BGM Projects Pty Ltd v Brisbane City Council & Ors [2026] QPEC 13
PLANNING AND ENVIRONMENT COURT
OF QUEENSLAND
CITATION: BGM Projects Pty Ltd v Brisbane City Council & Ors [2026]
QPEC 13
PARTIES: BGM PROJECTS PTY LTD (ACN 102 165 328)
(applicant)
v
BRISBANE CITY COUNCIL
(first respondent)
And
ROCHEDALE C4 PTY LTD (ACN 125 605 950)
(second respondent)
And
REMLEE PTY LTD (ACN 611 857 795)
(third respondent)
FILE NO: 3121 of 2025
DIVISION: Planning and Environment
PROCEEDING: Application in pending proceeding
ORIGINATING
COURT: Planning and Environment Court, Brisbane
DELIVERED ON: 30 March 2026 (ex tempore)
DELIVERED AT: Brisbane
HEARING DATE: 30 March 2026
JUDGE: Williamson KC DCJ
ORDER: The parties are to prepare a draft order reflecting the
reasons for judgment.
CATCHWORDS: PLANNING AND ENVIRONMENT – ORIGINATING
APPLICATION – APPLICATION TO AMEND
ORIGINATING APPLICATION – where the Originating
application seeks orders setting aside a conditional
development approval for operational works – where the
applicant seeks leave to amend the Originating application –
where leave was opposed by the second and third respondents
– whether there is an adequate explanation for the
amendment – whether the amendment is late – whether the
amendment gives rise to prejudice that cannot be cured by a
costs order.
-- 1 of 11 --
2
[1] The application in pending proceeding before the Court seeks leave to amend an
Originating application, filed 31 October 2025. The Originating application seeks
declaratory and consequential relief about a development approval granted by
Council’s delegate in respect of land at Rochedale Road, Rochedale. The approval
authorises the carrying out of operational work and was granted subject to
conditions. It is alleged the decision to grant the development approval is infected
with legal error and should be set aside.
[2] The Originating application has progressed to the point that the applicant, BGM, has
filed its affidavit material in support of the relief it seeks. BGM has also filed a
written outline. The material was all served on the respondents by 23 February
2026. BGM’s case has been fully disclosed to the respondents.
[3] Council has filed a certificate of its Chief Executive Officer, but no other material.
The certificate contains the material said to be before the decision maker.
[4] The second and third respondents have filed no material. Nor have they identified
any formal position in response to the Originating application, including
discretionary reasons that are said to militate against granting the relief sought.
[5] A review of the Originating application reveals BGM’s case. It asserts the
development approval granted by Council’s delegate is contrary to law and invalid.
Consequential relief is sought, namely that the approval be set aside and taken to
have no effect.
[6] The grounds relied upon by BGM are set out in the Originating application. The
grounds allege that Council’s assessment of the development application it
approved “miscarried and was in legal error” because: (1) Council failed to take
into account relevant considerations; and (2) Council took irrelevant considerations
into account.
[7] The legal error is said, in the circumstances, to have the following result:
“…the First Respondent [Council] could not:
(a) be satisfied that the Development Application
complied with the relevant assessment benchmarks
of the Planning Scheme, including Performance
Outcome (“PO”) 1(b), PO2, PO3, PO4, PO5,
LEGISLATION: Planning Act 2016, s 45
Planning and Environment Court Rules 2018, r 4
Uniform Civil Procedure Rules 1999, r 377
COUNSEL: Ms M Rodgers for the applicant
Ms S McCabe (solicitor) for the first respondent
Mr J Horton KC with Mr T Stork for the second and third
respondents
SOLICITORS: Connor O’Meara for the applicant
Brisbane City Legal for the first respondent
Cooper Grace Ward for the second and third respondents
-- 2 of 11 --
3
Acceptable Outcome 8.2 and corresponding PO8,
PO11 and PO12 of the Stormwater Code; and
(b) properly exercise its power to approve the
Development Application.”
[8] The grounds of the Originating application also allege: (1) the development
approval was granted contrary to law because the development application made to
obtain it did not include all of the relevant land; (2) the development approval lacks
finality because it imposes conditions deferring material matters for future
consideration; and (3) the exercise of the decision making power was unreasonable.
[9] There can be little doubt that each of the allegations I have just referred to seek to
impugn the development approval the subject of the proceeding. The Originating
application plainly puts the validity of the approval at risk. As a consequence, from
the date this proceeding was commenced, there has always been a risk for the
second and third respondents that the development authorised by the conditional
operational works approval may be subject to further consideration against
Council’s planning scheme.
[10] The Originating application was drawn with the benefit of a statement of reasons,
which were provided to BGM’s solicitors on 21 October 2025, some 10 days before
the proceeding was commenced.
[11] The first return date for the Originating application was 8 December 2025. On that
day, orders were made requiring Council to file the material it contends was before
the decision maker. Further, an order was made requiring BGM to file and serve
any further material, including its written submissions.
[12] Council filed a certificate of its Chief Executive Officer on 23 January 2026.
[13] BGM filed its affidavit material on 20 February 2026, after two extensions of time
were granted, by consent, on the papers. The written submissions followed on 23
February 2026.
[14] This application in pending proceeding accompanied BGM’s affidavit material and
was served on 20 February 2026. The form of the amendments proposed to the
Originating application are set out in Annexure A to the application in pending
proceeding. A review of Annexure A reveals amendments are proposed to one of
the declarations sought and supporting grounds. The amendments fall into one of
two categories; editorial or substantive.
[15] Editorial changes are proposed to paragraphs 19(a)(ii) and 19(a)(iii) of the
Originating application. The former involves deleting the word “and”. The latter
involves deleting a semicolon at the end of the subparagraph. In my view, leave is
not required for these amendments. They properly fall within an amendment
contemplated by a combination of r 4(2) of the Planning and Environment Court
Rules 2018 and r 377(2) of the Uniform Civil Procedure Rules 1999. If I am wrong
about this, I would have granted leave in any event. The editorial amendments are,
on any view, de minimis.
-- 3 of 11 --
4
[16] As to substantive changes, they appear at paragraphs 19(c) and 20(a) of Annexure
A. The change to paragraph 19(c) is also reflected in an amendment to the
declaration sought at paragraph 2 of the Originating application.
[17] Paragraph 19(c) is a new subparagraph. It is in the following terms:
“(c) The First Respondent failed to assess and decide the
Development Application in accordance with the Planning
Act 2016.
Particulars
(i) the Development Application was assessed against a
version of City Plan which was not in effect at the
time the Development Application was properly
made;
(ii) the Development Application was not assessed
against the overall outcomes and purpose of the
Infrastructure design code, Stormwater code and
Operational work code;
(iii) the Development Application was not assessed
against the provisions of the Flood overlay code and
Waterway corridors overlay code.”
[18] The amendment proposed to subparagraph 20(a) involves a deletion. BGM seeks
leave to delete reference to specific Performance outcomes and Acceptable
outcomes in the Stormwater code of Council’s planning scheme. The relevant
provision numbers follow the word “including”.
[19] Paragraph 20 of the Originating application, in its unamended form, asserts that the
decision maker could not have been satisfied the development application, if
approved, complied with relevant assessment benchmarks of the planning scheme,
including provisions of the Stormwater code. Paragraph 19 identifies the
circumstances relied upon to found this contention. Paragraph 19 alleges that the
decision maker failed to, amongst other things, take into account relevant
considerations, and took into account irrelevant considerations.
[20] Despite the opening words of paragraph 19(c), the amendment in Annexure A
introduces further particulars of the assertion made in paragraph 19(a) of the
Originating application. Indeed, the new subparagraph alleges the decision maker
failed to take into account: (1) the version of the planning scheme in force when the
application was properly made; and (2) the outcome of an assessment against
specific parts of a number of codes in the planning scheme, which are said to be
relevant assessment benchmarks.
[21] To remove any doubt about this, an amendment I allow will involve deleting the
opening words to subparagraph 19(c) and relocating the particulars that follow to
paragraph 19(a) of the Originating application.
[22] The codes referred to in paragraph 19(c)(ii) and (iii) of Annexure A include the
Stormwater code, which is pleaded at paragraph 20 of the Originating application.
This is what follows the word “including”. The balance of the codes referred to are
-- 4 of 11 --
5
new. The new codes referred to are the Infrastructure design code, the Operational
works code, the Flood overlay code and the Waterway corridors overlay code.
Reference to the particulars provided in relation to these codes reveal they are relied
upon to allege the first respondent failed to take into account relevant
considerations.
[23] An explanation was given for the amendments in affidavit form. The affidavit was
sworn by Mr Connor of Connor O’Meara Solicitors. A review of the affidavit
reveals that Mr Connor’s firm was given instructions to file and serve this
proceeding as quickly as possible. To draw the proceedings, a statement of reasons
was requested and obtained. The reasons, as I have already said, were delivered on
21 October 2025. The proceedings were filed some 10 days later, and some 8
weeks after the impugned decision was made. The 10 day turnaround period
between receiving the statement of reasons and filing the Originating application,
given the complexity of the decision making process and its associated content, is
by no means slow. The timing does not suggest there was any unreasonable delay
associated with the commencement of the proceeding.
[24] Mr Connor knew why he had been given instructions to file the proceeding as
quickly as possible. He understood that works under the development approval had
commenced on or about 15 October 2025. It is against this background, and having
received the statement of reasons on 21 October 2025, his focus when drawing the
proceeding was on four things. They are identified at paragraph 3 of Mr Connor’s
affidavit as follows: (1) the potential impacts of the development approval on the
land owned by BGM; (2) the adequacy and relevancy of the reporting provided by
the second respondent lodged in support of the development application; (3)
whether the supporting material was adequate to demonstrate compliance with the
applicable assessment benchmarks in the planning scheme; and (4) whether the
development application should have included BGM’s land.
[25] Mr Connor goes on to say that he did not turn his mind to whether the decision
maker had failed to consider particular assessment benchmarks. He gave reasons
for this. They can be summarised as follows: (1) he wrongly assumed Council had
identified the correct version and provisions of the planning scheme required for
assessment; (2) time pressure meant he overlooked the accuracy of Council’s
identification of the relevant planning scheme version and assessment benchmarks;
and (3) at the time the Originating application was drafted, only limited advice was
sought from the applicant’s stormwater engineer, which was directed to a review of
the reporting included with the development application, and referred to in the
statement of reasons. It was pointed out that the reporting provided with the
development application, and reviewed by the stormwater engineer, does not refer
to the assessment benchmarks pleaded in paragraph 19(c) of Annexure A.
[26] Council did not file and serve the material it contends was before the decision
maker until 23 January 2026. Mr Connor said it was upon closer review of this
material that it became apparent an assessment against the Flood overlay code and
Waterway corridors overlay code might have been required.
[27] The review of Council’s material caused Mr Connor’s team to contact BGM’s
stormwater engineer to confirm a preliminary view, namely that the development
application should have been assessed against the two codes I have referred to in
[26]. Advice was received from the engineer on the 13 February 2026. The advice
-- 5 of 11 --
6
confirmed the correctness of the preliminary view, namely, the development
application triggered assessment against two particular overlay codes in version 30
of Council’s planning scheme.
[28] Unsurprisingly at this point, Mr Connor undertook a further review of the material.
He said this led him to conclude that: (1) Council had relied on an incorrect version
of the planning scheme in its assessment; and (2) Council had not assessed the
development application against the purpose and overall outcomes of relevant
assessment benchmarks.
[29] On 19 February 2026, BGM’s stormwater expert provided Connor O’Meara
Solicitors with more substantial advice about the triggers for assessment against the
overlay codes. This advice forms part of the evidence at paragraphs 46 and 47 of
Mr Giles’ affidavit, which is Court document No. 18.
[30] On 19 February 2026, when the stormwater engineer’s advice was received, BGM’s
affidavit material and written submissions were well advanced. The substance of
the material, in total, led Mr Connor to conclude that the matters not identified in
the Originating application were of consequence to the decision maker’s assessment
and were material to the exercise of the power under the Planning Act 2016.
Instructions were then sought to amend the Originating application to include the
amendments set out in Annexure A. The application in pending proceeding and the
amendments in Annexure A were served on the respondents on 20 February 2026.
[31] I accept Mr Connor’s explanation for the amendments. It is frank, accepting that
assumptions were made as to the correctness, or otherwise, of Council’s assessment
and decision that, with the benefit of hindsight, should not have been made. The
assumptions were made given time pressure. They were not unreasonable
assumptions given: (1) Council is a very experienced assessment manager for
applications of the kind that were approved and can be assumed to correctly
identify, inter alia, the version of the planning scheme against which the assessment
must proceed; and (2) the development application material appears, on BGM’s
case, to make the same alleged errors as Council, providing a false sense of security
that the decision maker’s assessment was carried out against the correct assessment
benchmarks. The assumptions made by Mr Connor about the correctness, or
otherwise, of the assessment and decision making process here were not, in my
view, unreasonable in the circumstances.
[32] The explanation given by Mr Connor also demonstrates that the amendments to the
Originating application evolved, in part, with the provision of new material and
further advice. The material provided by Council on 23 January 2026, and the
advice received from BGM’s stormwater engineer, fall into this category. It is “new
information” received after the commencement of the proceeding. This information
informed the decision to amend the Originating application.
[33] The explanation given by Mr Connor is an adequate one for leave to amend the
Originating application. Taken in combination with the following matters, it is my
view, a strong case for leave has been demonstrated. The matters are: (1) the
amendments to paragraph 19(a) of the Originating application are de minimis; (2)
the amendments to paragraph 20(a) of the Originating application involve deleting
particulars, and do not add issues, nor change BGM’s case in a fundamental way;
(3) the amendment proposed to 19(c) of the Originating application is, in substance,
-- 6 of 11 --
7
a new particular of an existing allegation in paragraph 19(a), namely the decision
maker failed to have regard to a relevant consideration – any doubt or concern about
this can be resolved in the way identified at [21]; (4) the amendments have, contrary
to the second and third respondents’ submission, been advanced in a timely way;
and (5) it has not been contended the amendments have no prospects of success or
lack utility.
[34] I would add a further matter to the above, which is particularly directed at paragraph
19(c)(i) of Annexure A. The allegation contained therein is a simple one. It is
alleged the development application was assessed against a version of the planning
scheme, which was not in effect at the time the development application was
properly made. The allegation, in my view, makes express what is otherwise
implied in the assertion that Council failed to take into account a relevant
consideration.
[35] There appears to be little room for argument that the development application,
which was approved and now challenged, was subject to code assessment and
treated as properly made on 2 December 2024. The statutory assessment rules
prescribed by the Planning Act 2016, and applying to code assessment, contain a
strict assessment regime. The assessment regime requires the development
application to be assessed against only two things, one of which is an assessment
benchmark: s 45(3) of the Planning Act 2016. The assessment benchmark/s
referred to are those in effect when an application was treated as properly made:
s 45(6) of the Planning Act 2016.
[36] With this in mind, and taking paragraph 20(a) of the Originating application in its
unamended form, the issues to be determined in the proceeding already include this
question for determination: was the decision maker satisfied the development
application complied with the relevant assessment benchmarks in effect on 2
December 2024? This question, and the answer to it, will be the same that is
prompted by the new particular sought to be added to the Originating application in
paragraph 19(c)(i). The new particular begs this question: was the development
application assessed against the relevant assessment benchmarks in effect on 2
December 2024? On BGM’s case, the answer will be the same to both questions.
[37] The above demonstrates, in my view, that it is inescapable the particular alleged in
paragraph 19(c)(i) will need to be considered in order to resolve issues already
pleaded in the Originating application.
[38] The application to amend is unopposed by Council. It accepts the issues as
presently cast will require consideration of the matter expressly raised by paragraph
19(c)(i) of Annexure A.
[39] The application to amend was opposed by the second and third respondents. Three
reasons were advanced in opposition: (1) there is no adequate explanation for the
amendments; (2) the amendments are late; and (3) granting leave would give rise to
prejudice that cannot be remedied by a costs order.
[40] The second and third respondents criticise, in the first instance, the explanation for
the amendments given by junior counsel at a review on 10 March 2026. The
explanation, which was given in response to a question from the Court, was to the
effect that the amendments had arisen out of expert input during the preparation of
-- 7 of 11 --
8
affidavit material. It was submitted this explanation does not accord with the
evidence. This is an unfair submission.
[41] In the light of Mr Connor’s evidence, the explanation given by junior counsel does
accord, in part, but not completely, with the evidence. The explanation given by
junior counsel captures those amendments attributable to advice received from
BGM’s stormwater engineer. I would also add that the criticism is unfair because
the explanation provided to the Court by junior counsel was reluctantly provided
during a review when this application was listed for hearing. The explanation was
not advanced in the hearing of the application proper, nor was it suggested by junior
counsel that the explanation given at the review on 10 March 2026 was supported
by affidavit material.
[42] The criticisms of greater weight are those directed to Mr Connor’s affidavit. The
criticisms can be reduced to this proposition: at the time the Originating application
was prepared, BGM had sufficient information to raise the matters it now seeks to
plead in Annexure A. This is said to be made good having regard to: (1) the
statement of reasons received on 21 October 2025; (2) correspondence from BGM
to Council before, and during, the development application assessment process; and
(3) BGM’s own development application, which makes reference to the very codes
that are now sought to be raised in Annexure A. All of these matters, taken in
combination, are said to demonstrate that BGM had, or should be imputed with,
knowledge of the relevance of Flooding, Waterway and Stormwater codes, which
are the subject of the amendments proposed in paragraphs 19(c)(ii) and (iii) of
Annexure A. This can be accepted in so far as it relates to BGM, but only to a point.
I will return to this at [44].
[43] It does not follow, in my view, that the above criticisms, even if accepted, render
Mr Connor’s explanation inadequate. The evidence does not establish that Mr
Connor was armed with all of the knowledge referred to above and failed to take it
into account. Rather, in drawing the originating document, Mr Connor said he made
assumptions about the material, which have proven to be wrong. The assumptions
made, and the reliance placed upon them, as I have said, are fairly explained by time
pressure. The assumptions were also based on a misapprehension that Council had
correctly identified the relevant assessment benchmarks for assessment. Mr Connor
was not required for cross-examination to suggest otherwise.
[44] Further, the adequacy of Mr Connor’s explanation is not diminished because there
is an absence of evidence from a BGM representative who can explain why the
topics underlying the amendments were not drawn to Mr Connor’s attention prior to
filing the proceeding. To expect BGM to have drawn what are legal errors or
matters of planning scheme construction to Mr Connor’s attention is a step too far,
even assuming the history set out above. This area of the law can be complex,
requiring specialist knowledge to navigate. To suggest BGM had that necessary
experience and knowledge to give Mr Connor instructions to plead legal errors, or
particulars thereof, based on the history referred to above is unpersuasive. Further,
the proposition should not be lightly accepted in any event where, as here: (1) the
legal issues raised are not straight forward, requiring a detailed examination of
development application material in concert with Council’s planning scheme; and
(2) BGM was entitled to act on the advice of its lawyers, and experts, as to the
appropriate grounds and relief to be sought in the proceeding.
-- 8 of 11 --
9
[45] I am satisfied the explanation given by Mr Connor is an adequate one. The first
reason advanced by the second and third respondents in opposition to a grant of
leave is rejected.
[46] The second reason for opposing a grant of leave is delay. It was submitted that
delay in making the amendments should be considered against the background of
the relevant history, dating back to February 2025. This is the first time proceedings
of the kind commenced were threatened by BGM.
[47] It can be accepted BGM engaged in an exchange of correspondence with Council,
and the respondents, from February 2025 about the development application the
subject of this proceeding. It does not however follow that delay is to be measured
from this point. To do so would be unfair to BGM – the impugned decision was not
made until 7 months later.
[48] The evidence reveals the Originating application was filed after a request for a
statement of reasons was received on 21 October 2025. From this point, it took
BGM four months to finalise all its affidavit material, including submissions. The
amendments arise out of the evolution of that material and were communicated in a
timely way to the respondents. To suggest delay of this kind is sufficient to deny a
grant of leave, in my view, is unpersuasive. Delay is not a reason to refuse a grant of
leave to amend in this case.
[49] The third reason for opposing a grant of leave is prejudice. This point arises in the
context that the operational works the subject of the Originating application and
impugned development approval are well underway. This is known to all parties. It
explains the urgency with which the Originating application was filed relative to the
receipt of the statement of reasons.
[50] The evidence reveals Mr Pask made the decision to continue with the works the
subject of the impugned approval despite the commencement of this proceeding. At
paragraph 77 of his affidavit, Mr Pask identified the following impacts that he says
would arise if the amendments proposed to the Originating application are
permitted:
“77. The proposed new grounds now allege that some key
Planning Scheme Codes and other criteria were entirely
missed in the First Respondent’s original assessment, such
that the Applicant proposes to change how it now says the
OPW Approval may be invalid. I am concerned that if the
grounds are included this:
(a) could affect my ability to lawfully progress
the Stormwater Works; and / or
(b) could result in design or condition changes
to the Stormwater Works if they have to be
re-assessed and approved…”
[51] This evidence is relied upon to establish: (1) a grant of leave will give rise to
prejudice; and (2) the prejudice cannot be cured by a costs order.
-- 9 of 11 --
10
[52] I do not accept Mr Pask’s affidavit establishes the foundation for (1) and, in turn,
(2).
[53] Mr Pask’s evidence exposes the difficulty with the prejudice point advanced on
behalf of the second and third respondents. He has sworn that the amendments to
the Originating application will change BGM’s case in a way that says the
operational works approval is invalid for different reasons. I do not accept this is an
accurate characterisation of the proposed amendments. The Originating application
has always alleged that the development approval is invalid because of a failure to
take into account relevant considerations. The amendments do not alter this
position. Further, Mr Pask’s evidence ignores, in my view, that the amendments to
the Originating application: (1) include deletions and minor changes to editorial
form; (2) raise new particulars, rather than new reasons, for alleging the operational
works approval is invalid; and (3) do not alter the position that the proceeding
challenges the validity of the operational works approval, which could be set aside,
requiring further assessment of works already, or partially completed, against
Council’s planning scheme. Once these matters are appreciated, it is difficult to see
how the prejudice referred to arises by reason of the proposed amendments to the
Originating application.
[54] The risk to which Mr Pask refers in his affidavit, in my view, has always existed in
this proceeding. That a decision was made to proceed with the works despite that
risk is a commercial decision. The decision appears to have been made assuming:
(1) BGM has poor prospects of success, which was tied to the grounds pleaded in
the Originating application; and (2) a particular risk profile informed by (1). The
first assumption is problematic.
[55] The assumption made in (1) appears to have been approached as if prospects of
success are static. That is, no allowance was made by Mr Pask for a change in
circumstance, let alone a change in prospects. As experience shows, this is always a
risk in litigation.
[56] More specifically, there is always a risk of amendment to an Originating
application, such as here, where there is a time lag between the issues identified in
the originating document and provision of the decision maker’s material. That the
originating process might be the subject of amendment, such as to add new
particulars upon the receipt of the decision maker’s file, should have been accounted
for in Mr Pask’s decision to proceed with the works the subject of challenge. That
this factor was not apparently accounted for bespeaks an under assessment of risk
rather than prejudice arising by reason of an amendment to the Originating
application (that is intended to further particularise an existing allegation of legal
error).
[57] This is not to say, however, that prejudice to the second and third respondents by
reason of the relief sought in this proceeding will not be a valid issue at trial. That
works have been undertaken and are well underway, if not substantially completed,
will be relevant to the exercise of the discretion to grant the relief sought. Nothing
that I have said should be taken as a statement about considerations of this kind for
the trial of the proceeding. My remarks are limited to prejudice associated with a
grant of leave to amend the Originating application.
-- 10 of 11 --
11
[58] The application to amend the Originating application will be allowed, and more
specifically: (1) leave is granted to make the editorial changes to the Originating
application; and (2) leave is granted to amend the Originating application such that
the particulars below paragraph 19(c) are to form part of the particulars for
paragraph 19(a) with the remainder of paragraph 19(c) to be deleted. With respect
to paragraph 20(a), the amendment proposed is also allowed to the extent it involves
striking through the words “including” down to the word “code”.
[59] There is one final matter. The second and third respondents have cross-applied for
their costs of the application in pending proceeding. I accept the Court’s costs
power is enlivened here by reason of BGM’s decision to introduce new material. A
costs order will be made. The costs will be as agreed between the parties. The order
will be as follows: the applicant pay the second and third co-respondents’ costs of
the application in pending proceeding, fixed at $15,000.
[60] The parties are to forward a draft order to my chambers that reflects the above
reasons.
[61] I will also hear from the parties as to additional directions that can be made to
facilitate the hearing of the Originating application.
-- 11 of 11 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2026/013