[2024] SASC 46
Applicant: CPB CONTRACTORS PTY LTD (ABN 98 00 893 667) AND HANSEN YUNCKEN PTY LTD
(ABN 38 063 384 056) JOINTLY AND SEVERALLY TRADING AS HYLC JOINT VENTURE
Counsel: MR B ROBERTS KC - Solicitor: KING & WOOD MALLESONS (NSW)
Respondent: STATE OF SOUTH AUSTRALIA Counsel: MR D O'LEARY SC WITH MS A DOECKE
KC - Solicitor: LK LAW
Interested Party: CELSUS PTY LTD No Attendance
Hearing Date/s: 19/12/2023, 20/02/2024, 22/02/2024
File No/s: CIV-23-012771
B
SUPREME COURT OF SOUTH AUSTRALIA
(Civil: Application)
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply
to this judgment. The onus remains on any person using material in the judgment to ensure that the intended use of that material does not breach
any such order or provision. Further enquiries may be directed to the Registry of the Court in which it was generated.
CPB CONTRACTORS PTY LTD AND HANSEN YUNCKEN
PTY LTD v STATE OF SA
[2024] SASC 46
Judgment of the Honourable Chief Justice Kourakis
28 March 2024
PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS
- DISCOVERY AND INTERROGATORIES - DISCOVERY AND INSPECTION
OF DOCUMENTS - PRODUCTION AND INSPECTION OF DOCUMENTS -
GROUNDS FOR RESISTING PRODUCTION - PRIVILEGE - PUBLIC
INTEREST IMMUNITY - CLAIM OF PRIVILEGE
PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS
- DISCOVERY AND INTERROGATORIES - DISCOVERY AND INSPECTION
OF DOCUMENTS - PRODUCTION AND INSPECTION OF DOCUMENTS -
GROUNDS FOR RESISTING PRODUCTION - PRIVILEGE - OTHER
GROUNDS
This was an application for the adjudication of various claims of public interest immunity and
parliamentary privilege made by the respondent for the purposes of resisting production to the
applicant of certain documents discovered in arbitral proceedings.
The applicant, comprised of two corporate entities undertaking a joint venture, contracted with the
interested party, Celsus Pty Ltd, to perform design and construction work for the proposed renovation
of the Royal Adelaide Hospital. That contract existed alongside a separate contractual relationship
between the interested party and the respondent, concerned with the design, construction, and
operation of the hospital for a fixed term. It was, in essence, the applicant’s contention that, during
the course of construction of the hospital, the respondent and the interested party wrongfully
prevented it from discharging its contractual obligations and conspired effectively to exclude it from
the project moving forward.
-- 1 of 31 --
In the underlying arbitral proceedings between the parties, the respondent discovered a number of
documents relevant to the issues in dispute, but over which it claimed, varyingly, public interest
immunity and parliamentary privilege. Those claims to immunity and privilege were premised, for
the most part, on the documents in question either being Cabinet documents, making reference(s) to
Cabinet discussions, or relating to the preparation of Cabinet documents such that this would reveal
the content of Cabinet documents. The respondent having raised a jurisdictional objection to the
arbitrator determining whether its resistance to production of those documents was well-founded, the
applicant approached the Court to determine its entitlement to production thereof.
Held, dismissing the application:
1. The documents over which the respondent claimed public interest immunity were properly
covered thereby, such that the applicant was not entitled to the production and inspection
thereof.
2. The documents over which the respondent claimed parliamentary privilege were properly
covered thereby, such that the applicant was not entitled to the production and inspection
thereof.
Adelaide Brighton Cement v South Australia (1999) 75 SASR 209; Commonwealth v Northern Land
Council (1993) 176 CLR 604; Sankey v Whitlam (1978) 142 CLR 1, considered.
Alister v The Queen (1983-1984) 154 CLR 404, 414-415.
Legal Services Commission v Trotter (1990) 54 SASR 74, 84-85.
-- 2 of 31 --
CPB CONTRACTORS PTY LTD AND HANSEN YUNCKEN PTY LTD v
STATE OF SA
[2024] SASC 46
Civil: Application
1 KOURAKIS CJ: This is an application for an adjudication of claims made by
the State of public interest immunity and parliamentary privilege in respect of
documents discovered in arbitral proceedings which are pending before the
Australian Centre for International Commercial Arbitration (ACICA). The State’s
claims are supported by open and closed (confidential) affidavits.
2 CPB Contractors Pty Ltd and Hansen Yuncken Pty Ltd (HYLC) were
unincorporated joint venturers in the construction of the new Royal Adelaide
Hospital (nRAH) and, together, the applicant in these proceedings. The
respondent, the State of South Australia (the State), and the interested party in this
action, Celsus Pty Ltd (Celsus), are also parties to the arbitral proceedings. Celsus
is the corporate trustee of the Celsus Trust, and was formerly known as SA Health
Partnership Nominees Pty Ltd. Celsus has elected not to participate in this
application and does not support either party in these proceedings. The
subject-matter of the dispute in the arbitration is the design and construction of the
nRAH.
3 The development of the nRAH Project was undertaken by way of a
private-public partnership. Celsus contracted with the State, through the South
Australian Minister for Health, to design, construct, and operate the nRAH for a
fixed 35-year period. One of the two claims made in the arbitral proceeding is
Celsus’ claim against the State. The other claim is made by Celsus against HYLC.
The arbitrations of those claims are being heard concurrently. The evidence in one
arbitration will be taken as evidence in the other.
4 The parties have each given discovery in the arbitral proceedings. This
application relates to documents discovered by the State over which it claims
public interest immunity or parliamentary privilege, either in whole or in part. The
State has produced redacted copies of some documents and has entirely withheld
others from production. The applicant seeks the production of those documents,
listed in the Updated Challenged Documents Schedule, on an unredacted basis.
The State’s position is that the redacted passages of the Updated Challenged
Documents Schedule are not relevant or that they do not support the applicant’s
case.
5 The applicant seeks the following orders:
1. an order that the Respondent provide to this court in unredacted format the
Challenged Documents for inspection;
2. in respect of Challenged Documents entirely withheld from production in the
ACICA Arbitrations:
-- 3 of 31 --
[2024] SASC 46 Kourakis CJ
2
a. an order that all the Challenged Documents be disclosed on an open basis in
the ACICA Arbitrations; or
b. in the alternative, an order that certain of the Challenged Documents
identifiable by reference to the ‘Document ID’ column of Annexure A be
disclosed on an open basis; or
c. in the alternative, an order that the Challenged Documents be disclosed on a
redacted basis in the ACICA Arbitrations, such redactions to be determined
by this court;
3. in respect of Challenged Documents disclosed on a redacted basis in the ACICA
Arbitrations:
a. an order that the Challenged Documents be disclosed on an open basis in the
ACICA Arbitrations; or
b. in the alternative, an order that certain of the Challenged Documents
identifiable by reference to the ‘Document ID’ column of Annexure A be
disclosed on an open basis; or
c. in the alternative, an order that redactions to certain of the Challenged
Documents identifiable by reference to the ‘Document ID’ column of
Annexure A be amended in a manner required by this court;
3A. An order in like terms to the orders set out at above [1]–[3] in respect of any
documents that are discovered by the Respondent subject to claims of public interest
immunity and/or parliamentary privilege pursuant to order 6 to 10 of the orders made
by the Honourable Kevin Lindgren AM KC on 6 December 2023 in ACICA Case
Nos. 2018–119 and 2018–124 regarding the Adequacy of Discovery Applications
by the Builder and the State.
4. such further or other orders as the court deems fit;
5. costs.
6 For the reasons which follow I uphold the State’s claims of parliamentary
privilege and public interest immunity.
The contractual relationships
7 The following is the context to HYLC’s claims in the arbitral proceedings.
8 HYLC and Celsus are parties to a contract dated 20 May 2011 for the design
and construction of the nRAH (the Construction Contract). The Construction
Contract was amended twice, first on 8 August 2011, and again on
31 January 2014. Celsus is also party to a separate project agreement with the
South Australian Minister for Health dated 20 May 2011, which was amended on
8 August 2011 and again on 31 January 2014 (the Project Agreement).
9 On or around 20 May 2011, Celsus, the State, and Donald Cant Watts Corke
Pty Ltd (DCWC) entered into an independent certifier agreement (the IC
Agreement), appointing DCWC as the independent certifier. A Financier Direct
-- 4 of 31 --
[2024] SASC 46 Kourakis CJ
3
Deed was entered into by the State, Celsus, and the financiers of the nRAH project,
SA Health Partnerships Pty Ltd and ANZ Fiduciary Services Pty Ltd (the
financiers).
10 There is no direct contractual relationship between HYLC and the State in
relation to the construction of the nRAH. Instead, the State entered into a ‘Builder
Direct Deed’ with HYLC in respect of the State’s role in the Construction Contract.
11 The Construction Contract required the applicant to achieve ‘Technical
Completion’ (TC) by 19 January 2016, and, not less than 90 days later (18 April
2016), to achieve ‘Commercial Acceptance’ (CA). The Construction Contract
provided that, if TC were not achieved by the due date, and there was no extension
to the date of CA stipulated in the Construction Contract, HYLC would be liable
to pay liquidated damages of $827,072 per day, up to an agreed cap of
$184,983,454 (10 per cent of the initial contract price).
12 Prior to September 2015, HYLC notified Celsus of a number of claims,
including claims for extensions of time and delay costs. On 17 September 2015,
separate deeds of settlement were entered into between HYLC and Celsus, and
between the State and Celsus respectively (together the 2015 Settlement
Agreements). The 2015 Settlement Agreements resolved HYLC’s extension of
time and delay costs claims. They also varied the date of TC to 4 April 2016, and
the date of CA to 3 July 2016. The 2015 Settlement Agreements also contained
an acknowledgment and an agreement by HYLC that it would be liable to pay
liquidated damages, if TC and CA were not achieved by the revised dates.
13 The State established the nRAH Project Steering Committee (the Steering
Committee) as its peak decision-making body for the nRAH project. The
membership of the Steering Committee comprised senior officers of the executive
of the State. They included the Chief Executive Officers of the Department of
Health and Aging, the Department of Planning, Transport and Infrastructure, the
Under Treasurer, and the Deputy Crown Solicitor. Its terms of reference included:
The Steering Committee is the peak decision making body for the New RAH Project and
is chaired by the Chief Executive (CE), DHA who is accountable for the success of the
project.
The Steering Committee meets at least monthly and focuses on decisions that have a
material impact on the business case for the project.
The membership of the Steering Committee includes senior representatives of relevant
Government stakeholders, whose role is to:
• Monitor and provide advice and direction to the project and ensure it is delivered
against the business case;
• Support decision making on any matter than could have a material impact on the
project business case, including key document approvals, issues, risks, benefits,
scope etc;
-- 5 of 31 --
[2024] SASC 46 Kourakis CJ
4
• Identify policy and Government commitment implications; and
• Support stakeholder engagement and issues management.
14 I will refer to the roles so identified as the Steering Committee’s ‘project
management’ role. The Steering Committee was also charged with ‘making
submissions to Cabinet on any decisions that have a material impact on the
business case for the project’. I will refer to that role of the Steering Committee
as its ‘Cabinet advisory’ role.
15 The Steering Committee’s Cabinet advisory role adds important context to
the State’s claims of public interest immunity. The Steering Committee’s dual role
has the consequence that the meeting agenda papers prepared for its meetings and
the meeting minutes are likely to refer to Cabinet decisions and directions on
material aspects of the nRAH project. It also has the consequence that disclosure
of the fact that a document, received by the Steering Committee in its project
management role, was sent to Cabinet might reveal that Cabinet deliberated on it,
and that it either acted on it, for example, by giving a direction to the Steering
Committee or exercising its prerogative, statutory, or personal powers, or took no
action at all, on that report or advice.
16 The work of the Steering Committee was assisted by a ‘Commercial Strategy
Team’ headed by Mr Chris Gray, an Assistant Crown Solicitor. The Commercial
Strategy Team included the persons named in the following table, which also
shows the office, and responsibilities, of each of them in the middle and righthand
side columns respectively:
Name Title Accountability/Responsibility
Vickie
Kaminski
Interim Chief
Executive
Accountable to government for the
success of the new RAH Project – key
decision maker, ensures service provider
accountability, provides whole of
Government input and supports
stakeholder management.
Don Frater Deputy Chief
Executive, Finance and
Corporate Services
Accountable for system wide finance and
business services matters (incl. eHS &
PSCM).
Michael
Deegan
Chief Executive
Officer, DPTI
Accountable for effective administration
of the Project Agreement with SA Health
Partnership up to CA, in particular the
successful delivery of design,
construction and facilities management
services under the agreement.
David
Reynolds
Chief Executive
Officer, DTF
Advice on whole of Government
affordability – input to value for money
-- 6 of 31 --
[2024] SASC 46 Kourakis CJ
5
discussions on changes to the business
case and its relationship to achieving the
national efficient price for service
delivery.
Lidio
Andreotti
Senior Legal Counsel
& Executive Solicitor,
Crown Solicitor’s
Office
Provides legal oversight and advice on
contractual and other relevant matters.
Paul Myers Project Director Accountable for Contract Administration
and Management through to [CA]
including FTP Management and
Coordination.
17 Ms Carr, a Project Director of DPTI, regularly reported on the progress of
the nRAH Project to the Minister for Health and to the Steering Committee.
18 At a meeting of the Steering Committee held on 27 January 2016, Celsus
representatives reported that TC would not be achieved by 4 April 2016, the
revised date stipulated in the 2015 Settlement Agreements. Celsus also advised
that TC would be delayed by two months, despite HYLC’s view that it might still
manage to achieve TC on 4 April 2016.
19 On 10 February 2016, a paper recommending the issuing of Default Notices
to HYLC was presented to and endorsed by the Steering Committee.
20 On 9 March 2016, the Steering Committee endorsed the position that the
State would not make any concession to Celsus on its existing contractual
obligations to meet TC by 4 April 2016. By 16 March 2016, the nRAH Project
was behind schedule by an estimated three months.
21 On 8 November 2016, HYLC forwarded a Notice of Claimed Entitlement to
Celsus, which set out its explanations for not complying with the deadlines on the
nRAH Project. Its reasons included:
(a) failures and misrepresentations by the State in relation to the Enterprise
Patient Administration System (EPAS);
(b) the failure by DCWC (the independent certifier) to provide its services
in accordance with its obligations;
(c) the notification and conduct of the State’s works;
(d) delays and maladministration in the processing and approval of works
and modifications by the State and Celsus;
(e) the wrongful rejection of HYLC’s extension of time requests by the
State and Celsus; and
-- 7 of 31 --
[2024] SASC 46 Kourakis CJ
6
(f) the unlawful issuing of default notices by the State and Celsus.
22 The State admits receipt of the Notice but denies the allegations.
23 From January to March 2017, the State, Celsus, and the financiers entered
into agreements without the consent of HYLC. The agreements comprised:
(a) an agreement in relation to the completion of the nRAH Project reached
after a mediation (the Mediated Agreement);
(b) a deed to embody the effect of the Mediated Agreement (Completion
Deed);
(c) a purported Cure Plan to give effect to the obligations set out in the
Mediated Agreement and/or the Completion Deed (Purported Cure
Plan); and
(d) a deed known as the Consents & Acknowledgment Deed.
24 The State contends that TC was achieved by Celsus on 15 March 2017 and
CA by 13 June 2017 in accordance with the amended technical completion criteria
under the Mediated Agreement, the Completion Deed and the purported Cure Plan.
HYLC contends that TC and CA were achieved, but does not reference those
arrangements.
25 The new Royal Adelaide Hospital commenced operation on 5 September
2017.
Privilege claims made in the arbitration
26 Hearings were held in December 2022 and again in September 2023 before
the arbitrator, the Honourable Roger Gyles AO KC (the arbitrator), to resolve
disputes over the claims for privilege and immunity made by the State. The
December 2022 hearing concerned the parties’ first tranche of discovered
documents, and the September 2023 hearing concerned the parties’ second tranche
of discovered documents.
27 On 24 April 2023, orders were made which required the parties to ‘identify
the documents in relation to which a party intends to challenge another party’s
claim for privilege’. On 11 August 2023, HYLC notified the State of its challenges
to approximately 200 documents subject to claims of parliamentary privilege and
115 documents subject to claims of public interest immunity. Relevantly to this
application, HYLC challenged the State’s claims for privilege in the following two
categories:
(a) Parliamentary privilege: not apparent on the face of the available
information whether the privilege would apply; and
-- 8 of 31 --
[2024] SASC 46 Kourakis CJ
7
(b) Public interest immunity: not apparent on the face of the available
information whether the privilege would apply.
28 On 16 August 2023, the State served documents to support its privilege claim,
which comprised written submissions and a supporting affidavit of Ms Lisa
Loechel. The State made the following submissions in respect to the claim of
privilege:
4.1 the State’s claims for privilege are properly made [and] have been the subject of
multiple rounds of review by the State’s solicitors (LK);
4.2 in respect of the State’s claims of LPP, the communications were made for the
dominant purpose of the obtaining or provision of legal advice or relating to legal
proceedings (actual or anticipated), such that the claims should be upheld;
4.3 in respect of the State’s claims of WPP, the communications were part of, or
reasonably incidental to, negotiations, or record negotiations and decisions made to
resolve a dispute, including internal communications regarding the negotiations.
Further no exceptions apply in respect of any of those communications;
4.4 in respect of the State’s claims of PII, the documents refer to or contain the contents
of Cabinet documents or are Cabinet submissions, and therefore contain material
disclosing Cabinet deliberations such that PII applies; and
4.5 in respect of the State’s claims of PP, the documents comprise parliamentary briefing
notes prepared for the Minister of Health to use in the South Australian parliament
such that PP applies.
29 On 5 September 2023, HYLC served submissions challenging the State’s
claim for parliamentary privilege and public interest immunity. HYLC’s primary
contentions were:
161. The State cannot hide behind its claims of parliamentary privilege so as to preclude
the Arbitrator inspecting the documents identified in paragraph 160 above in
circumstances where those documents do not appear to have a sufficiently close and
clear connection with proceedings of Parliament.
…
186. The State cannot hide behind its claims of public interest immunity so as to preclude
the Arbitrator inspecting the documents identified in paragraph 185 above in
circumstances where those documents do not appear to be Cabinet documents or
Cabinet submissions or otherwise attract public interest immunity.
30 At the hearing in September 2023 before the arbitrator, the State submitted
that the arbitrator lacked jurisdiction to inspect the relevant documents and
determine claims. The applicant did not prosecute its challenge to the State’s
privilege and immunity claims in the arbitral proceeding but instead brought this
application.
-- 9 of 31 --
[2024] SASC 46 Kourakis CJ
8
The controversies before the arbitrator
31 The arbitral proceedings were commenced in 2018. In summary, HYLC
claims that the State conducted itself wrongfully throughout the nRAH Project,
and that Celsus did not take sufficient steps to ensure that the State met its
obligations relating to the nRAH Project (the wrongful conduct claim). The State
denies HYLC’s claim and contends that the dispute arose out of circumstances in
which HYLC was 421 days late in meeting the CA date and was therefore liable
to pay mandatory liquidated damages in the amount of approximately $185 million
to Celsus.
32 Paragraph [53] of the seventh amended statement of claim in the arbitral
proceedings pleads that the State adopted a strategy in breach of its duty to
co-operate in the development of the nRAH:
53 Overviews
53.1 From a point in time unknown to the Builder, but by no later than 2 November 2016,
the State determined to, and subsequently did, embark upon a course of conduct,
which included (amongst other things):
(a) hindering Project Co and the Builder achieving TC and CA;
(b) failing to cooperate with Project Co and the Builder;
(c) delaying the achievement of TC and CA (and thereby payment of QSPs);
(d) demanding $600 million in Ransom Compensation;
(e) issuing invalid Notices of Default;
(f) rejecting Cure Plans;
(g) raising baseless allegations of safety issues;
(h) inducing (or seeking to induce) Project Co, in breach of its obligations under
the Construction Contract, to terminate the Builder’s ongoing involvement in
the Project and remove it from Site as soon as possible following the
achievement of TC, to withdraw all EOT claims against the State and to
procure the cessation of further claims being made by the Builder; and
(i) inducing Project Co to enter into a series of unlawful agreements in breach of
the Construction Contract,
in breach of the Upstream Duty of Cooperation.
53.2 By reason of the State’s conduct and pursuant to clause 79.16(d) of the Construction
Contract, the Builder reasonably believes that Project Co has a claim against the
State for breach of the Upstream Duty of Cooperation.
53.3 The Builder is entitled to any relief granted to Project Co by reason of the State’s
breach of the Upstream Duty of Cooperation.
-- 10 of 31 --
[2024] SASC 46 Kourakis CJ
9
53.4 Further, by reason of the matters pleaded below, Project Co breached the
Downstream Duty of Cooperation and clause 1.8 of the Construction Contract.
33 Paragraph [55] of HYLC’s claim pleads that, from at latest November 2016,
the State determined to hinder Celsus and HYLC from achieving TC and CA and
not to cooperate with HYLC and Celsus in the discharge of the Construction
Contract. It also pleaded that the State determined to pursue compensation of
about $160 million when it knew it had not reasonable entitlement to that sum and
to procure Celsus to terminate HYLC’s ongoing involvement in the nRAH project.
34 HYLC also contended that the State:
(a) engaged in a course of conduct whereby the State’s failures were hidden
from the Builder with the State delaying TC and CA to postpone its
obligations to make payments until it considered, for the
then-Government’s political purposes, that it wished to open the nRAH,
just prior to the March 2018 South Australian election (furthered
through, amongst other things, a strategy of issuing and maintaining
defect notices against the Builder’s works – see section F.2.4 below);
and
(b) entered into a series of unlawful contracts with Celsus in breach of, and
interfering with, the existing contractual framework for the Project so
as to change the regime for completion of the nRAH, thereby masking
its own failures and depriving the Builder of its entitlements.
35 The State denies the allegations. It contends that they are not supported by
any evidence and are inconsistent with the State’s attempt to facilitate the
achievement of TC earlier than would otherwise have been the case.
36 Another of the controversies before the Arbitrator concerns the State’s
electronic patient administration system for nRAH, known as the Enterprise
Patient Administration System (EPAS). HYLC contends on this issue that the
State had a contractual obligation to provide EPAS prior to TC on 19 January 2016
as part of the ‘State Works’. HYLC also contends that Celsus was contractually
bound to ensure that the State complied with its contractual obligation to provide
EPAS to HYLC prior to TC as part of the State Works. HYLC’s case is that it was
a necessary precondition to HYLC achieving TC that it demonstrate the integration
of discrete applications of Celsus’ Network with discrete applications on the State
Network (including EPAS). In order to demonstrate the integration of discrete
applications on Celsus’ Network with discrete applications on the State Network
(including EPAS) HYLC required the State to provide a fully functional
production and configured versions of EPAS in sufficient time for HYLC to
perform necessary testing before TC.
37 The State denies that it undertook any such obligation, pointing out that
neither the Project Agreement nor the Construction Agreement referred to EPAS
at all. The State contends that its obligation was limited to providing an interface
-- 11 of 31 --
[2024] SASC 46 Kourakis CJ
10
and to allowing such access to its applications as was necessary to allow an
interface with Celsus’ ‘integration engine’. It pleads that that interface was
provided by September 2015.
38 HYLC also claims that the State represented that it would provide the EPAS
system prior to TC. HYLC contends that in the period between July to
September 2015, and immediately prior to the 2015 Settlement Agreements, the
State and Celsus represented to HYLC that EPAS for nRAH would be provided to
HYLC by 30 September 2015. HYLC contends that it relied on the representation
when it agreed to an amended date for TC of 4 April 2016 in the Settlement
Agreements.
39 HYLC pleads that, at the time of entry into the Settlement Agreements, the
State and Project Co had no proper basis for representing that EPAS for nRAH
would be provided to NYLC by 30 September 2015 and, in any event, prior to TC
and that the State and Celsus knew, or ought to have known, that EPAS for nRAH
would not be provided by 30 September 2015.
40 HYLC alleges that EPAS was not provided by 30 September 2015 and claims
damages for the State’s failure to provide EPAS for nRAH. HYLC also claims
that, by reason of the State’s failure to provide EPAS, it was prevented from
achieving TC and is therefore entitled to relief.
41 The State denies that any such representation was made and contends that
HYLC never suggested that it required access to the EPAS system for any purpose.
It also contends, in the alternative, that the witnesses on whose evidence HYLC
relies did not have authority to speak on, or receive assurances on behalf of, HYLC.
It further contends that the meetings in which those persons allege that the
representations were made were informal.
42 It is common ground, therefore, that the documents relating to the EPAS
system may have relevance to the controversies in the arbitral proceeding insofar
as they may disclose:
1. deceptive and misleading conduct leading up to the settlement in
September 2015;
2. that the contractual relationships between the parties were such as to
give the applicant a reasonable expectation of being kept informed of
the state of development of the EPAS system so that it could plan its
integration into the IT systems to be incorporated to the build of the
nRAH.
43 Another of the controversies before the arbitrator are the claims by HYLC
against the State for additional costs it incurred because it encountered unknown
not known pre-existing contamination and latent ground conditions. HYLC’s
claim was not accepted by Celsus. Neither were its claims for extensions of time
and prolongation costs. In particular, HYLC complains that the State and Celsus
-- 12 of 31 --
[2024] SASC 46 Kourakis CJ
11
failed to issue appropriate time cost fee directions to the IC, instructing it to
determine the Builder’s claim. The failure to give those directions was in breach
of the obligation of the State and Celsus to cooperate in the discharge of the
Construction Contract. HYLC also pleads that, by reason of the contamination
and latent ground conditions, it changed its construction schedule, resulting in lost
productivity. It complains that the interim settlement agreements on those issues
were procured by misrepresentation and unconscionable conduct.
44 The State denies that the alleged contamination was contamination within the
meaning of the Project Agreement and alleges that HYLC did not follow the agreed
site remediation plan. The State contends that the nRAH was constructed on a
former railyard. HYLC was provided with detailed site investigation reports to
guide the remediation of the site. HYLC’s remediation management plan formed
part of its bid and the resulting contract. The State denies that HYLC discovered
unknown contamination. It contends that HYLC’s claim relates largely to
disposing of waste soil which had to be excavated from the site in any event to
reach the required ‘bench’ levels for construction and the cost associated with its
unilateral and unauthorised decision to alter the remediation strategy.
45 The State contends that Celsus was not a disclosed agent, a ‘mere post box’,
or a ‘pass-through vehicle’ between the State and HYLC. The State pleads that
Celsus had represented that it had an experienced and expert management team.
The State also relies on the settlement of HYLC’s contamination claim in the
Upstream Settlement Agreement entered into on 17 September 2015.
Taxonomy of public interest immunity claims
46 The State interest immunity claims over the documents by reference to the
following categories:
Category A1
Cabinet
Documents
Documents that are a Cabinet document (final, draft or
attachment) or repeat content within a Cabinet document.
Enclosures to Cabinet documents include reports, business
cases and independent reviews prepared by external
consultants for consideration by Cabinet.
Category A2
References to
Cabinet
discussions
Documents that would reveal Cabinet decisions,
deliberations or discussions.
Documents within A2 broadly fit into: speech notes, packs
and minutes of meetings of the EPAS Programme Board and
Steering Committee, which contains mentions of cabinet
decisions, deliberations or discussions, briefing notes.
Category A3
Preparatory
Documents
Documents that relate to the preparation of Cabinet
documents (including directions, options, budget or timing)
and would reveal the content of Cabinet documents.
Direct quotes from Cabinet documents, documents that
disclose the nature or content of Cabinet documents, briefing
notes, e-mails.
-- 13 of 31 --
[2024] SASC 46 Kourakis CJ
12
47 The claim for category A1 and A2 documents is that, if the documents were
disclosed, they would reveal that some or all of the information they contain was
the subject of a Cabinet decision, deliberation, or discussion. By corollary,
categories A1 and A2 do not include documents which were prepared for a purpose
other than for submission to Cabinet, but which were attached to, or accompanied,
Cabinet documents, unless their disclosure would show that they were put before
Cabinet.
48 In respect of category A3 preparatory documents, the objection is that
production of the document, or the redacted part thereof, would reveal that the
information it contains was provided to Cabinet.
49 The State’s position is, therefore, that it has not withheld from production
documents which were prepared, or received, for the Steering Committee’s project
management role merely because they also happen to have been provided to
Cabinet in the discharge of its Cabinet advisory role. Objection to the production
of documents is only made if, by that production, the information provided to
Cabinet for its deliberations would be revealed.
Legal principles
50 In Alister v The Queen1 Gibbs CJ commented on the division of opinion in
the House of Lords on the necessary condition which must be satisfied before a
judge would be warranted to inspect a document to which public interest immunity
attaches. Gibbs CJ articulated the ‘on the cards’ test for inspection of documents
in criminal cases.
Both Burmah Oil Co. Ltd v. Bank of England and Air Canada v Secretary of State for
Trade support the view that where the Crown objects to the production of a class of
documents on the ground of public interest immunity, the judge should not look at the
documents unless he is persuaded that inspection would be likely to satisfy him that he
ought to order production; in the words of Lord Wilberforce in Air Canada v Secretary of
State for Trade [at 529], he must have “some concrete ground for belief which takes the
case beyond a mere ‘fishing’ expedition”. In the latter case the House of Lords divided on
the question whether, before inspection is ordered, the documents should appear likely to
support the case of the party seeking discovery, or whether it is enough that they should
appear likely to assist any of the parties to the proceedings; the majority favoured the
former view. In both cases the proceedings were civil and not criminal. Just as in the
balancing process the scales must swing in favour of discovery if the documents are
necessary to support the defence of an accused person whose liberty is at stake in a criminal
trial (see Sankey v Whitlam [at 42, 62]), so, in considering whether to inspect documents
for the purpose of deciding whether they should be disclosed, the court must attach special
weight to the fact that the documents may support the defence of an accused person in
criminal proceedings. Although a mere “fishing” expedition can never be allowed, it may
be enough that it appears to be “on the cards” that the documents will materially assist the
defence. If, for example, it were known that an important witness for the Crown had given
a report on the case to ASIO it would not be right to refuse disclosure simply because there
were no grounds for thinking that the report would assist the accused. To refuse discovery
1 (1983-1984)154 CLR 404, 414-415.
-- 14 of 31 --
[2024] SASC 46 Kourakis CJ
13
only for that reason would leave the accused with a legitimate sense of grievance, since he
would not be able to test the evidence of the witness by comparing it with the report, and
would be likely to give rise to the reproach that justice had not been seen to be done.
(Underlining added)
51 I observe that the underlined precondition to inspecting documents covered
by public interest immunity laid down in the Air Canada decision is something
more than direct relevance to an issue.
52 In Legal Services Commission v Trotter2 Cox J considered the same English
authorities in the context of a civil claim:
There is a question - indeed, it was the question that Gibbs CJ went on to consider in Alister
v The Queen whether the court should look at the disputed documents to assist it in reaching
its decision. There is a conflict of judicial opinion on the subject. In Burmah Oil Co Ltd v
Governor and Co of the Bank of England [1980] AC 1090, the House of Lords was divided
on the question whether it was possible to resolve the Crown's claim for public interest
immunity from discovery without inspecting the documents. The majority held that it was
not possible to decide whether the balance of public interest lay for or against disclosure
without an inspection. Their Lordships therefore inspected the documents for themselves.
(There had been no inspection by the judge of first instance, but there had been by the Court
of Appeal.) In inspecting the documents in this way, in order to decide whether or not they
should be made available in the litigation, the House of Lords was following precedents
that can be traced back through Conway v Rimmer to the Privy Council decision
in Robinson v South Australia State (No 2) [1931] AC 704. The Burmah Oil case was
followed by the Court of Appeal in Campbell v Tameside Metropolitan Borough Council
[1982] 1 QB 1065, where a class immunity objection was overruled. However, in Air
Canada v Secretary of State for Trade (No 2) [1983] 2 AC 394, the House of Lords took a
different view. That was a Crown claim for a class immunity, and the plaintiffs' claim for
discovery and production rested upon their assertion that the documents were relevant and
were necessary for “disposing fairly of the cause or matter” as provided by the relevant
rules of court. The majority held that, where such a claim was made, the judge should not
inspect the documents unless he was satisfied that they contained material that would give
substantial support to the party seeking disclosure on an issue which arose in the case. The
minority test was somewhat wider but still required a favourable assessment by the judge
before he could make an inspection. The decision stands as a strong discouragement of a
mere fishing expedition. The Burmah Oil and Air Canada cases were both civil cases, and
they were distinguished by the High Court in Alister v The Queen for that reason. The High
Court had inspected the disputed documents for itself in Sankey v Whitlam and it took the
same course in Alister v The Queen. Both of those cases, of course, related to criminal
proceedings. In Casley-Smith v District Council of Stirling (supra), a civil action in this
Court, the Full Court confirmed the Court's power to inspect the documents that were
produced by a third party before trial under r 60 of the Supreme Court Rules but in respect
of which a number of objections, including public interest class immunity, were taken. The
members of the Full Court looked at the documents for themselves, as the Master and Perry
J had before them. Certainly there are disadvantages in making a court inspection of
documents that may possibly, as a result, never be seen by at least one party to the litigation
— see Gaskin v Liverpool City Council [1980] 1 WLR 1549, per Megaw LJ (at
1555); Alister v The Queen (1984) 154 CLR 404 at 469 — but that course may simply
2 (1990) 54 SASR 74, 84-85
-- 15 of 31 --
[2024] SASC 46 Kourakis CJ
14
represent in some circumstances the lesser of two evils. Not all of Justice's balancing
exercises are best carried out blindfolded.
(Underlining added)
53 I observe again that the test for inspection derived from the Air Canada
decision by Cox J is something more than the direct relevance test.
54 In Commonwealth v Northern Land Council (Northern Land Council),3
Mason CJ, Brennan, Deane, Dawson, Gaudron and McHugh JJ discussed the
problematic features of inspecting documents in respect of which the Crown
claims that their very disclosure is ‘detrimental to the public interest’:4
In a case where a document fell into a class of document the disclosure of which would be
injurious to the public interest regardless of the contents, a court could conclude that
“disclosure would not really be detrimental to the public interest” only in circumstances
where there was a competing public interest, such as the public interest in the advancement
of justice, which outweighed the public interest in the preservation of confidentiality. To
inspect the contents of documents as a matter of course would be to disregard the basis of
the immunity for a document falling within the class described. The apparent dilemma is,
we think, to be resolved by recognizing that the classification of claims for immunity into
“class” claims and “contents” claims is indeed often rough and imprecise. In many
so-called “class” cases a court may find it necessary to consider a document, inspecting it
if necessary, in order to determine whether it does in truth fall into a class which attracts
immunity. The contents of the document may have a bearing on that question as may the
topic with which it deals, particularly if it is no longer current or controversial.
Where, however, a document clearly falls within a class which attracts immunity, a
different approach is called for. Documents recording Cabinet deliberations upon current
or controversial matters, such as the records in question in this case, are an example.
Obviously, there are extremely strong considerations of public policy weighing against
their production regardless of how significant disclosure of their contents might be to the
case of one side or the other in the proceedings in which the claim for immunity is raised.
However, as we have said, the immunity which membership of the class confers is not
absolute and that is so even if, as in the case of records of Cabinet deliberations, the highest
degree of protection against disclosure is warranted. Nevertheless, where it is established
that a document belongs to a class which attracts immunity, a court will lean initially
against ordering disclosure. Whether the circumstances of a particular case will be
sufficient to displace the considerations which favour immunity depends to a large extent
upon the nature of the class. In the case of documents recording the actual deliberations of
Cabinet, only considerations which are indeed exceptional would be sufficient to overcome
the public interest in their immunity from disclosure, they being documents with a pre-
eminent claim to confidentiality. The process of determining whether an order for
disclosure of documents in that class should be made remains one of weighing the public
interest in the maintenance of confidentiality against the public interest in the due
administration of justice, but the degree of protection against disclosure which is called for
by the nature of that class will dictate the paramountcy of the claim for immunity in all but
quite exceptional situations.
3 (1993) 176 CLR 604.
4 (1993) 176 CLR 604, 617-18.
-- 16 of 31 --
[2024] SASC 46 Kourakis CJ
15
Indeed, for our part we doubt whether the disclosure of the records of Cabinet deliberations
upon matters which remain current or controversial would ever be warranted in civil
proceedings. …
(Footnotes omitted, underling added)
55 It is apparent from the descriptions of the documents in this case that they are
not minutes of Cabinet deliberations which is the primary focus in the above
passage from the judgment in Northern Land Council. I have determined the
State’s claims on the basis that the documents, or parts of the documents, withheld
were put before Cabinet for its deliberations on budgetary decisions and the
directions which it would give, or refrain from giving, to the Steering Committee
on how it should manage the project.
56 Nonetheless the determination I must make requires a balancing of the public
interest in the due administration of justice against the degree of protection against
disclosure which that class of documents, which comprises the subject matter of
Cabinet deliberation, demands. The degree of protection required will, of course,
vary depending on the nature of the matter and whether it is a matter of current or
only historical importance.
57 In Northern Land Council, the plurality made the following observations
about weighing the competing public interest in disclosure in order to assist in the
administration of justice:5
The present case is a civil case. Although the Northern Land Council seeks to attack the
agreement upon the separate ground of unconscionable behaviour on the part of the
Commonwealth, the other claims of unfairness, breach of fiduciary duty, duress and the
exercise of undue influence are in one sense all forms of unconscionable conduct. The
claims are alleged to arise out of the position of relative disadvantage which the Northern
Land Council occupied in comparison with the Commonwealth, having regard to its
experience and the resources available to it; the course of negotiations leading to the
conclusion of the agreement; the refusal of the Commonwealth to supply documents
relating to the mining of the Ranger land which were in its possession; various
misrepresentations made by the Commonwealth; and the inadequacy of the agreement in
the events which have transpired. The Northern Land Council cannot be dependent upon
access to the deliberations of Cabinet for proof of these matters, which occurred outside
the confines of the Cabinet room. No doubt access to the records of the deliberations of
Cabinet may disclose material which is relevant in the extended sense which is adopted for
the purpose of discovery. Indeed, it is necessary to assume as much because the records
were discovered. But in no way does it appear that access to those records is crucial to the
conduct by the Northern Land Council of its case. True it is that some years have passed
since the agreement was executed and the government has changed in the meantime, but it
cannot be said that the matters which are the subject of the agreement have ceased to be
current or controversial. It cannot, in our view, be said that exceptional circumstances exist
which would justify the denial of the claim of public interest immunity, as a class claim,
for the documents in question.
(Footnotes omitted, underlining added)
5 (1993) 176 CLR 604, 619-20.
-- 17 of 31 --
[2024] SASC 46 Kourakis CJ
16
58 Again, even though the documents sought in Northern Land Council
concerned Cabinet deliberations, in any balancing exercise, between the relative
importance of confidentiality on the one hand and the extent to which the
administration of justice might be compromised on the other, both must be
considered in the particularity of the circumstances of each.
59 In Northern Land Council, Toohey J was the only member of the Court who
considered whether there is an additional ‘threshold’ which an applicant for
production must pass in the case of privileged documents before a judge is required
to undertake the exercise of balancing the competing public interests. In dealing
with the Commonwealth’s submission that the applicant must demonstrate
something more than that the documents may advance its case or damage the case
against it, Toohey J commented that:6
While the rules of court do not offer a threshold test, they do point up that the production
of documents is part of the adversarial process, aimed at ensuring fairness as between the
parties in the resolution of their dispute. In the ordinary course fairness demands that each
party produce for inspection documents which relate to any issue in the action. Public
interest immunity recognizes that there is a public interest to be protected, sometimes at the
cost of withholding documents that may advance the case of the other party or damage the
case of the party in possession of the documents. Once it is apparent that there are
documents that fall into one or other of those categories (that is, that there is not simply a
fishing expedition) and the court is satisfied that an order for the production of documents
is necessary in the sense discussed, it is hard to see why there should be a further threshold
onus on the party seeking production. …
…
It follows that once the existence and relevance of documents has been demonstrated (their
inclusion in an affidavit of documents will satisfy that requirement), the party seeking
production has ordinarily done enough to establish that access to the documents is
necessary and therefore to require the court to take the further step of balancing the
competing public interests. It is necessary to add the qualifying term “ordinarily” because
the party from whom production is sought may demonstrate that the documents are of such
“high level governmental public interest”, to use the language of Lord Wilberforce in
Burmah Oil Co. v Bank of England, that the public interest immunity should prevail without
any examination of the documents. Or it may be apparent that, while the documents fall
short of that description, their confidentiality is important to government and their
relevance to the issues in the action is peripheral. However, in most cases it will be
necessary for the court to take the next step in order to resolve the competing public
interests. What is required to persuade the court to undertake the task of balancing the
competing public interests necessarily depends on the circumstances. But once it is
accepted that absolute immunity does not attach to any category of documents, the class
into which documents fall serves to point up the likely character of the documents rather
than to conclude the matter of their production.
(Footnotes omitted, underlining added)
60 It is important to appreciate that, in the above passages, Toohey J was first
considering the threshold which must be crossed before a Judge needs to embark
6 (1993) 176 CLR 604, 634-36.
-- 18 of 31 --
[2024] SASC 46 Kourakis CJ
17
on a balancing exercise at all. Indeed, that is the heading of that part of his
Honour’s judgment.7 In that respect, Toohey held that it was sufficient that the
documents may advance the applicant’s case or damage the case of the opposing
party. Once that is shown, the applicant has established a case for production,
which then requires the Court to undertake the exercise. I acknowledge that his
Honour did refer to an examination of the documents in that context, but it is clear
enough, with respect, that his Honour was primarily concerned with the balancing
exercise, which might involve an inspection of the document. So much is clear
from the later passages in his Honour’s judgment under the heading ‘Should the
Judge have inspected the documents before ordering production?’ in which his
Honour recognised that the decision whether or not to inspect a document was a
discretionary one.8
61 In Adelaide Brighton Cement v South Australia, Debelle J defined Cabinet
documents to mean:9
(1) Cabinet minutes or other records of Cabinet discussions and records of discussions
between heads of departments;
(2) papers prepared as submissions to Cabinet; and
(3) any documents which relate to framing of government policy at a high level.
62 His Honour explained that since the High Court’s decision in Sankey v
Whitlam,10 absolute immunity does not attach to any of these categories. His
Honour observed that the protection from production does not necessarily endure
forever, and that documents which might at one time be immune from disclosure
may later be disclosed if circumstances have changed. Debelle J recognised that
the amenability of documents to production depends on a range of factors, which
include the status of the documents; the subject matter of the documents; the age
of the documents; and whether the documents have already been published.
63 Debelle J then articulated the following principles:11
Some relevant principles
The following propositions are relevant to the issues in this application and have been
drawn from the cases just mentioned.
(1) The general rule is that a court will not order the production of a document, although
relevant and otherwise admissible, if it would be injurious to the public interest to
disclose it: Sankey v Whitlam at 38.
7 P 631.
8 (1993) 176 CLR 604, 635-36.
9 (1999) 75 SASR 209, 212 [8]-[9].
10 (1978) 142 CLR 1.
11 (1999) 75 SASR 209, 212 [9(1)-(2)].
-- 19 of 31 --
[2024] SASC 46 Kourakis CJ
18
(2) However, the court recognises that there are two aspects to the public interest which
may conflict. They were described by Lord Reid in Conway v Rimmer at 940 in
these terms:
“There is the public interest that harm shall not be done to the nation or the public
service by disclosure of certain documents, and there is the public interest that the
administration of justice shall not be frustrated by the withholding of documents
which must be produced if justice is to be done.”
…
64 Debelle J’s consideration of the circumstances in which it may be appropriate
for a judge to inspect documents in respect of which public interest immunity or
parliamentary privilege is claimed is as follows:12
It is now beyond question that the Court has power to inspect the document or documents
privately: Sankey v Whitlam at 46. There is, however, a question whether the court should
look at the documents for assistance in the balancing exercise, that is to say, when weighing
the two conflicting aspects of the public interest. In some cases, the Court might be able
to determine that the public interest requires that the documents be withheld from
production without inspection of the documents: see Commonwealth v Northern Land
Council where it was held that documents recording the deliberations of Cabinet on topics
which were current and controversial would not be disclosed except in quite exceptional
circumstances. It was unnecessary in that case to inspect the documents to determine the
claim for privilege. Only in cases where the ministerial affidavit demonstrates with
sufficient particularity the nature and the significance of the documents both in terms of
any need to preserve their confidentiality on the one hand and for the actual litigation on
the other is it likely that it will be possible to reach such a conclusion: cf Woodhouse P in
Fletcher Timber Ltd v Attorney-General at 295.
(Underlining added)
65 In my respectful opinion the underlined passage correctly states the ambit of
the discretion which a judge exercises in deciding whether or not to inspect any
Cabinet documents. Debelle J continued:
In almost all other cases, an inspection will be necessary. There is a question whether the
applicant for production of the document must satisfy some threshold test before the court
inspects the documents. Plainly, the documents must be relevant. The question is whether
any further or more stringent test is necessary … As Toohey J pointed out in
Commonwealth v Northern Land Council at 634-635, the process of discovery (in this
Court, the list of documents) demonstrates the existence and relevance of the documents to
the issues in the action. The application for production for inspection is a usual
concomitant of the process of discovery. It would seem, therefore, that where there is a
claim for privilege on the ground of public interest immunity, the Court should without
more inspect the documents for the purpose of weighing the competing public interests.
The decisions in Burmah Oil and Air Canada suggest that there may be a further test. They
suggest that in England a judge should not look at the documents unless he is persuaded
that an inspection would be likely to satisfy him that he should order production, that the
judge should have some concrete ground for belief of that fact which takes the case beyond
a mere fishing expedition, to use the words of Lord Wilberforce in Air Canada at 439.
12 (1999) 75 SASR 209, 214 [9(9)].
-- 20 of 31 --
[2024] SASC 46 Kourakis CJ
19
Burmah Oil and Air Canada were cases in which the documents were sought in civil
proceedings. There was a division of opinion in the House of Lords whether, before
inspection is ordered, the document should appear likely to support the case of the parties
seeking discovery, or whether it is enough that they should appear likely to assist any of
the parties to the proceedings. In Air Canada the majority favoured the former view. The
High Court has not had occasion to consider the question in civil proceedings. Only
Toohey J had to consider the issue in Commonwealth v Northern Land Council as the
question did not fall for examination on the approach taken by the majority. It must be
remembered that the rules in England as to discovery are not as liberal as those in this State
and in other jurisdictions. Order 24 r 8 of the Rules of Court in England requires discovery
only if disclosure is necessary “for disposing fairly of the cause or matter or for savings
costs”. Rule 58.01 of the Rules of this Court requires documents to be discovered if they
are documents “relating to any matter in question in the action”. For these reasons, the two
English decisions may be distinguished. The procedure of issuing subpoenas of documents
for production may lead to concerns as to fishing and Alister v The Queen was such a case.
Where the parties have exchanged lists of documents concerns as to fishing will arise only
if a party seeks documents which have not been discovered. That is not the position in this
application. Concerns as to fishing and the principles to be applied when a party subpoenas
documents may, therefore, be put to one side.
…
For these reasons, I respectfully agree with Toohey J at 635 that, once documents appear
in a list of documents, concerns as to relevance may be put to one side and it is hard to see
why there should be a further threshold onus on the parties seeking production. As Cox J
said in Legal Services Commission v Trotter, “Not all of Justice’s balancing exercises are
best carried out blindfolded”. For those reasons, I do not think there is any test beyond
relevance to be satisfied. Relevance is established by inclusion of a document in a list of
documents. The court will then inspect the documents for the purpose of weighing the
competing public interests.
(Underlining added)
66 HYLC has plainly laid a sufficient foundation to require me to undertake a
balance of the public interest in Cabinet confidentiality and the public interest in
the administration of justice. However, I respectfully do not accept the principle
stated in the last two underlined passages just cited. They seem to me to go further
than any earlier authority in respect of civil proceedings. A judge exercises a
discretion over whether or not to inspect the documents having regard to the
likelihood that their contents will materially assist the party seeking production. I
have not found it necessary to inspect the documents in respect of the challenges
to the public interest immunity claim made over the first tranches of discovery
because of descriptions of the nature of the documents in the open and confidential
affidavits makes it clear that they properly fall within the classes of public interest
immunity claimed by the State. Furthermore, the summaries of the controversies
which are the subject-matter of the arbitration provided by the parties has allowed
me to form a clear view based on the dates and descriptions of the documents in
the open and closed affidavits that the administration of justice would not be
materially compromised by withholding production.
-- 21 of 31 --
[2024] SASC 46 Kourakis CJ
20
Consideration of individual documents
67 I now move to consider the challenges to the State’s claims of public interest
immunity and parliamentary privilege made by the State in respect of particular
documents.
68 I deal in detail with the documents in respect of which submissions were put
to me. I have considered those submissions in evaluating the claims of public
interest immunity made over all the documents in respect of which the State’s
claims are challenged.
Documents 1A – 8A
69 Document 1A is dated 15 May 2011 and is entitled a ‘Briefing Note EPAS
Program Board Out of Session’. Disclosed parts of the documents show that it is
concerned with the fitness for purpose of EPAS and an estimation of its cost. The
testing of the product in a ‘pre-production environment’ is discussed. Similar text
and redactions appear on document 2A, dated 19 May 2011, which, on its face, is
an email sent by the chair of the EPAS Program Board, Mr David Swan. It refers
to the desirably of SA Health executing contracts by 31 May 2011 in order to
secure the strongest ‘Allscripts’ team to support and facilitate the pre-production
planning activities. Category A2 and A3 objections are taken to the production of
those documents.
70 Documents 3A to 7A are dated 21 November 2011. Document 3A is
described as an email entitled ‘Business Case’ sent by Ms Pam Zervas, who was
then the Acting Business Change Director of EPAS. Documents 4A to 7A are
attachments to that email. Varying category A1 and A3 objections are taken to
disclosure of those documents.
71 Ms Zervas’s email was sent to David Swan, the Chief Executive of the
Department of Health, to a number of other senior executives of the Department
of Health, and to two external consultants. The titles of the attachments are
described in an annexure ‘RSG’ to the open affidavit of Ms Green of 8 December
2023 as a Cabinet coversheet, a Ministerial Brief on an EPAS Cabinet submission,
a Cabinet submission, and ‘version 5’ of an EPAS business case. I find from the
descriptions of the documents, and on the closed affidavit of Ms Green of
8 December 2023, that they fall within category A3.
72 Document 8A is described as the ‘Final EPAS Business Case’. It is dated
2 July 2012. Category A1 andA2 objections are taken to production of the redacted
parts of that document. I infer from the timing of the documents that the
documents attached to Ms Zervas’ email of 21 November 2011 were developed
into the final business case which is document 8A. It is not surprising that full
disclosure would reveal information provided to Cabinet, and, therefore, the nature
of its deliberations and indicate decisions which it made, or did not make, on the
business cases.
-- 22 of 31 --
[2024] SASC 46 Kourakis CJ
21
73 The confidential affidavit of Ms Green sworn on 8 December 2023 is
consistent with the inferences available on the face of the descriptions of
documents 3A to 8A and materially supports the claims made in respect of those
documents.
74 Documents 1A and 2A predate the development of the business case in 2011
by about six months. Plainly, they cannot reveal anything about the Cabinet
decisions and deliberations which in fact took place on the submission of the
finalised business case to Cabinet. However, it cannot be assumed that there were
not earlier Cabinet decisions on the development of a business case. Indeed, it can
be expected that there were. In that respect I note that a paragraph of
document 8A, which was not redacted, reveals that in November 2010 Cabinet was
asked to note the selection and imminent public announcement that ‘Allscripts’
was the preferred software vendor for EPAS.
75 I am satisfied on the basis of the confidential affidavit of Robyn Green sworn
on 8 December 2023,13 the disclosed contents of documents 1A and 2A, and the
position held by Ms Zervas, that her email of 21 November 2011, together with
the attached documents, relate to the preparation of documents to be submitted to
Cabinet in respect of the EPAS system and that they would disclose that
information in them was submitted to Cabinet for its deliberations.
76 The documents having been disclosed, their relevance can be accepted.
However, the materiality of the documents to a just determination of the
controversies referred to arbitration and their probative weight is another thing
altogether.
77 Documents 1A to 8A predate the communications around the
2015 Settlement Agreements but could possibly contain information which
disproves representations made at about that time. Nonetheless, documents which
were prepared to assist Cabinet to make decisions on the EPAS business case, and
whether to approve expenditure for the development of the EPAS system, are
highly unlikely to do so. The nature of a business case for a complex IT system is
largely predictive and aspirational. What is thought to be the case at the beginning
of a complex IT project might later be found in fact not to be the case. Nor is it at
all likely that the documents would contain information that would have been the
subject of a contractual obligation to disclose at a much later time.
78 I am satisfied that documents prepared for the purposes of informing
Cabinet’s consideration of the business case for developing and installing EPAS is
unlikely to support CPB’s pleaded case or damage the State’s defence in respect
of the identified issues concerning EPAS. On the information available to me, I
see no need to inspect the documents.
13 FDN 23.
-- 23 of 31 --
[2024] SASC 46 Kourakis CJ
22
79 On the other hand, it can also be accepted that the documents are unlikely to
disclose the views of individual Cabinet Ministers. Nonetheless, Cabinet
confidentiality serves other important public purposes.14 It allows Ministers, senior
public servants, and third-party consultants to provide advice and make decisions
unburdened by any anxiety over unfair of retrospective criticism of their positions.
The advice to government might be expressed cautiously or boldly depending on
the professional evaluation of the public servant. Changes in the structure of the
public service have reduced the tenure of senior public servants and therefore the
confidence with which they can give strong advice. In that context, Cabinet
confidentiality makes an important contribution to the encouragement of frank
advice.
80 Even though Cabinet solidarity and accountability is the primary reason for
protecting Cabinet deliberations from disclosure, public interest immunity serves
other purposes. Cabinet, as a body, will often be called upon to manage complex
and expensive State public projects. In the context of EPAS, it is important to keep
in mind that the complexity of modern technological developments is such that
there cannot always be a high degree of certainty about the preferred course.
81 Unless a reasonably high level of confidentiality is maintained, defensive
advice and decisions may result in the failure to take up valuable opportunities.
82 The balancing of the competing public interests falls in favour of the State’s
claims.
83 I therefore uphold the State’s public interest immunity claims.
Document 12A
84 Document 12A is described as ‘unconfirmed minutes’. I infer from what is
not redacted that it concerns discussions at a meeting between senior public
servants, including Mr Swan, Ms Richter, the Deputy Chief Executive of Health
(System Performance), and Mr Phillips, the Chief Medical Officer. The subject of
the discussion was the desirability of seeking additional funding through Cabinet
for EPAS in order to address a risk arising from having internet access at bedside
computers. Category A2 and A3 objections are taken on the face of the unredacted
passages. The redacted parts of the documents are likely therefore to refer to
Cabinet deliberations on funding.
85 I am satisfied on the basis of the confidential affidavit of Ms Green that the
document is properly the subjects of public interest immunity. The usefulness of
information of that kind to HYLC in the arbitration can only be marginal at best
for the reasons given at [77] above. Yet the importance of protecting Cabinet
confidentiality in its stewardship of projects of this nature is high.
14 See, e.g., Spencer v Commonwealth [2012] FCA 637, [11]-[16] (Emmett J).
-- 24 of 31 --
[2024] SASC 46 Kourakis CJ
23
86 The balance of considerations lies against disclosure. I uphold the State’s
public interest immunity claims.
Document 15A
87 Document 15A is described as a ‘Steering Committee Agenda and Papers’.
It is partly redacted on the ground of a category A1 objection. The papers relate
to a Steering Committee meeting held on 22 August 2013. I am satisfied on the
basis of the confidential affidavit of Ms Green of 18 December 2023 that the
redacted information is from a report which is properly the subject of a claim of
public interest immunity. I am also satisfied on the basis of the confidential
affidavit of Ms Green, deposing to certain directions given by Cabinet in respect
of that document, that the report was procured for the purposes of submission to
the Cabinet.
88 Document 15A is the report of a third-party provider, the subject matter of
which is project governance and is for that reason unlikely to materially assist
HYLC on any of the issues in dispute. I am, therefore, satisfied, given the nature
and content of the report disclosed in the confidential affidavits, that it is extremely
unlikely to assist in the prosecution of its claim in the arbitration. I am also
satisfied, on the basis of oral submissions made on that document in a closed court,
that the redactions would not materially add to information available to the
applicant in the already discovered and produced documents.
89 I uphold the State’s public interest immunity claim.
Documents 30A to 37A
90 Documents 30A to 37A comprise the RAH steering committee agenda and
papers between 25 June 2014 and 10 August 2014. Category A3 claims are made
over all but two documents. A category A2 claim is made in respect of document
30A. Category A3 claims are made over documents 30A, 31A, 32A and 33A. The
redacted parts of the documents are said to be reports, or references to reports,
which were provided to Cabinet.
91 I am satisfied on the basis of the confidential affidavits of Ms Green that the
redacted portions relate to matters which the Steering Committee was considering
for the purpose of inclusion in a Cabinet document for consideration and decision
by Cabinet.
92 Two of the documents bear titles which relate to site safety. Others relate to
remediation of the site. Information on site safety is very unlikely to materially
assist HYLC. The controversy over contamination on the site will be determined
on the objective construction of the contractual documentation and the actual
levels of contamination.
93 I uphold the State’s claim to public interest immunity over documents 30A
to 37A.
-- 25 of 31 --
[2024] SASC 46 Kourakis CJ
24
Document 46A
94 Document 46A is an EPAS Program Board Briefing Note dated
13 November 2014. A category A3 objection is made. I am satisfied that the
document is one produced and created for the purpose of preparing Cabinet
documentation. Even if it be the case that the briefing note refers to a report
provided by an external consultant for the purposes of the Steering Committee
project management role, I am satisfied that it would disclose information put
before Cabinet, if the document were provided in an unredacted form. I am also
satisfied having regard to the subject matter of the note that it is most unlikely to
provide material assistance in support of HYLC’s claims.
95 I uphold the State’s public interest immunity claim.
Documents 79A, 93A and 95A
96 Documents 79A, 93A, and 95A are EPAS Program Board packs and EPAS
Program Status reports. The documents are dated 9 October, 18 May 2016 and
20 September 2016.
97 Document 95A is part of an EPAS Program Status Report. A section on
page 3 is headed ‘Benefits Summary’. HYLC contends that it relates to the
wrongful conduct claim, which is a course of conduct alleged to have commenced
on 2 November 2016. On the basis of the confidential information, I am satisfied
that the single sentence redacted reveals the content of Cabinet documents. Its
description as a ‘Report’ does not mean that it is the report of an external
consultant.
98 I am satisfied on the basis of the confidential affidavit of Ms Green that these
documents they fall within the categories A2 and A3.
99 The documents were created after the 2015 Settlement Agreements. They
can only have limited relevance to any of HYLC’s claim that misleading
representations were made.
Document 96A
100 Ms Green’s confidential affidavit satisfies me that the redacted portions of
document 96A are the nRAH Steering Committee agenda and papers for
26 October 2016 which refer to Cabinet deliberations and documents which had
been before Cabinet.
Documents 57A, 61A and 65A
101 Mr Roberts relied on documents 57A, 61A, and 65A to contend that part of
the minutes of the EPAS Board meeting in document 57A which were initially
redacted were subsequently disclosed with the progressive removal of those
redactions in documents 61A and 65A. Mr Roberts contended that the documents
showed that claims for immunity have been, at least in respect to those documents,
withdrawn or waived.
-- 26 of 31 --
[2024] SASC 46 Kourakis CJ
25
102 Mr Roberts submitted:15
Now, as I say, it might be said against us that that claim is no longer pressed. It might have
been recognised as something that wasn’t properly made and your Honour, on inspection,
might find that those documents are quite different, but that was previously the subject of
a public interest immunity claim on the same foundation of a to and from Cabinet
communication as a secondary reference in committee minutes and the like.
103 Document 57A is dated 8 April 2015. There are redactions under the
headings ‘Unconfirmed Minutes’ and ‘Update’. Document 61A is dated 15 May
2015 and is an extract of what is described in the Schedule to Ms Green’s open
affidavit of 8 December 2023 as the confirmed minutes of a meeting, and records
that an update was completed and ‘can be progressed to Treasury’. Document 65A
is an extract from what is described as confirmed minutes, dated 1 July 2015.
Under the heading ‘Update’, it records that an ‘Action’ relating to the EPAS
program was ‘closed May 2015’. It also records other updates as of 8 May 2015
and 16 April 2015.
104 I was informed in open court by counsel for the State that the documents 57A,
61A, and 65A were not the same document and that no redactions had been
removed.
105 I do not accept HYLC’s submission that an inference can be drawn from
those documents that the updates seen in later documents had been redacted in
document 57A. The use of similar terms and formats for updates and actions on
matters arising from previous meetings is to be expected. Moreover, the draft
minutes and the confirmed minutes are different documents. The confidential
affidavit of Ms Green is consistent with my analysis of the documents on their
face.
106 I reject the submission that the documents show an acceptance that a
redaction was not properly made and the subsequent release of the same document
with fewer redactions. I reject as mere speculation the further submission
premised on that inference, that the unjustified earlier redaction reflects a
misunderstanding of the proper treatment of reports received in the project
management role of the Steering Committee which happens to have been included
in a Cabinet submission.
107 I uphold the State’s claim for public interest immunity in respect to
documents 57A, 61A, and 65A.
Parliamentary privilege
108 Mr Roberts accepted that the descriptions of the documents over which a
claim of parliamentary privilege is taken properly invoke parliamentary privilege.
15 T48.38-49.8.
-- 27 of 31 --
[2024] SASC 46 Kourakis CJ
26
109 Mr Roberts, however, challenges the parliamentary privilege claim made
over the document 140B, entitled ‘Commercial Settlement [STA.234.011.4500]’
and dated 10 February 2016.
110 Ms Rodwell, in her affidavit of 8 December 2023, describes the document as
appearing to be a briefing for the Minister in preparation for attendance at
Parliament, even though it is not in the same template as more formal
parliamentary briefing notes. Ms Rodwell does not have a specific recollection of
any of the many briefing notes she has prepared or sent. However, Ms Rodwell
deposes that less formal documents were occasionally prepared when there was
some real urgency to provide a Minister with information. Such notes were
occasionally delivered to the Minister when he or she was in a parliamentary
chamber. I have no reason to doubt her evidence, even though it is based on her
recollection of the form taken by parliamentary briefing notes and not a specific
recollection of document 140B.
111 Document 1 is entitled ‘Quick reference hot topic [STA.121.004.2678]’.16
Mr Roberts makes the point that Mr Knez, a Director of the Women’s and
Children’s Health Network employed by the Department of Health, disavows any
personal involvement in the document. Mr Knez deposed at [16.3] of his affidavit:
Document [STA.121.004.2678] is entitled “QUICK REFERENCE HOT TOPICS”. While
I was not personally involved in the preparation of this specific document, I am familiar
with similar “Hot Topics” documents which contained abbreviated briefings for topics of
importance, or which were particularly relevant at the time. These documents were also
used for the purpose of attendance at the BFC. I confirm that during my time in the role,
the Chief Executive would routinely take documents in this format to BFC hearings.
112 The acronym ‘BFC’ refers to the Budget and Finance Committee of the
Parliament. I understand the sentence commencing ‘These documents’ to mean
that informal documents of that type were ‘also’, in the sense of ‘in addition to’
the fuller more formal briefing notes referred to in the earlier parts of his affidavit,
used to brief Ministers before the BFC. Accordingly, that paragraph does not mean
that ‘Hot Topics’ documents had a use other than to brief Ministers appearing
before the BFC. I understand Mr Knez to depose that they were prepared
specifically to brief a Minister for appearance before the BFC as an alternative to
a formal parliamentary briefing note.
113 Mr Knez deposed that he was also familiar with similar ‘Hot Topics’
documents which contained abbreviated briefings on topics of importance or
particular relevance. He deposed that these documents were also used for
attendance at the BFC. He confirmed that the ‘Chief Executive would routinely
take documents in this format to BFC hearings’.
114 I uphold the claim to parliamentary privilege over documents 140B and 157B
in the annexure to the originating application.
16 This document is document 157B in the annexure to the originating application.
-- 28 of 31 --
[2024] SASC 46 Kourakis CJ
27
The Balance of the Claims
115 I have considered the objections to the claims of public interest immunity and
parliamentary privilege having regard to the submissions made on the applicable
general principles, and the application of those principles to the particular
documents on which submissions were made. I uphold the State’s claims.
Epilogue
116 After the hearing of argument on this matter, HYLC amended its statement
of claim to seek a determination of the State’s public interest immunity claims in
respect to a further 13 documents. Parliamentary privilege claims have been made
in respect of five of those documents. Two of the documents have since been
produced. The remaining six documents are the subject of public interest
immunity claims.
117 The documents over which public interest immunity is claimed and the nature
of the privilege claimed are:
Item Document
Date
Title Respondent
Category
1C 27/02/2015 Agenda Item 3_EPAS
update_HRCC (04March14) (5).doc
A1
4C 3/12/2015 HCC item 3.2 – nRAH ICT Review
– FINAL.doc
A1
5C 3/12/2015 HRCC item 5.0 – EPAS Progress
Report – Draft – FINAL.doc
A1
7C 11/04/2016 Cabinet Note – NRAH Commercial
Negotiation Strategy and
Governance.doc
A1
8C 13/04/2016 Cabinet Note – NRAH Commercial
Negotiation Strategy and
Governance (edits 12 Apr 16).doc
A1
9C 13/04/2016 Cabinet Note – NRAH Commercial
Negotiation Strategy and
Governance (edits 12 Apr 16).doc
A1
118 The documents over which parliamentary privilege is claimed are:
Item Document
Date
Title Respondent
Category
2C 1/07/2015 PBN Auditor General Report on
Health ICT v02.docx
B1
3C 14/10/2015 New RAH – Costings – including
Project Co Payment.docx
B1
10C 21/06/2016 PBN NRAH Construction.doc B1
11C 14/10/2016 D3. New RAH – Completion
Date.doc
B1
-- 29 of 31 --
[2024] SASC 46 Kourakis CJ
28
119 I am satisfied on the basis of the confidential affidavit of Robin Green that
the documents in question were prepared for, and only for, submissions to a
Cabinet subcommittee. In respect of documents 4C, 5C, 7C, and 8C, they were
prepared for the purpose of deliberation and possible decision by Cabinet.
120 It is apparent from the dates and titles of the documents that the subject matter
of the discussions may be relevant to the controversies which have been referred
to arbitration proceeding on that premise. I directed that the documents to be
produced to me because of their temporal proximity to those issues and because
the subject-matter of the documents conveyed by their titles suggested that they
may contain information which would materially assist the prosecution of HYLC’s
claims. I therefore examined those documents.
121 I find that the information in the documents was provided for the purpose of
assisting Cabinet to make important strategic and policy decisions in respect of the
construction of the nRAH in the context of the commercial dispute with HYLC
and Celsus. The subject-matter of Cabinet’s consideration was the centrepiece of
the South Australian hospital system, and at issue was the expenditure of
substantial public moneys and resources. The critical importance to the State
required its highest organ of executive government to be able to make the decisions
in the best interests thereof as it perceived them to be without concern about
personal criticism which the decision might attract if the documents were
disclosed. On the other hand, I have formed the view that the information does
not materially advance HYLC’s case beyond that which would be apparent from
the overt actions of the State taken through the largely discoverable documents of
the Steering Committee.
122 I am satisfied on the basis of the second affidavit of Helen Rodwell made on
6 February 2024 that all the notes are parliamentary briefing notes and are,
therefore, protected by parliamentary privilege.
123 Ms Rodwell was the senior policy advisor for the Minister for Health between
November 2013 and November 2017. She was responsible for the preparation of
parliamentary briefing notes. A parliamentary briefing note is a relatively short
document, usually no more than a few pages, following a standard template which
provides a summary of key information to assist Ministers in the conduct of
parliamentary proceedings. They often took the form of speaking notes. In her
time in the Minister’s office, the construction of the nRAH was the most significant
infrastructure project being undertaken by the State and was central to the State’s
health services strategy. It was the State’s flagship hospital. She prepared a large
number of parliamentary briefing notes.
124 The preparation of notes for a Minister to participate in parliamentary debate
and answer questions which might be raised either directly or in the course of the
debate falls well within the core purpose of parliamentary privilege and the
-- 30 of 31 --
[2024] SASC 46 Kourakis CJ
29
privilege is essential for the purposes of ensuring free debate in Parliament and, in
particular, for the purposes of ministerial accountability to Parliament.
125 I uphold the State’s claim for public interest immunity and parliamentary
privilege in respect of the documents in the table at [117]-[118] above.
-- 31 of 31 --