SWEETMAN and SKYTREE HOMES PTY LTD [2026] WASAT 42 (S)
[2026] WASAT 42 (S)
Page 1
JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL
ACT : BUILDING SERVICES (COMPLAINT
RESOLUTION AND ADMINISTRATION) ACT
2011 (WA)
CITATION : SWEETMAN and SKYTREE HOMES PTY LTD
[2026] WASAT 42 (S)
MEMBER : MS R PETRUCCI, MEMBER
HEARD : DETERMINED ON THE DOCUMENTS
DELIVERED : 9 JULY 2026
FILE NO/S : CC 55 of 2025
BETWEEN : JOSHUA SWEETMAN
First Applicant
CAROLINE SWEETMAN
Second Applicant
AND
SKYTREE HOMES PTY LTD
Respondent
Catchwords:
Building Services (Complaint Resolution and Administration) Act 2011 (WA) -
Regulated building service complaint - Remedial works - Claim for site
supervision costs - Claim for alternative accommodation costs - Reasonable
duration (days/hours) owners are required to vacate property - Reasonable
amount - Turns on own facts
-- 1 of 12 --
[2026] WASAT 42 (S)
Page 2
Legislation:
Building Services (Complaint Resolution and Administration) Act 2011 (WA),
s 36(1)(b), s 38(1)(a), s 38(1)(b)
State Administrative Tribunal Act 2004 (WA), s 32, s 46(1), s 60(2)
Result:
Application partly successful
Category: B
Representation:
Counsel:
First Applicant : Mr M Lang
Second Applicant : Mr M Lang
Respondent : Mr S Mintz & Mr W Vogt
Solicitors:
First Applicant : Lang Litigation and Construction Law
Second Applicant : Lang Litigation and Construction Law
Respondent : Vogt Legal
Case(s) referred to in decision(s):
Sweetman and Skytree Homes Pty Ltd [2026] WASAT 42
-- 2 of 12 --
[2026] WASAT 42 (S)
Page 3
REASONS FOR DECISION OF THE TRIBUNAL:
Background
1 On 1 May 2026, the Tribunal delivered its substantive decision in
Sweetman and Skytree Homes Pty Ltd [2026] WASAT 42
(Sweetman No 1). These supplementary reasons concern the two
matters that were deferred in that decision:1
(a) the reasonable amount to be allowed for site supervision; and
(b) the reasonable amount to be allowed for alternative
accommodation for the owners and their children during the
period in which they must vacate the property.
2 In Sweetman No 1, the Tribunal accepted that the duration of the
remedial works could not be finalised until the scope of the builder's
liability was determined. The owners' expert, Mr Lachlan Deshon,
agreed that the scope of works required refinement depending on the
contractor engaged.2 For those reasons, we did not fix site supervision
costs at that time.
3 We also accepted that some remedial items may require the
owners and their children to vacate the property temporarily. However,
we did not determine the duration of any required relocation, instead
directing the parties to provide further evidence as to the reasonable
duration (day/hours) that the property is required to be vacated.3
Procedural history and determination on the documents
4 To facilitate the provision of evidence, we made programming
orders on 1 May 2026 requiring the parties to confer and lodge
proposed orders addressing the timetable for submissions on the two
outstanding issues. The parties were unable to reach agreement.
5 Consequently, at a directions hearing on 27 May 2026, we made
orders requiring each party to file submissions and any additional
documents. We indicated that, subject to any further order, the issues
would be determined on the documents after 19 June 2026 pursuant to
s 60(2) of the State Administrative Tribunal Act 2004 (WA) (SAT Act).
1 Sweetman No 1 at [670] to [696].
2 Ibid at [676].
3 Ibid at [689].
-- 3 of 12 --
[2026] WASAT 42 (S)
Page 4
6 The builder's deadline was subsequently extended to
24 June 2026.
7 While the Tribunal may determine how to proceed with a hearing
as provided for in s 32 of the SAT Act, it is not the role of the Tribunal
to take the lead in the investigation of the facts. Rather, the role of the
Tribunal is to make a decision on the basis of the evidence presented to
it and the usual practice is that the parties have the management of their
respective case. Therefore, the owners, as the applicants, bear the
burden of proving their case, that is, persuading the Tribunal that they
are entitled to the relief (orders) they seek, being the civil standard of
proof, being on the balance of probabilities.
8 We have now determined the two matters (see above at [1]) on the
written materials and make the orders following [46].
Evidence
9 The owners rely on evidence from:
• Mr Lachlan Deshon, who prepared a report titled 'Assessment
of Supervision costs and the Owners alternative accommodation
costs and duration while remedial work is being completed at
the property'. The report included a Gantt chart estimating the
duration of the remedial works and the associated site
supervision and accommodation requirements; and
• Mr Greg Mithen, who reviewed Mr Deshon's report and
provided his own opinion.
10 The builder relies on evidence from:
• Mr Christopher Jones, who provided a report titled
'Supplementary Quantity Surveying Report' addressing site
supervision hours and accommodation duration and cost.
11 Both parties filed written submissions.4
12 We have considered all the evidence and submissions to determine
the issues as set out below.
4 The owners filed written submissions on 5 June 2026 and the builder filed written submissions on
24 June 2026.
-- 4 of 12 --
[2026] WASAT 42 (S)
Page 5
Issues
13 The issues for determination are:
(a) what amount, if any, should be allowed for site supervision?
and
(b) what amount, if any, should be allowed for alternative
accommodation?
What amount, if any, should be allowed for site supervision?
Owners' position
14 The owners submit that 160 hours of site supervision at $135 per
hour should be allowed, totalling $21,600. Their position is based on
Mr Deshon's:
• estimate that the remedial works will take 58 working days
(80 calendar days);
• opinion that a site supervisor should attend the property for
approximately 20 hours per week (or a total of 150 hours); and
• opinion that an additional 10 hours is required for pre-planning.
15 Mr Mithen agreed with the 58 working day duration but
considered that:
• planning should be 40 hours, not 10 hours; and
• site supervision should be full-time (312 hours), due to the
complexity and volume of the works and the fact that the house
is fully furnished and occupied by the owners and their children.
Builder's position
16 Mr Jones considered that 120 to 180 hours of site supervision was
reasonable.
17 Mr Jones explained that site supervision typically involves:
• initial planning and contractor coordination;
• periodic inspections at critical stages;
• review of completed works; and
-- 5 of 12 --
[2026] WASAT 42 (S)
Page 6
• final defect inspections.
18 Mr Jones did not consider full-time site supervision necessary or
consistent with industry practice.
19 Because the owners' claim of 160 hours fell within Mr Jones'
range, the builder accepts that 160 hours is reasonable for site
supervision.
Tribunal's consideration
20 We begin by noting that the parties ultimately agree that 160 hours
is reasonable for site supervision in this case. That agreement is
consistent with the evidence of both Mr Deshon and Mr Jones.
21 In Sweetman No 1, we accepted $135 per hour as a reasonable
rate for site supervision.5 Applying that rate, we find it reasonable and
appropriate to allow the owners site supervision costs of $21,600 under
s 36(1)(b) read with s 38(1)(a) of the Building Services
(Complaint Resolution and Administration) Act 2011 (WA)
(BSCRA Act).
What amount, if any, should be allowed for alternative accommodation?
Owners' position
22 The owners submit that they and their children must vacate the
property for nine weeks, at a cost of $38,889, based on an average
weekly rate of $4,321 ($4,403 + $4,240/2) derived from the following
two Airbnb properties (Property 2 and Property 3) identified by
Mr Deshon:
(a) The Grand Family Mansion: 5BR with Pool table, BBQ:
• Entire home in Winthrop (fully furnished);
• 10 guests - 5 bedrooms - 6 beds - 4 baths; and
• Check in 11/9/2026 - Checkout 13/11/2026 (a period of
nine weeks) $39,628.27 (or $4,403 per week);
(b) North Freo Retreat Walk to Beach River and Train:
• Entire home in North Fremantle (fully furnished);
5 Sweetman No 1 at [678].
-- 6 of 12 --
[2026] WASAT 42 (S)
Page 7
• 8 guests - 4 bedrooms - 4 bedrooms - 2 baths;
• Check in 11/9/2026 - Checkout 13/11/2026 (a period of
nine weeks) $38,164.27 (or $4,240 per week).
23 The owners submit that they and their children must vacate:
(a) one week prior to the remedial works commencing for
pre-planning;
(b) the entire eight-week remedial period; and
(c) until internal cleaning is completed.
24 The owners rely on Mr Deshon's opinion that the remedial works
will be noisy, disruptive, unsafe, and will obstruct access to parts of
their property. Further, the owners refer to the Gantt chart prepared by
Mr Deshon (Appendix A attached to his report) where he assesses the
items of complaint and sets out the estimated duration (days) for
the remedial works.
25 In his report, Mr Deshon identifies:
• complaint items where he states the remedial work will be
substantial, noisy, disruptive and cause an unsafe living
environment;
• complaint items where he states the remedial work in the
bedrooms will cause the rooms not to be habitable;
• complaint items where he states the remedial work will obstruct
access; and
• complaints items which he says will require a site meeting with
the site supervisor for pre-planning and which will interrupt the
owners amenity of the property.
26 Mr Mithen agrees with Mr Deshon requiring the owners and their
children to vacate the property while remedial works are completed.
Mr Mithen opined that 'it is not feasible to have a young family living
in a house whilst this volume of work is happening around them'.
Builder's position
27 The builder submits that the owners and their children only need
to vacate the property for remedial works required for the flooring and
-- 7 of 12 --
[2026] WASAT 42 (S)
Page 8
associated finishing works on the second storey, which is estimated at
two to four weeks. According to the builder, this is because the ground
level of the owners' dwelling has one bedroom with a contained ensuite
bathroom along with kitchen and cooking facilities and there are a
number of other rooms which could be used to accommodate the
owners and their children over the course of the remedial works.
28 In support of its position, relying on Mr Jones' report, the builder
contends that:
• Airbnb rates are excessive because they reflect holiday pricing;
• 'like-for-like' accommodation is unnecessary; and
• a reasonable cost is $11,000 for four weeks based on short-stay
accommodation rates (being the average of the rates referred to
under 'Option Two' in Mr Jones' report of $8,500 and $13,500
for four weeks rent of a furnished short-term accommodation
for a family sized holiday home and a relocation allowance).
29 In the alternative, if Airbnb is to be used, the builder submits that
Property 1 identified by Mr Deshon should be preferred because it is
less expensive but still suitable.
Tribunal's consideration
30 Most of the 111 complaint items require remedial work
(Sweetman No 1 at [4]).
31 There is a significant disparity between the parties as to firstly, the
duration (days/hours) the owners and their children are required to
vacate the property while remedial works are undertaken, and secondly
as to the cost of the alternative accommodation. The owners' position
is the duration is nine weeks and the cost is $38,889. In contrast, the
builder's position is the duration is four weeks and the cost is $11,000.
Whether the owners and their children must vacate the week before the
remedial works commence?
32 We are not persuaded that the owners and their children must
vacate the week before the remedial works commence. This is because
the owners' children attend school during weekdays, thereby reducing
disruption. Further, there is no evidence before the Tribunal that the
owners work from home in a manner that would be materially affected.
-- 8 of 12 --
[2026] WASAT 42 (S)
Page 9
33 We therefore do not allow any of the alternative accommodation
costs claimed for the week prior to remedial works commencing.
Whether the owners and their children must vacate for eight-weeks?
34 We are also not persuaded that the owners and their children must
vacate for the entire eight-week period opined by Mr Deshon and
Mr Mithen. While Mr Deshon listed specific items of complaint
requiring the owners and their children to vacate the property,
suggesting the remedial work will be 'substantial', 'noisy', and
'disruptive' causing 'an unsafe living environment' no explanation for
this was provided. Only one item of complaint, item 74, was listed by
Mr Deshon requiring the property to be 'non-habitable' for four days in
order to remediate the window reveals upstairs but again without
explanation.
35 While some remedial works will be inconvenient or disruptive,
inconvenience and disruption is not the same as uninhabitability.
What is a reasonable duration that the owners and their children are required
to vacate the property?
36 We also do not accept the builder's submission that only
four weeks are required.
37 We have reviewed the Gantt chart prepared by Mr Deshon and
would reduce the eight weeks claimed by the owners for alternate
accommodation by 21 days (or three weeks) for the following
adjustments:
• item withdrawn (complaint item 109.1) reduce the one day for
remedial work to zero days (see Sweetman No 1 at [770]);
• internal cleaning time claimed reduce the three days for
remedial work to zero days (see Sweetman No 1 at [653], [665]
and [667]);
• painting duration reduce from the 13 days for remedial work
to three days (see Sweetman No1 at [315] and [318]);
• door-straightening reduce the five days for remedial work to
one day (see Sweetman No 1 at [323]); and
• window-reveal works reduce the four days remedial work
to one day (see Sweetman No 1 at [447 and [450]]).
-- 9 of 12 --
[2026] WASAT 42 (S)
Page 10
38 After these adjustments, we find that five weeks is a reasonable
duration in this case that the owners and the children will be required to
vacate the property while remedial works are done.
What is the reasonable alternative accommodation weekly rate?
39 The owners' claim a weekly rate for alternative accommodation of
$4,321 based on Airbnb; the builder's range is $2,000 to $3,000, but no
source or reference was provided.
40 The owners originally claimed $500 per night (or $3,500 per week
for a period of eight weeks).6
41 Property 1, which Mr Deshon excluded, is $3,698 per week.
Property 1 is described by Mr Deshon as:
• 4BR Ardross Mid-Century Home - Walk to Garden City
(fully furnished);
• guests - 4 bedrooms - 5 bedrooms - 2.5 baths;
• Check in 11/9/2026 - Checkout 13/11/2026 (a period of
nine weeks) $33,285.42 (or $3,698 per week).
42 We accept the builder's submission that Property 1 is appropriate
in this case because it is reasonably comparable in size and location to
the owners' property. While it may be older, 'like-for-like' does not
require a near-identical property. As we stated at [687] in
Sweetman No 1, the appropriate test is reasonableness in the
circumstances, which in this case may include proximity to school,
work, and the owners' home. The difference between Property 1 and
Property 2 appears to be the number of bathrooms and that Property 3
has a pool table and BBQ.
43 We find the reasonable weekly rate for alternative accommodation
in this case is $3,698.
What amount is to be allowed for alternative accommodation?
44 On balance, in our view, it is reasonable and appropriate to allow
the owners alternative accommodation costs for five weeks and that the
weekly rental for Property 1 is to be used to calculate the alternative
accommodation cost in this case. Applying the weekly rate of $3,698
for five weeks, we conclude that it is reasonable and appropriate to
6 Ibid at [680].
-- 10 of 12 --
[2026] WASAT 42 (S)
Page 11
allow the owners an alternative accommodation cost of $18,490 under
s 36(1)(b) read with s 38(1)(a) of the BSCRA Act.
Conclusion
45 In summary, for all of the above reasons, we conclude that it is
reasonable and appropriate to allow the owners' claim for site
supervision costs in the amount of $21,600 as agreed by the parties and
to allow alternate accommodation costs for five weeks at a weekly cost
of $3,698 (based on Property 1 per Mr Deshon's report) or a total of
$18,490. Consequently, we would make orders under s 36(1)(b) read
with s 38(1)(a) of the BSCRA Act requiring the builder to pay to the
owners the sum of $21,600 for site supervision costs and $18,490 for
alternate accommodation costs. The payments will be required to be
made by 10 August 2026.
46 Finally, as stated at [651] and [769] to [770] of Sweetman No 1,
we will make final orders as follows:
(a) a monetary order (rather than a remedial works order) under
s 36(1)(b) read with s 38(1)(a) of the BSCRA Act requiring the
builder to pay to the owners $177,201.55. Having considered
the owners submission that the payment should be made within
14 days and the builder's submission that the payment should be
made within 35 days, we consider is reasonable to require
the builder to make the payment by 31 July 2026. This is on the
basis that the Tribunal published Sweetman No 1 on
1 May 2026 and therefore the builder has been on notice of the
impending payment since that date;
(b) an order under s 46(1) of the SAT Act giving leave to the
owners to withdraw complaint items 109.1, 109.9 and 109.10;
and
(c) an order under s 38(1)(b) of the BSCRA Act that we decline to
make any order for complaint items 40, 54, 55, 62, 66, 72, 75,
83 and 109.7 and that those items are dismissed.
Orders
The Tribunal orders:
1. Pursuant to s 46(1) of the State Administrative Tribunal Act
2004 (WA), the applicants have leave to withdraw the following
-- 11 of 12 --
[2026] WASAT 42 (S)
Page 12
items of complaint and they are hereby withdrawn: items 109.1,
109.9 and 109.10.
2. Pursuant to s 38(1)(b) of the Building Services
(Complaint Resolution and Administration) Act 2011 (WA), the
Tribunal declines to make a building remedy order for the
following items of complaint: 40, 54, 55, 62, 66, 72, 75, 83 and
109.7 and those items are dismissed.
3. Pursuant to s 36(1)(b) and s 38(1)(a) of the Building Services
(Complaint Resolution and Administration) Act 2011 (WA), the
respondent must, by 31 July 2026, pay the applicants costs of
$177,201.55 to remedy the following items of complaint: 1, 2,
3, 5 to 34, 35, 36, 37, 38, 39, 41, 42, 43, 44, 45, 46, 47 to 50, 51,
52, 53, 56, 57, 58, 59, 60, 61, 63, 64, 65, 67, 68, 69, 70, 71, 73,
74, 76, 77, 78, 79, 80, 81, 82, 84, 85, 86, 87, 88, 89, 90, 91, 92,
93, 94, 95, 96, 97, 98, 99, 100, 101, 102, 103, 104, 105, 106,
107, 108, 109.1, 109.2, 109.3, 109.4 to 109.5, 109.6, 109.8,
109.10a, 109.10b, 109.11, 109.12, 109.13, 109.13a, 109.14,
109.15, 109.16, 110, 111 and 112.
4. Pursuant to s 36(1)(b), s 36(1)(c) and s 38(1)(a) of the Building
Services (Complaint Resolution and Administration) Act 2011
(WA), the respondent must, by 10 August 2026, pay the
applicants $21,600 (site supervision).
5. Pursuant to s 36(1)(b), s 36(1)(c) and s 38(1)(a) of the Building
Services (Complaint Resolution and Administration) Act 2011
(WA), the respondent must, by 10 August 2026, pay the
applicants $18,490 (alternative accommodation).
I certify that the preceding paragraph(s) comprise the reasons for decision of
the State Administrative Tribunal.
MS R PETRUCCI, MEMBER
9 JULY 2026
-- 12 of 12 --