Carter v Queensland Building and Construction Commission & Ors [2025] QCAT 339
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Carter v Queensland Building and Construction
Commission & Ors [2025] QCAT 339
PARTIES: LOUISA CARTER
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(respondent)
MAXCON CONSTRUCTIONS PTY LTD
(respondent)
THE BODY CORPORATE FOR THE JOHNSON
CTS 49098
(respondent)
THE BODY CORPORATE FOR THE JOHNSON
APARTMENTS CTS 49099
(respondent)
APPLICATION NO/S: GAR 259-19
MATTER TYPE: Building matters
DELIVERED ON: 8 September 2025
HEARING DATE: 24 October 2024
HEARD AT: Brisbane
DECISION OF: Member Bertelsen
ORDERS: The decision of the Queensland Building and
Construction Commission dated 10 May 2018 to
give a direction to rectify is confirmed.
The application by the Queensland Building and
Construction Commission to extend the timeframe
within which to issue a direction to rectify is
dismissed.
CATCHWORDS: PROFESSIONS AND TRADES – BUILDERS –
STATUTORY POWER TO REQUIRE RECTIFICATION
OF DEFECTIVE OR INCOMPLETE BUILDING WORK
– where the Queensland Building and Construction
Commission made a decision to give a direction to rectify to
a builder for rectification of building work and then issued
the direction to rectify to the builder to rectify – where the
direction to rectify assertedly not complied with – where the
applicant sought review of the initial direction to rectify
-- 1 of 20 --
2
given by the Queensland Building and Construction
Commission – whether it is fair and reasonable to issue a
further direction to rectify – consideration of extension of
time application by the Queensland Building and
Construction Commission to issue a further direction to
rectify in respect of defective or incomplete building works
required to be rectified – whether it is fair and reasonable to
extend time to issue direction to rectify
Queensland Building and Construction Commission Act
1991 (Qld), s 72, s 72A
Queensland Building and Construction Commission
Regulation 2018 (Qld)
Queensland Civil and Administrative Tribunal Act 2009
(Qld), s 19, s 20, s 21
Body Corporate for Alto Gladstone v Queensland Building
and Construction Commission [2020] QCATA 6
Turner v Queensland Building Services Authority [2012]
QCAT 229
APPEARANCES &
REPRESENTATION:
Applicant: Dr Louisa Carter self-represented
Respondents: Ms Nean in house lawyer Queensland Building and
Construction Commission with Mr Srivastava in house
lawyer.
Mr Kidston of Counsel instructed by Diakou Faigen lawyers
for Maxcon Constructions Pty Ltd.
Mr Robinson of Robinson Locke lawyers for the Body
Corporate for the Johnson CTS 49098 and the Body
Corporate for the Johnson Apartments CTS 49099.
REASONS FOR DECISION
[1] By application filed 2 July 2019 the applicant Dr Louisa Carter (‘Dr Carter’) sought
external review of the decision of the Queensland Building and Construction
Commission (‘Commission’) (‘QBCC’) of 10 May 2018 to give a direction to rectify
to Maxcon Constructions Pty Ltd (‘Maxcon’) (‘contractor/licensee’) in respect of
works at the Johnson 477 Boundary Street, Spring Hill.
Background and Evidence
[2] The multi-story building at 477 Boundary Street, Spring Hill was formerly the
Queensland Main Roads Building. It was purchased by a property developer Asia
Pacific Group which contracted Maxcon to repurpose the building as a combined hotel
and residential apartment complex. Works were completed on about 9 September
2016 when a certificate of classification was issued for the whole of the building
complex. Dr Carter purchased residential unit 1510 in the complex in 2017.
-- 2 of 20 --
3
[3] On 21 February 2018 Dr Carter complained to the Commission about defective
building work and consequential damage at the complex and at and within unit 1510.
There were numerous complaint items. Consequent on inspection by Commission
inspector Cornelius Koen on 9 April 2018 the Commission made the decision on 10
May 2018 to give a direction to rectify to Maxcon. The decision was notified to Dr
Carter the same day. On the same day a direction to rectify was issued to Maxcon for
five items from Dr Carter’s numerous complaint items. Specifically, items one to five
stated.
1. The Queensland Building and Construction Commission finds the licensee
responsible in that the installation of the rainwater drainage system at the top
units were not installed in accordance with the relevant Australian Standards
and or the BCA FFI.2 and 3.5.2 (gutters and downpipes) resulting in water being
directed to the units below and caused extensive damage to the adjacent building
elements including carpets - Pertains to item one of the QBCC complaint form.
2. The QBCC holds the licensee responsible to rectify the damage which occurred
at the time of the splash back installation in that (it) does not meet a reasonable
standard of finish expected of a competent holder of a contractor’s license of
the relevant class, resulting in visual defect.
3. The QBCC holds the licensee responsible in the installation of the paint work
in bedroom 2 in that (it) has not been done in accordance with AS/NZS
2311:2009 Guide to painting of buildings appendices C, in that there is an
uneven surface finish which does not meet a reasonable standard of construction
or finish expected of a competent holder of a contractor’s licence resulting in a
visual defect.
4. Inspection of the timber platform revealed that the sharp unfinished plywood
edges do not adversely affect the structural integrity or performance of the
building, but does constitute a safety issue, therefore Queensland Building and
Construction Commission hold the licensee responsible in rectifying this issue
to prevent any danger or injury to the owner or occupants of the unit.
5. The QBCC hold the licensee responsible in the re-seal and silicon of the bath
surround to prevent water ingress and cause damage to the adjacent elements
and the lower unit.
[4] Works the subject of the direction to rectify were to be completed by 12 June 2018.
On 11 June 2018 the Commission undertook a site reinspection and confirmed by
notification dated 14 June 2018 that Maxcon had attended to the items in the direction
to rectify dated 10 May 2018. No further action would be undertaken by the
Commission in relation to the direction to rectify. In early 2018 Dr Carter had notified
the Body Corporate insurer Chubb Insurance Australia Ltd (‘Chubb’) about water
ingress and damage. Chubb inspected and tested unit 1510 and found mould to be in
excess of habitable levels. That resulted in Chubb in late April and early May 2018
enacting its emergency protection measures to arrest mould infestation. Specialist
contractor New Life Restorations carried out mould removal/remediation which
included removal of ceilings and wall linings skirtings and floor coverings necessary
before any repairs could be commenced. By the time the Commission’s direction to
rectify was issued on 10 May 2018, Chubb, through New Life Restorations, had
completed its emergency protection works. Of the five items constituting the
-- 3 of 20 --
4
Commission’s direction to rectify item one the rainwater drainage system and water
ingress into unit 1510 was of primary concern for Dr Carter.
[5] On 10 October 2018 Dr Carter sought confirmation from the Commission as to
whether it undertook a compliance review of the full roof/rain water drainage system.
By same day return the Commission confirmed that it did not undertake a full review
of the roof water drainage system stating that its role was to determine the cause of
the water penetration into the dwelling. The source of water entry was located, and
the contractor directed to rectify that area only. A Commission reinspection found
rectification to that area was satisfactory and met the requirements of the National
Construction Code (‘NCC’).
Statements and evidence of Dr Louisa Carter at hearing
[6] Dr Carter stated she purchased unit 1510 on level 15 at the Johnson on 31 January
2017. During the first storm that occurred subsequent to purchase there was water
ingress. She approached the body corporate, the developer, and the builder Maxcon.
Some inspections took place and some work undertaken. Some damaged plasterboard,
ceilings and carpets were replaced but were subsequently damaged again. Aris
Margaritis project manager for Maxcon attended. Maxcon accessed the unit for about
a year. There seemed to be little progress.
[7] Mould had begun to appear in the summer of 2017/2018. Dr Carter applied to the
Commission in February 2018 listing numerous defects and consequential damage.
She contacted the body corporate insurer Chubb which arranged for
inspections/reports which documented ongoing water ingress. Chubb under its body
corporate insurance contract emergency repair powers arranged for removal of mould
infested areas through Asta Group Chartered Loss Adjusters which retained New Life
Restorations which undertook mould remediation at unit 1510 but did not undertake
any structural remediation work. A report from Mould Lab confirming “normal mould
ecology level” accompanied Asta Group’s fourth report of 10 May 2018. In that same
month Dr Carter stayed in her unit for a week to ten days as she had nowhere else to
go and it was at least temporarily safe. In the meantime, unit 1601 directly above on
level 16 was sold by the developer. New balcony membrane and tiles were applied to
unit 1601.
[8] In October 2018 Asta Group provided its eighth report wherein it confirmed through
New Life Restorations that mould samples taken were within acceptable levels.
Queried about having stopped living at her unit Dr Carter said she was aware it was
going to leak again. Nor was Chubb going to replace the ceiling or otherwise reinstate
until the cause of damage had been addressed.
[9] Unit 1510 had been abandoned by Dr Carter since June 2018 and was still so
abandoned to date though she had returned/entered/stayed on a few occasions. She
understood that the only work done by Maxcon was installation of a pipe spreader. A
QBCC inspector Cornelius Koen had attended unit 1510. The assessment method
adopted by the QBCC was inadequate and failed to identify all possibilities with
respect to water ingress.
[10] In the course of giving evidence Dr Carter was referred to Newsky Constructions’
report of 1 February 2020 prepared for the QBCC regarding water testing of the
balcony of unit 1601 directly above unit 1510 and the invasive investigation of the
ceiling space of unit 1510. Newsky Constructions retained Leakless Plumbing which
carried out flood tests to the balcony of unit 1601 resulting in water leaking into unit
-- 4 of 20 --
5
1510 indicating firstly a leaking puddle flange1 connection to the drain at unit 1601,
and secondly an issue with the balcony waterproofing membrane at unit 1601. During
the course of testing water was heard dripping onto the ceiling of bedroom 4 of unit
1510. Water pooling was observed. There was moisture in the ceiling above the
lounge room with removed lagging from the lagged stormwater line being saturated.
There was moisture and water dripping onto the ceiling of bedroom 1 with water
dripping from a lagged stormwater line.
[11] On 25 March 2020 Dr Carter filed an application in the Tribunal seeking an order to
“direct the QBCC and respondent parties to desist any building and rectification works
to the Johnson roof drainage system pending the Tribunals review under GAR259-
19”. The application was refused on 7 December 2020.
[12] It was put to Dr Carter that this water ingress was further back 1.5 metres in from the
area where water ingress that occurred in 2017/2018 (which was beneath the rainwater
drainage system). Dr Carter confirmed that where new openings were cut in bedroom
4, the lounge room and bedroom 1 “water poured through”.
[13] In cross-examination Dr Carter was asked whether she had a copy of the GHD
Engineering Consultants (‘GHD’) report dated 16 October 2024 authored by Bruce
Clarke with commentary by Dale Lovett. She answered she had only received it last
week (prior to hearing) and that it described some remaining unrectified items. She
was asked whether she accepted the possibility that if works targeting water
penetration had been carried out (as described in the GHD expert report dated 16
October 2024) then the issue of water penetrating her property may have already been
addressed. Dr Carter answered that she was denied information. She did not know
whether the issue of water penetration had been addressed or not.
[14] Given that GHD’s report of 16 October 2024 stated that there had been no further
leaks at the unit would Dr Carter be in a position to settle her insurance claim with
Chubb, Dr Carter answered that Chubb required a form 162 before proceeding further.
Despite requests the body corporate had not furnished her or Chubb with a copy of
any form 16.
[15] It was put to Dr Carter that following the Commission’s direction to rectify and prior
to the work so directed being undertaken Chubb carried out works (in unit 1510) in
respect of fixtures and fittings that Maxcon was directed to undertake. Dr Carter
answered yes. Of the five items listed in the Commission’s direction to rectify dated
10 May 2018 Dr Carter did not dispute (apart from item one) that minor items two,
three and five were generally repaired with item four, inspection of timber floor not
actioned. Dr Carter was aware of the principal body corporate’s Supreme Court
proceeding against Maxcon for defects which included a complaint about water
penetration at unit 1510.
1 A puddle flange is a component installed around, here, a posts penetration point in a concrete structure
to create a waterproof seal preventing water from seeping through the walls or floor and causing
damage. It connects the water proofing to the drainage system ensuring water flows into the drain and
not under the floor. Here it was where balustrade posts met tilework.
2 Form 16 – Inspection Certificate/QBCC Licensee Aspect Certificate under the Building Act 1975 (Qld)
and Building Regulation 2006 (Qld).
-- 5 of 20 --
6
Evidence of Herbert John Muller
[16] Mr Muller chartered professional engineer/mechanical engineer certified the level 15
siphonic drainage system3 as part of the overall rainwater drainage system for levels
16 and 15 at the Johnson complex in 2016. His involvement was limited to design and
installation of the siphonic roof drainage system. He provided a form 16 for the system
design. He relied, in part, on his plumber confirming that the job of installing was
completed according to plans. He explained that Aqualogical specialist hydraulic
designer was the overall hydraulic engineer for the Johnson project and that Beavis &
Bartels was the plumbing contractor he was working for. He did not sight a form 15
for hydraulic design by Aqualogical. He did not personally inspect completed
drainage works (though he was there during construction) relying rather on his
plumber telling him that the system had been installed to his design. Mr Muller signed
off on a form 154 dated 24 February 2016 for the Valsir siphonic roof drainage system
/rainwater drainage system from box gutter level 12 (redesignated as level 15 for the
Johnson repurpose project).
[17] When asked about the siphonic flange (intake) sitting proud of the box gutter base Mr
Muller answered the “siphonic head – the flange is obviously fitted in the gutter, and
it is sealed into the gutter”. Mr Muller went on to confirm that the Johnson project
level 15 and the newly created top floor level 16 utilised unusually both a traditional
box gutter downpipe gravity system and a siphonic system. Level 16 used a downpipe
gravity system to feed into the level 15 siphonic system. As part of the siphonic head
in the box gutter there was a blue coloured baffle plate designed to hold a water
column intact to stop any air from being sucked into the system thereby preventing a
vortex from occurring. When presented with a photo of the siphonic head as now
installed he confirmed that was how it was meant to be. Any provision for overflow
would be located in the box guttering. Even without provision for overflow the
siphonic system was sufficient to allow for the discharge of the volume of water he
had calculated, and which included discharge from level 16. As far as he was aware
there had never been since installation a complaint or an issue with the siphonic
drainage system since his involvement.
Evidence of Peter McLean
[18] Mr McLean mechanical and electrical engineer of McLean Consulting Engineers was
a consulting engineer who was involved in the initial stage of the Main Roads/Johnson
project as a design engineer. He provided forms 15 for mechanical, electrical, fire
protection, and hydraulics. His hydraulics form 15 dated 5 November 2015 did not
include the additional three sixteenth level top floor units nor the siphonic drainage
system installed. His engagement was then discontinued by the builder.
3 Here a Valsir siphonic roof drainage system was installed. It is a stormwater management system for
generally flatter roofs that uses a siphon effect to rapidly draw water at high-speed allowing for smaller
pipework. It efficiently removes water from roofs by using negative pressure to create vacuum effect
in the vertical pipes allowing rainwater to be carried away (in this case from the level 15 box guttering)
through smaller diameter pipes. Here the siphonic drainage head is the point where the water gets away
from the box gutter into the downpipe.
4 Form 15 – Compliance Certificate for Building Design or Specification for the purposes of section 10
of the Building Act 1975 (Qld) and/or section 46 of the Building Regulation 2006 (Qld).
-- 6 of 20 --
7
Inspections and Evidence of Cornelius Koen
[19] Cornelius Koen Senior QBCC Building Inspector inspected unit 1510 on 9 April 2018
consequent on a number of complaints by Dr Carter. His job was to visually inspect
only that which was included in the complaint items. He confirmed he did not conduct
incline tests on the balcony tiles of the level 16 units. With respect to water ingress in
unit 1510 the issue was more about flashing that was not properly sealed and absence
of a downpipe spreader. He confirmed that there was nothing wrong with balustrading
on level 16 balconies where balustrade posts met tile work. Balustrading was never
an issue nor was balustrading the subject of a complaint item. He confirmed, “we only
went for the gutters and the downpipes and the flashings because we clearly could see
after that I test it from the top with the pipe hose (an orthodox approach) where the
water came in”. Mr Koen went on to say, “We checked your unit, and we look where
the water ingress (is). There’re multiple areas at that unit at the top there that might
be defective. But that was not part of our investigation. We only looked at where your
water came into your (unit)…...and we could see where it came from the flashings”.
[20] In his inspection report of 15 April 2018 Mr Koen stated, “evidence of water ingress
directly underneath the downpipes was evident in the form of water staining, mould
and drip marks to the painted plasterboard ceiling”. At the time he observed water
ingress directly under the box gutter which he reasoned was due to there being no
(downpipe) spreader or flashings. Nor did he observe water ingress from under the
balcony area of unit 1601. He did not consider there were other areas that needed to
be inspected to identify the source of water ingress.
[21] On 11 June 2018 at the time of reinspection to determine direction to rectify
compliance Mr Koen said Maxcon had installed the roof tile flashing and spreaders to
the drainage system in the lower roof. It was hose tested and there was no water
ingress into unit 1510. There was no one in a hundred rain event test conducted
because that was a design issue and the QBCC was not there for design issues. Nor
did the QBCC look at certification, engineering matters, architectural matters or
drawings. What was looked at was defective material if that had been installed and
water ingress to the property. Maxcon issued a form 15 or perhaps a form 16 sent by
Asbuilt Constructions to Aris Margaritis project manager of Maxcon but Mr Koen did
not sight it.
[22] With respect to the box guttering not working it was to look to see if it was not draining
properly and look at the downpipes or the slope or rivet joints separation. The box
gutter was hose tested and “the water was draining to the downpipes from the spreader
– from the gutter flashing to the gutter”. Mr Koen was asked did the hose test show
water falling away from the siphonic drainage head. He said no. With the siphonic
drainage head being the point where the water gets away from the box gutter how did
he know whether the box gutter fell to that point. Mr Koen answered to the effect that
on visual inspection all the water got away. He said long edge box guttering had been
replaced such that when tested there was no backflow. Mr Koen was asked did he
notice that the siphonic drainage head seemed to be above the level of the base of the
box guttering by maybe 20 ml. He answered no.
[23] Mr Koen was queried about the painting of the replaced Colorbond box guttering and
the use of Sikaflex as a box guttering sealant. Mr Koen said rectification work was
tested. If it works and it is new building work, it is guaranteed for six years and six
months. Mr Koen was asked about overflow spouts off the box guttering and whether
they were correctly installed. Mr Koen answered they were placed two thirds on the
-- 7 of 20 --
8
top (of the box gutter) and were there for a safety reason in case the box gutter
overflowed.
[24] Mr Koen was queried about other complaint items addressed in his initial report of 15
April 2018 including nonfunctionally of a steam extraction fan, joinery being non
moisture resistant board, glazing frame finish, external membrane and paint finish to
external balustrade, weight allowances on glass doors leading to the balcony and fire
inadequate separation between units 1509 and 1510. Mr Koen’s answers included
insufficient evidence of defective construction, reasonability of issuing a direction to
rectify, absence of defective construction practices, and withdrawal of complaints.
Complaint withdrawals referred to in Mr Koen’s initial report of 15 April 2018 were
never questioned by Dr Carter at least not prior to hearing.
[25] Mr Koen acknowledged that other sources of water leaks may come into existence
over time and that maintenance programmes may apply to membranes and sealing of
parts of buildings. He agreed that the direction to rectify items fell into two categories
those which Maxcon contended were rectified and those unable to be complied with
due to intervening factors which in the present case was removal of damaged unit
internals by Chubb. Mr Koen in his reinspection report of 11 June 2018 stated, “the
licensee was unable to rectify the consequential damage due to the fact that the
insurance company of the body corporate undertook the rectification of this work.
Confirmation with the owner is that the insurance company will finalise the
rectification of the consequential work”.
Reports and evidence of Rathlin Trohear
[26] Mr Trohear was formerly a senior building inspector and currently director Building
and Technical Inspectorate at the QBCC. Mr Trohear conducted four inspections at
levels 15 and 16 at the Johnson on 30 July 2019, 16 August 2019, 26 August 2019
and 17 September 2019. He discerned there was potential for water entry through the
balcony of level 16-unit 1601 and in particular through puddle flanges. There were
“watermarks on the ceiling that were not in the vicinity of the small roof and gutter
(drainage system) above unit 1510…...there was a likelihood that there was another
water entry point.” He said he could not see evidence of an ongoing leak beyond the
work that had been done by Maxcon and that he formed the view it was most likely
that water was entering from another source (other) than the small box gutter and the
small roof above unit 1510. He did not see any evidence of a leak in the (box) guttering
though some ponding was observed. Waterproofing works to unit 1601 balcony were
not undertaken by Maxcon but by another contractor engaged by the unit owner (of
unit 1601) who had engaged with the QBCC.
[27] In unit 1510 he observed primarily at the outermost part of the unit underneath the
box guttering system some plasterboard watermarks. There was no mould damage.
Mr Trohear formed the view that fire separation between unit 1601 and unit 1510 was
not defective. In cross-examination Mr Trohear confirmed that the balustrading and
the aluminium columns forming part of the balustrading system (on level 16) when
flood tested did not leak. Observationally they were compliant.
[28] With respect to fire separation between units 1601 and 1510 Mr Trohear considered
the plasterboard and vermiculite that had been installed as well as the full passive fire
system reaching the conclusion that there was no sufficient evidence to identify
defective building work by Maxcon. Nothing he had been taken to since or had learnt
about since had altered his opinion. He understood that since Maxcon had carried out
-- 8 of 20 --
9
its rectification work that the owner of unit 1601 had engaged a contractor to carry
out waterproofing works in respect of its balcony. As for linings/plasterboard in Dr
Carter’s unit he understood those were removed by the insurer Chubb.
[29] Mr Trohear said his review was against the decision made by the previous inspector
Cornelius Koen about whether or not the (box) gutter was now leaking. In his view
there was not a sufficient change to the extent that the Commission could exercise a
new power. He said QBCC inspectors primarily rely on the defect definition in the
rectification of building work policy given effect by the Building Regulation. For
something to be defective it first must be faulty or unsatisfactory. He said there are
times where something (building element) does not comply with a relevant code or
standard but performs reasonably such that there is no evidence that it is faulty or
unsatisfactory. A performance-based assessment formed a large part of the
investigation method.
[30] At his site attendance on 17 September 2019, it was not clear to Mr Trohear that the
box guttering was leaking. Though he formed the view that the box guttering was not
leaking the decision was made to engage GHD. Within unit 1510 there was evidence
of water entry further back inside unit 1510 below the balcony of unit 1601. GHD was
not able to confirm that the box guttering was in fact leaking. He said considering all
the material that there were no grounds for him to exercise a new power. Nothing had
changed since the original matter was under review. He was of the view that there was
a separate issue relating to the balcony above and that a significant degree of water
damage to unit 1510 (at that time) was the result of the balcony above unit 1510
allowing water to enter through puddle flanges.
Evidence of Stephen Baird
[31] Mr Baird of Set Tiling in liquidation was referred to a form 16 dated 28 June 2016
which he signed for waterproofing including external balconies on level 16 at the
Johnson. A waterproof membrane was applied and then tiled over. He was also
referred to a form 16 dated 26 March 2018 for waterproofing over all existing balcony
tiles and perimeter flashing on level 16. He thought it must have been with respect to
rectification work “for works over the top”. He was not aware of any other work that
needed to be done to make level 16 external balconies waterproof. They were
remediated and watertight. He had not “heard anything about it (level 16
waterproofing) in a long time”.
Reports and evidence of John Steven Mayer
[32] On 9 November 2018 a visual inspection was conducted by NJA Consulting Pty Ltd
structural civil forensic engineers (John Mayer) (‘NJA’) instructed by NPS
Commercial on behalf of Chubb to assist in determining the effectiveness of the water
ingress remediation works previously undertaken to prevent water ingress at the site
with its report being made on 11 December 2018.
[33] The report confirmed steel framed units 1601 to 1603 were located on the added upper
level with unit 1510 on the second top floor directly below upper (top) level unit 1601.
Tiled balcony areas extended around the perimeter of the upper-level units with unit
1601 balcony set above the bedroom and living areas of unit 1510. It was noted that
at the time of inspection there was evidence of water staining and mould growth to
several areas of exposed lining to the balcony underside. Leakage into the bedrooms
appeared to have occurred from the ceiling areas above the internal sides of external
glazed doors during heavy rain events. However, it could not be confirmed if it was
-- 9 of 20 --
10
recent or historical. Nor could it be visually confirmed if there had been recent water
ingress to the unit since remediation works had been carried out. There were no further
indications of potential (water) ingress. The unit appeared dry with no mouldy smell.
[34] The report concluded that the QBCC work list indicated water ingress into unit 1510
was related to plumbing installation to the upper-level units and given that recent
water ingress had not occurred at times of recent wet weather it appeared rectification
work had been successfully undertaken. If further water ingress was found to occur in
unit 1510 additional testing could be undertaken to attempt to isolate any additional
source of water ingress to unit 1510.
[35] A further visual inspection was conducted by NJA on 21 June 2019 attempting to
identify and assess any further damage or defects that may have occurred since the
November 2018 inspection with its report being made on 26 June 2019. Mr Mayer
observed the extent of water staining marks to the exposed areas of lining to the
balcony underside above the internal bedroom areas to unit 1510 did not appear to
have increased since the initial November 2018 inspection. There was no indication
of significant water ingress adjacent to the balcony sliding glass doors or ceiling in
the interim. Some other minor items were identified such as lifting of joinery tape
above the entry but there was no indication of excessive moisture and were in any
event in areas other than those initially reported. It was suggested that might be the
subject of further investigation.
[36] In a revision report of 13 September 2019 Mr Mayer referred to his inspection of 21
June 2019 concluding “the location and extent of the recently noted defect items are
inconsistent with the location and extent of the noted defect items from our initial
inspection and as such would appear to have ingressed or developed independently of
the initial ingress related defects. Notwithstanding the above it is possible that the
moisture from each instance may have resulted from the same general moisture entry
source (ie; from above the unit)”.
Report and evidence of Peter John Blain
[37] Mr Blain a QBCC multilicensee prepared a report dated 15 August 2019 based on an
inspection and photographs taken by two of his employees reviewing fire separation
issues at unit 1510. He stated the (ceiling) plasterboard, due to mould, and being water
affected was damaged beyond repair rendering it non-compliant and requiring
replacement. His report did not consider whether there was a concrete slab above the
plasterboard separating unit 1510 from the unit above. But his report indicated a
requirement to have a fire rated ceiling.
[38] It was put to Mr Blain that unit 1510 did not require a plasterboard fire rated ceiling
because there was a concrete slab and sprinklers installed. But he was unsure because
no destructive testing was done. He only commented on what he (his employees) saw.
He did not know what was above the fire rated ceiling. If there were other separation
issues, then a fire rated ceiling may not be required. Nor was there any inspection of
box guttering.
Report and evidence of Andrew Corrigan
[39] On instruction from Chubb, Gould Development Solutions (‘Gould’) (Andrew
Corrigan director) was retained to inspect and report on the water leak from the box
gutter and roof drainage system into unit 1510. A site inspection was carried out on
6 August 2019 with Gould furnishing its report on 19 September 2019. The report
-- 10 of 20 --
11
helpfully clarified that Dr Carter’s unit 1510 is situated on level 15 of the complex
with level 16-unit 1601 above that includes a balcony/terrace that is above the roof of
the interior of unit 1510. A box gutter is located outside the balcony/terrace of unit
1601 and above the ceiling level of unit 1510. Adjacent to the box gutter is a narrow
width roof that extends the length of the box gutter which conveys water runoff from
level 16 and level 17. The water runoff is collected and conveyed in downpipes which
discharge through a downpipe spreader onto the narrow width roof and then into the
box gutter which has overflows. But if the box gutter capacity is exceeded or leaks
the water run off may penetrate the interior of unit 1510.
[40] The QBCC considered such a defect and issued a direction to rectify to Maxcon. Some
rectification work was carried out which led to the QBCC advising rectification work
had been carried out and no further action would be taken. Mr Corrigan was of the
view the rectification work was not sufficient and that the QBCC should not have
concluded that Maxcon had completed rectification of defects.
[41] Mr Corrigan attached a report from BG Group Qld Pty Ltd (‘BG Group’) which
concluded the box gutter did not have the capacity required by the relevant Australian
Standard nor did it comply with the requirements of that Australian Standard. Mr
Corrigan stated it appeared the QBCC had not previously considered that the box
guttering was not of sufficient capacity. In concluding that Maxcon had installed roof
tray flashing and spreaders to the drainage system to the lower roof the QBCC did not
consider installation defects of the box gutter other that discharge from the higher
levels of the complex into the box gutter. Hence water ponding, lack of fall, lack of
sumps and incorrectly located overflows were not considered by the QBCC and could
be reported as new defects. Installation of roof tray flashing, and spreaders did not
rectify the (water ingress) defect.
[42] Mr Corrigan considered Beavis & Bartels, Maxcon’s plumbing subcontractor, which
issued the form 16 inspection certificate and QBCC licence aspect certificate dated 24
August 2016 which included installation of stormwater and rainwater downpipes
certified in compliance with AS3500 had done so incorrectly. The Beavis & Bartels
form 16 referred to the form 15 for the design of hydraulic services by Aqualogical, a
specialist hydraulic designer. He considered issues of design could be directed
ultimately to Aqualogical. The siphonic drainage system designed and installed by
Siphonic Solutions appeared to operate satisfactorily. The absence of prolonged heavy
rain since 2018 meant the capacity of the box guttering had not been tested. Finally,
whilst the previously leaking balcony/terrace membrane of unit 1601 may have
contributed to water ingress into unit 1510 the evidence indicated the box guttering as
the primary cause.
[43] In evidence Mr Corrigan said a box gutter without sumps was unusual though he had
seen siphonic systems with and without sumps; that for a box gutter to discharge
properly particularly where a siphonic system was utilised a sump was usually
installed to create a sufficient depth of water to the (siphonic) head to discharge/force
water into the downpipe. But he had not been to unit 1510 since 2019.
[44] Mr Corrigan was taken to a report by GHD of 11 November 2019 which reached a
different conclusion to his about the capacity of the box guttering because it seemed
each had different data about the dimensions of the box guttering involved possibly
due to box guttering dimensions being taken in different locations. Mr Corrigan said
the devil was in the detail with those sorts of things. He had relied on/adopted capacity
calculations provided to him by BG Group.
-- 11 of 20 --
12
[45] Mr Corrigan was also taken to the list of works undertaken and photographs in GHD’s
report of 16 October 2024 and was asked did such works address his concerns. Mr
Corrigan said, “I can see that the type of work in those photos is directed at the nature
of those defects”. But he could not be definitive. He confirmed that the water staining
he observed in unit 1510 tended generally to be in locations near the box gutter. He
concentrated on the box gutter being the primary cause of water ingress not any issues
connected to the balcony above unit 1510. Whilst the first QBCC direction to rectify
seemed to pick up on all the issues he believed his inspection indicated that there were
still some defects. The indicator of that was water ponding in the box gutter.
Newsky Constructions Pty Ltd report
[46] Newsky at the request of the QBCC provided an invasive investigation report dated 1
February 2020 (on site 29 January 2020) in respect of units 1510 and 1601. Newsky’s
plumbers Leakless Plumbing Pty Ltd conducted flood tests to the balcony of unit
1601. Puddle flange leaking was identified as well as an issue with the water proofing
membrane. There was water dripping into the ceiling of bedrooms one and four as
well as moisture and saturation in the lounge room ceiling space of unit 1510.
Evidence of Kristopher Steven Asher
[47] Mr Asher director of Specialty Roofing stated his firm was initially to be engaged by
Maxcon to rectify issues at the Johnson but in the event was engaged by the body
corporate directly instead. Specialty Roofing worked with GHD as supervising
engineers which provided the scope of works and which inspected works in the
persons of Bruce Clarke and Nick de Jonge of GHD. Works carried out included non-
compliant level 15 box gutters not having sufficient fall to the sumps and round
overflows (guttering overflow spouts) not fully engaging. Major works involved
building scaffolding on the balcony. Box gutters were adjusted to create adequate fall,
joins were redone, new box gutter flashings installed, spreader made compliant as well
as core drilling through the existing wall to install rectangular overflows. That
necessitated cleaning every joint, resealing those joints, cleaning joints not
undersealed, checking rivet spacings, repairing joints to the effect that the box
guttering was fully compliant. The works were carried out recently in
September/October 2024.
[48] Mr Asher said, “our business is all about rectification works” and was “carried out in
accordance with the relevant Australian Standards”. There were no unremedied
sources of ingress of water to unit 1510 that he was aware of. Nor had he received any
complaints about further leaks in unit 1510.
Evidence of Aris Sylvio Margaritis
[49] Mr Margaritis, former site manager/project manager for Maxcon at the Johnson and
qualified builder, confirmed Beavis & Bartels as the plumbing contractor and
hydraulic consultant for installation of the rainwater drainage system for levels 15 and
16 at the Johnson. A subcontractor Set Tiling pressure and water tested the balcony
drains on level 16 and rectified some balcony panel flanges to unit 1601. He referred
to the form 16 dated 26 March 2019 from Set Tiling for waterproofing over all existing
balcony tiles and perimeter flashing on level 16.
[50] GHD’s 2024 report indicated additional flashings and new rectangular overflows
when compared to Maxcon’s repair work in 2018. Asked whether he considered that
to be additional work in 2018 he said no because it was engineer compliant at the time.
-- 12 of 20 --
13
He recalled that at the time of carrying out rectification works the body corporate
insurer Chubb had come through and removed plasterboard and floorboards.
[51] With respect to unit 1510 emergency measures undertaken by New Life Restorations
(for Chubb) Mr Margaritis said more than the quantum of works that was fair and
reasonable was removed because too much building fabric was removed. Maxcon’s
position was that it would remove and replace the ceilings and all carpets only as
directed by QBCC. But the opportunity never arose due to New Life’s removal of unit
internals.
[52] In cross-examination Mr Margaritis confirmed Beavis & Bartels as a DNC (design
and construct) hydraulic and plumbing company that designed and installed the roof
guttering and drainage system at the Johnson. When the direction to rectify was
received Beavis & Bartels as specialised contractor inspected the works. Suggestions
and advice were followed. A flood test of the box guttering was conducted to identify
any leaking anywhere. No leaks were identified. Spreader and flashing work were
carried out. The roof and drainage system were rectified. No other sources of leaking
were identified.
[53] All the tiles on level 16, unit 1601 were changed. The whole system all the way to the
flashing on the edge. That involved complete removal of tiles, screed, and membrane
with replacement of membrane, screed, and new tiles. The interior of unit 1510 was
inspected as part of the direction to rectify to identify internal damage remediation
necessary before engaging a contractor. On a subsequent attendance and in the interim
Chubb through its contractors had carried out internal demolition work which he
considered excessive because it was carried out in areas where there was no water
ingress and because damaged internals such as floorboards could be salvaged,
repaired or individually replaced. He added the norm in commercial construction was
to obtain three quotes select one and proceed. Due to Chubb’s intervention
opportunity to do so was lost.
[54] Mr Margaritis was also asked which of the four elements of the drainage system did
he identify as leaking. He answered the roof then possibly the puddle flange on level
16.
[55] Subsequently unit 1601 was sold to a private person in 2020 and all tiling was changed
(again) at that time by another builder.
Report and evidence of Dale Lovett
[56] Mr Lovett technical director – hydraulic and fire services at GHD/hydraulic services
designer was initially engaged by the QBCC in 2019. In a GHD report dated 11
November 2019 he stated that since the initial water ingress event (in 2018) a pipe
spreader and roof flashing had been installed. However they were not fully compliant.
Wider flashing needed to be installed. He subsequently provided a response to
hydraulic issues as part of GHD’s report of 20 April 2022. He said while he could
look at the box gutters and their compliance with the relevant Australian Standard, he
could not calculate the siphonic drainage system. In his investigation he found box
gutter fall was insufficient, provision for overflows insufficient, the spreader or the
gravity drainage from the upper most roof level was not compliant in that it was not
broad enough and there was not sufficient sealing of the roof sheeting itself for the
size and discharge of the downpipe coming from the upper roof.
-- 13 of 20 --
14
[57] Mr Lovett considered the rectangular overflow pipes even as built by Specialty
Roofing in October 2024 as still non-compliant because they needed to be coordinated
with a sump. Because it was not necessary to have a sump within a siphonic drainage
system it was not possible to design an overflow to comply with the relevant
Australian Standard. Any overflow would have to be certified as an alternative
solution.
[58] Asked, if so instructed, could he carry out the work necessary to say whether the
overflow met Australian Standards or not he said that was something an engineer
would need to do. He was not aware of the present overflow system resulting in any
leaks. Nor did the lack of fall in the box gutter identified by him.
[59] Mr Lovett was referred to spreader and flashing installed in 2018 and his opinion
subsequently that the spreader and flashing needed to be wider. But he could not say
definitively whether leaks were post or pre the “installation of the flashing”. It was
put to him that when he opined that the width of the flashing and spreader needed to
be increased it was not necessary to prevent any further water ingress; it was just to
make it strictly comply with the applicable Australian Standard. He answered yes. He
was unaware of any leaking from the point where the flashing and spreader were
installed.
[60] Mr Lovett was last on site in 2022 and though aware of the works carried out in
October 2024 he had not sighted them and could not comment on their effectiveness.
When asked of the three main elements identified with the guttering system namely
insufficient fall, overflow location and the downpipe spreader which did he consider
may have caused or were causing water ingress he answered the inappropriate design
of the spreader and flashing. When referred to GHD’s 2024 report did he still have
concerns about compliance Mr Lovett said he still had concerns about overflow
provision.
[61] As an overall observation Mr Lovett recalled unit 1510 was in a bit of a mess. Water
was dripping through from a stack in the corner that was leaking where the balcony
(of unit 1601) had been flooded. He said, “we flooded the balcony and water was
coming down through the stack in the corner”. The building element causing the issue
was the seal between the riser through to the penetration in the slab.
Evidence of Anthony Elzain
[62] Mr Alzain was the construction director of Maxcon Constructions for the Johnson
project. Maxcon’s involvement was construction only and renovation of an old
building converted into an hotel and apartments. It was a design and construct
contract. He said when informed there was a leak, he spoke to management on site in
Brisbane to immediately address any issues. He added, “we were just unfortunately
never allowed to get in ……to investigate the leak”. With respect to the QBCC
direction to rectify he instructed Mr Margaritis to conform and do exactly what was
required by the QBCC. He believed Mr Margaritis would not have done anything
without the QBCC accepting it (he was speaking with a gentleman Cornelius at
QBCC).
[63] He recalled there were issues with the roofing and a membrane which were repaired.
Maxcon installed a new downpipe and spreader system and flashing over the level 15
roof. He recalled that unit 1601 balcony was remembraned and retiled. He said, “we
did predominately, most of the balconies again because I believe body corporate
started doing something, which was incorrect, and we had to come in and assist at that
-- 14 of 20 --
15
time”. A form 16 from Set Tiling was delivered. He could not remember anything
else about what was causing or may have been causing water ingress. During
construction he would fly in every two or three weeks for two or three hours.
[64] It was only after QBCC issued its direction to rectify that Maxcon was able to gain
access. He said, “once the insurer came in no one was allowed to do anything after
that. It made things very difficult for us”.
GHD water damage repairs progress report of 15 October 2024 and GHD Expert
Witness Report of 16 October 2024
[65] Both reports were prepared for the purpose of the body corporate for the Johnson CTS
49098 Supreme Court action against Maxcon. The 15 October 2024 progress report
stated roof work as 100% complete. The level 15 balcony roof repairs had been
completed in the first week of October (2024). The works included the installation of
new box gutters and box gutter flashings above each balcony. Flashing and parapet
seals were cut back and resealed. The overflows on the gutters were core drilled and
widened to a rectangular shape to improve water flow. A level 16 ceiling water leak
had been identified and was in the process of being rectified. Invoices issued and to
be issued by Specialty Roofing indicated rectification costs at the Johnson of which
roof works affecting level 15 were a part would be in the vicinity of $265,000.00.
Evidence of Luke Doyle
[66] Mr Doyle body corporate chairperson confirmed GHD’s report of 15 October 2024
regarding progress of repairs at the Johnson. GHD was the job superintendent and
Specialty Roofing the contractor. That report in particular was the current report from
which the bodies corporate were working. They relied on GHD as their expert
consultants to complete roof works. Though questioned about various aspects of
recent rectification work he was only able to reference GHD as the expert consultants.
He was able to say that through GHD the bodies corporate engaged a contractor to
carry out roof repairs. He confirmed those works had been completed save for defects
or warranty periods. He confirmed that GHD’s report of 15 October 2024 noted some
rainwater penetration of the level 16 ceiling but that did not concern unit 1510.
[67] Mr Doyle further confirmed that the cost of engaging GHD and the contractor to carry
out rectification work at the Johnson formed the body corporates (CTS49098) claim
against Maxcon in its ongoing Supreme Court action. When asked about Dr Carter’s
requirements for a form 15 for work carried out for the bodies corporate Mr Doyle
said there was a request for a form 15 in May 2023 but otherwise Bruce Clarke (the
primary author of the GHD reports) was the person more likely to be involved. Mr
Doyle expressed reservations about any return by Maxcon to undertake building work.
Application to amend.
[68] During the course of the proceeding Dr Carter sought to amend her initiating
application to have the Commission’s subsequent decision, to the effect that
rectification work required by the direction to rectify of 10 May 2018 had been
satisfactorily completed, reviewed.
[69] Dr Carter argued that there was no prejudice/detriment to Maxcon because as builder
it should have fixed unit 1510 roof and consequential damage in the first place. She
said section 19(b) and (c) of the Queensland Civil and Administrative Tribunal Act
2009 (Qld) (‘QCAT Act’) allowed the Tribunal to perform the functions of the
-- 15 of 20 --
16
Commission and issue a direction to rectify. Whilst she was notified of certain works
having been undertaken at her unit in the week or two prior to hearing she had no trust
in the bodies corporate. Nor was the Commission fulfilling its duty to assist the
Tribunal by opposing the amendment. It was in the public interest that the amendment
be allowed.
[70] Ms Nean for the Commission argued that Dr Carter’s review application was made
about a year out of time and that an extension was granted. The Alto Gladstone5
decision was a Tribunal appeals decision to the effect that there can only be one
decision reviewed by a single application. Whilst the Tribunal may have power to
amend an application the review application could still only relate to one decision. It
was not possible for the application to be amended to review both the direction
decision and the satisfactorily rectified decision. Even if the Tribunal was to set aside
the decision of Mr Koen that the rectification work was satisfactorily undertaken at
the Commission’s direction there was no consequence that would lead to a remedy
for Dr Carter such as referral for assessment under the statutory insurance scheme
because there was no entitlement to insurance. Nor would it be likely to lead to any
prosecution of Maxcon due to effluxion of time. Nor would it lead to another direction
to rectify being issued.
[71] It was not acceptable practice for the Tribunal nor supported by the QCAT Act that
the decision under review could be changed after years of litigation and after over half
a hearing had elapsed. Examining the decision about whether work undertaken at the
direction of the Commission was satisfactorily rectified was a different exercise to
whether there was defective work somewhere at the property after that. Consistent
with the Alto Gladstone decision allowing parties to change the decision under review
particularly at an advanced proceeding stage did not lead to the effective
administration of the merits review scheme. Nor did the Commission’s duty to assist
the Tribunal include consenting to an application of this nature.
[72] Counsel for Maxcon reiterated the applicability of Alto Gladstone that there be a
single decision the subject of review. Whilst the application as originally made was a
reviewable decision namely a decision to give a direction to rectify or not to give a
direction the Commission’s notification set out in its 14 June 2018 letter confirming
that Maxcon had attended to the items listed in the direction of 10 May 2018 was not
a decision that the work undertaken was or was not of a satisfactory standard. It just
stated such work as completed. To that extent it was never a reviewable decision and
as such could not be added to the application. The Tribunal did not have jurisdiction
to review that decision. Additionally given the delay, the stage of the hearing reached,
and prejudice suffered by the parties in the disruption of the hearing, it would be unfair
to now give a direction to rectify.
[73] The Tribunal considered that Dr Carter’s original application was clear enough at part
B which was about the direction to rectify decision. Alto Gladstone was applicable in
that there be one separate review application for each reviewable decision. The
resultant delay in allowing the amendment at such a late stage was unacceptable.
5 Body Corporate for Alto Gladstone v Queensland Building and Construction Commission [2020]
QCATA 6.
-- 16 of 20 --
17
Application by the Commission to extend.
[74] Latterly on 24 October 2024 (the fourth day of hearing) the Commission made
application for the time frame within which to issue a direction to rectify to Maxcon
under section 72 of the Queensland Building and Construction Commission Act 1991
(Qld) (‘QBCC Act’) in respect of work undertaken at unit 1510 and the rainwater
drainage system at 477 Boundary Street, Spring Hill be extended in accordance with
section 72A(4) of the QBCC Act. Such direction was sought conditionally upon the
Tribunal determining that a further or alternate direction to rectify should be given.
The Tribunal stated the application would be addressed as necessary as part of the
consideration of the substantive application.
Conclusions
[75] At hearing the Tribunal stated that an expansive approach was to be taken in view of
the protracted nature of the proceeding. All witnesses called were given the
opportunity to have their say and be cross-examined. Evidence of witnesses has been
summarised, as opposed to quoted, at some length and given the number of persons
involved over the intervening years in some semblance of chronological/logical order.
Statements and evidence of witnesses overlap and on occasion contradict one another.
A number of issues/events over the years led to the proceeding becoming protracted
including the commencement of a Supreme Court action by the principal body
corporate CTS 49098 against Maxcon on 6 September 2022. On 26 June 2023
Maxcon’s application for a stay of the subject proceeding, pending determination of
the Supreme Court proceeding, was dismissed.
[76] The direction issued 10 May 2018 by the QBCC regarding installation of the rainwater
drainage system clearly relates only to the roof works. That was because Mr Koen
identified water ingress in the area beneath the box guttering and flashing. There was
no water ingress identified in the area beneath unit 1601 balcony. The power to issue
a direction to rectify, a limited statutory remedy, resides in section 72 of the QBCC
Act and could only be given to the entity that carried out/performed the building work
which in this case was Maxcon. Section 72A (4) of the QBCC Act provides that a
direction to rectify cannot be given more than six years and six months after building
work to which the direction relates was completed unless the Tribunal is satisfied, on
application by the Commission, that there is sufficient reason for extending the time
for giving the direction and extends the time accordingly. Relevant works were
completed on 9 September 2016.
[77] None of architectural work, engineering work, certification work by a building
certifier nor various forms certifying compliance under the Building Act 1975 (Qld)
are building work.
[78] Maxcon responded to the roof works direction to rectify. Its specialised contractor
Beavis & Bartels inspected the works. Spreader and flashing work were carried out.
A flood test of the box guttering was conducted. No other sources of leaking were
identified. A site reinspection took place on the 11 June 2018 and confirmed by
notification dated 14 June 2018 that Maxcon had attended to (this) direction to rectify
and that no further action would be undertaken by the Commission in relation to (this)
direction to rectify. Dr Carter claimed subsequent water ingress denied her
occupancy.
[79] In the course of the complaint process the body corporate insurer Chubb carried out
emergency protection measures to arrest mould infestation. To a substantial degree
-- 17 of 20 --
18
unit 1510’s internals were stripped. But that did not affect any claim that Dr Carter
considered she might have for consequential damage. Numerous persons and entities
became involved leading to a protracted litany of inspections/opinions/reports. In
2020 the Johnsons bodies corporate as common lot/common property owners were
joined as respondents as was Maxcon.
[80] The QBCC in issuing a direction to rectify for defective building work does not direct
the method or manner of rectification work to comply with the direction to rectify.6
Rather it is a case of requiring an outcome to be achieved. In deciding whether to
require rectification of building work the Commission has regard to its Rectification
of Building Work Policy which states defective building work to mean building work
that is faulty or unsatisfactory. As stated by Mr Trohear in evidence, for something to
be defective it first must be faulty or unsatisfactory; that there were times where
something (building element) did not comply with a relevant code or standard but
performed reasonably such that there was no evidence that it was faulty or
unsatisfactory. A performance-based assessment formed a large part of the
investigation method.
[81] In view of subsequent complaints about water ingress and a review of Mr Koen’s
initial decision Mr Trohear attended site on 17 September 2019. Whilst he formed the
view that the box guttering was not leaking a decision was made to engage GHD.
There was evidence of water entry further back inside unit 1510 below the balcony of
unit 1601 (as opposed to the area below the box guttering). GHD was not able to
confirm that the box guttering was in fact leaking. Considering all the material before
him Mr Trohear did not consider there were grounds for him to exercise a new power.
[82] Newsky’s invasive investigation of 29 January 2020 makes it clear that any water
ingress into unit 1510 emanated from the balcony of unit 1601 an area that had
previously been retiled in 2018 and again on sale of unit 1601 in 2020. More to the
point water ingress into bedrooms one and four and the lounge area of unit 1510 was
well away from that area under the box guttering where initial water ingress had
occurred in 2018. This proceeding is limited to building work carried out by Maxcon.
Its involvement with level 16 balcony has been superseded by balcony
building/retiling/sealing work undertaken by others. Nor is it the case that any form
of liability can be imposed on the bodies corporate here in terms of this application.
[83] Mr Muller considered the siphonic drainage system was correctly installed and
sufficient to allow for the discharge of the volume of water he calculated would flow
through from level 16. There was no evidence before the Tribunal that the siphonic
drainage system, sump, or no sump, was defective nor any evidence that ponding in
the box guttering or incorrectly installed overflow provision was directly responsible
for water ingress.
[84] Nor was there any evidence pointing directly to a continuity of water ingress from the
box gutter after Maxcon completed rectification works. Rather the level 16-unit 1601
balcony was the later source of water ingress as evidenced by Newsky’s report of 1
February 2020 and Mr Trohear’s and Mr Lovett’s own observations. In light of level
16-unit 1601 balcony retiling in 2020 it seems that balcony was no longer the source
of water ingress. More to the point any issues about tiling of unit 1601 balcony and
water ingress are now beyond the jurisdiction of the Tribunal for the reason that
6 Turner v Queensland Building Services Authority [2012] QCAT 229.
-- 18 of 20 --
19
Maxcon is not responsible for the state of that tiling undertaken by a third party. Nor
was there any evidence that fire separation provision between unit 1510 and unit 1601
was inadequate or defective.
[85] The whole of the downpipe, spreader, flashing, box gutter, and overflow provision
was fully overhauled/renewed in September/October 2024. Mr Asher’s Specialty
Roofing did the rectification work and GHD were the supervising engineers. GHD’s
report of 15 October 2024 is definitive in recording roof works and level 15 balcony
roof repairs as 100% complete. Mr Lovett may have had some minor concerns about
compliance but as Mr Asher stated the work was carried out in accordance with
Australian Standards. But that work does not appear to be based on identified faulty
or unsatisfactory building work enlivening a direction to rectify but rather contractual
issues as between the principal body corporate and Maxcon (the GHD reports were
prepared for the purposes of a Supreme Court action). The Tribunal cannot accept that
structurally defective building work was the source of the GHD reports for the
purposes of a direction to rectify. What can be said though is that it is now beyond
doubt that the whole of the level 15/16 roof water drainage system is
functional/performing and unit 1510 is watertight.
[86] Nor does the absence of or at least the non-production of forms 15 and 16 render the
works carried out in September/October 2024 somehow defective. In the broader
context those forms are not relevant to a determination as to whether building work is
defective or otherwise.
[87] Given the protracted nature of this proceeding fairness is a heightened consideration
in determining whether to give a direction to rectify for any perceived non-
compliance. The whole of the roof top drainage system was overhauled/renewed by
Specialty Roofing with the associated cost encapsulated in the principal body
corporate’s Supreme Court Action against Maxcon such that the roof top drainage
system can no longer be considered the subject of a direction to rectify to Maxcon.
[88] With respect to consequential damage there were a number of factors which impacted
on whether Maxcon ought to be the subject of a further direction to rectify. These
were the intervention of Chubb’s emergency internal stripping and mould measures,
disputed as excessive by Mr Margaritis, the retiling of unit 1601 balcony in 2020
which may have caused further damage to unit 1510 internally and an absence of
mitigation of loss evidenced by an application made by Dr Carter on 25 March 2020
seeking orders that all respondents desist from any building and certification works to
the roof drainage system pending the Tribunal’s review (refused on 7 December
2020). Years passed with costs no doubt increasing. Additionally consequential
damage to unit 1510 formed part of the loss claimed in the Supreme Court action
against Maxcon commenced in 2022 by the principal body corporate. At this late stage
the Tribunal cannot see that it would be fair (or even of utility) to give a further
direction to rectify for consequential damage.
[89] Based on the initial complaint made by Dr Carter about water ingress into unit 1510
there was nothing inadequate about the Commission’s response. The decision to issue
a direction to rectify was clearly correct as was the direction to rectify which clearly
identified the water ingress issue to be remedied. It was for Maxcon to address that
and only that which was the subject of the direction to rectify. Rectification work was
examined and tested. The rainwater drainage system performed. There was no water
ingress. It was never the case that the complaint nor the Commission’s response would
or should unfold into some sort of commission of inquiry encompassing numerous
-- 19 of 20 --
20
aspects of building practice. The most that can be said is that at a later time another
source of water ingress was identified and that was from the balcony of unit 1601. On
the evidence presently before the Tribunal that has been rectified since at least 2020.
[90] Even taking into account the large volume of material/evidence placed before it the
Tribunal cannot see any reason here to make any change to the direction to rectify
given on 10 May 2018. The Commission’s decision to give a direction to rectify is
confirmed. It is therefore not necessary to consider the Commission’s application to
extend and accordingly it is dismissed.
-- 20 of 20 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2025/339