MR SCOTT CHRISTOPHER DUNCAN v BERT FARINA CONSTRUCTIONS PTY LTD [2024] SASCA 67
On Appeal from DISTRICT COURT OF SOUTH AUSTRALIA (HER HONOUR JUDGE THOMAS) CIV-
22-007659
First Appellant: MR SCOTT CHRISTOPHER DUNCAN Counsel: MR A LAZAREVICH - Solicitor:
LEVENTIS LAWYERS
Second Appellant: MS FIONA JANE ROBERTS Counsel: MR A LAZAREVICH - Solicitor:
LEVENTIS LAWYERS
Respondent: BERT FARINA CONSTRUCTIONS PTY LTD Counsel: MR B JENNER - Solicitor:
FBR LAW
Hearing Date/s: 06/11/2023
File No/s: CIV-23-005055
A
SUPREME COURT OF SOUTH AUSTRALIA
(Court of Appeal: Civil)
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply
to this judgment. The onus remains on any person using material in the judgment to ensure that the intended use of that material does not breach
any such order or provision. Further enquiries may be directed to the Registry of the Court in which it was generated.
DUNCAN v BERT FARINA CONSTRUCTIONS PTY LTD
[2024] SASCA 67
Judgment of the Court of Appeal
(The Honourable Justice Doyle, the Honourable Justice Bleby and the Honourable Justice Blue)
30 May 2024
STATUTES - ACTS OF PARLIAMENT - INTERPRETATION
LIMITATION OF ACTIONS - LIMITATION OF PARTICULAR ACTIONS
This is an appeal from the primary judge’s determination of a preliminary question of law.
The appellants (owners) issued proceedings against the respondent (builder), claiming damages for
defective building work in the construction of their house. The owners alleged breaches of statutory
warranties under s 32(2) of the Building Work Contractors Act 1995 (SA) (‘BWCA’) and common
law negligence.
Section 32(5) of the BWCA establishes a five year limitation period for claims made under s 32(2)
of the BWCA. Section 73 of the Development Act 1993 (SA) (‘DA’) (and its successor, s 159 of the
Planning, Development and Infrastructure Act 2016 (SA) (‘PDIA’)) contain a 10 year limitation
period for actions for damages for economic loss or rectification costs resulting from defective
building work.
At first instance, the owners pleaded that the time limit for commencing proceedings for breach of
statutory warranties under s 32(2) of the BWCA is 10 years from the date of completion of the
building work by reason of s 73 of the DA. The builder pleaded in its defence that the limitation
period applicable under s 32(2) of the BWCA is five years, pursuant to s 32(5) of the BWCA. The
primary judge generally accepted the builder’s contention and held that, in proceedings for damages
for defective building work relying on breach of a statutory warranty under s 32(2) of the BWCA, a
respondent is able to elect to plead the expiry of the five year warranty under s 32(5) BWCA as a
defence, and, properly read, s 73 of the DA, and its successor s 159 of the PDIA, do not displace the
-- 1 of 34 --
shorter five year limitation period in s 32(5) of the BWCA. The owners appeal the primary judge’s
determination.
Held, (per the Court), dismissing the appeal:
1. The relevant textual, contextual and purposive considerations support the construction of s 73
of the Development Act 1993 (SA) and s 159 of the Planning, Development and Infrastructure
Act 2016 (SA) as imposing a 10 year long stop limitation period in respect of claims for
economic loss or rectification costs arising out of defective building work which does not
operate so as to displace the five year time limit for claims based on the statutory warranties
in respect of domestic building work under s 32 of the Building Work Contractors Act 1995
(SA).
Builders Licensing Act Amendment Act 1983 (SA); Builders Licensing Act 1967 (SA); Builders
Licensing Act 1986 (SA) pt 5; Building Act 1992 (NT) ss 160-161; Building Act 1993 (Vic) s 134;
Building Act 2004 (ACT) s 142(3); Building Act 2016 (Tas) s 327; Building Work Contractors Act
1995 (SA) ss 3, 32(1), 32(2), 32(3), 32(5), 32(6), 37(2), 37(6), 40(1); Competition and Consumer Act
2010 (Cth) sch 2; Defective Houses Act 1976 (SA) s 4; Development Act 1993 (SA) ss 4, 72, 73;
Domestic Building Contracts Act 1995 (Vic) ss 8, 9, 20; Environmental Planning and Assessment
Act 1979 (NSW) s 6.20(4); Legislation Interpretation Act 2021 (SA) ss 14, 16; Limitation of Actions
Act 1936 (SA) ss 35(a), 35(c), 36, 48; Limitation of Actions Act 1958 (Vic) ss 5(1)(a), 33; Limitation
of Actions Act 1974 (Qld) ss 10(1)(d), 26(1); Planning, Development and Infrastructure Act 2016
(SA) ss 158, 159, referred to.
Alcan (NT) Alumina Pty Ltd v Commissioner of Territory Revenue (2009) 239 CLR 27; Attorney-
General (Cth) v Oates (1999) 198 CLR 162; Aussie Blinds and Canvas Products Pty Ltd v Smith
[2015] SADC 154; Brirek Industries Pty Ltd v McKenzie Group Consulting (Vic) Pty Ltd (2015) 48
VR 558; Brisbane City Council v Amos (2019) 266 CLR 593; Certain Lloyd’s Underwriters v Cross
(2012) 248 CLR 378; CIC Insurance Ltd v Bankstown Football Club Ltd (1997) 187 CLR 384;
Commonwealth v Mewett (1997) 191 CLR 471; Commonwealth v Verwayen (1990) 170 CLR 394;
Disorganized Developments Pty Ltd v South Australia (2023) 97 ALJR 575; Duncan v Bert Farina
Constructions Pty Ltd [2023] SADC 37; Goodwin v Phillips (1908) 7 CLR 1; Maybury v Plowman
(1913) 16 CLR 468; Price v Spoor (2021) 270 CLR 450; Project Blue Sky Inc v Australian
Broadcasting Authority (1998) 194 CLR 355; Re McE [2009] 4 All ER 335; SZTAL v Minister for
Immigration and Border Protection (2017) 262 CLR 362; Taylor v Owners – Strata Plan No 11564
(2014) 253 CLR 531; Walford Anglican School for Girls Incorporated v Romaldi Constructions Pty
Ltd [2020] SADC 146; Wardley Australia Ltd v Western Australia (1992) 175 CLR 514; Woolcock
Street Investments Pty Ltd v CDG Pty Ltd (2004) 216 CLR 515, considered.
-- 2 of 34 --
DUNCAN & ANOR v BERT FARINA CONSTRUCTIONS PTY LTD
[2024] SASCA 67
Court of Appeal – Civil: Doyle and Bleby JJA and Blue AJA
1 THE COURT: This is an appeal from the primary judge’s determination of a
preliminary question of law. The issue raised by the question is whether s 73 of
the Development Act 1993 (SA) (the DA) (which was in identical form to its
successor, s 159 of the Planning, Development and Infrastructure Act 2016 (SA)
(the PDIA)) creates a single limitation period of 10 years for all claims for
damages for economic loss or rectification costs arising out of defective building
work, or whether a shorter period of five years applies where those claims rely on
a breach of a statutory warranty under s 32(2) of the Building Work Contractors
Act 1995 (SA) (the BWCA).
2 The answer given by the primary judge1 was that in proceedings for breach
of a statutory warranty under s 32(2) of the BWCA, including a claim for
compensation for defective building work under that subsection, a respondent may
elect to plead the expiry of the non-extendable five year limitation period in s 32(5)
of the BWCA by way of defence. Neither the 10 year limitation period in s 73 of
the DA, nor its successor in s 159 of the PDIA, displaces that shorter limitation
period.
3 For the reasons given below, the primary judge’s answer is correct. Properly
understood, s 73 of the DA (and hence also s 159 of the PDIA) operates only as a
‘long stop’ limitation provision. It operates only to prohibit the commencement of
a claim for damages for economic loss or rectification costs arising out of defective
building work after 10 years has elapsed. It does not give permission for, or
authorise, the commencement of such claims at any time up to the expiry of that
period. There is no inconsistency between s 73 (or s 159) and the operation of the
shorter five year time limit that applies in respect of such claims when based upon
the breach of a statutory warranty under s 32(2) of the BWCA. They may operate
concurrently in respect of a particular claim. Where both time limits are potentially
applicable, a respondent may rely upon the shorter period as barring the applicant’s
claim.
Relevant legislative provisions
4 It is appropriate to commence by identifying the legislative provisions
containing the statutory warranties applicable to contracts for domestic building
work in the BWCA and the five year time limit in respect of claims involving those
warranties; the 10 year time limit for claims for damages for economic loss or
rectification costs resulting from defective building work in s 73 of the DA and
s 159 of the PDIA; and the time limits applicable in relation to contractual and
tortious claims under the Limitation of Actions Act 1936 (SA).
1 Duncan v Bert Farina Constructions Pty Ltd [2023] SADC 37 (Reasons) at [21].
-- 3 of 34 --
[2024] SASCA 67 The Court
2
Key provisions of the BWCA
5 Part 5 of the BWCA contains various provisions regulating domestic building
work. In Division 2 of Part 5, s 32 provides for several statutory warranties to be
implied in every domestic building work contract:
32—Statutory warranties
(1) This section applies to a contract entered into on or after 22 January 1987¹.
(2) The following warranties on the part of the building work contractor are implied in
every domestic building work contract:
(a) a warranty that the building work will be performed in a proper manner to
accepted trade standards and in accordance with the plans and specifications
agreed to by the parties;
(b) a warranty that all materials to be supplied by the contractor for use in the
building work will be good and proper;
(c) a warranty that the building work will be performed in accordance with all
statutory requirements;
(d) if the contract does not stipulate a period within which the building work must
be completed—a warranty that the building work will be performed with
reasonable diligence;
(e) if the building work consists of the construction of a house—a warranty that
the house will be reasonably fit for human habitation;
(f) if the building owner has expressly made known to the contractor, or an
employee or agent of the contractor, the particular purpose for which the
building work is required, or the result that the building owner desires the
building work to achieve, so as to show that the building owner relies on the
contractor's skill and judgment—a warranty that the building work and any
materials used in performing the building work will be reasonably fit for that
purpose or of such a nature and quality that they might reasonably be expected
to achieve that result.
(3) A person who has purchased or otherwise acquired a house succeeds to the rights of
the person's predecessor in title in respect of statutory warranties.
(4) If a person has purchased a house from a building work contractor who performed
domestic building work in relation to the house, the purchaser has rights under
statutory warranties as if the house had been purchased from a third party for whom
the vendor had performed the building work under a contract subject to statutory
warranties.
(5) Proceedings for breach of a statutory warranty must be commenced within five years
after completion of the building work to which the proceedings relate.
(6) The period of limitation prescribed by subsection (5) may not be extended.
-- 4 of 34 --
[2024] SASCA 67 The Court
3
(7) In proceedings for breach of a statutory warranty, it is a defence for the defendant to
prove that the deficiencies of which the plaintiff complains arose from instructions
insisted on by the building owner contrary to the advice in writing of the defendant.
Note—
1 22 January 1987 was the date of commencement of the corresponding section
of the repealed Builders Licensing Act 1986.
6 The following definitions from s 3 of the BWCA inform the application of
these statutory warranties:
building work contractor means—
(a) a person who carries on the business of performing building work for others; or
(b) a person who carries on the business of performing building work with a view to the
sale or letting (whether by lease, licence or other agreement) of land or buildings
improved as a result of the building work;
building includes a wall or structure and part of a building or structure;
building owner, in relation to a domestic building work contract, means the person for
whom domestic building work is or is to be performed under the contract;
building work means—
(a) the whole or part of the work of constructing, erecting, underpinning, altering,
repairing, improving, adding to or demolishing a building; or
(b) the whole or part of the work of excavating or filling a site for work referred to in
paragraph (a); or
domestic building work means—
(a) the whole or part of the work of constructing, erecting, underpinning, altering,
repairing, improving, adding to or demolishing a house; or
(b) the whole or part of the work of excavating or filling a site for work referred to in
paragraph (a); or
(c) work of a class prescribed by regulation;
domestic building work contract means a contract between a building work contractor and
another person for the performance by the contractor of domestic building work (including
any variation of such a contract), but does not include a subcontract for the performance of
domestic building work;
statutory warranty means a warranty arising under Division 2 of Part 5.
7 The statutory warranties in s 32(2) of the BWCA are only implied in
contracts for “domestic” building work. Having regard to the definitions set out
above, this means that they only apply to building work involving a house. They
are also only implied in contracts with “building work contractors” (that is,
-- 5 of 34 --
[2024] SASCA 67 The Court
4
builders), and not others (such as architects, engineers, surveyors, certifiers or
developers) who might be involved in aspects of the building project. As to the
content of the statutory warranties, while claims based on the warranties in
ss 32(2)(a), (b), (c), (e) and (f) may aptly be described as claims relating to
defective building work, claims based on the warranty in s 32(2)(d) relate to a lack
of reasonable diligence or delay.
8 It may also be observed that the statutory warranties are transmissible to
subsequent owners of a house (s 32(3)); that proceedings for breach of a statutory
warranty must be brought within five years from completion of the building work
(s 32(5)); and that this time limit is not able to be extended (s 32(6)).
9 Division 5 of Part 5 governs the courts’ powers in relation to claims relating
to domestic building work. In particular, s 37(2) provides for proceedings relating
to a statutory warranty or domestic building work contract to be brought in the
Magistrates Court (but transferred to the District Court if the value of the claim
exceeds $100,0002). Under s 37(6), if the Court is satisfied that there has been a
breach of, or failure to perform or fulfil, a contract or warranty, then it may make
“an order requiring the performance of remedial work” (s 37(6)(a)) or “an order
requiring the payment of an amount due under the contract or … an amount by
way of compensation for the breach” (s 37(6)(b)).
Key provisions of the DA and PDIA
10 The DA and its successor, the PDIA, are wider ranging pieces of legislation
governing various aspects of planning, development and building work.
11 Relevantly for present purposes, Part 6 of the DA contains a suite of
provisions regulating several aspects of building work. Division 7 of that Part is
headed “Liability” and contains provisions relating to both the negation of joint
and several liability in certain cases (s 72), and the imposition of a 10 year time
limit on actions for damages for economic loss or rectification resulting from
defective building work (s 73). In particular, s 73 provides:
73—Limitation on time when action may be taken
(1) Despite the Limitation of Actions Act 1936, or any other Act or law, no action for
damages for economic loss or rectification costs resulting from defective building
work (including an action for damages for breach of statutory duty) can be
commenced more than 10 years after completion of the building work.
(2) This section does not affect an action to recover damages for death or personal injury
resulting from defective building work.
(3) The period prescribed by subsection (1) cannot be extended.
2 BWCA, s 40(1), referring to proceedings involving a monetary claim exceeding $100,000, or a claim
for relief in the nature of an order to carry out work where the value of the work exceeds $100,000.
-- 6 of 34 --
[2024] SASCA 67 The Court
5
12 Both “building” and “building work” are defined broadly in s 4 of the DA:
building means a building or structure or a portion of a building or structure (including any
fixtures or fittings which are subject to the provisions of the Building Code of Australia),
whether temporary or permanent, moveable or immovable, and includes a boat or pontoon
permanently moored or fixed to land, or a caravan permanently fixed to land;
building work means work or activity in the nature of—
(a) the construction, demolition or removal of a building (including any incidental
excavation or filling of land); or
(c) any other prescribed work or activity,
but does not include any work or activity that is excluded by regulation from the ambit of
this definition.
13 Notably, the 10 year time limit in respect of claims resulting from defective
building work is confined to damages for economic loss or rectification costs; it
does not apply to claims for death or personal injury. Further, like the shorter time
period under s 32(5) of the BWCA, the 10 year time limit under s 73 of the DA
commences to run from completion of the building work, and is not able to be
extended. However, it applies to claims in respect of defective building work
generally and not merely domestic building work. It is also not confined to claims
against the builder; it applies to claims against others involved in the defective
building works such as architects, engineers, surveyors, certifiers and developers.
14 Part 11 of the successor Act, the PDIA, contains a similar suite of provisions
regulating building work. In particular, ss 158 and 159 in Division 7 of Part 11 of
the PDIA are in identical terms to ss 72 and 73 in Division 7 of Part 6 of the DA.
The PDIA also contains relevantly identical definitions of “building” and “building
work”.
Other limitation provisions
15 Claims for defective building work are, of course, often brought as common
law claims in contract and negligence. Under ss 35(a) and (c) respectively of the
Limitation of Actions Act, those claims “shall, save as otherwise provided in this
Act, be commenced within six years next after the cause of action accrued and not
after.” This is subject to a shorter, three year period, applicable in respect of claims
for damages for personal injury.3
16 In the case of contractual claims, the cause of action accrues, and hence time
runs, from the date of breach. Typically, this will be when the relevant building
work is undertaken. Proof of damage is not an element of the cause of action in
contract. This gives rise to a potential difficulty in cases involving latent defects,
3 Limitation of Actions Act 1936 (SA), s 36(1); noting that in the case of a latent injury time only begins
to run when the injury first comes to the person’s knowledge.
-- 7 of 34 --
[2024] SASCA 67 The Court
6
where the defect giving rise to the occasion for the claim may only be discovered
after the limitation period has expired.
17 Negligence, however, is only actionable upon proof of damage. It is accepted
that this requires, and hence time does not begin to run until, damage is suffered
or becomes reasonably apparent. In the case of latent defects, this may not occur
until many years after the work is undertaken. As McHugh J explained in
Woolcock Street Investments Pty Ltd v CDG Pty Ltd,4 it follows that those involved
in the design or construction of a building may be sued in negligence many years
after the work was undertaken, and indeed after the time has expired for suing in
contract:5
The now accepted doctrine is that, in the case of defective premises, damage does not occur
until the defect manifests itself. No cause of action arises in tort until the plaintiff suffers
damage. Consequently, those concerned with the design and construction of a building may
be required to defend themselves against an action in tort many years after completing the
task that now gives rise to the claims against them. On the other hand, a cause of action in
contract arises when the contract is breached. Time runs from the breach, not the sustaining
of damage. This creates the paradox that those involved in the design or construction of a
building may be sued in tort years after the time has expired for suing on the contract that
gave rise to the duty.
18 The time limits applicable to both contractual and tortious claims under the
Limitation of Actions Act may be extended under s 48 of that Act.
19 Claims in building disputes may, of course, be brought other than in contract
and tort. They may include, for example, claims for misleading and deceptive
conduct contrary to s 18(1) of the Australian Consumer Law.6 Claims of this nature
are subject to a limitation period of three years; and as damages is the gist of the
cause of action, time does not begin to run until loss or damage has been suffered
or becomes reasonably ascertainable.7
Background
20 The following background to the issue arising on appeal was agreed by the
parties, or is otherwise uncontentious because it reflects admissions in the
pleadings.
21 The appellants (the Owners) issued the proceeding against the respondent
(the Builder) on 13 July 2022, claiming damages for defective building work in
the construction of their house in Morphettville (the Morphettville property).
They allege breaches of statutory warranties under s 32(2) of the BWCA and
common law negligence.
4 Woolcock Street Investments Pty Ltd v CDG Pty Ltd (2004) 216 CLR 515.
5 Woolcock Street Investments Pty Ltd v CDG Pty Ltd (2004) 216 CLR 515 at [103] (McHugh J) (citations
omitted).
6 Competition and Consumer Act 2010 (Cth), Schedule 2.
7 Wardley Australia Ltd v Western Australia (1992) 175 CLR 514.
-- 8 of 34 --
[2024] SASCA 67 The Court
7
22 The Builder carried out the building work (the Works) on the Morphettville
property under a written contract (the Contract) with the original owner (the
South Australian Housing Trust (the SAHT)) dated 13 August 2014.
23 The Works the subject of dispute in these proceedings comprised “domestic
building work”, the Contract was a “domestic building work contract”, and the
Builder was a “building work contractor”, all within the meaning of the BWCA.
It follows that the statutory warranties in s 32(2) of the BWCA were implied in the
Contract. The Works also comprised “building work” within the meaning of s 73
of the DA and s 159 of the PDIA.
24 The Owners acquired the Morphettville property from its original owner, the
SAHT, on about 29 June 2016. By operation of s 32(3) of the BWCA, the Owners
are the successors to the rights of the SAHT in respect of the statutory warranties
under s 32(2) of that Act.
25 The parties are not agreed as to the date when the Works were completed.
The Builder contends that the Works reached practical completion under the
Contract on 10 December 2015, and that the defects liability period therefore
ended on 10 March 2016. The bank guarantee provided on behalf of the SAHT
was released on 27 June 2016.
26 The Owners plead that they do not know the precise particulars of the
Contract or the completion date. In any event, they say further that the time limit
for commencing proceedings for breach of the statutory warranties under s 32(2)
of the BWCA is 10 years from the date of completion by reason of s 73 of the DA
(now s 159 of the PDIA), with the result that the claim in respect of those
warranties is within time.
27 The Builder pleads in its defence that the limitation period applicable to the
claims under s 32(2) of the BWCA is five years, and that because the Works were
completed by 27 June 2016 at the latest, the Owners’ claim had to be commenced
by 27 June 2021. As the five year limitation period is not able to be extended
under s 32(6) of the BWCA, the claim under that Act is statute-barred.
28 It was in this context that the parties agreed the following issue for
determination by the primary judge:
Whether the time within which proceedings [must be commenced] for defective building
work relying on a breach of statutory warranty under ss 32(2) and 32(3) of the BWCA is:
(a) five (5) years after completion of the building work by reason of s 32(5) of the
BWCA; or
(b) ten (10) years after completion of the building work by reason of s 159(1) of the
PDIA and/or s 73 of the DA.
-- 9 of 34 --
[2024] SASCA 67 The Court
8
29 Part 11 of the PDIA commenced its operation on 1 July 2019.8 However,
because s 73 of the DA was not repealed until 19 March 2021,9 both provisions
were in force at the expiry of the five year limitation period commencing on the
earlier dates relied upon by the Builder (being the dates of practical completion
(10 December 2015) and the end of the defects liability period (10 March 2016)).10
However, only s 159 of the PDIA was in force at the expiry of the five year
limitation period commencing on the latest date relied upon by the Builder (being
the release of the guarantee on 27 June 2016).
30 Determining which of s 73 of the DA and/or s 159 of the PDIA apply to the
Owners’ claim in these proceedings is not straightforward and will depend not only
upon a determination of the date of completion for the purposes of those sections,
but also whether s 159 of the PDIA may have retrospective effect. The parties are
not agreed as to which of these provisions will ultimately apply, but have
approached the issue arising on the preliminary question on the basis that it is not
necessary for that to be determined at this stage in the proceeding as the outcome
will be the same regardless of which of these sections apply.
31 The preliminary question agreed by the parties focuses upon the (non-
extendable) time limit applicable to the Owners’ claim under the statutory
warranties in ss 32(2) and (3) of the BWCA. However, it is apparent that an issue
may also arise in the proceeding as to whether the Owners’ claim in negligence is
statute-barred. The Builder’s position is that the shorter (but extendable) six year
period under s 35(c) of the Limitation of Actions Act applicable to actions in tort
applies to that claim, with the 10 year period under s 73 of the DA (and s 159 of
the PDIA) operating as a ‘long stop’ limit of 10 years upon any extension of that
time limit under s 48 of the Limitation of Actions Act. The Owners, on the other
hand, contend that this claim may be brought at any time within the 10 year period
under s 73 of the DA, or s 159 of the PDIA, albeit that they plead an entitlement
to an extension of time under s 48 of the Limitation of Actions Act in the event that
the shorter period under that Act is the applicable time limit.
32 In her reasons, the primary judge commenced by summarising the parties’
respective contentions. As she explained, in arguing for a single 10 year limitation
period, the Owners advanced several contentions, including:
• that a claim for compensation for breach of a statutory warranty under s 32
of the BWCA is a claim for damages for economic loss or rectification costs
resulting from defective building work within the meaning of s 73 of the DA
(and s 159 of the PDIA);
8 Planning, Development and Infrastructure Act (Commencement) Proclamation 2019’ in South
Australia, The South Australian Government Gazette, No 30, 27 June 2019, 2320.
9 Planning, Development and Infrastructure Act (Commencement) Proclamation 2021’ in South
Australia, The South Australian Government Gazette, No 14, 4 March 2021, 822.
10 These dates are taken from the agreed facts, but confusingly the dates used in the respondent’s defence
are 20 November 2015 and 20 February 2016. Nothing turns on this difference.
-- 10 of 34 --
[2024] SASCA 67 The Court
9
• that ss 73 and 159 are expressed to apply “[d]espite” the Limitation of Actions
Act or “any other Act or law” (which would include the time limit in s 32(5)
of the BWCA);
• that the mischief to be addressed by ss 73 and 159 was the uncertainty about
the various time limits applicable to claims in relation to defective building
work, with the corresponding purpose of the sections being to provide
uniformity in this respect;
• that the construction urged by the Owners is supported by the decision of the
Victorian Court of Appeal in Brirek Industries Pty Ltd v McKenzie Group
Consulting (Vic) Pty Ltd11 in relation to a similar provision in the Victorian
legislation, and two decisions of the South Australian District Court; and
• that a survey of, and comparison with, similar interstate provisions also
supports the Owners’ construction.
33 On the other hand, in arguing for the continued operation of the shorter five
year time limit in relation to claims under s 32 of the BWCA, the primary judge
noted that the Builder contended:
• that there was no reason in the text, context or statutory purpose of the
relevant provisions to conclude that the legislature intended that s 73 of the
DA (or s 159 of the PDIA) would modify, replace or affect the operation of
the five year time limit in s 32(5) of the BWCA;
• that there was no necessary or direct conflict between the relevant provisions
of the BWCA and the DA (or PDIA);
• that the provisions should be construed as pursuing harmonious goals, with
coherence achieved by reading the more general provisions in ss 73 and 159
as not applying to the more specific context of statutory warranties under s 32
of the BWCA;
• that a consideration of the relevant legislative history demonstrated both
long-standing legislative support in South Australia for a balance between
protecting “house” owners with transmissible statutory warranties and
confining that protection to a (non-extendable) period of five years, and the
absence of any clear indication that either of ss 73 and 159 was intended to
alter that history or balance; and
• that the decision in Brirek Industries Pty Ltd v McKenzie Group Consulting
(Vic) Pty Ltd is distinguishable by reason of the different legislation in
Victoria, and the two District Court decisions are of little assistance as they
simply applied that decision.
11 Brirek Industries Pty Ltd v McKenzie Group Consulting (Vic) Pty Ltd (2015) 48 VR 558.
-- 11 of 34 --
[2024] SASCA 67 The Court
10
34 The primary judge addressed each of these arguments in her careful and
thorough reasons. Having commenced with a summary of the orthodox approach
to statutory construction, her Honour addressed each of the textual, contextual and
purposive considerations relied upon by the parties. In addressing the textual
considerations, the primary judge considered the general approach of the courts to
limitation provisions, the absence of any clear conflict or inconsistency between
the relevant provisions of the DA/PDIA and the BWCA, the overlap in their fields
of operation, and the significance of the introductory words of ss 73 and 159
(“despite … any other Act”). In next addressing matters of broader context and
purpose, the primary judge summarised the regulation in South Australia of
domestic building work under the BWCA, and building work more generally under
the DA/PDIA, and relevant aspects of the legislative history in relation to these
matters. Her Honour concluded by addressing the authorities relied upon by the
Owners.
35 The primary judge generally accepted the Builder’s contentions in relation to
each of these issues. Rather than summarise the entirety of her Honour’s reasoning
it will be sufficient to note aspects of her reasoning as matters arise in the reasons
that follow.
The appeal
36 The Owners rely upon 10 grounds of appeal. They involve a wide-ranging
challenge to several aspects of her Honour’s analysis of the textual, contextual and
purposive considerations relevant to her acceptance of the Builder’s construction
of ss 73 and 159. While we have had regard to each of the grounds of appeal, it is
not necessary to set them out in full. They are all addressed in the reasons given
below for upholding her Honour’s construction of ss 73 and 159.
Approach to statutory construction
37 Resolution of the preliminary question ultimately involves a question of
statutory construction and, in particular, the proper construction of s 73 of the DA
and s 159 of the PDIA.
38 The primary judge accurately summarised the principles governing statutory
construction,12 and what follows largely reflects her Honour’s collection of those
principles.
39 The fundamental task of the Court in construing legislation is, of course, to
give the words used in the relevant provisions the meaning that the legislature is
taken to have intended.13
12 Reasons at [43]-[52].
13 Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355 at [78] (McHugh,
Gummow, Kirby and Hayne JJ).
-- 12 of 34 --
[2024] SASCA 67 The Court
11
40 The contemporary approach to this task is conveniently summarised in the
following passage from the reasons of Kiefel CJ, Gordon and Nettle JJ in SZTAL
v Minister for Immigration and Border Protection:14
The starting point for the ascertainment of the meaning of a statutory provision is the text
of the statute whilst, at the same time, regard is had to its context and purpose15. Context
should be regarded at this first stage and not at some later stage and it should be regarded
in its widest sense16. This is not to deny the importance of the natural and ordinary meaning
of a word, namely how it is ordinarily understood in discourse, to the process of
construction. Considerations of context and purpose simply recognise that, understood in
its statutory, historical or other context, some other meaning of a word may be suggested,
and so too, if its ordinary meaning is not consistent with the statutory purpose, that meaning
must be rejected.
41 Similarly, in CIC Insurance Ltd v Bankstown Football Club Ltd,17
Brennan CJ, Dawson, Toohey and Gummow JJ emphasised that context in its
widest sense and statutory purpose are to be considered from the outset, and not
only when an ambiguity might be thought to arise on the text. This may include
consideration of matters such as the existing state of the law, and the mischief
which the legislation was intended to remedy.
42 In the case of South Australian statutes, s 14 of the Legislation Interpretation
Act 2021 (SA) expressly provides that the interpretation that best achieves the
purpose or object of the Act (even if not expressly stated in the Act) is to be
preferred to any other interpretation.
43 Any inconvenience or improbability in the result of a construction may
indicate a meaning other than the literal meaning of the relevant provision.18
Whether a particular construction assists or interferes with the coherent operation
of the relevant legislation scheme may also be a relevant consideration.
44 At the same time, contextual and purposive indications may not be used to
rewrite the legislation; the meaning derived must be consistent with the language
in fact used in the relevant legislation.19 Further, the purpose must be one which
may be discerned from the legislation itself, read in the context of any relevant
extrinsic material. Legislation must not be construed on the basis of some a priori
14 SZTAL v Minister for Immigration and Border Protection (2017) 262 CLR 362 at [14] (Kiefel CJ, Nettle
and Gordon JJ).
15 Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355 at 381-382 [69]-[71];
Alcan (NT) Alumina Pty Ltd v Commissioner of Territory Revenue (2009) 239 CLR 27 at 46-47 [47].
16 CIC Insurance Ltd v Bankstown Football Club Ltd (1997) 187 CLR 384 at 408.
17 CIC Insurance Ltd v Bankstown Football Club Ltd (1997) 187 CLR 384 at 408 (Brennan CJ, Dawson,
Toohey and Gummow JJ).
18 CIC Insurance Ltd v Bankstown Football Club Ltd (1997) 187 CLR 384 at 408 (Brennan CJ, Dawson,
Toohey and Gummow JJ).
19 Disorganized Developments Pty Ltd v South Australia (2023) 97 ALJR 575 at [15] (Kiefel CJ, Gageler,
Gleeson and Jagot JJ).
-- 13 of 34 --
[2024] SASCA 67 The Court
12
assumption as to the statutory purpose, or as to the desirable reach or operation of
the relevant provision.20
45 In SZTAL v Minister for Immigration and Border Protection, Gageler J
described the task as one involving “constructional choice” between the competing
meanings that may be available:21
The constructional choice presented by a statutory text read in context is sometimes
between one meaning which can be characterised as the ordinary or grammatical meaning
and another meaning which cannot be so characterised. More commonly, the choice is from
“a range of potential meanings, some of which may be less immediately obvious or more
awkward than others, but none of which is wholly ungrammatical or unnatural”, in which
case the choice “turns less on linguistic fit than on evaluation of the relative coherence of
the alternatives with identified statutory objects or policies”.22
46 In the present case, there is a constructional choice to be made between the
Builder’s construction of s 73 of the DA and s 159 of the PDIA (which has them
operating concurrently with s 32(5) of the BWCA, and as mere long stop limitation
provisions where they apply), and the Owners’ construction (which has them
operating to the exclusion of the shorter limitation periods such as the one
appearing in s 32(5) of the BWCA). In considering the Owners’ challenges on
appeal to the primary judge’s preference for the Builder’s construction, it is
convenient to commence by addressing the various textual considerations, before
then turning to the broader contextual and purposive considerations relied upon by
the parties.
Textual considerations
47 It is appropriate to commence with the text of s 73 of the DA, which has been
set out earlier in these reasons, and is in identical form to s 159 of the PDIA. This
is not, however, to overlook the relevance of broader contextual and purposive
considerations throughout the construction process. These reasons should not be
understood as reflecting an entirely sequential process of reasoning.
48 In general terms, s 73 creates a non-extendable 10 year time limit in respect
of certain types of actions for damages for defective building work. However,
when considering the potential application of this section in the context of the
present case, and in particular its impact upon the operation of the shorter five year
limitation period in s 32(5) of the BWCA, several aspects of the text of s 73(1)
warrant close attention. These include that it:
• applies to actions for “damages for economic loss or rectification costs
resulting from defective building work (including an action for damages for
breach of statutory duty)”;
20 Certain Lloyd’s Underwriters v Cross (2012) 248 CLR 378 at [26] (French CJ and Hayne J).
21 SZTAL v Minister for Immigration and Border Protection (2017) 262 CLR 362 at [38] (Gageler J).
22 Taylor v Owners – Strata Plan No 11564 (2014) 253 CLR 531 at 557 [66].
-- 14 of 34 --
[2024] SASCA 67 The Court
13
• is expressed in terms that “no action … can be commenced” after the 10 year
period; and
• is expressed to apply “[d]espite” the Limitation of Actions Act or any other
Act or law.
49 As to the first of these textual considerations, the Owners’ claim under s 32
of the BWCA is an action of the type contemplated by s 73 of the DA. The claim
alleges breaches of the s 32(2) statutory warranties based upon defective building
work. The Works, as well as being “domestic building work” for the purposes of
the BWCA, are also “building work” for the purposes of the DA. The claim seeks
monetary relief. While the monetary relief available for the breach of a s 32(2)
statutory warranty is described as “compensation” (s 37(6)(b)), this is
encompassed within an action for “damages” for the purposes of s 73 of the DA.
Further, the compensation sought is compensation for “economic loss or
rectification costs”.
50 It follows from the matters set out in the preceding paragraph that s 73 of the
DA is capable of applying to claims, such as the one brought by the Owners in the
underlying proceedings, for compensation for breach of a statutory warranty under
s 32(2) of the BWCA. However, determining the practical significance of this
conclusion requires consideration of the second and third textual considerations
identified above.
51 As to the second of these textual considerations, the use of the expression “no
action … can be commenced” after the relevant period is an orthodox mode of
expressing a time limit. In considering time limit provisions expressed in these
terms, several authorities have emphasised that they are not to be understood
literally as barring a plaintiff’s right to commence or bring (let alone the court’s
jurisdiction to entertain) an action or claim of the relevant type. Rather, they are
to be understood as conferring a right on the part of the defendant to rely upon the
expiration of the time limit as providing a defence by barring the plaintiff’s right
to the remedy sought.
52 This understanding of time limit provisions has been confirmed in several
High Court decisions, including Commonwealth v Mewett,23 Commonwealth v
Verwayen24 and Brisbane City Council v Amos.25 It was recently reiterated by
various members of the High Court in Price v Spoor,26 as conveniently summarised
in the following passage from the reasons of Gageler and Gordon JJ:27
23 Commonwealth v Mewett (1997) 191 CLR 471 at 534–535 (Gummow and Kirby JJ).
24 Commonwealth v Verwayen (1990) 170 CLR 394 at 405 (Mason CJ), 425-426 (Brennan J), 473-475
(Toohey J), 486-487 (Gaudron J), 497-499 (McHugh J).
25 Brisbane City Council v Amos (2019) 266 CLR 593 at [7] (Kiefel CJ and Edelman J), [40] (Gageler J),
[49] (Keane J).
26 Price v Spoor (2021) 270 CLR 450.
27 Price v Spoor (2021) 270 CLR 450 at [40] (Gageler and Gordon JJ) (citations omitted); see also at [9]-
[10] (Kiefel CJ and Edelman J), [116] (Steward J).
-- 15 of 34 --
[2024] SASCA 67 The Court
14
Section 13, in its terms, provides that ‘[a]n action shall not be brought by a person to recover
land after the expiration of 12 years from the date on which the right of action accrued to
the person … .’ It is in a form which, as has long been settled by judicial decision, is not
to be taken literally but merely provides a defence to an action that must be pleaded by a
defendant if the expiration of the limitation period is to be given effect. It is a provision by
which the remedy is barred, but not the right of the plaintiff to bring the cause of action.
53 A further observation to be made is that whilst a time limit expressed in terms
that “no action … can be commenced” may operate to defeat an action commenced
after expiry of the relevant period (by reason of the defendant pleading the time
limit as a defence, and thus barring the remedy), it does not, in its terms, confer
any permission, authority, right or entitlement on a plaintiff to commence an action
at any time up to the expiry of that period. That this is so is inherent in the words
used, which are negative or restrictive in nature, rather than positive or permissive
in nature.28
54 It is a corollary of this, acknowledged in Brisbane City Council v Amos,29 that
two differing time limits may apply in respect of the same action, with the result
that the defendant may rely upon the shorter of those time limits. As Gageler J
observed,30 while a plaintiff is free to choose to rely on the cause of action which
is most advantageous to the plaintiff (for example, because it has a longer
limitation period), in the event that more than one limitation period is applicable
to the cause of action upon which the plaintiff chooses to rely, the defendant is
correspondingly free to invoke by way of defence the limitation period which is
shortest and therefore most advantageous to the defendant.
55 In Brisbane City Council v Amos, the plaintiff council commenced
proceedings to recover overdue and unpaid rates levied on rateable land owned by
the defendant. The council was statutorily empowered to levy rates, with the
overdue rates being supported by a charge on the relevant land. Under s 10(1)(d)
of the Limitation of Actions Act 1974 (Qld), an action “shall not be brought after
the expiration of 6 years from the date on which the cause of action arose … to
recover a sum recoverable by virtue of any enactment.” Under s 26(1) of the same
Act, an action “shall not be brought to recover a principal sum of money secured
by a mortgage or other charge on property … after the expiration of 12 years from
the date on which the right to receive the money accrued.” The land owner pleaded
the shorter six year limitation period under s 10(1)(d) in its defence, whereas the
council maintained that the longer 12 year limitation period under s 26(1) applied.
56 The High Court held that s 26(1) did not exclude the operation of the shorter
period in s 10(1)(d). Both the 12 year limitation period in s 26(1), and the six year
limitation period in s 10(1)(d), applied concurrently to the council’s action and it
28 Cf the form of limitation provision considered in Attorney-General (Cth) v Oates (1999) 198 CLR 162
(“Despite anything in any other law, proceedings for an offence against this Law may be instituted
within a period of 5 years …”).
29 Brisbane City Council v Amos (2019) 266 CLR 593.
30 Brisbane City Council v Amos (2019) 266 CLR 593 at [40]-[41] (Gageler J).
-- 16 of 34 --
[2024] SASCA 67 The Court
15
was open to the land owner defendant to plead and rely upon the shorter limitation
period.
57 Their Honours accepted that ss 10(1)(d) and 26(1) had overlapping fields of
operation, including in respect of the council’s action against the land owner.31 The
land owner could thus rely upon the shorter limitation period in defence of the
claim unless there was some reason or basis for construing the longer limitation
period in s 26(1), where it applies, as excluding the operation of the shorter
limitation period in s 10(1)(d).32 Their Honours were unable to discern any basis
in the text, context or purpose of these provisions for giving s 26(1) this effect. To
the contrary, the text and other considerations (including the legislative history and
previous legal treatment of these provisions) supported their concurrent operation,
with a defendant entitled to rely upon the shorter limitation period.33
58 Put another way, in the case of different limitation periods with overlapping
fields of operation, the longer limitation period does not necessarily – or of itself
– operate to displace the shorter limitation period or otherwise extend the time
within which a relevant action may be brought. The longer limitation period may
continue to operate as something in the nature of a long stop provision, but with a
defendant in an action to which the shorter limitation period applies able to rely
upon the shorter limitation period in defence of that action.
59 The issue thus becomes whether there is anything in the text, context or
purpose of the provision with the longer limitation period that excludes the
operation of the shorter limitation period where they overlap. Translated into the
context of the present case, the issue becomes whether there is anything in the text,
context or purpose of s 73 of the DA that supports the exclusion of the operation
of the shorter five year limitation period in s 32(5) of the BWCA where they
overlap in their operation.
60 The Owners rely in this respect upon the third of the textual considerations
identified above, namely the introductory words to s 73 (“[d]espite the Limitation
of Actions Act 1936, or any other Act or law”).
61 The Owners argue that these words indicate a legislative intention that s 73
override any other limitation provision or law within the scope of its operation,
thereby displacing the limitation provision in s 32(5) of the BWCA.
62 This argument involves an unduly blunt or simplistic approach to the work
to be done by these introductory words. It is to be accepted that the use of the
word “despite” indicates an intention that the limitation period in s 73 may operate
to override another provision or law in relation to time limits. This reflects the
31 Brisbane City Council v Amos (2019) 266 CLR 593 at [3]-[4] (Kiefel CJ and Edelman J), [46]
(Gageler J).
32 Brisbane City Council v Amos (2019) 266 CLR 593 at [7] (Kiefel CJ and Edelman J), [38] (Gageler J).
33 Brisbane City Council v Amos (2019) 266 CLR 593 at [37] (Kiefel CJ and Edelman J), [39]-[43], [46]
(Gageler J), [48]-[49], [52] (Keane J), [54]-[56] (Nettle J).
-- 17 of 34 --
[2024] SASCA 67 The Court
16
dictionary meaning of the preposition “despite”; namely, “without being affected
or prevented by”, or “regardless of”. It is also consistent with its use as a synonym
for the word “notwithstanding”.34 However, the use of the word “despite” does not
indicate an intention that the limitation period in s 73 will necessarily operate to
displace any alternative limitation period whenever they overlap in their operation.
It merely indicates an intention that s 73 override another provision or law which
would operate inconsistently with s 73.
63 As explained above, by reference to the High Court’s reasoning in Brisbane
City Council v Amos, there is no inherent or necessary inconsistency between two
limitation provisions with an overlap in their fields of operation. Both may operate
concurrently as restrictions upon the right sought to be exercised by a plaintiff,
with the defendant entitled to rely upon the shorter (or more restrictive) of the two
provisions as barring the plaintiff’s claim.
64 Understood in this way, the use of the word “despite” in s 73 does not, by
itself, mean that the section operates to displace the shorter limitation period in
s 32(5).
65 The Owners contend that the primary judge’s similar explanation of the
meaning of the word “despite” reflects an inappropriately nuanced meaning of
“despite”, rather than its ordinary meaning. Although the primary judge did
describe her approach as involving a “nuanced” construction,35 this should not be
taken as indicating a departure from the ordinary meaning of the word. In
reasoning that there must be some inconsistency or conflict between s 73 and the
other limitation provision or law before s 73 overrides that other provision or law,
and rejecting the submission that s 73 automatically displaces any other limitation
provision or law with an overlapping operation, her Honour was not departing
from the ordinary meaning of the word “despite”. She was supporting a careful
approach to the meaning of “despite”; but supporting a meaning which
nevertheless reflects the ordinary meaning of that word, and indeed perhaps better
reflects it than the more simplistic approach contended for by the Owners.
66 The above should not be taken as indicating that the suggested meaning for
the word “despite” does not involve a constructional choice, or that the word
cannot bear the meaning contended for by the Owners. For that reason it remains
relevant to consider the range of contextual and purposive considerations
addressed in the balance of these reasons. However, as will be explained, these
considerations support rather than undermine the suggested meaning of the
introductory words of s 73.
67 Finally, before leaving the meaning of the word “despite”, we add, as the
primary judge observed,36 that to adopt the meaning of the word suggested is not
34 Attorney-General (Cth) v Oates (1999) 198 CLR 162 at [33] (Gleeson CJ, McHugh, Gummow, Kirby
and Hayne JJ).
35 Reasons at [86], [88].
36 Reasons at [91]-[93].
-- 18 of 34 --
[2024] SASCA 67 The Court
17
to render it, or the introductory words of s 73 more generally, redundant. They
will have work to do where there is an inconsistency or conflict between s 73 and
some other limitation provision or law.
68 An example is in the operation of the power to extend the time for the
commencement of an action under s 48 of the Limitation of Actions Act. While the
terms of that power permit an extension of the six year limitation period for
contractual and tortious actions for damages for defective building work, to permit
an extension beyond 10 years from the date of completion of the building work
would, if s 73 is construed as a long stop limitation period, be inconsistent with the
non-extendable 10 year period provided for by s 73. The same applies to s 45 of
the Limitation of Actions Act.
69 By way of further example, it will be recalled that the six year limitation
period in respect of tortious claims under s 35(c) of the Limitation of Actions Act
commences from the date the cause of action accrues. In the case of a claim based
upon a latent defect in building work, this may result in a limitation period which
does not expire until more than 10 years from completion of the building work.
Again, if s 73 is construed as a long stop limitation period, the potential for the
period contemplated by s 35(c) to extend beyond the 10 years provided for in s 73
would be inconsistent with s 73.
70 No equivalent inconsistency with the intended operation of s 73 can arise in
relation to claims subject to the five year time limit under s 32(5) of the BWCA,
because the five year period commences to run from the date of completion and is
not able to be extended. Nevertheless, the examples mentioned demonstrate the
work to be done by the 10 year limitation period under s 73 when construed as a
long stop limitation period operating concurrently with other limitation periods.
71 We acknowledge that the potential inconsistencies we have mentioned might
be met with a response, by reference to the reasoning in Brisbane City Council v
Amos embraced above, that they are not in fact inconsistencies; that in the
circumstances posited, the 10 year limitation period under s 73 of the DA would
apply because the defendant could choose to rely upon it as the shorter of the
alternative limitation periods. Whilst there is some force in this response in the
case of a latent defect resulting in the limitation period prescribed by s 35(c) of the
Limitation of Actions Act, it does not have the same force in respect of the power
of the court under s 48 to extend the time for the institution of an action. In the
latter case, it is not apparent (or at least not readily apparent) that the approach in
Brisbane City Council v Amos would enable a defendant to avoid the consequences
of such an extension. In any event, for the reasons developed elsewhere in these
reasons, we consider that the operation of s 73 as a long stop provision is the
proper, or preferable, construction of s 73. Even if the examples we have raised
do not, strictly speaking, involve inconsistences, the introductory words have work
to do in confirming the primacy of s 73 in its operation as a long stop limitation
provision.
-- 19 of 34 --
[2024] SASCA 67 The Court
18
Broader contextual and purposive considerations
72 In addition to the more textually-based considerations addressed in the
preceding section of these reasons, it is also appropriate to have regard to the
broader contextual and purposive considerations relied upon by the parties in
construing s 73 of the DA (and s 159 of the PDIA).
The regulation of domestic building work
73 The BWCA recognises and regulates a particular class of building work in
South Australia, defined as “domestic building work” and being essentially
building work carried out on a “house”. As the primary judge explained in some
detail,37 this class of building work has, for a long time, been more highly regulated
by comparison with other building work.
74 The provisions of the BWCA governing domestic building work are
primarily located in Part 5 of that Act. In particular, Divisions 1 to 6 of Part 5
operate in various ways to ensure minimum standards in the allocation of
contractual risk between builders and house owners. The evident purpose of these
provisions is the protection of house owners as against builders. At the same time,
they also represent a careful balance struck between the interests of house owners
and builders.
75 The provisions of Division 1, inter alia, impose various requirements in
relation to the formalities and content of domestic building contracts, including the
determination and specification of the price and payment terms. Division 2
contains the statutory warranties the subject of the underlying proceeding.
Divisions 3 (insurance), 4 (termination) and 6 (harsh and unconscionable terms)
provide other protections that are not presently relevant. Division 5 governs the
powers of the court in relation to disputes concerning domestic building work.
76 Returning to Division 2, we have already outlined its key provisions. In
summary, under s 32, house owners are provided with certain transmissible
statutory warranties as to the quality and timeliness of the building work. The
warranties are able to be enforced against the builder through orders for remedial
work or monetary relief. They are subject to a non-extendable time limit of five
years from the completion of the building work.
77 By comparison with the position at common law, the statutory warranties
represent significant extensions of the liability of builders in favour of house
owners, and a key aspect of the protections they are afforded under Part 5. At the
same time, the non-extendable five year time limit upon claims based upon these
statutory warranties represents an aspect of the balance struck between house
owners’ and builders’ interests, both in relation to the statutory warranties in
s 32(2) and the provisions of Part 5 more generally.
37 Reasons at [94]-[109].
-- 20 of 34 --
[2024] SASCA 67 The Court
19
78 As the primary judge observed,38 the replacement of the non-extendable five
year time limit under s 32(5) of the BWCA with a 10 year time limit under s 73 of
the DA would involve a material disruption of the balance struck between the
interests of house owners and builders under the BWCA. It would be somewhat
incongruous for the legislature to have intended such a fundamental change in
policy without clearly expressing such an intent.
79 Further, this incongruity is underscored by the fact that the balance struck in
Division 2 of Part 5 of the BWCA reflects a legislative policy that has a long
history in South Australia.39
80 The BWCA itself was assented to on 7 December 1995, and commenced
operation on 1 June 1996. No relevant amendments have been made to Part 5 of
the Act since its enactment.
81 However, the BWCA was preceded by, and repealed, the Builders Licensing
Act 1986 (SA). This 1986 legislation provided for the licensing and control of
builders generally, but also regulated building work defined as “domestic building
work”. In particular, Part 5 of that earlier legislation contained provisions in nearly
identical terms to Part 5 of the BWCA, including provisions implying six
transmissible statutory warranties into every domestic building contract.
82 This 1986 legislation was in turn preceded by, and repealed, the Builders
Licensing Act 1967 (SA). It was this 1967 legislation which had introduced a
system for licensing and controlling builders. And in 1983, it was amended to
introduce various provisions intended to protect the interests of house owners
against builders for domestic building work.40 It was these amendments which
introduced the concept of “domestic building work”, with a definition in
substantially the same form as the current definition in the BWCA. These
amendments also introduced four transmissible statutory warranties to be implied
in favour of house owners, and imposed a non-extendable time limit in respect of
those statutory warranties of five years from the date of completion of the relevant
work.
83 These 1983 amendments included the repeal of the Defective Houses Act
1976 (SA), which had regulated the construction and sale of new houses. This
1976 legislation had introduced three basic implied statutory warranties in
contracts for the construction and sale of new houses, with rights of subrogation in
favour of successor owners.41 These rights of subrogation were subject to a time
limit in the sense that they only applied to a person who purchased or acquired a
house within five years of it first being occupied.42 However, the 1976 legislation
38 Reasons at [109].
39 Reasons at [110]-[120].
40 Builders Licensing Act Amendment Act 1983 (SA).
41 Defective Houses Act 1976 (SA), s 4.
42 Defective Houses Act 1976 (SA), s 4(3).
-- 21 of 34 --
[2024] SASCA 67 The Court
20
had not otherwise placed any time limit upon claims based upon the implied
warranties.
84 In summary, the notion of transmissible statutory warranties by builders in
favour of house owners, but confined to domestic building work and a period of
five years, has formed part of the legislative landscape in South Australia since
1976. It follows that the balance struck in the present provisions of the BWCA
has a long legislative history that has survived several amendments to the relevant
legislation. As mentioned, this observation serves to underscore the incongruity
inherent in construing s 73 of the DA as materially disrupting that balance without
any clear indication of a legislative intention to do so.
The regulation of building work more generally
85 The provisions of Division 7 of Part 6 of the DA, and subsequently Division
7 of Part 11 of the PDIA, have been set out earlier.
86 While the provisions of the BWCA are confined in their operation to
“domestic building work”, the 10 year time limit under s 73 of the DA, and s 159
of the PDIA, applies to claims in relation to defective building work more
generally, including commercial building work. It applies to all claims for
damages for economic loss or rectification costs arising from defective building
work,43 regardless of the underlying cause of action; that is, regardless of whether
the claim is brought for breach of contract, a tort (such as negligence or nuisance)
or a breach of statutory duty. And, unlike claims under s 32 of the BWCA, the
class of potential defendants in respect of whom it applies is not confined to
builders; it extends to claims against others involved in building work such as
architects, engineers, surveyors, certifiers and developers.
87 As the primary judge observed,44 it is uncontroversial that the broad statutory
purpose of s 73 of the DA, and its successor s 159 of the PDIA, is to promote
finality in building disputes and litigation by addressing the notorious difficulties
in building actions arising from uncertainty about the operation of time limits, and
in particular the potentially open-ended liability that might arise from latent defects
(particularly when they arise from design work early in the life of the relevant
project), and the extendable nature of the six year time limits for contractual and
tortious claims under the Limitation of Actions Act.
88 The key feature of the legislative response to this mischief in the pre-existing
legal landscape was to provide greater certainty in the operation of relevant time
limits through the imposition of an overarching time limit which commences to
run from the completion of the building work, and ends 10 years from that point
in time. The non-extendable 10 year period was plainly intended to represent a
fair and reasonable balance between providing potential defendants (and their
43 With claims for damages for death or personal injury excluded under s 73(2) of the DA.
44 Reasons at [128].
-- 22 of 34 --
[2024] SASCA 67 The Court
21
insurers) with the certainty of a clear end point for their exposure, and ensuring
that potential plaintiffs have an adequate opportunity to commence claims.
89 This objective would be achieved by treating s 73 of the DA as introducing a
long stop limitation period; that is, a limitation period which represents an end
point for the commencement of all claims for damages of the relevant type. It does
not require that s 73 be construed as operating to replace all other (shorter) time
limitation provisions in respect of the claims to which it applies.
90 Construing s 73 as displacing shorter time limitation provisions, through the
imposition of a single time period of universal application in claims for damages
of the relevant type, might be said to create even greater certainty than construing
it as a long stop provision. It might be said to do so by replacing multiple
potentially applicable time limits with a single time limit applicable for all
defective building claims caught by s 73.
91 However, construing s 73 in this way would go beyond addressing the
mischief and purpose described above. It would permit s 73 to operate to extend
the time within which claims under s 32 of the BWCA may be brought from five
years to 10 years. It would permit s 73 to operate to extend the time within which
common law contractual or tortious claims might be brought, even when the six
year time limit under the Limitation of Actions Act has clearly expired and there is
no basis for any extension of that time limit under s 48 of that Act. There does not
appear to be any firm basis for thinking that the mischief to be addressed, and
hence the purpose or intention of introducing s 73, extended beyond the
uncertainty associated with the potentially open-ended nature of the operation of
the existing time limitation provisions; or for thinking that the purpose or intention
of s 73 was to introduce a single universally applicable limitation provision for
affected claims, and in effect to extend the time within which potential plaintiffs
might bring their claims.
92 Construing s 73 as involving the introduction of a universally applicable time
limit of 10 years for claims of the relevant type would also not only materially
disrupt the careful and long-standing balance struck in the context of domestic
building work in the BWCA, but it would also do so in a way which might be
described as lacking coherence (as described below). On the other hand,
construing s 73 of the DA as introducing a long stop provision would permit that
section to achieve its apparent purpose without interfering with the balance struck
by s 32 of the BWCA, and in that sense permit the concurrent and harmonious
operation of both provisions.
Incoherence
93 Construing s 73 of the DA and s 159 of the PDIA as replacing the five year
time limit in s 32(5) of the BWCA would not only materially disrupt the balance
struck by s 32, but also introduce an element of incoherence in the way in which
that section operates.
-- 23 of 34 --
[2024] SASCA 67 The Court
22
94 By way of explanation, even if s 73 of the DA were to be construed as
replacing the five year time limit in s 32(5), it could only do so in respect of claims
within the former’s field of operation. It could only do so in relation to claims for
damages for economic loss or rectification costs arising from defective building
work. It could not do so, for example, in relation to claims arising from a breach
of the statutory warranty to perform the building work with reasonable diligence
(s 32(2)(d) of the BWCA). Nor could it do so in relation to claims seeking an order
for remedial work (s 37(6)(a)), rather than monetary relief in the form of
compensation for the breach (s 37(6)(b)).
95 A consequence of the Owners’ construction of s 73 would thus be to replace
the five year time limit under s 32(5) of the BWCA with a 10 year time limit in
relation to some claims under s 32, but not others. The Owners seek to justify
these differing time limits for claims under s 32 on the basis that there is good
reason to think that Parliament might have intended shorter time frames would be
appropriate for claims arising from delay in completing building work, and claims
for remedial work. Whilst it was suggested that such claims might tend to be more
appropriate when brought closer in time to the building work being carried out,
there does not seem to be any basis for attributing this quite specific intention to
Parliament, or for otherwise distinguishing between the different types of claims
that might be brought under s 32 of the BWCA in this way.
96 In circumstances where there is no clear basis for distinguishing between the
different types of claims that might be brought under s 32 in this way, it may be
said that the Owners’ construction of s 73 of the DA, and s 159 of the PDIA, would
bring a degree of incoherence to the operation of s 32 of the BWCA.
Generalia specialibus non derogant
97 The Builder seeks to draw support for its construction of ss 73 and 159 from
an application of the maxim generalia specialibus non derogant.
98 The maxim was described in the following terms by O’Connor J in Goodwin
v Phillips:45
Where there is a general provision which, if applied in its entirety, would neutralize a
special provision dealing with the same subject matter, the special provision must be read
as a proviso to the general provision, and the general provision, in so far as it is inconsistent
with the special provision, must be deemed not to apply.
99 The rationale for the maxim was explained by Barton ACJ in Maybury v
Plowman:46
The judgment under appeal turns upon the application of the principle involved in the
maxim “generalia specialibus non derogant” to cases in which the legislature, after having
dealt specially with a particular matter, has afterwards passed an enactment in general terms
wide enough to repeal, or supersede, or qualify the original provision. … I wish to quote a
45 Goodwin v Phillips (1908) 7 CLR 1 at 14 (O’Connor J).
46 Maybury v Plowman (1913) 16 CLR 468 at 473-474 (Barton ACJ) (citations omitted).
-- 24 of 34 --
[2024] SASCA 67 The Court
23
passage from the judgment of Wood V.C. in Fitzgerald v. Champneys, quoted by Stirling J.
in the case cited as follows: - “The reason in all these cases is clear. In passing the special
Act, the legislature had their attention directed to the special case which the Act was meant
to meet, and considered and provided for all the circumstance of that special case; and,
having so done, they are not to be considered by a general enactment passed subsequently,
and making no mention of any such intention, to have intended to derogate from that which,
by their own special Act, they had thus carefully supervised and regulated.”
100 A helpful articulation of the maxim also appears in Halsbury’s Laws:47
It is difficult to imply a repeal where the earlier enactment is particular, and the later
general. In such a case the maxim generalia specialibus non derogant (general things do
not derogate from special things) applies. If Parliament has considered all the
circumstances of, and made special provision for, a particular case, the presumption is that
a subsequent enactment of a purely general character would not have been intended to
interfere with that provision; and therefore, if such an enactment, although inconsistent in
substance, is capable of reasonable and sensible application without extending to the case
in question, it is prima facie to be construed as not so extending. The special provision
stands as an exceptional proviso upon the general. If, however, it appears from a
consideration of the general enactment in the light of admissible circumstances that
Parliament’s true intention was to establish thereby a rule of universal application, then the
special provision must give way to the general.
101 In approving this articulation of the maxim in the House of Lords decision in
Re McE,48 Lord Carswell explained that, like other linguistic canons, it operates
not as a technical rule, but rather as an application of common sense, logic and
other textual considerations used in discerning legislative intention.49
102 In the context of the present case, the primary judge did not explicitly rely
upon this maxim. Her Honour rejected a submission by the Owners to the effect
that ss 73 and 159 could be regarded as the more specific provisions because they
are directed at damages for economic loss and rectification costs resulting from
defective building work.50 Later in her reasons, her Honour accepted that s 32(5)
of the BWCA should be construed as the more specific provisions, with s 73 of the
DA and s 159 of the PDIA the more general provisions, adding that “Part 5 of the
[BWCA] enacts a specific scheme for the purpose of regulating domestic building
work that could be undermined if s 73 of the [DA] and s 159 of the [PDIA] were
construed as displacing the five-year limitation period in s 32(5)”.51 However, her
Honour did not consider it necessary to construe s 32(5) as a proviso to ss 73 and
159 because she had been able to reconcile them by construing them as operating
concurrently.52
103 We agree with her Honour that there is no need in the present case to describe
s 32(5) as operating as a proviso to ss 73 and 159, at least not in any strict sense.
47 Halsbury’s Laws of England (4th edition, 1995) vol 44(1), [1300] (citations omitted).
48 Re McE [2009] 4 All ER 335.
49 Re McE [2009] 4 All ER 335 at [98] (Lord Carswell).
50 Reasons at [135].
51 Reasons at [178].
52 Reasons at [178].
-- 25 of 34 --
[2024] SASCA 67 The Court
24
We would only qualify her Honour’s observations by adding that this does not
exhaust the relevance of the considerations that underpin the maxim, and in
particular the primacy generally afforded to more specific provisions over more
general provisions. That is particularly so where, as here, the specific provisions
reflect a careful and long-standing balancing of interests, and the general provision
was enacted later in time without any clear indication of a legislative intention to
disturb that balance.
104 Whilst the Owners point to the introductory words of ss 73 and 159 as
indicating a clear legislative intention to disturb that balance, we have already
explained why that is not so. The relative specifity of s 32(5), and generality of
ss 73 and 159, support a construction of the latter provisions which permits both
s 32(5) and ss 73 and 159 to operate concurrently, with the shorter time limit in
s 32(5) able to be relied upon where both apply.
Extrinsic materials
105 We have made some general observations as to the apparent mischief and
purpose underpinning the introduction of s 73 of the DA (and its re-enactment
through s 159 of the PDIA).
106 As the primary judge observed, the use of extrinsic material is expressly
authorised by s 16 of the Legislation Interpretation Act in certain circumstances.
However, as the primary judge also observed, the parties accepted that no
assistance could be gained from the relevant materials in resolving the question of
construction to be resolved in these proceedings.
107 While the second reading speech preceding the introduction of the DA made
reference to the legislation being “the culmination of a process of study, review,
and consultation over a period of almost three years”,53 the only reference to s 73
was in terms that it “restricts the time within which an action for damages for
economic loss or rectification costs arising from defective building work to the
period of 10 years”.54 It was accepted that there was nothing in the second reading
speech or other extrinsic materials that added to what could be gleaned from the
matters already addressed in relation to the existing legal landscape as to the
regulation of building work and time limitation provisions, the legislative history
of s 32 of the BWCA, and the coherent and harmonious operation of the relevant
provisions.
108 For completeness, we mention that there was, in the early 1990s, a push to
adopt a nationally consistent approach to the regulation of building work, including
through the introduction of a 10 year limitation period. Whilst this effort was
generally unsuccessful, each of the States and Territories other than Queensland
53 South Australia, Parliamentary Debates, House of Assembly, 10 March 1993, 2433 (GJ Crafter).
54 Ibid, 2441; the second reading speech also made reference to the planning review, being the ‘2020
Vision’ Report dated June 1992, which also made reference (p 30) to the then proposed legislation
limiting liability by putting a time limit on it.
-- 26 of 34 --
[2024] SASCA 67 The Court
25
and Western Australia have since introduced 10 year limitation periods for
building work.
109 However, there is no uniformity in the legislative provisions through which
this time limit has been introduced. Indeed, they are each expressed quite
differently. Whilst some of these provisions (for example, in New South Wales55
and the Australian Capital Territory56) make it plain they are intended merely as
long stop provisions, others are less clear and at least leave open a construction
which would have them operating to the exclusion of shorter limitation periods
where they overlap in their operation.57 Indeed, as will be seen, the Victorian
provision was construed in this way by the Court of Appeal in Brirek Industries
Pty Ltd v McKenzie Group Consulting (Vic) Pty Ltd.58
110 In the circumstances, no assistance in resolving the present matter can be
obtained from a consideration of the push for national consistency or the
patchwork of 10 year limitation periods for building disputes that exist across the
various States and Territories.
Authority
111 The Owners seek to draw support for their construction of s 73 of the DA and
s 159 of the PDIA from the decision of the Victorian Court of Appeal in Brirek
Industries Pty Ltd v McKenzie Group Consulting (Vic) Pty Ltd (Brirek). However,
as the primary judge explained, this authority is distinguishable and ultimately of
little assistance in the present matter.59
112 In that case, the owner of an office building sued a building surveyor involved
in the construction of the building. The proceeding included claims arising under
a 2004 contract that had been introduced through an amendment to the owner’s
statement of claim. The trial judge concluded that the limitation period for these
claims was six years, as provided in s 5(1)(a) of the Limitation of Actions Act 1958
(Vic). His Honour rejected the owner’s contention that s 134 of the Building Act
1993 (Vic), which provided for a 10 year limitation period for building actions,
altered the limitation period. Section 134 of the Building Act was in the following
terms:
134—Limitation on time when building action may be brought
Despite anything to the contrary in the Limitation of Actions Act 1958 or in any other Act
or law, a building action cannot be brought more than 10 years after the date of issue of the
occupancy permit in respect of the building work …
113 The trial judge concluded that s 134 operated as a long stop provision
applicable to negligence claims involving latent defects, and did not operate to
55 Environmental Planning and Assessment Act 1979 (NSW), s 6.20(4).
56 Building Act 2004 (ACT), s 142(3).
57 Building Act 1993 (Vic), s 134; Building Act 1992 (NT), ss 160-161; Building Act 2016 (Tas), s 327.
58 Brirek Industries Pty Ltd v McKenzie Group Consulting (Vic) Pty Ltd (2015) 48 VR 550.
59 Reasons at [148]-[169].
-- 27 of 34 --
[2024] SASCA 67 The Court
26
extend the six year limitation period applicable to contractual claims under the
Limitation of Actions Act. Treating the contractual claims as having been
commenced on the date of the relevant amendment, they were out of time.60
114 In its joint reasons, the Court of Appeal (Redlich, Whelan and
Santamaria JJA) allowed the owner’s appeal on two grounds. The first was that
the 10 year limitation period under s 134 of the Building Act operated to the
exclusion of the shorter six year limitation period under s 5 of the Limitation of
Actions Act, and that the trial judge erred in concluding otherwise.61 The second
was that the trial judge erred in failing to apply the doctrine of ‘relation back’ with
the result that the contractual claims were not out of time even if the shorter six
year limitation period was applicable.62
115 In its reasoning on the first issue, the Court commenced by referring to the
second reading speech of the Minister for Planning for the Building Bill 1995 (Vic)
which contained s 134.63 The Minister had made reference to confusion in building
claims over when the existing six year limitation period started and ended,
including by reason of the difficulty in ascertaining when damage occurred. The
Minister explained that this had given rise to liability with an effective limitation
period of “infinity plus six” years, and hence “absurdly open-ended” liability. The
Bill was described as providing a clear start date (the issue of an occupancy permit)
and end date (10 years from the issue of that permit) for calculating time. It was
said that this would remove the existing ambiguity, and also provide property
owners with additional protection beyond “the very short number of years” that
then existed for bringing claims. It was also said that the “10-year cap” reflected
international trends and laws that had been promulgated in the Northern Territory,
South Australia and New Zealand over the past 18 months.
116 The Court said that the background to the introduction of s 134 was “well
known and not controversial”, referring to difficulties associated with determining
when time began to run for negligence claims (given that latent defects may not be
discovered for some time), and with the ability to obtain insurance for long-tail
claims.64 Their Honours noted that legislation had been enacted in various
jurisdictions to provide some relief from the problem, but that the terms of the
legislation differed between jurisdictions.65 Whilst acknowledging the relevance
of understanding the problem or mischief to be addressed when construing
legislation, their Honours emphasised that the task was “to identify the solution
that recommended itself to Parliament”; and “to construe the statutory provision,
not the second reading speech”. Accordingly, “[t]he court must be astute not to
bend the words of the statute to accommodate some other solution to the problem
60 Brirek at [7], [92], [94].
61 Brirek at [136].
62 Brirek at [203].
63 Brirek at [93].
64 Brirek at [103]-[105].
65 Brirek at [106].
-- 28 of 34 --
[2024] SASCA 67 The Court
27
that it may think the more desirable, or which some other jurisdiction has
adopted”.66
117 The Court criticised the trial judge’s focus upon s 134 providing a long stop
time limit for negligence claims, holding that the section applied to both
negligence and contractual claims; that there was nothing in the text of the section
to confine its operation to negligence claims.67 Their Honours later added that this
construction of s 134 was consistent with the reference in the second reading
speech to additional protection beyond the short periods that then existed for
bringing claims, which it considered must have been, or included, a reference to
contractual claims.68
118 Referring to the opening words of s 134 (“Despite anything to the contrary
in the Limitation of Actions Act 1958 or in any other Act or law”), the Court said
that this meant that where another Act provided for a different period of limitation,
then the period provided for in s 134 operated despite that different period.69 In
this way, the time limit in s 134 operated to the exclusion of the time limit in s 5
of the Limitation of Actions Act.
119 The Court added that support for this conclusion was found in s 33 of the
Limitation of Actions Act:
33—Saving
The periods of limitation prescribed by this Act shall not apply to any action or arbitration
for which a period of limitation is prescribed by any other enactment including, without
affecting the generality of the foregoing, and except as provided in Part IIA, the provisions
of section twenty-nine of the Administration and Probate Act 1958 and section twenty of
the Wrongs Act 1958.
After observing that this section had not been relied upon at trial,70 the Court held
that it prevented s 5 of the Limitation of Actions Act operating with respect to
building actions. It did so because s 134 of the Building Act was “a period of
limitation … prescribed by any other enactment” within the meaning of s 33.71
120 The Court also mentioned another broader contextual matter supporting its
construction of s 134, being certain amendments to the Building Act, made
contemporaneously with amendments to the Limitation of Actions Act, which
expressly dealt with long stop limitation provisions but did not introduce any long
stop provision for building actions.72
66 Brirek at [108] (citations omitted).
67 Brirek at [112]-[114].
68 Brirek at [118].
69 Brirek at [115].
70 Brirek at [97].
71 Brirek at [116].
72 Brirek at [119]-[126].
-- 29 of 34 --
[2024] SASCA 67 The Court
28
121 After then addressing several authorities, which did not directly assist, their
Honours stated their conclusion in the following terms:73
The words of s 134 of the Building Act should not be read down so that they are confined
in their operation to claims in tort in such a way that it is only those claims that have the
benefit of, and are subject to, the 10-year limitation period stipulated. The construction
given to s 134 by the trial judge imposes unwarranted limitations on the scope and
applicability of the section. In our opinion, actions founded in contract, independent of any
tort claim, fall within the scope of s 134 and may be brought within 10 years from the date
of issue of the occupancy permit.
Accordingly, the trial judge was wrong to hold that the claims made in reliance upon the
2004 contract were statute-barred.
122 Not surprisingly, given the similarity between the introductory words of
s 134 of the Building Act in Brirek and ss 73 and 159 in the present case, the
Owners relied heavily upon the reasoning of the Court of Appeal in Brirek.
123 In considering the significance of the Court’s reasoning in Brirek to the
present case, the first point to note is that because the Court decided that, applying
the doctrine of ‘relation back’, the contractual claims were not out of time even if
the shorter six year limitation period under s 5 of the Limitation of Actions Act was
applicable, the Court’s conclusion that s 134 of the Building Act operated to
exclude the operation of the time limit under s 5 was not strictly necessary for the
resolution of the appeal.
124 More significantly, even though there are some similarities between the
wording of the Victorian provision and the South Australian provisions under
consideration in the present case, the differences between the issues arising in
Brirek and the present case, and in the broader statutory contexts relevant to their
resolution, mean that the reasoning of the Court in Brirek is distinguishable on
several grounds.
125 First, there is no equivalent of s 33 of the Victorian Limitation of Actions Act
in the South Australian Limitation of Actions Act. This is critical given the reliance
that the Court in Brirek placed upon s 33. Given the existence of s 33 in the
Victorian Limitation of Actions Act, the Court’s conclusion that s 134 of the
Building Act operated to exclude the operation of the time limit under the
Limitation of Actions Act was inevitable.
126 Secondly, the matter directly in issue in the present case concerns whether
the relatively generally expressed and stand alone provisions in ss 73 and 159
operate to displace the time limitation provision under s 32(5) of the BWCA, being
a specific provision which forms a key part of the balance struck under s 32 in
relation to domestic building work disputes. The reasoning in Brirek, on the other
hand, concerned whether a time limitation provision (s 134) which existed as part
of an Act (the Building Act) regulating building work in a fairly detailed and
73 Brirek at [135]-[136].
-- 30 of 34 --
[2024] SASCA 67 The Court
29
comprehensive manner operated to displace the general time limitation provision
applicable to tortious and contractual claims under the Limitation of Actions Act.
127 It may also be observed in passing that, whilst there is Victorian legislation
providing transmissible warranties in relation to domestic building work,74 it does
not contain any time limit in relation to claims based upon those warranties. As
reflected in a note to the legislation, the 10 year limitation period under s 134 of
the Building Act therefore applies to those claims. As such, the issue which arises
in the present case (being a contest between the differing time limits applicable to
warranty claims and defective building claims more generally) does not arise under
the Victorian legislation.
128 Thirdly, the second reading speech which accompanied the introduction of
s 134 of the Building Act made specific reference to extending the time for
plaintiffs to bring building actions. While the Court cautioned against over-
emphasising this contextual consideration at the expense of the language used by
the Parliament, their Honours ultimately attached some significance to this
articulation of the mischief and corresponding purpose. Whilst it might be said
that s 73 of the DA was South Australia’s response to the same general mischief,
there is no reference in any extrinsic material accompanying ss 73 or 159 to an
extension of the time within which plaintiffs might bring claims, as opposed to
merely providing defendants (and their insurers) with the certainty of an ultimate
time limit of 10 years from completion of the building work.
129 Fourthly, the Court in Brirek emphasised that s 134 was intended to operate
in relation not only to tortious claims but also to contractual claims. Implicitly, the
Court was concerned to ensure that s 134 had work to do in relation to those claims.
It gave it work to do in contractual claims by construing it as excluding the general
limitation provision for those claims under s 5 of the Limitation of Actions Act.
However, in South Australia, the contractual limitation period under s 35(a) of the
Limitation of Actions Act is subject to a general right to extend the six year time
limit under s 48 of that Act. As such, there is work for ss 73 and 159 to do as a
long stop limit upon extensions for contractual limitation periods, even without
construing those sections as displacing any shorter limitation periods.
130 In summary, there are critical differences between the issues, and the
statutory contexts in which they arose, in Brirek and the present case. As the Court
in Brirek emphasised, whilst the Victorian and South Australian provisions in
question were both enacted as responses to the same general mischief, and are
expressed in similar terms, their construction should not be approached with an
assumption that both Parliaments intended to adopt precisely the same solutions to
that mischief. Rather, the focus must be on the particular words used, but having
regard to the quite different statutory contexts in which those words were used.
74 Domestic Building Contracts Act 1995 (Vic), ss 8, 9 and 20.
-- 31 of 34 --
[2024] SASCA 67 The Court
30
Understood in this way, the reasoning of the Court in Brirek is distinguishable and
of limited assistance in the present case.
131 In addition, there are aspects of the reasoning in Brirek which, in our view,
limit its persuasiveness. In particular, their Honours do not appear to have had
regard to the various textual considerations addressed earlier in these reasons. In
particular, the Court approached the matter on the basis that there was a necessary
inconsistency between limitation provisions which overlapped in their operation.
Their Honours in effect assumed that different time limits were necessarily
inconsistent. However, in so concluding, their Honours did not address the
significance of the negative or proscriptive terms in which the time limit in s 134
was expressed, the potential for limitation provisions to operate concurrently in the
sense described in Brisbane City Council v Amos, and the implications of this for
the meaning of, and work to be done by, the introductory words to s 134. The
Court’s decision has been the subject of academic criticism for the failure to
address such matters.75
132 All things considered, whilst we have had had close regard to the reasoning
of the Victorian Court of Appeal in Brirek, we are not persuaded that the reasoning
in that case is of much assistance in the context of the present case.
133 The same may be said of the two District Court authorities relied upon by the
Owners: the decision of Judge Barrett in Aussie Blinds and Canvas Products Pty
Ltd v Smith (Aussie Blinds)76 and the decision of Judge O’Sullivan in Walford
Anglican School for Girls Incorporated v Romaldi Constructions Pty Ltd
(Walford).77 Having addressed at length our reasons for distinguishing the
reasoning in Brirek, it is not necessary to say much about these cases.
134 In Aussie Blinds, Judge Barrett merely applied the reasoning of the Victorian
Court of Appeal in Brirek in holding that s 73 of the DA applied to the exclusion
of the six year time limit under s 35 of the Limitation of Actions Act on the basis
that s 73 of the DA was materially the same as s 134 of the Building Act.78 His
Honour did not address any of the grounds on which we have suggested that the
reasoning in Brirek is distinguishable.
135 In Walford, Judge O’Sullivan construed s 73 of the DA as introducing a
single 10 year limitation period for building actions to which it applied, thereby
displacing the limitation period under s 35 of the Limitation of Actions Act that
would otherwise have been applicable. In holding that this construction of s 73
flowed from the introductory words of s 73,79 his Honour relied upon the decision
of the Victorian Court of Appeal in Brirek. However, his Honour also did so
75 See, for example, David Levin, ‘The Period of Limitation in Victorian Building Actions’ (2015) 31
BCL 268, referring at footnote 7 to various earlier articles and texts to similar effect, and generally in
support of the construction of s 134 as a long stop limitation provision.
76 Aussie Blinds and Canvas Products Pty Ltd v Smith [2015] SADC 154.
77 Walford Anglican School for Girls Incorporated v Romaldi Constructions Pty Ltd [2020] SADC 146.
78 Aussie Blinds at [30]-[31].
79 Walford at [162]-[164], [170]-[174].
-- 32 of 34 --
[2024] SASCA 67 The Court
31
without any consideration of either the distinctions between the statutory contexts
in which the issue arises in the two different jurisdictions, or the textual
considerations we have set out earlier in these reasons. Whilst his Honour
suggested that the mischief and purpose underpinning the legislation supported his
construction, it is unclear how his Honour discerned this mischief or purpose. The
only extrinsic material his Honour referred to was the excerpts from the second
reading speech set out earlier in these reasons,80 which the parties accept do not
assist in construing s 73. While his Honour made some reference to the difficulties
arising in relation to time limits in building actions, his Honour did not identify
any contextual or purposive support for construing s 73 as a single extended
limitation period, as opposed to a limitation period that operated concurrently with,
but as a long stop to, other applicable limitation periods.
Conclusion
136 In summary, the combined force of the various textual, contextual and
purposive considerations addressed above supports the construction of s 73 of the
DA and s 159 of the PDIA contended for by the Builder and accepted by the
primary judge. They support the conclusion that they operate as a 10 year long
stop limitation period in respect of claims for economic loss or rectification costs
arising out of defective building work, but do not operate so as to displace the five
year time limit for claims based upon the statutory warranties in respect of
domestic building work under s 32 of the BWCA.
137 It is not necessary for the disposition of this appeal to determine whether
ss 73 and 159 might nevertheless operate to displace the six year time limit for
tortious and contractual claims under ss 35(a) and (c) of the Limitation of Actions
Act.
138 In theory at least, they might do so despite the conclusion we have reached
in relation to the five year time limit under s 32 of the BWCA. They might do so
bearing in mind the general nature of s 35 of the Limitation of Actions Act (relative
to the detailed and specific nature of s 32 of the BWCA), and the specific reference
to the Limitation of Actions Act in the opening words of ss 73 and 159.
139 On the other hand, most of the considerations to which we have had regard
in construing ss 73 and 159 would apply equally to the overlap between their
operation and the operation of s 35 of the Limitation of Actions Act. It also seems
unlikely that Parliament would have intended that ss 73 and 159 operate so as to
displace some overlapping limitation provisions but not others without making that
clear.
140 For these reasons, having reached the view that ss 73 and 159 do not operate
to displace the five year limitation provision under s 32(5) of the BWCA, the better
view is that they also do not operate to displace the six year limitation provision
under s 35 of the Limitation of Actions Act. Their operation in relation to general
80 Including the planning review report referred to therein.
-- 33 of 34 --
[2024] SASCA 67 The Court
32
tortious and contractual claims is confined to their operation as a long stop
limitation period of 10 years from the date of completion of the building work
where those claims would not otherwise be barred by s 35 of the Limitation of
Actions Act (for example, by reason of the latent nature of the defect relied upon,
or the availability of an extension of time under s 48 of that Act).
Orders
141 We dismiss the Owners’ appeal.
-- 34 of 34 --