CPB Contractors Pty Ltd & Ors v MSS Projects (NSW) Pty Ltd t/as MSS Steel & Ors [2025] QSC 239
SUPREME COURT OF QUEENSLAND
CITATION: CPB Contractors Pty Ltd & Ors v MSS Projects (NSW) Pty
Ltd t/as MSS Steel & Ors [2025] QSC 239
PARTIES: CPB CONTRACTORS PTY LIMITED ABN 98 000 893
677
BAM INTERNATIONAL AUSTRALIA PTY PTD ABN
47 152 589 850
GHELLA PTY LTD ABN 85 142 392 461
UGL ENGINEERING PTY LIMITED ABN 96 096 365
972
TOGETHER AN UNINCORPORATED JOINT
VENTURE TRADING AS CPB BAM GHELLA UGL
JOINT VENTURE ABN 80 900 474 484
(Applicants)
v
MSS PROJECTS (NSW) PTY LTD TRADING AS MSS
STEEL ABN 86 630 822 034
(First Respondent)
v
DAVID RICHARD BALDRY ADJUDICATOR NO.
J1248299
(Second Respondent)
FILE NO/S: BS No 1712 of 2025
DIVISION: Trial Division
PROCEEDING: Hearing
ORIGINATING
COURT:
Supreme Court at Brisbane
DELIVERED ON: 24 September 2025
DELIVERED AT: Townsville
HEARING DATE: 19 August 2025
JUDGE: Johnstone J
ORDER: The orders of the Court are:
1. The application be granted.
-- 1 of 22 --
2
2. It is declared that the response dated 21 August
2024 to the payment claim dated 1 August 2024 is a
payment schedule for the purposes of the Building
Industry Fairness (Security of Payment) Act 2017
(Qld).
3. I will hear the parties as to any additional orders
and as to costs.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION –
STATUTORY REGULATION OF ENTITLEMENT TO
AND RECOVERY OF PROGRESS PAYMENTS –
ADJUDICATION OF PAYMENT CLAIMS – where the first
respondent submitted a payment claim on 1 August 2024 –
where the applicant submitted a response to the payment claim
on 21 August, which it contends was a payment schedule –
where the adjudicator determined the payment schedule had
failed to comply with the requirements of s 69(c) of the
Building Industry Fairness (Security of Payment) Act 2017
(Qld) – whether the applicant’s response was a payment
schedule
Building Industry Fairness (Security of Payment) Act 2017
(Qld), s 69, s 75, s 76, s 77, s 78, s 79, s 82, s 88
Building and Construction Industry Payments Act 2004, s 18
Northbuild Constructions Pty Ltd v Central Interior Linings
Pty Ltd [2012] 1 Qd R 525
Melaluca View Pty Ltd v Sutton Constructions Pty Ltd & Ors
[2019] QSC 226
Kirk v Industrial Court (NSW) (2010) 239 CLR 531
Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd [2010]
NSWCA 190
Style Timber Floor Pty Ltd v Krivosudsky [2019] NSWCA
179
Ausipile Pty Ltd v Bothar Boring and Tunnelling (Australia)
Pty Ltd [2021] QCA 223
Minimax Fire Fighting Systems Pty Ltd v Bremore
Engineering (WA) Pty Ltd & Ors [2007] QSC 333
Witron Australia Pty Ltd v Against Turnkey Innovative
Engineering Pty Ltd [2023] NSWCA 305
State Water Corporation and Civil Team Engineering Pty Ltd
[2013] NSWSC 1879N
Acciona Agua Australia Pty Ltd & Monadelphous
Engineering Pty Ltd [2020] 4 QR 410
Multiplex Constructions Pty Ltd v Luikens [2003] NSW SC
1140
Clarence Street Pty Ltd v Isis Projects Pty Ltd (2005) 64
NSWLR 448
-- 2 of 22 --
3
COUNSEL: Mr MD Ambrose KC for the applicant
Mr DJ Butler KC and Ms FJ Chen for the first respondent
SOLICITORS: Carter Newell for the applicants
McInnes Wilson Lawyers for the first respondent
The Application
[1] The applicant is an unincorporated joint venture engaged in the construction of the
certain underground sections of the Cross River Rail station at Roma Street in Brisbane.
[2] On 25 May 2023 the joint venture entered into a written supply contract for steel in
relation to the project with the first respondent, MSS Projects.
[3] On 1 August 2024 MSS Projects submitted payment claim number 21 for works under
the subcontract in the sum of $2,557,707.59 (inclusive of GST) (the payment claim).
The payment claim comprised sums for original contract works (OCW) and Approved
Variations. There is no dispute that the payment claim met the requirements of the
Building Industry Fairness (Security of Payment) Act 2017 (Qld) (BIF Act).
[4] On 21 August 2024, the joint venture issued a response to the payment claim to MSS
Projects which it contends was a payment schedule under the BIF Act. Pursuant to that
response, the joint venture proposed to pay the sum of $227,925.58 (inclusive of GST).
On 2 October 2024, MSS Projects lodged an adjudication application under s 79 of the
BIF Act.
[5] On 18 November 2024, the joint venture lodged an adjudication response pursuant to
s 82 of the BIF Act.
[6] On 17 December 2024, the adjudicator, who is the second respondent to the application
(but against whom no relief is sought), provided the joint venture and MSS Projects
with his adjudication decision (adjudication decision number 2658135) dated 17
December 2024.
[7] On 16 January 2025 the adjudicator provided an amended adjudication decision and
determined that $2,671,393.13 (including interest and fees) was payable.
-- 3 of 22 --
4
[8] The adjudicator determined that the payment schedule failed to comply with the
requirements of s 69(c) of the BIF Act. The consequence being that by operation of
s 77 of the BIF Act, the joint venture became liable to pay the full amount claimed
under the payment claim.
[9] The applicant has paid $2,744,070.20 to the first respondent on account of this
adjudication decision in two payments, $2,682,554.91 on 14 January 2025 and
$61,515.30 on 22 January 2025.1 The total amount, I presume includes additional
interest, however it is not in dispute that the applicant paid these sums.
[10] In this application, the joint venture challenges the decision of the adjudicator on the
basis that the whole of the adjudication decision is attended by jurisdictional error. It
seeks an order that the adjudication decision be set aside or declared void together, with
an order that MSS Projects repay to the joint venture the sum of $2,744,070.20 together
with interest.
[11] The Court has the power to make such an order. Whilst an adjudicator’s decision is not
reviewable under the Judicial Review Act 1991 (Qld), it is well settled that an
adjudication decision may be declared void if it is affected by jurisdictional error:
Northbuild Constructions Pty Ltd v Central Interior Linings Pty Ltd [2012] 1 Qd R
525; Melaluca View Pty Ltd v Sutton Constructions Pty Ltd & Ors [2019] QSC 226
(per Brown J) at [11]. An error in the determination of a jurisdictional fact is a
jurisdictional error: Kirk v Industrial Court (NSW) (2010) 239 CLR 531 at [72].
Whether the payment schedule provided in response to a payment claim is a payment
schedule for the purposes of the BIF Act is a jurisdictional fact: Melaluca View Pty Ltd
v Sutton Constructions Pty Ltd & Ors [2019] QSC 226 (per Brown J) at [44]; Chase
Oyster Bar Pty Ltd v Hamo Industries Pty Ltd [2010] NSWCA 190; (2010) 78 NSWLR
393.
[12] At the commencement of the hearing, both parties agreed that if I determined that
contrary to the decision reached by the adjudicator, the payment schedule given by the
joint venture to MSS Projects was a valid payment schedule for the purposes of s 69 of
the BIF Act, then the whole of the adjudication decision should be declared void and
1 Affidavit of David John Rodighiero filed 29 April 2025, paragraph 21, pp 945-946 DJR-1.
-- 4 of 22 --
5
set aside and MSS Projects should be ordered to repay the sum it has received, because,
it is agreed, that the whole of that decision was attended by jurisdictional error.
[13] Accordingly, in this application I am only concerned with the question of whether the
payment schedule issued by joint venture was in fact a valid payment schedule for the
purposes of the BIF Act.
The BIF Act scheme
[14] Part 3 of Chapter 3 of the BIF Act deals with how a payment claim is to be progressed.
Section 75(1) provides:
“75 Making payment claim
(1) A person (the claimant) who is, or who claims to be, entitled
to a progress payment may give a payment claim to the
person (the respondent) who, under the relevant
construction contract, is or may be liable to make the
payment.”
[15] Section 76 prescribes the only manner in which a respondent to a payment claim may
validly respond. It provides:
“76 Responding to payment claim
(1) If given a payment claim, a respondent must respond to the
payment claim by giving the claimant a payment schedule
within whichever of the following periods ends first—
(a) the period, if any, within which the respondent must give
the payment schedule under the relevant construction
contract;
(b) 15 business days after the payment claim is given to the
respondent.”
[16] Section 76(2) provides that a respondent is not required to give the claimant a payment
schedule if the amount claimed in the payment claim is paid in full.
[17] Section 76(3) provides that if the respondent gives the claimant a payment schedule
then the amount proposed in the payment schedule must be paid no later than the due
date for the progress payment to which the payment schedule relates.
[18] Pursuant to s 77(2), if the respondent does not give to the claimant a payment schedule
as required under s 76, then the respondent is liable to pay the amount claimed under
the payment claim on the due date for the progress payment.
-- 5 of 22 --
6
[19] The factual elements required to be present for a response to constitute a “payment
schedule” are set out in s 69 of the BIF Act. That section provides:
“69 Meaning of payment schedule
A payment schedule, responding to a payment claim, is a
written document that—
(a) identifies the payment claim to which it responds; and
(b) states the amount of the payment, if any, that the
respondent proposes to make; and
(c) if the amount proposed to be paid is less than the amount
stated in the payment claim—states why the amount
proposed to be paid is less, including the respondent’s
reasons for withholding any payment; and
(d) includes the other information prescribed by
regulation.”
[20] Pursuant to s 78(2), where a respondent who is given a payment claim does not pay the
amount owed to the claimant in full on or before the due date for that progress payment,
the claimant may apply for adjudication of the payment claim under Part 4 of the BIF
Act.
[21] That is what happened in the present case.
[22] Section 82 provides for the provision by a respondent to an adjudicator of an
adjudication response after an adjudicator has accepted their appointment pursuant to s
81.
[23] Relevantly, s 82(2) is in these terms:
“82 Adjudication response
…
(2) However, the respondent must not give an adjudication
response if the respondent failed to give the claimant a
payment schedule as required under section 76.”
[24] Section 88 prescribes those matters than an adjudicator may decide. Relevantly it
provides:
“88 Adjudicator’s decision
(2) In deciding an adjudication application, the adjudicator is to
consider the following matters only—
-- 6 of 22 --
7
(a) … ;
(d) the payment schedule, if any, to which the application
relates, together with all submissions, including relevant
documents, that have been properly made by the
respondent in support of the schedule;
(e) … .
(3) However, the adjudicator must not consider any of the
following—
(a) an adjudication response, to which the adjudication
application relates, that was not given to the
adjudicator within the time required under section 83;
(b) a reason included in an adjudication response to the
adjudication application, if the reason is prohibited
from being included in the response under section 82.
…
[25] As I have already observed, the existence of a valid payment schedule was essential to
the creation of the jurisdiction of the adjudicator to proceed under the Act. This is
because section 88(3)(b) has the effect of removing from an adjudicator’s
consideration, an adjudication response, if the respondent failed to give a payment
schedule.
[26] In Melaleuca View Pty Ltd v Sutton Constructions Pty Ltd & Ors [2019] QSC 226,
Brown J said:
“[43] Section 88(2) of the Act provides that the adjudicator is to
consider, amongst other things, the payment schedule and an
adjudication response, unless it is prohibited from being taken
into account by the operation of s.82. The determination of
whether or not there is a payment schedule as provided for under
the Act determines the scope of the adjudicator's jurisdiction,
since its existence or absence determines what the adjudicator
may have regard to when making a determination.
[44] The language of s 88, which prescribes the “only” matters the
adjudicator is to consider in making a decision and excludes
consideration of an adjudication response in the absence of a
payment schedule having been given in accordance with s 76,
supports the contention that the determination of whether or not a
document constitutes a “payment schedule” is a jurisdictional
fact. That fact is one that must be determined prior to considering
the matters provided under s 88(2) of the Act and the making of
any decision. While an adjudication can still proceed in the
absence of a payment schedule, the scope of the decision-making
process that is undertaken by the adjudicator is determined by the
-- 7 of 22 --
8
presence or absence of a payment schedule. The effect of a finding
that no payment schedule has been provided is that the respondent
is precluded from making any response in opposition to the
claimant before an adjudication is made. Unlike the 2004 Act,
there is not a further opportunity to provide a payment schedule
after notice has been given of the claimant's intention to apply for
adjudication of the payment claim. The language of s 88 and the
legislative scheme whereby a party is precluded from having its
adjudication response considered as part of the adjudication
support the conclusion that the existence of a payment schedule
is a jurisdictional fact. I find that the determination of whether the
19 February email constitutes a payment schedule is a
jurisdictional fact. The Court may therefore determine whether
the jurisdictional fact exists or not.”
[27] Further, the applicant in its written submission said:
“It is accepted that non-compliance with the requirements of s 69 would
result in the Payment Schedule being invalid, with the consequence that
none of the “reasons” for paying less than the claimed amount would be
permitted to be relied upon in any subsequent adjudication (see s 82(2)
and 88(4)).2
What constitutes a payment schedule
[28] The BIF Act is part of a national legislation scheme, although the legislation is not
entirely consistent. In Style Timber Floor Pty Ltd v Krivosudsky [2019] NSWCA 179;
(2019) 100 NSW LR 133 at [44] and [45], Leeming JA considered the statutory regime
under the NSW equivalent of the BIF Act. Relevantly Leeming JA said:
“[44] Thirdly, whether or not a compliant “payment schedule” has been
provided in response to a payment claim falls to be determined in
the context of the statutory provisions consequent upon doing so.
Whether or not a document is a payment schedule must be
something which is capable of ascertainment readily, and (at least
ordinarily) without the assistance of a lawyer. The large majority
of the cases which have arisen under this Act have not involved
dispute as to whether a response was or was not a complaint
payment schedule.
[45] Fourthly, and perhaps most importantly for present purposes, the
payment schedule serves two important functions under the Act.
The first is to inform the claimant as to the metes and bounds of
its dispute with the respondent, so that it can make an informed
choice as to whether to engage the expedited pro tem adjudication
procedures under Div 2. The second is to articulate the
respondent's case which will then be determined by the
adjudicator. It will also enable adjudicators to assess whether to
2 Applicant’s written submissions, [31].
-- 8 of 22 --
9
accept appointment as an adjudicator to a dispute. At the time an
adjudication application is made, all that the claimant and the
prospective adjudicator will know of the nature of the
respondent's side of the case is what is contained in its payment
schedule.”
[29] It is important to note the legislative intent manifest in the regime to which Leeming JA
was referring. His Honour emphasised at [26] that “the provisions [of the Act] are
characterised by strict fast-past time constraints, and a deal of informality. It is to be
born steadily in mind that (enforceable albeit not conclusive) determinations for
hundreds of thousands or millions of dollars result from the fast paced regime for non-
curial adjudication.”
[30] In Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd [2010] NSWCA 190; (2010)
78 NSWLR 393 McDougall JA observed at [208] that the mandatory regime imposed
by the NSW Act had been described as “rough and ready” and, even “draconian”. A
similar view was expressed by Morrison JA in Ausipile Pty Ltd v Bothar Boring and
Tunnelling (Australia) Pty Ltd [2021] QCA 223; 9 QdR 2020 at [100]
[31] In Minimax Fire Fighting Systems Pty Ltd v Bremore Engineering (WA) Pty Ltd & Ors
[2007] QSC 333, Chesterman J said:
“[20] The Act emphasises speed and informality. Accordingly, one
should not approach the question of whether a document satisfies
the description of a payment schedule (or payment claim for that
matter) from an unduly critical viewpoint. No particular form is
required, one is concerned only with whether the content of the
document in question satisfies the statutory description.”
[32] After discussing the response relevant to that case Chesterman J said:
“[27] If the applicant had no objection to paying those amounts the Act
required it to say so in its payment schedule. The whole purpose
of such a document is to identify what amounts are in dispute and
why. The delivery of a payment claim and a payment schedule is
meant to identify, at an early stage, the parameters of a dispute
about payment for the quick and informal adjudication process for
which the Act provides. If a builder wishes to take advantage of
the Act to dispute the claim it must comply with its provisions and
must, relevantly, take the trouble to respond to a payment claim
in the manner required by the Act. The process is not difficult.
The applicant was required to identify those parts of the claim
which it objected to paying and to say what the grounds of its
objection were.”
-- 9 of 22 --
10
[33] Chesterman J was concerned with the predecessor legislation being the Building and
Construction Industry Payments Act 2004 (BCIPA). The same legislative intent exists
in the present legislation: Melaleuca at [55].
[34] In Witron Australia Pty Ltd v Against Turnkey Innovative Engineering Pty Ltd [2023]
NSWCA 305 at [17]-[21] Kurt JA, with whom Leeming and Payne JJA approved of
the above passage from Minimax and said:
“[35] … in general a failure to provide any reason or reason directed to
a distinct and substantial component of a payment claim will
constitute a failure sufficiently to indicate why the schedule
amount is less than the amount claimed for the purposes or s.14(3)
of the Act. Such an omission would fail to identify the parameters
of the dispute, impeding the claimant being able to make an
informed decision as to how to proceed and impeded in the
adjudicator in being able to identify what reasons could be raised
in the adjudication response.”
[35] A similar observation was made by Sackar J in State Water Corporation and Civil Team
Engineering Pty Ltd [2013] NSWSC 1879 at [63].
[36] In Acciona Agua Australia Pty Ltd & Monadelphous Engineering Pty Ltd [2020] 4 QR
410, at Bond J said:
“[21] …The language of ss 82(2), 82(4) and 88(3)(b) of the Payment
Act (namely “must not” and (prohibited)) represents a clear
legislative intention to emphasise the criticality of respondents
including in their payment schedules any reasons for withholding
payment on which they might wish to rely in any subsequent
adjudication. The significance of the statutory intention is only
emphasised further when one appreciates that the Payment Act no
longer includes any provision for a claimant’s reply.”
[37] Bond J emphasised that these provisions represented an important change from the
previous legislation. His Honour went on to note at [36(g)] that the evident policy
behind the BIF Act was “to alter what had been the status quo under the BCIPA so as
to ensure that a respondent includes in its payment schedule any reasons for
withholding payment on which it might wish to rely in any subsequent adjudication,
thereby permitting a claimant to engage in those submissions in its adjudication
application and avoiding the possibility of encountering a surprising new reason in the
adjudication response.”
-- 10 of 22 --
11
[38] In this respect it is important to observe that section 18(2)(b) to the BICPA Act was in
materially similar terms to s 69(b) of the BIF Act, however, that section does not
correspond identically with the corresponding sections of the New South Wales and
Victorian Acts. The reference to “must state” in the Queensland legislation is not
replicated. Rather, the NSW and Victorian Acts require the respondent to a payment
claim to “indicate the amount of the payment (if any) that the respondent proposed to
make”. In commenting on this particular provision, Palmer J in Multiplex Constructions
Pty Ltd v Luikens [2003] NSW SC 11403 said:
[76] A payment claim and a payment schedule are, in many cases,
given and received by parties who are experienced in the building
industry and familiar with the particular building contract, the
history of construction of the project and the broad issues which
have produced the dispute as to the claimant’s payment claim. A
Payment claim and a payment schedule must be produced
quickly; much that is contained therein in an abbreviated form
which would be meaningless to the uninformed reader will be
understood readily by the parties themselves. A payment claim
and a payment schedule should not, therefore be required to be as
precise and as particularised as a pleading in the Supreme Court.
Nevertheless precision and particularity must be required to a
degree reasonably sufficient to apprise the parties of the real
issues in the dispute.
[77] A respondent to a payment claim cannot always content itself
with cryptic or vague statements in its payment schedule as to its
reasons for withholding payment on the assumption that the
claimant will know what issue is sought to be raised. Sometimes
the issue is so straightforward or has been so expansively agitated
in prior correspondence that the briefest reference in the payment
schedule will suffice to identify it clearly. More often than not,
however, parties to a building dispute see the issues only from
their own viewpoint: they may not be equally in possession of all
of the facts and they may not equally appreciate the significance
of what facts are known to them. This will be so especially where,
for instance, the contract is for the construction of a dwelling
house and the parties are the owner and a small builder. In such
cases, the parties are liable to misunderstand the issues between
them unless those issues emerge with sufficient clarity from the
payment schedule read in conjunction with the payment claim.
[78] Section 14(3) of the Act, in requiring a respondent to ‘indicate’
its reasons for withholding payment, does not require that a
payment schedule give full particulars of those reasons. The use
3 Cited with approval in Clarence Street Pty Ltd v Isis Projects Pty Ltd (2005) 64 NSWLR 448; 2005
NSWCA 391 at [31]; Style Timber Floor Pty Ltd v Krivosudsky [2019] NSWCA 171; (2019) 100
NSWLR 133 at [46].
-- 11 of 22 --
12
of the word ‘indicate rather than ‘state’, ‘specify’ or ‘set out’,
conveys an impression that some want of precision and
particularity is permissible as long as the essence of the reason’
for withholding payment is made known sufficiently to enable the
claimant to make a decision whether or not to pursue the claim
and to understand the nature of the case it will have to meet in an
adjudication.”
[39] In Melaluca, Brown J referred to this passage and noted the legislative difference
between the Queensland and NSW legislation and at [48] observed that “the present
Act uses the term “state” rather than “indicates”, suggesting a greater level of detail
then the reasons in required than under the New South Wales Legislation.”
The issues raised by the payment schedule
[40] In its submissions to the adjudicator, MSS Steel contended that the payment schedule
received by it from the applicant was invalid because it failed to comply with each of s
69(a), (b) or (c).
[41] The adjudicator concluded that the payment schedule was invalid for noncompliance
with s 69(c) only. In the present application, MSS Steel initially sought to advance a
similar argument in its written submissions, but ultimately did not advance any
argument in reliance on s 69(a) and (b) and only relied on s 69(c) to contend that the
payment schedule was invalid. This meant that the only issue is whether payment
schedule identified the payment claim to which it responded and whether it stated the
amount of the payment that the joint venture proposed to make.
[42] In particular, MSS Steel submitted that the joint venture failed in the payment schedule
to state why the amount it proposed was to be paid is less, and failed to include its
reasons for withholding any payment by reference to two particular items in the
payment claim.
[43] Despite the acceptance by MSS Steel that requirements of s69(a) and (b), even this
aspect of the payment schedule delivered by the applicant was not without its
difficulties. The first page contained a summary of the payment schedule and whilst it
correctly referred to the relevant payment claim, being number 21, the total amount of
the payment claim (excluding GST) was stated to be $2,792,912.09 excluding GST.4
4 Affidavit of David John Rodighiero filed 29 April 2025 DJR 1, p 191. The payment schedule itself is
not separately paginated.
-- 12 of 22 --
13
[44] Payment claim 21 was in fact issued by MSS Steel in the amount of $2,557,707.59
inclusive of GST.5
[45] There is also an unfortunate though minor error in the schedule in that it identifies the
date upon which the claim was received as being 2 July 2024. Although it is common
ground that the payment claim was not issued until 1 August 2024.
[46] Returning to the divergence between the two documents of the stated amount of the
payment claim, the manner in which the total claimed by MSS Steel was calculated the
payment claim is set out on page 26. It is the sum of $637,087.00 on account of original
contract works for the month, and $1,709,792.34 for the month on account of approved
variations both amounts being exclusive of GST. The total of these amounts being
$2,346,879.34. When a cash retention of $21,690.62 was applied that gave a pre-GST
figure of $2,325,188.72 being $2,557,606.59 including GST.
[47] The joint venture took a different approach to the manner in which it calculated the
amount it proposed to pay. It produced a detailed spreadsheet in schedule 27 which does
not contain the figures set out in in the payment claim and reproduced in paragraph [45]
at all. Rather, schedule 2 included figures of $326,067.35 on account of total original
contract works and $1,835,356.14 for total variations for the month, purportedly
claimed by MSS Steel for the month. There is an obvious difference between both
sums. It is, to say the least, unhelpful to its own cause that the joint venture chose to
respond in this form rather than engaging directly with the sums in the payment claim.
[48] I was not addressed on why the joint venture included the figure of $2,792,912.09
(excluding GST) as the figure for the “Total Amount of this Payment Claim” in the
Schedule 1 summary. But as is evident from the first page of the payment schedule,
the amount which the joint venture proposed to pay in response to payment claim 21,
being $207,205.08, was calculated by deducting from $2,792,912.09 the amounts of
$1,687,469.84 as “Less Monies Not Due” and the sum of $898,237.18 as “Less Monies
Set/off/Defects/Backcharges”.
[49] At the bottom of the payment schedule summary on page 1 is included the following8:
5 Affidavit of David John Rodighiero filed 29 April 2025 DJR 1, p 168.
6 Affidavit of David John Rodighiero filed 29 April 2025 DJR 1, p 169.
7 Affidavit of David John Rodighiero filed 29 April 2025 DJR 1, p 192.
8 Affidavit of David John Rodighiero filed 29 April 2025 DJR 1, p 192.
-- 13 of 22 --
14
Attachment(s) Schedule 2 - Detailed Summary
Schedule 3 - General Reasons
Annexure 1 - Monies Withheld
Annexure 2 - Monies Not Due
Annexure 3 - Monies Set Off
[50] Those amounts of $1,687,469.84 and $898,237.18 total $2,585,707.02 and appear in a
separate table at the bottom of Schedule 2 to the payment schedule.
[51] I return to this aspect of schedule 2 below, but for the sake of completeness I observe
here that in the Detailed Summary in Schedule 2 of the payment schedule, the figure of
$2,792,912.09 is included with the line entry “Total Revised Contract Sum Payable”.
It has been calculated by adding the total amounts in the “Claimed this Month” column
appearing under the three separate table headings of “1.0 Original Contract Works”
($326,067.35), “2.0 Variations” ($1,835,356.14) and “3.0 Amounts Set Off”
($631,488.60) in that document.
[52] Mr Butler KC who appeared with Ms Chen for MSS Steel, drew my attention to the
fact that those figures did not bear any resemblance to those in the payment claim. That
submission was made principally in furtherance of the submission which ultimately
was not pursued based on s 69(b) of the BIF Act. However, for the purposes of MSS
Steel’s contention that the payment schedule did not comply with s 69(c) of the BIF
Act, it is the case that there is more than a $400,000 differential (once GST was applied
equally) between the amount the joint venture recorded the payment schedule as being
the amount claimed by MSS steel, and the amount actually claimed in the payment
claim. This disparity in the amounts between the payment claim and the payment
schedule also included a difference of more than $300,000 between the amount the
Joint Venture recorded MSS Steel claimed on account of original contract works and
the amount actually stated as being claimed in the payment schedule.
[53] As I have noted, the focus of the dispute between the parties was, in essence the manner
in which two particular payment claims had been addressed (or on MSS Steel’s case,
not addressed) in the payment schedule; being item 3.16 (Roof purlins) and variation
claims V-012 and V-014.
[54] I will discuss each of these below, but before doing so it is worth bearing firmly in mind
that all that s 69(c) of the BIF Act requires is that where the recipient to a payment
-- 14 of 22 --
15
claim proposes to pay less than the sum claimed, it state the reason or reasons with
sufficient clarity to define the parameters of any dispute. There is no particular way in
which a respondent must respond; the respondent need not provide a detailed
spreadsheet in response to a payment claim, though where, as here a payment claim
comprises a number of individual items, it may be the simplest way in which particular
a reason can be given.
Item 3.16
[55] The first disputed claim is the claim for item 3.16 for contract works in the sum of
$399,400.14. This claim was identified in this manner in the payment claim9:
Item
Ref Description GST Unit of
Measure Total When Complete Completed to Date (Cumulative) Completed This Period
% Qty Rate Total Previously Approved Now
Claimed
Claimed
Qty $ Qty $ Qty $
3.16 Roof Purlins inclusive of
all fixings and
consumable – Supply
10 tonne 97.54 $4,494.96 $438,442.89 8.69 $39,042.75 97.54 $438,442.89 88.86 $399,400.14
[56] In Schedule 3 to the payment schedule10, the joint venture’s response to the claim for
item 3.16 was expressed as follows (excluding irrelevant columns):
Item Descriptio
n
UoM Qty Rate Amount Claimed
this month
(QTY)
Claimed
this
month
($)
Claimed
this
month
(%)
Claimed
Previously
(Qty)
Claimed
Previously
($)
Claimed
Previously
(%)
This Claim
Certified
v
Claimed ($)
3.16 Roof
Purlins
inclusive of
all fixings
and
consumabl
es – supply
T 97.54 4,494.96 438, 438.40 0.00 0.00 0.00% 97.54 438,442.89 100.00% 0.00
[57] An additional column to the right of this table was included and headed “Comments”.
The corresponding comment was “Goods not supplied by Supplier. CBGU refer to
teambinder reference #TSD-SC-SBGU-005012.00 and attached Direction number
#TSD-SC-SBGU-005012.00. The same amount has been deducted under SO03.”
[58] MSS Steel points to a number of obvious inconsistencies between these two tables,
being:
(a) the joint venture records the sum claimed as $0, not $399,400.14;
9 Affidavit of David John Rodighiero filed 29 April 2025 DJR 1, p 173.
10 Affidavit of David John Rodighiero filed 29 April 2025 DJR 1, p 193.
-- 15 of 22 --
16
(b) the joint venture records the quantity and amount previously claimed as 97.54
tonnes and $438,442.89 whereas MSS Steel has an amount of 8.69 tonnes and an
amount of $39,042.75.
[59] Clearly, as was submitted by Mr Butler KC, it also was not the case that MSS Steel had
already claimed the full contract works value for item 3.16.
[60] Mr Butler KC, in oral submissions referred to the comment included in the payment
schedule and posed this question: “The payment schedule proceeds on the footing that
we’ve been paid in full $438,000. But now it’s saying the goods haven’t been supplied.
Well, if the goods haven’t been supplied, why have we been paid in full? It’s a reason,
but it’s a nonsensical reason…”.11
[61] There is of course nothing in the BIF Act that requires a particular quality to be attached
to reason given. Further, this rhetorical question posed belies the fact known by both
parties that the goods had not been supplied because, as was recorded in direction TSD-
SC-SBGU-005012.00 dated 15 May 2024 attached to the payment schedule12, the joint
venture had directed MSS Steel to “omit the Canopy Stramit (Girt, Bridging and Purlin)
supply scope…”.
[62] The effect of this direction was, as Mr Ambrose KC submitted, that this part of the
contract works had been removed from the scope of works or “descoped”. Mr Ambrose
KC submitted that the approach of the joint venture as revealed in the payment schedule
was to not include it in its contract works calculation because it no longer was a part of
the contract works by the time the payment claim was made.
[63] Further, the comment by the joint venture that “[t]he same amount has been deducted
under SO03” directed MSS Steel to “SO03” which the joint venture included in
Schedule 3 to the payment schedule13. That particular page of Schedule 3 identified 18
separate items, each with the prefix or identifier of “SO”. This was referred to by Mr
Ambrose KC, without objection, as the “Set Off Register” and identifies by item and
value, the individual amounts which the joint venture treats as being entitled to set off
against monies payable. The total amount of these set off items is $898,237.18, being
11 T, 1-63 ll 3-6.
12 Affidavit of David John Rodighiero filed 29 April 2025 DJR 1, p 223.
13 Affidavit of David John Rodighiero filed 29 April 2025 DJR 1, p 195.
-- 16 of 22 --
17
one of the amounts referred to in the payment schedule summary identified above at
paragraph [48].
[64] The line entry for SO03 (reproduced to take account of portrait rather than landscape
display with the intention that it be read as one line, and with irrelevant columns
excluded) said this:
Item Description Claimed this month Claimed previously
SO03 Not supplied – Roof Purlins inclusive of all fixings and
consumables – Supply (item 3.16) Claimed this
month (QTY) Claimed this
month ($) Claimed this
month
(%)
Claimed
previously
(QTY)
Claimed
previously ($) Claimed
previously (%)
-0.65 283,696.71 -$100.00% 1.00 -438,442.89 100.00%
Claimed to Date Certified this month Certified Previously
Claimed to Date
(QTY)
Certified this
month (QTY)
Certified this
month
($)
Certified this
month
(%)
Certified
Previously (QTY)
Certified
Previously ($)
Certified
Previously (%)
Claimed to Date
($)
Claimed to Date
(%)
0.35 0.00 0.00 0.00% 0.00 -438,442.89 0.00% -154,746.18 0.00%
This Claim Certified
v
Claimed ($)
To date certified
v
Claimed ($)
Comments
-283,696.71 -283.696.71 CBGU refer to the attached document TSD-SC-SBGU-005012.00 and
Teambinder reference
[65] The joint venture also included separately14 in the payment schedule, a summary table
of “Monies Set-Off” which included for each item, the item number, the ‘Specific
Reason’ and the amount. In relation to SO03, the ‘Specific Reason’ was stated as “Not
supplied – Roof Purlins inclusive of all fixings and consumables – Supply (item 3.16)”,
and the stated amount was -$283,696.71.
[66] As the table in the Set Off Register stated, that amount of $283,696.71 was calculated
by subtracting from $438,442.89, being the total amount which, but for the descoping,
would be payable on account of item 3.16, the sum of $154,746.18. The source of that
figure was MSS Steel. It was included in page 615 of the payment claim as an
“Approved Variation”. The relevant line in the table (excluding irrelevant columns)
was as follows:
References Description Total When Complete Completed to Date (Cumulative) Completed this Period
Previously Approved Now Claimed Claimed
S.C’s Contractor Qty Rate Total Qty $ Qty $ Qty $
VD-001 VD-001 Deducts Purlin 87.11 -$1,1776.36 -$154,746.18 0.00% 87.11 -$154,746.18 87.11 -$154,746.18
14 Affidavit of David John Rodighiero filed 29 April 2025 DJR 1, p 205.
15 Affidavit of David John Rodighiero filed 29 April 2025 DJR 1, p 176-178.
Certified this month Certified Previously Certified to date
Certified this
month (QTY)
Certified this
month
($)
Certified this
month
(%)
Certified Previously
(QTY)
Certified
Previously ($)
Certified
Previously (%)
Certified to Date
(QTY)
Certified to Date
($)
Certified to
Date (%)
0.00 0.00 0.00% 0.00 -438,442.89 0.00% 1.00 -438,442.89 0.00%
-- 17 of 22 --
18
Supply Cost to
Complete
from Item 3.16
[67] The rate of “-$1,1776.36” was also expressed as a per tonne rate, but the actual source
for that rate was not explained in the evidence beyond the description which
distinguishes this rate as a “supply cost” rate rather than the rate applicable to roof
purlins “inclusive of all fixings and consumables-supply”.
[68] Some further guidance in the payment claim is given on page 916 which contains a table
as part of a series of attachments described as “Relevant to Variation”. For “VD-001”
the explanation given is “Item 3.16 above is claimed in full. 12.98 tonnes of purlins and
bridging were delivered to CBGU’s Hamilton on 09 May 2024. Variation VD-001
deducts the supply only cost of $154,746.18 for the purlins that will not be supplied (at
CBGU D&C JV's direction) by the supplier as part of item 3.16.”
[69] As noted above, the direction TSD-SC-SBGU-005012.00 by which item 3.16 was
“descoped” bears the date 15 May 2024. This entry by MSS Steel suggests that it had
supplied some purlins and bridging on 09 May 2024 prior to the descoping of this item
and that the value of what was yet to supplied was $154,746.18. It also states that MSS
Steel otherwise claims for item 3.16 “in full”.
[70] By contrast, the joint venture in the Set Off Register applied this deducted sum to the
full contract price value of the descoped item 3.16 to calculate the set off amount of
- $283,696.71, and, reduce the amount it proposed to pay for that item to $0 as recorded
in Schedule 3 of the payment schedule set out in paragraph [56] of these reasons.
[71] Whether or not the joint venture is, as a matter of fact entitled, to avoid any liability to
pay for item 3.16 is not to the point: Façade Treatment Engineering Pty Ltd (in liq) v
Brookfield Multiplex constructions Pty Ltd [2016] VSCA 247; (2016) 337 ALR 452 at
[258]. What is necessary that the payment schedule state the reason or reasons why the
respondent objects to making the payment claimed. Here, both parties knew that item
3.16 at had been the subject of direction TSD-SC-SBGU-005012.00 such that MSS
Steel was no longer required to undertake that aspect of the contract. The joint venture
expressly stated that it proposed to pay $0 in relation to this claim, and in so doing,
referred to this direction and gave as the stated reason “Not supplied – Roof Purlins
16 Affidavit of David John Rodighiero filed 29 April 2025 DJR 1, p 181.
-- 18 of 22 --
19
inclusive of all fixings and consumables – Supply (item 3.16)”. Despite the fact that
the joint venture did not directly respond to the claimed sum of $399,400.14 for item
3.16, in approaching this item in the manner that it did, the joint venture stated that it
objected to pay the claimed sum and proposed to pay $0. By doing so, the joint venture
sufficiently apprised MSS Steel of the basis of its objection to making such payment
and adequately defined the parameters of the dispute with respect to his aspect of the
payment claim. Accordingly, I am satisfied that its response to this aspect of the
payment claim met the requirements of s 69(c) of the BIF Act.
Variations V-012 and V-014
[72] Variation V-012 claimed the sum of $225,360 for “Trial Assembly & 3D Scan -Full
Trusses”. V-014 claimed the sum of $125,351.22 for “Architectural Cover Plates &
Anti Climb Fins”. Each of those claims were included in the “Approved Variation”
table and appeared on page 717 of the payment claim. The relevant entry in the table
(excluding irrelevant columns) was:
References Description Total When Complete Completed to Date (Cumulative) Completed this Period
Previously Approved Now Claimed Claimed
S.C’s Contractor Qty Rate Total Qty $ Qty $ Qty $
VD-012 VD-012 Trial Assembly &
3D Scan – Full
Trusses
1.00 $227,520.00 $227,520.00 0.01 $2,160.00 1.00 $227,520.00 0.99 $225,360.00
V-014 V-014 Architectural Cover
Plates & Anti Climb
fins
1.00 $128,680.00 $128,680.00 0.03 $3,28.78 1.00 $128,680.00 0.97 $125,351.22
[73] The joint venture responded to these variation claims in the table in the summary in
Schedule 2 of the payment schedule. The joint venture’s response (again excluding
irrelevant columns), was:
2.0 Variations
Item Description Qty Unit Rate
(GST
Excl)
Value
(GST
Excl)
Claimed this
Month
Claimed
Previously
Claimed to
Date
Certified
Previously
Certified
to date
This Month
Approved v
Claimed
To Date
Approved v
Claimed
V-012.01 Horizontal
assembly and
disassembly of 12
no trusses prior to
Hot Dip
Galvanising
12.00 17,160 205,920 149,040.00 56,880.00 205,920.00 56,880.00 17,160.00 -188,760.00 -188,760.00
V-0.12.02 3D Scan of fully
assembled truss 12.00 1,800 21,600 19,440.00 2,160.00 21,600.00 2,160.00 1,800.00 -19,800.00 -19,800.00
V-014.01 Fabricate and paint
32 no. semi circular
cover plates to the
base of CHS610*32
columns
32.00 1,380.00 44,160.00 42,769.39 1,390.61 44,160.00 1,390.61 1,390.61 -42,769.39 -42,769.39
V-014.02 Fabricate and paint
36 no. semi circular
36.00 1,070.00 38,520.00 37,738.00 782.00 38,520.00 782.22 782.22 -37,738.00 -39,737.78
V-014.03 Fabricate and paint
40 no. ‘U’ shaped
cover plates to the
SHS 400*400*12.5
40.00 970.00 38,800.00 38,104.69 695.31 38,800.00 695.31 695.31 -38,104.69 -38,104.69
17 Affidavit of David John Rodighiero filed 29 April 2025 DJR 1, p 178.
-- 19 of 22 --
20
lower level wind
beams
V-014.04 Fabricate and paint
2 no. x 100 mm
anti-climb fins
welded to the
CHS355* 9.5 lower
diagonal bracing
2.00 3,600 7,200.00 6,739.36 460.64 7,200.00 460.64 460.64 -6,739.36 -6,739.36
[74] Whilst this response is obviously more detailed than the relevant claims to which it
responds, the first observation that ought be made is that the figures appearing in the
“Claimed this Month” and “Claimed Previously” columns corresponding with claims
comprising V-012 and V-014 add up to the amounts in the “Total when Complete” and
the “Now Paid” columns in the payment claim. It was therefore clear to MSS Steel that
the joint venture was responding to the same variations.
[75] It was also clear that what the joint venture proposed to pay in respect of the claims for
the relevant variations was what was set out in the “Certified to Date” column.
[76] Further, as explained about in relation to the claim for item 3.16, the figures in the “This
Month Approved v Claimed” column form part of the amount of the $1,637,469.84
being “Monies Not Due as per Annexure 2” which, together with the “Monies Set off”
total $2,585,707.02 being the “TOTAL MONIES WITHHELD/NOT DUE” amount at
the bottom of Schedule 2.
[77] When one turns to Annexure 2 “Monies Not Due” in the payment schedule18, the joint
venture had set out the following:
Item Specific Reasons Value Not Due
Excl. GST
V-012.01 1. According to CBGU records just one truss was scanned, not the claimed 12
2. Please provide the third-party invoice to verify actual costs incurred by Supplier.
-$188,760.00
V-012.02 1. According to the CBGU records just one truss was scanned, not the claimed 122.
2. Please provide the third-party invoice to verify actual costs incurred by Supplier.
-$19,800.00
V-014.01 Please refer to the attached “VO14 Assessment” for Valuation of certified amount. -$42,769.39
V-014.02 Please refer to the attached “VO14 Assessment” for Valuation of certified amount. -$37,738.00
V-014.03 Please refer to the attached “VO14 Assessment” for Valuation of certified amount. -38,104.69
V-014.04 Please refer to the attached “VO14 Assessment” for Valuation of certified amount. -$6,739.36
[78] In this table:
(a) with respect to V-012, the joint venture recorded its objection to the payment
claims on the basis of the numbers of trusses MSS steel claimed were scanned
and had calculated the total value of those trusses for which it is not liable as
$208,560; and
18 Affidavit of David John Rodighiero filed 29 April 2025 DJR 1, p 204.
-- 20 of 22 --
21
(b) with respect to V-014, MSS Steel is directed to the V014 attachment.
[79] As to V-012, the joint venture also attached19 a more detailed explanation of its position
with respect to this claim as follows (excluding unnecessary columns):
Item Description
SUBMISSION CBGU JV Assessment Comments
Qty Rate Total ($) Qty Rate Total Variance
1
each full assembled truss is circa
50.350 metres long by 4.5
metres Included Included
2 There are 12 no. main canopy
trusses each comprising 8 no.
assembly’s (96 no. total) Included Included
3 Horizontal assembly and
disassembly of 12 no trusses
prior to Hot Dip Galvanising 12.00 17,160,00 $205,920.00 1.00 17,160.00 $17,160.00 -$188.760.00
1. According to CBGU records just one truss
was scanned, not the claimed 12
2. Please provide the third-party invoice to
verify actual costs incurred by Supplier
4 3D Scan of fully assembled truss 12.00 1,800,00 $21,600.00 1.00 1,800.00 $1,800.00 -19.800.00
1. According to CBGU records just one truss
was scanned, not the claimed 122.
2. Please provide the third-party invoice to
verify actual costs incurred by Supplier.
3. The scanning data provided by the Supplier
was not usable or in the requested format;
also the third-party QA team discovered the
3d scan operator’s work is not trained or
qualified to operate the scanning equipment;
furthermore, CBGU D&C JV cannot use the
data sheet provided, a third party certifier was
requested to assist and supervise MSS’s
scanning; therefore the cost claimed is not an
accurate representation of the value of the
work performed.
Total 24.0000 $227,520.00 2.00 $18,960.00 -208,560.00
[80] It can be seen that the total amounts the joint venture assessed as payable by it, for the
reasons it gave, correspond with the amounts in the “Certified this Month” in Schedule
2 to the payment schedule.
[81] The attachment in relation to V-014 was similarly expressed with a similar level of
detail.20 Relevantly, in that attachment the joint venture said:
Item Description
SUBMISSION CBGU JV Assessment
Comments
Qty Rate Total ($) Qty Rate Total Variance
1
Fabricate and paint 32 no.
semi-circular cover plates
to the base of CHS610*32
columns
32.00 1,380.00 $44,160.00 0.320000 4.345.67 $1,390.60 -$42,769.39
Pursuant to CI34.1 (c) (i) and (ii),
assessed rate is selected according to
table AH-1, item 5.2; tonnage rate is
from ProjectWise model.
2
Fabricate and paint 36 no.
semi-circular cover plates
to the CHS355*9.5
bracing
36.00 1,070.00 $38,520.00 0.180000 4,4345.67 $782.99 -$37,737.78
Pursuant to CI34.1 (c) (i) and (ii),
assessed rate is selected according to
table AH-1, item 5.2; tonnage rate is
from ProjectWise model.
3
Fabricate and paint 40 no.
‘U’ shaped cover plates to
the SHS 400*400*12.5
lower level wind beams
40.00 970.00 $38,800.00 0.160000 4,345.67 $695.31 -$38,104.69
Pursuant to CI34.1 (c) (i) and (ii),
assessed rate is selected according to
table AH-1, item 5.2; tonnage rate is
from ProjectWise model.
4
Fabricate and paint 2 no. x
100 mm anti-climb fins
welded to the
CHS355*9.5 lower
diagonal bracing
2.00 1,800.00 $ 3,600.00 0.106000 4,345.67 $460.64 -$3,139.36
Pursuant to CI34.1 (c) (i) and (ii),
assessed rate is selected according to
table AH-1, item 5.2; tonnage rate is
from ProjectWise model.
Total 110.0000 $125,080.00 0.7660 $ 3,328.78 -121,751.22
19 Affidavit of David John Rodighiero filed 29 April 2025 DJR 1, p 221.
20 Affidavit of David John Rodighiero filed 29 April 2025 DJR 1, p 222.
-- 21 of 22 --
22
[82] Again, the total amounts the joint venture assessed as payable by it in relation to the V-
014 claims, for the reasons it gave, corresponded with the amounts in the “Certified
this Month” in Schedule 2 to the payment schedule.
[83] The joint venture therefore adequately explained how it had calculated its liability for
the V-012 and V-014 claims, as well as its reasons for undertaking the calculation in
the manner that it did. MSS Steel was also sufficiently able to appreciate the parameters
of the dispute with respect to these claims.
[84] I am therefore satisfied that the joint venture’s response to this aspect of the payment
claim met the requirements of s 69(c) of the BIF Act
Conclusion
[85] For these reasons, I am satisfied that the response given by the joint venture to the
payment claim in the payment schedule met the requirements of s 69(c) of the BIF Act.
[86] I will make a declaration to that effect.
[87] Given the agreed position of the parties as to how the balance of the application should
be dealt with should I find that the payment schedule given by the joint venture in
response to the payment claim complied with s 69(c) of the BIF Act, I will hear the
parties as to the balance of the orders I should make and as to costs.
-- 22 of 22 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2025/239