Domestic Building Contracts Regulations 2007
i
Domestic Building Contracts Regulations 2007
S.R. No. 25/2007
TABLE OF PROVISIONS
Regulation Page
1 Objectives 1
2 Authorising provision 2
3 Revocation 2
4 Commencement 2
5 Definitions 2
6 Building work to which Act does not apply—work to be carried
out under a contract for one type of work only 3
7 Building work to which the Act does not apply 3
8 Building work to which the Act does not apply—subdivisions 5
9 Certain contracts exempt from provisions of Act 6
10 Certain persons exempt from requirement to make allowance
for delays in time estimates 6
11 Type of cost plus contract allowed 6
12 Progress payments 7
__________________
SCHEDULE 8
Form 1—Warning to owner—change of legal rights 8
Form 2—Progress Payments 10
═══════════════
ENDNOTES 11
-- 1 of 12 --
1
STATUTORY RULES 2007
S.R. No. 25/2007
Domestic Building Contracts Act 1995
Domestic Building Contracts Regulations 2007
The Governor in Council makes the following Regulations:
Dated: 23 April 2007
Responsible Minister:
DANIEL ANDREWS
Minister for Consumer Affairs
RUTH LEACH
Clerk of the Executive Council
1 Objectives
The objectives of these Regulations are—
(a) to prescribe certain work as building work to
which the Act does not apply;
(b) to allow certain contracts to be cost plus
contracts for the purposes of section 13 of
the Act;
(c) to prescribe, with regard to progress
payments, the manner in which parties to a
contract may agree that sections 40(2) and
(3) of the Act do not apply;
(d) to exempt certain persons and contracts from
various provisions of the Act; and
(e) to prescribe other matters necessary for the
purposes of the Domestic Building
Contracts Act 1995.
-- 2 of 12 --
S.R. No. 25/2007
Domestic Building Contracts Regulations 2007
2
2 Authorising provision
These Regulations are made under section 135 of
the Domestic Building Contracts Act 1995.
3 Revocation
The following regulations are revoked—
(a) the Domestic Building Contracts and
Tribunal (General) Regulations 19961 ;
(b) the Domestic Building Contracts and
Tribunal (General) (Amendment)
Regulations 1999 2 ;
(c) the Domestic Building Contracts and
Tribunal (General) (Amendment)
Regulations 2004 3 .
4 Commencement
These Regulations come into operation on
28 April 2007.
5 Definitions
In these Regulations—
public construction has the same meaning as in
section 3(1) of the Project Development
and Construction Management Act 1994;
subdivision has the same meaning as in the
Subdivision Act 1988;
the Act means the Domestic Building Contracts
Act 1995.
r. 2
-- 3 of 12 --
S.R. No. 25/2007
Domestic Building Contracts Regulations 2007
3
6 Building work to which Act does not apply—work
to be carried out under a contract for one type of
work only
For the purposes of section 6(a) of the Act, work
is not building work to which the Act applies if
the work is to be carried out under a contract in
relation to one only of the following types of
work—
(a) attaching external fixtures (including
awnings, security screens, insect screens and
balustrades);
(b) electrical work;
(c) glazing;
(d) installing floor coverings;
(e) insulating;
(f) painting;
(g) plastering;
(h) plumbing work as defined in section 221C of
the Building Act 1993;
(i) tiling (wall and floor);
(j) erecting a chain wire fence to enclose a
tennis court;
(k) erecting a mast, pole, antenna, aerial or
similar structure.
7 Building work to which the Act does not apply
For the purposes of section 6(a) of the Act, work
carried out in relation to any of the following is
not building work to which the Act applies—
(a) the official residence of the Governor of
Victoria;
r. 6
-- 4 of 12 --
S.R. No. 25/2007
Domestic Building Contracts Regulations 2007
4
(b) premises that are used or intended to be used
at a school, university or other educational or
training institution as accommodation for
students or staff;
(c) premises that are used or intended to be used
as—
(i) a community service established under
section 57 of the Children and Young
Persons Act 1989; or
(ii) a community service approved under
section 58 of that Act and that are
situated on Crown land or land in
relation to which the Secretary to the
Department of Human Services or the
Director of Housing is registered as
proprietor; or
(iii) a remand centre within the meaning of
that Act; or
(iv) a secure welfare service within the
meaning of that Act; or
(v) a youth residential centre within the
meaning of that Act; or
(vi) a youth training centre within the
meaning of that Act;
(d) premises that are used or intended to be used
as—
(i) a prison established under section 10 of
the Corrections Act 1986; or
(ii) a community corrections centre
established under Part 9 of that Act;
r. 7
-- 5 of 12 --
S.R. No. 25/2007
Domestic Building Contracts Regulations 2007
5
(e) premises that are used or intended to be used
as—
(i) a residential institution within the
meaning of the Intellectually Disabled
Persons' Services Act 1986; or
(ii) a residential program within the
meaning of that Act;
(f) premises that are used or intended to be used
to provide accommodation within the
Parliamentary reserve within the meaning of
the Parliamentary Precincts Act 2001;
(g) movable units within the meaning of the
Housing Act 1983 that are constructed for
Kids Under Cover Inc. that are used or
intended to be used to provide
accommodation on a non-profit basis.
8 Building work to which the Act does not apply—
subdivisions
For the purposes of section 6(a) of the Act, work
is not building work to which the Act applies if it
is work for the design, construction, extension,
repair, replacement, maintenance, demolition or
removal of all or any of the following works in
relation to a subdivision of land—
(a) the provision of roads, access ways,
footpaths, bridges, dams, reserves, open
spaces, or ornamental or decorative works
associated with such works, within the
subdivision;
(b) works for sewerage, drainage, water supply,
power, gas or telecommunications to connect
the subdivision to the system serving
properties outside it, excluding works to
connect any particular property to the system
for the subdivision;
r. 8
-- 6 of 12 --
S.R. No. 25/2007
Domestic Building Contracts Regulations 2007
6
(c) engineering works, fencing works,
landscaping works or retaining structures
required under the planning scheme or the
permit under the Planning and
Environment Act 1987 for the subdivision;
(d) works required for the issuing of any
certificate or statement of environmental
audit under the Environment Protection
Act 1970 for the subdivision.
9 Certain contracts exempt from provisions of Act
(1) Section 15 of the Act does not apply to a domestic
building contract for public construction.
(2) Sections 31(1)(b), (c), (d), (i), (n) and (r), 31(2),
33, 34 and 35 of the Act do not apply to a major
domestic building contract for public construction.
10 Certain persons exempt from requirement to make
allowance for delays in time estimates
Section 32 of the Act does not apply to a builder
performing work under a major domestic building
contract for public construction.
11 Type of cost plus contract allowed
For the purposes of section 13(1)(a) of the Act,
the following classes of cost plus contracts are
allowed—
(a) contracts for work that it is reasonably
estimated will cost $500 000 or more;
(b) domestic building contracts for public
construction where the Crown or a public
statutory authority is a party to the contract.
r. 9
-- 7 of 12 --
S.R. No. 25/2007
Domestic Building Contracts Regulations 2007
7
12 Progress payments
For the purposes of section 40(4) of the Act, when
parties to a major domestic building contract agree
that sections 40(2) and (3) of the Act do not apply
to that contract, the manner of agreement is to
include in the major domestic building contract—
(a) a warning in the form of Form 1 in the
Schedule which is signed by the building
owner before the execution of the contract;
and
(b) a clause in the form of Form 2 in the
Schedule.
__________________
r. 12
-- 8 of 12 --
S.R. No. 25/2007
Domestic Building Contracts Regulations 2007
8
SCHEDULE
FORM 1
Regulation 12(a)
WARNING TO OWNER—CHANGE OF LEGAL RIGHTS
Section 40 of the Domestic Building Contracts Act 1995 provides that a
builder cannot charge more than a fixed percentage of the total contract price
at the completion of each stage of building a home.
The Act also allows the parties to a contract to agree in writing to change the
stages and the percentage of the contract price to be paid at the completion of
each stage.
There are several ways in which a particular contract can vary from the
normal, and it is these exceptional cases which have caused the law to allow
for these changes.
Examples would include—
• where it is very expensive to prepare the land for building for example,
where the site is steep or rocky;
• where the house is so large that it will take a long time to complete, and
intermediate progress payments are therefore required;
• where exceptionally expensive finishes are required, meaning that the
final stage will represent a much larger proportion of the whole price;
• where an architect is engaged to independently assess the value of
completed work for progress payments.
You should not agree to progress payments different from that provided in
the Act unless your house is unusual in some way and you are SURE THAT
DIFFERENT PROGRESS PAYMENTS ARE NECESSARY and you
understand clearly why the change is needed in the case of your particular
house.
Sch.
-- 9 of 12 --
S.R. No. 25/2007
Domestic Building Contracts Regulations 2007
9
If you have any doubts, you could contact
Housing Industry Association
The Master Builders' Association of Victoria
Consumer Affairs Victoria
Royal Australian Institute of Architects
…………………………………………..
I acknowledge that I have read this warning before signing the contract
Signature of Building Owner
Sch.
-- 10 of 12 --
S.R. No. 25/2007
Domestic Building Contracts Regulations 2007
10
FORM 2
Regulation 12(b)
PROGRESS PAYMENTS
The parties agree—
(i) that the progress payments fixed by section 40 of the Domestic
Building Contracts Act 1995 do not apply; and
(ii) that instead the percentages of the contract price and amounts payable
are as follows—
Name
of stage
If this stage is not the same as a
stage defined in section 40(1) of the
Domestic Building Contracts Act
1995, what does this stage mean?
Percentage
of total
contract
price
$
═══════════════
Sch.
-- 11 of 12 --
S.R. No. 25/2007
Domestic Building Contracts Regulations 2007
11
ENDNOTES
1 Reg. 3(a): S.R. No. 32/1996. Reprint No. 1 at 20 November 1997, and
amending S.R. Nos 126/1999 and 146/2004.
2 Reg. 3(b): S.R. No. 126/1999.
3 Reg. 3(c): S.R. No. 146/2004.
Endnotes
-- 12 of 12 --