GROUP KINETICA PTY LTD [2024] SADC 17
Applicant: GROUP KINETICA PTY LTD Counsel: MR P ADAMS - Solicitor: MINTER ELLISON
Respondents: SANGONG HOMES PTY LTD & XIAOSHAN SUN Counsel: MR T RICE - Solicitor:
XIAO LAWYERS
Hearing Date/s: 17/01/2024, 18/01/2024
File No/s: CIV-23-005401
B
DISTRICT COURT OF SOUTH AUSTRALIA
(Civil: Interlocutory Application)
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply
to this judgment. The onus remains on any person using material in the judgment to ensure that the intended use of that material does not breach
any such order or provision. Further enquiries may be directed to the Registry of the Court in which it was generated.
GROUP KINETICA PTY LTD v SANGONG HOMES PTY LTD
& ANOR
[2024] SADC 17
Judgment of her Honour Judge Thomas
21 February 2024
PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS
- SECURITY FOR COSTS
PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS
- DETENTION, INSPECTION AND PRESERVATION - FREEZING ORDERS
The applicant company instituted proceedings against the first respondent builder and its current
director, the second respondent, concerning delays in the completion of a residential development.
The claims against the director were limited to his alleged liability under a standstill agreement made
to avoid litigation over the builder’s alleged failure to complete the works. The Court was required
to determine two interlocutory applications that became entwined as the proceedings evolved.
The applicant sought freezing orders against only the second respondent restraining him from dealing
with his and the first respondent’s assets, relying on alleged threats to flee the jurisdiction and sell
up and an advertisement for sale of real property owned by the director.
Affidavit evidence filed in support of an unrelated application led the respondents to make
application for security for costs up to the first day of trial in the amount of $75,000 under s 1335(1)
of the Corporations Act 2001 (Cth).
The respondents relied on inferences sought to be drawn from limited evidence as to the company’s
assets and liabilities given it is no longer trading to establish the threshold requirement that there is
“reason to believe” the company will be unable to pay the costs of the respondents if their defences
are successful.
-- 1 of 28 --
Held, dismissing both applications and making no order as to costs.
1. On an evaluative assessment of the limited evidence before the Court, the respondents have
failed to establish the threshold requirement for an order for security for costs under s 1335(1)
of the Corporations Act.
2. Satisfaction of the threshold requirement that there is reason to believe the ‘plaintiff’ will be
unable to pay the costs of the ‘defendant’ if successful requires more than satisfaction that
there is a risk that this is so.
3. The respondents carried the onus in establishing the threshold requirement. Accordingly, the
applicant had no obligation to respond to a request for financial information or prove its
financial capacity to meet an adverse costs order. Its failure to do so was not relevant or of
assistance in reaching a conclusion as to whether the threshold requirement was satisfied in
the absence of other evidence casting doubt or giving rise to a concern about the financial
capacity of the applicant.
2. The applicant has not established that there is a real risk, absent the making of a freezing order
against the second respondent director, of any prospective judgment going wholly or partly
unsatisfied because the prospective judgment debtor might abscond or dissipate his assets.
4. The alleged threats to flee the jurisdiction were not made by, or with the knowledge of, the
second respondent director. There is no evidence of any conduct by the second respondent
director giving rise to any real risk of asset dissipation.
6. There should be a departure from the usual order that costs follow the event. Each side’s
success in defending the other side’s application is effectively neutralised by the dismissal of
their own application. There was considerable overlap in the issues and evidence considered
in determining both applications.
Australian Competition and Consumer Act 2010 (Cth), Australian Consumer Law sch 2, s 18;
Corporations Act 2001 (Cth) s 1335(1); Misrepresentation Act 1972 (SA) s 7; Uniform Civil Rules
2020 (SA) r 112, r 115, r 117, referred to.
Brentwood Village Ltd (in liq) v Terrigal Grosvenor Lodge Pty Ltd [2014] FCA 1203; Cardile v LED
Builders Pty Ltd (1999) 198 CLR 380; Deputy Commissioner of Deputy Commissioner of Taxation
v Hua Wang Bank Berhad (2010) 273 ALR 194 ; Jackson v Sterling Industries Ltd (1987) 162 CLR
612; Mannix Electrical Pty Ltd v Belport Pty Ltd (2019) 134 SASR 438; McEntee v SJ Berry Pty Ltd
[2024] SADC 8; National Australia Bank Ltd v Bond Brewing Holdings Ltd (1990) 169 CLR 271;
Patterson v BTR Engineering (Aust) Ltd (1989) 18 NSWLR 319; Seeley International Pty Ltd v
Millenium Electronics Pty Ltd [2020] SASC 205; Third Chandris Shipping Corporation v Unimarine
SA [1979] QB 645; Yadlamalka Land Pty Ltd v Ragless [2018] SASC 131, considered.
-- 2 of 28 --
GROUP KINETICA PTY LTD v SANGONG HOMES PTY LTD & ANOR
[2024] SADC 17
Civil
Introduction
1 This judgment concerns two interlocutory applications. The first is the
Respondents’ application for security for costs that was heard on 17 and
18 January 2024. The second concerns the Applicant’s application for freezing
orders against the Second Respondent, Mr Xiaoshan Sun (Mr Sun Junior), that
was part-heard on 4 August 2023 pending the Applicant considering whether it
would amend its application and seek relief directly against the First Respondent
builder (the Builder). The Applicant chose not to amend, and the application was
adjourned pending a private mediation and ongoing settlement negotiations. These
negotiations were ultimately unsuccessful, and on 23 January 2024 the parties
requested the Court rule on the Applicant’s application for freezing orders against
Mr Sun Junior.
Conclusion
2 I dismiss the Respondents’ application for security for costs.
3 I dismiss the Applicant’s application for freezing orders against Mr Sun
Junior.
4 I order the parties bear their own costs of and incidental to these unsuccessful
applications. There should be a departure from the usual order that costs follow
the event in this case since each side’s success in defending the other side’s
application is effectively neutralised by the dismissal of their own application in
circumstances where similar time and resources were taken up in dealing with each
application and there was considerable overlap in the issues and evidence
considered in determining both applications.
5 My reasons follow.
Background
6 This proceeding concerns a claim1 by the Applicant owner (the Company)
primarily for losses caused by the delay of the Builder in completing domestic
building works on a house (Residence 2) known as Unit 1 on land known as
23A Ferguson Avenue, Myrtle Bank (the Land).2
1 Claim – Revision 1 (FDN 26). At the time of hearing these applications the Applicant had not filed its
current Claim - Revision 2 (FDN 66) that was filed on 8 February 2024.
2 CT 6217/501.
-- 3 of 28 --
[2024] SADC 17
2
7 The Applicant relies on causes of action in contract, in tort for negligence,
misleading or deceptive conduct in contravention of s 18 of the Australian
Consumer Law3 and s 7 of the Misrepresentation Act 1972 (SA). The Respondents
deny the Company is entitled to the relief sought or any at all.4
8 The legal and factual disputes are numerous and complex.
9 Residence 2 is one of three residential lots on the Land.5 The Land was
purchased by the Company for the purpose of development by the construction of
three houses. Residence 1 was built on a second lot owned and sold by the
Company in September 2023. Until sold, it was the residence of the Company’s
sole director, Mr Omid Rad (Mr Rad). Residence 3 is built on a third lot on the
Land and was sold by the Company in November 2020 to Mr Park, who is not a
party to this proceeding. Mr Park separately contracted with the Builder for the
construction of Residence 3 on his lot.
10 The Second Respondent, Mr Sun Junior, is currently the sole director of the
Builder, appointed on 10 February 2021. A previous director and secretary of the
Builder, Mr Mingchuan Deng (Mr Deng), resigned on 24 October 2022. Between
10 February 2021 and 24 October 2022, both Mr Sun Junior and Mr Deng were
directors of the Builder company. 6
11 The Builder company was incorporated on 22 January 2016.7
12 The shareholders of the Builder company are Mr Zengmin Sun (Mr Sun
Senior) and Tao Zhou, following a change of members notified to ASIC on
9 February 2021, about the time Mr Sun Junior was appointed a director. Details
of these shareholding changes were not in evidence. Mr Sun Senior is the father
of Mr Sun Junior.8
13 There is a dearth of evidence about the circumstances in which Mr Sun Junior
and Mr Sun Senior became involved in the Builder company and Mr Deng
withdrew.
14 The Company relies on two alleged written agreements for its claims in
contract.
3 Comprising Schedule 2 of the Competition and Consumer Act 2010 (Cth).
4 Defence - Revision 1 (FDN 42). At the time of the substantive hearing of the Applicant’s application
for freezing orders against Mr Sun Junior on 4 August 2023, the Respondents had not yet filed their then
current Defence (FDN 33). A revised defence was filed on 1 November 2023 (FDN 42) that will be
superseded by a further defence in response to Claim - Revision 2 (FDN 66) filed on 8 February 2024.
5 CT 6216/703.
6 Exhibit OFR-5.1 to the Second Affidavit of Omid Farshid Rad (Rad) made on 10 July 2023 (FDN 22)
(the First Rad Affidavit). The short description given to each affidavit is based on its order by FDN,
not its title. This affidavit was filed twice as FDN 20 and FDN 22.
7 Ibid.
8 Seventh Affidavit of Ben Michael D’Andrea made on 15 January 2024 (FDN 59) (the Seventh
D’Andrea Affidavit) at [50].
-- 4 of 28 --
[2024] SADC 17
3
15 The form and terms of the first are not disputed. It is in writing in the form
of a standard MBA contract dated 18 December 2020 (the Contract)9 for a fixed
price of $402,500 and a contract completion date of 31 August 2021. It was
executed on 19 December 2020, well before Mr Sun Junior became a director of
the Builder.
16 The Company alleges delay in completion of Residence 2. The Respondents
admit practical completion of Residence 2 has not been achieved but say the
Builder is entitled to extensions of time for some 27 alleged events of delay
occurring up until November 2022 and say further, since at least 17 April 2023,
the Builder has been entitled to stop works due to non-payment by the Company.
17 The Company alleges the second agreement (the September Agreement)10
was made in September 2022 between the parties and Mr Park, following delay in
the completion of Residences 2 and 3, to avoid litigation and encourage the Builder
to complete the works for Residences 2 and 3. This agreement allegedly provides
for a new completion date for Residence 2 of 20 December 2022, the appointment
of a building inspector (Mr Edgar) and otherwise preserves the Company’s rights
under the Contract against the Builder.
18 The Company alleges the Builder knew the following matters at the time it
contracted with the Company.
• On the completion of Residence 2, the Company intended to lease
Residence 1 and Mr Rad would then live in Residence 2.
• The Contract for Residence 2 was not subject to finance because the
Company intended to finance its construction from its own resources,
including borrowings made against the security of Residence 1.
19 The Company claims that as a result of the delay in completion of Residence
2, Mr Rad has been unable to move out of Residence 1 into Residence 2 and lease
Residence 1. The Company claims it has suffered losses in the nature of additional
interest on its bank finance for the development, loss of rent for Residence 1, a
GST liability on the sale of Residence 1 and loss of a capital gain on Residence 1,
as well as a miscellany of other minor losses. The Company further claims for
wrongly charged variation claims and failures to credit variations where there were
alleged savings11 and for rectification of damage caused by the Builder to the
guttering and fencing of Residence 1, which has now been sold.12
9 Exhibit OFR-1 to the First Rad Affidavit.
10 Exhibit OFR-5 to the First Rad Affidavit.
11 $23,618.75 ex GST.
12 $12,000 ex GST.
-- 5 of 28 --
[2024] SADC 17
4
20 The Company further claims it is entitled under the terms of the September
Agreement to have any legal fees incurred since its date of execution by reason of
the Builder’s breaches of the September Agreement (including the costs of
litigation) paid by the Builder.
21 At the time of execution of the September Agreement, both Mr Deng and
Mr Sun Junior were directors of the Builder company.
22 The Company alleges that Mr Sun Junior is named as party in his own right
to the September Agreement and executed it twice, both as a director of the Builder
and for himself. Damages are claimed against Mr Sun Junior for breaches of the
September Agreement and for misleading or deceptive conduct under the
Australian Consumer Law and/or the Misrepresentation Act.
23 The Respondents say in their defence13 that neither the Company nor Mr Sun
Junior were parties to the September Agreement, and it confers no rights or
obligations on either the Company or Mr Sun Junior.
Status of Completion of Works
24 Self-evidently, the Residence 2 building works are incomplete.
25 There is substantive dispute over alleged defects in the works and whether
the works have reached 70% completion by reference to the seventh stage of
completion in the Contract: that is, substantial completion of the second-fix
carpentry (including built-in cupboards) and lock-up (Lock-up).14
26 The Company relies on the written evidence of Mr Edgar, a building
consultant and licensed building work contractor and supervisor, as to the status of
completion of Residence 2.15
27 Mr Edgar first inspected Residence 2 on 28 June 2022 on behalf of the
Company and identified defects he describes in his written evidence as ‘numerous,
and systematic major defects’.16 Thereafter, Mr Edgar regularly inspected
Residence 2 and, from time to time until October 2022, provided the Builder with
written defect lists identifying rectification works required to be undertaken.17
28 From September 2022, Mr Edgar also monitored progress of the works for
Residences 1 and 2. Mr Edgar inspected both Residences on 26 November 2022
to assess the rectification works and progress of the build in line with the revised
completion date of 20 December 2022 specified in the September Agreement. He
reported18 slower than expected progress, noting the schedule for completion of the
13 Defence - Revision 1 (FDN 42).
14 Item J, Part 4 – Schedule 4 of the Contract comprising Exhibit OFR-1 to the First Rad Affidavit.
15 Affidavits of Christopher John Edgar made on 11 July 2023 (FDN 16) (the First Edgar Affidavit) and
15 January 2024 (FDN 58) (the Third Edgar Affidavit).
16 First Edgar Affidavit at [6].
17 Ibid at [7]-10].
18 Exhibit CJE-4 to the First Edgar Affidavit.
-- 6 of 28 --
[2024] SADC 17
5
works for both residences was 29 days behind but there were only 19 business days
until the Christmas shutdown. He also reported on defects discussed at inspection
and identified incomplete works. Mr Edgar identified the general nature of the
defects and incomplete works as at the completion date in his written evidence.19
29 Between December 2022 and March 2023, Mr Edgar was refused access to
the site by the Respondents. There have been ongoing difficulties with site access
since the dispute became contentious and solicitors became involved. Based on his
then most recent inspection of Residence 2 in April 2023, Mr Edgar estimated in
July 2023 that it could be brought to completion within a period of 8 to 10 weeks.20
30 There is no explanation in the evidence for the change in his opinion from
29 days for two residence and 8 to 10 weeks for only Residence 2.
31 Mr Edgar inspected Residence 2 again on 21 December 2023. Following this
inspection, Mr Edgar confirmed in his written evidence his view that the works
had still not reached Lock-up because of the absence of a roller door, an
inappropriate lock on the double doors leading from the garage to the house and
unremedied defects in the works.21
32 The Respondents’ building expert, Mr Begg, was of the opposite view
following his inspection on the same day. Little weight should be attached to
Mr Begg’s opinions. His report22 does not provide any reasons for his opinion, nor
address any of the concerns raised by Mr Edgar. The attached photographs show
the absence of the garage roller door and are generally confirmatory of the
incomplete works identified by Mr Edgar.
33 Resolution of dispute over the alleged defects in the completed works, the
precise status of the completed works, and whether the works had reached the
seventh milestone for payment are issues for trial. For present purposes, it is
sufficient to identify that subject to the alleged defects (including the absence of
the garage roller door), the footings, external walls for both storeys, the roof cover
and internal linings, second-fix carpentry, doors and windows are substantially
complete and the dispute concerns the 70% completion milestone. That is, the
stages up to Lock-up are completed, save for defects.
Termination of Contract and September Agreement
34 By its solicitors’ letter dated 18 December 2023, the Company gave formal
notice of termination of the Contract and the September Agreement by reason of
19 Op cit [13].
20 First Edgar Affidavit at [20].
21 Third Edgar Affidavit.
22 Exhibit JX-1 to Affidavit of Jia Xiao (Xiao) made on 16 January 2024 (FDN 63) (the Sixth Xiao
Affidavit).
-- 7 of 28 --
[2024] SADC 17
6
the Respondents’ alleged ongoing defaults in the performance of the works,
ongoing breaches of contract and repudiatory conduct.23
Costs to Complete the Works
35 The quantum of the likely costs to complete construction of Residence 2 by
a new builder has not been ascertained and will be the subject of evidence at trial.
Although no longer contractually relevant, some indications of the likely quantum
can be inferred from the outstanding 30% of the Contract price ($120,750).
Bearing in mind the escalation of building costs since the Contract was executed,
it should be accepted that the costs to complete Residence 2 will be significantly
more than the unpaid balance of the Contract price. How much more is uncertain.
Application for Security for Costs
Basis of Application
36 By application dated 6 December 2023,24 the Respondents seek security for
their costs up to the first day of trial in the amount of $75,000 and that the
proceeding be stayed pending payment of that security into Court.
37 Their application is brought under s 1335(1) of the Corporations Act 2001
(Cth) and r 115.1(1)(d) of the Uniform Civil Rules 2020 (SA) (UCR).25
Relevant Legal Principles
38 Section 1335(1) of the Corporations Act provides:
Where a corporation is plaintiff in an action or other legal proceeding, the court having
jurisdiction in the matter may, if it appears by credible testimony that there is reason to
believe that the corporation will be unable to pay the costs of the defendant if successful in
his, her or its defence, require sufficient security to be given for those costs and stay all
proceedings until the security is given.
39 The relevant legal principles are well established and uncontentious.
40 Both parties rely on the judgment of Justice Doyle in Mannix Electrical Pty
Ltd v Belport Pty Ltd26 as a contemporary and convenient summary of the relevant
principles.27 It is therefore unnecessary to restate the law at length save to reiterate
four matters pertinent to the issues in this case.
23 Exhibit JX-3 to the Affidavit of Xiao made on 11 January 2024 (FDN 57) (the Fifth Xiao Affidavit).
24 FDN 49 [1]-[2].
25 That is, the Court may order that an applicant in an action provide security for costs if the order is
authorised by statute.
26 (2019) 134 SASR 438.
27 Ibid [11]-[17] in particular.
-- 8 of 28 --
[2024] SADC 17
7
41 First, that the discretion to order security for costs under s 1335(1) is
conditioned upon satisfaction of the threshold requirement that it appears by
credible testimony that there is reason to believe that the plaintiff corporation will
be unable to pay the defendant’s costs if it is successful in its defence.
42 Secondly, satisfaction of the threshold requirement requires more than
satisfaction of a risk that the plaintiff corporation will be unable to pay the costs of
the defendant if successful.
43 Thirdly, the Court’s assessment of the threshold requirement will necessarily
be preliminary by reason of the nature and timing of the application.
44 Fourthly, the onus of establishing the threshold requirement (that is, the onus
of adducing “credible testimony” and establishing that the requisite “reason to
believe” exists) is the defendant’s and remains on the defendant throughout the
application.
The Evidence
45 In support of their application for security for costs the Respondents rely on
four affidavits sworn by their solicitor, Mr Xiao.28
46 In opposing this application, the Company relies on two affidavits sworn by
its director, Mr Rad;29 three by its solicitor, Mr D’Andrea;30 and two by the building
inspector, Mr Edgar.31
47 In submissions, the Respondents refer to certain parts of some of the affidavit
evidence adduced by the Company as well as an earlier affidavit sworn by
Mr Rad32 in support of the Company’s application for an urgent assessment of the
Company’s losses following the entry of default judgment.33
Mr Rad’s Evidence
48 The Respondents submit Mr Rad’s earlier evidence as to the financial
position of the Company contradicts his later evidence and comprises assertions
unsupported by available objective evidence.
28 Affidavits of Xiao made on 13 July 2023 (FDN 24) (the Third Xiao Affidavit) and 1 December 2023
(FDN 51) (the Fourth Xiao Affidavit) together with the Fifth and Sixth Xiao Affidavits referred to
above. The earlier affidavits of Xiao filed in this proceeding do not concern this application.
29 Affidavits of Rad made on 1 August 2023 (FDN 27) (the Second Rad Affidavit) and 20 December
2023 (FDN 53) (the Third Rad Affidavit).
30 Affidavits of Ben Michael D’Andrea made on 17 November 2023 (FDN 46) (the Fifth D’Andrea
Affidavit); 5 December 2023 (FDN 48) (the Sixth D’Andrea Affidavit); and the Seventh D’Andrea
Affidavit.
31 Affidavits of Christopher John Edgar made on 11 July 2023 (FDN 16) (the First Edgar Affidavit) and
15 January 2024 (FDN 58) (the Third Edgar Affidavit).
32 First Rad Affidavit.
33 This application was superseded by default judgment being set aside by consent on 13 July 2023.
-- 9 of 28 --
[2024] SADC 17
8
49 In the First Rad Affidavit, Mr Rad deposes:34
For the reasons set out above, the applicant requires urgent assessment of its losses so that
it can enforce judgment before it is forced into insolvency.
50 The reasons set out in the previous paragraphs are Mr Rad’s evidence as to
the consequences of the Builder’s failure to complete Residence 2. They
relevantly include his evidence that the delay in completing the works has led to
the depletion of the Company’s finances by the ongoing accrual of interest on
borrowings against Residence 1 to fund the construction of Residence 2 at
increased interest rates and being forced to sell Residence 1 to mitigate the interest
incurred on finance.35
51 Mr Rad further deposes to the personal consequences of the delay in
completion of the works including relevantly:36
By reason of the financial consequences for my company, I will be unable to engage in
business again…
52 The Respondents refer to Mr Rad being quoted in a newspaper article
published on 9 December 2023 as losing his house and “basically exhausted
everything, including most of my personal and financial resources, in order to keep
the project going”.37
53 By contrast, in his Third Affidavit, Mr Rad deposes that the Company’s total
assets exceed its liabilities by approximately $985,000.38
54 The Respondents submit the positions deposed to in Mr Rad’s evidence are
‘strikingly inconsistent’, unexplained and raise real questions as to the credibility
of Mr Rad. This overstates matters somewhat.
55 First, the reference to the Company ‘being forced into insolvency’ and the
newspaper quote in context are emotive and carry little weight in assessing the
Company’s incapacity to meet an adverse costs order. The matters relied on in the
preceding paragraphs of Mr Rad’s earlier written evidence are relevant
considerations but dated given the sale of Residence 1 in September 2023 and more
recent documentary evidence of the Company’s financial position.
56 Secondly, Mr Rad’s conclusion as to the Company’s net assets is expressly
stated to be by reason of the matters set out in the preceding paragraphs and self-
evidently only current then as at December 2023. His conclusion is not persuasive
evidence in itself. It is for this Court to draw the necessary inferences as to the
34 [43]. Emphasis supplied.
35 Ibid [34]-[40].
36 Ibid [42(b)]. Emphasis supplied.
37 Exhibit JX-9 to Fifth Xiao Affidavit.
38 [11].
-- 10 of 28 --
[2024] SADC 17
9
Company’s net assets from an assessment of the referenced evidence as updated
by the further evidence relied on by both parties in January 2023.
57 In the circumstances, the alleged contradiction between Mr Rad’s earlier and
later evidence does not justify the Respondents’ application to cross-examine him
as to the financial position of the Company, an application I ultimately refused
during the course of the hearing of the Respondents’ application for security for
costs.
The Company’s Financial Position
Approach to Assessment
58 Mr Rad is the sole director and shareholder of the Company. The Company
was registered on 3 April 2000. Its paid-up capital is nominal and is not relied on
as a basis for reasonably believing the Company will be unable to meet an adverse
costs order.
59 The Company is no longer trading, incurring no further liabilities except
interest,39 plainly a relevant consideration in assessing whether the threshold
requirement has been met. The Company alleges it is no longer trading in
consequence of the Respondents’ wrongful conduct, a matter that would be
relevant to the exercise of the Court’s discretion if I were to find the threshold
requirement satisfied.
60 The assessment of the Company’s incapacity to meet an adverse costs order
in this case therefore turns on an analysis of its assets and liabilities and ongoing
expenses based on the limited and preliminary nature of the evidence before the
Court.
61 In support of the Respondents’ position, Mr Rice of counsel prepared a
summary (Respondents’ Summary) of the Company’s assets and liabilities
showing negative net assets of $63,000 based on a 12-month timeframe. Whilst a
helpful and convenient way of approaching the required analysis, the outcome
involves a series of unfavourable inferences against the Company that, ultimately,
I do not find persuasive and ground the requisite reason to believe that must be
proved.
Net Equity in Residence 2
62 By the hearing of this application in January 2024, the central dispute
between the parties concerned whether there is sufficient net equity in Residence 2
from which to pay the Respondents’ costs if successful in their defence, having
regard to the Company’s other assets and liabilities, ongoing expenses and the
incomplete construction of Residence 2.
39 T54.33-.38.
-- 11 of 28 --
[2024] SADC 17
10
63 Having terminated the Contract in December 2023, the Company’s intention
is to retain a new builder to complete the works in the next six months once tenders
have been received, using funds held in a term deposit to fund the building costs.40
64 The Respondents submit the Company has not demonstrated it has the
resources to complete Residence 2 given it has insufficient equity in it of some
$135,000 by its calculation41 by reason of its incomplete state and no other
resources to realise its market value. Further, its value ‘as is incomplete’ is
significantly below the ‘as if complete’ valuations.
65 The Company correctly submits that the Respondents carry the onus in this
application. It is not for the Company to persuade the Court of its financial
capacity. To the contrary, the Respondents must by credible testimony demonstrate
the Company’s financial incapacity to meet an adverse costs order. In any event,
the Company further submits there is no basis on the evidence before the Court for
reaching the conclusions contended for by the Respondents.
66 Indisputably, the Company’s principal asset is now Residence 2.42
Residence 1 was sold on 28 September 2023 for $1.41 million43 and the sale
proceeds used to discharge a mortgage over Residence 1 and reduce the
Company’s bank liabilities by approximately $1.15 million.44
67 Residence 2 is subject to a registered mortgage in favour of Australia & New
Zealand Banking Group Ltd (ANZ) for two business loans. The total of the
Company’s indebtedness to ANZ as of 14 January 2024 was $703,796.69.45 The
Company holds a term deposit of $163,343.81 as of 9 January 2024 as collateral
security for the business loans.46
68 Nonetheless, the Respondents submit it should be inferred from the ANZ’s
requirement for the term deposit to be held as collateral security for the business
loans, that Residence 2 is not sufficient security in itself. These are in my view
unsafe inferences to draw when nothing further is known about the terms of the
Company’s banking arrangements and why and for how long the collateral security
is required. On the evidence, any inferences about the insufficiency of Residence 2
as security for the business loans shed no light on its value if sold ‘as is
incomplete’.
69 Having regard to the onus the Respondents carry on this application, the
absence of evidence about this does not advance the Respondents’ position.
40 Seventh D’Andrea Affidavit [10] and [11].
41 Respondents’ Summary.
42 Exhibits JX-2 and JX-3 to the Fourth Xiao Affidavit.
43 Exhibit BMD-27 to the Seventh D’Andrea Affidavit.
44 Third Rad Affidavit at [10].
45 Exhibit BMD-29 to the Seventh D’Andrea Affidavit. That is, two business loans plus debit balances for
a commercial credit card and a bank account.
46 Seventh D’Andrea Affidavit [10] and Exhibit BMD-30.
-- 12 of 28 --
[2024] SADC 17
11
70 Since March 2023, interest has been capitalised on the business loans at the
rate of approximately $5,000 per month.47 This equates to increased bank liabilities
in 12 months’ time of $60,000. It may be inferred that interest will continue to be
capitalised as it has been since March 2023 in the short to medium term. In the
absence of any further evidence as to the terms of the Company’s banking
arrangements, there is no basis for inferring that the Company’s banker is not
prepared to continue to be supportive or when and why that position might change.
71 The market value of Residence 2 in its incomplete state is contentious.
72 The Company relies on two formal valuations, each prepared by different
licensed valuers of Residence 2 10 months apart. The first was prepared by Herron
Todd White (HTW Valuation) as at 28 February 202348 and the second by Opteon
(Opteon Valuation) as at 27 December 2023.49
73 The HTW Valuation assessed market value on an ‘as if complete’ basis at
$1.3 million (Land at $650,000 and Improvements at $650,000) with an
unfurnished rental assessment of $850 per week. In the Additional Comments’
section, the valuer notes the incomplete state of the works and notes four key
matters pertinent to this application.
74 The first is obvious. That is, Residence 2 is partly completed, rendering the
dwelling uninhabitable at the date of inspection. Secondly, ‘on advice’, there are
remaining progress payments of $120,750 being 30% of the contract price of
$402,500 (which was the case in February 2023). Thirdly, the contract price is
considered below market construction costs having regard to the significant
escalation in building costs since late 2020 when the contract was signed.
Fourthly, and most relevantly:50
It should be noted that many construction projects which have not been fully established
by owners and sold under adverse sale conditions have achieved prices considerably below
initial land and building costs…
75 The Opteon Valuation (although prepared by a different licensed valuer is in
the same format) assessed market value on an ‘as if complete’ basis 10 months
later at $1.5 million (Land at $600,000 and Improvements at $900,000) with the
same unfurnished rental assessment of $850 per week. The increased market value
reflects updated sales evidence and the market, and specifically the sale of
Residence 1 on 28 September 2023 at $1.41 million described in comparison to
Residence 2 as “Overall considered slightly inferior to the subject property”.51
47 ANZ Bank statement comprising part of Exhibit JX-6 to Fifth Xiao Affidavit.
48 Exhibit OFR-20 to the Third Rad Affidavit.
49 Exhibit JX-7 to the Fifth Xiao Affidavit.
50 Op cit page 13.
51 Op cit page 38.
-- 13 of 28 --
[2024] SADC 17
12
76 The ‘Additional Comments’ section contains some notable observations in
comparison to the HTW Valuation. The first is the reference to the Contract. It
had been terminated by the date of inspection, making the agreed contract price
less relevant given the notorious observation made in the HTW Valuation that
building costs have significantly escalated since the Contract price was struck.
77 The second is the bare statement that the dwelling was approximately 95%
complete at the time of inspection in December 2023, a percentage the Company
disputes and the Respondents acknowledge is overstated. This does not accord
with the advice provided to HTW about 70% of progress payments made and is
not supported by Mr Edgar’s evidence or a comparison of the photographs in each
report that show that only minor further works (installation of bench tops) had been
carried out between valuation inspections.
78 The third comment is emphasised by the Respondents as lending material
support to their submission that both market valuations of Residence 2 are
unreliable given their ‘as if complete’ basis:52
In providing the As If Complete market value, we have deducted an allowance for the
estimated cost to complete the property to a fully established standard. We have also made
a deduction for a profit and risk allowance, which reflects the expected discount a prudent
purchaser would require for buying the property in this incomplete state, allowing for the
effort, time and risk involved in completing the property.
79 There is no further explanation of the amount of the allowance for the
estimated costs to complete or the discount for profit and risk. More specifically,
this explanation as to the basis of valuation is inconsistent with the common sense
qualifications made in the HWT Valuation and unsubstantiated assumption of 95%
completion. For these reasons, I attribute little weight to this statement and
consider the assessed market value in the Opteon Valuation should be approached
on an ‘as if complete’ basis. I accept the increased market value ‘as if complete’
of $1.5 million is otherwise reasonable and reflects updated sales evidence and the
market some 10 months after the HWT Valuation.
80 It follows, as the Respondents submit, the HTW and Opteon Valuations do
not represent the market value of Residence 2 in its current incomplete state. It
should also be accepted that a lesser price would be achieved than the assessed
market value ‘as if complete’ if sold ‘as is incomplete’ and, further, under adverse
sale conditions, a sale price “considerably below initial land and building costs”
would likely be achieved.
81 However, once again the absence of evidence about the magnitude of the risk
of a ‘distressed sale’ (as the Respondents put it) and what price might be achieved
does not assist the Respondents’ position and presents a serious difficulty for the
Respondents in discharging their onus on the threshold requirement. It should be
52 Ibid page 39.
-- 14 of 28 --
[2024] SADC 17
13
emphasised again that it is not sufficient to merely show that there is a risk of such
an outcome.
82 The Respondents’ next submission is that because the term deposit is held as
collateral security, the Court should infer it cannot be used by the Company to pay
another builder to complete the works, contrary to Mr D’Andrea’s evidence on
instructions.53
83 To bolster their position in this regard, the Respondents submit the Court
ought to infer from the amount of the business loans and the term deposit held as
collateral security, that the ANZ Bank is only prepared to lend $540,000 against
its valuation of the (incomplete) property in the order of $675,000 and therefore
not prepared to lend any more to fund completion of the works. This limit was
deduced by deducting the term deposit from the total of the business loans and
assuming an LVR (Loan to Value Ratio) of 80%.54
84 The Respondents’ submissions are speculative. There is no basis for inferring
the applicable LVR or, more importantly, that the ANZ Bank (or for that matter
some other lender) is not prepared to lend any further funds to complete the works
or will not agree to release the term deposit to fund the completion works. There
may be a risk because it is held as “collateral” security on unknown terms, but as
already stated, a risk is not sufficient.
85 The following matters significantly militate against such a risk.
86 First, considerable value will be unlocked on completion of Residence 2
($1.5 million), securing current net bank liabilities of approximately $700,000 plus
accruing interest. Secondly, the amount of the term deposit exceeds the amount to
complete the disputed 30% or more of the works when valued by reference to the
Contract price ($120,750) leaving some $40,000 for escalation before recourse is
needed to any other assets or additional borrowings are required. Again, the
absence of evidence as to the likely costs does not assist the Respondents’ position.
Thirdly, the headroom between the market value when complete and the bank debt
is almost double the Contract Price of $402,500 and sixfold the unpaid Contract
value. These numbers appear sufficient to secure funding for a significant
escalation in the costs to complete.
87 In conclusion, the evidence there is does not support the Respondents’
analysis and submission that the equity in Residence 2 ‘as is incomplete’ is a net
$135,000 and both should be rejected. Nor am I persuaded that the Company’s net
equity in Residence 2 ‘as is incomplete’ limits its capacity to fund completion of
the works by further borrowings because of the insufficient value of Residence 2
or that the Company cannot have recourse to the term deposit on any terms. As
53 Seventh D’Andrea Affidavit [10] and [11].
54 That is $700,000 less $160,000 is $540,000 grossed up on an assumed LVR of 80% to $675,000.
-- 15 of 28 --
[2024] SADC 17
14
I have already said, the absence of evidence on these topics does not support the
Respondents’ position.
Other Assets and Liabilities
88 My conclusions in this regard are fortified by my analysis of the evidence of
the Company’s other assets and liabilities.
89 Mr Rad gave written evidence to the effect that as at 17 December 2023 the
Company has $101,097 cash in a bank account held with the Commonwealth Bank
of Australia that includes the remaining proceeds of sale of Residence 1.55 The
Respondents submit there is no evidence that the Company is the holder of the
bank account because the screenshot from Mr Rad’s mobile phone evidencing the
balance does not show any further detail.56
90 This submission should be rejected. Plainly, there is relevant evidence.
Mr Rad has deposed to it being the Company’s asset twice. The real substance of
the Respondents’ complaint is that the documentary evidence does not confirm
Mr Rad’s evidence that the cash is the Company’s asset. For the purposes of this
interlocutory application, I am prepared to accept Mr Rad’s evidence as truthful.
91 The Company’s only other liquid asset is in the form of a relatively
substantial cryptocurrency portfolio. As at 16 January 2024, the value of the
Company’s portfolio had increased since July 2023 from $141,388 to
$197,785.60.57 These assets are highly volatile and whilst it should be accepted
that the value will fluctuate as it has, that is not a reason to discount the asset as an
important source of funds to meet ongoing liabilities (whether interest, legal or
building costs).
92 The Company is the registered owner of a motor vehicle, a BMW M2 series
coupe (the BMW). The dispute about who owned it was resolved during the
hearing by the Company tendering the registration certificate.58 The Respondents
now accept that the balance of the finance owing on the BMW as at 14 January
2024 was $79,671.91, requiring monthly payments of $1,325.78,59 leaving value
and therefore net equity in the BMW as disputed issues.
93 The Respondents challenge the agreed insured value of $225,000 as not being
evidence of its condition or market value, pointing to the lower purchase price of
$145,000 after dealer charges and tax shown in a purchase order,60 the initial
finance price of $115,000 and depreciation after four years of ownership.
55 Third Rad Affidavit [7.3] and [8.3] and Exhibit OFR-23.
56 Respondents’ Summary.
57 Seventh D’Andrea Affidavit [12] and Exhibit BMD-28.
58 Exhibit A1.
59 $79,671.91 as shown in Exhibit BMD-26 to the Seventh D’Andrea Affidavit.
60 Seventh D’Andrea Affidavit [7] and Exhibit BMD-25.
-- 16 of 28 --
[2024] SADC 17
15
Ultimately, the Respondents submit the evidence shows there is no or negligible
net equity in the BMW.
94 The Company submits there is significant net equity in the BMW on the
evidence and the Respondents have not adduced any evidence to the contrary. It
is said to be a specialist vehicle, as indicated by the low odometer reading and
nominated annual distance to be driven of up to 1,000 km shown in the Enthusiast
Motor Insurance policy.61
95 As to condition, the insurance policy shows it is undamaged, garaged and had
a very low odometer reading as at 14 August 2023 of 1,239 km and a nominated
annual distance to be driven of 1,000 km.62 As to value, whether it is a specialist
vehicle or not does not resolve this question. Whilst the market value of the BMW
is not known, it is reasonable to infer that its value would likely be in the range
between its agreed insured value and the initial finance price and therefore there is
now some net equity in it. Bearing in mind the evidence of its good condition,
there is no evidence to show that it has depreciated materially below its purchase
price of approximately $170,000 including taxes to below the current loan balance.
Again, the absence of evidence of market value does not assist the Respondents’
position in light of the other evidence of considerably higher values.
96 The Company’s liability for unpaid legal fees as at 16 January 2024 was
$138,566.77 including GST after a payment of $40,000 was made in partial
satisfaction of this liability.63 The GST component is, of course, not a net liability.
97 Mr D’Andrea gave important evidence that the Company was not in default
of its arrangements with his firm.64 There is no other evidence of the Company’s
arrangement with its solicitors, by whom or how this payment was made and no
basis for inferring when the Company will need to pay its solicitors and whether
the incurring of future legal fees will prevent the Company from completing the
Residence 2 works as is intended.
98 As to future legal fees, there is no evidence of the terms of the Company’s
solicitors’ retainer before the Court. Whilst it should be accepted that the Company
will incur further significant legal fees, the Respondents’ estimate for a two-week
trial based on Mr Xiao’s estimate for the purposes of the Respondents’ application
for security for costs is at best indicative at this stage of the proceeding.
Failure to Provide Information Requested
99 In the solicitors’ correspondence and throughout the course of argument, the
Respondents repeatedly complained the Company had failed to demonstrate that it
61 Exhibit OFR-21 to the Third Rad Affidavit.
62 Ibid.
63 Seventh D’Andrea Affidavit [16].
64 Ibid [17].
-- 17 of 28 --
[2024] SADC 17
16
has the financial resources to complete the Residence 2 works and failed to provide
clear evidence of the ownership and value of its assets.
100 I respectfully adopt the analysis of Justice Doyle in Mannix65 on this topic. It
must be emphasised that the Company carries no onus in establishing the threshold
requirement. Any failure to provide information requested is only relevant and
assists in reaching a conclusion about the Company’s financial incapacity if there
is other evidence casting doubt or concern on an issue. The Company’s refusal to
proffer information requested by the Respondents must not be used to fill gaps in
the evidence or elevate suspicion and conjecture into evidence by inference. The
Company has no obligation in response to an application for security for costs to
provide a full account of its financial position and fill any evidentiary gaps arising,
particularly where the Respondents could have adduced relevant evidence. Key
examples in this case are the market values of the BMW or Residence 2 ‘as is
incomplete’.
Conclusion as to Threshold Requirement
101 Finally, having regard to all the matters raised by the Respondents, I am not
persuaded on the evidence that there is reason to believe that the Company will be
unable to pay the costs of the Respondents if they are successful in their defences.
Exercise of the Discretion
102 Given my conclusion that the threshold requirement has not been satisfied, it
is unnecessary for me to consider how the Court’s discretion to order security for
costs might have been exercised if I had found otherwise.
Quantum of Security Sought
103 Whilst it is strictly unnecessary to consider whether the amount of security
sought is appropriate, quantum is a relevant consideration as to the question of the
Company’s incapacity to meet an adverse costs order.
104 The starting point is that the $75,000 sought as security is not an onerous
liability by comparison to the magnitude of the Company’s assets and liabilities.
105 The amount of security sought is based on an estimate of costs prepared by
the Respondents’ solicitor Mr Xiao, an experienced litigation solicitor. 66 Mr Xiao
estimates the total costs to complete steps in the proceeding from the date of his
letter requesting security for costs up until the first day of trial will be $90,880 ex
GST. His estimate is made on the basis of the time to be taken by counsel and a
principal solicitor at hourly rates of $300 and $530 ex GST respectively. The
Respondents claim $75,000 in recognition that solicitors’ fees will be taxed at the
scale rate.
65 Op cit [50]-56].
66 Fourth Xiao Affidavit [18]-21].
-- 18 of 28 --
[2024] SADC 17
17
106 Having regard to the estimated time to complete the tasks identified, who
they will be done by and the hourly rates, I consider insufficient reduction has been
made for payment of taxed costs on the standard costs basis in accordance with the
Higher Courts Costs Scale. I would further reduce Mr Xiao’s estimate made on a
time costing basis on account of the notorious difference between time-charged
and scale costs, the considerably lower hourly rates for solicitor’s attendances
involving skill and those not involving skill, to allow some steps (such as
discovery) to be undertaken by a clerk at a lower rate again, the excessive time
estimated for a solicitor’s preparation for trial and consequent unnecessary
duplication with counsel in carrying out this work.
107 In my view, a further reduction of $10,000 ex GST to $65,000 ex GST would
be required if I had determined an order for security for costs should be made.
Conclusion
108 For these reasons, I dismiss the Respondents’ application for security for
costs.
Application for Freezing Order
Procedural History of the Application
109 The Company’s application for freezing orders against Mr Sun Junior as a
prospective judgment debtor was filed on 11 July 2023.67
110 The orders sought are that Mr Sun Junior not remove from Australia or in
any way dispose of, deal with or diminish the value of any of his assets in Australia
up to the value of AUD$1 million, and in particular two properties (one at Vale
Park and the other at Evanston Gardens) and the assets of his business the Builder
company. No relief is sought against the First Respondent Builder.
111 As the Respondents (correctly) point out, Mr Sun Junior is not a shareholder
of the Builder company and its assets are not his.
112 The application was opposed, and substantive argument proceeded on
4 August 2023. The Company relied on then filed written evidence of Mr Rad68,
Mr Edgar69 and Mr D’Andrea.70 The Respondents relied on the written evidence of
Mr Xiao.71 Both parties relied on written submissions.72
113 During the course of argument on 4 August 2023, the basis of the Company’s
application ostensibly changed, and its counsel foreshadowed making an oral
application to amend the application to seek a freezing order directly against the
67 FDN 21.
68 The First and Second Rad Affidavits.
69 The First and Second Edgar Affidavits.
70 The Affidavit of Mr D’Andrea made on 2 August 2023 (FDN 29) (the Third D’Andrea Affidavit).
71 Affidavit of Xiao made on 6 July 2023 (FDN 14) (the Second Xiao Affidavit) and the Third Xiao
Affidavit.
72 FDN 30 and FDN 32.
-- 19 of 28 --
[2024] SADC 17
18
Builder as well as relying on the principle in Cardile v LED Builders Pty Ltd73 as
the foundation for the orders sought against Mr Sun Junior as concerns the
Builder’s assets.74
114 The application was adjourned part-heard by agreement between the parties
to allow the Company to consider and propose its amendment and provide the
Respondents with an opportunity to put forward any further affidavit evidence to
meet the change in the Company’s position.75 To preserve the status quo, Mr Sun
Junior gave an undertaking not to deal with the Vale Park property without first
giving two business days’ written notice.76
115 Although the Company ultimately chose not to amend its application, an
affidavit of Mr Sun Junior (the Sun Affidavit) was filed in accordance with the
Court’s directions. 77 The adjourned application was next mentioned on 23 August
2023 but not ultimately pressed pending a private mediation and ongoing
settlement discussions. On 23 January 2024, the parties requested the Court rule
on the Applicant’s application for freezing and ancillary orders against Mr Sun
Junior on the basis the parties agreed to the tender of the following further written
evidence: the Sun Affidavit and the Fifth and Sixth D’Andrea Affidavits.
Relevant Legal Principles
116 In support of its application, the Company relies upon the Court’s power to
make freezing and ancillary orders as expressly provided in rr 112.14 and 112.15
of the UCR:
…for the purpose of preventing the frustration or inhibition of the Court’s process by
seeking to meet a danger that a judgment or prospective judgment of the Court will be
wholly or partially unsatisfied.78
117 Rule 112.17 sets out the requirements for freezing and ancillary orders
against a judgment debtor, prospective judgment debtor or third party in the
following terms:
The Court may make a freezing order or an ancillary order or both against a
judgment debtor or prospective judgment debtor if the Court is satisfied, having
regard to all the circumstances, that there is a danger that a judgment or
prospective judgment will be wholly or partly unsatisfied because any of the
following might occur—
(a) the judgment debtor, prospective judgment debtor or another person
absconds; or
73 (1999) 198 CLR 380.
74 T81.31-84.23.
75 T90.12-.22
76 T88.17-.22.
77 Affidavit of Xiaoshan Sun made on 11 August 2023 (FDN 35).
78 UCR 112.14.
-- 20 of 28 --
[2024] SADC 17
19
(b) the assets of the judgment debtor, prospective judgment debtor or another
person are—
(i) removed from Australia or from a place inside or outside Australia;
or
(ii) disposed of, dealt with or diminished in value.
118 The general principles relating to the grant of freezing and ancillary orders
are well-established and not in real contention here. In summary, an applicant
must satisfy the Court of the following matters as are relevant to the circumstances
of the case before any order is made.
119 First, there is a good arguable case79 on both facts and the law80 for an accrued
or prospective cause of action. The threshold for demonstrating a good arguable
case is low and all that is required is something which “is more than barely capable
of serious argument and not yet necessarily one the judge believed to have a better
than 50% chance of success”.81
120 Secondly, there is a danger that the prospective judgment will be wholly or
partly unsatisfied because the prospective judgment debtor will abscond82 or the
assets of the prospective judgment debtor will be disposed of, dealt with or
diminished in value.83 The Court will be satisfied there is a danger that a
prospective judgment will not be satisfied where there is a real risk of the judgment
debtor absconding or dissipating assets.84
121 The fact that assets within the jurisdiction are moveable or the respondent is
incorporated or resident outside the jurisdiction is not a sufficient basis for
inferring a finding of a relevant danger. There must be conduct from which
“a prudent, sensible commercial person” can “properly infer a danger of default
if assets are removed from the jurisdiction”.85
122 The relevant danger must be established by evidence and not be mere
assertion or speculation and conjecture.86 However, an applicant is not required to
prove an actual intention on the part of the respondent to deal with their assets and
defeat recovery of the prospective judgment sum. It is enough if the applicant
79 UCR 112.17(1) and (2).
80 Cardile op cit [68] per Gaudron, McHugh, Gummow and Callinan JJ.
81 Seeley International Pty Ltd v Millenium Electronics Pty Ltd [2020] SASC 205 (Seeeley) per Livesey J
(as he then was) at [8] citing Brentwood Village Ltd (in liq) v Terrigal Grosvenor Lodge Pty Ltd [2014]
FCA 1203, [24].
82 UCR 112.17(4)(a).
83 UCR 112.17(4)(b).
84 Cardile op cit at [122]; Seeley op cit at [16] citing Yadlamalka Land Pty Ltd v Ragless [2018] SASC
131 (Yadlamalka) per Hinton J at [35]-[44].
85 In Deputy Commissioner of Taxation v Hua Wang Bank Berhad (2010) 273 ALR 194 per Kenny J at
[12] citing Third Chandris Shipping Corporation v Unimarine SA [1979] QB 645 per Lawton LJ at 671.
86 Yadlamalka op cit at [43].
-- 21 of 28 --
[2024] SADC 17
20
establishes that in the absence of relief, there is a danger that the assets will be
dealt with in a way that will prevent recovery of the judgment sum. 87
123 Thirdly, the balance of convenience favours the making of an order.88
124 As the authorities emphasise, 89 a freezing order is an exceptional or drastic
remedy which should not be granted lightly. It imposes severe restriction on a
respondent’s right to deal with their assets. Its purpose is not to provide an
applicant with security in advance of a prospective judgment it fears may not be
satisfied nor to improve the applicant’s position if the respondent were to become
insolvent.
125 It is therefore important that any freezing order made be framed within the
limits set by the purpose for which it can properly be intended to serve,90 including
by not tying up assets beyond the extent of any likely judgment sum.91 Therefore,
an applicant must satisfy the Court with some precision as to the value of the
prospective judgment.92
126 Finally, no such relief should be contemplated without the provision of an
undertaking as to damages.93
Approach to Determination
127 The logical approach to an application for a freezing order in the case of a
prospective judgment is to first consider whether the applicant has established the
threshold requirement that it has a good arguable case and then next consider
whether the evidence establishes the requisite danger that a judgment will not be
satisfied and address other discretionary considerations as are relevant.
128 It is unnecessary to do that here because the evidence clearly does not
establish any real risk that a prospective judgment against Mr Sun Junior will not
be satisfied because he might abscond or dissipate his or the Builder company’s
assets.
129 For completeness, I mention there should be no real dispute that the Company
has a good arguable case against the Builder. Much time was taken by the parties
in debating the merits of the Company’s claims against Mr Sun Junior and whether
the Court could be satisfied there was a good arguable case. Ultimately, given this
threshold requirement is a ‘low bar’, I am satisfied that there is a ‘good arguable’
case against Mr Sun Junior. This is properly an issue for trial and determination
of the contractual claim will require evidence of the surrounding circumstances to
87 Patterson v BTR Engineering (Aust) Ltd (1989) 18 NSWLR 319 at 325 per Gleeson CJ.
88 Seeley op cit at [6].
89 Cardile op cit at [51].
90 Jackson v Sterling Industries Ltd (1987) 162 CLR 612 at 625.
91 Cardile op cit at [124.]
92 McEntee v SJ Berry Pty Ltd [2024] SADC 8 per Burnett DCJ at [35].
93 Cardile op cit [122] citing National Australia Bank Ltd v Bond Brewing Holdings Ltd (1990) 169 CLR
271 at 277.
-- 22 of 28 --
[2024] SADC 17
21
determine whether the September Agreement was objectively intended to be
binding or bind Mr Sun Junior in his personal capacity.
Danger of Unsatisfied Judgment
130 In conclusion, the Company submits:94
The applicant submits that on the facts and circumstances of this matter, the evidence
clearly establishes that there is a prima facie cause of action against the respondents and
that there is a very real danger by reason of the respondents absconding or of assets being
removed out of the jurisdiction or disposed of within the jurisdiction or otherwise dealt
with in some fashion, that the applicant, if he succeeds, will not be able to have his
judgment satisfied.
131 The Company submits the danger of a prospective judgment against the
Respondents not being satisfied arises in circumstances where the Respondents
have made threats to sell up and flee the jurisdiction, there is a proposed sale of a
property owned by Mr Sun Junior and the structures of the Builder company and
intercompany relationships are opaque. The Company relies on these
circumstances in combination, accepting each in isolation may be a ‘bit thin’.95
Alleged Threats to Sell Up and Flee the Jurisdiction
132 For the following reasons, I do not find the written evidence of the alleged
threats to sell up and flee the jurisdiction compelling in all the circumstances. The
relevant evidence is untested, was sworn some six months after the alleged
meetings occurred in February 2023 and comprised in remarks informally
translated by unknown third persons with no apparent authority to speak for the
Builder or Mr Sun Junior. As it transpires, the threats attributed to Mr Sun Junior
were made by his father, unknown to him.
133 Mr Rad and Mr Edgar both gave limited evidence about a meeting held at the
Builder’s offices on 6 February 2023 to discuss progress of the works and defect
rectification which was attended by them both, Tim (Mr Wei Yuan) and persons
only known as ‘Amanda’, ‘Annie’ and ‘Mr Sun’. Tim and Amanda acted as
translators for Annie and Mr Sun, who did not speak English.
134 It is Mr Rad’s evidence that Tim translated a remark made by Mr Sun to the
effect of:96
If this project is going to cost us any more losses, we will sell everything, pack up and go
back to China.
94 Applicant’s Submission FDN 30 [7.1].
95 4 August 2023 T42.7-.11.
96 Second Rad Affidavit [5]-[6], emphasis supplied.
-- 23 of 28 --
[2024] SADC 17
22
135 It is Mr Edgar’s evidence that Tim translated for Annie or Mr Sun words to
the effect:97
If it cost that after what I’ve lost, we’ll sell everything, pack our bags and go back to China.
136 Mr Rad gave evidence of a second meeting held on 24 February 2023 at the
Builder’s offices attended by among others Mr Edgar, Tim, Amanda, Annie,
Mr Sun and a “man known to me only as ‘Binh’ who was introduced to me as an
investor and director of the company.” 98 Mr Rad recalls ‘Binh’ saying words to
the effect:99
I would rather send the company bankrupt and pay nothing.
137 Mr Rad’s account of the second meeting is not supported by Mr Edgar, who
did not give any evidence about this meeting despite his being there, according to
Mr Rad, and swearing an affidavit about the first meeting. I infer that the absence
of his evidence does not assist the Company.
138 During the course of argument on 4 August 2023, the question arose as to
whether the Mr Sun in attendance at these meetings was Mr Sun Junior (the Second
Respondent and director of the Builder company) or Mr Sun Senior, who is not a
party and is the majority shareholder of the Builder company. Mr Sun Junior’s
subsequent written evidence makes clear it was not him in either meeting, he has
never met Mr Rad or Mr Edgar and was not aware of the alleged threats until told
by his solicitor Mr Xiao.100
139 Further, ‘Binh’ has no role and is not an investor involved in the Builder’s
business. He is a director of the roofing and cladding sub-contractor retained by
the Builder.101
140 The Respondents submit these alleged threats were made by a person with
no formal or any role within the Builder company. That should be accepted on the
evidence save it is now common ground that the Mr Sun in attendance at these
meeting is Mr Sun Senior, the major shareholder of the Builder company and father
of Mr Sun Junior, the director of the Builder company.102
141 There is on the evidence no basis for finding Mr Sun Junior made the alleged
threats to sell up and flee the jurisdiction. This is a fatal flaw in seeking a freezing
order against Mr Sun Junior on the basis there is a danger he might abscond.
97 Second Edgar Affidavit [6]; emphasis supplied.
98 First Rad Affidavit [8].
99 Ibid [9].
100 Sun Affidavit [3]-[7].
101 Ibid [8].
102 Seventh D’Andrea Affidavit [48]-[50].
-- 24 of 28 --
[2024] SADC 17
23
142 Finally, there is no evidence of any steps taken consistent with the alleged
threats since February 2023. This is an important consideration fortifying my
conclusion that little weight should be placed on this evidence in all the
circumstances.
Sale of Real Property
143 The Company further relies on an advertisement of a property for sale known
as 4 Chase Grove, Vale Park (the Vale Park Property).103 Mr Rad describes the
listing as the sale of a house and land package involving Mr Sun Junior’s land and
a building contract with the Builder.104 Much was sought to be made by the
Company during argument of the Builder’s role in dealing with the Vale Park
Property. However, it is in my view not surprising or of concern that the Builder
company, of which Mr Sun Junior is a director, would be a proposed party to a
building contract on land sold by Mr Sun Junior as part of a house and land
package, given their businesses.
144 Any concern that might arise from the advertised sale of the Vale Park
Property is allayed when two further matters are appreciated. First, this is not
Mr Sun Junior’s only asset. He is also the registered proprietor of another property
known as 26 Andreas Avenue, Evanston Gardens (Evanston Gardens).105 There
are two registered proprietors of this second property but the identity of the other
proprietor is not known. Secondly, it is now apparent that the Vale Park Property
has been on the market since about July 2022.106 It was purchased by Mr Sun in
April 2022 with the intention of developing it, and in November 2022 he decided
to demolish the existing house and build two new dwellings. Development
approval from the Walkerville Council was received on 11 May 2023 and
demolition work was planned to start in September 2023, and to the extent that the
Builder performs any construction work Mr Sun Junior deposes that it will be done
under a contract between Mr Sun Junior and the Builder.107 There is no reason to
disbelieve any of this evidence.
145 In the circumstances shown by the evidence before me, I do not consider that
the development and sale of one of Mr Sun Junior’s real property assets of itself
or in combination with the other matters relied on demonstrates any real risk of a
prospective judgment in favour of the Company being unsatisfied.
Opacity
146 The Company further relied on the alleged opacity of the Builder company’s
structure and intercompany relationships. This submission was grounded on two
matters: first, the alleged lack of substantive information about the affairs of the
Builder as a result of the Respondents’ alleged failure to provide certain
103 Second Rad Affidavit Exhibit OFR-15.4.
104 Ibid [47].
105 Ibid Exhibit OFR-15.3.
106 Sun Affidavit [9].
107 Ibid [9]-[13].
-- 25 of 28 --
[2024] SADC 17
24
information about its affairs as requested by the Company’s solicitors; secondly,
concerns arising from its apparent relationship with other entities (Myland
Constructions and JD Homes). The latter concern was based on Mr Rad’s internet
searches of the websites of the Builder and the other entities. In essence, he
deposed that the three website advertised the same common projects including an
image of the redeveloped Vale Park Property owned by Mr Sun Junior.108
147 It should first be emphasised that these matters all concern the First
Respondent Builder and not Mr Sun Junior, the person against whom the freezing
and ancillary orders are sought.
148 In any event, the Company’s evidence on this topic largely comprised bare
assertions, speculation and conjecture. Ultimately, any relevant concerns arising
were addressed by Mr Sun Junior’s written evidence filed after the 4 August
hearing but before the Company (and the Respondents) requested that the Court
determine the application for freezing and ancillary orders against Mr Sun Junior.
149 It is plain that the web pages searched and printed by Mr Rad are identical in
all respects save for the named vendor company. However, the images of ‘on sale’
properties relied on are images of new houses, and all that may reasonably be
inferred from it is that they are offered for sale by these companies. More is
required to infer any concern.
150 As to the other entities and their relationship with the Builder and Mr Sun
Junior, whilst the Company apparently conducted searches of these entities it did
not put them before the Court. Mr Sun Junior’s written evidence has since clarified
a number of issues the subject of potential concern. First, he identifies a number
of construction projects being undertaken by the Builder109 and deposes that neither
he nor the Builder has any relationship with Myland Construction and JDE Homes,
as shown in ASIC searches that he has now put in evidence.110 His written demands
that these entities take down its website appear contrived at worst.111
151 The matters raised by Mr D’Andrea in his responding affidavit112 in January
2024 also do not assist the Builder’s position. First, the Respondents’ liquidity is
not the issue.113 There must be conduct from which a danger of default can properly
be inferred. Secondly, demolition of the house on the Vale Park Property was the
subject of written notice in the form of Mr Sun Junior’s written evidence and
therefore did not breach the undertaking given in Court on 4 August 2023. As the
Respondents submit, continuing progress of their development projects is not only
consistent with their carrying on their usual business but negates any inference of
108 First Rad Affidavit [48]-[50] and Exhibits OFR-16 and OFR-17; Second Rad Affidavit [12]-[14] and
Exhibit OFR-19.
109 Sun Affidavit [14]-[15].
110 Ibid [16] and Exhibit XS-4.
111 Ibid [17].
112 The Seventh D’Andrea Affidavit [42]-[47].
113 Ibid [42].
-- 26 of 28 --
[2024] SADC 17
25
an intention to abscond from the jurisdiction or dissipate their assets to avoid a
prospective judgment.
152 Mr Sun Junior has shown by unchallenged evidence he is an Australian
citizen and therefore no longer a Chinese citizen.114 There is no basis for inferring
any risk of Mr Sun Junior absconding to China.
Other Matters
153 The alleged non-payment by the Builder of two sub-contractors does not give
rise to any relevant concern.115 It is consistent with the pleaded non-payment by the
Builder the subject of the proceeding made in the context of one of the
subcontractors telling Mr Rad this so Mr Rad would pay him. As already stated,
the illiquidity of the Builder of itself does not give rise to any risk of abuse or
frustration of the process of the Court by the dissipation of its assets.
154 The fact that the Company made payments in the past to the Builder into a
bank account in the name ‘Dangling Homes’116 does not without more give rise to
any adverse inference in favour of the Company’s application. There could be
many explanations and all would be speculation.
155 As I ruled during the 4 August 2023 hearing, Mr Rad’s evidence as to his
concerns about the Builder not being an established business or being unable to
satisfy an award of damages is an inadmissible conclusion. It is for the Court to
assess the evidence and determine whether the relevant risk arises. The purpose
of the grant of a freezing order is not to create security in favour of the applicant
Company for a prospective judgment or require the Respondents to provide
security as a condition of being permitted to defend the claims brought against
them.117 In any event, Mr Rad’s expressed and belated concerns lack credibility
given his dealings with the Company since at least late 2020.
Balance of Convenience
156 The balance of convenience does not favour the making of any freezing or
ancillary orders as sought. Further, the orders sought are not confined to the limits
set by the purpose of the freezing order: that is, a restraint against the disposal of
assets only to the extent the applicant Company may be thought likely to recover
from Mr Sun Junior.
157 First, any order generally restraining Mr Sun Junior from dealing with his
business or the Builder’s assets (whose assets are not his) would unreasonably
interfere with the operation of these businesses in circumstances where there is no
114 Sun Affidavit [18].
115 First Rad Affidavit [52].
116 Ibid [51].
117 Jackson v Sterling Industries Ltd op cit per Deane J at 625.
-- 27 of 28 --
[2024] SADC 17
26
evidence of any willingness to defeat a prospective judgment or real risk of that
outcome justifying such interference.
158 Secondly, the Company has not established with sufficient precision the
value of the prospective judgment against Mr Sun. The basis of the amount sought
of AUD$1 million has not been established, bearing in mind that Mr Sun’s alleged
liability only arises from delays since December 2022, the values of the Vale Park
and Evanston Gardens Properties are unknown, and the latter property is jointly
owned by Mr Sun Junior and an unknown third party.
159 Thirdly, there is no basis for restraining Mr Sun Junior’s assets to secure a
prospective judgment against the Builder. That the Builder owns no real property
or in fact may be impecunious is not a legitimate basis for seeking a freezing order
against Mr Sun Junior for the Builder’s assets.
Conclusion
160 The Company has not established on the evidence that there is a real risk that,
absent the freezing order sought against Mr Sun Junior, any prospective judgment
will be wholly or partly unsatisfied. The onus is on the Company to establish a
real risk of asset dissipation and it has not done so. I place little weight on the
untested alleged threats that are dated, were informally translated and did not
involve Mr Sun Junior. I do not find the sale of the Vale Park Property evidence
of asset dissipation as opposed to the carrying on of the Respondents’ usual
business with a view to enhancing the property’s value.
161 Accordingly, I dismiss the Company’s application for freezing and ancillary
orders against Mr Sun Junior.
-- 28 of 28 --