Bace Investments Pty Ltd v Queensland Building and Construction Commission [2025] QCAT 442
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Bace Investments Pty Ltd v Queensland Building and
Construction Commission [2025] QCAT 442
PARTIES: BACE INVESTMENTS PTY LTD
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(respondent)
APPLICATION NO: GAR299-24
MATTER TYPE: Building matters
DELIVERED ON: 6 November 2025
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Scott-Mackenzie
ORDERS: 1. The application by Queensland Building and
Construction Commission filed 22 November 2024
to dismiss the proceeding is granted.
2. The proceeding is dismissed.
3. Any application for costs in the proceeding be filed
in the Tribunal and given to the other party by
email, by:
4:00pm on 1 December 2025.
4. A reply to any application for costs in the proceeding
be filed in the Tribunal and given to the other party
by email, by:
4:00pm on 12 January 2026.
CATCHWORDS: ADMINISTRATIVE LAW – ADMINISTRATIVE
TRIBUNALS – QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL – where applicant
applied to dismiss the proceeding – whether the internal
review decision is reviewable – whether the application
lacks utility – whether the application for external review
should be dismissed
Queensland Building and Construction Commission Act
1991 (Qld), s 72, s 72A, s 75, s 77, s 86, s 86A, s 86B, s
86C, s 86D, s 86E, s 111C, sch 1B, s 4
-- 1 of 18 --
2
Queensland Civil and Administrative Tribunal Act 2009
(Qld), s 17, s 18, s 20, s 21, s 24, s 47
ACN 148 877 525 Pty Ltd v Queensland Building and
Construction Commission [2022] QCAT 72
Australian Broadcasting Tribunal v Bond [1990] HCA 33
Body Corporate for Parkside Bulimba CTS46539 v
Queensland Building and Construction Commission &
Anor [2024] QCATA 109
Body Corporate for Jade Apartments CTS40720 v Lee
Crocker v Queensland Building and Construction
Commission [2020] QSC 24
Fraser Property Developments Pty Ltd v Sommerfeld (No.
1) [2005] QCA 134
Jorg & Anor v Queensland Building and Construction
Commission & Anor [2021] QCATA 134
JM Kelly (Project Builders) Pty Ltd v Queensland Building
Services Authority [2013] QCAT 502
Queensland Building and Construction Commission v B &
L Constructions Qld Pty Ltd [2023] QCATA 71
Stephenson v Queensland Building and Construction
Commission [2017] QCAT 212
Tanna v Queensland Building and Construction
Commission [2023] QCATA 81
TCQ Pty Ltd ATF Midgley Family Trust v Queensland
Building and Construction Commission [2023] QCAT 485
The Body Corporate for Jade Apartments CTS 40720
v Queensland Building and Construction Commission
[2016] QCAT 445
Vytla v Queensland Building and Construction
Commission [2024] QCAT 346
APPEARANCES &
REPRESENTATION:
This matter was heard and determined on the papers
pursuant to section 32 of the Queensland Civil and
Administrative Tribunal Act 2009 (Qld)
REASONS FOR DECISION
Application
[1] On 22 November 2024 the respondent (‘Commission’) made application to the
Tribunal to dismiss the proceeding under section 47 of the Queensland Civil and
Administrative Tribunal Act 2009 (Qld) (‘QCAT Act’) (‘interlocutory application’).
It filed written submissions in support of the application.
[2] The applicant (‘Bace Investments’) filed written submissions in reply to the
application.
Issues
[3] The central issue to be decided by the Tribunal is whether it has jurisdiction to hear
and decide the proceeding. Alternatively, it is submitted, the original application lacks
utility and should be dismissed.
-- 2 of 18 --
3
Background
[4] Bace Investments does not dispute the background to the application set out in the
Commission’s submissions.
[5] On 10 August 2015, about 10 years ago, Bace Investments as building contractor and
Mr Kieran Bryce as building owner entered a Queensland New Homes Construction
Contract (‘contract’) for the construction of a home at 23 Bergamot Circuit, Griffin
(‘home’).
[6] On 10 August 2015 Bace Investments insured the building work under the statutory
insurance scheme with the policy providing cover until 10 February 2022.
[7] On 10 March 2016 the building work reached practical completion.
[8] On 22 December 2016 Mr Bryce became aware of the building defect.
[9] On 9 September 2023 Mr Bryce asked the Commission to give a direction to Bace
Investments to rectify building work he considered defective or incomplete. The
complaint item is in the following terms:
Item Location Description Date first noticed Attachments
1. En suite Water leaking in en suite shower.
Leak has been identified since
approx 22/12/2016. Water leak
comes out of shower, through
internal walls onto carpet. Leak
has attempted to be bandaid
patched over the years by builder.
Leak still present with mould
22/12/2016 4
[10] On 25 October 2023 the Commission decided not to give a direction to Bace
Investments to rectify or remedy the building work on the ground the application was
outside the time in section 72A(4) of the Queensland Building and Construction
Commission Act 1991 (Qld) (‘QBCC Act’) (‘original decision’).
[11] The work was inspected by the Commission on 14 February 2024. It gave to Mr Bryce
and Bace Investments a copy of the report. The decision of the Commission on the
complaint item is in the following terms:
The installation of the waterproof membrane to the ensuite wall has not been
installed in accordance with the NCC 2015 BCA Volume 2 in that water is
able to escape behind linings, or into concealed spaces, resulting in damage
to building elements
Pertains item 1 of the QBCC Complaint Form
[12] The Commission then gave to Bace Investments a letter dated 15 February 2024 (‘15
February 2024 letter’). The letter confirms the Commission will not be directing Bace
Investments to rectify or remedy the work on the ground mentioned in the original
decision. It then continues:
Kieran Bryce may still be entitled to a claim under the Queensland Home
Warranty Scheme. This this is your opportunity to have the necessary work
rectified by a licensed contractor, before assessment of Kieran Bryce's
entitlement to a claim.
-- 3 of 18 --
4
If the work detailed in the attached Defective Work List is not addressed, the
QBCC will consider if Kieran Bryce is entitled to a claim under the
Queensland Home Warranty Scheme.
The QBCC may recover payment made on an insurance claim as a debt from
the building contractor or a director (including a director at the time the
building work was carried out and a director at the time a payment is made
by the QBCC), as allowed under the Queensland Building and Construction
Commission Act 1991.
In addition, if a claim is approved, it will appear on the register of licensees
which is available to the public on the QBCC’s website.
[13] On 13 March 2024 the Commission determined the work had not been rectified or
remedied. A notice to that effect was given by the Commission to Bace Investments.
[14] Bace Investments, on 14 March 2024, applied for internal review. The decision
identified in the application was the 15 February 2024 letter.
[15] On 11 April 2024 the internal reviewer completed the internal review. She confirms
the original decision not to give a notice to rectify or remedy on the ground the
application is outside the time in section 72A(4) of the QBCC Act (‘internal review
decision’).
[16] The decision reviewed identified in the decision notice is the 15 February 2024 letter.
[17] On 30 April 2024 Bace Investments made application to the Tribunal to review the
internal review decision.
[18] In summary:
(a) on 25 October 2023 the Commission decided not to give a notice to Bace
Investments to rectify or remedy the defective work on the ground the
application was outside the time in section 72A(4) of the QBCC Act;
(b) the Commission gave to Bace Investments the 15 February 2024 letter
confirming it will not be directing Bace Investments to rectify or remedy the
defective work on the ground mentioned in the original decision and stating the
owner may be entitled to claim under the statutory insurance scheme;
(c) on 14 March 2024 Bace Investments applied for internal review of the 15
February 2024 letter, not the original decision;
(d) on 11 April 2024 the internal reviewer confirmed the original decision not to
give to Bace Investments a direction to rectify or remedy the work on the ground
mentioned in the original decision. The decision reviewed is the 15 February
2024 letter. It records submissions about the statutory insurance scheme which
cannot be considered because the original decision being reviewed is the
decision not to direct Bace Investments to rectify or remedy the work; and
(e) on 30 April 2024 Bace Investments made application to the Tribunal to review
the internal review decision.
Internal review decision
[19] The internal review decision is a review of the 15 February 2024 letter. The decision
reads:
-- 4 of 18 --
5
I have decided NOT to give a Direction to Rectify as the Statutory Timeframe
has expired.
[20] After setting out the background and Bace Investments’ submissions, the internal
review decision continues:
The letter and attachment of 7 February 2024 is a Notice Defective works
list (NODW). The QBCC Act allows for the reviewable decision under
S86(e) to be a decision to not give a direction to rectify or remedy.
The NODW is issued to allow the Director of the cancelled and or liquidated
company to take relevant and or appropriate action to rectify the alleged
defects identified by the affected party if the Director see fit.
Further, it reserves the QBCC ability to recover any debt that maybe incurred
at a later point in time if a claim is paid under the Statutory Insurance
Scheme.
[21] The decision highlights the confusion in the following paragraph. It reads:
During the course of the Internal review, the applicant has made reference to
the Insurance Claim against the Statutory Scheme, and the fundamental
elements that should be considered before accepting a claim. These
comments and allegations cannot be considered under this internal review
because the decision before me under Section 86(e) is relative to whether a
decision to issue a Direction to rectify or remedy or decision to not give a
direction.
[22] It then refers to legislation and policy considerations, and under the subheading
‘Statutory Timeframe’ continues:
Pursuant to sections 72(2A) and 72A(4) of the QBCC Act, a DTR cannot be
given more than six years and six months after the “building work” is
complete or left in an incomplete state.
Section 72A(4) of the QBCC Act provides a direction to rectify cannot be
given more than 6 years and 6 months after the building work was completed
or left in an incomplete state (the statutory period). However, an extension of
time for giving a direction to rectify may be granted by the Queensland Civil
and Administrative Tribunal (QCAT) if it is satisfied, upon application by
the QBCC, that there are sufficient reasons for extending the time to give
the direction.
The complaint item relates to building work that was completed on or about
10 March 2016 when the applicant provided a form 21, final inspection
certificate. Accordingly, the final date for the QBCC to be able to give a
direction to rectify was on 10 September 2022.
However, I have noted that complaint form was lodged on 9 September 2023
out of statutory time frame. As such, I am satisfied that the time to issue a
DTR has expired and a DTR cannot be issued.
Legislation
[23] Usefully, the Commission sets out the legislation relevant to the issues raised. It
commences with section 72 of the QBCC Act, the power to require rectification of
building work and remediation of consequential damage. Relevantly, the section
provides:
-- 5 of 18 --
6
(1) This section applies if the commission is of the opinion that:
(a) building work is defective or incomplete; or
(b) consequential damage has been caused by, or as a consequence of,
carrying out building work.
(2) The commission may direct the person who carried out the building work
to do the following within the period stated in the direction:
(a) for building work that is defective or incomplete - rectify the
building work;
(b) for consequential damage—remedy the damage.
(2AA) and (2A) …
(3) In deciding whether to give the direction, the commission may take into
consideration all the circumstances it considers are reasonably relevant
and, in particular, is not limited to a consideration of the terms of the
contract for carrying out the building work (including the terms of any
warranties included in the contract).
(4) …
(5) The commission is not required to give the direction if the commission is
satisfied that, in the circumstances, it would be unfair to the person to
give the direction.
Example for subsection (5):
The commission might decide not to give a direction for the
rectification of building work because an owner refuses to allow a
building contractor to return to the owner’s home or because an
owner’s failure to properly maintain a home has exacerbated the
extent of defective building work carried out on the home.
(6)–(8) …
[24] Subsection (4) of section 72A provides:
A direction to rectify or remedy cannot be given more than 6 years and 6 months
after the building work to which the direction relates was completed or left in
an incomplete state unless the tribunal is satisfied, on application by the
commission, that there is in the circumstances of a particular case sufficient
reason for extending the time for giving the direction and extends the time
accordingly.
[25] Reviewable decisions are provided for in section 86. Relevantly, a decision to give a
direction to rectify or remedy, or not to give the direction, is a reviewable decision.1
[26] A person who is given, or is entitled to be given, a notice of a reviewable decision
may apply to the internal reviewer to have the decision reviewed.2
[27] The requirements for an internal review application are set out in section 86B.
[28] Section 86C provides that if an internal review application is made under section 86B,
the internal reviewer must, as soon as practicable but within the required period, make
1 QBCC Act s 86(1)(e).
2 QBCC Act s 86A.
-- 6 of 18 --
7
the internal review decision as if the reviewable decision the subject of the application
had not been made.
[29] Reviewable decision is defined in section 86E of the QBCC Act. It means:
(a) a reviewable decision within the meaning of subdivision 1, other than a
decision that was the subject of an internal review under subdivision 1;
or
(b) an internal review decision within the meaning of subdivision 1.
[30] The Tribunal’s review jurisdiction is provided for in division 3 of part 1 of chapter 2
of the QCAT Act. Section 17, under the heading ‘Generally’, provides:
(1) The tribunal’s review jurisdiction is the jurisdiction conferred on the
tribunal by an enabling Act to review a decision made or taken to have
been made by another entity under that Act.
(2) For this Act, a decision mentioned in subsection (1) is a reviewable
decision and the entity that made or is taken to have made the decision is
the decision-maker for the reviewable decision.
[31] When the review jurisdiction is exercised is provided for in section 18 of the QCAT
Act. It is in the following terms:
(1) The tribunal may exercise its review jurisdiction if a person has, under
this Act, applied to the tribunal to exercise its review jurisdiction for a
reviewable decision.
(2) A person may apply to the tribunal to exercise its review jurisdiction for
a reviewable decision, and the tribunal may deal with the application,
even if the decision is also the subject of a complaint, preliminary inquiry
or investigation under the Ombudsman Act 2001.
[32] A review involves a fresh hearing.3 Section 21 contains provisions requiring a
decision-maker to help the Tribunal.
[33] The functions for the review jurisdiction are provided for in section 24. Subsections
(1) and (2) provide:
(1) In a proceeding for a review of a reviewable decision, the tribunal may:
(a) confirm or amend the decision; or
(b) set aside the decision and substitute its own decision; or
(c) set aside the decision and return the matter for reconsideration to
the decision-maker for the decision, with the directions the tribunal
considers appropriate.
(2) The tribunal’s decision under subsection (1)(a) or (b) for a reviewable
decision:
(a) is taken to be a decision of the decision-maker for the reviewable
decision except for the tribunal’s review jurisdiction or an appeal
under part 8; and
3 QCAT Act s 20.
-- 7 of 18 --
8
(b) subject to any contrary order of the tribunal, has effect from when
the reviewable decision takes or took effect.
[34] The Tribunal is given power to dismiss, strike out and decide if a proceeding, or part,
is unjustified. Sections 47(1) and (2) relevantly provide:
(1) This section applies if the tribunal considers a proceeding or a part of a
proceeding is:
(a) frivolous, vexatious or misconceived; or
(b) lacking in substance; or
(c) otherwise an abuse of process.
(2) The tribunal may:
(a) if the party who brought the proceeding or part before the tribunal
is the applicant for the proceeding, order the proceeding or part be
dismissed or struck out; or
(b) for a part of a proceeding brought before the tribunal by a party
other than the applicant for the proceeding—
(i) make its final decision in the proceeding in the applicant’s
favour; or
(ii) order that the party who brought the part before the tribunal
be removed from the proceeding; or
(c) make a costs order against the party who brought the proceeding
or part before the tribunal to compensate another party for any
reasonable costs, expenses, loss, inconvenience and
embarrassment resulting from the proceeding or part.
Does the Tribunal have jurisdiction to hear and decide the proceeding?
Commission’s submissions
[35] The Commission’s submissions identify the issue to be decided by the Tribunal and
background to the original application. It then refers to the relevant legislation and
several decided cases, including Fraser Property Developments Pty Ltd v Sommerfeld
(No. 1)4, JM Kelly (Project Builders) Pty Ltd v Queensland Building Services
Authority5, TCQ Pty Ltd ATF Midgley Family Trust v Queensland Building and
Construction Commission6 (‘TCQ’), The Body Corporate for Jade Apartments
CTS40720 v Queensland Building and Construction Commission7 (‘Jade
Apartments’), Queensland Building and Construction Commission v B & L
Constructions Qld Pty Ltd8 (‘B & L Constructions’) and Vytla v Queensland Building
and Construction Commission9 (‘Vytla’).
[36] I will return to the cases later in these reasons for decision.
4 [2005] QCA 134.
5 [2013] QCAT 502.
6 [2023] QCAT 485.
7 [2016] QCAT 445.
8 [2023] QCATA 71.
9 [2024] QCAT 346.
-- 8 of 18 --
9
[37] The submissions then address the application for early dismissal. Several cases are
referred to by the Commission, including Vytla. There, the Tribunal says:
[35] In considering whether to strike out a proceeding pursuant to s 47 of the
QCAT Act, I am satisfied I have the requisite material and have received
the necessary assistance from the parties to make a definite and certain
conclusion.
[36] The principles in considering whether to exercise the discretion to strike
out a proceeding were considered by Chief Justice Barwick in General
Industries Inc v Commissioner for Railways. His Honour said:
Although I can agree with Latham C.J. in the same case when he
said that the defendant should be saved from the vexation of the
continuance of useless and futile proceedings … in my opinion
great care must be exercised to ensure that under the guise of
achieving expeditious finality a plaintiff is not improperly
deprived of his opportunity for the trial of his case by the appointed
tribunal. On the other hand, I do not think that the exercise of the
jurisdiction should be reserved for those cases where argument is
unnecessary to evoke the futility of the plaintiff's claim. Argument,
perhaps even of an extensive kind, may be necessary to
demonstrate that the case of the plaintiff is so clearly untenable that
it cannot possibly succeed.
[37] The Tribunal is limited in a review of this decision to asking whether that
decision was the correct and preferable one. It is not an opportunity for
the Tribunal to make a completely different type of decision unrelated to
the one under review, for example, that a decision to issue a direction to
rectify be made instead. (Citations omitted)
[38] The Commission then submits the 15 February 2024 letter is not a direction to rectify
building work under section 72(2) of the QBCC Act but was taken to be a decision
not to give a direction to rectify. The internal review decision is not a reviewable
decision, applying B & L Constructions. It submits an internal review decision will
only be properly made if it relates to a properly made application for internal review
which in turn means the applicant must apply for review of a reviewable decision.
Bace Investments’ submissions
[39] Bace Investments submits the application is to review the internal review decision.
The decision is a reviewable decision within the meaning of section 86(1)(e) of the
QBCC Act.
[40] It disagrees with the Commission’s interpretation of B & L Constructions and Vytla
and submits the internal review decision is a reviewable decision irrespective of
whether the internal reviewer correctly or incorrectly characterised the 15 February
2024 letter.
[41] Bace Investments refers to the decision of the Tribunal in Stephenson v Queensland
Building and Construction Commission10. There, at [22], the Tribunal said:
The QBCC, after failing to correctly identify the ‘decision’ to be reviewed then
refused the internal review by considering the delay of 381 days. It says because
the IRU application was not correctly made within the requirement of section
10 [2017] QCAT 212.
-- 9 of 18 --
10
86B (i.e. within 28 days) no decision could be made under section 86C. This is
clearly wrong. If a review is requested it can be refused on the basis that there
is no reviewable decision. This decision, if appropriate, can be reviewed. This
is in fact what was done and notice of review rights were provided in that letter.
At that point the IRU letter was a reviewable decision. (Citation omitted)
[42] The 15 February 2024 letter, Bace Investments submits, is not sanctioned by
legislation. It is a ‘new decision’ and clearly directs rectification of the work.
[43] In the alternative, Bace Investments submits, the 15 February 2024 letter is a
reviewable decision by reason of section 86B of the QBCC Act it having made the
application within 28 days after it became aware of the decision.
Decided cases
[44] The Commission refers to several decided cases of the Tribunal and Appeal Tribunal.
In Jade Apartments, the applicant, on 20 June 2014, complained about defective work.
The Commission decided not to give a notice to rectify the building work on the
ground the company was not the building contractor and the company responsible had
been wound up and was no longer entitled to a licence under the QBCC Act.
[45] Subsequently, on 4 May 2016, the applicant again asked the Commission to give a
direction to rectify the building work, explaining in an accompanying letter the
complaint item restates the first complaint item.
[46] The Commission internally reviewed the original decision on the first complaint. It
was confirmed.
[47] The owner then applied to the Commission for internal review of the second
complaint. It did not decide the application but informed the owner it had upheld the
decision on the first complaint.
[48] The owner applied to the Tribunal for review of the two decisions.
[49] The Tribunal decided there is no decision in the list of reviewable decisions in section
86 of the QBCC Act which would extend to a decision to refuse to investigate a
complaint or refuse to consider an internal review application. It then continued:
A decision to give a direction to rectify or remedy or not to give the direction is
a reviewable decision under s86(1)(e). The decision on the first complaint not
to give a direction to rectify may be a decision of this character. A decision to
refuse to investigate a second complaint about the same subject matter which,
if investigated, may have lead to such a decision, is not.11
[50] The decision may be distinguished from the internal review decision now before the
Tribunal. The application for external review of the first decision was out of time, the
second decision was not a reviewable decision.
[51] In B & L Constructions, a building contractor constructed a home. It was sold and the
new owner complained about defective work. The complaint was disallowed but then
allowed on internal review. The building contractor applied to the Tribunal for review
of the internal review decision.
[52] The Tribunal decided it has jurisdiction to hear and decide the proceeding. At [11], it
observed:
11 Jade Apartments [5].
-- 10 of 18 --
11
The original decision of the appellant to reject the claim was a reviewable
decision within the meaning of subdivision 1, being within s 86(1)(h), a decision
to disallow a claim under the statutory insurance scheme, but it was the subject
of an internal review, so it does not satisfy paragraph (a). But as a result of the
internal review, there was an “internal review decision within the meaning of
subdivision 1” …
[53] It later continued:
In the present case, the internal reviewer made a decision, so there was an
internal review decision for the purposes of s 86(1) and hence within the
meaning of subdivision 1. If one reads the words of s 86E(b) literally, there was
also an internal review decision for the purposes of paragraph (b) of the
definition of “reviewable decision” in s 86E. That decision affected the builder,
because of the statutory indemnity in the Act s 71, so it was entitled to apply to
the Tribunal for review of that decision under s 87. That was the effect of the
decision of the Member. Unless the terms of s 86E(b) are read down in some
way, it was correct, and the appeal must be dismissed.12
[54] The Tribunal concluded the provisions establish that, once there has been an internal
review, the constraints on what are reviewable decisions imposed by section 86 have
been satisfied, so that any internal review decision becomes a reviewable decision.
[55] Here, the internal reviewer did not review the original decision, she reviewed the 15
February 2024 letter. The consequence is that unless the internal reviewed decision
can be said to be a ‘new decision’ that is a reviewable decision, it cannot be said Bace
Investments was a person who is given, or is entitled to be given, notice of a
reviewable decision.
[56] A notice to a director of a building contractor was considered by the Appeal Tribunal
in TCQ. The Commission gave a director a notice informing him it would not be
giving a direction to rectify building work on the ground that it was not registered but
the building owner may be entitled to assistance under the statutory insurance scheme.
[57] The director applied to the Commission for internal review of the decision. The
decision described the original decision as a decision not to give a direction to rectify
under section 72 of the QBCC Act. The internal reviewer found the application by the
building owner was not made within 12 months of the owner becoming aware of the
defective building work, it would be unfair to direct rectification of the work and
decided not to give the direction to rectify.
[58] The owner applied to the Tribunal for review of the internal review decision.
[59] The Tribunal decided the notice to the director is not a reviewable decision within the
meaning of section 86 of the QBCC Act. In so doing, it referred to the decision of
Mason CJ in Australian Broadcasting Tribunal v Bond13, and Jackson J in Crocker v
Queensland Building and Construction Commission14 (‘Crocker’). In the latter case,
his Honour considered a notice about the liability of a director for payment by the
Commission for assistance under the statutory insurance scheme under section 111C
of the QBCC Act. He said:
12 B & L Constructions [12].
13 [1990] HCA 33, [32].
14 [2020] QSC 24.
-- 11 of 18 --
12
Otherwise, on the material before me, the essential plank in the applicant’s case
to set aside the other decisions was that he ought to have been given notice of
the challenged decisions, which I have identified, in either paragraphs (c) or (d).
It is not contended that, under the statute, there was any express requirement for
him to be notified. The apparent difficulty that the implication of such a
requirement would create is that failure to give notice to a director of a building
contractor who may be affected under section 111C would have the
consequence of invalidating every decision which is made by the respondent.
That would be a startling conclusion. Nevertheless, if that is what is required on
the proper construction of the statute, there is no reason to shrink from it.
However, in my view, apart from the fact of the incidence of the liability that is
created under section 111C for a director who meets the requirements for that
Section to apply, there is no reason to think that the statute should require that,
for a valid decision of the kinds identified under paragraphs (c) or (d) to be
made, notice must be given to the director of any company building contractor
as well as to the company itself.
In my view, the fact of the operation of section 111C is not of itself a sufficient
reason to imply that requirement into the statute. It follows that, in the result,
none of the decisions that are challenged on the basis of the ground of absence
of procedural fairness are reviewable under section 20 for the reason that the
respondent was required to give the applicant notice of those decisions.15
[60] The view was repeated by the Tribunal in ACN 148 877 525 Pty Ltd v Queensland
Building and Construction Commission16 (‘ACN 148 877 525’):
This provision allows the QBCC to recover the insurance debt from the
directors personally, thereby displacing the common law separate entity
principle. This applies notwithstanding the company may have been
deregistered. The decision as to whether or not to recover the insurance debt is
made after the scope of works decision and depends upon whether the person
from whom recovery is sought was a director when the relevant building work
was carried out and when the payment under the scheme was made.17 (Citation
omitted)
[61] The Tribunal, in Vytla, considered an original decision building work undertaken on
direction by the Commission was of a satisfactory standard. The internal review
decision was a ‘deemed decision’, a decision the same as the original decision because
it had not been decided within 28 days. The Commission applied to the Tribunal to
strike out the external review proceeding on the ground the internal review decision
is not a reviewable decision.
[62] At [28], the Tribunal said:
I do not accept the submissions of the QBCC to the effect that the Tribunal on
review needs to be satisfied that the original decision was a ‘reviewable
decision’. I agree that this would be relevant if the Tribunal was reviewing the
original decision, but it is not. The Tribunal is reviewing the internal review
decision. The internal review decision is itself a “reviewable decision” within
the meaning of s 86E(b).
[63] The Tribunal’s conclusion is found in [31]:
15 Crocker 1.
16 [2022] QCAT 72.
17 ACN 148 877 525 [53].
-- 12 of 18 --
13
It follows, in my view, that whether the original decision was or was not
properly categorised as a reviewable decision is not relevant. The decision was
categorised as a reviewable decision and was the subject of an internal review.
The internal review decision is a reviewable decision and the Tribunal has
jurisdiction to review it. It follows that the application to strike out should not
be allowed on the basis the Tribunal lacks jurisdiction. That, however, is not the
end of the matter.
[64] The Commission disagrees with the decision in Vytla. It submits, ‘… where an
application for internal review is properly made to the Commission (i.e. pursuant to
section 86A and 86B, being an application for internal review of a “reviewable
decision” listed in section 86 of the QBCC Act), it is irrelevant that the decision
ultimately made within the “internal review decision” is one that is not listed in section
86, because a properly made “internally review decision” is of itself externally
reviewable in the Tribunal pursuant to section 86E(b).’ The submission gives rise to
a need to review the process for an internal review decision.
Internal review application
[65] A person involved in a building dispute, under section 77(1) of the QBCC Act, may
apply, as provided under the QCAT Act, to the Tribunal to have the Tribunal decide
the dispute. However, the person may not apply to the Tribunal unless the person has
complied with a process established by the Commission to attempt to resolve the
dispute.18
[66] The powers of the Tribunal are spelt out in section 77(3). They include ordering
rectification or completion of defective or incomplete tribunal work.19
[67] Building dispute is defined in schedule 2. It includes a domestic building dispute
which in turn includes a claim or dispute arising between a building owner and
building contractor relating to the performance of the reviewable domestic work or a
contract for the performance of reviewable domestic work.
[68] Reviewable domestic work is defined as domestic building work under schedule 1B,
section 4, except as provided in the definition. Here, the contract was a domestic
building contract.
[69] Tribunal work is defined in section 75(1). It includes the erection or construction of
a building. Reviewable domestic work is declared to be tribunal work.20
[70] The power given to the Tribunal is to order rectification or completion of defective or
incomplete tribunal work. Tribunal work includes the erection or construction of a
building. It extends to tribunal work.
[71] Reviewable decision is defined in section 86. It includes a decision to give a direction
to rectify or remedy or not to give a direction.21
[72] Under section 86A(1), a person who is given, or is entitled to be given, notice of a
reviewable decision may apply to the internal reviewer to have the decision reviewed.
However, the subsection does not apply if the person has applied to the Tribunal for
a review of the reviewable decision under subdivision 2.
18 QBCC Act s 77(2).
19 QBCC Act s 77(3)(g).
20 QBCC Act s 75(2).
21 QBCC Act s 86(1)(e).
-- 13 of 18 --
14
[73] The requirements for an internal review application are set out in section 86B. They
include a requirement the application be made within a specified period after the
applicant is given notice of the reviewable decision to which the application relates or
otherwise becomes aware of the decision. In other words, whilst the internal reviewer
may make a new decision under section 86C, it is in respect of the reviewable decision
to which the application relates.
[74] If an internal review application is made under section 86B, the internal reviewer, by
virtue of section 86C(1), must, as soon as practicable but within the required period,
make a new decision as if the reviewable decision the subject of the application had
not been made. However, if the internal reviewer does not decide the application
within the required period, the internal reviewer is taken to have made an internal
review decision at the end of the required period that is the same as the reviewable
decision.22
[75] Several matters flow out of sections 86A–86D. First, a person who is given, or is
entitled to be given, notice of a reviewable decision may apply to the internal reviewer
to have the decision reviewed. The right is confined to a reviewable decision.
[76] Secondly, the internal review application must comply with section 86B. Support for
the view the application must relate to the reviewable decision is found in paragraph
(b)(i). Otherwise, the Commission may decline to make a new decision.
[77] Thirdly, the internal review decision is a new decision unconstrained by the
reviewable decision the subject of the application but, in my opinion, in the context
of the original decision and the reviewable decision to which the internal review
application relates.
[78] Here, the internal review application was to review the 15 February 2024 letter. The
letter is not a reviewable decision; it is an advisory letter. The legislation makes clear
the entitlement to apply to the internal reviewer to have a decision reviewed is a person
who is given, or is entitled to be given, notice of a reviewable decision. The letter did
not fall within the category specified and, hence, the interlocutory application must be
granted.
[79] In case I am wrong, I have also considered whether the review application is lacking
in substance.
Does the original application lack utility?
Commission’s submissions
[80] The Commission, under the subheading Review Application lacking in substance,
submits a decision notice cannot be given because ‘… there is no question arising for
the Tribunal to answer.’ Then, under the subheading ‘Expiry of timeframe for issuing
direction to rectify’, the Commission refers to several decided cases.
[81] In Jorg & Anor v Queensland Building and Construction Commission & Anor23
(‘Jorg’), the Appeal Tribunal, at [43], observes:
Section 24(1) of the QCAT Act begins with the words ‘In a proceeding for a
review of a reviewable decision…’. The section assumes that the tribunal has
jurisdiction in a particular review proceeding. The jurisdiction of a court, or in
22 QBCC Act s 86C(3).
23 [2021] QCATA 134.
-- 14 of 18 --
15
this case a tribunal, is not to be confused with its powers. Where, as here, an
application to review a decision not to issue a direction to rectify is not filed
within 6 years and 6 months of the completion of the building work and where,
as here, there is no application by the commission to extend the time limit, the
tribunal has no jurisdiction to review the decision. Section 24(2)(b) cannot be
relied upon to create a jurisdiction that does not exist.24 (Citation omitted)
[82] In Body Corporate for Parkside Bulimba CTS46539 v Queensland Building and
Construction Commission & Anor25 (‘Parkside Bulimba’), the Appeal Tribunal
allowed an appeal from the Tribunal on the ground the jurisdiction of the Tribunal to
review a decision of the Commission was not limited by section 72A(4) of the QBCC
Act. The section, the decision continues:
… simply prevents the QBCC from sending a direction to rectify after expiry
of the period in s 72A(4) unless an extension of time is sought by the QBCC
and granted by the Tribunal. Once the decision to issue a direction to rectify is
viewed as separate to the direction itself, s 24(2)(b) of the QCAT Act can
properly come into play to deem any substituted decision to have been made on
the date of decision under review which is in this case within the 6-year 6-month
time frame.26
(See also Tanna v Queensland Building and Construction Commission27).
[83] In Parkside Bulimba, the Tribunal decided a question to be answered may arise in
circumstances where the time in section 72A(4) had passed. The circumstances, the
Commission submits, are limited to a decision under review where the direction to
rectify or remedy is given within six years and six months after the building work to
which the direction relates was completed or left in an incomplete state. That is not
what happened here.
[84] Bace Investments submits the 15 February 2024 letter is a direction to rectify. The
Commission disagrees, citing Vytla, at [37]. There, the Tribunal said:
The Tribunal is limited in a review of this decision to asking whether that
decision was the correct and preferable one. It is not an opportunity for the
Tribunal to make a completely different type of decision unrelated to the one
under review, for example, that a decision to issue a direction to rectify be made
instead.
[85] It follows, it is submitted by the Commission, the original application cannot succeed
because it did not give a direction to rectify. Further, the time for giving a direction
under section 72A(4) of the QBCC Act has passed.
Bace Investments’ submissions
[86] Bace Investments’ submissions focus on the 15 February 2024 letter. It should be
declared a ‘nullity’.
[87] Of critical importance, Bace Investments submits, is whether the 15 February 2024
letter is a direction to rectify and merits the internal review decision. It has an arguable
24 Jorg [43].
25 [2024] QCATA 109.
26 Parkside Bulimba [85].
27 [2023] QCATA 81, [49].
-- 15 of 18 --
16
case and it would be in the interests of justice to hear and decide the original
application on its merits.
[88] Bace Investments refers to the decision of the Tribunal in TCQ, in particular [34].
There, the Tribunal set aside an internal review decision on the ground the decision
was not a reviewable decision and went on to consider whether a complaint item was
in time.
[89] Bace Investments’ submissions conclude:
The Applicant submits that it would be in line with the objects of the QCAT Act
for the tribunal to proceed to hear and determine the Review Application on its
merits given the questionable approaches taken by the decision-maker in
relation to the decision under review to ensure fairness and consistency in
decisions by the Commission.
Consideration
[90] Mr Bryce gave the complaint item to the Commission on 9 September 2023, about six
years and nine months after the building work to which the direction relates was
completed or left in an incomplete state. The Commission declined to give a direction
to rectify on the ground the time for a direction had passed.
[91] The 15 February 2024 letter was then given by the Commission to Mr Bryce and Bace
Investments. On 14 March 2024 Bace Investments applied to the internal reviewer to
review the letter. The decision reviewed is in the following terms:
Decision made by Peter Doolan, Building Inspector on 15 February 2024 to
NOT issue a Direction to Rectify (DTR) under Section 72 of the Queensland
Building and Construction Commission Act 1991 (the Act)
[92] The background describes the 15 February 2024 letter as a decision, ‘… not to issue a
Direction to Rectify (DTR) instead issued a Notices of Defective a Work List
(NODW).’ The decision misdescribes the letter. What it does is confirm the complaint
item was given outside the time in section 72A(4) of the QBCC Act and the decision
is a reviewable decision.
[93] The 15 February 2024 letter then goes on to state that, unless the work in the defective
work list is carried out, the building owner may be entitled to assistance under the
statutory insurance scheme.
[94] The internal review decision refers to Bace Investments’ submissions. They include
submissions that:
(a) the 15 February 2024 letter was given outside of, and contrary to, legislation;
(b) the letter is invalid because it retrospectively imposes a responsibility on Bace
Investments for rectification of work; and
(c) the Commission decided by default Bace Investments is not liable for
rectification of work.
[95] The submissions are mistaken. The 15 February 2024 letter is an advisory letter, not
a decision to rectify. It does not impose responsibility on Bace Investments for
rectification work. It states that if the work in the defective work list is not carried out,
Mr Bryce may be entitled to assistance under the scheme. The Commission did not
decide, by default or otherwise, Bace Investments is not liable for rectification work.
It decided the complaint was given outside the time specified in section 72A(4).
-- 16 of 18 --
17
[96] The internal review decision refers to legislation. It concludes by deciding a direction
to rectify or remedy cannot be given because of the time in section 72A(4).
[97] The internal review decision reviews the 15 February 2024 letter. The letter is not a
reviewable decision. Notwithstanding, the decision confirms the original decision.
[98] Leaving to one side the internal review decision is not a review of a reviewable
decision, the issue now to be decided is whether the complaint item is outside the time
in section 72A(4) of the QBCC Act. The Commission, in its submissions, refers to the
decision of the Tribunal in Parkside Bulimba. The exception identified is accepted but
is not advanced by the parties in material filed in the Tribunal. They agreed the
complaint was outside the time in section 72A(4).
[99] The Tribunal may order in terms of section 24(1) of the QCAT Act. Here, the internal
review decision confirmed the original decision. The decision of the Tribunal, in my
opinion, cannot be otherwise.
[100] I am mindful of the provisions of section 47 of the QCAT Act and am satisfied the
Tribunal has before it all of the material relevant to the issue to be decided. Also, I am
mindful of what was said by Barwick CJ in General Steel Industries Inc v
Commissioner for Railways28. There, his Honour the Chief Justice, citing Dixon J (as
his Honour then was) in Dey v Victorian Railways Commissioners29, said:
As I have said, some of these expressions occur in cases in which the inherent
jurisdiction was invoked and others in cases founded on statutory rules of court
but although the material available to the court in either type of case may be
different the need for exceptional caution in exercising the power whether it be
inherent or under statutory rules is the same. Dixon J. (as he then was) sums up
a number of authorities in Dey v. Victorian Railways Commissioners where he
says: “A case must be very clear indeed to justify the summary intervention of
the court to prevent a plaintiff submitting his case for determination in the
appointed manner by the court with or without a jury. The fact that a transaction
is intricate may not disentitle the court to examine a cause of action alleged to
grow out of it for the purpose of seeing whether the proceeding amounts to an
abuse of process or is vexatious. But once it appears that there is a real question
to be determined whether of fact or law and that the rights of the parties depend
upon it, then it is not competent for the court to dismiss the action as frivolous
and vexatious and an abuse of process.” Although I can agree with Latham C.J.
in the same case when he said that the defendant should be saved from the
vexation of the continuance of useless and futile proceedings (1949) 78 CLR,
at p 84, in my opinion great care must be exercised to ensure that under the
guise of achieving expeditious finality a plaintiff is not improperly deprived of
his opportunity for the trial of his case by the appointed tribunal. On the other
hand, I do not think that the exercise of the jurisdiction should be reserved for
those cases where argument is unnecessary to evoke the futility of the plaintiff's
claim. Argument, perhaps even of an extensive kind, may be necessary to
demonstrate that the case of the plaintiff is so clearly untenable that it cannot
possibly succeed.
[101] The purpose of the review of a reviewable decision is to produce the correct and
preferable decision.30 The internal review is not a review of a reviewable decision and
therefore the internal review decision must be set aside. Further, the internal review
28 (1964) 112 CLR 125, [10].
29 (1949) 78 CLR 62, 91.
30 QCAT Act s 20(1).
-- 17 of 18 --
18
decision lacks utility. The interlocutory application must be granted and the
proceeding dismissed.
Decision
[102] The decision of the Tribunal is that the interlocutory application be granted. The
proceeding is dismissed.
[103] I will hear the parties on costs.
-- 18 of 18 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2025/442