Bright Days Herston Pty Ltd v ATG Project & Property Solutions Pty Ltd [2025] QSC 147
SUPREME COURT OF QUEENSLAND
CITATION: Bright Days Herston Pty Ltd v ATG Project & Property
Solutions Pty Ltd [2025] QSC 147
PARTIES: BRIGHT DAYS HERSTON PTY LTD
(ACN 601 164 309)
(applicant)
v
ATG PROJECT & PROPERTY SOLUTIONS PTY LTD
(ACN 160 517 493)
(first respondent)
CHRISTOPHER MORROW
(second respondent)
ADJUDICATION REGISTRAR APPOINTED UNDER
SECTION 150 OF THE BUILDING INDUSTRY
FAIRNESS (SECURITY OF PAYMENT) ACT 2017
(QLD)
(third respondent)
FILE NO/S: BS 4991/24
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT:
Supreme Court of Queensland at Brisbane
DELIVERED ON: 25 June 2025
DELIVERED AT: Brisbane
HEARING DATE: 19 March 2025
JUDGE: Treston J
ORDER: Application is dismissed, with costs.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION –
STATUTORY REGULATION OF ENTITLEMENT TO
AND RECOVERY OF PROGRESS PAYMENTS –
ADJUDICATION OF PAYMENT CLAIMS – where the
applicant and the first respondent entered into a construction
contract and the first respondent made an adjudication
application under the Building Industry Fairness (Security of
Payment) Act 2017 (Qld) after a dispute arose in relation to a
payment claim – where the applicant objected to the first
adjudicator determining the application due to a reasonable
apprehension of bias – where by an email in response to the
applicant’s objection, the first adjudicator advised that he did
not intend to issue a decision – where the first respondent
-- 1 of 22 --
2
then requested the Registrar refer the adjudication application
to a subsequent adjudicator (the second respondent) – where
the applicant advances two grounds by which the decision of
the second respondent was affected by jurisdictional error –
where the applicant contends the second respondent did not
have jurisdiction to determine the adjudication application
because the first adjudicator’s decision not to issue a
decision, was in fact, a decision made under the Act – where
the applicant contends the second respondent failed to take
into account mandatory considerations being, the applicant’s
submissions regarding the second respondent’s jurisdiction to
determine the application and the applicant’s submissions to
the first respondent regarding a subsequent payment –
whether the second respondent had jurisdiction to determine
the application – whether the second respondent failed to
consider mandatory considerations thereby constituting a
jurisdictional error
Building Industry Fairness (Security of Payment) Act 2017
(Qld), ss 80, 81, 84, 85, 88, 90, 94, 95
Building Industry Fairness (Security of Payment) Regulation
2018 (Qld), s 13
Acciona Agua Australia Pty Ltd v Monadelphous
Engineering Pty Ltd (2020) 4 QR 410
Ceerose Pty Ltd v A-Civil Aust Pty Ltd (2023) 112 NSWLR
225
Chevron Park Pty Ltd v Groupline Constructions Pty Ltd &
Ors [2024] QSC 202
Duro Felguera Australia Pty Ltd v Samsung C&T
Corporation (2018) 52 WAR 323
S.H.A. Premier Constructions Pty Ltd v Niclin Constructions
Pty Ltd [2020] QSC 307
Lendlease Building Pty Ltd v BCF Airport Systems Pty Ltd &
Ors [2024] QSC 164
Martinus Rail Pty Ltd v Qube RE: Services (No 2) Pty Ltd
(No 2) [2024] NSWSC 1223
Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty
Ltd (2018) 264 CLR 1
Shellbridge Pty Ltd v Rider Hunt Sydney Pty Ltd [2005]
NSWSC
Thiess Pty Ltd v Warren Brothers Earthmoving Pty Ltd &
Ors [2012] QSC 373
COUNSEL: M S Steele KC and M H Martinez for the applicant
D S Piggott KC and J Mitchenson for the first respondent
N J Miranda for the third respondent
SOLICITORS: Helix Legal for the applicant
Thomson Geer for the first respondent
Crown Law for the third respondent
-- 2 of 22 --
Introduction
[1] On 7 December 2021, Bright Days (the applicant) and ATG (the first respondent)
entered into a construction contract to design and construct a childcare centre at
Herston. The contracted price was just over $11 million.
[2] A dispute arose in late 2023 in relation to a payment claim and, by this application,
Bright Days seeks a declaration that an adjudication decision of the second
respondent dated 22 January 2024, is void on account of jurisdictional error and
applies for it to be set aside.
[3] For the reasons which follow, Bright Days’ application is dismissed.
Background
[4] On 25 September 2023, ATG served Payment Claim 22 on Bright Days for the sum
of $1,323,003.95 (including GST).
[5] On 10 October 2023, the Superintendent issued the Progress Payment Certificate 22
certifying the amount of $782,738.00 (including GST) in response to the Payment
Claim. The GST component was $711,580.00.
[6] On 17 October 2023, Bright Days served Payment Schedule 11 on ATG in
response, scheduling an amount of $71,158.00. Some of the detail in the Payment
Schedule is set out below at [61(b)].
[7] On 19 October 2023, ATG made an Adjudication Application under the Building
Industry Fairness (Security of Payment) Act 2017 (Qld) (the Act).
[8] On 26 October 2023, the adjudicator, Mr Trattler, in accordance with s 81 of the
Act, confirmed acceptance of the 19 October adjudication application No. QBCC
2381736.
[9] On 27 October 2023, solicitors on behalf of Bright Days wrote to Mr Trattler,
noting his appointment in respect of the 19 October Adjudication Application (and
another application irrelevant for the purposes of this proceeding) and observed:
“We invite you to consider:
(a) Section 80 of the Building Industry Fairness (Security of
Payment) Act 2017 (Qld);
(b) Section 13(1) of the Building Industry Fairness (Security of
Payment) Regulation 2018 (Qld); and
(c) The Code of Conduct for Adjudicators (Version 1.0, November
2018) issued by the Queensland Building Construction
Commission.”
[10] Although the letter did not expressly say it, the reference to s 80, s 13 and the Code
of Conduct, went to issues related to the adjudicator’s eligibility or otherwise, to
adjudicate. Section 80 of the Act provides:
-- 3 of 22 --
4
“80 When adjudicator ineligible to adjudicate
An adjudicator is not eligible to adjudicate an adjudication
application if the adjudicator─
(a) is a party to the construction contract to which the
application relates; or
(b) has a conflict of interest as prescribed by regulation.”
[11] Given that no party contended Mr Trattler was a party to the construction contract,
the letter of 27 October could only be construed as a reference to a potential conflict
of interest under subsection (b).
[12] On 30 October 2023, Mr Trattler replied with correspondence to the parties as
follows:
“The Respondent has requested that I consider whether I have a
conflict of interest under section 80 of the Act, with reference to the
regulation and code of practice.
The Regulation relevantly provides:
13 Conflicts of interest─Act, s 80
(1) For section 80(b) of the Act, an adjudicator has a
conflict of interest if─
(a) the adjudicator or a family member of the
adjudicator─
(i) is, or is contracted to be, employed or
otherwise engaged by the claimant or
respondent for the adjudication
application; or
(ii) is an owner of a building, structure or
land in relation to which construction
work or the supply of related goods and
services to which the adjudication
application relates is being carried out; or
(iii) is carrying out construction work or the
supply of related goods and services in
relation to a building, structure or land to
which the adjudication application
relates; or
(iv) has a direct or indirect pecuniary or other
interest in a matter to be considered
during the adjudication that could conflict
with the proper performance of the
adjudicator in adjudicating the
adjudication application; or
(b) the claimant or respondent for the adjudication
application is a family member of the adjudicator.
-- 4 of 22 --
5
I confirm that none of those subsections apply. Neither I nor any
family member has an interest in the parties or the work. I am not
aware of any conflict involving the Claimant or the Respondent or
any matter which would prevent me from deciding the adjudication
fairly between the parties. If there is something in particular, the
Respondent will need to be express in the communication regarding
the issue.
By way of disclosure, my employer engages the same solicitors as
the Respondent on an unrelated matter. I am providing instructions
to a different partner of that firm and will be communicating with her
about that unrelated matter during the time that these adjudications
are occurring. While not a conflict of interest under the legislation,
there is a possibility of a perceived conflict of interest.
I ask that both parties confirm in writing that they agree to me acting
in those circumstances. Please respond by 5pm on 31 October
2023.”
(underlining added)
[13] On 31 October 2023, solicitors on behalf of Bright Days objected to Mr Trattler
acting as the adjudicator, stating in an email:
“You have asked that our client confirm in writing whether it agrees
to you continuing to act as the adjudicator in both matters.
The issue is the perception of bias (see item 2 of the Code of
Conduct for Adjudicators).
We raised the matter because neither party is assisted if there is even
the perception of bias affecting the decisions that you have been
tasked with making.
We are instructed that our client is concerned that the circumstances
give rise to at least a perception of bias. This perception issue is
acknowledged in your notice below.
To be clear, our client does not consider that you are biased, only
that a fair-minded lay observer with knowledge of the relevant facts
might entertain that you might not bring an unprejudiced mind to the
matter. In the circumstances, our client considers it is best if an
adjudicator with no connection to the parties determines the
claimant’s applications.
Accordingly, we are instructed that our client does not agree to you
acting as the adjudicator in either adjudication.”
(underlining added)
[14] ATG’s solicitor responded later that same day recording that it did not consider
there was any conflict of interest and said:
“There is no mechanism under the BIF Act that would allow the
Respondent to ‘not agree’ to a particular adjudicator. It is not clear
-- 5 of 22 --
6
on what basis the Respondent has advised that it ‘does not agree to
you acting as the adjudicator in either adjudication’.”
[15] On 2 November 2023, Mr Trattler wrote to the parties as follows:
“Thank you for the response to my email, which I have considered.
I understand the comments from the Claimant regarding the process
and there not being any ability for a Respondent to ‘not agree’ to an
adjudicator.
Having considered the matter in detail, please be advised that I do
not intend to issue a decision, as given the Respondent’s stated
objections, I am concerned that an independent observer may
consider that there is an appearance of bias given the need to
communicate with the Respondent’s solicitors outside of the
adjudication process.
The Claimant’s attention is drawn to section 94 of the Act.”
(my underlining)
[16] Section 94 of the Act provides:
“94 Claimant may make new application in certain
circumstances
(1) Subsection (2) applies if an adjudicator, who accepts
a referral to decide an adjudication application (the
original application), does not decide the application
within the period required under section 85.
(2) The claimant may do either of the following within 5
business days after the period mentioned in
subsection (1)─
(a) request the registrar refer the original
application to another adjudicator; or
(b) make a new adjudication application (the new
application) under section 79 …”
[17] Section 94 therefore provides that in certain, limited, circumstances a claimant may
make a new application for an adjudication, or ask the Registrar to refer it to another
adjudicator. Those certain, limited, circumstances occur if an adjudicator has,
firstly, accepted a referral to decide an adjudication application and, secondly, does
not decide the application within the period required under s 85.
[18] Before making a new adjudication application, ATG wrote to Mr Trattler on 6
December 2023, observing that the 19 October 2023 Adjudication Application was
due to be decided on 4 December 2023, and made reference to the notice of 2
November 2023, referring the claimant’s attention to s 94 of the Act and asked:
“So that the Claimant can take the appropriate steps pursuant to that
section, we would be grateful if the Adjudicator would confirm the
following matters:
-- 6 of 22 --
7
1. The Adjudicator has not made a decision on either Adjudication
Applications 2381736 or 2381846 within the time required by
section 85 of the Act.
2. The Adjudicator has not received from the Respondent an
Adjudication Response in either of adjudication applications
2381736 or 2381846.”
[19] The adjudicator responded the same day as follows:
“I confirm that an adjudication decision was not made in either
application within the time required by the Act and did not receive an
adjudication response in either matter.”
[20] On 7 December 2023, ATG requested the Registrar refer the adjudication
application to another adjudicator, and on 13 December the second respondent
confirmed acceptance of that adjudication application.
[21] On 19 December 2023, ATG served the adjudication application on the adjudicator.
On 20 December 2023 Bright Days served its adjudication response.
[22] On 22 January 2024 the adjudicator, Mr Morrow, issued the adjudication decision.
After correction, the adjudicated amount was $1,004,306.52.
Ground 1 – no valid referral
[23] Bright Days’ primary position is that there was no valid referral to the second
adjudicator, Mr Morrow, because, irrespective of the characterisation given by
Mr Trattler to his decision of 2 November 2023 (set out at [15] above), his decision
was, in fact, a decision made under the Act. That is because, Bright Days contends,
that a decision not to decide an application is nevertheless a decision made under
the Act. In support of this submission, Bright Days points to ss 95(7) and 85(3) of
the Act.
[24] Section 95 is concerned with the adjudicator’s fees. It provides the circumstances in
which the adjudicator is entitled to be paid for adjudicating an adjudication
application:
“95 Adjudicator’s fees
…
(6) An adjudicator is not entitled to be paid any fees or
expenses for adjudicating an adjudication application
if the adjudicator fails to make a decision on the
application.
(7) An adjudicator does not fail to make a decision only
because─
(a) the adjudication application is withdrawn; or
(b) the adjudicator decided he or she did not have
jurisdiction to adjudicate the application; or
-- 7 of 22 --
8
(c) the adjudicator decided the application was
frivolous or vexatious; or
(d) the adjudicator refuses to communicate the
adjudicator’s decision on an adjudication
application until the adjudicator’s fees and
expenses are paid.”
[25] Section 95(7) does not support Bright Days’ argument. Section 95 is concerned
with the payment of the adjudicator’s fees, the obligation to pay them and by whom,
whether the obligation is joint and several (it is both),1 and other matters pertaining
to payment. It is not a provision directed towards determining what does, or does
not, constitute the making of a decision.
[26] The word “adjudicating” is defined in s 95(9) of the Act to include “accepting,
considering and deciding the (adjudication) application”. Adjudicating therefore
involves (at least) three elements – accepting, considering and deciding. The
meaning of s 95(7), that an adjudicator does not fail to make a decision “only
because” the adjudicator has decided he or she does not have jurisdiction to
adjudicate the application, refers to the circumstance where an adjudicator accepts,
considers and decides the application, but in so deciding, concludes that he or she
has no jurisdiction. In such a case, an adjudicator does not lose the entitlement to be
paid “only because” he or she decided there was no jurisdiction. It is a provision
directed towards ensuring fairness of payment to adjudicators in those limited
circumstances.2
[27] The construction that the term “adjudicating” in s 95(9) in fact involves three
elements - accepting, considering and deciding - is also consistent with s 94(1) that
if an adjudicator “accepts a referral”, but does not “decide” it, demonstrates that it is
possible for an adjudicator to accept a referral, but not complete it by considering
and deciding the application on its merits.
[28] As to s 85(3), Bright Days contends that section supports the conclusion that the
adjudicator’s statement that he had not made a decision on the application was in
fact a decision. Section 85 relates to the time for deciding an adjudication
application and s 85(3) relevantly provides:
“85 Time for deciding adjudication application
…
(3) An adjudicator must not decide an adjudication
application before the end of the period that the
respondent may give an adjudication response to the
adjudicator under section 83, unless─
(a) the adjudicator decides he or she does not have
jurisdiction to adjudicate the application; or
(b) the adjudicator decides the application is
frivolous or vexatious.”
1 Building Industry Fairness (Security of Payment) Act 2017 (Qld), s 95(4).
2 S.H.A. Premier Constructions Pty Ltd v Niclin Constructions Pty Ltd [2020] QSC 307 at [30].
-- 8 of 22 --
9
[29] Bright Days submits that whether the adjudicator has the jurisdiction to adjudicate
the application is in fact, “the very first thing an adjudicator must decide” within
s 84(2). Section 84 provides:
“84 Adjudication procedures
(1) Subject to the time requirements under section 85, an
adjudicator must decide the following as quickly as
possible─
(a) an adjudication application;
(b) applications for extensions of time under
section 83.
(2) For a proceeding conducted to decide an adjudication
application, an adjudicator─
(a) must decide─
(i) whether he or she has jurisdiction to
adjudicate the application; and
(ii) whether the application is frivolous or
vexatious; and
(b) may ask for further written submissions from
either party and must give the other party an
opportunity to comment on the submissions;
and
(c) may set deadlines for further submissions and
comments by the parties; and
(d) may call a conference of the parties; and
(e) may carry out an inspection of any matter to
which the claim relates.
…”
[30] Bright Days contends that where the adjudicator decided he had no jurisdiction to
determine the adjudication application, due to a reasonable apprehension of bias, a
decision permitted by ss 84(2)(a)(i) and 85(3) of the Act, this was a determination
of the adjudication application referred.
[31] Finally, Bright Days contends that the requirements for a decision under the Act are
undemanding in that the decision must simply be in writing, include reasons for the
decision (s 88(5)), and be given to the Registrar (s 88(6)). Bright Days submits that
the adjudicator complied with these requirements by sending an email to the parties
and the Registrar on 2 November 2023.
[32] As a matter of statutory construction, Bright Days’ submissions must be rejected
because:
(a) if the preliminary decision that the adjudicator makes that he or she does not
have jurisdiction to adjudicate the application was in fact the decision itself,
-- 9 of 22 --
10
then the adjudicator would not have to consider and decide any of the
substance of the application;
(b) having failed to do so, on Bright Days’ construction he or she would
nevertheless be fully entitled to be paid, having made a decision; and
(c) s 94(1) would never have any work to do, because on any occasion an
adjudicator decided they did not have jurisdiction, but had not considered the
substance of the application, no new application could ever be made.
[33] As a question of fact, Mr Trattler did exactly what Bright Days had instructed him
to do in their letter of 31 October 2023, when they expressed the position that it was
best if another adjudicator determined the application.
[34] But in any event, I conclude that the 2 November email was not a decision by
Mr Trattler that he did not have jurisdiction to adjudicate the adjudication
application. Bright Days agrees that the construction of Mr Trattler’s email is a
matter for the court to assess having regard to the words used. In my view, Mr
Trattler did not make any decision about jurisdiction. Rather he concluded only that
having considered the issue which had been raised against him, being a “perception
of bias”, he advised that he did not intend to issue a decision. His express reference
drawing the parties’ attention to s 94 of the Act, reinforced his own (correct) view
that he had not decided the application and a new application would be available
under s 94. That is the proper construction of the 2 November email. Mr Trattler
advised the parties that he did not intend to issue a decision at all, given Bright
Days’ objection to his appointment. Clearly, the 2 November email was not a
“decision” as Bright Days contends.
[35] In the circumstances, Ground 1 of the application fails. Bright Days’ submission
that Mr Trattler’s decision was not one which enlivens s 94 cannot be sustained.
Accordingly, the subsequent adjudicator did have jurisdiction to determine the
application and his decision cannot be impugned on the basis that he lacked
jurisdiction.
Ground 2 – failure to take account of mandatory considerations
[36] There appeared to be three sub-grounds to the second ground advanced by Bright
Days, being:
(a) the adjudicator failed to consider submissions made by Bright Days about the
first ground (jurisdiction), and thereby failed to comply with s 88(2)(d) of the
Act;
(b) the adjudicator failed to consider submissions made by Bright Days about a
payment which Bright Days had made to ATG after its Payment Schedule
had been served, but before the adjudicator issued the adjudication decision,
and thereby failed to comply with s 88(2)(d) of the Act; and
(c) in failing to consider Bright Days’ submissions about that subsequent
payment, the adjudicator failed to determine the “amounts of the progress
payment … to be paid” as required by s 88(1)(a) of the Act.
[37] In these ways, Bright Days submits that the adjudicator has fallen into jurisdictional
error.
-- 10 of 22 --
11
[38] As to the first sub-ground, Bright Days made the same submission to the adjudicator
which it made in this court, being that the effect of Mr Trattler’s email of 2
November was a “decision” under s 84(2)(a)(i) that he did not have jurisdiction to
adjudicate the application, that there was no power to refer the matter for a second
adjudication under s 94, meaning the adjudicator did not have jurisdiction to
determine the application.
[39] It is true that the adjudicator did not expressly refer to the matter having been
previously allocated to Mr Trattler, who then by his email of 2 November declined
to decide it.
[40] However, it cannot be said that the adjudicator did not turn his mind to the question
of jurisdiction. The adjudicator set out at paragraphs [13] to [33] of the decision,
that before he decided the adjudication application, he had to decide whether he had
jurisdiction to so adjudicate it. He addressed the matters necessary to reach that
conclusion including that there was a construction contract to which the Act
applied, a payment claim had been served on a person who is or may be liable to
make a payment, an adjudication application had been made and the application had
been “referred to and accepted by an eligible adjudicator”. The adjudicator then
turned to consider each of those matters, and concluded at paragraph 30, that he was
satisfied that he had jurisdiction to adjudicate the application.
[41] It was common ground between the parties that for this argument to succeed, Bright
Days must demonstrate:
(a) first, that the adjudicator failed to comply with s 88(2)(d) by failing to
consider Bright Days’ submission; and
(b) second, that the adjudicator’s failure to comply with s 88(2)(d) was material
in the sense that there was a realistic possibility that a different decision could
have been made had there been compliance with that condition.
[42] Bright Days submits, in effect, that because the adjudicator did not expressly refer
to the submissions pertaining to Mr Trattler’s email of 2 November that he must
have failed to consider it. In this way, Bright Days contends there was a
jurisdictional error by the adjudicator in the performance of the adjudication
function.
[43] What constitutes jurisdictional error under the Act was set out authoritatively by
Bond J, as his Honour then was, in Acciona Agua Australia Pty Ltd v Monadelphous
Engineering Pty Ltd.3 I summarised his Honour’s conclusions recently in Chevron
Park Pty Ltd v Groupline Constructions Pty Ltd & Ors4 and no party contended that
that summary was inaccurate. For brevity, and with no disrespect to his Honour’s
more thorough analysis, I repeat the summary below:
“[30] (a) the valid exercise of an adjudicator’s jurisdiction is
conditioned on the decision having complied with at
least the “basic and essential” statutory requirements
of the Payment Act at ss 64, 68, 70, 75, 79(4), 80, 81,
88 and 150;
3 (2020) 4 QR 410.
4 [2024] QSC 202 at [30].
-- 11 of 22 --
12
(b) the valid exercise of an adjudicator’s jurisdiction is
conditioned on the adjudicator having arrived at their
conclusion by a process which considers the matters
set out in s 88(2) of the Payment Act, noting:
(i) the valid exercise of the adjudicator’s
jurisdiction is not conditioned on the
adjudicator reaching what is objectively
the correct conclusion of all the questions
of fact or law required by the consideration
of the matters set out in s 88(2);
(ii) the question is not whether the court would
have come to the same conclusion as the
adjudicator, but whether the adjudicator
arrived at their conclusion by a process
which failed to consider the matters set out
in s 88(2);
(iii) an error in the identification of the terms of
the contract or their interpretation will not
be a jurisdictional error;
(iv) there is a difference between an error
which is not a jurisdictional error and that
which is; and
(v) if it can be demonstrated that the
adjudicator has not gone about their task
by carrying out the active process of
intellectual engagement with the issues and
the submissions before them that the
Payment Act requires, then they will have
fallen into jurisdictional error because they
will not have done the very thing that
s 88(2) requires them to do.
(c) the valid exercise of the adjudicator’s jurisdiction is
conditioned on the adjudicator having arrived at their
conclusion by a process which does not involve
consideration of the matter set out in s 88(3)(b),
being those matters which the adjudicator is required
to ignore;
(d) failure to provide written reasons for the decision in
compliance with s 88(5)(b) is a jurisdictional error;
(e) a valid exercise of an adjudicator’s jurisdiction
requires the adjudicator having provided parties with
“the necessary level of procedural fairness”; and
(f) the valid exercise of the adjudicator’s jurisdiction is
conditioned on the adjudicator having made a good
-- 12 of 22 --
13
faith attempt to perform the function specified in
s 88.”
(footnotes omitted)
[44] The jurisdictional error therefore to which Bright Days points, is a failure to
consider “all submissions” within the meaning of s 88(2)(d). Specifically, Bright
Days submits that the adjudicator failed to consider any of the matters pertaining to
jurisdiction, primarily, it seems, because the adjudicator did not expressly refer to
those submissions.
[45] By its nature, an adjudication cannot and does not, refer to each and every thing that
was said in the submissions. Further, an adjudication procedure is one which is
intended to be “a quick and inexpensive interim procedure for builders to be paid
for their work”,5 occurring in the context of “brutally fast” deadlines to ensure the
prompt resolution of payment disputes.6 The question is not to be approached
solely by reference to the presence or absence of explicit statements referring
expressly to particular submissions, but should be considered in the context of the
whole of the content and tenor of the adjudication.7
[46] Here, in my view, the adjudicator having expressly considered the question of
whether he was an “eligible adjudicator” and concluded that he was, the adjudicator
demonstrated, by the content and tenor of his reasons, that he had considered the
question of eligibility. In those circumstances, he did not fail to take account of the
submission, not expressly referred to, that he was in fact ineligible.
[47] Even were that not so, the adjudicator’s alleged failure to comply with s 88(2)(d)
was not material in the sense that there was not a realistic possibility that a different
decision could have been made because he would have had to conclude (as I have
above), that Mr Trattler’s email of 2 November was not a “decision”, and therefore
that he, the second adjudicator, had to decide the matter.
[48] That sub-ground is not made out.
[49] It is convenient to deal with the second and third sub-ground together. That is
particularly so as the oral argument was developed quite differently to the written
outline.
[50] Here, the alleged failure to consider was in respect of submissions made by Bright
Days about a payment which Bright Days had made to ATG after its Payment
Schedule had been served, but before the adjudicator issued the adjudication
decision, and thereby failed to comply with s 88(2)(d) of the Act. In the written
outline, this was described as:
“40. The payment of $719,435.45 on 1 November 2023 was not included in
ATG’s adjudication application (dated 19 October 2023), and ATG did
not bring the payment to the attention of the Adjudicator during the
course of the adjudication which led to the Impugned Decision.”
[51] The relevant detail of the Payment Schedule is set out at [62(b)] below.
5 Lendlease Building Pty Ltd v BCF Airport Systems Pty Ltd & Ors [2024] QSC 164 at [103].
6 Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd (2018) 264 CLR 1 at 17.
7 Shellbridge Pty Ltd v Rider Hunt Sydney Pty Ltd [2005] NSWSC 1152 at [20].
-- 13 of 22 --
14
[52] After the Payment Schedule, but as part of its adjudication response, Bright Days
identified that on 1 November 2023, it paid the amount of $719,435.45 which it
submitted to the adjudicator was payment in full for the works in the Payment
Claim.
[53] The $719,435.45 payment therefore was made, approximately, two weeks after the
Payment Schedule, but well before ATG requested the second adjudication.
[54] Bright Days submits that the second adjudicator ought to have taken the payment
into account, noting that the following post-dated the payment:
(a) the first adjudicator determined on 2 November 2023 that he did not intend to
issue a decision;
(b) on 7 December 2023, ATG requested the Registrar refer the original
application to another adjudicator;
(c) on 13 December 2023, the second adjudicator accepted the referral;
(d) on 19 December 2023, ATG provided the original adjudication application to
the second adjudicator;
(e) on 20 December 2023, Bright Days served its adjudication response.
[55] Bright Days submits that s 88(1)(a) of the Act requires an adjudicator “to
decide…the amount of the progress payment, if any, to be paid…” and as such must
take into account payments which have been made even if they post-date the
Payment Schedule. Bright Days relies upon a decision of the Western Australian
Supreme Court of Duro Felguera Australia Pty Ltd v Samsung C&T Corporation8
to support the contention that an adjudicator has a statutory obligation to consider
what amount should be paid at the time of the decision, and that this requires the
ascertainment of the extent of that liability by way of credit or other offsetting “at
the date of [the]…determination”.9 In particular, at [37] Martin CJ said:
“[37] … because the question which must be determined by the
adjudicator is the question of whether any party to the
payment dispute is liable to make a payment, the
adjudicator is required to ascertain that liability as at the
date of his or her determination. To give an obvious
example, if the respondent had paid an amount to the
claimant after the application for adjudication had been
lodged, clearly an adjudicator would be required to take
that payment into account in making his or her
determination ...”
(footnotes omitted)
[56] ATG submits that the Construction Contracts Act 2004 (WA) being considered by
Martin CJ in Duro’s case is materially different to the Queensland legislation under
consideration here. Importantly, ATG submits that the Western Australian
legislation contains no concept of a “reference date” as exists in the Queensland
legislation. Rather, the concept of a payment dispute in the Western Australian
8 (2018) 52 WAR 323.
9 Ibid at [37].
-- 14 of 22 --
15
legislation is a much broader concept than that of a payment claim in the
Queensland Act. ATG contends that Duro’s case is distinguishable and of little
assistance in determining the proper interpretation of s 88(1)(a) of the Act.
[57] ATG urges that the court follow the decision in Chevron where a similar argument
was raised in relation to payments which post-dated both the Payment Claim and
the Payment Schedule. ATG urges that I adopt the same approach as I did in that
case at paragraphs [52] to [62] where I held (ATG’s underlining added):10
“[52] Chevron submits that s 88(1) of the Payment Act provides
that the adjudicator is to decide the amount of the progress
payment, if any, to be paid by the respondent to the
claimant, which necessarily requires the adjudicator to
consider not just the construction work to which the
payment claim relates, but also whether any of the amounts
claimed have been discharged, either by payments made or
by operation of statute. Chevron submits that means the
adjudicator should have deducted from the adjudicated
amount both the Past Payments and the Subsequent
Payments.
[53] Chevron emphasises the words “to be paid” in s 88(1)(a).
In deciding the adjudicated amount “to be paid” pursuant to
s 88, Chevron submits that it is “axiomatic” that there must
be “reconciliation” by the adjudicator of the amount
claimed against the amounts known to have been paid in
respect of the amount claimed.
...
[55] I do not accept that construction of s 88(1) for the
following reasons.
[56] First, pursuant to s 88(1)(a), the adjudicator is to decide
“the amount” of the progress payment to be paid; that is the
adjudicated amount. The adjudicated amount is linked to
the payment claim (pursuant to s 68), and the payment
schedule (pursuant to s 69) which responds to the payment
claim. By s 68, the amount is expressly linked to the
identified “construction work” or “related goods and
services” to which the progress claim relates. Those are
each defined terms under the Payment Act. The
adjudication therefore is in respect of the work which has
been done or is claimed to be done under the payment
claim.
...
[58] Second, Chevron’s construction reads into s 88(1)(a) words
which do not appear there. Chevron contends that s 88
requires a determination of how much of the claimed
10 Chevron Park Pty Ltd v Groupline Constructions Pty Ltd & Ors [2024] QSC 202 at [52]-[53], [55]-
[56], [58]-[62].
-- 15 of 22 --
16
amount “is remaining to be paid at the date of the
decision”. No such words appear in, or can be read into, s
88(1).
[59] To the extent that the section identifies the date on which
any amount became or becomes payable, s 88(1)(b)
identifies that the adjudicator must decide that date; but the
date is identified by reference to other provisions of the
Act. Specifically, s 67 provides the definition of a
“reference date” for a construction contract, which means a
date stated in, or worked out under, the contract as the date
on which a claim for a progress payment may be made for
construction work carried out, or related goods and services
supplied under the contract. PC19 was concerned with a
reference date of 28 December 2023. The date was not in
dispute. The date was not the date the adjudicator made his
decision (6 June 2024) as submitted by Chevron, nor could
it be having regard to the mandatory considerations to
which the adjudicator must have turned his mind pursuant
to s 88(2).
[60] Third, the Subsequent Payments which Chevron contends
ought to have been taken into account by the adjudicator
post-dated the reference date. Nothing on a fair reading of
s 88 suggests that the adjudicator ought to take into account
events which post-dated the date to which the adjudicator
was required to turn his mind, even if they were the subject
of submissions.
[61] Fourth, it further follows that the adjudicator’s decision
cannot have regard to the Subsequent Payments when the
terms of s 88(3) are considered. That is because the
adjudication response which is provided by a respondent
must not include any new reasons for withholding payment
that were not included in the payment schedule given to the
claimant. As much was made clear by Bond J in Acciona
where his Honour described that the legislative intention
was clear that there were certain matters which the
adjudicator “must not” consider because the respondent
was prohibited from raising them.
[62] It follows that Chevron was not entitled to include
reference to reasons which arose after the date upon which
it delivered its payment schedule, which was 31 January
2024. In circumstances where none of the Subsequent
Payments were made until February 2024, Chevron could
not properly have adduced that evidence in any event.”
(footnotes omitted)
[58] ATG urges that this is a proper construction of s 88(1)(a), because what the
adjudicator is doing is valuing the construction work done under a Payment Claim
as at the reference date. The adjudicator is not determining a party’s residual
-- 16 of 22 --
17
liability to another at the time of the adjudication decision. Acknowledging that
Chevron was decided without any party having referred the court to Duro’s case,
ATG submits it would not have made any different to the conclusion.
[59] In contrast, Bright Days submits that what the adjudicator is to decide pursuant to
s 88(1)(a) of the Act, is not the amount of the progress payment itself, but the
amount of the progress payment “to be paid” by Bright Days to ATG. Bright Days
places emphasis on those words, read in conjunction with the provisions of s 90(1)
which section applies “… if an adjudicator decides that a respondent is required to
pay an adjudicated amount” then the respondent must pay the amount on or before
the day that is five business days after the day on which the adjudicator gives a copy
of their decision to the respondent.11 But where a payment has been made, as here,
after the Payment Schedule but before the adjudicator makes his adjudication, the
adjudicator was obliged to take the payment into account in order to determine the
amount of the progress payment “to be paid” pursuant to s 88(1)(a).
[60] Here, Bright Days submits the adjudicator found there was no dispute about the
value of the work under the contract, ATG having accepted Bright Days’
assessment of the amount payable for the original scope of the work under the
contract for the purposes of the adjudication application, being $979,396.78. Bright
Days contends however, that the issue is the amount which was actually payable to
the first respondent at the date of the determination, taking into account the further
payment of $719,435.45 prior to the adjudication.
[61] Bright Days contends that it raised the issue of those payments being relevant to the
amount due in this adjudication in the following ways:
(a) the Superintendent’s certificate, pertaining to Progress Payment 22 dated 10
October 2023, which records the following “qualification”:
“The Superintendent’s assessment of Progress Claim 21 is an assessment
of this particular progress claim. It does not take into account the state
of the account between the Principal and the Contractor, and therefore
does not reflect the balance of any amounts due to be paid by the
Principal to the Contractor. As such, the amount the Principal intends to
pay for Progress Claim 21 may not align with the amount identified in
the Superintendent’s assessment. It is also noted that the Principal has a
right of set off under clauses 37.2 and 37.6 of the Contract…”
(b) in Payment Schedule 11 of 17 October 2023, Bright Days recorded:
$ 979,396.78 Approved Complete (at time of claim) $ Works Under
Contract total
-$ 24,990.38 Approved Complete (at time of claim) $ Variations total
$ 954,406.40 Sub-total Approved Complete (at time of claim) $
Works Under Contract and Variations excluding
retention and GST
$ 95,440.64 GST
11 Building Industry Fairness (Security of Payment) Act 2017 (Qld), s 90(2)(a).
-- 17 of 22 --
18
$ 1,049,847.04 Sub-total
$ 369,148.33 Bright Days Credit balance at start of month
$ 71,158.00
The scheduled amount is $71,158.00 in accordance with
the Deed of Settlement and Release dated 9 August
2023 by which the parties compromised their rights and
obligations. This amount represents the GST as
calculated by the Superintendent’s progress certificate
22, dated and sent 10 October 2023.
$ 382,235.64 Bright Days Credit balance after PPS 11
Noting that this amount includes SCR GST payments
(c) in its adjudication response of 20 December 2023, Bright Days identified:
(i) that the adjudicator (if he had jurisdiction) was to determine whether
ATG was entitled to $228,683.35 for VAR087 and $206,263.41 for
VAR088;
(ii) that Bright Days maintained that no further payment was owing for the
Payment Claim or alternatively, ATG had “been paid the full amount of
its entitlement for the works complete”;
(iii) that ATG had been paid the amount of $719,435.45 for the works
completed, specifically at paragraph [92(c)] Bright Days said:
“92. The Respondent maintains that:
…
(c) the Claimant has been paid the amount of
$719,435.45 for the works complete in
accordance with the Agreements, and
specifically the Lender’s assessment of works
as evidenced at paragraph 15 of the Johnson
Declaration;
…
93. Accordingly, the Claimant has been paid the full
extent of its contractual entitlements in respect of
the works claimed in the Payment Claim and there
is no further amount to be awarded in this
Adjudication.”
(iv) further, in the material included in the Adjudication Response, a
statutory declaration of Davin Johnson asserted that:
(A) on 1 November 2023, ATG was paid $719,435.45; and
(B) there had been overpayments made to ATG, and proof of the
particular payment of $719,435.45 was exhibited to that
declaration.
-- 18 of 22 --
19
[62] When this evidence is considered, Bright Days submits that the adjudicator had an
obligation pursuant to s 88 to consider the submissions which had been made about
the amount which was “payable” to the first respondent, giving proper regard to
Bright Days’ submissions that in fact the sum of $719,435.45 had already been paid.
[63] The crux of the submission for Bright Days is that because the Payment Schedule of
17 October 2023 asserted that Bright Days was in “credit balance after PPS 11”,
Bright Days was not precluded from referring to the subsequent payment of
$719,435.45 as it was related evidence of the asserted credit balance, even if it
meant bringing in evidence of payments which were made after the Payment
Schedule.
[64] It can be accepted that nowhere in the adjudicator’s decision does the adjudicator
refer to the submissions or the evidence to which Bright Days referred in its
adjudication response (set out at [61] above), including at the heading “Parties’
submissions”. In particular, the adjudicator did not make reference to the asserted
credit balance in the Payment Schedule as set out at [61(b)] above. But Bright Days’
asserted correlation between the stated “credit balance” of $382,235.64 as at the
date of the Payment Schedule, and the later payment of $719,435.45 remained
opaque throughout the hearing.
[65] ATG contends that the reference to the Bright Days asserted credit balance after
PPS 11 of $382,235.64 cannot be construed as a reference to a payment which had
not yet been made, and so could not be a reference to the payment of $719,435.45
which was made on 1 November 2023.
[66] Proceeding on the basis of the reasoning in Chevron’s case at [52] to [62], the core
dispute on this issue comes down to this. If the Payment Schedule of 17 October
2023 did not identify (expressly, or by inference or incorporation) the payment
which was subsequently made on 1 November 2023, then Bright Days was
precluded from relying upon that payment in the adjudication because that payment
would have constituted new reasons within the meaning of s 82(4). If, however, the
court is satisfied that that payment was in fact referred to, or somehow
foreshadowed, in the Payment Schedule, then it might be accepted that the
adjudicator wrongly ignored all the submissions relevant to that payment.
[67] The highest that Bright Days was able to put its submission was that the later
payment of $719,435.45 (which it characterised as a credit) was effectively raised in
the Payment Schedule by reference to the line which records:
“$382,235.64 – Bright Days credit balance after PPS 11”
[68] In oral submissions Bright Days accepted that there were “difficulties with that
figure”, but nevertheless maintained that because Bright Days had asserted in the
Payment Schedule that there was money owing to it, the adjudicator ought to have
dealt with that issue. If he did that, so the argument goes, he would have then had to
also consider the further payment on 1 November 2023.
[69] So far as the argument relies upon the failure to consider the payment of
$719,435,45, it must be rejected. The further payment of $719,435.45 which was
made after the Payment Schedule is factually distinct from the asserted “credit
balance”. The sum cannot be said to be an explanation of an issue raised in the
-- 19 of 22 --
20
Payment Schedule when it was not a factual matter that existed at the time of the
Payment Schedule. Bright Days’ submission in that regard really went no further
than to identify that simply because Bright Days asserted that a credit was owed to
it at the time of the Payment Schedule, any other matters going to Bright Days’
asserted credit, even those that arose much later, would be ones which would be
relevant for the adjudicator to consider. I reject that approach because:
(a) the submission demonstrates that Bright Days was seeking to rely upon new
reasons (i.e. a payment made long after the Payment Schedule) within the
meaning of s 82(4) of the Act which the adjudicator was right to ignore; and
(b) the sum of $719,435.45 was not a “credit” in the way, Bright Days seeks to
characterise it; it may have been a discharge of indebtedness for work under
the contract, but it was not a credit.
[70] It is also worth observing, that if the payment had in fact been a complete payment
of the amount stated in the Payment Claim before the adjudicator decided the
application, Bright Days ought to have asserted that it had paid the Payment Claim
and sought to withdraw from the adjudication pursuant to s 97 of the Act. That it did
not do so rather suggests the payment was something less than full payment.
[71] At the conclusion of the oral argument, Bright Days raised a further submission
which had formed no part of the written argument. The argument seemed to be that
in fact what the adjudicator had failed to consider in accordance with s 88(2) was
the asserted “credit balance” of $382,235.64 as set out in the Payment Schedule (see
[61(b)] and [67] above). I deal only briefly with this issue as it was raised, at best, in
passing by Bright Days.
[72] I accept that the adjudicator did not make any specific reference to this line item of
the Payment Schedule. A failure by an adjudicator to consider a submission will, if
material, constitute a jurisdictional error.12 However the failure to identify a
particular claim or response in reasons will not, of itself, demonstrate that the
adjudicator has failed to consider it.13 What constitutes a failure to consider all
submissions including relevant documents, is a factual question in any particular
case.
[73] Here, whilst there was a one-line reference to the “credit balance”, it did not form
the basis for any developed submissions by Bright Days before the adjudicator.
Rather, aside from the jurisdiction issue, Bright Days described the “Overview of
the Issues in Dispute”:
“27. The matters in dispute in this adjudication are:
…
(c) …whether the Claimant is entitled to payment for:
(i) the sum of $954,406.40 for works complete;
and
(ii) two disputed delay damages claims …”
12 Martinus Rail Pty Ltd v Qube RE: Services (No 2) Pty Ltd (No 2) [2024] NSWSC 1223 at [193] –
[197]; Thiess Pty Ltd v Warren Brothers Earthmoving Pty Ltd & Ors [2012] QSC 373.
13 Ceerose Pty Ltd v A-Civil Aust Pty Ltd (2023) 112 NSWLR 225 at [62].
-- 20 of 22 --
21
[74] Further, at the “Summary of the Parties’ Positions”, Bright Days submitted:
“28. The Respondent’s position can be summarised as follows:
…
(b) … the Adjudicator should value the Claimant’s
entitlement to payment in accordance with both the
D&C Contract and the Settlement Deed (the latter
varying for former), and find that no further payment
is owing to the Claimant under the D&C Contract for
this Payment Claim;
(c) further in the alternative, the Adjudicator should find
that the Claimant:
(i) has been paid the full amount of its entitlement
for the works complete; and
(ii) has no entitlement to the delay damages ...”
[75] The reference to the “full amount of its entitlement for the works complete” was
footnoted to the evidence in support of the payment of the $719,435.45, not to any
evidence in relation to the asserted “credit balance” of $382,235.64.
[76] Bright Days adjudication response does go on to identify some further submissions
in relation to the asserted “credit balance”. The following appears at pages 10 and
11 of the adjudication response:
“THE PAYMENT SCHEDULE
43. On 17 October 2023, the Respondent provided a Payment
Schedule, certifying a credit balance in favour of the
Respondent in the sum of -$382,235.64 (Payment Schedule).
…
48. The Respondent accepts that the Payment Schedule states the
amount it proposes to pay is $71,158.00 but says that amount is
not due and owing as it has been reduced by overpayments
made by the Respondent in accordance with the Settlement
Deed.
49. Further, while having no effect on any amounts to be paid to the
Claimant, the Respondent brings to the Adjudicator’s attention
a miscalculation in the credit balance recorded in the Payment
Schedule. That is, the sum of -$382,235.64 should correctly be
stated as -$32,060.02.
50. This is because the payment that the Respondent was liable to
pay of $71,158, when reduced by the previous months correct
credit balance of $103,218.02 brings the Scheduled Amount to
-$32,060.02. The Respondent concedes this deduction in the
amount it has scheduled whilst acknowledging that it has no
consequence on the amount to be paid to the Claimant in this
Adjudication which remains at Nil.”
(my underlining)
-- 21 of 22 --
22
[77] Properly understood, Bright Days was not in fact contending that the asserted credit
balance ($382,235.64), or even the corrected credit balance ($32,060.02), was a
matter which was of any consequence to the adjudication. In that factual context it
cannot be concluded that there was any jurisdictional error by the adjudicator failing
to identify the “credit balance” issue at all. Bright Days itself had acknowledged
that the “credit balance”, whatever its amount, was of “no consequence” on the
amount to be paid to ATG in this adjudication.
[78] In the circumstances the adjudicator’s failure to refer to this submission, was not a
“centrally important matter, clearly articulated and based on uncontested facts” in
the way described in Ceerose.14 Rather the adjudicator’s reasons reflect the
practical circumstances under which he was operating.15 In the circumstances,
given how the case was advanced by Bright Days16 I am satisfied that there was no
failure by the adjudicator to consider the issue in relation to the asserted “credit
balance”.
[79] The application is dismissed, with costs.
14 Ceerose Pty Ltd v A-Civil Aust Pty Ltd (2023) 112 NSWLR 225 at [69].
15 Martinus Rail Pty Ltd v Qube RE Services (No 2) Pty Ltd [2025] NSWCA 49 at [68].
16 Lendlease Building Pty Ltd v BCF Airport Systems Pty Ltd & Ors [2024] QSC 164 at [217].
-- 22 of 22 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2025/147