SHANE AGELIS DEVELOPMENTS PTY LTD v MARCUS JOHN SYVERTSEN [2024] SASC 89
On Appeal from MAGISTRATES COURT OF SOUTH AUSTRALIA (MAGISTRATE PANAGIOTIDIS)
CIV-22-004372
Appellant: SHANE AGELIS DEVELOPMENTS PTY LTD Counsel: MR A DAL CIN - Solicitor:
ECKERMANN LAWYERS
First Respondent: MARCUS JOHN SYVERTSEN Counsel: MR A LAZAREVICH - Solicitor:
JOHNSTON WITHERS
Second Respondent: MEGAN DANIELLE SYVERTSEN Counsel: MR A LAZAREVICH - Solicitor:
JOHNSTON WITHERS
Hearing Date/s: 24/05/2024
File No/s: CIV-24-001594
B
SUPREME COURT OF SOUTH AUSTRALIA
(Magistrates Appeal: Civil)
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply
to this judgment. The onus remains on any person using material in the judgment to ensure that the intended use of that material does not breach
any such order or provision. Further enquiries may be directed to the Registry of the Court in which it was generated.
SHANE AGELIS DEVELOPMENTS PTY LTD v SYVERTSEN
& ANOR
[2024] SASC 89
Judgment of the Honourable Justice Hughes
8 July 2024
MAGISTRATES - APPEAL AND REVIEW - SOUTH AUSTRALIA - APPEAL TO
SUPREME COURT
PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS
- COMMENCING PROCEEDINGS - TIME FOR SERVICE OF ORIGINATING
PROCESS AND RENEWAL
This is an appeal from an interlocutory decision of a Magistrate refusing to set aside an extension of
time to serve proceedings.
The appellant is a building company that was contracted by the respondents to undertake building
work at a property in Willunga. The construction was completed in April 2017. On 27 April 2024,
the respondents brought an action against the appellant for breach of contract, breach of statutory
warranties and breach of Australian Consumer Law. On 24 October 2022, just prior to the expiry of
the six-month period within which the filed claim was required to be served on the builder, the
homeowners applied to the Magistrates Court to extend the time for service. The application was
made on the basis that the respondents required more time to obtain expert evidence necessary to
properly particularise the claim. This application was granted ex parte on 25 October 2022.
An election for a moratorium on the steps was taken in the proceedings on 17 November 2022, and
the claim was served the following day.
The respondent sought to remove the moratorium in September 2023. On 9 November 2023, the
appellant applied to set aside the order dated 25 October 2022. The application was heard by a
different Magistrate on 30 January 2024, at which time the application was refused with reasons
given. This is the decision subject to this appeal.
-- 1 of 11 --
The appellant contended that the magistrate who heard the application to set aside the extension of
time erred in finding that the homeowners had discharged their duty of candour in respect of the
application. The appellant also contended that as a result of the respondent's non-disclosures, it had
lost the opportunity to defend the breach of warranty claim on the basis that it was out of time.
Held, refusing leave to appeal:
• The information placed before the first Magistrate was adequate for the making of the
extension of time decision. The granting of an extension of time sought before the time has
expired is a decision that permits consideration of a range of factors.
• The appellant did not establish that the Magistrate’s refusal to set aside the decision to extend
time was made on an erroneous appreciation of material that was, and was not, before the
initial decision maker.
• No question of principle or doubt arose such as to justify a grant of permission.
Building Work Contractors Act 1995 (SA) s 32(5); Uniform Civil Rules 2020 (SA) r 41.1, r 64.1, r
64, r 64.5, r 213.1, referred to.
Re Southern Equities Corporation Ltd (in liq); Bond v England (1997) 25 ACR 394; Bell Group NV
(in liq) v Aspinall (1988) 19 WAR 561, considered.
-- 2 of 11 --
SHANE AGELIS DEVELOPMENTS PTY LTD v SYVERTSEN & ANOR
[2024] SASC 89
Magistrates Appeal: Civil
1 HUGHES J: The respondents (homeowners) engaged the appellant (builder) to
undertake building work at a property in Willunga pursuant to a contract entered
into on 7 July 2016 and regulated by, amongst other things, the Building Work
Contractors Act 1995.
2 The homeowners contend that they have a right to recover damages from the
builder in respect of breach of contract, breach of statutory warranties and breach
of the Australian Consumer Law. The value of the contract was over half a million
dollars. The homeowners claim $50,000 in damages for alleged defects.
3 The homeowners filed a claim in the Magistrates Court on 27 April 2022 in
action CIV-22-004372.
4 In this decision, I am using the terms “homeowners” and “builder” to refer to
the parties because the parties’ roles changed from applicant to respondent as
between the proceedings in the Magistrates Court and the appeal in this Court.
This decision also requires consideration of decisions made by two Magistrates,
whom I shall refer to as the first Magistrate and the second Magistrate. By so doing,
I intend no disrespect. I consider that this nomenclature will make the decision
easier for the parties to understand.
5 The several causes of action the homeowners relied upon have different
limitation periods. By filing their action on 27 April 2022, the homeowners were
within the limitation period in respect of all of their causes of action, but it is
undisputed that they were only within time for the claim of breach of statutory
warranties by about two days. On 24 October 2022, just prior to the expiry of the
six-month period within which the filed claim was required to be served on the
builder, the homeowners applied to the Magistrates Court to extend time for
service.1
6 The affidavit in support of that application, sworn by the homeowners’
solicitor, said that the proceedings had been filed, “to protect the applicants’
[homeowners’] claim against the respondent [builder] with respect of (sic)
statutory warranties under the Building Work Contractors Act 1995”. The affidavit
states that, at the time of the filing of the proceedings, the homeowners did not
have all of the expert evidence necessary to properly particularise their claims. 2
The affidavit proceeds to specify the expert proposed to provide the report. The
solicitor indicated that the homeowners intended to obtain the evidence within six
weeks. The solicitor requested that the application be determined prior to 28
1 FDN 15.
2 FDN 16, affidavit of Timothy John Graney.
-- 3 of 11 --
[2024] SASC 89 Hughes J
2
October 2022, “being the date that the action will be placed in the list of inactive
cases.” The application requested a three-month extension of time.
7 The homeowners’ application was granted ex parte in chambers by a
Magistrate (the first Magistrate) on 25 October 2022. The order extended until 22
November 2022 the time within which the proceedings were required to be served
on the builder. In other words, the application was granted but a shorter period of
time was granted than was asked for.
8 An address for service was filed by the builder on the original action on 1
November 2022 although the proceedings had not yet been served on it.
9 On 17 November 2022, the homeowners filed an election for a moratorium
on the steps to be taken in the proceedings, and the following day, served the
original claim.
10 Approximately a year later, in September 2023, the homeowners sought to
remove the moratorium. On 9 November 2023, the builder applied to set aside the
order dated 25 October 2022 by which the extension of time had been granted.
The application to set aside was heard and determined by a different Magistrate
(the second Magistrate), on 30 January 2024. The application to set aside was
refused. Reasons were given.
The second Magistrate’s reasons
11 The second Magistrate’s decision was delivered ex tempore. The second
Magistrate set out the procedural history including that the original application for
the extension of time was made ex parte. The second Magistrate said,
At the time Magistrate Jackson was asked to consider the application extend the time for
service, she was dealing with the matter ex parte. There were other options available to
the applicant and, with hindsight, it might have been better to proceed with the respondent
having full knowledge of the matter. However, it was permissible for the application to be
made ex parte.3
12 The second Magistrate rehearsed the grounds on which the application to set
aside was made, noting that although it was alleged by the builder that there had
been a lack of relevant information given to the first Magistrate, there was no
allegation of fraud or impropriety.4
13 The second Magistrate rejected the builder’s contention that what had been
conveyed in the affidavit in support of the homeowners’ application for an
extension of time amounted to a non-disclosure of information material to the
proper exercise of the first Magistrate’s discretion. Her Honour found that the
supporting affidavit for the original application contained the necessary
3 [2024] SAMC 11 at [2].
4 Ibid at [6].
-- 4 of 11 --
[2024] SASC 89 Hughes J
3
information, namely that the homeowners were awaiting expert reports, even
though no explanation was offered as to why they were still awaited.5
14 The second Magistrate also found that it was evident from the solicitor’s
affidavit that the proceedings had not been served on the builder at that stage, such
that this could not amount to a non-disclosure.6
15 Her Honour found that the builder’s loss of the opportunity to assert that the
proceedings lacked particularity, and should be struck out, was a function of the
application being heard ex parte, but did not amount to a non-disclosure by the
homeowners.7
16 The second Magistrate dealt in some detail with the builder’s contention that
it was prejudiced by the grant of the extension insofar as the grant denied the
builder a defence to the statutory warranty claim under the Building Work
Contractors Act 1995. The builder contended that, without the extension of time,
the time limit for the statutory warranty claim would have expired and the builder
would have had an ability to rely upon the expiry of the limitation period to defend
the claim. The second Magistrate found that this argument was misconceived in
that the proceedings were issued within time, and that even if they were served out
of time, the claim itself would not be statute-barred.8 The second Magistrate
continued that if she were wrong about that, and service out of time did enliven a
defence against the action insofar as it concerned the claim of breach of statutory
warranty, the application to set aside the extension of time to serve would
nevertheless fail. The second Magistrate considered that it could be presumed that
the first Magistrate knew or could calculate the limitation periods applying to the
filing of the proceedings and the time within which to serve, and understood the
parties’ respective situations at the time she granted the extension of time.9
The appeal
17 The builder now appeals the second Magistrate’s order made on 30 January
2024 refusing to set aside the first Magistrate’s order granting an extension of time
for the service of the proceedings.
18 The builder requires permission to appeal because the judgement appealed
against is interlocutory.10 I will return to this in due course.
19 The builder raises three grounds of appeal, numbered 2-4, which numbering
I shall adopt in these reasons for ease of cross-reference to the parties’ written and
oral submissions.
5 Ibid at [10].
6 Ibid at [11].
7 Ibid at [12].
8 Ibid at [15].
9 Ibid at [17].
10 Rule 213.1 of the Uniform Civil Rules 2020 (“UCR”) provides that leave is required for an appeal
against an interlocutory decision (including an order or judgement).
-- 5 of 11 --
[2024] SASC 89 Hughes J
4
Ground 2
20 Ground 2 alleges errors in fact and law by the second Magistrate in
dismissing the application to set aside the earlier decision. This ground asserts
error in the second Magistrate’s finding that the process before the first Magistrate
had not miscarried by virtue of insufficient explanation and disclosure by the
homeowners in the extension of time application.
Ground 3
21 Ground three asserts that the exercise of the second Magistrate’s discretion
miscarried by virtue of the errors identified in ground 1.
Ground 4
22 This ground asserts that the first Magistrate’s order to extend time ought to
have been set aside because it was made following an ex parte consideration of the
application, which led to a failure in disclosure of relevant information, namely
that:
• There was no explanation for the failure to serve the claim within time;
• There was no explanation for the failure to have obtained expert reports;
• If the extension were granted, the builder would lose the limitation defence
in respect of the statutory warranty aspect of the claim.
Builder’s submissions
23 The builder was represented by Mr Dal Cin of counsel. Counsel for the
builder submitted that permission to proceed should be granted because sufficient
doubt attends correctness of the decision under appeal in light of the builder’s
contentions as to how the exercise of discretion should have been approached. The
particular aspect that demands consideration, in the builder’s view, is whether, in
circumstance in which an application to extend time to serve is made ex parte, an
applicant is obliged to clearly draw to the Court’s attention the time limit for the
underlying cause of action, and that the other party will lose the opportunity of a
particular defence if the application is granted.
24 In support of the significance of this issue, counsel for the builder observed
that the substantive claim was filed one day before the statutory time limit in
respect of the statutory warranty cause of action expired, and was not able to be
extended: s 32(5) Building Work Contractors Act 1995.
25 The builder relies upon the homeowners’ obligation to have served the
proceedings “as soon as practicable” pursuant r 41.1.11 In any event, r 64.1
11 UCR, r 41.1.
-- 6 of 11 --
[2024] SASC 89 Hughes J
5
required it to be served within six months (i.e. by 27 October 2022), or as ordered
by the court.12
26 The builder submits that the homeowners did not serve as soon as practicable
and waited until 24 October 2022 to seek the extension of time. The application
was granted by the first Magistrate the following day.
27 Relying on a note to r 64,13 the builder contended that the homeowners should
have applied for a moratorium in respect of the action which, at that stage, they did
not do. The Note says:
Note— The Court expects a party to serve a respondent if possible. If the claim is for
damages for personal injuries and the applicant’s condition is not yet stable or there is other
good reason for no further steps to be taken in the proceeding for the time being, the Court
expects the applicant to elect for a moratorium on steps under rule 64.5 rather than seek an
extension of time for service.
28 The builder argued that the homeowners failed to disclose to the first
Magistrate the date of the expiry of the limitation period for the bringing of the
proceedings insofar as they asserted a breach of statutory warranty. The builder
further argued that there had been inadequate explanation before the first
Magistrate as to why the proceedings could not be served within time. As a result
of these two failures, the builder had been unfairly deprived of its ability to defend
the action on the basis that the proceedings had not been served within time.
29 In reliance upon Re Southern Equities Corporation Ltd (in liq); Bond v
England,14 the builder contended that in the ex parte hearing before the first
Magistrate, the homeowners were under an obligation to disclose all matters
known to them that would have been raised by the other party in opposition to the
application.
30 Adopting the language of Bell Group NV (in liq) v Aspinall,15 the builder
contended that there had been a “material non-disclosure” by the homeowners to
the first Magistrate which “throws a new and different light on the situation of the
parties involved”.16
31 The builder contended that the second Magistrate’s finding that the
homeowners’ explanations were sufficient, failed to address the fact that the
experts whose opinions were sought for the defects were not retained at the time
the application was made. The builder maintains that the claim was sufficiently
pleaded to have been served when the application to extend time was made.
12 Ibid, r 64.1.
13 Ibid, r 64.
14 (1997) 25 ACR 394.
15 (1998) 19 WAR 561 at 15.
16 Bell Group NV (in liq) v Aspinall (1998) 19 WAR 561.
-- 7 of 11 --
[2024] SASC 89 Hughes J
6
Homeowners’ submissions
32 The homeowners were represented by Mr Lazarevich of counsel. The
homeowners contend that there is not sufficient doubt attending the decision, that
it raises no principle of general importance, and no substantial injustice to the
builder would be caused by refusal because the dispute will be heard on its
merits.The homeowners maintain that permission to appeal should be refused.
33 The homeowners contend that the crux of the builder’s argument is that it has
lost the opportunity of a defence, namely that the claim is statute-barred. The
homeowners submit that because the claim was filed within time, no such
‘defence’ arises.
34 The homeowners contend that the builder delayed in making its application
to set aside the order, there being approximately a year between the builder filing
an address for service and making the application to set aside the order of the first
Magistrate. The homeowners observe that the builder did not appeal the decision
when the claim and amended claim were served in November 2022.
35 The homeowners agree that the statutory warranty limit expired on or about
29 April 2022.
36 The homeowners contend that their affidavit in support of the application
sufficiently signalled to the Magistrate that the extension of time to serve was made
following the filing of a claim made close to the end of the limitation period. As
to grounds 2 and 3, the homeowners submit that there was no obligation to explain
any delay in obtaining an expert’s report or not serving the claim.
37 In relation to ground 4, the homeowners assert that there was no breach of
the duty of candour in the making of the application, and the builder did not lose
the benefit of a limitation period. They argued that s 32(5) of the Building Work
Contractors Act 1995 requires the proceedings to be commenced, not commenced
and served, within five years. They say that it is not in dispute that the proceedings
were commenced within time.
38 In any event, r 64 allows the time to serve to be extended even after the time
for service has expired.17 If the time limit for service had expired, the claim would
have been placed on the inactive list and could have been reinstated.
39 The homeowners argue, citing Cook v Dodds,18 that an application to set aside
such as was made to the second Magistrate was correctly refused, given that the
original decision could have been appealed, and in the absence of “additional
material evidence” that was not before the Court when it made the original
decision.
17 UCR, r 64.
18 (1985) 40 SASR 79.
-- 8 of 11 --
[2024] SASC 89 Hughes J
7
40 It was submitted that injustice, if the order were set aside, would accrue to
the homeowners, because the delay by the builder in bringing the application to set
aside means that if the application were granted, all of the causes of action, and not
just the statutory warranty claim, would likely be time-barred.
41 The home-owners contended that in addition to the reasons given by the
second Magistrate, the application to set aside should be refused on any re-exercise
of the discretion by this Court because of:
• The delay between service of the claim and the application for setting aside;
• Lack of prejudice to the builder;
• The fact that the gap between the time by which the proceedings were
required to be served in order to be within the six-month outer limit (27
October 2022), and the date on which the claim was in fact served (18
November 2022), was short.
42 The homeowners contend that they should be awarded costs on an indemnity
basis.
Consideration
43 The builder came before the Court with an ambitious task. That task was to
persuade this Court to set aside an interlocutory order made in the exercise of a
broad discretion. Further, if successful, this Court would be required to remit to
the Magistrate’s Court the making of the original decision and that is also a
decision made in the exercise of a broad discretion. For the reasons that follow,
that task has not been achieved.
44 The builder did not establish, either before the second Magistrate or before
the Court, that the homeowners breached the duty of candour for an extension of
time to serve the proceedings. The information placed before the first Magistrate
was adequate for the making of the extension of time decision.
45 The grant of an extension of time to serve proceedings is a decision that
permits consideration of a range of factors, and the attribution of weight to any of
those factors by reference to the particular circumstances of the case. In Gibbs v
Williams19 the Full Court of the Supreme Court of South Australia set out the
factors which are material to an application to renew a summons. Sangster J
observed that these included the applicant’s reasons for the failure to serve
within time, the contribution of each party to the failure to serve, the effect on
each party in respect of the litigation, whether the claim would be statute-barred
and where the interests of justice lay.20 These factors may also be relevant to the
determination of an application to extend time to serve before the time has
19 (1979) 24 SASR 243.
20 At p 247.
-- 9 of 11 --
[2024] SASC 89 Hughes J
8
expired. However, an application that is made within time will generally create
less tension between the parties’ competing interests than one that is made after
time has expired because a respondent will not have had a basis to anticipate that
litigation will not ensue and because the applicant has not been derelict in
complying with the procedural rules. The proceedings had been commenced
within the statutory time frame for all of the causes of action asserted. The time
limit for one of the causes of action, the breach of statutory warranty, subsequently
expired. The homeowners’ application to extend time to serve was within the
period within which service was required.
46 The chronology of relevant events was not withheld from the first Magistrate.
47 Not only were the proceedings filed within time, the application for service
to be extended was made at a time when it was still possible for the homeowners
to serve the builder if the order extending time to serve was not made. There was
a day or so following the determination of the homeowners’ application in which
the homeowners could have effected service within time if the application had been
refused. Whilst the builder contends that if the order had not been made then the
homeowners would not have served their application within time, the builder has
not established that factual proposition.
48 At its highest, what was not disclosed by the homeowners was the possibility
that if the application was refused and the homeowners failed to serve the
proceedings within the following day or so, the action would have been moved
into the inactive case lists and one of the causes of action would have become
statute-barred. Such a disclosure was not required. The extrapolation from the
circumstances in Re Southern Equities Corporation Ltd (in liq); Bond v England21
is not apt. In those proceedings, there were failures to disclose evidence of past
events (expiry of time limits) and future intentions (to take certain proceedings)
that bore upon the exercise of the discretion. In this proceeding, the second
Magistrate correctly concluded that no fact that was required to be disclosed was
omitted from the homeowners’ application.
49 The fact that the homeowners were nearly out of time was not a matter that
required disclosure. There was no “material non-disclosure” of facts or materials.
50 The allegation of a failure by the homeowners to provide sufficient
explanation for the need for an extension of time was also within the second
Magistrate’s discretion to reject.
51 The discretion to extend time to serve for the purpose of enabling a claimant
to gather evidence is one that entails a balance of factors. Had the proceedings
been served without the evidence, a further cost may have been incurred in
subsequent dispute as to the pleadings. The homeowners sought a three-month
extension. The first Magistrate granted an extension of approximately four weeks.
21 (1997) 25 ACR 394.
-- 10 of 11 --
[2024] SASC 89 Hughes J
9
The order required that the homeowners serve notice of the impending claim
before making any further application for an extension.
52 The order made reflected a flexible, balanced approach justified by the
desirability of keeping litigation progressing whilst enabling the parties to prepare
in a way that maintains the opportunity of settlement but ensures that the parties
are ready to proceed to trial if settlement cannot be achieved.
53 The application to the second Magistrate to set aside an earlier order made in
the exercise of a discretion, was required to be approached in a manner that did not
convert it into a de facto appeal of the first Magistrate’s decision. The second
Magistrate was required to focus on the adequacy of the material upon which the
original exercise of discretion was made. The second Magistrate quite properly did
so. The builder did not establish that the second Magistrate’s refusal to set aside
the first Magistrate’s decision to extend time was made on an erroneous
appreciation of material that was, and was not, before the first Magistrate.
54 Accordingly, the builder’s appeal does not succeed.
55 I do not consider that the appeal raises a point of general principle warranting
permission. The principle as to disclosure on an ex parte application is not
enlivened on these facts in a way that requires exploration of the parameters of that
principle.
56 I do not consider that sufficient doubt attends the exercise of the discretion
by the second Magistrate not to set aside the extension of time, to warrant a grant
of permission to appeal.
57 It is not necessary to canvas the re-exercise of the discretion. I consider that
the appeal is without merit and leave is refused.
58 In light of these conclusions, I award indemnity costs to the homeowners in
respect of the appeal.
-- 11 of 11 --