Croft v Queensland Building and Construction Commission [2025] QCAT 329
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Croft v Queensland Building and Construction
Commission [2025] QCAT 329
PARTIES: SCOTT CROFT
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(respondent)
APPLICATION NO/S: GAR390-20 & GAR391-20
MATTER TYPE: General administrative review matters
DELIVERED ON: 1 September 2025
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Richard Oliver
ORDERS: 1. The respondent pay the applicant’s cost of and
incidental to these proceedings to be agreed or failing
agreement to be assessed by way of a short form
assessment on the Distrct Court scale by a Costs
Assessor to be agreed between the parties and failing
agreement as determined by the Tribunal.
2. The parties have liberty to apply on the giving of 5
days notice in writing to the other party.
CATCHWORDS: ADMINISTRATIVE LAW – GENERAL
ADMINISTRATIVE REVIEW – QUEENSLAND CIVIL
AND ADMINISTRATIVE TRIBUNAL – COSTS – where
applicants achieved a positive outcome from their review
applications without a tribunal determination – where the
applicant incurred considerable costs and outlays in
prosecuting the applications – where applicants have
applied for costs – whether interests of justice require the
respondent to pay costs – whether costs and outlays of
applicant reasonable – whether exercise of discretion
should favour the making of an order for costs.
Queensland Civil and Administrative Tribunal Act 2009
(Qld), s 100, ss 100, 102 and 107.
Queensland Building and Construction Commission Act
1991.
Cantamessa v Queensland Building and Construction
Commission (No 2) [2021] QCAT 213
-- 1 of 15 --
2
Cowen v Queensland Building and Construction
Commission [2021] QCATA 103
Fuge v Queensland Building and Construction
Commission [2014] QCAT 383
Marzini v Health Ombudsman (No 4) [2020] QCAT 365
Neller v Queensland Building and Construction
Commission [2021] QCAT 426
Wardanski v Mawby (No 2) [2023] QSC 237
Pound v Queensland Building and Construction
Commission [2023] QCAT 298
Ralacom Pty Ltd v Body Corporate for Paradise Island
Apartments (No2) [2010] QCAT 412
Stuart v Queensland Building and Construction
Commission [2016] QCATA 135
APPEARANCES &
REPRESENTATION:
This matter was heard and determined on the papers
pursuant to s 32 of the Queensland Civil and
Administrative Tribunal Act 2009 (Qld)
REASONS FOR DECISION
Background
[1] Although the substantive issues in these two review applications have been resolved
between the applicant and the Commission, they have not been dismissed or
withdrawn because the applicant has applied for costs. His contention is that when
regard is had to the history of his complaints to the Commission about defective
building work in the construction of his house, and the outcome whereby he has
substantially succeeded by bringing these review proceedings, it is in the interest of
justice, pursuant to s 102(1) of the Queensland Civil and Administrative Tribunal
Act 2009 (Qld) (“QCAT Act”), that he should be awarded costs.
[2] In considering the question of costs, I am mindful that the Commission is a
regulatory authority and should not make decisions simply on the basis that it might
be exposed to costs.1 The objects of the Queensland Building and Construction
Commission Act 1991 (Qld) (“QBCC Act”), under s 3, is for the Commission to
achieve a balance between the interests of building contractors and consumers. It is
therefore necessary to consider carefully the conduct of the Commission, in its
regulatory role, in the manner in which it has dealt with a legitimate complaint, and
how it responds to any claim on the Home Warranty Insurance Scheme (“HWIS”).
[3] As to the general approach to costs in the Tribunal I refer to and adopt what I said in
Neller & Anor v Queensland Building and Construction Commission2 that is that
generally when proceedings are commenced in the Tribunal they are done so on the
1 Fuge v Queensland Building and Construction Commission [2014] QCAT 383, [28]; Stuart v
Queensland Building and Construction Commission [2016] QCATA 135, [58]; Cantamessa v
Queensland Building and Construction Commission (No 2) [2021] QCAT 213, [20]–[21].
2 [2024] QCATA 46, [12].
-- 2 of 15 --
3
premise that each party will bear their own costs.3 Then as evidence is put on and
issues crystalise, that basic premise may change. Therefore Senior Member
Aughterson’s approach in Pound v Queensland Building and Construction
Commission4 is a more practical way of addressing the question of costs under ss
100 and 102, rather than attempting to identify which of the two approaches
considered in that case should be favoured, i.e. Ralacom or Marzini.5 As he said:
[41] The objects of the QCAT Act, including the issues of access to the
Tribunal and the minimisation of costs, provide an appropriate reference
point for the operation of s 100 of the QCAT Act and, in that context,
may be placed in the balance along with the s 102(3) interests of justice
considerations. The interplay between s 100 and s 102(3) may well
vary, depending on the impact a costs order in the case at hand might
have on access to justice and the other objectives in s 3 of the QCAT
Act.
[42] For example, the prospect of an adverse costs order is likely to weigh
heavily on any decision to seek review of certain administrative
decisions, which will potentially have a significant impact on access to
justice. On the other hand, in relation to body corporate disputes
involving significant monetary or other considerations, the interests of
justice in awarding costs, as alluded to by Keane JA in Tamawood,
might weigh heavily in favour of a costs order. In those circumstances,
the disincentive of a potential costs order in bringing a matter before the
Tribunal is less likely to loom so large and, accordingly, considerations
of access to justice might weigh relatively lightly in the balance against
a costs order.
[43] On that basis, the underlying concern of s 100, in particular of not
impeding access to justice and maintaining a low cost jurisdiction, may
simply be placed in the balance along with the s 102(3) considerations,
with the weight accorded to it being largely dependent on the nature and
scope of the proceedings.
[4] The other relevant consideration is the claim on the HWIS. Although not strictly a
money claim as such, it is akin to a claim for breach of the insurance contract
entered into between a homeowner and the Commission when the mandatory
premium is paid before the commencement of building work. Judicial Member
McGill said in Cowen v Queensland Building and Construction Commission:6
The QBCC Act provides for the statutory insurance scheme in Part 5. Its
purpose is “to provide assistance to consumers of residential construction
work for loss associated with work that is defective or incomplete”: s 67X(2).
The Scheme was explained by Morrison JA, with whom the other members of
the Court agreed, in Schneider v Queensland Building and Construction
Commission [2021] QCA 155, and I respectfully adopt what his Honour said.
It is clear that, when cover under the scheme is provided to a consumer under
the QBCC Act, the consumer is in a position analogous to that of an insured
3 QCAT Act s100
4 [2023] QCAT 298.
5 Ralacom Pty Ltd v Body Corporate for Paradise Island Apartments (No 2) [2010] QCAT 412;
Marzini v Health Ombudsman (No 4) [2020] QCAT 365.
6 [2021] QCATA 103, [31].
-- 3 of 15 --
4
under a policy of insurance issued by the respondent as insurer.31 The terms of
cover under the scheme are set out in the Regulation under the QBCC Act.
The Regulation provides relevantly a limit in the amount of the cover
available in various circumstances of $200,000.
[5] The Judicial Member also went so far as to say that the insurance contract may well
support a civil claim for damages which could be brought in a Court, where costs
outcomes are more favourable. Although the statement does not have direct
application here, what it does signify is that the Commission must consider carefully
any claim made under the “policy” before rejecting it, as would any commercial
insurer.
[6] The application for costs is opposed by the Commission. Its primary position is that
firstly, the applicant cannot claim he has been wholly successful in the review
applications; and secondly, there was a fundamental disagreement between experts
as to whether pier footings7 were failing and causing structural damage and it was
therefore reasonable to decline to accept the complaint. Both the applicant and the
Commission have filed extensive material, both submissions and affidavits, in
support of their respective positions.
[7] However, there is some general agreement between the parties about:
(a) The general law with regard to costs (referred to above);
(b) The relative financial circumstances of the parties as a question of fact, that is
the applicant is in a parlous financial position compared to the Commission;
and
(c) The dispute is complex although it is disputed as to who is responsible for the
complexity.
[8] The costs sought are summarised in the submission of the applicant’s counsel dated
15 July 2024 at [4]:
For the avoidance of any doubt, this application does not seek the total costs
Mr. Croft has incurred across all matters before the Tribunal. He seeks only
those costs incurred directly in connection with these proceedings. For
example he does not seek the costs incurred for related proceedings GAR496-
22 and GAR347-23 (the related proceedings), or the legal costs incurred for
the prior three complaints. All that is sought in this application are the costs
incurred in these proceedings, and the discussion below and in the supporting
material regarding other matters are merely to give context to a procedurally
complex matter.
Brief History
[9] In June 2017 the applicant entered into a building contract with CMG Homes Pty
Ltd8 to construct a new house at Ocean View.9 The block was on a steep hillside and
the subject pier footings were on, or near, the downslope of the block. After the
construction was completed and the applicant had moved into the new house with
7 The subject of a number of complaints.
8 The company went into liquidation in February 2024.
9 A residential development between Dayboro and Mt Mee.
-- 4 of 15 --
5
his partner, he observed a number of defects with the building work carried out by
CMG Homes. This then led to a series of complaints to the Queensland Building and
Construction Commission about defective building work.
[10] The first complaint was in June 2018. This complaint included 78 items and
relevantly for the purpose of this decision, a complaint (no 51) was made about a
change in the footing design.10 There were further complaints made to the
Commission in September 2018, March 2019, February 2020, and November
2021.11 Each of these complaints raised concerns about the potential failure of the
footings, in particular the footings to posts 9 and 10.12 The footings for these posts
were not founded into rock as required by the approved plans.
[11] The significance of these posts for structural support can be seen by reference to
photographs “A” and “B” to Mr Steele’s statement of 31 January 2025. These posts
support the habitable area on the corner of the house to the left side (eastern) looking
towards the deck side of the house. In addition the other posts found not to be
founded in rock are also supporting the house structure. I make this point to avoid
any confusion that the posts were supporting the deck, with presumably a lesser
load, are the ones in question.
[12] It is the complaint made on 18 February 2020 which is the genesis of these
proceedings. This complaint specifically referred to movement in the building
demonstrated by cracks, walls out of plumb, windows and doors not level and
support posts being out of plumb. The defects were supported by expert reports
prepared by Robert Steele RPEQ of Steele Consulting, the first of which was
prepared in 2018.
[13] In response to this complaint, investigations were undertaken by the Commission. It
engaged NJA Consulting Engineers, Mr Van de Hoef, to provide a report about the
potential movement. Critical to this decision on costs, NJA engaged Newsky
Construction Pty Limited (“Newsky”) to excavate the footings to posts 9 and 10 on
27 April 2020. This investigation found that the piers for posts 9 and 10 were .9m
and 1.4m deep and founded in fill. Whereas the design required them to be 2m deep
and founded in rock. This was also confirmed by Core Consultants Geotechnical. It
was plainly evident at this point in time the construction of the pier footings for
these posts were structurally deficient.
[14] After all of the investigations and a considerable exchange of correspondence
between the applicant’s solicitor, Aitchison Reid, and the Commission, the
applicant’s complaint was declined. Also the applicant’s complaint making a claim
under the Home Warranty Insurance Scheme was declined. In other words the
Commission did not intend to take any action, by issuing a Direction to Rectify to
CMG, nor would the HWIS respond to the claim. As a consequence of this decision
the applicant commenced these two review proceedings in the Tribunal on 20
October 2020.
10 Affidavit of Claire Aitchison Reid (“the Reid affidavit”) Exhibit “FR1”.
11 Ibid Exhibits ‘FR2”, “FR3”, “FR4” and “FR5”.
12 Also referred to RW8009 and RW0010 with the footing plan included in the Commissions costs
submissions dated 6 November 2024 (“the Commissions submissions”) at [37] and [128].
-- 5 of 15 --
6
[15] Following the filing of the proceedings and some delay because of the COVID-19
pandemic the Tribunal made directions for completion of procedural steps. A
summary of the chronology of what then occurred is helpful.13
(a) 2 March 2021: Commission provided its statement of reasons;
(b) 9 April 2021: The applications were listed for a compulsory conference;
(c) 18 May 2021: Agreement that both applications be kept separate but be heard
and decided together;
(d) 27 August 2021: Mr Steele’s further report was filed and served;
(e) 1 April 2022: The Commission filed and served statements from Mr Rebibou
(Booth Engineering) and Mr Middleton with reports annexed;
(f) 12 May 2022: CMG Homes was joined as a party;
(g) 30 May 2022: Joint expert conclave with geotechnical engineers;
(h) 13 June 2022: Geotechnical engineers provided joint expert report;
(i) 25 July 2022: Joint expert conclave of engineers;
(j) 24 August 2022: Engineers provided joint expert report;
(k) 21 November 2022: CMG Homes seeks external review of the Direction to
Rectify in relation to 5th complaint (GAR496-22);
(l) 22 November 2021: Applicant’s further complaint to the Commission (the 5th
complaint);
(m) 31 January 2022: Compulsory conference;
(n) 26 October 2023 CMG Homes seeks external review of scope of work in
relation to 5th complaint (GAR347-23);
(o) 6 February 2024: Parties notified that CMG Homes had gone into liquidation
and its proceedings were withdrawn;
(p) 12 June 2024: Directions for filing submissions on costs.
[16] An important consideration in this application is the fact that there has not been final
determination of the review applications. No findings have been made about the
differences in the engineering evidence although the joint expert reports do provide
some assistance. It is not the function of the Tribunal on this application to embark
on a mini hearing to make any findings about which engineering, or other expert
opinion should be preferred. However, the history of complaints about the footing
system is relevant in considering the Commission’s response. In particular the
unequivocal evidence from the Newsky investigations in April 2020.
[17] In regard to the history of the matter, Ms Reid the applicant’s solicitor, has filed a
very comprehensive affidavit setting out relevant factual events and interactions
13 Applicant’s primary submissions [10] settled by Ms McAuliffe-Lake of counsel (“applicant’s
submissions”).
-- 6 of 15 --
7
with the Commission. Generally it is not argumentative nor opinionated but rather
an historical chronology. It also includes a schedule of costs and outlays incurred by
the applicant.
[18] Subsequent to the Tribunal’s direction to determine the application for costs, the
Commission, on 16 September 2024, instructed Mr Rebibou of Booth Engineering,
to provide a “statement of evidence” addressing specific questions posed in an
annexure to that correspondence. The statement was provided and is dated 5
November 2024. I don’t propose to canvass all questions asked and responses given
but there is a consistent theme, that is that although Mr Rebibou identifies areas of
disagreement with the Steele reports, he does concede that the pier footing to four
(not two) posts were not founded in rock as required. He is of the view that the
building structure had not moved or moved very little but accepted the conclusions
in the joint expert reports that the pier foundations were not bearing on suitable
material.14 Again consistent with the Newsky investigations.
[19] I should record that the further statement and opinion of Mr Rebibou is objected to
on the costs application. Also the report of Mr Van de Hoef. By the time the
direction was made that the question of costs be determined on the papers on 9
December 202415 all the evidence, including expert evidence had been filed. There
had been experts conclaves. There is notable difference of opinion as to whether the
inadequate pier footings were resulting in structural damage, however that was
ultimately accepted by the Commission after the 5th complaint. The applicant
submits with respect to these latter statements as follows:
The four experts – Mr Rebibou, Mr Steele, Mr Middleton and Mr Hurley –
have all participated in joint expert processes and provided joint reports.
None have been cross examined, as the proceeding finalised before hearing. It
visits a great unfairness on those experts, whose participation is to assist the
tribunal, to invite the tribunal to determine the costs application based on
adverse credit findings of experts who have not been cross examined, and who
have no opportunity to answer the allegations made against them without
reopening the proceeding completely and at significant cost to both parties. It
does a great prejudice to the applicant that he cannot test the allegations made
against his expert.16
[20] As I said above, it is not the Tribunal’s function to now make findings as to the any
disagreement between the experts, that is for a final hearing which will now not
happen. I therefore adopt the observations of counsel for the applicant as set out
above. Having said that, I have read Mr Rebibou’s statement, and can say it does not
really add anything persuasive in deciding the question of costs.
[21] I therefore now propose to address each of the criteria in s 102(3) of the QCAT Act,
accepting of course that these are only guidelines to assist the Tribunal to make a
decision about costs.
14 Reid affidavit “FR 10” & “FR 11”.
15 It seems by consent.
16 Applicant’s submissions in reply [16].
-- 7 of 15 --
8
Nature and complexity of the dispute
[22] It has already been accepted by both parties that the background to this dispute was
complex, extending over many years. What was not complex was the fact that both
sides accepted there was some movement in the building. The Commission says it
was minimal and even though the footings did not comply with the specification and
were not founded in rock, this did not impact the structural integrity of the building.
That of course was disputed by Mr Steele who made observations that the building
was showing signs of movement as early as 2018.
[23] Mr Steele also observed that it did not require engineering expertise to realise there
would be structural problems with the pier footing when informed, as Mr Hayman
the Commission’s building inspector was at the first inspection, that loose waste and
building debris was deposited in the post holes before the concrete was poured.
Photographs of this were given to him. Also, in the face of this evidence reliance
only on the Forms 15 and 16 (“the Forms”), engineering certification, should not
have been adopted as conclusive.
[24] The applicant, had good grounds for concern in 2018, and followed up with further
complaints subsequently. It is reasonable to conclude in the circumstances that the
Commission knew or ought to have known as early as 2018 there was a problem
with the footings, and undertaken further investigation rather than simply rely on the
Forms.
[25] Given the early and ongoing persistent complaint by the applicant, supported by
engineering evidence from Mr Steele, the complexity arose as a result of the position
taken by the Commission that firstly, the Forms were enough to establish there was
no defective building work; and secondly, failing to accept the obvious on receipt of
the Newsky and Core Consultants reports; and thirdly, even with the ultimate
knowledge that the posts were not founded in rock, contending there was no
structural damage;. This last point is somewhat puzzling because once the six years
has run post practical completion, and being aware that there was a latent structural
defect, the applicant’s access to the HWIS would technically have lapsed.17
[26] I find that the complexity did arise because of the way the Commission dealt with
the applicant’s complaint which ultimately proved to have substance. He had to
commence review proceedings before there was any acknowledgment by the
Commission of the applicant’s and Mr Steele’s concerns about the structural
integrity of the footings.
Relative strengths of the claims made by each party
[27] I have already referred to the concerns raised about the footing in the first complaint.
In the second complaint the issue of the footings was raised again in item 24. It
stated:
Footings have been changed from approved plans corner under block wall on
eastern side of house. No re-inspection done or redrawing confirmed by
engineer when Scott asked had planned being re-drawn. No change on footing
certificate was noted either when provided at handover.
17 There may have been an estoppel argument raised given the earlier complaints, but the outcome of
this would not provide the applicant with any guarantees.
-- 8 of 15 --
9
[28] The report from Mr Steele of November 2018 was relied upon. He was concerned of
the potential failure of the post foundations and retaining wall foundations and
bracing stability. He went so far as to say that the building should not be occupied
because of those concerns.
[29] A second report was provided by Mr Steele in February 2019 in which he noted that
the Commission’s engineer agreed that the concern about the footings for these
particular posts was a serious issue.
[30] The third complaint was made in March 2019 where the Commission’s engineer
noted that while there had been movement there was no significant impact on the
building. Strangely, it also noted that “non-compliance with the design documents is
not indicative of defective building work”. Also, there was a reference to the fact
that if the condition worsened in the future, further investigations would be required.
[31] That then leads to the fourth complaint which resulted in the Newsky investigations.
This conclusively established that the footings were not in accordance with the
specifications, not to the required depth, and not found in rock. Therefore, given the
location of the posts on the side of a hill, slippage, or movement of the foundation
could not be ruled out.
[32] The applicant relies on this sequence of events that:
Put simply, the commission's position was that a defect in the construction of a
key structural component the house was not a structural defect as it had not yet
failed enough. This is a misguided approach where there was expert evidence
before the Commission that such a failure could be catastrophic. Mr Steele is
very clear on how misguided this approach is as a question of engineering
practise and the maintenance of proper standards of construction, and how
dangerous. Mr Steele's view as to the ultimate risk of collapse has been
consistent throughout his involvement.18
[33] It might be said that Mr Steele's concerns may well have been overstated. That is,
the house was uninhabitable, was at risk of collapse, and the house was sliding down
the hill, however even Mr Van de Hoff accepted that the pad footing “had been
pushed downslope”.19 To be fair, even if it was an overstatement it was based on the
fundamental concern that the footing system of the posts was failing. This is also
consistent with not only the applicant’s evidence of debris being dropped into the
excavated post holes, but also signs of movement in the house.
[34] Global Testing, who provided the original site classification report, on 18 June 2020
in response to the applicant’s inquiry about the integrity of the footings said:
We stated in our report that the foundations (the target stratum) of the
structure was to be the Weathered Rock, at a depth of 1000mm below existing
ground level in BH1, and the Weathered Rock at a depth of 1500mm below
existing ground level in BH2. Based on what you have told me, this may not
have happened, which would be a major issue considering what we
recommended………
18 Applicant’s submissions [25].
19 Commissions submissions [146(d)].
-- 9 of 15 --
10
You then said they had cut/filled the site (which may have changed the ‘H1’
classification to a ‘P’ classification, depending on fill depth), but in any case it
would be Global Testing’s view that the foundations of the structure should
have gone through any uncontrolled fill, founded down to Weathered Rock
(original Target Stratum).20
[35] Then the following day on 19 June 2020, Core Consultants informed the
Commission that:
Core Comment No 2: Our findings are that at least two of the footings have
not been constructed as designed and that this is causing distress to the
building. It is likely that this distress will increase, possibly resulting in a
catastrophic building failure. We have recommended to the owners that
ongoing monitoring be undertaken by a licenced surveyor. Further advice will
be provided once monitoring records are available.
Core Comment No 3: The following comments relate to the NJA report.
Firstly, the inference that because there are a lack of significant defects and
that the floor was possibly built with a pre-existing full indicates that the
footings are currently performing adequately is a little misleading because, in
our opinion, the house is sliding down the hill. We do, however, note that NJA
recommended monitoring (at the end of their report) because of the risk of
ongoing movement.
Core Comment No 4: The inspected piers are of inadequate depth and do not
found in rock. The investigation works have proven this. Other footings might
also be inadequate. The NJI report does not provide comment about the
possible impacts of the constructed footings not being in accordance with the
design. There is a sound technical reason for the footing being designed to
found within the rock. It so they don't move down the hill.
Core Comment No 5: it is presumptuous to assume that the fill has moved the
footings. The movement of the footings may equally have caused the cracking
in the fill.
[36] This evidence, together with his own observations proved by the photographs,
establishes that the applicant had a strong case that there was defective building
work in relation to the pier footings. Ultimately at the joint expert conference of the
engineers, the concerns of the applicant were made out not only in relation to the
two posts [9 and 10] but also another two posts as well.
[37] I accept the submission of the applicant’s counsel, that by reference to the history of
consistent complaints about the same issue, the applicant’s concerns were vindicated
and had the Commission properly investigated those concerns, or even after the
Newsky report, the complaint should have been accepted. I find that the strength of
the applicant’s claim far outweighs that of the Commission.
Did the Commission act in a way that disadvantaged the applicant
[38] The applicant refers to conduct of the Commission in the review application. This
conduct is set out in paragraph 31 of counsel’s submission. Factually the chronology
is correct and draw from Ms Reid’s comprehensive affidavit. These complaints
include: failure to notify the applicant of the outcome of his complaints; holding
20 Reid affidavit [99].
-- 10 of 15 --
11
expert reports (geotechnical) for months before handing them over which delayed
his response; notices and decisions sent to the wrong address; requiring the applicant
to seek clarification of comments in correspondence and email to avoid time
limitations; interaction between the parties in relation to the fifth complaint;
unnecessary extensions of time sought by the Commission; refusal to engage in the
wording of an undertaking.
[39] The above complaints of a regulatory authority with limited resources is not
unusual. They are not, in my view, decisive of whether the applicant was
disadvantaged, although I do accept there was delay. The real disadvantage to the
applicant is the way the Commission approached the concerns expressed by both the
applicant and Mr Steele about the structural integrity of the structural pier
foundations. Even after it was apparent, despite Mr Steele’s concern the footings
were not founded in rock supported by the above geotechnical evidence.
[40] It took a fifth complaint, at the request of the Commission, before it acted and this
was after the joint expert reports were to hand. All of this could have been done at a
much earlier stage, certainly by mid 2020, avoiding the necessity to commence these
review proceedings.
[41] I find that the course of the Commission’s conduct with respect to the complaints as
a whole disadvantaged the applicant and this included the need to file the review
applications when the April 2020 Newsky geotechnical report, and the Core
Consultants findings, supported the applicant’s complaint.
Natural justice
[42] The complaint here is that the Commission did not provide a copy of the Direction
to Rectify decision to the applicant in a timely manner. Had it done so, it is
submitted, this may have avoided the need to commence the review proceeding in
relation to the insurance claim. Also, the matters relating to delay in providing the
geotechnical reports are relied upon.
[43] I cannot see that these complaints are a denial of natural justice. Even though there
was some delay, the applicant was provided with all necessary material which
ultimately resulted in a resolution of the substance of his review applications.
Financial Circumstances
[44] The applicant has gone to great expense to enforce his review rights under the
QBCC Act and also contractual rights under the HWIS. As the applicant’s counsel
submits, once in possession of the first Steele report and knowing what he did about
the debris in the excavated footing post holes, he had no choice but to take such
steps as necessary to ensure the structural stability of his house. If he had waited for
further damage to the house so that the Commission could be satisfied that the
movement in the footing was in fact causing structural damage, he may well have
been out of time to make a claim on the HWIS. Also, even though I am not in a
position to make any factual finding about whether the house was in fact
uninhabitable, or in danger of sliding down the hill, there was enough evidence to
cause serious concern for the applicant to about the structural integrity of his home.
[45] Expenses incurred both for legal advice and expert reports was necessary given the
attitude of the Commission to his complaints. His home was clearly at risk and the
-- 11 of 15 --
12
Commission ought to have appreciated this at an earlier stage or at least once the
Newsky investigations were undertaken.
[46] The applicant and his partner have limited income and have had to borrow money to
prosecute his applications. Again this could not have been lost on the Commission
given the communications between it and Aitchinson Reid and the production of the
expert reports provided to it.
[47] It is the Commission’s contention that the expert engineering evidence was so far
apart in terms of their respective opinions that it had no choice but to take the
position it did. As I have already said even if Mr Steele had overstated the
seriousness of the situation involving the pier footings, there was enough objective
evidence to indicate that there were serious concerns about the structural integrity of
the footing system, again I refer to the Newsky investigations in April 2020 and the
findings in the Core Consultants report referred to above.
[48] The Commission was aware, not only that the applicant was being assisted by Ms
Reid, but also knew that costs were being incurred with obtaining the engineering
reports. In addition the Commission was aware that the limit of the payout under the
HWIS was $200,000.00.
[49] In my view the financial disparity is a relevant consideration in considering the costs
application.
Other discretionary factors
[50] The concerns the applicant had about the structural integrity of the building were
reasonable in the circumstances where he had first-hand knowledge of the change in
the footing pad, and also the debris placed in the post holes. In addition, he had the
engineering and geotechnical reports which indicated that there was movement in
the house itself as well as the footings. Even the Commission’s engineer accepted
that there was some movement but was not enough to warrant the issuing of a
direction to rectify.
[51] The applicant’s counsel has summarised the conduct of the Commission as follows:
Despite having all the information necessary to properly investigate the
footings and take the steps it has now taken, it declined to do so. It declined to
do so on three occasions. It made errors and omissions in its dealings with Mr
Croft in the proceedings which caused delay and expense. It took steps (such
as with respect to the briefing of experts and provision of expert reports),
which caused delay an expense. It did not participate effectively or
meaningfully in attempts to resolve the proceedings early. These matters have
directly caused Mr Croft being handed a hollow success.21
[52] Having undertaken an overview of the material, particularly the source material
referred to in Ms Reid’s affidavit, I generally agree with this submission.
Was the applicant successful
[53] The Commission disputes that the applicant was successful in these applications.
That is because there has been no final hearing and the ultimate decision to accept
21 Applicant’s submissions [48].
-- 12 of 15 --
13
the complaints was as a result of lodging a fifth complaint which came out of the
joint experts conclave. Factually that is correct in the sense that it was the fifth
complaint to which the HWIS responded but this was more of a practical way to
activate the access to insurance when the fourth complaint was rejected.
[54] Although there has not been a final hearing, it was clearly open for the Tribunal to
conclude that the correct and preferable decision in the reviews under consideration
was that firstly, the subject footings were structurally defective and the direction to
rectify should issue; and secondly given the builder was in liquidation the HWIS
should respond.
[55] Even though it was the fifth complaint which activated the insurance, I am of the
view that when considering all of the evidence objectively, success for the applicant
on the current proceedings was the most likely outcome.
Conclusion on Costs
[56] Despite reservations that may be applicable to allowing costs awards against
regulatory authorities, I am of the opinion that:
(a) having regard to the history of these applications;
(b) the investigations by Newsky in April 2020 and the subsequent reports and
comments from Core Consultants in the middle of 2020 clearly identifying
non-compliance with the footing design;
(c) the financial circumstances of the applicant, and
(d) the purpose of the HWIS,
that a costs order against the Commission is appropriate in the interests of justice.
[57] In coming to this conclusion I respectfully adopt what Judicial Member McGill SC
said in Cowen v Queensland Building and Construction Commission22 that in view
of the probable success by the applicant in these proceedings any benefit will be
significantly eroded without an order for costs.
Fixing Costs or Assessment
[58] The QCAT Act requires the Tribunal to fix the costs if possible.23 Ms Reid has
provided a schedule of costs and outlays in her affidavit from [321]. The applicant is
only asking for the costs of these proceedings which were filed on 20 October 2020.
The Commission submits that if a costs order is to be made the order should be that
costs be agreed or assessed on the District Court scale of costs.
[59] Having regard to the sequence of events set out in Ms Reid’s affidavit, which is not
really challenged, I could assess costs, because generally, reasonable outlays
incurred are recoverable. That then leaves the solicitors costs. However, given the
large amount of costs claimed it really should be left to an expert to make that
assessment if the parties cannot agree. However, to assist the parties to come to an
agreement on costs I propose to make some general observations about the costs
22 [2021] QCATA 103, [75].
23 QCAT Act s 107.
-- 13 of 15 --
14
claimed. This, hopefully, will save the applicant further delay and costs in going to a
formal costs assessment, which may ultimately end up back before me in any event
if there is no agreement.
[60] I am of the view that given the complexity of the matter it was reasonable to engage
counsel at an early stage in these proceedings, which occurred in early October
2020. Both counsel and the solicitors have reduced the fees claimed in the schedule.
Invoices have been attached.
[61] Except for some outlays, I would propose that the solicitors costs be assessed from 1
October 2020 which would include the preparation of the applications and filing of
same. I consider this is reasonable because by then, even before then in mid 2020, it
was established that the footing system was defective in its construction contrary to
the design. The debate about whether they were causing structural damage to the
house is somewhat irrelevant when it knew, or ought to have been known, they were
likely to fail in any event.24
[62] The basis for the solicitors reduced cost is to exclude the costs related to the review
proceedings commenced by CMG Homes against the Commission, ultimately
withdrawn. It would seem that the costs claimed are really claimed on an indemnity
basis rather than the usual standard basis. I am satisfied that indemnity costs are not
warranted here. Therefore there should be a reduction in the costs claimed to reflect
this.
[63] As a guide I note that in Wardanski v Mawby (No 2)25 Cooper J adopted the
submission of the applicant that costs be reduced 40% to reflect the difference
between actual or indemnity costs and standard costs. His Honour also considered
that it was desirable to fix costs to “save the parties further delay, trouble and
aggravation, which I think the parties would continue to encounter if costs were left
to be assessed”. There are decided cases in the Tribunal where they were reduced by
about one third.26 However, given the Commission has preferred an assessment, and
has not made any submission with respect to the quantum. Considering procedural
fairness issues here, and given the large amount involved, an assessment is
ultimately preferable.
[64] Counsel’s reduced fees as particularised in the Reid affidavit from 1 October 2020
are $32,126.97 which seem reasonable for this protracted matter. However, again a
matter ultimately for the assessor.
[65] As for the expert reports, the applicant claims all of these costs from the first
complaint in 2018. The schedule of costs include (in summary) costs related to,
building reports, concrete scanning, and the engineering and geotechnical reports. It
is contended by the applicant that all of these reports were necessarily relevant to the
negotiation and expert conclaves.
[66] I am satisfied that the engineering reports from Steele Consulting and the
geotechnical reports from Core Consulting were critical to the final outcome in these
24 The solicitors costs from 1 October 2020 are $134,602.38 including those referred to in [328] of the
Reid affidavit.
25 [2023] QSC 237, [83].
26 Ibid [86].
-- 14 of 15 --
15
proceedings. Particularly those produced in early 2020 when the Newsky
investigations were undertaken. As for the other, mainly building reports, I cannot
be so satisfied because each of the complaints (the first four) included multiple items
of complaint unrelated to the engineering and geotechnical issues.
[67] I would consider it reasonable to allow the cost of these expert reports starting from
25 February 2020 in the Schedule,27 because they were necessary to respond to the
Commission’s report. I am aware that the earlier reports were also relevant to the
final outcome but I am also conscious of what I said above about when proceedings
are commenced or when issues crystalise, as they clearly did in mid 2020.28
[68] With these observations in mind, one can only hope the parties can agree to costs so
as to bring these proceedings to an end. I assume if an agreement can be reached all
that will be necessary is for the applicant to file a Notice of Withdrawal. However, I
propose to give the parties liberty to apply back before me if it is necessary for
further orders.
[69] Therefore there will be an order that the Commission pay the applicant’s costs to be
agreed or failing agreement to be assessed by way of a short form assessment on the
Distrct Court scale from a Costs Assessor to be agreed between the parties and
failing agreement as determined by the Tribunal.
27 Reid affidavit [322].
28 The outlays for Steele Consulting and Core Consultants from early 2020 are about $70,000.
-- 15 of 15 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2025/329