Bridgeman Agencies Pty Ltd v S.E. QLD Plumbing & Drainage Pty Ltd [2025] QSC 167
SUPREME COURT OF QUEENSLAND
CITATION: Bridgeman Agencies Pty Ltd v S.E. QLD Plumbing &
Drainage Pty Ltd [2025] QSC 167
PARTIES: BRIDGEMAN AGENCIES PTY LTD
ACN 077 601 962
(applicant)
v
S.E. QLD PLUMBING & DRAINAGE PTY LTD
ACN 124 742 865
(first respondent)
SEAN THOMAS MILNEX
(second respondent)
FILE NO/S: BS No 15679 of 2024
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 18 July 2025
DELIVERED AT: Brisbane
HEARING DATE: 14 February 2025; 27 June 2025
JUDGE: Kelly J
ORDERS: 1. The originating application filed 18 November 2024
is dismissed.
2. I will hear the parties as to costs.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION –
STATUTORY REGULATION OF ENTITLEMENT TO
AND RECOVERY OF PROGRESS PAYMENTS –
PAYMENT CLAIMS – where the applicant and the first
respondent entered two subcontracts by which the first
respondent undertook to perform certain hydraulic services
works on a project – where the first respondent issued to the
applicant a payment claim which claimed a progress payment
– where the first respondent subsequently lodged an
adjudication application in respect of the payment claim –
where the second respondent issued an adjudication decision
pursuant to which the second respondent determined that the
amount was payable by the applicant to the first respondent
pursuant to the payment claim – where the applicant has
applied to the Court for an order that the adjudication decision
be set aside or declared void for want of jurisdiction – where
the applicant contents that the payment claim was not a
-- 1 of 21 --
2
“payment claim” within the meaning of the Building Industry
Fairness (Security and Payment) Act 2017 (Qld) because,
contrary to the requirements of s 68(1)(a), it did not identify
the construction work or related goods and services to which
the progress payment related – where in deciding whether
work has been sufficiently identified, the background of each
of the parties derived from their past dealings and exchanges
of documentation is properly to be taken into account –
whether the payment claim met the statutory definition of a
“payment claim” – whether the adjudication decision should
be set aside or declared void for want of jurisdiction
Building Industry Fairness (Security and Payment) Act 2017
(Qld), s 3(1), s 3(2), s 68(1)(a)
Baguley Build Pty Ltd v Olcon Concrete & Construction Pty
Ltd [2025] QSC 126
Brodyn Pty Ltd t/as Time Cost and Quality v Davenport
(2004) 61 NSWLR 421, considered
Coordinated Construction Company Pty Ltd v Climatech
(Canberra) Pty Ltd (2005) 21 BCL 364, cited
E Home Construction Pty Ltd v GCB Constructions Pty Ltd
[2020] QSC 291, cited
KDV Sport Pty Ltd v Muggeridge Constructions Pty Ltd
[2019] QSC 178, cited
MWB Everton Park Pty Ltd v Devcon Building Co Pty Ltd
[2024] QCA 94, followed
Nepean Engineering Pty Ltd v Total Process Services Pty Ltd
(in liq) (2005) 64 NSWLR 462, cited
T & M Buckley Pty Ltd v 57 Moss Rd Pty Ltd [2010] QCA
381, considered
COUNSEL: B A Reading for the applicant
M C Long for the first respondent
No appearance for the second respondent
SOLICITORS: Mahoneys for the applicant
Holding Redlich for the first respondent
No appearance for the second respondent
An adjudication decision is alleged to be void for want of jurisdiction
[1] The applicant, as contractor, entered a head contract in respect of a project. The
applicant and the first respondent (“the subcontractor”) then entered two
subcontracts by which the subcontractor undertook to perform certain hydraulic
services works on the project. The materially relevant subcontract is dated
26 March 2024 and is headed “Trade: 3002 Hydraulic Services Early Works” (“the
subcontract”). The original subcontract sum for the subcontract was $101, 449.30
(excluding GST).
-- 2 of 21 --
3
[2] On 22 September 2024, the subcontractor issued to the applicant a payment claim
(“the fourth payment claim”) which claimed a progress payment of $180,310.94
(including GST). On 8 October 2024, the applicant issued a payment schedule in
respect of the fourth payment claim. On 17 October 2024, the subcontractor lodged
an adjudication application in respect of the fourth payment claim. On
14 November 2024, the second respondent issued an adjudication decision (“the
decision”) pursuant to which the adjudicator determined that the amount of
$103,509.44 was payable by the contractor to the subcontractor pursuant to the
fourth payment claim.
[3] Section 68(1)(a) of the Building Industry Fairness (Security and Payment) Act
2017 (Qld) (“the Act”) provides:
“68 Meaning of payment claim
(1) A payment claim, for a progress payment, is a written document
that—
(a) identifies the construction work or related goods and services
to which the progress payment relates.”
[4] The ultimate issue raised in this proceeding is whether the fourth payment claim
met the statutory definition of a “payment claim”. The applicant contends that the
fourth payment claim was not a “payment claim” within the meaning of the Act
because, contrary to the requirements of s 68(1)(a), it did not identify the
construction work or related goods and services to which the progress payment
related. The payment claim was said to contain no description of work at all or,
alternatively, to the extent that it relied upon percentages to describe the extent of
completed work, that was said to be not a sufficient identification of the work to
which the progress payment related.
[5] The applicant seeks an order that the decision be set aside or declared void for
want of jurisdiction. A further order is sought that the subcontractor be
permanently restrained from enforcing or seeking to enforce the decision.
Section 68(1)(a) “identifies the construction work”
[6] The object of the Act is “… to help people working in the building and construction
industry in being paid for the work they do”.1 That purpose is to be achieved by
“granting an entitlement to progress payments, whether or not the relevant contract
makes provision for progress payments” and “establishing a procedure for …
making payment claims … and … responding to payment claims”.2 The builder’s
entitlement to a progress payment under the Act depends upon the builder having
given a “payment claim” as claim as defined by s 68 of the Act, relevantly, a
document which identified the construction work or related goods and services to
which the progress payment related.
[7] In MWB Everton Park Pty Ltd v Devcon Building Co Pty Ltd,3 Dalton JA4
relevantly said:
1 Section 3(1).
2 Sections 3(2)(b) and (c).
3 [2024] QCA 94 at [24] and [26].
4 With whom Brown and Kelly JJ agreed.
-- 3 of 21 --
4
“In determining whether or not a document identifies the work, goods
and services to which the claim relates, the Courts take a practical, and
not overly technical, attitude. In T & M Buckley Pty Ltd v 57 Moss
Road Pty Ltd Philippides J, writing in this Court, said that the issue for
determination was, ‘... not whether the payment claim explained in
every respect the means by which a particular claim item had been
calculated, but whether the relevant construction work or related
goods and services was sufficiently identified ... That is, whether
the payment claim reasonably identified the construction work to
which it related such that the basis of the claim was reasonably
comprehensible to the applicant.’ It has been accepted by the Courts
that, in deciding whether or not work has been sufficiently identified,
the background of each of the parties ‘derived from their past dealings
and exchanges of documentation’ is to be taken into account.
… Unless something which meets the statutory definition of a
payment claim is delivered to the principal, the principal has no
statutory obligation to make a payment or respond with a payment
schedule. … Further, whether or not the document claimed to be a
payment claim meets the statutory definition must be a matter of
objective construction; the Court cannot be concerned with a
subjective understanding of the principal.”
[8] As this passage makes plain, it is a settled principle that, in deciding whether work
has been sufficiently identified, the background of each of the parties “derived
from their past dealings and exchanges of documentation” is properly to be taken
into account.5 The application of that principle has been explained in a number of
appellate level decisions.
[9] In Coordinated Construction Company Pty Ltd v Climatech (Canberra) Pty Ltd,6
the New South Wales Court of Appeal considered a statutory provision which
provided that a payment claim “must identify the construction work (or related
goods and services) to which the progress payment relates”. Hodgson JA
relevantly observed of that statutory provision:
“[25] … s.13(2)(a) requires that a payment claim “identify” the
construction work or related goods or services to which the payment
relates. … In my opinion, the relevant construction work or related
goods and services must be identified sufficiently to enable the
respondent to understand the basis of the claim …”.
[10] In separate reasons, Basten JA relevantly said:7
“In John Holland v Cardno MBK, Einstein J expressed the view that,
in order to satisfy the statutory scheme, a payment claim did not need
to be ‘comprehensible by the respondent in terms of its supporting
materials’ … However, as Hodgson JA notes at [25] above, the claim
5 T & M Buckley Pty Ltd v 57 Moss Rd Pty Ltd [2010] QCA 381 at [14]; Neumann Contractors Pty Ltd
v Peet Beachton Syndicate Ltd [2011] 1 Qd R 17 at [25]; Nepean Engineering Pty Ltd v Total Process
Services Pty Ltd (in liq) (2005) 64 NSWLR 462 at [48].
6 (2005) 21 BCL 364.
7 Ibid at [42].
-- 4 of 21 --
5
must “identify” the work, goods or services to which the payment
sought relates. The term ‘identify’ should be given a purposive
construction: what must be done must be sufficient to draw the
attention of the principal to the fact that an entitlement to a payment
is asserted, arising under the contract to which both the contractor and
the principal are parties. In that sense, the claim, to be valid, must be
reasonably comprehensible to the other party. If the entitlement does
not arise absent the supply of supporting documentation, then the
claim must be accompanied by that documentation, unless it has
already been provided.”
[11] In Nepean Engineering Pty Ltd v Total Process Services Pty Ltd (in liq),8 Hodgson
JA,9 after having referred to his earlier statement in Climatech Pty Ltd and having
noted Basten JA’s statements in the same case as set out above, described the
degree of identification required in terms of whether “in all circumstances, the
material in the payment claim was … sufficient to convey to [the recipients] just
what was the work for which payment was claimed”.10
[12] In separate reasons in Nepean Engineering Pty Ltd, Santow JA said:11
“… consistent with the object of the Act and the means for its
achievement, I consider that there must be sufficient specificity in the
payment claim for its recipient actually to be able to identify a
‘payment claim’ for the purpose of determining whether to pay, or to
respond by way of a payment schedule indicating the extent of
payment, if any. [The recipient] needs to be in a position to determine
in a meaningful fashion whether to make payment, or else dispute it
with reasons so as in that case to permit adjudication of the dispute,
utilising the summary procedures under the Act. Those requirements
underlying s 13 (2)(a) are satisfied in my view by a relatively
undemanding test, though still one with some content; one which
recognises the mandatory character of s 13(2)(a) signalled by the word
‘must’. It is that ‘the relevant construction work (or related goods and
services) must be identified sufficiently to enable the respondent to
understand the basis of the claim’ This moreover is an objective not
subjective test, taking into account the background knowledge each of
the parties derive from their past dealings and exchange of
documentation.”
[13] In T & M Buckley Pty Ltd,12 Philippides J stated that the approach taken in
Climatech Pty Ltd and Nepean Engineering Pty Ltd “indicates what is required in
determining whether there has been sufficient identification for the purpose of s
17(2)(a).” Philippides J went on to describe that requirement as being “whether
the relevant construction work or related goods and services was sufficiently
identified as explained above. That is, whether the payment claim reasonably
identified the construction work to which it related such that the basis of the claim
8 (2005) 64 NSWLR 462.
9 With whom Ipp JA agreed.
10 Ibid at [28].
11 Ibid at [48].
12 [2010] QCA 381 at [37].
-- 5 of 21 --
6
was reasonably comprehensible to the applicant”.13 By reference to the facts of
T & M Buckley Pty Ltd, Philippides J reasoned as follows:
“[39] Approaching the question in that manner, the respondent has
demonstrated that the learned judge erred in finding that
there was a real prospect of the applicant defending the
payment claim on the basis that the payment claim did not
sufficiently identify that part that related to suspension of
time costs. For the same reasons, the learned judge erred in
the approach he took in finding that the claim for retentions
($1,156) was invalid. Those items were identified in a
manner that sufficiently allowed the applicant to understand
the basis for the claims.
[40] The same applies in relation to the claim for sediment
control costs. The payment claim sought an amount of
$2,772 for ‘Sediment Control as attached Claim No 30’.
That description, in conjunction with the attachment, was
sufficient to identify the relevant construction work to which
that part of the claim related for the purposes of s 17(2)(a)
BCIPA. It is to be noted that the attachment particularised
the claim for sediment control costs in considerable detail,
providing a description of the items of cost, unit, quantity,
rate amount, extent of completion and claim value.”
[14] This objective approach to construction endeavours to ascertain how the parties to
the contract “would have understood” the payment claim.14 Hence, it has been
observed that “documents which appear to be extremely summary, or to the
uninformed but not unintelligent observer brief to the point of incomprehensibility,
may be sufficiently meaningful to the parties to enable them to know, respectively,
the bases on which a particular payment claim is advanced”.15
[15] The applicant relied upon Baxbex Pty Ltd v Bickle16 as authority for the proposition
that “documents relied upon to sustain a payment claim must be included in that
payment claim”.17 In Baxbex, a document, described as “the schedule”, purported
to be a payment claim pursuant to s 17 of the Building and Construction Industry
Payments Act 2004 (Qld) (“BCIPA”). The schedule had referred to, but not
attached, various invoices. The information provided in the schedule for each
invoice was limited to the invoice number, the invoice date and the balance owing.
Daubney J found that the schedule was “on its face, not compliant” and noted that
the schedule “did not identify the construction work” and “merely invoked
invoices by invoice number and amount”.18 His Honour then said:19
“In this case, there has not been strict compliance with the provisions
of the BCIPA. It cannot be said, as was argued by the applicant, that
13 Ibid at [38].
14 Leighton v Arogen [2012] NSWSC 1323 at [69].
15 Ibid; See also ISIS Projects Pty Ltd v Clarence Street Pty Ltd [2004] NSWSC 714 at [36] and [37].
16 [2009] QSC 194.
17 T1-12.45.
18 [2009] QSC 194 at [15].
19 Ibid at [18] to [20].
-- 6 of 21 --
7
prior receipt of the invoices by the respondent amounted to sufficient
identification for the purposes of s 17. The letter which was relied on
as constituting the ‘payment claim’ did not comply with s 17 of the
BCIPA as neither the construction work nor related goods or services
were identified within the payment claim itself. As was postulated by
McDougall J in Isis Projects v Clarence Street, quoting Palmer J in
Multiplex Constructions Pty Ltd v Luikens & Anor in relation to a
payment claim, ‘precision and particularity must be required to a
degree reasonably sufficient to apprise the parties of the real issues in
the dispute.’
It would have been possible for the applicant to have sent copies of the
invoices as part of, or annexed to, the schedule but this was not done.
The present case is therefore quite different from the circumstances
considered in Austruct Qld Pty Ltd v Independent Pub Group Pty Ltd
where the invoices and supporting documentation were attached to the
payment claim. While making no comment on whether or not on its
proper construction it is necessary to separately identify construction
work and related goods and services, Dutney J in that case found that
the payment claim, including the attached invoices and supporting
documentation, identified sufficiently for the purposes of s 17 of the
BCIPA, the nature of each item claimed.
I conclude, therefore, that the letter dated 27 April 2009 was not a
‘payment claim’ under s 17 (2).”
[16] Baxbex was considered by the Court of Appeal in T & M Buckley.20 Notably,
Philippides J (with whom Fraser and White JJA agreed) referred with apparent
disapproval to the statement to the effect that “in relation to a payment claim,
‘precision and particularity must be required to a degree reasonably sufficient to
apprise the parties of the real issues in the dispute’.” Philippides J cited appellate
court authority which emphasised that a payment claim had a different function to
a payment schedule. Whilst a payment schedule was required to identify the
payment claim to which it relates, indicate the amount of the payment (if any) that
was proposed to be made and why the payment in full was withheld, a payment
claim was no more than a claim and its function was not to identify the scope of
any dispute. Philippides J considered that the statement in relation to a payment
claim that “precision and particularity must be required to a degree reasonably
sufficient to apprise the parties of the real issues in the dispute” set the bar too high
in respect of what was required of a payment claim.
[17] With reference to the first instance decision in T & M Buckley, Philippides J found
that the primary judge in that case had erred by making a finding, in reliance on
Baxbex, to the effect that a claim lacked sufficient identification “because the
relevant attachment provided with the payment claim referred to various supplier
invoices that were not also attached to the payment claim”. In respect of that
finding, Philippides J relevantly said:21
“… in this regard the judge misconstrued the remarks of Daubney J in
Baxbex Pty Ltd and thus erred in considering what was required in
20 [2010] QCA 381 at [16].
21 Ibid at [41].
-- 7 of 21 --
8
terms of s 17(2)(a). Daubney J’s conclusion in Baxbex Pty Ltd, that
the payment claim there under consideration did not comply with s
17(2)(a), was made in circumstances where the payment claim
referred to an attached schedule which provided no information as to
the construction work to which the claim related, other than merely
invoking invoices by invoice number and date, but without attaching
or providing those invoices. Baxbex Pty Ltd does not stand for the
proposition implicit in the judge’s reasons that a failure to provide
documents referred to in a payment claim or attachment thereto per se
results in there being a deficiency in identification for the purposes of
s 17(2)(a). In the present case, the fact that the attachment referred to
certain supplier invoices without also attaching them did not detract
from the identification that was provided being sufficient.”
[18] Where a payment claim describes the percentage of work carried out, that
description may be insufficient to identify the construction work in respect of the
claim. In KDV Sport Pty Ltd v Muggeridge Constructions Pty Ltd,22 Brown J
found, on the facts of that case, that a payment claim which provided the
percentage of work carried out lacked clarity and did not identify the construction
work in respect of that claim. Her Honour relevantly observed:
“It may be possible to identify the work done where the claim is
working off a zero base, but … in the present case it is unclear what
the percentages actually mean, given the fact that the figures for a
number of items cannot be reconciled.”
[19] In MWB Everton Park, Dalton JA, after referring with approval to this part of the
reasoning in KDV, observed that the contract in MWB Everton Park had been for
the construction of 56 townhouses and, in those circumstances, “it was all but
meaningless to say that 5% of concreting or 12% of plumbing had been
completed”.23 By reference to those facts, her Honour considered that more
description was needed if the document was to sufficiently identify the
construction work or related goods and services for the purposes of s 68(1)(a) of
the Act. In a footnote to her reasoning, Dalton JA relevantly noted:
“In different factual circumstances, a trade summary or trade
breakdown might be sufficient. Hypothetically, if the contract was to
build a single domestic dwelling and the only concreting was to the
driveway, a description that 50% of the concreting had been achieved
would allow the party receiving the claim to understand what work the
builder said had been done.”
The fourth payment claim, and the circumstances in which it was made
[20] On 22 June 2024, the respondent emailed the first payment claim to the applicant.
The first payment claim included a worksheet headed “Worksheet for Early Works
Contract Claim 1”. Prior to sending the first payment claim, the respondent’s
Mr Mundt had received a phone call from the applicant’s project manager,
Mr Mills. During that phone call Mr Mills requested that the respondent email
“draft” copies of its proposed payment claims to be issued in respect of the 22 June
22 [2019] QSC 178 at [37].
23 [2024] QCA 94 at [25].
-- 8 of 21 --
9
2024 reference dates under each of the two subcontracts. Mr Mills said words to
the effect that if those “draft claims” were correct and acceptable then they would
be approved and paid. On 21 June 2024, Mr Mundt emailed drafts of the then
proposed payment claims as requested. Later that day, Mr Mundt received a phone
call from Mr Mills in respect of the draft payment claims during which Mr Mills
advised Mr Mundt that the drafts were “okay” and to lodge the payment claims.
The draft of the proposed first payment claim under the subcontract as emailed on
21 June 2024 contained a worksheet which was materially identical to the
worksheet which formed part of the first payment claim as made on 22 June 2024.
On or about 28 June 2024, the applicant issued its payment schedule in response
to the first payment claim. The full amount of the first payment claim was paid.
[21] On 22 July 2024, the respondent sent by email the second payment claim to the
applicant. The second payment claim included a worksheet headed “Worksheet
for Early Works Contract Claim 2”, which adopted the same format of the
worksheet contained in the first payment claim. On or about 5 August 2024, the
applicant issued its payment schedule in response to the second payment claim.
On 22 August 2024, the respondent sent by email the third payment claim to the
applicant. The third payment claim included a worksheet headed “Worksheet for
Early Works Contract Claim 3”, which adopted the same format of the worksheets
contained in the first and second payment claims. On or about 5 September 2024,
the applicant issued its payment schedule in response to the third payment claim.
[22] On 22 September 2024, the respondent sent an email to the applicant with the
subject line “Northshore Payment Claim 4 for September and Variation 3 changed
pits to concrete”. The 22 September 2024 email relevantly attached the fourth
payment claim, which included a worksheet, which adopted the same format of
the previous worksheets, headed “Worksheet for Early Works Contract Claim 4”
(“the fourth payment claim’s worksheet”). The email also included a separate
worksheet headed “Contract Variation 3: change manholes to concrete” (“the
variation 3 worksheet”).
[23] The material parts of the fourth payment claim’s worksheet may be set out as
follows:
1
2 Original Contract Value $ 101,449.30 Start 17/6/24
3 Variation Value Added $ 282,307.77 Finish 30/4/2024
4 New Contract Value $ 383,757.07
…
7
Breakdown
%
Completed
Value
completed Previous Value Certified Value This Claim
…
11 1.03 Sewer drainage services $ 38,000.00 50% $ 19,000.00 $ 17,100.00 $ 1,900.00
12 1.04 Stormwater drainage services $ 16,000.00 100% $ 16,000.00 $ 12,000.00 $ 4,000.00
…
19 $ 101,449.30 $ 60,000.00 $ 5,900.00
20 Variations Amount % Claimed $ This claim $ Paid $ Not paid
…
22 SEQ1 *Per Quote 1659 QUU Req $ 65,285.00 50% $ 32,642.50 $ 29,378.25 $ 3,264.25
23 SEQ2 Extra concrete removal $ 291.50 100% $ 291.50 $ 291.50 -
-- 9 of 21 --
10
24 SEQ3 Changed manholes $ 12,361.72 85% $ 10,507.46 - $ 10,507.46
25 SEQ4 Concrete cutting over 200mm $ 2,936.11 100% $ 2,936.11 $ 2,352.00 $ 584.11
26 SEQ1 Supp 1 sewer extra over $ 50,714.55 100% $ 50,714.55 $ 43,654.84 $ 7,059.71
27 SEQ1 Supp 2 sewer extra over $ 47,777.22 100% $ 47,777.22 - $ 47,777.22
28 SEQ1 Supp 3 sewer to stage 1 $ 101,303.17 100% $ 101,303.17 - $ 101,303.17
…
30 SEQ5 Fill compact after asbestos $ 1,638.50 100% $ 1,638.50 - $ 1,638.50
…
33 Variation Total $ 282,307.77 0% $ 274,811.01 $ 75,676.59 $ 172,134.42
34 Contract plus Variation Total $ 202,752.47 $ 307,811.01 $ 75,676.59 $ 178,034.42
This Claim plus Retention Exc GST
$
178,034.42
RETENTION AT 10% This claim $ 14,115.38
This Claim less Retention Exc GST $ 163,919.04
[24] The fourth payment claim sought payment of two items claimed as owing under
the subcontract, items 11 and 12, and seven items claimed by way of variations,
items 22, 24, 25, 26, 27, 28 and 30.
[25] Item 11 was identified as “1.03 Sewer Drainage Services”. An item described as
“1.03 Sewer Drainage Services” appeared in a schedule to the subcontract headed
“Schedule B Pricing Schedules”. Annexure B to the subcontract, which contained
the Scope of Works, included a description of “Sewer Drainage Services” as
“including” the following:
o “underground service location;
o cutting and removal of existing concrete and bitumen surfaces as
required;
o excavation and removal of spoil offsite;
o provide safety boxes, shoring etc for safe working depth;
o connection to existing council manhole with internal drop as per SEQ
code and standards;
o supply & install new 160 PE sewer main pipework (approximately 140
metres);
o supply and install type F manhole with class D lid and frame as per
SEQ code and standards;
o supply & install type B4 property connection as per SEQ code and
standards;
o raise inspection opening to surface at property connection;
o backfill trench with approved materials including compaction to
existing surface level”.24
24 Page 66 of 1075.
-- 10 of 21 --
11
[26] From the making of the first payment claim, item 1.03 Sewer Drainage Services
had been allocated a “breakdown” figure of $38,000.
[27] Item 12 was identified as “1.04 Stormwater Drainage Services”. An item
described as “1.04 Stormwater Drainage Services” appeared in a schedule to the
subcontract headed “Schedule B Pricing Schedules”. Annexure B to the
subcontract, which contained the Scope of Works, included a description of
“Stormwater Drainage Services” as “including” the following:
o “underground service location;
o cutting and removal of existing concrete & bitumen surfaces as
required;
o execution and removal of spoil offsite;
o locate and connect to existing stormwater infrastructure;
o supply & install 150dia uPVC SW pipework including bends,
junctions, capping etc;
o supply & install 225dia uPVC SW pipework including bends,
junctions, capping etc;
o supply & install 300dia uPVC SW pipework including bends,
junctions, capping etc;
o supply & install IOS where required;
o supply of installed grated pits GP1/4no;
o backfill with improved materials including compaction to existing
surface level; and
o allow provisional allowance for stormwater treatment system
(hydrocarbon)”.
[28] From the making of the first payment claim, item 1.04 Stormwater Drainage
Services had been allocated a “breakdown” figure of $16,000.
[29] As to item 22, on 18 July 2024, the respondent had emailed the applicant a
worksheet described as “Contract Variation 1 Quote 1659”. That worksheet
described the nature of the works the subject of the variation as “Extra
requirements for sewer to QUU approved and revised for extra changes on 2 nd July
2024”. The worksheet detailed the manner of calculation of the amount of $65,285
as follows:
Work outside 40hrs per week will be charges as per MA000036
Item Each, Hours, Invoice, Weight, Length,
Units
Ea Cost-GST Scope
%
$Total Date Labour $rate # Hrs Amount
Neg pressure test, air test, 1 $ 7,000.00 $ - $ 7,000.00 Plumber $ -
ADAC file creation for surveyor 1 $ 4,000.00 $ 4,000.00 A/Plumber $ -
Level 1 compaction 1 $ 6,000.00 $ 6,000.00
-- 11 of 21 --
12
[30] As to item 25, on 12 August 2024, the respondent had emailed the applicant a
worksheet headed “Contract Variation 4 Concrete Cutting over 200mm deep”. The
worksheet described the nature of the works the subject of the variation as
“Concrete Cutting in excess of quoted 200mm thick”. The worksheet contained a
statement that the variation referred to “work undertaken for the sewer line up to
the location of the black metal pipe encountered under the concrete slab, extra cuts
against the poured slab necessary to bring downpipe within 50mm of poured slab
side and extra cuts to remove concrete for changed bin wash”. The worksheet
detailed the manner of calculation of the amount of $2,936.11 as follows:
[31] As to item 26, on 19 August 2024, the respondent emailed the applicant a
worksheet headed “Variation 1 Supp 1 Sewer to Road connection extra/over”. The
spreadsheet described the nature of the works the subject of the variation as “Extra
depth of concrete cutting – extra quantities of concrete removal, jackhammering
and disposal. Downtime of machines and operators due to extra and unknown
Create and install 150mm internal
jump-up
1 $ 7,500.00 $ 7,450.00
Extra to meet SEQ Code including
increase of invert level
1 $ 9,625.00 $ 9,625.00
Hold points, inspections and stand
downs
1 $ 7,500.00 $ 7,500.00
Construction of insuite sewer
manholes, incl step irons
1 $ 6,230.00 $ 6,230.00
Road plates hire for 3 weeks only 1 $ 16,480.00 $ 16,480.00
Management of train tracks 1 $ 1,000.00 $ 1,000.00
0
$ 65,285.00 $ -
Item Each, Hours, Invoice, weight,
Length, Units
Ea Cost-
GST
Scope% $Total Date Labour $rate # Hr
s
Amount
Hibbo
17/6/24
240 x 250 concrete floor (Hibbo
charge $22m) (see reduced cost)
240 $ 7.00 $ 168.00 $ 1,848.00 Plumber $ 120.00 1 1 $ 120.00
14411 % setup – blade changes 1 $ 25.00 $ 2.50 $ 27.50 T/A $ 65.00 1 1 $ 65.00
14681 7.8m x 300mm NE End to
accommodate changed bin wash
7.8 $ 37.95 $ 29.60 $ 325.61
Ring saw (Hibbo charge $135m)
(see reduced charge)
10 $ 45.00 $ 45.00 $ 495.00
Establishment 1 $ 50.00 $ 5.00 $ 55.00
0 $ - $ - $ -
$ 2,751.11 $ 185.00
-- 12 of 21 --
13
factors. Abnormal findings by [the respondent] when area exposed – see email
below. Under engineer’s instructions – Remove black unsuitable material down to
sand layer, build back up to below invert level CBR; (compacted). Geofab, then
bedding sand to invert level.” The worksheet noted that only amounts over those
amounts allowed in variation 1 were included in the calculation. The worksheet
detailed the manner of calculation of the amount of $50,714.55 over some 4 pages
by reference to the operation of identified plant, equipment and labour charges.
The worksheet noted that 24.5 metres of trenching had been completed and
19.5 metres of pipe had been laid.
[32] As to item 27, on 22 August 2024, the respondent emailed the applicant a
worksheet headed “Variation 1 Supp 2 Unsafe site closure to road crossing”. The
worksheet described the variation as being supplementary to Quote 1659. The
worksheet described the nature of the works the subject of the variation as follows
“… quote 1659 was based upon trenching in solid soil, free of rock or concrete,
1.5m deep by .5m wide. In all calculations only X/O (extra over) is claimed after
consideration of variation 1. Abnormal findings by [the respondent] when area
exposed – see email below. Under engineer’s instructions – Remove black
unsuitable material down to sand layer, build back up to below invert level with
CBR; (compacted). Geofab, then bedding sand to invert level”. The worksheet
detailed the manner of calculation of the amount of $47,777.22 over some 4 pages
by reference to the operation of identified plant, equipment and labour charges.
The worksheet noted that the variation was concerned with work “[f]rom the
19.5 m mark to the road crossing 21/8/214.”
[33] As to item 28, on 7 September 2024, the respondent emailed the applicant a
worksheet headed “Variation 1 Supp 3 Sewer to Road connection 31 st Aug 24”.
The worksheet described the variation as being supplementary to Quote 1659. The
worksheet described the nature of the works the subject of the variation as follows
“Remove unsuitable soil spoil from Compound. Lay sewer line, supply and
compact CBR continuing to end of stage 1. Downtime of machines and operators
due to extra and unknown factors. Under engineer’s instructions – remove black
unsuitable material down to sand layer, build back up to below invert level.
Geofab, then bedding sand to invert level”. The worksheet detailed the manner of
calculation of the amount of $101,303.17 over some 4 pages by reference to the
operation of identified plant, equipment and labour charges. The worksheet noted
that the variation was concerned with work which had completed the trenching
required for Stage 1.
[34] As to item 30, on 18 September 2024, the respondent had emailed the applicant a
worksheet headed “Variation 5 Fill Compact trenches after asbestos removed”.
The worksheet described the nature of the works the subject of the variation as
follows “as per BBG request-Supply machinery and labour to fill and compact
trenches at front and side of house after asbestos contamination removed. Clean
area”. The worksheet detailed the manner of calculation of the amount of
$1,638.50 as follows:
Item Each, Hours, Invoice, weight,
Length, Units
Ea Cost-GST Scope% $Total Labour $rate # Hrs Amount
-- 13 of 21 --
14
[35] As to item 24, as has already been noted, under cover of the fourth payment claim,
the variation 3 worksheet was provided. The variation 3 worksheet that variation
as “Change manholes to concrete”. The variation 3 worksheet described the nature
of the works the subject of the variation as “Changed Pits from quoted materials
to concrete”. The worksheet identified the difference in material and labour costs
between poly pits changed over to concrete pits. The worksheet detailed the
manner of calculation of the amount of $12,361.72 as follows:
Machine and attachments as per
scope
3 $ 145.00 $ 43.50 $ 478.50 Supervisor/
Op $ 150.00 1.00 3.00 $ 450.00
T/A $ 65.00 1.00 3.00 $ 195.00
Travel to and return Supervisor/
Op
$ 150.00 1.00 3.00 $ 450.00
Travel to and return T/A $ 65.00 1.00 1.00 $ 65.00
$ - $ - $ -
$ 478.50 $1,160.00
Item Each, Hours, Invoice,
Weight, Length, Units
Ea Cost-GST Scope% $Total Date Labour $rate # Hrs Amount
Reece Rebated Inspection
Chamber 1050x150
1 $ 193.50 $ 19.35 $ 212.85 Supervisor $150.00 1.00 10.0 $ 1,500.00
1005375037 Rebated Inspection
Chamber 1050x300
1 $ 223.00 $ 22.30 $ 245.30 A/Plumber $ 65.00 1.00 10.0 $ 650.00
Rebated Inspection
Chamber 1050x600
1 $ 281.25 $ 28.13 $ 309.38 Plumber $120.00 1.00 10.0 $ 1,200.00
Truck Delivery
standard
1 $ 136.36 $ 13.64 $ 150.00 $ -
289418836 Rebated Inspection
Chamber 1050x900
2 $ 459.18 $ 91.84 $ 1,010.20 $ -
Rebated Inspection
Chamber 1050x1200
1 $ 359.93 $ 35.99 $ 395.92 $ -
SW Aspro 1200
(1650od)x900x900
1 $ 680.49 $ 68.05 $ 748.54 $ -
Class D grate and
frame H/G (900x900)
1 $ 600.00 $ 60.00 $ 660.00 $ -
-- 14 of 21 --
15
Class D grate and
frame (1650)odx175
900x600 Void
1 $ 730.49 $ 73.05 $ 803.54 $ -
Class D grate and
frame H/G 600x900
Void
2 $ 453.33 $ 90.67 $ 997.33 $ -
Crane Hiab Unload per
delivery
1 $ 227.27 $ 22.73 $ 250.00 $ -
Rebated Inspection
Chamber 1050x300
1 $ 234.00 $ 23.40 $ 257.40 $ -
SW Aspro 1200
(1650od)x175
900x600
2 $ 730.49 $ 146.10 $ 1,607.08
Bedding Gravel x 4
Chambers
$ - $ -
Tools and
Consumerables (Quick
cut foam fill, morter)
1 $ 325.00 $ 32.50 $ 357.50
Concrete SW Pit
600x600x600
1 $ 185.37 $ 18.54 $ 203.91
Concrete SW Pit Riser
600x600x600
1 $ 157.50 $ 15.75 $ 173.25
Gms Drop in grate suit
pit 600x600
1 $ 137.33 $ 13.73 $ 151.06
Excavation
over/above
1500x1500 opposed
to 450 sq pit
3 $ 145.00 $ 43.50 $ 478.50
Pour a concrete base
(Concrete Cost)
1 $ 750.00 $ 75.00 $ 825.00 A/Plumber $65.00 1.00 3.50 $ 227.50
Pit Right front Altering concrete pits
and risers to suit PVC
SW pipes using
Plumber $120.00 1.00 3.50 $ 420.00
Quickcut saw and
Bobcat
1 $ 45.00 $ 4.50 $ 49.50 T/A $65.00 1.00 4.00 $ 260.00
Pit Left Front Shape concrete pits
and risers to suit PVC
SW pipes using
Plumber $120.00 1.00 3.00 $ 360.00
Quickcut saw and
Bobcat
1 $ 55.00 $ 5.50 $ 60.50 T/A $65.00 1.00 2.00 $ 130.00
Pit back of
house
Holes concrete pit and
riser to suit PVC SW
pipes using
Plumber $120.00 1.00 1.50 $ 180.00
Drills and saws 1 $ 33.00 $ 3.30 $ 36.30 T/A $65.00 1.00 1.50 $ 97.50
Provide other tools
(Laser etc)
1 $ 40.00 $ 4.00 $ 44.00
$ 10,027.04 $ 5,025.00
CREDITS This shows the material and labour difference between Poly pits changed over to concrete pits
Rein 450mm Stormwater Pit
510mm Deep with Grate Light Duty
2 $ 203.19 $ - $ 406.38 Allowed Supervisor $ 150.00 1.00 2.00 $ 300.00
Rein 450mm Stormwater Riser -
300mm Deep
2 $ 71.60 $ - $ 143.20 A/Plumber $ 65.00 1.00 2.00 $ 130.00
-- 15 of 21 --
16
The fourth payment claim is valid
[36] The applicant submitted that the fourth payment claim was not a valid payment
claim because it did not identify the construction work or related goods and
services to which the progress payment related. There were two essential limbs to
that argument. The first was that the fourth payment claim did not within itself
identify construction work, the words used within the payment claim being apt to
describe trade packages but not work performed. The second limb was to the effect
that even if the Court were permitted to look for the identification in the previously
exchanged documentation, the use of percentages to describe the work performed
meant that the work was not identified.
[37] As to the first limb, the argument as developed orally on behalf of the applicant
was to the effect that “… a payment claim can’t be a payment claim unless it
identifies the construction work or related goods and services to which it relates
… [a]nd … that cannot be achieved by reference to documents that do not form
part of the payment claim itself”.25 That submission was explained in terms that
“the failure of a payment claim to identify construction work [could not] be
remedied by reference to documents that did not form part of the payment claim
itself”.26 The applicant variously submitted that regard could not be had to
documents which did not form part of a payment claim for the purpose of deciding
whether the payment claim identified the construction work,27 that “what’s
25 T 1-4.37 to 45.
26 T 1-4.43 to 45.
27 T 1-4.28 to 35.
Rein 600mm Stormwater Pit Square
660mm Deep with Grate Medium
Duty
1 $ 546.55 $ - $ 546.55 Allowed Plumber $ 120.00 1.00 2.00 $ 240.00
Rein 600mm Stormwater Riser -
300mm Deep
1 $ 125.44 $ - $ 125.44
Consumables incl hole saw, tools 1 $ 25.00 $ - $ 25.00
Excavation for 600sq 1 $ 145.00 $ - $ 145.00
Credit for base of pits (Nil – poly
pits come with basis)
2 0.00 $ -
Pit
Right
front
Drop in PVC Pit Allowed Plumber $ 120.00 1.00 1.00 $ 120.00
Recipro cut to suite 1 $ 45.00 $ - $ 45.00 Allowed T/A $ 65.00 1.00 1.00 $ 65.00
Pit Left
front
Drop in PVC Pit Allowed Plumber $ 120.00 1.00 1.00 $ 120.00
Drill and saw holes PVC 1 $ 35.00 $ - $ 35.00 Allowed T/A $ 65.00 1.00 1.00 $ 65.00
Pit
back of
house
Drop in PVC Pit Allowed Plumber $ 120.00 1.00 0.50 $ 60.00
Drill holes and adjust saw 1 $ 30.00 $ - $ 30.00 Allowed T/
A
$ 65.00 1.00 0.75 $ 48.75
Provide other tools (Laser etc) 1 $ 40.00 $ - $ 40.00
-$ 1,541.57 - $ 1,148.75
-- 16 of 21 --
17
relevant is what’s delivered”28 and documents relied upon to sustain a payment
claim must be included in the payment claim.29 The applicant reached the point
of submitting that the court could not look at any document outside of a payment
claim for the purpose of identifying the work or related goods or services.30 The
ultimate contention made by the applicant’s submission was that the fourth
payment claim, on its face was “insufficient to be construed as … any description
of work.”31 It was submitted that the fourth payment claim, properly construed,
contained “no description of the work at all”.32
[38] I reject these submissions. It is a settled principle that, in deciding whether work
has been sufficiently identified, the background of each of the parties “derived
from their past dealings and exchanges of documentation” is properly to be taken
into account.33 Once it is appreciated that the objective task of construction takes
into account the background knowledge of each of the parties derived from their
past dealings and exchanges of documentation, the question whether the relevant
construction work is identified sufficiently cannot be answered by confining the
inquiry to the actual document or documents comprising the payment claim.
Hence, as has been observed in the case law a payment claim “which appear[s] to
be extremely summary, or to the uninformed but not unintelligent observer brief
to the point of incomprehensibility, may be sufficiently meaningful to the parties
to enable them to know, respectively, the bases on which a particular payment
claim is advanced”.34 In this case, items 11 and 12 respectively contained
shorthand identifications of the work described in Annexure B to the subcontract
as Sewer drainage services and Stormwater drainage services. The seven items
claimed by way of variations, items 22, 24, 25, 26, 27, 28 and 30, having regard
to the previous correspondence exchanged between the parties and the
correspondence included with the fourth payment claim in respect of variation
three, contained sufficiently meaningful words to be understood as a reference to
identified work.
[39] As to the second limb of its argument, in oral submissions the applicant conceded
that if the Court were entitled as a matter of law to look at the previous
documentation exchanged between the parties for the purpose of identifying work,
the exchanged documentation was sufficient to identify construction work. The
applicant’s real point was that the fourth payment claim’s use of percentages meant
that the work the subject of the progress payment had not been identified.
[40] Adopting an objective interpretation of the fourth payment claim’s worksheet:
(a) As to item 11, the amount of $1,900.00 was claimed representing a percentage
value of 5% of the work comprising Sewer Drainage Services. Having regard
to the nature and extent of the work described in Annexure B to the subcontract
28 T 1-49.14 to 15.
29 T 1-12.45 to 46.
30 T 1-55.33.
31 T 1-57.38 to 40.
32 T 1-58.14.
33 T & M Buckley Pty Ltd v 57 Moss Rd Pty Ltd [2010] QCA 381 at [14]; Neumann Contractors Pty Ltd
v Peet Beachton Syndicate Ltd [2011] 1 Qd R 17 at [25]; Nepean Engineering Pty Ltd v Total Process
Services Pty Ltd (in liq) (2005) 64 NSWLR 462 at [48].
34 Leighton v Arogen [2012] NSWSC 1323 at [69]; See also ISIS Projects Pty Ltd v Clarence Street Pty
Ltd [2004] NSWSC 714 at [36] and [37].
-- 17 of 21 --
18
as Sewer Drainage Services, I find that it is unclear from the fourth payment
claim what work comprised that 5% of the Sewer Drainage Services. The use
of a percentage figure in this instance was not sufficient to identify the
particular work the subject of the claim.
(b) As to item 12, the amount of $4,000 was claimed representing a percentage
value of 25% of the work comprising Stormwater Drainage Services. Having
regard to the nature and extent of the work described in Annexure B to the
subcontract as Stormwater Drainage Services, I find that it is unclear from the
fourth payment claim what work comprised that 25% of the Stormwater
drainage services. The use of a percentage figure in this case was not sufficient
to identify the particular work the subject of the claim.
(c) As to item 22, the amount of $3,264.25 was claimed representing a percentage
value of 5% of the work comprising “variation 1 Quote 1659”. Having regard
to the nature and extent of the work described in the previous correspondence
as comprising “variation 1 Quote 1659”, I find that it is unclear from the fourth
payment claim what work comprised that 5% of the work comprising
“variation 1 Quote 1659”. The use of a percentage figure in this case was not
sufficient to identify the particular work the subject of the claim.
(d) As to item 25, the amount of $584.11 was claimed representing a percentage
value of approximately 20% of the work comprising “Contract Variation 4
Concrete Cutting over 200mm deep”. Having regard to the nature and extent
of the work described in the previous correspondence as comprising “Contract
Variation 4 Concrete Cutting over 200mm deep”, I find that it is unclear from
the fourth payment claim what work comprised the approximately 20% of the
work comprising “Contract Variation 4 Concrete Cutting over 200mm deep”.
The use of a percentage figure in this case was not sufficient to identify the
particular work the subject of the claim.
(e) As to item 26, the amount of $7,059.71 was claimed representing a percentage
value of approximately 14% of the work comprising “Variation 1 Supp 1 Sewer
to Road connection extra/over”. Having regard to the nature and extent of the
work described in the previous correspondence as comprising “Variation 1
Supp 1 Sewer to Road connection extra/over”, I find that it is unclear from the
fourth payment claim what work comprised the approximately 14% of the work
comprising “Variation 1 Supp 1 Sewer to Road connection extra/over”. The
use of a percentage figure in this case was not sufficient to identify the
particular work the subject of the claim.
(f) As to item 27, the amount of $47,777.22 was claimed being 100% of the work
comprising “Variation 1 Supp 2 unsafe site closure to road crossing”.
(g) As to item 28, the amount of $101,303.17 was claimed being 100% of the work
comprising “Variation 1 Supp 3 Sewer to Road connection 31st Aug 24”.
(h) As to item 30, the amount of $1,638.50 was claimed being 100% of the work
comprising “Variation 5 Fill Compact trenches after asbestos removed”.
(i) As to item 24, the amount of $10,507.46 was claimed representing a percentage
value of approximately 85% of the work comprising “Variation 3 Changed
manholes”. I find that it was sufficiently clear from the fourth payment claim
what work comprised the approximately 85% of the work comprising
-- 18 of 21 --
19
“Variation 3 Changed manholes”. This particular work was being claimed from
a zero base and was discrete work in the sense that it was wholly concerned
with the material and labour differences between changing from poly pits to
concrete pits. The use of a percentage figure in this case was sufficient to
identify the basis on which this part of the payment claim was being advanced
and the work the subject of this part of the claim.
[41] The applicant sought declaratory relief that the decision be declared void for want
of jurisdiction.35 As has been observed by Copley J in Baguley Build Pty Ltd v
Olcon Concrete & Construction Pty Ltd,36 the statutory provision which confers
functions on an adjudicator, s 88, is the correct point from which to commence
when considering the issue of jurisdictional error. One of the matters identified in
s 88(2) is “the payment claim to which the application relates”. In Niclin
Constructions Pty Ltd v Robotic Steel Fab Pty Ltd37 Applegarth J relevantly said:
“The valid exercise of an adjudicator’s jurisdiction is conditioned on
the adjudicator having considered the matters set out in s 88(2) of
the Act. The valid exercise of an adjudicator’s decision is not
conditioned on the adjudicator reaching what is objectively the
correct conclusion on the questions of fact or law that are required
by the consideration of the matters set out in s 88(2). Expressed
differently, ‘there are many errors of fact and law which might be
made by an adjudicator which would not be regarded as going to
jurisdiction’.”
[42] In Brodyn Pty Ltd v Davenport 38 Hodgson JA (with whom Mason P and Giles JA
agreed) drew a distinction between ss 13(1) and (2) of the Building and
Construction Industry Security of Payment Act (1999) (NSW) (“the NSW Act”).
Those sections were materially in these terms:
“13 Payment claims
(1) A person … who is or who claims to be
entitled to a progress payment (the claimant)
may serve a payment claim on the person
who, under the construction contract
concerned, is or may be liable to make the
payment.
(2) A payment claim:
(a) must identify the construction work (or
related goods and services) to which
the progress payment relates, and
(b) must indicate the amount of the
progress payment that the claimant
claims to be due (the claimed amount),
and
35 Originating Application, Final orders sought paragraph 1.
36 [2025] QSC 126 at [19].
37 (2023) 16 QR 336 at [18].
38 (2004) 61 NSWLR 421 at 441-442 [53] to [55].
-- 19 of 21 --
20
(c) must state that it is made under this
act.”
[43] Hodgson J described s 13(1) as containing a “basic and essential requirement”
which was part of the “conditions laid down for the existence of an adjudicator’s
determination”. His Honour described s 13(2) as containing “more detailed
requirements” as to “the content of payment claims”. After having drawn that
distinction, his Honour then said in relation to the requirements of s 13(2):
“A question arises whether any non-compliance with any of these
requirements has the effect that a purported determination is void, that
is, is not in truth an adjudicator’s determination. That question has
been approached in the first instance decision by asking whether an
error by the adjudicator in determining whether any of these
requirements is satisfied is a jurisdictional or non-jurisdictional error.
I think that approach has tended to cast the net too widely; and I think
it is preferable to ask whether a requirement being considered was
intended by the legislature to be an essential pre-condition for the
existence of an adjudicator’s determination.
In my opinion, the reasons given above for excluding judicial review
on the basis of non-jurisdictional error of law justify the conclusion
that the legislature did not intend that exact compliance with all the
more detailed requirements was essential to the existence of a
determination: cf Project Blue Sky Inc v Australian Broadcasting
Authority (1998) 194 CLR 355 at 390–391. What was intended to be
essential was compliance with the basic requirements (and those set
out above may not be exhaustive), a bona fide attempt by the
adjudicator to exercise the relevant power relating to the subject matter
of the legislation and reasonably capable of reference to this power (cf
R v Hickman; Ex parte Fox and Clinton (1945) 70 CLR 598), and no
substantial denial of the measure of natural justice that the Act requires
to be given. If the basic requirements are not complied with, or if a
purported determination is not such a bona fide attempt, or if there is
a substantial denial of this measure of natural justice, then in my
opinion a purported determination will be void and not merely
voidable, because there will then not, in my opinion, be satisfaction of
requirements that the legislature has indicated as essential to the
existence of a determination. If a question is raised before an
adjudicator as to whether more detailed requirements have been
exactly complied with, a failure to address that question could indicate
that there was not a bona fide attempt to exercise the power; but if the
question is addressed, then the determination will not be made void
simply because of an erroneous decision that they were complied with
or as to the consequences of non-compliance.”
[44] Later, Hodgson JA continued:39
“If there is a document served by a claimant on a respondent that
purports to be a payment claim under the Act, questions as to whether
39 Ibid at [66].
-- 20 of 21 --
21
the document complies in all respects with the requirements of the Act
are generally, in my opinion, for the adjudicator to decide. Many of
these questions can involve doubtful questions of fact and law; and as
I have indicated earlier, in my opinion the legislature has manifested
an intention that the existence of a determination should not turn on
answers to questions of this kind. However, I do not need to express
a final view on this.”
[45] The reasoning of Hodgson JA in Brodyn is consistent with the approach of Bond
J in E Home Construction Pty Ltd v GCB Constructions Pty Ltd.40 In that case, his
Honour relevantly said “The characterisation exercise necessary to be done in
order to deal with the jurisdictional argument is a characterisation exercise that has
to be done in relation to the entirety of the payment claim”. His Honour went on
to accept as correct the proposition that “… because the majority of the payment
claim was for things that plainly could be claimed for in a valid payment claim,
the payment claim still could be appropriately characterised as such”. In the
present case, the two biggest claim items, items 27 and 28, together with items 24
and 30 sufficiently identified the construction work and services the subject of the
fourth payment claim. Those items accounted for approximately $161, 000, an
overwhelming majority of the total amount of the payment claim. Having regard
to the characterisation exercise necessary to be undertaken by reference to the
entirety of the fourth payment claim, the fourth payment claim is appropriately
characterised as a valid payment claim and no jurisdictional error has been
established.
Orders
[46] The orders I make are as follows:
1. The originating application filed 18 November 2024 is dismissed.
2. I will hear the parties as to costs.
40 [2020] QSC 291 at pp 6–7.
-- 21 of 21 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2025/167