SPRY CIVIL CONSTRUCTION PTY LTD v AUSSIE-DRAIN PTY LTD [2025] SASC 99
On Appeal from MAGISTRATES COURT OF SOUTH AUSTRALIA (MAGISTRATE JACKSON) CIV-
22-010382
Appellant: SPRY CIVIL CONSTRUCTION PTY LTD Counsel: MR S CARRAGHER - Solicitor:
WRP LEGAL & ADVISORY
Respondent: AUSSIE-DRAIN PTY LTD Counsel: MR T RICE - Solicitor: LYNCH MEYER
Hearing Date/s: 03/03/2025
File No/s: CIV-24-011524
B
SUPREME COURT OF SOUTH AUSTRALIA
(Magistrates Appeal: Civil)
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply
to this judgment. The onus remains on any person using material in the judgment to ensure that the intended use of that material does not breach
any such order or provision. Further enquiries may be directed to the Registry of the Court in which it was generated.
SPRY CIVIL CONSTRUCTION PTY LTD v AUSSIE-DRAIN
PTY LTD; AUSSIE-DRAIN PTY LTD v SPRY CIVIL
CONSTRUCTION PTY LTD
[2025] SASC 99
Judgment of the Honourable Justice B Doyle
20 June 2025
CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS -
PERFORMANCE OF WORK - REMEDIES FOR BREACH OF CONTRACT
MAGISTRATES - APPEAL AND REVIEW - SOUTH AUSTRALIA - APPEAL TO
SUPREME COURT
The respondent and cross-appellant (‘Aussie-Drain’) agreed by a contract entered into with the
appellant and cross-respondent (‘Spry’) to carry out sub-surface drainage works at the Murray Bridge
Racecourse. The contract was for a lump sum but included a clause that if rock was encountered,
prices ‘need to be reviewed’.
After carrying out about 37% of the required work, Aussie-Drain encountered rock. In order to
complete the works, a rock saw was required and a different and more labour-intensive work method
was called for. In the course of discussions, Aussie-Drain’s principal asserted that it was ‘not my
job anymore’. Although one of Aussie-Drain’s workers remained on site, the other workers left and
returned to Victoria.
A magistrate found that Aussie-Drain repudiated the contract. With reference to the rule in Sumpter
v Hedges [1898] 1 QB 673, Aussie-Drain’s claim for a restitutionary award in respect of the work it
had carried out failed, save that the magistrate recognised an exception for the cost of the materials
it had supplied. The magistrate also made an award in Aussie-Drain’s favour for work carried out
(and materials supplied by it that were used in such work) after its repudiation of the contract.
On appeal, Spry contends that the magistrate erred by finding that Aussie-Drain was entitled to
recover in respect of the materials supplied by it in partially completing the works prior to repudiating
the contract. Additionally, Spry contends that in respect of the subsequent work, the magistrate erred
by including in the award a component reflecting GST.
-- 1 of 30 --
By its cross-appeal, Aussie-Drain contends that:
1. when rock was encountered, the contract was automatically terminated, and the magistrate
therefore erred by finding that Aussie-Drain repudiated the contract;
2. consequently, and in any event, it was entitled to recover on a quantum meruit basis for the
work done and materials supplied by it before rock was encountered because the benefit of
that work was freely accepted by Spry.
Held, allowing the appeal in part and dismissing the cross-appeal:
1. the contract was not automatically terminated when Aussie-Drain struck rock;
2. the magistrate did not err by finding that Aussie-Drain repudiated the contract;
3. in accordance with the rule in Sumpter v Hedges, Aussie-Drain was precluded from recovering
both for the work done and the materials supplied or installed on site prior to its repudiation
of the contract;
4. the magistrate did not err by including a component reflecting GST in the award made for
work carried out and materials supplied after Aussie-Drain’s repudiation of the contract.
A New Tax System (Goods and Services Tax) Act 1999 (Cth) s 9-5, Public Ruling GSTR 2001/4,
referred to.
Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640; Sumpter v Hedges
[1898] 1 QB 673; United Group Rail Services Ltd v Rail Corporation New South Wales (2009) 74
NSWLR 618, applied.
Nguyen v Luxury Design Homes Pty Ltd [2004] NSWCA 178; Eminent Forms Pty Ltd v Formosa
[2004] SASC 192, distinguished.
Adamson v Ede [2008] NSWSC 767; Angelopoulos v Sabatino (1995) 65 SASR 1; Attorney General
of Belize v Belize Telecom Ltd [2009] 1 WLR 1988; Aussie-Drain Pty Ltd v Spry Civil Construction
Pty Ltd [2024] SAMC 149; Australian Financial Services and Leasing Pty Ltd v Hills Industries Ltd
(2014) 253 CLR 560; Baltic Shipping Co v Dillon (1993) 176 CLR 344; Baumgartner v Baumgartner
(1987) 164 CLR 137; Bolton v Mahadeva [1972] 1 WLR 1009; Booker Industries Pty Ltd v Wilson
Parking (Qld) Pty Ltd (1982) 149 CLR 600; BP Refinery (Westernport) Pty Ltd v Shire of Hastings
(1977) 180 CLR 266; Caves Beachside Cuisine Pty Ltd v Boydah Pty Ltd [2015] NSWSC 1273;
Cleveland Bridge UK Ltd v Multiplex Construction (UK) Ltd [2010] EWCA Civ 139; Coal Cliff
Collieries Pty Ltd v Sijehama Pty Ltd (1991) 24 NSWLR 1; Commonwealth Bank of Australia v
Barker (2014) 253 CLR 169; Cordon Investments Pty Ltd v Lesdor Properties Pty Ltd [2012]
NSWCA 184; David Securities Pty Ltd v Commonwealth Bank of Australia (1992) 175 CLR 353;
Dual Homes Victoria Pty Ltd v Moores Legal Pty Ltd (2016) 306 FLR 277; Equuscorp Pty Ltd v
Haxton (2012) 246 CLR 498; Farah Constructions Pty Ltd v Say-Dee Pty Ltd (2007) 230 CLR 89;
Fibrosa Spolka Akcyjna v Fairbairn Lawson Combe Barbour Ltd [1943] AC 32; Gagner Pty Ltd v
Canturi Corporation Pty Ltd (2009) 236 FLR 401; Hawkins v Clayton (1988) 164 CLR 539; Lumbers
v W Cook Builders Pty Ltd (in liq) (2008) 232 CLR 635; Mackay v Dick (1881) 6 App Cas 251;
Millington v Waste Wise Environmental Pty Ltd (2015) 295 FLR 301; Mineralogy Pty Ltd v Sino
Iron Pty Ltd (no 6) (2015) 329 ALR 1; Moraghan v Cospak Pty Ltd [2007] VSC 483; Muschinski v
Dodds (1985) 160 CLR 583; Oliver v Lakeside Property Pty Ltd (as trustee for the Lakeside Property
Trust) [2005] NSWSC 1040; Paciocco v Australia and New Zealand Banking Group Ltd (2015) 236
FCR 199; Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR 221; Peet Ltd v Richmond (No 2)
[2009] VSC 585; Peters American Delicacy Co Ltd v Champion (1928) 41 CLR 316; Phillips v
Ellinson Bros Pty Ltd (1941) 65 CLR 221; Realestate.com.au Pty Ltd v Hardingham (2022) 277 CLR
115; Redland City Council v Kozic (2024) 98 ALJR 544; Secured Income Real Estate (Australia) Ltd
v St Martins Investments Pty Ltd (1979) 144 CLR 596; South Sydney District Rugby League Football
Club Ltd v News Ltd (2000) 177 ALR 611; Steele v Tardiani (1946) 72 CLR 386; Taylor v Laird
(1856) 25 LJ Ex 329; United Group Rail Services Ltd v Rail Corporation New South Wales (2009)
74 NSWLR 618; Walsh v KC & WL Brain Pty Ltd (No 6) [2024] NSWDC 339, discussed.
Mann v Paterson Constructions Pty Ltd (2019) 267 CLR 560, considered.
-- 2 of 30 --
-- 3 of 30 --
-- 4 of 30 --
SPRY CIVIL CONSTRUCTION PTY LTD v AUSSIE-DRAIN PTY LTD;
AUSSIE-DRAIN PTY LTD v SPRY CIVIL CONSTRUCTION PTY LTD
[2025] SASC 99
Magistrates Appeal: Civil
1 B DOYLE J: The respondent and cross-appellant Aussie-Drain Pty Ltd (‘Aussie-
Drain’) entered into a contract with the appellant and cross-respondent Spry Civil
Construction Pty Ltd (‘Spry’) to carry out sub-surface drainage works at the
Murray Bridge Racecourse. The work involved digging trenches and installing
drainage pipes. The contract was a lump sum contract but it included a clause that
stated that if rock was encountered, prices ‘need to be reviewed’.
2 A dispute arose when, having partially completed the work, Aussie-Drain
encountered rock. This caused its trenching machine to break down on 7 October
2021. A rock saw was then needed to complete the works, and a different work
method was called for. Most of Aussie-Drain’s workers and machinery departed
the site on 8 October 2021, but one of its workers remained with a sanding
machine. The balance of the work was carried out or procured using labour and
machinery arranged by Spry, with the assistance of the remaining Aussie-Drain
labourer and Aussie-Drain’s sanding machine. The pipes and other materials that
Aussie-Drain had brought to site but not yet laid or installed were also used in
carrying out the balance of the works.
3 Aussie-Drain made a claim in contract and restitution against Spry for the
work done by it. Aussie-Drain contended that Spry had repudiated the contract on
8 October 2021 by refusing to allow Aussie-Drain to conclude the works with its
labourers. By contrast, Spry contended that it was Aussie-Drain that had
repudiated the contract, when its principal Mr Boersma had said to Spry’s
Mr Rasheed words to the effect, ‘It is not my job anymore, I excluded rock’. Spry
resisted Aussie-Drain’s claim in contract or restitution for the partially performed
works.
4 Following a trial of Aussie-Drain’s claim, a magistrate1 found that when rock
had been encountered this enlivened Aussie-Drain’s right to seek a review of the
contract price,2 but that Aussie-Drain had by its conduct repudiated the contract
before an attempt had been made to ‘activate the price review clause’.3 In this
respect, the magistrate preferred the evidence of Spry’s witness Mr Rasheed about
what had occurred during his discussion with Mr Boersma on 8 October 2021.4
5 The magistrate found that the contract was an entire, and not divisible,
contract.5 Although Aussie-Drain had completed about 37% of the work required,6
1 Aussie-Drain Pty Ltd v Spry Civil Construction Pty Ltd [2024] SAMC 149 (‘Reasons’).
2 Reasons [124].
3 Reasons [156]-[157].
4 Reasons [84].
5 Reasons [162].
6 Reasons [84], [163].
-- 5 of 30 --
[2025] SASC 99 B Doyle J
2
this did not amount to substantial performance, and so it was not entitled to
payment under the contract.7
6 Because Aussie-Drain had repudiated the contract, the magistrate held it was
not entitled to succeed in a quantum meruit claim for the work done prior to
8 October 2021,8 applying the rule in Sumpter v Hedges.9 The magistrate qualified
that conclusion by finding that payment for the costs of the materials was
recoverable.10
7 The magistrate found that Aussie-Drain was also entitled to an award for
work done and machinery provided after 8 October 2021.11
8 The total award made in favour of Aussie-Drain on its claim was
$33,800.35.12 The magistrate rejected a set-off claim advanced by Spry.13
9 On appeal, Spry contends that insofar as the award included an allowance for
materials supplied prior to Aussie-Drain’s repudiation, this was in error. The
drainage pipe and other materials supplied prior to the repudiation were not loose
materials that by some subsequent act Spry could be taken to have ‘freely accepted’
so as to warrant recovery. Spry submitted that the award therefore should only
have been $21,125.30 (plus any pre-judgment interest).
10 By its cross-appeal, Aussie-Drain contends that the magistrate erred in
finding that it repudiated the contract. That is because, on Aussie-Drain’s case,
the contract had been discharged (other than for breach on its part) at or before the
time of the conduct which the magistrate found constituted a repudiation of the
contract. Aussie-Drain contends that there was therefore no preclusion on it
recovering on a quantum meruit basis for the value of the work done to that point.
11 Alternatively, Aussie-Drain contends that even if it repudiated the contract,
its claim in quantum meruit should have succeeded on the basis that the
requirements of ‘free acceptance’ were made out. Spry ‘took the benefit’ of
Aussie-Drain’s work in partially completing the contract works, and by relying
upon Aussie-Drain’s work as partially discharging its obligations to its head
contractor, for which it was paid.
12 The disposition of the appeal and cross-appeal turns upon:
7 Reasons [163].
8 Reasons [171].
9 [1898] 1 QB 673.
10 Reasons [172].
11 Reasons [173]-[180].
12 Reasons [186], [193]-[195].
13 Reasons [185]-[190].
-- 6 of 30 --
[2025] SASC 99 B Doyle J
3
(1) the proper construction of the contract and, in particular, the effect of the
statement that the contract price needed to be reviewed if rock was
encountered; and
(2) whether if, Aussie-Drain repudiated the contract, it could nevertheless
recover on a quantum meruit basis for the value of work and materials
provided because Spry in effect adopted the works and, together with the
completion of the balance of the works undertaken by or at its direction,
relied upon Aussie-Drain’s part performance as discharging its contractual
obligation to its principal.
13 If these two issues are resolved adversely to Aussie-Drain, it accepts that
Spry’s appeal should be allowed and the award reduced on the basis sought by
Spry. That is to say, if it does not succeed in its contention that it should recover
for all the work it carried out before 8 October 2021, Aussie-Drain does not seek
to support the distinction made by the magistrate between the provision of labour
and the provision of materials prior to that date.
The salient facts
14 Neither party challenges any of the magistrate’s findings as to the basal or
background facts. So far as is relevant to the issues for resolution, the facts as
found are summarised below.
15 The Murray Bridge Racing Club engaged Spry to construct an inner turf track
at the Murray Bridge Racecourse in 2021.14
16 The inner turf track was to be situated within the course proper. To ensure
the integrity of the inner turf track, it was necessary to create a system of sub-soil
drainage. That involved digging narrow trenches, five metres apart, running from
the outer edge to the inner edge of the inner turf track. The trenches were to slope
towards the centre of the racecourse. A length of agricultural pipe was then to be
placed in each of the trenches, with holes pierced into the pipe to allow for drainage
of moisture into the pipes. The pipes were to be capped on the outer (top) end and
fed into a collection pipe on the inside end. The collection pipe finished with a
collection drain, to allow for the overall removal of moisture from the inner turf
track.15
17 Aussie-Drain was engaged for the ‘Stormwater and Subsoil Drainage’
portion of the project. Spry’s Mr Rasheed contacted Aussie-Drain’s Mr Boersma
and invited him to provide a quote for the works.16
18 The request for a quote was by email and specified in outline the work to be
done, including by attaching plans and specifications. The work involved the
14 Reasons [9].
15 Reasons [9].
16 Reasons [10]-[11].
-- 7 of 30 --
[2025] SASC 99 B Doyle J
4
installation of 8,225 metres of drainage piping and the supply of that piping (but
not the collector pipes).
19 The email asked Aussie-Drain to provide ‘details within your submission of
any inclusions and/or exclusions that you have allowed within your pricing’. It
stated that ‘[y]our price must be a fixed lump sum with a SOR for variations’.17
20 Mr Boersma’s email of 26 July 2021 in response attached a quotation in these
terms:18
Sam
Thank you for the opportunity to quote for the Drainage at the Inner Turf Track.
8225 m 65 mm AG drains + Sand @ $15.50 = $127,487.50
10% GST $ 12,748.75
Total $140,236.25
The price includes Installation and supply of all materials, including flushing caps.
Disposal of spoil stockpiled on site.
If rock is encountered or digging under utilities is required prices need to be reviewed.
Regards
Bill
21 Mr Rasheed spoke with Mr Boersma by telephone on 2 August 2021 and
accepted the quotation by email dated 2 August 2021.19
22 The parties did not discuss what it would mean if rock was encountered.
Mr Boersma’s evidence was that this was something he included for all of his
quotations for jobs.20
23 The work was undertaken during the COVID-19 pandemic. There were some
delays in Aussie-Drain mobilising its Victorian crew to the site in this State. The
magistrate found there was no express term that the work start on a particular date.
Neither the start nor the finish dates were ‘essential terms’.21 Those conclusions
are not challenged on appeal.
24 The work commenced on 25 September 2021. The Aussie-Drain crew
comprised Mr Boersma, Mr De Vent and two others. They had with them the
17 Reasons [12].
18 Reasons [14].
19 Reasons [15]. The Reasons state that the telephone discussion occurred on 2 September 2021. The
parties to the appeal agree this is a slip.
20 Reasons [17].
21 Reasons [27].
-- 8 of 30 --
[2025] SASC 99 B Doyle J
5
trenching machine, a sand backfiller, a tip truck, a front end loader, a trench
backfiller and a skidsteer.22
25 Mr Boersma was the project manager and he operated the trenching machine.
He organised the equipment for the site and the accommodation for his crew.23
Mr De Vent’s principal role was to operate the sanding machine, which pressed
sand into the trenches on top of the pipes.24 Mr De Cleene was a truck driver. He
drove the front-end loader with sand in it, putting the sand behind the trenching
machine. He also loaded spoil into the tip truck. Mr Reich drove the tip truck,
which collected the spoil from the trenching machine’s conveyor belt. He took the
spoil to a designated area in the middle of the racecourse.25
26 Mr Boersma would drive the trenching machine along the trench’s string line.
The machine would dig the soil, remove the soil (spoil) from the trench, lay pipe,
and then add sand on top. Mr De Cleene would then deposit a pile of additional
sand at the newly dug trench after every four or five lines had been completed.
Subsequently, Mr De Vent would drive the sanding machine and put another load
of sand over the trench. He would also cap the ends of the pipes.26
27 Mr Boersma said he saw rocks in the soil when they arrived but did not raise
it due to the late start. He commenced in a location which appeared to have the
least amount of rock.27
28 Rainfall led to some delays, but work resumed on 6 October 2021. It was on
7 October 2021 that the trenching machine broke down. On Mr Boersma’s
evidence, which was accepted on this score, it failed due to the presence of rocks
in the subsoil. He could feel rocks in the subsoil when operating the machine and
could see little rocks flying everywhere. It broke down a few times and eventually
required a bearing to fix the machine and it needed to be returned to the Victorian
depot for repairs.28
29 The magistrate rejected Spry’s case that the trenching machine had been in
poor condition from the outset,29 and it was accepted that there were rocks at the
site sufficient to cause damage to the trenching machine, and that this required an
alternative methodology to be derived.30
30 Mr Boersma told Mr Rasheed that the rock was too hard for the trenching
machine and a rock saw was required. Mr Rasheed said he could arrange a rock
saw to be onsite the next day. Mr Boersma’s evidence was that on the evening of
22 Reasons [31].
23 Reasons [32].
24 Reasons [33].
25 Reasons [34]-[35].
26 Reasons [36]-[38].
27 Reasons [39].
28 Reasons [41], [44]-[45].
29 Reasons [103]-[105].
30 Reasons [121].
-- 9 of 30 --
[2025] SASC 99 B Doyle J
6
7 October 2021 he devised a methodology for the rock saw with his crew that
involved the rock saw digging the trench, displacing spoil to either side. Workers
with shovels would then move the spoil out of the way. Another person would lay
pipe into the trench.31
31 By this stage, on the magistrate’s findings, the trenching that had been dug
was 3,036 metres of the total of 8,225 metres.32
32 On 8 October 2021 there was a meeting between Mr Boersma, Mr Rasheed
and Spry’s supervisor Mr Kelly, during which Mr Boersma announced he would
stay to establish a new methodology with the rock saw, and then he would return
to Victoria.33
33 What was said during the meeting was contentious but the magistrate
accepted Mr Rasheed’s evidence to the effect that Mr Boersma had said that it was
‘not his job anymore’ because he had excluded rock from the contract. The
qualification to the magistrate’s acceptance of Mr Rasheed’s evidence was that she
did not accept that Mr Boersma had offered to leave Mr De Vent and the sanding
machine behind at no cost. 34
34 The magistrate found that by this time Aussie-Drain’s crew were keen to
return to Victoria, having been confined to their rented accommodation for a
number of days due to heavy rainfall and COVID-19 restrictions.35 The magistrate
found that Mr Boersma said on 8 October 2021 that he was leaving the site with
Mr De Cleene and Mr Reich. The labour hire had not been arranged before his
planned departure.36
35 The rock saw arrived on site on 8 October 2021 and by discussion a
methodology was devised. It was a lot more involved than had been the case with
the trenching machine. It required more people. The rock saw made quite a mess
and was quick, making the clean up work required more intensive. There was
some contention about for how long Mr Boersma stayed onsite. Mr De Vent, who
operated the sanding machine, continued with connecting the pipes and cleaning
out the drains. The work was substantially but not entirely finished by around
25 October 2021, when Mr De Vent left the site.37 The work done after 8 October
2021 involved the use of sand and drainage pipe that Aussie-Drain had brought to
site.38
31 Reasons [46]-[49].
32 Reasons [78], [84].
33 Reasons [51].
34 Reasons [58], [146].
35 Reasons [147]-[148].
36 Reasons [152]-[153].
37 Reasons [72].
38 Reasons [76].
-- 10 of 30 --
[2025] SASC 99 B Doyle J
7
The magistrate’s reasoning in relation to the legal issues
36 The magistrate found that the contract did not stipulate a particular mode of
performance. That is to say, it would have been permissible for Aussie-Drain to
complete the works with the use of the rock saw and associated labour.39
37 However, the magistrate found that Aussie-Drain repudiated the contract on
8 October 2021. In reaching that conclusion, the magistrate evidently considered
that the contract had not been discharged automatically when rock was
encountered. The magistrate reasoned as follows:40
Aussie-Drain’s position was that the clause regarding encountering rock provided that a
new price could be agreed, or the agreement could be discharged at that point because an
essential term (price) could not be agreed. The accepted email quote stated:
If rock is encountered or digging under utilities is required prices need to be
reviewed.
While this submission by Aussie-Drain is correct at law, factually, neither party attempted
to activate the price review clause. There was no discussion about pricing for Aussie-Drain
to continue the Works.
I find that Aussie-Drain repudiated the contract by Mr Boersma stating that it was no longer
his job, and then leaving the site with three out of four of its crew and all its machinery
save for the sanding machine.
38 As has been observed, the magistrate was not satisfied that there had been
substantial performance by this date of what she found was an entire contract. The
result was that Aussie-Drain could not recover in contract.41
39 In respect of the alternative claim in quantum meruit, the magistrate accepted
Spry’s submission that such a claim was not available because Aussie-Drain,
having repudiated the contract, was not the innocent party. Spry had no option but
to take the benefit of the completed works. It could not be said to have freely
accepted the partially completed works. The magistrate referred to Sumpter v
Hedges and to Australian authority considering that decision.42 She observed that
the decision in Mann v Paterson Constructions Pty Ltd43 (‘Mann’) concerned a
restitutionary claim by the innocent party to a terminated contract.44
39 Reasons [154].
40 Reasons [155]-[157].
41 Reasons [158]-[163].
42 Oliver v Lakeside Property Pty Ltd (as trustee for the Lakeside Property Trust) [2005] NSWSC 1040,
which in turn refers to Steele v Tardiani (1946) 72 CLR 386.
43 (2019) 267 CLR 560.
44 Reasons [168]-[170].
-- 11 of 30 --
[2025] SASC 99 B Doyle J
8
40 Accordingly, Aussie-Drain’s claim in quantum meruit for payment for this
portion of the works failed.45 However, in a further paragraph which is the subject
of Spry’s appeal, the magistrate added:46
The exception here is payment for the cost of the materials. Aussie-Drain is entitled to
recover the cost of the materials.
41 The magistrate found there was no contractual agreement on 8 October 2021
in relation to the basis upon which the works would be carried out now that rock
had been encountered. No price was agreed for Mr De Vent staying on with the
sanding machine.47 But the work that was done after 8 October 2021 was clearly
at the request of Spry, and Aussie-Drain chose to accept that work and the materials
that had been left onsite for use. Having rejected Mr Rasheed’s evidence that
Mr Boersma had offered these things on a gratuitous basis, there was a
restitutionary claim based on an implied promise to pay a reasonable cost for the
services.48
The contract and its repudiation
42 Aussie-Drain’s first ground of cross-appeal is that having found that there
were rocks on site sufficient to cause damage to the trenching machine and to
require an alternative methodology to be devised, the magistrate erred by failing
to find that the contract was ‘discharged as between the parties in accordance with
its terms’. Aussie-Drain contends that accordingly the contract could not have
been (and was not) repudiated by it.
43 In its submissions on appeal, Aussie-Drain contended that the magistrate’s
finding that Aussie-Drain had a ‘right’ to seek a review was inconsistent with the
mandatory language of ‘need’ which appeared in Mr Boersma’s quotation email
that formed, on the magistrate’s findings, part of the contract. It argues that if the
clause were not mandatory – that is to say, if one party could decline to participate
in the review – the clause would be rendered ineffectual and would not meet its
commercial purpose.
44 The next step in the argument was that the effect of the clause or terms was
to discharge the agreement as to price and require a new agreement as to price.
45 The final step in the argument was that because price is an essential term, the
absence of any provision as to how it would be determined meant that the
agreement was discharged when rock was encountered.
46 Aussie-Drain contends that if the parties had reached agreement as to price,
they would have been bound to continue performing, but since no such agreement
45 Reasons [171].
46 Reasons [172].
47 Reasons [131], [173].
48 Reasons [173]-[177].
-- 12 of 30 --
[2025] SASC 99 B Doyle J
9
was reached here, the agreement was and remained discharged by operation of its
terms. Aussie-Drain could therefore recover based on a total failure of
consideration.
47 The steps in that argument might be thought to reveal an internal tension, if
not contradiction. It is said that the commercial purpose of the review clause can
only be achieved if the review is mandatory. But the result of accepting the
argument is said to be that the contract is automatically discharged upon the
encountering of rock. If that is so, the apparent mandatory obligation to participate
in or give effect to the review is not binding. In other words, giving effect to what
is said to be the commercial purpose of the clause renders it inoperative.
48 However, another way of making the submission, which leads to the same
result in this case, is to contend that the clause should be understood as providing
that in the absence of agreement on a new price, Aussie-Drain is not required to
carry on with the works if rock is encountered (or if digging under utilities is
required). In other words, the clause should be construed as though it read:
If rock is encountered or digging under utilities is required the parties are not required to
continue performing the contract unless prices need to be are reviewed and agreed.
49 In order for Aussie-Drain to succeed, the effect of the clause must be that
immediately upon rock being encountered or digging being required under utilities
the contract is terminated. It only revives if there is a review that leads to
agreement. On that approach, the statement that ‘prices need to be reviewed’ is
non-promissory. At most, the review process is a contingency which, if it results
in agreement, causes the contractual obligations to revive or continue (as varied).
Since it is always within the power of the parties to agree to revive a terminated
contract by fresh agreement, the clause in question is, in substance and reality,
simply a termination clause.
50 Spry also appeals to the commercial purpose which it submits should be
attributed to the clause, contending that if the effect of the clause permitted the
parties simply to ‘go their separate ways’ upon the encountering of rock, the clause
would not achieve its apparent purpose of seeking to facilitate a review of the price.
51 The question begged, however, is what effect does the clause have in law if
the contract is not automatically discharged? Spry submitted in writing that a
number of outcomes were open to the parties, including that Spry might agree to
remove a rock or rocks at its own cost, with Aussie-Drain continuing to complete
the works at an unadjusted price, or the parties might agree to an adjusted price, or
they might be unable to agree but submit the issue for expert determination. Spry
submits that none of those things happened because Aussie-Drain abandoned the
job before engaging in any discussion or process that could amount to a review.
52 That submission identified a number of factual possibilities, but did not
confront the legal question that arises if the parties are unable to agree a price or a
process for review by which they will be bound.
-- 13 of 30 --
[2025] SASC 99 B Doyle J
10
53 In the course of oral submissions, Spry contended that in the absence of
reaching agreement there was an implied term to pay a reasonable price for the
additional work or cost occasioned by the presence of rock.
54 Spry submitted in the alternative that if such a term would not satisfy the
requirements for implication, the agreement was that the parties’ obligations would
be discharged once efforts to agree had been exhausted. The concept of a deferred
termination of this kind is not entirely novel.49
55 On either approach, the contract had not yet been discharged when
Mr Boersma said it was not his job anymore, or when three of the four workers left
South Australia.
56 Spry’s alternative construction is similar to the construction urged by Aussie-
Drain, save for one critical difference. On Aussie-Drain’s case, the contract is
discharged automatically upon rock being encountered, with it being contemplated
that the parties would review the price to attempt to agree a revised price that would
see the balance of the works undertaken, but with the parties not being bound to
engage in that process. On Spry’s alternative construction, the contract remains
on foot whilst the parties undertake a review, but if the review does not result in
an agreed price, the contract is discharged. On that approach, the parties must have
some obligation to participate in the review, even though the result of their
compliance with that obligation may fail to yield an agreed revised price. If not,
it would be impossible to determine when they had discharged that obligation such
that, in the absence of agreement, the contract would be at an end.
57 The rival contentions must be resolved by applying the well-familiar
principles of construing commercial agreements. In Electricity Generation
Corporation v Woodside Energy Ltd,50 the plurality summarised the relevant
principles:51
… this Court has reaffirmed the objective approach to be adopted in determining the rights
and liabilities of parties to a contract. The meaning of the terms of a commercial contract
is to be determined by what a reasonable businessperson would have understood those
terms to mean. That approach is not unfamiliar. As reaffirmed, it will require consideration
of the language used by the parties, the surrounding circumstances known to them and the
commercial purpose or objects to be secured by the contract. Appreciation of the
commercial purpose or objects is facilitated by an understanding “of the genesis of the
transaction, the background, the context [and] the market in which the parties are
operating”. As Arden LJ observed in Re Golden Key Ltd, unless a contrary intention is
indicated, a court is entitled to approach the task of giving a commercial contract a
businesslike interpretation on the assumption “that the parties ... intended to produce a
49 A different situation again is illustrated by Peters American Delicacy Co Ltd v Champion (1928) 41
CLR 316. There, a clause in a long-term supply agreement read: ‘Prices are subject to alteration on
giving [the] customer seven days’ notice in writing’. The majority considered that possible fluctuations
in the prices of raw materials, machinery, wages and other eventualities made it reasonable to conclude
the supplier had reserved to itself the right to ‘retire from a losing contract’, but only after fair notice
had been given.
50 (2014) 251 CLR 640.
51 (2014) 251 CLR 640 at [35] (French CJ, Hayne, Crennan and Kiefel JJ) (citations omitted).
-- 14 of 30 --
[2025] SASC 99 B Doyle J
11
commercial result”. A commercial contract is to be construed so as to avoid it “making
commercial nonsense or working commercial inconvenience”.
58 The application of these principles is complicated in the present case by the
proposition that, generally speaking, price is an essential term of a contract for the
provision of construction work and services, with the result that if price is not
agreed, or if there is not an agreed process by which it is to be determined, the
putative contract may be void for uncertainty.
59 Although uncertainty and incompleteness are conceptually distinct,52 in cases
where no price is agreed at the outset, it may also be appropriate to conclude that
the parties have not reached a consensus on the range of terms necessary before
they are taken to have become bound.53
60 This is not such a case. No party suggests that the contract was void ab initio,
nor that, because the parties failed comprehensively to stipulate how prices should
be reviewed if rock were to be encountered, they had not reached the stage of
entering into a binding agreement at all.
61 The parties plainly intended to be bound and acted accordingly. The question
is as to their intention (objectively assessed) in the event that rock were to be
encountered and, relatedly, whether that intention can be given effect.
62 On Spry’s preferred construction of the contract, it may be necessary to
consider the principles relating to the implication of terms because on that
approach, unless otherwise agreed, there is an obligation to pay a reasonable
increase to the contract price to reflect the additional costs associated with the rock
encountered in digging the trenches. Aussie-Dry contended that the BP Refinery
requirements54 for implication could not be met in this case.
63 There may be scope for debate about whether each of the five requirements
must be stringently and separately applied to a case such as the present where the
contractual terms are not laid out in a comprehensive legally drafted document,55
or whether the test is simply whether the proposed term is ‘necessary for the
52 United Group Rail Services Ltd v Rail Corporation New South Wales (2009) 74 NSWLR 618 at [50]
(Allsop P, Ipp and Macfarlan JJA agreeing).
53 See the discussion in Carter, Contract Law in Australia (2023, 8th ed) at [4-01].
54 BP Refinery (Westernport) Pty Ltd v Shire of Hastings (1977) 180 CLR 266 at 283 (Privy Council).
The requirements are that the term: (1) must be reasonable and equitable, (2) must be necessary to give
business efficacy to the contract, so that no term will be implied if the contract is effective without it (3)
it must be so obvious that it ‘goes without saying’, (4) it must be capable of clear expression, and (5) it
must not contradict any express term of the contract.
55 cf. Attorney General of Belize v Belize Telecom Ltd [2009] 1 WLR 1988 at [27] (Lord Hoffmann),
referred to in Commonwealth Bank of Australia v Barker (2014) 253 CLR 169 at [22] (French CJ, Bell
and Keane JJ) and Mineralogy Pty ltd v Sino Iron Pty Ltd (No 6) (2015) 329 ALR 1 at [1002]
(Edelman J).
-- 15 of 30 --
[2025] SASC 99 B Doyle J
12
reasonable or effective operation of a contract of that nature in the circumstances
of the case’.56
64 But this is not a case where the putative implication addresses a topic which
is not mentioned at all in the written terms or in the parties’ discussions. Where
the subject matter of the posited term is one which is addressed, albeit briefly or
cryptically, a distinction between implication and exegesis can become hard to
maintain. Unless the sentence in the quotation had no legal effect, the real question
is: what did it mean? That question is answered by the interposition of the
reasonable businessperson familiar with the relevant context.
65 Spry’s alternative construction involves an acceptance that the parties are
subject to some kind of binding obligation to participate in a price review. This
alternative construction would only be accepted if the obligation in question were
sufficiently certain to be binding. In order to be binding the content of the
obligation must be able to be ascertained so as to permit a determination of whether
a party has failed to comply with the obligation.
66 Whilst the clause is expressed in passive terms (‘prices need to be reviewed’),
it is useful to recall Lord Blackburn’s statement in Mackay v Dick that:57
as a general rule … where in a written contract it appears that both parties have agreed that
something shall be done, which cannot effectually be done unless both concur in doing it,
the construction of the contract is that each agrees to do all that is necessary to be done on
his party for the carrying out of that thing.
67 The statement that prices need to be reviewed if rock is encountered may
therefore be understood as carrying with it the implication that the parties will
participate in such a review. The question then becomes whether the promise to
participate has sufficient content to constitute a binding obligation.
68 In the context of commercial agreements the parties will often, if not
generally, be taken to have agreed that they will perform their obligations in good
faith. The content of a duty of good faith is typically said to include a duty to act
honestly, reasonably and with fidelity to the bargain,58 but it does not require
altruism to the point of ignoring self-interest as if the party was a fiduciary.59
69 Where the good faith requirement is said to attend an obligation to negotiate,
an absence of any sufficient contractual indication about what any ultimate
56 Hawkins v Clayton (1988) 164 CLR 539 at 573 (Deane J), cf. Realestate.com.au Pty Ltd v Hardingham
(2022) 277 CLR 115.
57 (1881) 6 App Cas 251 at 263. See also Secured Income Real Estate (Australia) Ltd v St Martins
Investments Pty Ltd (1979) 144 CLR 596 at 607 (Mason J, Barwick CJ, Gibbs, Stephen and Aickin JJ
agreeing).
58 See, eg, Paciocco v Australia and New Zealand Banking Group Ltd (2015) 236 FCR 199 at [288]
(Allsop CJ, Besanko and Middleton JJ agreeing).
59 See, eg, South Sydney District Rugby League Football Club Ltd v News Ltd (2000) 177 ALR 611 at
[432] (Finn J), United Group Rail Services Ltd v Rail Corporation New South Wales (2009) 74 NSWLR
618 at [70] (Allsop P, Ipp and Macfarlan JJA agreeing).
-- 16 of 30 --
[2025] SASC 99 B Doyle J
13
agreement might look like may, in some cases, lead to the conclusion that a good
faith obligation to negotiate with respect to an agreement lacks legal content.60 If
no base price is agreed at all, and the basis for payment for works to be performed
is entirely at large, a contract in which the price is to be fixed by agreement or
negotiation between the parties may be open to the criticism that it is a ‘bare’
agreement to agree.61
70 Here, of course, the base price for the works including the provision of the
relevant materials was fixed. An agreement to participate in a review, or to
negotiate a revised price, in the event of an identified contingency arising, is
different from a bare agreement to agree. It is an agreement to negotiate with
respect to a variation to a fixed price occasioned by two identified contingencies.
The posited agreement is ancillary to an existing binding contract. It is perhaps
more akin to a dispute resolution clause by which the parties agree to seek to
resolve the dispute before taking particular steps,62 or to a case where a firm
agreement has been made and the parties undertake to seek to reach a fuller or
more detailed agreement,63 than it is to a case in which the parties have not yet
reached a consensus on the terms essential to a binding agreement.
71 As the analysis undertaken in United Group Rail Services Ltd v Rail
Corporation New South Wales64 by Allsop P shows, the question whether an
agreement to negotiate in good faith about a matter is capable of being binding
depends upon the contractual context in which it arises. The greater the variety of
circumstances that are likely legitimately to bear on the parties’ negotiating
positions, and the fewer the surrounding terms which are available to anchor, or
provide a frame of reference for, the negotiations, the more likely the agreement is
to be uncertain and unenforceable.
72 As Allsop P explained, one aspect of good faith is fidelity to the existing
bargain. In the present case, there is an existing bargain with a clearly agreed scope
of works and base price. There are two identified contingencies. The result is that
there is a framework against which questions of good faith participation can be
assessed, even though there is no clear statement of the nature of the revision to
the price contemplated.
73 In context, however, the nature of the contemplated revision is obvious
enough. In the case of rock, the contemplation of the clause is that the parties will
negotiate in good faith in relation to any increase in price that may be required to
reflect the additional time, risk, machinery, labour or materials that may be
necessitated by the presence of rock.
60 See, eg, the discussion in Caves Beachside Cuisine Pty Ltd v Boydah Pty Ltd [2015] NSWSC 1273 at
[98]-[124] (Kunc J).
61 cf. Booker Industries Pty Ltd v Wilson Parking (Qld) Pty Ltd (1982) 149 CLR 600 at 604 (Gibbs CJ,
Murphy and Wilson JJ).
62 United Group Rail Services Ltd v Rail Corporation New South Wales (2009) 74 NSWLR 618.
63 Coal Cliff Collieries Pty Ltd v Sijehama Pty Ltd (1991) 24 NSWLR 1 at 26 (Kirby P).
64 (2009) 74 NSWLR 618 at [30]-[69].
-- 17 of 30 --
[2025] SASC 99 B Doyle J
14
74 The review would not be an occasion more generally to revisit the
profitability of the job in relation to the work already completed to that point. A
party in the position of Aussie-Drain who nominated a revision to the price which
did not reflect any assessment by it of the additional work now required by the
discovery of work, and which was instead designed to ensure that there would be
no agreement, thus enabling Aussie-Drain to escape the contract and make a claim
based on a quantum meruit, would likely breach its obligation to honestly and to
genuinely review the price.
75 As Allsop P said:65
It may well be that it will be difficult, in any given case, to conclude that a party has not
undertaken an honest and genuine attempt to settle a dispute exhibiting fidelity to the
existing bargain. In other cases, however, such a conclusion might be blindingly obvious.
Uncertainty of proof, however, does not mean that this is not a real obligation with real
content.
76 Spry contends that whatever may be the difficulty in more borderline cases,
since Mr Boersma effectively disclaimed the job and announced that the labourers
would be leaving South Australia before any proposal for a revised price had been
made by Aussie-Drain, this is an obvious case.
77 As I have observed, Spry contended that because Aussie-Drain’s conduct was
repudiatory it is not necessary to resolve whether, on a failure of good faith
negotiations, the contract would be discharged, or whether an obligation to pay a
reasonable increase to the price should be recognised. All that is necessary is to
reject Aussie-Drain’s contention that the contract was discharged immediately
upon the encountering of rock.
78 At one level that may be so, but I would only reject Aussie-Drain’s
submission if I am satisfied that one or other of Spry’s constructions is tenable and
correct. If I am to reject Aussie-Drain’s submission without finding that there is
an obligation to pay a reasonable price increase in the absence of agreement, I must
consider whether the posited good faith obligation would be sufficiently certain to
be enforceable on that hypothesis.
79 There is, in my view, much to be said for the proposition that there is here an
obligation to pay a reasonable additional amount occasioned by the presence of
rock, but even if I assume there is no such obligation, with the result that the
contract is discharged if negotiation fails to yield agreement, I am satisfied that
there is a sound basis to recognise a binding obligation to participate in good faith.
Even if the effect is that the parties’ obligations will come to an end if, having so
conducted themselves, they fail to reach agreement, this is more consistent with
the meaning that would be attributed to the clause by a reasonable businessperson
than is the construction urged by Aussie-Drain.
65 (2009) 74 NSWLR 618 at [74].
-- 18 of 30 --
[2025] SASC 99 B Doyle J
15
80 First, the clause in question speaks of a review. Spry’s construction gives
greater voice to those words than does Aussie-Drain’s, which results in an
automatic termination, and therefore does not mandate participation in a review.
Aussie-Drain’s construction is to the effect that the parties have only agreed to the
carrying out of the excavation works if rock is not encountered. That does not
seem to reflect the language and objectively manifested intent of the parties.
81 Secondly, viewed in prospect, it could not be known whether, if rock was to
be encountered, this would have a significant or a relatively insignificant effect on
the nature of the work, and thus the time, risk, equipment or materials that would
be involved. It is a surprising intention to attribute to the parties that, should any
rock be encountered, either would be free to escape the bargain, without more.
82 Thirdly, the nature of the work required was not highly complex. In the event
that rock was encountered which did not entirely preclude the work being done,
the negotiation about a satisfactory adjustment to the price would not be likely to
be complex or subject to such imponderables that it would be impossible to assess
whether the parties were in fact participating in a review of the price in good faith.
The same observation may be made in relation to the other contingency (digging
under utilities).
83 The fact that one cannot exclude circumstances where it may be difficult to
say whether the parties have participated in a price review in good faith should not,
in my view, deter the Court from giving the contract a meaning which reflects the
apparent attitude of the parties. Aussie-Drain said that prices would need to be
reviewed if rock was encountered. It did not say that it would not carry out the
works if rock was encountered. Spry accepted the quote without expressing a
reservation about precisely how far it might be called upon to go in participating
in a review of the price. The parties’ conduct is consistent with an acceptance that
meaning could be given to that qualification upon the quoted price. A lawyer may
have stopped to wonder exactly what would be required, but the parties were not
lawyers. They were practical business-people. The commercial law should foster
and support commercial practice, not fight it.66
84 For those reasons, I would reject Aussie-Drain’s contention on the cross-
appeal that the contract was automatically discharged on the encountering of rock.
I am satisfied that even in the absence of an implied obligation to pay a reasonable
increase to the price in the event of a failure to reach agreement, there was an extant
obligation upon Aussie-Drain to participate in good faith in a review of the price
necessitated by the encountering of rock when it engaged in the conduct found by
the magistrate. The challenge to the finding that Aussie-Drain repudiated (or
renounced) the contract therefore fails.
66 P Devlin, ‘The Relation Between Commercial Law and Commercial Practice’ (1951) 14 Modern Law
Review 249, referred to with approval in United Group Rail Services Ltd v Rail Corporation New South
Wales (2009) 74 NSWLR 618 at [57] (Allsop P, Ipp and Macfarlan JJA agreeing).
-- 19 of 30 --
[2025] SASC 99 B Doyle J
16
A claim in restitution by a party found to have repudiated the contract
85 There is no challenge to the finding that the contract was an entire contract
which was not substantially performed. Accordingly, on the footing that Aussie-
Drain repudiated the contract, the only basis upon which it might recover for work
done or materials supplied prior to the repudiation is on a restitutionary claim for
quantum meruit or quantum valebat.
86 Authority suggests that a contract-breaker will not succeed in a restitutionary
claim of that kind solely by virtue of pointing to the fact that the innocent party
has received a benefit as a result of partial performance. This is the so-called rule
in Sumpter v Hedges.67
87 In that case, the plaintiff builder contracted to build two houses and stables
on the defendant’s land for a lump sum price. Before the work was substantially
complete, the plaintiff said he could not go on with it, and the finding was that he
abandoned the contract. The defendant therefore found his land with unfinished
buildings on it, and he thereupon completed the work. The plaintiff had in fact
received a part payment but not, he contended, the full value of the work he had
completed. He pursued a claim in quantum meruit. The Court of Appeal
unanimously rejected the claim.
88 Chitty LJ observed that the mere fact the defendant had completed the work
was not evidence from which the inference could be drawn that he entered into a
fresh contract to pay for the work done by the plaintiff. 68 Collins LJ said, in a
passage later adopted by Dixon J in Steele v Tardiani,69 that:70
There are cases in which, though the plaintiff has abandoned the performance of a contract,
it is possible for him to raise the inference of a new contract to pay for the work done on a
quantum meruit from the defendant’s having taken the benefit of that work, but, in order
that that may be done, the circumstances must be such as to give an option to the defendant
to take or not to take the benefit of the work done. It is only where the circumstances are
such as to give that option that there is any evidence on which to ground the inference of a
new contract. Where, as in the case of work done on land, the circumstances are such as to
give the defendant no option whether he will take the benefit of the work or not, then one
must look to other facts than the mere taking the benefit of the work in order to ground the
inference of a new contract. In this case I see no other facts on which such an inference
can be founded. The mere fact that a defendant is in possession of what he cannot help
keeping, or even has done work upon it, affords no ground for such an inference. He is not
bound to keep unfinished a building which in an incomplete state would be a nuisance on
his land.
89 The position was different, however, with respect to loose materials left
onsite by the plaintiff builder. The trial judge had awarded the plaintiff the value
of those materials and no challenge was made to that conclusion on appeal. This
67 [1898] 1 QB 673.
68 [1898] 1 QB 673 at 675.
69 (1946) 72 CLR 386 at 403 (McTiernan J agreeing).
70 [1898] 1 QB 673 at 676.
-- 20 of 30 --
[2025] SASC 99 B Doyle J
17
was undoubtedly on the basis that the defendant had a choice whether to keep or
return those materials.
90 The reasoning in Sumpter v Hedges reflects that a claim in quantum meruit
at that time which did not rely on an express promise to pay a reasonable amount
for the work done or materials provided was seen as lying in quasi-contract.71 The
problem was analysed by asking whether an implied promise to pay could be
inferred. That was also the way the principle was summarised by Starke J in
Phillips v Ellinson Bros Pty Ltd:72
It is a principle of English law that parties having contracted to do an entire work for a
specific sum can recover nothing unless the work be done or it can be shown that it was the
other party’s fault that the work was incomplete or that there is something to justify the
conclusion that the parties have entered into a fresh contract.
91 Australian law no longer resorts to the fiction of implied contract and
recognises a variety of cases in which a claim in restitution succeeds in order to
avoid unjust enrichment.73 But the rule in Sumpter v Hedges apparently survives,
as does the problem of identifying when, if ever, a claim by the repudiating party
may nevertheless succeed by reference to the ‘free acceptance’ by the innocent
party of the work or materials undertaken or provided.74
92 In order to consider Aussie-Drain’s contention that it should be permitted to
recover on a non-contractual quantum meruit in respect of work done and materials
provided prior to its repudiation, it is helpful to locate the rule in Sumpter v Hedges
within the broader framework of principles relating to restitutionary claims for
work carried out under or with reference to a contract.
93 Broadly, the position is as follows.
(1) No claim in restitution may be made by a party who has provided goods or
services under a contract which remains enforceable, open and capable of
performance.75
(2) A claim in restitution may be made by a party who has provided goods or
services under a contract which is found to have been inoperative or
unenforceable for some reason,76 unless the policy of the law which renders
the contract inoperative or unenforceable also precludes a claim in
restitution.77
71 Mann v Paterson Constructions Pty Ltd (2019) 267 CLR 560 at [182] (Nettle, Gordon and Edelman JJ).
72 (1941) 65 CLR 221 at 233-234.
73 Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR 221.
74 Lumbers v W Cook Builders Pty Ltd (in liq) (2008) 232 CLR 635 at [52] (Gleeson CJ). See also Bolton
v Mahadeva [1972] 1 WLR 1009.
75 Mann v Paterson Constructions Pty Ltd (2019) 267 CLR 560 at [169] (Nettle, Gordon and Edelman JJ).
76 Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR 221.
77 Equuscorp Pty Ltd v Haxton (2012) 246 CLR 498.
-- 21 of 30 --
[2025] SASC 99 B Doyle J
18
(3) Whilst the matter is not free from controversy,78 it appears that a claim in
restitution may be made by a party who has provided goods or services under
a contract which is subsequently frustrated.79
(4) Where a contract is terminated because a party has repudiated the contract, it
is necessary to consider whether the contract was an entire contract, or a
divisible contract and, if so, whether divisible in discrete stages, or infinitely
divisible. That is because the innocent party:
(a) is confined to claims that have accrued under the contract in respect of
a completed divisible part of contract works, or in respect of any work
undertaken pursuant to an infinitely divisible contract; but
(b) may elect between a claim for damages or a restitutionary claim based
upon a quantum meruit in respect of work carried out under an entire
contract where the work was not substantially complete, or in respect
of a divisible component of the contract works that was not substantially
completed.
94 The decision in Mann concerned this last category of case.
95 A majority (comprising Gageler J and Nettle, Gordon and Edelman JJ) held
that a restitutionary claim was available in such a case and to the extent described.
The minority (Kiefel CJ, Bell and Keane JJ) placed emphasis on the proposition
that restitutionary claims should not disturb or interfere with the risk allocation
under a contract, and therefore considered that the innocent party was in such a
case confined to remedies under or for breach of the contract.
96 The majority justices held, however, that the contract price exerted an
influence over the quantification of the quantum meruit award. Gageler J
concluded that the award should never exceed the contract price,80 so as to
substantially eliminate the distortion of contractual incentives.81 Recognising that
a degree of deference to the contract as a reflection of the parties’ risk allocation
is appropriate in point of principle,82 Nettle, Gordon and Edelman JJ held that the
award should prima facie not exceed a fair value calculated in accordance with the
contract or appropriate part of the contract price. But they did not exclude the
possibility of cases where, in accordance with principle, the circumstances would
dictate that it would be unconscionable to confine the plaintiff to the contractual
measure.83
78 See, eg, Mason, Carter and Tolhurst, Restitution Law in Australia (2025, 5th ed) at [1234], Carter,
Contract Law in Australia (2023, 8th ed) at [34-10].
79 Mann v Paterson Constructions Pty Ltd (2019) 267 CLR 560 at [189] (Nettle, Gordon and Edelman JJ),
Redland City Council v Kozic (2024) 98 ALJR 544 at [184] (Gordon, Edelman and Steward JJ).
80 (2019) 267 CLR 560 at [94]-[95].
81 (2019) 267 CLR 560 at [90]-[91].
82 (2019) 267 CLR 560 at [214].
83 (2019) 267 CLR 651 at [215]-[216].
-- 22 of 30 --
[2025] SASC 99 B Doyle J
19
97 The rule in Sumpter v Hedges concerns a variant upon the fourth class of case
described above, where the party whose repudiatory conduct has led to the
contract’s termination seeks to advance a claim for restitution in relation to work
done pursuant to the contract but which did not amount to substantial performance
of an entire contract or a divisible component of the works.
98 Although Gageler J described this as the ‘more difficult category of case’84
which he put to one side, in my view, there is nothing in the reasons of the other
majority justices85 that warrants abandoning the prima facie preclusion on recovery
synonymous with Sumpter v Hedges.
99 It may be observed that if a claim were to be permitted by the party whose
repudiation resulted in the termination of the contract it would, consistently with
Mann, be limited by the contract price in the same way as is the claim of an
innocent party. Accordingly, to allow a claim in restitution by the contract-breaker
would not permit the contract-breaker to achieve a higher return for the completed
work than it would have recovered had it continued to perform. To that extent, at
least, the restitutionary award would reflect a degree of deference to the contractual
allocation of risk and return.
100 It has also been argued that the reliance by Nettle, Gordon and Edelman JJ
upon failure of the agreed return, independently of fault, as supplying a
justification for restitution, might logically entail that Sumpter v Hedges was
wrongly decided.86 In my respectful view however, it is not apparent that the
reasoning of Nettle, Gordon and Edelman JJ was necessarily independent of fault,87
and their Honours were careful to warn against reasoning based on any universal
theory, as distinct from incremental development by reference to and analogy with
decided cases.88 They emphasised that in this country restitution arises in
recognised categories of case and is not necessarily available whenever, and to the
extent that, a defendant is enriched at the plaintiff’s expense in circumstances that
render the enrichment unjust.89
101 In any case, the general rule in Sumpter v Hedges was, as earlier noted,
approved in the earlier High Court decision of Steele v Tardiani. There is no
occasion or justification for a single judge of this Court to question its continued
application as a prima facie rule of preclusion.
84 (2019) 267 CLR 560 at [81] (Gageler J).
85 The minority justices must be taken to have regarded such claims as even less deserving, and more
likely to subvert the contractual allocation of risk and responsibility, than would the claim under
consideration in Mann.
86 Mason, Carter and Tolhurst, Restitution Law in Australia (2025, 5th ed) at [1160].
87 See, eg, (2019) 267 CLR 560 at [170] (and see also Gageler J’s reasons at [79]). See also Redland City
Council v Kozik (2024) 98 ALJR 544 at [180] (Gordon, Edelman and Steward JJ).
88 (2019) 267 CLR 560 at [212]-[213].
89 (2019) 267 CLR 560 at [213], referring to David Securities Pty Ltd v Commonwealth Bank of Australia
(1992) 175 CLR 353 at 378-378 (Mason CJ, Deane, Toohey, Gaudron and McHugh JJ), Australian
Financial Services and Leasing Pty Ltd v Hills Industries Ltd (2014) 253 CLR 560 at [73]-[74] (Hayne,
Crennan, Kiefel, Bell and Keane JJ, at [139] (Gageler J).
-- 23 of 30 --
[2025] SASC 99 B Doyle J
20
102 Even if I were unconstrained by authority, and notwithstanding the
arguments made by respected scholars against retention of the rule,90 I consider
that there is much to be said for its retention, including for the reasons that have
been advanced in its defence by McFarlane and Stevens.91 The law of contract
having determined that – on the proper construction of a contract – a party is not
entitled to payment under the contract until they complete the works (or a divisible
portion of the works), it is difficult to see a reason in justice why that party should,
by reason of it having renounced its obligations under the contract, be in a position
to advance a claim on restitutionary grounds for the value of the work performed.
103 Considered in terms of ‘unjust factors’,92 in the case of a claim by a contract-
breaker in respect of their incomplete performance, it is also difficult to identify
an unjust factor, independent of the fact of the receipt of a benefit by the defendant.
104 At least in respect of an entire contract or a divisible portion of a contract,
the party who by their conduct renounces the contract cannot say that they provided
the services on a basis that has failed or failed to sustain itself. The services were
provided on the basis that they would be paid for under the contract when the work
was substantially completed by them. Nothing has relevantly changed when the
contract-breaker repudiates the contract and fails substantially to complete the
works.
105 In the case of ‘entire contracts’, as Professor Birks once put it, such a plaintiff
finds him or herself: 93
… in the same position as a payor of money in advance whose payment is construed not as
a mere prepayment but as a deposit to bind. Of both of them it then becomes true that their
restitutionary claim based on failure of consideration is defeated for the reason, obvious
once that construction has been adopted, that the consideration has not failed. The
consideration in such a case is that the value to be forfeited shall serve as a sanction against
non-performance, so that, when the sanction attaches, the consideration cannot be said to
fail. The only hope of such parties is recourse to relief from penalties and forfeitures.
106 Or, as it has been expressed by Edelman and Bant:94
In other words, the agreed basis upon which the builder performed was that he would only
be entitled to payment when entire performance was rendered. Because the builder did not
render entire performance, and because the defendant did not prevent the builder from
completing, the basis upon which the builder performed the work could not be said to have
failed.
90 See, eg, Burrows, The Law of Restitution (2002, 2nd ed) at 354-359.
91 McFarlane and Stevens, ‘In defence of Sumpter v Hedges’ (2002) 118 Law Quarterly Review 569.
92 In Farah Constructions Pty Ltd v Say-Dee Pty Ltd (2007) 230 CLR 89 at [150], the Court said that
restitutionary recovery for unjust enrichment ‘depends on the existence of a qualifying or vitiating factor
falling into some particular category’.
93 Birks, ‘In Defence of Free Acceptance’ in Burrows (ed), Essays on the Law of Restitution (1991) at 113-
114. See also Virgo, The Principles of the Law of Restitution (2015, 3rd ed) at 340-341, referring inter
alia, to Cleveland Bridge UK Ltd v Multiplex Construction (UK) Ltd [2010] EWCA Civ 139 at [135]
(Sir Anthony May).
94 Edelman and Bant, Unjust Enrichment (2016, 2nd ed) at 268.
-- 24 of 30 --
[2025] SASC 99 B Doyle J
21
107 In this way, fault is a relevant point of distinction between the present case
and the position of an innocent claimant who may advance a claim of the kind that
succeeded in Mann, or a claimant who seeks restitution in the aftermath of the
frustration of a contract. That is not to suggest that fault on the part of the
defendant is an ingredient in a claim in restitution, but rather that fault on the part
of the claimant may deny the existence of a reason for restitution because it may
mean that it cannot really be said that the basis upon which the benefit was
provided has relevantly failed.95
108 Edelman and Bant explained the position in this way:96
It is in this sense that Lord Wright stated in Fibrosa that failure of consideration requires a
failure for a reason ‘not involving fault on the part of the plaintiff’.97 Similarly, in Baltic
Shipping, Mason CJ, with whom Brennan and Toohey JJ agreed, said that ‘There can, of
course, be no such failure when the plaintiff’s unwillingness or refusal to perform the
contract on his or her part is the cause of the defendant’s non-performance’98 upon which
the failure of consideration relies. These cases do not signify, therefore, some independent
requirement of fault in the unjust factor of failure of consideration. Instead, they merely
serve as emphasis for the need for the consideration to have wholly failed. This in turn is
necessary to ensure that the claim in restitution does not undermine or contradict the
contractual regime.
109 To permit a non-contractual restitutionary claim by the party who has
repudiated an entire contract to succeed, without more, would be contrary to
authority and would, in my respectful view, result in undesirable incoherence with
the law of contract.99
110 The real question is whether there is more in this particular case, by analogy
with the basis upon which the builder in Sumpter v Hedges had been able to recover
for the materials left onsite and which the owner of the land chose to use in
completing the works.
111 The label that has often been applied to describe the cases in which recovery
is permitted by the contract-breaker is ‘free acceptance’. This concept has a wider
operation than as an exception or qualification to the rule in Sumpter v Hedges. It
is also used to describe cases in which, absent any contract, a party who has
provided goods or services to another without any request, may nevertheless be
95 It may be noted, by way of analogy, that recovery of contributions to a joint endeavour by the medium
of the imposition of a constructive trust, is only available where the substratum of a joint relationship
or endeavour is removed ‘without attributable blame’: Muschinski v Dodds (1985) 160 CLR 583 at 620
(Deane J), referred to in Baumgartner v Baumgartner (1987) 164 CLR 137 at 148 (Mason CJ, Wilson
and Deane JJ). The connection between the principles informing that case and non-proprietary common
law restitutionary claims may be seen from the references to Muschinski v Dodds in Roxborough v
Rothmans of Pall Mall Australia Ltd (2001) 208 CLR 516 at [16] (Gleeson CJ, Gaudron and Hayne JJ),
[100]-[104] (Gummow J). See also Edelman, ‘Unjust enrichment and the law of trusts’ (2011) 35
Australian Bar Review 219 at 235-236.
96 Edelman and Bant, Unjust Enrichment (2016, 2nd ed) at 277.
97 Fibrosa Spolka Akcyjna v Fairbairn Lawson Combe Barbour Ltd [1943] AC 32 at 64-65 (Lord Wright).
98 Baltic Shipping Co v Dillon (1993) 176 CLR 344 at 352.
99 See also Virgo, The Principles of the Law of Restitution (2015, 3rd ed) at 95, 340-341.
-- 25 of 30 --
[2025] SASC 99 B Doyle J
22
able to advance a restitutionary claim.100 In such cases an act of free acceptance
provides both a basis upon which it would be unjust to permit the recipient of the
goods or services to retain the benefit, and proof that the goods and services were
of benefit so as to comprise an enrichment.
112 In the case of claims for restitution by a party who has repudiated a contract,
the work or services rendered may or may not have been compliant with the
contract. In the present case, there is no suggestion that the trenching work that
was completed was not in accordance with the contractual specifications; the only
issue is that it was not completed. It could in one sense be said that the work was
‘requested’ and, given it was requested under the contract, in a general sense, it
would be hard for the recipient to say that it was not of any benefit. But on another
view: ‘An order for a whole house cannot be understood as a request for or free
acceptance of part of a house’.101 Or, as another has put it:102
Where the basis of the claim is assent or acceptance the receipt of part performance cannot
in itself amount to such assent because it was received with the expectation and subject to
the condition that more was to come. If that expectation and condition fail, the failure
cannot affect the quality of the original receipt.
113 At all events, when ‘free acceptance’ is relied upon as an exception to the
preclusion upon recovery arising under the rule in Sumpter v Hedges, factual
benefit is insufficient to demonstrate ‘free acceptance’.103 And the fact that the
work was called for by the contract and, therefore, requested to that extent, is
insufficient, without more, to ground recovery. The authorities support the
proposition that over and above the implicit request for the provision of the work
or services under the contract that has been terminated, there must be an element
of choice in the receipt of the relevant benefit or, put another way, an opportunity
to reject the claimant’s partial performance.104
114 Aussie-Drain submitted that whereas Sumpter v Hedges illustrates that
merely by taking possession of their land, a party cannot be taken to have chosen
to accept or reject work performed on their land, the position was different here.
Spry was not the owner but was engaged to perform works to construct the racing
track for Racing SA at the Murray Bridge Racecourse. Aussie-Drain submits that
Spry elected to accept the benefit of the works performed by Aussie-Drain by
seeking and accepting payment for the works from Racing SA and by taking
contractual responsibility for any defect in those works.
115 In my view, the fact that Spry is not the owner of the land is not of itself
significant, at least not in the way contended for by Aussie-Drain. Indeed a party
100 See, eg, Angelopoulos v Sabatino (1995) 65 SASR 1 at 6-13 (Doyle CJ, Duggan and Nyland JJ
agreeing).
101 Birks, Unjust Enrichment (2003) at 52.
102 Beatson, ‘The Use and Abuse of Unjust Enrichment’: Essays on the Law of Restitution (1991) at 69.
103 See, eg, Steele v Tardiani (1946) 72 CLR 386 at 402 (Dixon J), Lumbers v W Cook Builders Pty Ltd (in
liq) (2008) 232 CLR 635 at [51] (Gleeson CJ).
104 See, eg, Oliver v Lakeside Property Trust Pty Ltd [2005] NSWSC 1040 at [80] (Barrett J).
-- 26 of 30 --
[2025] SASC 99 B Doyle J
23
that does not own the land on which works have been undertaken (here, trenches
dug in which drainage pipe has been installed and covered with sand) may have
even less practical capacity to reject or somehow return the value of the work
undertaken than does the owner of land. Either way, short of pointlessly digging
up the drainage pipes that had been laid, there was no practical means available to
Spry to return, or not accept, the benefit of the works done.
116 The question whether a benefit is accepted after the exercise of a real choice
is not answered by reference to whether the benefit is to land owned by the person,
but by reference to the factual realities of the matter. The same problems arise
whether services are provided to land or in respect of chattels. ‘One cleans
another’s shoes; what can the other do but put them on?’105
117 The fact that Spry relied upon the works performed by Aussie-Dry as partly
discharging its obligation to its principal in relation to the broader contract works
seems to me to be neither here nor there. It is no different to the homeowner in
Sumpter v Hedges completing the works and enjoying the benefit of the builder’s
part performance by living in the home.
118 It is also difficult to see why Spry taking contractual responsibility for any
defect in the works, vis-à-vis its principal, involves an act of free acceptance.
119 That Spry was prepared to rely on the partly performed works (rather than
re-perform them) and to be exposed to a risk of liability in the event that they were
inadequate may reflect that Spry considered the works were competently
performed, although it may equally reflect a commercial decision that the risk of
relying on the works was outweighed by the cost of re-performing them. But even
assuming the former, it does little more than demonstrate that Spry received a
benefit from the partly performed works. If a party who renounces a partly-
performed entire contract wishes to recover on a quantum meruit, they are required
to demonstrate more than that the work was of benefit.
120 Aussie-Drain also relied upon the fact that Spry had pleaded a set-off in its
defence which was premised on a breach of the contract. By reference to the
decisions in Nguyen v Luxury Design Homes Pty Ltd106 (‘Nguyen’) and Eminent
Forms Pty Ltd v Formosa107 (‘Eminent Forms’), this was said to involve an act of
acceptance of the works.
121 Both Nguyen and Eminent Forms involved the proposition that where the
innocent party seeks damages for defective performance this may permit the party
in breach, and who would otherwise be precluded by the rule in Sumpter v Hedges
105 Taylor v Laird (1856) 25 LJ Ex 329 at 332 (Pollock CB), recently referred to in Redland City Council
v Kozic (2024) 98 ALJR 544 at [208] (Gordon, Edelman and Steward JJ).
106 [2004] NSWCA 178.
107 [2004] SASC 192.
-- 27 of 30 --
[2025] SASC 99 B Doyle J
24
from making a restitutionary claim, to responsively claim the reasonable or fair
value of the work carried out.
122 In most cases of that kind, there will be no occasion to decide whether the
making of a claim for damages based on alleged defects in the works gives rise to
a basis for an independent claim in restitution. The value of the work done (but
not paid for) can be and will usually need to be brought to bear in the proper
quantification of the claim for damages.
123 The point is captured in the following passages from Hudson’s Building &
Engineering Contracts,108 referred to with approval by McColl JA in Nguyen:109
Thus where the contract is entire, the owner may get the benefit of valuable works not
entirely completed by the builder without having to pay for them, unless the circumstances
are such as to justify a quasi-contractual remedy. So a builder who has not fully completed
the work, through no fault of the owner, cannot overcome his difficulty by ignoring the
contract and sue on a quantum meruit for the work he has done. However, the rigours of
this rule are often considerably reduced because, in a large number of cases where there is
not entire performance, the owner may decide to sue the builder for damages for breach of
contract. If he does, he will, on general principles of damages for breach of contract, have
to give credit for what he would have had to pay had the contract been properly performed.
But in a case where the owner decides not to sue he may derive considerable advantage
from the foregoing rules, which are, however, an essential and necessary sanction to
discourage the deliberate breaking or abandonment of contracts, which would be absent if
in such cases the builder was entitled to demand partial payment notwithstanding his own
breach …
…
But it remains true that an owner should weigh carefully the damages recoverable, on the
one hand, against the advantage he may derive under the [entire contract rule] from the
builder's inability (depending on the state of the accounts) to sue for the balance of the price
of the work, on the other, since if the owner decides to sue for damages he will have to give
credit under the basic Robinson v Harman … principle … for what the work would have
cost him if properly completed or performed.
124 It is not apparent to me why the mere making of a claim based on defective
performance should be taken to amount to an act of acceptance of the works for
relevant purposes.110 Perhaps it may be said that to complain about the work that
was done and to seek a remedy based upon its departure from the required
contractual standard is in some way to treat the works as being performed under
or with reference to the contract, rather than on some other basis. However, if and
to the extent that the making of such a claim can be taken to amount to an act of
free acceptance which then, quite separately from any question of quantification
of the damages, permits a claim to be made in restitution for the work done, I
consider that the present case does not fall within that class of case.
108 (1995, 11th ed) at [8.114].
109 [2004] NSWCA 178 at [54].
110 See Cordon Investments Pty Ltd v Lesdor Properties Pty Ltd [2012] NSWCA 184 at [203] (Bathurst
CJ, Macfarlan and Meagher JJA agreeing).
-- 28 of 30 --
[2025] SASC 99 B Doyle J
25
125 In the present case, Aussie-Drain made a claim against Spry in restitution. It
was only subsequently to this that Spry pleaded, by way of set-off, and not by way
of any distinct counter-claim, that it had suffered loss and damage by having been
required to carry out the balance of the works for a price which was only
approximately $12,000 less than the entire contract price. Whatever the merits of
it, the gravamen of its pleading was that as a consequence of this, it could not be
said to have been unjustly enriched.111 The claim did not seek to hold Aussie-Drain
to any particular contractual standard for the works completed.
126 In my view, the pleading is entirely defensive and does not amount to conduct
which is in the nature of free acceptance. And looking at the matter more
generally, I would not conclude that by raising this pleading, Spry has acted in a
manner that makes it unconscientious to retain the benefit of the works partly
performed.
Disposition
127 It follows that I would dismiss the cross-appeal and allow the appeal, with
the result that the award in Aussie-Drain’s favour is to be reduced by the amount
of the materials supplied by it prior to its repudiation of the contract.
128 Standing back, the result might from one perspective appear surprising.
Aussie-Drain carried out work about which no specific complaint is made and
which must, to some extent, have been of benefit to Spry, but for which it will
receive no payment. However, to a significant extent, this follows from the
unchallenged characterisation of the contract as ‘entire’, and from Aussie-Drain’s
repudiation of its obligations.
GST
129 Spry made a further contention in its written and oral submissions that the
remaining award by way of restitution in respect of the loose materials left behind
and which were properly the subject of a restitutionary claim ought not to have
included a component for GST.
130 Citing a New South Wales District Court decision,112 Spry contended that the
amount payable in respect of the materials should be GST exclusive because, as
an operator of a commercial business, Aussie-Drain would be entitled to claim a
tax input credit for any GST it paid in respect of the materials.
131 That decision relied entirely upon the judgment of the New South Wales
Court of Appeal’s in Gagner Pty Ltd v Canturi Corporation Pty Ltd,113 but does
not contain an analysis of its applicability to a restitutionary award. The discussion
of the issue by Campbell JA (with whom Macfarlan JA and Sackville AJA agreed)
111 The appropriateness of framing a defence in this way be doubted. See, eg, Redland City Council v Kozic
(2024) 98 ALJR 544 at [217] (Gordon, Edelman and Steward JJ).
112 Walsh v KC & WL Brain Pty Ltd (No 6) [2024] NSWDC 339.
113 (2009) 236 FLR 401; [2009] NSWCA 413.
-- 29 of 30 --
[2025] SASC 99 B Doyle J
26
in that case was in the context of a damages claim.114 In that context it is
understandable that a claimant who asserts that they have incurred expenses that
should be compensated for by way of damages should only recover the net cost to
them of the expenses. If they will obtain an input tax credit for any GST remitted,
the net cost to them is the GST-exclusive amount.115 In such a case the damages
award is not itself a taxable supply.116
132 I am not persuaded that the present case is on all fours. A claim in restitution
is not a claim for compensation for loss and damage. I do not think it is appropriate
to assume that a quantum meruit award would not give rise to an obligation to
remit GST in circumstances where the basis for the award, being the provision of
goods and services, will often if not usually amount to a ‘taxable supply’.117
133 The award to be made in respect of the materials left onsite and which were
used by Spry after the repudiation should include a component for GST. The
relevant figure is therefore $8,215.68. The award in respect of Mr De Vent’s
labour and the hire of the sanding machine is not disputed and should stand in the
amount of $13,656.60. The total award (before any pre-judgment interest) is
therefore $21,872.28.
134 I would allow the appeal to the extent only of reducing the award in the
manner indicated. I would dismiss the cross-appeal. I will hear the parties on the
precise form of order and as to costs.
114 (2009) 236 FLR 401; [2009] NSWCA 413 at [133]-[154].
115 See also Millington v Waste Wise Environmental Pty Ltd (2015) 295 FLR 301; [2015] VSC 167 at [36],
[66]-[67] (Croft J), Dual Homes Victoria Pty Ltd v Moores Legal Pty Ltd (2016) 306 FLR 277; [2016]
VSC 86 at [289] (Dixon J).
116 A New Tax System (Goods and Services Tax) Act 1999 (CR), s 9-5, Public Ruling GSTR 2001/4.
117 My view appears to accord with the position adopted in Adamson v Ede [2008] NSWSC 767 at [62]-
[63], [67]-[68] (Smart AJ) and Peet Ltd v Richmond (No 2) [2009] VSC 585 at [70]-[82]
(Hollingworth J). See also Moraghan v Cospak Pty Ltd [2007] VSC 483 at [55] (Lasry J).
-- 30 of 30 --