Downer EDI Rail Pty Ltd v DT Infrastructure Pty Ltd [2025] QSC 212
SUPREME COURT OF QUEENSLAND
CITATION: Downer EDI Rail Pty Ltd v DT Infrastructure Pty Ltd [2025]
QSC 212
PARTIES: DOWNER EDI RAIL PTY LTD
(applicant)
v
DT INFRASTRUCTURE PTY LTD
(first respondent)
CHRISTOPHER JACQUES NEL
(second respondent)
FILE NO/S: BS 1999/25
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT:
Supreme Court of Queensland at Brisbane
DELIVERED ON: 4 June 2025 (ex tempore)
DELIVERED AT: Brisbane
HEARING DATE: 4 June 2025
JUDGE: Treston J
ORDERS: 1. A declaration that by operation of s 97(1)(b) of the
Building Industry Fairness (Security of Payment) Act
2017 (Qld), adjudication application number
2833440 was taken to have been withdrawn by the
First Respondent on 15 May 2025.
2. The First Respondent is to pay the Applicant’s costs
of and incidental to the proceeding to be assessed on
the standard basis.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION –
STATUTORY REGULATION OF ENTITLEMENT TO
AND RECOVERY OF PROGRESS PAYMENTS –
ADJUDICATION OF PAYMENT CLAIMS – where the
applicant (as head contractor) and the first respondent (as
builder) are parties to a design and construct contract – where
the first respondent served a payment claim on the applicant
and the applicant subsequently served a payment schedule of
an amount approximately $8.7 million less – where the first
respondent applied for adjudication in respect of its payment
claim – where the amount in issue was a variation claim of
$681,445.37 – where both parties accept that no submissions,
evidence, witness statements or other documents were directed
-- 1 of 10 --
2
to any other part of the payment claim, only the $681,445.37
amount – where the applicant seeks a declaration that having
paid the sum of $681,445.37 for which the adjudication
decision was sought, by operation of s 97(1)(b) of the Building
Industry Fairness (Security of Payment) Act 2017 (Qld), the
adjudication application is taken to have been withdrawn –
where the first respondent contends it is the statutory
obligation of the adjudicator pursuant to s 88, to determine
every element of the payment claim not just those aspects of
the payment claim a claimant directs the adjudicator to
determine in its submissions – where the first respondent
contends that the scope of submissions made to the adjudicator
does not impact the adjudicator’s duty to decide the entirety of
the payment claim – where the first respondent contends that
the words in s 97(1)(b) “the subject of the adjudication” refer
to the amount of the payment claim itself not particular
amounts expressly addressed in the adjudication application or
submissions in support of it – where the applicant contends for
a contextual construction of s 97(1)(b) reflecting the purpose
of the Act to provide a quick and inexpensive process for
securing payment – whether the “subject of the adjudication”
per s 97(1)(b) must be the whole of the amount stated in the
payment claim or may be some particular part of the payment
claim – whether the adjudication application can be taken to
have been withdrawn pursuant to s 97(1)(b) in circumstances
where the applicant has paid the sum for which the
adjudicator’s decision was sought but not the total payment
claim
Acts Interpretation Act 1954 (Qld), s 14A
Building Industry Fairness (Security of Payment) Act 2017
(Qld), ss 75, 79, 84, 85, 88, 97
Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW)
Pty Ltd (2005) 63 NSWLR 385
R v A2 (2019) 269 CLR 507
COUNSEL: D O’Sullivan KC with BA Reading for the applicant
JJ Baartz for the first respondent
SOLICITORS: White & Case for the applicant
CDI Lawyers for the first respondent
[1] This is an application for declarations regarding the proper construction of s 97(1)(b)
of the Building Industry Fairness (Security of Payment) Act 2017 (Qld) (the Act).
There are no issues of fact in dispute, and the second respondent (who is the
adjudicator to an adjudication application) does not appear and agrees to abide the
order of the court.
-- 2 of 10 --
3
[2] The applicant, Downer EDI Rail Pty Ltd (Downer), as a contractor, entered into a
design and construct contract with the first respondent, DT Infrastructure Pty Ltd
(DTI), as a builder. The contract relates to the design and construction of a train
maintenance and stabling facility at Ormeau. The contract was entered into on 29
June 2023.
[3] On 24 February 2025, DTI served a payment claim on Downer under the Act for just
over $22 million excluding GST. This will be referred to throughout as either “the
payment claim” or “payment claim 21”. On 17 March 2025, Downer served a
payment schedule, referred to throughout as either “the payment schedule” or
“payment schedule number 21”. Downer certified the sum in respect of payment
schedule 21 to be a sum of approximately $13.5 million excluding GST. The
difference therefore between the claimed amount in the payment claim and the
payment schedule is some $8.7 million. Part of that sum of $8.7 million included a
sum for variation claims of $681,445.37.
[4] On 30 April 2025, DTI applied for adjudication said to be in respect of payment claim
21.
[5] On 1 May 2025, DTI served on Downer a copy of its adjudication application,
submissions and other material in support of the application. I will return to those
submissions shortly.
[6] The second respondent was appointed and accepted appointment as adjudicator on 12
May 2025.
[7] To give the argument which follows some context, I refer to some parts of the
submissions made by DTI in support of its adjudication application. I set it out at
some length because the factual matrix is important to the outcome of the case. First,
in its submissions in support of its adjudication application at paragraph 13 (which
appears at page 111 of the affidavit of Mr Pfeiffer), DTI identified that the “decision
sought” in the adjudication application was that the adjudicator should determine
those matters which were set out at paragraph 13. That paragraph reads:
“13. For the reasons elaborated upon later in these submissions, the
Adjudicator should determine that:
(a) Downer pay DTI the amount of $681,445.37 (ex GST);
(b) Downer pay DTI interest on that amount at the rate of 14.09%
from 31 March 2025 (being the due date for payment); and
(c) under section 96(1) of the Act:
(i) Downer is liable for 100% of the Adjudicator’s fees; and
(ii) Downer is to reimburse DTI for 100% of the fee payable
under section 79(2)(d) of the Act.”
[8] Second, at paragraph 49 of the application, DTI recorded “DTI pursues two variation
claims in the Adjudication Application”. It identified the first variation being number
41 in respect of which DTI claimed a sum of $678,570.37 in the payment claim, and
secondly, variation number 53 for which DTI claimed a sum of $2,875 in the payment
claim. The claim went on to identify at paragraph 50 that, “[t]hough the amounts
-- 3 of 10 --
4
claimed by DTI in the Payment Claim for these two variations are relatively small,
these are major variations to the Contract and will ultimately have significant time
and cost consequences for DTI.”
[9] At paragraphs 51 through to 61, DTI went on to provide a high-level summary of the
dispute in relation to variations numbered 41 and 53. Next, at paragraph 62 of its
application, DTI recorded “[i]n this Adjudication Application, DTI pursues a total of
$681,445.37”, relating to variations 41 and 53. There is no reference in the summary
of the dispute section of the adjudication application to any other part of the
outstanding $8.7 million under payment claim 21.
[10] Next, turning to paragraph 156 of the adjudication application, DTI provided an
overview of the claim in respect of variation number 41 and again identified the
particulars which it claimed in respect of that variation. From paragraph 177, DTI
outlined its position as to why it was contractually entitled to the variation, being
variation 41. From paragraph 259 onwards, DTI set out why the adjudicator should
determine the quantum of variation 41 in the amount sought by DTI. DTI then
reached its conclusions in relation to that particular variation and identified at
paragraph 269 that:
“269. The Adjudicator should determine that:
(a) DTI is entitled to a Variation under the Contract in order to
comply with the amended requirements of BPIC 2024; and
(b) Downer is liable to pay DTI the amount of $678,570.37 for the
extra-over costs incurred by DTI relating to the increase in the
hourly rate for workers who performed works in the months of
April 2024 to July 2024.”
[11] Commencing then at paragraph 270, DTI identified its claim in respect of variation
number 53. It specifically identified that it claimed the sum of $2,875 in respect of
that variation. It identified that variation 53 was associated with the solar works for
the project. From paragraph 275, DTI set out its position as to why it was
contractually entitled to the variation for the solar works set out in variation number
53. Commencing from paragraph 359, DTI provided submissions as to the quantum
relevant to variation number 53. At paragraph 362, DTI set out “[f]or the purposes
of this Adjudication Application, DTI only asks the Adjudicator to determine the
elements in subparagraph (a) of the definition of Variation Effects”, and then went on
to describe the certain matters that it required, that it described as variations in respect
of the solar works. At paragraph 369, DTI submitted:
“369. The Adjudicator should determine that:
(a) DTI is entitled to a Variation under the Contract in respect of
the Solar Works; and
(b) Downer is liable to pay DTI the amount of $2,875 for the
variation work performed by DTI and claimed in the Payment
Claim.”
[12] Finally, at paragraph 384, in its conclusion to its adjudication application, DTI
submitted that DTI sought a determination from the adjudicator in terms that merit
-- 4 of 10 --
5
those under paragraph 13 which I earlier described under the heading “decision
sought”.
[13] Although DTI’s adjudication application was supported by extensive evidence
running to several hundreds of payments, pages of schedules, witness statements and
similar material, both parties accepted that no submissions, evidence, witness
statements or other documents were directed at any other part of the approximately
$8.7 million claimed by DTI in payment claim 21 that Downer declined to certify as
being payable. The claim, submissions, witness statements and other documents were
limited to the two identified variation claims, 41 and 53. As such, the only decision
which was sought by the adjudication application pertained to those two variations in
the sum of $681,445.37.
[14] DTI also accepts that the evidence that it provided to the adjudicator did not attempt
to identify the work for which the $8.7 million was claimed but not paid, nor what
was said to be the basis for an entitlement to the payment other than that which was
contained in the payment claim. It can be accepted therefore, that the adjudicator was
not asked to make any determination that Downer pay any part of the approximately
$8.7 million claimed but not certified, that fell outside the scope of the variations that
comprise the amount for which the decision was sought.
[15] Having been served with DTI’s adjudication application, submissions and other
evidence, Downer paid the amount identified in paragraph 13 of the adjudication
application, being the amount of $681,445.37. DTI does not dispute that Downer has
paid the amount in full, including the interest in accordance with its request at
paragraph 13 under the heading “decision sought.” The adjudicator has not yet made
a decision, and no decision is in fact due until the 11th of June 2025. By this
proceeding, Downer seeks a declaration that, by having paid the sum for which the
decision was sought plus the interest, the provisions of s 97 of the Act are operative.
Section 97 of the Act provides:
“97 Withdrawing from adjudication
(1) An adjudication application─
(a) is withdrawn if the claimant has given a
written notice of discontinuation to the
adjudicator and respondent; or
(b) is taken to have been withdrawn if the
respondent has, before an adjudicator has
decided the application, paid the claimant the
amount stated in the payment claim the
subject of the adjudication application.
Note─
Despite the withdrawal of an adjudication application an
adjudicator is still entitled to be paid fees for
considering the application, see section 95.
(2) If subsection (1)(b) applies, the claimant must as soon
as practicable inform the adjudicator and the
-- 5 of 10 --
6
respondent that the adjudication application has been
withdrawn because of payment.
(3) As soon as practicable after an adjudication
application is withdrawn, the claimant must inform the
registrar that the application has been withdrawn and
whether it was withdrawn as mentioned in subsection
(1)(a) or (b).
Maximum penalty—20 penalty units.”
[16] The court is therefore required to construe the words of s 97, but in particular,
subparagraph (1)(b), in order to decide whether the adjudication application “is taken
to have been withdrawn” within the meaning of the subsection. That is in fact the
relief which the applicant seeks by paragraph 1 of the originating application, being
a declaration that, by operation of s 97(1)(b) of the Act, adjudication application
number 2833440 was taken to have been withdrawn by the first respondent on 15
May 2025.
[17] The parties also agree as to the principles of construction that guide me. Primarily,
that the words of the section must be given their ordinary meaning, and that meaning
is to be taken from the text, purpose and context of the legislation, including the
surrounding provisions, what can be drawn from other aspects of the statute and the
statute as a whole.1
[18] Pursuant to s 79 of the Act, a claimant may apply for an adjudication of a payment
claim if the amount stated in the payment schedule which is given in response to a
payment claim, is less than the amount stated in the payment claim. By s 88(1)(a),
the adjudicator is then required to decide the amount of the progress payment, if any,
to be paid by the respondent to the claimant. That is referred to as “the adjudicated
amount”. Section 88(2) then identifies the matters which the adjudicator is obliged
to have consideration to in deciding the adjudication application to which the
application relates, together with all the submissions and other documents properly
made by the claimant in support of the claim, the payment schedule, submissions and
relevant documents as well as the provisions of the Act. By s 88(3), the adjudicator
must not consider an adjudication response that was not given within the time
required under s 83, or a reason included in the adjudication response to the
adjudication application if the reason is prohibited from being included in the
response under s 82.
[19] At the core of the argument before me today is the question as to whether the
adjudication application is taken to have been withdrawn within the meaning of
s 97(1)(b), in circumstances where the amount paid by Downer was only in respect
of the variations in issue. Or, whether the section is only triggered if Downer pays the
total amount of the payment claim, being the disputed sum of $8.7 million.
[20] Downer submits that what s 97(1)(b) is referring to when it speaks of paying “the
amount stated in the payment claim the subject of the adjudication application” is as
the words say, the amount stated in the payment claim that is the subject of the
adjudication. The emphasis here is on the words, the payment claim that is “the
1 See R v A2 (2019) 269 CLR 507 at [32] – [37] and Acts Interpretation Act 1954 (Qld), s 14A(1).
-- 6 of 10 --
7
subject of the adjudication”. If the subject of the adjudication application is the whole
of the amount stated in the payment claim, then the whole of that amount must be
paid for the application to be taken to be withdrawn. In this case, that would be the
sum of some $8.7 million.
[21] However, if the subject of the adjudication application is some particular part of the
payment claim, and that part is the part which is paid, then upon the payment of that
part is the application taken to be withdrawn? DTI submits that it is the statutory
obligation of the adjudicator to decide every element of the payment claim, not just
those aspects of the payment claim which it directed that the adjudicator “should
determine” in its submissions. DTI’s counsel accepted that this was a complex task,
there being hundreds of line items to consider but, notwithstanding the onerous nature
of the task, pointed to what was described as the adjudicator’s statutory obligation to
do precisely that. In particular, DTI pointed to the adjudicator’s statutory obligations
set out in s 88 to consider all the matters set out therein, specifically those the
adjudicator is obliged to consider under s 88(2). But submitted that the scope of the
submissions made by DTI to the adjudicator did not impact upon the scope of the
adjudicator’s duty to decide the entirety of the disputed payment claim.
[22] DTI further submits that, where a claimant decides to only raise certain claims in an
adjudication application, no concession is thereby made by the claimant as to the
balance of the claims where there is a difference between the claim and the scheduled
amount. Put another way, DTI submits that the manner in which the claimant puts its
adjudication application does not derogate from the obligations of the adjudicator to
determine the amount of the statutory progress payment.
[23] DTI refers in particular to Coordinated Construction Co Pty Ltd v JM Hargreaves
(NSW) Pty Ltd,2 where Hodgson JA describes that the task of an adjudicator is to
determine the amount of the progress payment to be paid by the respondent to the
claimant, and that requires a determination on the material available to the adjudicator
of the amount that is properly payable. His Honour there referred to the fact that the
adjudicator is to consider only the provisions of the Act, the contract, the payment
claim and the claimant’s submissions duly made, as well as the payment schedule and
submissions made, but that did not mean that consideration of the provisions of the
Act and the contract and the merits of the claim are “limited to issues actually raised
by submissions duly made”.3 Assuming that that statement should be accepted as
correct, it does not support the proposition that, where the only issues to be decided
are ones which have been so clearly identified as they have been here and, by
inference, all other aspects of the claim are not being pursued, the adjudicator is bound
to consider and decide facts which are not in dispute on the face of the application.
[24] DTI submits that the words in s 97(1)(b) “the subject of the adjudication” refer to the
amount of the payment claim itself and not just particular amounts expressly
addressed in the adjudication application or the submissions in support of it. That
construction, DTI submits, is consistent with the relevant purpose of the Act, which
is for the adjudicator to decide the amount of the progress payment to be made. It
follows, DTI submits, that for the adjudication to be “taken to be withdrawn” and the
adjudicator discharged from the function to determine the progress payment, the
whole of the payment claim must be paid, or at least the whole of the amount not
2 (2005) 63 NSWLR 385 at [52].
3 Ibid.
-- 7 of 10 --
8
otherwise expressly abandoned by the claimant. Further, DTI submits that, if the
operation of s 97 were tied merely to the issues addressed by the claimant in the
adjudication application, then the words “stated in the payment claim” as they appear
in s 97(1)(b) would not need to appear in the section.
[25] I do not accept DTI’s construction of s 97(1)(b). Firstly, one starts with the words of
the section. The section is designed so as to facilitate two ways in which an
application might be withdrawn. The first, is where the claimant gives written notice
that it intends to discontinue the application. That is found in subparagraph (a). The
second way in subparagraph (b), is where the application “is taken to have been
withdrawn”. That means that the application is not in fact withdrawn in accordance
with subparagraph (a), but a payment has been made of the disputed sum such that
there is, on the face of the application, no longer a dispute. The inference then, that
it is taken to be withdrawn arises when the application or, relevantly, as here, part of
it, is taken to have been withdrawn because there has otherwise been satisfaction of
the amount in dispute.
[26] DTI accepts that an application could be taken to have been withdrawn if it was
expressly withdrawn in the submissions for example. If, for example, under the
existing paragraph 13 for the “decision sought”, there had been a further subparagraph
identifying that DTI did not require any other parts of the payment claim to be
adjudicated, it would expressly be taken to be withdrawn. But DTI does not accept
that an implication or inference can arise, or be taken to arise, from submissions which
would cause the adjudication to be withdrawn other than expressly. Further, DTI
submits that there can be no inference drawn from the submissions by the use of DTI’s
language that the adjudicator “should determine” variations 41 and 53, that there had
in fact been an abandonment of the other parts of the payment claim.
[27] DTI’s construction must be rejected because express withdrawal is what is
contemplated by subparagraph (a). Subparagraph (b) must by necessity be directed
towards a different circumstance. But the real argument in terms of construction here
is the emphasis to be placed on the words, “the amount stated in the payment claim
the subject of the adjudication application.” DTI’s construction, in my view,
effectively gives no work to do to the words, “the subject of the adjudication
application.” On DTI’s construction, the clause could have finished after the words,
“stated in the payment claim”.
[28] DTI then points to the explanatory memorandum which, in respect of cl 97, explains
that the clause allows a claimant to withdraw an application, including where the
respondent pays the claimed amount.4 DTI says the phrase “the claimed amount” is
a defined term under the Act. That is correct because the phrase “the claimed amount”
is defined in s 68(1)(b). The definition of “the claimed amount” would, in the
circumstances of this claim, be the total of some $21 million identified in the payment
claim. But had the drafters of s 97(1)(b) wished to use the phrase “the claimed
amount”, thereby invoking that defined term, they could have done so. The
legislation does not use that terminology. It uses a different terminology contained
in the subsection. That the legislature used a different set of words to achieve a
different meaning seems clear to me.
4 Explanatory Note, Building Industry Fairness (Security of Payment) Bill 2017 (Qld) at 31.
-- 8 of 10 --
9
[29] Contrary to DTI’s submission, the explanatory memorandum does not support DTI’s
construction. Rather, in my view, it supports the construction offered by the
applicant. The addition of the words, “the subject of the adjudication application” at
the end of cl 97 directs attention towards that which is genuinely in issue in the
payment claim. In this case, limited to those matters to which DTI sought the
adjudicator should direct his determination.
[30] In my view, the section should be read in the contextual way for which Downer
contends where the words “the subject of the adjudication” are linked to the words of
the amount. The contextual reading must be the correct one, in my view, because,
firstly, the process is intended to be one which is fast and efficient. The DTI
construction does not support this intention because it means things need to be
decided by the adjudicator that are not genuinely, or in fact at all, in issue. Secondly,
the process is intended to identify those matters genuinely in dispute, not those which
are not.
[31] There are other aspects of the legislation which support the applicant’s contextual
approach to interpretation, and they include but are not limited to the following. First,
s 75(5), by which the legislation permits a later payment claim to bring forward those
parts of payment claim 21 that remain unpaid. This means that the currently unpaid
part of payment claim 21 is not abandoned. It can properly be dealt with by a
subsequent payment claim.
[32] Second, s 79(3) and (4), provide that the adjudication application may be
accompanied by submissions relevant to the application and those submissions will
be given to the respondent within four business days after making the application.
The purpose of giving the submissions which themselves narrow the matters in
dispute, is to allow the respondent to substantively respond to the actual matters in
issue. That substantive response process is consistent with the otherwise brutal
timeframes referred to in the cases under the Act, which require that the payment
claim process is dealt with quickly and efficiently. That is consistent with the purpose
and object of the Act which is to provide a quick and inexpensive interim procedure
for builders to be paid for their work.
[33] Third, ss 84 and 85, again are directed towards allowing the adjudicator to decide the
disputed amounts as quickly as possible which necessarily carries with it a
construction of the legislation that the adjudicator is not required to decide those
matters which are not genuinely in dispute.
[34] Fourth, the provisions of s 88(2) which set out the matters which the adjudicator must
consider includes at subparagraphs (c) and (d), the submissions which the parties
make. It would be an onerous construction of the legislation if the adjudicator was
required to consider matters pertaining, in this case, to some $8.7 million worth of
claims where the submissions on both sides had been confined to $681,445.37 worth.
[35] I therefore reject the respondent’s construction and am prepared to make the
declaration sought at paragraph 1 of the originating application.
[36] As a matter of completeness, however, I ought to deal with DTI’s alternative
argument being that, if I am against DTI’s construction, then I ought to consider the
matters which are contained in the respondent’s submissions at paragraphs 34 to 39.
The heart of that argument seems to be that, when Downer paid the amount which it
-- 9 of 10 --
10
did in respect of variations 41 and 53, its correspondence of 15 May 2025 recorded
that the payment was made pursuant to cl 32.6(a) of the building contract, being on
account without admission of liability and without prejudice to the contractor’s
position in relation to those two stated variations.
[37] In my view, this argument can be dealt with quite quickly. I do not take the letter of
15 May 2025 to be other than recording that the payment which is being made, is
being made pursuant to the identified clause of the contract. I accept the applicant’s
characterisation, that this is an entirely unremarkable procedure to pay an amount in
accordance with a contractual obligation to do so. I understand DTI’s submission to
be that, if the payment is not a payment made under the adjudication application, then
s 97(1)(b) of the Act is not engaged. It can be accepted that the payment which has
been made by the applicant in this case is not a payment under the adjudication
application and therefore does not attract the character of the binding amount which
might otherwise be revisited at a later time, as other payments under the contract
might be. That is because, there is in fact no adjudication of the sum involved. The
whole point of the payment, it seems to me, is that the adjudication application is
therefore taken to be withdrawn, and the payment could not be other than a payment
made pursuant to the contractual terms.
[38] I therefore make the following orders:
1. A declaration that by operation of s 97(1)(b) of the Building Industry Fairness
(Security of Payment) Act 2017 (Qld), adjudication application number
2833440 was taken to have been withdrawn by the First Respondent on 15 May
2025.
2. The First Respondent is to pay the Applicant’s costs of and incidental to the
proceeding to be assessed on the standard basis.
-- 10 of 10 --