Falantin v Keys [2025] QCAT 479
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Falantin v Keys [2025] QCAT 479
PARTIES: DOROTA FALANTIN
(applicant)
v
WILLIAM KEYS
(respondent)
JACQUELINE KEYS
(respondent)
APPLICATION NO/S: NDR170-23
MATTER TYPE: Other civil dispute matters
DELIVERED ON: 17 November 2025
HEARING DATE: 1 October 2025
HEARD AT: Brisbane
DECISION OF: Member McLean-Williams
ORDERS: A new boundary fence and associated retaining wall
are to be constructed on the surveyed boundary
between Number 7 Atlas Place Chapel Hill, and
Number 130 Fig Tree Pocket Road Chapel Hill, in
accordance with an engineering design specification
obtained from a licensed engineer, to be engaged by
the Applicant. Obtaining any necessary certification
or Council approval for those works is the
responsibility of the Applicant.
The associated retaining wall is to be constructed in
accordance with the engineering design required by
Order (1) above, using concrete sleepers and
galvanised steel posts, and is to be constructed in
accordance with the requirements of the Applicable
Australian Standard(s). The boundary fence is to be
constructed in timber (comprised by hardwood
posts and rails, with treated pine palings with a gap
between palings of no more than 5mm), to a height
of 1.8 metres. Palings are to be placed on the
Eastern-facing side of the new fence.
The new boundary fence and associated retaining
wall is to be constructed on, or as near to the
surveyed boundary as is practically achievable, but
no less than 500mm further to the West of the
existing timber fence.
-- 1 of 17 --
2
All vegetation necessary for the construction of the
new boundary fence and associated retaining wall is
to be removed as part of the fencing works required
by these orders.
Removal of the existing timber wooden fence on the
land at Number 7 Atlas Place and removal of the
existing cold-formed steel retaining wall on the land
at Number 130 Fig Tree Pocket Road are also
fencing works for the purposes of these orders.
The costs of any engineering design, council
certification, as well as the costs for necessary
materials and construction/labour costs for the
fencing works, including foundation and drainage,
as now required by Orders (1)–(5) above, are to be
borne equally (i.e. 50:50) by the Applicant and the
Respondents. The costs that must be shared by the
Respondents are confined to that portion of fencing
works along the shared boundary between the
properties and do not extend to any fencing costs
beyond either the Northern or Southern boundary
of the land at 130 Fig Tree Pocket Road at Chapel
Hill.
The costs of any necessary preliminary works
beyond those contemplated by Orders (4) and (5)
above, (including but not limited to any relocation of
sheds, garden beds, pool fences, paving, etc), and
post-construction remediation or landscaping costs
arising after the fencing works required by Orders
(1)–(5) above, are to be borne on the basis that the
Applicant will pay for any such costs arising at
Number 7 Atlas Place, and the Respondents will pay
for any such costs arising at Number 130 Fig Tree
Pocket Road.
Any replacement planting in the vicinity of the new
boundary fence and associated retaining wall at the
conclusion of the ordered fencing works is to be
confined to low shrubbery, or ground covering
plants that do not have a root structure that is
capable of detrimentally affecting either the new
fence, or the associated retaining wall.
Within six (6) weeks of obtaining an engineering
design (Order (1), above) the Applicant will provide
the Respondents with two (2) quotes for the
necessary works (Orders (2), (4) & (5) above), and
the Respondents are at liberty to select between the
provided quotes within 14 days after provision of the
quotes. In the event of no response from the
Respondents to the provided quotes the Applicant is
-- 2 of 17 --
3
at liberty to determine which of the two quotes will
be accepted.
The parties will provide all necessary access upon
their land for trades and/or designing engineers to
do any works ancillary, necessary or incidental to
the performance of these orders.
In the event of any non-compliance with these orders
by the Respondents the Applicant and her
contractors are at liberty, pursuant to s 94 of the
Neighbourhood Disputes (Dividing Fences and Trees)
Act 2011 (Qld), to enter upon the land at Number
130 Fig Tree Pocket Road to carry out the necessary
works upon the giving of at least seven (7) days’
written notice to the Respondents. Any costs
incurred by the Applicant in the performance of any
works caused by non-compliance with any of these
orders by the Respondents is a sum that may be
recovered, in full, by the Applicant from the
Respondents.
The Applicant will bear all of the costs associated
with the erection and certification of a fire-rated
wall, wholly within the land at 7 Atlas Place Chapel
Hill.
CATCHWORDS: DIVIDING FENCE DISPUTE – circumstances wherein
adjoining neighbours unable to reach agreement –
circumstances wherein existing fence no longer sufficient –
further circumstances in which fence constructed with an
adjacent retaining wall – arguments regarding who has the
benefit of (and hence responsibility for the costs of
replacing) the retaining wall – Tribunal finding that
retaining wall necessary for boundary fence for purposes of
s 35(1)(f)
Neighbourhood Disputes (Dividing Fences and Trees) Act
2011 (Qld), s 13, s 15, s 16, s 20, s 21, s 35, s 46, s 94
Battiato v Clifton [2025] NSWLEC 1391
Yared v Glenhurst Gardens Pty Ltd [2002] NSWSC 11
APPEARANCES &
REPRESENTATION:
Applicant: Self-represented
Respondents: Self-represented
-- 3 of 17 --
4
REASONS FOR DECISION
[1] The Applicant and the Respondents (‘the parties’) are adjoining owners1 who share a
rear boundary in Chapel Hill. The Applicant resides at Number 7 Atlas Place
(‘Number 7’), and the Respondents reside at Number 130, Fig Tree Pocket Road
(‘Number 130’).
[2] On 16 September 2023 the Applicant commenced an ‘Application for a tree dispute’
pursuant to the Neighbourhood Disputes (Dividing Fences and Trees) Act 2011 (Qld)
(the ‘Act’), seeking orders from the Tribunal in relation to a number of trees, located
within the boundary of the Respondents’ land. Therein, the Applicant makes various
complaints about the Respondents’ vegetation, for purposes of submitting that
Number 7 qualifies as ‘land affected’ by those trees, for purposes of s 46 of the Act.
[3] Although originally commenced by the Applicant specifically as a Form 51 tree
dispute, the Application makes clear that the Applicant’s concerns extend to the
condition of “the Respondents’” disintegrating retaining wall,2 and the leaning
boundary fence, which the Applicant contends “cannot be replaced until the
Respondents’ retaining wall is rebuilt, and all the trees and vegetation are removed”.3
[4] Ultimately, the parties have finally agreed that the dividing fence and the retaining
wall that are the subject of these proceedings have each reached the stage at which
neither are sufficient,4 and need to be replaced.5 For practical reasons, the parties also
agree that the trees that are the subject of these Tribunal proceedings need to be
removed,6 as a necessary preliminary for fencing works.
[5] Because the subject trees will now become the subject of specific fencing work orders
made by the Tribunal pursuant to s 16 of the Act, it becomes otiose for the Tribunal to
make further determinations regarding the trees pursuant to s 46 of the Act, or any
consequential orders, under s 66 of the Act.
[6] Prior to the commencement of these proceedings there had been an extensive and
unsuccessful history of efforts between the parties to reach an agreement, particularly
in relation to whom should bear the costs associated with the removal and replacement
of the retaining wall.
Situational Appreciation
[7] Number 7 is land more properly described as Lot 19 on Registered Plan 133975 within
the Brisbane City Council local government area. Number 130 is land that is more
properly described as Lot 8 on that same registered plan.
[8] Topographically, Number 130 sits physically below—and immediately to the West
of—Number 7, with the house at Number 7 facing to the East and constructed at the
watershed of a ridge that falls away to the West, in the direction of Chapel Hill Road.
The frontage of Number 130 then faces Westwards, towards Fig Tree Pocket Road.
1 Act s 15(1).
2 Form 51, answer given in response to Questions 22, 25, 51. At the time of commencing her
Application, the Applicant was of the understanding that the retaining wall was wholly owned by the
Respondents.
3 Form 51, answer given in response to Question 37.
4 Act s 13.
5 Transcript p 26, line 16, p 81, lines 9–13.
6 Act s 16(b).
-- 4 of 17 --
5
[9] The shared rear boundary between the two properties runs generally North-South, over
a length of about 19 metres. Number 7 also shares its rear boundary with Number
128, and Number 132 Fig Tree Pocket Road, which are, respectively, to the immediate
North, and South, of the Respondents’ home at Number 130.7 All three of the Fig
Tree Pocket Road properties are lower down the slope from Number 7, although it is
the case that this section of Fig Tree Pocket Road also gently climbs, as it proceeds
further towards the North.
[10] Number 130 was constructed a number of years prior to the house at Number 7, and
sits on a house pad partly cut into the land on the lot. There is a low retaining wall
immediately behind the house at Number 130, with a set of concrete stairs set into that
retaining wall, leading up to a higher back yard, that continues to slope upwards until
it meets the cold-formed steel retaining wall at the real centre of this dispute.
[11] The cold-formed steel retaining wall is approximately 750 millimetres high and runs
approximately North-South, in parallel with the boundary, with the land behind the
cold-formed steel retaining wall then climbing again, albeit even more steeply, up to
meet the base of a dilapidated 1.8 metre wooden boundary fence shared with Number
7, that is set upon one wooden sleeper, approximately 200mm high.
[12] When standing in the back yard at Number 130, the height differential between the
top of the cold-formed steel retaining wall and the base of the wooden fence above it
is somewhere between about 1.3–1.5 metres. The lineal distance between these two
appurtenances is then about one metre. Once on the other side of that fence, the rear
wall of the house at Number 7 is within about 3 metres of the fence. There is also a
paved patio area, approximately 2.5 metres wide, with an associated roof structure
coming off the back of the house at Number 7. Originally, this patio was about 4
metres long, yet for reasons that will be elaborated further below, the patio and its roof
were subsequently extended by the Applicant, by about another 3 metres.
[13] The Applicant informed the Tribunal that she had purchased the house at Number 7
about 25-years ago, and that she has now lived in the house for the past 21 years.
[14] Although the Applicant had always (until recently) assumed the wooden fence to
constitute the rear boundary between her house and Number 130, a survey conducted
in 2024—as part of this dispute—has confirmed that the legal boundary is actually
located approximately 500 millimetres further to the West, beyond the existing
wooden fence, running in a generally North-South line, that transects the
approximately one metre gap between the wooden fence and the cold-formed steel
retaining wall further down the slope.
[15] In light of the recent survey, the parties are now in agreement in relation to the location
of their common boundary.
[16] The Respondents have lived in the house at Number 130 since long before the arrival
of the Applicant at Number 7.
[17] During their oral evidence given on 1 October 2025—and although now accepting8 of
the fact that the cold-formed steel retaining wall has been erected wholly within their
7 The total length of the rear boundary for 7 Atlas Place is 36.361 metres.
8 Transcript p 23, line 26.
-- 5 of 17 --
6
land—the Respondents endeavoured to explain the history of the current boundary
arrangements, advising the Tribunal in these terms:
• When the area was developed for housing in the 1970s, the original developer had
constructed retaining walls on the boundary, from Koppers logs, in order to retain
the land at Number 7. Remnant artefacts of the original retaining wall may still
be found along the line of the boundary in the undergrowth.
• Over the years, the former occupants of Number 7 had failed to adequately
maintain the Koppers log retaining wall, such that it degraded, and parts of it
slumped and encroached onto Number 130.
• The Respondents purchased their home at Number 130 in 1988. In about 1993–
94, the former owner of Number 7, with the permission of the Respondents,
rebuilt the retaining wall, this time using cold-formed steel ‘C’ sections:
[W]e didn’t interfere with what he did. He took the cheapest option. He
only came and advised us of what he was doing, and all access was
actually from his land. He took the fence down; that fence was removed.
The fence was removed, and then he bought in – he worked for a steel
company right? So, he got these steel sleeper[s]. We have very young
children. We were too busy to even pay attention to what he was doing,
but we can tell you that the original Koppers logs are still there, and in
many places I have photographic evidence where the Koppers logs are
about that far within the boundary on the applicant’s property. He just
put a fence, a steel structure, in front of it.9
• Mr Keys helped the former owner at Number 7 bring materials onto the land at
Number 130 to construct the cold-formed steel retaining wall, but did not
otherwise aid in the construction. “We also paid for half the things”.10
• After the retaining wall had been re-constructed in cold-formed steel, the
Respondents also contributed to the cost of a new timber dividing fence. This
was also built by the former owner of Number 7 in about 1993–94, and was
positioned further up the hill:
[B]ecause that land had degraded so much, the land on her side, slippage
had happened so much, they could not put the fence back on the boundary.
It was actually moved, to higher ground, which is what her – closer to,
you know, into her land. And they only did that, I believe, although I
didn’t discuss it with at the time, but I believe they did that because there
was too much slippage to build the fence lower.11
Matters that are now agreed
[18] Ultimately, by the conclusion of the hearing, the parties were able to reach substantial
agreement regarding the following:
• There is definitely a need for a new boundary fence;
• Desirably, the new fence should be erected on the surveyed boundary. Any new
retaining wall should also be located on the boundary;
9 Ibid pp 22–23, lines 44/22–06/23.
10 Ibid p 62, line 40.
11 Ibid p 24, lines 35–41.
-- 6 of 17 --
7
• For practical reasons associated with construction of the new fence, all of the
vegetation that is the subject of these proceedings will need to be removed;
• The new boundary fence should be a timber fence 1.8 metres high with a very
narrow paling gap (so as to maximise privacy), with the palings fixed on the same
side as the palings on the current fence;
• In order to rectify the timber boundary fence, the lower retaining wall needs to be
rectified, as well. These two property appurtenances, together, are really part of
a system.12
[19] The parties remain at odds regarding who should bear the financial responsibility for
the costs associated with removing and then replacing the cold-formed steel retaining
wall.
Respondents’ Contentions
[20] Mr and Mrs Keys contend that the cold-formed steel retaining wall was built by the
former owner of Number 7, and entirely for the benefit of the owner of Number 7, and
should now become the sole financial responsibility of the current owner of Number
7. Although the Respondents agree that the cold-formed steel retaining wall was never
built properly, and that it has since failed and must be replaced, they claim that these
proceedings are, in large measure, an attempt by the Applicant to try and shift
responsibility13 for the costs of this task onto the Respondents:
Over decades, the applicant and her predecessors have failed to maintain it.
The result is that the wall degraded, slumped, and parts of it now encroach on
my property. That is not where it was original [sic] built. It is a result of
collapse and neglect. Her predecessor then built a sleeper wall, without
engineering, in front of the collapsing land to try and hold the slippage up.14
[21] The Respondents further contend that rainwater runoff from Number 7 (particularly
from the roof over the patio at the back of Number 7) has always been a big part of
the problem;15 causing scouring of the land on the slope between the two properties,
and for the land to erode and then slip, further down the hill, towards their house at
Number 130; and for the wooden fence (already re-constructed once, further uphill
from its original location), only to have it to fail again because of continuing rainwater
erosion.16
[22] Mr and Mrs Keys also assert that the already very parlous state of the wooden fence
has been further exacerbated by tradesmen, recently employed by the Applicant, who
cut through the rails of the fence to gain access to the underside of the patio slab, whilst
doing some repair works to that slab:
We thought it was unfair that damage that is caused by her water damage… and
the scouring, and the fact that she cut [the fence] in four places without our
12 Ibid p 92, lines 34–47.
13 Ibid p 21, line 35.
14 Ibid p 22, lines 08–11.
15 Ibid p 25, lines 31–47. See also Transcript, p. 29–30, lines 22/29–03/30.
16 Although not articulated as such, the position taken by the Respondents’ is consistent with Leakey v
National Trust [1980] 1 QB 485 (‘Leakey’s Case’).
-- 7 of 17 --
8
permission – she did not contact us about that at all. We just came out and said,
“Oh, my God, she’s cut the fence”.17
[23] In response to the Respondents’ contentions, the Applicant said that, originally, her
patio roof was only 2.5 metres by 3 metres, and it did not require any gutters, by reason
that it did not harvest any rainwater from the main house roof (which has its own
gutters), and no complaints about rainwater runoff had been received from any of her
lower neighbours.
[24] Mrs Falantin next said that she took the extra step of enlarging the roof and installing
gutters with rainwater discharge out onto Fig Tree Pocket Road via pipes laid at
Number 132 Fig Tree Pocket Road (with the consent of that neighbour) only after
these proceedings had already been commenced in the Tribunal:
MEMBER: All right. Why did you enlarge the roof over the pergola,
the patio?
MRS FALANTIN: Only because – that was the only reason, because, like,
the respondent was saying that, well, we have – that was
when we already lodged their complaints. They said,
well, it’s because of the water. So, I said, “God, if that’s
what the case, if there having too much water even from
that,” so we just extended this little roof 3 metres, get the
gutters. That’s what I’ve put.18
[25] Regarding the contention that her actions had exacerbated the state of the fence by her
tradesmen having cut the rails in four places, Mrs Falantin says that the fence was, by
that stage, already in a parlous condition; these proceedings were already underway;
and the repairs to the patio foundation were required urgently.
[26] A further point of relevance to the Tribunal’s reasons is to note that the Applicant’s
recent additional efforts to mitigate the rainwater runoff complaints raised by the
Respondents (by way of her extending the patio roof at Number 7) have now created
a consequential problem for the Applicant: by reason that the extended roof structure
over the patio is now much too-close to the boundary fence; such that the Brisbane
City Council now requires that the Applicant install a fire-rated boundary wall along
an approximately 3 metre section of the patio that abuts the fence. However, until
such time as the wooden fence is first moved further to the West (and thus closer to
the actual boundary), there is just not the room for the Applicant to be able to erect the
Council-mandated firewall.
Evidence heard before the Tribunal
Engineering Evidence
[27] At the Tribunal hearing conducted on 1 October 2025, the Tribunal received evidence
from a consulting structural and civil engineer, a Mr Josef Balanag of ‘JBSE
Engineering & Design Pty Ltd’. Mr Balanag has also provided a report dated 12 May
2023, based on a site inspection that he had conducted on 24 April 2023.
17 Transcript p 28, lines 30–37.
18 Ibid p 31, lines 19–25.
-- 8 of 17 --
9
[28] Mr Balanag’s report and oral evidence (given by telephone) indicates that the purpose
of his inspection was primarily an effort to determine the causes for the failure of the
cold-formed steel retaining wall. In relation to his findings, Mr Balanag reported:
• The (lower) retaining wall structure is 19 metres in length and approximately 750
millimetres high, constructed of ‘C250.19’ cold-formed steel purlins, with
C250.19 cold-formed steel purlins also used as soldier piles, set at approximately
2 metre centres, running parallel with the common boundary between 130 Fig
Tree Pocket Road and 7 Atlas Place, Chapel Hill, yet at least one metre wholly
within the boundary of 130 Fig Tree Pocket Road.
• The retaining wall had ‘disintegrated,’ with sleepers either misaligned, or no
longer in resting on their soldier piles. The soldier piles have rotated—by an
average of 17 degrees—along their vertical plane. At least one sleeper and one
soldier pile appear to be missing. No fixings, of any type, were evident at any of
the joints between soldier piles and sleepers.
• There are trees of varied diameter both above, and below, the retaining wall.
These trees are situated much too close to the boundary wall and fence (within
200 mm). Trees increase ‘active pressure’ against the retaining wall.
• Two tree stumps of at least 400-millimetre diameter are situated at the Northern
end, and towards the middle of, the retaining wall. These trees appear19 to have
contributed to the disintegration of the retaining wall as they grew.
• The wooden boundary fence (set on a single 200mm high wooden sleeper)
between 7 Atlas Place and 130 Fig Tree Pocket Road is located above the lower
retaining wall, and now leans at an angle of approximately 20 degrees, towards
130 Fig Tree Pocket Road. Mr Balanag opines that many years of poor
maintenance of the cold-formed steel retaining wall below the wooden fence has
ultimately caused the wooden fence to collapse. “It appears the excessive rotation
of the C250.24 soldier piles below have caused the ground on 7 Atlas Place to
loosen causing the 200mm high [upper] retaining wall to sink and [for the]
boundary fence to lean 20 degrees”.
[29] Mr Balanag concludes his written report by stating that the failure of the lower
retaining wall is attributable to:
• Active pressure against the wall, caused by the large trees with only stumps now
remaining.
• Inadequate soldier pile footings, able to be undermined by tree roots.
• An inadequate retaining wall design, with soldier piles placed too far apart, and
an overall wall height that was insufficient in the circumstances, which really
necessitated a retaining wall of at least 1.3 metres height, rather than the observed
750 millimetres.
• The cold-formed steel retaining wall now needs to be removed, and replaced by a
concrete sleeper or concrete masonry wall, of at least 1.3 metres, designed by a
19 It was put to Mr Balanag during cross examination by the Respondents that the cold-formed steel wall
had been constructed with deliberate gaps in it, in order to accommodate these trees. That extra
information did not change his conclusions regarding the adverse influence caused by the trees.
-- 9 of 17 --
10
qualified engineer in accordance with the specifications of AS 4678-2002 (Earth
Retaining Structures), and other relevant Australian standards.
[30] During his oral evidence, Mr Balanag additionally informed the Tribunal that:
• Even if the lower retaining wall had been originally constructed with a deliberate
break in it to accommodate for the fact of the presence of a tree (or trees), as was
now put to him as being the case by the Respondents, subsequent growth by those
same trees has still caused adverse influence on the retaining wall;20
• Although unable to entirely exclude the possibility of rainwater runoff from
Number 7 and associated ‘ground creep’ having contributed to the observed poor
condition of the (upper) timber fence, he was unable to determine whether it was
rainwater runoff that had caused this fence to fail.21
• The fact of the soldier piles for the lower retaining wall having rotated 17 degrees
is a finding of particular significance. It suggests that the footings for the soldier
piles were never adequate.22
• From an engineering perspective, the condition of the upper wooden fence cannot
be rectified until such time as the lower retaining wall has first been remediated,
and work on the lower retaining wall really necessitates preliminary demolition
of the wooden fence, by reason that the wooden fence represents a danger to those
who will be required to work below it, when remediating the retaining wall.23
Evidence of the Tribunal Appointed Tree Expert
[31] Pursuant to directions issued by the Tribunal on 4 July 2024, an expert tree assessor,
Mr Steven Richards, was appointed to prepare a report.
[32] Mr Richards attended on site at 130 Fig Tree Pocket Road on 16 July 2024 and
prepared a report on that inspection which is now dated 15 August 2024. Mr Richard’s
report deals with six (6) trees, each located in the area near to the (upper) timber fence
constructed on a retaining wall one sleeper high and the (lower) cold-formed steel
retaining wall that are now the subject of these proceedings.
[33] In some parts of his report Mr Richards purports to give opinion evidence, well beyond
the scope of his acceptable expertise as an arborist, in relation to engineering issues
including stormwater scouring, and the adequacy of construction methods used in both
the upper fence, and the lower retaining wall. Insofar as Mr Richards strays into
engineering territory, his report will not be relied upon by the Tribunal.
[34] Unfortunately, Mr Richards has also since retired, and did not make himself available
to give oral evidence on 1 October 2025, such that the adequacy of any of the
conclusions expressed by him in his report were issues that were unable to be explored
by the Tribunal. However, so far as is relevant (and with the aforementioned caveats
in mind), Mr Richards does opine that:
20 Transcript pp 44–45, lines 10(44)–13(45).
21 Ibid p 45, line 22–23.
22 Ibid p 46, lines 1–6.
23 Ibid p 46, lines 35 and continuing until p 46, line 25.
-- 10 of 17 --
11
It is unquestionable that both retaining walls require a complete rebuild which
necessitates the removal of all the vegetation which renders any other further
complaints of [vegetation] encroachment or future pruning moot.
Survey Evidence
[35] The Tribunal has also received written evidence of the results of a boundary survey
conducted on 7 June 2024 by Mr Allan McLoughlin, licensed surveyor, of ‘A&T
Surveying’.
[36] A&T Surveying have placed survey pegs on the actual boundary between 7 Atlas
Place and 130 Fig Tree Pocket Road, and these pegs were able to be observed by the
Tribunal during a site visit conducted as part of the proceedings on 1 October 2025.
[37] The boundary survey reveals that the (upper) boundary fence is wholly within the land
at 7 Atlas Place, whereas the lower cold-formed steel retaining wall—constructed
approximately one metre further to the West—is situated wholly within the land at
130 Fig Tree Pocket Road, with the shared boundary located approximately
equidistant between these two appurtenances.
[38] The parties accept24 the validity of the survey findings, and each now agrees that it
would be preferable for the dividing fence to be erected on the surveyed boundary.25
The Relevant Law
[39] Relevantly, the Neighbourhood Disputes (Dividing Fences and Trees) Act 2011 (Qld)
provides:
16 Meaning of fencing work
Fencing work, for a dividing fence, means—
(a) the design, construction, modification, replacement, removal, repair or
maintenance of the whole or part of the dividing fence; and
(b) the surveying or preparation of land, including the trimming, lopping
or removal of vegetation, along or on either side of the common
boundary of adjoining lands for a purpose mentioned in paragraph (a);
and includes—
(c) the planting, replanting and maintenance of a hedge or similar vegetative
barrier as the dividing fence; and
(d) the cleaning, deepening, enlargement or alteration of a ditch,
embankment or watercourse that serves as the dividing fence; and
(e) obtaining an approval required for fencing work.
(Emphasis not in the original, yet included here by the Tribunal)
20 Liability for fencing work
(1) If there is no sufficient dividing fence between 2 parcels of land
consisting of adjoining land, an adjoining owner is liable to contribute to
carrying out fencing work for a sufficient dividing fence.
24 Transcript p 12, lines 9–30; p 38 lines 39–41; p 65, lines 35–36.
25 Ibid p 80, lines 9–10; p 82, lines 25–26.
-- 11 of 17 --
12
Note—
An adjoining owner may contribute by a payment of an amount or
provision of labour or materials.
(2) If carrying out fencing work includes construction or replacement of a
sufficient dividing fence, the fence must be constructed or replaced on the
common boundary other than to the extent it is impracticable to do so
because of natural physical features.
(3) However, other than for urgent fencing work, subsection (1) is only
enforceable if—
(a) the adjoining owners have agreed under this chapter about carrying
out the fencing work; or
(b) QCAT has ordered that the fencing work be carried out.
(4) To remove any doubt, it is declared that subsection (1) applies even if—
(a) there is already a dividing fence other than a sufficient dividing
fence; or
(b) one or both parcels of land are vacant land.
21 Contribution between adjoining owners—generally
(1) Adjoining owners are each liable to contribute equally to carrying out
fencing work for a sufficient dividing fence.
(2) An adjoining owner who wants to carry out fencing work for a dividing
fence to a standard greater than the standard for a sufficient dividing fence
is liable for the fencing work to the extent that it is greater than the
standard for a sufficient dividing fence.
35 Orders about carrying out fencing work
(1) QCAT may, for an application in relation to fencing work for a dividing
fence, decide and order any 1 or more of the following—
(a) the line on which the fencing work is to be carried out, whether or
not that line is on the common boundary of the adjoining land;
(b) the fencing work to be carried out, including the kind of dividing
fence involved;
(c) the way in which contributions for the fencing work are to be
apportioned or reapportioned or the amount that each adjoining
owner is liable to pay for the fencing work;
(d) the part of the dividing fence to be constructed or repaired by either
adjoining owner;
(e) the time by which the fencing work is to be carried out;
(f) any other work to be carried out that is necessary to carry out
the fencing work ordered under this section including work for
a retaining wall;
(g) that, in the circumstances, no dividing fence is required for all or
part of the boundary of the adjoining lands;
-- 12 of 17 --
13
(h) that a fence has been used, or could reasonably be used, as a
dividing fence under section 15;
(i) the amount of compensation payable to an adjoining owner for
damage or destruction to a dividing fence caused by another
adjoining owner or a person mentioned in section 26(1)(b);
(j) that an adjoining owner remove a thing attached to a dividing fence
and restore the dividing fence;
(k) the amount of compensation payable to an adjoining owner for the
removal of a fence under section 33(3).
(2) The occupation of land on either side of a dividing fence, as a result of an
order that fencing work is to be carried out on a line other than on the
common boundary of the adjoining lands, does not affect the title to, or
possession of, the land.
(Emphasis not in the original, yet included here, by the Tribunal)
Tribunal Consideration
[40] On the basis of the photographs, the site visit conducted by the Tribunal, and the
positions now expressed by the parties during their evidence and in their final
submissions, it is readily apparent that the wooden fence and the lower cold-formed
steel retaining wall are completely inadequate, and that these appurtenances are in dire
need of replacement.
[41] On the basis of the evidence given by each of the Applicant and the Respondents, and
the evidence from the Engineer Mr Balanag, and the views now formed by the
Tribunal from the photographs, as aided by the situational appreciation afforded by
the site inspection, the Tribunal determines—for purposes of ss 13(1)(c)(ii) and 20(1)
of the Act—that there is not, at present, any ‘sufficient fence’ between Number 7 and
Number 130. Section 21(1) of the Act is thus enlivened.
[42] Although the Respondents contend26 that scouring of the land caused by rainwater
runoff from Number 7 has been the primary cause for the observed poor condition of
the wooden fence and the cold-formed steel retaining wall, there is scant evidence in
support of that, beyond speculation and assertion. The state of the evidence is
insufficient to allow any specific finding by the Tribunal in relation to the contribution
that may have been made by rainwater runoff.
[43] The Tribunal accepts the engineering evidence of Mr Balanag, which is to the effect
that the failure of both the wooden fence and the cold-formed steel retaining wall arise
primarily as a consequence of the inadequate construction of the cold-formed steel
retaining wall, as then exacerbated over time by the adverse influence of the trees
growing near to it.
[44] Although the Respondents contend that the original Koppers log retaining wall and its
cold-formed steel replacement were constructed entirely for the benefit of Number
7—and accordingly should now be the sole responsibility of the Applicant—the
Tribunal is unable to accept that contention. There are a number of reasons for that.
26 Leakey’s Case, supra, n 16.
-- 13 of 17 --
14
[45] Firstly, other than the opinion expressed by the Respondents, there is no specific
evidence that the original Koppers log wall was constructed entirely for the benefit of
Number 7. When viewed via the lens of the house and land at Number 130 having
been developed prior to the house at Number 7, the original Koppers log wall was an
appurtenance that was more likely to have been erected as part of enabling the
development of the land at Number 130, rather than at Number 7.
[46] Secondly, Leakey’s Case and the notion that the owner of land above a retaining wall
assumes responsibility for it is not necessarily reflective of current Australian law,
which considers retaining walls as able, in site-specific circumstances, to provide
mutual benefits to adjoining land owners, above and below the wall. In this regard, in
Yared v Glenhurst Gardens Pty Ltd [2002] NSWSC 11 Austin J has observed:
In my opinion, however, the principle in Leakey's case does not lead to the
conclusion that in the present case, the defendant has a duty to take all necessary
steps at its own expense to retain its land, after the collapse of the retaining wall.
There is an analogy with Leakey's case, in that in the present case the defendant's
land now overhangs the plaintiff's land and there is a real risk of slippage and
consequently further damage to the plaintiff. But the present state of affairs has
arisen because of the collapse of the retaining wall, which retained the
defendant's land adequately for the whole of the time that the defendant and the
plaintiff had been owners and occupiers of their respective properties, until
August 1998. The retaining wall was not, as I have said, wholly on the
defendant's land. It benefited the defendant by retaining the defendant's soil, and
it benefited the plaintiff by maximising the plaintiff's use of her land and
protecting the plaintiff from landslip. The problem has arisen because the wall
is no longer there to confer these mutual benefits.
These considerations suggest that while the defendant has a relevant duty under
the Leakey principle, it is not a duty to replace the retaining wall or otherwise
retain its land wholly at its own expense. As Megaw LJ said (at 524) in the
passage quoted above, it is a duty to do that which is reasonable in the
circumstances, and no more or less than that. Citing a passage from the Privy
Council's advice in Goldman v Hargrave, his Lordship contemplated (525) that
where the hazard arises on a small parcel of land, threatening a neighbour with
substantial interests, the owner of the small property should not have to do so
much as one with larger interests of his own at stake and greater resources to
protect them: if the small owner does what he can and promptly calls on his
neighbour to provide additional resources, he may be held to have done his duty.
In my opinion those observations, while not directly applicable to the present
case, suggest that in an appropriate case the landowner's duty may be to
contribute to the cost of remedial work, rather than to pay the whole of the cost.
In my opinion this is such case. Here the defendant's duty with respect to the
risk of further landslip might be discharged by contributing an appropriate
portion to the cost of remedial work, and by allowing access to contractors so
that the work can be carried out.
Therefore, in my view the plaintiff is not entitled to the mandatory quia timet
injunction that she seeks, because the defendant has no duty to carry out the
whole of the remedial work alone. Even if the law as stated in Leakey's case
required me to recognise such a duty, I would decline for discretionary reasons
to make the mandatory order that the plaintiff seeks. The leading authority on
final mandatory injunctions is Redland Bricks Ltd v Morris [1970] AC 652 (cf
Lawlor v Johnston [1905] VLR 714). The Redland Bricks case indicates that the
-- 14 of 17 --
15
granting of a mandatory injunction is always a discretionary matter (at 655 for
Lord Upjohn).27
[47] Finally, it bears observing that the parties are now in agreement that the new fence
should be erected on their common boundary. Here, the topography is such that the
erection of fence on the common boundary will not be possible unless a new retaining
wall is also constructed on the boundary. This is consistent with the usual expectation
expressed in the Act that boundary fences should ordinarily be erected on the common
boundary;28 as well as the power conferred on the Tribunal by way of s 35(1)(f) of the
Act to order ‘any other work to be carried out that is necessary to carry out the fencing
work ordered under this section including work for a retaining wall’.
Tribunal Determination:
[48] The Tribunal determines on the basis of the evidence given by Mr Balanag that the
existing cold-formed steel retaining wall is an associated appurtenance, by reason that
it was always necessary for the support of the fence,29 yet by reason of its dilapidation
through age, adverse influence over time caused by surrounding trees, and an
inadequate original construction, the cold-formed steel retaining wall has not achieved
that intent. For purposes of s 35(1)(f) of the Act it is necessary to order the
replacement of the cold-formed steel retaining wall as part of any fencing works now
ordered by the Tribunal.
[49] The Tribunal further determines that a timber paling fence is appropriate for the
replacement fence, being a style of fence desired by the parties, and that is consistent
with a style of fence commonly used in Chapel Hill, and throughout greater Brisbane.
[50] Given the evidence before it, the Tribunal determines that the associated retaining wall
should be constructed using concrete sleepers and galvanised steel posts, and should
be constructed to the relevant Australian standard, which Mr Balanag informs is AS
4678 – Earth Retaining Structures. The Tribunal will order that there be an
engineering design specification for the replacement retaining wall.
Tribunal Orders
[51] Pursuant to the powers conferred on the Tribunal by s 35 of the Act, the Tribunal
orders as follows:
1. A new boundary fence and associated retaining wall are to be constructed on the
surveyed boundary between Number 7 Atlas Place, Chapel Hill, and Number
130 Fig Tree Pocket Road, Chapel Hill, in accordance with an engineering
design specification obtained from a licensed engineer, to be engaged by the
Applicant. Obtaining any necessary certification or Council approval for those
works is the responsibility of the Applicant.
2. The associated retaining wall is to be constructed in accordance with the
engineering design required by Order (1) above, using concrete sleepers and
galvanised steel posts, and is to be constructed in accordance with the
requirements of the Applicable Australian Standard(s). The boundary fence is
to be constructed in timber (comprised by hardwood posts and rails, with treated
27 [2002] NSWSC 11, [107]–[109].
28 Act ss 12(1), s 20(2).
29 Battiato v Clifton [2025] NSWLEC 1391.
-- 15 of 17 --
16
pine palings with a gap between palings of no more than 5mm), to a height of
1.8 metres. Palings are to be placed on the Eastern-facing side of the new fence.
3. The new boundary fence and associated retaining wall is to be constructed on,
or as near to the surveyed boundary as is practically achievable, but no less than
500mm further to the West of the existing timber fence.
4. All vegetation necessary for the construction of the new boundary fence and
associated retaining wall is to be removed as part of the fencing works required
by these orders.
5. Removal of the existing timber wooden fence on the land at Number 7 Atlas
Place and removal of the existing cold-formed steel retaining wall on the land at
Number 130 Fig Tree Pocket Road are also fencing works for the purposes of
these orders.
6. The costs of any engineering design, council certification, as well as the costs
for necessary materials and construction/labour costs for the fencing works,
including foundation and drainage, as now required by Orders (1)–(5) above, are
to be borne equally (i.e. 50:50) by the Applicant and the Respondents. The costs
that must be shared by the Respondents are confined to that portion of fencing
works along the shared boundary between the properties and do not extend to
any fencing costs beyond either the Northern or Southern boundary of the land
at 130 Fig Tree Pocket Road at Chapel Hill.
7. The costs of any necessary preliminary works beyond those contemplated by
Orders (4) and (5) above, (including but not limited to any relocation of sheds,
garden beds, pool fences, paving, etc), and post-construction remediation or
landscaping costs arising after the fencing works required by Orders (1)–(5)
above, are to be borne on the basis that the Applicant will pay for any such costs
arising at Number 7 Atlas Place, and the Respondents will pay for any such costs
arising at Number 130 Fig Tree Pocket Road.
8. Any replacement planting in the vicinity of the new boundary fence and
associated retaining wall at the conclusion of the ordered fencing works is to be
confined to low shrubbery, or ground covering plants that do not have a root
structure that is capable of detrimentally affecting either the new fence, or the
associated retaining wall.
9. Within six (6) weeks of obtaining an engineering design (Order (1), above) the
Applicant will provide the Respondents with two (2) quotes for the necessary
works (Orders (2), (4) & (5) above), and the Respondents are at liberty to select
between the provided quotes within 14 days after provision of the quotes. In the
event of no response from the Respondents to the provided quotes the Applicant
is at liberty to determine which of the two quotes will be accepted.
10. The parties will provide all necessary access upon their land for trades and/or
designing engineers to do any works ancillary, necessary or incidental to the
performance of these orders.
11. In the event of any non-compliance with these orders by the Respondents the
Applicant and her contractors are at liberty, pursuant to s 94 of the
Neighbourhood Disputes (Dividing Fences and Trees) Act 2011 (Qld), to enter
upon the land at Number 130 Fig Tree Pocket Road to carry out the necessary
-- 16 of 17 --
17
works upon the giving of at least seven (7) days’ written notice to the
Respondents. Any costs incurred by the Applicant in the performance of any
works caused by non-compliance with any of these orders by the Respondents
is a sum that may be recovered, in full, by the Applicant from the Respondents.
12. The Applicant will bear all of the costs associated with the erection and
certification of a fire-rated wall, wholly within the land at 7 Atlas Place Chapel
Hill.
-- 17 of 17 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2025/479