Subdivision (Fees) Interim Regulations 2011
Authorised by the Chief Parliamentary Counsel
Authorised Version
i
Subdivision (Fees) Interim Regulations 2011
S.R. No. 64/2011
TABLE OF PROVISIONS
Regulation Page
1 Objectives 1
2 Authorising provision 1
3 Commencement 1
4 Revocation 2
5 Definition 2
6 Fees for applications 2
7 Fee for engineering plan prepared by Council 2
8 Fee for supervision of works 2
9 Fee for checking engineering plans 3
10 Power to waive or rebate the payment of a fee 3
11 Expiry 3
═══════════════
ENDNOTES 4
-- 1 of 5 --
Authorised by the Chief Parliamentary Counsel
Authorised Version
1
STATUTORY RULES 2011
S.R. No. 64/2011
Subdivision Act 1988
Subdivision (Fees) Interim Regulations 2011
The Governor in Council makes the following Regulations:
Dated: 19 July 2011
Responsible Minister:
MATTHEW GUY
Minister for Planning
MATTHEW McBEATH
Clerk of the Executive Council
1 Objectives
The objectives of these Regulations are—
(a) to prescribe fees payable to Councils and
referral authorities under the Subdivision
Act 1988; and
(b) to empower Councils to waive or rebate the
payment of a fee payable under the
Subdivision Act 1988 in specified
circumstances.
2 Authorising provision
These Regulations are made under section 43 of
the Subdivision Act 1988.
3 Commencement
These Regulations come into operation on 24 July
2011.
-- 2 of 5 --
S.R. No. 64/2011
Subdivision (Fees) Interim Regulations 2011
2
Authorised by the Chief Parliamentary Counsel
4 Revocation
The Subdivision (Permit and Certification Fees)
Regulations 2000 1 are revoked.
5 Definition
In these Regulations, the Act means the
Subdivision Act 1988.
6 Fees for applications
(1) A person who applies to the Council for
certification of a plan of subdivision must pay a
fee of $100 plus $20 for each lot to be created by
the subdivision.
(2) A person who applies to the Council for
certification of a plan, other than a plan of
subdivision, must pay a fee of $100.
(3) A fee payable under this regulation must be paid
at the time at which the application is made.
7 Fee for engineering plan prepared by Council
If a Council prepares an engineering plan under
section 15(6) of the Act, the applicant must pay
the Council the prescribed fee being 3⋅5 per cent
of the estimated cost of constructing the works
proposed on the engineering plan.
8 Fee for supervision of works
If a Council or referral authority appoints a
person to supervise construction of works under
section 17(2)(b) of the Act, the applicant must pay
to the Council or referral authority (as the case
may be) a prescribed fee being 2⋅5 per cent of the
estimated cost of constructing the works.
r. 4
-- 3 of 5 --
S.R. No. 64/2011
Subdivision (Fees) Interim Regulations 2011
3
Authorised by the Chief Parliamentary Counsel
9 Fee for checking engineering plans
(1) A Council may fix a fee for considering an
engineering plan submitted under section 15 of the
Act.
(2) The maximum fee that may be fixed by a Council
under subregulation (1) is 0·75 per cent of the
estimated cost of constructing the works proposed
on the engineering plan.
(3) An applicant who submits an engineering plan to
a Council under section 15 of the Act must pay
the Council the fee (if any) fixed by the Council
under subregulation (1).
(4) A fee payable under subregulation (3) must be
paid at the time at which the engineering plan is
submitted.
10 Power to waive or rebate the payment of a fee
A Council may waive or rebate the payment of all
or part of any fee payable under the Act if—
(a) an application under the Act is withdrawn
and a new application is submitted; or
(b) in the opinion of the Council the payment of
the prescribed fee is not warranted because
of the minor nature of the consideration of
the matter to be decided; or
(c) in the opinion of the Council the requested
service imposes on the Council no
appreciable burden or a lesser burden than
usual.
11 Expiry
These Regulations expire on 23 July 2012.
═══════════════
r. 9
-- 4 of 5 --
S.R. No. 64/2011
Subdivision (Fees) Interim Regulations 2011
4
Authorised by the Chief Parliamentary Counsel
ENDNOTES
1 Reg. 4: S.R. No. 94/2000 as extended in operation by S.R. No. 20/2010.
Endnotes
-- 5 of 5 --