Alinta LGA Limited (Formerly The Australian Gas Light Company) v Mine Subsidence Board [2008] HCA 17
HIGH COURT OF AUSTRALIA
GUMMOW, HAYNE, HEYDON, CRENNAN AND KIEFEL JJ
ALINTA LGA LIMITED (FORMERLY
THE AUSTRALIAN GAS LIGHT COMPANY)
& ANOR APPELLANTS
AND
MINE SUBSIDENCE BOARD RESPONDENT
Alinta LGA Limited (Formerly The Australian Gas Light Company) v
Mine Subsidence Board
[2008] HCA 17
24 April 2008
S520/2007
ORDER
Appeal dismissed with costs.
On appeal from the Supreme Court of New South Wales
Representation
J T Gleeson SC with J R Williams for the appellants (instructed by Freehills)
M J Leeming SC with S J Free for the respondent (instructed by Crown Solicitor
(NSW))
Notice: This copy of the Court's Reasons for Judgment is subject to
formal revision prior to publication in the Commonwealth Law Reports.
-- 1 of 25 --
-- 2 of 25 --
CATCHWORDS
Alinta LGA Limited (Formerly The Australian Gas Light Company) v Mine
Subsidence Board
Statutes – Interpretation – Mine Subsidence Compensation Act 1961 (NSW)
("the Subsidence Act") – Appellants claimed compensation from statutory fund
for cost of works to prevent damage to pipeline from subsidence – Pursuant to
s 15(5)(b) "no claim shall be entertained or payment made" where improvement
erected without approval unless certificate is issued – Respondent Board found
pipeline erected without approval and refused to issue certificate or entertain
claim – Section 12B(b) conferred right of appeal to Land and Environment Court
against "the decision of the Board as to the amount of the payment from the
Fund" – Whether refusal of Board to entertain claim in absence of jurisdictional
facts appealable under s 12B(b) or subject only to judicial review in Supreme
Court.
Courts and judicial system – Jurisdiction – Land and Environment Court –
Appeals – Class 3 – Sections 16 and 19(fl) of the Land and Environment Court
Act 1979 (NSW) conferred jurisdiction to hear and determine appeals under
s 12B of the Subsidence Act – Whether jurisdiction to hear and determine
appellants' appeal against Board's decision – Relevance of breadth of powers
under s 39(3) to conduct de novo rehearing.
Words and phrases – "amount", "appeal", "jurisdictional facts", "no claim shall
be entertained or payment made".
Land and Environment Court Act 1979 (NSW), ss 16, 19(fl), 39.
Mine Subsidence Compensation Act 1961 (NSW), ss 12B, 15(5)(b).
-- 3 of 25 --
-- 4 of 25 --
1 GUMMOW, HAYNE, HEYDON, CRENNAN AND KIEFEL JJ. The Appin
Mine Subsidence District was proclaimed under s 15(1) of the Mine Subsidence
Compensation Act 1961 (NSW) ("the Subsidence Act") on 20 March 19681.
Located within that district are the Appin and West Cliff Collieries. Between
May 1998 and July 2003, coal was extracted by a third party from longwalls in
these collieries. AGL Gas Networks Limited owned the Wilton to Horsley Park
natural gas pipeline ("the Pipeline") at that time. It had acquired the Pipeline in
1985 from The Australian Gas Light Company. The Pipeline was built in or
around 1975 and passes through the Appin Mine Subsidence District.
2 The Australian Gas Light Company is now styled Alinta LGA Limited
(the first appellant) and AGL Gas Networks Limited is now styled Alinta AGN
Limited (the second appellant). It is convenient to refer to the appellants
collectively as Alinta. Alinta alleges that the extractions between May 1998 and
July 2003 caused subsidence to occur in the vicinity of the Pipeline and that it
undertook preventative and mitigatory works to prevent damage to the Pipeline
as a result of that subsidence. Alinta claims that the works cost $2,392,229.29.
3 Section 10(1) of the Subsidence Act establishes a Mine Subsidence
Compensation Fund ("the Fund"). The Fund is under the direction and control of
the respondent, the Mine Subsidence Board ("the Board") (s 10(4)). Sections 12
and 12A establish a scheme for the payment from the Fund of compensation for
damage to improvements caused by subsidence, of amounts to meet the expense
of preventing or mitigating such damage and of compensation for damage caused
by the Board carrying out certain works. "Improvement" is defined by s 4 to
include any building or work erected or constructed on land and, relevantly to
this appeal, any pipeline.
4 The litigation which has reached this Court stems from the treatment by
the Board of a claim made by Alinta on 28 September 2004. Alinta made a claim
for compensation from the Fund in the sum of $2,392,229.29. By letter dated
14 October 2005, the Board informed Alinta that the claim could not be
entertained by reason of s 15(5)(b) of the Subsidence Act. This states that "no
claim shall be entertained or payment made under [the Subsidence Act]" in the
circumstances there described. It will be necessary to set out the text of
s 15(5)(b) in full later in these reasons. It is sufficient now to note that the
1 In their submissions the appellants identified the source of the proclamation in
legislation which in fact had been repealed in 1961 by s 2 of the Subsidence Act.
-- 5 of 25 --
Gummow J
Hayne J
Heydon J
Crennan J
Kiefel J
2.
consequence of the Board's refusal to entertain Alinta's claim was that no
payment of compensation from the Fund was made.
5 Alinta filed an application in the Land and Environment Court of New
South Wales ("the LEC") on 10 February 2006. The application was identified
as an "[a]ppeal under s 12B of [the Subsidence Act] against the decision of [the
Board] as to non-payment from the Fund". Section 12B of the Subsidence Act
states:
"A person claiming compensation under section 12 or 12A may appeal to
[the LEC] against the decision of the Board:
(a) as to whether damage has arisen from subsidence or could
reasonably have been anticipated, or
(b) as to the amount of the payment from the Fund."
6 The Board sought to defend the application by contending that the LEC
did not have jurisdiction to hear and determine the application for two reasons.
The first was that the impugned decision was not a decision refusing a claim
under s 12 or s 12A. The second was that, in any event, the Board had not made
any decision as to the matters specified in pars (a) and (b) of s 12B. The primary
judge (Biscoe J) identified as a preliminary question2:
"whether [the LEC] has jurisdiction to hear and determine the application
filed by [Alinta] on 10 February 2006".
His Honour directed that the preliminary question be determined separately and
subsequently ordered that it be answered "yes".
7 At issue in this appeal from the Court of Appeal of the Supreme Court of
New South Wales (Tobias JA and Handley AJA, Hodgson JA dissenting)3 is
whether that answer to the preliminary question was correct. On appeal by the
Board, a majority of the Court of Appeal reached the opposite conclusion and
ordered that the preliminary question be answered "no". Alinta seeks the
reinstatement by this Court of the affirmative answer given by Biscoe J. For the
reasons which follow the appeal to this Court by Alinta should be dismissed.
2 Australian Gas Light Co v Mine Subsidence Board (2006) 147 LGERA 433 at 436.
3 Mine Subsidence Board v Australian Gas Light Company (2007) 152 LGERA 73.
-- 6 of 25 --
Gummow J
Hayne J
Heydon J
Crennan J
Kiefel J
3.
8 No question arises in this appeal as to the merits of Alinta's claim to
compensation or the correctness of the Board's decision. The preliminary
question concerns the construction of s 12B of the Subsidence Act and the
jurisdiction of the LEC to hear and dispose of appeals under that provision. The
starting point in this regard is the Land and Environment Court Act 1979 (NSW)
("the LEC Act").
The LEC Act
9 The LEC is constituted by s 5 of the LEC Act. It is a superior court but of
limited jurisdiction. Section 16 of the LEC Act provides:
"(1) [The LEC] shall have the jurisdiction vested in it by or under this
or any other Act.
(1A) [The LEC] also has jurisdiction to hear and dispose of any matter
not falling within its jurisdiction under any other provision of this
Act or under any other Act, being a matter that is ancillary to a
matter that falls within its jurisdiction under any other provision of
this Act or under any other Act.
(2) For the purposes of this Act, the jurisdiction of [the LEC] is
divided into 7 classes, as provided in this Division."
10 Of the seven classes of jurisdiction referred to in s 16(2), it is the third
class that is relevant to this appeal. Class 3 of the LEC's jurisdiction is titled
"land tenure, valuation, rating and compensation matters" (s 19). Pursuant to
s 19(fl), the matters within Class 3 of the LEC's jurisdiction include jurisdiction
to hear and dispose of "appeals under section 12B of [the Subsidence Act]".
11 The powers of the LEC when hearing and disposing of appeals in Class 3
of its jurisdiction are described by s 39. They include the following. First, in
accordance with s 39(3), the "appeal" is conducted by way of a de novo
rehearing; fresh evidence or evidence in addition to, or in substitution for, the
evidence given on the making of the decision under appeal may be received.
Secondly, for the purposes of hearing and disposing of the "appeal", the LEC has
all the functions and discretions which the person or body whose decision is
under appeal had in respect of "the matter the subject of the appeal" (s 39(2)).
Thirdly, the decision of the LEC on the "appeal" is deemed, where appropriate, to
be the final decision of the relevant person or body and shall be given effect
accordingly (s 39(5)). Proceedings in Class 3 of the LEC's jurisdiction are
-- 7 of 25 --
Gummow J
Hayne J
Heydon J
Crennan J
Kiefel J
4.
conducted with as little formality and technicality as possible (s 38(1)). The LEC
is not bound by the rules of evidence (s 38(2)) and may obtain the assistance of
other persons (s 38(3)), such as an assessor.
12 Alinta relies on the breadth of the LEC's powers under s 39 of the LEC
Act to hear and dispose of appeals under s 12B of the Subsidence Act by way of
a de novo rehearing. It submits that such a proceeding is an appeal in name only,
and that the proceeding is in truth an original proceeding for a determination of
the claimant's entitlement to payment from the Fund where the LEC is given by
s 39(2) of the LEC Act all the functions and discretions of the Board.
13 While s 39 grants the LEC powers and discretions that provide, in effect,
for a full merits review4, those powers and discretions are only conferred in
respect of an "appeal" as defined by the section5. Section 39(1) defines "appeal"
when used in s 39 to mean:
"an appeal, objection, reference or other matter which may be disposed of
by the Court in proceedings in Class 1, 2 or 3 of its jurisdiction".
(emphasis added)
Whether Alinta's application may be so characterised turns on the construction
and application of s 12B of the Subsidence Act as no other matter arising under
the Subsidence Act is included in Class 1, 2 or 3 of the jurisdiction of the LEC.
This requires an understanding at the outset of the legislative scheme in which
s 12B is located and the jurisdiction of the Board to make "decisions" of the kind
referred to in s 12B.
14 An examination of the provisions of the Subsidence Act discloses an
accommodation, on particular terms, between the interests of colliery proprietors
and the owners of damaged improvements. The nature of that accommodation
appears only from analysis of complex provisions of the statute. It is necessary
to undertake that analysis for an appreciation of the issues on this appeal.
4 cf Administrative Appeals Tribunal Act 1975 (Cth), s 43(1); Australian Securities
and Investments Commission v Donald (2003) 136 FCR 7 at 13-14.
5 See Dwyer v Calco Timbers Pty Ltd [2008] HCA 13 at [2].
-- 8 of 25 --
Gummow J
Hayne J
Heydon J
Crennan J
Kiefel J
5.
The Board and the Fund
15 Section 5(1) constitutes the Board. It is a body corporate capable of suing
and being sued in its corporate name (s 6(1)). Its functions and duties include
directing and controlling the Fund (s 10), collecting the contributions of colliery
proprietors (s 11), investigating and determining claims for compensation (ss 12
and 12A), purchasing damaged improvements and effecting remedial works
(s 13), carrying out preventative or mitigatory works (s 13A) and determining
approvals and certifications (ss 15 and 15B).
16 The Board consists of the Director-General of the Department of Primary
Industries or a member of staff of that Department as chairperson (s 5(2)(a)), the
Chief Inspector of Coal Mines (s 5(2)(b))6 and four persons appointed by the
Governor (s 5(2)(c)). The persons appointed by the Governor must include a
representative of the colliery proprietors (s 5(2)(c)(i)) and a person nominated by
the Minister to represent improvement owners within mine subsidence districts
(s 5(2)(c)(iii)). The composition of the Board is illustrative of the balance the
Subsidence Act seeks to strike between the interests of the colliery proprietors
and the owners of improvements within a mine subsidence district.
17 The Fund consists of the contributions of colliery proprietors (s 10(2)(b))
and certain other sums (s 10(2)(a), (c) and (d)), such as interest accruing from the
investment of moneys in the Fund (s 10(2)(c)). Colliery proprietors are obliged
to make contributions to the Fund in accordance with s 11(1A), (1B) and (1C)
and the amount so calculated is deemed a debt due to the Crown and recoverable
by the Board (s 11(8)).
18 The statutory quid pro quo for the contributions of colliery proprietors to
the Fund lies in s 14(1) of the Subsidence Act. Provided the proprietor of a
colliery holding is not in arrears with contributions (s 14(1)(a)) and observes
operational covenants of the kind described by s 14(1)(b), the proprietor "shall
not be liable for any damage to improvements or household or other effects
occasioned by subsidence" (s 14(1)). This statutory immunity is stated not to
extend to relieve the liability of a proprietor for damage caused by subsidence
due to negligence (s 14(2)). Alinta submitted that s 14(1) would displace the
6 By force of amendments to s 5(2)(b) commencing after the filing of Alinta's
application in the LEC, now a person nominated by the Minister who has
appropriate expertise in coal mine operations.
-- 9 of 25 --
Gummow J
Hayne J
Heydon J
Crennan J
Kiefel J
6.
liability of a proprietor under the tort of nuisance; it is unnecessary to determine
whether that is so.
Claims for payment from the Fund
19 Compensation is paid out of the Fund (s 10(3)(a)). There are two species
of claim on the Fund, one in respect of damage (s 12) and the other for
preventative or mitigatory works (s 12A). These will now be considered in turn.
20 Section 12(1) provides for the making of claims for payment from the
Fund of compensation for damage caused by subsidence. The key provision is
par (a) of that sub-section. This states that claims may be made for payment
from the Fund of:
"compensation for any damage to improvements that arises from
subsidence, except where the subsidence is due to operations carried on by
the owner of the improvements".
Claims may also be made for payment from the Fund of an amount to meet the
expenses incurred in undertaking certain works (s 12(1)(b)) and an amount
equivalent to lost rent where premises are untenantable or "such sum in lieu of
rent as the Board deems just" where all or part of any building or work is
occupied (s 12(1)(c)). "Household or other effects" are defined by s 4 and
compensation for damage to such effects that arises from subsidence may also be
claimed, save where subsidence is due to the owner's operations (s 12(1)(d)).
21 The procedure for making claims for payment from the Fund under
s 12(1) is laid out in par (a) of s 12(2): the owner of an improvement, household
or other effect damaged by subsidence may notify the Board of the details of
such damage, the location of the improvement damaged, the description of the
effect damaged, the amount claimed from the Fund, and such other particulars as
may be prescribed; that notification is then treated as a claim for payment from
the Fund; the notification must be in a form approved by the Board and within
the time limit prescribed by the regulations7.
7 At the time of Alinta's claim, reg 6 of the Mine Subsidence Compensation
Regulation 2002 (NSW) imposed a 12 month time limit (subject to extension by
the Board in certain circumstances) by reference to the day on which the owner
knew, or the Board determined the owner should have known, that damage was
caused by subsidence. Regulation 6 of the Mine Subsidence Compensation
Regulation 2007 (NSW), now in force, is to the same effect.
-- 10 of 25 --
Gummow J
Hayne J
Heydon J
Crennan J
Kiefel J
7.
22 The obligations of the Board to investigate, report and make a decision on
the claim are specified in par (b) of s 12(2). The notification:
"shall be recorded and investigated by the Board, an officer of the Board
or some other officer in the Public Service acting for the Board and on
receipt of a report of such investigation the matter shall be placed before a
meeting of the Board for a decision as to the payment, if any, to be
allowed in respect of the damage to which such notification relates".
23 This is an important provision in the statutory scheme and must be read
with s 8. For the purpose of exercising and discharging its powers, authorities,
functions and duties under the Subsidence Act, s 8 grants the Board and the
chairperson of the Board the powers, authorities, protections and immunities
conferred on Royal Commissioners and the chairperson of a Royal Commission
respectively by Div 1 of Pt 2 of the Royal Commissions Act 1923 (NSW). These
powers include, for example, the power to summon persons to give evidence on
oath or affirmation and produce any document or other thing8. The powers
afforded to individual members of the Board by s 16 include the power to make
inspection, examination and inquiry as may be necessary to ascertain the nature
and extent of any damage to property and to ascertain whether the provisions of
the Subsidence Act have been complied with (s 16(1)). Section 16(1A) confers a
power of entry upon any land, subject to the conditions respecting entry into
dwelling houses (s 16(1B)) and the giving of notice to occupiers of land
(s 16(1C)).
24 We turn to the second species of compensation claim. The right to claim
compensation for certain preventative or mitigatory works derives from par (b) of
s 12A(1) of the Subsidence Act. This provides:
"(1) Subject to this section, claims may be made under this Act for
payment from the Fund of:
...
(b) an amount to meet the proper and necessary expense
incurred or proposed by or on behalf of the owner of
improvements or household or other effects in preventing or
mitigating damage to those improvements or household or
8 Royal Commissions Act 1923 (NSW), ss 8 and 9.
-- 11 of 25 --
Gummow J
Hayne J
Heydon J
Crennan J
Kiefel J
8.
other effects that, in the opinion of the Board, the owner
could reasonably have anticipated would otherwise have
arisen, or could reasonably anticipate would otherwise arise,
from a subsidence that has taken place, other than a
subsidence due to operations carried on by the owner."
Compensation to recover damage incurred as a result of the Board exercising its
powers to undertake preventative or mitigatory works may also be claimed under
par (a) of s 12A(1). Pursuant to s 13A, the Board may carry out "such works as,
in its opinion, would reduce the total prospective liability of the Fund by
preventing or mitigating damage" of the kind described in the section.
25 Claims made under s 12A(1) must specify the particulars required by
s 12A(2)(c) and (d) and be made within the time limit prescribed by s 12A(2)(a)
and (b). Once such a claim is made, s 12A(3) relevantly provides that:
"The provisions of section 12(2)(b) … shall, mutatis mutandis, apply to
and in respect of claims and payments under this section in the same
manner as they apply to and in respect of notifications and payments
under section 12."
It follows that, in dealing with a claim made under s 12A(1) of the Subsidence
Act, the Board has the same functions and duties earlier described and is charged
with the function of dealing with the claim in accordance with par (b) of s 12(2),
to which reference has been made above.
Necessary approvals and certification
26 The statute also imposes obligations upon the owners of improvements
and those effecting improvements. Observance of those obligations assists the
interests of the colliery proprietors. That observance is encouraged by provisions
denying the competency of claims to compensation from the Fund to which the
colliery proprietors are required to contribute.
27 It is an offence for a person to do or cause to be done any work in
connection with the erection or alteration of an improvement within a subsidence
district without the Board's approval or in disconformity with such approval as is
given (s 15(7)). It is also an offence for a person to subdivide or cause to be
subdivided any land within a subsidence district without approval of the Board
(s 15(8)). It is the former offence (s 15(7)) that is relevant to this appeal.
-- 12 of 25 --
Gummow J
Hayne J
Heydon J
Crennan J
Kiefel J
9.
28 Three possible consequences flow from a contravention of s 15(7) of the
Subsidence Act. First, there may be a prosecution under s 17, provided
proceedings to prosecute are brought within 12 months of commission of the
offence (s 15(10)). The maximum penalty is 20 penalty units. Secondly, where
any improvement has been erected or altered in contravention of the section, a
purchaser may cancel a contract for sale and recover any deposit paid together
with reasonable costs and expenses (s 15(5)(a)). The reason why a purchaser
might wish to do so becomes apparent when one has regard to the third possible
consequence of a contravention. This is provided by s 15(5)(b). Read together
with s 15(7), s 15(5)(b) relevantly provides that where an improvement has been
altered or erected without the approval of the Board, "no claim shall be
entertained or payment made under [the Subsidence Act] in respect of damage
caused by subsidence" unless a certificate is issued under s 15B(3A). Such
certificates take their place in the scheme of the Subsidence Act as follows.
29 A contravention of s 15(7) of the Subsidence Act may be avoided by a
person applying to the Board for its approval to alter or erect improvements in
the form required by s 15(2A). The Board may grant its approval conditionally
or unconditionally (s 15(3)) and certificates of compliance in respect of that
approval may be obtained under s 15B. A certificate of compliance is deemed to
be conclusive evidence that the requirements of the Subsidence Act relating to an
improvement have been complied with up to the date of the certificate (s 15B(4)).
The rationale of the certification regime was explained by the then Minister for
Minerals and Energy in the second reading speech upon the Bill for what became
the Mine Subsidence Compensation (Amendment) Act 1989 (NSW) ("the 1989
Act"). The Minister said9:
"The community is protected by certificates issued by the [B]oard … I am
aware … of recent cases where members of the community have suffered
financial loss because of the action of previous owners in failing to obtain
the [B]oard's approval for erection or alteration of improvements ..."
30 So far as material, the Subsidence Act provides for the issue of
compliance certificates in two circumstances. The first is found in s 15B(3):
where the Board is satisfied that an improvement was erected in accordance with
the Board's approval and an application for certification is made in the form
required by s 15B(2), the Board shall issue a certificate in respect of the relevant
9 New South Wales, Legislative Assembly, Parliamentary Debates (Hansard),
19 September 1989 at 10127-10128.
-- 13 of 25 --
Gummow J
Hayne J
Heydon J
Crennan J
Kiefel J
10.
improvement. Secondly, if the Board is satisfied that an improvement would
have met the requirements of s 15B(3) had the Board's approval been obtained
(s 15B(3A)(a)), and it is appropriate having regard to the circumstances of the
case to do so (s 15B(3A)(b)), the Board "may" issue a certificate under
s 15B(3A).
31 Section 15B(3A) was inserted into the Subsidence Act by the 1989 Act10.
Read together with s 15(5)(b), the effect of an exercise by the Board of its
discretion to issue a s 15B(3A) certificate is to enable the Board to entertain a
claim in respect of damage caused by subsidence notwithstanding that an
improvement was constructed or altered without its approval and in
contravention of s 15(7). The objective of the insertion of s 15B(3A) is
explained in the Explanatory Note to the Bill for the 1989 Act. The note gives as
an aim of the Bill:
"(d) to extend the compensation provisions to improvements ... that
have met all requirements except prior approval".
32 It is now appropriate, with the statutory scheme in mind, to return to the
facts and circumstances of this appeal.
The application for a s 15B(3A) certificate
33 Alinta applied for a "[c]ertificate under s 15B" in relation to the Pipeline
in a letter to the Board dated 23 April 2003. No distinction was drawn in that
letter between the two limbs of s 15B on which such a certificate might issue.
Alinta asserted as the basis for its application that the Pipeline was constructed in
compliance with the Pipelines Act 1967 (NSW) ("the Pipelines Act") and that
Alinta had been granted a licence by the Governor and had the consent of the
Minister for Mines to operate. At that time, the Minister for Mines was also
responsible for administering the Subsidence Act.
34 No point has been taken at any stage in these proceedings as to the
interaction (if any) between the Pipelines Act and the Subsidence Act or the
statutory relationship (if any) between any licence granted to Alinta under the
Pipelines Act and the requirement for approval under s 15 of the Subsidence Act.
Nor has either party referred at any stage to any relevant Commonwealth
legislation.
10 Schedule 1, Item 9.
-- 14 of 25 --
Gummow J
Hayne J
Heydon J
Crennan J
Kiefel J
11.
35 In further correspondence to the Board dated 24 March 2004, Alinta asked
the Board to treat "this letter, and our previous correspondence, as an
application" for a "section 15B(3A) certificate" for that part of the Pipeline which
traversed the Appin Mine Subsidence District. The letter asserted, as the basis
for the application:
"It is clear … that [the Board] would have given the requisite
approval to [Alinta] (assuming for these purposes only, because of the
lack of records both within [Alinta] and [the Board], that no such approval
was in fact sought or given at the time)."
36 The Board informed Alinta of its refusal to issue a certificate under
s 15B(3A) by letter of the Secretary dated 29 July 2005. The Secretary stated
with reference to s 15B(3A)(b) that the Board was not satisfied that it was
appropriate to issue a certificate in the circumstances. The reasons given for the
Board's lack of satisfaction included Alinta's "failure to obtain approval" at the
time of construction of the Pipeline, delay in applying for certification, and the
Board's belief that:
"Issue of a certificate under s 15B(3A) will mean the entertainment
and payment of a compensation claim from [Alinta] under [the Subsidence
Act] is not precluded by operation of s 15(5)(b)".
37 Alinta took issue with that interpretation by further letter to the Board
dated 28 September 2005. Alinta asserted that:
"[S]ection 15(5)(b) of the Act refers only to payments in respect of
'damage caused by subsidence'. This wording is the same as the wording
used in section 12 of the Act and clearly differs from the wording used in
section 12A of the Act. That latter section refers to 'damage … that … the
owner could have reasonably anticipated would otherwise have arisen'.
On this basis, section 15(5)(b) of the Act:
(A) precludes payments under section 12 of the Act unless a
section 15B(3A) Certificate has been issued; but
(B) does not preclude payments under section 12A of the Act if no such
certificate has been issued."
38 Alinta's letter of 28 September 2005 also pressed the Board to reconsider
its decision to refuse to grant a s 15B(3A) certificate. The Board responded to
-- 15 of 25 --
Gummow J
Hayne J
Heydon J
Crennan J
Kiefel J
12.
these matters when dealing with Alinta's claim for compensation on 14 October
2005.
The application for compensation
39 Alinta applied to the Board for compensation from the Fund on
28 September 2004, before the Board's decision to refuse its application for
certification. The amount of the claim was specified as $2,392,229.29, being the
costs of the mitigatory works that Alinta allegedly undertook to prevent damage
to the Pipeline that would otherwise have arisen because of subsidence.
Although the initial claim drew no distinction between ss 12 and 12A of the
Subsidence Act, it was later particularised by reference to both those provisions.
40 By the letter of 14 October 2005, under the hand of the Secretary, the
Board informed Alinta of its decision to refuse to entertain Alinta's claim to
compensation. The letter stated that the Board did not propose to reconsider its
refusal to issue a s 15B(3A) certificate and that:
"Given the Board's decision to refuse to issue a certificate,
[Alinta's] claims under ss 12(1) and 12A(1)(b) of [the Subsidence Act]
cannot be entertained, by reason of s 15(5)(b)."
The letter then set out the following additional observations:
"Your comments on the application of s 15(5)(b) to s 12A(1)(b) in your
letter of 28 September 2005 are noted. However, the Board respectfully
disagrees with your interpretation of s 15(5)(b).
…
Insofar as [Alinta] claims compensation from the [F]und with respect to
expenses incurred to prevent damage that might otherwise have arisen had
anticipated subsidence occurred, I draw the following matters to your
attention. The key provisions of the Act regarding compensation for
damage arising from subsidence (s 12) and the recovery of expenses
incurred in preventing or mitigating damage that would otherwise arise
from subsidence (s 12A) apply only in respect of subsidence that has
taken place. Those sections do not provide for the owner of an
improvement to recover expenses incurred in preventing or limiting the
damage that might be caused by anticipated subsidence … It is the
Board's view that the only way in which a claim may be made with
respect to expenses for works to prevent damage that might otherwise
-- 16 of 25 --
Gummow J
Hayne J
Heydon J
Crennan J
Kiefel J
13.
have arisen had anticipated subsidence taken place is through the
operation of s 13A." (original emphasis)
41 It was that additional commentary which founded the primary judge's
affirmative answer to the preliminary question. Biscoe J accepted that, by
expressing the "view" that ss 12 and 12A did not provide for the recovery of
expenses incurred in connection with "anticipated subsidence", the Board had
made a decision "as to whether damage has arisen from subsidence or could
reasonably have been anticipated" within the meaning of s 12B(a) of the
Subsidence Act. It followed that his Honour found that the LEC had jurisdiction
to hear and dispose of an appeal against that decision (s 16(1) of the LEC Act)
and matters ancillary to it (s 16(1A) of that statute). The matters his Honour
considered to be within the ancillary jurisdiction included the Board's decisions
to refuse to issue a s 15B(3A) certificate and to refuse to entertain Alinta's claim
to compensation.
The appeal to this Court
42 It is no longer contended by Alinta that the Board's "view" as to
"anticipated subsidence" as expressed in the letter of 14 October 2005 was a
decision "as to whether damage … could reasonably have been anticipated"
within s 12B(a) of the Subsidence Act. Each of the members of the Court of
Appeal concluded that the primary judge erred in so finding11. No complaint is
made by Alinta as to their Honours' conclusion in that respect. Nor does Alinta
now contend that the refusal of the Board to issue Alinta with a s 15B(3A)
certificate involved a decision as to the matters specified in s 12B(a) or (b) of the
Subsidence Act.
43 At issue in this Court is whether the Board's refusal to entertain Alinta's
claim to compensation was a decision against which an appeal lay to the LEC
under s 12B(b) of the Subsidence Act. The majority in the Court of Appeal
concluded that a decision as to "the amount of the payment from the Fund" under
s 12B(b) is a decision that determines the quantum of compensation to be paid
from the Fund and that the Board's refusal to entertain Alinta's claim by reference
to s 15(5)(b) could not be so characterised.
11 (2007) 152 LGERA 73 at 78 per Hodgson JA, 97 per Tobias JA and 99 per
Handley AJA.
-- 17 of 25 --
Gummow J
Hayne J
Heydon J
Crennan J
Kiefel J
14.
44 Alinta's fundamental contention before this Court is that any decision of
the Board which has the legal effect that there be no payment from the Fund
engages the right of appeal in s 12B(b), and that this is so however that decision
is reached. That proposition was adopted by Hodgson JA in his dissenting
reasons. His Honour considered there were 10 issues which might arise for
determination on a claim for payment from the Fund and stated that he could see
no reason why the legislature would permit an appeal in respect of some (but not
other) issues "if that decision results in a nil award"12.
45 The contention advanced by Alinta should be rejected as contrary to the
text and scheme of the Subsidence Act.
"No claim shall be entertained"
46 The Subsidence Act adopts the expression "no claim shall be entertained
or payment made under [the Subsidence Act]" in two provisions. The first is the
penultimate paragraph of s 12(1), which refers to the earlier legislation, the Mine
Subsidence Act 1928 (NSW) ("the 1928 Act"), and provides13:
"No claim shall be entertained or payment made under this Act in respect
of any improvement which was the subject of a conditional right to insure
granted under section 16 of [the 1928 Act] unless the conditions of such
conditional right have been, and are at the date of making such claim,
complied with, or, where such conditions have not been or are not being
so complied with, unless the Board is satisfied that any departure from or
contravention of such conditions is such that it need not be rectified."
47 The second provision is s 15(5)(b), summarised earlier in these reasons.
Section 15(5) states:
12 (2007) 152 LGERA 73 at 76.
13 The 1928 Act established a different scheme whereby owners of improvements
paid a premium for certificates of insurance against damage caused by subsidence
(ss 4(1) and 5(2)) and the Board determined claims against that insurance (s 10(1)).
Section 16(1) of the 1928 Act forbad owners of land within a subsidence district to
alienate any portion of their land in subdivision unless an application for insurance
in respect of improvements had first been made to the Board, which insurance
could be granted unconditionally or conditionally (s 16(3)).
-- 18 of 25 --
Gummow J
Hayne J
Heydon J
Crennan J
Kiefel J
15.
"Where any improvement has been erected or altered or subdivision has
been made in contravention of this section:
(a) …
(b) no claim shall be entertained or payment made under this Act in
respect of damage caused by subsidence to any such improvement
or to any improvement upon land within any such subdivision,
unless a certificate is issued under section 15B(3A) in respect of
the improvement or land."
48 The language of "entertain" and "payment" is also found in s 12(1A) of
the Subsidence Act. Section 12(1A) relevantly provides that the Board "may
refuse to entertain a claim, or make a payment" where improvements or
household or other effects were used in extractive industries or operations and the
Board is satisfied that the relevant subsidence was caused by the carrying on of
that industry or operation. Alinta submitted that the use of "may" in s 12(1A) is
akin to that discussed in Leach v The Queen14 and confers no discretion on the
Board as to whether it should refuse to entertain a claim or make a payment in
such circumstances. It may be assumed, without deciding, that this analysis is
correct.
49 Alinta characterises the Board's refusal to entertain its claim to
compensation as a "decision" made under s 12(2)(b) that "no payment be made
from the Fund in the absence of a s 15B(3A) certificate". That decision of "no
payment" is said to be a decision "as to the amount of the payment from the
Fund" for the purposes of s 12B(b) of the Subsidence Act.
50 However, in this characterisation there is implicit a misunderstanding of
the decision-making process mandated by the provisions just described and by
s 15(5)(b) in particular. Section 15 manifests a policy that the alteration or
erection of improvements within a mine subsidence district should only take
place with the Board's approval. One of the means of giving effect to that policy
is to place persons who contravene s 15 in a position where they are unable to
recover compensation from the Fund in respect of damage caused by subsidence
by force of s 15(5)(b), unless a certificate is issued under s 15B(3A).
51 This object might readily have been achieved by stating "no payment shall
be made under this Act", but the disjunctive phrase "no claim shall be
14 (2007) 230 CLR 1 at 17-18 [38]; [2007] HCA 3.
-- 19 of 25 --
Gummow J
Hayne J
Heydon J
Crennan J
Kiefel J
16.
entertained or payment made under this Act" is adopted in s 15(5)(b) (emphasis
added). This provides a powerful textual indication that s 15(5)(b) curtails not
just a claimant's entitlement to payment from the Fund, but also the Board's
jurisdiction to investigate, report and make a decision as to the payment, if any,
to be allowed under s 12(2)(b). In this regard, both Alinta and the Board accept
that the words "under this Act" in s 15(5)(b) should be read as providing "no
claim shall be entertained [under this Act] or payment made under this Act".
52 The Board submits that s 15(5)(b) requires the Board to satisfy itself that
the approval regime prescribed by s 15 has been complied with before exercising
its extensive powers to investigate, report and determine claims for payment
from the Fund under s 12(2)(b). This construction is explained by the statutory
context. Expenses incurred by the Board in administering the Subsidence Act,
including expenses incurred in investigating notifications of damage and claims
for payment, are paid out of the Fund (s 10(3)(b)). Determining the cause and
extent of damage in a claim for payment from the Fund may be complex and
difficult, especially where (as here) the improvement concerned is a major
underground infrastructure. However, where the Board finds that an
improvement was altered or erected in a mine subsidence district without the
Board's approval and no certificate has issued under s 15B(3A), the words "no
claim shall be entertained" take effect. They relieve the Board from incurring
unnecessary costs investigating and determining whether damage has been
caused by subsidence and the extent and quantum of such damage when, in any
event, no payment could be made because there has been a contravention of s 15.
53 Subject to one additional matter, the Board's construction of s 15(5)(b)
should be accepted. So construed, s 15(5)(b) presents jurisdictional facts upon
which the exercise of the Board's powers under s 12(2)(b) to investigate and
determine claims for compensation are conditioned15. In this case, the Board
found that requisite facts presented by s 15(5)(b) (approval under s 15 or the
issue of a certificate under s 15B(3A)) were not established.
15 R v Connell; Ex parte The Hetton Bellbird Collieries Ltd (1944) 69 CLR 407 at
430, 432; Minister for Immigration and Multicultural Affairs v Eshetu (1999) 197
CLR 611 at 650-654 [127]-[137]; [1999] HCA 21; Graham Barclay Oysters Pty
Ltd v Ryan (2002) 211 CLR 540 at 609 [183]; [2002] HCA 54.
-- 20 of 25 --
Gummow J
Hayne J
Heydon J
Crennan J
Kiefel J
17.
54 Alinta has never conceded in this litigation that the Pipeline was erected
without the Board's approval. Relevantly in this regard, Hodgson JA observed in
the Court of Appeal that16:
"If the Board erroneously decides that an improvement was erected
otherwise than in accordance with an approval of the Board, and for that
reason does not entertain an application, then presumably, unless s 12B
applies, the claimant could seek an order in the nature of mandamus in the
Supreme Court."
In this Court, the Board did not seek to resist that suggestion. To the contrary, it
accepted that no specific time limit applies to an application for orders in the
nature of mandamus in the New South Wales Supreme Court17 and referred the
Court to s 65 of the Supreme Court Act 1970 (NSW) ("the Supreme Court Act").
Section 65 confers powers on the Supreme Court to "order any person to fulfil
any duty" (s 65(1)) and is a simplified procedure unencumbered by the
technicalities which attend the issue of the writ of mandamus at common law18.
55 The additional matter concerns Alinta's submission that s 15(5)(b) applies
only to claims for payment made under s 12(1) and has no application to s 12A.
That contention was summarised in Alinta's letter to the Board of 28 September
2005. This is reproduced in part earlier in these reasons. Alinta's claim was
particularised there by reference to both ss 12 and 12A.
56 However, it is unnecessary to determine whether s 15(5)(b) precludes the
Board from entertaining claims made under s 12A in addition to its operation on
claims made under s 12(1). That question might arise in proceedings for an order
in the nature of mandamus, but does not arise here. The Board decided that it
could not entertain Alinta's claim by reason of s 15(5)(b). Whether that decision
was right or wrong, it will be seen that no decision was made as to the subject
16 (2007) 152 LGERA 73 at 77.
17 cf r 25.07.2 of the High Court Rules 2004 (Cth). As to the discretionary
considerations that would apply at common law, see Bodruddaza v Minister for
Immigration and Multicultural Affairs (2007) 228 CLR 651 at 667 [40]-[42];
[2007] HCA 14.
18 Dickinson v Perrignon [1973] 1 NSWLR 72 at 82-83; McBeatty v Gorman [1976]
2 NSWLR 560 at 564.
-- 21 of 25 --
Gummow J
Hayne J
Heydon J
Crennan J
Kiefel J
18.
matter referred to in s 12B and there arose no right of appeal to the LEC. We
turn now to s 12B.
Section 12B
57 Section 12B is set out earlier in these reasons and repeated for
convenience. The section provides:
"A person claiming compensation under section 12 or 12A may appeal to
[the LEC] against the decision of the Board:
(a) as to whether damage has arisen from subsidence or could
reasonably have been anticipated, or
(b) as to the amount of the payment from the Fund."
58 Three observations may be made about the text of s 12B. First, there must
be a decision of the Board on a claim under ss 12 or 12A for the right of appeal
provided by s 12B to be enlivened. The Board's decision on an application for
approval under s 15 or certification under s 15B will not meet the statutory
description called for by the section. It may thus be observed at the outset that
not every decision of the Board will be the subject of an appeal to the LEC.
59 The second observation is that the Board's decision on the claim must be a
decision "as to" one of two classes of subject matter (identified in pars (a) and (b)
of s 12B) for the right of appeal to be enlivened.
60 The third observation is that the subject matter prescribed in pars (a)
and (b) is identified and delimited by the language of ss 12 and 12A. This
proposition is elucidated by a textual comparison. The disjunctive expression
"arisen from subsidence or could reasonably have been anticipated" in par (a)
corresponds to the language used to prescribe causal elements of claims under
ss 12 and 12A respectively. Under s 12(1), compensation may be claimed for
damage which "arises from subsidence" (s 12(1)(a) and (d)) (emphasis added).
That language is adopted by the first limb of s 12B(a) which refers to a decision
"as to whether damage has arisen from subsidence" (emphasis added). By way
of example, the Board may decide on a claim under s 12(1)(a) that there is no
damage or less damage than is claimed or that the relevant damage pre-existed
the alleged subsidence or has some other cause. Those decisions would be
decisions as to the subject matter identified by s 12B(a). Similarly, a claim may
be brought under s 12A(1)(b) in respect of an amount to meet the expense of
preventing or mitigating damage that, in the opinion of the Board, the owner
-- 22 of 25 --
Gummow J
Hayne J
Heydon J
Crennan J
Kiefel J
19.
could "reasonably have anticipated would otherwise have arisen, or could
reasonably anticipate would otherwise arise" from a subsidence that has taken
place (emphasis added). This language is reflected by the second limb of
s 12B(a). This provides a right of appeal against a decision "as to whether
damage … could reasonably have been anticipated". Pursuant to s 12B(a), an
appeal lies to the LEC against the Board's decision as to that subject matter on a
claim under s 12A.
61 As to par (b) of s 12B, claimants under ss 12(1) or 12A(1) must specify
the "amount claimed" from the Fund in their application (ss 12(2)(a) and
12A(2)(c)) (emphasis added). Sections 12(1)(b) and 12A(1)(b) confer the right
to make a claim for an "amount to meet the proper and necessary expense" of
undertaking certain works (s 12(1)(b)) or preventing or mitigating damage
(s 12A(1)(b)) and s 12(1)(c) confers the right to make a claim for an "amount
equivalent to the rent which would have been payable" (emphasis added). The
Board may also reduce "the amount of compensation" where the damage caused
by subsidence is greater because of the negligent or improper manner in which an
improvement is constructed or maintained (s 12(1), ultimate paragraph)
(emphasis added). The Board's decision as to the quantum of payment from the
Fund pursuant to these provisions would be a decision "as to the amount of the
payment from the Fund" within s 12B(b) of the Subsidence Act.
62 The Board submits that, if a broader construction of s 12B(b) be accepted,
s 12B(a) would be rendered redundant. This would be because any adverse
decision by the Board on the question of causation which leads to the refusal of a
claim and hence "no payment" or a reduced payment is appealable under
s 12B(b). Hodgson JA recognised the force of this submission but observed
that19:
"It seems to me unlikely that the legislature intended that the
availability of an appeal, and the availability or need to approach the
Supreme Court, should depend upon capricious distinctions … so
although there is force in the contention that a broad construction of
s 12B(b) would render s 12B(a) otiose, I think the broad construction of
s 12B(b) is preferable."
63 However, there may be a number of reasons for the distinction drawn by
the text of s 12B. One is that s 12B reflects an intention to limit the liability of
19 (2007) 152 LGERA 73 at 77.
-- 23 of 25 --
Gummow J
Hayne J
Heydon J
Crennan J
Kiefel J
20.
the Fund under s 10(3)(b) to the costs of a rehearing in the LEC on any decision
of the Board that goes on appeal. Another is that the legislature left to the Board
the determination of jurisdictional facts, subject to scrutiny only on judicial
review in the Supreme Court. That state of affairs is more readily understood
where, as here, the jurisdictional impediment was in the alleged absence of
approval and the absence of a certificate respecting Alinta's improvement. On
the other hand, the legislation left for determination by the LEC de novo such
questions as the determination of causation and quantum of compensation in
claims competently made against the Fund.
64 The right of appeal to the LEC is restricted to appeals against decisions of
the Board as to the subject matter identified in s 12B(a) and (b). The outcome of
"no payment" in this case followed not from a decision as to either of those
subject matters, but from the Board's application of the statutory requirement that
no claim be entertained in the circumstances prescribed by s 15(5)(b). In these
circumstances, there was no decision of the Board "as to the amount of the
payment from the Fund" under s 12B(b) against which an appeal would lie to the
LEC. The jurisdiction to hear and dispose of an appeal under s 12B of the
Subsidence Act is not enlivened by Alinta's application.
65 One final point may be noted. This concerns Alinta's reliance on the
legislative history of the right of appeal under the Subsidence Act. Alinta
referred the Court to the 1928 Act and the Subsidence Act as it stood before
amendment to include s 12B. It is unnecessary to set out that history here. The
submission raised essentially the same question as to construction and takes
Alinta's case no further.
Orders
66 It follows that the answer to the preliminary question is "no". The appeal
should be dismissed with costs.
-- 24 of 25 --
-- 25 of 25 --