Bradwell Constructions Pty Ltd v Queensland Building and Construction Commission [2026] QCAT 327
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Bradwell Constructions Pty Ltd v Queensland Building and
Construction Commission [2026] QCAT 327
PARTIES: BRADWELL CONSTRUCTIONS PTY LTD
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(respondent)
APPLICATION NO/S: GAR174-26
MATTER TYPE: General administrative review matters
DELIVERED ON: 2 July 2026
HEARING DATE: 19 May 2026
HEARD AT: Brisbane
DECISION OF: Member Lee Benjamin
ORDERS: The application to extend the time limit filed by the
Applicant on 11 March 2026 is granted.
CATCHWORDS: ADMINISTRATIVE LAW – ADMINISTRATIVE
TRIBUNALS – QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL – where application for
review filed out of time – whether to extend time to file
application for review – where extension of time given to
comply with direction to rectify by Queensland Building
and Construction Commission – where application for
review has merit – where discretion to extend time
unfettered – whether extension of time to file application
for review is in the interests of justice
Queensland Civil and Administrative Tribunal Act 2009
(Qld) s 33, s 61
Harper Property Builders Pty Ltd v Queensland Building
and Construction Commission [2018] QCATA 70
Quinlan v Queensland Building and Construction
Commission [2019] QCAT 349
Childs v Queensland Building and Construction
Commission [2019] QCAT 281
Barth v Queensland Building and Construction
Commission [2026] QCAT 63
-- 1 of 6 --
2
APPEARANCES &
REPRESENTATION:
This matter was heard and determined on the papers
pursuant to s 32 of the Queensland Civil and Administrative
Tribunal Act 2009 (Qld).
REASONS FOR DECISION
What is this decision about?
[1] On 11 March 2026, Bradwell Constructions (Bradwell) filed a review application for
a 27 June 2025 Queensland Building and Construction Commission (Commission)
notification that building work was not satisfactorily rectified at a Gold Coast property
(Property). The review application is around 230 days beyond the appeal deadline.
Bradwell seeks an extension of time. Bradwell’s explanation for the delay is that: (a)
the validity of an underlying internal review decision and internal review direction
were actively disputed; (b) related internal review proceedings were ongoing; and (c)
a related Tribunal proceeding concerning the same alleged defects had already been
commenced. The Commission opposes the extension and says, among other things,
that Bradwell’s (a) delay in lengthy; (b) explanation for the same in insufficient; and
(c) prospects of success in the underlying proceeding are poor. The question for the
Tribunal is whether it is in the interests of justice to extend the appeal deadline. In my
view, the answer is yes.
What happened?
[2] On 19 July 2024, the Commission received a ‘Residential and Commercial
Construction Work complaint’ from the Property owners (Owners) regarding work
performed at the Property (Complaint). The Complaint included 64 items. On 15
August 2024, the Owners sent an email to the Commission requesting that an
additional item be added to the Complaint. Collectively, the Complaint consists of 65
complaint items (Complaint Items).
[3] On 10 February 2025, the Commission notified Bradwell and the Owners of its
decision not to issue a direction to rectify or complete building work to Bradwell in
respect of any of the Complaint Items (Original Decision).
[4] On 19 February 2025, the Owners applied for an internal review of the Original
Decision (IR Application).
[5] On 17 April 2025, the Commission advised the Owners and Bradwell of its decision
(IR Decision) to:1
(a) give a direction to rectify in relation to 33 complaint items (DTR Items); and
(b) not give a direction to rectify in relation to 10 complaint items.
[6] On 23 April 2025, the Commission issued a direction to rectify or complete building
work to Bradwell (IR Direction), in accordance with the IR Decision.
[7] On 26 May 2025, Bradwell corresponded with the Commission requesting an
extension of time to comply with the IR Direction. Bradwell requested the extension
1 The Owners withdrew four Complaint Items from the Complaint. These items were therefore, not
considered in Internal Review.
-- 2 of 6 --
3
be in effect until the completion of a related QCAT proceeding (GAR279-25 – a
QCAT review application matter commenced by Bradwell to review the IR Direction)
and a related internal review matter.2
[8] On 27 May 2025, the Commission approved Bradwell’s extension of time application
to comply with the IR Direction to 24 June 2025.
[9] On 16 June 2025, Bradwell requested a further extension of time, again seeking an
extension to remain in effect pending the final determination of the related QCAT
proceeding and internal review matter (Further Extension Request).
[10] On 18 June 2025, the Commission declined to grant the Further Extension Request.
The Commission contends that the request was declined because:
(a) no attempt had been made to rectify any of the items shown in the IR Direction;
(b) the QCAT process can take 12 months or more to be finalised and it is not
reasonable for the Owners to wait until the QCAT proceeding is finalised to
have the items rectified;
(c) no record of the direction to rectify or any failure to rectify would be displayed
on their licence until after the QCAT matter was resolved; and
(d) if the QCAT process revealed the QBCC had been in error in issuing the
direction to rectify, the IR Direction would be removed from Bradwell’s licence.
[11] On 24 June 2025, the Owners wrote to the Commissioner and stated that Bradwell
had not attempted to rectify any of the Complaint Items contained in the IR Direction.
The Owners’ correspondence to the Commission may not be accurate.
[12] On 27 June 2025, the Commission issued the failure to rectify notice (FTR Notice)
to Bradwell.
[13] On 11 March 2026, Bradwell filed a review application for the FTR Notice.
What question needs to be answered?
[14] In an extension of time application, the Tribunal must consider whether it is in the
interests of justice to grant the extension.
What is the answer to the question?
[15] In my view (and I find that), it is in the interests of justice to grant an extension of
time.
Why are these the answer to the questions?
[16] The Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act)
empowers the Tribunal to extend a time limit fixed for the start of a proceeding.3
2 Application filed on 6 May 2025. Bradwell has been engaging with the Commission via a Tribunal
supervised alternative dispute resolution process.
3 QCAT Act, s 61.
-- 3 of 6 --
4
[17] In Harper Property Builders Pty Ltd v Queensland Building and Construction
Commission4 (Harper) the Appeal Tribunal said the following in relation to s 61:
(a) the discretion to extend time is unfettered;5
(b) the following matters have been recognised as particularly relevant
considerations in the exercise of discretion:
1. the length of the delay;
2. the adequacy of explanation for the delay;6
3. the merits of the proceeding sought to be litigated;
4. prejudice to others; and
5. the interests of justice (sometimes expressed as ‘general considerations of
fairness’).7
[18] I will briefly address these factors.
[19] On the length of the delay and prejudice: there is no dispute that the Applicant was
required to file its a review application for the FTR Notice in the Tribunal within 28
days after the “relevant day”.8 Bradwell was notified of the FTR Notice on 27 June
2025. Accordingly, Bradwell was required to have filed the review application by 25
July 2025. Bradwell did not file the review application until 11 March 2026, some
228 days outside the prescribed timeframe.
[20] The Commission submits that the delay in this case is “a very lengthy delay” in the
context of the 28-day time period intended by the QCAT Act. In making this
submission, the Commission has referred me to several cases in which past Tribunals
have cited delay periods of more six months to over two years as constituting “a very
lengthy delay”.9 I accept the Commission’s contention. I also accept the
Commission’s submission that it is entitled to expect external review applications to
be filed promptly.10 This factor obviously weights against Bradwell. However, as the
Commission concedes, the length of the delay is not the only factor to which the
Tribunal must have regard.
[21] On the explanation for the delay: Bradwell says:
4 [2018] QCATA 70.
5 Except to the extent that s 61 precludes such an extension when it would cause prejudice or detriment,
that could not be remedied by an appropriate order for costs or damages.
6 The Appeal Tribunal did not state that this factor was a pre-condition to the exercise of the Tribunal’s
Discretion.
7 At [26].
8 Section 33(3) of the QCAT Act provides that an application for the review of a “reviewable decision”
must be made within 28 days after the relevant day. “Relevant day” is defined in section 33(4)(a) of
the QCAT Act as “the day the applicant is notified of the decision”.
9 Commission submissions dated 16 April 2026 at [60] - [69]: Quinlan v Queensland Building and
Construction Commission [2019] QCAT 349 at [23]; and Childs v Queensland Building and
Construction Commission [2019] QCAT 281 at [15].
10 Commission submissions dated 16 April 2026 at [54] - [59]:
-- 4 of 6 --
5
(a) that the validity of the underlying IR Decision and IR Direction was actively
disputed;
(b) related QBCC internal review proceedings were ongoing; and
(c) a related QCAT proceeding concerning the same alleged defects had already
been commenced.
[22] The Commission submits that Bradwell has provided insufficient explanation for the
delay, in circumstances where:11
(a) a review of a decision does not stay a direction to rectify, nor does the lodging
of a review application before the Tribunal. Per section 87A of the QBCC Act,
the Tribunal cannot grant a stay of the effect of the decision to give a direction
to rectify to Bradwell;
(b) the delay is very lengthy; and
(c) on page 5 of the FTR Notice, the Commission advised Bradwell of their review
rights and the requisite timeframes for such rights to be exercised.
[23] On balance, while I accept that Bradwell’s stated explanation for its delay in filing the
review application is light on, I consider it sufficient. I would observe that the
legislative scheme for reviewing Commission decisions arguably invites multiple
review applications across separate but related matters for a single transaction of
building work on a single property.
[24] On the merits of the proceeding sought to be litigated: the Commission contends
that Bradwell’s prospects of success in their review application are poor and the
application lacks substance.12
[25] The Commission says that this is so because the matter concerns the question of
whether the building work undertaken by Bradwell at the direction of the Commission
was or was not of a satisfactory standard.
[26] The Commission submits that evidence before the Commission indicates that
Bradwell did not undertake any building work at the direction of the Commission
following the issue of the IR Direction (and subsequent extension period), operable
between 23 April 2024 and its expiry on 24 June 2025, as outlined above. The
Commission, therefore, submits the Applicant has not undertaken “building work”
pursuant to the IR Direction.
[27] It is unclear how the Commission can make these submissions. The Commission
appears to be aware that Bradwell (and its subcontractors) attempted to undertake
“building work” at the Property but was otherwise prevented from doing so by the
Owners. In Barth v Queensland Building and Construction Commission,13 the
Tribunal concluded that:
…it may be satisfied that “undertaking” building work is to include the
arrangement of meetings and inspections. If there exists a manifestation of an
11 Commission submissions dated 16 April 2026 at [47] - [48].
12 Commission submissions dated 16 April 2026 at [14] - [15]:
13 [2026] QCAT 63.
-- 5 of 6 --
6
intention to conduct on-site inspections and meetings, whether that be through
communication with the possessor of the property subject to the decision to
rectify, in a sense, building work could … have occurred as a matter of fact.14
if a builder endeavoured to comply … but was denied access by the homeowner,
it would be an unjust outcome to issue a decision that work undertaken by the
builder at the direction of the Commission was not of a satisfactory standard
because it wasn’t completed – even if such a statement is factually correct. If
such a decision were to issue as a matter of course, it may bring the building
industry into disrepute, striking an unreasonable balance between the interests
of building contractors and consumers, directly in breach of the Commission’s
objectives under the Act.15
[28] It seems to me that Bradwell has arguably good prospects for success in its
application. I find this factor to be compelling.
[29] On the interests of justice: in my view, when considering all the factors together, I
find that it is in the interests of justice for the Tribunal to exercise its discretion to
grant the extension of time application.
14 At [44].
15 At [59].
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2026/327