ACN 057 690 034 Pty Limited v Wykrota [2020] NSWSC 1430
Catchwords: LEGAL PROFESSION – duty of candour – undefended hearing – principles at [ 83 ], [ 91 ] – no breach of duty – trial judge not misled. SET ASIDE JUDGMENT – building contract –problems getting occupation certificate – damages sought from builder including loss of rent – first defendant appeared in person on occasion – 12 directions hearings – no appearance at final hearing – aware of hearing – unsatisfactory medical certificate – inadequate explanation – experienced litigant – access to legal advice – writ of execution registered against first defendant’s property – property sold and judgment sum paid into court – application to set aside judgment, being 18 months after judgment . JUDGMENT IRREGULARLY OBTAINED – r 36.15 UCPR – principles at [ 3 ]-[ 7 ] – whether admissions arising from failure to file defence provided basis for judgment – imperfect pleading against multiple defendants – admissions by first defendant founded judgment against him – whether damages awarded outside pleaded case – damages sought notified to first defendant in schedule of damages – no misconduct or dishonourable conduct by plaintiff –failure to accord procedure fairness no basis to set aside judgment (nor such unfairness here) . JUDGMENT IN ABSENCE OF PARTY – r 36.16 UCPR – principles at [ 8 ]-[ 12 ] – inadequate explanation for failure to attend – significant delay in bringing application – inadequate explanation for delay – little proffered to reduce hardship of judgment creditor – second defendant now deregistered – plaintiff took large discount in its claim before trial judge in order to finalise proceedings and only the judgment amount secured – offers in respect of plaintiff’s legal costs parsimonious – arguable defence – not unjust to let judgment stand.
Supreme Court
New South Wales
Medium Neutral Citation:
ACN 057 690 034 Pty Limited v Wykrota [2020] NSWSC 1430
Hearing dates:
7 October 2020
Date of orders:
16 October 2020
Decision date:
16 October 2020
Jurisdiction:
Equity
Before:
Rees J
Decision:
Dismiss m otion to set aside judgment
as made irregularly, against good faith or in the absence of the first defendant ,
with costs.
Catchwords:
LEGAL PROFESSION – duty of candour – undefended hearing – principles at [
83
], [
91
] – no breach of duty – trial judge not misled.
SET ASIDE
JUDGMENT
– building contract –problems getting occupation certificate – damages sought from builder including loss of rent – first defendant appeared in person on occasion – 12 directions hearings – no appearance at final hearing – aware of hearing – unsatisfactory medical certificate – inadequate explanation – experienced litigant – access to legal advice –
writ of execution registered against
first defendant’s property – property sold and judgment sum paid into court – application to set aside judgment, being 18 months after judgment .
JUDGMENT IRREGULARLY OBTAINED
– r 36.15 UCPR – principles at [
3
]-[
7
] – whether admissions arising from failure to file defence provided basis for judgment – imperfect pleading against multiple defendants –
admissions by first defendant founded judgment against him – whether damages awarded outside pleaded case – damages sought notified to first defendant in schedule of damages – no misconduct or dishonourable conduct by plaintiff –failure to accord procedure fairness no basis to set aside judgment (nor
such unfairness here) .
JUDGMENT IN ABSENCE OF PARTY –
r 36.16 UCPR – principles at [
8
]-[
12
] – inadequate
explanation for failure to attend
– significant delay in bringing application – inadequate explanation for delay – little proffered to reduce hardship of judgment creditor – second defendant now deregistered – plaintiff took large discount in its claim before trial judge in order to finalise proceedings and only the judgment amount secured – offers in respect of plaintiff’s legal costs parsimonious – arguable defence – not unjust to let judgment stand.
Legislation Cited:
Civil Procedure Act
2005
(NSW) ,
ss
91(2),101
Uniform Civil Procedure Rules 2005 (NSW) ,
rr
36.15 ,
36.16 , 36.16(2)(b)
Cases Cited:
Acclaim Holdings Pty Ltd v
Vlado
[1989] 1 WAR 128
ACN 057 690 034 Pty Limited v
Wykrota
[2019]
NSWSC
197
ACN 076 676 438 Pty Ltd (in
liq) v A-Comms
Teledata
Pty Ltd
[2000] WASC 214
Alexander v Ajax Insurance Co Ltd
[1956] VLR 436
Anlaby
v
Praetorius
(1888) 20 QBD 764
BH Australia Constructions Pty Ltd v
Kapeller
(2019) 100
NSWLR
367;
(2019) 375 ALR 159;
[2019] NSWSC 1086
Burrell v R
(2008) 238 CLR 218; [2008] HCA 34
Coles v Burke
(1987) 10 NSWLR 429
Collie v
Merlaw
Nominees Pty Limited
[2003] VSC 424
Commonwealth Bank of Australia v Buffett
(1993) 114 ALR 245
D’Orta-Ekenaike
v Victoria Legal Aid
(2005) 223 CLR 1;
[2005] HCA 12
Daly v
Silley
[1960] VR 353
Day v
Sternhell
[2020]
NSWSC
513
Deputy Commissioner of Taxation v
Tabuso
(2013) 94
ATR
343; [2013] NSWSC 688
DJL v Central Authority
(2000) 201 CLR 226
Fenato
v Chief Commissioner of State Revenue
(2010) 78 NSWLR 20; [2010] NSWCA 80
Kavia
Holdings Pty Ltd v
Werncog
Pty Ltd
[1999] NSWSC 839
Kendell v Carnegie
(2006) 68 NSWLR 193; [2006] NSWCA 302
Leichhardt Council v
Geitonia
Pty Ltd (No 7)
[2015] NSWLEC 79
Magnate Projects Pty Ltd v
Youma
Constructions (No
2) Pty Ltd
[2005] NSWCA 331
Miltonbrook
Pty Limited v Westbury Holdings Kiama Pty Limited
(2008) 71 NSWLR 262; [2008] NSWCA 38
Northey
v Bega Valley Shire Council
[2012] NSWCA 28
Perpetual Trustees Australia Ltd v
Heperu
Pty Ltd (No 2)
(2009) 78 NSWLR 190; [2009] NSWCA 387
Pethybridge
v
Stedikas
Holdings Pty Ltd
[2007] NSWCA 154
Pham v Gall
[2020] NSWCA 116
Vacuum Oil Co Pty Ltd v Stockdale
(1942) 42 SR NSW 239
White v Weston
[1968] 2 QB 647
Zakaria
v Dr
Noyce
[2012] NSWSC 981
Texts Cited:
G E Dal Pont,
Lawyers’ Professional Responsibility
(6th ed, 2017, Law Book Company)
Category:
Principal judgment
Parties:
ACN 057 690 034 Pty Limited (Plaintiff)
Mick Wykrota (First Defendant)
Arrowfab Pty Limited (Second Defendant)
Arrowcon Construction Pty Limited (Third Defendant)
Representation:
Counsel:
Mr EC Muston SC / Mr S Jayasuriya (Plaintiff)
Mr JM Ireland, Solicitor (First Defendant)
Solicitors:
Swaab Attorneys (Plaintiff)
Hall & Wilcox (First Defendant)
File Number(s):
2017/337742
Judgment
HER HONOUR:
This is an application to set aside a judgment
given
some 18 months ago as
either made irregularly ,
against good faith or in the absence of
a
part y .
By motion filed on 4 August 2020, the first defendant, Mick
Wykrota , seeks an order pursuant to rule 36.15 of the Uniform
Civil
Procedure Rules 2005 (NSW)
(
UCPR
)
or, alternatively, rule 36.16, that judgment entered against
him
in favour of the plaintiff, ACN 057 690 034 Pty Limited ,
on 28 February 2019 by Emmett
A J A
be set aside, together with an order for the costs of the motion.
Other p arties to the proceedings, but not the motion, were second defendant,
Arrowfab
Pty Limited (now deregistered) ,
and third defendant,
Arrowcon
Construction Pty Limited. Mr
Wykrota
is the sole director and shareholder of
Arrowcon
Construction.
Sadly, this judgment is far longer than that of
Emmett
A J A , being
ACN 057 690 034 Pty Limited v
Wykrota
[2019]
NSWSC
197.
Reference need also be made to a judgment of Darke J
in related proceedings
Day v
Sternhell
[2020]
NSWSC
513.
It should be noted immediately that this is not an appeal from the judgment of
Emmett AJA, albeit the submissions on occasion had something of that flavour. The question is whether
Mr
Wykrota
has established that he is entitled to an order under
either
rule
of the UCPR
and
whether , in the circumstances of this case, the Court ’ s discretion should be exercised to make
the
orders sought .
Setting aside judgment irregularly obtained
Rule 36.15(1) of the UCPR provides:
36.15
General power to set aside judgment or order
(1)
A judgment or order of the court in any proceedings may, on sufficient cause being shown, be set aside by order of the court if the judgment was given or entered, or the order was made, irregularly, illegally or against good faith.
What this rule envisages was described in
Coles v Burke
(1987) 10 NSWLR 429 by Kirby P (with whom Samuels and McHugh JJA agreed) at 437:
The genus which is involved in the phrase “irregularly, illegally or against good faith” appears to me to be misconduct or dishonourable conduct of the person who procured the judgment which it is suggested undermines the authority of that judgment warranting the exceptional course for which [the rule] provides.
This description was adopted in
Kendell v Carnegie
(2006) 68 NSWLR 193;
[2006] NSWCA 302 by Bryson JA (with whom Hodgson and McColl JJA agreed) at [44] and [54]. Further, Bryson JA added that
“ against good faith" is an expression which requires the impeachment of the intention or behaviour of the person whose good
faith is impugned: at [60].
As Davies J also observed in
Zakaria
v Dr
Noyce
[2012] NSWSC 981 at [22]:
The significant matter is that for a judgment to be set aside as having been entered against good faith there must be misconduct or dishonourable conduct by the person who procured the judgment. The matter is directed, not to the Court or the Judge who entered the judgment, but to the party who was responsible for bringing it about.
Thus, in that case, failure to accord procedural fairness to a party did not form a basis to set aside the judgment under the rule, which was directed to the conduct of the judgment creditor.
Where a judgment has been entered irregularly for an y
of these reasons, the Court is not obliged to enquire whether or not there is a good defence on the merits :
ACN 076 676 438 Pty Ltd (in
liq
) v A-
Comms
Teledata
Pty Ltd
[2000] WASC 214
per Parker J at [17],
citing
Anlaby
v
Praetorius
(1888) 20 QBD 764;
Alexander v Ajax Insurance Co Ltd
[1956] VLR 436;
White v Weston
[1968] 2 QB 647;
Daly v
Silley
[1960] VR 353 ;
Acclaim Holdings Pty Ltd v
Vlado
[1989] 1 WAR 128.
However,
the rule also requires
“ sufficient cause
being shown ”
before a judgment will be set aside, recognising the need for finality by protecting judgments from being set aside for slight or uncertain causes (
Kendell v Carnegie
at [45]) and the fundamental principle of the general finality of judgments (
Perpetual Trustees Australia Ltd v
Heperu
Pty Ltd (No 2)
(2009) 78 NSWLR 190; [2009] NSWCA 387 at [32]-[33] and [45]).
As the High Court made plain in
Burrell v R
(2008) 238 CLR 218;
[2008] HCA 34
at [15]
(per
Gummow
ACJ , Hayne,
Heydon ,
Crennan
and
Kiefel
JJ ) :
As was said in
D’Orta-Ekenaike
v Victoria Legal Aid
(2005) 223 CLR 1 at 17 [34]; [2005] HCA 12:
“A central and pervading tenet of the judicial system is that controversies, once resolved, are not to be reopened except in a few, narrowly defined, circumstances.”
That tenet finds reflection in rules concerning the bringing of an action to set aside a final judgment on the ground that it was procured by fraud [citing
DJL v Central Authority
(2000) 201 CLR 226 at 244–245 [36]–[37]]
and in the doctrines of res judicata and issue estoppel. The principal qualification to the general principle of finality is provided by the appellate system. But in courts other than the court of final resort, the tenet also finds reflection in the restrictions upon reopening of final orders after they have been formally recorded.
Thus, it
will not be appropriate to set aside a judgment under this rule where the irregularity is inconsequential or causally unrelated to the making of the judgment or order:
Deputy Commissioner of Taxation v
Tabuso
(2013) 94
ATR
343;
[2013] NSWSC 688 at [18] per Harrison J;
Commonwealth Bank of Australia v Buffett
(1993) 114
ALR
245 ;
A-
Comms
Teledata
Pty Ltd
at [18].
As Nettle J observed in
Collie v
Merlaw
Nominees Pty Limited
[2003]
VSC 424 at [38],
“ Plainly, the Court may disregard irregularities of a kind that are insignificant. Technical defects are an obvious example of the kind ” .
The
example cited by Nettle J was
Commonwealth Bank v Buffett,
where default judgment was entered on a summons which contained errors, including as to when an appearance was to be filed.
Chief Justice
Morling
(sitting on the Supreme Court of Norfolk Island) considered that the errors did not cause any injustice to the defendant, lead him to change his position nor cause him any prejudice ;
the
defendant would not have filed an appearance in any event and did not intend to defend the proceedings: at 251.
Setting aside judgment regularly obtained
Rule 36.16(2)(b)
of the UCPR
provides:
36.16
Further power to set aside or vary judgment or order
…
(2)
The court may set aside or vary a judgment or order after it has been entered if—
…
(b)
it
has been given or made in the absence of a party, whether or not the absent party had notice of the relevant hearing or of the application for the judgment or order …
As Barrett JA succinctly explained in
Northey
v Bega Valley Shire Council
[2012] NSWCA 28, an applicant for an order under this rule must still contend with the proposition that great value attaches to certainty in the outcome of litigation: at [14]. At [16]:
The central question is whether it is unjust to let the perfected order stand. The matter was put thus by Jordan CJ (Davidson J and Roper J concurring) in
Vacuum Oil Co Pty Ltd v Stockdale
(1942) 42 SR NSW 239 at 243-4:
The question is whether, upon the material that has been placed before us, there is a real likelihood that it would be unjust to the defendant to allow the judgment to stand. If so, it should be set aside on such terms as it will minimise the possibility of injustice to the plaintiff. If not, we should not interfere.
Similarly, Hodgson JA described the task before an applicant in
Magnate Projects Pty Ltd v
Youma
Constructions (No 2) Pty Ltd
[2005] NSWCA 331 at [52]:
In my opinion, an applicant seeking to set aside a judgment obtained after an undefended hearing does not have to show that a different result is likely should the judgment be set aside and a new trial ordered. However, the circumstances may be such, as Jordan CJ says, as to require ‘a reasonably clear case of merits to be shown’; that is, that it appears
reasonably clearly that there is a defence capable of producing a different result. If that defence depends on facts, then there should be some evidence of those facts; and the circumstances may be relevant to the quality of the evidence that is required to show a defence on the merits in particular cases. Among such circumstances could be the degree of the applicant’s default, and hardship to the respondent.
Both statements of principle were recently endorsed by the Court of Appeal in
Pham v Gall
[2020] NSWCA 116 (Payne JA with whom Leeming and McCallum JJA agreed). As Payne JA summarised the position at [110]:
UCPR r 36.16(2)(b) provides an unfettered, though judicial, discretion .
It is unwise to attempt to lay down rules of universal application in the exercise of that broad discretion which
… necessarily involves the Court in making a broad evaluative judgment.
… [I] t is necessary to consider (a) whether any useful purpose would be served by setting aside the judgment, and (b) how it came about that the applicant became bound by a judgment regularly obtained.
Further, Payne JA noted an
“ important qualification ” , being,
“ The more egregious the delay in seeking to set aside an undefended judgment, the greater the burden of persuasion that will be required ” : at [98], [109],
[ 112].
Leeming JA similarly observed that it was necessary for the Court to have regard to the positive defence sought to be raised by the applicant, the explanation for non-appearance and delay in bringing the application, and what is proffered to reduce the prejudice to the judgment creditor: at [57].
FACTS
The plaintiff owned property in Lansvale and obtained development approval from Fairfield City Council to undertake building work. In Ju ne
2010, the plaintiff
put the building work out to
tender. According to
Mr
Wykrota , the
project
engineer, Angelo
D ’ Ambrosio , introduced him to Tony Le, a director of the plaintiff , and
suggested that
Mr
Wykrota
submit a
tender. On 2 November 2010, Mr
Wykrota
sent an email from
a personal
Yahoo email
account
bearing his name rather than any corporate or business name , stating:
We have
great pleasure to submit our lump sum price to carry out and complete the above works
…
Mick
Wykrota
Arrowfab
Pty Limited
Mr
Wykrota
relies on the reference in the email to “We” and the email signature referring to
Arrowfab
as supporting the existence of a contract between the plaintiff and
Arrowfab
rather than himself, whilst the plaintiff notes the personal nature of the email address and the direct personal dealings between Mr
Wykrota
and Mr Le. Either way, Mr
Wykrota
says that Mr Le accepted the price and, in December 2010, demolition work commenced. Mr
Wykrota
submitted the first progress claim on 31 January 2011, requesting Mr Le to pay the progress claim to “Arrowbab
(sic)
Pty Limited”.
In February 2011, Mr
Wykrota
transferred his shares in
Arrowfab
to a colleague . On 22 February 2011,
Arrowcon
Construction
was incorporated and Mr
Wykrota
says work on the project was then undertaken by this
company.
On 15 April 2011, Mr
Wykrota
submitted a progress claim to Mr Le, asking that the payment be made to
Arrowcon
Construction. Mr Le replied :
Hi Mick no problems we will pay you
asap!!!!
Mick have you signed building contract yet? I need
to have a copy
please!!!
A building contract was drafted between the plaintiff and
Arrowcon
C onstruction but not signed, nor
was
there any evidence on this application that the document was ever provided to the plaintiff.
S ubsequent progress payments were
made
by
Arrowcon
Construction, although the final progress payment was made to J & E Excavations & Plant Hire Pty
Ltd.
By February 2012, according to Mr
Wykrota , the contract works had been completed. By November 2012 ,
the plaintiff was endeavouring to
obtain an occupation certificate and Mr
Wykrota ’ s
assistance was sought in this regard, apparently with mixed success. On 23 May 2014, the plaintiff commenced proceedings in the NSW Civil
and
Administrative Tribunal
(
NCAT
)
against
“ a rrow con
c onstructions ” . The application was prepared by Mr Le . Some
$30,000
was claimed
in order to repair electrical works, carpentry and glazing under warranty and to obtain a final occupation certificate.
The application form called for
“ A greement Details ” , which were supplied by Mr Le as follows:
“ a lot of building works need to be fixed under builder warranty and certificates needed for final occupation certificates but builder does not want to answer phone calls, emails, trying to avoid us ” .
However, on
5 September 2014, the following orders were made in the NCAT proceedings:
1.
The application is dismissed as the Tribunal has no jurisdiction to determine the application, as the premises are commercial premises.
2.
The respondent’s name ARROWCON
CONSTRUCTIONS,
is amended to ARROWCON CONSTRUCTIONS Pty Ltd.
NOTE: The applicant is to obtain legal advice in relation to his claim and the correct jurisdiction to lodge a claim.
Mr
Wykrota
relies on the fact that the proceedings were commenced by the plaintiff against
Arrowcon
Construction as consistent with an understanding on the plaintiff’s part that the building contract was with that company rather than with Mr
Wykrota . Such an inference
can certainly be drawn from these events, although
it appears
that Mr Le did not have the benefit of any legal advice
at the time
and, at least from the
tribunal’s point of view, should get some.
It appears that Mr Le heeded the
t ribunal ’ s suggestion and retained solicitors.
In October 2016 and December 2016, the plaintiff ’ s solicitor sent letters of demand to
Arrowcon
Construction
(again, consistent with an apprehension by the plaintiff that the building contract was with
Arrowcon
Construction) . F rom June to August 2017, Mr
Wykrota ’ s
assistance was again sought to obtain a final occupation certificate. In August 2017, Mr Le threatened to sue
Mr
Wykrota ,
having
become aware from the plaintiff ’ s solicitors searches that
Mr
Wykrota
owned several properties and thus, presumably, was worth suing.
These proceedings
On 8 November 2017, the plaintiff commenced these proceedings by filing a statement of claim. T he plaintiff
sued
Mr
Wykrota ,
Arrowfab
and
Arrowcon
Construction ,
seeking specific performance ,
damages and costs.
The claim for specific performance concerned procuring production of the necessary certifications to obtain an occupation certificate. As to damages, particulars were given of damage said to flow from the lack of an occupation certificate, being an inability to lease, occupy, resell or re-zone the premises. No particulars of damages were given of building defects.
As to the contract
said to found the claims for relief , it was
pleaded,
(emphasis added)
In about November 2010 the plaintiff and
the first defendant
agreed that
the first defendant
would carry out building work comprising alterations and additions to the premises at … Lansvale …
(“the building contract”).
Particulars of the building contract were
supplied , including that Mr
Wykrota
was obliged to
supply all certificates and documents to the certifier to enable an occupation certificate to issue.
The pleading then bec a me less clear. It
was
pleaded
that the contract was partly oral and partly in writing comprising the tender documents, the email
“ from the first defendant ”
referred to at [
13
] and
“ various conversations between Tony Le on behalf of the plaintiff and the first defendant
on behalf of the second and third defendants
” .
It
was
then pleaded that Mr
Wykrota
represented
that
Arrowfab
and then
Arrowcon
C onstruction would be performing part or
all of the
contract
“ on behalf of the first defendant ” . Further, it was
said to be
a term of the building contract
“ that
the defendants
would upon completion of the building work and as part of the work do all things necessary to obtain a Certificate of Occupation so that
the plaintiff
s
[there being only one plaintiff] could occupy the premises ” . It
was
then said that the plaintiff performed the building contract by making the payments required
“ to the second and third defendants when directed to do so by the first defendant ” .
It
wa s then pleaded that
“ the defendant ”
represented orally that the plaintiff could move back into the property and an occupation certificate would issue but since then the plaintiff ha d,
variously ,
requested
“ the defendants ”
or
“ the defendant ”
to provide the necessary documents to the certifier so that an occupation certificate
could
be obtained but ,
“ The defendants have failed to perform the building contract ”
and,
“ In breach of the building contract the defendants have, since 2012 failed to provide the Certificates
…” .
Thus,
it can be seen that
the plaintiff joined as defendants all parties who were, or may have been,
parties to the
building contract ,
obliged to perform it
and failed to do so . It
was
tolerably clear that the plaintiff ’ s
primary
position was that
the building contract was with Mr
Wykrota ,
although the pleading
proceeded
to
‘ cover all bases ’ ,
albeit in a manner that was not entirely consistent or clearly delineated . Such
pleading
imperfections may, of course, be clarified in the ordinary course of legal proceedings by queries raised by
defendants in correspondence ,
requests for further particulars or defence s
and addressed, including by amending pleadings to clarify the plaintiff ’ s case.
But t hat is not how these proceedings unfolded.
The matter was first listed for directions on 12 December 2017 when Mr
Wykrota
appeared in person . As
the plaintiff ’ s counsel, Elizabeth Cohen,
reported
to her instructing solicitors ,
Mr
Wykrota
appeared
“ to advise the Court he had not been properly served, but that he knew about the matter because the companies had been served. ”
Mr
Wykrota
required that the
statement of claim
be
personally
served upon him
and asked
that the
proceedings
be adjourned until
13 February 2018 ,
a request to
which the register acceded .
The
R egistrar
“ also requested that we both go outside and he could tell me how to serve him. ”
Ms Cohen so enquired ,
“ but
he refused to tell me. ”
On 28 December 2017, the statement of claim was personally served on Mr
Wykrota , although he does not recall
it .
Whether Mr
Wykrota
recalls it or not, according to an
affidavit of service
duly
filed
and relied upon by the plaintiff at the hearing before Emmett AJA ,
he was so served . On 11 January 2018, the plaintiff ’ s solicitor wrote to Mr
Wykrota
noting that the matter was next before the Court on 13 February 2018 and
enquir ed
as to
the name
and contact details
of his solicitor.
According to Mr
Wykrota , in February 2018, he met with Mr Le and Mr
D ’ Ambrosio
and offered to organise for various certificates to be re-issued in respect of insulation, hot water, lighting and waterproofing if Mr Le would tell his solicitor to withdraw the proceedings. It is said that Mr Le agreed. Mr
Wykrota
set about obtaining the certificates.
He supplied two certificates.
On 13 February 2018, Ms Cohen appeared at the directions hearing before the Registrar and mentioned the matter by consent for the defendants. The matter was relisted on 4 April 2018. However, on that occasion, there was no appearance for the defendants. The Registrar made orders for any defences
to be filed by 2 May 2018 and stood the matter over to 9 May 2018. The plaintiff ’ s solicitors notified Mr
Wykrota
of the orders, advising:
We also hereby formally notify you that if no defence
is
filed, we will on 9 May 2018 have the matter listed for hearing as an undefended matter
On 9 May 2018, there was again no appearance for the defendants and the Registrar made orders that the plaintiff serve its evidence in respect of damages by 15 June 2018 and stood the matter over to 20 June 2018. The plaintiff ’ s solicitors wrote to Mr
Wykrota
informing him of these orders, including that the matter was listed on 20 June 2018
“ for the purposes of obtaining a hearing date for an undefended hearing ” . On
20
June 2018, the Registrar extended the time for the plaintiff to serve its evidence and relisted the matter on 8 August 2018 for the purposes of obtaining a hearing date for an undefended hearing. The plaintiff ’ s solicitors wrote to Mr
Wykrota
advising of these orders.
On 30 July 2018, the plaintiff ’ s solicitor wrote to Mr
Wykrota
advising that
the plaintiff
intended to seek an extension of time to put on
its
evidence and to
re- list the matter on 5 September 2018 for the purposes of obtaining a hearing date. Mr
Wykrota
says that, at the time he received this letter, he believed that Mr Le had agreed to withdraw the proceedings on the basis of the agreement reached in February 2018 ,
which he says he had then fulfilled. Consistently with this, on 6 August 2018, Mr
Wykrota
sent an email to Mr Le, Mr
D ’ Ambrosio
and the certifier referring to the meeting:
We have had meeting at Angelo office some time ago, we agree that I will cooperate and help to obtain water proof
certificate and insulation certificate ALL BOTH.. done, Angelo was witness …You inform me that
You will
instract
[sic] Your solicitor
to withdraw Supreme Court papers,,, if You change Your mind PLEASE let me Know ASAP
The email
was sent
from the email address referred to at [
13
].
Mr
Wykrota
does not recall receiving a response to this email,
nor
receiving any other notices ,
and presumed that Mr Le was not proceeding with the court action. Whether Mr
Wykrota
recalls it or not, it is
likely
that he continued to
receive emails and letters from the plaintiff ’ s solicitor on a regular basis. The very next day, on 7 August 2018, the plaintiff ’ s solicitor sent an email to the
R egistrar ,
copied to Mr
Wykrota ,
requesting an extension of time to file the plaintiff ’ s evidence. The
R egistrar made the orders sought and, also on 7 August 2018, emailed the parties including Mr
Wykrota , informing the parties of the orders made, including that the matter was now listed on 5 September 2018
“ for the purposes of obtaining a hearing date for an undefended hearing ” .
Both emails
were sent
to the email address referred to at [
13
] , from which
Mr
Wykrota
had sent an email the previous day .
The plaintiff ’ s solicitor also sent a letter to Mr
Wykrota
notifying him of the orders.
On 5 September 2018, there was no appearance for the defendants. The matter was relisted on 7 November 2018 and the plaintiff ’ s solicitor wrote to Mr
Wykrota
advising him of the orders made.
O n 30 October 2018, an occupation certificate was obtained.
The plaintiff ’ s claim for specific performance thus became otiose.
On 3 November 2018,
two affidavits were sworn for the plaintiff, one by Mr Le and another by an expert
valuer
a ssessing the market rent al
for the property.
On 6 November 2018, these affidavits were served on Mr
Wykrota . An affidavit of service was duly filed.
For completeness, a second affidavit of the
valuer
was sworn on 26 November 2018 and, according to a
“ successful service report ” ,
was served that day.
Mr Le ’ s affidavit
set out in some detail
–
over 91 paragraphs and 190 pages of exhibits
–
the contractual arrangements, correspondence concerning the inability to obtain an occupation certificate, efforts to obtain the relevant certifications and expenses incurred along the way.
As to the contractual arrangements, Mr
Wykrota
relied
particularly
on
the following passage of
Mr Le ’ s affidavit :
(emphasis added)
The building work was put out to tender
…
and
the second defendant
won that tender. After the Tender was accepted I did all negotiations with
the second defendant
on behalf on the plaintiff
and I dealt with a Mick
Wykrota
on behalf of the first defendant and later the second defendant.
In about September 2010,
…
the plaintiff
and the first defendant
agreed that
the first defendant
would carry out building work
…
(“the building contract”).
As I read this passage, Mr Le describes initially dealing with
Arrowfab
in respect of the tender and associated negotiations but ultimately
entered into a contract
with Mr
Wykrota .
Mr Le also
deposed
that the plaintiff
had
commenced action
in
NCAT
against
Arrowcon
Construction.
The documents to which Mr
Wykrota
points as supporting a meritorious defence of these proceedings were referred to in the body of Mr Le ’ s affidavit and exhibited to it.
On 7 November 2018, there was no appearance for the defendants. The Registrar listed the matter
for hearing
on 28 February 2019 before Emmett AJA.
The plaintiff ’ s solicitor wrote to Mr
Wykrota
informing him of the se
orders.
Pre-trial directions hearings before Emmett AJA
On 20 November 2018, the associate to Emmett
AJA
sent an email to the parties ,
listing the matter for directions on 28 November 2018. On 27 November 2018, Mr
Wykrota
replied ,
“ T hanks ” ,
using the email address
referred to at [
13
] .
W hilst Mr
Wykrota
said that he only became aware that the matter was listed before Emmett AJA on 28 November 2018 because he was already at Court that day in relation to other proceedings, this is not consistent with the contemporaneous documents which indicate that Mr
Wykrota
was informed of the listing by Emmett AJA ’ s
A ssociate
on 20 November 2018 , and acknowledged receipt of
the
email
on 27 November 2018,
the day before the directions hearing .
On 28 November 2018,
Mr
Wykrota
appeared in person
before Emmett
AJA . Mr
Wykrota
informed his Honour that, given the meeting in February 2018
described at [
25
] , he had not thought it necessary to defend the proceedings nor instruct a lawyer.
Further:
I did the work for Mr Lee Tuan which company is listed there. I completed work in 20[0]9. I obtained an interim occupation certificate because he didn’t pay certain amounts of money.
I said, well, it was not my responsibility to obtain final construction certificate because I only supply the certificates for the work which I did and I supervised.
The plaintiff observed that,
at no time during the directions hearing, did Mr
Wykrota
suggest that the building contract was with anyone other than him.
His Honour enquired of the plaintiff ’ s counsel as the relief sought. Ms Cohen
advised
that, although
specific performance had been sought,
the plaintiff was now claiming damages as it had achieved the issue of a n occupation
certificate through the use of consultants .
Damages was
also sought for
loss of rent. His Honour enquired whether the statement of claim needed to be amended or whether the damages now sought were adequately particularised. Ms Cohen explained that
particulars of the damages
w ere now
to be found in the affidavit s, but was unclear as to the
total
amount sought.
His Honour asked whether Mr
Wykrota
now understood the claim against him and
asked
what his answer to it was. Mr
Wykrota
again
relied upon the
agreement said to have been reached at the
February 2018
meeting .
Given the apparent ly substantial
amount of damages sought,
his Honour suggested
in strong terms
that Mr
Wykrota
obtain legal representation. Mr
Wykrota
said he would . His
Honour indicated he would bring the matter back for directions before the end of the year to
give
Mr
Wykrota
time to do so . In addition, Emmett AJA directed the plaintiff to provide a detailed schedule of the claim for damages to be served on anybody who filed an appearance.
The
matter was stood over for further directions on 13 December 2018. On 29 November 2018, Emmett AJA ’ s
A ssociate sent an email to the parties confirming the orders which had been made.
On 6 December 2018, the plaintiff filed a schedule of damages, which was served on Mr
Wykrota
on 7 December 2018.
The schedule listed 20 items. In respect of each item, a description was given
together with the
date when the loss was
said to have been
incurred, a reference to Mr Le ’ s affidavit
where
evidence in support of the item could be found , the amount claimed and the payee, where applicable. The bulk of the items were expenses incurred in 2018, apparently in the course of obtaining the necessary certificat ions
to
support the issue of
an occupation certificate.
The largest item was lost rent of some $171,375.
On 7 December 2018, Mr
Wykrota
filed
a notice of appearance
“ for defendant ” .
On 13 December 2018,
Mr
Wykrota
appeared in person before Emmett AJA for directions.
Ms Cohen
confirmed
that
the
schedule of damages had been filed . The
following exchange
ensued
between Emmett
AJA
and Mr
Wykrota :
HIS HONOUR: You've seen the claim?
DEFENDANT: Yes,
your
Honour. I had a [n]
advice from my solicitor and they couldn't take the case, and for that case I have to spend $25,000
…. This is bogus claim. I had an agreement. There is no further damage occurring to the plaintiff because he obtained an occupation certificate. If I have to I will ask for postponement on the hearing and lodge the defence, but I'm hoping that they will get some sense and will drop the case. Sorry for being--
HIS HONOUR: Well--
DEFENDANT: --stressed, but that's the case
…
HIS HONOUR: Well, why--
DEFENDANT: --if you give us to January, because the
-
my solicitor who is going to represent me is involved in case to 29 January.
HIS HONOUR: The case is fixed for 28 February, I think.
DEFENDANT: I understand that, but we'll ask for
-
we'll make the application for postponement if I can--
HIS HONOUR: Well--
DEFENDANT: Need, need the time with my solicitor.
HIS HONOUR: It's fixed for hearing at the moment and--
DEFENDANT: I understand, I understand. I apologise for, for the chaotic approach, but I don't believe that this is a genuine case
…
… I would like
-
I would like to ask you to give me till early February, like, the
-
to organise myself and--
HIS HONOUR: Well, I gave you until today and--
DEFENDANT: Yes, I, I, I spoke to my solicitor
… I'm not lying, I'm just trying to organise myself, that stressing situation, because I don't have a
-
money to spend on this, I lost a lot of money on this project and these people are really very unreasonable. They obtained a [n]
occupation certificate by now with my cooperation and
everybody,
it was not my responsibility to give them occupation certificate in first place because when I took the job they didn't have a construction certificate …
…
the
person who is pivotally in this everything is Mr Angelo
[D’Ambrosio], who is the engineer who asked me to do this job, I did it for the small quote
…
On this application, the
plaintiff again observed that at no time did Mr
Wykrota
suggest that the building contract was with anyone other than him.
His Honour
indicated that
he would list the matter for directions
on 6
February 2019 and advised Mr
Wykrota
that
an y
application to vacate the
hearing would have to be dealt with then . Mr
Wykrota
advised that his lawyer was in another case from 29 January 2019 but,
“ I ’ ll talk to him and try to lodge the application to postpone the case as soon as I can ” .
On 6 February 2019, there was no appearance
by Mr
Wykrota
before Emmett
AJA . His Honour confirmed the hearing o n 28 February 2019.
Pre-trial communications with the
Associate
On 27 February 2019,
Emmett AJA ’ s
A ssociate sent an email to the parties confirming the hearing on 28 February 2019. Mr
Wykrota
replied,
P lease be
inform
that
i
am very sick and not able to be in Court tomorrow.
Later that day, Mr
Wykrota
sent a further email to
Emmett AJA ’ s
A ssociate
attaching a medical certificate
and
advised:
I am very sorry but
i
can not
be in Court tomorrow
pleaswe
pas my apologies to Justice Emmett
Attached was a certificate of incapacity for work issued by a medical doctor that day in respect of Mr
Wykrota , declaring him unfit for work from 28 February 2019 until 15 March 2019 by reason of
“ acute viral illness ” .
Emmett
AJA later observed,
“ The certificate made no reference to any incapacity to attend Court ” :
ACN 057 690
034 Pty Limited v
Wykrota
at [8] .
On this application,
Mr
Wykrota ’ s
solicitor accepted that the medical certificate was unsatisfactory. That concession was rightly made.
His Honour ’ s
A ssociate replied by email shortly afterwards,
I t should not be assumed that the hearing will not proceed.
The hearing
On
28 February 2019 ,
there was no appearance for Mr
Wykrota . Ms Cohen informed his Honour that it had come to her attention that an application for voluntary deregistration of
Arrowfab
had been filed on 1 July 2018 and the fee had been paid
on 27 February 2019
but,
“ in any event, the plaintiff is seeking a judgment against Mr
Wykrota
because that was the person he always dealt with. He received invoices from the second defendant but paid most of the money to the third defendant by way of progress payments ” .
The following exchange followed:
(emphasis added)
HIS HONOUR: Are you proceeding just against Mr
Wykrota
or against the second and third defendants, or what?
COHEN: Well, we're happy to proceed against Mr
Wykrota
rather than the second and third.
HIS HONOUR: Well, it's a matter for you.
COHEN: It's not disputed by the defendant that it was he that entered into the building contract.
HIS HONOUR: Well, I have the statement of claim, but first of all, what steps do I need to satisfy myself that Mr
Wykrota
was aware of the hearing today? …
Whilst Mr
Wykrota
was the
first
defendant, he was referred to in the transcript by both Ms Cohen and his Honour as simply “the defendant”.
Mr
Wykrota
relied heavily on the italicised portion as an assurance by the plaintiff ’ s counsel on the basis of which
Emmett AJA proceeded thereafter and was
misled .
T he plaintiff says there is nothing misleading about what Ms
Cohen informed
his
Honour given that no defence
had been filed
and , also,
Mr
Wykrota ’ s
remarks to the Court on 28 November 2018 and 13 December 2018 set out at [
36
] and [
40
].
Sometime was then spent by Emmett AJA and Ms Cohen
examining evidence of service of
the statement of claim , affidavits and schedule of damages
on Mr
Wykrota .
The affidavits of Mr Le and the expert
valuer
were
then
read. His Honour was
then
taken to the schedule of damages, which totalled $260,296.85.
It is clear from the transcript that his Honour proceeded to check each of the evidentiary references in the schedule to see whether the head of damage claimed was supported by
the
evidence.
His Honour was not prepared to allow Item 10, which sought an estimated amount of $15,000 for opportunity costs for loss of time taken in 2018 to obtain outstanding certificates and other requirements necessary to obtain the issue of an occupation certificate. His Honour also queried Items 13
and
16
(building inspection report in 2014 and un b locking toilets due to defective work) .
Particular difficulties were encountered with Item 20
–
lost rent
–
as
Emmett AJA
was concerned whether there was evidence to support the claim. His Honour observed:
HIS HONOUR: I mean, the fact that Mr
Wykrota
hasn't chosen to come is one thing, but if I proceed in his absence and make a judgment, he's entitled to come and ask for the judgment to be set aside.
COHEN: Yes.
HIS HONOUR: But whether it would be is a different matter, but it seems to me it would be in everybody's interest, if there is proper evidence of these things, for me to be able to do that, rather than have Mr
Wykrota
come back next week or some other time and say, "I now want to have another go, and there was no real evidence to support these claims".
COHEN: Yes.
HIS HONOUR: It's in the plaintiff's interest to make sure we can tie it up, if we can.
After his Honour raised a number of evidentiary and legal issues in respect of the claim for lost rent , Ms Cohen
asked
Emmett AJA
to stand the matter down
to enable her to consider the evidentiary and legal problems
raised .
His
Honour
adjourned
the hearing until
2.15 pm
to
enable
counsel to do so .
At 2.15 pm,
Ms Cohen made further submissions in respect of the evidence and applicable legislation
in respect of the claim for lost rent .
Ms Cohen advised that she was trying to get an affidavit from a real estate agent to address concerns expressed by Emmett AJA
as to the demand for rental properties at the time.
His Honour
observed
that the claim for lost rent
appeared to be
in the nature of
a loss of opportunity case but ,
unless the plaintiff could show that there was actually a tenant who would have been able to move
in , the claim
would
need to be
discount ed by
some 25% to 30%.
The transcript records:
HIS HONOUR: That's why it seems to me I have to put a very substantial discount on it unless you want
-
as I say, I'm not inviting you to adjourn the matter.
COHEN: Yes, I'll get some instructions.
…
COHEN: My client's happy for you to put a discount on it on that basis.
It
then
became apparent that the figure claimed in the schedule of damages for lost rent was incorrect and should have been $339,992.52, not $171, 375 . His Honour noted that the highe r
figure had not been provided to Mr
Wykrota .
HIS HONOUR: … One course that I could adopt would be to say, well, that clearly represents a discount, and therefore, that's an appropriate figure to give you.
COHEN: That's a very big discount.
HIS HONOUR: It is.
COHEN: Obviously.
A search was then made of the transcript of the directions hearing on 28 November 2018
to see
whether Ms Cohen had informed the Court, and thus Mr
Wykrota ,
on that occasion
that the damages claimed exceeded the amount
subsequently particularised
in the schedule of damages. In the absence of
a ny
clear communication of the quantum sought on that occasion, the following exchange followed:
HIS HONOUR: On that basis I'd find it difficult to
…
go beyond the figure that's served.
COHEN: I'll just get some instructions.
HIS HONOUR: Yes.
COHEN: My client's prepared to accept that.
The judgment
His Honour then delivered an
ex tempore
judgment.
His Honour
observed
at [1]:
The plaintiff seeks damages from the first defendant, Mr Mick
Wykrota, alleging that Mr Wykrota
committed breaches of a building contract entered into between the plaintiff and Mr
Wykrota. There are two other defendants, each of which is a limited liability company associated with Mr Wykrota. However, the plaintiff does not seek to proceed further against the second and third defendants.
That is, Emmett AJA did not ignore the fact that the plaintiff had pleaded a cause of action against each of the defendants, but noted
that the plaintiff had
chosen to press only its primary
claim
against Mr
Wykrota.
His Honour ’ s judgment then addressed the question of service
and
Mr
Wykrota ’ s
knowledge that the matter was listed for hearing today , concluding
at [9]:
…It is clear that Mr Wykrota
was aware of the hearing fixed for today but has elected not to attend. In the circumstances, I consider that it is appropriate to proceed with the hearing in his absence. He will no doubt have a right under the rules to apply to have any order set aside that was made in his absence. That will be a matter for him if he is so advised. If he wishes to have any order that I make set aside, he will be required to indicate precisely why he was not in attendance today when the matter was called on for hearing.
His Honour then
reproduced
the
pertinent paragraphs of
the statement of claim and noted that no defence had been filed. At [11]:
…It follows in effect that the allegations made in the statement of claim are admitted. Nevertheless, having regard to the amounts claimed and the absence of Mr Wykrota , I have given some attention to the quantum of the plaintiff's claim for damages.
In respect of the claim for damages, Emmett AJA
was ,
“ satisfied from that evidence that the expenses referred to in the Schedule of Damages have in fact been incurred by the plaintiff as a consequence of breach of the building contract by Mr
Wykrota ”
:
at [12]
.
Nonetheless, h is Honour disallowed Items 10, 13 and 16. As to Item 20 , Emmett AJA
set out the difficulties with th e
claim
for lost rent , including that Mr
Wykrota
was informed that the claim was for $171, 375 ,
“ and has had no forewarning that the claim would be for $339, 994 ” . His Honour considered that th e
head of damage should be assess ed on the basis of
a
loss of opportunity and, given that the amount claimed in the schedule of damages was
“ certainly a substantial discount from the full amount of the claim, I consider that that is an appropriate measure of the loss of opportunity in the present circumstances ” : at [18].
Further, his Honour was satisfied that Mr
Wykrota
had breached his obligation to produce an occupation certificate and that there was a causal connection between that breach and the los t
opportunity to let the premises: at [20].
Thus, his Honour was prepared to enter judgment against Mr
Wykrota
in the amounts claimed in the schedule of damages sa ve
for Items 10, 13 and 16.
The transcript
then
records the following exchange:
HIS HONOUR: Now, what about the other defendants, Ms Cohen?
COHEN: They've never appeared. One doesn't exist.
HIS HONOUR: Do you want [to] proceed, or should I simply otherwise dismiss the proceedings?
COHEN: Otherwise dismiss the proceedings.
His Honour completed his
ex tempore
judgment accordingly, at [22]. Ms Cohen then sought to rely on a further affidavit
(which I apprehend was the affidavit awaited from the real estate agent) , but his Honour was not prepared to have regard to the further affidavit as it had
not
been served on Mr
Wykrota .
Final
orders
were thus
made
as follows :
1.
I direct the entry of judgment for the sum of $244,896.85 against Mr
Wykrota.
2.
I order Mr
Wykrota
to pay the plaintiff's costs in the proceedings.
3.
I order that the proceedings be dismissed as against the second and third defendants.
The second defendant has been deregistered. According to the records of the Australian Securities
and
Investments Commission,
the de-registration
took effect on 12 December 2018.
Explanation for absence
and delay
Mr
Wykrota
says that, although he was aware of the hearing before Emmett AJA, he did not appear as he had shingles and was in great pain.
Further,
Mr
Wykrota
said that since about November 2014, he had been involved in a dispute with a former joint venture partner in relation to a property
development
at Wh eeler Heights. In 2017, proceedings were commenced by purchasers of
L ot
3
in
the
proposed sub-division
against his joint venture partner and
Mr
Wykrota
was joined as a cross-defendant.
In addition, s ince 2017 ,
Mr
Wykrota
had been involved in various proceedings concerning the Polish Club . O ne of those proceedings was heard at the Court on
29 to 31 January 2019, 1, 6, 22 and 26 to 28 February 2019,
thus overlapping with the hearing in this matter on 28 February 2019.
In addition, Mr
Wykrota
says that the effect of
“ all of this litigation ”
had taken a toll on his mental and physical health and he had not been able to properly focus on any one thing and was being treated for depression. It is not clear whether
Mr
Wykrota
was
affected
by depression
at the time of the hearing before Emmett AJA or
subsequently .
In addition,
Mr
Wykrota
sa id ,
“ I did not find out about the judgment made against me
…
until June or July 2019
… ” .
Enforcement action
On
9 July 2019, the plaintiff sought to enforce the judgment by filing a motion seeking the issue of a writ for the levy of property against Mr
Wykrota . A writ was issued by the Court on 10 July 2019.
The writ was recorded against properties owned by Mr
Wykrota
in Dural, North Narrabeen and Wheeler Heights.
Efforts to record the writ on
a
property in Willoughby failed due to other caveats lodged on title.
On 10 July 2019, the Office of the Sheriff of NSW sent a letter to Mr
Wykrota
advising of pending enforcement action on the judgment.
At the time that the writ was issued, Mr
Wykrota
had already exchanged contracts to sell Lot 3 in the Wheeler Heights subdivision . The
purchasers had lodged a caveat on title in respect of their interest under the contract of sale. On 18 July 2019, Mr
Wykrota
consented to an order for specific performance of th e
contract:
Day v
Sternhell
[2020]
NSWSC
513 at [7].
On 23 August 2019, Sheriff
O fficers attended at Mr
Wykrota ’ s
address. The Sheriff later reported in a Notice of Non-Levy:
Sheriff’s officers attended the given address and made enquiries with the occupant who identified himself as “Matt”
and was very evasive. Officers were then able to identify the occupant as the judgement debtor.
The judgement debtor argued with officers that there is a dispute with regard to the debt. …
While
in attendance, Office rs made an assessment and concluded that it would be unlikely that a seizure of the available goods and chattels would justify their removal, storage and sale in order to satisfy the judgement debt.
The
Office of the Sheriff of NSW issued a Notice of Non-Levy.
On 19 December 2019, a notice of appointment of solicitor was filed on behalf of Mr
Wykrota
in these proceedings. Mr
Wykrota
says that he had instructed
a
solicitor to apply to set aside the judgment but was unable to place the solicitor in funds
as
he was awaiting completion of sale of Lot 3 of the Wheeler Heights property.
On 20 December 2019, a lapsing notice
was served
on the purchasers of Lot 3
at the request of the plaintiff.
The purchasers
file d
a motion on 23 December 2019 seeking an order to extend
the caveat , which
was extended by consent :
Day v
Sternhell
at
[16] .
On 13 January 2020, Mr
Wykrota ’ s
solicitor
contacted the plaintiff ’ s solicitor,
request ing
the urgent removal of the plaintiff ’ s application to record a writ
over the Wheeler Heights property
so that
sale of
Lot 3 could be completed .
On 11 February 2020, Mr
Wykrota ’ s
solicitor enquired of the plaintiff ’ s solicitor ,
“ C ould you please tell me what you believe your client is owed pursuant to the Judg e ment
[sic] , calculated to date? ” .
This information was duly provided.
In addition to the judgment debt and post-judgment interest, the plaintiff sought payment of its costs of the proceedings together with legal costs incurred in seeking to enforce the judgment which,
together with the judgment and interest , amounted to some $346,000. The plaintiff ’ s solicitor sought payment in full from the proceeds of sale although, if the costs were not accepted,
noted
that
the
plaintiff ’ s
costs could be submitted for assessment.
On 6 March 2020, consent orders were made in respect of the Wheeler Heights property to withdraw caveats and writs in order to permit registrat ion of a plan of sub division for the property. On 10 March 2020, sale of Lot 3 was completed . The
net proceeds of sale
were
paid to the registered mortgagee.
Thus, Mr
Wykrota
says he
did not receive funds from which to pay his solicitor to apply to set aside the judgment.
The plaintiff lodge d
a writ over the remaining two lots in the Wheeler Heights property.
Mr
Wykrota
also
says that ,
shortly after the completion of the sale
of Lot 3,
the
COVID -19 pandemic hit, although it is not
clear
how
this
affected his ability to bring an application to set aside his Honour ’ s judgment.
On 30 April 2020, Mr
Wykrota
exchanged contracts to sell Lot 1 in the Wheeler Heights sub-division for $2.1 million . The registered mortgage e was
owed some $1.35 million, which Mr
Wykrota
intended to pay from the
proceeds of sale.
Thus, Mr
Wykrota
could expect to receive some $750,000 on completion of the sale of this property.
Mr
Wykrota
says that in June and July 2020 he was involved in other proceedings in this Court.
On 22 June 2020, Mr
Wykrota ’ s
current
solicitors sent a letter to the plaintiff advising that they intended to bring this application and, on 30 June 2020 wrote again proposing to pay $250,000 from settlement of the sale of Lot 1 into court pending the resolution of these proceedings.
Obviously, without reaching some agreement with the plaintiff such that the plaintiff withdrew the writ, Mr
Wykrota
would not be able to complete the sale of the property.
On 3 July 2020, a bankruptcy notice was issued to Mr
Wykrota
on the application of the plaintiff, claiming $268,382.41, being the amount of the judgment debt together wi th
interest under section 101 of the
Civil Procedure Act 2005
(NSW). On 9 July 2020, Mr
Wykrota ’ s
solicitors proposed to deposit $270,000 into Court if the writ lodged by the plaintiff over Lot 1 was removed pending determination of the motion to have
the
judgment set aside. The plaintiff did not consent to this course.
On 4 August 2020, the motion to set aside the judgment was filed.
On 6 August 2020,
on
the undertaking of Mr
Wykrota
to pay $270,000 from the proceeds of sale of Lot 1 into Court ,
Kunc J
removed the writ of execution over the property. The sale of Lot 1 was completed on 11 September 2020 and the money paid into Court.
Was judgment irregularly
obtained ?
Mr
Wykrota
contends that the judgment was given
“ irregularly ”
as deemed admissions arising from failure to file a defence did not support the judgment, relying on
Fenato
v
Chief
Commissioner of
State
Revenue
(2010) 78 NSWLR 20; [2010] NSWCA 80 where the statement of claim failed to plead a material fact that was a condition precedent to the orders made.
Mr
Wykrota
submitted that the plaintiff ’ s
claim
as pleaded was
obscurely and confusingly formulated , in particular, in identifying the contracting parties and their obligations.
Given the problems with the pleading, the admissions which
resulted from Mr
Wykrota ’ s
failure to file a defence
were
said
not
to
support the judgment and orders.
The plaintiff ’ s counsel ’ s statement that,
“
It
’s
not disputed by the defendant that it was he who entered into the building contract
” , was not justified in the circumstances and t he Court was
thereby
misled . It was submitted that the
Court was entitled to greater frankness from the
p laintiff in the course of an
ex parte
hearing .
It was submitted that the judge was, in effect, side tracked, misled or distracted by an assumption, inaccurately made, that there was no question
“ because when it said there was no issue that is really telling the Judge it is agreed in some way ” .
It was submitted that Emmett AJA did not, in his judgment, consider or evaluate the question of the identity of the contracting parties but treated the allegations in the statement of claim as admitted in the absence of a defence.
Further, the Court was asked to award damages but the statement of claim did not plead any case of defective work under the building contract. The statement of claim did not refer to the unsigned building contract (described at [
14
]) including
the warranties in clause 1.A.24 or the obligation to rectify defects in clause 1.A.25.
The allegations of breach were said to be broad and meaningless, alleging not facts but an unvarnished conclusion of law. Thus, it was submitted that any admissions which flowed from a failure to file a defence were of limited significance.
Further,
by allowing parts of the damages claim outside the parameters of the pleading,
the plaintiff submitted that Emmett AJA
failed to afford procedural fairness to Mr
Wykrota ,
being a fundamental irregularity entitling the person aggrieved to have the judgment set aside:
Miltonbrook
Pty Limited
v Westbury Holdings Kiama
Pty Limited
(2008) 71 NSWLR 262;
[2008] NSWCA 38 at [85]. It was said that damages were awarded without his Honour having it drawn to his attention that there was nothing in the statement of claim to support such a claim.
His Honour
gave damages for
items in
the
s chedule
of damages
which were unrelated to the
pleaded
terms of the contract.
Such
damages ought not to have been awarded and the judgment was
said to be
irretrievably infected by th is
error,
said to have been
induced by the
p laintiff ’ s conduct
at
the
ex parte
hearing.
This alone
was said to
entitle and
require
the
Court to set aside the judgment.
I t was submitted that the
damages
" cannot now become supportable or legitimised by an
ex post facto
attempt to re-assign them as costs of obtaining an Occupation Certificate ” .
Further, Mr
Wykrota
contend ed
that the judgment was given
“ against good faith ”
by reason of a failure by the plaintiff ’ s counsel to specifically draw his Honour ’ s attention to documents or portions of Mr Le ’ s affidavit which may support a conclusion that the building contract was not with Mr
Wykrota
but another defendant.
Although Mr Le ’ s affidavit
was read , it was said to be
“ not enough ”
that his Honour was not taken to the passage set out at [
32
] by the plaintiff ’ s counsel.
The fact that the plaintiff ’ s counsel did not
specifically
take his Honour to the email
set out at [
13
] ,
nor the application filed in NCAT ,
nor point out the ambiguous nature of the quotation or the admission which might be thought to arise from commencing the
NCAT
proceedings against
Arrowcon
Construction ,
was said to have had the result of misleading Emmett AJA as these documents indicated that there
was
an issue in respect of the identity of the defendant with whom the plaintiff had a contract.
Whilst
Mr
Wykrota ’ s
solicitor accepted that Emmett AJA would have read the whole of the affidavit in any event, it was said to be wrong to conclude that his Honour ignored the assurance given by Ms Cohen that there was no issue in the case about the identity of the contracting parties.
The plaintiff submitted that the judgment was not given against good faith. Counsel ’ s statement that
“
It’s not disputed by the defendant that it was he who entered into the building contract
”
was accurate: the defendants had not filed a defence. Emmett AJA recognised as much in
his Honour ’ s j udgment .
Further, although Mr
Wykrota
indicated during the directions hearings on 28 November 2018 and 13 December 2018 that he may defend himself, he never suggested that he was not a party to the contract.
The plaintiff submitted that the
pleadings were broad enough to encompass the damages awarded, including damages for building work not properly performed.
The statement of claim pleaded that there was a contract between the plaintiff and Mr
Wykrota
whereby Mr
Wykrota
would carry out
building work; Mr
Wykrota
failed to perform the contract and the plaintiff suffered damage as a result.
The essential elements of a cause of action for breach of contract were pleaded. The particular damages suffered were set out in the
s chedule of
d amages. The damages awarded by Emmett AJA were based squarely on Mr
Wykrota ’ s
breach of contract and the loss particularised in the
s chedule, which had been provided to Mr
Wykrota
before the hearing.
Nor
could
there said to be any procedural unfairness.
Conclusion
Having in mind the principles described at [
3
]-[
7
], the question is whether the judgment of Emmett AJA was procured by the
plaintiff ’ s
misconduct or dishonourable conduct and the suggested irregularity is not inconsequential or causally unrelated to the making of the judgment and orders. Mr
Wykrota
relie d
on matters of pleading and evidence ,
combined with the
contention
that the plaintiff ’ s counsel breached her duty of candour. I note, of course, that the hearing before Emmett AJA was not an
ex parte
hearing in the sense that Mr
Wykrota
was not informed of the hearing but rather that Mr
Wykrota , having been informed, did not attend.
While the duty of candour applies with especial stringency to
ex parte
applications, its scope extends to any application, contested or not, where evidence is presented to the court in support of an application:
Kavia
Holdings Pty Ltd v
Werncog
Pty Ltd
[1999]
NSWSC
839 per
Santow
J at [1].
Turning to the pleading point,
b y failing to file a defence, Mr
Wykrota
was deemed to have admitted the allegations made against him in the statement of claim, which included the primary allegation that the building contract was with him; that he was obliged to supply certificates and documents to the certifier to enable an occupation certificate to issue; and that he failed to do so. The fact that the plaintiff also contended that the second and third defendants had obligations which they failed to perform did not detract from the fact that Mr
Wykrota
admitted that he had failed to perform an obligation which he owed.
T he fact that, after being informed by Ms Cohen that it was
“ not disputed ”
that Mr
Wykrota
entered into the building contract, Emmett AJA replied,
“ Well, I have the statement of claim
…”
indicates an appreciation by his Honour that Ms Cohen ’ s assertion was referable to the failure to file a defence, but also an indication that his Honour had the pleading against which to check whether Mr
Wykrota
could be taken to have
made
such an admission. This is confirmed by the
ex tempore
judgment,
in which Emmett AJA
reproduced the relevant paragraphs of the statement of claim, noting that no defence had been filed.
Importantly, his Honour summarised not only the paragraph of the statement of claim setting out the plaintiff ’ s primary case against Mr
Wykrota
but other portions of the statement of claim which referred to the second and third defendants,
“ the defendants ”
and
“ the defendant ” . The plaintiff ’ s claim, in all its forms, did not escape Emmett AJA ’ s notice.
His Honour
then
observed,
“ I t follows in effect that the allegations made in the statement of claim are admitted ” : at [11].
It is thus clear that, whatever assurance was made by the plaintiff ’ s counsel in the opening moments of the hearing, Emmett AJA carefully checked what admissions had in fact been made by reason of Mr
Wykrota ’ s
failure to file a defence and whether the admissions were sufficient to support judgment against him for breach of the building contract.
Further, having reviewed the 26 pages of transcript of the hearing, one thing is clear: whatever the plaintiff ’ s counsel submitted to Emmett AJA, his Honour was in no way misled. Emmett AJA carefully checked each and every proposition put
inter alia
because Mr
Wykrota
had not appeared.
As to the damages claim ,
it was not incumbent on the plaintiff to plead that the building contract comprised the unsigned document prepared by Mr
Wykrota . That was not the plaintiff ’ s case. In circumstances where there was no evidence on this application that the unsigned document had been provided to the plaintiff, it was not incumbent on the plaintiff ’ s counsel to draw his Honour ’ s attention to the possibility that, if the matter was defended, then Mr
Wykrota
might rely on
such a
document.
Nor
is there any substance to the contention that the plaintiff ’ s counsel failed to draw to his Honour ’ s attention
to
the fact
that the damages sought at trial fell outside the particulars in the statement of claim. That subject had been canvassed at length, in the presence of Mr
Wykrota , at the pre-trial directions hearings on 28 November 2018 and 13 December 2018, with orders made, and complied with, for the preparation and service of
a
schedule of damages.
As described at [
49
]-[
53
], Emmett
AJA
did not enter judgment simply on the basis of Mr
Wykrota ’ s
admission that, by reason of his failure to perform his obligations under the building contract, the plaintiff had suffered damage. His Honour was careful to ensure that each item of damage of which notice had been given to Mr
Wykrota
was established by the evidence on which the plaintiff relied. Given his Honour ’ s finding that the items in the schedule of damages
“ have in fact been incurred by the plaintiff as a consequence of breach of the building contract by Mr
Wykrota ” , the plaintiff ’ s submission that the damages were unrelated to the pleaded terms of the contract cannot succeed. As the plaintiff submitted, the fact that some of the items claimed in the schedule of damages might relate to rectification of defective building work does not assist Mr
Wykrota
as, s elf-evidently ,
rectification work
may
have been required to obtain an
o ccupation
c ertificate.
This was a question of fact to be determined on the evidence , as it was .
To the extent that Mr
Wykrota
relied on any failure by Emmett AJA to afford procedural fairness,
any
such failure does not assist Mr
Wykrota
as, on an application to set aside a judgment,
the Court is concerned
with whether
the
judgment creditor
was responsible for bringing about the judgment
by
engag ing
in misconduct or dishonourable conduct:
Zakaria
v Dr
Noyce
at [22]. In any event, I accept the plaintiff ’ s submissions on this subject.
Emmett AJA was explicitly mindful to ensure that Mr
Wykrota
had forewarning of the damages sought. Emmett AJA held the plaintiff to the quantum sought in the schedule of damages in relation to lost rent, even though that figure understated the correct amount of the plaintiff ’ s claim, as Mr
Wykrota
had only been informed of the lower claim set out in the schedule and had no forewarning of the higher amount. Mr
Wykrota
knew precisely
the
case
against him . He had the opportunity to
file
a defence,
serve
evidence refuting
the plaintiff ’ s claim and appear at the hearing .
H e chose not to.
T he consequences of this choice were not the product of any denial of procedural fairness.
As to the suggested lack of candour of the plaintiff ’ s counsel in respect of the evidence relied upon by the plaintiff, the plaintiff ’ s counsel read the affidavit of Mr Le which, in the body of the affidavit and in the annexed documents, contained the email described at [
13
], Mr Le ’ s description of his
pre-contractual
dealings with Mr
Wykrota
set out
[
32
], the fact that proceedings were initially commenced in
NCAT
against
Arrowcon
Constructions and the orders made by NCAT set out [
16
]. Where Mr
Wykrota
had, effectively, admitted that he was liable to the plaintiff for failure to perform the building contract, it was not strictly necessary for the plaintiff ’ s counsel to read these portions of Mr Le ’ s affidavit, nor tender the exhibited documents, at all.
The affidavit evidence, quotation and NCAT orders did not have
such adverse
connotations for the plaintiff ’ s primary claim against Mr
Wykrota
that failure to specifically bring this material to his Honour ’ s attention
misled the Court or
had the result that judgment was entered on the basis of facts which
were
false or on the basis of a misapprehension: G E Dal Pont,
Lawyers’ Professional Responsibility
(6 th
ed,
2017,
Law Book Company) at [17.95].
There was no misconduct or dishonourable conduct on the part of the plaintiff in proceeding in the manner in which
it
did. Thus, I conclude that the judgment and orders of Emmett AJA were not given or entered irregularly or against good faith.
Should judgment otherwise be set aside?
Alternatively, Mr
Wykrota
submitted that an order should be made under rule 36.16
UCPR
in circumstances where he has a defence on the merits. There was an explanation for his failure to attend the hearing as he was ill, unrepresented and caught up in other litigation at the time. The delay in moving the Court for an order setting aside the judgement of 28 February 2019 was significant, but not decisive. It was submitted that Mr
Wykrota
learned of the entry of judgment against him in June or July 2019. He had since
been heavily preoccupied with other litigation
and
also suffered health and financial difficulties .
The plaintiff submitted that
the discretion to set aside
the judgment
under
rule
36.16(2 )( b)
UCPR
should not be exercised in this case .
Great value attaches to certainty in the outcome of litigation and the more egregious the delay in seeking to set aside an undefended judgment, the greater the burden of persuasion of the strength of its case that will be required:
Northey
v Bega Valley Shire Council
at [16] per Barrett JA;
Pham v Gall
at [110] per
Payne
JA.
The procedural background readily suggested that Mr
Wykrota
took the view that engagement with the proceedings was optional. He did not file or serve any documents in the proceedings apart from a Notice of Appearance. He attended some, but not all, of the numerous direction hearings. Nevertheless, he was kept informed of the progress of the case and the orders made by the Court.
Mr
Wykrota ’ s
explanation for his failure to attend the hearing before Emmett AJA was said to be inadequate. Mr
Wykrota ’ s
explanation for his delay in seeking to set aside the judgment was also said to be unconvincing, being an important and potentially decisive factor:
Pham
v Gall
at [57], [144] .
Mr
Wykrota ’ s
asserted health and financial difficulties did not stand in the way of him participating in proceedings against a former joint venture partner, being involved in
“
various proceedings
”
concerning the Polish Club (two of which were heard in the Supreme Court between January and March 2019) and another unspecified proceeding in the Supreme Court.
The plaintiff submitted that a
factor to be taken into account was whether the proposed defence was strong:
Magnate Projects
v
Youma
Constructions (No 2
)
at
[52] per Hodgson JA;
Pham
v Gall
at [98].
Identification of the parties to
a
contract must be made in accordance with the objective theory of contract , including considering post-contractual conduct:
Pethybridge
v
Stedikas
Holdings Pty Ltd
[2007] NSWCA 154 at [54];
BH Australia Constructions Pty Ltd v
Kapeller
(2019) 100
NSWLR
367;
(2019) 375 ALR 159;
[2019] NSWSC 1086
at [91] per Leeming JA .
It was submitted that there was persuasive evidence that the contract was between the plaintiff and Mr
Wykrota .
Mr Le gave evidence that in about September 2010, the plaintiff and Mr
Wykrota
agreed that Mr
Wykrota
would carry out the contract. When Mr
Wykrota
was introduced to Mr Le, he appears to have been introduced in his personal capacity; there was no evidence that he was introduced as an agent of
Arrowfab . Mr Le also reported that Mr
Wykrota
told him,
“
My
company
Arrowfab
will be doing the building work for me
” . The implication of this statement was said to be that, although Mr
Wykrota
was the contracting party,
Arrowfab
would be doing the building work on his behalf.
The email set out at [
13
]
was sent
from an email address that was plainly a personal address. Although Mr
Wykrota ’ s
email contained the words
“ Arrowfab
Pty Limited ”
under his name, there was no evidence that Mr
Wykrota
had explained anything about this company to Mr Le.
Mr
Wykrota
unilaterally determined the corporate entity to which the plaintiff ’ s payment was to be directed at any point in time. Mr
Wykrota ’ s
directions came from his personal email address. Mr
Wykrota
unilaterally determined which corporate entity would undertake the contract work at any point in time. Such conduct was said to be consistent with Mr
Wykrota
being the contracting party rather than the corporate defendants. He alone determined how the works would be performed and did so in his personal capacity.
Contrary to the pleading in the proposed defence, the plaintiff submitted that there was no evidence that the parties agreed that
Arrowcon
Construction would take over the contract from
Arrowfab . A reasonable observer considering the matter objectively would not come to such a conclusion in circumstances where there is no evidence Mr Le knew anything about
Arrowcon
Construction, much less that it was properly licensed and insured and therefore a suitable contracting party for building work. The fact that, long
after the event, the plaintiff commenced
NCAT
proceedings naming
Arrowcon
Construction as defendant was said to add little to the question of who the contracting parties were. It was submitted that Mr
Wykrota
would face serious difficulties in making out the proposed defence. Whilst the case was not unarguable, it did not satisfy the greater degree of persuasion required from Mr
Wykrota
in the circumstances.
The plaintiff submitted that it would be p rejudice d if the judgment was set aside, in the form of
the costs incurred
in obtaining the judgment in the first place, together with the costs of seeking to enforce the judgment during which time
Mr
Wykrota
stood by in a manner inconsistent with his currently stated intention to contest the proceedings.
P rejudice naturally arose from the passage of time. The contract was formed in November 2010 and breached in 2012. The memory of the relevant witnesses was naturally receding, as was the plaintiff ’ s ability to locate any further relevant documents.
Further,
the plaintiff submitted that
t he proposed
d efence denie d
that Mr
Wykrota
was a party to the
c ontract and plead ed
that the
s tatement of
c laim
did
not disclose a cause of action against him.
If
that
d efence had been file d on or before 2 May 2018, the p laintiff could have met it by simply amending its
s tatement of
c laim to plead, in the alternative, that
Arrowcon
Construction
was a party to
–
and liable for the breach of
–
the contract.
That course
was
no longer available to the
p laintiff
as
the proceedings against
Arrowfab
and
Arrowcon
Construction
were dismissed : section 91(2) of the
Civil Procedure Act
. Dismissal of the proceedings against
Arrowfab
and
Arrowcon
Construction
was said to be an
entirely reasonable course considering the
c ontract was found to have been with Mr
Wykrota
and judgment had been given against him.
Mr
Wykrota
accepted that the dismissal of the proceedings against
Arrowcon
Construction should also be set aside by consent, although it was not entirely clear how this could be done in circumstances where
Arrowcon
Construction was
not a party to
the motion. Mr
Wykrota ’ s
solicitor informed the Court that he was instructed on behalf of
Arrowcon
Construction to consent to
such an order .
After the hearing of this application, Mr
Wykrota ’ s
solicitors filed a Notice of Appearance for
Arrowcon
Construction .
Finally, the plaintiff submitted that w hilst ,
if
the judgment
was
not set aside, Mr
Wykrota
would remain obliged to satisfy a judgment which he now says should not have been entered against him, this outcome was less prejudicial than it appeared. Mr
Wykrota ’ s
proposed defence
was
that
Arrowcon
Construction
was
liable for any breach of the contract. As
Mr
Wykrota
is the sole director and shareholder of
Arrowcon
Construction, in the event he succeed ed
in his proposed defence and judgment
was
entered against that company, that loss would ultimately
be
suffered by him as the company ’ s sole shareholder. Thus, at a practical level, he would not avoid the consequence of any breach of that contract, relying on
Leichhardt Council v
Geitonia
Pty Ltd (No 7)
[2015] NSW L EC 79 at [51] by analogy.
Consideration
As will be apparent from the recitation of the procedural history at [
23
], [
24
], [
29
], [
35
], [
45
] , Mr
Wykrota ’ s
participation in the proceedings
was
intermittent .
His
evidence as to how the proceedings unfolded, and his knowledge of the proceedings,
was not
consistent with contemporaneous documents. I am satisfied that he became aware of the proceedings shortly after they were commenced and was regularly informed, both by the plaintiff ’ s solicitor and, on occasion, by the Court ,
over the course of
a
dozen directions hearing s , as to its progress towards a final hearing.
His engagement with the proceedings was, however, selective.
Mr
Wykrota
was involved in several pieces of litigation at the time and had solicitors, although not in these proceedings. Mr
Wykrota
was ,
however,
able to, and did, consult his solicitor in relation to these proceedings. Mr
Wykrota
was able to appear in person, and did on occasion. He appears to have been an experienced litigant who deployed his legal resources where he saw fit.
W hen Mr
Wykrota
appeared before
Emmett AJA in November and December 2018 ,
it was apparent
that his focus was to postpone the final hearing.
It is also apparent that, when Mr
Wykrota ’ s
efforts to postpone the
hearing
proved futile, he chose not to appear.
Mr
Wykrota ’ s
explanation for his failure to attend the hearing before Emmett AJA was inadequate.
Mr
Wykrota ’ s
medical certificate referr ed
to his unfitness for work, rather than any inability to attend Court. The medical certificate provided no explanation for Mr
Wykrota ’ s
failure to have filed a defence, adduce evidence or make any attempt to arrange for someone else
to
appear on his behalf at the hearing, as he indicated at earlier directions
hearings that he would.
Accepting that Mr
Wykrota
was involved in other pieces of litigation, some of which were being heard at the same time as the se
proceedings, t here is obviously a tension between Mr
Wykrota
suggesting that he was unwell and thus unable to attend the hearing before Emmett AJA, on the one hand, and suggesting that he could not attend the hearing because he was busy participating in other legal proceedings, which he was presumably well enough to attend at the same time.
Mr
Wykrota ’ s
explanation for his delay in seeking to set aside
the judgment was also problematic. The suggestion that Mr
Wykrota
did not find out about the judgment until June or July 2019 is
inconsistent with the contemporaneous documents and thus unlikely .
On 6 March 2019, the
A ssociate to Emmett AJA sent a copy of the
ex tempore
judgment by email to the parties, including to Mr
Wykrota
at the email address referred to at [
13
]. Further, on 13 March 2019, the plaintiff ’ s solicitor sent a letter to Mr
Wykrota
by Express Post informing him of the orders made by his Honour. According to the records of Australia Post, the letter was delivered on 14 March 2019.
E ven if Mr
Wykrota
was
previously
unaware of
his
ability
to seek to have the judgment set aside , Emmett AJA ’ s judgment
expressly
informed him of that
right .
The suggestion that ,
having filed a notice of appointment of solicitor in these proceedings in December 2019, Mr
Wykrota
was not able to place his solicitor in funds to apply to set aside the judgment
is not consistent with the fact that, over the next few months, Mr
Wykrota ’ s
new solicitor
did
take steps on his behalf ,
described at [
69
] and following , albeit did not take any steps in these proceedings.
As the plaintiff submitted, Mr
Wykrota
gave no evidence of his financial position apart from making bare assertions. His conduct as
described in his affidavit told against his inability to fund an application to set aside the judgment.
I consider that realising Lot 1, and a
wish to preserve the
net
proc e eds of sale ,
is a more
likely
explanation for why Mr
Wykrota
has delayed acting until now.
Turnin g to the hardship to the plaintiff, and what is proffered to reduce that hardship (
Pham
v Gall
per Leeming JA at [57]), three items stand out. First,
Arrowfab
is now deregistered. It is not entirely clear
when
Arrowfab
was deregistered, although it appears to have been at or about the time of the hearing before Emmett AJA.
Having obtained judgment and orders against Mr
Wykrota , the
proceedings against
Arrowfab
were
dismissed. There was no suggestion by Mr
Wykrota
as to
whether, or how, this company should be reinstated.
If the judgment and orders are now to be un-done, it is unclear how this head of prejudice is to be ameliorated.
Second , as described at [
50
]-[
53
],
i n order to finalise the proceedings and its claims on 28 February 2019, the plaintiff accepted a substantial discount of $168,607.52, or 50%, of its claim for lost rent, being roughly double the discount which Emmett AJA had earlier indicated that he considered appropriate.
Mr
Wykrota
has paid into Court $270,000, representing the judgment and orders made by Emmett AJA together with interest. But that amount does not reflect the additional $168,000 which the plaintiff forewent . If Mr
Wykrota
had appeared at the hearing, the plaintiff could have pressed for the full amount of lost rent as the evidence on which it relied had been served on Mr
Wykrota . Even if His Honour had discounted the
claim by
25% to 30%, the plaintiff would likely have be awarded damages in a greater sum than that ordered in
Mr
Wykrota ’ s
absence .
Third, the plaintiff has costs
thrown
away, both in obtaining judgment from Emmett AJA and seeking to enforce his Honour ’ s orders which Mr
Wykrota
now seeks to set aside.
As best could be clarified during Mr
Wykrota ’ s
solicitor ’ s reply submissions, Mr
Wykrota
accepted that, in the event that the judgment was set aside, an order would properly be made that he pay the plaintiff ’ s costs thrown away, although Mr
Wykrota
did not accept that those
costs equated to the plaintiff ’ s costs
leading up to
obtaining judgment from Emmett
AJA , nor in any particular amount, but accepted such costs may be appropriate to be paid forthwith and, if the plaintiff put forward a suggested figure, then he would consider it. Mr
Wykrota
also
ultimately
accepted it may be appropriate to order that he pay the plaintiff ’ s costs of seeking to enforce his Honour ’ s judgment, but only as assessed.
Whilst during oral submissions, Mr
Wykrota ’ s
solicitor
said he could get some instructions about whether Mr
Wykrota
was able to give an undertaking to meet any costs orders made against the third defendant, in circumstances where there was no evidence as to whether the third defendant had any assets , no further
instructions
were
forthcoming .
Mr
Wykrota ’ s
willingness to redress any hardship which the plaintiff may suffer if his Honour ’ s judgment and orders
are
set aside was
reluctant and ungenerous , particularly having regard to the fact that, on sale of Lot 1, Mr
Wykrota
appears to have received a substantial sum, even after paying $270,000 into Court, accepting of course that Mr
Wykrota
may have other creditors.
As to whether Mr
Wykrota ’ s
defence suggests a clear case of merit, the proposed defence is arguable but
not
overwhelming. The defence faces a number of hurdles, not least of which is that Mr
Wykrota
contends that the building contract was with a company which did not exist at the time the contract was formed. The evidence on this application suggests a degree of informality and lack of attention to detail and proper paperwork, being a problem that
‘ cuts both ways ’
in terms of the plaintiff ’ s claim and the proposed defence.
Having regard to the principles set out at [
8
]-[
12
],
Mr
Wykrota
has not established that it is unjust to let the judgment and orders stand having regard to the circumstances in which the orders were made, the inadequate explanation
for
the subsequent 18 months ’
delay before bringing this application, the proposed defence and what is proffered to
re duce the prejudice to the judgment creditor. I decline to make the orders sought.
Orders
For these reasons, I
make the following orders:
D ismiss the first defendant ’ s motion filed on
4 August 2020 .
Order the first defendant to pay the plaintiff ’ s costs of the motion.
Grant liberty to the parties to apply on two days ’
notice to seek any variation of the costs order, or any further orders in respect of the monies paid into Court by the first defendant on 14 September 2020.
**********
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Decision last updated:
16 October 2020
Official source: https://www.caselaw.nsw.gov.au/decision/1752e59c78ae58483115aa8a