Blair v Coyne [2026] QCAT 93
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Blair v Coyne [2026] QCAT 93
PARTIES: LOUISE BLAIR
(applicant)
v
JOSEPH JAMES COYNE
(respondent)
APPLICATION NO/S: BDL133-25
MATTER TYPE: Building Matters
DELIVERED ON: 24 February 2026
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Bellamy
ORDERS: 1. Joseph Coyne must pay the amount of $97,850 to
Louise Blair within 60 days of this decision.
2. Joseph Coyne must pay the amount of $852 to Louise
Blair within 28 days of this decision.
3. Joseph Coyne must pay costs of $379.50 to Louise
Blair within 28 days of this decision.
CATCHWORDS: JURISDICTION – DOMESTIC BUILDING DISPUTE –
REVIEWABLE DOMESTIC BUILDING WORK – where
domestic building work includes construction of an
inground pool
PROCEDURE – CIVIL PROCEEDINGS IN STATE
TRIBUNAL – ENDING PROCEEDINGS EARLY – where
one party unnecessarily disadvantages another party – where
respondent failed to engage in proceeding and repeatedly
failed to comply with Tribunal directions without reasonable
excuse – where discretion of Tribunal exercised to make
final decision in applicant’s favour
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
LEGALITY – PERFORMANCE OF WORK – where
engineer refused to certify work because it did not conform
to the engineering plans – where builder failed to rectify
defect and principal terminated the contact – whether
builder breached statutory warranties – whether builder
liable to pay damages for the cost of rectification
-- 1 of 10 --
2
Queensland Building and Construction Commission
Act 1991 (Qld), s 77; Sch 1B, s 1, s 4(1)(c), s 14(2),
s 14(10); Sch 2; 7(1)(a), 7(2)
Queensland Building and Construction Commission
Regulation 2018 (Qld), reg 45
Queensland Civil and Administrative Tribunal
Act 2009 (Qld), s 32, s 48
Bellgrove v Eldridge (1954) 90 CLR 613
APPEARANCES &
REPRESENTATION:
This matter was heard and determined on the papers
pursuant to s 32 of the Queensland Civil and Administrative
Tribunal Act 2009 (Qld)
REASONS FOR DECISION
Introduction
[1] The applicant contracted with the respondent to build an inground pool at her property.
The engineer refused to certify the construction of the pool on the basis that it had not
been done in accordance with the plans. The applicant applied to the Tribunal for
restitution in the amount that it would cost to rectify the defects, and she sought some
additional orders. The respondent has not engaged in this proceeding despite having
ample opportunity to do so.
[2] The Tribunal decided to determine this application without further delay, based on the
material that has been filed. That material was all provided by the applicant. The
respondent could have challenged it but has not done so. Where the information
provided appears to be credible and reasonable, I accept it.
Power to make a final decision
[3] The Tribunal has jurisdiction to hear and decide building disputes, and order various
remedies, under s 77 of the Queensland Building and Construction Commission Act
1991 (Qld) (‘QBCC Act’). Relevantly, those remedies include:
(a) …;
(b) order relief from payment of an amount claimed by 1 party from another;
(c) award damages, and interest on the damages at the rate, and calculated in
the way, prescribed under a regulation;
(d) …;
(e) …;
(f) …;
(g) order rectification or completion of defective or incomplete Tribunal
work;
(h) award costs.
-- 2 of 10 --
3
[4] A building dispute includes a domestic building dispute.1 A domestic building dispute
includes a dispute between a building owner and building contractor relating to the
performance of reviewable domestic work.2
[5] I am satisfied that the applicant is a building owner, and the respondent is a building
contractor, according to the definitions in the QBCC Act.3 Reviewable domestic work
includes domestic building work. Domestic building work includes ‘associated work’,
which includes swimming pools4 so I am satisfied that the work is reviewable
domestic work.
[6] According to an affidavit of service filed by the applicant, on 10 May 2025, she
witnessed her partner give a copy of the application to the respondent at his registered
address. She also sent a copy by email to his business email address. I note that the
email address appears on invoices issued by the respondent and it was used to
communicate with her.
[7] The tribunal made the following directions that were ignored by the respondent:
(a) on 16 May 2025, to file and serve a response and/or counter-application by
4:00pm on 13 June 2025;
(b) on 5 August 2025, to file and serve a response and/or counter-application by
4:00pm on 19 August 2025; and
(c) on 7 October 2025, to file and serve a response to the application by 4:00pm on
21 October 2025.
[8] Each direction included a warning that if the respondent did not comply, the applicant
would be entitled to a final decision.
[9] The direction made on 7 October 2025, stated that:
If Louise Blair is entitled to a final decision in accordance with Direction 2
herein, the matter will be determined on the papers without an oral hearing on
the basis of the documents forming the Tribunal record, after 18 November
2025.
[10] To date, the respondent has not complied with any of the Tribunal’s directions or
engaged in this proceeding at all.
[11] A person involved in a building dispute may apply to the Tribunal to decide the
dispute provided the person has complied with a process established by the QBCC to
attempt to resolve the dispute.5 I am satisfied that the applicant has complied with that
process.
[12] Under s 48 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)
(‘QCAT Act’), if the Tribunal considers that a party to a proceeding is acting in a way
that unnecessarily disadvantages another party to the proceeding, including by not
complying with the Act or an enabling Act, the Tribunal may make its final decision
in the proceeding in the applicant’s favour.
1 QBCC Act sch 2 (definition of ‘domestic building dispute’).
2 Ibid (definition of ‘reviewable domestic work’).
3 Ibid (definition of ‘building contractor’ and ‘building owner’).
4 Ibid sch 1B s 4(1)(c).
5 Ibid s 77(2).
-- 3 of 10 --
4
[13] In the exercise of this power, the Tribunal must have regard to:
(a) the extent to which the party causing the disadvantage is familiar with the
Tribunal’s practices and procedures;
(b) the capacity of that party to understand, and act on, the Tribunal’s orders and
directions; and
(c) whether the party causing the disadvantage is acting deliberately.
[14] I am satisfied that the respondent’s failure to engage in this proceeding is
unnecessarily disadvantaging the applicant by delaying the determination of her legal
entitlements.
[15] The evidence about the matters to which the Tribunal must have regard is limited. I
am unable to form a view about the extent to which the respondent is familiar with
the Tribunal’s practices and procedures. The respondent has the ability to conduct a
business, enter into a contract, issue quotes and invoices and perform work. The
application was personally served on him. The Tribunal’s orders and directions were
expressed in plain English. I am not satisfied that he lacks the capacity to understand,
and act on, the Tribunal’s orders and directions. In the absence of an explanation to
the contrary, I am satisfied that the respondent’s failure to engage in this proceeding
is deliberate.
[16] Having regard to the matters in s 48 of the QCAT Act, I am satisfied that it is
appropriate to make a final decision in the applicant’s favour.
The dispute
[17] On 11 February 2022 the applicant and respondent entered into a contract for the
construction of a swimming pool for an amount of $43,835. The respondent was at all
relevant times licensed to carry out that work. The business name he used was Coyne
Pool Construction.
[18] The general conditions of the contract included that the work would be carried out in
accordance with the plans and specifications. The first payment stage, which was the
deposit, covered ‘Site preparation, Engineering plans, Certification and QBCC
insurance’. Engineering plans by Structural Innovations Australia, Consulting
Engineers (‘SIA’), were certified on 21 April 2022 by Coastline Building Certification
Group (‘Coastline’). The plans are detailed and they reference relevant building
standards.
[19] The QBCC Act provides that a domestic building contract for an amount equal to or
more than $20,000 is a level 2 regulated contract.6 As the contract was for $43,835 it
is classified as a level 2 regulated contract. A level 2 regulated contract must meet
certain criteria in order to have effect.7 One criterion is that it includes:
any plans and specifications for the subject work, including all plans and
specifications required for carrying out the work in compliance with any
development approvals or similar authorisations that are required by law for
carrying out the work
6 Ibid sch 1B, ss 1 (definition of ‘regulated amount’), 7(1)(a), 7(2); Queensland Building and
Construction Commission Regulation 2018 (Qld) reg 45.
7 Ibid sch 1B, s 14(2), (10).
-- 4 of 10 --
5
[20] While the contract did not include the engineering plans when it was formed, it
contemplated the plans being provided and certified. I am satisfied that the contract
incorporated the plans once they were certified. I am also satisfied that the contact met
the other criteria for a level 2 regulated contract and was therefore compliant.
[21] The respondent commenced the building work on 26 April 2022. The Contract gave
the date for practical completion as 21 June 2022.
[22] The contract was varied twice, with the variations being agreed in writing, signed by
both parties on the QBCC Form 5 variation document.
[23] There is a document dated 11 May 2022 on Coastline letterhead that is entitled
‘Inspection report QB2210158 – 1. Pool steel inspection’, signed by a Mark Leeves
– Inspector. It states:
Provide a revised engineering and Form 15 design certificate for the pool with
no coping bars as per the engineering plans.
The final inspection report by Mr Leeves dated 9 November 2022 also referred to this
issue. It said ‘Generally satisfactory (minor issues) subject to documents being
provided’ and asked for (among other things)
Confirmation from the engineer that it is acceptable for the concrete pool
surround to be supported on the pool coping (plans indicated the surround slab
to be separate). See below for additional information from the engineer.
and
Revised engineering and Form 15 design certificate for the pool with no coping
bars to the perimeter as shown on the engineering plans as per the pool steel
inspection report dated 11/05/2022 (see item 5 for concrete slab surround).
[24] Mr Leeves also identified some other defects including that the glass pool fencing did
not conform to the mandatory safety standard.
[25] On 11 November 2022, Danielle Coyne8 of Coyne Pool Construction sent an email to
the applicant that said they would ‘get this changed by the engineer and send the
revised plans to you and the certifier’. On 20 December 2022, the applicant sent a
reply that said ‘Just wondering if you have received the revised engineering plans &
could you please forward them onto me?’.
[26] On 11 January 2023, the applicant sent another email that said ‘Just checking in as
it’s been 6 weeks since I last heard from you. Do you have any updates on revised
engineering plans and pebblecrete?’ There were some more emails about those topics
but it does not appear that any progress was made.
[27] I note that although the applicant asked about ‘revised engineering plans’ she has not
conceded that she had, at that time, waived her entitlement to a pool that was
constructed according to the plans. Further, there is no variation document in the
Tribunal materials with respect to revised plans. I am not satisfied that the contract
was ever varied so that the respondent was relieved of the obligation to construct the
pool in accordance with the certified SIA plans.
8 Presumably married to, or otherwise related to, the respondent.
-- 5 of 10 --
6
[28] An invoice for the final payment of $5,000 was issued in February 2023. The applicant
had paid the three previous invoices but she did not pay this one.
[29] On 29 March 2023, the applicant sent an email to the Coyne Pool Construction that
referred to a handover on 6 March 2023 and an earlier conversation about the pool
lights being dangerous, patching of pebblecrete and ‘discharging the backwash’. On
20 April 2023, the applicant sent another email listing more defects that she said had
been pointed out during handover and she asked if they could be attended to. Photos
of some of these have been provided to the Tribunal.
[30] On 9 June 2023, the applicant informed the respondent that she had lodged a
complaint with the Queensland Building and Construction Commission (‘QBCC’).
QBCC did not order the respondent to rectify the claimed defects and closed the case
on 22 December 2023. The applicant claims that the pool did not qualify for the home
warranty scheme.
[31] There is an email dated 12 January 2024 from Mark Trenchard-Smith, Senior
Structural Engineer, SIA, with a subject line that includes the applicant’s name and
address. It states:
As discussed, we are not certifying the construction of the pool shell due to
photographs taken during the private certifier inspection showing the pool shell
coping reinforcement not being in accordance with our drawings.
Additionally, we require concrete slabs on ground to be fixed to the pool shell
to ensure no differential movement between pool shell and slab on ground.
[32] While it is not entirely clear, it appears that the deviance from the plans resulted in
poorer reinforcement in the pool shell, and poorer stability, than the certified plans
required.
[33] Clause 3.1 of the contract included:
(a) the work under this Contract will be carried out in an appropriate and
skilful way and with reasonable care and skill and reasonable diligence;
…
(d) the work under this Contract will be carried out in accordance with the
plans and specifications and any other Contract documents;
[34] Clause 23.4 provided that:
Substantial breach by the Contractor includes, but is not limited to:
(a) failing to perform the works under this contract competently;
…
(d) unreasonably failing to perform the work diligently…
[35] On 23 January 2024, the applicant’s lawyers emailed the respondent a notice of
intention to terminate the contract.
[36] The notice asserted that the works had not reached practical completion by the due
date or at all, which was a substantial breach of the contract. The notice further alleged
that by failing to construct the pool in accordance with the plans and specifications,
the respondent had breached the contract, by failing to carry out the work under the
Contract in an appropriate and skilful way with reasonable care, skill and reasonable
-- 6 of 10 --
7
diligence; carry out the work under the Contract in accordance with all relevant laws
and legal requirements including the Building Act 1975 (Qld); and carry out the work
under the Contract in accordance with the plans, specifications and other Contract
documents. Further, this constituted a substantial breach.
[37] It seems clear that failing to conform to plans constitutes lack of reasonable care and
diligence. The notice did not explain how that constituted a failure to carry out the
works in accordance with all relevant laws and legal requirements including the
Building Act 1975 (Qld).
[38] The notice listed the following additional alleged defects, that were said to collectively
constitute a substantial breach, presumably on the basis that the work was not
performed competently or diligently:
(a) Defective installation of two pool lights which are sticking out/not flush
with the wall due to uneven pebblecrete;
(b) Stain and discolouration of pebblecrete on pool bench;
(c) Pebblecrete on most of the bench step of the pool is failing;
(d) Pebblecrete is missing on west side of skimmer box of the pool;
(e) Blackspot in the pebblecrete upon the western wall;
(f) Multiple rust stains of entire pool in the pebblecrete;
(g) Pebblecrete remains on polished concrete surrounds of pool.
[39] These defects had previously been mentioned during the handover and in the email of
20 April 2023. The letter gave the respondent 10 business days to rectify the alleged
breaches or the applicant would terminate the contract.
[40] Clause 23.1 of the contract provided that:
If:
(a) a party is in substantial breach of this Contract; and
(b) the other party gives a notice to the party in breach identifying and
describing the breach and stating the intention of the party giving notice
to terminate the Contract if the breach is not remedied within 10 business
days from the giving of the notice; and
(c) the breach is not so remedied, then, the party giving that notice may
terminate this Contract by a further written notice given to the party in
breach and may recover from the party in breach all damages, loss, cost
or expense occasioned to the party so terminating by or in connection
with the breach or that termination and may set off such claim against
payment otherwise due by the party so terminating.
[41] The respondent did not perform any further work and on 8 February 2024, the
applicant terminated the contract. I am satisfied that the termination was done in
accordance with the requirements in the contract.
[42] I note that clause 25 provided for the practical completion stage payment to be made.
‘Practical completion’ was not defined in the contract. However, it is uncontroversial
that while practical completion may be achieved where there are only minor defects,
it will not be achieved where there is a major structural defect.
-- 7 of 10 --
8
[43] In April 2025, the applicant applied to the Tribunal. Her application included the
following representations:
Certification was not awarded as the builder did not follow the engineers (sic)
drawings. The pool had been built incorrectly.
The pool and it’s (sic) surrounds had been completed and the builder issued an
invoice for final payment however, practical completion had not been reached
so the final payment was not due as per the contract.
When practical completion was delayed i (sic) looked into the issue and realised
the builder had made a massive mistake with the pool shell.
I emailed the engineer to find out why he would not certify the pool and realised
the problem cannot be fixed.
The pool and its surrounds need to be completely removed and rebuilt hence the
large sum for restitution.
The builder went silent after multiple attempts asking them to rectify the
situation so I then got legal advice and terminated the contract.
I then applied to the Queensland home warranty scheme and after nine months
of waiting I was told the pool didn’t qualify for the scheme. QCAT is my last
option.
[44] The applicant has provided quotes for remedial work and photographs of the pool and
surrounding area.
Findings
[45] I am satisfied that the applicant and respondent entered into a compliant level 2
regulated building contract that required the respondent to construct a pool and spa in
accordance with certified engineering plans that were later incorporated into the
contract. I am further satisfied, on the basis of the certifier’s reports and the email
from the senior engineer, that the pool was not constructed in accordance with the
plans and that the variance from the plans related to a structural issue, being the
reinforcement of the pool shell. While the senior engineer required concrete slabs on
the ground to be fixed to the pool shell, which suggests that this was required by the
plans, he was not clear about this and it is not readily apparent on my reading of the
plans.
[46] The respondent’s failure to include reinforcing in accordance with the engineering
plans breached clause 3(a) and clause 3(d) of the contract. I am satisfied that the failure
to adhere to the plans constituted a failure to perform the contracted works
competently, and failure to perform the work diligently, so it was a substantial breach
under sub-clauses 23.4(a) and 23.4(d), respectively. This meant that practical
completion was never reached. That was also a breach of the contract as the date for
practical completion was not met.
[47] The applicant claims there are numerous other defects in the work, although these
appear to be non-structural and relatively minor. I accept that these defects were
brought to the attention of the respondent in April 2023 at the latest, and that the
respondent did not rectify them. I accept that the respondent’s failure to rectify them
constituted a substantial breach under sub-clauses 23.4(a) and 23.4(d), respectively
-- 8 of 10 --
9
[48] I am satisfied that the applicant gave notice under clause 23.1(b) and the defects were
not remedied within 10 business days. Accordingly, under clause 23.1(c), the
applicant was entitled to terminate the contract, which she did, and she became
entitled to damages, loss, cost or expense occasioned to her by or in connection with
the breach(es) or the termination.
Damages
[49] The measure of damages recoverable by a building owner for breach of a building
contract is the difference between the contract price for the work and the cost of
making the work conform to the contract, subject to the rectification work being a
reasonable course to adopt.9
[50] The applicant has not had any rectification work done yet. According to her, the only
way to rectify the non-conformity with the plans is to demolish the swimming pool
and build another one. Given the defect involves reinforcement within the pool shell,
and in the absence of evidence to the contrary, I accept that. If a new pool is to be
built, that would obviate the need to fix the other defects.
[51] The applicant also claims that the surrounding area including a large shed will have
to be demolished and rebuilt because it is all tied to the polished concrete surrounds.
[52] It is incumbent upon the applicant to establish a reasonable basis for the proposed
work and cost of the work. She provided quotes from people she described as licensed
tradespersons. One was from a Troy Piggot of Infinity Pools, with a QBCC license
number, for demolition and re-build of the pool. The quote lists the following items:
Removal of existing Shed that blocks the access path to the back yard
Supply of excavator, bobcat, labourer and truck
Allowance of 3 days to jack hammer, cut and remove honed concrete
Remove existing pool shell
Disposal of concrete
Engineering plans
Private Certifier
Reform a 7 x 3m pool
Steel a 7 x 3m pool
Plumbing provisions
Concrete shell pour
Pebblecrete
Handover and Certification
[53] The quote gives an ‘approximate costs range from $83,000 - 90,000 + GST’.
However, the cost is not itemised despite the items being listed. Some items require
explanation. The photographs provided by the applicant show a two meter wide path
to the backyard, which is not blocked by the shed. If the shed is somehow preventing
access, the evidence before the Tribunal does not establish that. I also query the
inclusion of ‘engineering plans’ given there are already engineering plans and the
applicant is entitled to have a pool constructed in accordance with those plans. If there
is a cost associated with using those plans outside of the building contract, it is not
established by the evidence.
[54] I am not satisfied that the applicant is entitled to damages for the cost of demolishing
the shed or for engineering plans. Without itemisation, it is not possible to tell what
9 Bellgrove v Eldridge (1954) 90 CLR 613.
-- 9 of 10 --
10
the cost of the rectification work would be without those items. I will adopt a
conservative approach by starting with the low end of the estimated total, being
$83,000 and deduct $10,000 for the excluded items. That leaves a total of $73,000
plus GST ($80,300) for demolition of the pool and surrounding concrete, and
construction of a compliant pool.
[55] The applicant provided a quote from another builder for the area around the pool to
be re-paved. That quote said:
60m2 pool surround 100mm think with thickenings, S182
Mesh, 32mpa concrete
Pumped in, saw cut and crusher dust included $11,000
Grind and seal pool surround 28 days later
60m2 and 20lm meters of coping to grind inc sealers and glass grit $9,500
Plus GST = $22,550.00
[56] In the absence of challenge from the respondent or evidence to the contrary, I accept
that this is a reasonable quote. The applicant is entitled to damages in that amount for
re-paving around the pool.
[57] The applicant provided a quote of $10,040 for the supply and construction of a kit
shed. As stated, I am not satisfied that the existing shed must be demolished. The
applicant is not entitled to damages for the cost of a new shed.
[58] The total damages that I have allowed is $102,850. The applicant paid the respondent
$5,000 less than the agreed contract price because of the defects. That amount should
be deducted, which leaves a total of $97,850.
[59] The applicant provided an itemised, paid, invoice for $852 for legal services in
relation to the termination of the contract. I am satisfied that the amount is reasonable
and was incurred in connection with the termination of the contract, so it is
recoverable under clause 23.1(c).
[60] The Tribunal may order interest to accrue on the damages awarded from the day of
the order. However, the applicant did not seek an order for interest, so I decline to
make one.
[61] I will give the respondent longer than the standard period to pay the damages for the
cost of rectification because it is a large amount for a small business.
Other orders
[62] The applicant sought recovery of $400 for the filing fee. The filing fee was $379.50.
The Tribunal may order costs under s 77(3)(h) of the QBCC Act. The discretion is a
broad one. I am satisfied that the cost of the filing fee was reasonably incurred by the
applicant in her efforts to pursue her legal entitlements. It is appropriate that the
respondent reimburse the $379.50 filing fee.
[63] The applicant also sought an apology from the respondent and for the respondent to
be issued a fine and demerit points on his QBCC licence. However, the Tribunal does
not have the power make such orders.
-- 10 of 10 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2026/093