Body Corporate for Infinity 1 Community Titles Scheme 45404 v Queensland Building and Construction Commission & Anor (costs) [2025] QCAT 193
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Body Corporate for Infinity 1 Community Titles Scheme
45404 v Queensland Building and Construction
Commission & Anor (costs) [2025] QCAT 193
PARTIES: BODY CORPORATE FOR INFINITY 1
COMMUNITY TITLES SCHEME 45404
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(first respondent)
KARIMBLA CONSTRUCTIONS SERVICES (QLD)
PTY LTD
(second respondent)
APPLICATION NO: GAR327-20
MATTER TYPE: General administrative review matters
DELIVERED ON: 16 May 2025
HEARING DATE: On the papers
DECISION OF: Member McVeigh
ORDER: Each party must bear its own costs.
CATCHWORDS: ADMINISTRATIVE LAW – ADMINISTRATIVE
TRIBUNALS – QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL – costs – statutory basis
– where application to review administrative decision of
first respondent – where second respondent made a
Calderbank offer to the applicant – where applicant did not
accept the offer – where the decision of the first respondent
was confirmed – where second respondent applied for a
costs order against the applicant – approach to costs orders
in the Tribunal – whether order for costs should be made
Queensland Civil and Administrative Tribunal Act
2009 (Qld), s 100, s 102, s 105
Queensland Civil and Administrative Tribunal Rules 2009
(Qld), s 86
Body Corporate for Infinity 1 Community Titles Scheme
45404 v Queensland Building and Construction
Commission [2025] QCAT 54
-- 1 of 8 --
2
APPEARANCES &
REPRESENTATION:
This matter was heard and determined on the papers
pursuant to s 32 of the Queensland Civil and Administrative
Tribunal Act 2009 (Qld)
Applicant: S S Monks instructed by Hynes Legal
Second Respondent: G A Sirtes SC with J Bridgett instructed by Meriton
corporate counsel
REASONS FOR DECISION
What is this application about?
[1] On 3 February 2025 I confirmed the decision of the Queensland Building and
Construction Commission (Commission) not to direct the second respondent
(Contractor) to rectify the aluminium composite panels which act as sunscreens on
Meriton tower.1
[2] The Meriton tower is a very tall building in the Brisbane CBD. It was completed in
April 2014. It features sunscreens attached to floor slabs. The horizontal sunscreens
consist of a polyethylene core encapsulated in aluminium, commonly known as
aluminium composite panels (ACPs). If the Meriton tower was constructed today it
would not have ACPs attached as sunscreens as use of such material as part of, or
attached to, the exterior of a building was essentially prohibited following the
Lacrosse building fire in Melbourne in 2014 and the Grenfell tragedy in London 2017.
[3] When the Meriton tower was constructed and certified the relevant building code
permitted the use of sunscreens constructed, in part, of combustible material
(polyethylene is combustible) if they did not constitute an undue risk of fire spread
via the facade of the building. In the proceedings the applicant Body Corporate argued
unsuccessfully that the ACPs constituted an undue risk of fire spread via the facade
of the building and that as a consequence that the Commission’s decision should be
reversed with the consequence that the Contractor be directed to rectify.
[4] On 31 May 2023 the Contractor made a Calderbank offer to the applicant Body
Corporate. Had the offer been accepted the application for review would have been
withdrawn.
[5] This decision relates to the Contractor’s application for costs of the proceedings
including all reasonable costs from 31 May 2023.
Relevant legislation
[6] Section 100 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)
(QCAT Act) provides:
Each party usually bears own costs
Other than as provided under this Act or an enabling Act, each party to a
proceeding must bear the party's own costs for the proceeding.
1 Body Corporate for Infinity 1 Community Titles Scheme 45404 v Queensland Building and
Construction Commission [2025] QCAT 54.
-- 2 of 8 --
3
[7] However, if the tribunal considers the interests of justice require it, section 102 of the
QCAT Act permits the making of an order requiring a party to a proceeding to pay all
or a stated part of the costs of another party. Factors that may be taken into account
include:
(a) whether a party to a proceeding is acting in a way that unnecessarily
disadvantages another party to the proceeding including not complying
with a tribunal order or direction without reasonable excuse;
(b) the nature and complexity of the dispute the subject of the proceeding;
(c) the relative strengths of the claims made by each of the parties to the
proceeding;
(d) for a proceeding for the review of a reviewable decision:
(i) whether the applicant was afforded natural justice by the decision-
maker for the decision; and
(ii) whether the applicant genuinely attempted to enable and help the
decision-maker to make the decision on the merits:
(e) the financial circumstances of the parties to the proceeding; and
(f) anything else the tribunal considers relevant.
[8] The making of an offer to settle that was not accepted may be taken into account.2
[9] Rule 86 of the Queensland Civil and Administrative Tribunal Rules 2009 (Qld)
(QCAT Rules) provides:
86 Additional power to award costs if particular offers to settle rejected
(1) This rule applies if—
(a) a party to a proceeding, other than a proceeding for a minor civil
dispute, makes another party to the proceeding a written offer to
settle the dispute the subject of the proceeding; and
(b) the other party does not accept the offer within the time the offer
is open; and
(c) in the opinion of the tribunal, the decision of the tribunal in
proceeding is not more favourable to the other party than the offer.
(2) The tribunal may award the party who made the offer all reasonable costs
incurred by that party in conducting the proceeding after the offer was
made.
(3) If a proceeding involves more than 2 parties, this rule only applies if the
acceptance of the offer would have resulted in the settlement of the
matters in dispute between the parties.
(4) In deciding whether a decision is or is not more favourable to a party than
an offer, the tribunal must—
(a) take into account any costs it would have awarded on the date the
offer was given to the other party; and
2 Queensland Civil and Administrative Tribunal Act 2009 (Qld) s 105.
-- 3 of 8 --
4
(b) disregard any interest or costs it awarded relating to any period
after the date the offer was given to the other party.
Do the interests of justice require an order for costs to be made in favour of the
Contractor?
Nature and complexity of the dispute
[10] The proceedings were administrative review proceedings arising from a decision of
the Commission. Although the scope of the application to review the Commission’s
decision had narrowed significantly by the time of the hearing, the issue remaining
was complex.
[11] All the parties were legally represented, leave having been given on 12 April 2021.
[12] In order to reach a conclusion, it was necessary to consider all the evidence to decide
whether the decision of the Commission should be confirmed or set aside. It was also
necessary to interpret the Building Code of Australia (BCA), in particular General
Requirement 2.4(iii), to decide whether the risk of retaining the ACPs was undue. This
required assessment of expert evidence. The experts maintained differing views about
the proper interpretation of the BCA, with the consequence that their views differed
in relation to the balance of the likelihood of fire spread against the gravity of the
consequences of fire spread.
[13] This evidence included:
(a) Mr Hofstetter’s affidavit. He is a senior building certifier and the person who
certified the Meriton tower.3
(b) Mr Igoe’s report. He is a level 1 building certifier. He has 20 years of experience
as a private certifier of commercial buildings.4
(c) A fire safety analysis and assessment of the ACPs on the Meriton tower by AED
Fire Pty Ltd (AED) which had been commissioned by Meriton Group, but not
prepared for these proceedings.5
(d) Mr Stratton’s reports. He is a fire engineer, who was called by the Body
Corporate. He provided a number of reports, the first in September 2021,6 the
second in June 2022.7
(e) Mr Alexander’s reports. He is qualified in both fire safety and building
certification. He was called by the Contractor. He provided a number of reports,
the first in March 2022.8
(f) A joint report by Mr Stratton and Mr Alexander.9
(g) Mr Alexander’s commentary on a report prepared by Ignis Labs Pty Ltd (Ignis)
regarding large scale tests to evaluate fire spread risk if an external sprinkler
3 Body Corporate for Infinity 1 Community Titles Scheme 45404 v Queensland Building and
Construction Commission [2025] QCAT 54, [59].
4 Ibid [61].
5 Ibid [68].
6 Ibid [79].
7 Ibid [90].
8 Ibid [85].
9 Ibid [93].
-- 4 of 8 --
5
system (drenchers) were to be installed on the Meriton tower. The testing and
subsequent report was prepared at the request of Meriton.10
[14] The Contractor submits that if an order for costs is not made in favour of a successful
party in complex review proceedings, then parties would be disincentivised from
engaging and obtaining multi-disciplinary expertise to assist the tribunal. I
acknowledge that the experts provided considerable assistance. However, it was plain
on the face of the reports from AED and Ignis that they had not been engaged for the
primary purpose of assisting the tribunal. The authors of those reports did not give
evidence.
[15] The Contractor had a significant financial incentive in supporting the Commission’s
original decision. I accepted the Contractor’s submission that the replacement of the
sunshades over a major proportion of the floors of this building would impose a
substantial cost (the only evidence of the cost of rectification came from a cost
estimate prepared by Sedgwick Quantity Surveyors dated 17 August 2020 which
estimated the cost of replacing the cladding to be $3,787,167 plus GST) and that the
cost would be even greater more than four years after that estimate was given.11
[16] I accept the Body Corporate’s submissions that complexity and the need to deal with
technical evidence are not sufficient on their own to justify the making of an order for
costs. Those factors might well have influenced the Contractor’s decision to be joined
and to be legally represented. Clearly its interests could have been affected by the
outcome of the proceeding. Had the Commission’s decision been reversed the
financial consequences for it would have been significant.
[17] If the guidance provided by Keane JA in Tamawood Ltd v Paans,12 a case about costs
orders in a domestic building dispute, applies in administrative review proceedings
where the parties are not entitled to legal representation as of right, there are
countervailing considerations to be taken into account. The Contractor had a
significant commercial interest in supporting the decision of the Commission. It is
better resourced than the Commission, enabling it to engage experts and senior
counsel to support the decision the subject of the challenge. It could afford bespoke
testing. It had reports from AED and Ignis that were not prepared solely for the
purpose of the review proceedings but which it used to support its arguments. There
are sound commercial reasons for it to have spent less than $400,000 when faced with
a potential liability of considerably more than ten times that amount.
The relative strengths of the claims made by each of the parties
[18] The Body Corporate had a statutory right to seek a review of the decision of the
Commission.13 I reject the submission from the Contractor that the Body Corporate’s
position was, at all stages of the proceeding, without merit.
[19] The Body Corporate relied on advice from a well-qualified expert. Mr Stratton’s
interpretation of General Requirement 2.4(iii) of the 2009 BCA differed from the
interpretation adopted by Mr Alexander. Unlike Mr Alexander, and other experts
relied on by the Contractor, Mr Stratton did not think it acceptable to rely on
certificates provided by suitably qualified professionals when undertaking a risk
10 Ibid [100].
11 Ibid [145].
12 [2005] 2 Qd R 101.
13 Queensland Building and Construction Commission Act 1991 (Qld) s 87.
-- 5 of 8 --
6
assessment. I found that Mr Stratton’s opinion that a qualitative assessment of the risk
was required in order to comply with General Requirement 2.4(iii) of the 2009 BCA
was correct.14 Although I had regard to Mr Alexander’s list of characteristics of the
building that minimised the risk of fire spread,15 I did not adopt his approach to
assessing the risk. When reaching the decision that the Commission’s decision under
review should be confirmed, I concluded that it could not be said that there was no
risk of fire spread, but that the risk of fire spread via the façade was not undue. I had
regard to Mr Statton’s concerns about the gravity of a fire in the Meriton tower.16
Whether the applicant genuinely attempted to enable and help the decision-maker to
make the decision on the merits
[20] I reject the Contractor’s argument that the Body Corporate provided no meaningful
support of its position. Its position was supported by the evidence of Mr Stratton, a
well-qualified expert. I accepted his interpretation of General Requirement 2.4(iii) of
the 2009 BCA.
[21] The Commission made no complaint about a lack of assistance from the Body
Corporate. I have no complaint about the conduct of the Body Corporate in the
proceedings.
Financial circumstances of the parties
[22] The financial circumstances of either party is not a factor that has swayed me in the
exercise of my discretion in this application for costs.
[23] Neither the Body Corporate nor the Contractor is in a precarious financial position.
There is common ground that the Body Corporate has both funds available to it and
the ability to raise further funds via a special levy. The Contractor is part of the
Meriton Group of companies, a very successful Australian business. Its senior
corporate counsel affirmed that it had incurred costs in the amount of $357,309.98
(excl. GST) as at 3 March 2025.17
The Calderbank offer
[24] On 31 May 2023, the Contractor made an offer to the Body Corporate, on a without
prejudice save as to costs basis, proposing to resolve the application on a commercial
basis, on the premises that the Body Corporate withdraw the proceedings, and in
exchange for the withdrawal of the proceedings, that the parties agree that there be no
order as to costs.18
[25] The Body Corporate’s failure to take up the offer was not unreasonable.
[26] The offer was made on the day the report from Ignis was provided to the Body
Corporate. Mr Alexander’s commentary on it was not provided until later. The report
related to two bespoke tests carried out by Ignis. The second test related to the risk of
fire spread from one level to another including lateral spread. Ignis summarised the
test result as indicating that when an uncontrolled fire event occurred directly on the
14 Body Corporate for Infinity 1 Community Titles Scheme 45404 v Queensland Building and
Construction Commission [2025] QCAT 54, [138].
15 Ibid [128].
16 Ibid [142].
17 Affidavit of Lily Amelia McMillan made 3 March 2025.
18 Ibid [37].
-- 6 of 8 --
7
panel without automatic fire sprinklers, limited fire spread was likely to occur.19 The
report made no comment about the qualitative assessment of the risk which I found
was required in order to comply with General Requirement 2.4(iii) of the 2009 BCA.
[27] I reject the Contractor’s submission that the results of the Ignis testing coupled with
the expert evidence relied on by the Contractor revealed that the application was
bound to fail. The Ignis test results were only relevant to the possibility of fire spread
eventuating. In considering whether there was an undue risk of fire spread I adopted
a multi-factorial test. I considered the circumstances and context in which the ACPs
were used. Factors considered included:
(a) the objective of Section C of the 2009 BCA to ensure safety of people from fire;
(b) location of the panels;
(c) fire safety features of the building;
(d) ignitability of the ACPs;
(e) the possibility of fire spread eventuating; and
(f) gravity of the risk.20
[28] Mr Stratton, the expert advising the Body Corporate, was always of the opinion that
the gravity of the risk was undue. The Ignis report did not change his opinion.
Contrary to the Contractor’s submissions, the Body Corporate with the benefit of
informed legal advice could not have known that its application was unlikely to
succeed. It certainly was not doomed to failure. Mr Stratton had always maintained
his opinion, which was ultimately accepted, that a Deemed to Satisfy solution did not
comply with General Requirement 2.4(iii) of the 2009 BCA. His qualitative
assessment of the risk was not changed by the test results as the possibility of fire
spread eventuating was but one of the factors he took into account when undertaking
the risk assessment.
[29] I reject the Contractor’s submission that the offer canvassed the Body Corporate’s
prospects of success ‘in some detail’. Two of the four points addressed the proposal
to install an automatic fire sprinkler system which had no relevance to the
proceedings. Although the other points were relevant to matters in issue, no attempt
was made to canvass all matters that needed to be considered when applying the multi-
factorial test required to address the risk assessment issue. At its highest, one of the
four points addressed in the offer provided additional factual support to opinions
expressed by Mr Alexander. The final point was merely a repetition of the
Contractor’s argument about the requirements of the BCA. It did not canvass the key
issue of compliance with General Requirement 2.4(iii) of the 2009 BCA.
Public interest
[30] The Body Corporate submits that another relevant factor is that these proceedings
were in the nature of public interest litigation. While there is no doubt that the use of
combustible materials as an external cladding on high rise buildings is a nation-wide
problem, these proceedings cannot be characterised as a test case. They are
19 Body Corporate for Infinity 1 Community Titles Scheme 45404 v Queensland Building and
Construction Commission [2025] QCAT 54, [101].
20 Ibid [140].
-- 7 of 8 --
8
administrative review proceedings with a decision based on a qualitative assessment
of the risk for the particular building in question.
Decision
[31] Having taken into account:
(a) the nature and complexity of the dispute the subject of these proceedings;
(b) the relative strengths of the claims made by the Body Corporate and the
Contractor;
(c) the Body Corporate’s attempts to enable and help the Commission and the
tribunal standing in the shoes of the Commission to make the decision on the
merits;
(d) the financial circumstances of the parties to the proceeding;
(e) the Calderbank offer; and
(f) other submissions made by the Body Corporate and the Contractor;
I have decided that the interests of justice do not require the making of an order
requiring the Body Corporate to pay any of the costs of the Contractor.
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2025/193