Fazlollahi v Iconic Line Constructions Pty Ltd [2026] QCAT 299
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Fazlollahi v Iconic Line Constructions Pty Ltd [2026]
QCAT 299
PARTIES: SAMIRA FAZLOLLAHI
(applicant)
v
ICONIC LINE CONSTRUCTIONS PTY LTD
(respondent)
APPLICATION NO/S: BDL198-23
MATTER TYPE: Building matters
DELIVERED ON: 12 June 2026
HEARING DATE: 4 June 2026
HEARD AT: Brisbane
DECISION OF: Member Alex Nelson
ORDERS: 1. Iconic Line Constructions Pty Ltd is to pay Samira
Fazlollahi the sum of $345,512.53 including damages
in the amount of $296,700 and interest in the amount
of $48,812.53.
2. It is declared that the Applicant had no liability to
pay the Respondent’s invoice issued on 19 April 2023
in the amount of $50,911.
3. It is declared that the Applicant is entitled to the
return of the $50,911 deposited by her to the trust
account of Romans and Romans Lawyers on or
about 2 May 2024.
4. The Respondent’s counter-application filed 18
December 2023 is dismissed.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION –
EXTRAS AND ALTERATIONS – where building
owner and building contractor signed a contract for the
construction of a new home - where the building
contractor made a further claim for payment for site
work claimed as a provisional sum as well as amount
in addition to the provisional sum for unforeseen rock
excavation – where the building contractor did not have
the foundations data at the time of entering the contract
where no variation was agreed - whether the building
owner is obliged to pay that invoice – whether the
-- 1 of 9 --
2
contract was validly terminated by the building owner
– whether the building owner is entitled to damages -
whether the building owner is entitled to costs
Queensland Building and Construction Commission Act
1991 (Qld), s 77, Schedule 1B s 3, Schedule 1B s 5,
Schedule 1B s 31, Schedule 1B s 40
Queensland Civil and Administrative Tribunal Act 2009
(Qld), s 57, s 92, s 93
APPEARANCES &
REPRESENTATION:
Applicant:
Respondent:
Self-represented
No appearance
REASONS FOR DECISION
[1] This is a residential building dispute.
[2] The Applicant purchased vacant land in Milton and set about organising the
construction of a new house which I am satisfied was intended to be used by her as an
investment property, in the sense that it was to be rented out through an agent once it
had been constructed. Armed with plans and engineering drawings that had been
prepared for the lot by a well-known residential construction company and firm of
engineers, the Applicant sought and obtained tenders for the construction. She
accepted a tender from the Respondent and they entered into a Home Industry
Association (‘HIA’) standard form contract on 20 June 2022.
[3] It was not a great start to that relationship when the Respondent recorded in the
contract that the price excluding GST was $816,328, then added $90,703 (11.111%)
for the GST component.
[4] The relationship soured completely on about 19 April 2023 when the Respondent
issued an invoice for ‘site works variation’ for the amount of $50,911. When the
Applicant disputed that invoice, the Respondent purported to suspend its work under
the contract and that suspension persisted for about one year until the parties reached
a further agreement that:
(a) the Applicant would pay the disputed amount to the trust account of the
Respondent’s solicitors; and
(b) the Respondent would complete the construction of the house.
[5] Although the Applicant deposited those funds, the Respondent reneged on doing the
further work, leading to the construction contract being terminated by the Applicant.
[6] The Applicant retained a new builder to complete the construction of the house and
she now seeks:
(a) relief from payment of the invoice from the builder for disputed charges
amounting to $50,911.11 and, by extension, the release of that amount from the
funds held on trust by the Respondent’s former solicitors;
(b) damages for delay in completing the construction at the contract rate of $50 per
day;
-- 2 of 9 --
3
(c) damages for breach of contract where it became necessary to appoint a new
builder to finish the construction work at an additional cost, less the amount of
$200,000 which the Applicant had received from the Queensland Building and
Construction Commission (‘QBCC’) under the Queensland Home Warranty
Scheme;
(d) damages for loss of rental income at the rate of $2,500 per week;
(e) interest on the damages so awarded;
(f) costs.
Respondent Failing to Comply with Directions
[7] The Respondent was directed to file a Response by 27 October 2023, but it did not do
that until 19 December 2023 at which time it also filed a counter-application seeking
payment of its disputed invoice.
[8] On 26 August 2024 directions were made for the filing and delivery of statements of
evidence. The Applicant complied but the Respondent did not do so.
[9] On 25 November 2024 the date for the Respondent’s statements of evidence was
extended, but still, it did not comply.
[10] On 22 May 2025 the parties were directed to file and deliver an amended application
and amended counter-application. The Respondent was given yet another opportunity
to file and deliver its witness statements. Those directions provided that the parties
would not be permitted to adduce evidence at the hearing that was not contained in
the statements without justifying the need for such additional evidence to the Tribunal.
Still the Respondent did not comply.
[11] On 16 July 2025 the Tribunal again extended the date for the Respondent to file its
statements of evidence. Again, it did not comply.
[12] The time for the Respondent to comply was extended again on 22 September 2025
with a direction that a failure to comply may entitle the Applicant to a ‘final decision
in the proceeding’. Still the Respondent did not comply.
[13] On 7 November 2025 the Applicant applied for a decision by default but that was
refused on 12 November 2025. It was, however, directed that the Respondent was not
permitted to file an amended counter-application and was not permitted to file or rely
upon any statements of evidence at the hearing which was then scheduled for 4 and 5
June 2026.
[14] On 2 June 2026 it was directed that if the Respondent failed to attend at the hearing
on 4 and 5 June 2026, the counter-application filed on 18 December 2026 would be
dismissed.
[15] Given the history of non-compliance by the Respondent, it came as no surprise that
the Respondent failed to appear when the trial started on 4 June 2026. The Hearing
Support Officer searched for the Respondent outside the hearing room but to no avail.
Accordingly, I dismissed the counter-application.
[16] The Tribunal may ‘act in the absence of a party who has had reasonable notice of a
proceeding’ under the general powers in s 57 of the Queensland Civil and
Administrative Tribunal Act 2009 (Qld) (‘QCAT Act’). Further, under s 93 of
the QCAT Act, the Tribunal may hear and decide a matter in a person’s absence,
-- 3 of 9 --
4
including where the person is a party, if the person has not attended a hearing and the
Tribunal is satisfied the person has been given notice of the hearing under s 92. I was
satisfied that a compliant notice had been sent to the Respondent and I proceeded with
the hearing in its absence.
[17] The Applicant gave her evidence and called her witnesses to give their evidence which
plainly went unchallenged.
Background
[18] The contract included a progress payment schedule as follows:
(a) deposit, $45,351;
(b) site Cut, $63,492;
(c) pool shell installed, $72,562;
(d) slab pour, $136,055;
(e) frame, $226,758;
(f) enclose, $181,406;
(g) fixing, $136,055; and
(h) practical completion, $45,352.
[19] Schedule 3 of the contract identified that the contract price included a Provisional Sum
allowance of $60,000 for ‘Provide Site Works Allowance above standard Inclusions’.
It also acknowledged that in order for that item to be included in the contract as a
Provisional Sum, the amount that was included was a reasonable estimate of the price
for the supply of the item and/or the work to be performed.
[20] Following payment of the deposit and payment of an invoice for the construction of
the swimming pool shell, on 12 October 2022 the Respondent issued an invoice for
the ‘site cut’ for an amount which was identical to the progress payment amount at
paragraph 18(b) above. On or about 6 October 2022 the Applicant had visited the site
and was told by the Construction Manager that ‘there were no unusual conditions on
site such as rocks or any other issues’. The Applicant paid the ‘site cut’ invoice and
the construction continued.
[21] The slab was constructed and the Slab Pour invoice was issued on 27 February 2023.
That was paid in full, as was the Frame stage invoice issued on 5 April 2023.
Site Cost Variation
[22] On 19 April 2023 the Respondent issued an invoice for ‘site cost variation’, claiming
the sum of $50,911 including GST. That invoice was not sent to the Applicant until a
week later, at which point the Respondent immediately queried her liability to pay it.
She received an email response in the following terms:
total site and foundation cost $140,065.93 invoice on link below
(please note some invoices sent after the works as we have varies account
payment period up to 60 days account)
[link]
-- 4 of 9 --
5
Our calculations for standard site and foundation cost $37,640
Slab area 282m2
Site prep,Concreting prep and pour, (no piers/special strip footing): $9,000 +
$2,000 pump = $11,000
Concrete supply M type slab 57m3 @ $220/m3 = $12,540
Pods,reo,Steel bar : 282 units x $50 = $14,100
Provisional allowance for site cost over standard $60,000
I will fix the invoice dates
[23] It should be noted, the contract does not contain any provision about the ‘standard site
and foundation cost’ being $37,640.
[24] The Applicant immediately challenged this invoice and asked to be provided with
supporting documents. The Respondent then wrote, ‘As you reject paying the agreed
completed extra works, we are putting the job on hold for 10 business days or more’.
[25] The Respondent provided documents which it alleged supported the additional
charges that were being levied, but:
(a) two of the documents provided were quotes only, and there was no evidence
they were ever accepted, let alone paid; indeed one of them had area for the
respondent’s signature as a form of acceptance, but that was still blank;
(b) a number of the invoices were plainly for works that were part of the ‘Slab Pour’
stage.
[26] The Respondent gave a further explanation that during the site cut the Respondent had
unexpectedly encountered rock, but of course that was at odds with the statement that
had been made by the site supervisor on 6 October 2022. In addition, none of the
supporting ‘invoices’ evidenced significant rock breaking or dumping activities.
[27] Had it been the case that significant rock was rock was discovered and a variation to
the contract was required because the price was to increase, the Respondent had an
obligation under s 40 of Schedule 1B to the Queensland Building and Construction
Commission Act 1991 (Qld) (‘QBCC Act’) to reach an agreement about the additional
and unexpected work that was required and to put that into a written variation before
the first of the following happened:
(a) within 5 business days of that agreement being reached; and in any event
(b) before any domestic building work the subject of the variation had started.
[28] There was no agreement about the variation, nor was there ever a written version of
the variation before the work was (allegedly) undertaken.
[29] Another of the Applicant’s complaints about the invoice for ‘site cost variation’ was
that clause 21.10 of the HIA contract provides:
Where the provisional sum relates to excavation, footings or the slab, the builder
is only entitled to claim an amount in excess of the allowance where the builder
had the foundations data when the builder entered into this contract, the need
for the additional amount cannot be established from that data.
[30] The Applicant says that she cannot recall the Respondent seeking access to the
property for site enquiries at any time before the contract was signed. She provided a
-- 5 of 9 --
6
chain of email correspondence with the Respondent on 1 August 2022 which made it
clear that the Respondent was not in possession of the foundations data at that time,
which was about 6 weeks after the contract had been signed. Even as late as 25 August
2022 the Respondent sent an email to the Applicant to the effect that it had been unable
to get the soil test results.
[31] I find that the Respondent had signed the contract with the Applicant at a time when
the Respondent did not have the foundations data. I am fortified in that conclusion by
the fact that the QBCC investigated the Respondent and then issued it with an
infringement notice for breaching s 31(2) of Schedule 1B of the QBCC Act by failing
to obtain the foundations data before entering into the contract with the Applicant.
[32] I am not at all satisfied that the Respondent actually incurred the additional costs that
it tried to claim from the Applicant, but even if those costs had been incurred, I am
not satisfied that the Respondent had any entitlement to pass them on to the Applicant
as a ‘site cost variation’ because it was not ‘site work’ and because the Respondent
did not comply with s 40 of Schedule 1B of the QBCC Act.
[33] On 6 June 2023 the Applicant referred the dispute to the QBCC. When the Respondent
refused to engage, the QBCC issued a letter confirming that it was unable to assist
further, thereby enlivening the jurisdiction of this Tribunal.1
[34] The Applicant filed an application for domestic building disputes in the Tribunal on
4 July 2023. Despite that, the Respondent’s ‘suspension’ of work continued through
to the following year.
[35] On 11 March 2024 the Applicant issued the Respondent with a notice to remedy
breach. Clause 28.5 of the contract gave the Respondent five (5) working days to file
an application in the QBCC or QCAT if it wished to prevent termination of the
contract, but it did not take that step.
[36] On 19 April 2024 the Applicant generously and sensibly offered to pay the amount of
the disputed ‘site cost variation’ invoice to the trust account of the Respondent’s
solicitors on the basis that the Respondent recommence work within 10 days and
continue through to Practical Completion. On 1 May 2024 the Respondent accepted
that offer and on the following day the Applicant duly deposited $50,911 to the trust
account of Romans and Romans Lawyers.
[37] On 20 May 2024, and then again on 29 May 2024, the Applicant sought confirmation
that the Respondent had recommenced work on her property and sought a copy of the
design and inspection certificates for the work that had been undertaken to that point.
The Respondent gave no reply and the requested information and certificates were not
provided.
[38] Despite the agreement that had been made, the Respondent did not ever recommence
work on the Applicant’s property.
[39] On 5 June 2024 the Applicant terminated the contract and I find that termination was
valid because:
(a) the Respondent had suspended its works when it was not entitled to do so and
that amounted to a substantial breach under clause 28.1 of the contract;
1 QBCC Act, s 77(2).
-- 6 of 9 --
7
(b) the Applicant had given the Respondent a notice to remedy breach;
(c) the Respondent did not comply with that notice to remedy breach within 10
working days; and
(d) the Respondent did not apply to set aside the notice to remedy breach.
[40] On 7 June 2024 the Applicant made a claim for assistance under the Queensland Home
Warranty Scheme and on 25 March 2026 the QBCC paid the Applicant $200,000 in
respect of that claim.
[41] The Tribunal has jurisdiction to hear and decide this building dispute, and to order
various remedies under s 77 of the QBCC Act. Pursuant to s 77(3) of the QBCC Act
the Tribunal can:
(a) order the payment of an amount found to be owing by one party to another;
(b) order relief from payment of an amount claimed by one party from another;
(c) award damages, and interest on the damages at the rate, and calculated in the
way, prescribed under a regulation;
(d) order restitution;
(e) declare any misleading, deceptive or otherwise unjust contractual term to be of
no effect, or otherwise vary a contract to avoid injustice;
(f) avoid a policy of insurance under the statutory insurance scheme;
(g) order rectification or completion of defective or incomplete tribunal work;
(h) award costs.
[42] I find that the Applicant had no liability to pay the invoice for ‘site work variation’ in
the amount of $50,911 (or any amount). Accordingly, the funds held on trust by
Romans and Romans Lawyers, together with any interest earned by the investment of
those funds, should be released to the Applicant forthwith.
Delay Damages
[43] Clause 3 of the contract required the Respondent to reach Practical Completion within
340 calendar days from ‘Commencement’.
[44] On 22 February 2023 the Respondent sent a notice of commencement of construction
to the Applicant. Understandably, the Applicant objected to that notice and required
the Respondent to issue a new notice of commencement of construction. The
Respondent did so, claiming to have commenced work on 22 December 2022. The
Applicant continued to object until eventually the Respondent gave a notice of
commencement of construction with effect from 15 September 2022. Even that I do
not accept as being an accurate record of when work actually commenced
[45] The date of ‘Commencement’ was defined in clause 2.1 of the contract to mean the
Anticipated Start Date stated in Item 14 of Schedule 1 of the contract. As that item
was left blank by the parties, the contract’s default position was that ‘Commencement’
was 60 days from the contract date. As the contract date was 20 June 2022, I find that
Commencement was 22 August 2022 and it follows that the date for Practical
Completion was therefore 25 July 2023. That period was able to be extended pursuant
-- 7 of 9 --
8
to clause 17 of the contract if there were ‘claimable delays’, but I find that there were
none.
[46] Clause 32 of the standard form contract provided that late completion damages were
payable at $50 per day from the due date for Practical Completion until the contract
was brought to end, including by termination.
[47] I find that the Applicant was entitled to late completion damages from 26 July 2023
until 5 June 2024, being a total of 316 days which equates to $15,800.
Damages for Additional Costs to Complete the House
[48] Having terminated her contract with the Respondent, the Applicant obtained three
quotes from builders to complete the work and then selected the cheapest of the three,
however that quote was for $896,346. There was a necessary variation to that contract
attracting an additional amount payable of $5,207 in order to correct the misalignment
of framing work that had been completed by the Respondent, making the total to be
paid to the new contractor $901,553. That work has since been completed and those
additional costs incurred.
[49] GST on the Respondent’s contract price would ordinarily have been $81,632. There
were agreed variations which totalled $66,911 inclusive of GST. The total price that
was to be paid by the Applicant was therefore $964,871.
[50] Disregarding the amount deposited to the Respondent’s solicitors’ trust account, the
Applicant had paid the Respondent a total of $544,218. At the time of termination,
there remained an amount of $420,653 that would have been payable to the
Respondent, had it completed the construction work
[51] I find that the Respondent is liable to pay the Applicant damages for breach of contract
being the additional costs that the Applicant incurred in having the house construction
completed by another builder ($901,553) less:
(a) the $200,000 received from the QBCC under the Queensland Home Warranty
Scheme; and
(b) the amount that was remaining to be paid under the contract with the Respondent
($420,653).
[52] I find that the Respondent is liable to pay the Applicant damages for breach of contract
in the amount of $280,900.
Damages for Lost Rental Income
[53] The Applicant’s claim for loss of rental income for the period between expected
Practical Completion and the date when the house construction was in fact finished
by another builder was supported by a letter from a real estate agent giving the
Applicant a rental appraisal of $2,500 per week, but the agent did not give a statement,
nor were they called to give evidence at the hearing. Even putting those matters aside,
I had no evidence about the agent’s expertise.
[54] There was also no evidence to establish what the likely outgoings would have been
had the property been available and been rented for that weekly amount.
[55] At the hearing the Applicant abandoned that aspect of her claim. Accordingly, I
dismiss the claim for damages for loss of rental income.
-- 8 of 9 --
9
Interest
[56] Section 77(3)(c) of the QBCC Act provides that the Tribunal may award ‘interest on
the damages at the rate, and calculated in the way, prescribed under a regulation’.
Regulation 54 of the Queensland Building and Construction Commission Regulation
2018 (Qld) (‘QBCC Reg’) provides:
(1) For section 77(3)(c) of the Act, interest is payable on the amount of
damages awarded—
(a) if the parties have entered into a contract—at the rate provided
under the contract; or
(b) at the rate agreed between the parties; or
(c) otherwise—at the rate of 10%.
(2) The interest is payable on and from the day after the day the amount
became payable until and including the day the amount is paid.
[57] The Applicant should have interest at the rate of 10% per annum upon the late
completion damages from 5 June 2024 until 12 June 2026 being 738 days and equating
to $3,192.15.
[58] The Applicant should have interest at the rate of 10% per annum upon the damages
payable for the additional costs that the Applicant incurred in having the house
completed. That interest should run from the date that the Applicant contracted with
the alternate builder, being 17 March 2025. That is 453 days and equates to
$34,862.38.
[59] The Applicant should have interest upon the monies that she was required to deposit
to the trust account of the Respondent’s solicitors. There is no evidence that the sum
deposited to the Respondent’s solicitors’ trust account was invested. In circumstances
where there was clearly no proper basis for the ‘site work variation’ invoice to have
been issued, and where those funds had been deposited in good faith after reaching a
further agreement with the Respondent for the completion of the construction, I find
that the Respondent should pay interest on that sum at the rate of 10% per annum from
the date of its deposit, 2 May 2024 until 12 June 2026 being 772 days, amounting to
$10,758.
Costs
[60] The parties may make written submissions about costs, including:
(a) who, if anyone, should pay costs;
(b) whether those costs should be assessed on a standard or indemnity basis; and
(c) identifying the relevant court scale that should apply.
[61] The Applicant has until 26 June 2026 to file and serve her submissions.
[62] The Respondent has until 10 July 2026 to file and serve its submissions.
[63] I will determine the issue of costs on the papers after that time.
-- 9 of 9 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2026/299