASC 84; Chan v Zacharia (1984) 154
CLR 178; Clark v Macourt (2013) 253 CLR 1; Electricity Generation Corporation v Woodside
Energy Ltd & Ors (2014) 251 CLR 640; Empirnall Holdings Pty Ltd v Machon Paull Partners Pty
Ltd (1988) 14 NSWLR 523; Ermogenous v Greek Orthodox Community of SA Inc (2002) 209 CLR
95; Et-China.com International Holdings Ltd v Cheung (2021) 388 ALR 128; European Bank Ltd v
Evans (2010) 240 CLR 432; Film Bars Pty Ltd v Pacific Film Laboratories Pty Ltd (1979) 1 BPR
9251; GC NSW Pty Ltd v Galati [2020] NSWCA 326; Grimaldi v Chameleon Mining NL (No 2)
-- 3 of 105 --
[2012] FCAFC 6; (2012) 200 FCR 296; Hadley v Baxendale (1854) 154 ER 145; Holt v Bunney
[2020] SASCFC 89; Hospital Products Pty Ltd v United States Surgical Corporation (1984) 156
CLR 41; Howard v Commissioner of Taxation [2014] HCA 21; (2014) 253 CLR 83; Integrated
Computer Services Pty Ltd v Digital Equipment Corp (Aust) Pty Ltd (1988) 5 BPR 11,110; John
Alexander’s Clubs Pty Ltd v White City Tennis Club Ltd [2010] HCA 19; (2010) 241 CLR 1; Johnson
v Perez (1988) 166 CLR 351; King Tide Company Pty Ltd v Arawak Holdings Pty Ltd [2017] QCA
251; Kuehn & Kuehn v Masterton Homes (NSW) Pty Ltd [2020] NSWSC 1049; L Albert & Son v
Armstrong Rubber Co (1949) 178 F. 2d 182; Links Golf Tasmania Pty Ltd v Sattler [2012] FCA 634;
Pilmer v Duke Group Ltd (in liq) [2001] HCA 31; (2001) 207 CLR 165; Realestate.com.au Pty Ltd
v Hardingham & Ors [2022] HCA 39; Robinson v Harman (1848) 154 ER 363; Sagacious
Procurement Pty Ltd v Symbion Health Ltd [2008] NSWCA 149; Sion v NSW Trustee & Guardian
[2013] NSWCA 337; Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009) 236 CLR 272; The
Commonwealth v Amann Aviation Pty Ltd (1991) 174 CLR 64; Toll (FGCT) Pty Ltd v Alphapharm
Pty Ltd (2004) 219 CLR 165; United Dominions Corporation Ltd v Brian Pty Ltd (1985) 157 CLR
1; Wenham v Ella (1972) 127 CLR 454, considered.
-- 4 of 105 --
CHEHADE & SONS CONSTRUCTIONS PTY LTD & ANOR v LAWRDO
SUPER PTY LTD & ANOR (No 2)
[2026] SADC 3
CONTENTS
THE ISSUES ............................................................................................................................................... 3
Background ...................................................................................................................................... 3
The Applicants’ Claims ................................................................................................................... 4
THE TRIAL AND THE EVIDENCE ....................................................................................................... 6
The Witnesses................................................................................................................................... 7
FACTS ....................................................................................................................................................... 21
The Parties...................................................................................................................................... 21
The Beginning ................................................................................................................................ 22
The First Development .................................................................................................................. 23
The Second Development .............................................................................................................. 25
Subsequent Developments ............................................................................................................ 26
2016 Changes.................................................................................................................................. 27
Third Party Ventures .................................................................................................................... 36
Charmaine Avenue Purchase – March 2017............................................................................... 37
Upton Street Purchase – March 2017 .......................................................................................... 38
Glen Rovala Street Purchase – April 2017 .................................................................................. 39
O’Connell Street Purchase Contract – April 2017 ..................................................................... 39
Settlement of O’Connell Street – January 2018 ......................................................................... 40
February 2018 Discussion & Emails ............................................................................................ 40
Upton Street Sale – June 2018 ...................................................................................................... 41
Connie Street Sale – October 2018............................................................................................... 41
January 2019 – Cash Flow Difficulties ........................................................................................ 42
Radar Street Approval – April 2019 ............................................................................................ 42
30 April 2019 Email ....................................................................................................................... 42
5 July 2019 Email........................................................................................................................... 45
Sale of 17 Radar Street – January 2020 ...................................................................................... 46
Sale of Gregory Street – February 2020 ...................................................................................... 46
‘Early’ 2020 Discussions ............................................................................................................... 47
O’Connell Street – Progress as at March 2020 ........................................................................... 49
Funding O’Connell Street – March 2020 .................................................................................... 50
17A Radar Street – May 2020 ...................................................................................................... 51
O’Connell Street – May to August 2020 ...................................................................................... 51
Chicklade Street – September 2020 ............................................................................................. 52
O’Connell Street – September to November 2020...................................................................... 53
Chicklade Street – December 2020 .............................................................................................. 54
O’Connell Street – January to March 2021 ................................................................................ 54
-- 5 of 105 --
[2026] SADC 3
2
Sale of Chicklade Street – April 2021 .......................................................................................... 55
O’Connell Street – June to August 2021 ..................................................................................... 55
Caveat over O’Connell Street – October 2021............................................................................ 57
Completion of 17A Radar Street – October 2021 ....................................................................... 57
Completion of O’Connell Street ................................................................................................... 57
CONTRACT CLAIMS............................................................................................................................. 58
Issues ............................................................................................................................................... 58
Principles – Ascertainment of terms ............................................................................................ 59
Threshold Questions ...................................................................................................................... 63
Alleged Profit Share Variation ..................................................................................................... 71
Interest and other costs ................................................................................................................. 72
FIDUCIARY DUTY CLAIM................................................................................................................... 85
UNPAID INVOICE CLAIMS ................................................................................................................. 90
Radar Street Invoices – $614 and $500........................................................................................ 90
Connie Street Invoice – $10,000 ................................................................................................... 90
Chicklade Street Invoices.............................................................................................................. 92
O’Connell Street Invoices ............................................................................................................. 96
SET OFF FOR GST ON EARLY JVS ................................................................................................... 98
RELIEF ...................................................................................................................................................... 99
Property Partners .......................................................................................................................... 99
Chehade Constructions ............................................................................................................... 100
-- 6 of 105 --
[2026] SADC 3
3
THE ISSUES
Background
1 In December 2011, Mr Nabil Chehade and Mr Dillan Lawrence established a joint
venture to acquire and develop a residential property in the northern suburbs of
Adelaide under a written agreement made between Mr Chehade’s company, the
second applicant, Property Partners Pty Ltd (Property Partners) and
Mr Lawrence. At settlement, Mr Lawrence’s company, the second respondent,
Lawrdo Investments Pty Ltd (Lawrdo Investments) was nominated as purchaser
and became a party to the joint venture.
2 On completion of the development of this property, Property Partners and Lawrdo
Investments entered into a second written joint venture agreement on the same
fundamental terms for a second property.
3 Property Partners and Lawrdo Investments then undertook and completed five
further developments as joint venturers between 2013 and 2016 without recording
the terms of their agreement in writing. These developments were referred to by
the parties as Dulkura Road, Hawke Street, Goodall Road, Williamson Road and
Welsh Crescent. It is common ground that without express agreement, these
parties shared profits and losses for these developments in equal proportions and
conducted them on the same fundamental terms as they had for the first two joint
ventures.1
4 For these early developments, the fundamental terms of these parties’ joint venture
agreements are not controversial. Essentially, Mr Chehade through Property
Partners would find the property and manage all the development works.
Mr Lawrence through Lawrdo Investments would fund the purchase, development
and holding costs. On completion of the development, in determining the profit on
any development, interest was paid to Lawrdo Investments on 80% of the
property’s purchase price at an agreed rate and treated as a joint venture cost. The
resulting profits were shared in equal proportions between Property Partners and
Lawrdo Investments.
5 These joint venture arrangements changed in 2016.
6 In June 2016, Mr Chehade identified the Radar Street property for development
and signed a purchase contract for it in the name of one of his companies and/or
nominee(s). He told Mr Lawrence he had found another property. They met face
to face over coffee as they usually did and discussed developing it together and
some changes to their arrangements going forward. Mr Chehade told
Mr Lawrence he had decided to focus on property development fulltime and was
not continuing in real estate. There is controversy about what Mr Chehade said at
this meeting, if anything, about his construction company having a role in their
joint venture arrangements.
1 Statement of Agreed Facts and Issues (FDN 107) MFI 1 [2].
-- 7 of 105 --
[2026] SADC 3
4
7 They discussed Mr Lawrence’s self-managed superannuation fund Lawrdo Super
Pty Ltd (Lawrdo Super) participating in funding future developments.
Mr Lawrence said he would seek advice from his accountant about structures.
Over the following months, they had some further discussions and exchanged
several draft contracts proposing changes to the written agreement that had
governed their earlier joint ventures.
8 Between December 2016 and January 2018, purchase contracts were settled for a
further five properties and they began developing them as joint ventures. These
developments were referred to by the parties as Radar Street, Glen Rovala Street
and/or Gregory Street,2 Upton Street and/or Chicklade Street,3 Charmaine Avenue
and/or Connie Street4 and O’Connell Street.
9 Each development was begun without any written agreement being signed or any
express agreement about the terms of the parties’ joint venture, despite the
exchange of draft contracts in late 2016. There is consensus however that there
was initially an oral agreement made between Mr Chehade and Mr Lawrence on
behalf of Property Partners and the respondent companies to share profits, but there
is dispute as to the precise terms of their agreement about these developments.
10 There were various difficulties in progressing these developments to completion.
In 2018 and 2019, Mr Lawrence proposed changes to the parties’ existing
agreement as to interest and the introduction of other funding fees as joint venture
costs. There is a dispute about whether this proposal was accepted and agreed by
Mr Chehade or not.
11 By February 2020, of these five developments, only the Glen Rovala
Street/Gregory Street development had been completed at a small loss. There is an
unpleaded dispute about what was agreed with regards to sharing this loss that is
only relevant to credit.
12 The remaining four of these five developments are the subject of the claims pressed
by the applicants in this proceeding: that is, Radar Street, Upton Street/Chicklade
Street, Charmaine Avenue/Connie Street and O’Connell Street.
The Applicants’ Claims
13 In summary, the applicants claim the respondents have not properly accounted to
them for what is owed for these developments. Property Partners claims common
law damages for breach of contract for its 50% profit share for the Radar Street
and Upton Street/Chicklade Street joint ventures that were completed before this
proceeding was instituted. For the Charmaine Avenue/Connie Street joint venture,
2 The purchased property was a corner block. It was subdivided into a house block on Glen Rovala Street
and a vacant block on Gregory Street.
3 The vacant block subdivided from Upton Street was on Chicklade Street.
4 The vacant block subdivided from Charmaine Avenue was on Connie Street.
-- 8 of 105 --
[2026] SADC 3
5
Property Partners seeks payment of an unpaid invoice for reimbursement of sales
commission it paid and claims is a project cost.
14 For O’Connell Street, the largest development that was completed before trial
without the applicants’ participation, the applicants claim the respondents have
unlawfully excluded them from and failed to recognise their interests in this joint
venture and its assets in breach of their contractual and fiduciary obligations.
Property Partners seeks damages for breach of the joint venture agreement in the
amount of its lost 50% profit share. Property Partners also seeks declarations that
the respondents have breached their fiduciary duties, entitling it to a full
accounting, equitable damages and a constructive trust over the land and a charge
over the proceeds of sale of O’Connell Street. Property Partners contends the
contractual measure is the same as it is for equitable compensation and it will make
its election before judgment.
15 Chehade & Sons Constructions Pty Ltd (Chehade Constructions), the first
applicant, presses two claims against the respondents.
16 First, it claims payment of outstanding invoices issued to one or other respondent
for building work and costs incurred for the Upton Street/Chicklade Street and
O’Connell Street developments.
17 Secondly, it claims the potential profit on the construction works it would have
undertaken for the O’Connell Street development but for the respondents’ alleged
breaches of the parties’ joint venture agreement.
18 The applicants’ case was advanced on the basis of an overarching joint venture
agreement on terms arising partly in writing, partly through oral discussions and
partly through a past course of dealing that was adopted as the basis for the parties’
developments. For the writing, the applicants rely on the written joint venture
agreement that governed the first two developments.
19 The respondents deny that this written joint venture agreement applies to the
disputed developments, alleging the parties’ relationship as joint venturers for
these developments was governed by a series of agreements, initially made on the
terms of a written Project Manager Services Agreement and subsequently varied
orally as to interest and to end profit sharing.
20 Ultimately, the parties’ disputes about the terms of their joint venture turn on what
passed between the parties’ principals, Mr Chehade and Mr Lawrence during oral
discussions at critical junctures in their dealings in 2016, July 2019 and early 2020.
21 There are also questions as to whether any estoppels arise in the absence of the
Court finding the parties’ existing agreement for any development was varied as
regards interest and profit sharing as alleged by the respondents and a minor
question about set off for GST allegedly paid by the respondents on the first joint
venture (Baldock Road).
-- 9 of 105 --
[2026] SADC 3
6
22 Should the Court find that Property Partners is entitled to share the profits of the
Radar Street, Upton Street/Chicklade Street and O’Connell Street developments,
the quantum of profits to which it is entitled depends on the Court’s findings as to
what was the agreed basis for calculating interest.
23 For O’Connell Street, further questions arise as to whether Chehade Constructions
is a party to the joint venture agreement that incontrovertibly was made between
Property Partners, Lawrdo Investments and Lawrdo Super when Mr Chehade and
Mr Lawrence agreed to develop it as joint venturers in 2017, what entitlement it
had to undertake the building works for this development (if any) and, if so, what
profits it has lost by reason of the respondents’ alleged breaches of contract.
24 By reason of the way the interlocutory proceedings unfolded, Property Partners’
pleaded claim for rights under an alleged option agreement and for specific
performance of that agreement were not pursued at trial.
THE TRIAL AND THE EVIDENCE
25 The trial began on the then current pleadings5 and a Statement of Agreed Facts and
Issues6 that confined the issues in dispute. The trial proceeded over seven days with
a further day for closing addresses.
26 The parties relied on written openings7 and closings8 and a further Statement of
Agreed Facts concerning the Glen Rovala Street/Gregory Street development.9 A
joint tender book comprising five volumes for the historical and disputed joint
ventures10 and various other documents were received in evidence. Despite the
volume of the documentary evidence, it was an incomplete record of the parties’
dealings.
27 The applicants also relied on a chronology that was updated with evidence
references at the close of trial.11
28 On the third day of trial, the respondents abandoned their cross claim12 and an order
was made dismissing the cross claim and reserving the question of costs.13
5 Claim – Revision 4 (FDN 67) (Claim) and Defence (Revision 2) (FDN 87) (Defence).
6 MFI 1.
7 Written Opening of the Applicants (FDN 105) (Applicants Written Opening); Written Submissions
of the Respondents (FDN 110) (Respondents Written Opening).
8 Applicants’ Written Submissions (FDN 119) (Applicants Written Closing); Written Submissions of
the Respondents (FDN 121) (Respondents Written Closing).
9 MFI 39, emailed to Chambers on 3 December 2024 at 10:00am from F Trimboli, without objection from
the Applicants.
10 T647-648.
11 FDN 120.
12 FDN 69.
13 T180.20-182.17; Record of Outcome (FDN 112).
-- 10 of 105 --
[2026] SADC 3
7
The Witnesses
Generally
29 The applicants called four witnesses: Mr Nabil Chehade, Ms Louisa Rossi,
Mr Hugh McPharlin and Mr Chris Sale. Mr Dillan Lawrence was the only witness
called by the respondents.
30 Mr Chehade and Mr Lawrence were the key witnesses. Both gave evidence about
their early joint ventures and the later ones the subject of dispute. Whilst there was
a degree of common ground about key aspects of their previous contractual
dealings and the fundamental basis upon which they began the last five ventures,
they gave opposing accounts of the specific communications that allegedly varied
their existing agreement as regards interest and profit sharing, giving rise to
important questions of credit.
31 Credit issues aside, there were difficulties with the reliability of both their
evidence.
32 This was in part because both were questioned about what was said over the course
of many years of informal dealings that were “messy” (adopting the words of the
respondents’ counsel).14 After the first two joint ventures their contractual dealings
were informal. Nearly all of their communications were oral. Mr Chehade and
Mr Lawrence made decisions about whether to start a new development and about
what to do next in conducting their joint ventures as they went. They did so during
regular café meetings that were almost entirely undocumented, exchanging
infrequent brief emails and SMS texts from time to time. Many of the emails
Mr Lawrence relied on as evidencing the terms of their joint venture agreements
from time to time were unanswered in writing.
33 The evidence plainly showed that Mr Chehade liked “to do things verbally”15 and
that is how he invariably conducted his dealings with Mr Lawrence.
34 Mr Lawrence accepted this was the case. He said in cross-examination with regard
to the unanswered 30 September 2016 email he sent Mr Chehade:16
Mr Chehade was non-responsive because he hardly put anything in email. We had
conversations, a number of meetings…
35 Unsurprisingly, neither Mr Chehade nor Mr Lawrence were able to recall reliably
or precisely the detail of the numerous conversations that took place many years
before they gave evidence. As a result, their evidence was at times generalised,
conclusionary and sometimes plainly reconstructed. Nonetheless, there was broad
consensus about the agreed terms upon which the historical and the disputed joint
14 T694.21.
15 T224.38.
16 T497.1-.2.
-- 11 of 105 --
[2026] SADC 3
8
ventures began, despite the informality of their dealings after the first two
agreements.
36 Accordingly, it was necessary to scrutinise their evidence carefully, paying close
regard to the logic of events and the context of specific communications in
assessing the reliability and veracity of their evidence about the key oral
discussions.
37 In assessing their evidence where it conflicted, it was also important to bear in
mind that their relationship began to deteriorate from early 2018 as various
problems emerged in completing the developments then underway. Completion
of the later developments was impacted by cash flow difficulties and both referred
to some of these developments as effectively being on hold due to cash flow
difficulties, each in evidence blaming the other for their problems. As a result,
there was evident tension and frustration on both their parts that escalated during
2020 to the point that by about May 2021 they were no longer talking, lawyers
were engaged and their relationship broke down irretrievably.
Mr Chehade
38 The respondents criticise the generality and admissibility of Mr Chehade’s
evidence and his reliability and truthfulness where it conflicts with that of
Mr Lawrence on the basis that Mr Lawrence was a witness of truth, doing his best
to assist the Court. On specific topics, the respondents submit Mr Chehade’s
evidence was vague, evasive or unconvincing.
39 Whilst aspects of Mr Chehade’s evidence were not entirely satisfactory and in
some cases unconvincing, ultimately these instances do not lead to the conclusion
that his evidence must be rejected where it conflicts with that of Mr Lawrence,
putting aside the premise as to Mr Lawrence’s credit.
40 Furthermore, I reject the premise that Mr Lawrence was a witness of truth or did
his best to assist the Court. Generally, for the reasons discussed below, where
Mr Lawrence’s evidence conflicts with that of Mr Chehade, I have preferred
Mr Chehade’s evidence.
41 Mr Chehade’s recollection of the nature of the development works undertaken for
the parties’ joint ventures was reasonably detailed and largely unchallenged.
Generally, he gave clear and direct answers to questions about what was done and
when. I have no hesitation in accepting Mr Chehade’s evidence about the
development works undertaken from time to time and prefer his evidence on these
matters to that of Mr Lawrence. In doing so, I have borne in mind that Mr Chehade
was the working partner and it was not Mr Lawrence’s role to manage the
development works. It is therefore unsurprising that Mr Chehade’s memory is
more reliable than Mr Lawrence about some of this detail.
-- 12 of 105 --
[2026] SADC 3
9
42 Significant time was taken in Mr Chehade’s cross-examination on peripheral and
“small”17 matters in an attempt to entirely discredit Mr Chehade as a reliable
witness and portray him as taking unfair advantage of Mr Lawrence by controlling
at all times the way in which their joint venture proceeded. It was submitted that
Mr Chehade had access “to all the information” about their joint venture and
Mr Lawrence had “at some times very limited visibility” over what was going on
despite providing the funding.18
43 Cross-examination to this end ranged over Mr Chehade’s superior expertise in
property joint ventures, his financial interest in a residential building company
(Integrity New Homes), the marketing of the subdivided vacant land in the early
developments as house and land packages, Mr Chehade’s alleged control over the
split between the land and building contracts and the of loss his real estate licence.
Mr Chehade was repeatedly challenged about failing to fully inform Mr Lawrence
about these matters.
44 Ultimately, these challenges on peripheral matters concerned the early
developments, were not pleaded and do not undermine the reliability or veracity
of Mr Chehade’s evidence about the key oral discussions. Having proper regard
to Mr Chehade’s role as the working partner, the admissions made by the
respondents and uncontentious evidence of his and Mr Lawrence’s dealings, it was
generally not the case that Mr Lawrence was as uninformed or uninvolved in joint
venture affairs as he claimed in evidence. He accepted that they met often to
discuss their developments and make decisions about whatever was going on as
necessary.
45 For example, Mr Lawrence said he visited the Baldock Road property regularly.
Mr Chehade’s unchallenged evidence was that Mr Lawrence visited all the sites.
No doubt he did and more than once. The earlier properties were marketed through
Mr Chehade’s real estate agency. The subdivided vacant land was also marketed
as house and land packages through Integrity New Homes. Mr Lawrence knew
that Integrity New Homes were doing the construction works. He knew because
Mr Chehade discussed that with him and Mr Lawrence paid their invoices.
46 Mr Lawrence also knew about Mr Chehade’s connection to Integrity New Homes,
although he said this did not become apparent until later when they were doing the
Goodall Road development. Accepting this was the case, Mr Lawrence made no
complaint about Mr Chehade’s connection to Integrity New Homes until trial. To
the contrary, at the time he relied on Mr Chehade’s connections to promote their
best interests as joint venturers by marketing the land through two channels and by
speaking to his contacts at Integrity New Homes to reduce the $40,000 variance
on the build at the end of the Goodall Road development.
17 T698.23.
18 T698.17-.20.
-- 13 of 105 --
[2026] SADC 3
10
47 On the reliable evidence, there is no real substance to the unpleaded contention
that Mr Chehade “secretly profited” from his interest in Integrity New Homes at
the expense of Mr Lawrence.19 Mr Chehade and Mr Lawrence had a common
interest in reducing the adverse construction variance of $40,000 that would have
reduced the overall joint venture profit and in turn, their individual equal profit
shares by $20,000. As Mr Chehade frankly acknowledged, he was in business to
make money. He undoubtedly would have been alive to the substantial advantage
of maximising joint venture profits for his and Mr Lawrence’s mutual benefit by
reducing the build cost as compared to the indirect benefit he would receive as
shareholder in the building company making a 20% margin including overheads
of $8,000 on the $40,000 variance.
48 The same should be said about the suggestion that Mr Chehade unilaterally
allocated profit between his interests and those of Mr Lawrence by determining
the allocation of the price between the land and the building contracts where a
property was sold as a house and land package. This allegation is not pleaded and
there is no reliable evidence that the prices of the land and build contract were in
fact manipulated to favour Mr Chehade’s interests. I am not satisfied that
Mr Chehade acted improperly by making unilateral decisions about sale prices and
their spilt between land and building contracts.
49 The respondents’ criticism of the admissibility of Mr Chehade’s evidence
(presumably because of its form and generality) was not developed in any detail.
Whilst Mr Chehade’s evidence about his recollection of contentious dealings was
at times generalised, his evidence in cross-examination on contentious topics was
unequivocal and consistent. As elaborated later in these reasons in the context of
the key disputes about what was said at specific junctures about interest and profit
sharing, Mr Chehade’s account was generally more plausible and persuasive than
Mr Lawrence’s account and is preferred.
50 There was one topic on which Mr Chehade’s evidence was unsatisfactory and
I have not accepted his evidence.
51 It concerns the Glen Rovala Street/Gregory Street development that was not the
subject of any claim pressed at trial. Since only passing attention was given to it in
the documentary evidence and in the openings, his cross-examination on this topic
was difficult to follow.
52 Nonetheless, the respondents placed substantial emphasis on Mr Chehade’s
evidence about this development, contending in closing submissions it was
important because it gave context to the alleged 2020 agreement about profit
sharing and how Mr Chehade’s explanations as to why he did not contribute to the
19 Respondents Written Closing [13].
-- 14 of 105 --
[2026] SADC 3
11
loss on this joint venture “made no sense at all”,20 demonstrating “he would say
whatever he needs to say to advance his case at any particular moment”.21
53 This submission was at odds with the earlier submission that it was the
respondents’ case that the unhappiness between the parties over this project
directly led to “a need to go to 10% interest,”22 a variation that was allegedly
agreed in July 2019.
54 This earlier submission should be disregarded. Its foundation was not correct. The
documentary evidence establishes that Mr Lawrence first complained about the
Glen Rovala Street/Gregory Street joint venture in an email he sent in July 2017
when the renovation costs for the existing house came in excess of Mr Chehade’s
estimate.23 It was January 2020 when Chehade Constructions’ final invoice for the
build on the subdivided block (Gregory Street) came in and
Mr Lawrence complained: “Nabil how does $7k variation get to 32k. Please ring
me.”24
55 Mr Chehade’s evidence about an agreement to ‘wipe off’ the loss on this
development against Connie Street was confusing. Connie Street was subdivided
from the Charmaine Avenue and sold as a house and land package in October 2018.
Unless Mr Chehade was mistakenly referring to the cost overrun on the Charmaine
Avenue renovations (the house block), it is unclear how any ‘wipe off’ agreement
could have been made having regard to the different completion dates for these
developments. Ultimately, there is insufficient evidence to resolve this unpleaded
issue.
56 It is however common ground that the Glen Rovala Street/Gregory Street
development went badly and was the source of much unhappiness between
Mr Chehade and Mr Lawrence from beginning to end. Further, resolving what
happened with regard to the overall loss on this development does not resolve the
key factual disputes about what was said about interest and profit sharing for other
developments at the critical junctures. Nor do I consider Mr Chehade’s evidence
on other topics was unreliable or untruthful because his evidence about this
unpleaded issue was unsatisfactory.
Mr Lawrence
57 Overall, Mr Lawrence was an unimpressive witness on many counts, none the least
being the false statements he made in affidavits filed in this proceeding about an
alleged project cost arising under an alleged agreement with Adelaide Building
Consulting (ABC) for consulting services for O’Connell Street. During the
interlocutory stages of this proceeding, Mr Lawrence’s false affidavit evidence
20 T702.33.
21 T702.1-.2.
22 This submission was made in the course of argument about the relevance of this topic of examination in
chief. T357.17.
23 Exhibit A2.11.160 (.11 referring to tab 11 and .160 to page 160).
24 Exhibit A2.25.
-- 15 of 105 --
[2026] SADC 3
12
was repeatedly relied on by the respondents to understate the profitability of this
development. Ultimately the Court was misled by his evidence in making orders
that favoured the respondents.
58 Before addressing the ABC issue more fully, it is significant that there were other
serious difficulties with the reliability and veracity of Mr Lawrence’s evidence in
circumstances where there was ample opportunity to assess him as a witness.25
59 At times, Mr Lawrence’s evidence in chief was implausible, both inherently and
in combination with other reliable evidence including his own admissions. He was
thoroughly cross-examined on the critical topics in contention. He was often
uncooperative and argumentative, giving evasive and non-responsive answers that
overall were repetitions of matters his counsel described in submissions as
contextually important. There were notable unexplained and material
inconsistencies in his evidence on important topics.
60 Self-evidently, Mr Lawrence’s evidence was coloured by his strongly held views
that Mr Chehade had been making more than his equal share of profit out of their
property development joint ventures. His evidence to this effect was plainly given
with a view to discrediting Mr Chehade and advanced as an explanation as to why
Mr Chehade allegedly agreed to change their initial agreement in Mr Lawrence’s
favour as regards interest and profit sharing, which otherwise made no commercial
sense. As explained later in these reasons, I do not accept Mr Lawrence’s evidence
in this regard.
61 A particularly disingenuous example was Mr Lawrence’s evidence early in
examination in chief about his dissatisfaction with the profitability of the early
developments, the time taken to complete them, his purported lack of knowledge
and visibility over the development activities that he suggested Mr Chehade
manipulated to maximise his own benefit at the expense of joint venture profit.
62 On the topic of the first development, Baldock Road, Mr Lawrence said that
considering the work that needed to be done, the return from the first development
was “absolutely unacceptable”,26 time was wasted in the 12 months it took to
finish and “we had lost opportunities and we didn’t make the money that we should
have made.”27 He then went so far as to say that towards the end of it Mr Chehade
was avoiding his calls and there was an altercation on site between them about
getting the property finished within a reasonable time. This was said to have
happened before they agreed to do another 11 developments and became friends
as well as business partners.
63 This evidence was contradicted by Mr Lawrence’s other evidence. Earlier he said
that he had no previous experience or expertise in property development and
25 He gave evidence over the course of four days (although the first and last were not full days).
26 T326.23-.28.
27 T326.37-.38.
-- 16 of 105 --
[2026] SADC 3
13
wanted to get into property development to “make a little bit of money”.28 Next
he said they invested in excess of $300,000 for a $2,000 return but immediately
qualified it by saying “…the only reason I made any money was because of the
interest that we agreed on at that point of time”. 29 This was in circumstances where
his contribution to the joint venture was limited to providing the funding and
Mr Chehade was the working partner whose role was to manage all the
development work (which work Mr Lawrence had earlier acknowledged was
considerable). 30
64 Yet, despite being “very disappointed”31 with the Baldock Road development,
Mr Lawrence engaged in six further joint ventures with Mr Chehade between 2013
and 2015. Mr Lawrence accepted that the performance of these joint ventures was
better but was again disingenuous in downplaying the outcome. He said his
“satisfaction rate would have been around about 50% throughout those sets of
developments”.32
65 It does not make commercial sense that Mr Lawrence would have agreed to engage
in a further five developments with Mr Chehade in 2016 and 2017 if he was really
as dissatisfied with the return on the earlier ventures as he said he was at trial. His
evidence on this topic was unsatisfactory and I do not accept it.
66 This theme of dissatisfaction was repeated by Mr Lawrence in justifying
Mr Chehade’s alleged agreement to a change in the basis for charging interest in
late 2016. Early on, Mr Lawrence gave evidence that “there’s always been [an]
issue in terms of what the return was, and it needed to be an incentive, if you like,
for him to perform. He indirectly is in control of the cost”.33 This evidence was
telling. Mr Lawrence’s dissatisfaction with Mr Chehade’s control of the
renovation and building costs was first expressed in the documentary evidence in
July 2017 about the overrun of the Glen Rovala renovation costs. Mr Lawrence
did not speak of the need for incentives in his emails until two years later in April
and July 2019. His evidence about there always being an issue about the return on
his money is an exaggeration and a recent invention designed to bolster his case
on interest and the end of profit sharing.
67 There is another aspect of Mr Lawrence’s evidence that warrants specific criticism.
He constantly repeated that Mr Chehade benefited more than he did from their
joint venture because of the building contracts. He also said he had limited
visibility over the house and land packages and the building contracts Mr Chehade
made with third parties that were “nothing to do with me”.34
28 T321.28.
29 T327.8-.10.
30 T326.4-.11.
31 T331.29.
32 T331.32-.36.
33 T339.7-.10.
34 T364.18.
-- 17 of 105 --
[2026] SADC 3
14
68 As regards O’Connell Street, Mr Lawrence’s evidence on this theme was
particularly incongruous. Despite contending that in early 2020, it was agreed that
the only way Mr Chehade would make any money out of this development was
through third party building contracts and then agreeing to sell house and land
packages nominating Chehade Constructions as the builder, Mr Lawrence
disagreed that on his case it followed that the house and land packages were going
to be with Chehade Constructions. He said:35
No, there was no guarantee. If you could get the – if you got a construction build from the
third party that’s between him and the third party. I wouldn’t have yielded any benefit.
There’s no guarantee that that would have been the outcome.
69 His evidence on this topic was unconvincing and I do not accept it for three
reasons.
70 First, it makes no commercial sense for Mr Chehade to agree to vary their existing
profit sharing agreement with no guarantees of any benefit from their development
activities in circumstances where he had introduced the development opportunity
to Mr Lawrence and had already managed a considerable part of the development
works.
71 Secondly, Mr Lawrence clearly knew about the house and land packages that
nominated a specific builder. The subdivided land in their early joint ventures had
always been marketed through two channels. Until 2016, joint venture land was
marketed through both Mr Chehade’s real estate firm and through Integrity New
Homes as house and land packages. Mr Lawrence knew about Integrity New
Homes “from their invoices”.36 Thereafter with Mr Lawrence’s knowledge, third
party agents were engaged to market vacant land as house and land packages,
nominating Chehade Constructions as the builder. Specifically, in May 2020, Ray
White was appointed to sell the O’Connell Street allotments as house and land
packages under a written agency agreement nominating Chehade Constructions as
the builder. Their written agency agreement was signed by Mr Chehade with
Mr Lawrence’s agreement and approval.
72 Thirdly, the building contracts with third parties added value to the parties’ joint
ventures by providing an avenue to sell the subdivided land, particularly in the
earlier joint ventures where they had otherwise been unsuccessful in selling the
land as a vacant blocks. It was commercially sensible to market their developments
through multiple channels.
73 Turning to the topic of what was said in the key discussions allegedly varying their
existing agreement as to interest and profit sharing, it was plain Mr Lawrence was
reconstructing and had no actual memory of these discussions. He repeatedly said
matters were ‘understood’ or ‘accepted’ by Mr Chehade. When asked what was
discussed he gave explanations by reference to what he subjectively required or
35 T606.22-.26.
36 T327.19-.24.
-- 18 of 105 --
[2026] SADC 3
15
intended and when pressed about what was said to indicate such acceptance, his
answers were not persuasive.
74 A prime example was his evidence in chief on the significant change to the basis
of calculating interest as a joint venture cost that first appeared in the draft
agreements exchanged in late 2016.
75 When shown the first draft he had sent to Mr Chehade by email on 30 September
2016, Mr Lawrence’s evidence was: “I would say I certainly initiated the drafting
of that document, the template looks like something that I would have done”.37
When asked what he meant, he said he drafted it, then immediately agreed he had
just proposed changes to an existing document. He then changed position yet
again, saying he started with a blank page and typed the document that “would
have been based on stuff that I got from the internet and stuff that I would have
gleaned from the original agreement in 2011.”38
76 Yet his covering email expressly refers to him amending the agreement that
Mr Chehade had provided to him. This email is plainly the more reliable record
of what happened than Mr Lawrence’s oral evidence.
77 He repeatedly referred to there being numerous discussions about this draft of the
document, his subjective intention being that it be “tight enough and understood
by both sides, and it was”39 and there was a need for “a contract that was rigid,
based on my accountant’s advice”,40 all of which were apparently ‘agreed’ and
‘understood’ by Mr Chehade. He then gratuitously volunteered: “At no time did
he reject this particular clause.”41 despite later stating that Mr Chehade was non-
responsive because “he hardly put anything in email”.42
78 When asked what was said to indicate Mr Chehade’s acceptance, Mr Lawrence
gave the following unconvincing and somewhat contradictory evidence that:43
Well, we would discuss it, and he says “That’s fine, that’s okay’. He was okay with going
forward with it. There was no arguments in regards to this, he accepted it. I mean, it was
a short discussion. It was more refining the words to make sure that it was properly
articulated.
79 As discussed later in these reasons, I also do not accept Mr Lawrence’s evidence
that Mr Chehade agreed with his proposed changes for the calculation of interest
as a joint venture cost between October and December 2016.44 The emails attaching
successive drafts of a proposed agreement demonstrate that no agreement was
reached on the terms of the superseded drafts. When this proposition was put to
37 T333.17-.19.
38 T334.19-.21.
39 T353.13-.14.
40 T353.31-.32.
41 T352.9-.10.
42 T497.1-.2.
43 T353.19.
44 T496.23-.26. See [157]-[184] and [187]-[197] below.
-- 19 of 105 --
[2026] SADC 3
16
him, Mr Lawrence reluctantly agreed that this was the case, thereby undermining
his earlier evidence about them.
80 There were similar difficulties with his evidence about the alleged agreement made
in July 2019 for extra costs and 10% interest to be charged by the Lawrdo entities.
In cross-examination Mr Lawrence said:45
Q. And at p. 255 there was no email agreeing to the contents of your restated email on
5 July 2019.
A. No.
Q. And I’m suggesting to you there was no oral discussion where Mr Chehade agreed
to the terms.
A. Same as the previous answer. He – neither did he disagree with those terms. He’s
the project manager, his job – part of his job is to communicate. He should have
responded if he disagreed. All he needed to have said was – if it was true, which
he’s denied – “As discussed, did not agree”. He hasn’t expressed that anywhere.
81 As discussed later in these reasons, I prefer Mr Chehade’s evidence on this topic
and have found he did tell Mr Lawrence that he did not agree to these extra funding
costs being joint venture costs. Furthermore, Mr Lawrence’s justification for
imposing these extra costs to cover his overheads in line with ‘financial
organisations’ funding property developments was simply not compelling. Neither
of Mr Lawrence’s entities were subject to the strict prudential regulation and
controls that applied to financial institutions, even accepting that Lawrdo Super as
a SMSF was subject to stricter prudential controls than other proprietary
companies. It is therefore unsurprising Mr Chehade did not agree to such extra
costs.
82 Mr Lawrence’s evidence on the topic of the 2020 agreement to end profit sharing
was particularly unsatisfactory. His evidence was inherently implausible and not
credible for the reasons discussed below.46
The “ABC Story”
83 It is however Mr Lawrence’s conduct and evidence with regard to the alleged
liability to ABC for consulting services for O’Connell Street that warrants the most
serious criticism. Mr Lawrence’s admissions (both on affidavit and in cross-
examination) and the documentary evidence demonstrate that Mr Lawrence was
the architect of a scheme to understate the profit of the O’Connell Street joint
venture by $318,175 (including GST) by overstating the project costs. He did so
by falsely reporting a project cost that was not genuine. Neither the ABC
agreement47 nor the ABC invoice48 purportedly evidencing this cost were genuine
nor was it true that there was any intention on Mr Lawrence’s part for ABC to
perform the consulting services described in the ABC agreement.
45 T535.17-.28.
46 See [274]-[311] below.
47 Exhibit DO11 to Exhibit A25.
48 Ibid.
-- 20 of 105 --
[2026] SADC 3
17
84 The “ABC story” (as the applicants’ counsel described it),49 was first advanced in
the respondents’ solicitor’s letter dated 22 April 202250 offering to pay into Court
$76,184.74 to resolve the dispute over the extension of time for removal of
Property Partners’ caveat over the O’Connell Street property. This amount was
said to be the respondents’ “reasonable” calculation of 50% of the estimated profit
of the O’Connell Street development based on overstated project costs that
included $318,175 (including GST) for ABC’s purported fee for consulting
services under the ABC agreement.51
85 The respondents’ solicitor’s letter was sent on Mr Lawrence’s instructions, without
his solicitor knowing that any liability under the ABC agreement for consulting
services that was not a genuine development cost and thereby the project costs
were overstated and the expected net profit for O’Connell Street was understated.52
86 The “ABC story” was repeated in two further affidavits of Mr Lawrence made on
18 May53 and 18 June 2022.54 These affidavits were relied on by the respondents
in an argument before Judge Burnett on 22 June 2022 in opposition to the extension
of time for the removal of Property Partners’ caveat over the O’Connell Street
property.
87 Having regard to his Honour’s ruling delivered on 28 June 2022, 55 it is apparent
that in assessing the balance of convenience in favour of removing the caveat,
Judge Burnett accepted Mr Lawrence’s evidence that the calculation of the likely
profit from the development included the amount of the ABC invoice as an
allegedly genuine liability for marketing the allotments. His Honour noted that
“ABC is a third party with whom the respondents entered into a written
agreement”.56 Relying undoubtedly on Mr Lawrence’s evidence, Judge Burnett
ordered that the caveat be removed on the respondents’ undertaking to the Court
that they would pay into the Court Suitors Fund $150,000 within 24 hours of
settlement on the sale of the sixth of the 13 lots comprising the O’Connell Street
subdivision.57
88 The ”ABC story” was advanced again in an affidavit made on 14 September 2022
by the respondents’ solicitor by exhibiting the 22 April 2022 solicitors letter in
support of the respondents’ application for costs of the applicants’ application to
extend the time for the removal of the caveat.58 On 21 September 2022, having
regard to this affidavit, Judge Burnett ordered that the respondents have 70% of
49 Applicants Written Closing [190].
50 Exhibit CGM2 to Exhibit A24 (FDN 27).
51 Ibid.
52 Exhibit A2.51 [3.3].
53 Exhibit A25 (FDN 11) which was read into evidence on 22 June 2022 as Exhibit R3.
54 This affidavit (FDN 17) was not tendered at trial but was read into evidence on 22 June 2022 as
Exhibit R4.
55 FDN 38.
56 Ibid at 13.
57 Granted Order (FDN 24).
58 Exhibit A24.
-- 21 of 105 --
[2026] SADC 3
18
their costs of and incidental to the application to extend the time for the removal
of the caveat on the standard basis.59
89 On 1 May 2023, Mr Lawrence made a third affidavit60 advancing the “ABC story”
in support of the respondents’ interlocutory application to be relieved of the
existing undertaking provided to the Court on 28 June 2022 as a condition of an
order to remove the caveat over the O’Connell Street property. This application
(and others) were argued before Judge Burnett on 19 April and 3 May
2023. Following the hearing, the respondents did not press their application to be
relieved of their existing undertaking to the Court.61 On 26 May 2023, Judge
Burnett dismissed the respondents’ application to vary their existing undertaking
to the Court.62 The undertaking remains in place.
90 On 18 June 2024, Mr Lawrence made a fourth affidavit for “the purpose of
correcting various paragraphs of the affidavits filed” by him in this proceeding.
In summary, Mr Lawrence affirmed that previous statements made in his three
earlier affidavits about the consultancy fee arising under the ABC agreement were
false and therefore the expected net profit calculations were understated.63 He
further affirmed that in respect of his statement in his second affidavit that it was
his intention that the amount owing to ABC would be paid from the sale proceeds
for O’Connell Street:64
As the ABC Agreement was not a genuine cost of the O’Connell Street Property
Development, the intention stated…is not now my intention…I accept the rejection of
Mr Chehade of the ABC Agreement as a genuine cost of the Project.
91 Further, although he had signed the ABC agreement on 21 April 2022,
Mr Lawrence affirmed it was not a valid agreement, the respondents did not intend
that ABC would perform any consultancy works and to the extent that ABC did
perform any works for the development, they would not be remunerated. He
further affirmed that ABC only undertook a very small part of the work and did
not substantially complete the scope of works set out in the ABC agreement. The
ABC fee was therefore not a genuine development cost.65
92 Mr Lawrence’s affidavit concluded:66
I sincerely apologise to the Court for deposing to the false statements and implications in
my previous Affidavits that are referred to herein.
59 FDN 32.
60 Exhibit A26 (FDN 49).
61 Chehade & Sons Constructions Pty Ltd & Anor v Lawrdo Super Pty Ltd & Anor [2023] SADC 62 at [3].
62 FDN 58.
63 Exhibit A2.51 [2]-[3] (FDN 78).
64 Ibid at [4]-[5].
65 Ibid at [6].
66 Ibid at [8].
-- 22 of 105 --
[2026] SADC 3
19
93 The respondents amended their defence to reflect the matters Mr Lawrence
identified as false in his fourth affidavit.67
94 In cross-examination, Mr Lawrence accepted he intended by his affidavits to
convey that the ABC consultancy fee was a genuine project cost. In answer to a
question from the bench, Mr Lawrence explained that he intended to pay ABC the
amount of its invoice but he would have then had all of that money returned to
him.68
95 When asked in cross-examination whether he had lied in his May 2023 affidavit,
Mr Lawrence admitted he had deliberately misled the Court for which he
apologised.69 He also admitted he did so because he wanted to show the lowest
possible profit position for the O’Connell Street development.70
96 Despite the overwhelming evidence to the contrary, the respondents submitted in
closing that:71
Lawrence was a witness of truth and did his best to assist the Court. The Applicants sought
to make a lot of a previous inconsistency in relation to a cost of the O’Connell St project.
This error was corrected by Lawrence in advance of the trial and does not impugn the
remainder of his testimony.
97 This submission is devoid of merit. It is an egregious understatement in the proven
circumstances to describe Mr Lawrence’s false affidavit evidence as “a previous
inconsistency in relation to a cost” or a mere “error [that] was corrected” in
advance of trial. In fact, Mr Lawrence made deliberately false statements designed
to mislead the Court and secure a forensic advantage for the respondents in
interlocutory proceedings. Mr Lawrence caused these false statements to be
repeated on a number of occasions and has given no defensible explanation or
excuse for his conduct.
98 The applicants submitted the Court should find that Mr Lawrence is someone who
is prepared to lie on oath if he considers that the answers would benefit his case.
Having regard to all of the evidence, I accept this submission and reject
Mr Lawrence’s denial that this is so. I found Mr Lawrence overall to be an
unreliable and untruthful witness and do not find the admissions he made before
trial about his false affidavit evidence exculpatory. As a result, I do not accept
Mr Lawrence’s evidence except where it is an admission against interest, it is not
material or uncontentious or confirmed by and consistent with other reliable
evidence. Where his evidence is contentious and conflicts with Mr Chehade’s
evidence, I have generally preferred Mr Chehade’s evidence.
67 Defence [36].
68 T442.13-.22.
69 T447.19-.20.
70 T457.28-.31.
71 Respondents Written Closing [3].
-- 23 of 105 --
[2026] SADC 3
20
Ms Rossi
99 Ms Luisa Rossi is a registered tax agent and operates an accounting and
bookkeeping business, Painless Accounting. She has been serving clients from the
property development and construction industry since 2006.
100 From 2006 to 2011 and again from 2015 onwards, Ms Rossi kept the books for
Mr Chehade and his entities including Chehade Constructions, as well as other
clients. From 2015, Ms Rossi also kept the accounting records and did the
bookkeeping for the joint ventures between Mr Chehade’s and Mr Lawrence’s
entities. For their joint ventures, Ms Rossi regarded both Mr Chehade and
Mr Lawrence (and their entities) as her clients and undertook her work in both of
their best interests. She regularly met with and took instructions from both
Mr Chehade and Mr Lawrence. If there was any inconsistency between their
instructions or disagreement, she would tell them to talk to each other and come to
an agreement and instruct her accordingly.
101 Ms Rossi gave evidence on limited discrete topics including the Baldock Road
GST issue and her instructions as to the calculation of interest from time to time.
Her cross-examination was brief and her evidence not seriously challenged.
102 Ms Rossi should be accepted as a reliable witness of truth whose evidence was
unshaken in cross-examination. She was of assistance to the Court on the GST and
interest issues.
Mr McPharlin
103 Mr Hugh McPharlin is an experienced forensic accountant. His expertise and
experience in his field were not challenged and his oral evidence was brief.
104 The applicants relied on an expert report prepared by Mr McPharlin that was
received in evidence without objection for the calculation of their 50% profit share
for the O’Connell Street development.72
105 The respondents contended Mr McPharlin’s evidence was of little assistance since
it was “no more than an accounting exercise based on figures that he was
provided”.73 Whilst I accept the latter was the case, Mr McPharlin’s report was of
assistance in adding up the numbers. For the reasons discussed below, whilst
further adjustments are required to calculate Property Partners’ 50% profit share,
Mr McPharlin’s report is a useful starting point.74
Mr Sale
106 Mr Chris Sale is a certified quantity surveyor, with a diploma in construction
economics and more than 45 years of experience in the construction industry. To
formulate its contractual damages claim, Chehade Constructions relied on an
72 Exhibit A20.
73 Respondents Written Closing [5].
74 See [496]-[508] below.
-- 24 of 105 --
[2026] SADC 3
21
expert report prepared by Mr Sale that was received in evidence without
objection.75
107 The respondents did not challenge Mr Sale’s expertise or experience or his
opinions, save in an immaterial respect and to say they were of little assistance.
Contrary to the respondents’ submissions, Mr Sale’s opinions were of assistance
in formulating Chehade Constructions’ contractual damages claim, as discussed
later in these reasons.76
FACTS
The Parties
Property Partners
108 Property Partners (the second applicant) carries on business as a property
developer. Its sole director from 30 September 2010 until 16 March 2022 was
Mr Chehade.77 It is the vehicle by which Mr Chehade participated in developing
residential properties with Mr Lawrence and his entities, the respondent
companies, as joint venturers since December 2011.
The Lawrdo Group
109 Whilst Mr Lawrence was party to the written joint venture agreement for the first
development (Baldock Road), his entity Lawrdo Investments (the second
respondent) was nominated as a purchaser of the land at settlement. Lawrdo
Investments was the vehicle by which Mr Lawrence participated in the next six
joint ventures completed in 2015. From 2016, either or both of Mr Lawrence’s
entities, Lawrdo Investments and Lawrdo Super (the first respondent), were parties
to the joint venture agreements.
Chehade Constructions
110 Chehade Constructions (the first applicant) was incorporated on 6 January 2009.
It is a building work contractor licensed from 21 December 2016 to carry out
additions, alterations and commercial and residential building work of certain
classes.78
111 Its sole director from 6 January 2009 until 28 September 2017 was Mr Chehade.
On 28 September 2017, Mr Chehade’s wife, Ms Rola Chehade was appointed as a
second director. Mr Chehade resigned as a director on 28 September 2018
following insurance issues arising from his conviction in 2015 for breaching real
75 Exhibit A21.
76 See [509]-[516] below.
77 Exhibit A2.56. Mr Chehade’s wife, Rola Chehade was appointed sole director in place of Mr Chehade
on 16 March 2022 and Mr Chehade reappointed on 15 June 2023.
78 Exhibit A22.
-- 25 of 105 --
[2026] SADC 3
22
estate laws that was upheld on appeal in mid-2016. Mr Chehade was reappointed
as a director on 15 June 2023.79
112 No point was taken about Mr Chehade’s authority to legally bind Chehade
Constructions although he was not a director at all relevant times.
113 From early 2017, Chehade Constructions was engaged to undertake building
renovation works on the Charmaine Avenue, Glen Rovala Street and Upton Street
properties under oral contracts made by Mr Chehade on behalf of Chehade
Constructions and Mr Lawrence on behalf of Lawrdo Investments or Lawrdo
Super (depending on which entity was the registered proprietor of the property).80
114 Chehade Constructions was also engaged under written building contracts by
either of Lawrdo Investments or Lawrdo Super (depending on which entity was
the registered proprietor of the property) to build houses on each of Gregory Street,
Radar Street and Chicklade Street that were made sometime in about 2019, 22 May
2019 and 15 September 2020, respectively.81
115 The written contracts were all in the same form. It was a term of each of these
contracts that the price that Chehade Constructions would be entitled to charge
Lawrdo Investments and/or Lawrdo Super and be paid on a cost plus 15% basis.82
116 Whether Chehade Constructions is a party to the joint venture that incontrovertibly
existed between Property Partners, Lawrdo Investments and Lawrdo Super and has
an entitlement to undertake the building work for O’Connell Street is contentious
and considered later in these reasons.83
Integrity New Homes
117 Prior to December 2016, the building work for the parties’ joint ventures was
carried out by Fazche Pty Ltd trading as Integrity New Homes. Mr Chehade was
a director of this company from 12 March to 30 June 2015 and one of its
shareholders.
The Beginning
118 The transactions the subject of contention had their genesis in a series of joint
ventures by Mr Chehade and Mr Lawrence established to develop residential
properties with the object of equally sharing profits between them after payment
of the purchase price of the property and development and holding costs.
119 Their first development (Baldock Road) came about after Mr Chehade had spoken
at a property investment seminar in late 2011 and sought out potential investors
for an opportunity he had identified. Mr Lawrence was introduced to him as a
79 Exhibit A2.57.
80 T407.14-408.10.
81 Exhibit A2.22 (Gregory Street); Exhibit A3.12 (Radar Street); Exhibit A4B.4.
82 Ibid.
83 See [375]-[429] below.
-- 26 of 105 --
[2026] SADC 3
23
potential investor in property development ventures. At the time, Mr Chehade was
a licensed real estate agent and Mr Lawrence an engineering project manager with
BAE Systems with no experience in property development.
120 After initial email contact, they first met at Mr Chehade’s office. Mr Chehade
outlined his business model for a joint venture to acquire and develop residential
property. Basically, he told Mr Lawrence that Mr Chehade’s contribution would
be to identify and secure a contract to purchase the property and manage all the
work required to subdivide, renovate, build and market the subdivided properties
at a profit. Mr Lawrence’s contribution as his joint venture partner would be to
fund the development. Profits would be shared equally.
121 Mr Chehade gave Mr Lawrence his written joint venture agreement and a power
of attorney to review. There is an unimportant dispute as to whether Mr Lawrence
took the documents away or signed them in this meeting. Mr Chehade said
Mr Lawrence took the documents away to review. Mr Lawrence denied this was
the case but in cross-examination he accepted he could be mistaken. It is more
likely that he did take them away given his inexperience in property development,
their importance for a new business venture and Mr Lawrence’s subsequent email
referring to a meeting with a lawyer to establish corporate structures.
122 Their first two developments (Baldock Road and Lauder Street) were established
under written joint venture agreements.
The First Development
123 The first property they developed as joint venturers was a house on a corner block
at 54 Baldock Road, Ingle Farm. It was established by a written contract made
between Property Partners and Mr Lawrence on 15 December 2011 (the First
Agreement).
124 Its terms were as follows:
• Clause 2 provides the terms of the joint venture continue until terminated
either on completion and sale of the property and finalisation of all accounts
between the joint venturers or mutual written consent or on failure to remedy
a default after 14 days’ written notice.
• Clause 3 provides that the property to be acquired would remain solely
registered in the name of Mr Lawrence.
• Clause 4 provides that Mr Lawrence would fund the joint venture as equity
or as debt by a bank loan from the Commonwealth Bank secured by a
mortgage over the property. All further contributions to the joint venture
expenses were to be funded by Mr Lawrence, with “such amounts and the
manner of the funding to be determined by mutual agreement from time to
-- 27 of 105 --
[2026] SADC 3
24
time”.84 Clause 4(g) provides that any rental or other income shall be applied
at the earliest opportunity in repaying Mr Lawrence’s financial contributions
taking into consideration income (if any) and joint venture expenses.
• Clauses 4(d) and 6 provide that Property Partners shall manage and
coordinate the entire joint venture until completion and, subject to the terms
of the agreement, have joint control of the joint venture with Mr Lawrence.
• Clause 5 provides that Property Partners is entitled to lodge a caveat over the
property to secure its entitlements hereunder should it desire.
• Clause 5 further provides for the manner of development. Firstly, planning
consent and development approval is to be sought for a subdivision into three
allotments; secondly the three allotments are to be marketed for sale; thirdly
if the land is not sold, three community title houses are to be constructed and
sold; and fourthly, by tenanting the three houses if not sold.85
• Clause 7 provides that the joint venturers shall share any profits of losses in
equal proportions.
• Clause 9 provides that the joint venturers shall maintain at all times proper
and accurate accounting records and that the joint venturers should have free
and uninterrupted access to such records.
• Clause 10 provides the joint venturers’ duties are (among other things) to use
their best endeavours to promote the best interests of the joint venture,
consult and meet regularly with one another, be just and faithful to the other
in relation to all transactions and give a true account of the same when
reasonably required and inform the other of all information in respect of the
joint venture. Clause 18 provides that the relationship between the joint
venturers is not a partnership or a principal and agency relationship. By
clause 25, the joint venturers undertake to deal with each other in good faith.
• Clause 12 provides for restrictions on the joint venturers including (among
other things) not to incur any liabilities on behalf of the joint venture other
that in the ordinary course of business conducted in a normal and proper
manner and that the joint venturers shall not sell or transfer or deal with their
interest in their property except as provided in the agreement.
• Clause 13 provides the terms for sale of the property should there be a dispute
between the joint venturers they are unable to resolve amicably by written
notice being given to sell or by default of either joint venture party. The
proceeds of sale are to be applied to discharge of the mortgage first, sale costs
84 Exhibit A2.2.5.
85 None of the joint venture properties were developed in this manner.
-- 28 of 105 --
[2026] SADC 3
25
second, unpaid third party liabilities third and Mr Lawrence’s unpaid
contributions last.
• Clause 14 sets out the default provisions which also provide for the option of
purchasing the interest of the defaulting joint venture party.
125 Mr Chehade identified the Baldock Road property for development and he
contributed his expertise, experience, contacts and time in subdividing and
developing the property. Through Property Partners, he also organised the
necessary approvals for the subdivision of the property into two allotments and
adding of an extension to the rear of the existing house. In February 2013, both
the renovated house and the vacant allotment (as a house and land package) were
sold.
126 Mr Lawrence’s company Lawrdo Investments was nominated at settlement as the
purchaser of the property and contributed all of the funding for its purchase and
the development costs incurred. Interest was factored into the profit sharing
calculation on the basis of 80% of the purchase price at an agreed rate.
127 In 2013 after completion and sale of the two allotments, following an accounting
between the parties of the profit derived from their joint venture in developing this
property, a small profit was made and $2,149.42 including GST was distributed to
each of Property Partners and Lawrdo Investments.
128 Despite the equal sharing of profit in 2013, the respondents claim a set off in the
amount of $6,130.70 for GST payable on the sale of the development that they
contend should have been taken into account in calculating profit on the first joint
venture, alleging that in fact a loss was made.86
The Second Development
129 The second property developed by Property Partners and Lawrdo Investments as
joint venturers was a house at 4 Lauder Street, Ingle Farm.
130 The terms of the parties’ agreement to develop this property as a joint venture were
recorded in a written contract made between Property Partners and Lawrdo
Investments on 13 February 2013 in the same form as the First Agreement, save
there was no reference to bank funding. In evidence there were some ancillary
authorities executed by Mr Lawrence for Property Partners to act on behalf of
Lawrdo Investments in finalising all documentation, sales agency, purchase and
sale contracts and authorising all works on the property.
131 As for Baldock Road, Mr Chehade identified the property for development and
through Property Partners managed its development. Minor renovations were
carried out to the existing house (carport, fence, new driveway), the block was
86 See Defence [48.1] and [593]-[601] below.
-- 29 of 105 --
[2026] SADC 3
26
subdivided and the vacant land marketed as a house and land package by
Chehade’s real estate firm and Integrity New Homes.
132 Mr Lawrence through Lawrdo Investments funded all of the purchase and the
development costs. As for Baldock Road, interest was factored into the profit
sharing calculation on the basis of 80% of the purchase price at an agreed rate.
133 The development was completed in 2014 and the profit shared equally between
Property Partners and Lawrdo Investments.
Subsequent Developments
134 By early 2016, Property Partners and Lawrdo Investments had undertaken a further
five developments as joint venturers on the same fundamental terms to the first
two developments but without any formality as regards the terms of their
agreement or their decisions about how they progressed these projects. 87
135 These properties were as follows:
• 11 Dulkara Road, Ingle Farm
• 7 Goodall Road, Para Hills
• 27 Williamson Road, Para Hills
• 27 Hawke Street, Ridgehaven
• 6 Welsh Crescent, Para Hills
136 Each of these developments involved the purchase of a residential property in the
northern suburbs, subdivision into two allotments and renovation and sale of the
existing house and land. The vacant allotments for Dulkara Road, Hawke Street
and Welsh Crescent were sold as a house and land packages marketed through
Chehade’s real estate firm and Integrity New Homes. New houses were built on
the vacant allotments for Goodall Road and Williamson Road and then sold.
137 Each development began by Mr Chehade telling Mr Lawrence that he had found
another property. They then met at their local café and discussed the property, its
potential and essentially agreed to proceed without any express agreement about
the terms of their agreement to develop it as joint venturers. Unsurprisingly, neither
Mr Chehade nor Mr Lawrence were able to recall their initial discussions about
these properties with any greater specificity. In evidence they both agreed there
was no particular discussion about the terms of their joint venture agreement
because it was understood and agreed that they would develop the property as joint
87 MFI 1 [2].
-- 30 of 105 --
[2026] SADC 3
27
venturers, sharing profits equally on the same fundamental terms as the earlier
developments.88
138 As before, the purchase contract was entered into the name of Mr Chehade or his
entity and/or nominee and settled by the nomination of Lawrdo Investments as the
purchaser. Mr Chehade through Property Partners managed all the development
work from initial purchase through to sale, including managing all the work
necessary to subdivide the property and renovate the existing house or build a new
house on the vacant allotment for the joint venture parties if the land was not first
sold either as vacant land or as a house and land package.
139 Mr Lawrence funded their joint ventures by paying the purchase, development and
holding costs. As for their early joint ventures, interest was factored into the profit
sharing calculation on the basis of 80% of the purchase price at an agreed rate.
140 Any building works required by the joint venture were generally carried out by
Fazche Pty Ltd trading as Integrity New Homes on a cost plus 20% margin basis.
141 Mr Chehade and Mr Lawrence met regularly to discuss their joint ventures. There
is no substance to the contention that Mr Lawrence was not consulted or
uninformed of Mr Chehade’s relationship with Integrity New Homes or had no
input to how the developments progressed or what building company was used to
build on the land.
142 On completion, after an accounting of the project revenue and costs prepared by
Ms Rossi, the profits of each of these joint ventures were shared equally between
Property Partners and Lawrdo Investments. There is no substance to the suggestion
that the process was controlled by Mr Chehade and not transparent. The evidence
shows that Mr Lawrence dealt directly with Ms Rossi in questioning her
calculations without any interference from Mr Chehade.
143 All their joint ventures progressed to completion by the sale of the developed
properties and an accounting and equal sharing of the profit made.
2016 Changes
144 There is an important dispute on the pleadings about what was orally agreed
between Mr Chehade and Mr Lawrence in 2016 about the terms upon which they
would continue to develop properties together and share profits equally. The
applicants allege three key matters were agreed. First, that Mr Lawrence through
Lawrdo Super and Lawrdo Investments would fund the developments. Secondly,
that Mr Lawrence would receive a return on the monies provided at the Reserve
Bank of Australia cash rate plus 2%. Thirdly, that Chehade Constructions would
undertake any building works on a cost plus 15% basis instead of Integrity New
Homes. 89
88 Defence [1.1], [1.3] and [1.4]; T408.12-413.6.
89 Claim [3(b)].
-- 31 of 105 --
[2026] SADC 3
28
145 In their pleaded claim, the applicants identify this café meeting by reference to a
discussion where Mr Chehade said he was retiring from real estate and would work
full time in the property development business.90
146 In their defence, the respondents accepted there were discussions between
Mr Chehade and Mr Lawrence “around 2016” but otherwise denied these
allegations about agreed changes to their joint venture arrangements and relied on
the series of agreements pleaded earlier in answer to the applicants’ claim of an
overarching joint venture agreement.91
147 On the evidence, the relevant café meeting and discussion about Mr Chehade
getting out of real estate likely took place in about June 2016, shortly after
Mr Chehade had identified the Radar Street property as a development
opportunity.
148 As to the first two matters alleged by the applicants, whilst Lawrdo Super’s
involvement in funding their future development and interest may have been
discussed at this one meeting, ultimately it is not necessary to determine what was
said then (if anything at this time) about these matters for varying reasons. Indeed,
it is more than likely these matters were the subject of ongoing discussion from
June to December 2016. Accordingly, nothing was finalised in a single discussion
in June 2016 and intended to be legally binding.
149 First and in any event, Lawrdo Super’s involvement and participation in these
developments as a joint venture party is not contentious. Incontrovertibly, Lawrdo
Super funded the acquisition of four later developments: Radar Street, Charmaine
Avenue/Connie Street, O’Connell Street and Glen Rovala Street/Gregory Street.
Furthermore, having regard to the fact that the initial purchase contracts were
signed and settled for these properties at different times between June 2016 and
January 2018, it is most likely that Mr Chehade and
Mr Lawrence discussed and agreed Lawrdo Super’s participation in their joint
venture arrangements on a number of occasions during this period. Despite the
informality of their dealings, there was agreement for Lawrdo Super to participate
in each the various joint ventures that it did and such agreement was most likely
made proximate to the settlement of each of the relevant property.
150 Secondly, having regard to the various drafts of the interest provision in the draft
agreements exchanged between June and December 2016, it is more likely that the
first discussion about changing the interest rate to the Reserve Bank of Australia
cash rate plus 2% occurred closer to December 2016 than June 2016.92 However,
as discussed later in these reasons, on the proven evidence there was no agreement
made between Mr Chehade and Mr Lawrence for the interest rate to be applied in
calculating profit going forward to be in the terms alleged by the applicants. Had
I concluded otherwise, any agreement to this effect would have been superseded
90 Claim [3(a)].
91 Defence [3].
92 See [436]-[442].
-- 32 of 105 --
[2026] SADC 3
29
by their subsequent agreement made in February 2018 that the applicable rate
going forward would be 6.5%.93
151 The third of these alleged agreed changes is the subject of an important dispute
over the O’Connell Street development. For the reasons discussed below, the
reliable evidence does not establish that any oral agreement was made in 2016 for
Chehade Constructions to undertake any building works required to develop any
future properties as alleged by the applicants.94 However, the evidence does
establish that binding agreement for Chehade Constructions to carry out the
building works for the O’Connell Street development was made in 2020.95
Purchase of Radar Street
June 2016 Café Meeting
152 By about June 2016, Mr Chehade had identified the Radar Street property as a
further development opportunity and entered into a purchase contract in the name
of his company Kjtc Nominees Pty Ltd and/or nominee. He told Mr Lawrence
about it and they met at a café to discuss it as a new joint venture project.
153 Mr Chehade told Mr Lawrence he was going to focus on property development
fulltime and he was getting out of the building company he had been involved
with, Integrity New Homes. Mr Chehade gave Mr Lawrence a new form of joint
venture agreement for him to review and sign for Radar Street that his lawyers had
“renovated”.96
154 There is a dispute on the evidence about whether Mr Chehade told Mr Lawrence
the reason why he was getting out of real estate. This dispute is only relevant to
credit.
155 Mr Chehade said he told Mr Lawrence that he had lost his real estate licence.
Mr Lawrence disagreed. When it was put to Mr Chehade in cross-examination
that he had not told Mr Lawrence this, he insisted he had told him, said
Mr Lawrence knew and that it was all over the news. When Mr Lawrence was
pressed on this issue, he conceded that Mr Chehade told him he had legal issues
that he was addressing but maintained his ignorance about the detail. I prefer
Mr Chehade’s evidence on this issue. Given the publicity about Mr Chehade’s
conviction for contravening real estate laws and their good relationship at this time,
there was no reason for Mr Chehade not to tell Mr Lawrence about the nature of
his legal issues and how that affected their joint venture arrangements.
156 Mr Lawrence took the revised joint venture agreement away to review.
93 See [229]-[235] and [472]-[478].
94 See [398]-[413] below.
95 See [414]-[435] below.
96 T202.23.
-- 33 of 105 --
[2026] SADC 3
30
30 September 2016 Email
157 Mr Lawrence sent Mr Chehade an email on 30 September 2016, referring to their
last meeting. When that meeting was is not known. The subject of the email is
“Lawrdo SMSF Proposed JV Agreement and Power of Attorney”,97 confirming the
parties’ intention to involve Mr Lawrence’s SMSF in their joint ventures going
forward.
158 Mr Lawrence’s email stated that he was unable to accept Mr Chehade’s documents
on advice from his accountant, noting “some of the clauses have substantially
changed from our previous arrangements”. Instead, to “address some of [his]
fundamental issues”, he proposed an amended draft for review, acceptance and
discussion.98
159 The document is not marked up and the earlier version “renovated”99 by
Mr Chehade’s lawyers is not in evidence. It is therefore not possible to discern
what he meant specifically by substantial changes to the parties’ previous
arrangements. It is apparent however, format aside, that the revised draft was
modelled on the First Agreement and the parties accept that this was so. It contains
the same clause headings, numbering and much of the same wording including
identical boilerplate clauses. There is some simplification of the wording in places.
There are indications from the references to agreements to agree in some parts that
a non-lawyer has drafted parts of the document.
160 The draft identifies Radar Street as the property to be developed by the parties to
the draft agreement as joint venturers and oddly, it is post-dated: “7th day of
October 2016”.100
161 Mr Lawrence’s SMSF, Lawrdo Super, is now a proposed party and some obvious
changes have been made to a number of clauses with the aim of minimising its
risk.
162 For example, there is greater specificity provided particularly as to Property
Partners’ obligations and clauses 8 and 9 provide that Lawrdo Super is to establish
and control the bank account for the venture and keep the books and records, rather
than them being controlled and kept jointly.
163 By clause 6 providing for Property Partners’ equity contribution through the
identification, management and co-ordination of the project activities to
completion, there is considerably more detail of the development process to be
undertaken. Clause 10 now provides that the joint venturers will use their best
97 Exhibit A2.7.83.
98 Exhibit A2.7.83-.97.
99 T202.23.
100 Exhibit A2.7.86.
-- 34 of 105 --
[2026] SADC 3
31
endeavours to promote the best interest of the joint venture “to maximise the
profit”.101
164 Clause 13 has been substantially amended to address sale of the developed
property in the usual course of the joint venture and not where there is a dispute,
removing the right of Property Partners to have first preference to buy the property
at an agreed valuation in case of a dispute.102 Clause 14 concerning default has
been substantially redrafted to introduce an option for the non-defaulting party to
purchase the property and joint venture and provides for different scenarios
depending on who is the defaulting party.
165 Despite these changes, the fundamentals of the parties’ respective contributions to
the joint venture and the sharing any profit or loss in equal proportions remain
unchanged.
166 In this regard, clause 7 maintains the sharing of profits and losses in equal
proportions but provides for profits or losses to be mutually agreed (somewhat
uncertainly) and to be inclusive of specified costs. A significant change was
proposed as regards the parties’ previous agreement as to the basis of calculating
the interest to be paid to Lawrdo Super for funding the joint venture as follows:103
6. Interest based on an LVR of 80% for the total costs incurred by “A” (i.e. Property
Purchase, total development costs inclusive of Rates and Taxes);
167 It is uncontentious that for all of the parties’ previous joint ventures it was agreed
in calculating joint venture profit, interest was calculated at an agreed interest rate
on the basis of 80% of the purchase price of the property and not on total project
costs.
168 Mr Lawrence accepted that he was by this email proposing a change to the way
interest was calculated and paid to his entities as a joint venture cost.104
169 This draft was superseded by two subsequent drafts.
9 December 2016 Email
170 Mr Chehade did not reply to Mr Lawrence’s 30 September email, as was his habit.
The parties then met for breakfast on 9 December 2016 to further discuss the
development of Radar Street.
171 It was Mr Chehade’s evidence that he did not agree to change their existing
agreement for interest. Mr Chehade said he met with Mr Lawrence and said: “This
101 Exhibit A2.7.89.
102 Clause 13(b)(3) is unintelligible but nothing turned on this at trial.
103 Exhibit A2.7.88.
104 T337.31-.36; T495.24-.38.
-- 35 of 105 --
[2026] SADC 3
32
has to be changed back to the original agreement.”105 He was not happy with the
proposed change to charge interest on all project costs because:106
That wasn’t our agreement. Our agreement was only what the bank will lend you is what
get returns on. The bank doesn’t lend on council rates, water rates, development costs. So
it is only the 80. Our initial agreement was that you only get return on 80% like the bank,
of your money that you lent. That’s the agreement.
172 In cross-examination, Mr Chehade was not shaken. He denied he did not say at
their meeting that interest is only to be applied to the purchase price of the property
and said he did mention that to Mr Lawrence. The respondents’ submission that
he did not answer the question is incorrect.107
173 In examination in chief, Mr Lawrence gave generalised and unpersuasive evidence
that he had discussed his proposal for changing the basis upon which interest was
calculated as a project cost three or four times with Mr Chehade who agreed it was
acceptable saying: “I understood. I understand.”108
174 Later, in cross-examination, Mr Lawrence gave quite different evidence. He said
he recalled Mr Chehade not being happy about the proposed change to interest and
their conversation being:109
…on the lines of he was not content with the changes as proposed in this document, 80%
of the total cost and he advocated to change it to, I think it was the ABR [sic] rate plus 2%
which I ultimately agreed to subject to me adding the words, ‘or as mutually agreed’.
I remember that conversation taking place.
175 When pressed that it was more than just the rate that Mr Chehade was unhappy
about, Mr Lawrence said he did not recall that. When it was put to him that between
October and December 2016, Mr Chehade did not say anything to him to the effect
that he agreed with his changes, he answered emphatically: “Yes, he did.”110 He
said there were a number of meetings to agree the changes and these “changes”
were “finalised and agreed as a way to go forward on these developments”.111
176 I reject this evidence that Mr Chehade agreed to Mr Lawrence’s proposed change
to interest and find it untruthful. Not only was it contrary to Mr Lawrence’s
evidence that Mr Chehade was unhappy with the proposed change generally
(which evidence was consistent with Mr Chehade’s evidence which I accept) but
it was contrary to the contemporaneous emails attaching successive proposed
drafts that plainly show no agreement had been reached. Moreover, the proposed
additions of “or as mutually agreed” and a rate pegged to the RBA cash rate did
105 T78.24-.25.
106 T77.34-78.3.
107 T206.22-.29.
108 T340.38.
109 T496.7-.14.
110 T496.26.
111 T497.4-.5.
-- 36 of 105 --
[2026] SADC 3
33
not resolve Mr Chehade’s issue with interest being calculated on 80% of all project
costs.
177 On the afternoon of 9 December 2016, Mr Lawrence sent Mr Chehade an email
attaching another revised draft joint venture agreement and power of attorney for
Radar Street.
178 Mr Lawrence’s proposed changes are marked-up and his email message reads as
follows:112
Hi Nabil,
Thanks for Breakfast today, much appreciated.
Please find the changes incorporated as discussed with track changes =pplied [sic]. I
have also added the following:
• A front page to each of the documents
• Added four areas into the JV Agreement for your =esponsibilities [sic].
Please feel free to discuss accordingly – I think we are almost =here [sic] !!!!!
179 This email makes it plain that Mr Chehade and Mr Lawrence had still not reached
a binding agreement on the terms of the 30 September 2016 draft, let alone agreed
to change the basis upon which interest was factored into their calculation of joint
venture profit going forward.
180 Coversheet aside, it is apparent the draft agreement is a revision of the
30 September 2016 draft that was prepared from the starting point of the First
Agreement. The fundamentals of the parties’ respective contributions to the joint
venture and equal sharing of any profits or losses remained unchanged.
181 As his covering email says, Mr Lawrence has added to clause 6 additional
responsibilities for Property Partners’ management of the joint venture with regard
to maintenance of the property, preparation of construction budgets and timetables,
management of development timelines and required any insurances to be in the
name of Lawrdo Super.
182 Importantly, clause 7.6 now provided as to interest:113
6. Interest based on an LVR of 80% or otherwise agreed for the total costs incurred by
“A” [Lawrdo Super] (i.e. Property Purchase and/or Construction development costs).
The interest shall be calculated as being the Royal [sic] Bank Australia (RBA) Cash
Rate plus 2%
183 This is the first written reference to an interest rate pegged to the Reserve Bank of
Australia cash rate and the reference to ‘Royal’ is apparently
Mr Lawrence’s mistake. Again, these amendments do not address Mr Chehade’s
objection to Mr Lawrence’s entities charging interest on 80% of all project costs.
112 Exhibit A2.8.98.
113 Exhibit A2.8.103.
-- 37 of 105 --
[2026] SADC 3
34
184 Mr Chehade did not reply to this email in writing.
Settlement of Radar Street
185 On 12 December 2016, Lawrdo Super became the registered proprietor of
17 Radar Street, St Agnes in performance of an agreement made between
Mr Chehade and Mr Lawrence that they would develop it as a joint venture through
their entities Property Partners and Lawrdo Super.
186 Despite the exchange of draft agreements contemplating the purchase and
development of this property before and after settlement, the parties did not record
the terms of their joint venture for this property in writing.
15 December 2016 Email
187 By email dated 15 December 2016, Mr Lawrence sent Mr Chehade a completely
different draft agreement with the following message:114
Hi Nabil,
As discussed, please find the Agreement will be used [sic] for the Development activities
going forward. This was reviewed by my Accountant to better protects [sic] my Super
Unit Trust.
188 The attached agreement expressly identifies Radar Street as the property to be
developed in Recital A and Exhibit A, although it is incomplete in a minor respect
(Recital B).
189 This was the first time this form of agreement was proposed to Mr Chehade, it
apparently having been prepared with the help of Mr Lawrence’s accountant and
not previously the subject of discussion between Mr Chehade and Mr Lawrence.
190 It is styled as “Project Manager Services Agreement” (PMS Agreement) and
provides for a fundamental change to the nature of the parties’ existing relationship
as joint venturers. It provides for Property Partners to be engaged as a project
manager to manage the planning and development of the property for its owner
Lawrdo Super. Clause 3 provides that Property Partners is to be compensated for
its service by “a share in any profits derived in equal proportions”,115 but profits
are to be mutually agreed and inclusive of specified costs including interest as
follows:116
5. Interest based on an LVR of 80% or otherwise agreed for the total costs incurred by
“A” (i.e. Property Purchase and/or Construction development costs). The interest
shall be calculated as being the Royal [sic] Bank Australia (RBA) Cash Rate plus
2%
114 Exhibit A2.9.116.
115 Exhibit A2.9.118.
116 Exhibit A2.9.119. The incorrect reference in the previous draft of this clause to the “Royal Bank
Australia” is perpetuated.
-- 38 of 105 --
[2026] SADC 3
35
191 In cross-examination, Mr Lawrence’s evidence about the significance of the draft
PMS Agreement was unpersuasive. He denied that it was a completely different
document. He said:117
The terms I believe are the same. It’s just a different format because I wanted to make it
more a formal contract document.
192 He then said this was the “final version” which “was agreed to go forward with”118
(contrary to his earlier evidence that Mr Chehade had already agreed to the terms
of the previous draft agreements). This was apparently despite not previously
discussing with Mr Chehade his engagement as a project manager instead of being
a joint venturer:119
That was never discussed, that was proposed by my accountant to change it because he
thought that that reflected what he was doing.
193 Mr Lawrence then confirmed his proposal that the PMS Agreement would be the
agreement to be used going forward, and not the previous drafts he had circulated
by email on 30 September and 9 December 2016: “It was discussed with
Mr Chehade”120 and “I believed that I had an understanding with Mr Chehade that
that [the PMS Agreement] was the document to be used.”121
194 Mr Lawrence’s evidence in cross-examination as to why he had that belief when
Mr Chehade had not seen the draft PMS Agreement before and he had sent it to
him after settlement of the purchase of Radar Street was not compelling. The
concessions that he later made that he had sent the document as “a closure action”
prior to departing for the UK and did not sign it,122 and wished he had closed it out
before he left were telling.
195 Most fundamentally, Mr Lawrence accepted there was no conversation or email
from Mr Chehade saying: ‘I accept the terms of the PMS Agreement’.123
196 Mr Chehade gave evidence that he noticed the email with the draft PMS
Agreement some days after it was sent (but before Christmas) and as soon as he
read the heading, he objected to it: “I wasn’t an employee of Dillan… I was a joint
venturer with him.”124 He then tried to telephone Mr Lawrence who was travelling
overseas, messaged him and when they eventually spoke:125
117 T497.110-.16.
118 T499.14-.15.
119 T499.19-.21.
120 T499.33.
121 T502.28-30.
122 T503.7.
123 T501.19-25.
124 T210.5-.8.
125 T81.1-.17.
-- 39 of 105 --
[2026] SADC 3
36
Then I said to him, I said 'Look, I've received this email from you, what's it all about?'. He
goes 'you know that's what - not exact words, but he sort of said to me that's what my
accountant's already replied'. I said 'I'm sorry man, but at the end of the day we've got a
joint venture between myself and you. I don't know what this Property Management [sic]
Services Agreement is about -', I said '- but I don't work for anyone. I've always been
working for myself. If that's the way you want to go, I'm not interested, see you later'. And
he goes 'Nah, nah', I said 'Look', and then we put it past us, and at that moment, in the same
phone conversation I said to him 'I've got this deal and this deal that I've secured'. Actually
it was one deal, the one at Lawrie Street, Pooraka, which was based on the same phone call.
I said 'I've got another one which I'm working with', and that's my brother-in-law's property.
197 Mr Chehade’s evidence in cross-examination was consistent and, as the applicants
submit, “rings true.”126 I accept that Mr Chehade told Mr Lawrence by telephone
that he was not interested in any other arrangement but a joint venture and therefore
did not agree with the terms of the draft PMS Agreement or that it should govern
their relationship going forward. I further accept Mr Chehade’s evidence that
Mr Lawrence did not press the issue of the draft PMS Agreement any further and
the parties continued to conduct their joint ventures on the same informally agreed
terms as before, save for the involvement of Lawrdo Super.
Third Party Ventures
198 In January and August 2017, Property Partners and Lawrdo Investments entered
into two written “Development Management Agreements” with third parties for
the subdivision and development of two residential properties.
199 The first of these agreements concerned the development of property at
16a Liberman Road, Para Hills with Yehya El Haj and Safa El Haj, relatives of
Mr Chehade. This was the property Mr Chehade had told Mr Lawrence about in
his telephone conversation at Christmas time when Mr Lawrence was in the UK.
The second concerned the development of property at 15 Barakoola Street,
Pooraka that was entered into on 2 August 2017 with a third party, Maha
Ghazzawi.127
200 The first agreement concerning Liberman Road was executed on 20 January
2017.128 It was prepared by Mr Lawrence. It is similarly styled as the draft joint
venture agreements Mr Lawrence proposed to Mr Chehade in September and
December 2016 but provides for a very different commercial arrangement between
the parties, described as a development project.
201 By contrast to the parties’ joint ventures the subject of dispute, the development
management agreements provide for the subdivision and development of land
owned by the third parties.
202 Property Partners’ role is as ‘Project Manager’ and Lawrdo Investments’ role is as
‘Banker’. However, together, Property Partners and Lawrdo Investments are
126 Applicants Written Closing [45].
127 Exhibit A29.
128 Exhibit A2.10.
-- 40 of 105 --
[2026] SADC 3
37
defined as the ‘Property Developers’. They are appointed by the owners to
construct a three-bedroom house for which the owners will be paid $140,000 as
their equity contribution to the project. They are to be paid in two instalments, one
of $25,000 before any improvements are carried out and the balance of $115,000
once the property is sold or on expiry of the agreement.
203 The development management agreement for Liberman Road contemplates the
entry into a building contract between the owners and a builder with the ‘Property
Developers’ bearing all the constructions costs as part of the project costs.
204 The provision for profits and losses is modelled on the same ‘agreement to agree’
clause in the draft September joint venture agreement. As regards interest, it
provides:129
v) interest based on an LVR of 80% or otherwise agreed for the total costs incurred by the
Banker (i.e. Property Purchase and/or Construction development costs). The interest
shall be calculated as being the Reserve Bank Australia (RBA) Cash Rate plus 2%;
205 I accept the applicants’ submission that these agreements do not assist in resolving
the disputes between the parties about the terms of their joint ventures which turn
on a factual inquiry about what was said as between Mr Chehade and Mr Lawrence
at key junctures in their dealings concerning the disputed joint ventures in
circumstances where their commercial interests are quite different from the third
party ventures.
Charmaine Avenue Purchase – March 2017
206 In about February or March 2017, Mr Chehade identified the Charmaine Avenue
property for development. On 2 March 2017, Mr Chehade signed a contract
naming himself or his nominee as purchaser for a price of $317,000. At settlement
on 2 June 2017, Lawrdo Super was nominated as the purchaser and became the
registered proprietor of this property in performance of an agreement made
between Mr Chehade and Mr Lawrence that they would develop it as a joint
venture through their entities Property Partners and Lawrdo Super.
207 Mr Chehade told Mr Lawrence about this property at or about the time he signed
the contract and recalled discussing its purchase and development at the same time
as the Upton Street property. It had been a rental property and the house was in a
fairly poor condition.
208 There are no written terms recording the parties’ agreement to purchase and
develop this property. The evidence shows that Mr Chehade and Mr Lawrence
met from time to time and discussed and made decisions about things that needed
to be done as they arose including for example the appointment of Ray White as
sales agent, to sell the house block by auction and set a reserve price at auction of
$375,000.
129 Exhibit A2.10.142.
-- 41 of 105 --
[2026] SADC 3
38
209 The Charmaine Avenue property was subdivided and the house block sold at
auction after a substantial renovation had been carried out by Chehade
Constructions. Settlement occurred on 25 January 2018.
210 The subdivided vacant block on Connie Street was put on the market when the
house block was sold but it did not sell immediately. Ray White was the listed
agent.
Upton Street Purchase – March 2017
211 In about March 2014, Mr Chehade identified a house on a corner block at
14 Upton Street, Elizabeth Vale as a development opportunity. On 14 March 2017,
he entered into a contract naming himself or his nominee as a purchaser for the
price of $190,000.
212 Mr Chehade told Mr Lawrence about this property in about March 2017 at one of
their café meetings. They proceeded with the purchase and development of this
property together after Mr Lawrence texted Mr Chehade advising that he could get
“a loan ($200K) from a family member to cover Upton”.130
213 On 7 July 2017, settlement took place. Lawrdo Investments as trustee for the
Lawrdo Family Trust was nominated by Mr Chehade as the purchaser.
214 There is no written record of the terms of the parties’ agreement to purchase and
develop this property as a joint venture nor was there any express oral agreement
about the terms of their joint venture.
215 The respondents’ pleaded case is that Mr Chehade and Mr Lawrence agreed in oral
discussions in about 2017 that Property Partners and Lawrdo Investments would
split any profits or losses equally from the Upton Street/Chicklade Street
development.131
216 Whilst consistent in effect, Mr Lawrence’s evidence in cross-examination was
more nuanced. Mr Lawrence said that when he and Mr Chehade initially met to
discuss Upton Street, they did not go through the terms on which they would do a
deal. He accepted that was because they had done so many joint ventures in the
past and there was “no argument” that it was going be a 50/50 split in terms of
profit share.132 Having regard to the way in which Mr Chehade and Mr Lawrence
dealt with one another in establishing and conducting all their previous joint
ventures, a reasonable businessperson in their position would have understood they
intended to develop the Upton Street property on the same fundamental terms as
their earlier joint ventures.
130 Exhibit A4B.2.9.
131 Defence [1.6].
132 T555.1-.19.
-- 42 of 105 --
[2026] SADC 3
39
217 As with the previous developments, Property Partners managed the development
works and Lawrdo Investments funded the purchase of the property and other
development costs.
218 The vacant allotment known as 2 Chicklade Street was marketed initially for
$119,000 and then the price dropped to about $100,000 without finding a buyer.133
Two different sales agents were retained before Ray White was appointed in July
2020.
Glen Rovala Street Purchase – April 2017
219 On 20 April 2017 at settlement of the purchase, Lawrdo Super was nominated as
the purchaser and became its registered proprietor of 2 Glen Rovala Street. On the
application of Property Partners, it was subdivided into two titles on 23 October
2017. The vacant block was known as 18 Gregrory Street, Brahma Lodge.
220 During 2017, the existing house on Glen Rovala Street was renovated by Chehade
Constructions under an oral building contract for the agreed price of cost plus 15%.
Mr Lawrence complained by email about an unexpected overrun in the renovation
costs in July 2017.134
221 The house block was sold on 24 January 2018.
222 Lawrdo Super and Chehade Constructions entered into a written contract to build
a house on the Gregory Street vacant land at an agreed price of cost plus 15% in
or about 2019.
O’Connell Street Purchase Contract – April 2017
223 On 4 April 2017, Mr Chehade signed a contract for the purchase of vacant land at
6 O’Connell Street, Salisbury Downs in the name of Property Partners and/or
nominee for the price of $640,000. He also signed a contract for the land opposite
it, 7 O’Connell Street.
224 Mr Chehade and Mr Lawrence met to discuss these development opportunities.
Mr Chehade told Mr Lawrence he had secured both
6 and 7 O’Connell Street. Mr Lawrence told him his funds would not stretch that
far, so they decided to purchase and develop the larger block, No. 6, as a joint
venture.
225 The contracted settlement date of 1 May 2017 was deferred multiple times due to
Mr Lawrence’s inability to fund its purchase. To extend the settlement date,
Mr Chehade agreed on their behalf to pay the vendors an increased deposit sum
and default interest.
133 T103.32.-.33.
134 Exhibit A2.11.
-- 43 of 105 --
[2026] SADC 3
40
226 The land area was 3,958 sqm. In about November 2017, Mr Chehade instructed
the architect ET Design to prepare plans for subdividing it into 12 blocks.
Ultimately the architect was able to configure it into 13 blocks. The revised plans
were emailed to Mr Lawrence on 29 November 2017 to which he responded
enthusiastically: “Looks great - Very sexy. Would like to run over the numbers
again…...”135
Settlement of O’Connell Street – January 2018
227 On 31 January 2018, the land was conveyed to Lawrdo Super and Lawrdo
Investments as tenants in common in the proportions of 90/10 respectively. The
purchase was funded in part by sale proceeds from Glen Rovala Street and
Charmaine Avenue. Lawrdo Investments borrowed the shortfall from
Mr Lawrence’s family members, since Lawrdo Super could not. This was why
Lawrdo Investments became a part owner.
228 At this time, the parties’ expectation was that development costs for O’Connell
Street would be funded from completion of other joint ventures as the developed
properties were sold. How they would ultimately develop it was to be discussed
and agreed.
February 2018 Discussion & Emails
229 On 20 February 2018, Mr Chehade and Mr Lawrence exchanged emails following
a discussion about interest. These emails confirm that it was agreed that the interest
rate to be applied in calculating profit going forward was 6.5%. This is expressly
stated in the covering email and in the cell labelled “APR” in the attached
spreadsheet listing the developments then underway: Glen Rovala Street/Gregory
Street, Charmaine Avenue/Connie Street, Upton Street/Chicklade Street,
Liberman Road, Barakoola Street, Radar Street and O’Connell Street.136
230 This agreement was made in circumstances where interest rates were dropping and
according to Mr Chehade, Mr Lawrence wanted a higher return than the cash rate
plus 2%.
231 That Mr Lawrence was agitating to be paid more interest is plain from the face of
the email and the attached spreadsheet. The spreadsheet records
Mr Lawrence’s observations about perceived disadvantages to the Lawrdo Group
from the current arrangement as the basis for his recommendations for varying
their agreement on interest as follows. 137
135 Exhibit A5.2.17.
136 Exhibit A2.14.234.
137 Ibid.
-- 44 of 105 --
[2026] SADC 3
41
For Non JVs:
LawrDo Interest = ( PropertyPrice + Build/Reno Cost at Completion ) x LVR x APR x
ProjectDuration + (PropertyPrice + Build/Reno Cost at Completion ) x ( 1 +
%BudgetVariation ) x %EST fee
For JVs:
LawrDo Interest = 10% x ( Build Cost at Completion )
232 Mr Lawrence’s recommendations are new terms and yet another proposed
variation to their existing agreement on interest.
233 The respondents do not suggest Mr Chehade agreed to these recommendations
made by Mr Lawrence for calculating interest. Indeed, in examination in chief
Mr Lawrence had no recollection of any discussion about having agreed to this
rate but said in cross-examination the 6.5% interest rate only applied to the
Liberman Road development.
234 I reject Mr Lawrence’s evidence that this rate only applied to Liberman Road. It
is contrary to the covering email.
235 I find that on about 20 February 2018, Mr Chehade and Mr Lawrence agreed that
the interest rate to be applied in calculating profit for all joint ventures going
forward was 6.5%.
Upton Street Sale – June 2018
236 The Upton Street property was subdivided into two allotments and the existing
house on the Upton Street block was renovated by Chehade Constructions and sold
for $220,000 in June 2018.
Connie Street Sale – October 2018
237 The subdivided land on Connie Street was eventually sold as a house and land
package to third party introduced by ABC trading as ‘Your Property Academy’ for
a commission of $20,000 payable in two instalments. When the sale of the
property settled in October 2018, Lawrdo Super paid $10,000 of the commission
due to ‘Your Property Academy’.
238 Chehade Constructions signed a written building contract138 with the purchaser on
26 September 2018. Property Partners paid the outstanding balance of $10,000 due
to ‘Your Property Academy’ after the foundation was poured for the new build
because Mr Lawrence did not have the funds to do so.
239 As with their previous joint ventures, Property Partners managed the development
works but this time, Lawrdo Super funded the purchase of the property and some
but not all of the development costs. Property Partners invoiced Lawrdo Super on
138 Exhibit A4.9.38.
-- 45 of 105 --
[2026] SADC 3
42
27 February 2020 for reimbursement of the $10,000 sales commission it paid
‘Your Property Academy’ for Connie Street.
240 This invoice was not paid and is the subject of the dispute addressed later in the
reasons.139
January 2019 – Cash Flow Difficulties
241 By January 2019, the Radar Street, Glen Rovala Street, and Upton Street
developments had still not been completed. Upton Street had only settled in June
2018 and Connie Street in September 2018.
242 The development of O’Connell Street was effectively on hold, despite initial plans
for the subdivision being drawn more than a year earlier in late November 2017.
Mr Lawrence had cash flow problems. When he nominated Lawrdo Super as the
90% owner of O’Connell Street, he had not thought about the challenges there
would be for it to borrow money as a SMSF. The ongoing joint ventures were not
generating any income. Mr Lawrence explained in evidence that they did not do
anything to develop O’Connell Street because “the funds weren’t there, there were
higher priorities to address and that was to complete the other projects.”140
243 These cash flow difficulties are referred to in an agenda for a meeting scheduled
for 11 January 2019 prepared by Mr Lawrence. There is a discussion item:
“Cashflow strategy to finish off Glen Rovala, Radar St and Upton St.”141
Radar Street Approval – April 2019
244 In furtherance of the Radar Street joint venture, Property Partners sought and on
22 April 2019 obtained approval for the subdivision of the land into two
allotments. This was more than two years since its purchase. The subdivision was
not straightforward due to issues arising from a creek running through the land and
the need to change the current zoning.
245 The plan of division was deposited in June 2019.
30 April 2019 Email
246 By the end of April 2019, there had been limited further progress towards
completion of the parties’ ongoing joint ventures. Although council approval had
been granted to subdivide the vacant blocks at Radar Street and Upton
Street/Chicklade Street, the joint venture parties were unable to build on these
properties without further funding.
247 On 30 April 2019, Mr Lawrence sent Mr Chehade the following email:142
139 See [544]-[557] below.
140 T598.4-.6.
141 Exhibit A2.18.250.
142 Exhibit A2.19.252. Further insertions of code resulting from the email software are omitted.
-- 46 of 105 --
[2026] SADC 3
43
Hi Nabil, as initially raised the LawrDo bu=iness needs to start to covered [sic] their
overhead cost. To address this, it is=necessary to factor and reflect the cost of money inline
with other f=nancial organisations prepared to fund the types of developments being
unde=taken. To address these overheads, minimise losses and incentivise you as the proje=t
manager all current and future developments will now attract the fol=owing costs:
• An interest rate of 10% of the P=operty purchase price will be charged and offset
against any sales achieved=during the development period;
• A finance Fee of 3% of the prop=rty purchase price shall be applied to cover
operating and overhead cost incurred by the Lawrdo Group;
• A penalty fee of $2000 per week=is entitled to be claimed in the event of any
construction build not being c=mpleted Within 70 working days from pour of
foundation, inclusive of hand-o=er to the selling agent; and
• Any builder’s construct=on percentage variation increases exceeding the contract
value shall also a=ply to the construction interest being calculated.
248 Mr Chehade did not respond in writing.
249 Mr Lawrence accepted in cross-examination that the 10% interest rate and other
funding costs and penalty were new changes proposed by him that had not applied
to any previous development.143
250 When asked in examination in chief, what discussions he had with Mr Chehade
before sending this email, Mr Lawrence’s evidence was unsatisfactory. He did not
immediately answer the question, instead explaining his subjective rationale for
demanding that these additional costs apply:144
This was more targeted at the rate of it - sorry. There was an exercise previously where I
tried to raise money, and dealing with these financial organisations, I came to the realisation
that the cost of money that was being reflected on my developments wasn't in line with
what you could get - that I could get commercially. They were a lot harsher than what was
imposed in this particular - or these types of developments. So I wanted to reflect the cost
of money appropriately.
251 Mr Lawrence then said he believed that there were previous emails and discussions
about the 10% interest rate. This was contradicted by the documentary evidence.
Mr Lawrence sent Mr Chehade an email in nearly identical terms after (not before)
on 5 July 2019 demanding that the same 10% interest rates, additional costs and
penalty apply retrospectively.
252 His evidence that Mr Chehade agreed to the terms he demanded was not
persuasive. He said:145
143 T521.16-522.21.
144 T366.4-.13.
145 T367.31-.36.
-- 47 of 105 --
[2026] SADC 3
44
He didn’t - I said it’s going to be 10%. I think I also argued that I wanted the LVR raised
from 80% to 100%. He-he-he understood where I-I-I was coming from. We had a
discussion on that, and he was not adverse to that. At no point in the discussion did he say
‘No, that is not acceptable’.
253 The applicants submitted Mr Lawrence’s evidence about what was said was
vague and only supports a finding about what Mr Lawrence wanted. 146 Their
criticisms were well made. I also concur that Mr Lawrence’s evidence in cross-
examination is not evidence of acceptance, having regard specifically to his
concession that:147
…those terms were discussed. Did I believe that all of them would be implemented? No, I
didn't.
254 Mr Chehade said he discussed this email with Mr Lawrence after he received it at
one of their café meetings. Mr Chehade’s said his exact response was: “‘You call
this incentives?’. I said ‘Are you serious?’.”148 He then told Mr Lawrence not to
mention anything about interest, especially in these terms as long as Mr Lawrence
owed him money.
255 This is where the issue was left until the next time it was raised by Mr Lawrence’s
5 July 2019 email.
256 I accept that Mr Lawrence was frustrated and wanted to increase the return on his
investments in the parties’ joint ventures. However, Mr Chehade’s evidence as to
what was said and agreed is more plausible and commercially rational. As to the
new interest rate of 10%, their existing agreement since February 2018 was 6.5%
on 80% of the property purchase price. As for their building contracts, the agreed
completion period was 150 business days after foundation pour, not 70 working
days.149 Bearing in mind the margin of 15% on relatively low-cost builds, as the
applicants submit, it was “fanciful” to suggest Mr Chehade would agree to a
penalty that would quickly erode any profit on the building contract if there were
even a small delay.150
257 There was no good reason for Mr Chehade to agree to new terms and a penalty
that were materially disadvantageous to his interests in circumstances where their
relationship for the existing properties was as joint venturers, not as developer and
arms-length banker/owner. Mr Lawrence’s entities did not have the overheads of
financial institutions.
258 Mr Lawrence did agree in cross-examination that there were unpaid invoices
outstanding to Chehade Constructions. However, he denied that Mr Chehade
specifically raised this as a reason for not paying increased interest saying that for
146 Applicants Written Closing [73]-[74].
147 T524.22-.29.
148 T86.3-.5.
149 Exhibit A3.12.91.
150 Applicants Written Closing [76] and [81].
-- 48 of 105 --
[2026] SADC 3
45
Gregory Street, they had agreed these invoices would be paid at settlement. I do
not accept Mr Lawrence’s denial or his explanation. The short point is there was
money owed to Mr Chehade by Mr Lawrence’s entities despite it being their role
to fund the development and Chehade Constructions was not charging interest on
what it was owed.
259 Having regard to these matters and the unsatisfactory nature of his evidence about
this email overall, I do not accept Mr Lawrence’s evidence about it and prefer
Mr Chehade’s evidence to the contrary. I find that a reasonable businessperson in
Mr Lawrence’s position would have understood from what Mr Chehade said to
him that he did not accept and objected to a 10% interest rate, additional funding
costs and a penalty based on an unrealistic construction period.
5 July 2019 Email
260 On 5 July 2019, Mr Lawrence sent Mr Chehade an email in nearly identical terms
to his 30 April 2019 email. This time, the same 10% interest rate and additional
funding costs were stated to apply retrospectively to all current and future
developments.
261 As for the earlier email, Mr Chehade did not respond in writing. Nor did
Mr Chehade say anything to communicate acceptance of these terms, having
already told Mr Lawrence orally not to mention anything about interest in their
earlier café conversation.
262 Mr Lawrence’s evidence about the 5 July 2019 email was unsatisfactory and I do
not accept it.
263 Mr Lawrence said in examination in chief that he recalled discussing this email
with Mr Chehade who boasted and laughed about the $2,000 a week penalty fee,
saying that getting house builds done within four months was not a problem. When
asked how long after this email that conversation occurred, Mr Lawrence said it
would have been beforehand because he would have generated the email based on
their conversation.
264 This evidence was plainly reconstruction. Whilst it is plausible that
Mr Chehade may have laughed at Mr Lawrence’s demand for new funding costs
to apply, I do not accept that any laugh was accompanied by words that any
reasonable businessperson in Mr Lawrence’s position would have understood as
meaning he agreed to these new terms. In reaching this conclusion, I accept
Mr Chehade’s evidence that it was not commercially feasible to build a house in
70 working days.
-- 49 of 105 --
[2026] SADC 3
46
265 Mr Lawrence said in cross-examination there were several iterations of the clauses
in his July email sent. He then denied that the July email was sent because
Mr Chehade had not agreed its terms, saying:151
… I also sent it via text as well, to make sure that the words were properly understood and
agreed. And I wanted confirmation from him that he was happy with the words. The words
in these – the changes were probably very, very subtle, but it was an update. It was part of
the conversation.
266 Not only was this evidence given by Mr Lawrence entirely unpersuasive, but it
was untrue. The terms demanded in both emails were identical (which he
eventually and reluctantly conceded). I do not accept that Mr Chehade ever told
him he was ‘happy with the words’ or that there was an ongoing conversation on
this issue to that effect.
Sale of 17 Radar Street – January 2020
267 In furtherance of the parties’ joint venture for Radar Street, Property Partners
caused it to be subdivided into two allotments known as 17 and 17A Radar Street.
17 Radar Street was sold as a house and land package in January 2020. The land
sale settled on 24 March 2020 for a price of $165,000.
268 On 3 February 2020, Chehade Constructions entered into a written building
contract with a third party purchaser for the construction of a single storey three-
bedroom house with a single car garage.
Sale of Gregory Street – February 2020
269 In January 2020, Chehade Constructions invoiced Lawrdo Super for the final
instalment of the price for the construction of the house on Gregory Street.
Mr Lawrence complained about the invoice in an email:152
Nabil, how does $7K variation get to 32K.
Please ring me.
270 Mr Lawrence gave evidence in examination in chief about how he had discussed
with Mr Chehade the $7,000 variance at a café meeting then received an invoice
for $30-odd thousand. He said he went ballistic, sent an email about it and when
they met at the café to discuss it they had a “big barmy”.153
271 The sale of the Gregory Street land as part of a house and land package settled on
4 February 2020.
272 Aside from the consensus that this development was loss making, as already
mentioned, the evidence about it was sparse and confusing.154 Mr Lawrence
151 T526.25-.31.
152 Exhibit A2.25.274.
153 T362.10.
154 A Statement of Agreed Facts about the Glen Rovala Street/Gregory Street development was not
provided until after trial. See MFI 39.
-- 50 of 105 --
[2026] SADC 3
47
complained that Mr Chehade did not pay his fair share of the loss incurred and
believed an interest rate of 10% applied to it. Contrary to Mr Chehade’s evidence,
Mr Lawrence denied any discussion with Mr Chehade about wiping off this loss
against the building contract for Connie Street, describing that proposition as
“ridiculous”.155
273 Once the cross claim was withdrawn, there was no pleaded issue in dispute about
the Glen Rovala Street/Gregory Street joint venture. Disputes about this
development were only relevant to credit and advanced by the respondents as
important context to the alleged agreement to end profit sharing made in early
2020.
‘Early’ 2020 Discussions
274 It is the respondents’ pleaded case that at a meeting at Almina’s café in about early
2020 around the time the Glen Rovala Street development was completed,
Mr Chehade and Mr Lawrence orally agreed that there would be no profit sharing
for existing and future development projects.156 It is alleged that it was agreed that
the respondents would profit from the development activities and the applicants
would profit from any building contracts if they were engaged to carry out any
building works.
275 In evidence in chief Mr Lawrence said he forced a meeting with Mr Chehade by
outlining to Mr Chehade the topics he wanted to sort out. He went armed with two
reports he previously generated and his iPad and told Mr Chehade the return on
each of the developments was unsustainable, ignoring interest. He said he gave
Mr Chehade an ultimatum:157
…I said to him ‘You either take the 15% out and we share the profit or you relinquish the
sharing arrangement and you keep your 15%’. He elected to take the 15%. I can see why
because he at least he was making 15% on something, right. And that’s what the agreement
was to go forward. So the profit share agreement came to an end at the meeting.
276 Mr Lawrence said Mr Chehade was reluctant to agree, but he forced the issue, told
Mr Chehade it was not a negotiation, it was an ultimatum and if he didn’t do it, he
was going to liquidate.
277 Mr Chehade denied this conversation occurred.
278 Mr Lawrence’s evidence on this topic was unsatisfactory on a number of counts
and I prefer and accept Mr Chehade’s consistent denials that the conversation
occurred as alleged.
279 That said, I accept that it is likely that Mr Lawrence continued to express his
dissatisfaction with the return on their joint ventures to Mr Chehade throughout
155 T364.26.
156 Defence [1.13].
157 T371.7-.14.
-- 51 of 105 --
[2026] SADC 3
48
2020. There were difficulties with cash flow and Mr Lawrence had no funds. I am
not satisfied however that Mr Lawrence ever expressed his dissatisfaction in the
form of an ultimatum as to the options going forward to which Mr Chehade
reluctantly agreed. If Mr Lawrence had forced the issue as he claimed he did, it is
implausible that Mr Chehade would not have objected in the strongest of terms as
he did in December 2016 when Mr Lawrence proposed their relationship change
from joint venturers to owner/project manager. It is even more implausible that
Mr Chehade would have agreed for Property Partners to forego its equal profit
share on existing joint ventures and instead, ‘reluctantly’ elected to take a 15%
margin on building contracts if he was awarded any.
280 Secondly, the alleged agreement to end profit sharing is a fundamental departure
from the parties’ existing agreement. It had endured for nine years over their
previous ventures without argument despite Mr Lawrence’s continuing complaints
about falling interest rates, budget cost overruns and the rate of return he was
receiving. Moreover, this variation to their existing agreement is alleged to have
occurred part way through the Radar Street, Upton Street/Chicklade Street and
O’Connell Street joint ventures.
281 By early 2020, Mr Chehade had already undertaken substantial work to manage
the development of these properties that he had identified and introduced to
Mr Lawrence to pursue as a joint venture on the same fundamental terms as their
earlier joint ventures. It is important that the O’Connell Street development was
anticipated to be their largest and most lucrative development yet and their plan
was to finalise the other joint ventures before completing this joint venture.
282 To this end, by January 2020 they had finally subdivided Radar Street after many
setbacks and only just sold the house block.
283 It makes no commercial sense for Mr Chehade to agree that Property Partners
would not profit from the substantial development work he had undertaken over
the preceding three years without any guaranteed return.
284 Thirdly, Mr Chehade had no reason to accept any ultimatum from Mr Lawrence.
Mr Lawrence could not unilaterally liquidate the properties the subject of existing
joint venture agreements without Mr Chehade’s agreement. These properties were
joint venture property. Mr Lawrence had no legal entitlement to deal with the joint
venture properties as if they were his own. Moreover, since they were partly
developed, it makes not commercial sense to liquidate them before completion and
not maximise their development profit.
285 In these circumstances, it is not credible to suggest that Mr Lawrence proposed to
change the terms of their deal part way through and Mr Chehade ‘reluctantly’
agreed.
-- 52 of 105 --
[2026] SADC 3
49
286 Mr Lawrence’s evidence that he could see why Mr Chehade ‘reluctantly’ agreed
because he “was making 15% on something” was also not convincing.158
If Mr Lawrence was genuinely concerned about the significant risk involved in
completing the O’Connell Street development, it would have been in his
commercial interests to share the risk of a loss with Property Partners rather than
deliver an ultimatum that led to an agreement that increased Mr Lawrence’s risk.
287 Fourthly, the alleged agreement to end profit sharing is unsupported by any
contemporaneous documentary evidence. It is surprising there are no emails from
Mr Lawrence proposing such a fundamental change to their arrangements given
his propensity to record his complaints in emails to Mr Chehade. More concerning
is the absence from evidence of the “two reports” Mr Lawrence said he generated
to show why their developments were not sustainable ignoring interest.159 He was
led in examination in chief by his counsel to say these reports were “something
similar” to the March 2018 report Mr Chehade was shown.160 I do not accept this
evidence as reliable and give it no weight.
288 There is another reason why I found Mr Lawrence’s evidence about the alleged
agreement to end profit sharing uncompelling. Despite his precisely pleaded case
that the alleged conversation at Almina’s café occurred in about early 2020 at about
the same time the Glen Rovala Street development was completed, Mr Lawrence
was unable to consistently date that conversation in his evidence. He variously
and generally referred to this agreement as being made “in 2020”,161 “sometime in
2020”,162 “mid 2020”,163 “by September 2020”164 and “I don’t know whether it was
May or whether it was later than that than May, but certainly in 2020 that
agreement was struck.”165
289 These shifts in Mr Lawrence’s evidence were telling having regard to the logic of
events at different times in 2020. They undermine the respondents’ submission
that Mr Chehade’s alleged failure to share the loss on the Glen Rovala
Street/Gregory Street development was a precursor to the alleged agreement to end
profit sharing. It makes even less commercial sense for Mr Chehade to forego the
development profit on O’Connell Street after the grant of development approval
and building consent in July and August 2020.
O’Connell Street – Progress as at March 2020
290 By March 2020, much of the work required to seek planning and development
approval for O’Connell Street had been undertaken by Mr Chehade through
Property Partners. The architect ET Design had prepared detailed location, site
158 T371.11-.12.
159 T372.1-.10.
160 T372.2-.10.
161 T627.28-.29.
162 T623.27-.31.
163 T536.6-.13.
164 T611.15-.20.
165 T606.32-.34.
-- 53 of 105 --
[2026] SADC 3
50
and floor plans and elevations for 13 proposed single storey articulated masonry
veneer houses to be built on the subdivided lots. A stormwater study was
undertaken and its design prepared by KP Squared Engineering Pty Ltd. It had
provided a fee proposal for civil engineering design and structural and footing
design for the proposed residences in January 2020.
291 Arborists and traffic engineers had been consulted. There were numerous design
issues, including as to rubbish collection, to meet Salisbury Council’s requirements
for development approval and building consent.
292 The plan of proposed community division was lodged with Salisbury Council in
late March 2020. On 31 March 2020, Chehade Constructions invoiced Lawrdo
Investments $3,355.00 for the arborists, the plan of proposed community division
and the engineer’s fees for the storm water drainage plan, which Lawrdo
Investments paid without objection.166
293 The explanation given in the evidence as to why Chehade Constructions invoiced
these as project costs, instead of Property Partners was that Property Partners
instructed Chehade Constructions to manage these works.
Funding O’Connell Street – March 2020
294 In early 2020, Mr Chehade had meetings with PCU to discuss funding the
O’Connell Street development and identified that there were difficulties in
borrowing development funds because the current ownership structure involved a
SMSF.
295 By email dated 16 March 2020, Mr Chehade wrote to Mr Lawrence recommending
that they start planning how they were going to move forward with funding to
complete the development of O’Connell Street since they were nearing planning
and development approvals. Mr Chehade identified the costs of the following
steps:167
Once approvals have been granted, we will have to pay the following
• open space contribution $120k
• sewer and water fees sa water will forward a quote once it has been approved, as
there some upgrades ive estimate around $50k
• sa power networks, $30k
We will need to pay all the above before we can lodge for separate titles except for the
sa power networks that can wait when we begin construction.
Then we will start on the civil works which we are estimating will be around $250k
166 Exhibit A5.12.
167 Exhibit A5.10.43.
-- 54 of 105 --
[2026] SADC 3
51
296 Mr Chehade’s email continued by setting out two potential options for funding the
development he had discussed with PCU. Both options required the title to be
solely owned by Lawrdo Investments and not Lawrdo Super and contemplated
funding construction of a house on each allotment. The first option proposed PCU
funding the development in four stages. The second funding option was for
construction of 13 houses after creation of 13 separate allotments and titles and
completion of the civil infrastructure works, all proposed to be funded by Lawrdo
Investments as the sole registered proprietor of O’Connell Street.
297 Mr Chehade’s email concluded with him promising to keep Mr Lawrence posted
about the approvals and said they could discuss the matter further when they next
met.
298 On 21 March 2020, Mr Lawrence asked his financial adviser to review the
proposed funding options on condition that the title to O’Connell Street would be
transferred from Lawrdo Super to Lawrdo Investments and propose a way
forward.168
299 It is evident from these communications that Mr Chehade and Mr Lawrence had
not reached any concluded agreement about how they would fund the further
development of O’Connell Street. I do not accept Mr Lawrence’s evidence in
cross-examination that Mr Chehade in his email was simply “regurgitating
something” Mr Lawrence sent him.169 There was no such email in evidence.
17A Radar Street – May 2020
300 On 22 May 2020, Chehade Constructions entered into a building contract with
Lawrdo Super for 17A Radar Street on a cost plus 15% basis.
O’Connell Street – May to August 2020
301 By written agency agreement dated 21 May 2020, Ray White was appointed to
market and sell the O’Connell Street allotments as house and land packages with
Chehade Constructions as the nominated builder. In about July 2020, marketing
materials were prepared to advertise house and land packages for this
development.
302 Mr Chehade gave evidence that when he “got a hint”170 that the pending approvals
were imminent, he caught up with Mr Lawrence and they discussed and agreed to
appoint Ray White as agent to start marketing house and land packages.
Mr Chehade signed the agency agreement on behalf of Lawrdo Investments and
Lawrdo Super. He did so with Mr Lawrence’s approval and authority.
303 Whilst Mr Lawrence said he did not recall this discussion with Mr Chehade or
having seen the agency agreement, in cross-examination he accepted that he knew
168 Exhibit A5.11.46.
169 T600.24-.25.
170 T152.10.
-- 55 of 105 --
[2026] SADC 3
52
Ray White was engaged to sell house and land packages for O’Connell Street,171
and most importantly, that he had agreed with Mr Chehade that he could sell house
and land packages.172
304 That this was the case was confirmed by the text Mr Chehade sent him attaching
the advertising proof of signboard for O’Connell Street prepared by Ray White
depicting built houses.
305 On 10 July 2020, development plan consent was granted for O’Connell Street for
13 single storey dwellings and associated internal driveway and landscaping
subject to four reserved matters and eleven conditions. Building rules consent
and development approval was still pending.
306 On 4 August 2020, the subdivision of the O’Connell Street land was approved
and registered.173
Chicklade Street – September 2020
307 In September 2020, Mr Chehade and Mr Lawrence decided to build on the
subdivided block because they had been unable to sell it as vacant land at a price
that would yield a profit.
308 On 15 September 2020, Lawrdo Investments and Chehade Constructions entered
into a written building contract for the construction of a new house on the
Chicklade Street block.
309 The contract is based on a HIA 2014 SA Building Contract for New Homes and
includes the usual clauses found in that form of contract. The works to be done
and completed under the contract are defined by reference to contract documents,
which are generically defined. None were in evidence. Whilst the contract price
specified in the Contract Information is $160,000 including GST, it is also states:174
IMPORTANT: THIS PRICE MAY CHANGE.
310 In clause 14 of the addendum, it is expressly stated that the price is “subject to
variation” and:175
171 T607.38-608.7.
172 T610.1-.3.
173 Exhibit A5.18.121.
174 Exhibit A4B.4.16.
175 Exhibit A4B.4.43.
-- 56 of 105 --
[2026] SADC 3
53
ALSO, THE FINAL CONSTRUCTION PRICE IS TO BE CALCULATED AS COST
15%.
ONCE THE HOUSE HAS BEEN COMPLETED AND THE PRICE OF THE
CONSTRUCTION IS GREATER THAN THE PRICE CHARGED THEN THE OWNER
WILL PAY A DIFFERENCE TO THE BUILDER, TO BE CALCULATED TO THE
ABOVE PERCENTAGE; FURTHERMORE IF THE PRICE OF THE CONSTRUCTION
ONCE THE HOUSE IS COMPLETED IS LESS THAN THE PRICE QUOTED THEN A
REFUND WILL BE PAID TO THE OWNER TO BE CALCULATED TO THE ABOVE
PERCENTAGE.
WARNING THIS PRICE MAY CHANGE
14. The Owner and the builder both agree that once the house has been completed the
builder will work out the final cost price which is the cost-plus profit plus GST. Once the
final price has been finalised and if the total monies paid by the Owner equal to a higher
amount than the final cost, the Builder will refund the monies charged over the final cost
to the owner within 5 days. Furthermore; if the amount paid by the Owner equals to a lesser
amount than the final cost, the owner will pay the Builder the difference within 5 days.
311 To fund the cost of construction, Lawrdo Investments took out a construction loan
with PCU.
O’Connell Street – September to November 2020
312 In September 2020, Mr Lawrence sent Mr Chehade a text telling him “to hold
everything on O’Connell Street” because he had no funds to pay the stamp duty
that would apply to the proposed transfer of the property from Lawrdo Super to
Lawrdo Investments and was necessary for PCU to fund the development.176
313 By November 2020, the parties had not resolved how they would fund the further
development of O'Connell Street. Mr Lawrence still did not want to pay the
stamp duty on the transfer of the land from Lawrdo Super to Lawrdo
Investments.
314 Attempts to sell the O’Connell Street allotments as house and land packages had
not been very successful. By November 2020, only two allotments had been
sold. Two building contracts were made between Chehade Constructions and
third parties on 18 September and 11 November 2020. Both contracts
subsequently fell through.
315 I accept Mr Chehade’s evidence that he was not really chasing sales in 2020
because they had not ‘figured out’ the funding and he told the agent to slow down
the marketing. Mr Chehade was frank that he did not want to commit to fixed
prices for the building works when he did not know when he would be starting to
build.
176 Exhibit A5.20.129.
-- 57 of 105 --
[2026] SADC 3
54
Chicklade Street – December 2020
316 On 17 December 2020, Chehade Constructions invoiced Lawrdo Investments
$440 for repegging the boundary of Chicklade Street. The invoice is unpaid and is
the subject of the dispute addressed later in these reasons.177
317 On 24 December 2020, a contract for sale of the Chicklade Street property for a
price of $315,000 was signed by Mr Chehade on behalf of Lawrdo Investments.
The contract was subject to the approval of finance and specified the inclusion of
certain chattels and vendor’s works. It is common ground that before signing this
contract on Christmas eve, there were discussions between Mr Chehade and
Mr Lawrence about the upgrade works required by the purchaser but there is
contention about how much Mr Chehade told Mr Lawrence these works would
likely cost.
318 This dispute is more conveniently dealt with later in these reasons in the context
of Chehade Constructions’ claim for unpaid construction costs.178
O’Connell Street – January to March 2021
319 By letter dated 15 January 2021, PCU set out the indicative terms of finance for
the further development of O’Connell Street by the construction of new houses in
three stages. The letter expressly stated that its terms did not represent an offer of
finance. Its conditions were extensive and included confirmation of the ownership
structure and minimum pre-sales.
320 By this time, Mr Chehade through Property Partners as project manager had
applied for planning and development approval for the subdivision of O’Connell
Street into 13 separate community title allotments. Bartlett Drafting had been
engaged to complete an outer boundary survey and prepare a suitable plan of
division for lodgement at the LTO.
321 In March 2021, Mr Chehade and Mr Lawrence again exchanged emails about the
future of the development. Mr Lawrence asked for estimates to support the future
costs of the project at the request of his financial adviser and expressed concerns
about the high risk of the project.
322 Mr Chehade asked to meet him to discuss the project, noting that they had contracts
that would fall over if they could not show works being carried out and that he was
still waiting on quotes to come in. In response, Mr Lawrence told Mr Chehade
that he needed the sales of Radar Street and Chicklade Street to settle to
demonstrate that he had sufficient funds to live on and until the background
information was provided, his financial adviser “won’t underwrite or recommend
property transfer titles from the Super to Unit Trust.”179
177 See [560]-[565] below.
178 See [566] and following below.
179 Exhibit A5.24.150.
-- 58 of 105 --
[2026] SADC 3
55
323 This correspondence is important because it demonstrates that Mr Chehade and
Mr Lawrence had still not reached a concluded agreement to develop O’Connell
Street by the joint venture constructing houses on the subdivided allotments and
selling built houses. This left open as the agreed way forward the sale of house
and land packages with Chehade Constructions as the nominated builder as they
had agreed in May 2020.
324 Meanwhile, without consulting Mr Chehade, Mr Lawrence through ABC
approached National Realty (Aust) Pty Ltd and Lawrdo Super and Lawrdo
Investments appointed it as residential sales agent for O’Connell Street under a
written agreement signed on 7 March 2021.
325 In evidence, Mr Lawrence accepted that by this time he had considered completing
the development without Mr Chehade. Although he also said he did not take this
step to actively cut him out, I do not accept his evidence. Other evidence shows
that Mr Lawrence was already engaged in discussions with ABC about progressing
the development without Mr Chehade despite the O’Connell Street property being
a joint venture asset that Mr Lawrence’s entities held on trust. He was not free to
deal with it as he chose and this step was plainly taken to position himself to exploit
the O’Connell Street development on his own.
326 On 24 March 2021, Chehade Constructions invoiced Lawrdo Investments for
$16,233.30 including GST for costs incurred for O’Connell Street. This invoice
has not been paid and is the subject of the dispute addressed later in these reasons.180
Sale of Chicklade Street – April 2021
327 On 21 April 2021, a second sale contract was signed for Chicklade Street at a price
of $335,000. The first sale contract had fallen through. This second sale settled
on 20 May 2021.
328 On 21 May 2021, Chehade Constructions invoiced Lawrdo Investments $32,870
for the balance of the construction costs. This invoice was not paid and is also the
subject of the dispute addressed later in these reasons.181
329 After completion of the Upton Street/Chicklade Street development, Lawrdo
Investments refused to share any of the profit generated by this project with
Property Partners on the basis that any profit sharing ceased in early 2020
following the oral agreement allegedly made between Mr Chehade and
Mr Lawrence.
O’Connell Street – June to August 2021
330 By email sent on 2 June 2021, Mr Lawrence terminated Ray White’s sales agency
without consulting Mr Chehade. His email gave as the reason for no longer
requiring their services that they had not met presale prerequisites and stated he
180 See [566]-[576] below.
181 See [566]-[576] below.
-- 59 of 105 --
[2026] SADC 3
56
would be “looking at other options going forward”.182 In context of the other
reliable evidence, it is apparent Mr Lawrence’s other options did not include
Mr Chehade.
331 On 7 June 2021, Mr Lawrence sent Mr Chehade the following email:183
Nabil,
My concerns in regards [O’Connell Street] have already been communicated to you, plus
it was made abundantly clear to me that the Radar Street issues has [sic] complicated things.
Based on the avove [sic], this email has been sent to formally inform you that you are not
to proceed or action any further matters associated with this development and your
association with this development ceases with immediate effect and as such you do not
represent any of the LawrDo’s Groups interests.
332 This email was sent absent any prior discussion with Mr Chehade. Mr Chehade
did not respond and instead engaged solicitors to deal with his disputes with
Mr Lawrence over their joint ventures.
333 None of the justifications that Mr Lawrence gave in examination in chief for taking
this step were discussed with Mr Chehade and are legally not relevant.
334 On 9 August 2021, Mr Lawrence emailed Ms Rossi and instructed her to remove
all invoices for O’Connell Street from her accounts, to instruct Bartlett Drafting to
reissue all invoices to Lawrdo Investments and he would pay the subdivision costs
for O’Connell Street “when this project is reactivated,” implying that it was on
hold.184 However, it was not true that the project was on hold because Mr Lawrence
was already secretly dealing with ABC to complete the development without
Mr Chehade and his entities’ participation.
335 On 12 August 2021, referring to an invoice for soil bore logs and a footing
construction report from KP Squared Engineering, Mr Lawrence sent Mr Chehade
a further email:185
Nabil, the above mentioned invoice is not recognised by the LawrDo Group. The work you
have actioned or progressing was not sanctioned, authorised or agreed…The LawrDo
Group is not in a financial position to proceed with this development and is unable and
unwilling to underwrite any liabilities as a result of your actions.
Notwithstanding, you have been advised that your participation in this development is not
required.
336 Mr Lawrence did not tell Mr Chehade that he was secretly dealing with ABC to
complete the development without Mr Chehade and his entities’ participation.
182 Exhibit A5.27.158.
183 Exhibit A5.27.158.
184 Exhibit A5.30.168.
185 Exhibit A5.32.171.
-- 60 of 105 --
[2026] SADC 3
57
Caveat over O’Connell Street – October 2021
337 On 12 October 2021, Property Partners’ solicitor prepared and lodged a caveat
claiming it has an interest in the O’Connell Street land under an unsigned written
joint venture agreement dated 7 October 2016 in the same terms as a series of
earlier joint venture agreements between the caveator and the caveatee that are
signed.186
338 In support of their case that the terms of the PMS Agreement initially applied to
the disputed joint ventures, the respondents submitted that “Chehade even relied
on one of the versions (7 October 2016)” when lodging the caveat.187
339 The respondents’ submission lacks merit and the points taken by the applicants in
their submissions in this regard are well made.188 The evidence does not establish
that the version relied on in the caveat is Mr Lawrence’s revision emailed on
30 September 2016 or is even Mr Chehade’s earlier draft. In any event, it does not
matter since the caveat is not in issue. More fundamentally, Property Partners’
reliance on it in the caveat is no basis for inferring that Mr Chehade and
Mr Lawrence subsequently agreed to be bound to the terms of the PMS
Agreement, a subsequent draft proposed on substantially different terms.
Completion of 17A Radar Street – October 2021
340 17A Radar Street was sold to M&G Carlo by contract dated 13 September 2021
for $495,000. Settlement took place on 20 October 2021 and the net sale proceeds
of $64,371.50 were paid into the Lynch Meyer trust account.
341 The applicants claim they are entitled to share the profits of the Radar Street joint
venture in equal proportion to Lawrdo Super and seek a monetary judgment and
consequential order for payment out of the Lynch Meyer trust account or
alternatively an order for a taking of accounts.
342 The respondents contend the development of Radar Street is governed by the terms
of the PMS Agreement. They further deny the applicants have any entitlement to
share the profits of the Radar Street development on the basis of the alleged 2020
agreement not to share profits. In the alternative, the respondents disagree about
the calculation of interest in determining the profit to be shared equally.
343 These key disputes are addressed later in these reasons.
Completion of O’Connell Street
344 The respondents were not entitled to deal with the O’Connell Street land as if it
were their own. It was a joint venture asset and subject to ongoing contractual and
fiduciary obligations owed to Property Partners, as discussed later in these reasons.
186 Exhibit A5.55.
187 Respondents Written Closing [23].
188 Applicants Written Closing [29].
-- 61 of 105 --
[2026] SADC 3
58
345 From about March 2021, Mr Lawrence for the respondents took steps to exclude
the participation of Property Partners from the O’Connell Street development and
progressed the development to completion without further consulting Mr Chehade
or accounting for the profits generated by the development. The respondents did
so with the assistance of ABC and an interstate buyer’s agent, Mr Adam Albrecht
of Momentum Property Solutions introduced by ABC. ABC undertook the role of
project manager and provided sales consulting services in place of Property
Partners.
346 On 31 August 2022, Plan SA notified ABC of the grant of planning and land
division consent and development approval for O’Connell Street.189 ABC managed
the lodgement of a new application for the respondents using the documents that
had been prepared by Property Partners for the original application for which
approvals had been granted in July and August 2020.
347 On 20 July 2023, the respondents paid the open space contribution.
348 The civil infrastructure works were carried out by another builder, YY Group Pty
Ltd instead of Chehade Constructions.
349 Ultimately, the 13 subdivided allotments were sold as house and land packages
between April and July 2023 and between January and May 2024 with YY Group
Pty Ltd as the nominated builder instead of Chehade Constructions. The total price
received from the land sales was $2.618 million.
350 Whether the respondents’ conduct in completing the development without the
applicants’ further participation constituted breaches of their contractual and
fiduciary duties to the applicants are key questions addressed later in these reasons.
CONTRACT CLAIMS
Issues
351 In this case the Court’s task in ascertaining the terms of the parties’ agreement is
confined by the admissions made in the pleadings and the evidence, as well as
concessions made in the Statement of Agreed Facts and Issues.
352 It is common ground and established by the evidence that without any written or
express oral agreement, the parties initially agreed to share profits and losses for
the disputed joint ventures in equal proportions.190 The evidence also establishes
that initially the parties conducted themselves for these developments in the same
fundamental terms as they had for their earlier joint ventures, save for the
participation of Lawrdo Super from 2016. Indeed, both Mr Chehade and
Mr Lawrence accepted that this was their common understanding and agreement
at the time they orally agreed to proceed with the settlement of the purchase
189 Exhibit A5.38.196.
190 MFI 1 [4].
-- 62 of 105 --
[2026] SADC 3
59
contract and develop each of the Radar Street, Upton Street/Chicklade Street,
Charmaine Avenue/Connie Street and O’Connell Street properties.
353 It is also common ground and established by the evidence that where Chehade
Constructions was engaged to do any building works after 2016 instead of Integrity
New Homes, this was done on a cost plus 15% basis.
354 Contrary to the respondents’ submission, it is therefore not necessary for the Court
to untangle the parties’ “messy” arrangements spanning many years and determine
precisely all that was agreed and when and whether it was agreed in writing, orally
and/or by conduct. The applicants’ pleaded case has not shifted as submitted by
the respondents in closing oral submissions, which submission was contrary to
their opening. 191
355 Ultimately, the parties’ disputes about the precise terms of their agreement about
the disputed joint ventures concern essentially three questions.
356 First, there is a threshold question about whether there is an overarching joint
venture agreement or a series of joint venture agreements between the parties.
Depending on the answer, there is a further question as to whether Chehade
Constructions was a party to the overarching joint venture agreement or
agreements to which Property Partners, Lawrdo Super and Lawrdo Investments
were incontrovertibly parties.
357 The second question is whether Property Partners is entitled to share profits equally
with the respondents for the disputed joint ventures. The answer turns on whether
Mr Chehade and Mr Lawrence agreed in early 2020 that Property Partners would
no longer be entitled to share any profits for the developments then underway,
bearing in mind the uncontentious starting point that there was an existing
agreement between the parties that they would share profits equally for each of
these developments as joint venturers.
358 The third question is what was the agreed basis for calculating interest in
determining profit should the Court find Property Partners is entitled to share
profits equally. The answer turns first on whether the parties agreed in December
2016 that the terms of the draft PMS Agreement would apply to their joint ventures
going forward and secondly, whether Mr Chehade agreed to an interest rate of 10%
and other funding costs applying to the calculation of interest in July 2019.
Principles – Ascertainment of terms
359 The applicable legal principles are well-established and uncontentious.
360 Incontrovertibly, whether an agreement has been entered into is to be objectively
assessed. The objective intention of the parties is fact-based, found in all the
191 Respondents Written Opening at [2]: “A key issue that affects most of the claims is whether the
commercial arrangements between the parties continued in the same manner for each joint venture, or
whether at certain moments the arrangement changed.”; T694.20-.24.
-- 63 of 105 --
[2026] SADC 3
60
circumstances, including by drawing inferences from the parties’ words and
conduct in making their agreement.192 Uncommunicated subjective intention is not
determinative.193
361 The question whether there is an intention to create legal relations depends on “the
subject matter of the agreement, the status of the parties to it, their relationship to
one another, and other surrounding circumstances” as well as standards of
reasonable conduct in the known circumstances.194
362 In a commercial context, determination of the requisite contractual intention
involves a consideration of: 195
…the surrounding circumstances known to [the parties] and the commercial purpose or
objects to be secured by the contract. Appreciation of the commercial purpose or objects
is facilitated by an understanding “of the genesis of the transaction, the background, the
context [and] the market in which the parties are operating.” As Arden LJ observed in Re
Golden Key Ltd, unless a contrary intention is indicated, a court is entitled to approach the
task of giving a commercial contract a businesslike interpretation on the assumption “that
the parties … intended to produce a commercial result”. A commercial contract is to be
construed so as to avoid it “making commercial nonsense or working commercial
inconvenience.”
(Citations omitted)
363 In a case such as this where the contract is informal, it is necessary for the Court
to have regard to the whole of the evidence (not just the evidence of what was said)
at the time of contracting to find what the terms of the alleged contract were. In
finding the facts:196
…the evidence of witnesses as to words written or spoken by the parties (and their
knowledge of the relevant matters at the time of the contract) must be weighed alongside
the objective surrounding facts (which are undisputed or which are established by other
objective evidence) and also with the apparent logic of events. It may be difficult in this
process to distinguish between terms of the contract based solely or centrally upon words
used by the parties and those based only in part on those words but also upon surrounding
facts and logic of events.
The task is to ascertain what the words and conduct of the parties would have conveyed in
all the circumstances to a reasonable person who had the knowledge reasonably available
to the parties. The essential question is whether the parties’ conduct – what was said and
192 Kuehn & Kuehn v Masterton Homes (NSW) Pty Ltd [2020] NSWSC 1049 (Kuehn) at [29] citing Allen
v Carbone (1975) 132 CLR 528, 532; Australian Broadcasting Corporation v XIVth Commonwealth
Games Ltd (1988) 18 NSWLR 540, (Australian Broadcasting Corporation) at 548-9; Ermogenous v
Greek Orthodox Community of SA Inc (2002) 209 CLR 95 at [25] (Gaudron, McHugh, Hayne and
Callinan JJ).
193 Australian Broadcasting Corporation at 548-549; Sion v NSW Trustee & Guardian [2013] NSWCA
337 at [38] (Emmett JA, Basten and Barrett JJA agreeing); Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd
(2004) 219 CLR 165 at [40] (Gleeson CJ, Gummow, Hayne, Callinan and Heydon JJ).
194 Ermogenous at [25] (Gaudron, McHugh, Hayne and Callinan JJ); Film Bars Pty Ltd v Pacific Film
Laboratories Pty Ltd (1979) 1 BPR 9251 (Film Bars) at 9255.
195 Electricity Generation Corporation v Woodside Energy Ltd & Ors (2014) 251 CLR 640 at 656-657.
196 Realestate.com.au Pty Ltd v Hardingham & Ors [2022] HCA 39 at [46]-[47] (Gordon J).
-- 64 of 105 --
[2026] SADC 3
61
not said and the evident commercial aims and expectations of the parties in the context of
what they knew – reveals an understanding or agreement or, as sometimes expressed, a
manifestation of mutual assent to be legally bound in some particular respect.
(Citations omitted)
364 Whilst the subsequent conduct of the parties may generally not be referred to in
construing the terms of a previously concluded contract, such conduct is
admissible on the question of whether a contract is formed. It is well-established
that regard may be had to the parties’ subsequent communications for the purpose
of assessing whether it was not in their contemplation to be bound until all the
essential preliminaries had been agreed or until a formal contract had been drawn
up embodying all the matters incidental to the transaction.197
365 Continuing negotiations or other expressions of a common understanding not to
be bound, objectively viewed, are directly probative of whether a contract exists.
Simply expressed, words and conduct inconsistent with the existence of a
concluded contract are relevant but the weight they carry in negativing the
conclusion that a contract exists will depend on the circumstances.
366 However, a party’s conduct not in the presence of or involving the other party will
have little, if any, probative value in determining contractual intention because
subjective intention is not relevant.198 That said, such conduct may be relevant to
assessing the reliability of the witnesses’ testimony199 or, depending on the
circumstances, may be legitimately used against a party as an admission by
conduct of the existence or non-existence, as the case may be, of a subsisting
contract.200
367 It is also well accepted that an enforceable contract may be inferred when the
manifest intention of the parties, objectively ascertained, evinces a tacit agreement
with sufficiently clear terms.201 However, as a general rule, an offeree’s silence
will not be taken as acceptance of a contractual obligation sought to be imposed
by an offeror:202
Various explanations may be offered for this principle. One is that it derives from the
disinclination of the common law to impose legal liability upon individuals for omissions.
Another is that it is a consequence of the common law's protective attitude towards liberty
of conduct and its resistance to the unilateral imposition of obligations. Still another is that
it derives from the contractual theory of the common law that a binding and legally
enforceable agreement must be mutually achieved by offer and acceptance. Whatever the
history of and reasons for the general rule, its existence is not in doubt.
197 Australian Broadcasting Corporation at 547-8 and the authorities cited therein.
198 Holt v Bunney [2020] SASCFC 89 (Holt v Bunney) at [2] (Kourakis CJ) and at [143] (Nicholson J).
199 Et-China.com International Holdings Ltd v Cheung (2021) 388 ALR 128 at [25]-[29] (Bell P).
200 Film Bars at 9255–6 (McClelland J).
201 Holt v Bunney at [148] (Nicholson J) citing King Tide Company Pty Ltd v Arawak Holdings Pty Ltd
[2017] QCA 251 at [17]-[21] (Bond J).
202 Empirnall Holdings Pty Ltd v Machon Paull Partners Pty Ltd (1988) 14 NSWLR 523 at 527-8
(Kirby P).
-- 65 of 105 --
[2026] SADC 3
62
(Emphasis in original)
368 Nonetheless, the silence of an offeree in conjunction with other circumstances may
indicate acceptance. For example, where an offeree with a reasonable opportunity
to reject the offer of goods or services takes the benefit of them in circumstances
indicating that they were to be paid for in accordance with the offer, a finding that
the offer was accepted is open.
369 It is not enough, however, for the evidence of the parties’ subsequent conduct to
be merely consistent with the terms of the allegedly binding agreement. The
evidence must positively establish that a reasonable businessperson would regard
the conduct of the offeree, including their silence, as signalling to the offeror that
their offer was accepted.203
370 In this regard, it is important to avoid the fallacy of inferring from conduct that is
not inconsistent with the existence of a contract that the conduct actually took place
because of the contract.204 As it was said in Integrated Computer Services Pty Ltd
v Digital Equipment Corp (Aust) Pty Ltd:205
… it is an error to “suppose that merely because something has been done then there is
therefore some contract in existence which has thereby been executed”.
371 On the question of onus, two observations are pertinent.
372 First, the respondents have joined issue with the applicants as to whether Chehade
Constructions is a party to the alleged overarching joint venture agreement and
entitled by its terms to undertake the building works generally and specifically for
O’Connell Street. The applicants bear the onus of proving the conversations and
conduct relied on to the reasonable satisfaction of the Court and establishing there
was a binding contract as alleged.206
373 Secondly, since the parties have joined issue about whether the existing terms of
the parties’ joint venture agreement as regards profit sharing and interest were
varied, the respondents bear the onus of proving the conversations relied on to the
reasonable satisfaction of the Court and establishing there was a binding variation
to the existing contract as alleged.207
374 This onus was explained in Kallin Pty Ltd v ACN 107 851 847 Pty Ltd208 by
Hammerschlag J (as his Honour then was) as follows:
203 Ibid at 535 (McHugh J).
204 GC NSW Pty Ltd v Galati [2020] NSWCA 326 at [90] (Gleeson JA) citing Heydon on Contract (2019),
[2.110].
205 (1988) 5 BPR 11,110 at 11,117 (McHugh JA) citing Howard W, “Contract, Reliance and Business
Transactions”, [1987] Journal of Business Law at 127.
206 Ermogenous at [26] (Gaudron, McHugh, Hayne and Callinan JJ); Sagacious Procurement Pty Ltd v
Symbion Health Ltd [2008] NSWCA 149 at [69].
207 Ibid.
208 [2018] NSWSC 124 at [42].
-- 66 of 105 --
[2026] SADC 3
63
Where a party seeks to rely upon spoken words as a foundation for a cause of action,
including a cause of action based on a contract, the conversation must be proved to the
reasonable satisfaction of the Court, which means that the Court must feel an actual
persuasion of its occurrence or its existence. In the absence of some reliable
contemporaneous record or other satisfactory corroboration, a party may face serious
difficulties of proof. Such reasonable satisfaction is not a state of mind that is obtained or
established independently of the nature and consequences of the fact or facts to be proved.
The seriousness of an allegation made, inherent unlikelihood of an occurrence of a given
description, or the gravity of the consequences flowing from a particular finding are
considerations which must affect the answer to the question of whether the issue has been
proved to the reasonable satisfaction of the Court. Reasonable satisfaction should not be
produced by inexact proofs, indefinite testimony, or indirect inferences: see Briginshaw v
Briginshaw (1938) 60 CLR 336 at 362; Helton v Allen (1940) 63 CLR 691 at 712; Rejfek v
McElroy (1965) 112 CLR 517 at 521; Watson v Foxman (1995) 49 NSWLR 315 at 319.
Threshold Questions
The Issues
375 The applicants’ pleaded case is that there is an overarching joint venture agreement
between the parties, including Chehade Constructions, and it would undertake any
building work required on a cost plus 15% basis.209 The respondents join issue with
this allegation in their pleaded defence generally and specifically contend Chehade
Constructions had no legal entitlement to be awarded any building work for the
O’Connell Street development.
Conclusion
376 The evidence clearly establishes that a series of joint venture agreements was made
and each was varied from time to time. Whilst the essential terms were the same,
these agreements take various forms and each governs a single development. There
is no overarching joint venture agreement between the parties that governs all of
the developments.
377 The evidence also establishes that Chehade Constructions has no contractually
binding entitlement to carry out the building works for the parties’ joint ventures
generally as a party to an overarching joint venture agreement.
378 Whether Chehade Constructions has any contractual entitlement to carry out the
building work under any agreement specific to the O’Connell Street development
is a different question and important to resolve for the disputes over the O’Connell
Street development.
379 In evidence, Mr Lawrence essentially conceded that it was agreed that Chehade
Constructions would carry out the civil infrastructure works and I have found so.
For the reasons that follow shortly, I have also found there was a legally binding
agreement made between Mr Chehade and Mr Lawrence for Chehade
Constructions to carry out the residential building works for O’Connell Street as
209 Claim [1].
-- 67 of 105 --
[2026] SADC 3
64
the nominated builder for house and land packages that Ray White were engaged
to sell.
Analysis
Confinement to the Pleadings
380 In closing oral submissions, the respondents contended the applicants in their
written closing had changed their case as pleaded, opened on and advanced at trial.
Particular attention was drawn to the applicants’ submissions referring to
“repudiation” of contractual obligations and the respondents having “terminated”
the joint venture.210 The respondents further submitted that the applicants had
always cast their claims for their alleged profit share from these developments on
the basis of breaches of fiduciary and not contractual duties because it suited the
applicants in the interlocutory stages.
381 I reject the respondents’ contentions for the following reasons.
382 The applicants’ claims in contract and the underlying facts in issue, whilst not
‘perfectly’ pleaded (adopting the words of the applicants’ counsel), are tolerably
clear and give fair notice of the case to be met in contract. This is made plain by
the orders sought211 and the applicants’ case as advanced and defended at trial.
383 The contractual terms and their breach by the respondents’ alleged failure to
provide any accounting to determine Property Partners’ 50% profit share were
expressly pleaded for each of the Radar Street, Upton Street/Chicklade Street and
O’Connell Street joint ventures.212
384 For O’Connell Street, the (amended) plea alleging repudiation of the joint venture
(whilst oddly placed in the claim) and the submissions referring to termination of
the joint venture were plainly advanced in support of alleged breaches of contract
as well as fiduciary duties. Whether the respondents “repudiated” the joint
venture for O’Connell Street was identified as a separate issue to be determined in
the Statement of Agreed Facts and Issues.213
385 That Chehade Constructions only advanced a claim in contract and none for breach
of fiduciary duty demonstrates this complaint is without merit. Otherwise, what
case were the respondents meeting?
386 Further, the respondents’ alleged conduct in completing the O’Connell Street
development without consulting the applicants and excluding their further
participation was squarely put in issue and the subject of extensive evidence.
Whilst there is no pleaded case of termination of contract to be met, it is trite law
210 Applicants Written Closing [5.3], [5.4.5] and [5.6].
211 Claim Part 4 [2(g)].
212 Claim [1]-[5], [11], [21], [33], [36] and [40].
213 MFI 1 [36] and [37].
-- 68 of 105 --
[2026] SADC 3
65
that a cause of action for common law damages in contract arises from any proven
breach of contract, whether or not the contract is terminated.
No Overarching Joint Venture Agreement
387 The evidence establishes that from 2011 to 2017 separate agreements were made
for each property that was purchased in the name of Lawrdo Investments and/or
Lawrdo Super for the purpose of developing each one with Property Partners as a
joint venture.
388 The first joint venture was established under a written agreement made between
Property Partners and Mr Lawrence on 15 December 2011, the terms of which
were specific to the Baldock Road property. Lawrdo Investments became a party
to the joint venture at settlement of Baldock Road, when it was nominated as
purchaser and became the registered proprietor of the land. By operation of
clause 2, this joint venture terminated on completion of the development and sale
of the property and the subsequent finalisation of an accounting between Property
Partners and Lawrdo Investments.
389 At the time this agreement was made, there is no evidence indicating that the
parties intended they would develop any further properties together as joint
venturers.
390 The second joint venture for Lauder Street was established under a written
agreement made between Property Partners and Lawrdo Investments on
13 February 2013 on the same fundamental terms as Baldock Road. It was made
after the Baldock Road joint venture had terminated. Like Baldock Road, by
operation of clause 2, this joint venture terminated on completion of the
development and sale of the property and the subsequent finalisation of an
accounting between Property Partners and Lawrdo Investments.
391 Between 2013 and 2015 five further properties were purchased and developed in
substantially the same way by Property Partners and Lawrdo Investments as joint
ventures as Baldock Road and Lauder Street. Each property was purchased and
its development completed at different times. There was a separate accounting and
equal sharing of profits between the joint venture parties for each property. The
evidence does not support a conclusion that the parties intended these or any future
joint ventures to be the subject of an overarching agreement, although the essential
terms of each agreement were the same.
392 The joint ventures with third parties (Liberman Road and Barakoola Street) were
established under separate written agreements made at different times.
393 Between 2016 and 2017 joint ventures for another five properties were established
at different times by oral agreements made between Mr Chehade and Mr Lawrence
to proceed to develop each property as joint venturers. Each agreement was made
on the common understanding and assumption that the terms of their agreement
would be the same as adopted for their earlier joint ventures. That is, essentially,
-- 69 of 105 --
[2026] SADC 3
66
Mr Chehade through Property Partners would find the property and manage all the
development works. Mr Lawrence through Lawrdo Investments and/or Lawrdo
Super would fund the purchase, development and holding costs. Whilst
Mr Chehade through Property Partners would control the development works, he
would consult Mr Lawrence and key decisions would be made jointly. On sale of
the developed property there would be an accounting and the profits or losses
would be shared equally between the joint venture parties.
394 Having regard to the way the parties conducted all their joint ventures, a reasonable
businessperson in the position of the parties would have understood that they
intended neither of them could unilaterally terminate any joint venture or exclude
the other from further participating in the joint venture
395 For Radar Street, Mr Chehade’s unchallenged evidence was that he discussed
developing it as a joint venture with Mr Lawrence at a café meeting in about June
2016. He said he gave Mr Lawrence a copy of his “re-done paperwork”, who was
not happy with it. 214 Mr Lawrence sent him revised drafts and ultimately, on
15 December 2016, the draft PMS Agreement. Each draft agreement expressly
identified Radar Street and terms providing for a joint venture between Property
Partners and Lawrdo Super to purchase and develop only that property. None of
these drafts were in a form suitable for an overarching joint venture agreement for
the development of multiple properties.
396 For Upton Street, Mr Chehade’s unchallenged evidence was that he and
Mr Lawrence discussed developing it together after he had signed the purchase
contract. There was no specific discussion about terms: “…I basically just rang
him up, tell him I got another one and that was it…”215 He said the same thing
happened for Charmaine Avenue. Whilst his evidence about establishing the Glen
Rovala Street and O’Connell Street joint ventures was generalised, I am satisfied
their practice was to meet and discuss development opportunities as Mr Chehade
identified them and when they decided to proceed with these properties, they did
so on the common understanding and assumption that the same essential terms
would apply as had for their previous joint ventures.
397 In the proven circumstances, the inference that Mr Chehade and Mr Lawrence
intended each property to be the subject of a separate joint venture agreement
between Property Partners on the one hand, and Lawrdo Investments and/or
Lawrdo Super on the other, is compelling.
Chehade Constructions’ Right to Build
Generally
398 Chehade Constructions did not carry out any building work in relation to joint
venture properties until 2017. It was not licensed until December 2016. Plainly it
214 T76.23-77.6.
215 T102.4-.7.
-- 70 of 105 --
[2026] SADC 3
67
was not a party to the early joint ventures and the applicants do not contend that it
was.
399 The applicants’ pleaded case was that in 2016, Mr Chehade and Mr Lawrence
agreed to changes to their joint venture arrangements going forward, including that
Chehade Constructions would be the builder for their overarching joint venture
instead of Integrity New Homes. In advancing their case, the applicants allege with
specificity this change was agreed in a discussion that took place at a meeting in
2016 at Almina’s café at 140 Prospect Road, Prospect.216
400 There is consensus that a meeting took place in about June 2016 at which some
changes to the parties’ arrangements were discussed without objection. In his
evidence about this meeting, Mr Chehade did not mention any discussion, let alone
an agreement being made about Chehade Constructions or its proposed role going
forward. On the topics of builders, he only referred to discussing getting out of the
building company he had been involved with.217
401 In cross-examination, when asked whether Mr Chehade told him that Chehade
Constructions was going to do the construction work going forward instead of
Integrity New Homes, Mr Lawrence said: “No, that wasn’t expressly
expressed.”218
402 Having regard to all the evidence, I am not satisfied that the topic of Chehade
Constructions or its role as builder for the joint ventures going forward was
discussed at this June 2016 café meeting, let alone was the subject of any
agreement that was intended to be legally binding.
403 Thereafter, the evidence does not establish any overarching understanding or
agreement or as sometimes expressed, any manifestation of legally binding mutual
assent for Chehade Constructions to be a joint venture party on terms entitling it
to carry out the building works required for subsequent joint ventures, whether for
renovations or new builds. What works it would carry out for any development
was a matter to be discussed and agreed in the circumstances of that joint venture.
404 The following considerations lead to this conclusion.
405 From 2017, Chehade Constructions only carried out the building works for the
specific developments where it was engaged to do so, which works varied
depending on what was agreed as required.
406 The building works carried out by Chehade Constructions were undisputedly the
subject of separate oral or written agreements made between Mr Chehade on behalf
of Chehade Constructions on the one hand, and Mr Lawrence on behalf of Lawrdo
Investments and/or Lawrdo Super on the other that were property specific and
216 Claim [3(b)].
217 See [153] above.
218 T490.6-.9.
-- 71 of 105 --
[2026] SADC 3
68
made at different times in varying circumstances.219 The first building works
carried out by Chehade Constructions concerned renovations in 2017.
407 Whilst Chehade Constructions always charged and was paid for any building
works it carried out on the basis of cost plus 15%, consistent pricing does not
support the existence of an overarching agreement to be entitled to be the builder
for all developments going forward.
408 The costs of building work were treated as expenses in determining joint venture
profit that was shared equally between Property Partners on the one part and
Lawrdo Investments and/or Lawrdo Super on the other part. Self-evidently
Chehade Constructions did not share joint venture profits.
409 The proposed parties to the draft agreements exchanged between Mr Chehade and
Mr Lawrence for Radar Street between June and December 2016 were Property
Partners and Lawrdo Super and did not include Chehade Constructions. There is
no mention of Chehade Constructions or the topics of builders and building works
in the emails exchanged between Mr Chehade and Mr Lawrence in 2016
concerning the terms of a proposed joint venture agreement.
410 As regards Radar Street, the context in which changes to the parties’ joint venture
arrangements were discussed, the evidence does not establish that in 2016
Mr Chehade and Mr Lawrence discussed Chehade Constructions, let alone agreed
to it carrying out the building works for Radar Street specifically or generally going
forward. This is not surprising for two reasons.
411 First, Chehade Constructions was not licensed to carry out building works until
21 December 2016.
412 Secondly, no building works were initially contemplated in developing Radar
Street because it was purchased as vacant land and it was the only proposed
development under consideration in 2016. It was not until April 2019 that approval
to subdivide Radar Street was granted and the first allotment sold as a house and
land package in January 2020. It was in May 2020 that Chehade Constructions
and Lawrdo Super entered into a written agreement to build a house on the
remaining subdivided block at Radar Street.
413 Finally, Mr Chedade’s evidence was that he told Mr Lawrence “on many
occasions, not once, not twice, on many occasions” he was more than happy for
them to use another builder if Mr Lawrence could find one that would provide the
same service for a lesser price.220 This evidence does not establish a binding
agreement. It reveals that which builder would carry out any building works was
a matter to be agreed depending on the circumstances and was property specific.
219 See [113] and [114] above.
220 T223.8-.9.
-- 72 of 105 --
[2026] SADC 3
69
For O’Connell Street
414 As already observed above, it is a different question whether there was any
subsequent understanding or agreement or, as sometimes expressed, any
manifestation of legally binding mutual assent for Chehade Constructions to be the
builder for O’Connell Street that was breached by the respondents from about
March 2021 by excluding the applicants from further participating in this
development and unilaterally progressing it to completion by the sale of house and
land packages with another builder.
415 For O’Connell Street, the applicants’ pleaded case was that Mr Chehade and
Mr Lawrence agreed in early 2020 to start marketing the property and get all plans
organised to start construction, following which Chehade Constructions entered
into two building contracts with third parties.221 The applicants further allege these
building contracts could not proceed because the respondents had not funded the
finalisation of the subdivision in breach of the contract and then excluded Chehade
Constructions from any entitlement to be the builder through the sale of house and
land packages nominating another builder and engaging that builder to carry out
the civil infrastructure works to complete the development.222
416 The respondents’ position is that the Chehade Constructions had no legal
entitlement to be awarded the building works for O’Connell Street and, in any
event, was given the opportunity to sell residential building contracts, but after
15 months failed to achieve any sales. In advancing their case, the respondents
described as fatal Mr Chehade’s evidence that he and Mr Lawrence had agreed
that if he could find another builder at a better price with the better or same quality,
Mr Chehade was more than happy to use them.
417 In closing, the applicants submitted that Mr Lawrence agreed in evidence that
Chehade Constructions would have carried out the civil and residential
construction works or ‘at least’ he agreed that Mr Chehade “assumed” that the
houses were going to be built by Chehade Constructions and Mr Lawrence “didn’t
stop him” and it was “fine [if] he could do that”.223
418 Contrary to the respondents’ contentions, the evidence establishes that there was a
binding agreement for Chehade Constructions to be the builder for the O’Connell
Street development.
419 Mr Chehade’s evidence was that he “was the builder for O’Connell Street”224. He
said he and Mr Lawrence had discussed and agreed to build houses on the
developed land as house and land packages to get a better price for the land.
420 Mr Chehade’s evidence was consistent with the appointment in May 2020 of Ray
White to sell house and land packages for O’Connell Street with Chehade
221 Claim [30] and [31].
222 Claim [32], [33], [36(b)(i)] and [36(b)(iv)].
223 T606.1-.6.
224 T267.10.
-- 73 of 105 --
[2026] SADC 3
70
Constructions as the nominated builder, an appointment made with Mr Lawrence’s
agreement and approval. Not only did Mr Lawrence accept in cross-examination
that he knew about Ray White’s engagement to sell house and land packages and
that Mr Chehade assumed Chehade Constructions would build the houses,
Mr Lawrence accepted it was “correct” that he “had agreed with Nabil that he
could sell house and land packages”.225
421 With Mr Lawrence’s agreement and approval, marketing materials were prepared
and Ray White began marketing the O’Connell Street land as house and land
packages with Chehade Constructions as the nominated builder. Two lots were
sold this way. That these contracts later fell over or no further house and land
packages were sold by Ray White before June 2021 does not detract from the
inevitable conclusion that follows. That is, there was a legally binding agreement
made in May 2020 for Chehade Constructions to build the houses on the land sold
the land as house and land packages.
422 A reasonable businessperson in the position of the parties’ would have readily
understood that it was intended by their agreement to start selling the O’Connell
Street land as house and land packages with Chehade Constructions as the
nominated builder, Mr Chehade and Mr Lawrence were necessarily agreeing that
Chehade Constructions would build the houses on the land, albeit under third party
building contracts.
423 There is no good reason to consider that the agreement for Chehade Constructions
to be the builder was not intended to be legally binding. This was a commercial
transaction. Indeed, Ray White’s engagement to sell house and land packages was
formalised in a written agency agreement and Mr Chehade and Mr Lawrence’s
joint venture was conducted for mutual profit.
424 Nor can the respondents rely on any failure of the applicants to sell house and land
packages that was ultimately prevented by Mr Lawrence terminating Ray White’s
appointment and engaging another agent to sell house and land packages
nominating another builder on behalf of the respondents in breach of contract.226
425 In the circumstances, Mr Lawrence’s evidence in cross-examination that there was
no guarantee that the house and land packages would be with Chehade
Constructions was against the weight of the evidence and not persuasive. Whilst
construction funding for the joint venture parties to build houses on O’Connell
Street was pursued in 2020 that yielded a letter setting out indicative terms in
January 2021, no agreement was reached to develop O’Connell Street that way.
The evidence about this is clear. Mr Lawrence was advised and considered this
option for developing O’Connell Street too high a risk and told Mr Chehade so.
426 Finally, it is necessary to address the significance of Mr Chehade’s evidence about
being happy for another builder to be found for O’Connell Street and that this was
225 T610.1.
226 Built Environs Pty Ltd v Tali Engineering Pty Ltd [2013] SASC 84 at [152] (Blue J).
-- 74 of 105 --
[2026] SADC 3
71
discussed on a number of occasions. It was suggested to Mr Chehade in cross-
examination that since his evidence was that they had discussed using another
builder and he was happy to do so, Mr Lawrence did not have to use him for the
building contract for O’Connell Street. In answer, Mr Chehade said:227
We had to agree and we agreed if he could produce someone else to build those houses at
a better price and with better quality or the same quality, I’m more than happy to use them
but that was never produced.
427 By his answer, Mr Chehade was disagreeing with the proposition that had been put
to him. Moreover, it is one thing to say something and another to make a binding
oral contract. Objectively viewed, what was said and ‘agreed’ does not constitute
a binding agreement to use another builder instead of Chehade Constructions. As
Mr Chehade said, that had to be agreed and it was not. No definitive proposal was
ever made for another builder to be involved in O’Connell Street, a matter that
would have required mutual agreement.
428 I am satisfied that despite the absence of any express agreement, there was also a
common understanding between Mr Chehade and Mr Lawrence and mutual assent
for Chehade Constructions to carry out the civil infrastructure works for O’Connell
Street. Such works were required to be carried out before construction could start
on any houses to be built on the allotments to be sold as a house and land
packages. Two matters fortify my conclusion in this regard. First it is implicit in
the email communications between Mr Chehade and Mr Lawrence in early 2020
about the civil development works that both of them assumed Chehade
Constructions would carry out that work. Secondly, Mr Lawrence said in evidence
that he shared Mr Chehade’s assumption that the civil infrastructure works would
have been carried out by Chehade Constructions.228
429 I am also satisfied that such works would have been carried out on a cost plus 15%
basis. Mr Lawrence agreed this would have been the case. It was the agreed price
for all other construction works carried out by Chehade Constructions for every
other development where it was engaged.
Alleged Profit Share Variation
The Issue
430 Given its importance, it is appropriate next to deal first with the question of
whether the parties’ agreement to share profits equally was varied in early 2020.
431 The respondents’ pleaded case is that at a meeting at Almina’s café in about early
2020, prior to completion of the Radar Street and O’Connell Street developments
and at about the time the Glen Rovala Street/Gregory Street development was
completed, Mr Chehade and Mr Lawrence orally agreed that there would no longer
227 T268.1-.8.
228 T607.1-.9.
-- 75 of 105 --
[2026] SADC 3
72
be any profit splitting for these developments.229 Instead, it was orally agreed that
the respondents were to profit from the development and the applicants were to
profit from the build if they were engaged to carry out the build.230
432 Property Partners denies any such agreement was made. It relies on the
uncontentious starting position that it was agreed at the time of entry into each joint
venture to share profits equally and it claims its equal share of the profits for Radar
Street ($58,221.98 including GST), Chicklade Street ($7,994.77 including GST)
and O’Connell Street ($711,389.80 including GST).231
433 Resolution of this issue turns on a factual dispute about whether an oral agreement
was made between Mr Chehade and Mr Lawrence as alleged by the respondents.
Conclusion
434 For the reasons discussed above,232 I have found that Mr Chehade and
Mr Lawrence did not agree in early 2020 to vary their existing agreement to share
profits equally for the Radar Street, Upton Street/Chicklade Street and O’Connell
Street joint ventures. Specifically, I have found that there was no oral agreement
made that ended Property Partners’ existing entitlement to share profits equally for
these joint ventures or that Mr Chehade’s only benefit from these joint ventures
would be the revenue/profit from any building contracts that Chehade
Constructions was engaged to do, of which there was no guarantee.
435 Accordingly, the parties’ existing agreement prevails. That is, Property Partners
on the one part and Lawrdo Investments and/or Lawrdo Super on the other part are
contractually bound to share the profits and losses of these joint ventures in equal
proportions.
Interest and other costs
Alleged June 2016 Agreement
Issues
436 The applicants’ pleaded case is that Mr Chehade and Mr Lawrence agreed in a café
discussion in 2016 that they would continue to do developments together on the
basis that “Lawrence would receive a return on the monies provided at reserve
bank rate plus 2%.”233 The respondents deny any such agreement was made,
relying on the terms of the draft PMS Agreement as initially governing the
disputed joint ventures, despite clause 3 of that agreement providing that in
calculating profits, interest as a project cost would be calculated as “being the
Royal [sic] Bank Australia (RBA) Cash Rate plus 2%”.234
229 Defence [1.13].
230 Respondents Written Opening [2.3]; Respondents Written Closing [33].
231 Applicants Written Closing [230]; Exhibit A20.14.
232 See [274]-[289] above.
233 Claim [3(b)].
234 Exhibit A2.9.119.
-- 76 of 105 --
[2026] SADC 3
73
Conclusion
437 For the following reasons, I have found the evidence does not establish that any
agreement was reached in 2016 for the interest rate on funds provided by
Mr Lawrence’s entities to be the RBA cash rate plus 2% for future developments
going forward.
Analysis
438 There was consensus that Mr Chehade and Mr Lawrence initially met in about
June 2016 at their local café to discuss changes to their joint venture arrangements
going forward after he had identified Radar Street as a development opportunity.
439 The evidence establishes there was no discussion about the interest rate that would
apply to funds provided by Mr Lawrence’s entities, let alone any legally binding
agreement that the rate would be the RBA cash rate plus 2%.235
440 There is also no evidence of any subsequent agreement in 2016 that this interest
rate would apply, although it may have been discussed in or about December 2016,
proximate to the sending of the emails attaching draft joint venture agreements that
provided for this interest rate as a proposed term.
441 This interest rate was first proposed in the second revision to the draft joint venture
agreement attached to Mr Lawrence’s 9 December 2016 email, albeit incorrectly
referencing the “Royal Bank Australia (RBA) cash rate plus 2%”236 and repeated
in the same terms in the draft PMS Agreement. By comparison, there was no
interest rate specified in the first revision of Mr Chehade’s draft joint venture
agreement dated 7 October 2016 proposed by Mr Lawrence’s 30 September 2016
email.237
442 However, for the reasons that follow shortly, I have found that there was no
agreement for the terms of the draft PMS Agreement to apply to the parties’
property development joint ventures going forward, and therefore no agreement to
the terms of clause 3 that provided that the applicable interest rate in calculating
profit would be the RBA cash rate plus 2%.
PMS Agreement
Issues
443 The respondents contend that the terms of the draft PMS Agreement emailed to
Mr Chehade on 15 December 2016 initially governed the disputed joint ventures,
which the applicants deny.238 Whether its terms apply determines whether it was
initially agreed that in calculating profit for the disputed joint ventures, interest is
235 See [152]-[156] above.
236 Exhibit A2.8.103.
237 Exhibit A2.7.
238 MFI 1 [6.1].
-- 77 of 105 --
[2026] SADC 3
74
to be calculated on 80% of the purchase price of the property or on all project costs
as per clause 3(b) of the draft PMS Agreement at the RBA cash rate plus 2%.
444 The respondents’ pleaded case239 is that agreement to the terms of the PMS
Agreement was reached on the basis of Mr Chehade’s silence and failure to dispute
the following statement in Mr Lawrence’s covering email:240
As discussed, please find the Agreement will be used for the Development activities going
forward. This was reviewed by my Accountant to better protects my Super Unit Trust.
445 The respondents submitted the parties then conducted their joint ventures on the
basis of the PMS Agreement and the application of its terms is confirmed by the
purchase of Radar Street by Lawrdo Super settling soon after Mr Lawrence’s
email.241
446 Save that the draft PMS Agreement provided that the parties shared profits equally,
its terms were materially different from the agreements for all of the parties’
previous joint ventures, including the term for calculating interest as a joint venture
cost.
447 It is uncontentious that the PMS Agreement is unsigned and that Mr Chehade did
not respond to the email in writing. As the applicants correctly point out, there is
no pleaded conduct or reliable evidence justifying a finding that Mr Chehade
accepted the terms of the PMS Agreement orally or by conduct.
448 In the alternative, the respondents’ pleaded case relies on an estoppel on the basis
of Property Partners’ alleged failure to take issue with what was stated in the
15 December 2016 email.242
449 Ultimately, resolution of these issues turns on a factual dispute about whether
Mr Chehade told Mr Lawrence in a telephone conversation in December 2016 that
he did not accept the terms of the draft PMS Agreement.
Conclusion
450 For the reasons that follow shortly, I have found that Mr Chehade did dispute
Mr Lawrence’s proposal that the PMS Agreement apply to the parties’ joint
ventures going forward and he did not agree to its terms.
451 Accordingly, and contrary to the respondents’ case, the parties’ common
understanding and agreement in entering into each of the disputed joint ventures
was that they would share profits equally and conduct them on the same
fundamental terms as their earlier joint ventures and not on the terms of the draft
PMS Agreement.
239 Defence [1.7].
240 Exhibit A2.9.116.
241 Respondents Written Closing [24]-[25].
242 Defence [1.8].
-- 78 of 105 --
[2026] SADC 3
75
452 Specifically, Mr Chehade and Mr Lawrence did not agree to change their existing
agreement or for interest to be calculated on the different basis of total project
costs. Accordingly, their existing agreement prevailed that in determining joint
venture profit, interest was to be calculated on the basis of 80% of the purchase
price of the property.
Analysis
453 For the reasons discussed above,243 I accept Mr Chehade’s evidence that he
objected to the terms of the draft PMS Agreement in a telephone conversation with
Mr Lawrence in late December 2016. I reject Mr Lawrence’s evidence to the
contrary. His evidence that it was the ‘final version’ and Mr Chehade ‘knew this’
in the absence of any credible evidence about what Mr Chehade said to accept its
terms was self-serving and unsatisfactory. Furthermore, Mr Lawrence had no
recollection of what was discussed between this email and 9 December 2016 when
he met Mr Chehade for breakfast.
454 The words in the covering email “As discussed”, do not assist the respondents’
case when read in context of the reliable evidence of the surrounding
circumstances. It is plain that the draft PMS Agreement was sent to Mr Chehade
for the first time under cover of Mr Lawrence’s email of 15 December 2016. Its
terms are materially different to the draft Mr Lawrence sent Mr Chehade on
9 December 2016. Mr Lawrence’s evidence to the contrary and his rhetorical
justification that “it doesn’t make sense to write stuff that he disagreed about”
does him no credit in the proven circumstances.244
455 Neither the draft PMS Agreement nor its term as to interest were mentioned again
in any communication between the parties. Indeed, the interest term is inconsistent
with subsequent emails sent by Mr Lawrence in February 2018 and in April and
July 2019 proposing different changes to the basis of calculating interest in
determining joint venture profit.
456 I also reject the respondents’ submission that Mr Chehade knew a document
needed to be agreed before Mr Lawrence would agree to develop the Radar Street
property and this was confirmed by the timing of the Radar Street settlement soon
after. It was not. The email attaching the draft PMS Agreement was sent after the
Radar Street settlement, and not before. The respondents’ submission in this regard
is not correct.
457 In any event, Mr Lawrence’s evidence in chief on this topic did not support this
submission. Mr Lawrence said that he wanted to get this document signed before
the purchase of Radar Street and did not specifically remember discussing this with
243 See [187]-[197] above.
244 T503.23-.28.
-- 79 of 105 --
[2026] SADC 3
76
Mr Chehade. His evidence “but the intention of the document was known”245 is not
sufficient proof of a mutual assent to be legally bound.
458 The respondents’ estoppel case fails on the proven facts. It is therefore unnecessary
to address the conceptual difficulties arising from the respondents’ inadequately
pleaded estoppel claim. Suffice it to say, no material facts are pleaded identifying
any alleged detriment or unconscionability and none was proven or ventilated at
trial or in closing submissions.
10% Interest and New Funding Costs
Issues
459 The respondents contend that on about 5 July 2019 it was agreed by
Mr Chehade and Mr Lawrence that in calculating joint venture profit for the
disputed developments, an interest rate of 10% would be charged on funds spent
by the respondents in purchasing the property and paying for construction works
as well as other fees. The respondents rely on the terms of an email sent by
Mr Lawrence to Mr Chehade on 5 July 2019 that he allegedly did not dispute. 246
460 In the alternative, the respondents contend that Property Partners is estopped from
denying a 10% interest rate was agreed on the basis that Property Partners did not
take issue with what was stated in the email.247
461 It is uncontentious that Mr Chehade did not respond in writing to this email.
462 Again, resolution of these issues turns on a factual dispute about whether
Mr Chehade ever objected orally to the imposition of new costs and a 10% interest
rate as demanded in this email.
Conclusion and Analysis
463 For the reasons discussed above,248 I have accepted and preferred
Mr Chehade’s evidence to Mr Lawrence’s evidence about what was said about
Mr Lawrence’s demands to vary the parties’ agreement as to interest, additional
funding costs and a penalty as reiterated in his 5 July 2019 email.
464 I find that a reasonable businessperson in Mr Lawrence’s position would have
understood from what Mr Chehade said that he did not accept a 10% interest rate
or the additional funding costs and penalty demanded by Mr Lawrence in his
30 April and 5 July 2019 emails.
465 Absent Mr Chehade’s agreement for the terms of the 5 July 2019 email to apply to
their current joint ventures, the parties’ existing agreement prevailed and was not
245 T354.1-.11.
246 Defence [1.11].
247 Defence [1.12].
248 See [246]-[266] above.
-- 80 of 105 --
[2026] SADC 3
77
varied. That is, interest was agreed to be calculated on the basis of 80% of the
purchase price of the property in determining joint venture profit.
466 In closing, the respondents submitted that it was implausible that an experienced
developer such as Mr Chehade would not have responded to
Mr Lawrence’s 5 July 2019 email if he disagreed. This submission is without merit
and against the weight of the evidence, including Mr Lawrence’s evidence that
Mr Chehade “hardly put anything in email”.249
467 The respondents’ estoppel case also fails on the proven facts. It is inadequately
pleaded, suffering from the same fundamental defects as the estoppel plea made
for the PMS Agreement. There are no material facts pleaded identifying any
alleged detriment or unconscionability and none was proven or ventilated at trial
or in closing submissions.
Conclusion on Interest on Disputed Joint Ventures
Basis of Calculation
468 At the time the disputed (and other) joint ventures were established in 2016 and
2017, it was the common understanding and intention of the parties that interest
would be calculated on 80% of the purchase price of the property. This was the
basis upon which interest had been calculated in determining joint venture profit
for the previous seven joint ventures completed by 2015.
469 That this was the case was uncontentious. The respondents’ case was that the
parties’ initial agreement as to the basis of calculating interest in determining joint
venture profit was varied first by the terms of the PMS Agreement and secondly,
by the terms of Mr Lawrence’s 5 July 2019 email. Indeed, in cross-examination
Mr Lawrence explained that the parties’ assumption at the date of purchase of the
disputed joint ventures properties changed:250
…The arrangements changed as the sequence of emails and discussions which established
that the interest rate would be in the order of 10%. In fact I think it was 10% and the LVR
rate was also varied from 80% to 100%. So in terms of your questions previously, at the
time of buying that was the understanding, but it subsequently changed.
470 For the reasons set out above, I have concluded there was no agreement reached
to vary the parties’ initial agreement for calculating interest. Their common
understanding at the time of purchase of each of the disputed joint venture
properties as to the basis of calculating interest as a project cost remains the agreed
basis for determining joint venture profit.
471 That is, interest as a project cost is to be calculated on 80% of the purchase price
of the property for the period between settlement of the purchase and repayment
of the funds provided by Lawrdo Investments and/or Lawrdo Super.
249 T497.1-.2.
250 T519.9-.15.
-- 81 of 105 --
[2026] SADC 3
78
Interest Rate
472 There was some dispute about the agreed interest rate. There was consensus that
5.5% was the agreed interest rate for the early joint ventures, save for Baldock
Road. Mr Lawrence recalled that 8% was agreed for this development.251
473 The applicants’ pleaded case was that it was orally agreed in 2016 that
Mr Lawrence’s return on funds provided to purchase joint venture property would
be the RBA cash rate plus 2%.252
474 Mr Chehade said the agreed rate for the earlier joint ventures was based on
prevailing bank rates that varied. His evidence in this regard was vague and
unhelpful. Ms Rossi was more precise. Her instructions as to the agreed formula
were that interest was to be calculated on 80% of the purchase price at a rate 2%
above the cash rate but the rate changed from time to time depending on movement
in the cash rate or her instructions as to what Mr Chehade and Mr Lawrence had
otherwise agreed.253
475 Contrary to the respondents’ pleaded case that the draft PMS Agreement (and
therefore its term as to interest) initially governed the disputed joint ventures,
Mr Lawrence’s evidence was that the parties’ agreement on the applicable interest
rate was ad hoc and not set by reference to the RBA cash rate.254 He said they
simply negotiated and struck an agreed rate from time to time.
476 I accept Mr Lawrence’s evidence that he and Mr Chehade negotiated and agreed
an interest rate for their joint ventures on an ad hoc basis. I also accept that such
agreements were struck without express reference to the RBA cash rate plus 2%,
although it is likely that this formula was discussed. That it was discussed in the
proven circumstances is not sufficient proof that it was agreed.
477 For the reason discussed above,255 I have found Mr Chehade and Mr Lawrence
agreed in February 2018 that the interest rate to be applied in calculating profit
going forward would be 6.5% and this agreement supersedes any agreement made
in 2016.
478 Accordingly, the previously agreed interest rate of 6.5% applies to the calculation
of interest as a joint venture cost in determining joint venture profit for the disputed
developments.
Breach
479 Having concluded that there was no agreement to end the parties’ existing
agreement to share profits in equal proportions for the disputed joint venture made
251 T505.7.
252 Claim [3(b)].
253 T298.36-299.1.
254 T515.31-517.18.
255 See [229]-[235] above.
-- 82 of 105 --
[2026] SADC 3
79
in 2020,256 Property Partners is entitled to be paid its contractually agreed 50%
share of the profits generated in developing the Radar Street and Upton
Street/Chicklade Street properties. Despite both joint ventures reaching
completion by the sale of the developed subdivided land and a calculation of the
profits and an accounting taking place, the respondents have not paid Property
Partners its profit share for these joint ventures.
480 The respondents’ continuing refusal since completion of these developments to
account to Property Partners for its 50% profit shares undisputedly constitutes a
breach of the respondents’ contractual obligations.
481 As regards O’Connell Street, the respondents’ conduct from about March 2021 -
in completing the development on their own without the applicants’ participation,
denying their interests in the joint venture and its assets, failing to account for
Property Partners’ 50% profit share, selling house and land packages nominating
YY Group Pty Ltd instead of Chehade Constructions as the builder and engaging
YY Group Pty Ltd to carry out the civil infrastructure works instead of Chehade
Constructions - constitutes continuing breaches of the respondents’ contractual
obligations. As I have found, the obligations to Property Partners arise under a
joint venture agreement made when parties initially decided to acquire the
O’Connell Street property in 2017 and develop it as joint venturers for mutual
profit on the same fundamental terms as their previous joint ventures.257 As I have
also found, the obligations to Chehade Constructions arise under an informal
agreement for it to undertake the civil infrastructure works and an oral agreement
made in May 2020 for it to be the nominated builder in house and land packages
to be sold by Ray White.258
482 These breaches of contract entitle the applicants to common law damages.
483 For completeness, it is necessary to mention the applicants’ pleaded contention
that the respondents breached their obligation to fund the development of
O’Connell Street. Whilst it is clear from the evidence that Mr Lawrence’s role
was as funder and there were difficulties raising the funds required to develop
O’Connell Street, there was no agreement about the amount and manner of
funding, nor any agreed timeline. These difficulties were not ventilated at trial.
The evidence does not establish a breach of any funding obligation. That there
was no breach of the respondents’ funding obligations for the O’Connell Street
joint venture does not affect the outcome of this proceeding.
256 See [434]-[435] above.
257 See [223]-[228] above.
258 See [414]-[429] above.
-- 83 of 105 --
[2026] SADC 3
80
Damages
Principles
484 It is well established that a breach of contract by one party always gives the other
party a right to recover damages for the breach.259
485 In assessing damages for breach of contract the ‘ruling principle’ is that the award
should put the injured party, so far as money can do it, in the same situation as if
the contract had been performed as promised.260 Incontrovertibly, the purpose of
the award of damages is compensatory.
486 The corollary of the ‘ruling principle’ in Robinson v Harman261 is that an award of
damages for breach of contract should not put the injured party in a superior
position than they would have been had the contract been performed.262 Therefore,
where an injured party claims damages for a loss caused by a breach of contract,
any benefit received by the promisee must be taken into account in determining
the extent of their loss.
487 There are qualifications to the ‘ruling principle’. One is that the law does not
compensate an injured party for the non-fulfilment of an expectation that could not
reasonably be supposed to have been within the contemplation of the other party
when they made their contract as the probable result of breach.263 Another is that
damages which are too remote are not recoverable.
488 The injured party bears the onus of establishing that there has been actual loss, that
the breach of contract has caused it, that the loss was not too remote and the
measure to be awarded.264
489 The general, although not universal, rule is that damages in contract are assessed
at the date of breach or when the cause of action arises.265 They are assessed on a
“once and for all basis”.266 The rule is motivated by concerns about mitigation and
in part by notions of fairness to the defaulting party.267 In Clark v Macourt,
Keane J said:268
259 Agricultural Rural Finance Pty Ltd v Gardiner (2008) 238 CLR 570 at 589 (Gummow, Hayne and
Kiefel JJ).
260 Robinson v Harman (1848) 154 ER 363 at 365; Wenham v Ella (1972) 127 CLR 454 at 460, 471;
Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009) 236 CLR 272 at 286 [13]; Clark v Macourt
(2013) 253 CLR 1 at [7], [26], [60] and [106].
261 (1848) 154 ER 363.
262 The Commonwealth v Amann Aviation Pty Ltd (1991) 174 CLR 64 (Amann Aviation) at 82 citing L
Albert & Son v Armstrong Rubber Co (1949) 178 F. 2d 182 at 189; and also 136, 155 and 163.
263 European Bank Ltd v Evans (2010) 240 CLR 432 at 438 [12]-[13], referring to Hadley v Baxendale
(1854) 154 ER 145 at 151.
264 Amann Aviation at 80, 99, 118 and 137.
265 Johnson v Perez (1988) 166 CLR 351 at 356 (Mason CJ) (Johnson).
266 Bellgrove v Eldridge (1954) 90 CLR 613 at 620.
267 Johnson at 357-358.
268 (2013) 253 CLR 1 at [109] citing Johnson at 355-356.
-- 84 of 105 --
[2026] SADC 3
81
The value to be paid in accordance with the ruling principle is assessed at the date of breach
of contract, not as a matter of discretion, but as an integral aspect of the principle, which is
concerned to give the purchaser the economic value of the performance of the contract at
the time that performance was promised. In this way, the measure of damages captures for
the purchaser the benefit of the bargain and so compensates the purchaser for the loss of
that benefit.
(Citations omitted)
490 The rule that damages are assessed at the time of breach is not absolute. The Court
will depart from it to avoid injustice.269
Property Partners’ Loss
491 Property Partners claims common law damages in contract in the amount of its
50% share of the profits generated by each of the Radar Street, Upton
Street/Chicklade Street and O’Connell Street joint ventures. The quantum of its
pleaded profit shares were estimates. In December 2023, when the claim was filed,
not all the project costs and revenues were known. Indeed, many of the O’Connell
Street allotments had not been sold.
492 Ultimately, Property Partners formulated its 50% profit shares for the disputed
joint ventures as follows:
• $58,221.98 including GST for Radar Street270
• $7,994.77 including GST for Upton Street/Chicklade Street271
• $711,389.80 including GST for O’Connell Street272
Radar Street and Upton Street/Chicklade Street
493 Having found in Property Partners’ favour on the profit share question, there is no
real contest about the measure of its loss.273
494 The calculations of Property Partners’ profit share prepared by the applicants for
the Radar Street274 and Upton Street/Chicklade Street275 joint ventures factor in
interest at a rate of 5.5% on 80% of the purchase price. Apart from interest, the
respondents do not challenge these calculations because their primary challenge
was unsuccessfully directed at Property Partners’ contractual entitlement to share
profits at all.
269 Johnson at 355-356, 367 and 386-387.
270 Applicants Written Closing [106] and [230.1]; Exhibit A3.21.
271 Applicants Written Closing [135] and [230.3]; Exhibit A4B.22.
272 Applicants Written Closing [205] and [230.5]; Exhibit A20.
273 See [434]-[435] above.
274 Exhibit A3.21.
275 Exhibit A4A.22.
-- 85 of 105 --
[2026] SADC 3
82
495 Having found that interest as a project cost should be calculated on basis of 80%
of the purchase price of these properties at an interest rate of 6.5%, Property
Partners’ profit calculations require adjustment. I will make orders for revised
calculations to be brought into Court as part of the proposed form of the final
judgment to be entered.
O’Connell Street
496 For O’Connell Street, the applicants ultimately relied on Mr McPharlin’s report276
estimating Property Partners’ loss of “potential profit” of $711,389.80 (including
GST) based on actual sales revenue of $2.618 million.277
497 The respondents did not seriously challenge Property Partners’ formulation of its
damages claim, other than to suggest Mr McPharlin’s estimate does not include all
necessary expenses.
498 Having regard to the evidence, I am satisfied that the respondents’ breaches of
contract have caused Property Partners’ loss and damage in the amount of the profit
it would have earned from the completion of the development in the proven
circumstances. Such loss was both within the reasonable contemplation of the
parties and not too remote. The respondents did not contend otherwise.
499 The only questions arising for consideration concern the adequacy of
Mr McPharlin’s estimate of the loss of potential profit on the proven evidence,
accepting that if Property Partners remained involved, the development would
have proceeded to completion by the sale of house and land packages nominating
Chehade Constructions as the builder, as was agreed by the parties in May 2020.
Indeed, that was how it ultimately did proceed with the assistance of ABC and the
services of a buyer’s agent and all allotments were sold once the civil infrastructure
works were completed but with another builder instead of Chehade Constructions.
500 Whilst the sale contracts for all 13 allotments had settled before trial, there had not
been a final accounting. For trial, Mr McPharlin revised his earlier estimate to take
account of the actual sales. His estimate was qualified in several key respects.
501 First, his estimate made no allowance for interest as a project cost. Interest should
be allowed as a project cost at the 6.5% interest rate that I have found applied to
80% of the purchase price of the property.
502 Secondly, no allowance was made for additional holding costs incurred since his
first estimate was made. An allowance should be made for these costs.
503 Thirdly, as he explained in examination in chief, for expenses he relied on the
estimates provided to him, which amounts he verified against the vouchers
provided to him, save for some 6% by value (in table 4.7) that he could not
276 Exhibit A20.
277 Ibid; Applicants Written Closing [205].
-- 86 of 105 --
[2026] SADC 3
83
reconcile.278 Nor did he consider the further discovered invoices provided to him
before he gave evidence. In cross-examination, Mr McPharlin readily accepted the
obvious that if there were any further expenses that were not in the spreadsheet of
costs he had allowed, profit would reduce.279 He also confirmed that he did not give
any independent consideration as to whether there were any items that were not
allowed as expenses that should have been.
504 Whilst making this point, the respondents in presenting their case at trial did not
plead or adduce any evidence of expenses omitted from Mr McPharlin’s estimate
that would have reduced his estimate of profit. In the absence of such evidence, it
is reasonable to conclude that there are no further expenses to be taken into account
in calculating profit.
505 Fourthly, as regards selling costs, Mr McPharlin allowed $750 in commission per
property and quite properly did not allow the ABC consulting fee of $318,175
including GST as an expense.
506 Plainly, as the respondents ultimately conceded, the ABC consulting fee should be
disregarded as a project cost280 as should the sales consultancy fee of $2,500 per
property paid to ABC for Ms Rochelle Adams’ services. The ABC consultancy fee
was not a genuine project cost and there would have been no need for ABC to
provide any sales consulting services if Property Partners had remained involved
in the development.
507 That said, the documentary evidence shows that the sales of the O’Connell Street
allotments at the higher prices involved the services of an interstate buyer’s agent
whose commission was factored into the ultimate selling prices by increasing
them. Such commission should be allowed as a project cost. It was not a service
that Property Partners could have provided. On the evidence, I am not satisfied
that these higher prices would have been obtained from buyers in the local market
without the services of the interstate buyer’s agent.
508 For these reasons, I have concluded that further material adjustments are required
to be made to Mr McPharlin’s profit estimate for O’Connell Street. Accordingly,
I will make orders for further submissions to be made on quantum having regard
to my findings, rather than make a broad brush allowance for the required
adjustments.
Chehade Constructions’ Loss
509 For the O’Connell Street joint venture, Chehade Constructions is entitled to
contractual damages for the loss of profit it would have made if it had carried out
the civil infrastructure works for the joint venture parties and the residential
278 T283.19-284.13.
279 T290.16-.29.
280 Defence [40].
-- 87 of 105 --
[2026] SADC 3
84
building works for third parties who purchased allotments as house and land
packages.
510 Chehade Constructions submitted the Court should award contractual damages in
the range set out in Mr Sale’s expert report for 15% builder’s margin on the
reasonable costs of carrying out the civil infrastructure and residential building
works in September/November 2020 or September 2023 as follows:281
2023 2020
Building Works $398,000.00 $352,000.00
Main Civil Works $59,000.00 $52,000.00
Total (excluding GST) $457,000.00 $404,000.00
Total (including GST) $502,700.00 $444,400.00
511 His opinion as to the 15% builder’s margin in 2020 was based on his opinion as to
the reasonable costs of carrying out the works at September/November 2020 rates,
the date when Chehade Constructions entered into building contracts with third
party purchasers of house and land packages for O’Connell Street. His opinion as
to the 15% builder’s margin in 2023 was based on his opinion as to the reasonable
costs of carrying out the works at September 2023 rates when he prepared his
report.
512 The respondents did not challenge Mr Sale’s opinions, having unsuccessfully
advanced a case that Chehade Constructions has no legal entitlement to carry out
the building works for O’Connell Street.
513 Having regard to Mr Sale’s instructions, methodology and detailed workings,
I accept Mr Sale’s opinions as to the builder’s margin on the reasonable costs of
carrying out the relevant works, noting that in his opinion that rates offered by
Chehade Constructions and its subcontractors were within the market range for
residential construction of a house of ‘basic design’.
514 The question as to whether 2020 or 2023 rates were appropriate for estimating
reasonable building costs in this case was not ventilated in submissions at trial.
Having regard to the date of the respondents’ breaches, when it was likely Chehade
Constructions would have carried out the works and when the works were in fact
done by YY Group Pty Ltd, the more appropriate time for assessing damages is
September 2023.
515 The question as to whether the 15% builder’s margin overstated Chehade
Constructions’ loss of profit was also not ventilated at trial. Whilst builder’s
margin includes off-site overhead and is not all profit, it is reasonable to infer that
by losing its margin, Chehade Constructions lost a contribution to off-site overhead
that was a sunk cost. For this reason, I accept 15% builder’s margin is a fair
measure of Chehade Constructions’ loss of profit.
281 Exhibit A21.
-- 88 of 105 --
[2026] SADC 3
85
516 For these reasons, Chehade Constructions is entitled to common law damages of
$502,700.00 including GST for lost builder’s margin of 15% on a cost plus basis.
This amount comprises $59,000.00 for the civil infrastructure works and
$398,000.00 for the residential building works (both excluding GST) plus GST of
$45,700.00.
FIDUCIARY DUTY CLAIM
Issues
517 Property Partners seeks various relief for alleged breaches of the respondents’
fiduciary duties concerning O’Connell Street arising by virtue of the parties’ joint
venture relationship.282 It contends the terms of the parties’ joint venture agreement
gave rise to fiduciary obligations of honesty and good faith, not to act in conflict
of interest and not to develop or use the O’Connell Street land for their own
interests or make secret profits from it. Property Partners relies on the nature and
terms of the joint venture agreement it contended governed the parties’ joint
venture to develop O’Connell Street.
518 Property Partners further alleges the respondents breached their fiduciary
obligations by not funding the development,283 by retaining the O’Connell Street
land for their own purposes, excluding Property Partners from participating in its
further development and failing to account for any profits derived from this
development.284 As a result, Property Partners contends it has lost its 50% share of
the profit from the O’Connell Street joint venture.
519 Property Partners submits the measure of damages is the same as in contract,
estimated to be $711,389.80 (including GST) on the basis of Mr McPharlin’s
expert report.285
520 The respondents formally join issue with Property Partners’ fiduciary duty claim,
mounting a positive case in defence that the PMS Agreement initially governed
their agreement and in early 2020 Mr Chehade and Mr Lawrence agreed to end
profit sharing and this was consistent with the way in which the parties conducted
the O’Connell Street development. The respondents further contend that no
fiduciary obligation can arise in the (unpleaded) circumstances where
Mr Lawrence depended on Mr Chehade’s skill and experience from the
commencement of the relationship and Mr Chehade withheld key information
from him.
521 There is no substantive dispute about the respondents’ conduct that allegedly
breached the respondents’ fiduciary duties or following Mr Lawrence’s fourth
282 Defence [34]-[39]; Claim Part 4 [2(b)]-[2(f)]; MFI 1 [30] and [37].
283 Claim [33].
284 Claim [36].
285 Exhibit A20.
-- 89 of 105 --
[2026] SADC 3
86
affidavit,286 any significant challenge to the estimated quantum of Property
Partners’ claimed 50% profit share save for interest.
522 Having concluded the PMS Agreement did not initially govern their joint venture
and no oral agreement was made in early 2020 to end Property Partners’ existing
entitlement to share profits equally for O’Connell Street, the critical question
arising is whether the respondents stood in a fiduciary relationship to Property
Partners as joint venturers on the proven terms of their agreement to share profits
equally.
Principles
523 The general principles to be applied are uncontentious. They are well established
and for present purposes may be briefly summarised as follows.
(1) Whether a relationship between joint venture parties is necessarily a fiduciary one
will depend upon the form the joint venture takes and the content of the
obligations undertaken by the parties to it.287
(2) As a general principle, fiduciary duties may arise when one party undertakes to
act in the interests of another in a manner that invokes trust and confidence.
A fiduciary undertakes to act for, or on behalf of, or in the interests of another
person in the exercise of a power or discretion which will affect the interests of
the other person in a legal or practical sense.288
(3) Where a person who owes fiduciary duties finds themselves in a position of
conflict between personal interest and fiduciary duty, or a significant possibility
that a conflict will arise, the ‘conflict rule’ precludes the fiduciary from acting in
the fiduciary’s personal interest.289
(4) Under the ‘conflict rule’, a fiduciary acting without informed consent is under an
obligation not to promote their personal interests by making or pursuing a gain in
circumstances in which there is a conflict, or a real or substantial possibility of a
conflict, between personal interest and those to whom the duty is owed.290
(5) The ‘profit rule’ is directed at requiring “the fiduciary to account for any benefit
or gain obtained or received by reason of or by use of [the] fiduciary position or
286 Exhibit A2.51.
287 United Dominions Corporation Ltd v Brian Pty Ltd (1985) 157 CLR 1 at 11 (Mason, Brennan &
Deane JJ).
288 Hospital Products Pty Ltd v United States Surgical Corporation (1984) 156 CLR 41 (Hospital
Products) at 96-97 (Mason J); John Alexander’s Clubs Pty Ltd v White City Tennis Club Ltd [2010]
HCA 19; (2010) 241 CLR 1 at [87].
289 Chan v Zacharia (1984) 154 CLR 178 (Chan) at 198-199 (Deane J); Breen v Williams (1996) 186 CLR
71 (Breen) at 93 (Dawson and Toohey JJ); Ancient Order of Foresters in Victoria Friendly Society Ltd
v Lifeplan Australia Friendly Society Ltd [2018] HCA 43; (2018) 265 CLR 1 (Foresters) at [68]–[69]
(Gageler J); Grimaldi v Chameleon Mining NL (No 2) [2012] FCAFC 6; (2012) 200 FCR 296 (Grimaldi)
at [178]–[179] (Finn, Stone and Perram JJ).
290 Pilmer v Duke Group Ltd (in liq) [2001] HCA 31; (2001) 207 CLR 165 at [78] (McHugh, Gummow,
Hayne and Callinan JJ).
-- 90 of 105 --
[2026] SADC 3
87
of opportunity or knowledge resulting from it.”291 The objective of the ‘profit
rule’ is to preclude “the fiduciary from actually misusing [the fiduciary’s]
position for personal advantage.”292
(6) The existence and scope of fiduciary duties are inherently fact-dependent. Not
only must the scope of a fiduciary duty be determined according to the facts of
the case, “it must be moulded according to the nature of the relationship…”293
(7) Fiduciary duties imposed by equity are proscriptive as opposed to prescriptive.294
(8) As a general rule, fiduciary obligations end with the fiduciary relationship,
however there are key exceptions to this principle such as obligations of
confidentiality.295
524 The ‘conflict rule’ operates to preclude a fiduciary from acting without informed
consent where there is a conflict or a real or substantial possibility of a conflict
between the fiduciary’s personal interest and those to whom the duty is owed in
the fiduciary’s personal interest. It is directed to ensuring the fiduciary is not
swayed by consideration of personal interest. The High Court explained in
Foresters,296 where the ‘conflict rule’ alone is invoked, the unconscionability
which attracts equitable remedies is the retention by the fiduciary of any benefit or
gain which equity considers, in conscience, should be disgorged to the principal
(in this case, joint venturer, Property Partners).
525 The ‘profit rule’ is directed at precluding a fiduciary from misusing the fiduciary’s
position for personal advantage. Under those circumstances, equity requires the
fiduciary to account for any benefit obtained or received by the fiduciary. The
unconscionability which attracts equitable remedies in such circumstances lies in
the pursuit by the fiduciary of self-interest, or, more precisely, in pursuit of an
interest other than the exclusive interest of Property Partners as their joint venturer.
Conclusion
526 In the proven circumstances, the relationship between Property Partners and the
respondents under their joint venture agreement exhibited all the indicia of, and
plainly was fiduciary.
527 Having concluded that the respondents stood in a fiduciary relationship with
Property Partners, there can be no doubt the respondents acted in breach of their
291 Chan at 198-199 (Deane J); Breen at 93 (Dawson and Toohey JJ); Foresters at [68]-[69] (Gageler J);
Grimaldi at [178]-[179] (Finn, Stone and Perram JJ).
292 Breen at 93 (Dawson and Toohey JJ); Foresters at [68]-[69] (Gageler J); Grimaldi at [178]-[179] (Finn,
Stone and Perram JJ).
293 Hospital Products at 102 (Mason J). See also Howard v Commissioner of Taxation [2014] HCA 21;
(2014) 253 CLR 83 at [34] (French CJ and Keane J); Links Golf Tasmania Pty Ltd v Sattler [2012] FCA
634; (2012) 213 FCR 1 at [481] (Jessup J).
294 Breen at 113 (Gaudron and McHugh JJ).
295 Blythe v Northwood [2005] NSWCA 221; (2005) 63 NSWLR 531 at [195] (Mason P).
296 (2018) 265 CLR 1 at [68] (Gageler J).
-- 91 of 105 --
[2026] SADC 3
88
fiduciary obligations and it is entitled to the declarations and orders sought for an
account of profits or equitable damages at its election.
528 Here, the respondents’ alleged breaches of fiduciary duty offend both the ‘conflict’
and the ‘profit’ rules and obligations of honesty and good faith. The
unconscionability attracting equity’s intervention arises from the respondents’
allegedly misusing their position as the registered proprietors of the trust property
to exclude Property Partners from participating in the development for the
respondents’ individual gain.
Analysis
Do obligations of a fiduciary nature arise?
529 The relationship between Property Partners and the respondents in the O’Connell
Street joint venture was a fiduciary one. It is apparent that it was from the outset
in 2017 when Mr Chehade and Mr Lawrence decided to develop this property as
joint venturers (in a commercial sense) for mutual profit.
530 The essential terms of their joint venture were not varied. Profits were to be shared
equally. The joint venture property (the O’Connell Street land) was acquired for
mutual benefit and was held on trust by the respondents for the parties as joint
venturers. The opportunity to develop the land was identified and secured by
Property Partners. It did the work to secure the approvals to subdivide the property
into 13 allotments. The subdivision was approved in August 2020. The
respondents’ role was to fund the development, which ultimately was fraught with
difficulties due to lack of funds and the ownership structure involving a SMSF.
531 Decisions about how the development would ultimately proceed were matters for
joint decision. Absent breach, neither party had any unilateral right to terminate
their joint venture agreement.
532 The parties’ relationship and the informality of their dealings necessarily involved
the reposing of mutual trust and confidence in one another in their dealings as joint
venturers and with the joint venture property.
533 It was submitted by the respondents that no fiduciary relationship existed and no
fiduciary duties arose because Mr Lawrence depended on Mr Chehade’s skill and
experience from the relationship and Mr Chehade withheld key information from
him, secretly profiting from the building contract made with Integrity New Homes.
Further, at all times Mr Chehade exercised a position of power over Mr Lawrence,
controlling the way in which the projects proceeded, who was to build on the
vacant land and the allocation of profits.297
534 I do not accept the respondents’ submissions.
297 Respondents Written Closing [13]-[14].
-- 92 of 105 --
[2026] SADC 3
89
535 There is no substance to their (unpleaded) factual foundation. The evidence does
not establish that key information was withheld from Mr Lawrence or any secret
profit made by Mr Chehade through building contracts with Integrity New
Homes. Nor does the evidence establish that Mr Chehade controlled the way in
which projects proceeded in any inappropriate way, bearing in mind that it was
the role of Property Partners through Mr Chehade to manage the development for
the joint venture parties’ mutual benefit. Moreover, Mr Lawrence accepted in
evidence that they met regularly and he did know about Mr Chehade’s
involvement in Integrity New Homes. How this matter is relevant to the
agreement made in 2017 to purchase and develop the O’Connell Street property
as a joint venture when they had stopped dealing with Integrity New Homes
before 2016 was not explained.
536 To the extent that Mr Lawrence reposed trust and confidence in Mr Chehade and
was vulnerable to Mr Chehade’s dealings in managing the development of the
joint venture property, were important indicia of a fiduciary relationship in
circumstances where Mr Chehade reposed trust and confidence in Mr Lawrence
as the registered proprietors of the O’Connell Street land. The relationship was
(in the terms sometimes used in academic discussion of the principles) a
‘horizontal’, not ‘vertical’ one.
Did the respondents act in breach of fiduciary duty?
537 In about March 2021, Mr Lawrence first contemplated proceeding with the
development without Property Partners and made the unilateral decision to appoint
National Realty as sales agent for O’Connell Street, apparently having contacted
ABC about them assisting in completing the development instead of Mr Chehade.
On 2 June 2021, Mr Lawrence terminated Ray White’s agency without consulting
Mr Chehade. On 7 June and 12 August 2021, Mr Lawrence sent Mr Chehade
emails telling him in no uncertain terms that he was not to have any further
involvement with the development or represent the respondents’ interests. His
email to Ms Rossi implying the development was on hold was, in the
circumstances of his prior dealings with ABC, misleading. The respondents then
proceeded to complete the development of O’Connell Street without the
participation of Property Partners or accounting to it for any profits made.
538 By their conduct in excluding Property Partners from further participation in the
development of O’Connell Street, they breached both the ‘conflict rule’ and ‘profit
rule’. Their conduct with regard to the purported ABC agreement and consulting
fee was dishonest and intended to understate project profits to gain more than a
50% profit share, should Property Partners be entitled to share profits.
Equitable Remedies
539 Having found the respondents breached their fiduciary obligations to Property
Partners, they are liable to account to it for the benefit or gain improperly obtained
by their breaches of fiduciary duty. That benefit or gain is the 50% profit share for
-- 93 of 105 --
[2026] SADC 3
90
the O’Connell Street joint venture to which Property Partners is entitled that the
respondents kept for themselves.
540 As the successful applicant, Property Partners is entitled to the declarations sought
in its claim and to make an election between the inconsistent remedies of equitable
compensation and an account of profits before the entry of judgment and final
orders. I will defer the making of final orders and entry of judgment for seven
days to give Property Partners an opportunity to make a formal election.
541 The amount of equitable compensation should Property Partners make an election
in favour of that remedy would be same measure as in contract. The respondents
do not contend otherwise.
UNPAID INVOICE CLAIMS
542 The applicants claim payment for various unpaid invoices issued to the
respondents.
Radar Street Invoices – $614 and $500
543 The applicants in the orders sought claim payment of two outstanding invoices for
$614 and $500 (both including GST) apparently for the Radar Street development
that were otherwise not pleaded or proven to be unpaid or mentioned at trial.298
I will make orders dismissing these claims.
Connie Street Invoice – $10,000
The Issue
544 Property Partners claims from Lawrdo Super payment of its unpaid invoice
no. 0009-1 dated 27 February 2020 for $10,000 including GST for reimbursement
of commission paid to ‘Your Property Academy’ for the sale of Connie Street in
October 2018.299 Property Partners claims it paid the commission on behalf of
Lawrdo Super in pursuit of their joint venture to develop this property.
545 The respondents’ defence is that the $10,000 commission paid by Property
Partners was related to securing the building contract as distinct from the land and
therefore it was a cost of the builder and not a project cost. Further, having put
Property Partners to proof of its claim, the respondents submitted in closing that
the applicants had not proved the order in which the invoices were produced or
what work they were for and the Court could not be satisfied as to the underlying
facts.300
Conclusion
546 For the following reasons, I do not accept the respondents’ contentions in regard
to this unpaid invoice. Property Partners is entitled to be reimbursed by Lawrdo
298 Claim Part 4 [1(a)(vi)] and [2(h)(i)].
299 Claim Part 4 [2(h)(ii)].
300 Respondents Written Closing [55].
-- 94 of 105 --
[2026] SADC 3
91
Super for commission properly incurred as a project cost for Connie Street and
paid on behalf of Lawrdo Super.
Analysis
547 Contrary to the respondents’ submissions, the evidence is sufficient for the Court
to make factual findings as to what occurred and to be satisfied about the facts
relevant to this claim.
548 The subdivided land referred to as Connie Street was listed for sale with Ray White
from about late 2017. There was no interest in it and the sale price was dropped
from $169,000 to $149,000.
549 After the property had been on the market for some time, Mr Tim Rogers and
Mr Andrew Le from ABC trading as ‘Your Property Academy’ approached
Mr Chehade about their business model generally and specifically about marketing
house and land packages for a sales commission. When they were told by
Mr Chehade that the properties they had in stock included Connie Street, ‘Your
Property Academy’ proposed introducing a buyer for a house and land package for
Connie Street for a commission of $20,000. The terms of this introduction were
negotiated by Mr Chehade without any formality.
550 On 23 October 2018, Mr Le sent Mr Chehade by email a ‘Your Property Academy’
invoice dated 23 October 2018 for $20,000 including GST for unspecified
“marketing services”, stating: 301
1st Payment payable at Land Settlement (no GST) $10,000
2nd Payment payable at Slab pour $9,090 + $910 GST
551 Both Mr Chehade and Mr Lawrence accepted in oral evidence this was the first of
the ‘Your Property Academy’ invoices issued for their commission for Connie
Street.
552 On 1 November 2018, Mr Lawrence asked Mr Chehade by email to have the
invoice for $20,000 commission reissued and addressed to Lawrdo Super with the
correct GST amount included.
553 Following Mr Lawrence’s request, the first ‘Your Property Academy’ invoice was
reissued to Lawrdo Super for the same date and for a total amount of $20,000
including GST of $1,820 (for all not just part as a taxable supply) for “Marketing
Services for 2b Connie St Para Vista” but not in two payments.302 Mr Chehade
asked for the invoice to be reissued a third time to permit payment in two
instalments of $10,000 that he had negotiated. This was done.303
301 Exhibit A12.
302 Exhibit A14.
303 Exhibit A34.
-- 95 of 105 --
[2026] SADC 3
92
554 Mr Chehade gave oral evidence that he discussed the offer from ‘Your Property
Academy’ and their commission with Mr Lawrence and told him it “doesn’t work
out that bad because…these guys are basically increasing the price by $20,000”
and since they were willing to take a lower price anyway, Mr Lawrence said at the
time in effect it was “fine”. 304
555 It is clear from the evidence at the time the decision to sell Connie Street to the
purchaser introduced by ‘Your Property Academy’ was made that Mr Lawrence
knew about the $20,000 commission, that it was to be paid in two instalments and
had agreed to this cost being incurred as a project cost. Furthermore, at this time
the parties’ relations were good and they were working together to share profits
from their ongoing joint ventures. Objectively viewed, Mr Lawrence’s request
that the commission be reinvoiced to Lawrdo Super having agreed to incur the
commission is persuasive evidence that there was a common understanding that
the commission paid to ‘Your Property Academy’ was to be treated as a joint
venture expense.
556 That this was the case was confirmed by Mr Lawrence’s evidence in cross-
examination that it was only later that he disputed it:305
A. At that time it was assumed that that was a total invoice expenditure against the
project, subsequently that’s not the case, it pointed – the split was identified as being
one on the sale and one on the pour and once I got that understanding, I disputed that
I should be paying for the pour.
Q. And so because of that, that’s a decision you made because of reasoning that’s going
on in your head.
A. At that time, yes.
557 Accordingly, the earlier and contradictory evidence Mr Lawrence gave that he and
Mr Chehade had discussed and agreed that Mr Chehade yielded the benefit of the
building contract and therefore it was his bill to pay is rejected. The same
conclusion follows as regards Mr Lawrence’s earlier evidence that he insisted he
had paid all of the $20,000 commission. Mr Lawrence ultimately accepted in cross-
examination that Lawrdo Super only paid $10,000 of the final ‘Your Property
Academy’ invoice for $20,000. He conceded this after a call for production of his
payment records was answered showing only $10,000 was in fact paid.306
Chicklade Street Invoices
Issues
558 It is uncontentious that after the purchase of the Upton Street property in July 2017,
it was subdivided into two allotments and the existing house renovated and sold
for $220,000 in June 2018. The vacant allotment known as Chicklade Street was
304 T136.31-.35.
305 T585.11-.19.
306 Exhibits A35 and A36.
-- 96 of 105 --
[2026] SADC 3
93
marketed initially for $119,000 and then the price dropped to about $100,000
without finding a buyer. Since they were unable to sell the vacant allotment at a
price that would result in a profit, Mr Chehade and Mr Lawrence decided to build
on it and then sell it as joint venturers.
559 On 15 September 2020, Lawrdo Investments and Chehade Constructions entered
into a written building contract for a price of $160,000 that was subject to an
express term that there would be an adjustment on completion with the effect that
the final construction price would be cost plus 15%.
17 December 2020 Invoice for $440
560 There is no dispute that the first surveyor’s peg went missing and it was necessary
to ‘re-peg’ before construction started so there could be no mistakes about the
location of the boundary of the allotment. Nonetheless, when this invoice was
issued, despite knowing the repegging had to be done, Mr Lawrence disputed by
email that it should be his cost as “vendor” and said it should be covered by the
builder’s insurance.307 Mr Chehade quickly replied with:308
It’s a variation as it really is part of the development costs.
561 At trial, the respondents resisted payment of this invoice on the basis that it was
not a project cost, the invoice was issued by Chehade Constructions not Property
Partners, Lawrdo Investments had already paid for the original surveyor’s pegging
and “repegging was the responsibility of the Applicants as they were in control of
the site”.309 Further, the applicants’ contention that the insurance excess would
have been more that the cost of repegging is “a red herring”.310
562 Save that the issue of insurance is a red herring, the respondents’ grounds of
defence are unprincipled.
563 The Upton Street property was surveyed and ‘pegged’ when it was subdivided in
mid-2018. Unquestionably that cost was a project cost and liability of the joint
venture. The vacant land remained undeveloped for about three years, the block
was slashed annually and unexceptionally the peg went missing. It was repegged
in November 2020 before construction started at the expense of Chehade
Constructions. It is apparent Chehade Constructions was not in control of the site
when the peg went missing and the cost of repegging should have been accounted
for between the parties as a project cost and liability of the joint venture in any
event.
564 Given the necessity for repegging, it was proper and reasonable for Chehade
Constructions to have incurred this cost and invoiced Lawrdo Investments for its
reimbursement and it was entitled to do so and add 15% but did not to
307 Exhibit A4B.13.72.
308 Ibid.
309 Respondents Written Closing [46].
310 Ibid.
-- 97 of 105 --
[2026] SADC 3
94
Mr Lawrence’s advantage. Given the informality with which Mr Chehade and
Mr Lawrence dealt with one another, the complaint that Property Partners should
have invoiced it as a project cost lacks substantive merit.
565 Chehade Constructions is entitled to be paid $440 including GST for its invoice
no. 0107 dated 17 December 2020 which was due on 24 December 2020.
20 May 2021 Invoice for $32,870
566 On 20 May 2021, Chehade Constructions issued invoice no. 0126 to Lawrdo
Investments for $32,870 including GST for the balance of the price outstanding
under the written building contract made in September 2020 for construction of a
new house on the Chicklade Street subdivided land. The price was calculated on a
cost plus 15% basis. The invoice has not been paid.
567 When Mr Lawrence received Chehade Constructions’ 20 May 2021 invoice he
emailed Mr Chehade asking him to send a breakdown of cost plus proof of
payment, saying the variance was agreed to be “(12-15)$K” and “You have
effectively taken the property increase as the variance.”311 In a subsequent email
he complained: “The only one make [sic] money on my Property developments is
you”.312
568 Mr Chehade’s immediate response and consistent position since then was that he
had told Mr Lawrence that the upgrades would cost approximately $35,000, the
retaining walls and air conditioning alone costing approximately $12,000-
$15,000.313
569 Ultimately, there was no challenge to the actual costs incurred for the upgrades or
that the price under the building contract was cost plus 15%. It is also plain on the
face of the contract that the final price under the building contract is subject to
variation if the costs of construction changed.314 Mr Lawrence in cross-
examination accepted as much was “correct.”315
570 Lawrdo Investments nevertheless disputes Chehade Constructions’ contractual
entitlement for the invoiced balance of the construction costs on the ground that
Mr Chehade told Mr Lawrence over the telephone in December 2020 that the costs
of upgrades would be $10,000-$12,000 not $30,000-$35,000316 and a construction
variation at that price was not agreed. Chehade Constructions contends
Mr Chehade’s evidence should be preferred to Mr Lawrence’s evidence, and in
any event, it does not matter because the invoice reflects the contractual
entitlement.
311 Exhibit A4B.17.125.
312 Exhibit A4B.17.124.
313 Ibid.
314 Exhibit A4.4.43.
315 T558.8-.22.
316 Defence [18.3].
-- 98 of 105 --
[2026] SADC 3
95
571 I accept that this invoice reflects Chehade Constructions’ contractual entitlement
to be paid for agreed works on a cost plus 15% basis. Undisputedly, Chehade
Constructions was only entitled to payment for the costs of agreed works, however
what was ultimately in dispute was the quantum of the estimate Mr Chehade gave
to Mr Lawrence.
572 That said, I prefer Mr Chehade’s evidence about what was discussed and agreed.
Mr Chehade’s account of their conversation was plausible and his recollection of
the detail clear whereas Mr Lawrence’s evidence was inconsistent with his pleaded
case and his rationale for objecting to the invoice in the first place questionable.
573 The amount of the ‘agreed variance’ the subject of dispute was discussed in the
context of an offer made on 24 December 2020 to purchase Chicklade Street with
extra inclusions. Mr Chehade estimated the cost of the extras required by the
purchaser would be $30,000-$35,000 and negotiated an increased contract price
with the purchaser to cover those costs. When he telephoned Mr Lawrence and
told him this to seek his approval to proceed, Mr Lawrence said he did not have
the funds to pay for the extras. Mr Chehade told him he would take care of it.
574 The evidence and logic of events confirm Mr Chehade’s account. The increased
price in the sale contract reflects an increase by more than the estimated costs of
the extras in the previously advertised price. It made good commercial sense to
agree the inclusions for an increased price, despite the risk from the subject to
finance clause. The joint venture parties were better off by agreeing to sell
Chicklade Street on this basis.
575 Mr Lawrence’s complaint that Mr Chehade had ‘gouged’ him on completion and
taken ‘all’ of the increase as a construction variance lacks merit.317 The variance
represented properly incurred cost plus 15% and was not purely profit to Chehade
Constructions earned at Mr Lawrence’s sole expense. His entity’s profit share was
50% and Property Partners’ profit share was also reduced by extra building costs.
576 Accordingly, Chehade Constructions is entitled to be paid cost plus 15% for the
extra works that were agreed to be done, bearing in mind that at the time,
Mr Chehade gave Mr Lawrence a rough estimate to secure the sale of the property
and negotiated an increased sale price to cover the extra costs.
28 May 2021 Invoice for $617
577 At trial, the respondents conceded Chehade Constructions’ claim for payment of
its invoice no. 0118 dated 28 May 2021 for $617 including GST issued to Lawrdo
Investments for LJ Hooker’s fees for the Chicklade Street property.318 It was due
for payment on 4 June 2021.
317 Exhibit A4B.17.124.
318 Respondents Written Closing [38.2].
-- 99 of 105 --
[2026] SADC 3
96
O’Connell Street Invoices
27 February 2020 Invoice for $600
578 At trial, the respondents did not contest Property Partners’ claim for payment of
its invoice no. 0009-2 dated 27 February 2020 for $600 (no GST) issued to Lawrdo
Super for the reimbursement of wages.319 It was due for payment on 5 March 2020.
24 March 2021 Invoice for $16,233.30
579 By March 2021, save for the issue of titles for the subdivided allotments, most of
the work required to obtain the necessary approvals to progress the O’Connell
Street development had been done by Mr Chehade through his entities. Chehade
Constructions incurred and paid certain costs on Mr Chehade’s instructions for the
O’Connell Street joint venture.
580 On 24 March 2021, Chehade Constructions issued invoice no. 0122 to Lawrdo
Investments for $16,233.30 including GST for various disbursements incurred in
progressing the development on behalf of the joint venture parties.320 It was due
for payment on 31 March 2021.
581 The $350 plus GST for gardening and rubbish was formally admitted by the
respondents to be claimable as a proper project cost in their defence, subject to set
off.321
582 The $6,500 plus GST claimed is for the costs incurred for ET Design’s work in
preparing architectural drawings to secure planning and development approval. In
October 2021, Mr Lawrence told Mr Chehade he objected to these costs because
they were part of “the Builders feasibility on residential construction Builds which
the builder independently initiated in advance of any agreed construction
contract”.322
583 ET Design’s fees were properly incurred as a project cost. Planning and
development approval was granted and necessary for the construction of houses in
circumstances where Mr Chehade and Mr Lawrence had agreed in about May 2020
to market the allotments as house and land packages and they were marketed by
Ray White as such from July 2020. Contrary to Mr Lawrence’s claim, there was
value in these costs being incurred because the promotion of house and land
packages facilitated the sale of the land.
584 The remaining costs totalling $8,133.30 plus GST (where applicable) for Bartlett
Drafting’s fees and disbursements were also properly incurred project costs.
Bartlett Drafting prepared the final community plan of division, did the preparation
319 Respondents Written Closing [53].
320 Exhibit A16.
321 Defence [29.2].
322 Exhibit A5.34.176.
-- 100 of 105 --
[2026] SADC 3
97
for final clearances to DAC, Council and SA Water and paid various
disbursements including LTO lodgement fees and for the outer boundary survey.
585 Mr Lawrence acknowledged this was the case in his October 2021 email to
Mr Chehade. However, he said he would pay them “subject to the Open Space
application name being corrected [and] transferred from the builder to LawrDo
Super”.323
586 Dispute about the applicants’ purported obligation to transfer the approvals granted
to Property Partners is beside the point. The respondents as the joint venture
funders were obliged to reimburse Chehade Constructions for payment of these
costs that should be treated as project costs in determining joint venture profit as a
term of the parties’ joint venture agreement. These costs are also a loss incurred
by Property Partners for its liability to Chehade Constructions for costs paid at its
direction by reason of the respondents’ breach of contract.324
587 In the proven circumstances, Mr Lawrence’s refusal to pay these costs unless
Mr Chehade transferred the Open Space application to his entities does not ground
any valid defence.
588 Accordingly, Chehade Constructions is entitled to be paid $16,233.30 for its
unpaid invoice no. 0122 dated 24 March 2021 which was due on 31 March 2021.
11 August 2021 Invoice for $7,810
589 In its pleaded claim, Chehade Constructions seeks payment of its invoice no. 140
issued to Lawrdo Investments for $7,810.00 including GST. An invoice bearing
that description was in evidence for the O’Connell Street development for
reimbursement of soil bore logs and the quoted costs of a footing construction
report prepared by KP Squared Engineering. The report of KP Squared
Engineering and the soil bore logs were referred to in the applicants’ pleadings and
in oral evidence as works undertaken by Chehade Constructions at Property
Partners’ direction in developing O’Connell Street,325 but otherwise there was no
plea about non-payment of this invoice other than in the orders sought.
590 This invoice and its GST exclusive total appeared in Appendix 6 to
Mr McPharlin’s report as a development cost for O’Connell Street.326
591 I am satisfied that the structural engineering and footing design work was done,
was necessary to sell house and land packages and the cost of this work was a
genuine project cost. Mr Lawrence objected to paying this invoice by email dated
323 Ibid.
324 Applicants Written Closing [175.3].
325 Claim [27].
326 Exhibit A20, appendix 6.
-- 101 of 105 --
[2026] SADC 3
98
12 August 2021 because it was “not sanctioned, authorised or agreed”327 the day
after it was emailed to him.
592 Accordingly, Chehade Constructions is entitled to be paid $7,810 including GST
for its unpaid invoice no. 140 dated 11 August 2021 which was due on 18 August
2021.
SET OFF FOR GST ON EARLY JVS
593 Despite the respondents’ pleaded defence claiming a set off for GST payable for
three historical joint ventures,328 the only claim pressed in closing submissions was
for the Baldock Road joint venture.329 Ultimately, the applicants proved that
agreement was reached and payment made for the Dulkara Road and Hawke Street
joint ventures that resolved these issues in 2020.
594 As for the Baldock Road joint venture, in their pleaded defence, the respondents
claim a set off of $6,130.70 for GST payable by the respondents that had not been
factored into the profit calculation after completion in 2013 when the respondents
accounted for and paid Property Partners $2,149.42 as their entitlement to 50% of
the profit made from the development.330
595 There is no dispute that any GST paid by the respondents was not factored into the
profit calculation for Baldock Road.
596 There are, however, a number of difficulties with the claim as pleaded and
advanced at trial. The first is that Lawrdo Super was not a party to these early joint
venture agreements. Any set off available is therefore limited to any proven
liability of Lawrdo Investments. Secondly, there is no reliable evidence that
Lawrdo Investments ever paid any GST on the sale of the Baldock Road properties,
let alone any evidence of the quantum of any GST liability net of any GST credits
on purchases in subdividing and selling the Baldock Road properties.
597 The claim for GST was first agitated in 2015 in an email from Mr Lawrence on
advice about the GST payable on the Baldock Road joint venture, and reagitated
again in 2020. The bookkeeper, Ms Rossi responded on both occasions. In an
email she sent to Mr Lawrence on 5 August 2020, she asked for a copy of the sales
contract to be forwarded to her and the BAS331 reporting the amount of GST
payable to the ATO including any GST credits. Mr Lawrence replied to
Mr Chehade the following day saying: “Bas or Tax information will not be
provided”.332
327 Exhibit A5.32.171.
328 Defence [48].
329 Applicants Written Closing [220] and [229]; Respondents Written Closing [56].
330 Defence [48].
331 Ie a Business Activity Statement.
332 Exhibit A2.30.294.
-- 102 of 105 --
[2026] SADC 3
99
598 In cross-examination, Mr Lawrence accepted that he had not ever provided any
BAS in relation to the Baldock Road joint venture: “...'cos I didn’t’ think that I
needed to”.333
599 The respondents’ counsel in opening submitted that evidence of payment would
be provided, despite the respondents having not discovered any documents on the
topic. Yet by the end of trial the respondents had failed to adduce any documentary
proof that any GST was ever paid. Mr Lawrence’s oral evidence that “yes”334 he
paid the GST that was payable is unpersuasive and I do not accept it in
circumstances where it was in his power to adduce the evidence necessary to prove
this payment but he has chosen not to do so.
600 The claim for set off is in any event is statute barred.
601 For these reasons, the respondents’ remaining defence claiming a set off for GST
payable on the Baldock Road joint venture fails.
RELIEF
602 For the preceding reasons, the following relief should be granted for the applicants’
successful claims.
Property Partners
603 The following declarations should be made in Property Partners’ favour.
(1) That Property Partners is entitled to share the profits of the Radar Street, Upton
Street/Chicklade Street and O’Connell Street joint ventures in equal proportion
with Lawrdo Investments and/or Lawrdo Super (as the case may be).
(2) That in determining joint venture profit for the Radar Street, Upton
Street/Chicklade Street and O’Connell Street joint ventures, interest is to be
allowed as a project cost and calculated on the basis of 80% of the purchase
price of each property at an interest rate of 6.5%.
(3) That in determining profit for the O’Connell Street joint venture, no amount is
to be allowed for any amount paid to or invoiced by ABC or for any costs
incurred in making a second application for subdivision or for project
management or sales consultancy services but any buyer’s agent commission
paid should be allowed as a project cost.
(4) That the respondents breached their fiduciary duties owed to Property Partners
for the O’Connell Street joint venture and Property Partners is entitled to an
equitable interest in the net sale proceeds of the 13 allotments comprising the
whole of the land comprised in CT Volume 5397 Folio 273 to the extent of
50% of the profits of this development.
333 T593.10-.29.
334 T406.22-.23.
-- 103 of 105 --
[2026] SADC 3
100
604 Property Partners is entitled to an order against Lawrdo Super for payment out of
the Lynch Meyer trust account of an amount representing its equal profit share for
the Radar Street joint venture that is to be calculated by adjusting the profit split
calculation in Exhibit A3.21 for interest. Interest as a project cost is to be calculated
on the basis of 80% of the purchase price of the Radar Street property at an interest
rate of 6.5%.
605 Property Partners is entitled to an order against Lawrdo Investments for payment
of an amount representing its equal profit share for the Upton Street/Chicklade
Street joint venture that is to be calculated by adjusting the profit split calculation
in Exhibit A4.22 for interest. Interest as a project cost is to be calculated on the
basis of 80% of the purchase price of the Upton Street/Chicklade Street property
at an interest rate of 6.5%.
606 Property Partners is entitled to an order against Lawrdo Investments and Lawrdo
Super for payment of an amount representing its 50% profit share for the
O’Connell Street joint venture that is to be calculated by adjusting the profit
calculation made by Mr McPharlin for interest and sales commission as identified
earlier in my reasons.
607 The parties should be heard as to the calculation of Property Partners’ 50% profit
share for the O’Connell Street joint venture.
608 As regards its claim for breach of fiduciary obligations, Property Partners is
entitled to the declaration and orders sought for an account of profits or equitable
damages at its election.
609 Property Partners is entitled to judgment against Lawrdo Super in the following
amounts:
(1) $10,000 including GST for its unpaid invoice no. 0009-1 dated 27 February
2020 for reimbursement of marketing commission for Connie Street.
(2) $600 (no GST) for its unpaid invoice no. 0009-2 dated 27 February 2020
for the reimbursement of wages paid for the O’Connell Street joint
venture.335
610 Property Partners’ claim for its invoice no. 0007 dated 3 May 2019 for $500
including GST for the Radar Street joint venture is dismissed.
Chehade Constructions
611 Chehade Constructions is entitled to judgment against Lawrdo Investments for the
following amounts due to it for unpaid invoices:
335 It was conceded at trial that this invoice was payable subject to the set off claim which was ultimately
unsuccessful.
-- 104 of 105 --
[2026] SADC 3
101
(1) $440 including GST for its invoice no. 0107 dated 17 December 2020;
(2) $16,233.30 including GST for its invoice no. 0122 dated 24 March 2021;
(3) $32,870 including GST for its invoice no. 0126 dated 20 May 2021;
(4) $617 including GST for its invoice no. 0118 dated 28 May 2021;
(5) $7,810 including GST for its invoice no. 0140 dated 11 August 2021.
612 Chehade Constructions’ claim for its invoice no. 0138 for $614 including GST for
the Radar Street joint venture is dismissed.
613 Chehade Constructions is entitled to contractual damages in the amount of
$502,700 including GST for the O’Connell Street joint venture.
614 The parties should be heard as to the form of orders and the judgment to be entered,
interest and costs and any incidental matters. I will defer the entry of final orders
and judgment for seven days to allow Property Partners the opportunity to make
an election between an order for equitable compensation or an account of profits.
-- 105 of 105 --