[2024] SASC 108
Applicant: GOYDER WIND FARM 1 PTY LTD (AS TRUSTEE FOR THE GOYDER WIND FARM
TRUST 1) Counsel: MR R FENWICK ELLIOTT WITH MR P ADAMS - Solicitor: INKBLACK LEGAL
First and Second Respondents: GE RENEWABLE ENERGRY AUSTRALIA PTY LTD AND ELECNOR
AUSTRALIA PTY LTD Counsel: MR N FLOREANI KC WITH MR C HUMBY - Solicitor: K&L GATES
Third and Fourth Respondents: DAVID THYER AND RESOLUTION INSTITUTE No Attendance
Hearing Date/s: 06/08/2024
File No/s: CIV-24-006801
A
SUPREME COURT OF SOUTH AUSTRALIA
(Civil: Judicial Review)
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply
to this judgment. The onus remains on any person using material in the judgment to ensure that the intended use of that material does not breach
any such order or provision. Further enquiries may be directed to the Registry of the Court in which it was generated.
GOYDER WIND FARM 1 PTY LTD v GE RENEWABLE
ENERGY AUSTRALIA PTY LTD & ORS
[2024] SASC 108
Judgment of the Honourable Justice Stein
20 August 2024
CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS -
REMUNERATION - STATUTORY REGULATION OF ENTITLEMENT TO AND
RECOVERY OF PROGRESS PAYMENTS - ADJUDICATION OF PAYMENT
CLAIMS
CONTRACTS - GENERAL CONTRACTUAL PRINCIPLES - CONSTRUCTION
AND INTERPRETATION OF CONTRACTS
STATUTES - ACTS OF PARLIAMENT - INTERPRETATION - GENERAL
APPROACHES TO INTERPRETATION - TO GIVE OPERATION AND EFFECT
TO ACT
ADMINISTRATIVE LAW - PREROGATIVE WRITS AND ORDERS -
CERTIORARI - GROUNDS FOR CERTIORARI TO QUASH - EXCESS OR
WANT OF JURISDICTION - PARTICULAR INSTANCES OF
JURISDICTIONAL ERROR
PROCEDURE - STATE AND TERRITORY COURTS: JURISDICTION,
POWERS AND GENERALLY - INHERENT AND GENERAL STATUTORY
POWERS - TO PREVENT ABUSE OF PROCESS - ATTEMPTS TO
RELITIGATE
ESTOPPEL - ESTOPPEL BY JUDGMENT - ISSUE ESTOPPEL - GENERAL
PRINCIPLES
-- 1 of 54 --
ESTOPPEL - ESTOPPEL BY JUDGMENT - ANSHUN ESTOPPEL -
GENERALLY
Goyder Wind Farm 1 Pty Ltd, the applicant (“Goyder”), entered into contracts with GE Renewable
Energy Australia Pty Ltd and Elecnor Australia Pty Ltd, the first and second respondents
(“GE-Elecnor”), for the construction of a windfarm.
GE-Elecnor has issued at different times three separate claims for progress payments relating to
claimed entitlement to delay costs arising from a claimed an extension of time pursuant to the
contract. Two of the claims have proceeded to adjudication determination pursuant to Building and
Construction Industry Security of Payment Act 2009 (SA) (“the Act”). The third claim is currently
enjoined from proceeding by interim orders made at the commencement of these proceedings.
Goyder applied for review of the second determination by the adjudicator and sought an order
quashing that second determination in addition to orders preventing GE-Elecnor taking steps to
enforce the determination and from taking steps to progress a third claim to adjudication.
Goyder submitted the adjudicator had erred in the second determination on the basis he failed to
apply s 22(4) of the Act and wrongfully permitted GE-Elecnor to re-agitate the claim for delay costs.
GE-Elecnor submitted the various delay cost claims were different and there had been no
impermissible re-agitation of claims as between the first and second determination and the third
payment claim.
Held (dismissing the application insofar as it relates to the second adjudication determination):
1. The delay claims did not constitute a singular claim for construction work which would have
been carried out in the extension of time period.
2. Section 22(4) of the Act did not apply. If it had applied, s 22(4) of the Act is not a matter of
jurisdiction.
3. The prolongation and procurement premium delay cost claims did not overlap and it was not
an abuse of the processes of the Act to claim those amounts in separate payment claims.
Held (allowing the application insofar as it relates to the thickening costs claim aspect of the third
adjudication claim):
4. The thickening costs claim aspect of the claim is precluded by the legislation as an
impermissible re-agitation by re-claiming thickening costs in respect of which the Adjudicator
has already discharged the statutory function by rejecting the claim as lacking evidential
foundation.
Building and Construction Industry Security of Payment Act 2009 (SA) ss 8, 13, 17, 22(4), 32;
Building and Construction Industry Security of Payment Act 1999 (NSW) ss 8, 9, 13(1), 13(5), 13(6),
17, 22(1), 22(4); Building and Construction Industry Payments Act 2004 (Qld); Building and
Construction Industry (Security of Payment) Act 2009 (ACT) ss 24(2), 24(4), 38, referred to.
Coordinated Construction Co Pty Ltd v Climatech (Canberra) Pty Ltd [2005] NSWCA 229;
Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd (2005) 63 NSWLR 385;
EnerMech Pty Ltd v Acciona Infrastructure Projects Aust Pty Ltd [2024] NSWCA 162; John Goss
Projects Pty Ltd v Leighton Contractors Pty Ltd (2006) 66 NSWLR 707; Dualcorp Pty Ltd v Remo
Constructions Pty Ltd (2009) 74 NSWLR 190; Civil & Allied Technical Construction Pty Ltd v
Resolution Institute [2019] SASC 193; Rothnere Pty Ltd v Quasar Constructions NSW Pty Ltd [2004]
NSWSC 1151; Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421; Chase Oyster Bar Pty Ltd v
Hamo Industries Pty Ltd (2010) 78 NSWLR 393; Project Blue Sky Inc v Australian Broadcasting
Authority (1998) 194 CLR 355.; Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd
(2018) 264 CLR 1; Harlech Enterprises Pty Ltd (ATF Harlech Family Trust) v Beno Excavations
Pty Ltd (2022) 18 ACTLR 245; University of Sydney v Cadence Australia Pty Ltd [2009] NSWSC
635; Urban Traders Pty Ltd v Paul Michael Pty Ltd [2009] NSWSC 1072; Watpac Constructions
(NSW) Pty Ltd v Austin Corp Pty Ltd [2010] NSWSC 168; Wiggins Island Coal Export Terminal Pty
Ltd v Monadelphous [2016] QSC 96; Caltex Refineries (Qld) Pty Ltd v Allstate Access (Australia)
-- 2 of 54 --
Pty Ltd [2014] QSC 223; Estate Property Holdings Pty Ltd v Barclay Mowlem Construction Ltd
[2004] NSWCA 393, considered.
-- 3 of 54 --
-- 4 of 54 --
GOYDER WIND FARM 1 PTY LTD v GE RENEWABLE ENERGY
AUSTRALIA PTY LTD & ORS
[2024] SASC 108
Civil: Application
1 STEIN J: Goyder Wind Farm 1 Pty Ltd as trustee for the Goyder Wind Farm 1
Trust (“Goyder”) entered into contracts with the first and second respondents,
GE Renewable Australia Pty Ltd and Elecnor Australia Pty Ltd (collectively
“GE-Elecnor”) for the construction of a wind farm. GE-Elecnor claimed
entitlement to various extensions of time and delay costs said to arise from delays
to site access caused by Goyder. GE-Elecnor relevantly issued three separate
claims for progress payments at different times and made three separate
applications for adjudication of such payment claims pursuant to the provisions of
the Building and Construction Industry Security of Payment Act 2009 (SA) (the
“Act”). Two applications resulted in adjudication determinations. A further
application for adjudication was commenced but has not yet proceeded as a
consequence of orders made in this action.
2 In this action Goyder seeks review of the second determination of the third
respondent, Mr Thyer (the “Adjudicator”), which determined that Goyder pay a
progress payment in the amount of $21,029,854.77 to GE-Elecnor. Goyder seeks
an order quashing that determination. Alternatively, Goyder seeks declaration that
the determination is of no effect at all or, alternatively, is of no effect insofar as it
purported to determine rights for delay costs in respect of GE-Elecnor’s extension
of time claims.
3 Goyder seeks to restrain GE-Elecnor from taking any steps to enforce the
determination and from taking steps to progress a third claim for a progress
payment made on 1 July 2024 to adjudication determination.
4 Goyder sought an urgent hearing of its application for review. Interim
injunction orders were made pending the hearing and determination of the
application. The parties complied with an extremely tight timetable to file
materials, the hearing was expedited and I have written reasons as a matter of
urgency.
5 The Adjudicator and the fourth respondent, the Resolution Institute, did not
take an active role and will abide the outcome of these proceedings.
6 For the reasons that follow I have determined to refuse the application insofar
as it relates to the adjudication determination made on 17 July 2024 but to make
orders in relation to aspects of the application for adjudication which is presently
enjoined from proceeding.
-- 5 of 54 --
[2024] SASC 108 Stein J
2
Background
The contract
7 In 2021, Goyder and GE-Elecnor entered into engineering, procurement and
construction contracts for the construction of a wind farm (the “contract”). The
project was divided into Stage 1A and Stage 1B with Stage 1A relating to 38 wind
turbines.
8 In the contract, delay costs are defined as “costs payable to GE-Elecnor for
delay and disruption determined in accordance with cl 13.11”.
9 Clause 13.3 of the contract provides for GE-Elecnor’s entitlement to, and
process for, seeking extensions of time (“EOT”). If GE-Elecnor considers it has
been or is likely to be delayed, it must give written notice of the delay. If a delay
event continues for a period longer than contemplated in the EOT claim,
GE-Elecnor may amend the EOT claim by submitting a revised claim.1
10 Under cl 13.11(a) of the contract, where GE-Elecnor has been granted an
extension of time under cl 13.3 for delays of the kind defined as a Delay Cost
Event, Goyder must pay to GE-Elecnor delay costs being “such extra costs as are
directly and necessarily incurred by [GE-Elecnor] in connection with the extension
by reason of the Delay Cost Event”. Delay costs are valued in accordance with
schedule 5 to the contract.
11 Pursuant to clause 20.1 of the contract, in each calendar month, if GE-Elecnor
considers there has been a completion of a milestone event or that other amounts
are payable to GE-Elecnor under the contract, GE-Elecnor is to submit to the
Principal’s Representative (as defined in the contract) a claim for payment.
12 Clause 20 sets out the matters which must be addressed in a payment claim.
It includes calculation of milestone amounts and any other amounts payable to GE-
Elecnor in accordance with the contract.
13 GE-Elecnor may only submit one payment claim per calendar month.
14 The contract provides for a payment schedule to be issued to GE-Elecnor
certifying, among other things, the milestone amount attributable to a certified
completed milestone event and any other amounts payable to GE-Elecnor in
accordance with the contract.2 The amount to be certified in a payment schedule
is able to be adjusted by, among other things, any correction to amounts previously
certified in a previous payment certificate.3
1 Contract, cl 13.3(c).
2 Contract, cl 20.3.
3 Contract, cl 20.4(b).
-- 6 of 54 --
[2024] SASC 108 Stein J
3
15 Pursuant to the contract, any payment certificate or payment of monies under
cl 20.6 is only a payment on account.4
16 A failure to include in a payment certificate any amount which Goyder is
entitled to retain, deduct, withhold or set off does not prejudice Goyder’s right to
subsequently exercise such rights to retain, deduct, withhold or set off any amount.5
17 Pursuant to cl 20.15, GE-Elecnor agrees and acknowledges that the dates
specified in cls 20.1(a) and 23.76 of the contract are a ‘reference date’ as defined
in the Act.
18 Nothing in the contract restricts or limits GE-Elecnor’s right to refer any
dispute to adjudication.7
19 If a dispute arises between the parties, the contract provides that a notice must
be issued referring the matter to senior representatives of Goyder and GE-Elecnor
for negotiation.8 In the event a dispute relating to a commercial or legal issue is
not able to be resolved through negotiation, the contract stipulates that the dispute
must be referred to arbitration.9
20 Schedule 1 of the contract defines “balance of plant” (“BoP”) as all aspects
of the works except works relating to the wind turbines, including but not limited
to their installation, commissioning and testing.
21 Schedule 5 of the contract sets out the principles for valuing delay costs.
Those principles include that the amounts determined are to be applied in a manner
that only compensates GE-Elecnor for the additional costs directly and reasonably
incurred by it that relate to the period of delay for which an extension of time has
been granted under cl 13.3. Overhead and profit cannot be included apart from the
stipulated overhead component of 12 percent of the value of delay costs.
22 The valuation of delay costs is to be calculated by adding (where applicable)
the labour component, plant component, services and sub-contractor work
component, materials component, and allowable overhead (each defined as a
component). Each component is to be calculated in accordance with the schedule.
The labour component is valued in the same manner as the valuation of a labour
component for a variation, which is by reference to units of labour used, or to be
used, applied to labour rates set out in the schedule.
23 The specifications in schedule 2 to the contract set out the scope of works as
detailed engineering investigation and design, procurement, manufacture, supply,
delivery, storage, construction, installation, testing, commissioning and defects
4 Contract, cl 20.8.
5 Contract, cl 20.8(b).
6 Contract, cl 23.7 relates to the issue of a final payment claim.
7 Contract, cl 20.15(b).
8 Contract, cl 43.2.
9 Contract, cl 43.4(a).
-- 7 of 54 --
[2024] SASC 108 Stein J
4
liability, operations, maintenance, repair, refurbishment and modification of a
complete wind farm at the site.
24 Section 4.2 of schedule 2 sets out a range of components of work. The
specifications list numerous areas and items of work comprising the defined works,
including construction of sub-stations, wind farm collector system (including
underground cabling), wind turbines (including support stands and platforms),
access infrastructure, structural works, civil works including earthworks and
trenching, enabling works and all required site investigations, installation, and
commissioning of control systems.
25 Payment is made by reference to milestone events which relate to stages of
completion of components of the work. Milestone events are defined in schedule
4. The schedule contains milestone events for the wind turbine generator price
component of the contract and the BoP component. Such milestone events include
mechanical completion, sectional completion, commencement of establishment
works, commencement of execution of internal access roads, stages of delivery of
tower foundations, structural concrete pouring, delivery of tower foundations,
stages of erection of towers, termination of sub-station earthworks (embankment,
access road and external drainage), delivery of main equipment, stages of delivery
of medium voltage (“MV”) cables, stages of delivery of MV trenches, assembly
of towers and so on.
26 The contract provides for phasing of permitted activities as set out in schedule
28. During each phase, GE-Elecnor is permitted to carry out permitted activities
as defined in the contract. Phases 1 includes geotechnical investigations, certain
earthworks and any aspects of the work to be performed on public land. Phase 2
includes all phase 1 permitted activities in addition to site establishment
(construction compound set up). Phase 3 includes all elements of the works
permitted under the contract.
EOT claims
27 GE-Elecnor made EOT claims, EOT 001 and EOT 002, by letters dated
19 July 2022 and 8 August 2022 and claimed costs arising from the alleged delays.
First payment claim
28 On 29 February 2024, GE-Elecnor served on Goyder a payment claim in the
amount of approximately $19.1 million (the “First Payment Claim”).
29 The First Payment Claim was a claim pursuant to cl 13.11(a) of the contract
for delay costs alleged to be directly and necessarily incurred by reason of an
alleged delay cost event the subject of GE-Elecnor’s EOT 001 and EOT 002
claims. The reference date under the Act for the First Payment Claim was
29 February 2024.
30 The First Payment Claim sought payment of approximately $3.8 million in
respect of milestone events and $15.3 million for prolongation costs and costs for
-- 8 of 54 --
[2024] SASC 108 Stein J
5
thickening of indirect resources pursuant to cl 13.11 of the contract or,
alternatively, as an adjustment to contract price under cl 12.4.
First adjudication application and first adjudication determination
31 After receiving Goyder’s payment schedule, on 8 April 2024, GE-Elecnor
submitted an adjudication application in respect of the First Payment Claim (“First
Adjudication Application”).
32 In the First Adjudication Application, GE-Elecnor claimed “partial payment
of the total delay costs incurred by reason of extension of time claims”. Those
costs were split into:
prolongation costs; and
thickening costs.
33 GE-Elecnor maintained Goyder’s delays caused GE-Elecnor to change its
strategy for procurement and delivery of foundations and earthworks and MV
trenching and electrical works packages. GE-Elecnor’s position was that it was
required to supplement its resources to deliver the works by entering into
additional sub-contracts as well as using self-delivery crews.
34 After receiving documents and submissions from the parties, the Adjudicator
on 2 May 2024 made an adjudication determination (“First Adjudication
Determination”).
35 In the First Adjudication Determination, the Adjudicator determined, among
other things that:
1. the alleged delays the subject of GE-Elecnor’s EOT 001 and EOT 002 claims
were delay events as defined under the contract;
2. the (combined) delay the subject of GE-Elecnor’s EOT 001 and EOT 002
was 118 days and, pursuant to cl 13.3(f) of the contract, GE-Elecnor was
entitled to an extension of time of 118 days to the date for practical
completion;
3. GE-Elecnor was entitled pursuant to cl 13.11(a) of the contract for extra costs
as were directly and necessarily incurred by reason of the delay event.
36 The Adjudicator did not agree with Goyder’s submission that GE-Elecnor
was not entitled to an EOT by reason of concurrent delay or failure to mitigate.10
The Adjudicator was satisfied the delays were on the critical path, no reasonable
reprograming or alteration of sequences of activities could avoid the delay without
10 First Adjudication Determination at [252]-[261].
-- 9 of 54 --
[2024] SASC 108 Stein J
6
incurring additional costs and GE-Elecnor took all reasonable steps that could be
taken without incurring additional costs to mitigate the delays.
37 In respect of the claim for prolongation costs, the Adjudicator referred to
cl 13.11(a) of the contract which provided that where GE-Elecnor had been
granted an extension of time for a Goyder caused delay, Goyder must pay such
extra costs as are directly and necessarily incurred by GE-Elecnor in connection
with the extension by reason of the delay cost event. The Adjudicator accepted
GE-Elecnor’s entitlement to prolongation and allowed an amount for prolongation
costs.
38 In relation to thickening of indirect resources, GE-Elecnor submitted the
costs incurred for thickening were substantiated by GE-Elecnor having identified
the additional personnel mobilised as a consequence of the delays on the basis of
payroll records, supplemented by third party invoices.
39 The Adjudicator considered the burden of proof was on GE-Elecnor to
establish entitlement to its thickening of indirect resources claim. A project
manager for Elecnor, Mr Joven, assessed the thickening of indirect resources based
on additional resources he identified by comparing the tender manning schedule
against actual personnel Mr Joven asserted were required as a result of the change
in procurement strategy due to the EOT delays.11 The Adjudicator pointed out that
the correctness of Mr Joven’s assessment and valuations were reliant on
GE-Elecnor’s tender manning schedule being reasonable and achievable and that
each of the additional resources claimed were required due to the delays the subject
of EOT 001 and EOT 002.12
40 The Adjudicator considered it was not enough to evidence a cost being
incurred. Rather, GE-Elecnor had to demonstrate how delay caused the incurrence
of those costs; that GE-Elecnor did not establish any basis to “join the dots”
between the costs and the delay and, absent any evidence of any linkage between
alleged delay and thickening costs, there was no proper basis for the claim. The
fact of a cost did not mean an entitlement to recovery.13
41 Based on the information provided, the Adjudicator was not satisfied that
GE-Elecnor’s tender manning schedule was reasonable and achievable and the
resources claimed by GE-Elecnor in the thickening of indirect resources claim
were additional resources required due to delays the subject of EOT 001 and EOT
002.14
42 In the circumstances, the Adjudicator did not consider GE-Elecnor had
discharged its burden of proof to establish entitlement to its thickening of indirect
resources claim either pursuant to cl 13.11 of the contract or as a variation pursuant
11 First Adjudication Determination at [319].
12 First Adjudication Determination at [327].
13 First Adjudication Determination at [330].
14 First Adjudication Determination at [332].
-- 10 of 54 --
[2024] SASC 108 Stein J
7
to cl 12.4 of the contract. The Adjudicator therefore determined that GE-Elecnor
was not entitled to any amount in respect of the thickening of indirect resources
claim and allowed $0 for the claim in calculating the adjudicated amount.15
Second payment claim
43 On 30 April 2024, GE-Elecnor served a payment claim in the amount of
$28.5 million pursuant to the contract (Second Payment Claim).
44 In the Second Payment Claim, GE-Elecnor claimed payment of $2.3 million
for milestone events and $26.1 million for procurement premiums for civil BoP
said to be additional direct costs of procuring civil BoP works due to a change in
procurement strategy resulting from delays caused by Goyder. The costs claimed
in the Second Payment Claim arose out of EOT 001 and EOT 002. On
GE-Elecnor’s case, the costs claimed were separate and distinct.
Second adjudication application and second adjudication determination
45 After receiving Goyder’s payment schedule, GE-Elecnor submitted an
adjudication application (“Second Adjudication Application”). Goyder
provided an adjudication response. The Adjudicator received voluminous
documents and submissions.
46 On 17 July 2024, the Adjudicator delivered an adjudication determination
upon the Second Payment Claim (“Second Adjudication Determination”).
47 In the Second Adjudication Determination, the Adjudicator determined the
amount of the progress payment to be paid by Goyder as $21,029,854.77.
48 The progress payment of $21,029,854.77 provided for in the Second
Adjudication Determination was calculated as follows:
an amount for milestone events: $1,419,518.68;
delay claims as follows:
− procurement premiums for civil BoP: $21,098,688.44;
− 12 percent for overheads: $2,531,842.62;
less delay liquidated damages: $5,932,000,00;
GST (10 percent): $1,911,804.98.
49 Based on his review of the claim for delay costs in the First and Second
Payment Claims, the Adjudicator was satisfied that the construction work and
goods and services the subject of the claim for delay costs as determined in the
First Adjudication Determination were separate and did not overlap with the
15 First Adjudication Determination at [334].
-- 11 of 54 --
[2024] SASC 108 Stein J
8
construction work and goods and services the subject of the claim for delay costs
in the Second Adjudication Application.16
50 The Adjudicator considered he had not in the First Adjudication
Determination determined the value of the construction work and goods and
services the subject of the claim for delay costs made in the Second Adjudication
Determination. Accordingly, s 22(4) did not apply. In the event he was wrong
about that, the Adjudicator considered any assessment as to change in value should
be made by assessing whether or not there had been any change in the value since
the reference date of the First Payment Claim (as opposed to the date of the First
Adjudication Determination). In such case, the Adjudicator was satisfied the value
of the work had changed since the date of the First Payment Claim. The exception
in s 22(4) of the Act applied in that scenario and therefore the Adjudicator was not
bound by the value determined in the First Adjudication Determination.
51 The Adjudicator was satisfied that the changes in procurement strategy made
by GE-Elecnor were made as a result of the delays the subject of the claims for
EOT 001 and EOT 002 and the changes were reasonable and appropriate in the
circumstances. The Adjudicator was satisfied the delay costs claimed were
reasonable and necessarily incurred in connection with the delays the subject of
EOT 001 and EOT 002.17
Third payment claim
52 On 2 July 2024, GE-Elecnor served a payment claim claiming $25.3 million
(“the Third Payment Claim”). The amount of the Third Payment Claim
comprised $4.6 million in respect of milestone events and $20.7 million in respect
of thickening costs and procurement premiums for the MV trenching work
pursuant to cl 13.11 or, alternatively, as an adjustment to contract price under
cl 12.4 of the contract.
53 GE-Elecnor thereafter submitted an adjudication application which, as set out
above, has not proceeded as a result of orders made.
Nature of delay costs claimed
54 The delay costs claimed in the three payment claims were termed
prolongation costs, thickening costs and procurement premiums.
55 Prolongation costs were said to be indirect time related costs of labour, plant
and services, and site running costs resulting from delays.
56 Thickening costs were said to be the indirect costs of additional personnel
and light vehicles required as a result of the delays.
16 Second Adjudication Determination at [255].
17 Second Adjudication Determination at [282].
-- 12 of 54 --
[2024] SASC 108 Stein J
9
57 Procurement premiums were said to constitute a claim for direct costs paid
in the form of premiums by GE-Elecnor in relation to BoP works incurred due to
delays. The procurement premiums claims were divided into two parts. The first
was for civil BoP Foundations and Earthworks works and the second for electrical
MV Trenching and Electrical reticulation works.
58 On GE-Elecnor’s case, procurement premiums are separate and distinct
direct, additional costs incurred in engaging sub-contractors, third-party labour and
plant hire providers as opposed to indirect resources comprised in thickening
claims.
Comparison between amounts claimed in the first, second and third payment
claims
59 The First Payment Claim included approximately $10.6 million in respect of
additional (thickened) personnel costs for GE-Elecnor’s own personnel, primarily
relating to supervision and management of works.
60 The Third Payment Claim included approximately $14.3 million in respect
of additional (thickened) personnel costs for GE-Elecnor’s own personnel,
primarily relating to supervision and management of the works.
61 Mr Joven deposed by affidavit dated 30 July 202418 to the circumstances in
which the claim for thickening costs in the Third Payment Claim was made.
62 Mr Joven deposed to the value of the thickened costs changing from the value
claimed in the First Payment Claim. He said GE-Elecnor also included the cost of
light vehicles used by thickened personnel in its thickening claim in the Third
Payment Claim.
63 Mr Joven said that following the submission of the First Payment Claim and
the First Adjudication Application, some end dates for thickened resources became
known and forecast hours per month on the Stage 1A project became known.
While not all thickened resource end dates became known, because their work was
ongoing, some of the forecasts changed. Eight new staff were captured in staff
records after September 2023 resulting in an increase of approximately
$2.8 million and staff hours of 13 existing staff were adjusted resulting in a
decrease of approximately $1.9 million.
64 Mr Joven prepared a comparison of claims included in each of the First
Payment Claim and First Adjudication Determination, Second Payment Claim and
Second Adjudication Determination and the Third Payment Claim. The key parts
are set out as follows:
18 Affidavit of Jose Antonio Joven made on 30 July 2024 (FDN 26).
-- 13 of 54 --
[2024] SASC 108 Stein J
10
February 2024
Payment Claim
April 2024
Payment Claim
July 2024
Payment Claim
Prolongation Costs
EOT 001
Indirect Costs – Staff $ 3,104,312.91 Not Claimed Not Claimed
Indirect Costs – Site running costs $ 219,410.51 Not Claimed Not Claimed
Overheads (12%) $ 398,846.81 Not Claimed Not Claimed
EOT 002
Indirect Costs – Staff $ 740,105.10 Not Claimed Not Claimed
Indirect Costs – Site running costs $ 64,937.13 Not Claimed Not Claimed
Overheads (12%) $ 96,605.07 Not Claimed Not Claimed
Subtotal Prolongation $ 4,624,217.53 $ - $ -
Thickening
Additional Staff $ 9,517,947.36 Not Claimed $11,638,868.80
Additional Vehicles Not Claimed Not Claimed $ 1,414,586.30
Overheads (12%) $ 1,142,153.68 Not Claimed $ 1,533,654.61
Subtotal Thickening $10,660,101.04 $ - $14,314,109.71
Procurement Premiums
CBOP (Civils) – Foundations and Earthworks
Additional Direct Costs Not Claimed $23,336,123.96 Not Claimed
Overheads (12%) Not Claimed $ 2,800,334.87 Not Claimed
MV Trenching and Electrical Reticulation
Additional Direct Costs Not Claimed Not Claimed $ 5,729,551.57
Overheads (12%) Not Claimed Not Claimed $ 687,546.19
Subtotal Procurement Premiums $ - $26,136,458.83 $ 6,417,097.76
Total Delay Costs $15,284,318.57 $26,136,458.83 $20,731,207,47
65 I return to address the extent of overlap between claims below.
Notice of arbitration
66 On about 27 December 2023, GE-Elecnor issued a notice of arbitration and
referred a dispute to arbitration claiming a total of $61,451,756.11 in delay costs
pursuant to cl 13.11 of the contract in respect of GE-Elecnor’s EOT 001 and
EOT 002 claims. Those amounts included amounts for prolongation costs of
$7,554,516.01 and procurement premiums of $38,053,873.24 including an amount
of $7,591,882.22 for “thickening”.
67 Goyder included in its submissions a table setting out a comparison of the
amounts claimed in the notice of arbitration and the amounts claimed in the
payment claims as follows:
-- 14 of 54 --
[2024] SASC 108 Stein J
11
Notice of Arbitration SOPA #1 SOPA #2 Potential SOPA?
Item Description TOTAL First Payment
Claim
Second Payment
Claim
Third Payment
Claim
1 Prolongation Costs
1.1 Personnel 3,865,144.29 3,844,418.0119
1.1.1
Cost personnel due to late
start including costs of
personnel due to longer
duration of works (1A +
1B)
2,595,996.54
1.2 Site Running Facilities 1,093,375.18 284,347.64
2 Procurement Premiums
2.1 Foundations &
Earthworks 23,484,544.30 23,336,123.96
2.2 MV Trenching 6,977,446.72 5,729,551.57
2.3 Thickening 7,591,882.22 9,517,947.36 12,780,455.10
3 Other (Additional Costs)
3.1 Purchase of Additional
Steel 1,126,643.75
3.2 Double handling costs 73,370.50
3.3 Steel rectification costs 122,273.25
3.4 Storage costs 996,635.09
3.5 Cost of Money 252,650.54
3.6 Crane costs - 3 Cranes
Day vs 2 Crane Day/Night 6,206,356.71
3.7 Transport 55,651.90
3.8 Warranty Extension
(Defects liability period) 425,668.40
4 Overheads
4.1 12% for overheads 6,584,116.73 1,637,605.56 2,800,334.88 2,221,200.80
TOTAL 61,451,756.11 15,284,318.57 26,136,458.84 20,731,207.47
Issues for determination
68 Goyder contends the Second Adjudication Determination is fatally flawed on
the following grounds:
1. Section 22(4) of the Act.
2. By reason of the prohibition on the re-agitation of claims in adjudications
variously categorised as abuse of process, issue estoppel, res judicata, Anshun
estoppel and/or adjudication estoppel.
3. The Adjudicator lacked jurisdiction.
19 This is split up into 2 components in the February payment claim ($3,104,312.91 for EOT 001 and
$740,105.10 for EOT 002); see page 314 of DAO1.
-- 15 of 54 --
[2024] SASC 108 Stein J
12
69 Goyder challenged the validity of the Third Payment Claim insofar as it
claimed delay costs. On Goyder’s case, the Third Payment Claim should be
prohibited from proceeding to a Third Adjudication Determination.
70 Goyder contends its grounds of challenge raise a number of issues as follows:
1. whether, in making the Second Adjudication Determination, the Adjudicator
made a jurisdictional error in failing to apply s 22(4) of the Act and thereby
failing to give to the delay claim the same value as determined in the First
Adjudication Determination;
2. whether the Second Payment Claim and/or the Second Adjudication
Application was an abuse of process;
3. whether providing an adjudication certificate under s 24 of the Act in respect
of the Second Adjudication Determination or filing such a certificate under
s 25 of the Act would be an abuse of process; and
4. whether making the Third Payment Claim is an abuse of process.
Overview of Goyder’s submissions
71 Goyder contended the Adjudicator erred in the Second Adjudication
Determination on the basis he:
failed to exercise the task required of him by s 22(4) of the Act; and
wrongfully permitted GE-Elecnor to re-agitate the claim for delay costs arising out
of the alleged extension of time determined of 118 days.
72 Goyder did not challenge the finding of the Adjudicator that GE-Elecnor is
entitled to an EOT of 118 days which it will challenge in arbitration. For the
purposes of these proceedings, Goyder accepted GE-Elecnor is entitled to an EOT
of 91 days for EOT 001 for site access delay for Phase 3 permitted activities from
24 March to 23 August 2022 and 96 days, of which 69 were co-critical, for
EOT 002 for site access delay for Phase 2 permitted activities from 7 March to
7 July 2022.
73 Goyder did not challenge GE-Elecnor’s entitlement to seek recovery of
alleged delay costs pursuant to the Act while an arbitration is proceeding.
However, it contends that GE-Elecnor could and should have made the whole of
the $61.4 million claim in the First Payment Claim instead of making successive
payment claims, “picking off different line items on successive occasions and
revising and recycling failed elements”.
74 The thrust of Goyder’s case is that the Second and Third Payment Claims
each impermissibly seek to re-agitate a claim which was made in the First Payment
Claim and determined in the First Adjudication Determination. On Goyder’s case,
-- 16 of 54 --
[2024] SASC 108 Stein J
13
the First Adjudication Determination fully determined GE-Elecnor’s entitlement
to delay costs arising out of an EOT of 118 days.
75 On Goyder’s case, the construction work to which the delay costs were added
by way of increased price was the construction work which would have been
carried out within the 118 day period of delay but for that delay. It therefore
contended that in the First Adjudication Determination, the Adjudicator
determined the value of the construction work that would have been performed in
the 118 days but for the delay. As a result, the Second Adjudication Determination
required the Adjudicator to determine the value of precisely the same construction
work.
76 Goyder contended the Adjudicator was required by s 22(4) of the Act to give
that work the same value as previously determined, namely $3.1 million, but
instead he impermissibly added $21 million plus 12 percent in overheads for the
same 118 days. Goyder submitted that the same work again will be valued if the
Third Adjudication Application proceeds.
77 On Goyder’s position, s 22(4) does not concern whether a particular kind of
alleged cost has or has not been advanced previously. Rather it is concerned with
the value of construction work which has been valued in a previous adjudication.
Goyder submitted this is not a case in which the exception to s 22(4) applies. It
contended the procurement premiums were incurred in 2022 or 2023 so there was
no change in value between the First Adjudication Determination and the Second
Adjudication Determination.
78 On Goyder’s position, the Adjudicator erred in finding the construction work
and goods and services in the Second Adjudication Application were separate and
did not overlap with the construction work and goods and services in the First
Adjudication Determination. Further, Goyder criticised the Adjudicator’s finding
the exception in s 22(4) applied and GE-Elecnor was entitled to another
$21 million in delay costs for the same 118 days extension. Rather than valuing a
change in the value of construction work, Goyder submitted the Adjudicator was
revisiting his previous valuation of the same construction work to take account of
changes in the amounts claimed. On Goyder’s position, the work was already
valued, as set out in the notice of arbitration.
79 In addition to relying on s 22(4) of the Act, Goyder contended concepts of
abuse of process prevent re-agitation of the delay. Goyder contended for the
purposes of abuse of process, the focus is on whether the same claim has been
made or could have been made in a previous payment claim. Goyder’s case on
abuse of process was that the claim for delay costs from the 118 days of delay was
a single claim and it was an abuse to re-agitate it. Insofar as the procurement
premium head of claim was not previously advanced, it was an abuse of process
to seek recovery because the head of claim could and should have been advanced
in the First Payment Claim. On Goyder’s case, the entitlement to delay costs had
-- 17 of 54 --
[2024] SASC 108 Stein J
14
already been determined, the claim for delay costs was a single claim and the
separate heads of claim were merely separate line items from the same claim.
80 Goyder contended that s 22(4) is jurisdictional. On Goyder’s position, if the
work in question has previously been valued then, subject to the exception, an
adjudication does not have jurisdiction to give that work a different value.
81 Goyder contended that the Second and Third Payment Claims were not valid
payment claims and as such, the Adjudicator had no jurisdiction to make the
Second Adjudication Determination and there is no jurisdiction for an adjudicator
to make any determination on the Third Payment Claim.
82 Goyder acknowledges that the Second Payment Claim, the Third Payment
Claim and the Second Adjudication Determination are severable and it would be
appropriate for the Court to allow severability. However, Goyder contended
severability would serve no useful purpose and should not be attempted. This is
primarily because the separable part of the delay costs claim was less than the
deduction allowed by the Adjudicator for liquidated damages. Accordingly,
Goyder contended the Second Adjudication Determination should be quashed in
its entirety.
83 Goyder contended the Court has power to restrain a threatened adjudication
and the power should be exercised as a Third Adjudication process would be an
abuse of process.
Overview of GE-Elecnor’s submissions
84 GE-Elecnor contended that Goyder’s case proceeded on an erroneous basis
that delay costs and the work or goods or services to which they relate were the
same thing. GE-Elecnor submitted the various delay cost claims were different
and there had been no impermissible re-agitation of claims as between the First
and Second Adjudication Determinations and the Third Payment Claim.
85 On GE-Elecnor’s case, a particular contractor was selected as the preferred
civil BoP work sub-contractor. As a consequence of the delay, the particular
contractor was no longer available to perform the work. The civil BoP works
which would have been delivered by that sub-contractor were then delivered via a
multi sub-contractor and self-delivery hybrid model. The MV Trenching and
Electrical Reticulation works were also to be performed by one subcontractor (a
different entity to the civil works subcontractor) but, as a result of the delay, a
different procurement strategy was also employed.
86 GE-Elecnor submitted the fundamental premise of Goyder’s case was simply
wrong because its entitlement to delay costs was not determined in the First
Adjudication Determination. There were no overlapping heads of claim between
the First and Second Payment Claims. On GE-Elecnor’s case, the prolongation
and thickening claims made in the First Payment Claim and determined in the First
Adjudication Determination were different to those in the Second Payment Claim
-- 18 of 54 --
[2024] SASC 108 Stein J
15
determined in the Second Adjudication Determination. The prolongation and
thickening claims made in the First Payment Claim were for indirect costs and the
procurement premium claim made in the Second Payment Claim was for direct
costs which are fundamentally different.
87 On GE-Elecnor’s position, the fact that amounts for delay costs relate to the
same extension of time is not to the point. The claims in the Second Payment
Claim were not determined in the First Adjudication Determination as they were
entirely different claims.
88 GE-Elecnor submitted the Act excludes the jurisdiction of the courts to make
an order in the nature of certiorari to quash an adjudicator’s determination for
non-jurisdictional error of law on the face of the record. Accordingly, for Goyder
to succeed in quashing the Second Adjudication Determination it must establish
jurisdictional error. On GE-Elecnor’s position, there cannot be jurisdictional error
where the Adjudicator found there was no prior valuation to attract s 22(4) or
alternatively that the exception to s 22(4) applied.
89 GE-Elecnor’s primary submission was there was no impermissible
re-agitation of claims. At least to some extent, the Act allows claims or similar
claims to be the subject of successive payment claims and adjudication
determinations because otherwise ss 13(6) and 22(4) of the Act would have no
work to do.
90 GE-Elecnor disputed any requirement for all costs to have been claimed in
the First Payment Claim on the basis that no provisions in the contract or in the
Act provide that costs must be claimed once and for all under a certain head of
costs such as delay costs. It pointed to statutory provisions which provide to the
contrary, including s 32 of the Act.
91 In relation to indirect thickening costs, GE-Elecnor contended that the only
common head of claim between the First and Second Payment Claims and the
Third Payment Claim was the additional staff and overheads component. The
value of that claim had changed on GE-Elecnor’s case because of an additional
and separate claim for light vehicles and an increase in additional staff because of
changes to the value of the work undertaken.
92 In relation to s 22(4), GE-Elecnor submitted three questions arise:
whether there was any valuation of construction work or related goods or services
such that s 22(4) applied;
if there was, did the Adjudicator fail to apply s 22(4); and
if the answer to both questions is “yes”, was the failure by the Adjudicator a matter
of jurisdiction?
-- 19 of 54 --
[2024] SASC 108 Stein J
16
93 GE-Elecnor contended that injunctive relief would be premature unless an
adjudication application had been made and determined. It submitted that the
complaint that the Third Payment Claim was an abuse is hypothetical, the Court
should let the process run its course and treat judgment entered on a subsequent
adjudication as an abuse of process if the adjudication is invalid.
Is there a factual overlap in costs and if so, to what extent?
94 As is evident from the annexure to the affidavit of Mr Joven,20 set out in part
above, the prolongation costs claimed in the First Payment Claim were claimed
only in the First Payment Claim. The Second and Third Payment Claims do not
include any amount on account of prolongation costs. The First Payment Claim
does not include any amount on account of procurement premiums. The Second
Payment Claim includes procurement premiums for the civil BoP Foundation and
Earthworks component of works. The Third Payment Claim does not include any
such amounts. The Second Payment Claim does not include any amount on
account of procurement premiums in respect of MV Trenching and Electrical
reticulation, whereas the Third Payment Claim includes amounts described in that
way.
95 It is thus apparent that as between the First, Second and Third Payment
Claims, while procurement premiums are claimed in both the Second and Third
Payment Claims, procurement premiums in relation to BoP Foundations and
Earthworks are not replicated as between the payment claims and nor are
MV Trenching and Electrical Reticulation procurement premiums.
96 There is, however, an apparent overlap in thickening costs claimed.
97 The First Payment Claim claimed $9.5 million on account of additional staff
albeit nothing on account of additional vehicles for additional staff. The Third
Payment Claim claimed $1.14 million on account of additional vehicles and
$11.63 million on account of additional staff. In his affidavit, Mr Joven deposed
to the First Payment Claim including a claim for additional personnel costs for
Elecnor’s own personnel primarily relating to the supervision and management of
the works. The amounts claimed were based in part on actual costs and in part on
forecast costs. Actual costs were included up to September 2023 and the costs
from October 2023 to May 2024 were based on forecast figures.21 Mr Joven
described the Third Payment Claim as including amounts for additional personnel
costs for Elecnor’s own personnel primarily relating to the supervision and
management of the works. The value of the thickened costs was said to have
changed from the value claimed in the First Payment Claim. This was because
some of the end dates for thickened resources became known and forecast hours
became known. Further, some of the forecasts changed due to new staff and
20 Affidavit of Jose Antonio Joven made on 30 July 2024 (FDN 26), 11.
21 Exhibit JJ-1 to the affidavit of Jose Antonio Joven made on 30 July 2024 (FDN 26), 1010.
-- 20 of 54 --
[2024] SASC 108 Stein J
17
adjustment to the hours of existing staff. The claim for thickened personnel costs
in the Third Payment Claim was based on actual costs to the end of May 2024.
98 Accordingly, factually there was no overlap between the First, Second and
Third Payment Claims for prolongation and procurement premiums. However,
there was some overlap as between the First and Third Payment Claims in relation
to thickening.
99 I address the consequences of the lack of overlap and the extent of overlap
below.
Summary of the Act
100 The parties’ submissions primarily focussed on s 22(4) of the Act to which I
will turn below. It is necessary to consider the provisions of the Act as a whole in
order to understand the parties’ submissions and the authorities which address that
Act.22
101 The Act has as its object ensuring that a person who undertakes to carry out
construction work under a construction contract is entitled to receive and recover
progress payments.23 The Act does not limit any other entitlement a claimant may
have under a construction contract or otherwise for recovering any other
entitlement.
102 The Act defines “progress payment” as a payment to which a person is
entitled under s 8. “Claimed amount” means the amount of a progress payment
claimed to be due for construction work carried out or for related goods and
services supplied, as referred to in s 13.
103 “Reference date” is defined to mean a date determined by, or in accordance
with, the terms of the contract as the date on which a claim for a progress payment
may be made in relation to work carried out or undertaken to be carried out or
related goods and services supplied or undertaken to be supplied under the
contract. In the case in which the contract makes no express provision with respect
to the matter, reference date is defined to be the last day of the named month in
which the construction work was first carried out or the related goods and services
first supplied and the last day of each subsequent named month.
104 Construction work is defined in s 5 of the Act. The definition includes a
range of kinds of work, such as construction, alteration, repair, restoration,
maintenance and so on and includes any operation that forms an integral part of,
or is preparatory to, such work. I discuss further below the concept of delay costs
and its relationship to construction work.
22 There is similar legislation in other States which is addressed in authorities to which I refer below. The
Act is substantially based upon the New South Wales equivalent legislation.
23 The Act, s 3.
-- 21 of 54 --
[2024] SASC 108 Stein J
18
105 The Act provides for rights to progress payments. On and from each
reference date under a construction contract, a person who has undertaken to carry
out construction work under a contract or to supply related goods and services is
entitled to a progress payment.24 The amount of a progress payment to which a
person is entitled is to be the amount calculated in accordance with the terms of
the contract. If the contract does not provide for such calculation, then the amount
is calculated on the basis of the value of the construction work carried out or
undertaken to be carried out or of related goods and services supplied or
undertaken to be supplied under the contract.25
106 Construction work is to be valued in accordance with the terms of the
contract. If the contract does not make express provision for valuation, the Act
sets out the relevant factors to be taken into account.26 Similarly, related goods and
services are to be valued in accordance with the terms of the contract or, in the
absence of an express provision, by reference to considerations set out in the Act.27
107 The Act provides for the due date upon which a progress payment becomes
due and payable and for interest paid on unpaid amounts.
108 A person who is entitled to a progress payment may serve a payment claim
on a person who is or may be liable to make the payment. The payment claim
must identify the construction work or related goods and services to which the
progress payment relates and indicate the amount of the progress payment claimed
to be due.28
109 A payment claim may be served only within the period (whichever is the
later) of the period allowed for by the terms of the contract or within six months
after the construction work to which the claim relates were last carried out or the
related goods and services were last supplied.29
110 Sub-sections 13(5) and (6) provide as follows:
(5) A claimant cannot serve more than 1 payment claim in respect of each reference date
under the construction contract.
(6) However, subsection (5) does not prevent the claimant from including in a payment
claim an amount that has been the subject of a previous claim.
111 A respondent to a payment claim may reply to the claim by providing a
payment schedule. Among other things, a payment schedule must indicate the
amount of the payment, if any, the respondent proposes to make.30 Where the
24 The Act, s 8.
25 The Act, s 9.
26 The Act, s 10.
27 The Act, s 10(2).
28 The Act, s 13(2).
29 The Act, s 13(4).
30 The Act, s 14.
-- 22 of 54 --
[2024] SASC 108 Stein J
19
amount is less than that claimed, reasons must be provided.31 If the respondent
provides a payment schedule in an amount less than the claimed amount, the
claimant may apply for adjudication of a payment claim.32
112 It is the duty of an authorised nominating authority to which an adjudication
application is made to refer the application to an adjudicator as soon as
practicable.33 The respondent may lodge a response to the adjudication application.
The respondent cannot include in the adjudication response reasons for
withholding payment unless those reasons have already been included in the
payment schedule provided to the claimant.34
113 Section 22 of the Act sets out the matters the adjudicator is to determine and
the matters the adjudicator is to consider in determining an adjudication
application. The adjudicator determines the amount of the progress payment (if
any) to be paid, the date on which such amount became payable and the rate of
interest payable.35 The adjudicator is to consider only the provisions of the Act,
the provisions of the contract, the payment claim together with submissions and
documents duly made by the claimant in support of the claim, the payment
schedule, if any, together with the submissions and documents duly made by the
respondent in support of the schedule and the results of any inspection carried out
by the adjudicator.36 The adjudicator is required to provide written reasons.37
114 Section 22(4) of the Act provides as follows:
If, in determining an adjudication application, an adjudicator has, in accordance with
section 10, determined—
(a) the value of construction work carried out under a construction contract; or
(b) the value of related goods and services supplied under a construction contract,
the adjudicator (or any other adjudicator) is, in any subsequent adjudication application that
involves the determination of the value of that work or those goods and services, to give
the work (or the goods and services) the same value as that previously determined unless
the claimant or respondent satisfies the adjudicator concerned that the value of the work
(or the goods and services) has changed since the previous determination.
115 Accidental slips or omissions, clerical mistakes, material miscalculation of
figures and other mistakes can be corrected.38
31 The Act, s 14(3).
32 The Act, s 17.
33 The Act, s 17(6).
34 The Act, s 20(4).
35 The Act, s 22(1).
36 The Act, s 22(2).
37 The Act, s 22(3).
38 The Act, s 22(5).
-- 23 of 54 --
[2024] SASC 108 Stein J
20
116 If an adjudicator determines an amount is payable, the respondent is obliged
to pay that amount within a timeframe specified by the Act.39 In the event of failure
to pay part or the whole of the adjudicated amount, the claimant may request the
issue of an adjudication certificate which can be filed as a judgment for a debt in a
court of competent jurisdiction and enforced accordingly.40
117 In any proceedings to have the judgment set aside, the respondent is not
entitled to bring a cross claim or raise a defence concerning matters arising under
the construction contract or challenge the adjudicator’s determination and is
required to pay into court as security the unpaid portion of the adjudicated amount
pending final determination.41
118 The Act provides for a new adjudication application to be made in certain
circumstances, which relate to an adjudicator failing to accept an adjudication
application within the specified timeframe or failing to determine the application
within a specified timeframe or notifying the parties the adjudicator has
withdrawn.42
119 Section 32 provides that, subject to s 33, nothing in Part 3 (procedure for
recovering progress payments) affects any rights a party may have under a
construction contract or under Part 2 (progress payments) or may have apart from
the Act in relation to anything done or omitted to be done under the construction
contract. It further provides that nothing done under or for the purposes of Part 3
affects any civil proceedings arising under a construction contract other than as
provided for by s 32(3). That subsection requires a court or tribunal to allow for
an amount paid to a party for the purposes of Part 3 in any order or award made.
A court or tribunal may make orders it considers appropriate including for
restitution for amounts paid. Section 33 prevents parties from contracting out of
the Act.
120 The mischief addressed by sub-ss 13(5), 13(4) and 22(4) was expressed in
the second reading speech for the Building and Construction Industry Security of
Payment Amendment Bill 2002 (NSW).43 The second reading speech referred to
the provisions as restricting claimants to one claim in respect of each reference
date and limiting how long after construction work is completed a claimant can
continue to make payment claims. The second reading speech characterised the
amendments as designed to prevent abuses of the intention of the legislation by
claimants. It referred to adjudicator shopping, being the practice of a dissatisfied
claimant making repeated adjudication applications until the claimant gets the
adjudication decision the claimant wants. The remedy referred to in the second
reading speech was said to be provided in s 22(4), that is, if one adjudicator has
decided that work or goods and services have a certain value, a subsequent
39 The Act, s 23.
40 The Act, ss 24, 25.
41 The Act, s 25(4).
42 The Act, s 26.
43 These provisions were included in the Act in substantially identical terms.
-- 24 of 54 --
[2024] SASC 108 Stein J
21
adjudicator will have to give the work, goods or services the same value. An
exception is where the adjudicator is satisfied the value of the work, goods or
services has changed since the previous adjudication.
Characterisation of delay claims
121 An important plank in Goyder’s argument was the contention that delay costs
arising from the EOTs granted to GE-Elecnor constitute a singular claim for delay
costs. Goyder contended the work to which the delay costs added by way of
increased price was the construction work which would have been carried out
within the 118 day period of delay but for that delay.
122 Goyder characterised the work which would have been carried out in the
delay period as early bulk earthworks of the kind required to construct access
roads, construct hard stands at each location on which a wind turbine is to be
erected and to create trenching for medium voltage cables which will run between
the turbines. Counsel for Goyder submitted that attention must be focused on the
work which would have been done rather than the line-by-line cost items or heads
of claim said to arise. Counsel drew an analogy with a plaintiff injured in a road
accident being restricted to one claim for different heads of damage.
123 GE-Elecnor disputed that delay costs constitute a single one-off claim.
Counsel characterised the analogy with the personal injury claim as an anathema
to the Act.
124 GE-Elecnor contended that within the scope of work, GE-Elecnor was
obliged to perform a significant number of individual items of construction work
and related goods and services within the meaning of the Act. In relation to direct
procurement premiums, the head of claim was divided into civil BoP premiums
and MV Trenching and Electrical premiums. Civil BoP premiums were claimed
in the Second Payment Claim and the MV Trenching and Electrical premiums in
the Third Payment Claim. Accordingly, GE-Elecnor says thickening costs
changed and procurement premiums related to an entirely different scope of work.
125 GE-Elecnor pointed to the fact that the First Adjudication Application sought
partial payment of total delay costs, thus making clear it was not a claim for all
delay costs.
126 Counsel for GE-Elecnor did not accept that the relevant construction work in
the context of delay costs is the actual works which would have been performed in
the period of the EOT. Counsel contended that delay costs are standalone under
cl 20 of the contract and under the Act and there is no requirement to attach delay
costs to the actual works which would have been performed.
Contractual provisions in relation to works
127 Consideration of the proper characterisation of delay claims and resolution
of whether delay costs constitute a singular claim commences with the provisions
of the contract.
-- 25 of 54 --
[2024] SASC 108 Stein J
22
128 As set out above, the contract provides for a range of different components
of work to be performed, including civil BoP earthworks claims and MV trenching
works. Within each, a myriad of different items of works are required to be
performed.
129 On GE-Elecnor’s case, there are a significant number of individual items of
construction work and related goods and services referred to within the
specifications.
130 In accordance with the program for the Stage 1A contract, the civil works for
the transport route and road and intersection upgrades were due to commence on
19 March 2022 and bulk earthworks were due to commence on 29 April 2022.44
Schedule 8 of the Stage 1A contract identifies nominated sub-contractors for the
civil works.
131 The works which would have been performed in the 118 days period
encompassed, at a high level, both civil BoP and MV Trenching and Electrical
Reticulation works which were different packages of work.
132 EOT 001 related to site access delay for Phase 3 permitted activities and
EOT 002 for site access delay for Phase 2 permitted activities for a different but
overlapping period. The permitted activities were broadly described but of
differing natures.
133 I agree with Goyder that the two overlapping EOT claims arose from a
common underpinning cause, that is, a delay in access to the site by reason of
delays in obtaining necessary environmental approvals. Those delays gave rise to
two overlapping EOT periods. However, I do not consider that it necessarily
follows that delay costs arising from the delay constitute a singular claim for delay
costs. I also do not consider that it necessarily follows that delay costs are to be
characterised as referable to, or to be treated as, costs of the construction works
which would have been undertaken in the 118 day EOT period.
134 Goyder criticised GE-Elecnor for referring to components or types of cost as
separate claims. However, the contract envisages claims for amounts in the form
of claims for costs which have directly and necessarily arisen as a result of the
EOT.
135 Under the contract, a delay cost event gives rise to an obligation to pay
GE-Elecnor “extra costs”. If GE-Elecnor considers other amounts are payable to
it (which includes amounts for delay costs) it is entitled to make a claim for
payment under cl 20 of the contract. Any payment made is only on account. The
valuation of delay costs is calculated by reference to components of cost.
136 There are no express provisions in the contract which define or characterise
delay claims in a manner which expressly or by necessary implication gives rise
44 Schedule 21 of the Stage 1A contract.
-- 26 of 54 --
[2024] SASC 108 Stein J
23
to the conclusion that delay costs arising from an extension of time event
necessarily constitute a singular claim. Nor are there any express provisions which
require a claim for delay costs on account of a delay event to be submitted in one
and one only payment claim.
137 The contract expressly provides for amendments of claims for EOTs. In a
case in which an amendment to extend a previously accepted EOT is accepted, the
contract must contemplate the possibility of more than one delay cost claim
referable to the same underlying cause. In the case of an accepted EOT and
accepted delay cost claim made in a progress payment claim, the contract does not
preclude a further claim for delay costs arising in later periods of time which can
be established to meet the contractual requirements in cl 13.11. Put differently,
there are no provisions in the contract which require GE-Elecnor to wait until all
potential costs which may fall within cl 13.11 from an EOT have been incurred
before making a claim for amounts in a progress payment which it asserts fall
within the entitlement in cl 13 of the contract.
138 Further, the contract does not expressly require GE-Elecnor to substantiate
the entitlement to delay costs by reference only to the specific works which would
have been carried out during the period for which the extension of time is granted.
Clause 3 of schedule 5 requires GE-Elecnor to provide the claim for delay costs
with all supporting calculations and data and other information reasonably
requested for the purposes of making the determination of valuation. Goyder’s
obligation is to pay “such extra costs as are necessarily and directly incurred in
connection with the extension” by reason of the delay cost event. The amounts
claimed are costs. The required connection is with the extension. It is conceivable
that costs properly falling within the description in cl 13.11 may arise in different
ways by reference to the construction works. Such costs could be referable to work
adversely impacted by delay which was to be, and was, carried out within the
extension period; to work which was not to be carried out within the extension
period but was so carried out as a result of scheduling changes resulting from
delay; to work which would have been, but was not carried out at all, in the
extension period as a result of delay or to costs properly characterised as falling
within the contractual provisions even if not directly associated with the work
which would have taken place within that extension period.
139 In my view, properly construed, the contract does not expressly or by
necessary implication limit GE-Elecnor to claiming delay costs in one payment
claim. It enables GE-Elecnor to claim for “amounts” which could include a claim
to entitlement to a component of delay costs. The provisions in the contract in
relation to delay claims do not require the characterisation of the delay cost claims
for prolongation, thickening and procurement premiums as a singular claim.
140 For the reasons I address separately below, I also consider the provisions of
the Act do not require the characterisation of the delay claims as a singular claim
or compel all delay costs claimed from an extension of time to be claimed in only
one progress payment or adjudication application.
-- 27 of 54 --
[2024] SASC 108 Stein J
24
Nature of the delay claims and connection with construction work under the Act
141 Entitlement to a progress claim under s 8 of the Act is not limited to
construction work actually performed or the actual supply of related goods and
services. Persons who have undertaken to carry out construction work or supply
related goods and services are given the entitlement to a progress payment. Section
8 must be read together with the definition of progress payment, which refers to a
payment “for construction work” and s 13 which refers to a payment claim
identifying the “construction work … to which the progress payment relates”.
142 I turn now to consider some relevant interstate authorities. Those authorities
must be considered in the context of the legislation in force from time to time in
those jurisdictions. The provisions of the Building and Construction Industry
Security of Payment Act 1999 (NSW) (“the NSW Act”) are relevantly similar to
those of the Act.
143 In Coordinated Construction Co Pty Ltd v Climatech (Canberra) Pty Ltd
(“Climatech”),45 the New South Wales Court of Appeal considered whether a
claim for “delay damages” as provided for in a construction contract was not a
claim for construction work. Justice Hodgson repeated views expressed by him in
Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd
(“Hargreaves”)46 as follows.
144 His Honour said the definition of “progress payment” in s 8 does not limit
the payment to payment for construction work and/or related goods and services
nor does the amount of the progress payment, as dealt with in s 9, impose such a
limit. While s 13 requires a payment claim to indicate the claimed amount which
is defined as an amount claimed to be due “for” construction work or related goods
and services supplied, it is the payment claim which is adjudicated pursuant to
s 17. While giving some support to the argument that an adjudicator can only
include in a progress payment amounts claimed to be due for construction work
carried out and/or for related goods and services supplied, Hodgson JA said the
terms of s 13 spoke against that construction. His Honour considered it by no
means clear that “carried out” and “supplied” should be given a strict temporal
connotation.47 Section 9(a) strongly suggested that in the case of a construction
contract providing for progress payments to include certain amounts, such amounts
are to be included in progress payments required by the legislation whether or not
they are for construction work or related goods and services. That, in turn, suggests
any requirement from s 13 and the definition of “claimed amount” that the progress
45 [2005] NSWCA 229.
46 [2005] NSWCA 228; (2005) 63 NSWLR 385.
47 Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd [2005] NSWCA 228; (2005) 63
NSWLR 385 at [39] see also, Coordinated Construction Co Pty Ltd v Climatech (Canberra) Pty Ltd
[2005] NSWCA 229 at [22].
-- 28 of 54 --
[2024] SASC 108 Stein J
25
payment be “for” construction work carried out or related goods and services
supplied should not be given a narrow construction.48
145 The fact a particular amount may be characterised by a contract as damages
or interest could not be conclusive as to whether or not it was for construction work
carried out or related goods and services supplied. In his Honour’s view, any
amount that a construction contract “requires to be paid as part of the total price of
construction work is generally…an amount due for that construction work”.49 His
Honour characterised delay damages payable for an extension of time for a
compensable cause as additional amounts which may become due and payable
under the contract, which are then to be included in progress payments and thus
prima facie within s 9(a).
146 Justice Hodgson then said:50
If in substance they represent the increased cost or price of construction work actually
carried out, in my opinion they are clearly for construction work carried out. If they
represent the cost or price of goods or services actually supplied in connection with the
construction work under the contract, they are for related goods or services supplied, even
if not for construction work carried out.
If they represent off-site costs (such as office overheads) or other on-site costs, it may be a
question of fact and degree whether they are for construction work carried out or for related
goods and services supplied. They would in my opinion properly be regarded at least as
part of the price for the totality of the construction work when completed. And it would
seem artificial to say that they are excluded from the Security of Payment Act if they are
not referable to work that has already been carried out, particularly when s 9(b) refers to
the value of construction work undertaken to be carried out and related goods and services
undertaken to be supplied. However, it is not necessary in this case altogether to exclude
the possibility that some delay damages claimed under this contract might possibly not be
for construction work carried out or related goods and services supplied within the
definition of “claimed amount” in s 4; but it is certainly not obvious that this is so in relation
to any of the claims in this case.
147 His Honour considered the relevant construction work or related goods and
services must be identified sufficiently to enable the respondent to understand the
basis of the claim. In the case of delay, it is generally sufficient that the basis of
contractual entitlement be shown which would generally be enough to ground
identification by inference of the construction work or related goods and services
to which the payment relates.51 It was therefore not to the point that the payment
48 Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd [2005] NSWCA 228; (2005) 63
NSWLR 385 at [40] see also, Coordinated Construction Co Pty Ltd v Climatech (Canberra) Pty Ltd
[2005] NSWCA 229 at [22].
49 Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd [2005] NSWCA 228; (2005) 63
NSWLR 385 at [41] see also, Coordinated Construction Co Pty Ltd v Climatech (Canberra) Pty Ltd
[2005] NSWCA 229 at [22].
50 Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd [2005] NSWCA 228; (2005) 63
NSWLR 385 at [43]-[44].
51 Coordinated Construction Co Pty Ltd v Climatech (Canberra) Pty Ltd [2005] NSWCA 229 at [26].
-- 29 of 54 --
[2024] SASC 108 Stein J
26
claim indicated the contractual basis was for delay damages rather than the supply
of goods and services.
148 Justice Ipp agreed with Hodgson JA for the reasons set out in paragraphs [38]
to [45] of his reasons in Hargreaves that delay damages can amount to payments
for construction work, that being sufficient to dispose of the appeal.52
149 In EnerMech Pty Ltd v Acciona Infrastructure Projects Aust Pty Ltd
(“EnerMech”),53 the New South Wales Court of Appeal considered whether or not
a payment claim was invalid because it was not a claim for payment on account of
construction work or related goods and services but in substance a claim for credit
for amounts obtained as a result of recourse to security and for other amounts not
on account of construction work or for related goods and services.
150 Justice Basten, with whom Meagher JA and Griffiths AJA agreed, considered
that the NSW Act does not prescribe as an essential condition of the validity of a
payment claim that it be “for construction work”. While it is necessary for a
payment claim to assert an entitlement to payment for work performed pursuant to
a construction contract, the fulfilment of that entitlement is a matter for
determination by the adjudicator subject to limited rights of review for
jurisdictional error.54 I address EnerMech further below in the context of the
discussion as to whether s 22(4) is jurisdictional.
151 The analysis in Hargreaves,55 Climatech56 and Enermech57 does not support a
conclusion that the Act requires a claimant or an adjudicator to identify the precise
construction work to which a delay claim relates. It is necessary to show the basis
of contractual entitlement, which generally will be sufficient to identify the
construction work or related goods and services to which the payment relates.
Delay costs may be properly characterised as part of the total price for the
construction work when completed.
152 It follows that I do not accept Goyder’s submission that the determination in
the First Adjudication Determination was a determination of the value of the
construction work that would have been performed within the EOT period. I also
do not accept the criticism that in the Second Adjudication Determination the
Adjudicator failed to identify the construction works to which the progress claim
related.
52 Coordinated Construction Co Pty Ltd v Climatech (Canberra) Pty Ltd [2005] NSWCA 229 at [34]-[36],
citing Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd [2005] NSWCA 228;
(2005) 63 NSWLR 385 at [38]-[45] (Hodgson JA).
53 [2024] NSWCA 162.
54 EnerMech Pty Ltd v Acciona Infrastructure Projects Aust Pty Ltd [2024] NSWCA 162 at [8].
55 [2005] NSWCA 228; (2005) 63 NSWLR 385.
56 [2005] NSWCA 229.
57 [2024] NSWCA 162.
-- 30 of 54 --
[2024] SASC 108 Stein J
27
153 I turn now to consider Goyder’s submission concerning the application of
s 22(4) to the claims.
Is Does s 22(4) and/or its exception apply and is s22(4) jurisdictional?
Application of s 22(4)
154 Goyder contended that this is not a case in which the exception to s 22(4)
applies. Goyder submitted that GE-Elecnor’s approach seeks in effect to amend
the wording of s 22(4) to change a reference to the value of construction work to
entitlement to a particular head of claim. It further contended that the $23 million
claim for procurement premiums was ascertained in December 2023 as evidenced
in the notice of arbitration; the premiums were incurred in 2022 or 2023 and there
was no change in value between the adjudications.
155 On Goyder’s position, s 22(4) is not concerned with whether a particular
dollar value has previously been determined but whether the value of a particular
part of the construction work has been previously determined. Goyder contended
it is not a matter of changing the way the claimant frames the claim or changing
the dollar figure attached to the claim, but rather whether there is a change in value
as a matter of objective fact.
156 GE-Elecnor’s point was s 22(4) did not apply to the Second Adjudication
Determination because the relevant work or goods or services the subject of the
Second Adjudication Determination were not valued in the First Adjudication
Determination.
157 GE-Elecnor contended that if s 22(4) applies, the Adjudicator expressly
applied the exception to that provision. Even if the Adjudicator’s findings on this
basis could be said to be wrong, which GE-Elecnor did not accept, it contended
there can be no challenge to a finding on this basis. GE-Elecnor submitted it is
irrelevant that a claim under the same head was advanced in the earlier notice of
arbitration. Further, GE-Elecnor’s position is that a failure to apply s 22(4) is not
a matter of jurisdiction and not reviewable.
158 In John Goss Projects Pty Ltd v Leighton Contractors Pty Ltd (“John
Goss”),58 McDougall J pointed out the distinction between the calculation of the
amount of a progress payment and the valuation of construction work. The issue
pursuant to s 22(4) in this matter is whether in the First Adjudication
Determination the Adjudicator in accordance with s 10 of the NSW Act valued
construction work the value of which was to be determined in the Second
Adjudication Determination and the value of which will be required to be
determined in the Third Adjudication Determination, if it proceeds.
159 In a case where the value of construction work or the value of related goods
and services supplied has been determined in a previous adjudication, s 22(4)
requires a subsequent adjudicator to give “that” work or “those” goods and services
58 [2006] NSWSC 798; (2006) 66 NSWLR 707 at [40].
-- 31 of 54 --
[2024] SASC 108 Stein J
28
the same value as previously determined. This is subject to an exception where
the subsequent adjudicator is satisfied that the value of the work or goods or
services has changed since the previous determination.
160 In order to succeed in its contention that s 22(4) applied, Goyder had to
establish that the determination of the value of the work in the Second Adjudication
Determination was for “that” work previously valued in the First Adjudication
Determination. Similarly, it must establish that the Third Adjudication
Application seeks the determination of the value of “that” work valued in the First
Adjudication Determination. The contention depends upon success in the
arguments that the costs claimed were only heads of claim within one singular
claim for the same construction work which would have been carried out in the
118 day extension period.
161 In my view, that argument fails for the reasons I have articulated above.
Properly characterised, the delay costs included in the three payment claims do not
constitute a single claim for the same construction work which would have been
carried out in the EOT period. Accordingly, as there was no overlap between the
prolongation and procurement premium claims as between the First and Second
Claims and First and Second Adjudication Determinations and the Third Payment
Claim, s 22(4) did not apply to the prolongation and procurement premium claims.
The Adjudicator in the Second Adjudication Determination did not value “that”
work or “those” goods or services which he valued in the First Adjudication
Determination. The Adjudicator in the Second Adjudication Determination
therefore was not bound in the Second Adjudication Determination to apply the
same value to the delay costs addressed in the First Adjudication Determination.
162 The thickening costs claims raise different issues to which I return below.
Jurisdiction
163 Determinations made by adjudicators pursuant to the provisions of the Act
are amenable to orders in the nature of certiorari for jurisdictional error.59
However, the court does not have jurisdiction to make orders in the nature of
certiorari to quash an adjudicator’s determination for errors on the face of the
record.60
164 In case I have erred in my conclusion that s 22(4) does not apply, I proceed
to address the arguments in relation to whether s 22(4) is a matter of jurisdiction.
165 Goyder contended s 22(4) is jurisdictional based on the reasoning of Allsop P
in Dualcorp Pty Ltd v Remo Constructions Pty Ltd (“Dualcorp”),61 and
59 Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd [2010] NSWCA 190; (2010) 78 NSWLR 393,
overturning Brodyn Pty Ltd v Davenport [2004] NSWCA 394; (2004) 61 NSWLR 421 in this respect.
60 Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4; (2018) 264 CLR 1.
61 [2009] NSWCA 69; (2009) 74 NSWLR 190.
-- 32 of 54 --
[2024] SASC 108 Stein J
29
Kourakis CJ in Civil & Allied Technical Construction Pty Ltd v Resolution
Institute (“CATCON”).62
166 On GE-Elecnor’s case, s 22(4) is not jurisdictional. GE-Elecnor relied in part
on the decision of Rothnere Pty Ltd v Quasar Constructions NSW Pty Ltd
(“Rothnere”).63 However, Goyder submitted that Rothnere64 does not assist
GE-Elecnor as it is a first instance decision pre-dating Dualcorp,65 and the concept
of basic and essential requirements set out in Brodyn Pty Ltd v Davenport
(“Brodyn”)66 is of no continuing legal significance following the decision in Chase
Oyster Bar Pty Ltd v Hamo Industries Pty Ltd (“Chase”).67 GE-Elecnor disputed
the contention that Brodyn is of no continuing significance and submitted Brodyn68
remains good law as to what may give rise to jurisdictional error.
167 Given the urgency of the matter, time does not permit a detailed consideration
of the authorities on jurisdiction in the context of the Act. In my view the cases
discussed below provide sufficient basis for concluding that s 22(4) is not a matter
of jurisdiction.
168 In Chase Oyster Bar,69 the New South Wales Court of Appeal considered a
number of questions. One question was whether the decision in Brodyn70 was
incorrectly decided in the light of Kirk v Industrial Relations Commission71 insofar
as it held that the Supreme Court was not required to consider and determine the
existence of jurisdictional error by an adjudicator, an order in the nature of
certiorari was not available to quash a decision of an adjudicator, and the NSW
Act limited the Supreme Court’s power to quash a determination for jurisdictional
error by an adjudicator in reaching a determination.
169 In Chase Oyster Bar,72 an adjudicator erroneously concluded that a party had
given notice of its intention to make an adjudication application within the time
provided for by s 17(2)(b) of the NSW Act (which set a time limit within which
notice of an application to apply for adjudication had to be given).
170 The New South Wales Court of Appeal in concluded that determinations
made under the legislation by adjudicators are amenable to judicial review and to
orders in the nature of certiorari for jurisdictional error. To the extent Brodyn73
determined the matters referred to in the question posed, the decision was in error.
62 [2019] SASC 193.
63 [2004] NSWSC 1151.
64 [2004] NSWSC 1151.
65 [2009] NSWCA 69; (2009) 74 NSWLR 190.
66 [2004] NSWCA 394; (2004) 61 NSWLR 421.
67 [2010] NSWCA 190; (2010) 78 NSWLR 393.
68 [2004] NSWCA 394; (2004) 61 NSWLR 421
69 [2010] NSWCA 190; (2010) 78 NSWLR 393.
70 [2004] NSWCA 394; (2004) 61 NSWLR 421.
71 [2010] HCA 1; (2010) 239 CLR 531.
72 [2010] NSWCA 190; (2010) 78 NSWLR 393.
73 [2004] NSWCA 394; (2004) 61 NSWLR 421.
-- 33 of 54 --
[2024] SASC 108 Stein J
30
The failure in Chase Oyster Bar to comply with s 17(2)(b) rendered the
adjudicator’s determination invalid as there was no valid adjudication application.
171 In Rothnere,74 McDougall J considered whether on the facts s 22(4) was
engaged and, if so, whether compliance with s 22(4) was a fundamental provision
of the legislation such that non-compliance would have the effect there was in law
no determination.
172 Justice McDougall observed that an adjudication determination may involve
questions of quantification and of entitlement or one or the other. An adjudication
determination need not necessarily include the value of the construction work.
Section 22(4) therefore only applies where a component of the determination of
the amount of the progress payment includes determination of the value of
construction work.75
173 In relation to the question whether non compliance would mean there was no
valid determination, McDougall J referred to the judgment of Hodgson JA (with
whom Mason P and Giles JA agreed) in Brodyn76 which articulated “basic and
essential requirements” the failure to comply with which would render an
adjudication determination not a valid determination. While accepting that the list
of basic and essential requirements in Brodyn may not be exhaustive, McDougall J
did not accept that s 22(4) should be added to that list.
174 Justice McDougall considered that s 22(4) regulates in one respect the way
an adjudicator is to exercise the adjudication function and the reasons given in
Brodyn77 for holding that the requirements of s 22(2) were not basic and essential
applied with equal force to s 22(4).78 Justice McDougall observed that Hodgson
JA referred to the majority decision in Project Blue Sky Inc v Australian
Broadcasting Authority (“Project Blue Sky”).79 After considering Project Blue
Sky, McDougall J stated the approach of the majority in that case and that of
Hodgson JA in Brodyn80 dictated that s 22(4) was not to be regarded as a provision
the non-compliance with which would have the effect of undoing a purported
exercise of power by an adjudicator.81
175 In John Goss, McDougall J reiterated his conclusion in Rothnere82 that
s 22(4) was not a basic and essential requirement of validity and, if the
74 [2004] NSWSC 1151.
75 Rothnere Pty Ltd v Quasar Constructions NSW Pty Ltd [2004] NSWSC 1151 at [44].
76 Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421 at [53].
77 Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421 at [56].
78 Rothnere Pty Ltd v Quasar Constructions NSW Pty Ltd [2004] NSWSC 1151 at [18], [25].
79 [1998] HCA 28; (1998) 194 CLR 355.
80 [2004] NSWCA 394; (2004) 61 NSWLR 421.
81 Rothnere Pty Ltd v Quasar Constructions NSW Pty Ltd [2004] NSWSC 1151 at [24].
82 [2004] NSWSC 1151.
-- 34 of 54 --
[2024] SASC 108 Stein J
31
adjudicator’s reasoning displayed mistake, it would be a mistake within the ambit
of the jurisdiction entrusted to the adjudicator by the legislation.83
176 In Dualcorp,84 Macfarlan JA referred to McDougall J’s consideration of
s 22(4) in Rothnere85 and John Goss.86 After quoting from particular passages,
Macfarlan JA agreed with the approach taken by McDougall J to the construction
of s 22(4) while stating that s 22(4) should not be regarded as an exhaustive
statement of the matters determined by an earlier adjudication which will bind a
subsequent adjudicator. In his Honour’s view, when read as a whole, the
legislation manifests an intention to preclude re-agitation of the same issues.87 I
return to address re-agitation below.
177 Goyder’s counsel correctly pointed out that the passages of Rothnere88 and
John Goss89 quoted by Macfarlan JA did not include the passage in which
McDougall J expressed his view that s 22(4) is not a matter of jurisdiction.
However, equally, Macfarlan JA did not qualify his agreement to the approach
taken by McDougall J.
178 In Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd
(“Probuild”),90 the High Court considered whether the scheme established by the
legislation ousted the jurisdiction of the Supreme Court of New South Wales to
make an order in the nature of certiorari to quash a determination by an adjudicator
for error of law on the face of the record that is not a jurisdictional error. The Court
concluded that the legislation does oust that jurisdiction.
179 Chief Justice Kiefel and Justices Bell, Keane, Nettle and Gordon considered
it would not be consistent with the terms, structure or purposes of the statutory
scheme to read the legislation as not interfering with the bases upon which a
determination may be judicially reviewed and quashed. It would frustrate the
operation and evident purposes of the scheme to allow potentially costly and time
consuming judicial review proceedings to be brought on the basis of error of law
on the face of the record regardless of whether an adjudicator exceeded the limits
of their statutory functions and powers. Thus, the jurisdiction to make an order in
the nature of certiorari to quash a determination for error of law on the face of the
record is excluded.91
83 John Goss Projects Pty Ltd v Leighton Contractors Pty Ltd [2006] NSWSC 798; (2006) 66 NSWLR
707 at [22]-[23] (McDougall J).
84 [2009] NSWCA 69; (2009) 74 NSWLR 190.
85 [2004] NSWSC 1151.
86 [2006] NSWSC 798; (2006) 66 NSWLR 707.
87 Dualcorp Pty Ltd v Remo Constructions Pty Ltd [2009] NSWCA 69; (2009) 74 NSWLR 190 at
[66]-[67].
88 [2004] NSWSC 1151.
89 [2006] NSWSC 798; (2006) 66 NSWLR 707.
90 [2018] HCA 4; (2018) 264 CLR 1.
91 Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4; (2018) 264 CLR 1at
[48].
-- 35 of 54 --
[2024] SASC 108 Stein J
32
180 Their Honours stated that the consequences of non-jurisdictional error are
dealt with by the provisions of the legislation which enable a party to bring civil
proceedings. The limited exclusion of review does not irrevocably entrench the
consequences of an erroneous determination.92 This understanding of the scheme
was said to accord with that of the decision in Brodyn and the New South Wales
Court of Appeal was right to follow Brodyn in this respect.93
181 Justice Gageler (as he then was) referred to the authority granted to an
adjudicator in s 22(1) of the legislation to determine the amount and timing of a
progress payment. That statutory entitlement exists by operation of s 8 separately
and in parallel to such other rights as the parties to the construction contract may
have under that contract.94 His Honour observed that the principal statutory object
to ensure a person undertaking to carry out construction work is entitled to receive
and able to recover progress payments would be thwarted if mere error of law made
by the adjudicator in the interpretation of the contract rendered it liable to be
quashed.95 The statutory scheme would be internally contradictory and the
authority granted to the adjudicator to go wrong in law would be illusory if a
determination made validly in the exercise of authority conferred by s 22(1) was
susceptible to an order in the nature of certiorari where the adjudicator made an
error of law in the reasons.96 His Honour considered that s 22(1) is properly
interpreted as conferring authority on the adjudicator to make a determination
notwithstanding it may be based on a legally erroneous interpretation of the
contract. The affirmative conferral of the decision making authority to err in law
displaces the general supervisory jurisdiction of the Court to make an order in the
nature of certiorari for error of law on the face of the record.97
182 Probuild98 was decided after Chase Oyster Bar.99 While not expressly
addressing Hodson JA’s reference to “basic and essential” requirements of the Act,
in Probuild100 the High Court endorsed the understanding of the scheme of the
legislation referred to in Brodyn.101 It is clear from the reasons in Chase Oyster
Bar102 and the endorsement of Brodyn103 in Probuild104 that not all aspects of
92 Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4; (2018) 264 CLR 1 at
[51].
93 Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4; (2018) 264 CLR 1 at
[52], referring to Brodyn Pty Ltd v Davenport [2004] NSWCA 394; (2004) 61 NSWLR 421.
94 Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4; (2018) 264 CLR 1 at
[80].
95 Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4; (2018) 264 CLR 1 at
[81].
96 Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4; (2018) 264 CLR 1 at
[82].
97 Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4; (2018) 264 CLR 1 at
[83].
98 [2018] HCA 4; (2018) 264 CLR 1.
99 [2010] NSWCA 190; (2010) 78 NSWLR 393.
100 [2018] HCA 4; (2018) 264 CLR 1.
101 [2004] NSWCA 394; (2004) 61 NSWLR 421.
102 [2010] NSWCA 190; (2010) 78 NSWLR 393.
103 [2004] NSWCA 394; (2004) 61 NSWLR 421.
104 [2018] HCA 4; (2018) 264 CLR 1.
-- 36 of 54 --
[2024] SASC 108 Stein J
33
Brodyn105 were overturned. Authorities since Chase Oyster Bar106 have referred to
“essential pre-conditions” to a valid payment claim.107 In EnerMech,108 the New
South Wales Court of Appeal addressed whether a payment claim was a valid
payment claim using the language of essential preconditions. Justice Basten
considered it is necessary to consider the terms of the legislation in addressing the
essential pre-conditions to a valid payment claim and stated:109
However, it is convenient to note at the outset that for some 20 years, since Brodyn Pty Ltd
t/as Time Cost and Quality v Davenport, this Court has been restrained in implying
essential preconditions to the engagement of statutory powers, which would invite judicial
intervention. Thus, in BSA Advanced Property Solutions (Fire) Pty Ltd v Ventia Australia
Pty Ltd a five-judge bench observed:
“35 There are undoubtedly limits to the characteristics of a valid payment claim. It is
commonly accepted that s 13(2) identifies such limits by use of the obligatory ‘must’.
However, conscious of the objects of the legislative scheme, the courts have been
cautious in identifying these as ‘basic requirements’, precise compliance with which
is a precondition to the exercise by the adjudicator of his or her function. Spigelman
CJ observed in Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd: ‘As Hodgson
JA recognised in Brodyn, the purpose of the legislative scheme is best served by
restricting the scope of intervention by the courts’.”
(The respondents accepted that s 13(2) did not create jurisdictional requirements: see also
Ceerose Pty Ltd v A-Civil Aust Pty Ltd in relation to s 22(2).)
(Footnotes omitted)
183 After observing that the legislation does not purport to limit the nature of a
payment or the amount of a payment to which a person is entitled, his Honour
cautioned against the risk of compartmentalising payments according to their
character, irrespective of the contractual terms, to contend that some fall within
and some do not fall within the concept of a progress payment.110 His Honour
considered that the statutory scheme accepted by the High Court as inconsistent
with any broader form of review is consistent also with a restrained approach to
the construction of the legislation in identifying matters which may constitute
essential pre-conditions to the exercise of the adjudicator’s function.111
Justice Basten further said no provision was identified in the legislation which
required a payment claim to be made “for construction work”.112 Rather, a payment
claim is a claim for money owing on account of construction work or related goods
and services. Thus, the definition of “progress payment” gives a primary meaning,
being a payment to which a person is entitled under s 8, and a secondary meaning,
105 [2004] NSWCA 394; (2004) 61 NSWLR 421.
106 [2010] NSWCA 190; (2010) 78 NSWLR 393.
107 The language employed in Project Blue Sky Inc v Australian Broadcasting Authority [1998] HCA 28;
(1998) 194 CLR 355 at [94]-[95] (McHugh, Kirby, Gummow and Hayne JJ) is of “essential
preliminaries”.
108 [2024] NSWCA 162.
109 EnerMech Pty Ltd v Acciona Infrastructure Projects Aust Pty Ltd [2024] NSWCA 162 at [9].
110 EnerMech Pty Ltd v Acciona Infrastructure Projects Aust Pty Ltd [2024] NSWCA 162 at [16].
111 EnerMech Pty Ltd v Acciona Infrastructure Projects Aust Pty Ltd [2024] NSWCA 162 at [46].
112 EnerMech Pty Ltd v Acciona Infrastructure Projects Aust Pty Ltd [2024] NSWCA 162 at [59].
-- 37 of 54 --
[2024] SASC 108 Stein J
34
by way of inclusions of each of three matters which are identified as illustrative
and not restrictive.113 His Honour concluded that whether an amount is in fact
payable will depend on the:114
proper construction of the contract, identification of the work which has been carried out
and a determination as to whether that work has already been paid for. These are matters
to be determined by an adjudicator in the case of a dispute; they are not preconditions to
the validity of a claim.
184 His Honour considered the focus must be on payments due under the
construction contract.115 Assessment of a progress claim will involve a range of
evaluative assessments, such as whether the work complies with the terms of the
contract and the degree to which it has been completed.116 His Honour considered
there was little scope for implying unstated conditions as essential to the validity
of a payment claim or a payment schedule.117 In Basten JA’s view, it should be
accepted that the object of the legislation and the way in which it is expected to
operate is that, with few exceptions, all questions arising from the construction of
the contract and the provisions of the legislation itself as applied to the particular
factual circumstances are matters for the adjudicator to determine.118
185 In light of these authorities, I do not accept Goyder’s submissions set out
above concerning Rothnere119 and Brodyn.120
186 I do not accept Goyder’s submissions that Allsop P’s reasons in Dualcorp121
and Kourakis CJ’s preference for those reasons in CATCON122 have the effect that
s 22(4) is jurisdictional. I discuss both of those decisions in more detail below. In
Dualcorp, Allsop P agreed with Macfarlan JA’s approval of the approach of
McDougall J to s 22(4) in John Goss.123 His Honour agreed the legislation
manifests an intention to prevent repetitious re-agitation of the same issues, the
primary mechanism for the effectuation of that intention appearing to be ss 13(5)
and 22(4).124 President Allsop’s decision was based upon s 13(5) thus his reference
to s 22(4) was obiter. In CATCON, Kourakis CJ preferred Allsop P’s reasoning in
113 EnerMech Pty Ltd v Acciona Infrastructure Projects Aust Pty Ltd [2024] NSWCA 162 at [61].
114 EnerMech Pty Ltd v Acciona Infrastructure Projects Aust Pty Ltd [2024] NSWCA 162 at [62].
115 EnerMech Pty Ltd v Acciona Infrastructure Projects Aust Pty Ltd [2024] NSWCA 162 at [67].
116 EnerMech Pty Ltd v Acciona Infrastructure Projects Aust Pty Ltd [2024] NSWCA 162 at [70].
117 EnerMech Pty Ltd v Acciona Infrastructure Projects Aust Pty Ltd [2024] NSWCA 162 at [74].
118 EnerMech Pty Ltd v Acciona Infrastructure Projects Aust Pty Ltd [2024] NSWCA 162 at [77].
119 [2004] NSWSC 1151.
120 [2004] NSWCA 394; (2004) 61 NSWLR 421.
121 [2009] NSWCA 69; (2009) 74 NSWLR 190.
122 [2019] SASC 193.
123 Dualcorp Pty Ltd v Remo Constructions Pty Ltd [2009] NSWCA 69; (2009) 74 NSWLR 190 at [16]
(Allsop J), [64]-[66] (Macfarlan JA), quoting John Goss Projects Pty Ltd v Leighton Contractors Pty
Ltd [2006] NSWSC 798; (2006) 66 NSWLR 707 at [37]-[40] (McDougall J). See also, Rothnere v
Quasar [2004] NSWSC 1151 at [41]-[44] (McDougall J).
124 Dualcorp Pty Ltd v Remo Constructions Pty Ltd [2009] NSWCA 69; (2009) 74 NSWLR 190 at [16]
(Allsop J).
-- 38 of 54 --
[2024] SASC 108 Stein J
35
Dualcorp over Macfarlan JA (with whom Handley AJA agreed).125 His Honour
did not express any view as to whether 22(4) is jurisdictional. In my view, these
decisions do not result in a conclusion that s 22(4) is a matter of jurisdiction.
187 I respectfully adopt McDougall J’s reasons and conclusion concerning
s 22(4) in Rothnere and John Goss.
188 In my view, the reasoning of the High Court and in particular Gageler J (as
he then was) in Probuild126 and Basten JA in EnerMech127 also supports the
conclusion that s 22(4) is not a matter of jurisdiction.
189 In determining the amount of a progress payment (pursuant to s 22(1)), where
relevant, an adjudicator is to consider whether there has been a previous
determination of value of that work or those related goods and services and, if so,
any change in that value. This may entail construction of the contract as well as
making evaluative assessments of the payment claim, schedule and other materials
required to be considered in s 22(1). In my view, taking into account the matters
referred to in the authorities above and the purposes of the Act, the preferable
construction is that s 22(4) falls for consideration in the course of the adjudicator’s
decision-making process in determining the amount of any progress payment to be
paid. The s 22(4) considerations are addressed by an adjudicator in the process of
determining the amount of the progress payment which is within the authority
conferred by s 22(1) upon the adjudicator.
Abuse of process, issue estoppel and Anshun estoppel
190 The second ground on which Goyder challenged the Second Adjudication
Determination and the Third Payment Claim was abuse of process. Goyder’s
position was the re-agitation of a claim previously made was impermissible under
the rubric of abuse of process as was the failure to include all heads of claim in one
payment claim. Goyder framed its submissions by reference to an overarching
principle of abuse of process with a focus on whether the same claim has been
made or could have been made in a previous payment claim. Its case was that the
claim for delay costs was a single claim which had already been determined and it
was an abuse to re-agitate it. Insofar as the procurement premium head of claim
was not re-agitated because it was not advanced in the first payment claim, Goyder
submitted it was an abuse of process to subsequently seek recovery of those costs
because the alleged costs or head of claim could, and should, have been advanced
in the First Payment Claim.
191 Goyder referred to a number of authorities which it characterised as cases
applying principles akin to the Anshun principle128 to the security of payment
125 Civil & Allied Technical Construction Pty Ltd v Resolution Institute [2019] SASC 193 at [57], citing
Dualcorp Pty Ltd v Remo Constructions Pty Ltd [2009] NSWCA 69; (2009) 74 NSWLR 190 at [13]-
[15].
126 [2018] HCA 4; (2018) 264 CLR 1.
127 [2024] NSWCA 162.
128 Port of Melbourne Authority v Anshun Pty Ltd [1981] HCA 45; (1981) 147 CLR 589.
-- 39 of 54 --
[2024] SASC 108 Stein J
36
regime. These authorities included a number of decisions of single Judges in other
States and the New South Wales Court of Appeal decision in Dualcorp129 and
Australian Capital Territory Court of Appeal decision in Harlech Enterprises Pty
Ltd (ATF Harlech Family Trust) v Beno Excavations Pty Ltd (“Harlech”).130
192 GE-Elecnor’s primary response to the alleged abuse of process assertion was
there has been no impermissible re-agitation of claims and the extent to which any
principles of abuse of process, issue estoppel and Anshun131 estoppel apply can only
be determined by reference to the Act.
193 In Dualcorp,132 Macfarlan JA with whom Handley AJA agreed, concluded
that principles of issue estoppel were applicable to the determinations of
adjudicators under the NSW Act. His Honour stated that abuse of process was
probably also applicable, but it was unnecessary to reach a final view on that
issue.133 Relying on the objects of the Act and general principles precluding re-
litigation, Macfarlan JA considered that adjudication determinations were intended
to be conclusive and final and binding as to the issues determined except to the
extent the NSW Act allows the determination to be revisited.134
194 President Allsop approached the issue differently, addressing question of
re-agitation by reference to the construction of the NSW Act. His Honour
preferred to leave consideration of principles of estoppel to prevent any apparently
abusive operation of the legislation not specifically addressed by ss 13(5) and
22(4) to another occasion. President Allsop regarded the terms of s 13(5) as a
prohibition and a sufficiently clear statutory indication that a document purporting
to be payment claim in respect of the same reference date as a previous claim is
not a payment claim under the Act and does not attract the statutory regime of the
Act.135
195 Time does not permit a fulsome review of the authorities. It suffices for
present purposes to observe that the majority decision in Dualcorp136 has been
applied in a number of interstate first instance decisions including in New South
Wales and Queensland as standing for the proposition that principles of issue
estoppel apply in relation to adjudication determinations including decisions
discussed below. However, the application, or extent of application, of issue
estoppel concepts have been questioned in other cases. Some authorities have
considered concepts of abuse of process and some have considered an “extended”
129 [2009] NSWCA 69; (2009) 74 NSWLR 190.
130 [2022] ACTCA 42; (2022) 18 ACTLR 245.
131 Port of Melbourne Authority v Anshun Pty Ltd [1981] HCA 45; (1981) 147 CLR 589.
132 [2009] NSWCA 69; (2009) 74 NSWLR 190.
133 Dualcorp Pty Ltd v Remo Constructions Pty Ltd [2009] NSWCA 69; (2009) 74 NSWLR 190 at [68].
134 Dualcorp Pty Ltd v Remo Constructions Pty Ltd [2009] NSWCA 69; (2009) 74 NSWLR 190 at [60].
135 Dualcorp Pty Ltd v Remo Constructions Pty Ltd [2009] NSWCA 69; (2009) 74 NSWLR 190 at [14].
136 [2009] NSWCA 69; (2009) 74 NSWLR 190.
-- 40 of 54 --
[2024] SASC 108 Stein J
37
Anshun137 estoppel in the context of security for payment legislation. I discuss a
number of those authorities below.
196 In University of Sydney v Cadence Australia Pty Ltd (“Cadence”),138 as part
of an expanded claim, a party sought to re-agitate a delay costs claim it had
previously made. The first claim for delay costs sought an adjustment to costs of
employees for the period of the delay. The adjudicator found a nil balance was
due. In particular, the adjudicator concluded the claimant had not provided any
evidence to satisfy the adjudicator of compliance with the relevant requirements
of the contract. The claim accordingly had to fail.
197 After the adjudication, the party served a second claim in which delay costs
were reclaimed for all periods of delay claimed in the first claim together with
further periods. There was overlap as between the two payment claims in the delay
costs. The time frames in respect of which delay claims were made were not
identical but overlapped to varying degrees.
198 Justice Hammerschlag considered that sub-ss 13(1), (5) and (6) and 22(4)
inhibited repetitious use of the legislation in respect of the same claim.139
Justice Hammerschlag took the view that s 22(4) did not apply on the facts
because, in the first adjudication, the adjudicator rejected the claim which was not
established on the evidence. The findings in the first adjudication therefore did
not give rise to an issue estoppel. However, Hammerschlag J concluded the party
had exhausted its statutory entitlement to claim the delay costs the subject of the
first claim. The fact that costs for periods of delay beyond those claimed
previously were included did not detract from the fact that the party was seeking
to use the adjudication process to have a second go because the party was
dissatisfied with the first outcome. Justice Hammerschlag considered s 13(6) does
not have in contemplation a payment claim for an amount previously claimed,
adjudicated upon and rejected. As the second claim had the object of obtaining an
advantage over that offered by the legislation, it was an abuse of process. The
legislation gave no right to remake a payment claim earlier made and adjudicated
on. Thus, to the extent the second claim sought to do so, it was not a payment
claim within the meaning of the legislation. The party had no right to apply for
the adjudication of the second claim and the adjudicator had no jurisdiction to
adjudicate it. There was a sufficient degree of overlap and dealing with the
application would require the adjudicator to re-perform the statutory adjudication
function already discharged.
199 Justice Hammerschlag rejected the submission that the question whether the
later payment claim should be adjudicated upon should be left to the adjudicator
given the lack of jurisdiction.140
137 Port of Melbourne Authority v Anshun Pty Ltd [1981] HCA 45; (1981) 147 CLR 589.
138 [2009] NSWSC 635.
139 University of Sydney v Cadence Australia Pty Ltd [2009] NSWSC 635 at [38]-[39].
140 University of Sydney v Cadence Australia Pty Ltd [2009] NSWSC 635 at [57].
-- 41 of 54 --
[2024] SASC 108 Stein J
38
200 In Urban Traders Pty Ltd v Paul Michael Pty Ltd (“Urban Traders”),141
McDougall J described the essence of abuse of process established by the
legislation as what Allsop P in Dualcorp described as the repetitious use of the
adjudication process to require an adjudicator or successive adjudicators to
exercise the same statutory task in respect of the same claim on successive
occasions, use of the legislation to have another go when dissatisfied by the result
of the first adjudication or repetitious re-agitation of the same issues.142
201 However, his Honour did not consider that every repetition in a subsequent
payment claim of a claim made in an earlier payment must amount to an abuse of
process, observing that the relevant concept is not abuse of process at large but
rather specifically abuse of the processes of the legislation which are designed to
ensure that builders receive prompt and progressive payment for construction work
performed or related goods and services provided. The question whether there has
been an abuse of the processes of the NSW Act must take into account relevant
provisions, specifically, ss 13(6) and 22(4). Further, on his Honour’s view, all
relevant contextual facts must be considered in determining whether or not
repetition of a claim will amount to an abuse of process. His Honour did not
consider it possible to state in an exhaustive fashion the factors which would lead
to the conclusion of abuse of process.143
202 Justice McDougall considered any abuse of process would be limited to the
extent of the re-agitation and the re-agitated claims were severable.144
203 In Watpac Constructions (NSW) Pty Ltd v Austin Corp Pty Ltd (“Watpac”),145
McDougall J addressed the validity of an adjudication determination in
circumstances in which the payment claim addressed in the adjudication included
variation claims which had been addressed in an earlier adjudication
determination. In that earlier determination, the adjudicator determined the party
had no entitlement, as claimed, to the variations. Further work was performed
between the dates of the payment claims. Reliance was placed on issue estoppel
and Anshun146 estoppel. Justice McDougall stated that, other than in special
circumstances, a party should put the whole of its case in support of a particular
payment claim before an adjudicator charged with the responsibility of deciding
the parties’ entitlements to the amounts claimed.
204 Justice McDougall continued to say that whether or not a repetition of a claim
will be an abuse of process requires consideration of all relevant contextual facts
and the reasons why courts intervene to prevent abuse, which includes preventing
141 [2009] NSWSC 1072.
142 Urban Traders Pty Ltd v Paul Michael Pty Ltd [2009] NSWSC 1072 at [38], citing Dualcorp Pty Ltd v
Remo Constructions Pty Ltd [2009] NSWCA 69; (2009) 74 NSWLR 190 at [2], [16].
143 Urban Traders Pty Ltd v Paul Michael Pty Ltd [2009] NSWSC 1072 at [38]-[43].
144 Urban Traders Pty Ltd v Paul Michael Pty Ltd [2009] NSWSC 1072 at [60].
145 [2010] NSWSC 168.
146 Port of Melbourne Authority v Anshun Pty Ltd [1981] HCA 45; (1981) 147 CLR 589.
-- 42 of 54 --
[2024] SASC 108 Stein J
39
a person from being vexed by having to re-argue an issue previously
authoritatively decided.147
205 Justice McDougall thought the statement of Hammerschlag J in Cadence148
that s 13(6) did not contemplate resubmission of a claim previously adjudicated
and rejected found support in both the approach of Macfarlan JA and Allsop P in
Dualcorp.149 However, his Honour had some difficulty with the wider statement
of Hammerschlag J to the effect that the legislation gives no right to remake a
payment claim earlier made and adjudicated upon.150 While s 22(4) is not an
exclusive code dealing with all occasions on which amounts are claimed again, as
the prospect of re-valuation is expressly preserved in s 22(4), it cannot be said that
the legislation impliedly prohibits the inclusion of an amount the subject of a prior
adjudication in a later payment claim.151
206 In the case before his Honour, the first determination did not bind the second
adjudicator because the first adjudicator did not value the work in question.152
207 Justice McDougall thought that if the proper construction of the legislation
gives rise to a prohibition on repeating claims in the context of ongoing
construction work, the prohibition should be limited to circumstances not
expressly covered by s 22(4), that is, where the prior adjudicator has considered
the claim and in the course of performing the statutory function of deciding the
amount of any progress payment has determined there was no entitlement to
recover.153
208 Justice McDougall went on to say there were two possible categories of
payment claims that could be described as invalid. First, the kind of case described
by Allsop P in Dualcorp, being a repetitious payment claim being no more than
the same claim for the same completed works resubmitted after work had ceased
purely for the purposes of creating a fresh reference date.154 Such a claim would
be outside s 8(2)(b) and 13(6) of the Act. The second is a payment claim claiming
an amount the subject of a prior payment claim and adjudication in circumstances
where the prior adjudicator has determined nothing is due by the respondent to the
claimant. That could occur where the prior adjudicator rejected the claim because
the claimant had not made out any legal entitlement to it or had not put the claim
on a basis capable of being the subject of the adjudicator’s determination.155
147 Watpac Constructions (NSW) Pty Ltd v Austin Corp Pty Ltd [2010] NSWSC 168 at [53], quoting Urban
Traders Pty Ltd v Paul Michael Pty Ltd [2009] NSWSC 1072 at [42].
148 [2009] NSWSC 635.
149 Watpac Constructions (NSW) Pty Ltd v Austin Corp Pty Ltd [2010] NSWSC 168 at [63], citing
University of Sydney v Cadence Australia Pty Ltd [2009] NSWSC 635 at [54].
150 Watpac Constructions (NSW) Pty Ltd v Austin Corp Pty Ltd [2010] NSWSC 168 at [64], citing
University of Sydney v Cadence Australia Pty Ltd [2009] NSWSC 635 at [56].
151 Watpac Constructions (NSW) Pty Ltd v Austin Corp Pty Ltd [2010] NSWSC 168 at [60] and [64].
152 Watpac Constructions (NSW) Pty Ltd v Austin Corp Pty Ltd [2010] NSWSC 168 at [84].
153 Watpac Constructions (NSW) Pty Ltd v Austin Corp Pty Ltd [2010] NSWSC 168 at [85].
154 Watpac Constructions (NSW) Pty Ltd v Austin Corp Pty Ltd [2010] NSWSC 168 at [86], citing Dualcorp
Pty Ltd v Remo Constructions Pty Ltd [2009] NSWCA 69; (2009) 74 NSWLR 190 at [13].
155 Watpac Constructions (NSW) Pty Ltd v Austin Corp Pty Ltd [2010] NSWSC 168 at [86].
-- 43 of 54 --
[2024] SASC 108 Stein J
40
Justice McDougall continued to say that the case for invalidity is stronger where
the earlier adjudicator has determined there is no entitlement to the amount of the
payment claim or a severable portion of it. That is because s 22(4) deals with a
situation where entitlement having been found, the prior adjudicator determines
the value of the work and this avoids the difficulty of inconsistent outcomes.
However, s 22(4) does not operate where the prior adjudicator determined the fate
of the payment claim on the basis the claimant had not made out an entitlement to
be paid. In those circumstances there is no question of a finding by the previous
valuation or of showing the value of the work has changed and no question of a
cumulative payment claim where work is ongoing. Accordingly, it is easier to see
why mere resubmission might be regarded as outside the scheme of the Act and,
in particular, outside whatever permission to resubmit can be implied from
s 8(2)(b) and s 13(6).
209 Justice McDougall considered that re-agitation would not mean the whole of
a later payment claim was not a payment claim for the purposes of the legislation.
Any invalidity could apply only to the extent of the repetition.156
210 In Wiggins Island Coal Export Terminal Pty Ltd v Monadelphous,157 Jackson
J accepted an extended Anshun158 estoppel based on a concept of unreasonableness
to have a role in the context of the Building and Construction Industry Payments
Act 2004 (Qld) (“the Qld Act”).159
211 In Caltex Refineries (Qld) Pty Ltd v Allstate Access (Australia) Pty Ltd,160
Philip McMurdo J said that Macfarlan JA in Dualcorp must have had in mind
something less than the common law doctrine of issue estoppel.161 This is because
the estoppel in Dualcorp162 precludes re-agitation in some forums but not others.
Thus, the source of the more limited estoppel must be found, if at all, in the
legislation. In his Honour’s view, the legislation did not provide it. Rather, his
Honour considered the limited finality described by Macfarlan JA to be founded
upon the combined effect of several provisions in the legislation.
212 In CATCON,163 Kourakis CJ addressed an interlocutory application for a stay
in the context of an application for judicial review seeking orders setting aside a
referral to adjudication on the basis a payment claim was invalid because it was a
second claim in respect of the same reference date.
156 Watpac Constructions (NSW) Pty Ltd v Austin Corp Pty Ltd [2010] NSWSC 168 at [74].
157 [2016] QSC 96.
158 Port of Melbourne Authority v Anshun Pty Ltd [1981] HCA 45; (1981) 147 CLR 589.
159 Wiggins Island Coal Export Terminal Pty Ltd v Monadelphous [2016] QSC 96 at [162]. The provisions
of the Qld Act are relevantly similar to those of the Act.
160 [2014] QSC 223.
161 Caltex Refineries (Qld) Pty Ltd v Allstate Access (Australia) Pty Ltd [2014] QSC 223 at [48]-[55], citing
Dualcorp Pty Ltd v Remo Constructions Pty Ltd [2009] NSWCA 69; (2009) 74 NSWLR 190 at [68].
162 [2009] NSWCA 69; (2009) 74 NSWLR 190.
163 Civil & Allied Technical Construction Pty Ltd v Resolution Institute [2019] SASC 193.
-- 44 of 54 --
[2024] SASC 108 Stein J
41
213 After analysing the reasons in Dualcorp, Kourakis CJ stated a preference for
the reasoning of Allsop P. His Honour then referred to a number of authorities,
including Cadence,164 which have prohibited a further payment claim for items the
subject of previous adjudications. Chief Justice Kourakis agreed with
Hammerschlag J that there is no statutory mechanism available to an adjudicator
to prevent double adjudication.165 After referring to the reasons given by
McDougall J in Urban Traders166 for the basis upon which a court may enjoin a
second adjudication of the same claim, Kourakis CJ observed that the application
of issue estoppel and abuse of process to the statutory procedure did not directly
arise in the matter before him.167
214 His Honour characterised the question whether decisions, other than the
valuation of building work which arise in successive adjudications, can be
re-argued as a difficult one.168 Chief Justice Kourakis considered there is some
difficulty in adopting principles of issue estoppel and res judicata to administrative
decisions made under the Act. This difficulty is exacerbated by s 32 of the Act
which has the result that issue estoppel or abuse of process will not bind the parties
in any subsequent judicial determination of their contractual disputes.169 After
posing an alternative solution to the double adjudication problem as treating the
judgment entered in a court on a second or subsequent adjudication as an abuse of
process, his Honour continued to say that the difficulty in identifying an express
provision on which to base those provisions is a reason for not assuming too
narrow an operation for s 13(5) of the Act. Chief Justice Kourakis concluded it
was reasonably arguable that provision precluded the making of a second payment
claim for the same entitlement.
215 Chief Justice Kourakis considered the fact of referral of the adjudication, its
validity and the effectiveness in enlivening the power of the adjudicator was
dependent on whether the referral was effective in law. If the payment claim was
not a valid claim under the Act and such a claim was a pre-condition to a valid
adjudication, there could be no such authority.170
216 In Harlech,171 the appellant, Harlech Enterprises Pty Ltd was the vehicle
through which the respondent, Beno Excavations Pty Ltd, a civil contracting
company, engaged its general manager until 2020. Harlech made a payment claim
under the Building and Construction Industry (Security of Payment) Act 2009
(ACT) (“the ACT Act”),172 against Beno, claiming an amount for work in 2020.
164 [2009] NSWSC 635.
165 Civil & Allied Technical Construction Pty Ltd v Resolution Institute [2019] SASC 193 at [60], citing
University of Sydney v Cadence Australia Pty Ltd [2009] NSWSC 635 at [57]-[60].
166 [2009] NSWSC 1072.
167 Civil & Allied Technical Construction Pty Ltd v Resolution Institute [2019] SASC 193 at [62], citing
University of Sydney v Cadence Australia Pty Ltd [2009] NSWSC 635 at [21]-[23], [25], [28], [58]-[59].
168 Civil & Allied Technical Construction Pty Ltd v Resolution Institute [2019] SASC 193 at [62].
169 Civil & Allied Technical Construction Pty Ltd v Resolution Institute [2019] SASC 193 at [63]-[64].
170 Civil & Allied Technical Construction Pty Ltd v Resolution Institute [2019] SASC 193 at [80].
171 [2022] ACTCA 42; (2022) 18 ACTLR 245.
172 The provisions of the ACT Act are relevantly similar to those of the Act.
-- 45 of 54 --
[2024] SASC 108 Stein J
42
Beno provided a payment schedule of nil with reasons for non-payment. An
adjudication occurred, resulting in a determination that the full amount claimed by
Harlech was payable.
217 Harlech then served two further payment claims for work in 2017 and 2018.
Beno served a payment schedule indicating the amount it would pay was nil and
repeating the previous contentions and supplementing them with additional
reasons. The adjudicator determined almost the total amount claimed was payable.
The adjudicator concluded that most of the reasons provided by Beno were the
same reasons previously presented and raised as part of the first response.
218 Relief was granted in proceedings seeking prerogative relief commenced by
Beno. On appeal, the Australian Capital Territory Court of Appeal concluded that
the primary Judge did not err in granting relief to Beno. Justices Lee and Kennett
reached the same conclusion but by different routes. Justice Elkaim, without
rejecting Kennett J’s path, generally preferred that of Lee J, in particular his
reliance on the ACT Act.
219 Justice Lee described the formal and substantive requirements for an
adjudicator’s decision in s 24173 as framing each adjudication as an independent
exercise. Section 24(2) contains a list of mandatory considerations which does not
include previous adjudication decisions.
220 Justice Lee considered that s 24(4) expressly contemplates the circumstances
in which the decision of a previous adjudicator will bind a subsequent adjudicator,
expressly referring only to circumstances where an adjudicator has valued
construction work or related goods and services.
221 After analysis of the reasons in Dualcorp174 and other decisions referring to
it, including Caltex Refineries (Qld) Pty Ltd v Allstate Access (Australia) Pty Ltd,175
and CATCON,176 Lee J stated that issue estoppel in the context of security of
payment legislation deviates from the principles of issue estoppel as commonly
understood. Even where the doctrine has been found to operate, it is characterised
as narrow, inchoate, and based upon broader principles of preclusion.177
222 Justice Lee considered the legislation manifests an intention to preclude
abuse of the statutory scheme by repetitive claims for the same work or related
goods or services including an abuse of the process of obtaining judgment. This
intention is reflected in the provisions which have the following effect:
On and from each reference date a person is entitled to a payment.
173 Section 24 of the ACT Act is relevantly similar to s 22 of the Act.
174 [2009] NSWCA 69; (2009) 74 NSWLR 190.
175 [2014] QSC 223 at [54]-[55].
176 [2019] SASC 193.
177 Harlech Enterprises Pty Ltd (ATF Harlech Family Trust) v Beno Excavations Pty Ltd [2022] ACTCA
42; (2022) 18 ACTLR 245 at [88].
-- 46 of 54 --
[2024] SASC 108 Stein J
43
A claimant must not render more than one payment claim for each reference date.
There can only be one payment claim in relation to each reference date,
precluding a claimant from pursuing a payment claim for a reference date
which has already been the subject of adjudication.
The provision which mandates that if an adjudicator has valued construction work
or related goods or services, the adjudicator or any other adjudicator is bound
by that valuation in a later adjudication.
The provisions which enable an adjudication certificate to be entered as a judgment
for debt and enforced. A court cannot enforce a judgment for the same debt
more than once, thus, there cannot be two adjudication certifications with
respect to the same work.178
223 Justice Lee considered the common law concept of issue estoppel is an inapt
label to apply to the preclusion identified in Dualcorp179 which was best described
as an abuse of process. His Honour agreed with Kourakis CJ in CATCON180 that
the best frame of reference to speak of the extent of preclusion arising from a
double adjudication is to treat the judgment on a second or subsequent adjudication
as an abuse of process of the court faced with an attempt to enter judgment
concerning a subsequent adjudication. However, it would also constitute a form
of abuse of process if, before judgment, a party purported to re-agitate a claim
which had already been decided. Not every repetition in a subsequent payment
claim of a claim made in an earlier payment must amount to an abuse of process
even if the earlier payment claim has been the subject of a determination. The
relevant concept is an abuse of the processes of the Act, not an abuse of process at
large. Specifically, it is an abuse of the processes of the Act designed to ensure
that builders and subcontractors receive prompt and progressive payment for
construction work performed or goods and services provided.
224 Justice Lee also referred to Cadence in which Hammerschlag J did not
conclude that the first adjudication gave rise to an issue estoppel but the second
claim could not be legitimately pursued under the New South Wales legislation.181
225 Justice Lee eschewed the use of the term issue estoppel as consistent with
recognising the starting point is the Act itself.
226 It followed that Beno was not precluded from restating the contentions
previously made in the second adjudication. The two adjudications concerned
178 Harlech Enterprises Pty Ltd (ATF Harlech Family Trust) v Beno Excavations Pty Ltd [2022] ACTCA
42; (2022) 18 ACTLR 245 at [89].
179 [2009] NSWCA 69; (2009) 74 NSWLR 190.
180 [2019] SASC 193.
181 Harlech Enterprises Pty Ltd (ATF Harlech Family Trust) v Beno Excavations Pty Ltd [2022] ACTCA
42; (2022) 18 ACTLR 245 at [94], citing University of Sydney v Cadence Australia Pty Ltd [2009]
NSWSC 635 at [56].
-- 47 of 54 --
[2024] SASC 108 Stein J
44
different work completed years apart and there was no precluded re-agitation or
attempt to value the same work anew.182
227 Justice Lee said there will be matters incidental and antecedent to a valuation
determination which Parliament cannot have intended be open to abuse by
dissatisfied or creative complainants. However, his Honour considered it
important to bear in mind that the legislation’s purpose is to facilitate security of
payment by creating a right to interim payment and to protect those payment claims
once adjudicated on from interference. The purpose is not to protect the broader
findings of adjudicators. Justice Lee considered this another indication that the
only issue which cannot resurface and be reconsidered in a subsequent
adjudication is the question of the value of work with respect to a particular
reference date.183 If an adjudicator was bound to a previous adjudicator’s
determination as to matters such as the existence of a contract, the construction of
it, and the agreed rate of payment, it would be inconsistent with the ability to turn
his or her mind to the prerequisites to the exercise of power which are set out as
mandatory considerations.
228 Justice Kennett agreed with the outcome of the appeal but stated his reasons
differently.
229 Justice Kennett accepted the possibility that a repetitious claim for the
re-agitation of contentions previously rejected could properly be characterised as
an abuse of process and the court might grant injunctive relief on that basis. That
would follow from the application of a doctrine based on protection of scarce
resources and institutional integrity of courts and tribunals. However, that did not
answer the question whether issue estoppel, with its distinct concerns and doctrinal
foundations, limits the contentions that parties can rely on in an adjudication.184
230 The matter submitted for adjudication is a payment claim. Nothing in the
legislation suggests a decision on an adjudication is intended to be conclusive of
rights under the contract. Section 38185 of the legislation is to the contrary. Thus,
the extent to which adjudication is final is circumscribed. The legislation creates
a regime for interim payments, not a regime for enforcing contracts. Section 38
has the effect that an adjudication decision does not affect any right a party may
have to a progress payment under the Act. Justice Kennett considered that read
that way, s 38 left no room for any issue estoppel to arise at common law in an
adjudication in respect of issues decided in a prior adjudication.186 A number of
aspects of the statutory context supported that conclusion including the nature and
182 Harlech Enterprises Pty Ltd (ATF Harlech Family Trust) v Beno Excavations Pty Ltd [2022] ACTCA
42; (2022) 18 ACTLR 245 at [100].
183 Harlech Enterprises Pty Ltd (ATF Harlech Family Trust) v Beno Excavations Pty Ltd [2022] ACTCA
42 at [111].
184 Harlech Enterprises Pty Ltd (ATF Harlech Family Trust) v Beno Excavations Pty Ltd [2022] ACTCA
42 at [19].
185 Section 38 of the ACT Act is relevantly similar to s 32 of the Act
186 Harlech Enterprises Pty Ltd (ATF Harlech Family Trust) v Beno Excavations Pty Ltd [2022] ACTCA
42 at [35].
-- 48 of 54 --
[2024] SASC 108 Stein J
45
timing of the adjudication process, and construing s 24(4) as legislating against
particular examples of re-agitation of settled issues.187
231 Justice Kennett disagreed with Dualcorp188 to the extent the majority saw the
result as flowing from principles of issue estoppel. He considered Dualcorp
correct for the reasons given by Allsop P as founded on statutory provisions
precluding repeat claims.189
232 While rejecting the application of issue estoppel, Harlech countenances the
grant of remedies based on abuse of the processes of the legislation.190
233 Neither Dualcorp191 nor Harlech192 on the facts engaged Anshun193 estoppel
concepts.
234 Based on Harlech194 and CATCON,195 I accept that concepts of abuse of
process, in the sense of abuse of the processes of the Act, play a role in the context
of payment claims and adjudications under the Act. While Lee and Kennett JJ in
Harlech196 approached the question differently, their conclusions both depended
upon the construction of the legislation. In light of Kourakis CJ’s preference for
the approach of Allsop P in Dualcorp197 and the Australian Capital Territory Court
of Appeal’s approach in Harlech,198 I address the question of abuse of process from
the perspective of the construction of the Act.
Security of Payment Act provisions
235 As set out above, on and from each reference date under a construction
contract s 8 provides an entitlement to a progress payment to a person who has
undertaken to carry out construction work or to supply related goods and services
under a construction contract. A reference date is a necessary prerequisite to the
entitlement to issue a progress payment. Section 8 attaches the right to a progress
payment to reference dates rather than to specific work. A reference date is defined
in the Act in relation to when a claim for a progress payment may be made, not by
reference to a period of time during which specific work was carried out. This is
made clear by reference to work “undertaken to be carried out” or goods and
services “undertaken to be supplied”. The provisions of a contract, however, may
187 Harlech Enterprises Pty Ltd (ATF Harlech Family Trust) v Beno Excavations Pty Ltd [2022] ACTCA
42 at [36].
188 [2009] NSWCA 69; (2009) 74 NSWLR 190.
189 Harlech Enterprises Pty Ltd (ATF Harlech Family Trust) v Beno Excavations Pty Ltd [2022] ACTCA
42 at [37], citing Dualcorp Pty Ltd v Remo Constructions Pty Ltd [2009] NSWCA 69; (2009) 74
NSWLR 190.
190 ACTCA 42; (2022) 18 ACTLR 245.
191 [2009] NSWCA 69; (2009) 74 NSWLR 190.
192 [2022] ACTCA 42; (2022) 18 ACTLR 245.
193 [1981] HCA 45; (1981) 147 CLR 589.
194 [2022] ACTCA 42; (2022) 18 ACTLR 245.
195 [2019] SASC 193.
196 [2022] ACTCA 42; (2022) 18 ACTLR 245.
197 [2009] NSWCA 69; (2009) 74 NSWLR 190.
198 [2022] ACTCA 42; (2022) 18 ACTLR 245.
-- 49 of 54 --
[2024] SASC 108 Stein J
46
contain such a requirement. When the contract does not provide a date for making
a progress payment, the definition captures a period of time from the last day of
the month in which construction work was first carried out and ending on the last
day of each subsequent month.
236 In this case, each calendar month constitutes a reference date if GE-Elecnor
considers there has been completion of a milestone event or other amounts are
payable. The manner in which amounts which constitute delay claims are
calculated and valued is described above.
237 Section 13 of Act requires a payment claim to identify the construction work
or related goods and services to which the progress payment relates and indicate
the amount claimed. As discussed above, in the case of delay claims, the basis of
contractual entitlement is to be shown which generally will be enough to identify
by inference the construction work or related goods and services to which the
payment relates.199
238 A payment claim must be served within whichever is the later of the
contractual period or six months after the construction work to which the claim
relates was last carried out. Section 13(4) thus requires a payment claim to include
a claim for payment for some work performed in the previous six month period.200
239 Section 13(5) precludes a claimant serving more than one payment claim in
respect of each reference date. However, there is no legislative provision which
provides that specific work performed in the period of time encompassed by a
reference date can only be claimed in a payment claim for that specific reference
date. Subject again to the terms of the contract and re-agitation issues, the Act
does not limit a claimant to only one opportunity to make a claim for ongoing
construction work (or ongoing provision of related goods and services) in a
payment claim for a reference date corresponding to the timeframe within which
the specific construction work was performed. Allowing a claim to be made up to
six months after construction work was carried out is inconsistent with that
position.
240 In Brodyn, Hodgson JA considered the only non-contractual limit to the
occurrence of reference dates is that flowing from s 13(4) such that reference dates
cannot support serving a payment claim outside the time frames allowed for by
that subsection.201 This conclusion was supported by s 13(6) which in his Honour’s
view indicates that successive payment claims do not necessarily have to be in
respect of additional work.202 This was particularly so by reason of s 13(3)(a)
which allows amounts for which a party is liable under s 27(2A), being losses and
199 Coordinated Construction Co Pty Ltd v Climatech (Canberra) Pty Ltd [2005] NSWCA 229 at [26]
(Hodgson JA).
200 Estate Property Holdings Pty Ltd v Barclay Mowlem Construction Ltd [2004] NSWCA 393 at [21]
(Hodgson JA, Mason P and Giles JA agreeing).
201 Brodyn Pty Ltd v Davenport [2004] NSWCA 394; (2004) 61 NSWLR 421 at [63].
202 Brodyn Pty Ltd v Davenport [2004] NSWCA 394; (2004) 61 NSWLR 421 at [64].
-- 50 of 54 --
[2024] SASC 108 Stein J
47
expenses arising from suspension of work, to be included in payment claims.
Thus, the subsection contemplates further payment claims for amounts of this
nature being made progressively.203
241 Section 13(6) expressly accommodates the inclusion in a payment claim of
an amount included in a previous payment claim. GE-Elecnor’s counsel accepted
that s 13(6) of the Act accommodates the circumstances of a cumulative payment
process within a construction contract but contended it also enabled the inclusion
of an amount included in a previous payment claim subject to the qualification that
such amount has not been included in a payment claim the subject of an
adjudication determination. It is not necessary for me to determine the potential
ambit of s13(6) for this matter. It is sufficient for present purposes to acknowledge
that the Act does not prevent a claimant in all circumstances from including
amounts which have been included in a prior payment claim. Some level of
overlap is expressly envisaged by ss 13(6) and 22(4). Section 22(4) contemplates
the prospect of some overlap and addresses it to the extent that a later adjudicator
is bound by an earlier determination of “that” work or “those” goods and services
unless satisfied the value has changed. By expressly allowing for overlap and
articulating the consequences, by inference the subsection does not preclude the
inclusion in later payment claims of claims for value other than for “that” work
and “those” goods and services.
242 In my view it follows that, subject to the terms of any contract, the provisions
of the Act do not require a claim for all (non-overlapping) components of delay
costs incurred by reason of a delay event to be claimed in one and one only
progress claim. Further, such a conclusion would be inconsistent with the purposes
of the Act.
243 I therefore do not consider it was an abuse of the processes of the Act for
GE-Elecnor to include different, non-overlapping, aspects of delay costs in
different payment claims. Put differently, it was not an abuse of process to fail to
include all aspects of delay costs in one payment claim.
244 It follows that I reject Goyder’s contention that it was, and would be, an abuse
of process for GE-Elecnor to include in a payment claim after the First Payment
Claim any claim for aspects of delay costs which were not included in the First
Payment Claim and addressed in the First Adjudication Determination.
245 This leaves for consideration the overlap between the claims for thickening
costs.
203 Brodyn Pty Ltd v Davenport [2004] NSWCA 394; (2004) 61 NSWLR 421 at [64].
-- 51 of 54 --
[2024] SASC 108 Stein J
48
Re-agitation of thickening costs claim
246 As set out above, there is an overlap in the thickening costs claim as between
the First Adjudication Determination and the Third Payment Claim and Third
Adjudication Application.
247 Goyder relied significantly on Cadence.204 It contended I am bound to follow
Cadence by reason of Kourakis CJ’s decision in CATCON.205
248 Turning to the facts in this matter, in the First Adjudication Determination,
the Adjudicator was not satisfied on the information provided that, among other
things, the indirect resources claimed in the thickening claim were additional
resources required due to the delays the subject of EOT 001 and EOT 002.
Accordingly, GE-Elecnor had not discharged its burden of proof to establish
entitlement to thickening of indirect resources claim and was not entitled to any
amount for the thickening claim.
249 For the purposes of my decision, it is not necessary to consider the extent to
which s 22(4) may inhibit repetition, address concerns such as those expressed by
McDougall J with broader aspects of statements made by Macfarlan JA in
Dualcorp206 and Hammerschlag J in Cadence207 or address Goyder’s submission
that s 22(4) only allows a subsequent adjudicator to value the change in value of
construction work. Section 22(4) does not apply in this case because the
Adjudicator did not determine the value of the thickening claim in the First
Adjudication Determination, but instead rejected that claim.
250 The Adjudicator’s conclusion that GE-Elecnor failed to establish the basis
for the claim renders the claim for thickening costs made in the Third Payment
Claim indistinguishable from the delay costs claim in Cadence.208 The thickening
costs claim in the Third Payment Claim is a claim for amounts included in the First
Payment Claim and addressed in the First Adjudication Determination in
circumstances where the Adjudicator determined nothing is due by Goyder to
GE-Elecnor. The thickening costs claim thus falls within the description given by
McDougall J in Watpac209 as one of the kinds of claims precluded by the legislation
as an impermissible re-agitation by re-claiming thickening costs in respect of
which the Adjudicator has already discharged the statutory function by rejecting
the claim as lacking evidential foundation.
251 The fact that the Third Payment Claim includes additional amounts claimed
in the First Payment Claim or amounts referable to a period after the First Payment
Claim does not overcome this difficulty. The inclusion of the costs for light
204 [2009] NSWSC 635. Sections 13 and 22 of the NSW legislation at the time were relevantly the same
as the equivalent provisions in the Act.
205 [2019] SASC 193.
206 [2009] NSWCA 69; (2009) 74 NSWLR 190.
207 [2009] NSWSC 635.
208 [2009] NSWSC 635.
209 [2010] NSWSC 168.
-- 52 of 54 --
[2024] SASC 108 Stein J
49
vehicles also does not justify a different conclusion. Thickening costs in the form
of additional vehicle costs were not claimed in the First Adjudication
Determination. However, the vehicle thickening costs are for light vehicles used
by the thickened personnel in the thickening costs claim. Accordingly, the light
vehicles thickening claim is inextricably related to, and reliant on, the success of
the thickening claim for additional personnel. The Adjudicator rejected thickening
costs for additional personnel on the basis GE-Elecnor failed to provide sufficient
evidence to substantiate a connection between the alleged delay and the additional
personnel thickened costs. If the vehicle costs been included in the same claim,
such claim would necessarily have failed by reason of the failure to substantiate
the necessary link with the additional personnel claimed. Accordingly, the claim
for vehicle costs necessarily would entail re-agitation of the personnel costs claim
and thus constitute an impermissible re-agitation of the claim for thickening costs
in respect of which the Adjudicator had already discharge the statutory function in
rejecting the claim.
252 This conclusion does not, of course, preclude GE-Elecnor from pursuing
thickening claims in arbitration.
Notice of Arbitration
253 The issue of the notice of arbitration and its contents does not, in my view,
impact on my conclusions or fetter GE-Elecnor in the manner in which it brought
its payment claims and adjudication applications.
254 I reach this conclusion by reason of s 32 of the Act. That provision protects
the contractual rights of parties. Relevantly in this case, that includes the right to
arbitrate disputes which is provided for by the contract. The protections provided
for by s 32 are broad. Section 32 provides that nothing done for the purposes of
Part 3 affects any civil proceedings other than requiring a court or tribunal to allow
for amounts paid to a party in making an order or award. It protects the rights a
party may have under Part 2 (that is, the part providing for entitlements to claim
progress payments) in respect of the contract. Consequently, use of the legislative
provisions for recovering progress payments does not affect a party’s rights to
claim entitlements in subsequent civil litigation. Equally, the existence of an
entitlement to make claims in arbitration or litigation or the commencement of
such does not preclude a party’s entitlement to claim progress payments under
Part 2 of the Act.
Conclusion
255 For the reasons expressed above, I do not consider delay claims referable to
EOT 001 and EOT 002 are properly characterised as a singular claim nor that the
contract requires the inclusion of all components of such delay claim in one only
progress payment claim. The failure to include all aspects of both in one payment
claim is not relevantly an abuse of the processes of the Act.
-- 53 of 54 --
[2024] SASC 108 Stein J
50
256 This is not a case in which GE-Elecnor has sought to proffer the prolongation
and procurement premium claim on one basis and then re-agitate them on a
different basis. It is also not a case in which GE-Elecnor sought to get a better
outcome in the Second Adjudication Determination than it obtained in the First
Adjudication Determination nor is it seeking to achieve a better outcome in the
Third Adjudication Application insofar as it relates to procurement premium
claims.
257 Given my conclusions above, I dismiss the application and decline to grant
relief insofar as the application related to the Second Adjudication Determination.
The injunctive orders made in relation to the Second Adjudication Determination
should be lifted.
258 However, I accept that the Court has the power to grant orders in relation to
the thickening costs claim aspect of the Third Adjudication Application based on
the decisions to which I have referred above. I do not accept GE-Elecnor’s
submission that any orders should await the outcome of the Third Adjudication
Application for the same reason Hammerschlag J rejected such a contention in
Cadence.210 On the basis of decisions including Dualcorp211 and Cadence,212 the
aspect of the payment claim relating to the thickening costs is invalid and
consequently the adjudicator will lack jurisdiction to address it.
259 Goyder accepts the invalid part of the Third Payment Claim can be severed
but submitted that any Third Adjudication Application is foredoomed because of
Goyder’s claim for delay liquidated damages. During submissions, GE-Elecnor’s
counsel accepted the quantum of liquidated damages determined in the Second
Adjudication Determination. However, GE-Elecnor’s counsel did not expressly
address Goyder’s submission concerning the impact of the liquidated damages
claim in the context of any orders which may be made concerning the Third
Adjudication Application. I am not in a position to form a view whether the Third
Adjudication Application is foredoomed in its entirety such that I should make
orders in relation to the Third Adjudication Application in its entirety.
Consequently, I propose to make orders addressing only the aspect of the Third
Payment Claim and Third Adjudication Application which relates to thickening
costs claims.
Orders
260 I will hear the parties in relation to the orders to be made.
261 I direct the parties to confer with a view to providing agreed draft minutes of
order or, failing agreement, to provide draft minutes of order in the terms proposed
by each party to give effect to these reasons.
210 [2009] NSWSC 635 at [57]-[60].
211 [2009] NSWCA 69; (2009) 74 NSWLR 190
212 [2009] NSWSC 635.
-- 54 of 54 --