Dias & Butcher v Dale Hassam trading as Richters Kitchen and Glass [2026] QCAT 113
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Dias & Butcher v Dale Hassam trading as Richters
Kitchen and Glass [2026] QCAT 113
PARTIES: STEVEN DIAS and NICOLE BUTCHER
(applicants)
v
DALE HASSAM TRADING AS RICHTERS
KITCHEN AND GLASS
( respondent)
APPLICATION NO/S: BDL033-25
MATTER TYPE:
DELIVERED ON:
Building matters
9 March 2026
HEARING DATE: 2 March 2026
HEARD AT: Wynnum
DECISION OF: Member Roney KC
ORDER/S: I order and declare that the Applicants are
relieved from payment of any further sum which
might have fallen due under the contract, if any,
and declare that there is no further payment due.
I order that the Applicants be awarded damages
or compensation for breach of contract in the sum
of $34,450 against the respondent, with such sum
to be paid within 30 days of the making of these
orders.
I grant the parties liberty to apply in respect of
any other consequential or other orders which
might be required to be made.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
GENERALLY – PERFORMANCE OF WORK –
REMEDIES FOR BREACH OF CONTRACT –
DAMAGES – MEASURE OF – where home owners
contracted with a cabinetmaker to construct a kitchen
to an existing house – where repeated delays and
interruption to the work – where the works never
completed – lack of due diligence based on delay in the
progress of construction – where the owners sought
damages for the cost of replacing the kitchen entirely
rather than repairing or completing existing work
-- 1 of 22 --
2
Queensland Building and Construction Commission
Act 1991 (Qld), s 77, Schedule 1B, s4,
s14, s40 & s41, Part 3 Division 2
Dura (Australia) Constructions Pty Ltd v Hue
Boutique Living Pty Ltd (No 3) [2012] VSC 99
Hometeam Constructions Pty Ltd v McCauley [2005]
NSWCA 303
Hooker Constructions Pty Ltd v Chris’s Engineering
Co [1970] ALR 821
Walsh v Australian Building and Construction Group
[2016] QCAT 187
APPEARANCES &
REPRESENTATION:
Applicants: Self-Represented
Respondent: Self-Represented
Introduction and the scope of the issues for determination .................................................. 2
The chronology of the parties’ dealings and progress of the works ...................................... 4
Jurisdiction of the Tribunal .................................................................................................. 10
Domestic Building Work and warranties under the QBCC Act ........................................... 11
Findings in relation to the incomplete and defective state of the works.............................. 16
Polytec warranty process and delay ................................................................................... 17
Tile Selection and Delay. .................................................................................................... 17
Delays Due to Changing the Overhead Cabinet Design and ducting issues ..................... 18
Allegations that the applicants improperly engaged Outside Contractors .......................... 18
The Allegation of Refusing Access to Site .......................................................................... 19
Findings in relation to fundamental breach and the right to terminate the contract for
demonstrated lack of due diligence..................................................................................... 20
The expert evidence and the solution to the defective and incomplete state of the works 21
Disposition and Orders ........................................................................................................ 22
REASONS FOR DECISION
Introduction and the scope of the issues for determination
[1] The applicants entered into a Master Builders QLD - Basic Works Contract -
Residential) (the contract) with the respondent, who operated a cabinet making
business called Richters Joinery (Richters) and traded as Richters Kitchen and Glass.
The contract provided for the construction and installation of a kitchen in their home
in Agnes Waters. The price for the works was $38,220.67.
-- 2 of 22 --
3
[2] There were some irregularities in relation to who the proper parties were to the
dispute, and which I drew to the attention of the parties. They included that in fact,
only the female applicant was named on the contract, and the party named as the
builder was identified as something suggesting it was a corporation not a natural
person. I was told by the parties to proceed on the basis that the parties to the contract
were the parties to this proceeding and I have done so.
[3] The applicants seek remedies that arise out of the way in which that contract was
performed, or rather not performed. During the course of their opening, the applicants
made clear that their claim was for 3 forms of relief. Other various claims were not
pressed or were abandoned so I will not refer to them.
[4] The first was that they ought to be given the benefit of an order or declaration that
they were relieved from payment of the balance due under the contract of $10,235.29.
[5] Secondly, they sought an order by way of damages or compensation for the yet to be
expended cost to replace the partially built kitchen put in by the respondent on the
basis that the only appropriate remedy for the defective and incomplete works was a
complete replacement.
[6] After initially, articulating a claim that they be entitled to interest on the amount that
they had already paid under the contract, the applicants elected not to prosecute that
claim because they were not pressing for recovery of the costs they had already paid
to this respondent for the cabinet work. They instead sought damages reflecting the
cost that they would have to pay to someone else to complete the kitchen and since
that cost had not yet been incurred no claim for interest upon it would lie.
[7] In relation to whether a replacement kitchen was appropriate as distinct from either
permitting the respondent to complete the kitchen or incurring the cost to make good
what was there, the applicants relied upon the professional opinion of an experienced
builder Leonard Smith.
[8] The applicants contend that three independent contractors were engaged solely to
inspect the existing kitchen, as left by the respondent, and to provide professional
advice and quotations on either completing the works or undertaking a full
replacement. The applicants contend that all three advised that, given the extent of the
defects, it would be more appropriate to remove the existing kitchen entirely and start
afresh. In fact, the quotations they provided to replace the kitchen do not specifically
say that although there is a report from a builder who does.
[9] They put into evidence three quotes from other suppliers to install a replacement
kitchen. None of those suppliers was the subject of any cross-examination by the
respondent to challenge the reasonableness of the estimates. The applicants elected to
submit that the quotation to perform the works which sat between the other two
quotations, was the one that they relied on in seeking an order for damages or
compensation. That quote was for an amount of $34,450 and was from an
organization called Cabinet Connections. Again, there was no submission made by
the respondent to mount any challenge to this as a reasonable assessment of the cost
to replace this kitchen. Instead, the respondent placed his emphasis on the contention
that it was unfair or unreasonable, not to permit them to go back to complete this
kitchen. He did not articulate a contractual or other legal basis upon which it
contended that it should be allowed to do that, or was legally entitled to do so. He did
mount a case as to why he thought that should occur.
-- 3 of 22 --
4
The chronology of the parties’ dealings and progress of the works
[10] The contract provided for a construction period of 30 days, but with the specified
commencement date under item 8 of 26 June 2023 with practical completion required
by 7 August 2023. Despite practical completion being required by 7 August 2023, the
contract was associated with a document that provided for an “anticipated project
timeline for (the) kitchen renovation” in these terms;
TASK ANTICIPATED DATE
Electrical Pre-Wire 13/11/2023 - 21/11/2023
Plumber Rough-In 13/11/2023 - 21/11/2023
Kitchen Install 22/11/2q23 to 24/11/2023
Stone Bench Installation 04/12/2023 - 08/12/2023
Stainless Steel Bench Installation 04/12/2023 - 08/12/2023
Plumbing Hook-Up 11/12/2023 - 15/12/2023
Tiled Splashback 11/12/2023 - 15/12/2023
Electrician Hook-Up 11/12/2023 - 15/12/2023
[11] All those dates post-date the agreed practical completion date. Whatever
inconsistencies are to be found in those documents, it is clear that all of the parties
had as a common understanding and expectation that this kitchen to be completed and
in use by Christmas 2023.
[12] The first 2 substantial payments to be made under the contract were made. The 3 rd
instalment of $11.466.20 for stage 3 of the works being the 3 rd of 4 scheduled
payments was made on 3 August 2023, so when no work had been done on site to
install any of the kitchen. That left only one last payment of $7,644.13 being 20% of
the contract price on practical completion. Practical completion has never been
achieved.
[13] The respondent’s workers first attended the property to commence work in mid-
November 2023. By then the date for practical completion had passed 3 months
earlier, and it was only 6 weeks till Christmas. There was no usable kitchen in the
house once work commenced. Work commenced on 15 November 2023 when
cabinetry and the applicants’ appliances were delivered. The installation did not start
until 2 weeks later.
[14] Precisely why it was that although the contract was entered into in December 2022,
the date for practical completion was allowed to pass in August 2023 without the
works having been performed is not fully explained in the material. It is not however
critical to the issues to be decided.
[15] In April 2023 the respondent was still doing arrangements for a check-measure. On
15 May 2023 the applicants first received the CAD design to approve.
[16] In September 2023 the applicants tried on numerous occasions to call Richters and
email them however the message bank was full and some emails were bouncing back.
The respondent himself would not respond. The applicants had concerns that they had
closed down leaving them feeling panicked as they had a large amount of their money
plus their appliances and kitchen sink and accessories. They did a 3 hour return trip
-- 4 of 22 --
5
into Bundaberg twice to find the respondent’s front shop door open but no one
present.
[17] In October 2023 one of the applicants called and spoke to the respondent himself, and
expressed concerns that the kitchen hadn't started and they had family staying for
Christmas and needed the kitchen to be completed before their arrival. The respondent
said with a jovial laugh ...” oh it will be in well before Christmas”. It wasn’t.
[18] On 31 Oct 2023 the applicants emailed the following to Richters;
Hi team, I'm following up on our kitchen install. Do we have a date as
yet?
I am quite concerned about the length of time it is taking. We are entering
into November and it has now been 12 months since we started this
process. Is there anything we can do this end to make this happen? We
would appreciate an update.
[19] The works did commence with the delivery of materials to site on 15 November 2023,
some 3 months after the date for practical completion was required, but shortly after
the works commenced, the respondent’s staff left the site saying they were finished
for Christmas.
[20] On 20 Nov 2023 the applicants emailed asking again for an install date and noted they
hadn't received any contact from an electrician or plumber and asked if there needed
to be holes cut through the floor for the plumbing before the cabinetwork installation.
They asked this question a few times as they were concerned that the respondent had
said that his plumber was sick and that the plumbing roughing in can be done after
the kitchen is installed. He was thought to be reluctant to send out trades and wouldn’t
use local trades, apparently preferring his own form elsewhere.
[21] On 22 Nov 2023 the respondent returned with a tradesperson to start the kitchen
install. At that time there was a cabinetry mountain in the middle of their loungeroom
creating a safety issue. They only managed to re-sheet one wall and did not place the
insulation back in the wall. When they were about to leave for the day, one of the
applicants asked why the insulation was over the other side of the room in which they
replied "we thought it was industrial waste". They also said that they didn’t really
need it.
[22] Little else then happened to progress the work, until on 12 Dec 2023 there was a
meeting to discuss timelines. There was work on the site in the week before Christmas
but by now the applicants were noticing defective work and one particular matter was
that with the electrician on site he had to cut the rear of the board that divided the two
ovens in the oven tower cabinetry as there was no vent allowance as per the oven
supplier’s requirements and the Building Code, so Ms Butler believed. She raised this
as a concern. As was that the cabinetry was out of alignment. There were visible glue
lines on edges of cabinetry and tape mark lines. At one point a visitor pulled at the
top oven handle and the whole oven slid out towards him.
[23] Next in January 2024 they were advised by email from Richters that Wide Bay Stone
was supposed to be on-site to measure up for Ceasar Stone bench. That did not occur.
-- 5 of 22 --
6
[24] At this stage it had been observed that there was a defect in the cabinet doors supplied
to the respondent by its contractor Polytec. I will describe that problem later, but it
was a problem that belonged to the respondent not the applicants.
[25] Virtually nothing more then happened to advance the works for months.
[26] In March 2024, the applicants sent three notices to remedy breach, respectively on the
11th , 19th and 21st March 2024.
[27] The 11th of March notice came with a letter that said that they were concerned over the
delayed completion of the kitchen and insisted on a timely and expeditious
completion of the installation in accordance with the contract. It mentioned that they
were being subjected to considerable inconvenience and disruption. They said that
they had chosen the respondent based on its reputation for delivering high quality
craftsmanship, but the prolonged delay was causing them undue, stress and had
financial implications for them. They emphasised the importance of adhering to the
contractual obligations and requested that the respondent provide a detailed
explanation for the delay and a revised timeline to complete the works. It attached a
report identifying what was required to be rectified and invited him to treat the matter
with utmost urgency and take immediate steps to rectify the position to ensure prompt
completion. It attached a document described as a breach of contract Notice number
2. This contract had terms that permitted such notices to be given to invite remedial
activity. There was no response offering to perform.
[28] The next notice was 8 days later, on the 19th of March 2024, which referred to the
11th of March email and again requested an immediate response, because none had
been received. It noted that they had since spoken to the foreman who had confirmed
that the respondent had received the 11th of March email but that he had said that
there would be delays due to the absence of one of the office staff. The letter
complained that there had been delays ongoing since June 2023 and then sought
confirmation about various aspects of the state of the works, including requesting an
indication of whether the overhead cupboards, stonework, kickboards, bins and other
hardware was ready to be installed. There was no response to this notice offering to
perform either.
[29] The letter of 21 March 2024 was not in evidence, and could not be located it was said,
but was said to be to similar effect.
[30] None of these notices was responded to either by a responsive letter or other
communication, or by a response which actually led to the performance of the works.
[31] Some activity resumed in April 2024. On 8 April 2024 the respondent’s workers
arrived at 10.30am and departed at 6.45pm. The workers arrived in the rain and the
overhead cabinetry, being the oven tower, bottom board above fridge, overhead
cabinetry and new oven were strapped down on the back of a long flatbed trailer
covered with a tarp. When they carried in the wall oven tower inside and turned it
upright, water from inside it spilled out onto the floor. The applicants raised concerns
about things being wet but were told the panels were made quite well and not to worry.
The respondent ended up pulling all the cabinetry out at various stages as nothing was
fitting effectively or lining up.
[32] The bins and hidden drawer they were given were again the wrong ones therefor the
respondent left an empty cabinet space until next the visit. The applicants could not
-- 6 of 22 --
7
use the cooktop as they now had to wait for electrician to return to install power points
etc. They removed glue from floor so that they could then remove Texta markings off
the tile floors.
[33] There was more work later in April 2024, but the applicants were not getting
responses to their requests to know what was going on. Richters sent them a variation
after the respondent itself could not find an electrician to do the works and they were
told to find their own electrician at their own expense, even though it was part of the
Richter contract to supply and oversee the electrical work.
[34] On 23 April 2024, upon calling Mariah Robinson (the sales and design consultant)
asking when Richters would return on site to complete defects, Ms Butcher was told
that she would no longer help them or answer questions and everything had to be
referred to the respondent himself.
[35] On 9 May 2024 the Nikpol overhead cupboards were removed and taken back to
Richters. On 21st May Mr Dias called the respondent because they had received no
contact since they removed the Nikpol overhead cabinet on 9th May.
[36] A litany of problems was emerging concerning the work which had been carried out.
By 7 June 2024 the applicants were trying to get the regional manager from Master
Builders Queensland to assist, but not intervene, to get something to happen.
[37] On 18 July 2024 Polytec was due to be back to do the cupboard warranty re-
installation. But when they got there, they found that Richters had changed the
measurements for the work and failed to update Polytec of the new measurements for
the overhead cupboards above the fridge and therefore they were not replaced and to
this day are missing.
[38] For all practical purposes, all work on-site ceased from July 2024, and no further work
of any kind was done on the site again.
[39] The last occasion on which any representative of Richters attended the property to
undertake work was on 12 July 2024. On that date, the overhead cabinetry was
removed for a third time, as it continued to be incorrectly constructed and remained
unfit for purpose.
[40] Subsequently, 3 weeks later, on 5 August 2024, the applicant Mr Dias, contacted the
Richters' site foreman, to enquire as to when the tradesmen would next return to the
property to continue and complete the outstanding kitchen works. The site foreman
responded with words to the effect that "unfortunately it won't be for a while," citing
his being away on holiday and advising that the other Richters tradesmen were
presently engaged on new kitchen installations elsewhere in Agnes Waters.
[41] The applicants say that this response, coupled with the lack of any further attendance
or communication from Richters, reinforced their understanding that completion of
their kitchen was not being prioritised. It further exacerbated their frustration, distress,
and the ongoing disruption caused by the prolonged and incomplete state of the
works.
[42] The applicants say that by this point, they had already given Richters numerous
opportunities over many months to rectify and complete the kitchen. It was at this
stage that they decided that they had been more than reasonable, that Richters had
failed to meet their obligations despite repeated assurances, and that they could no
-- 7 of 22 --
8
longer rely on them to finish the job. Accordingly, they determined that they did not
want Richters to return to their property and that the matter would need to be resolved
through legal proceedings.
[43] I find that this decision, albeit not communicated in precisely those terms, was
communicated and constituted an election to terminate the contract and proceed with
a legal remedy
[44] A dispute application was lodged with the Queensland Building and Construction
Commission (QBCC) on 5, August 2024. The applicants then formally lodged a claim
with the QBCC on 2 September 2024. It was a Residential and Commercial
Construction Complaint Form. It set out 53 complaint items and said access would be
permitted to the site. It said that;
Various defects throughout the construction of our new kitchen have
been on-going since the installation began on the 15th of November
2023. Therefore, we have numerous email responses and phone call
responses over the previous 11 months. On 23 April 2024, upon calling
Mariah Robinson (sales and design consultant) asking when Richters
would return on site to complete defects, I was told by Mariah that she
would no longer help us or answer questions and everything had to be
referred to Kent.
[45] On 17 Sept 2024 Polytec had been again booked in to reinstall the cabinets involved
in the warranty claim for the under-sink cabinetry, and above oven cabinetry.
[46] Eventually nearly 3 weeks later, on 4 Oct 2024, Polytec completed the warranty claim
installation work.
[47] A notice was sent by the applicants to the respondent on 8 October 2024. In that letter
the applicants said inter alia;
We are writing to formally address the ongoing issue regarding the
incomplete kitchen build at our home that was contracted over 12 months
ago.
We are absolutely disgusted and appalled at how we have been
mistreated and treated with contempt by your company. We contracted
your company in good faith and expected the agreed kitchen build to be
carried out in a timely and professional manner. None of which have
occurred.
Our kitchen build should have been completed well over 12 months ago,
as yet we still have an unfinished and non-functioning kitchen.
No one from your company has bothered to contact us for over one
month. To make matters worse, we have been made aware that your
company has been in Agnes Waters completing kitchen builds for a local
building company. Yet at no time did anyone from your company come
to our property to complete our kitchen build from a contract that was
signed in 2022.
Our contracted agreement stipulated a completion timeline that has not
been honoured. Despite numerous discussions and reassurances
regarding the project's progress, the work remains unfinished. This delay
-- 8 of 22 --
9
has not only caused significant inconvenience but has also resulted in
emotional distress for my family, hindering our ability to undertake
further renovations.
We have now begun the escalation process as advised by our solicitor
and have commenced action with the Queensland Building and
Construction Commission.
Please consider this letter as commencement of formal proceedings with
which to resolve the matter. We appreciate your immediate attention to
this issue and look forward to your prompt response
[48] On the 15th of October 2024, the respondent sent an email describing his version of
what had been occurring and seeking to excuse what had happened as beyond his
control. The respondent’s email asked when they could return to install overhead
cabinetry. By this stage he was obviously aware that the applicants were dealing with
the QBCC and the email felt to the applicants like he sent it to make it look like he
was trying. The email failed to address the remainder of the works such as tiling,
electrician fit-off, finding a solution to the island bench which still has no pop-up
GPO or power that they could plug into, that the cabinets above fridge need replacing,
that the push to open catches required removal, there were drill holes in cabinetry and
other issues.
[49] The applicants decided to not respond to his email as they considered that they would
be “fools to continue to allow access to their property to cause more damage” and to
not have the works completed or “achieve anything”. It had been almost 2 years since
they had signed the contract with them and 11 months since they had started any
works onsite.
[50] There appears to have been some negotiation conducted between the respondent and
someone within the QBCC in which, as between the 2 of them, they came to the view
that the matter could be resolved by the respondent agreeing to go back to site to
complete the works. But there is no evidence that the applicants were a party to those
negotiations or that outcome. However, on the 8th November 2024, the QBCC wrote
a letter to both parties purporting to confirm that there had been agreement reached
and that no direction to rectify would be issued. But then, months later, on the 14 th
January 2025, the respondent emailed, asking for access to the site. The applicants
did not reply to those requests for access. Tacitly they were refusing it because they
had decided to seek alternate remedies.
[51] On or about 4 February 2025, the applicants brought the present application
constituting an application for domestic building dispute, identifying 61 separate
complaints of defective or incomplete work.
[52] Although there is some ambiguity in the correspondence as to whether and if so, at
what specific date the applicants elected to terminate the contract based upon non-
performance and its breach, I find that at the very latest that occurred when this
proceeding was commenced. I find that it was probably effectively an election made
and communicated when they made complaint to the QBCC and thereafter refused
access to Richters to return to site to do whatever work it was proposing to do
thereafter, as evidenced by their letter of 8 October 2024.
-- 9 of 22 --
10
[53] In cross-examination, Ms Butcher made clear that they had entirely lost faith and any
confidence in the respondent’s willingness or capacity to perform under the contract
and their decision not to respond to the request to allow further access when the
applicant requested it in vague terms on 15 October 2024 constituted the making of
that election and the communication of it to the respondent.
Jurisdiction of the Tribunal
[54] Sections 77 (1) and 77 (2) of the Queensland Building and Construction Commission
Act 1991 (Qld), (the QBCC Act) are as follows:
77 Tribunal may decide building dispute
(1) A person involved in a building dispute may apply, as provided under the
QCAT Act, to the tribunal to have the tribunal decide the dispute.
(2) However, the person may not apply to the tribunal unless the person has
complied with a process established by the commission to attempt to resolve
the dispute.
[55] In Walsh v Australian Building and Construction Group [2016] QCAT 187 Senior
Member Brown ruled at [12]:
Section 77(2) QBCC Act is expressed in clear and unequivocal terms. A
person may not apply to the tribunal to decide a building dispute unless
the person has complied with a process established by the QBCC to
attempt to resolve the dispute. Compliance with the section is a
precondition to the jurisdiction of the Tribunal being enlivened.
The provision is not merely procedural; it is mandatory and has
substantive effect. The Tribunal cannot exercise the powers conferred by
s 61 QCAT Act to waive compliance with s 77(2) QBCC Act.
[56] I am satisfied that the Tribunal has jurisdiction although I should say that this dispute
had a unique element, the provenance of which was never properly identified, in that
in the process of the complaint the applicants made to the QBCC being dealt with,
the QBCC notified both parties that the dispute had been resolved, the respondent
thinking it was resolved by it agreeing to return to site to complete the works, but with
the applicants knowing nothing of any such resolution, not having agreed to it and
thinking a letter sent to them to tell them it had resolved being treated by them as
evidencing that they had complied with the process established by the commission to
attempt to resolve the dispute and could then bring their application in this Tribunal.
[57] Under section 77(3) of the QBCC Act, QCAT is empowered to make a wide range of
orders to resolve building disputes. Section 77 (3) of the QBCC Act states:
(3) Without limiting the tribunal’s powers to resolve the dispute, the
tribunal may exercise 1 or more of the following powers—
(a) order the payment of an amount found to be owing by 1 party to
another;
(b) order relief from payment of an amount claimed by 1 party from
another;
-- 10 of 22 --
11
(c) award damages, and interest on the damages at the rate, and
calculated in the way, prescribed under a regulation;
(d) order restitution;
(e) declare any misleading, deceptive or otherwise
unjust contractual term to be of no effect, or otherwise vary a contract to
avoid injustice;
(f) avoid a policy of insurance under the statutory insurance scheme;
(g) order rectification or completion of defective or incomplete tribunal
work;
(h) award costs.
Domestic Building Work and warranties under the QBCC Act
[58] Domestic Building Work includes1;
(i) the erection or construction of a detached dwelling (and any
associated work);
(ii) the renovation, alteration, extension, improvement or repair of a
home (and any associated work);
(iii) removal or resiting work for a detached dwelling (subject to some
exclusions);
(iv) the installation of a kit home at a building site; and
[59] This work involved the renovation, alteration, extension, improvement or repair of a
home (and any associated work). This was a level 2 contract involving $20,000 and
above. That means it was required to contain a provision that states the date for the
start of the subject work at the building site, or how the date is to be determined and
a provision that states the date for practical completion or how the date is to be
determined, and a statement of each of the statutory warranties that apply to the
subject work2.
[60] For Domestic Building Work the QBCC Act3 sets out the mechanism for varying the
work under a contract and obtaining an extension of time to the date for practical
completion. It is necessary that a builder/contractor follow these procedures in order
to validly vary the works or extend time. A failure to do so can result in the contractor
not being paid for work they have done or being liable for liquidated damages if the
date for practical completion is not validly extended.
The scope of the warranty that work will be carried out with reasonable diligence.
[61] Part 3 of The QBCC Act 1991 (Qld) sets out statutory warranties. The warranties
mentioned in Part 3 Division 2 are part of every regulated contract. They include that
the building contractor warrants the subject work will be carried out with reasonable
diligence. The “diligence” of a builder in performing works has been said to include
1 Schedule 1B, s4, QBCC Act
2 Schedule 1B, s14, QBCC Act
3 Schedule 1B, s40 & s41 QBCC Act
-- 11 of 22 --
12
not only “personal industriousness” but also efficiency by the builder and the
builder’s employees; Hooker Constructions Pty Ltd v Chris’s Engineering Co [1970]
ALR 821, 822;
[62] In Hometeam Constructions Pty Ltd v McCauley [2005] NSWCA 303 the NSW Court
of Appeal said;
[169] It might be accepted that the appellant’s failure to complete the
Works by the date for practical completion might be some evidence of
delay (see Westminster Corporation v J Jarvis & Sons Ltd and Another
[1970] 1 WLR 637 at 643 per Lord Hodson, at 645 per Viscount
Dilhorne). However, whether delay is of itself sufficient to raise an
inference of lack of due diligence must depend on the circumstances.
[170] Despite the prevalence of clauses in building contracts requiring
the work to be performed with “due diligence”, defining the nature of
that obligation has proven elusive.
[171] In Re Stewardson Stubbs & Collett Pty Ltd & Bankstown
Municipal Council, Moffitt J observed (at 1675–1676) that:
… [T]he question of what precisely constitutes a failure to proceed with
reasonable diligence is a matter of some difficulty. However, it is an
allegation of a general failure to proceed with that degree of promptness
and efficiency that one would expect of a reasonable builder who has
undertaken a building project in accordance with the terms of the
contract in question.
[172] In Hounslow London Borough Council v Twickenham Garden
Developments Ltd Megarry J considered a requirement that a building
contractor “proceed regularly and diligently with the works” and said (at
269):
[W]hat is the meaning of the words ‘regularly’ and ‘diligently’? These
are elusive words, on which the dictionaries help little. The words
convey a sense of activity, of orderly progress, and of industry and
perseverance: but such language provides little aid on the question of
how much activity, progress and so on is to be expected. They are words
used in a standard form of building contract in relation to functions to be
discharged by the architect, and in those circumstances it may be that
there is evidence that could be given, whether of usage among architects,
builders and building owners or otherwise, that would be helpful in
construing the words. At present, all that I can say is that I remain
somewhat uncertain as to the concept enshrined in these words; and this
necessarily increases the task of Mr Harman in establishing a strong case
that the contractor has failed to proceed regularly and diligently with the
works, so that the architect's notice is good.
[173] In Hooker Constructions Pty Ltd v Chris’s Engineering Co [1970]
ALR 821 at 822–823, Blackburn J considered whether a head contractor
had validly terminated a building sub-contract on the basis that the sub-
contractor had failed “to proceed with the works with reasonable
diligence” as required by the contract. After observing that the “onus is
-- 12 of 22 --
13
on the plaintiff to show the [sub-contractor] was in default in a way …
caught by this provision”, his Honour said (at 822) that he had “not found
it easy to construe this phrase ‘reasonable diligence’ in the context of this
case”. He concluded that “a sensible construction of the phrase is that the
actual extent of work completed is of some significance” and that
“‘diligence’ in the contract means … not only the personal
industriousness of the defendant, but his efficiency and that of all who
worked for him”.
[174] He also said (at 823) that he was entitled to accept as evidence that
the defendant had not displayed reasonable diligence, “evidence that the
work was, at the material time, seriously incomplete together with
evidence that there were no circumstances preventing the defendant from
overcoming this situation”.
[175] In Hooker the plaintiff led evidence that at the time it purported
to terminate the sub-contract, the defendant’s work was “seriously
behind what could reasonably be expected [and] that the situation was
not due to anything which was beyond the defendant’s control”.
Although the defendant adduced evidence to show that “through no fault
of his own, he was unable to get the necessary material to bring the work
to the stage where it should have been at the material time”, this did not
convince Blackburn J who held the plaintiff had proved the contract was
validly terminated.
[176] In Australian Development Corporation Pty Ltd v White
Constructions (ACT) Pty Ltd (1996) 12 BCL 317 Giles J (as his Honour
then was) accepted that “where there was a specified future date for
practical completion, whether [the builder] was prosecuting the project
diligently was a question of fact, substantially determined by whether it
was proceeding at a rate of progress according to which practical
completion would be achieved by the specified date but with regard also
to whether accelerative measures could bring achievement of completion
by the specified date.” His Honour considered competing expert
evidence as to the time required to complete the building work but
concluded it was unnecessary in the circumstances of that case to resolve
the difference between those views.
[177] As each of these cases demonstrates, “you cannot have diligence
in the abstract. It must be related to the objective”: Greater London
Council v Cleveland Bridge and Engineering Co Ltd (1986) 34 BLR 50;
see also Hick v Raymond & Reid [1893] AC 22 at 29 per Lord Herschell
LC (“there is no such thing as reasonable time in the abstract”); Maynard
v Goode [1926] HCA 4 ; (1926) 37 CLR 529 at 538 per Isaacs J (“[t]he
question of what is ‘reasonable time’ is always relative; that is, it means
‘a reasonable time under the circumstances’ ”).
[178] There were, in my view, in the context of the Contract, at least
two ways the respondent could have established that the appellant had
failed to perform the works with due diligence.
[179] First she could have proved:
-- 13 of 22 --
14
(a)the work the appellant was required to carry out under the Contract;
as events transpired this included the original contract works and the
rectification work;
(b)what, in addition to the contract period, was a reasonable time within
which the appellant ought to have executed the original contract works
and the rectification work;
(c)that the appellant had failed to execute the work within that reasonable
time;
(d)that, to the extent the appellant proffered explanations of why the
work had not been executed within that reasonable time, those
explanations were unacceptable.
[180] As I shall explain, the appellant’s case was, essentially, that this
was the way the respondent was required to prove her case and that she
had failed to do so.
[181] Secondly, in my view, the respondent was also entitled to seek to
prove lack of due diligence by establishing a case of delay in progress
during construction. This appears from both Stubbs and Hooker. On this
basis she could have established a failure to carry out a reasonable
amount of work by a given time; that that period of time be measured by
reference to all the work to be performed under the Contract or, in
absolute terms, by reference to a lack of activity on site over a significant
period that could not be satisfactorily explained. The onus of proving
lack of due diligence was on the respondent. If the facts established by
the respondent are capable of giving rise to an inference of lack of due
diligence, the appellant may discharge any evidentiary onus that may
pass to it, by explaining why the work progressed at that rate: see Hobbs.
That evidence should be “sufficient … to turn the scale”: Brady v Group
Lotus Car Cos plc [1987] 3 All ER 1050 at 1059 (CA) per Mustill LJ
[63] These principles have been regularly considered and applied by the Courts and this
Tribunal.
[64] Dealing with a lack of due diligence based on delay in the progress of construction,
an owner might successfully terminate a residential building contract by
demonstrating that at the time the notice to remedy breach is served, the building
works are seriously incomplete; and there are no circumstances preventing the
builder from having performed the works at a more rapid rate; Dura (Australia)
Constructions Pty Ltd v Hue Boutique Living Pty Ltd (No 3) [2012] VSC 99, [439];
Hometeam Constructions Pty Ltd v McCauley [2005] NSWCA 303, [199].
How the parties conducted the proceeding
[65] Essentially the applicants’ case was that there was a failure by the respondent to
deliver a kitchen of acceptable quality within a reasonable period of time and that its
attempts to improperly shift blame onto the applicants or other contractors it had
engaged were misplaced.
-- 14 of 22 --
15
[66] At every point on the journey to this matter coming on for a hearing and for a large
part of the hearing, neither party was focused upon what, if any, legal foundations the
applicants’ case had, the terms of any statutory warranties or what foundation any
defence or resistance to it had. The arguments put up for the respective sides involved,
suggesting that one should have regard to the fact that the respondent claimed always
to be willing to complete the works or at the very least at some point, made clear that
it was willing to do so, but was not permitted to do so. It also suggested there were
variations, and changes being made to the design, the finishes and other aspects of
what was to be constructed, and that somehow or other this ought to be brought into
consideration in deciding the outcome.
[67] Neither party focussed upon the terms of the contract between them. As an obvious
example, the contract provided for a date for practical completion, but also made
provision for extensions in certain circumstances where there were variations and
other matters, which had occurred, which entitled the builder, an extension of that
date. Despite that, neither party apparently adopted or took advantage of the
procedures or scheme that was set out in the contract to accommodate those changes.
[68] Neither party addressed whether the contract had been terminated by one or other of
them or whether there was in fact an entitlement based on what had occurred, to do
so. Neither party addressed the legal foundation for an award of damages by reference
to the contract or legal principle.
[69] Initially, the applicants were seeking a declaration to the effect that the contract was
no longer on foot, but the legal and factual foundation for that was not identified. And
seeking that relief was, in the end, not pressed. I have made a finding of fact on this
issue
[70] What that left was for the Tribunal to focus upon what legal foundations might exist
for the claims and as to their merit, having regard to those legal foundations.
[71] The applicants made reference in their final address to the statutory warranties under
the QBCC Act, but I was not taken to what particular warranties were referred to or
how it is said that they were not met in this case or addressed or what consequences
flowed from that.
[72] The statutory warranties which are implied in this contract are as follows:
The building contractor warrants that all materials to be supplied for use
in the subject work— (a) will be good and, having regard to the relevant
criteria, suitable for the purpose for which they are used; and (b) unless
otherwise stated in the contract, will be new.
The building contractor warrants the subject work will be carried out in
accordance with all relevant laws and legal requirements, including, for
example, the Building Act 1975;
The building contractor warrants the subject work will be carried out—
(a) in an appropriate and skilful way; and (b) with reasonable care and
skill.
[73] Clause 5.1 of the contract itself provided that the respondent will carry out the Works;
a) in an appropriate and skilful way;
-- 15 of 22 --
16
b) with reasonable care and skill;
c) in accordance with the Drawings and the Specifications:
d) with reasonable diligence; and
e) in accordance with all relevant laws and legal requirements. including,
for example, the Building Act 1975 and the National Construction Code.
[74] Clause 5.4 of the contract itself provided that;
Subject to Clause 5.5, the Contractor warrants that all materials to be
supplied by the Contractor for use In the Works:
a). will be good and having regard to generally accepted practices or
standards applied in the building industry for the materials, or the
specifications. instructions or recommendations of manufacturers or
suppliers of the materials, suitable for the purpose for which they are
used:
Findings in relation to the incomplete and defective state of the works
[75] I do not propose to traverse the 61 defective or incomplete items listed in the
application, and the applicants’ evidence. I accept that the defective and incomplete
work listed there is accurately described. In my view it is clear that the work has not
been carried out in an appropriate and skilful way; and with reasonable care and skill.
The kitchen is all but unusable, not just because it is incomplete. I will give some
examples. I accept that the Nikpol overhead is not onsite nor installed. The integrated
rangehood is still sitting in pieces potentially unusable.
[76] No tiling has been carried out to make the splash backs. The electrical finishing off
has not been done. The overhead front boards above the fridge need to be replaced as
the grain on them runs in a direction different to the grain in the remainder of kitchen.
These doors also sit ajar due inoperable push to open catches. These doors also have
unsightly glue lines and tape marks.
[77] The respondent attempted to remove the existing window architraves to fit larger
architraves to try and hide the unsightly installation of his work The architraves are
not properly fitted. The gyprock sheeting behind the cooktop is yet to be tiled flexes
causing concern that tiling on it will not be effective as a splashback.
[78] The existing cabinetry is not flush on the wall, and one can see daylight or the back
wall between the items of cabinetry. The cabinetry is not level, and the drawers do
not close flush. The cabinetry does not marry up.
[79] The pantry is sitting on about 3cm of glue and the top is not flush or level.
[80] There are structural integrity issues with Caesarstone Island bench. There is no
support board under the 2m length of bench top, and there is a gap so large that one
can fit half a hand through it.
[81] The LED strip lighting does not work and there is no functioning LED strip lighting.
[82] The applicants have never used the ovens as no inspection has confirmed whether
they are legally compliant. The top oven slid out of the oven tower for 3 months before
the applicants discovered why. The top oven could not be opened for the first few
-- 16 of 22 --
17
months as jamming against the bottom board. The bottom oven may not have the
required ventilation.
Polytec warranty process and delay
[83] The respondent asserts that the Polytec warranty process contributed to the delay in
completing the kitchen. The applicants reject this assertion and say that after the
cabinetry was initially installed, they discovered that the surface panels were visibly
defective. Even gentle contact would leave smudges and fingerprint marks which
could not be removed, despite multiple cleaning attempts. This issue was later verified
by representatives from Polytec, who acknowledged that the panels were defective
and would need to be replaced under warranty. While the applicants appreciated
Polytec's willingness to honour their warranty (and it is not clear what that warranty
was), the applicants were nevertheless dismayed that Richters, -whom they had
trusted to build their “dream kitchen”, had installed visibly defective cabinetry in the
first place. This caused them to lose confidence in their professionalism and
judgment, and it marked an early turning point where their trust in their ability to
deliver a high-quality kitchen began to erode.
[84] On 4 August 2025, Polytec's Warranty Manager, Mr Dale Powell asserted in writing
that Polytec had never required or instructed Richters to cease or delay their works
due to the warranty claim. Mr Powell said that while Polytec's preference is that works
be completed before they are engaged, they certainly didn’t look to delay works. The
applicants had prior phone discussions with a Mr Brookes of Polytec, who had
similarly advised that the warranty process relating to panel defects did not prevent
Richters from proceeding with the remainder of the kitchen works.
[85] The response to that by the respondent was to say it was preferable for all such
cabinet work to have gone in and be rectified if the subject of a warranty claim, before
they came to complete the kitchen. Preferable or not, that did not justify the delay.
Tile Selection and Delay.
[86] The respondent asserts that delays occurred because the applicants had not selected
tiles for the kitchen splash back. The applicants categorically reject this assertion. I
accept that the applicants selected and purchased three boxes of 'Natura Artico' tiles
from Linda's Tiles in Bundaberg on 15 March 2024. The three boxes of tiles remain
on site to this day, completely unused, as the kitchen has never reached a stage where
tiling could be undertaken.
[87] There was a period of delay, but this was not due to any indecision on the applicants’
part. Rather, it arose solely because the respondent Mr. Hassam believed that the
thickness of their chosen tiles might prevent General Power Outlets (GPOs) from
being installed over them. He engaged his tiler, "Felix," to investigate the issue.
While the applicants waited for this to be resolved, the applicants also undertook their
own enquiries and contacted Clipsal, who confirmed there would be no issue
installing GPOs over the selected tiles provided that a standard mounting box frame
was used. This resolved the matter, and no change to the chosen tiles was ever
required.
[88] This alleged cause for delay was inconsistent with the respondent's own
communications. In an email dated 5 June 2023 from Ms. Mariah Robinson, Design
Consultant at Richters Joinery, she advised them that:
-- 17 of 22 --
18
"We've had plenty of clients over the years who cannot decide on a
splashback, and our advice is to wait until the kitchen is installed. There
is no need to rush these things, especially if you're more of a visual
person. We're more than happy to leave the tiled splashback selection
until after the kitchen is installed."
[89] That statement implies that tiling is commonly left until the end of a kitchen build and
does not prevent the works from otherwise progressing. I accept the applicant Ms
Butcher’s evidence that their tiles were selected and purchased well in advance, and
any brief pause was caused entirely by the respondent's misunderstanding about GPO
installation, not by any indecision or delay on their part.
[90] I find that the suggestion that tile selection contributed to justifiable delay is without
foundation.
Delays Due to Changing the Overhead Cabinet Design and ducting issues
[91] The respondent contends that there were also justifiable delays caused by the
applicants repeatedly changing their minds about the overhead cabinetry. There were
photos before me that show that even to this day there are no overhead cabinets
installed. The respondent says they are built and sitting in its factory ready to be
installed.
[92] I find that the overhead cabinetry was long ago removed completely and remains in
the respondent's possession, leaving an empty space and a large open untiled and
unfinished space where the functioning cabinets should be.
[93] I find that the overhead cabinetry was installed but then removed from the kitchen on
three separate occasions due to multiple design and installation faults identified by
the respondent's own team, including problems with its size and positioning, the
ducting for the exhaust fan, the method of opening the cabinet doors, and the
installation of the undermounted strip lighting.
[94] The respondent also contends that the provision of ducting was "never included in the
contract." I find that the applicants contracted with Richters to supply and install a
fully functioning kitchen, and ducting forms an essential and integral component of a
functional overhead exhaust system but even if it was not included, there is no basis
to conclude that any dispute about who was responsible for it explains to failure to
construct and install the kitchen agreed on .
[95] The applicants contend that due to the number of times this cabinetry has been
removed, transported, altered, and reinstalled, they had lost and have still entirely lost
confidence in its structural integrity and safety and no longer wish to have it returned
or installed in their home. The need to remove it arose from workmanship and design
issues, not from any change of mind on their part.
[96] I accept the evidence of the applicant Ms Butcher’s that at no time did they request
unnecessary alterations and that the removal of these cabinets was entirely initiated
by the respondent in attempts to correct his own work.
Allegations that the applicants improperly engaged outside contractors
[97] One of the contentions made by the respondent was that somehow, he was relieved
of his responsibilities to perform these works was because the applicants engaged
-- 18 of 22 --
19
outside contractors to complete, alter, or rectify the kitchen works, and that doing so
constituted a breach of contract.
[98] This assertion was denied by the applicants in their evidence and submissions, and
they contend that the only outside party used was a plasterer and he was the
respondent’s plasterer anyway.
[99] I find that following the respondent's prolonged failure to complete the works, they
sought independent assessments from licensed cabinet makers to obtain professional
opinions and written quotations regarding possible rectification however, these
attendances were strictly limited to inspection and assessment only. No work,
modifications, or interference with the existing installation were carried out by those
parties. I accept the evidence to that effect.
[100] I find that the kitchen remains in precisely the same condition as it was left on the
last occasion that representatives of the respondent attended the property, which to in
or about July 2024. Since that time, no physical works, alterations, or repairs have
been undertaken and the applicants deliberately preserved the site in its incomplete
state.
[101] When challenged on this issue, it was in effect conceded by the respondent that he
could point to no evidence that such contractors had been engaged.
The Allegation of refusing access to site
[102] The respondent alleges that the applicants refused access to the property or otherwise
obstructed the completion of the contracted works. I have already partly dealt with
this issue and will deal with whether the respondent was entitled to insist on being
permitted access to return to site to perform his obligations under the contract in what
follows. In my view, even if he was refused such access, it does not affect the outcome
of the proceeding.
[103] I reject the respondent's claim that he was "always been willing to complete the
contracted works" as contrary to the objective documentary record. The applicants
have, on multiple occasions and over an extended period, provided genuine
opportunities for the respondent to complete and rectify the works. On each such
occasion, the respondent either failed to attend, or continually delayed the work for
no lawful reason, and as the applicants say did work of a substandard quality, or
introduced additional defects requiring further correction.
[104] The only refusal was implicit and arose when the point had been reached when the
contract had been terminated.
[105] I agree that. as the applicants put it;
Given the extensive history of unrectified defects, unfulfilled assurances,
and disregard for professional standards, the applicants have entirely lost
confidence in the respondent's capacity to safely or competently
complete the works. The respondent's professed "willingness" is, at this
stage, irrelevant and immaterial - the time for voluntary completion has
long since passed, and the matter now properly falls within the
jurisdiction of this Tribunal for determination.
-- 19 of 22 --
20
Findings in relation to fundamental breach and the right to terminate the
contract for demonstrated lack of due diligence
[106] I find the conduct of the respondent in breaching both the implied and express
contractual warranties in relation to the quality of the work and the materials to be
supplied were serious breaches. These were important, indeed essential terms or
conditions of the contract, and the breaches which occurred were great in number,
extended over a long period and were not accompanied by any genuine or actual
manifest intention to remedy those breaches by providing work and materials which
complied with those warranties. Notices requiring them to be remedied were all but
ignored.
[107] Secondly, although time was not of the essence of the contract, having regard to what
I have identified earlier as to what is required to perform work with reasonable
diligence there has been a demonstrated lack of due diligence by establishing a case
of delay in progress during construction. The applicants have shown a failure to carry
out a reasonable amount of work by a given time with that that period of time being
measured by reference to all the work to be performed under the contract or, in
absolute terms, by reference to a lack of activity on site over a significant period that
could not be and has not been satisfactorily explained.
[108] At the times notices to remedy breach were served, as well as later, the works were
and even now are seriously incomplete and there were and are no circumstances
preventing the respondent from having performed the works at a more rapid rate.
[109] In my view, this was a manifest example of a party that not only by its conduct over
time in failing to meet deadlines, or agreed timelines, but by his failure to respond to
invitations to improve performance , showed a flagrant and intentional disregard for
the times upon which the parties had agreed for the performance of these works, but
also a manifest and repeated unwillingness to acknowledge that works should be
performed in some timely way. This was after all, an expensive kitchen, which was
intended to be the heart of residential activity in this house, including obviously for
the preparation and cooking of meals but also all the ancillary activities that go on in
what is typically the hub of a household. Some elements of what were installed were
actually or potentially electrically unsafe and undermined the applicant’s sense of
security in their own home.
[110] The applicant was sent three or more notices effectively calling upon him to affirm
his responsibilities under the contract and indicate how it was that he intended to meet
his obligations under it, but no useful response was ever received. Excuses came
instead. In my view, that in itself is capable of being treated as repudiatory conduct,
or at least conduct, which was in fundamental breach of the terms the parties had
agreed upon.
[111] In those circumstances, I find the applicants were entitled to and did terminate the
contract and are relieved from any further burden under it to pay any further sums. In
fact, only the last payment, which was due under it might have become outstanding
had the contract works been completed, but they were not.
[112] I order that the applicants are relieved from payment of any further sum which might
have fallen due under the contract, if any, and declare that there is no further payment
due.
-- 20 of 22 --
21
[113] The next question is what damages or compensation they ought they receive arising
out of the respondent's breach of the contract. The relevant test is to identify that
which would put the applicants in the position they would have been had the
respondent performed according to his obligations under the contract and to give them
that which they bargained for under that contract.
The expert evidence and the solution to the defective and incomplete state of the
works
[114] Mr Leonard Smith has provided a report in relation to the quality of the work and
what is the appropriate way to deal with the works as they stand and what solutions
present. He is a licensed builder with approximately 57 years of experience in the
building industry. That includes residential construction, renovations and kitchen
installations. He has experience with removal of existing kitchens, coordination and
supervision of plumbing and electrical preparation, structural works were required,
and re-sheeting and reinstatement prior to new kitchen installations.
[115] The opinions in his report are not challenged except to suggest that he may not be
impartial, or to suggest that the respondent should be allowed to rectify the work and
complete it. I accept that he is impartial.
[116] His opinions are based on what he observed on site, his experience in the trade, and
normal building practice, and are not influenced by his personal acquaintance with
the owners. He was the original builder of the house in question, but not for these
owners. He inspected the kitchen area on multiple occasions including prior to
installation, during installation, arid following.
[117] His evidence, which I accept is that the preparation works carried out prior to
installation were of a poor standard. Gyprock sheeting appeared to have been partially
removed and reinstalled rather than replaced with full sheets; In moisture-prone areas,
water-resistant board was not installed; These are not the sort of preparation practices
he would expect to see in a properly prepared kitchen.
[118] During installation, cabinetry was not installed so as to be level or plumb, with
inconsistent margins and gaps. These issues are consistent with an inaccurate or
poorly executed site check-measure.
[119] As for the Polytec panels that were identified as defective and replaced by Polytec,
from his experience, selectively replacing cabinetry components in this situation is
not appropriate. Full removal is required to ensure consistency of finish, alignment,
and quality. He also observed inconsistent grain orientation in cabinetry panels, which
is unacceptable workmanship.
[120] His evidence, which I accept is that the preparation and installation of the kitchen
were not done to an acceptable standard. There were ongoing issues with fit, finish,
and coordination that should not occur in a properly planned and installed kitchen. In
his experience, trying to fix these issues bit by bit would be difficult and unlikely to
produce a satisfactory result. In his view, taken together, the defects and incomplete
items mean the kitchen is not suitable for normal day-to-day use. Until these issues
are properly addressed, the kitchen can't be considered finished or usable as intended.
[121] He has safety concerns arising from the way the kitchen has been left incomplete.
This includes unfinished cabinetry, areas where components were not properly
supported, and electrical wiring and ventilation components that were not properly
-- 21 of 22 --
22
finished or built into the kitchen. In his opinion, using the kitchen in this condition
creates a real risk of damage, component failure, or unsafe use until it is properly
rectified.
[122] His evidence, which I accept is that the Caesarstone bench top has not been provided
with a full support board beneath it, as would normally be expected. In his experience,
stone bench tops rely on proper support to prevent movement over time. He has
already observed signs of bowing, and without adequate support, there is a real risk
that the benchtop may continue to move and potentially crack in the future.
[123] He concludes and I accept that there are only two practical options to resolve the
situation. Trying to fix the issues bit by bit in a situation like this usually leads to more
problems including further defects and poor alignment. He says the only real solution
is to remove the kitchen and start again.
[124] As I observed earlier, the applicants elected to submit that the quotation to perform
the works which sat between the other two quotations they obtained, was the one that
they relied on in seeking an order for damages or compensation. That quote was for
an amount of $34,450 and was from an organization called Cabinet Connections.
There was no submission made by the respondent to mount any challenge to this as a
reasonable assessment of the cost to replace this kitchen. I find that a payment to them
of that about would appropriately compensate them for the respondent’s breaches of
contract.
Disposition and Orders
[125] It must follow that the application is upheld.
[126] I order and declare that the applicants are relieved from payment of any further sum
which might have fallen due under the contract, if any, and declare that there is no
further payment due.
[127] I order that the applicants be awarded damages or compensation for breach of contract
in the sum of $34,450 against the respondent, with such sum to be paid within 30 days
of the making of these orders.
[128] I grant the parties liberty to apply in respect of any other consequential or other orders
which might be required to be made.
-- 22 of 22 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2026/113