Abbott Builders (Qld) Pty Ltd v Queensland Building and Construction Commission [2025] QCAT 144
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Abbott Builders (Qld) Pty Ltd v Queensland Building and
Construction Commission [2025] QCAT 144
PARTIES: ABBOTT BUILDERS (QLD) PTY LTD
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(respondent)
APPLICATION NOS: GAR367-19; GAR499-19; GAR003-20
MATTER TYPE: General administrative review matters
DELIVERED ON: 28 April 2025
HEARING DATE: 20 January 2025
HEARD AT: Brisbane
DECISION OF: Member Chapple
ORDERS: 1. GAR367-19: The Direction to Rectify decision is
amended as follows:
a. For the conceded items, to omit direction
items, DTR 15 and 52.
b. For direction item, DTR 4, to read:
The installation of the James Hardie soffit is
not consistent with the proper usage of the
Inex Maxideck decking and the doorways onto
the three decks are void of flashings.
2. GAR499-19: The Unsatisfactory Work decision is
amended as follows:
a. For the conceded items, to omit the
references to unsatisfactory rectification
work in respect of direction items, DTR 13,
47 and 49.
b. To omit the references to unsatisfactory
rectification work in respect of direction
items, DTR 1, 2, 9, 10, 14, 22, 26, 27, 30, 35,
39, 43 and 45.
-- 1 of 30 --
2
3. GAR499-19: The Unsatisfactory Work decision in
respect of direction item, DTR 23 is set aside, and
the matter is returned to the QBCC for
reconsideration with the direction that the
property’s stormwater drainage system be
reinspected to ascertain the existence of a second
stormwater line at the time of the decision.
4. GAR003-20: The Scope of Works decision is
amended as follows:
a. For the conceded items, to omit scope of
work items, SOW 8, 22, 23, 24 and 25.
b. For SOW 3 in respect of direction item, DTR
4, to read:
• Install flashing to the openings around the
doorways onto the three decks in
accordance with Clauses 2.2.2 and 3.5.3.6
of the National Construction Code.
• In relation to the three decks:
o Remove the James Hardie soffit.
o Install perforated steel sheeting on
the underside of the decking in
accordance with the construction
contract.
o Apply rust-resistant paint to the
steel joists supporting the decking
in accordance with the corrosion
protection requirements of the
National Construction Code.
c. To omit SOW 7 in respect of direction item,
DTR 14.
d. To omit SOW 12 in respect of direction item,
DTR 24.
5. GAR003-20: The Scope of Works decision for SOW
5 in respect of direction item, DTR 10 is confirmed.
6. GAR003-20: The Scope of Works decision for SOW
11 in respect of direction item, DTR 23 is set aside,
and the matter is returned to the QBCC for
reconsideration with the direction that the
property’s stormwater drainage system be
reassessed to ascertain the existence of a second
stormwater line at the time of the decision.
-- 2 of 30 --
3
7. GAR003-20: The Scope of Works decision for SOW
17 in respect of direction item, DTR 39 is confirmed.
8. GAR003-20: The Scope of Works decision for SOW
19 in respect of direction item, DTR 43 is confirmed.
CATCHWORDS: GENERAL ADMINISTRATIVE REVIEW – where
Tribunal review of QBCC Direction to Rectify,
Unsatisfactory Work, and Scope of Works decisions –
where review applications heard concurrently
Acts Interpretation Act 1954 (Qld), s 14A
Queensland Building and Construction Commission Act
1991 (Qld), s 67X(3), s 71A, s 72, s 86(1), Schedule 2
Queensland Civil and Administrative Tribunal Act 2009
(Qld), s 24
ACN148 877 525 Pty Ltd v Queensland Building and
Construction Commission [2022] QCAT 72
Queensland Building and Construction Commission v
Groupline Constructions Pty Ltd [2020] QCA 245
Ramke Constructions Pty Ltd v Queensland Building
Services Authority (No 2) [2013] QCAT 575
APPEARANCES &
REPRESENTATION:
Applicant: Mr Tim Elliss, instructed by Robinson Locke Lawyers
Respondent: Ms Melanie Hudson, in-house solicitor for the Queensland
Building and Construction Commission
REASONS FOR DECISION
Background
[1] On 5 December 2016, the applicant, Abbott Builders (Qld) Pty Ltd (‘Abbott’) entered
into a contract for the construction of a new home at a property owned by Mr and Mrs
Forrest (‘the homeowner’) and located at 89 Outlook Terrace, Ferny Grove in the
State of Queensland (‘the property’).
[2] Abbott reached practical completion of the home on 20 June 2018. On that date, the
homeowner notified Abbott of a series of defects, and on 15 July 2018 lodged a formal
complaint accompanied by a list of defects with the respondent, the Queensland
Building and Construction Commission (‘the QBCC’).
[3] The QBCC issued Abbott a direction to rectify (‘the DTR’) defective work. In
response, Abbott sought to rectify the defects the subject of the DTR. The QBCC then
approved a claim by the homeowner under the statutory insurance scheme for those
items of work the QBCC considered had not been satisfactorily rectified (‘the USW’).
[4] Abbott applied to the Tribunal for the review of three decisions made by the QBCC
under the Queensland Building and Construction Commission Act 1991 (Qld) (‘the
QBCC Act’). The review applications are as follows, heard together by the Tribunal
on 20 and 21 January 2025:
-- 3 of 30 --
4
(a) GAR367-19 Application for review of a decision to give a direction to rectify
(‘the DTR decision’).
(b) GAR499-19 Application for review of a decision that building work undertaken
at the direction of the QBCC was not of a satisfactory standard (‘the USW
decision’).
(c) GAR003-20 Application for review of a decision about the scope of works to
be undertaken under the statutory insurance scheme (‘the SOW decision’).
Legislation and policy
[5] Building work includes the erection or construction of a building.1
[6] Where the QBCC is of the opinion that building work is defective or incomplete, it
may direct the person who carried out the work to rectify the building work within a
specified period.2 Defective, in relation to building work, includes faulty or
unsatisfactory work.3 To rectify building work means to remedy defective building
work or to complete incomplete building work.4
[7] The QBCC Rectification of Building Work Policy further assists in defining defective
building work as work that does not comply with the Building Act 1975 (Qld),
Building Code of Australia or an applicable Australian Standard, or involves the use
of a manufactured product where that product has been used, constructed or installed
in a way that does not comply with the product manufacturer’s instructions.
[8] In deciding whether to give a direction to rectify, the QBCC may take into
consideration all the circumstances it considers are reasonably relevant and, in
particular, is not limited to a consideration of the terms of the contract for carrying out
the building work.5 The QBCC is not required to give the direction to rectify if it is
satisfied that, in the circumstances, it would be unfair to the person to give the
direction.6
[9] There is no process in the QBCC Act for making a decision about whether or not a
direction to rectify has been complied with. The only reference to such a decision is
among the list of reviewable decisions, being “a decision that building work
undertaken at the direction of the commission is or is not of a satisfactory standard”.7
[10] Part 5 of the QBCC Act establishes a statutory insurance scheme to provide assistance
to consumers of residential construction work for loss associated with work that is
defective or incomplete.8
1 QBBC Act sch 2 (definition of ‘building work’).
2 Ibid s 72(2).
3 Ibid sch 2 (definition of ‘defective’).
4 Ibid (definition of ‘rectify’).
5 Ibid s 72(3).
6 Ibid s 72(5).
7 Ibid s 86(1)(f).
8 Ibid s 67X(3).
-- 4 of 30 --
5
[11] There is no process in the QBCC Act for making a decision about the necessary scope
of the rectification works. The only reference to such a decision is among the list of
reviewable decisions, being “a decision about the scope of works to be undertaken
under the statutory insurance scheme to rectify or complete tribunal work”.9
[12] The purpose of a scope of works decision is to outline a programme of works which
is reasonable and necessary to rectify identified defects. It may also extend to
consideration of whether the relevant programme of works is a reasonable cost-
effective method of rectifying the identified defects. A review of a scope of works
decision is limited to asking what rectification works are reasonable and necessary
given the nature of the work to be undertaken.10
[13] The cost of performing the works in accordance with the scope of works may be
established by the QBCC seeking tenders for the carrying out of the works.11 Where
the QBCC makes a payment on a claim under the statutory insurance scheme, it may
recover the amount as a debt from the building contractor whose fault gave rise to the
claim.
[14] Section 86(1) of the QBCC Act identifies the decisions that are reviewable decisions,
including:
(e) a decision to give a direction to rectify or remedy or not to give the
direction;
(f) a decision that building work undertaken at the direction of the
commission is or is not of a satisfactory standard;
(g) a decision about the scope of works to be undertaken under the statutory
insurance scheme to rectify or complete tribunal work;
[15] Section 87 of the QBBC Act provides that a person affected by a reviewable decision
of the commission may apply, as provided under the Queensland Civil and
Administrative Tribunal Act 2009 (Qld) (‘QCAT Act’) to the Tribunal for a review of
the decision.
Tribunal’s jurisdiction
[16] I am satisfied that the DTR decision, the USW decision, and the SOW decision are
reviewable decisions, and the Tribunal has jurisdiction to review each of the decisions
and to make certain orders.12
Issues for determination
[17] The parties made a concerted effort to narrow the issues in dispute and for
determination by the Tribunal. The table below is a précised overview of these issues
as at hearing commencement. The parties also produced a ‘Detailed Itemised
Overview’, which is too lengthy to reproduce here, however I reference relevant
excerpts throughout these reasons.
9 Ibid s 86(1)(g).
10 ACN148 877 525 Pty Ltd v Queensland Building and Construction Commission [2022] QCAT 72.
11 QBCC Act s 71A.
12 QCAT Act s 24.
-- 5 of 30 --
6
DTR
ITEM
DESCRIPTION DTR USW SOW
1 Apron flashing – upper-level veranda roof
2 Soffit moulding – upper-level veranda
4 Decking substrate and openings to all three
decks
3
9 Painting – external corner stops to the dwelling
10 Butt joints to the decks 5
14 Bracing wall gaps – bedroom 2 7
22 Rainwater tank
23 Stormwater system – lines to kerb 11
24 Window flashing – carport/workshop 12
26 Fascia and gutter – upper-level carport
27 Fascia/barge – above office and laundry
30 Main roof sheeting
35 Laundry door, jambs and mouldings
39 Timber floor levels – throughout dwelling 17
43 Timber walls out of plumb – throughout
dwelling
19
45 Cavity sliding doors – ensuite and laundry
[18] I note the following items have been conceded by the QBCC:
(a) The DTR decision in respect of DTR 15 and 52.
(b) The USW decision relating to unsatisfactory work in respect of DTR 13, 47 and
49.
(c) The SOW decision relating to SOW 8, 22, 23, 24 and 25.
Statements of evidence
[19] Mr Wayne Steven Abbott is a director of Abbott, and Mr Ron Paterson is a project
manager employed by Abbott.
[20] Mr John Reeve is a director of Professional Certification Group and a level 2 building
certifier retained by Abbott to assess the certification requirements for the
construction of the new home at the property.
[21] Mr Andrew Stephen Kirby is a senior building inspector employed by the QBCC who
was allocated responsibility for assisting in these applications in December 2024. The
original investigation was conducted by another building inspector for the QBCC, Mr
Robert Murphy, who left the employ of the QBCC in mid-2023.
-- 6 of 30 --
7
[22] In respect of each of the review applications, Abbott relies on the following statements
of evidence:
GAR367-19: DTR decision
(a) Statement of evidence of Wayne Steven Abbott dated 17 April 2023 (‘SOE:
DTR Abbott’).
(b) Statement of evidence of Ron Paterson dated 17 April 2023 (‘SOE: DTR
Paterson 1’).
(c) Statement of evidence of Ron Paterson dated 12 March 2024 (‘SOE: DTR
Paterson 2’).
(d) Statement of evidence of John Reeve 19 April 2024 (‘SOE: DTR Reeve’).
GAR499-19: USW decision
(e) Statement of evidence of Wayne Steven Abbott dated 17 April 2023 (‘SOE:
USW Abbott’).
(f) Statement of evidence of Ron Paterson dated 17 April 2023 (‘SOE: USW
Paterson’).
GAR003-20: SOW decision
(g) Statement of evidence of Wayne Steven Abbott dated 17 April 2023 (‘SOE:
SOW Abbott’).
(h) Statement of evidence of Ron Paterson dated 17 April 2023 (‘SOE: SOW
Paterson’).
All applications
(i) Statement of evidence of Ron Paterson dated 16 January 2025 (‘SOE: ALL
Paterson’).
[23] In respect of all of the review applications, the QBCC relies on the statement of
evidence of Andrew Stephen Kirby dated 10 January 2025 (‘SOE: QBCC Kirby’).
Consideration
[24] I am assisted by the parties’ submissions as follows:
(a) Written Submissions of the Applicant dated 17 January 2025.
(b) Commission’s Outline of Submissions dated17 January 2025.
(c) Applicant’s Further Submissions on Bedroom 2 Wall dated 31 January 2025.
(d) Commission’s Post-Hearing Submissions dated 31 January 2025.
-- 7 of 30 --
8
DTR 4: DTR + SOW 3 decisions
[25] The DTR decision described the item 4 defect as follows:
The construction detail of the decks, the installation of the decking material and
openings to all 3 external decks are defective and not in compliance with the
National Construction Code 2016 Volume 2 – Clauses P2.2.2 & 3.5.3.6, in that
the openings onto the decks (doorways) are void of flashings, deck substrate
(Inex-Maxideck) is allowing moisture to penetrate the decks which has resulted
in the deterioration of the building elements.
[26] The SOW decision described the item 3 scope of works as follows:
• Allow to disassemble all decks, reuse balustrading, joist where
applicable.
• Remove sliding doors that open onto decks and supply and install a
compliant flashing/sub-sill to openings – reinstall sliding doors.
• Reinstate/construct decks as per working drawings ensuring compliant
stepdown at openings and adequate fall is achieved.
• Supply and install Maxideck as per manufacturers recommendations.
• Reinstall balustrading.
• Paint and make good all affected surfaces.
[27] At the outset, I note the QBCC’s post-hearing submissions in relation to this issue. I
consider the issue of whether the decks are Class 1a or Class 10a buildings is a
threshold issue of fact I am required to determine by reference to the National
Construction Code and other relevant publicly available documents, an analysis of
which is set out in these reasons. It was open to the QBCC to include in its post-
hearing submissions further submissions supporting their claims regarding the
building classification of the decks. I do not consider the issue to be a matter of
opinion, for example, of Mr Reeve, and therefore do not accept the QBCC has been
disadvantaged in any way by not having the opportunity to cross-examine Mr Reeve.
I reject the QBCC’s submission that the Tribunal ought to give no weight to Abbott’s
submission about the building class of the decks.
[28] I summarise Abbott’s evidence as follows:
(a) Prior to entering into the construction contract, the homeowner stipulated to Mr
Paterson the installation of Inex Maxideck for the decking on all three decks, a
product the homeowner had researched for this purpose.13
(b) Inex Maxideck is made up of 2700 mm x 600 mm sheeting of a composite fibro
with a woodgrain stain-like finish depending on the chosen paint colour. The
sheeting interlocks and an inex bond sealant is used to seal the joints when used
in wet areas.14
13 SOE: ALL Paterson, para 4a.
14 Ibid.
-- 8 of 30 --
9
(c) The Maxideck product is intended to be external and to deal with exposure to
weather. The manufacturer’s product and installation guides state that the
product is water resistant not waterproof. The product has since been withdrawn
from the market.15
(d) Abbott subcontracted a carpenter to install the Maxideck product and provided
the relevant installation manual to them. The carpenter had not seen or used the
product before.16
(e) While on site during the fixing stage of the contract, Mr Paterson received a
verbal request from the homeowner that the underside of the deck be sheeted
with a 4.5 mm James Hardie soffit, a fibre-reinforced cement sheet painted on-
site, to match the office area adjacent to the large front deck, for a more
appealing finish than the perforated steel sheeting specified in the specifications.
The soffit material did not change the use of the under-croft area. Mr Paterson
had no reason to believe the installation of the soffit material would negatively
impact the Inex Maxideck.17
(f) The soffit material and installation were a variation, though there was no
additional documentation.18
(g) The provision in the specifications for perforated steel sheeting on the underside
of the deck meant that the steel joists supporting the deck would not be enclosed
and would require rust-resistant paint to comply with the corrosion protection
requirements of the National Construction Code. As a result of the homeowner’s
requested variation to the soffit material, the steel joists were enclosed and the
National Construction Code 2016 – Building Code of Australia (‘the NCC’)
requirements did not apply.19
(h) In relation to the QBCC site report noting a slight step down from the finished
floor level to deck level (approx. 10-15 mm) when working drawings specify
40 mm, Mr Abbott and Mr Paterson were present when, during inspection, the
QBCC inspector did not measure the step down. In Mr Abbott’s presence, Mr
Paterson measured the step down at 40 mm. The homeowner has acknowledged
a 30-40 mm step down. There is no Australian Standard requirement for a step
down, however Mr Abbott and Mr Paterson acknowledge that it is good building
practice.20
15 SOE: DTR Paterson 2, para 14.
16 SOE: ALL Paterson, para 4c.
17 Ibid, para 16; SOE: ALL Paterson, paras 4b, 4e.
18 SOE: ALL Paterson, para 4f.
19 SOE: ALL Paterson, paras 12b, 12c.
20 SOE: DTR Abbott, paras 17-20; SOE: DTR Paterson 1, paras 15-18.
-- 9 of 30 --
10
(i) In relation to the DTR defect that the doorways onto the decks are void of
flashings, water ingress into the dwelling is not the issue. There has been no
water ingress into the dwelling or any such complaint.21 The dwelling is fully
sealed and there is a gap between the dwelling and the decking such that there
can be no water ingress caused by the absence of flashing on the door. The water
issue relates to the soffit beneath the Inex Maxideck, in that it is the recess
between the decking and the soffit that is alleged to be accumulating moisture.22
(j) The water damage only relates to the rear deck evidenced by small amounts of
mould on the underside of the soffit.23
(k) The use of Maxideck prevents a waterproof membrane from being installed. In
accordance with the Australian Standard for waterproofing of external decks,
AS 4654.2-2012, a decking material would need to be installed under the
Maxideck and waterproofed, however, the fixing of the Maxideck would
penetrate the waterproof membrane, thus allowing water to penetrate the
enclosed soffit. As the Maxideck is only moisture resistant, the soffit needs to
be removed.24
(l) The soffit should be removed in accordance with Mr Reeve’s advice and the
steel members should be treated in accordance with the NCC coating to external
steel. This would enable the Inex Maxideck product to remain and would
eliminate the water into the patio ceiling. This would have achieved the desired
outcome without the enormous expense that would be incurred by removing and
reinstalling all of the decking.25
[29] I summarise the QBCC’s evidence26 as follows:
(a) There are two aspects to DTR 4: waterproofing the three decks (entry, front and
back), and flashing the doorways that open onto the decks.
(b) Part 2.2 of Volume 2 of the NCC prescribes the damp and weatherproofing
requirements applicable to a dwelling, noting the limitation that the
requirements do not apply to a Class 10 building except where its construction
contributes to the weatherproofing of the Class 1 building.
(c) The decks are part of a Class 1 building (the dwelling), the deck surfaces
constituted ‘roofs’ because they were fully lined on top with Inex Maxideck
boards and underneath with fibre cement sheeting, and they were therefore
required to be weatherproof to prevent the penetration of water.
(d) The inspection report shows severe water damage to the Inex Maxideck and
surrounding building elements including severe rusting of the deck joists, the
results of a water test, and extensive mould to the ceiling linings underneath the
decks constituting non-compliance with the NCC.
21 SOE: DTR Abbott, paras 15, 16; SOE: DTR Paterson 1, paras 13, 14.
22 Ibid, paras 7, 8.
23 Ibid, para 10a.
24 SOE: DTR Reeve, paras 9, 10.
25 SOE: ALL Paterson, para 9.
26 SOE: QBCC Kirby.
-- 10 of 30 --
11
(e) Clause 3.5.3.6 of the NCC prescribes that openings around external wall
openings must be adequately flashed in accordance with the Australian Standard
for damp-proof courses and flashings AS/NZS 2904:1995. Clause 3.6.0 of the
NCC prescribes that glazing must be installed in accordance with the Australian
Standard for windows and external doors in buildings, AS 2047:2014.
(f) The inspection identified no flashing installed to the area and the water test
confirmed water penetration of the doorways onto the decks constituting non-
compliance with the NCC and relevant standard.
(g) The Australian Standard for waterproofing of external decks AS 4654.2-2012
does not apply as there is no waterproof membrane installed to the deck,
however under Part 2.2 of the NCC a roof and wall (including around window
and door openings) must not allow water penetration that could cause undue
dampness or deterioration of the building elements.
(h) There is a visible gap under the doors onto the deck that allows water
penetration.
(i) The soffit forms part of the Class 1 dwelling and has evidence of deterioration
and therefore does not comply with the NCC.
(j) There is no Australian Standard requirement for a step down, however the
building approval approved plans show a 40 mm step down on each of the three
decks.
(k) The sliding doors need to be removed install suitable flashing that is compliant
with AS/NZS 2904:1995.
(l) SOW 3 is reasonable and necessary.
[30] I summarise Abbott’s submissions dated 17 January 2025 as follows:
(a) The decking is a separate structure to the dwelling; it was bolted to the outside
of the dwelling during the fixing stage when the dwelling had been sealed and
closed. There is a gap between the decking and the door entry, and it is not
possible to connect any waterproofing.
(b) The decking is better characterised as a Class 10 building, being non-habitable
buildings of structure. The enclosed structure created by the addition of the
soffit to the decking is uninhabitable; it is not intended to be a roof or to provide
cover to the area underneath the decking.
(c) The water ingress and damage alleged is not to the dwelling itself, it is to the
sealed decking structure. There is no evidence of water ingress or damage to the
dwelling.
(d) The decking does not contribute to the weatherproofing of the dwelling.
(e) Insofar as there has been non-compliance with relevant standards, it arises
because of design decisions made by the homeowner for which it would not be
fair or reasonable to impose liability for rectification on Abbott.
-- 11 of 30 --
12
(f) The design of the decking and its relationship with the building envelope is such
that it is not necessary to install flashing in accordance with the NCC and
relevant standard:
(i) There is no opening in the doorway or to the dwelling that would permit
water ingress.
(ii) The water testing showed a gap between the decking and the dwelling that
allowed water egress for any accumulated water that doesn’t run off due
to the step down.
(iii) Flashing is not required for a Class 10 building. If the Tribunal determines
that the decking is a Class 1 building, there is no need for flashing if the
soffit is removed and replaced with perforated steel sheeting.
(g) SOW 3 is disproportionate, unreasonable and unnecessary and unlikely to solve
the problems arising from water ingress into the decking substrate.
[31] The NCC is published in three volumes: Building Code of Australia (‘BCA’) (Volume
One and Volume Two) and the Plumbing Code of Australia (Volume Three). Any
provision of the BCA may be overridden by or subject to State or Territory legislation.
The following references are to parts and clauses contained in Volume Two of the
NCC.
[32] Clause 1.3.2 classifies Class 1 and Class 10 buildings. Class 1 includes a Class 1a
single dwelling being a detached house. Class 10 includes a Class 10a non-habitable
building being a private garage, carport, shed, or the like.
[33] Clause 1.3.3 provides that each part of a building must be classified separately; and
(inter alia) Classes 1a and 10a are separate classifications; and where parts have
different purposes, if not more than 10% of the floor area of a Class 1 building is used
for a purpose which is a different classification, the classification of Class 1 may apply
to the whole building.
[34] Functional Statement 2.2.2 of Part 2.2 relating to weatherproofing and dampness
provides that a building is to be constructed to provide resistance to moisture from the
outside and moisture rising from the ground. However, this does not apply to a Class
10 building except where its construction contributes to the weatherproofing of the
Class 1 building.
[35] Clause 2.2.2 provides that a roof and external wall (including openings around
windows and doors) must prevent the penetration of water that could cause (a)
unhealthy or dangerous conditions, or loss of amenity for occupants; and (b) undue
dampness or deterioration of building elements. However, this does not apply to a
Class 10 building except where its construction contributes to the weatherproofing of
the Class 1 building.
[36] Clause 3.5.3.6 provides that openings in external wall cladding exposed to the weather
must be flashed using materials that comply with AS/NZS 2904, and flashings must
be securely fixed at least 25 mm under the cladding and extend over the ends and
edges of the framing of the opening [ref: Figure 3.5.3.5].
-- 12 of 30 --
13
[37] Clause 1.1.1 provides that “habitable room” means a room used for normal domestic
activities, and (a) includes a bedroom, living room, lounge room, music room,
television room, kitchen, dining room, study, playroom, family room, home theatre
and sunroom; but (b) excludes a bathroom, laundry, water closet, pantry, walk-in
wardrobe, corridor, hallway, lobby, photographic darkroom, clothes-drying room, and
other spaces of a specialised nature occupied neither frequently nor for extended
periods.
[38] Clause 1.1.1 provides that “external wall” means an outer wall of a building which is
not a separating wall.
[39] The publicly available Queensland Government Growth Management Queensland
Building newsflash 453 issued 16 November 2010 (‘Newsflash 453’) is expressed to
provide clarification of the appropriate classification for domestic patios, verandahs,
shade structures, decks and similar structures, noting that since newsflashes issued in
1998 and 2002, there have been changes to the Queensland Development Code and
the Building Act 1975 (Qld). Relevant excerpts are as follows:
…In determining the appropriate classification for a building or structure
under the BCA, building certifiers must consider the purpose for which the
building or structure is to be used and must apply the most appropriate
classification on the basis of a ‘best fit’ approach...
…Class 1a buildings have habitable spaces and ancillary non-habitable
rooms to support habitation. Class 10a buildings are non-habitable. The term
‘non-habitable’ is not defined by the BCA, although the term ‘habitable
room’ is defined…
…Dictionary definitions help to establish that open sided domestic patios,
verandahs, shade structures, decks or similar structures should not qualify
as ‘rooms’, nor do they generally meet the definition of ‘habitable’.
Using domestic patios, verandahs, shade structures, decks or similar
structures, whether detached or attached to another structure, intermittently
for domestic recreational purposes does not change the classification of the
building or part to a class 1a building. Where domestic patios, verandahs,
shade structures, decks or similar structures are used on an ongoing basis for
a ‘habitable’ purpose, they will have changed classification and they must
comply with the relevant BCA performance requirements for the new
classification.
In practical terms, these structures typically do not meet the BCA
requirements for class 1a buildings, such as damp and weatherproofing.
Therefore, it is generally not appropriate to classify these structures as class
1a buildings under the BCA ‘10% rule’ as they would not normally meet the
BCA requirements for a class 1a building.
Domestic patios, verandahs, shade structures, decks or similar structures
should therefore be classified as class 10a buildings, provided they are not
fully enclosed, or provided with opening partitions or doors or windows or
sashes or the like that can enclose the area.
-- 13 of 30 --
14
[40] The publicly available Queensland Government Department of Energy and Public
Works Building and Plumbing Newsflash 604 dated June 2022 (‘Newsflash 604’) is
expressed to clarify the intent of concessions for light-weight class 10 buildings and
structures under the Queensland Development Code. The document is relevant to this
case insofar as it further informs the nature of Class 10 buildings. Relevant excerpts
are as follows:
Examples [of a light-weight class 10] include a …timber patio, deck or gazebo.
…Typical light-weight class 10s have the appearance of a building or structure
that is ancillary to the main building…
…The following should not be classified as light-weight class 10s:
• Class 10 buildings or structures with roofing that is integral to or a
continuation of the main building’s roof…These structures are under
the same roofline of the main building i.e. their roofs are a continuation
of the roof trusses of the main building. They are often constructed at
the same time as the main building e.g. integrated outdoor
entertainment rooms, entranceways and garages/carports.
• Class 10 buildings or structures that form an integral part of the design
of the main building…such as a porch whose floor is connected to the
main structure of the house, rather than being attached to the house.
…The following can be classified as light-weight class 10s:
• …simple decks and gazebos that are attached to, rather than form part
of, the main building…
[41] The first issue to consider is whether the three decks are Class 1a or Class 10a
buildings. I consider that the definitions in Clauses 1.3.2 and 1.3.3 must be informed
by and read subject to the contents of Newsflash 453 and 604 set out in these reasons.
[42] I accept Abbott’s evidence that the three decks were attached to or bolted on to the
dwelling at the fixing stage of construction, that being the stage when internal
components and finishes to the dwelling are installed. I note that in respect of
complaint 12, Mr Murphy’s initial inspection report dated 19 February 2019 states
that “3 x decks have been attached to the dwelling…”.
[43] I am satisfied on the evidence before the Tribunal that the floor of each of the three
decks is not connected to the dwelling.
[44] I am satisfied on the evidence before the Tribunal that the three decks are not under
the same roofline of the dwelling and their roofs are not a continuation of the
dwelling’s roof. The large upper front deck (also referred to in the plans as the ‘living
deck’) has its own roof separate from the roof of the dwelling, and the lower front
deck (also referred to in the plans as the ‘entry deck’) sits below the upper deck,
however, is much smaller in area and depth, and as such does not have a roof. The
small rear deck also does not have a roof.
[45] I am satisfied on the evidence before the Tribunal that the three decks are not fully
enclosed nor are they fitted with doors and/or windows or the like capable of fully
enclosing the decked areas. Rather, each deck is an open-sided space fitted with rails
and balustrading.
-- 14 of 30 --
15
[46] I am satisfied there is no evidence before the Tribunal that the three decks are or were
intended to be used other than intermittently for domestic recreational purposes.
[47] I find that the three decks are not rooms, are not habitable, and are ancillary to the
dwelling and on that basis should properly be classified as Class 10a buildings. Clause
1.3.3 provides that each part of the building must be classified separately, and that
Classes 1a and 10a are separate classifications.
[48] I note the Development Application Notice dated 27 January 2017 issued by
Professional Certification Group (of which Mr Reeve is a director) and the Form 21
Final Inspection Certificate dated 20 June 2016 signed by Mr Reeve describe the
works as “new construction of dwelling – 2 storey” with the classification Class 1a,
and make no reference to the three decks as being part of the certification. I find that
the dwelling itself clearly falls within the Class 1a building classification and these
documents evidence that position. I do not consider however that these documents
provide any evidence of the building classification of the three decks. I further note
that in respect of complaint 1, Mr Murphy’s Initial Inspection Report dated 19
February 2019 confirms no certification for any of the decks.
[49] The second issue to consider is whether the construction of the three decks, classified
as Class 10a buildings, contributes to the weatherproofing of the Class 1a dwelling
and is therefore subject to the Clause 2.2.2 weatherproofing and dampness
requirements.
[50] I note that Newsflash 453 states that “In practical terms, these structures [referring to
Class 10a structures] typically do not meet the BCA requirements for Class 1a
buildings, such as damp and weatherproofing. Therefore, it is generally not
appropriate to classify these structures as Class 1a buildings under the BCA ‘10%
rule’ as they would not normally meet the BCA requirements for a Class 1a building.”
[51] In the decision of Ramke Construction Pty Ltd v Queensland Building Services
Authority (No 2)27 (‘Ramke’), Member Howard considered the weatherproofing
requirements in the case of a garage, a Class 10 building. The homeowners’ complaint
to the authority claimed that when it rains against the roller door, water runs off the
door, onto the slab, into the garage, and ponds against the study wall. The plans
indicated that the garage abutted the house wall, with a step up of 100 mm from the
garage to the house. The Member found that whatever the fall from the house to the
garage was, it was insufficient to stop water from sitting inside. On that basis, the
Member accepted that while the garage is not a habitable area, it contributes to the
weatherproofing of the house.
[52] Mr Murphy’s Amended Reinspection Report dated 2 October 2019 relevantly
addressed DTR item 6, which referred to negative falls in the substrate framing on the
upper-level deck that resulted in water ponding near the front entry door creating a
hazard for the occupants. The reinspection report found that while the flashing had
not been installed beneath the door, as directed, sufficient fall had been achieved to
the deck to the front entrance door, and water poured on the deck adjacent to the front
entry door penetrated the structure and exited to the concrete paving below. I consider
that by correcting the fall, Abbott ensured that water would drain away from the front
entry door area.
27 [2013] QCAT 575.
-- 15 of 30 --
16
[53] I note there is no other reference in Mr Murphy’s Initial Inspection Report or
Amended Reinspection report to water ponding on the decks such as to create a hazard
for the occupants of the dwelling.
[54] I note there is no other evidence before the Tribunal of water ponding on the decks
such as to create a hazard for the occupants of the dwelling nor is there any evidence
of water ingress into the dwelling.
[55] I note there is variable evidence before the Tribunal regarding the height of the step
down from the dwelling to the decks. I am satisfied however that it is reasonable to
find that the height of the step down is somewhere between 30 and 40 mm and as
such, in contrast to Ramke, is sufficient to stop water ponding and ingress.
[56] I find that the construction of the Class 10a decks does not contribute to the
weatherproofing of the dwelling and therefore the decks are not subject to the Clause
2.2.2 weatherproofing and dampness requirements.
[57] I note the Product Information Sheet for Inex Maxideck describes the product as
“moisture resistant and retains its structural integrity when subjected to multiple
soak/dry cycles in accordance with clause 8.2.5 of AS/NZ 2908.2 2000 ‘Cellulose-
cement products part 2: Flat sheets’”.
[58] I note it is not contested that the Inex Maxideck product is water resistant and not
waterproof, and that there is no requirement or recommendation in the manufacturer’s
installation guide that a waterproof membrane be installed.
[59] I note that in respect of complaint 20, Mr Murphy’s Initial Inspection Report dated 19
February 2019 states that:
The Inex Maxideck has not been installed in accordance with the manufacturers
Installation Guide because the screw fixings have not been predrilled,
consequently decking is damaged/split at screw fixings. Screw fixing is
incomplete. Evidence of correct application of sealant to the deck joists and
correct sealing of joints is not apparent. Excess sealant has not been removed
where installed. Screw fixings have been installed closer than 12 mm from the
edge at butt joints.
[60] I note that complaint 20 resulted in DTR 5, which is not the subject of this review
proceeding.
[61] I note the Manufacturers Technical Specification for Inex Maxideck sets out a 4-step
guide for the installation and coating system. Referencing the Product Information
Sheet, I note the Inex Maxideck can be coated to achieve a timber look. The steps
involve coating the edges of the product and applying bond to joists and joints prior
to fixing and applying further coats within two weeks after fixing. The only reference
to sealing is the caution to ensure that all screw heads are sealed with the subsequent
coats as Inex Maxideck may absorb moisture and while this will not affect the
structural performance of the board, it may result in a small amount of discolouration.
[62] I am satisfied that the Inex Maxideck specification provided for sealing only to the
extent of the screw heads, and otherwise provided for coating to achieve a timber look.
I am satisfied that coating does not mean sealing.
-- 16 of 30 --
17
[63] I note that the construction contract specifications provided for perforated steel
sheeting on the underside of the Inex Maxideck decking. It is not contested that the
homeowner verbally required that this material be replaced with the 4.5 mm James
Hardie soffit, a product the homeowner had researched and decided would meet their
requirements. It is noteworthy too that the Inex Maxideck product was also required
by the homeowner.
[64] I accept Mr Paterson’s evidence regarding the circumstances surrounding the
replacement of the perforated steel sheeting with the James Hardie soffit, that he was
not familiar with the Inex Maxideck product, and that he had no reason at the time to
believe the James Hardie soffit installation would be a problem.
[65] I am satisfied on the evidence before the Tribunal that the James Hardie soffit was not
an appropriate product for the underside of the decking and that its installation caused
moisture from the decking to be trapped in the cavity enclosed by the soffit leading to
rust damage to the steel joists supporting the decking and mould damage to the soffit.
[66] I am satisfied that if the homeowner had not required the installation of the James
Hardie soffit, Abbott would have installed the perforated steel sheeting on the
underside of the decking and applied rust-resistant paint to the exposed steel joists in
accordance with the construction contract specifications and the corrosion protection
requirements of the National Construction Code.
[67] It is arguable that Abbott should bear the responsibility for the consequences of the
installation of the James Hardie soffit in circumstances where the homeowner
specifically required that the steel perforated sheeting specified in the construction
contract be replaced with the James Hardie soffit, and where the homeowner had also
specifically required the installation of the Inex Maxideck product, the homeowner
telling Mr Paterson they had researched the products and decided both would meet
their requirements.
[68] I note however that Abbott has maintained in response to SOW 3 that the direction
should be limited to installing the Inex Maxideck in a way that is consistent with its
proper usage; that is, Abbott should have been directed to remove the soffit, replace
it with the perforated steel sheeting specified in the construction contract and apply
rust-resistant paint to the steel joists in accordance with the corrosion protection
requirements of the National Construction Code.
[69] The third issue to consider is whether the dwelling is subject to the Clause 2.2.2
weatherproofing and dampness requirements. I have already found that the dwelling
is a Class 1a building. I therefore find that the dwelling is subject to the requirements
that a roof and external wall (including openings around windows and doors) must
prevent penetration of water that could cause (a) unhealthy or dangerous conditions,
or loss of amenity for occupants; and (b) undue dampness or deterioration of building
elements.
[70] I consider that the doorways onto the decks are part of the external wall of the dwelling
and that the openings around the doorways are subject to the Clause 3.5.3.6 flashing
requirements for openings in external wall cladding exposed to weather.
[71] I order that the DTR decision in respect of DTR 4 is amended to read as follows:
The installation of the James Hardie soffit is not consistent with the proper
usage of the Inex Maxideck decking and the doorways onto the three decks
are void of flashings.
-- 17 of 30 --
18
[72] I order that the SOW decision for SOW 3 in respect of DTR 4 is amended to read as
follows:
• Install flashing to the openings around the doorways onto the three
decks in accordance with Clauses 2.2.2 and 3.5.3.6 of the National
Construction Code.
• In relation to the three decks:
o Remove the James Hardie soffit
o Install perforated steel sheeting on the underside of the decking
in accordance with the construction contract
o Apply rust-resistant paint to the steel joists supporting the
decking in accordance with the corrosion protection
requirements of the National Construction Code.
DTR 1, 2, 9, 10, 22, 26, 27, 30, 35, 39, 43 and 45 – USW decision
[73] Abbott submits that these rectification items were not completed because there was
not sufficient time and the QBCC denied their request for an extension of time.
Consequently, Abbott submits, 28 days (the period allowed by the QBCC for the
rectification work) is a very short period to undertake very substantial rectification
work, and the QBCC’s approach to considering the request for an extension of time
was not fair or reasonable. I note the DTR decision was dated 12 August 2019 and
required the rectification work to be completed by 11 September 2019.
[74] I will deal with the extension of time issue before considering Abbott’s other
submissions. The Tribunal has no jurisdiction in these proceedings to review the
QBCC’s decision not to grant Abbott an extension of time to complete the rectification
works as such a decision is not a reviewable decision under the QBCC Act.
[75] Abbott further submits that rectification items were not completed due to sequencing
issues (that is, having insufficient time to program the works/tradespeople in the most
efficient sequence), access being denied by the homeowner, and strong winds posing
a safety risk to the tradespeople engaged to complete the roofing rectification works.
[76] Mr Abbott’s and Mr Paterson’s evidence provides detail in support of these
submissions, including the steps taken following the issue of the direction to rectify
to arrange the necessary trades to attend the property; Metal Line Roofing’s refusal to
do the roofing rectification works because of strong winds causing a workplace health
and safety issue, and the painting work on the soffit moulding being held up as a
consequence; the painters being denied access by the homeowners on the final date
for rectification, and Metal Line Roofing being denied access by the homeowners the
following day.28
[77] Mr Abbott’s evidence further states that:
(a) in relation to DTR 1, 2, 26, 30 and 45, the homeowner prevented the rectification
work from being completed within the time stipulated.29
28 SOE: USW Abbott; SOE: USW Paterson; SOE: ALL Paterson.
29 SOE: USW Abbott, paras 17, 23, 29, 38, 46.
-- 18 of 30 --
19
(b) in relation to DTR 1, 26 and 30, the rectification work was subsequently
performed, and there has been no subsequent complaint;30
(c) in relation to DTR 2 and 27, all works were performed within the time stipulated
other than the painting;31
(d) in relation to DTR 9, 10, 14, 22, 23, 35 and 43, the rectification was compliant
and recertified.32
[78] Mr Kirby’s evidence states that:
(a) He is not aware of any evidence that the homeowners prevented reasonable
access during the DTR period, and the concern was not raised with the QBCC
in correspondence at the end of the DTR period.33
(b) He is not aware of any evidence of rectification work being carried out after the
DTR period expired and unsatisfactory work items were dealt with by way of
an insurance claim.34
(c) The issue of high winds was not raised by Abbott in its request for an extension
to comply with the DTR, and the rectification works performed in relation to
DTR 1, 26 and 30 were unsatisfactory.35
(d) He does not consider there is any evidence that the rectification works
performed in relation to DTR 9, 10, 14, 22, 23, 35 and 43 was compliant and
recertified; the reinspection report provides evidence otherwise.36
[79] I note that the roofing issue and related sequencing issue was identified in Abbott’s
request for an extension of time, and Abbott in its letter the QBCC on 12 September
2019 advised that the “Roofing company could not attend last week due to high winds
(per one of the reasons for requesting extension of time) completing this week and
agreed with owners!”.
[80] I am satisfied therefore that the QBCC was aware of the high winds being an
impediment to the roof rectification works being completed in the time stipulated.
[81] I am not satisfied there is any evidence to support Abbott’s claims that in relation to
DTR 1, 26 and 30, the rectification work was subsequently performed, and there has
been no subsequent complaint.
[82] I am not satisfied there is any evidence to support Abbott’s claims that in relation to
DTR 9, 10, 14, 22, 23, 35 and 43, the rectification was compliant and recertified.
[83] I accept Abbott’s evidence regarding the reasons the rectification work could not be
completed in the time stipulated.
30 Ibid, paras 16, 28, 37.
31 Ibid, paras 21, 31.
32 Ibid, paras 51, 52.
33 SOE: QBCC Kirby, para 60.
34 Ibid, para 59.
35 Ibid, para 58.
36 Ibid, para 61.
-- 19 of 30 --
20
[84] Abbott submits that in the circumstances of this case it is manifestly unfair and
unreasonable and not in accordance with natural justice to make findings of non-
compliance with a direction to rectify.
[85] The threshold issue to determine is whether the QBCC, and therefore the Tribunal in
conducting merits review, has the power to make a decision that work undertaken at
its direction is not of a satisfactory standard where the builder has been unable to
complete the work for reasons beyond its control, for example, as in this case, strong
or high winds posing a safety risk, consequential impact on sequencing/timing of other
work, and the homeowner denying access. In other words, without reference to
considerations of fairness or reasonableness.
[86] Section 72 of the QBCC Act sets out the QBCC’s powers in relation to directing the
rectification of defective or incomplete building work, including taking into account
all reasonably relevant circumstances and not being required to give a direction where
it would be unfair to do so. In contrast, the Act is silent on the QBCC’s powers in
relation to deciding whether work undertaken at its direction is or is not of a
satisfactory standard, other than to identify such a decision as a reviewable decision.37
[87] The objects of the QBCC Act include: to regulate the building industry by ensuring
the maintenance of proper standards in the industry and achieving a reasonable
balance between the interests of building contractors and consumers, and to provide
remedies for defective building work.38
[88] Section 14A(1) of the Acts Interpretation Act 1954 (Qld) provides that, in the
interpretation of a provision of an Act, the interpretation that will best achieve the
purpose of the Act is to be preferred to any other interpretation.39
[89] I consider that the QBCC’s powers in relation to deciding whether work undertaken
at its direction is or is not of a satisfactory standard must be exercised having regard
to the object of the QBCC Act to achieve a reasonable balance between the interests
of building contractors and consumers.
[90] Further, it has been observed that a statutory power conferred for public purposes can
validly be used only in the right and proper way which Parliament is presumed to have
intended when conferring it and that in a system based on the rule of law, unfettered
governmental discretion is a contradiction in terms.40
[91] I consider that Abbott, due to circumstances beyond their control, was unable to
comply with the direction to rectify. I consider therefore that a reasonable balance
between the interests of Abbott and the interests of the homeowner is not achieved
where Abbott has not been allowed the opportunity to comply with the direction to
rectify despite its best efforts and willingness to do so. I further consider that the
consequent decision made by the QBCC that certain work so directed was not of a
satisfactory standard could not be regarded as right and proper use of its statutory
power.
37 QBCC Act s 86(1)(f).
38 Ibid ss 3(a), 3(b).
39 Acts Interpretation Act 1954 (Qld) s 14A(3) – applies to an Act passed after 30 June 1991. The QBBC
Act assented to 17 December 1991.
40 Queensland Building and Construction Commission v Groupline Constructions Pty Ltd [2020] QCA
245, [95].
-- 20 of 30 --
21
[92] I order that the USW decision is amended to omit the references to unsatisfactory
rectification work in relation to DTR 1, 2, 9, 10, 22, 26, 27, 30, 35, 39, 43 and 45.
DTR 10 – SOW 5 decision
[93] The DTR decision described the item 10 defect as follows:
The construction detail surrounding the external corner butt joints to the decks
and soffit junctions to steel columns has not been completed with a reasonable
standard of workmanship and finish expected of a competent holder of a Trade
Contractor’s Licence, in that the FC sheet is evident of mechanical blade
gouges, poor fitting soffits, cladding and soffit moulding has resulted in
excessive gaps and presents an unacceptable finish.
[94] The QBCC’s Statement of Reasons for the decision states that “although the applicant
has rectified one external butt joint to the lower-level front deck, there was no attempt
at rectification to the two external butt joints to the upper-level deck.”
[95] The SOW decision described the item 5 scope of works as follows:
• Allow to supply, fit and finish a metal trim to all external corner FC
butt joints to the decks and soffit junctions to steel columns (except LH
corner of lower level deck).
• Paint and make good all affected surfaces.
[96] Mr Abbott’s and Mr Paterson’s evidence states that minor paint touch-ups to the
external corner were required and that there was no requirement for a metal angle,
which is not standard practice.41
[97] Abbott submits that the QBCC has only required the metal trim to be added to the
corner butts that were not rectified; the implication therefore is that a properly rectified
corner butt does not require metal trim.
[98] There is no evidence before the Tribunal of how Abbott rectified the external butt
joint to the lower-level front deck in a manner that was satisfactory to the QBCC.
[99] There is no evidence before the Tribunal to support Abbott’s claim that the
requirement for a metal angle or trim is not standard practice.
[100] I find that SOW 5 is reasonable and necessary to rectify the item 10 defect.
[101] I order that the SOW decision for SOW 5 in respect of DTR 10 is confirmed.
DTR 14 – USW decision
[102] The DTR decision described the item 14 defect as follows:
The construction detail of the timber framed bracing wall to the rear left hand
elevation of Entry Level Bed 2 wall is defective and not in compliance with the
BCA/NCC, AS 1684-Residential Timber Framed Construction, QBCC
Standards and Tolerances Guide and acceptable building standards, in that the
timber frame overhang to the concrete slab is outside allowable tolerances
which has resulted in reducing the effectiveness of the bracing wall due to
insufficient slab edge distance to frame anchors and creating gaps greater than
3 mm in a bushfire prone area creating a safety hazard for the occupants.
41 SOE: SOW Abbott, para 23; SOE: SOW Paterson, para 21.
-- 21 of 30 --
22
[103] The USW decision stated that the rectification work was unsatisfactory because:
• The Applicant has inserted a piece of external grade treated pre-primed
pine timber moulding on top of the right-hand side.
• There was no attempt at addressing the concerns relating to the
embedment of the bracing wall anchors.
• Gaps greater than 3 mm are still presenting.
[104] The parties grappled with this issue in oral evidence. I considered that it was
appropriate to invite the parties to file further written submissions post hearing.
[105] The QBCC’s submission states at paragraph 7 that:
The key issue concerning this item is whether the bracing wall fixings (that
is, the bracing wall anchors) have been properly embedded. Proper
embedment and bracing requires fixings to be placed within a required
distance from the slab edge, and any overhang of the frame fall within
allowable tolerances.
[106] I consider that in making this submission the QBCC has so confined the issue for
consideration under review. DTR 14 is not the subject of this review proceeding.
[107] The QBCC’s submission sets out at paragraph 11 the QBCC’s determinations:
(a) The relevant wall is the rear left hand elevation of Bed 2.
(b) It is a 1200 mm bracing wall. Consequently, the wall needed to
include tie down rods.
(c) The plans require the bracing wall to be typically anchored to the slab
with 12 mm fixings (that is, fasteners) at 600 mm centres.
(d) It is timber framed; the framing being 90 mm thick.
(e) Tolerances allow for a maximum overhang, relevantly, of 15 mm
under the AS 1684 Residential Timber Framed Construction and
QBCC Standards and Tolerances Guide.
[108] The QBCC’s submission sets out at paragraph 12 the QBCC’s observations:
(a) The timber framing overhung the slab.
(b) There was a substantial gap between the bottom of the cladding and
the concrete slab.
(c) The overhang at the rear left hand corner measured 50 mm. Given the
90 mm thickness of the timber frame, this left 40 mm of the frame
width bearing on the concrete slab. Another part of the bracing wall
was measured to have an overhang of 35 mm.
(d) The Applicant installed a 50 mm x 25 mm RHS42 in an attempt to
support the frame.
(e) The RHS had not been affixed to support the frame.
(f) There was a gap at the top of the RHS.
42 Rectangular hollow section.
-- 22 of 30 --
23
(g) Gaps of more than 3 mm were present.
[109] The QBCC’s submission sets out at paragraph 13 the QBCC’s findings:
(a) Fasteners must be fixed a sufficient distance from the concrete slab edge.
(b) Given the 40 mm bearing on the slab that was presenting, the fasteners
could not achieve the minimum slab edge distance, as:
(i) The fasteners are required to be 12 mm thick. The dimensions of
the fasteners are relevant as they need to be incorporated in
addition to the minimum slab edge distance.
(ii) Typically, a chemical injected anchor fastener has an optimum slab
edge distance of 50 mm.
(iii) Alternatively, a mechanically fixed anchor has around a 70 mm
requirement from slab edge.
[110] The QBCC submits that Abbott implies it had used 12 mm Chemset rods (that is, fixed
chemically), the minimum edge distance for which was 35 mm, however it claims
there is no direct evidence that this is the case. QBCC further submits that given an
invasive inspection of the location of the fastener within the framing was not
undertaken (noting that it is not the Commission’s role to do so), it is unknown how
far from the slab edge the wall has been fixed to the slab.
[111] In relation to the tie down issue, Abbott submits at the following paragraphs that:
19. The Ramset ChemSet Reo 502 Strength Limit State Design Table 1b
requires there to be a 35 mm gap between the tie down (the vertical steel
rod attaching the base plate to the slab) and the edge of the slab.
20. The QBCC’s position in relation to this issue appears to be an extension
of its misunderstanding of the extent of the overhang. The wall bottom
plate is 90 mm. Its position appears to be that if the overhang is in fact 50
mm, then that leaves insufficient timber in the base plate connected to the
slab for the insertion of the tie down.
21. However, as evidenced by the photographs, the overhang is in fact 30-35
mm. This means there is 55-60 mm of wall plate inside the wall for the
insertion of the tie down. It is Mr Paterson’s evidence that the tie down
was 35 mm from the edge of the slab and the QBCC has no basis for
stating that is incorrect other than by reference to its misplaced belief
about the overhang for which the only evidence that is available is
inconsistent with its position.
[112] I consider the parties’ positions are entirely at odds as to the size of the overhang and
the effect of the installation of the RHS on the size of the overhang. It is not necessary
for me to make a finding on this issue. This review proceeding requires me to confine
my considerations to whether (per the wording of the USW decision) there was no
attempt at addressing the concerns relating to the embedment of the bracing wall
anchors such as to render Abbott’s rectification work unsatisfactory.
[113] The QBCC acknowledges in its submissions that it has not inspected the location of
the fastener within the framing. Regardless of whether the QBCC believes this to be
its role, the fact remains that an inspection was not undertaken. The QBCC is therefore
unable to produce credible evidence to refute Mr Paterson’s evidence that the tie down
was located 35 mm from the edge of the slab.
-- 23 of 30 --
24
[114] An inspection was however undertaken by the building certifier, Mr Reeve. I consider
therefore it is reasonable in the circumstances to give considerable weight to the Form
21 Final Inspection Certificate issued by Mr Reeve on 20 June 2018, in which he sets
out the inspection and certification dates for each building stage, including the framing
stage (30 August 2017), and certifies as follows:
I certify that on an inspection carried out in accordance with best industry
practice, the building work for the above building or structure was inspected
and complies with the building approval or certificates of inspection
accepted from competent persons at the following stages of the construction.
[115] I am not satisfied on the evidence before the Tribunal that Abbott’s rectification work
was unsatisfactory.
[116] I order that the USW decision is amended to omit the references to unsatisfactory
rectification work in relation to DTR 14.
DTR 14 – SOW 7 decision
[117] The SOW decision described the item 7 scope of works as follows:
• Allow to remove existing 50 mm x 25 mm RHS.
• Supply and install 50 mm x 75 mm x 10 mm galvanised angle to support
frame overhang.
• Remove sufficient plaster board to enable tie-down connection to angle.
• Patch/repair and make good all affected surfaces.
[118] My reasoning set out under the previous heading applies here.
[119] I am not satisfied on the evidence before the Tribunal that SOW 7 is reasonable and
necessary.
[120] I order that the SOW decision for SOW 7 in respect of DTR 14 is amended to omit
SOW 7.
DTR 23 – USW decision
[121] The DTR decision described the item 23 defect as follows:
The installation of the stormwater system to the dwelling is not in
compliance with the Building Code of Australia – Volume 2 and the
building development application requirements, in that 2 outlets to kerb and
channel has not been provided which may lead to water backing up through
the stormwater system during heavy period of rainfall affecting building
components.
[122] The USW decision stated that the rectification work was unsatisfactory because:
• The applicant has installed a “Y” junction directly behind the kerb.
• No attempt at evenly distributing the stormwater into two lines
servicing the dwelling, which may lead to water backing up through the
stormwater system during heavy periods of rainfall affecting building
components.
-- 24 of 30 --
25
[123] Clause 3.1.2.5 (Stormwater drainage) of the National Construction Code provides
that:
Where a stormwater drainage system is installed, it must comply with the
following:
(a) The position and manner of discharge of the stormwater drainage
system must be to the satisfaction of the appropriate authority.
(b) The stormwater drainage system must be designed so that any
overflow during heavy rain periods is prevented from flowing back
into the building.
[124] Mr Paterson’s evidence states that he engaged a plumber to attend to this defective
item and provided him with a copy of the direction to rectify; the plumber installed
two outlets to kerb and channel.43
[125] Abbott submits that there is no evidence that the (Y junction) design would result in
overflow during heavy rain periods flowing back into the building. Abbott states that
the stormwater outlet the subject of the direction to rectify relates only to the garage,
and that there is a second discharge point that discharges stormwater from the majority
of the house into the nearby bushland.
[126] I consider that a Y junction design that splits a line just before it discharges at the kerb
and channel cannot sensibly satisfy the requirement for two outlets to the kerb and
channel such as to ensure that any overflow during heavy rain periods is prevented
from flowing back into the building. I consider therefore it is for the most part a single
line with the capacity of a single line, and it is reasonable to conclude that the Y
junction at the end of the line would make little or no difference to the capacity of the
line to prevent flow back in heavy rain periods.
[127] I consider that would be the end of the matter, but for Abbott’s submission that there
is a second stormwater line from the property that discharges into the nearby bushland.
I note the QBCC’s inspection reports make no reference to the second line, and nor
does its evidence and submissions contest the existence of the second line.
[128] I consider that if, as claimed by Abbott, there was a second stormwater line in
existence at the relevant time, the first stormwater line, with or without the Y junction,
is satisfactory, in that (per the wording of the USW decision), there was an attempt at
evenly distributing the stormwater into two lines servicing the dwelling.
[129] I order that the USW decision in respect of DTR 23 is set aside and the matter is
returned to the QBCC for reconsideration with the direction that the property’s
stormwater drainage system be reinspected to ascertain the existence of a second
stormwater line at the time of the decision.
43 SOE: ALL Paterson, para 33.
-- 25 of 30 --
26
DTR 23 – SOW 11 decision
[130] The SOW decision described the item 11 scope of works as follows:
• Allow to install an additional stormwater line to kerb ensuring even
distribution of stormwater to street in both lines.
[131] Mr Abbott’s and Mr Paterson’s evidence states that the plumber installed two roadside
stormwater outlets, this dwelling was not subjected to an approved hydraulic
drawings/design, and works were completed and approved by Brisbane City
Council.44
[132] My reasoning set out under the previous heading applies here.
[133] I order that the SOW decision for SOW 11 in respect of DTR 23 is set aside and the
matter is returned to the QBCC for reconsideration with the direction that the
property’s stormwater drainage system be reinspected to ascertain the existence of a
second stormwater line at the time of the decision.
DTR 24 – SOW 12 decision
[134] The DTR decision described the item 24 defect as follows:
The installation of the flashing to the window above the carport/workshop has
not been completed in compliance with BCA/NCC 2016 – Volume 2 – Part
3.5.3.6, in that the flashing has been terminated to the underside of the
aluminium joinery and does not extend over the ends and edges of the framing
of the opening which will inevitably lead to water ingress.
[135] The SOW decision described the item 12 scope of works as follows:
• Allow to remove window and sufficient cladding to enable flashing
installation.
• Supply and install compliant flashing to window opening.
• Reinstall window, cladding and make good all affected surfaces.
[136] Mr Abbott’s and Mr Paterson’s evidence states that the window has been installed in
accordance with Trend Windows installation instructions with .250 mm dampcourse
flashing installed at Trend Windows factory then fastened to wall frame as per
window installation. The factory flashing extends .250 mm past each side of each
windows reveal. There is no defect and no work required to fix any problem.45
[137] Mt Paterson’s further evidence46 states that:
(a) During the roof completion and window installation stage, the
flashing to the window above the carport/workshop was installed as
part of the roof apron flashing by Metal Line Roofing.
44 SOE: SOW Abbott, para 33; SOE: SOW Paterson, para 31.
45 SOE: SOW Abbott, para 35; SOE: SOW Paterson, para 33.
46 SOE: ALL Paterson, para 34.
-- 26 of 30 --
27
(b) The site supervisor, Mr Carl Bell (during the construction period),
oversaw the building works of this stage and reported to me regularly,
with a job report occurring once a week. At this stage of the building
works, I was informed of the installation of windows to the
carport/workshop area of the property.
(c) A flashing goes over the roof and is run inside under the windowsill,
behind the cladding, prior to the installation of the window. A flashing
is a white metal angle that covers any joints to stop water ingress. The
wall cladding, which is coloured white as well, goes over the flashing
which means you cannot visually observe the flashing beneath which
would extend to the end of the cladding junction.
(d) Under the window, I say that the single piece of flashing has been
bent under the window and the window has been placed on top.
(e) As is standard building practice for both myself and the Applicant,
window flashing is installed in accordance with AS 3.5.3.6. From the
photographs depicted at pages 116 and 117, with an emphasis on page
117, it is not possible to determine from these photographs that the
flashings have not been installed in accordance with AS 3.5.3.6.
Additionally, and again as is standard building practice used by
myself and the Applicant, I can say that the flashing installed under
this window is not a separate window flashing as detailed in AS
3.5.3.6 and this is because it was installed as a continuous piece of
flashing that ran from the roof to the vertical part of the wall, and then
under the window. The standard does not mention that the flashing
must be continuous at a wall roof junction. I dispute the observation
made by Mr Murphy during the inspection as there was no physical
way to ascertain whether there was one continuous piece of flashing
or whether it was not in a continuous piece.
(f) I observed Mr Murphy conduct his inspection of the window and I
was present with him on the carport roof when he did so. The window
faces the right-hand side of the property. To reach this window, I had
to climb up 3m to reach the top of the carport, and the second level of
the house extends approximately 1m from the roof of the carport. The
window is located between the top of the carport and on the 1m of the
house which extends beyond the roof. I observed Mr Murphy look at
the window but did not observe him taking any measurements or
conducting any tests or exploratory work around the situation of the
window other than to take some photographs. I recall that the
observation lasted no longer 3 to 5 minutes.
(g) Accordingly, I dispute the validity of the SOW item 12.
[138] I consider Abbott’s evidence credible and persuasive. Mr Murphy was not called to
give evidence at hearing, and Mr Kirby’s evidence does not credibly refute Mr
Paterson’s account. I accept Abbott’s evidence.
[139] I order that the SOW decision for SOW 12 in respect DTR 24 is amended to omit
SOW 12.
-- 27 of 30 --
28
DTR 39 – SOW 17 decision
[140] The DTR decision described the item 39 defect as follows:
The installation of the timber floor framing, bearers and joists, to both levels
of the dwelling has not been completed to a reasonable standard expected of
a competent holder of a trade contractors licence, in that the framing has not
been adequately levelled prior to substrate installation which has resulted in
affecting the margins to doors, particularly sliding robe doors and creating
a loss of amenity for the occupants.
[141] The SOW decision described the item 17 scope of works as follows:
• Allow to remove skirting boards and floating floor (store floating floor
for reinstallation) to the following areas:
- Upper level – bed 1, 2, 3, WIR, Office, Entry, Hall, Kitchen &
Lounge
- Lower level – Bed 4.
• Adjust concrete slab, ply underlay (pack, plane, fill, sand) to achieve an
even plane on a room by room basis.
• Reinstall floating floor.
• Supply and install skirting boards.
• Paint and make good all affected surfaces.
[142] Mr Abbott’s and Mr Paterson’s evidence states that the homeowner advised not to
proceed with the repairs, despite trades ready to complete. As such there is no work
to fix any claimed defect.47
[143] Abbott has not produced any evidence that the scope of works is not reasonable and
necessary. Indeed, their evidence that they had trades ready to complete the work
strongly suggests their concurrence with the scope of works.
[144] I am satisfied that SOW 17 is reasonable and necessary to rectify the item 39 defect.
[145] I order that the SOW decision for SOW 17 in respect of DTR 39 is confirmed.
DTR 43 – SOW 19 decision
[146] The DTR decision described the item 43 defect as follows:
The installation of the timber wall framing to both levels of the dwelling has
not been completed to a reasonable standard of workmanship and finish
expected of a competent holder of a trade contractors licence and does not
comply with the requirements of the QBCC Standards and Tolerances Guide
2016, in that the timber frame deviates from plane/plumb more than 4 mm
which has resulted in presenting inconsistent margins, misalignment of
doors and creating an unacceptable finish. In addition, the top and bottom
edges of the internal doors have not been sealed as per manufacturers
recommendations which has resulted in voiding the warranty of the door and
may lead to excessive warp.
47 SOE: SOW Abbott, para 47; SOE: SOW Paterson, para 45.
-- 28 of 30 --
29
[147] The QBCC’s Statement of Reasons for the decision states that although the Applicant
has attempted rectification surrounding the Bedroom 1 entry door, the walls remain
outside allowable tolerances and are up to 14 mm out of plumb.
[148] Mr Murphy’s Amended Reinspection Report dated 2 October 2019 in respect of DTR
43 includes photographs of the 14 mm out of plumb measurements. In the absence of
any evidence supporting Abbott’s contrary claims, I accept the QBCC’s evidence.
[149] The SOW decision described the item 19 scope of works as follows:
• Allow to remove door and door frame from the entrance to Bed 1.
• Remove plaster linings sufficient to plumb frame.
• Supply and install plaster to affected areas.
• Reinstall door jambs and door, architrave.
• Adjust cupboard doors (main bedroom) to correct and parallel margins.
• Paint and make good all affected surfaces.
[150] Clause 4.2 of the QBCC Standards & Tolerances Guide 2016 relevantly provides that:
Within 6 years and 3 months from the completion of the work, posts and
wall frames are defective if they deviate from vertical by more than 4 mm
within any 2 metre height and as a result compromises the structural
adequacy of the wall or building, allows water penetration into the building
or compromises the health and safety of those who use the building.
[151] Mr Abbott’s and Mr Paterson’s evidence states that:
This item did not require rectification as it was within tolerances. QBCC
Standards & Tolerances Clause 4.2 specifically notes a wall is defective if
it deviates over 4 mm in 2 metres and as a result compromises the structural
adequacy of the wall and allows water penetration into the building and
compromises the health and safety of those who use the dwelling. This is
not the situation. Note 14.8 of the QBCC handbook notes defective if floor
varies 10 mm in a room, 4 mm in 2 metres and such adversely affects the
safe use. Here, the item does not affect use. Accordingly, within QBCC
standards and tolerances, there is no work required to fix a perceived
defect.48
[152] Mr Paterson’s further evidence49 states that:
(a) I recall that the timber frame deviates from plane/plumb
approximately 8 mm, however, as is noted in the QBCC Standards
and Tolerances Guide clause 4.2, I say that because there is no
compromise to structural adequacy of the wall, and that further as
there is no evidence suggesting that the wall is subject to being
compromised to water ingress, then there is no requirement to fix.
48 SOE: SOW Abbott, paras 51-53; SOE: SOW Paterson, paras 49-51.
49 SOE: ALL Paterson, para 42.
-- 29 of 30 --
30
(b) As to the rectification of the sealing of the doors, I arranged for the
subcontracting painting trade to attend the property to perform
various painting works, and this would include rectification of the
sealing of the door to bring into compliance with the manufacturer’s
installation recommendation, noting that it is only recommendation.
As to this item, not being completed, I repeat paragraphs 17 to 21 of
this statement as to the reason why the painting trade could not attend
to the rectification works to seal the edges of the doors.
[153] I consider that Abbott is effectively arguing that there is no defect. I note however that
DTR 43 is not disputed by Abbott and is not the subject of these review proceedings.
Issues such as the extent of deviation, consequent structural adequacy of the wall or
building, water penetration in the building, and compromises to health and safety are
not for my consideration here.
[154] I consider that Abbott’s evidence that they had arranged for the painters to seal the
door strongly suggests their concurrence with this aspect of the scope of works.
[155] In the absence of any credible evidence to the contrary, I find that SOW 19 is
reasonable and necessary to rectify the item 43 defect.
[156] I order that the SOW decision for SOW 19 in respect of DTR 43 is confirmed.
-- 30 of 30 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2025/144