Dixonbuild Pty Ltd v Queensland Building and Construction Commission & Anor [2025] QCAT 568
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Dixonbuild Pty Ltd v Queensland Building and
Construction Commission & Anor [2025] QCAT 568
PARTIES: DIXONBUILD PTY LTD
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(First respondent)
KIRSTY-LEA SEGADE
(Second respondent)
APPLICATION NO/S: GAR604-23
MATTER TYPE: General administrative review matters
DELIVERED ON: 22 December 2025
HEARING DATE: 16 May 2025
HEARD AT: Brisbane
DECISION OF: Member Paratz AM
ORDERS: The decision of the Queensland Building and
Construction Commission to issue a Direction to Rectify
issued on 15 July 2024 is set aside.
CATCHWORDS: ADMINISTRATIVE LAW – ADMINISTRATIVE
TRIBUNALS – QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL – whether building work
was defective – where the description of the location of the
alleged defect was unclear and confused – whether a
Direction to Rectify can be given without a complaint
having been lodged with the Queensland Building and
Construction Commission – whether a building inspector
can rely on their expertise to assess a defect in the absence
of photographs or measurements – whether it was fair to
issue a Direction to Rectify
Queensland Building and Construction Commission Act
1991 (Qld), s 72(3)
Shilleto v Queensland Building and Construction
Commission & Ors [2024] QCAT 137
APPEARANCES &
REPRESENTATION:
Applicant: Mr. C. Matthews of Counsel, instructed by CDI Lawyers
-- 1 of 18 --
2
Respondent: Ms. A. Hewish of HWL Ebsworth Lawyers.
REASONS FOR DECISION
[1] The Queensland Building and Construction Commission (‘QBCC’) made a decision
on 15 July 2024 (in the course of reconsidering its earlier decision dated 8 August
2023) to issue a Direction to Rectify to Dixonbuild Pty Ltd (‘the Builder’) in respect
of work conducted on a home at Cedar Vale in the State of Queensland.
[2] The Builder filed an Application to review a decision in the Tribunal on 29 August
2023 as to the decision made on 15 July 2024.
[3] I heard the matter on 16 May 2025.
[4] Kirsty-Lea Seagade (‘the Owner’), was a respondent in the matter. She did not attend
the hearing. I was satisfied that she had been given proper notice of the hearing, and
that it was appropriate to proceed in her absence.
[5] At the end of the hearing, I gave directions for the filing of Closing Submissions.
[6] The Builder filed its closing submissions on 11 June 2025 (37 pages). The QBCC
filed its closing submissions in Response on 15 July 2025 (39 pages). The builder then
filed its closing submissions in Reply on 6 August 2025 (19 pages).
[7] These are my Reasons in this matter.
The Direction to Rectify
[8] The QBCC issued a Direction to Rectify and/or Complete Work Number 0111112 on
8 August 2023. The Direction to Rectify related to three items of defective work as
follows:
1 QBCC finds the licensee is responsible for internal corner of the walk-in
robe which is not a level 4 finish per AS 2589-1 Gypsum Linings and
deviates by more than 4mm in the vertical and is unsatisfactory.
Pertains to item 2 of the complaint form.
2 QBCC finds the licensee is responsible for the margin between the
architrave and bedroom 2 door and the hallway wall which exceeds
tolerance and is unsatisfactory.
This pertains to item 5 of the complaint form.
3 QBCC finds the licensee is responsible for the installation of the bedroom
doors off the hallway whose clearances exceed 4 mm and are unsatisfactory.
Pertains to item 21 of the complaint form.
[9] On 24 May 2024 the Tribunal invited the Commission to reconsider its original
Direction to Rectify.
[10] On 15 July 2024 the Commission made a new decision not to issue a Direction to
Rectify in respect of complaint items 2 and 21, and to issue a Direction to Rectify in
respect of complaint item 5 only.
[11] The only matter before the Tribunal in this application to review therefore is Item 2
of the original Direction to Rectify, which relates to Item 5 of the complaint form.
-- 2 of 18 --
3
History
[12] The Owner entered into a domestic construction contract with the builder to construct
a dwelling at the property on 4 November 2020.1 Work under the contract commenced
around 29 January 2021.2 The work reached practical completion on 13 January
2022.3
[13] On 19 November 2022 the owners submitted an online complaint to the QBCC
advising of a number of complaints, including the complaint which is the subject of
this application.
[14] Mr Colin Rendall, a QBCC inspector, conducted an inspection of the premises on 1
August 2023 and produced an Initial Inspection Report.4 His report provided as to
complaint number 5 as follows:
Description of defect as per complaint form – poor workmanship to architrave
to hallway
Location of defect – hallway
Date claimant became aware of defect – 1/03/2022
On the day of the visual inspection, the claimant/representative directed the
inspector to the item of complaint.
The inspector found:
1. The margin between the bedroom 2 door and the wall on the hall
side is out of alignment.
2. The variation in margin exceeds 4mm over 2 metres.
3. The defect can be seen from the normal viewing position.
QBCC Reasoning:
1) QBCC standards and tolerance guide 10-8 for verticality states:
10.8 Verticality or plumbness of internal and external wall
surfaces.
Within the first 12 months from the completion of the work, all
surfaces are defective if they deviate from vertical by more than
4mm within any 2m height. For tolerances and masonry refer to
Table 4.4 in this Guide.
Next action: Direction to Rectify
QBCC decision: QBCC finds the licensee is responsible for the margin between
the architrave to bedroom 2 door and the hallway wall which exceeds tolerance
and is unsatisfactory.
Pertains to item 5 of the complaint form.
[15] There were varying descriptions made as to the location of the alleged defect
throughout the history of this matter. A copy of the floor plan was filed as below:5
1 Domestic Construction Contract, QBCC Statement of Reasons (‘SOR’) p 39.
2 Ibid SOR [3.1], p 21.
3 Ibid SOR [3.9,] p 22.
4 Ibid SOR-25, p 423.
5 Ibid SOR-1, p 133.
-- 3 of 18 --
4
[16] The owner in the original complaint described the location as being in the ‘hallway’.
[17] In his evidence at the hearing, Mr West, the Quality Assurance Assessor for the
builder, who attended the inspection conducted by Mr Rendall, said that the Direction
to Rectify which was given did not relate to the defect referred to by the owner in his
complaint to the QBCC, but was only raised in the course of the inspection, as
follows:6
Ms Hewish: But isn’t it correct to say that the owners identified that defect to
Mr Rendall on the day of the inspection?
Mr West: No
Ms Hewish: They didn’t?
Mr West: No, they – what happened was that he just would randomly point
out something. So we went through the whole thing, we’re on our
way out and he just randomly said ‘well, what about that’ and
that was just brought up like that, so.
Ms Hewish: So you weren’t going through it in order of…?
Mr West: This wasn’t on the list. There is – on the list of defects that we
went through, we completed all that and as we were leaving the
owner just said ‘Well, what about that doorway?’. So it wasn’t
on the list. We had no recollection or any evidence of that being
an issue to him. He just brought it up at that particular time. We
did a visual inspection and believe that there was no further
action needed. I reported to management and they – they sorted
it from there.
Ms Hewish: So is your position that this item that we are discussing wasn’t
on the complaint?
6 Transcript 1-22, Lines 5 to 48.
-- 4 of 18 --
5
Mr West: It was never on the complaint.
Ms Hewish: But doesn’t it relate to complete item 5, with the defect being
identified in the hallway and bedroom door 2?
Mr West: Yeah, it was a completely different bedroom. So he – he
previously complained about some gaps between the wall and the
architraves, which were completed and fixed, but this was not on
any of the – um, any evidence for us.
Ms Hewish: So you disagree this was not – have you seen a copy of the
complaint form?
Mr West: Yep
Ms Hewish: You’ve seen a copy of the complaint form – the – have you seen
a copy of the complaint form that the owners submitted to
QBCC?
Mr West: Yes
Ms Hewish: Yep
Mr West: Yeah, I disagree, because it wasn’t – it wasn’t bedroom 2, yeah.
[18] I clarified the identification of the location of the alleged defect with Mr West, who
said that it related to bedroom 4, which was on the other side of the corridor, as
follows:7
Member: Okay. All right. Now, which is the bedroom that you say the
original complaint was about?
Mr West: Bedroom 2 on the right-hand side.
Member: Using the numbers on the plan?
Mr West: So bedroom 2 listed on the plan here is on the – obviously looking
at the – –
Member: Bedroom 2. So that’s one of those three bedrooms that adjoin
each other?
Mr West: Correct.
Member: Alright. Now which is the bedroom that you say Mr Rendall was
referring to?
Mr West: Bedroom 4
Member: … That the homeowner pointed out as you were leaving?
Mr West: Bedroom 4.
Member: Okay. So that’s basically opposite, on the other side of the
corridor?
Mr West: Correct
7 Ibid 1-23, Lines 29 to 45.
-- 5 of 18 --
6
[19] In his evidence at the hearing, Mr Rendall, the building inspector for the Commission,
said that he relied on the bedroom number given by the owners, as follows:8
Mr Matthews: Now, just for clarification, in your statement you say – and I
don’t – correct me if I’m wrong, but you say there’s been a
suggestion by the builder that in fact the complaint was raised
about bedroom 4, but bedroom 2 as identified in the plans,
this door, was the subject of the complaint?
Mr Rendall: No, I didn’t say that.
Mr Matthews: No? Okay. What did you say?
Mr Rendall: Alright. The homeowner identified the room as bedroom 2.
Mr Matthews: Okay?
Mr Rendall: Right? It’s their house; right? You might have a room – I’ve
had houses where they’ve identified the room as a prayer
room. On the plan it’s a totally different thing. They identified
it as bedroom 2, right? My report identifies it as bedroom 2
because it corresponds with their complaint item as bedroom
2; right? The representative from the builder was there and
did not challenge this; right? A request was made to the
homeowner to get a set of plans at the beginning of this file,
and they were never, ever issued to us; right? And as a matter
of fact we received no plan from either party.
Mr Matthews: Which – I mean, I’m not, again, I’m not trying to – I’m not
trying to wed you in to either of these. I just want to know
which door was – based on these photographs door/wall –
door architrave and wall was the subject of the complaint
during the inspection to which you issued the Direction to
Rectify?
Mr Rendall: Would be bedroom – the one that’s marked here as bedroom
2.
Mr Matthews: Was that the one?
Mr Rendall: That one, yes.
Mr Matthews: Yep?
Mr Rendall: Yes.
Mr Matthews: So I just want to make sure?
Mr Rendall: Yeah
Mr Matthews: So the one on the next page it says bedroom 4. So the one –
sorry, if you go back. So at page 495 there is one that is
marked ‘bedroom 4’. And this is – you would have seen any
email Mr Bartholomaeu’s…?
Mr Rendall: Look, to be honest, I can’t – I can’t…
Mr Matthews: You can’t recall?
8 Ibid 1-64, Lines 6 to 41.
-- 6 of 18 --
7
Mr Rendall: ...recall. No, I can’t recall because I’m not sure whether there
was a door off that side or…
Mr Matthews: Okay?
Mr Rendall: … Or there wasn’t.
[20] Mr Rendall went on to give evidence that he could not say conclusively whether it
was the bedroom 2 door or the bedroom 4 door that was the subject of the complaint
during the inspection and the Direction to Rectify, as follows:9
Mr Matthews: I’m not trying to… Now, I’m only trying to clarify which is
which because all of my paperwork worked on the
homeowner stating this is bedroom 2.
Mr Rendall: Yes.
Mr Matthews: The homeowner – I want to clarify and make sure I’ve got
your evidence correct. You’re not precisely sure – you’re not
sure which of these particular bedroom doors?
Mr Rendall: No.
Mr Matthews: … Was the subject of the inspection and the Direction to
Rectify because it was – it might have been different to the
plan, and you are relying on the homeowner’s definition of
that during the inspection; is that fair to say?
Mr Rendall: Yes. Yes.
Mr Matthews: Okay. And looking at these photographs retrospectively you
can’t say one way or the other whether it was bedroom 2 door
or bedroom 4 door that was the subject of the complaint
during the inspection and the Direction to Rectify? You can’t
say one way or the other?
Mr Rendall: I can’t say that conclusively, and I’m not going to get into
that.
Submissions of the builder
[21] The builder submits that the decision to issue the Direction to Rectify ought to be set
aside and summarised its position as follows:10
a) First and primarily, the Commission exceeded its statutory power or
exercised it unfairly;
b) Second, the work was not effective and there is no objective evidence before
the tribunal that:
i. the gap varied in width; or,
ii. alternatively, if the gap did in fact vary in width (which Dixon denies),
that the variation is actually defective for the purposes of any written
code, standard or guideline (including section 10.8 of the Standards
and Tolerances Guide – which does not apply to the gap)
9 Ibid 1-65, Line 46 to 1-66 Line 11.
10 Written argument of the applicant (Dixon), filed on 11 June 2025
-- 7 of 18 --
8
c) third, the tribunal (stepping into the Commission’s position) should exercise
its discretion not to issue the DTR (recognising Dixon’s innocent position)
or it is unfair and all the circumstances to issue the DTR against Dixon
because:
i. the owners of the property replaced the hinges on the door at the
architrave surrounds which (as explained below) may have caused the
architrave to deviate from its original position;
ii. Dixon (prior to inspection) arranged for its trade contractor to attend
the property in order to address the alleged variation in the gap and
the owners, however, failed to advise whether they were content with
the trade contractor’s work (despite Dixon’s repeated requests);
iii. the alleged issue relating to the gap was not raised by the owners until
the day of the inspection such that Dixon was unable to attempt to
rectify the issue before the DTR was issued;
iv. the DTR was issued approximately 19 months after the work of the
property was completed by Dixon; and, or in the alternative; and
v. after Dixon notified Mr Rendall that it addressed the gap prior to the
DTR, Mr Rendall failed to confirm with the owners whether such
work was completed.
[22] The builder submits that the decision was unfair as it was not given notice of the
specific item of building work involved, or given sufficient time to attempt to rectify
the issue, as follows:11
58. On a proper interpretation of the above-mentioned provisions, the
Commission cannot direct a builder to rectify work that has not been the
subject of a written complaint by an owner of a residential property. In
the absence of such notice, a builder is not afforded the opportunity to
rectify the allegedly defective work prior to the Commission considering
whether a Direction to Rectify or to be issued and, as a matter of
practicality, is not permitted to access that part of the consumer’s
property that has not been referred to in a written complaint. This is a
matter which goes squarely to the requirement to consider the unfairness
to the builder in issuing a Direction to Rectify, and therefore a necessary
fact to be considered as part of the proper exercise of the discretion. In
the absence of a written complaint to the Commission (then being
communicated to builder) about a specific item of building work and, or
in the alternative, sufficient time being allowed following the
identification of the disputed item during an investigation to allow the
builder to attempt to rectify the issue, the unfairness ground would be
engaged.
59. Therefore, as the alleged issue concerning the gap between the architrave
surrounding the bedroom 4 door and the adjacent hallway wall was not
included in the owners written complaint to the Commission, Dixon was
not informed about this issue prior to the inspection and, as a result, was
not afforded a proper opportunity to assess this issue and (if necessary)
rectify the work before the DTR was issued, nor was the Commission
entitled to access that part of the property unrelated to any complaint by
the owner. Although Mr Rendall’s evidence is that item 5 of the owners
11 Written argument of the applicant (Dixon), filed on 11 June 2025, [58]–[59].
-- 8 of 18 --
9
complaint form alluded to this issue by referring to ‘poor workmanship
to architrave to hallway’, it is Dixon’s submission, (this based on Mr
West’s evidence) that such a discretion contains insufficient information
to refer to the gap between the bedroom 4 door and that this issue was
raised for the first time by the owners on the day of the inspection. On
the plan and photographs itself, is plainly ambiguous as to where the DTR
was referring where there are numerous architraves to hallways outside
of just bedroom 4. It follows that the DTR ought to be set aside on the
basis that it was unfair to direct Dixon to rectify work that had not formed
the basis of a written complaint from the owner and was only brought to
its attention on the day of the inspection (this being 5 days before the
DTR was issued).
[23] As to whether the building work was defective, the builder submits that the tolerance
specified in clause 10.8 of the Standards and Tolerances Guide does not apply to the
gap, and that ‘there is no other relevant building code, rule, specification, standard or
guideline pertaining to the gap and there is no evidence to suggest that the hallway
wall and architrave (individually) do not comply with the tolerance outlined in clause
10.8 of the guide’.12
[24] The builder submits that as there is no provision in the Queensland Building and
Construction Commission Act 1991 (Qld) (‘QBCC Act’) which gives the Commission
the power to direct a builder to rectify work that is not defective for the purposes of
any relevant code, standard or tolerance, that the Direction to Rectify ought to be set
aside as Mr Rendall’s findings are not supported by any relevant written rules
governing residential building work in Queensland.13
[25] The builder does not contest that the work referred to in the Direction to Rectify is
‘building work’ within the meaning of the QBCC Act.14
[26] The builder submits that Mr Rendall’s position is that the alleged variation in the gap
was visible from a normal viewing position, which (under section 1.4 of the defects
guide) is 1.5 m from the relevant surface, and that because the variation in the gap
exceeded 4 mm over 2 m, the ‘out of plumb building work’ did not comply with the
tolerance set out in section 10.8 of the Guide and was therefore a non-structural
defect.15
[27] The builder submits that the work is not defective, and that there is no evidence to
suggest that a gap existed between the architrave to the bedroom 2 door and the
hallway wall, or that if there was such a gap that this did not comply with the tolerance
outlined in clause 10.8 of the Defects Guide.16
[28] The builder notes that Mr Rendall did not use any device to measure the gap, and
simply relied on his observations, which was inadequate, as follows:17
90. In the absence of Mr Rendall using a level/other measuring device to
physically measure the gap or providing photos which demonstrate the
alleged variation in the gap, the method ultimately adopted (being to
12 Ibid [77].
13 Ibid [79].
14 Ibid [81].
15 Ibid [87].
16 Ibid [88].
17 Ibid [90].
-- 9 of 18 --
10
visually inspect the gap) is entirely inadequate to establish the existence of
the variation. This is notable where Mr Rendall confirmed that he had
various means of objectively measuring the variance, whether by
electronic spirit level or by use of specific packers on a straight edge. It is
possible that Mr Rendall has merely observed an optical illusion whereby
the gap (at a normal viewing position) appears to vary in width from the
top of the gap to the bottom (which is further from his eyeline). The
existence of the optical illusion further exemplifies the need for Mr Rendall
to have taken measurements of the gap or provide his own photos in order
to properly determine the existence of the variation. However, there is no
need to speculate as to what Mr Rendall did or did not observe where there
is (as above) no objective evidence of any defect evident.
[29] As to the bedroom door opening and closing by itself, as reported by the owner, the
builder notes that there is no evidence provided by the Commission to prove that such
an issue was present in the door between the date that the property was handed over
to the owners, and the date on which the hinges on the bedroom doors were replaced
by the owners; and that Mr Bartholomaeus stated that improper replacement hinges
may cause a door to close without assistance.18
[30] The builder submits that clause 10.8 of the guide relates only to the issue of whether
an individual wall is vertically plumb, and that there is no evidence before the tribunal
that either the hallway and/or the architrave door (when considered individually)
exceeded the tolerance in clause 10.8 of the guide.19
[31] The builder filed submissions in Reply to the closing submissions of the Commission.
[32] It noted the submission of the Commission that the definition of ‘defective’ in the
QBCC Act ‘does not require there to be a section in the guide or an Australian standard
for every element of defective building work in order for poor workmanship to satisfy
the definition of “defective”’; and submitted that this was incorrect as a matter of law
as the QBCC Act does not afford an inspector ‘an unfettered discretion in determining
whether a builder’s work is defective’.20
Submissions of the Commission
[33] The Commission submits that the work was defective, and that it was not unfair to
direct the builder to rectify the defective building work in all of the circumstances.
[34] It notes that the QBCC Standards and Tolerances Guide (‘the Guide’) is referred to
by Mr Rendall as providing guidance as to whether a complaint item is a defect; and
that the Guide is a guide only, and where there is any difference or contradiction
between the Guide and the QBCC Act, or any Act, Regulations, the National
Construction Code, Australian Standards, or manufacturers installation requirements,
they will take precedence over the Guide.21
[35] The Commission notes an email from ‘Dixon Homes Maintenance’ to Mr Rendall
dated 3 August 2023, which was not referred to in the builder’s evidence, nor put to
Mr Rendall in cross examination, which states:
18 Ibid [91]–[93].
19 Ibid [100].
20 Reply Submissions of the Applicant (Dixon), filed 6 August 2025, [3].
21 Closing submissions of the first respondent, filed 15 July 2025, [2.12], [2.13].
-- 10 of 18 --
11
‘following on from the site inspection we have had the plasterer attend today
and rectify the cornice in the bedroom 1 WIR. We have also had the carpenter
finish the doors margins and architrave and bedroom 4 today also. I have
requested the painter to now contact the owner to do paint touch-ups’.22
The Commission says that it brings it to the Tribunal’s attention due to the
Commission’s obligations to assist.23
[36] The Commission addressed the issue raised by the builder of the work allegedly
having been rectified between the inspection on 1 August 2023 and the Direction to
Rectify being issued on 8 August 2023, and submits it was not unfair in the
circumstances to give the Direction to Rectify to the applicant as follows:24
5.31 Notwithstanding that there is no clear evidence of if or when the building
work the subject of complaint item 5 was allegedly rectified by the
Applicant, the Commission’s position is that even if the work the subject
of complaint item 5 was rectified between the inspection on 1 August
2023 and the DTR being issued on 8 August 2023, it is not unfair in the
circumstances to give the Direction to Rectify to the applicant.
5.32 This is because the building work was defective and not rectified at the
time of the inspection. This position is consistent with the objects of the
QBCC act in ensuring the maintenance of proper standards in the industry
and achieving a reasonable balance between the interests of building
contractors and consumers.
[37] The Commission submitted that in determining whether something is defective
building work, Mr Rendall has regard to the standards of a reasonably competent
licensee and good building practice generally, as well as specific guidelines.25
[38] In relation to the question as to the inspector not measuring the defect, the
Commission referred to Mr Rendall’s expertise as follows:26
m) In response to Mr Bartholomeaus’ criticism that he did not measure the
defect, it is Mr Rendall’s role to use his expertise to identify defects, which
he did so by visually observing the clear defect from 1.5m away and
observing that the door swung by itself, which based on Mr Rendall’s
experience and expertise, Mr Rendall says is evidence that there is a
problem with the plumbness.
[39] The matters that Mr Rendall had regard to in considering whether the item was
defective, were submitted by the Commission to be as follows:27
o) In considering whether Complaint Item 5 was defective, he had regard to:
i. the noticeable difference in margin around the door;
ii. the acceptable standards of a licensee;
22 Ibid [5.25].
23 Ibid [5.28].
24 Ibid [5.31], [5.32].
25 Ibid [6.8j].
26 Ibid [6.8m].
27 Ibid [6.80].
-- 11 of 18 --
12
iii. the position of the door which did not have a standard equilibrium,
as it was out of plumb, meaning it would close by itself, or swing to
the open position;
iv. his testing of the door, by physically pushing it, which was observed
by Mr West; and
v. his observation at the inspection that the door would close by itself,
which indicated to Mr Rendall that the jam was reasonable plumb,
and that it was out of tolerance.
[40] The Commission submitted that it accepted that a photograph would have assisted, as
follows:28
6.28 With the benefit of hindsight, and the matters now agitated by the
Applicant in the Tribunal, the Commission acknowledges that the
tribunal would have been further assisted in determining whether
Complaint Item 5 is defective, if a photograph had been taken by Mr
Rendall of Complaint Item 5.
[41] The commission described Mr Rendall’s conduct in not taking measurements and
photos as ‘natural human behaviour’ as follows:29
6.30 In the above circumstances, the commission submits that the only
criticism of Mr Rendall can be that:
….
(b) Mr Rendall’s conduct was one of natural human behaviour, and his
usual process is not to measure and photograph clear defects, unless
contested by the builder’s representative (particularly in this case
where there were 25 complaint items)
[42] As to the changing of the hinges by the owners, the Commission submits that Mr
Rendall’s evidence was that the defect was identified by the owners before the hinges
were changed, and he did not agree that changing the hinges could make the architrave
or doorjamb move;30 and that there was no other evidence before the tribunal other
than the comments of Mr Rendall and Mr Bartholomaeus in respect of that issue.31
[43] The commission submitted that it was not necessary for a complaint to have been
made in order for the commission to issue a Direction to Rectify, as follows:
8.8 Firstly, the applicant submits that the commission cannot direct a builder
to rectify work that has not been the subject of a written complaint by an
owner of a residential property. This is wrong at law because there is no
limitation or pre-condition in the QBCC Act that this requires a complaint
to be made in order for the commission to issue a DTR. This was
confirmed in Shilleto v Queensland Building and Construction
Commission [2024] QCAT 137 at paragraph 19 where Member Olding
confirmed that ‘the power under s 72 to issue a DTR is not expressly
limited to defects about which complaint has been lodged’.
28 Ibid [6.28].
29 Ibid [6.30(b)].
30 Ibid [7.10].
31 Ibid [7.13].
-- 12 of 18 --
13
8.9 There is nothing in the text of the statute or the purpose of the QBCC Act
that supports the construction pressed by the applicant. A reading of the
whole of section 72 makes it clear that the commission can issue a
direction to a person where that person carried out what the commission
considers to be defective building work.
Legislation as to the issue of a Direction to Rectify
[44] Section 72(3) of the QBCC Act provides that, in deciding whether to give a direction,
it may take into consideration all the circumstances it considers are reasonably
relevant; and s 72(5) provides that the Commission is not required to give a direction
if the Commissioner is satisfied that in the circumstances it would be unfair to the
person to give the direction, as follows:
72 Power to require rectification of building work and remediation of
consequential damage
(1) This section applies if the Commission is of the opinion that—
(a) building work is defective or incomplete; or
(b) consequential damage has been caused by, or as a consequence of,
carrying out building work.
(2) The Commission may direct the person who carried out the building work
to do the following within the period stated in the direction—
(a) for building work that is defective or incomplete—rectify the
building work;
(b) for consequential damage—remedy the damage.
(2AA) A regulation may prescribe a period within which the Commission must
make the direction.
(2A) If a period is prescribed under subsection (2AA), the Commission must
make the direction during the prescribed period.
(3) In deciding whether to give the direction, the Commission may take into
consideration all the circumstances it considers are reasonably relevant
and, in particular, is not limited to a consideration of the terms of the
contract for carrying out the building work (including the terms of any
warranties included in the contract).
(4) The period stated in the direction must be the period prescribed by
regulation unless the Commission is satisfied that, if the direction is not
required to be complied with within a shorter period—
(a) a substantial loss will be incurred by, or a significant hazard will
be caused to the health or safety of, a person because of the
defective or incomplete building work or consequential damage;
or
(b) the defective or incomplete building work, or consequential
damage, will cause a significant hazard to public safety or the
environment generally.
(5) The Commission is not required to give the direction if the Commission
is satisfied that, in the circumstances, it would be unfair to the person to
give the direction.
-- 13 of 18 --
14
Example for subsection (5)—
The Commission might decide not to give a direction for the
rectification of building work because an owner refuses to allow a
building contractor to return to the owner’s home or because an
owner’s failure to properly maintain a home has exacerbated the
extent of defective building work carried out on the home.
(6) The Commission may, before it considers whether building work is
defective or incomplete, require the consumer for the building work
comply with a process established by the Commission to attempt to
resolve the matter with the person who carried out the work.
(7) In subsection (3), a reference to a contract for carrying out building work
includes a reference to a domestic building contract for managing the
carrying out of building work.
(8) To remove any doubt, it is declared that the Commission may act under
this section in relation to consequential damage whether or not an owner
or occupier has made a request under section 71J.
Discussion
[45] This matter has been highly contested. There is only one Direction to Rectify
involved, which relates to an alleged non-structural defect. No evidence was given as
to the cost of works which would be required to rectify the defect, but the extent of
the defect appears to be relatively minor, presumably requiring only minor carpentry,
plastering and painting work to repair.
[46] There are obviously broader issues of policy or principle between the parties at play
behind the continuation and the contest of these proceedings. My role is simply to
review the decision to issue a Direction to Rectify.
[47] There is contest as to whether there was a defect, whether the Commission had power
to give a Direction to Rectify in relation to the defect, and whether it was unfair to do
so.
[48] There is confusion as to what the initial complaint by the owner referred to, and
whether the Direction to Rectify addressed a complaint made by the owner prior to
the inspection.
[49] The Direction to Rectify was made in relation to bedroom number 2 which is shown
on the floor plan as being a bedroom sitting between the adjoining main bedroom and
another adjoining bedroom.
[50] The Direction to Rectify clearly appears to have been made in relation to another
bedroom, which is described as bedroom 4 on the plan, which is opposite, and
completely separate from, bedroom 2.
[51] The builder submits that the first time its employees or officers were made aware of
any defect in relation to the architrave of the door in bedroom 4 was at the time of the
inspection, which led to the issuing of the Direction to Rectify.
[52] Mr Rendall, the building inspector, related instances of owners misdescribing which
room was being discussed.
[53] The commission has submitted that it is not necessary for a complaint to have been
made in order for the commission to issue a Direction to Rectify, and have cited the
-- 14 of 18 --
15
decision in Shilleto v Queensland Building and Construction Commission & Ors32
(‘Shilleto’) as authority for that proposition.
[54] The decision in Shilleto considered the making of a complaint in terms of timing
issues. The Member noted the rectification policy of the QBCC as follows:
[14] Both submissions draw upon a Rectification of Building Work policy
(‘the Rectification Policy’) made by the then QBCC Board on 11 April
2014 and approved under the then s 19 of the QBCC Act with effect from
14 October 2014. This Rectification Policy, which was continued by the
QBCC Act, Schedule 1, s 76 and s 57 of the Queensland Building and
Construction Commission Regulation 2018 (Qld), is subordinate
legislation under sections 7 and 9 of the Statutory Instruments Act 1992
(Qld).
[15] The Policy relevantly provides:
(1) Rectification of defective building work
1. It is a policy of the Queensland Building and Construction
Board that a building contractor who carries out defective
building work should be required to rectify that work.
2. To remove any doubt, subsection (1) applies despite the
building contractor failing to comply with the contracted
plans and specifications for the work.
(3) Notification of defects
1. It is a policy of the Board that if a consumer is seeking the
assistance of the Queensland Building and Construction
Commission (QBCC) to issue a direction to a building
contractor to rectify defective building work, the consumer
must lodge a formal complaint with the QBCC of defective
building work as soon as possible but no later than within
12 months of becoming aware of the defects.
2. The QBCC will then consider the issuing of Direction to
Rectify to a building contractor:
a. for structural defective building work, within 6 years
and 3 months of the building work being completed;
or
b. for non-structural defective building work, within 12
months of the building work being completed.
(Emphases added.)
[55] The commission referred to paragraph [19] of the decision, which reads as follows:
[17] It is not immediately clear that the Commission may issue a DTR relating
to defects that have not been the subject of a complaint within 12 months
of the consumer becoming aware of the alleged defect as required by s
71J(4).
[18] On the one hand, the statutory scheme plainly contemplates consumers
lodging complaints and the Commission responding with a decision
32 [2024] QCAT 137.
-- 15 of 18 --
16
whether or not to issue a DTR. That is scarcely surprising since the
volume of building work undertaken in the State would make it
unrealistic to envisage the Commission undertaking audits or otherwise
becoming aware of defects outside of a complaints process in the usual
course. And providing a time limit on complaints, and thus the prospect
of a DTR issuing, could be seen as endeavouring to achieve a reasonable
balance between the interests of building contractors and consumers in
accordance with the objects of the QBCC Act (s 3, extracted above).
[19] On the other hand, the power under s 72 to issue a DTR is not expressly
limited to defects about which a complaint has been lodged. That, it might
be thought, is consistent with the objects of the QBCC Act not being
limited to protecting individual consumers but extending to ‘the
maintenance of proper standards in the industry’: s 3(a)(i), extracted
above.
[56] As the Tribunal noted in [18] of that decision, the statutory scheme ‘plainly
contemplates consumers lodging complaints’, and this is reinforced by the
Rectification Policy which plainly states that ‘the consumer must lodge a formal
complaint’.
[57] Shilleto considered the impact of a complaint being made outside a 12 month period
in question. It concluded that a complaint being lodged outside the 12 month period
could still be considered, as a matter of discretion, as follows:
[29] Accordingly, I approach this matter on the basis that the complaint being
lodged outside the 12-month period is not fatal to the issue of a DTR but
is a factor to be taken into account in deciding whether, as a matter of
discretion, that should occur.
[58] Shilleto therefore is not an authority for a broad proposition that it is irrelevant whether
a consumer has made a complaint for the commission to issue a Direction to Rectify.
[59] The statutory scheme and the commission’s procedures require a consumer to file a
complaint. That provides for an orderly handling of complaints.
[60] There may be instances where the commission in acting in accordance with the objects
of the QBCC Act deals with defects of the type which were noted in Shilleto as ‘not
being limited to protecting individual consumers but extending to “the maintenance
of proper standards in the industry”’33 and could issue a Direction to Rectify without
a complaint being lodged. That is a different situation to the handling of a consumer
complaint by an individual consumer.
[61] In dealing with a consumer complaint by an individual consumer, the consumer is
required to make a complaint by the commission’s procedures, and it is a matter of
procedural fairness that the builder should be given clear notice of a defect that it is
being asked to address through the complaints process of the Commission before a
direction adverse to the builder is given.
[62] The issue here is not as to the numbering of the bedrooms – as Mr Rendall says, rooms
can be misdescribed. However, the issue is as to whether, whatever description is
used, that description is effective to alert the builder as to the complaint being made
against it.
33 Shilleto [19].
-- 16 of 18 --
17
[63] The builder contends that it advised the Commission that the defects to both bedroom
2 and bedroom 4 had been rectified and that the Commission did not follow up with
a reinspection prior to the issuing of a Direction to Rectify.
[64] I consider that the email from the builder to the Commission dated 3 August 2023 as
to carpentry work being done in bedroom 4 on 3 August 2023, which the Commission
referred to in its submissions, as noted, is not determinative in relation to the
identification of the room concerned.
[65] That email is entirely consistent with the builder’s contention that nothing in bedroom
4 was brought to their attention through the complaints process, and it indicates that
the builder appears to have acted promptly and had further carpentry work conducted
to that room after an issue was brought to their attention by the owner at the inspection.
[66] The Commission contended that it was not unfair to issue a Direction to Rectify where
‘the building work was defective and not rectified at the time of the inspection’.34 This
submission would suggest that the Commission could issue a Direction to Rectify
immediately after an inspection, notwithstanding that the builder had not been given
clear notice of the defect, or any opportunity being given to resolve the matter.
[67] That submission of the Commission that a Direction to Rectify could fairly and
properly be issued simply upon the building work being assessed as ‘defective and
not rectified’ at the time of the inspection cannot be correct, as it does not address
issues of fairness.
[68] The builder has taken issue that the building inspector did not take any measurements
by the use of instruments, but relied upon his knowledge and experience to observe
the gap between the door and the architrave, and the verticality of the adjoining wall
and door.
[69] The builder also takes issue with the suggestion that a building inspector could be
satisfied that work was defective in the absence of any specific Australian Standard,
Code, guide or specification.
[70] I accept that the expertise of a building inspector is an important element in the process
of assessing whether work is defective, and that occasions may arise where there is
no relevant Australian Standard, Code, guide or specification, or there is a ‘lacuna’ or
gap in their provisions. This could conceivably readily happen in the case of new
technology or new materials being utilised, or simply in an unusual situation that was
not contemplated by the relevant specific Australian Standard, Code, or guide.
[71] It is fundamental to the determination of many construction disputes, and to the review
of decisions of the Commission, that regard be had to accepted industry practice as a
measure of compliance, which often comes to an assessment of what is ‘reasonable’
based upon the standard of ‘a reasonably competent and diligent builder’.
[72] In this matter the building inspector did not take any measurements or photos of the
defect. Where the issue is one relating to an observable and measurable defect, such
as the verticality of a wall, or the width of a gap, it would assist to take measurements,
and take photos, and put beyond doubt any question as to whether a wall is vertical,
or how wide a gap is.
34 Submissions of the Commission [5.32].
-- 17 of 18 --
18
[73] In the absence of clarity as to the identification of the defect prior to the inspection,
and as to the exact inclination of the wall and size of any alleged gap, I am left to
assess the matter on the basis of the evidence and opinions of the witnesses.
[74] Mr Rendall said that he could not say conclusively whether it was the bedroom 2 door
or the bedroom 4 door that was the subject of the complaint during the inspection and
the Direction to Rectify; and that he did not make any measurements or photographs
as he was confident in his own experience as to what he was observing.
[75] Mr West and Mr Bartholomeaus were particular in their recollections. I found their
narratives to be logical and supported by their contemporary communications with the
Commission.
[76] I am not satisfied that a defect to bedroom 2, as identified in the complaint to the
Commission, existed. Even if it is accepted that the complaint was intended to refer
to bedroom 4, I am not satisfied that the existence of a defect as to bedroom 4 is
established in the absence of any measurements or photographs substantiating a
defect; and where there is a compounding and untested suggestion that the owners, by
changing the hinges may have caused or contributed to the door closing by itself,
rather than being caused by defective work by the builder.
[77] Even if it is accepted that a defect was identified appropriately through the complaints
process, and that a defect existed at the time of the inspection, I consider it was unfair
to issue a Direction to Rectify where the builder had not been given clear notice of the
defect, or an opportunity to rectify it prior to the inspection, or a reasonable
opportunity to rectify after the inspection when the defect was discovered on
inspection, before a Direction to Rectify was issued.
[78] As I am not satisfied that a defect existed, or that it was fair to issue a Direction to
Rectify, the decision of the Commission made on 15 July 2024 to issue a Direction to
Rectify is set aside, and I order accordingly.
-- 18 of 18 --