CREIGHTON and BUILDMARK PTY LTD [2026] WASAT 87
[2026] WASAT 87
Page 1
JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL
ACT : BUILDING SERVICES (COMPLAINT
RESOLUTION AND ADMINISTRATION) ACT
2011 (WA)
CITATION : CREIGHTON and BUILDMARK PTY LTD [2026]
WASAT 87
MEMBER : MR T CAREY, MEMBER
MR R AFFLECK, SENIOR SESSIONAL MEMBER
HEARD : 11 - 12 MARCH 2026 AND 6 MAY 2026
DELIVERED : 24 JULY 2026
FILE NO/S : CC 150 of 2025
BETWEEN : LESLIE CREIGHTON
First Applicant
SHIRLEY ANNE CREIGHTON
Second Applicant
AND
BUILDMARK PTY LTD
Respondent
FILE NO/S : CC 364 of 2025
BETWEEN : LESLIE CREIGHTON
First Applicant
SHIRLEY ANNE CREIGHTON
Second Applicant
AND
-- 1 of 33 --
[2026] WASAT 87
Page 2
BUILDMARK PTY LTD
Respondent
FILE NO/S : CC 151 of 2025
BETWEEN : BUILDMARK PTY LTD
Applicant
AND
LESLIE CREIGHTON
First Respondent
SHIRLEY ANNE CREIGHTON
Second Respondent
Catchwords:
Building dispute - Complaints that regulated building service not carried out in a
proper or proficient manner or faulty or satisfactory - Modifications the subject of
building contract under National Disability Insurance Scheme - Builder prevented
from completing contract - Liability considered - Order to pay - Calculation of
reasonable cost in the absence of submissions and evidence from applicants
Building dispute - Contractual claims arising based upon failure to obtain a
building permit and home indemnity insurance - Whether building permit and
home indemnity insurance required
Building dispute - Contractual claims for payment for provision of regulated
building service and interest
Legislation:
Building Act 2011 (WA), s 9
Building Regulations 2012 (WA), s 41(3)
Building Services (Complaint Resolution and Administration) Act 2011 (WA),
s 11(1)(d), s 36(1), s 36(1)(b)
Home Building Contracts Act 1991 (WA), s 3(1), s 9(1), s 9(5), s 25B(4A),
s 25C(1), Pt 3A, Div 2
-- 2 of 33 --
[2026] WASAT 87
Page 3
State Administrative Tribunal Act 2004 (WA), s 35
Result:
Proceeding CC 150 of 2025 partially successful; order to pay made
Proceeding CC 364 of 2025 unsuccessful
Proceeding CC 151 of 2025 successful; order to pay made
Category: B
Representation:
CC 150 of 2025
Counsel:
First Applicant : In Person
Second Applicant : Non-appearance
Respondent : In Person
Solicitors:
First Applicant : N/A
Second Applicant : N/A
Respondent : N/A
CC 364 of 2025
Counsel:
First Applicant : In Person
Second Applicant : Non-appearance
Respondent : In Person
Solicitors:
First Applicant : N/A
Second Applicant : N/A
Respondent : N/A
-- 3 of 33 --
[2026] WASAT 87
Page 4
CC 151 of 2025
Counsel:
Applicant : In Person
First Respondent : In Person
Second Respondent : Non-appearance
Solicitors:
Applicant : N/A
First Respondent : N/A
Second Respondent : N/A
Case(s) referred to in decision(s):
Nil
-- 4 of 33 --
[2026] WASAT 87
Page 5
REASONS FOR DECISION OF THE TRIBUNAL:
1 The applicants have filed two complaints under the Building
Services (Complaint Resolution and Administration) Act 2011 (WA)
(the BSCRA Act) against the respondent concerning building works
performed by it under a contract dated 19 December 2022 for the
modification of an ensuite bathroom at 8 Orange Grove Boulevard
Clarkson for the fixed price of $50,358. The modification was designed
to cater for Mrs Creighton's special needs as a participant under the
National Disability Insurance Scheme (NDIS), with the contract price
to be paid by NDIS.
2 The applicants' initial complaint was against Celtic Builders Pty Ltd
(Celtic). Upon investigation by the Building Commissioner it was found
that Buildmark Pty Ltd was the builder who carried out the work and
Celtic was the designated project manager.
3 The first complaint (CC 150/2025), which initially comprising one
complaint item, has subsequently been fragmented into 21 items which
were referred by the Building Commissioner to the Tribunal
in accordance with s 11(1)(d) of the BSCRA Act. Of the 21 items, 8 are
known as 'HBWC items' (being contractual items under the
Home Building Contracts Act 1991 (WA)) (HBC Act) and 13 are known
as 'workmanship items' (being complaints under the BSCRA Act of work
not being carried out in a proper and proficient manner or being faulty or
unsatisfactory). The second complaint (CC 364/2025) comprises two
Home Building Work Contract (HBWC) items, previously in the first
complaint but withdrawn, concerned with the respondent's failure to take
out home indemnity insurance and obtain a building permit. Again, both
items have been referred to the Tribunal.
4 The respondent has filed its own complaint (CC 151/2025)
comprising two items, both of which have been transferred to
the Tribunal. The first seeks amounts allegedly due and unpaid, and the
second complains about the applicant's conduct in relation
to the respondent's tradespersons and contractors and, ultimately, their
action in preventing the respondent access to the site prior to practical
completion.
5 For ease of reference, when we consider CC 151/2025 in these
reasons we will continue to refer to Buildmark Pty Ltd as the 'respondent'
and Mr and Mrs Creighton as the 'applicants'.
-- 5 of 33 --
[2026] WASAT 87
Page 6
6 The Tribunal ordered that the three matters remain as separate
proceedings but be heard and determined together with evidence in one
being evidence in the others. The hearing commenced on 11 March 2026
and continued until lunchtime on 12 March, when it was adjourned
part-heard to allow Mr Creighton to care for Mrs Creighton in the face
of a medical emergency. The hearing proceeded to its conclusion on
6 May 2026.
7 We will deal, in order, with the applicants' first and second
complaints followed by the respondent's complaints. There are some
features of the entire matter we need to refer to before doing so.
Preliminary matters
(a) NDIS involvement
8 As mentioned, the project was the subject of arrangements under
NDIS. Those arrangements included:1
• An NDIS complex home modification assessment to provide a
wheelchair accessible bathroom for Mrs Creighton;
• A complex home occupational therapist and registered NDIS
service provider (Ms Rianne Colyer) was nominated; and
• A preferred project manager specialist and registered NDIS
service provider (Mr Jon Dunn from Celtic) was appointed.
9 Under these arrangements, a scope of works2 and drawings3 were
prepared and put to tender. The respondent was engaged by the
applicants as the cheaper of two quoting building companies.
10 Under the same arrangements, despite the building contract4 being
between the applicants and the respondent, the NDIS agents to whom we
have referred were directly involved in issues which arose in the course
of the project. Mr Dunn's role as project manager rendered him as
a decision-maker in relation to some issues, and some of those decisions
were strongly disputed by Mr Creighton (as evidenced by naming Celtic
as respondent to the applicants' original complaint). Be that as it may,
the legitimate role played by Mr Dunn, and the concomitant reduced
1 We base our comments regarding the NDIS aspect of the project upon the applicants' document 'Material facts
relevant to the complaint' (Hearing book commencing at page 28). (Exhibit 1).
2 Hearing book at page 341.
3 Hearing book at pages 301 - 302.
4 Hearing book at pages 384 - 411.
-- 6 of 33 --
[2026] WASAT 87
Page 7
legitimate role of the applicants, and specifically Mr Creighton, in
decisions which impacted upon the building service performed, is a
matter of some significance.
(b) The applicants' early termination of the contract
11 It is clear from the contemporaneous documentation that
Mr Creighton, at least, was under the impression that the respondent was
required to complete the project within 30 calendar days of
commencement, to the extent that he arranged for his wife's respite care
'for a total of 4 weeks only'5 (Mr Creighton continuing to reside at the
residence throughout the works). However, the contract is quite clear
in providing for a time for completion of '30 working days from'
commencement.6
12 The parties agreed on a commencement date of 31 January 2023.
The respondent therefore had until 14 March 2023 to complete the works
under the contract, rather than the date assumed by Mr Creighton of
2 March 2023.
13 Issues arising with the building project commenced early on.
Relevant to the current matters, Mr Creighton raised with the respondent
whether a structural head was required for the hallway door opening
widening, the type of fixing of mesh reinforcement of the floor screed,
progress (or lack thereof) being made by trades and its impact upon the
completion date, selection of a vanity unit and finishes, quality of
painting, and the relocation and alleged reduction of the ensuite door
opening and other consequential impacts upon wheelchair accessibility.
14 Suffice to say that the tone of the email communications between
the contractual parties deteriorated quickly, to the point that on
17 February 2023 Mr Creighton asked that his email of that day be
treated as a breach notice with an option to terminate the contract.
The same email said that Mr Creighton would be speaking with Mr Dunn
to 'decide on where we will be going from here on'.7
15 Although Mr Creighton disputes the point, we accept Mr Alujevic's
evidence that by 3 March 2023, Mr Creighton had denied access to all
trade contractors engaged for the project by the respondent.8
5 Hearing book at page 144.
6 Hearing book at page 525.
7 Hearing book at page 151.
8 Hearing book at page 521.
-- 7 of 33 --
[2026] WASAT 87
Page 8
16 Mr Creighton described the situation in terms of issues with the
building needing to be resolved, a toing and froing of emails between all
parties to try to fix the issues which went for a number of weeks until the
end of March, and relations between the contractual parties further
deteriorating to the point where Mr Creighton informed Mr Alujevic that
all communication was to be through the project manager.9 The builder
has never returned to site.
17 The question of whether or not the contract has been 'terminated'
is a vexed one. The applicants submit, on the one hand, that the contract
was never enforceable based upon their view of the consequences of the
respondent's failure to obtain a building permit and home indemnity
insurance. However, they arrived at this position well after the events of
early 2023. During that period, Mr Creighton apparently regarded the
situation as capable of resolution on the basis that the respondent retain
some but not all of their contractual obligations.10
18 The issues extant at the time, and proposals for their resolution, are
contained in various emails between 7 March 2023 and 14 April 2023
involving some or all of Mr Creighton, Mr Alujevic, Mr Dunn,
Ms Colyer and Ms Ashleigh Jones, an NDIS planner. There is
significant input from the NDIS officers, including settlement proposals
which would have included variations of the scope of works and plans
which were accepted by the respondent but not by the applicants.
Each party served its own respective breach notice on the other during
this period.11
19 It is, we believe, safe to say, and we find, that the parties have, by
their conduct, terminated the contract at some time between 7 March
2023 and 14 April 2023, the termination having been precipitated by the
applicants' refusal to allow the respondent entry to the site at a time
before the end of the period allowed under the contract for it to complete
the contracted building service.
20 Mr Creighton regarded his conduct as being warranted on behalf of
the applicants on the basis of the quality of the respondent's work
(and also by reason of his later claims concerning failure to obtain
a building permit and home indemnity insurance). Based on our findings
in relation to all claims against the respondent, we consider that the
9 ts 14 - 15, 6 May 2026.
10 See email Mr Creighton to Mr Dunn and Mr Alujevic dated 12 March 2023, in which it was proposed that
the respondent be permitted, on conditions, access to site for certain tasks, but not others: Hearing book at
pages 157 - 159.
11 Hearing book at pages 157 - 174, 582 - 603.
-- 8 of 33 --
[2026] WASAT 87
Page 9
applicants had insufficient ground to refuse entry. In light of their
repudiatory conduct in preventing the respondent entry to the site, any
claims of alleged defective workmanship which we allow can give rise
to a remedy only to the extent of faulty or unsatisfactory work already
apparent, and not incomplete work which the respondent was deprived
of the opportunity to complete.
(c) The applicants' absolutist approach and its rationale
21 Another feature of this case is the applicants' refusal to countenance
any outcome other than reimbursement of the cost of complete
demolition and reconstruction of the building service provided by the
respondent and other expenses claimed to have resulted from
the respondent's breaches.
22 The applicants' advocacy for such a comprehensive remedy relies
upon both the extent and nature of the respondent's defects and the
respondent's failure to obtain a building permit and home indemnity
insurance (the subject of CC 364/2025).
23 We do not consider that the cost of complete demolition and
reconstruction is required in order to remedy those defects for which we
find the respondent liable.
24 As will also be seen when we deal with complaint items the subject
of CC 364/2025, we do not accept that a building permit and home
indemnity insurance were required for the project. However, had they
been, this would not in our opinion have warranted granting the relief
sought by the applicants.
25 As was pointed out to Mr Creighton at the hearing, the absolutist
quality of the claim, and the lack of any particularisation in the quotation
relied upon by the applicants for the purpose of quantification, has meant
that the Tribunal has very little to go on in order to assess the reasonable
costs of remedying the isolated defective building service items as we
have found them to be. However, as we will explain, we have, with
the assistance of the respondent, fashioned an outcome which is of some
benefit to the applicants, albeit of considerably lower value than that
contended for.
CC 150/2023 - Liability
26 Neither party relies upon any independent expert evidence to
support its case on liability over and above the contents of any expert
reports they have filed. Mr Creighton has indicated that the expense of
-- 9 of 33 --
[2026] WASAT 87
Page 10
engaging such expert evidence was prohibitive for the applicants.
Whilst we sympathise with them in this regard, our task remains to assess
liability in light of the evidence and, in so doing, utilising the knowledge
and experience of the building sessional member hearing the matters.
As will become clear, we have had regard, to the extent we consider
reasonable, to the oral submissions provided by both Mr Creighton, who
informed us he is a qualified carpenter and has had some experience
managing building sites (albeit not as a registered builder), and the
respondent's director, Mr Alujevic, a registered builder.
27 We will deal with each item in turn. Concerned as we are with the
substance of the applicants' complaints, where we do not deal with
a particular item number according to the list of complaints referred by
the Building Commissioner to the Tribunal, this is because the same
complaint falls within and is dealt with under another item in the list, or
it was expressly withdrawn by Mr Creighton in the course of the hearing.
Item 2A: Tiling defects in bathroom
28 There is a number of different complaints within this item.
(a) Insufficient floor tile falls, in shower recess and the remainder of
ensuite
29 The primary documentation in relation to this and subsequent
workmanship complaints are the Celtic Builders drawings12 and the
scope of works.13
30 According to the scope of works:
• the slope of the floor of the shower recess shall have a gradient
between 1:60 and 1:80; and
• the slope of the floor of the remainder of the ensuite shall have a
gradient (between) 1:80 and 1:100.
31 The applicants rely upon a building defect inspection report of
Home Integrity Building Consultants (HIBC).14 This report contains15
photographs of a series of measurements conducted by spirit level to the
following effect:
12 Hearing book at pages 301 - 302.
13 Hearing book at pages 341 - 346.
14 Hearing book commencing at page 57.
15 Hearing book at page 61.
-- 10 of 33 --
[2026] WASAT 87
Page 11
• the slope of the shower recess floor towards the trench drain is
1:50; and
• the slope of the floor of the remainder of the ensuite is variously
1:56 and 1:59.
32 The respondent did not adduce any evidence of the slopes in
question, and Mr Alujevic conceded that the slopes of the as built shower
recess and ensuite were outside of the limits set by the scope of works.
33 All readings referred to in the HIBC report being outside the
required ranges under the scope of works, we find the tiling faulty and
unsatisfactory.
(b) Non compliant set out at doorway entrance
34 The HIBC report16 contains a photograph of a measurement by
spirit level indicating a 1:71 fall in the floor at the entrance to the ensuite,
where the floor should be level. We find this part of the tiling faulty and
unsatisfactory.
(c) Non compliant waterproofing
35 The genesis of this item appears in the following remark in the
HIBC report 'The perimeter waterproof flashing has not been brought
over the wet area/en-suite door jambs or waterproofed into a water stop
at the floor level opening'.17
36 As can be seen from the photographs accompanying the remark,
there is no waterstop at the ensuite entrance between the tiling and
wooden bedroom floor. The photographs on the preceding page of the
report show that the surface of the tiling is higher than the bedroom floor
tiling.
37 At the hearing, the parties were at odds over whether the existing
floor in the adjoining bedroom was the finished product, Mr Creighton
stating that the floor shown in the photographs is the finished product
while Mr Alujevic suggested that the applicants were to still install
a floor. It is unnecessary for us to determine who is correct, given the
need for the tiling in the ensuite to be redone.
38 Mr Alujevic also stated that as is the case in many NDIS
modifications, a waterstop is not feasible at the transition between the
16 Hearing book at page 61.
17 Hearing book at page 62.
-- 11 of 33 --
[2026] WASAT 87
Page 12
bedroom and the ensuite because of the lipping it creates. We simply
note that when the tiling of the ensuite is undertaken, a satisfactory
solution to the need for waterproofing at the bedroom/ensuite junction
will be required. We will incorporate a cost component for doing so in
our reasonable cost determination. The complaint is to this extent
allowed.
39 A further complaint of the lack of a reflux valve fitted to shower
waste system will be considered under item 12.
Item 2B: Plastering defects in ensuite and master bedroom
40 A number of deficiencies is evident in photographs shown in the
HIBC report.18 We say 'deficiencies' rather than 'defects', as it is clearly
the case, as submitted by Mr Alujevic, that the wall treatment
is incomplete, and the walls are not ready for painting. For example,
a 'topping compound' (which Mr Alujevic described as a gypsum-based
sandable product) needs to be applied and sanded before providing a
suitable surface for painting.
41 Mr Creighton suggested that despite the unreadiness of the walls for
painting, the respondents' painters had shown an intention to commence
painting the walls.19 He went as far as saying:
… when this - when the works, we had a completion - finish date for the
works, which was March 3, 2025. At that particular point, and on that
last day, Buildmark had maybe five to six trades tripping over each other
at that handover, project handover day.
…
They were commencing to paint over that defective work until it was
stopped.20
42 When pressed however, Mr Creighton was unable to produce
evidence of any paintwork on the walls in question, or otherwise explain
why the further preparation work described by Mr Alujevic prior to
painting was no longer feasible.
43 We therefore find that this item is not made out.
18 Hearing book at page 73.
19 ts 39 - 43, 11 March 2026.
20 ts 39, 11 March 2026.
-- 12 of 33 --
[2026] WASAT 87
Page 13
Item 2C: Missing and non-compliant door furniture in master bedroom
and ensuite
44 This item complains of missing architraves and sliding door floor
guides and inappropriate door handle.
45 In relation to the door handle, the HIBC report contains
a photograph of a pull handle on a sliding door, with the comment:
'[r]ecessed pull handle on the inside, moves past the frame, creating
a finger trap and potential Safety Hazard'.21
46 The scope of works requirement for this door handle is:
Supply and install … recessed rectangular finger pull handles to the new
sliding door'.22
47 The pull handle shown in the HIBC photograph complies with this
requirement. The safety hazard to which the HIBC report refers will be
eliminated when doorstops are installed. This is a normal aspect of the
installation of door hardware (to which the scope of works also refers)
which, had the respondent's trades been permitted back on site, they
would have been expected to perform.
48 Similarly, the remainder of the alleged defects in this item signifies
incomplete rather than faulty or unsatisfactory work.
49 We find that this item is not made out.
Item 7: Pre-pour floor slab preparation for ensuite bathroom
50 There is a number of different complaints within this item, which
derives from the structural engineering report of Australian Building
Specialist Pty Ltd (ABS report), supported by a concrete scan report of
Concrete Scanning & Locating WA Pty Ltd (CSL report). The absence
of both reports' authors prevented any questions being asked, for
example, as to the provenance and currency of photographs upon which
reliance is placed.
51 We will deal with each of the substantive complaints in turn.
21 Hearing book at page 71.
22 Hearing book at page 343.
-- 13 of 33 --
[2026] WASAT 87
Page 14
(a) No mechanical connection to starter bars
52 Mr Creighton relies upon a pre-pour photograph in the ABS report23
and the CSL report24 in support of a submission that 'the slab is just
floating'25 without connection to exiting mesh or starter bars.
53 Mr Alujevic denies this claim, drawing our attention to a later
photograph26 showing additional mesh going to the back corner and
dowls drilled to the perimeter of the which are not present in the
ABS report photograph. It is clear that Mr Lalli, the author of
the ABS report, did not have access to the later photograph, and the
author of the CSL report was unavailable to be asked questions about it.
54 We are satisfied that since it was poured, the concrete slab has
possessed the required connection between the slab and starter bars.
(b) Pre-pour slab prep mesh cut short
55 The applicants rely upon the following comment in the ABS report:
'[a]s reviewed, the pre-pour slab prep mesh appears to have been cut
short, and does not cover the entire floor space'.27
56 We consider that the later photograph of the mesh in the hearing
book28 demonstrates full mesh cover, contrary to the applicants'
assertion.
(c) Waterproofing membrane is not dressed up the slab edge and mesh
sitting on membrane and not lifted with risers
57 This sub-item repeats a comment in the ABS report.29
58 Regarding the lack of running the waterproof membrane up the
wall, we are satisfied that this was not practical for the reasons given by
Mr Alujevic, namely, the existence of penetrations in the membrane, and
to do so would create a cold joint.
59 Once again, the applicants' claim concerning the reinforcing mesh
relies upon the reporting of an absent expert based on dated photographic
evidence before the realisation of the final concrete slab.
23 Hearing book at page 297.
24 Hearing book at page 79.
25 ts 66, 11 March 2026.
26 Hearing book at page 282.
27 Hearing book at page 291.
28 Hearing book at page 283.
29 Hearing book at page 291.
-- 14 of 33 --
[2026] WASAT 87
Page 15
60 The asserted failure to lift the mesh above the sand base
is unsupported by evidence, and contrary to Mr Alujevic's expressed
expectation that when the concrete was poured, the tradesmen would
have lifted the mesh with hooks to the correct position (or installed bar
chairs immediately before the pour).
61 This item, in all respects, is not made out.
Item 8: Support for load-bearing wall in master bedroom hallway door
entrance inadequate
62 According to the ABS report upon which the applicants rely:
• …the doorway in the bedroom was widened to 900mm during
alterations.
• The load-bearing wall as reviewed has had no brick lintel
installed, even though there is a load-bearing steel beam sitting
directly above it.
• This has caused the load-bearing wall to be non-compliant as per
the scope of works.30
63 The applicants rely upon a photograph in the ABS report31 to
support the contention of a load-bearing beam directly above the
widened doorway. The photograph in question, taken inside the roof
cavity, does show a steel beam. Mr Alujevic said that the beam shown
is not over the doorway between the master bedroom and hallway.
No witness was called by the applicants to respond to this assertion.
64 The matter is put beyond doubt, in our view, by the following
written documents:
(a) An engineers certification (by Mr Ivan Marenko of Structural
Design Engineers Pty Ltd) dated 18 September 2024 of the
structural integrity of the doorway in question. The certification
was given on the basis that:32
1. No roof beam or roof strut supports over the top of span of the
door frame.
2. Use of standard timber door frame… being made from durian
or meranti hardwood timber as industry standard.
30 Hearing book at page 292.
31 Hearing book at page 296.
32 Hearing book at page 467.
-- 15 of 33 --
[2026] WASAT 87
Page 16
3. 343mm … of brickwork over the top of the door frame.
4. No lintel required … and
(b) The same engineer's letter dated 16 February 2023 stating (with
reference to the plans and photos of the applicants' building
project):
The widening of a … 820 door by an extra 100 mm and replacing the
door frame with a timber frame does not pose any structural issue.
That is - there is no structural impact...33
65 On the above basis, we find that this item is not made out.
Item 9: Ensuite set out not wheelchair accessible
66 This item exemplifies the added layer of complexity in considering
the applicants' claims due to the involvement of the NDIS agents.
67 The item is supported by the following extract from the ABS report:
• It is the opinion of this office that the adjoining wall needs to have
600mm of structure in front of the toilet pan, however, as
reviewed, the builder has reduced the wall by 275mm due to the
load bearing steel beam location.
• This has caused the opening to be non-compliant for disability
access as per the scope of works.34
68 The 275 mm referred to is attended by some doubt; the relocation
distance is referred to elsewhere as 300 mm.
69 At the hearing, Mr Creighton indicated his concern in relation to the
toilet was that the relocation of the doorway resulted in there being
inadequate wall space for compliance with the standard applicable
to disabled bathrooms, and hence, 'basically providing no fall protection
or any handrail protection for the end-user'.35
70 According to Mr Alujevic, the door location as shown in the
drawings 'could not have worked' because it would have resulted in
the doorway encroaching into the shower. His explanation at the hearing
of the process leading to the alternative positioning of the doorway was:
33 Hearing book at page 260 and 468.
34 Hearing book at page 292.
35 ts 92, 11 March 2026.
-- 16 of 33 --
[2026] WASAT 87
Page 17
The decision was made on site, and taken by Buildmark, because it could
not have worked the way it was drawn. As a remedy to that, when that
was highlighted, all parties and stakeholders had a meeting, and a
resolution was reached.36
71 The meeting was between Mr Dunn, Ms Colyer, Mr Alujevic and
Mr Creighton. Mr Creighton did not agree with the resolution reached
by the other participants.
72 The resolution included installing an upgraded toilet with a
concealed connection point and changing the grab-rail next to the toilet
from an L-rail to a T-rail.37
73 The respondent proceeded with the relocation of the door, which
seems to have been a major factor in Mr Creighton refusing entry to the
respondent's trades. The respondent did supply the toilet, but no
agreement between all parties was ever reached after the parties'
disputation commenced.
74 It would appear that Mr Creighton was not prepared to accept the
respondent's choice of an alternative toilet, and proposed another,
non-disability one. This was the subject of email correspondence
between Mr Creighton and Ms Colyer on 21 March 2023, when the latter
indicated that if Mr Creighton agreed with the non-disability toilet, she
would require from Mr Creighton an acknowledgement that he was
preferring not to accept with her recommendation and understand that
NDIS would not fund its rectification if a disability toilet was required in
the future.
75 Mr Creighton's position at the time regarding the relocation of the
door the subject of this complaint item is reflected by his two comments
in the same correspondence:
…Regrettably, its [sic] the only option, without ripping down the wall
and moving the door opening back to the original scope of works set
out…38 [and]
If these options don't work for shirley [sic] now or in the future, it will be
Buildmark covering the cost of changing everything and doing [it on the
scope] of works.39
36 ts 106, 11 March 2026.
37 The additional resolution terms are found in a number of versions of a revised work order culminating in
Revision D - see hearing book at page 339.
38 Hearing book at 164.
39 Hearing book at 163.
-- 17 of 33 --
[2026] WASAT 87
Page 18
76 There is no evidence that Mr Creighton resisted the door relocation,
for example, by asking Mr Alujevic not to proceed in accordance with
the resolution or refusing entry to the respondent's trades as he did
subsequently.
77 Mr Creighton referred us to the following passage from
the resolution document, Revision D, which he suggested indicated that
the solutions were only temporary:
On completion of these works, the property will be inspected by the PM,
document the outstanding works, differences to the original scope of
works, and photograph the project. At this stage whilst the complex
home modifications are not complete, the Bathroom will be functional
and allow Shirley to access with assistance.40
78 We cannot accept, in the NDIS context, that any building work
performed by the respondent which was not in accordance with the scope
of works or the drawings, but which followed identification of an issue
with the scope and a resolution between the project manager and the
respondent as builder which it executed, can by regarded as 'temporary'
in the sense that the builder is to be regarded as not having acquitted that
part of its contractual obligations pending a future appraisal of suitability.
The builder's work, in these circumstances, must be assessed in light
of the resolution's terms.
79 Assessing this item in this way, we find that the respondent
performed the work in accordance with the resolution reached.
Therefore, this item is not made out.
Item 11: Master ensuite doorway entrance inadequate for wheelchair
access
80 The applicants rely upon the ABS report where it says:
• Upon inspection, the doorway of the water closet was measured
to have been reduced by approximately 270 mm.
• As the doorway has been reduced, a wheelchair can [not]
sufficiently fit through the doorway, and therefore the doorway
as inspected is non-compliant.41
40 Hearing book at page 597.
41 Hearing book at page 425.
-- 18 of 33 --
[2026] WASAT 87
Page 19
81 Clearly, the premise - that the doorway was reduced by
approximately 270 mm - is incorrect. In fact, the correctly sized doorway
was moved by 270 mm (or 300 mm).
82 This may explain Mr Creighton's submission at the hearing that 'the
doorway now strikes the back wall and bedroom door. Not allowing it
to achieve minimum standard 850 millimetres minimum for
a wheelchair'.42 Following this submission, the discussion turned
to the extent, if any, of a door overhang into the doorway by reason of
the internal stopping mechanism for the door. Ultimately, Mr Creighton
was unable to take us to any evidence which persuaded us of any
outcome other than that asserted in the applicants' own HIBC report,
beneath a photograph of the doorway between the bedroom and the
ensuite, of a 'clear door opening of 900 mm'.43 This is sufficiently wide
for its intended purpose.
83 This item is not made out.
Item 12: Ensuite bathroom floor area
84 There are two different complaints within this item:
(a) Control floor waste lacking
85 Mr Creighton relies upon a reference in the scope of works at par
2.1 to floor wastes and adjusting the ensuite floor waste grates to suit the
new falls in the floor.
86 The drawings show no floor waste in the ensuite external to the
shower, which is generally the case where, as here, there is a hobless
shower. This is sufficient to dispose of this complaint.
87 We find this item is not made out.
(b) Reflux valve lacking
88 The need for a reflux valve is to be determined by a plumber
conducting the fit-off taking account of the on-site specifics. No fit off
was able to be conducted by the respondent's plumber because of the
applicants' denial of access. This item is another item of incomplete,
rather than faulty or unsatisfactory, work.
42 ts 116, 11 March 2026.
43 Hearing book at page 66.
-- 19 of 33 --
[2026] WASAT 87
Page 20
89 We find this item is not made out.
Item 18: Timber doors in bedroom 1 and ensuite
90 Although the applicants complain of incorrect and missing door
hardware, we are satisfied that the complaint is limited to incomplete,
rather than faulty or unsatisfactory, work. On this basis we find the item
is not made out.
CC 150/2025 - Remedy
91 In the usual case, in the scenario that one or more complaint items
is successful, the focus often turns to which of the available forms of
relief available under the BSCRA Act is appropriate. Those alternative
forms are an order to remedy, an order to pay and a compensation order.44
In this case, the relationship between the parties having clearly broken
down irretrievably making a return by the respondent to site impractical,
together with the respondent's expression of its acceptance of the rates
applied to any order to pay at a full market rate, indicate that an order
to pay based on market rates is appropriate.
92 'Order to pay' is a shorthand description of the type of order
described by s 36(1)(b) of the BSCRA Act as follows:
an order that a person who carried out a regulated building service pay to
an aggrieved person such costs of remedying the building service as
the… State Administrative Tribunal, … considers reasonable and
specifies in the order.
93 We referred earlier to the absolutist nature of the applicants' position
on remedy, and their failure to adduce evidence permitting allocation of
their global estimate to specific items we have upheld. Mr Alujevic
proved helpful regarding this evidentiary black hole. He suggested
a possible recalling of the matter to enable himself and Senior Sessional
Member Affleck to canvass the reasonable cost of remedying specific
found defects. Mr Creighton rejected such a possibility.
94 Near the end of the final hearing day, Mr Alujevic referred to the
respondent's original quotation forming the basis of the building
contract45 and noted that it contains itemised figures which might
facilitate a similar itemisation of relevant parts of the applicants'
quotation.
44 BSCRA Act s 36(1).
45 Hearing book (Exhibit 1) at page 637.
-- 20 of 33 --
[2026] WASAT 87
Page 21
95 On one view, it could be said that the applicants' intransigence
means that we do not have any evidence upon which we can arrive at
reasonable cost figures for the small number of successful complaint
items. However, in the circumstances, we have decided to adopt
Mr Alujevic's second suggestion in order to arrive at a figure for
the reasonable costs to remedy the building service to the extent of the
liability we have found.
96 The Buildmark quotation, as it appears in the hearing book, is
reproduced in Annexure A.
97 Senior Sessional Member Affleck has considered, in preparing
a notional scope of works and cost schedule, those components of the
original quotation relevant to the items for which we have found
in favour of the applicants, adjusted as required to allow for what needs
to be done to the existing building. The resultant remedial works scope
is Annexure B and cost schedule is Annexure C.
98 In accordance with the cost schedule, we allow the sum of $17,853
in respect of the applicants' claims.
CC 364/2025 - Liability
99 The applicants claim that the respondent breached the terms of the
contract (as well as applicable legislation) by failing to obtain a building
permit for the project and failing to obtain home indemnity insurance.
The respondent submits that no building permit and no home indemnity
insurance were required. We will deal with each issue in turn.
Building permit
100 We experienced great difficulty in extracting from Mr Creighton the
basis upon which we should find in favour of a requirement for a building
permit. He had, prior to the final hearing day, applied for an order to
produce under s 35 of the State Administrative Tribunal Act 2004 (WA)
directed to, effectively, the Building Services Board (the Board)
in respect of disciplinary proceedings against the respondent and
Mr Alujevic in respect of the building services the subject of these
proceedings which resulted in the respondent being fined $5,000
and Mr Alujevic being fined $2,500. The order to produce was issued
and a number of documents produced, which include inter-Departmental
correspondence supporting the view that a building permit was
required.46 On the final hearing day, Mr Creighton made much of this
46 The produced documents were tendered as Exhibit 4.
-- 21 of 33 --
[2026] WASAT 87
Page 22
correspondence, which he submitted should be sufficient for us to reach
the same conclusion.
101 The evidence before us does not include any formal statement of
the Board's reasons. The closest it comes to this is a media release on the
Department of Local Government, Industry Regulation and Safety
website under the heading 'Builder fined for failing to properly manage
and supervise vital NDIS works for wheelchair access'.47 In this media
release, there is reference to 'the [Board] found [the respondent] and its
director and nominated supervisor, Marko Alujevic… failed to provide
proper management and supervision of a building service as required by
WA's builder registration laws'. The release goes on:
A Building and Energy inspection later revealed several areas of
non-compliance with applicable building standards, including incorrect
placement of the toilet, shower taps and light switches; structural issues
with the concrete slab and mesh; inadequate doorframe support; and an
ensuite door position that prevented installation of toilet handrails.
Buildmark had also not obtained a building permit or home indemnity
insurance, which were both required for the project.48
102 The release leaves unstated the extent to which, if at all, the
respondent's failure to obtain a building permit and home indemnity
insurance contributed to the overall outcome (fines against the
respondent and Mr Alujevic), as opposed to the building issues which
it identifies. The only 'finding' referred to is in terms of a failure to
provide proper management and supervision of a building service.
103 There is, clearly, no possibility of an issue estoppel in relation to
any matter adverse to the respondent on the basis of the media statement.
And there is equally no merit to Mr Creighton's suggestion that we
should simply accept statements of opinion about the issues we need to
determine of the officers of the body investigating the disciplinary matter
on behalf of the Board.
104 We did manage to persuade Mr Creighton that it was incumbent on
him to explain the legislative or other underpinnings of any requirement
for a building permit here. He commenced by referring to s 9(1) of the
HBC Act which provides relevantly:
(1) Subject to subsection (5) every contract is conditional upon -
47 Exhibit 2 at page 5.
48 Exhibit 2 at page 5.
-- 22 of 33 --
[2026] WASAT 87
Page 23
(a) a building permit being granted, in respect of the home
building work included in the contract, within 45
working days from the date of the contract; …
105 We note that s 9(5) states:
(5) A condition referred to in a paragraph of subsection (1) does not
apply to a contract -
(a) to the extent that the subject matter of the condition was
completed before the contract was entered into; or
(b) where the only work to be performed under the contract
is the construction or carrying out of associated work; or
(c) for any other prescribed home building work.
106 The meaning of the expression of 'any other prescribed home
building work' is in our view most unclear on its face. For example, what
is the control group of 'prescribed home building work' with which the
'other' such work is being contrasted? However, when considered in its
context of following on from two specific exclusions, we believe the only
sensible interpretation the expression can carry is any home building
work, apart from the home building work referred to in (a) or (b), which
is prescribed by regulation49 to be exempt from the requirement
to comply with a condition otherwise applicable.
107 The issue of building permits and the circumstances in which they
are required are dealt with in the Building Act 2011 (WA) (Building Act)
and the Building Regulations 2012 (WA) (Building Regulations).
108 Section 9 of the Building Act sets out four alternative prerequisites
for the performance of building work, two of which are:
(a) a building permit is in effect for the building work; or
(b) a building permit is not required for the building work under
Part 5 or regulations or an order mentioned in Part 5 Division 1
…
109 Regulation 41(3) of the Building Regulations states:
A building permit is not required for building work of a kind described
in the Table in Schedule 4 clause 2 (Table).
49 Section 3(1) of the HBC Act defines 'prescribed' as 'prescribed by regulations'.
-- 23 of 33 --
[2026] WASAT 87
Page 24
110 The contents of the relevant clause of the table referred to are:
Item Description of building work for which building permit is not required
…
2. Renovation, alteration, improvement, repair or maintenance of a building or
incidental structure if the building work —
(a) will not adversely affect the structural soundness of the building or
incidental structure and does not include -
(i) an increase or decrease in the floor area or height of the
building or incidental structure; or
(ii) underpinning or replacement of footings; or
(iii) the removal or alteration of any element of the building or
incidental structure that is contributing to the support of any
other element of the building or incidental structure;
and
(b) is done using materials commonly used for the same purpose as the
material being replaced; and
(c) will not change the use or classification of the building or incidental
structure; and
(d) will not adversely affect the safety and health of the occupants or
other users of the building or incidental structure or of the public; and
(e) will not affect the way in which the building or incidental structure
complies with each building standard that applies to the building or
incidental structure; and
(f) is not work of a kind to which section 76, 77, 78 or 79 relates; and
(g) is not subject to a protection order, heritage works permit, repair
notice or repair order.
111 The aspects of the building project to which Mr Creighton pointed
as indicative of a building permit being required are:
• a wall was knocked down;
• a load-bearing wall was widened;
• removal of the wall created a bigger floor area;
• the floor slab was penetrated and broken out; and
• plumbing and electrical services were interfered with.50
50 ts 30 and 32, 6 May 2026.
-- 24 of 33 --
[2026] WASAT 87
Page 25
112 Of all the conditions referred to in cl 2 of the Table, the above
aspects of the work do, or might, invoke only condition (a) (the work will
not adversely affect the structural soundness of the building) and
sub-condition (i) (the work does not include an increase or decrease
in the floor area of the building).
113 A part of the wall which previously dissected the ensuite and
a walk-in robe was removed. As Mr Alujevic explained, prior to this
occurring, the respondent had its engineer, Mr Marenko, assess the
structural impact of the work. In his report, Mr Marenko states:
We have reviewed the photos and plans regarding the brick wall removal
and can confirm the brick wall to be removed is non-load bearing as the
roof can support itself. The ceiling joists are running parallel to the wall
and span the shorter span of the bathroom width. There is also no beam
or strut on top of this wall. Therefore there is no structural impact or
issue by removing this wall[.]51
114 No contrary evidence being before us, we accept that the proposed
removal of part of the wall had no potential for any adverse effect on
the structural soundness of the building.
115 We have already dismissed the potential for any similar effect in
the case of the widening of the bedroom/hallway door opening, based
upon Mr Marenko's certification that it involved no structural impact.
Again, in the absence of any evidence to the contrary was accept that
the widening of the doorway had no potential for any adverse effect on
the structural soundness of the building.
116 Although it is true that the floor area now forming part of the ensuite
has been increased to the extent of the footprint of the removed section
of wall, this is not, in our view, the sort of increase with which the
expression 'an increase… in the floor area' in the Table is concerned.
The floor area referred to in sub-condition (i) is of the building, not a
particular room or area. Hence, unless the works in question result in an
increase the footprint of the building, the sub-condition is not invoked.
These works have not increased the footprint of the building.
117 Although penetration of the slab might be regarded as structural,
that is not the same as 'affecting the structural soundness of the building'.
Mr Creighton did not explain how this expression applies to any slab
51 Hearing book at page 260.
-- 25 of 33 --
[2026] WASAT 87
Page 26
works, and we do not understand how it could. The same comment
applies to any interference with plumbing and electrical services.
118 For the above reasons, we do not consider that the builder was
required to obtain a building permit for the project.
Home indemnity insurance
119 The applicants submit that the respondent was obliged to take out
home indemnity insurance for the project. They rely upon s 25C(1) of
the HBC Act, which provides:
(1) A builder must not perform residential building work to which
this Division applies unless -
(a) a policy of insurance that complies with this Division is
in force in relation to the residential building work; or
(b) corresponding cover is provided by an approved fund in
relation to the residential building work.
Penalty: $10 000.
120 This provision relates only to building work to which the Div (Pt 3A
Div 2 of the HBC Act) applies. Among other examples, s 25B(4A) states
that the Division does not apply to residential work if a building permit
is not required for the work.
121 In the circumstances, we conclude that the respondent was not
required to take out a home indemnity insurance policy.
CC 151/2025
Unpaid invoices
122 The respondent seeks payment by the applicant of a tax invoice
dated 27 March 202352 in the amount of $12,924.26 (the first invoice),
described as 'Works completed' and 'Final completion payment, as per
contract'. It also seeks payment of a tax invoice dated 5 May 202653
in the amount of $6,489.49 (the second invoice) for interest on late
payment of the earlier invoice.
123 Based upon the applicants' written submissions, there are two
grounds for opposing the respondent's financial claims:
52 Hearing book at page 526.
53 In evidence as Exhibit 5.
-- 26 of 33 --
[2026] WASAT 87
Page 27
(a) the respondent's failure to obtain a building permit and home
indemnity insurance prevents the respondent from lawfully
demanding any payment under the contract;54 and
(b) some of the works for which payment is claimed are incomplete
or defective.
124 In his oral submissions, Mr Creighton said that he was resting his
defence of the respondent's claims on what he said was the unlawful
nature of the works, based on there being no building permit nor home
indemnity insurance.
125 Notably, the applicants do not argue, in the case of the first invoice,
that the work to which the invoice referred was not performed, nor that
the interest claimed was inconsistent with the contract.
126 Mr Alujevic explained the circumstances of the issuing of the first
invoice in terms of, on it becoming apparent that Mr Creighton was not
allowing the respondent to finish the works, the respondent invoiced him
on 27 March 2023 for the works done and unbilled for. Those works
included the vanity unit, a door, and tiling, evidence of which appears
in the HIBC report. As we have said, the fact of the works being
performed is not challenged.
127 Mr Alujevic also noted a number of deductions in the first invoice,
reflecting omissions made for things which had not been completed
(which, he said, included items which were partially complete).
He referred specifically to a deduction of $2,272.72 for 'gap to cover
shortfall from Buildmark quote to current market rates for outstanding
works', which was a credit to cover increased market prices for the work
still to be performed.55
128 Referring to the applicants' expressed sole ground in opposition, the
prohibition of a payment demand where no building permit and/or home
indemnity insurance have been obtained does not apply in this case for
reasons we have given. This ground therefore fails.
129 As for the ground in the applicants' written submission relating to
incomplete or defective works, to the extent that the applicants have
succeeded in their claims under the BSCRA Act, the respondents are
liable to either remedy the works or pay the reasonable cost of
54 We note that prior to home indemnity insurance being obtained where required, s 25C(1) of the HBC Act
precludes a builder making any demand for payment.
55 Hearing book at page 167.
-- 27 of 33 --
[2026] WASAT 87
Page 28
remediation (in this case we have determined the latter). The effect will
be to place the applicants in the position they would have been had the
respondent complied with its obligations. There is no basis for further
penalising the respondent by refusing their otherwise justified claim to
payment in accordance with the building contract.
130 For these reasons, the respondents' claim the subject of the first
invoice for $12,924.26 is allowed. The identical defence being raised
against the claim the subject of the second invoice for $6,489.49 in
interest under the contract, we also allow this claim.
Breach of contract by preventing access to site
131 The remedy sought by the respondent was that the applicants allow
unobstructed access to site for the respondent to complete outstanding
works. This possibility has now been overtaken by events. On this basis,
we decline to make any order on this claim.
Orders
The Tribunal shall issue orders in the following terms (the terms
'applicant/s' and 'respondent/s' here being appropriate according to each
respective proceeding):
CC 150 of 2025
The Tribunal orders:
1. Pursuant to s 38 and s 36(1)(b) of the Building Services
(Complaint Resolution and Administration) Act 2011 (WA), in
respect of complaint item 2A, by 14 August 2026 the respondent
shall pay the applicants the sum of $17,853.
2. Pursuant to s 38 of the Building Services (Complaint Resolution
and Administration) Act 2011 (WA), in respect of complaint
items 7, 8, 9, 10, 11, 12 and 18, the Tribunal declines to make an
order.
3. Pursuant to s 49(1) of the State Administrative Tribunal Act 2004
(WA), in respect of complaint items 5A, 5B, 5C, 6, 13 - 17 and
19, the applicants have leave to withdraw the complaints and they
are withdrawn.
-- 28 of 33 --
[2026] WASAT 87
Page 29
CC 364 of 2025
The Tribunal orders:
1. Pursuant to s 43 of the Building Services (Complaint Resolution
and Administration) Act 2011 (WA), in respect of complaint
items 1 and 2, the Tribunal declines to make an order.
CC 151 of 2025
The Tribunal orders:
1. Pursuant to s 43 and s 41(2)(b) of the Building Services
(Complaint Resolution and Administration) Act 2011 (WA), in
respect of complaint item 1, by 14 August 2026 the respondents
shall pay the applicant the sum of $19,413.75.
2. Pursuant to s 43 of the Building Services (Complaint Resolution
and Administration) Act 2011 (WA), in respect of complaint item
2, the Tribunal declines to make an order.
-- 29 of 33 --
[2026] WASAT 87
Page 30
Annexure A
-- 30 of 33 --
[2026] WASAT 87
Page 31
Annexure B
-- 31 of 33 --
[2026] WASAT 87
Page 32
Annexure C
-- 32 of 33 --
[2026] WASAT 87
Page 33
I certify that the preceding paragraph(s) comprise the reasons for decision
of the State Administrative Tribunal.
MR T Carey, MEMBER
24 JULY 2026
-- 33 of 33 --