Brisbane Airport Corporation Pty Ltd v Jacobs Group (Australia) Pty Ltd [2025] QSC 349
SUPREME COURT OF QUEENSLAND
CITATION: Brisbane Airport Corporation Pty Ltd v Jacobs Group
(Australia) Pty Ltd [2025] QSC 349
PARTIES: BRISBANE AIRPORT CORPORATION PTY LTD
(plaintiff/respondent)
v
JACOBS GROUP (AUSTRALIA) PTY LTD
(defendant/applicant)
FILE NO: BS No 13166 of 2024
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 16 December 2025
DELIVERED AT: Brisbane
HEARING DATE: 16 December 2025
JUDGE: Kelly J
ORDERS: 1. The proceeding be stayed pursuant to s 8(1) of the
Commercial Arbitration Act 2013 (Qld), pending any
arbitral reference between the parties or until further
order.
2. The plaintiff pay the defendant’s costs of the
application filed 25 November 2025 on the standard
basis.
CATCHWORDS: ARBITRATION – ARBITRATION AGREEMENT –
CONSTRUCTION OF ARBITRATION AGREEMENT OR
REFERENCE – GENERALLY – where the plaintiff and the
defendant are parties to a design consultancy agreement
entered into by deed – where the design consultancy agreement
concerned the provision of design engineering services by the
defendant for a new runway project at the Brisbane Airport –
where the plaintiff started a proceeding by way of claim and
statement of claim seeking an indemnity or damages for
allegedly defective design work performed by the defendant
said to have caused cracking in parts of the runway – where
the defendant contends that the proceeding has been started in
contravention of an arbitration agreement contained in a clause
in the deed – where the defendant applies for a stay pursuant
to s 8(1) of the Commercial Arbitration Act 2013 (Qld) or in
the court’s inherent jurisdiction – where there emerged four
real issues on this application – where the first issue concerned
-- 1 of 12 --
2
the proper construction of the clause and whether, properly
construed, the clause conferred upon the parties a choice or
option as to whether to commence litigation or to engage the
dispute resolution process – where the second issue concerned
whether, in circumstances where the steps outlined in the
clause had not occurred, the arbitration agreement was to be
regarded as “inoperative” within the meaning of that
expression as contained in s 8 – where the third issue
concerned whether, upon the proper construction of the clause,
what might be styled as “non-contractual claims” were
excluded from the agreement to arbitrate – where the fourth
issue concerned whether, in circumstances where s 8 had no
application, this court in its supervisory jurisdiction could and
should impose a stay of the proceeding – whether the
proceeding should be stayed pursuant to s 8(1) of the Act,
pending any arbitral reference between the parties or until
further order
Commercial Arbitration Act 2013 (Qld), s 8(1)
Australian Broadcasting Commission v Australasian
Performing Right Association Ltd (1973) 129 CLR 99, cited
Broken Hill City Council v Unique Urban Built Pty Ltd
[2018] NSWSC 825, cited
Ecosse Property Holdings Pty Ltd v Gee Dee Nominees Pty
Ltd (2017) 261 CLR 544, cited
Electricity Generation Corporation v Woodside Energy Ltd
(2014) 251 CLR 640, cited
John Holland Pty Ltd v Kellogg Brown & Root Pty Ltd
[2015] NSWSC 451, cited
Pacific Carriers Ltd v BNP Paribas (2004) 218 CLR 451,
cited
PMT Partners Pty Ltd (in liq) v Australian National Parks
and Wildlife Service (1995) 184 CLR 301, cited
Siam Steel International Plc v Compass Group (Australia)
Pty Ltd (2014) 293 FLR 260, cited
Stevens Constructions Pty Ltd v Zorko (2002) 81 SASR 316,
cited
WCX M4-M5 Link AT Pty Ltd v Acciona Infrastructure
Projects Australia Pty Ltd (No 2) [2022] NSWSC 505, cited
COUNSEL: A J H O’Brien and L Heit for the plaintiff/respondent
P Franco KC for the defendant/applicant
SOLICITORS: Carter Newell Lawyers for the plaintiff/respondent
Holding Redlich for the defendant/applicant
-- 2 of 12 --
3
An application for a stay
[1] The plaintiff (“BAC”) and the defendant (“Jacobs”) are parties to a Design
Consultancy Agreement entered into by deed on 12 February 2015. The Design
Consultancy Agreement concerned the provision of design engineering services by
Jacobs for a new runway project at the Brisbane Airport. The Design Consultancy
Agreement was varied by a further deed on 28 May 2018. I will refer to the initial
agreement as amended by the later agreement as the “Varied Deed”.
[2] On 1 October 2024, BAC started a proceeding by way of claim and statement of claim
seeking an indemnity or damages for allegedly defective design work performed by
Jacobs said to have caused cracking in parts of the runway. By that proceeding, BAC
seeks:
(a) an indemnity pursuant to a clause of the Varied Deed;
(b) damages for breach of contract;
(c) damages for negligence;
(d) damages pursuant to s 236 of the Australian Consumer Law (“the ACL”).
[3] On 14 November 2025, Jacobs filed a conditional notice to defend.
[4] Jacobs contends that the proceeding has been started in contravention of an arbitration
agreement contained in cl 23 of the Varied Deed. The application now before the
court is an application by Jacobs for a stay pursuant to s 8(1) of the Commercial
Arbitration Act 2013 (Qld) (“the Act”) or in the court’s inherent jurisdiction.
The Act and the Varied Deed
[5] Section 8(1) of the Act provides that a court before which an action is brought in a
matter which is the subject of an arbitration agreement must, if a party so requests
not later than when submitting the party’s first statement on the substance of the
dispute, refer the parties to arbitration proceedings unless it finds that the agreement
is null and void, inoperative or incapable of being performed.
[6] Clause 23 of the Varied Deed is in the following material terms:
“23 Disputes
23.1 Notice of dispute
Subject to clause 23.2, if a dispute or difference between the
Consultant and BAC arises out of or in connection with the
Agreement, then either party may serve the other with a notice
of dispute, in writing, adequately identifying and providing
details of the dispute or difference. Notwithstanding the
existence of a dispute or difference, the Consultant must
continue to perform its obligations under the Agreement.
23.2 Time for disputing direction
-- 3 of 12 --
4
If the Consultant disputes a direction or determination given
pursuant to the Agreement then the Consultant must serve BAC
with a notice of dispute which complies with clause 23.1,
within 5 Business Days of the direction or determination being
given. If the Consultant fails to serve a notice of dispute
regarding a direction or determination strictly in accordance
with this clause 23.2, the Consultant will be forever barred from
disputing BAC’s direction or determination.
23.3 Meeting of representatives
Within 5 Business Days after a dispute or difference is notified
in accordance with either clause 23.1 or 23.2, BAC’s
Representative (and any other representative of BAC,
nominated by BAC’s Representative) and the Consultant (if a
person) or a director of the Consultant (if a company) must
meet to discuss the issue in good faith with a view to resolving
the issue by agreement.
23.4 Referral to Management Committee
If a dispute or difference remains unresolved after the parties
have met in accordance with clause 23.3, either party may refer
the issue to the Management Committee immediately (or
within such longer period as the parties may agree). For the
purposes of this clause 23.4, Management Committee means
the committee established by the parties comprising two senior
managers from each party.
23.5 Management Committee to meet
The Management Committee must meet at BAC’s offices
within 10 Business Days of having the issue referred to it under
clause 23.4, to discuss the dispute or difference in good faith
with a view to resolving the issue by agreement.
23.6 Arbitration
(1) If the dispute or difference is not resolved within:
(i) 25 Business Days after the service of the notice of
dispute under clause 23.1 or clause 23.2 (as the case
may be); or
(ii) such longer period of time as the parties may agree
in writing,
then unless the parties have, prior to that time, agreed
some other means of attempting to resolve the dispute
or difference (such as mediation), the dispute or
difference shall be finally settled by arbitration under
the Rules of Arbitration of the International Chamber of
Commerce (Rules) in effect at the time of the arbitration
by one arbitrator appointed in accordance with the
Rules.
-- 4 of 12 --
5
(2) The seat of the arbitration shall be Brisbane, Australia,
and it shall be conducted in the English language.
(3) The arbitration award shall be final and binding on the
parties. The parties undertake to carry out any award
without delay and waive their right to any form of
recourse based on grounds other than those contained in
the United Nations Convention on the Recognition and
Enforcement of Foreign Arbitral Award of 1958 insofar
as such waiver can validly be made. Judgement upon
the award may be entered by any court having
jurisdiction thereof or having jurisdiction over the
relevant party or its assets.
(4) Either party has the right to apply to any court of
competent jurisdiction for interim relief, including
urgent injunctive relief, necessary to preserve the
party’s rights. A request by a party to a court of
competent jurisdiction for interim measures necessary
to preserve the party’s rights shall not be deemed
incompatible with, or a waiver of, this agreement to
arbitrate.
23.7 Condition precedent to commencing proceedings
Compliance with the procedures in this clause 23 is mandatory
and is a condition precedent to either party commencing
arbitration (other than urgent or injunctive relief) in relation to
a dispute under the Agreement.”
[7] BAC also referred to cl 5.8 which materially provides that the Varied Deed is
governed by the law of Queensland and each party submits to the non-exclusive
jurisdiction of the courts of Queensland.
[8] Section 7(1) of the Act provides that an “arbitration agreement” is an agreement by
the parties to submit to arbitration all or certain disputes which have arisen or which
may arise between them in respect of a defined legal relationship, whether contractual
or not. An arbitration agreement must be in writing.1
[9] BAC concedes that cl 23 contains an arbitration agreement within the meaning of that
expression as defined by s 7(1) of the Act. BAC submits that, whilst cl 23 contains
an arbitration agreement, the parties agreed that only those disputes for which a notice
under cl 23.1 had been issued, and where subsequent conditions contained in that
clause had been met, were disputes to be submitted to arbitration. BAC submitted
that, upon the proper construction of the Varied Deed, the parties were free to elect
whether to litigate their disputes or to trigger the dispute resolution process set out in
cl 23, and only in that latter case after the completion of certain steps would the
agreement to arbitrate operate.
1 s 7(3) of the Act.
-- 5 of 12 --
6
The real issues in dispute
[10] Having regard to the parties’ written and oral submissions, there emerged four real
issues on this application. The first concerned the proper construction of cl 23 and
whether, properly construed, that clause conferred upon BAC and Jacobs a choice or
option as to whether to commence litigation or to engage the dispute resolution
process under cl 23. The second concerned whether, in circumstances where the steps
outlined in cls 23.1 to 23.5 had not occurred, the arbitration agreement was to be
regarded as “inoperative” within the meaning of that expression as contained in s 8.
The third was whether, upon the proper construction of cl 23, what might be styled
as “non-contractual claims”, essentially involving claims in negligence and under the
ACL, were excluded from the agreement to arbitrate. The fourth concerned whether,
in circumstances where s 8 had no application, this court in its supervisory jurisdiction
could and should impose a stay of the proceeding.
The first issue
[11] As to the first issue, it was uncontroversial that the Varied Deed was an agreement
which fell to be construed as a commercial contract. It is convenient to outline some
relevant principles of interpretation. A starting point is the often cited statement in
Australian Broadcasting Commission v Australasian Performing Right Association
Ltd,2 where Gibbs J said:
“It is trite law that the primary duty of a court in construing a written
contract is to endeavour to discover the intention of the parties from
the words of the instrument in which the contract is embodied. Of
course the whole of the instrument has to be considered, since the
meaning of any one part of it may be revealed by other parts, and the
words of every clause must if possible be construed so as to render
them all harmonious one with another. If the words used are
unambiguous the court must give effect to them, notwithstanding that
the result may appear capricious or unreasonable, and notwithstanding
that it may be guessed or suspected that the parties intended something
different. The court has no power to remake or amend a contract for
the purpose of avoiding a result which is considered to be inconvenient
or unjust. On the other hand, if the language is open to two
constructions, that will be preferred which will avoid consequences
which appear to be capricious, unreasonable, inconvenient or unjust,
‘even though the construction adopted is not the most obvious, or the
most grammatically accurate’, to use the words from earlier authority
cited in Locke v Dunlop (1888) 39 Ch D 387, at p 393, which, although
spoken in relation to a will, are applicable to the construction of
written instruments generally; see also Bottomley's Case (1880)
16 Ch D 681, at p 686. Further, it will be permissible to depart from
the ordinary meaning of the words of one provision so far as is
necessary to avoid an inconsistency between that provision and the
rest of the instrument. Finally, the statement of Lord Wright in Hillas
& Co Ltd v Arcos Ltd (1932) 147 LT 503, at p 514, that the court
should construe commercial contracts ‘fairly and broadly, without
being too astute or subtle in finding defects’, should not, in my
2 (1973) 129 CLR 99 at 109–10.
-- 6 of 12 --
7
opinion, be understood as limited to documents drawn by businessmen
for themselves and without legal assistance (cf. Upper Hunter County
District Council v Australian Chilling and Freezing Co Ltd (1968)
118 CLR 429, at p 437).”
[12] The terms of a commercial contract are to be understood objectively by what a
reasonable businessperson would have understood them to mean.3 The reasonable
businessperson is someone placed in the position of the parties at the time of the
contract.4 It is from that person’s perspective that the court considers the language
used by the parties, the surrounding circumstances known to them and the commercial
purpose and objects of the contract.5 A court is entitled to approach the task of giving
a commercial contract a business like interpretation on the assumption “that the
parties intended to produce a commercial result”.6 A commercial contract is to be
construed so as to avoid it “making commercial nonsense or working commercial
inconvenience”.7
[13] BAC relied upon three principal arguments in support of its submission that cl 23
revealed the parties’ objective intention to provide a choice as to whether to
commence litigation or to trigger the dispute resolution process under cl 23. Those
submissions may be outlined as follows. No party was required to serve a notice of
dispute under cl 23.1. Emphasis was placed upon the word “may” as it appeared in
cl 23.1. Compliance with cl 23 was made a condition precedent to the commencement
of arbitration, but not to litigation. The parties, by cl 5.8, submitted to the non-
exclusive jurisdiction of the Queensland courts. Properly construed, cl 23 was said
to merely permit the instigation of contractual steps culminating in an arbitration and
s 8(1) of the Act was not “enlivened” until such time as either BAC or Jacobs had
elected to trigger the dispute resolution process under cl 23.
[14] I reject these arguments as to the proper construction of cl 23.1. I accept as a starting
point that a court will not treat a contract as preventing parties from pursuing their
remedies in the courts unless it is clear that that is what they have agreed. However,
I am also conscious of what was said by Brennan CJ, Gaudron and McHugh JJ in
PMT Partners Pty Ltd (in liq) v Australian National Parks and Wildlife Service8 to
the effect that the aims of dispute resolution are not well served and disputes are not
readily resolved by procedures which can be set at nought if one party elects to pursue
some other course of action. Having regard to cl 23, read as a whole and with regard
to the other provisions of the Varied Deed to which BAC referred, I favour the
construction of cl 23 which is to the effect that the parties have agreed to provide for
arbitration rather than litigation as the ultimate means of dispute resolution. The
presence of the word ‘may’ in cl 23.1 reflects the fact that if there is a dispute each
party has the option of acquiescing in the view of the other party or giving notice with
a view to arbitration. I would respectfully adopt, in this regard, the reasoning of
3 Ecosse Property Holdings Pty Ltd v Gee Dee Nominees Pty Ltd (2017) 261 CLR 544 at 551 per Kiefel,
Bell and Gordon JJ.
4 Ibid.
5 Pacific Carriers Ltd v BNP Paribas (2004) 218 CLR 451 at 461–2 [22] per Gleeson CJ, Gummow,
Hayne, Callinan and Heydon JJ; Electricity Generation Corporation v Woodside Energy Ltd (2014)
251 CLR 640 at 656–7 [35] per French CJ, Hayne, Crennan and Kiefel JJ.
6 Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640 at 656–7 [35].
7 Ibid.
8 (1995) 184 CLR 301 at 311.
-- 7 of 12 --
8
Doyle CJ in Stevens Constructions Pty Ltd v Zorko.9 I also note that cl 23.7 contains
express language that compliance with the procedures in cl 23 is mandatory. Those
words precede the words “and is a condition precedent …”. I find that the objective
agreement of the parties was that compliance with the procedures in cl 23 was
mandatory. The presence of the mandatory language in cl 23.7 is inconsistent with
the notion that arbitration was optional to litigation in the usual or ordinary course. It
is not surprising that cl 23.7 spoke in terms of the procedures being a condition
precedent to arbitration and made no mention of litigation. Upon the proper
construction of the Varied Deed, litigation in the usual course was not contemplated.
The presence of cl 5.8 does not warrant any different conclusion. Clause 23.6
conferred a right to apply to any court of competent jurisdiction for interim relief,
including urgent injunctive relief, necessary to preserve the party’s rights. The parties
agreed that the exercise of that limited right was not to be deemed incompatible with
or a waiver of the agreement to arbitrate.
The second issue
[15] As to the second issue, in the alternative to its primary submissions on the first issue,
BAC submitted that the arbitration agreement was “inoperative” within the meaning
of s 8 because the preconditions to arbitration had not been satisfied. According to
that submission, arbitration under cl 23.6 could only occur once mandatory
preconditions to arbitration set out in earlier subclauses of cl 23 had been satisfied.
As none of those preconditions had been met, the parties’ agreement to arbitrate was
to be regarded as “contractually dormant” with no party having an entitlement to
commence arbitration. I reject these submissions.
[16] It may be observed that s 8 appears in an Act which has the paramount object of
facilitating the fair and final resolution of commercial disputes. The Act aims to
achieve that object by enabling parties to agree about how their commercial disputes
are to be resolved and by providing procedures that enable commercial disputes to be
resolved in a cost-effective manner informally and quickly. The Act must be
interpreted so that the paramount object of the Act is achieved.
[17] In WCX M4-M5 Link AT Pty Ltd v Acciona Infrastructure Projects Australia Pty Ltd
(No 2),10 Rees J conducted a thorough and comprehensive analysis of the meaning
of “inoperative” as contained within equivalent provisions to s 8 of the Act. In the
course of her Honour’s analysis, reference is made to two decisions of Hammerschlag
J in John Holland Pty Ltd v Kellogg Brown & Root Pty Ltd11 and Broken Hill City
Council v Unique Urban Built Pty Ltd.12 In John Holland, Hammerschlag considered
that an arbitration agreement was “presently inoperative” within the meaning of s 8(1)
in circumstances where proceedings had been commenced before negotiation or
expert determination had taken place. His Honour reasoned that unless and until a
condition was fulfilled neither party could effectively refer a dispute to arbitration
and it was only when the condition was fulfilled that the arbitration agreement became
operative. In Broken Hill, his Honour interpreted “inoperative” to mean having no
field of operation or to be without effect.
9 (2002) 81 SASR 316 at [25] to [28].
10 [2022] NSWSC 505 at [95] to [121].
11 [2015] NSWSC 451.
12 [2018] NSWSC 825.
-- 8 of 12 --
9
[18] In the course of her Honour’s reasons in WCX M4-M5, and after having conducted a
detailed analysis of the authorities, Rees J relevantly reasoned and concluded as
follows:
“Generally, ‘inoperative’ has been interpreted across jurisdictions
implementing the Convention and the Model Law as meaning that the
arbitration agreement has ceased to have effect for the future, either
for a specific type of dispute or at large. An arbitration agreement may
be ‘inoperative’ as it is unenforceable, has been amended by a further
agreement, is the subject of res judicata, has been set aside by a Court,
has been frustrated or discharged by breach or by reason of waiver,
estoppel, election or abandonment or has otherwise been repudiated.
John Holland falls outside this rubric. It may be observed that
Hammerschlag J was not taken to the authorities referred to in this
judgment. Whilst John Holland was approved in Blanalko and
Transurban, neither case concerned whether proceedings should be
referred to arbitration notwithstanding that a preliminary step under a
tiered dispute resolution clause had yet to be completed. (The case
may also be distinguished as the arbitration agreement expressly
provided, ‘It is a condition precedent to a party being entitled to refer
a Dispute to arbitration … or to commence court proceedings … that
the procedures referred to … first be complied with.’ Schedule 3 of
the D&C Deed does not so provide.)
Whilst a more experienced commercial judge would be hard to find, I
respectfully consider that, to the extent that John Holland is authority
for the proposition that failure to complete preliminary steps in a tiered
dispute resolution clause before arbitration makes the clause
‘inoperative’, it should not be followed. Such a construction would
undermine the object of the Act, depart from the interpretation of the
term more widely and enable a party to bypass their contractual
bargain to submit their disputes to arbitration by commencing
proceedings before all preliminary steps have been completed:
Channel Tunnel Group at 669 (per Staughton LJ). As Findlay J put it
in Westco, ‘It cannot possibly have been the intention of the parties
that, if one of them issues a writ before that [preliminary] step is taken,
their joint wish to avoid proceedings at law is frustrated’: at [11]. Or
as Le Miere J stated in Siam Steel, ‘To construe “inoperative” to cover
such a situation would turn the exception … into a backdoor for a party
wanting to escape the arbitration agreement’: at [45].
I doubt that Hammerschlag J had such a result in mind. Rather, in both
John Holland and Broken Hill City Council v Unique Urban Built, his
Honour made facultative orders to hold the parties to their bargain to
arbitrate, notwithstanding a failure to comply with the precise terms
of the arbitration agreement, at least by the time that the application
for a stay was heard. Hammerschlag J either stayed or stood over the
proceedings until the preliminary steps required before arbitration had
been completed.
As such, the arbitration agreement in the D&C Deed is ‘operative’
notwithstanding that the expert determination phase has yet to be
-- 9 of 12 --
10
undertaken. As such, the Court “must” refer the parties to arbitration.
The fact that preliminary steps must be taken before the Jurisdiction
Dispute or Directions Dispute reaches the arbitration stage matters not.
As the Court explained in Hancock Prospecting Pty Limited v
Rinehart, section 8 ‘involves the referral to arbitration, by a stay of
court proceedings’: at [146]. In that case, the Court stayed the
proceedings under section 8(1) ‘pending any arbitral reference
between the parties or until further order’: at [417], relevantly upheld
by the High Court on appeal (Rinehart v Hancock Prospecting Pty Ltd
(2019) 267 CLR 514 at [81]. The same result was achieved, albeit by
a different route, in Channel Tunnel Group. As Staughton LJ observed
at 669:
‘The defendant in the court proceedings who applies for a stay may
not have any claim which he wishes to make against the plaintiff,
or any other reason either to start an arbitration or to carry out any
preliminary action before there can be one; he may merely wish to
resist the plaintiff’s claim. I can see no reason why he should not
say to the plaintiff: “I dispute your claim. If you wish to pursue it,
you must carry out the preliminary step and then proceed to
arbitration”.’”
[19] In Siam Steel International Plc v Compass Group (Australia) Pty Ltd,13 Le Miere J
observed:
“An arbitration agreement is not inoperative in relation to particular
claims merely because an arbitrator has not been appointed or a step
that must be taken before an arbitrator is appointed has not yet been
taken in relation to those claims. To construe ‘inoperative’ to cover
such a situation would turn the exception in s 7(5) into a backdoor for
a party wanting to escape the arbitration agreement. The effect of s 7
of the International Arbitration Act is that the parties are to be held to
their bargain to arbitrate except relevantly where the arbitration
agreement has ceased to have effect for the future at least in relation
to the claims the subject of the action.”
[20] Later, his Honour continued:
“Section 7(2) of the International Arbitration Act provides that if the
specified conditions are met the court shall stay the proceedings and
refer the parties to arbitration. The plaintiff objected that the court
cannot refer the parties to arbitration because no valid notice of referral
to arbitration has been given by the parties and no arbitrator has been
validly appointed. In its further written submissions filed on 30
October 2014 the defendant said that more than one construction s 7
of the International Arbitration Act was open but that the better
construction gave rise to the conclusion that the court should not stay
the proceedings where a condition precedent to the referral of the
relevant dispute to arbitration has not occurred. The argument is as
follows. The court's power under the International Arbitration Act s
13 (2014) 293 FLR 260 at [45].
-- 10 of 12 --
11
7(2) is to stay the proceedings and refer the parties to arbitration. If the
operation of the contractual provisions is such that the court cannot
refer the parties to arbitration because the matters in dispute have not
been identified by the mandatory mechanism provided by the contract
in the event of a dispute then that itself indicates that the agreement is
relevantly inoperative.
I do not agree that the arbitration agreement is inoperative because a
step that must be taken before an arbitrator is appointed has not yet
taken place. I do not agree that the court cannot refer the parties to
arbitration, and therefore cannot stay the proceedings, because an
arbitrator has not been appointed or a step that must be taken before
an arbitrator is appointed has not yet been taken.”
[21] The reasoning of Rees J in WCX M4-M5 and of Le Miere J in Siam is in my respectful
view, compelling and authoritative. In my consideration, the reasoning of Rees J and
of Le Miere J is consistent with authority and gives effect to the paramount object of
the Act. For the reasons explained by Rees J in WCX M4-M5, I decline to follow the
reasoning of Hammerschlag J in John Holland and Broken Hill City Council. The
arbitration agreement is not inoperative in the circumstances of the present case.
The third issue
[22] As to the third issue, BAC’s argument sought to limit the referral to arbitration to
what might be described as “non-contractual claims”. In that regard, BAC’s
arguments sought to focus upon the language in cl 23.7 “under the agreement”,
without paying proper regard to the earlier language in cl 23.1. The earlier language
in cl 23.1 contemplated that a notice of dispute might be given in respect of “a dispute
or difference” arising “out of or in connection with the agreement”. In oral
submissions, BAC conceded that this language in cl 23.1 was apt to encompass all
claims in its statement of claim in this proceeding. Counsel for Jacobs correctly
emphasised the introductory words of cls 23.4 and 23.6, namely “the dispute or
difference”. Those words are a clear reference to the dispute or difference referred to
in cl 23.1. The contemplated referral to arbitration is of a dispute of difference arising
out of or in connection with the agreement. The words “dispute under the agreement”
as they appear in cl 23.7 should be interpreted as a shorthand reference to “the dispute
or difference” the subject of any notice of dispute as referred to in cl 23.1. It would
also be uncommercial to interpret the Varied Deed as limiting arbitration to claims
strictly “under the contract” when cl 23 contemplated a notice of dispute being given
in respect of much wider claims, namely claims concerning a dispute or difference
arising out of or in connection with the agreement.
Orders
[23] Having regard to my reasons, it is not necessary for me to proceed to decide the fourth
issue.
[24] Jacobs proposed an order that the proceeding be stayed pursuant to s 8(1) of the Act,
pending any arbitral reference between the parties or until further order. BAC did not
make any submission to the effect that this form of order was inappropriate in the
event that its arguments in respect of the first to third issues were unsuccessful.
-- 11 of 12 --
12
[25] The orders I make are as follows:
1. The proceeding be stayed pursuant to s 8(1) of the Act, pending any arbitral
reference between the parties or until further order.
2. The plaintiff pay the defendant’s costs of the application filed 25 November
2025 on the standard basis.
-- 12 of 12 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2025/349