Body Corporate for Infinity 1 Community Titles Scheme 45404 v Queensland Building and Construction Commission & Anor [2025] QCAT 54
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Body Corporate for Infinity 1 Community Titles Scheme
45404 v Queensland Building and Construction
Commission & Anor [2025] QCAT 54
PARTIES: BODY CORPORATE FOR INFINITY 1
COMMUNITY TITLES SCHEME 45404
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(first respondent)
KARIMBLA CONSTRUCTIONS SERVICES (QLD)
PTY LTD
(second respondent)
APPLICATION NO: GAR327-20
MATTER TYPE: General administrative review matters
DELIVERED ON: 3 February 2025
HEARING DATES: 19, 20 September 2024
HEARD AT: Brisbane
DECISION OF: Member McVeigh
ORDERS: The decision of the Queensland Building and
Construction Commission not to direct Karimbla
Constructions Services Pty Ltd to rectify is
confirmed.
Any party that considers the interests of justice
require another party to pay all or part of its costs
must file its submissions in that regard within 28
days of the date of this decision.
If any party makes such submissions, the other
parties must file submissions in response within 56
days of the date of this decision.
CATCHWORDS: ADMINISTRATIVE LAW – ADMINISTRATIVE
TRIBUNALS – QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL – general administrative
review – where applicant made complaint about alleged
defective building work – where Queensland Building and
Construction Commission decided not to give a direction to
rectify to the builder – where applicant sought internal
review of decision – where QBCC confirmed decision –
where applicant applied to the Tribunal for external review
-- 1 of 29 --
2
of that decision – where application to review filed within
six years and six months after completion of the building
work – whether tribunal had jurisdiction to review the
decision
ADMINISTRATIVE LAW – ADMINISTRATIVE
TRIBUNALS – QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL – whether building work
was defective – whether building work complied with 2009
Building Code of Australia, Specification C1.1,
Requirement 2.4(a)(iii) – whether the use of the aluminium
composite panels as sunshades attached to an exterior wall
of a very tall building constituted an undue risk of fire spread
via the facade of the building
Queensland Building and Construction Commission Act
1991 (Qld), s 72, s 72A, s 86
Queensland Civil and Administrative Tribunal Act
2009 (Qld), s 3, s 24
Agius v Queensland Building and Construction
Commission & Anor [2023] QCATA 145
Body Corporate for Parkside Bulimba CTS46539
v Queensland Building and Construction Commission and
De Luca Corporation Pty Ltd [2023] QCAT 139
Clark v Queensland Building and Construction
Commission [2024] QCAT 329
Jorg & Anor v Queensland Building and Construction
Commission [2021] QCATA 134
McNab Constructions Australia Pty Ltd v Queensland
Building Services Authority [2013] QSC 57
Owners SP 92450 v JKN Para 1 Pty Ltd [2023] NSWCA
114
Strata Plan 92450 v JKN Para 1 Pty Ltd [2022] NSWSC
958
TAJ (costs) [2023] QCAT 133
Tanna v Queensland Building and Construction
Commission [2023] QCATA 81
Taylor Construction Group Pty Ltd v Strata Plan 92888
t/as The Owners Strata Plan 92888 [2021] NSWSC 1315
APPEARANCES &
REPRESENTATION:
Applicant: S S Monks instructed by Hynes Legal
First Respondent: K W Wylie instructed by the Queensland Building and
Construction Commission
Second Respondent G A Sirtes SC instructed by Meriton corporate counsel
-- 2 of 29 --
3
REASONS FOR DECISION
What is this claim about?
[1] The Meriton tower is a very tall building in the Brisbane CBD. It was completed in
April 2014. It features sunscreens attached to floor slabs. The horizontal sunscreens
consist of a polyethylene core encapsulated in aluminium, commonly known as
aluminium composite panels (ACPs). If the Meriton tower was constructed today it
would not have ACPs attached as sunscreens as use of such material as part of, or
attached to, the exterior of a building was essentially prohibited following the
Lacrosse building fire in Melbourne in 2014 and the Grenfell tragedy in London 2017.
[2] When the Meriton tower was constructed and certified the relevant building code
permitted the use of sunscreens constructed, in part, of combustible material
(polyethylene is combustible) if they did not constitute an undue risk of fire spread
via the facade of the building. In these proceedings the applicant argues that the ACPs
constitute an undue risk of fire spread via the facade of the building.
[3] This is an application to review a decision of the Queensland Building and
Construction Commission (Commission) not to direct the second respondent
(contractor) to rectify the ACPs. The applicant (Body Corporate) is a volumetric lot
Community Titles Scheme body corporate that controls common property that
generally falls between levels 25 to 64 of the Meriton tower.
[4] There is a threshold issue regarding whether or not this tribunal can conduct the
review, despite the fact it was filed within six years and six months of completion of
the building work. The Commission submits the application should be dismissed for
lack of utility, regardless of its merits on the facts, as it has decided not to seek leave
to give the contractor a direction to rectify regardless of the outcome of the review of
its decision.
Background
[5] The background facts are largely uncontroversial.
[6] The application relates to building work carried out by the contractor on the Meriton
building at 23 Herschel Street, Brisbane (Meriton tower). It is a tall building: 223
metres in height with 70 storeys (not including basement levels). The ACPs are an
architectural feature of the building. They are curved and appear as horizontal stripes
around parts of the building. They are attached to the floor slabs of the building to
function as sunshades.
[7] These ACPs comprise a polyethylene core encapsulated by aluminium. Aluminium is
generally considered non-combustible and polyethylene is generally considered
combustible. Until the contractor made its closing submissions no issue was raised
regarding combustibility of the panels. For reasons addressed in detail below1 I am
satisfied that the ACPs are combustible. In summary, this is because:
(a) by application of the definition of the word combustible in the 2009 Building
Code of Australia (2009 BCA) the ACPs are combustible because they are in
part constructed of polyethylene which is a combustible material;
1 Paragraphs [116] to [123] below.
-- 3 of 29 --
4
(b) the certifier proceeded on the basis the ACPs were combustible;
(c) the fire engineers engaged by Meriton to advise on possible solutions posed by
the presence of the ACPs assumed they were combustible and verified that
assumption by commissioning laboratory testing of samples of the ACPs from
Meriton tower. That testing showed that ‘the curved horizontal sun screens are
constructed from aluminium composite panel with a core material with 95%
PE’;
(d) additional laboratory tests carried out on samples of the ACPs from Meriton
tower showed that the material in the core of the samples ranged between 87%
to 92% polyethylene + Ethylene Vinyl-acetate co-polymers;
(e) the experts who gave evidence said they were combustible;
(f) testing performed by Ignis, under instruction of Meriton, which replicated the
ACPs in a test assembly, demonstrated the combustibility of the test assembly,
if not the actual panels on the Meriton tower.
[8] ACPs had been fixed to building exteriors for many years without an appreciation of
the fire risk posed by them. Since the Melbourne Lacrosse building fire in November
2014 and the June 2017 Grenfell building fire tragedy in London, fixing them to
building walls has essentially been prohibited.
[9] The building was constructed and certified when the 2009 BCA was in effect. Under
the 2009 BCA, there was no blanket prohibition against fixing combustible materials,
such as ACPs, to buildings. However, the Body Corporate argues that fixing
combustible materials such as ACPs to buildings could contravene more specific
provisions of the 2009 BCA, including Deemed to Satisfy Specification C1.1 Fire-
resisting construction, General Requirement 2.4 (General Requirement 2.4). The
Body Corporate argues that the heart of this application for review is its contention
that the ACPs (variously called sunshades, sunscreens or sunblinds) affixed to the
Meriton tower contravened General Requirement 2.4.
[10] Relevant to this application, and in particular to s 72A(4) of the Queensland Building
and Construction Commission Act 1991 (QBCC Act), the building work associated
with the ACPs was completed on 15 April 2014 when Mr Hofstetter, the private
building certifier engaged by the contractor, gave a certificate of classification for the
building.
[11] Section 71J(1) of the QBCC Act permits a consumer to ask the Commission to give a
direction to rectify building work the consumer considers is defective or incomplete.
[12] On 23 July 2019, the Commission received a complaint by the Body Corporate
alleging that 162 building work complaints set out in a Defects Register produced by
Paul Marko from Queensland Building and Fire Services Pty Ltd should be the subject
of a direction to rectify. In subsequent correspondence, this register was described as
the TASQ report.
[13] Defect 138 in the TASQ Report describes the alleged defect as follows:
External cladding, sun blinds, acrylic signage and ACP (aluminium composite
panels.) panels. These panels are fixed above around and on paths of egress and
fire doors with glue and plastic packers. …
-- 4 of 29 --
5
Combustible materials cannot be installed under the National Construction
Code (NCC) Volume One, Performance Requirement CP2 requires that a
building must have elements which will avoid the spread of fire in a building,
in a manner appropriate for that building. This requirement is met, in part, under
a Deemed to Satisfy Solution for buildings of Type A and Type B construction
by noncombustible external walls (Specification C1.1 Clauses 3.1(b) and
4.1(b)). The body corporate has followed the QLD legislative cladding
identification process and the fire engineers AE&D have identified the risks,
which will need to be addressed through an holistic approach to the fire safety
strategy of the building identifying robustness and weakness's (sic)
…
The installed cladding does not comply with the requirements of the BCA as a
DTS solution, in regard to spec C1.1, 2.4, spec C1.10 and clause 7: The
recommendations from the independent fire engineer will need to further look
at the stair press (sic) system, the passive fire risks, the bending moment of the
slab and the interaction of the curtain wall system, early detection, increased
fuel loads and the evacuation times.
[14] The Complaint referred to 2009 BCA Deemed to Satisfy Specification C1.1
Fireresisting construction, General Requirement 2.4, which provided (emphasis
added):
2.4 Attachments not to impair fire-resistance
(a) A combustible material may be used as a finish or lining to a wall
or roof, or in a sign, sunscreen or blind, awning, or other
attachment to a building element which has the required FRL if—
(i) the material is exempted under C1.10 or complies with the
fire hazard properties prescribed in—
(A) Clause 2 of Specification C1.10; or
(B) Clause 2 and 3 of Specification C1.10a; and
(ii) it is not located near or directly above a required exit so as
to make the exit unusable in a fire; and
(iii) it does not otherwise constitute an undue risk of fire
spread via the facade of the building.
(b) The attachment of a facing or finish, or the installation of ducting
or any other service, to a part of a building required to have an FRL
must not impair the required FRL of that part.
[15] After making the complaint, a replacement defects table was produced, and TASQ
defect 138 was renumbered to defect 135 (Defect 135), and provided as follows:
External cladding, sun blinds, acrylic signage and ACP (aluminium composite
panels) panels. These panels are fixed above around and on paths of egress and
fire doors with glue and plastic packers
…
AE&D Fire Engineers have identified risks to be addressed through the fire
safety strategy of the building. Refer TASQ report item 138.
-- 5 of 29 --
6
[16] On 17 June 2020, the Commission completed its investigation of the Body
Corporate’s complaint. While it decided to issue Directions to Rectify (DTRs) for
some defects, it decided not to give a DTR for Defect 135.
[17] On 12 July 2020, the Body Corporate applied to the Commission pursuant to s 86A(1)
of the QBCC Act seeking internal review of the Commission’s decision not to give
DTRs for several defects, including Defect 135.
[18] By letter dated 5 August 2020, the Commission gave notice of its internal review
decision made pursuant to s 86C of the QBCC Act (Review Decision). The Review
Decision decided, inter alia, to issue a DTR with respect to Defect 135, but responding
only to part of the complaint. In particular, the Review Decision provided the
following DTR responsive to Defect 135:
81 The installation of the cladding to the ground level fire isolated exits do
not comply with Spec C1.10-3 of the BCA 2009 Vol 1 in that the
composite panels are flammable resulting in unacceptable health and
safety risk to the users and occupants of the building in the event of a fire.
Pertains to item 135 of the QBCC complaint form.
[19] Put simply, what was required by that DTR was the removal of ACPs at the ground
level near the building exit, to comply with Requirement 2.4(a)(ii) set out above.
[20] These proceedings commenced on 2 September 2020 when the Body Corporate
applied to this tribunal pursuant to 87 of the QBCC Act. That application sought
review of:
(a) the decision to issue a DTR in relation to only part of Defect 135; and
(b) the decision not to issue DTRs with respect to defects 1, 10, 115 and 127.
[21] By the time the hearing commenced, as a result of compromise agreements between
the Body Corporate and the contractor, only Defect 135 needed to be considered. The
Body Corporate contends that an amended DTR should be issued with respect to all
horizontal sunshades fixed to the Meriton tower. The Commission and the contractor
contend that no such DTR should be issued.
Relevant legislation
[22] Section 72 of the QBCC Act provides:
(1) This section applies if the commission is of the opinion that—
(a) building work is defective or incomplete; or
…
(2) The commission may direct the person who carried out the building work
to do the following within the period stated in the direction—
(a) for building work that is defective or incomplete—rectify the
building work;
…
(5) The commission is not required to give the direction if the commission is
satisfied that, in the circumstances, it would be unfair to the person to
give the direction.
Example for subsection (5)—
-- 6 of 29 --
7
The commission might decide not to give a direction for the rectification
of building work because an owner refuses to allow a building contractor
to return to the owner’s home or because an owner’s failure to properly
maintain a home has exacerbated the extent of defective building work
carried out on the home.
[23] Section 72A of the QBCC Act provides:
Powers and limitations of directions to rectify or remedy
…
(4) A direction to rectify or remedy cannot be given more than 6 years and 6
months after the building work to which the direction relates was
completed or left in an incomplete state unless the tribunal is satisfied, on
application by the commission, that there is in the circumstances of a
particular case sufficient reason for extending the time for giving the
direction and extends the time accordingly.
[24] Section 86(1) of the QBCC Act provides:
Each of the following decisions of the commission under this Act is a
reviewable decision
…
(e) a decision to give a direction to rectify or remedy or not to give the
direction.
[25] Section 87 of the QBCC Act provides:
Application for review
A person affected by a reviewable decision of the commission may apply, as
provided under the QCAT Act, to the tribunal for a review of the decision.
[26] Section 3 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT
Act) provides:
The objects of this Act are
…
(b) to have the tribunal deal with matters in a way that is accessible, fair, just,
economical, informal and quick;
[27] Section 24 of the QCAT Act provides:
(1) In a proceeding for a review of a reviewable decision, the tribunal may:
(a) confirm or amend the decision; or
(b) set aside the decision and substitute its own decision; or
(c) set aside the decision and return the matter for reconsideration to
the decision-maker for the decision, with the directions the tribunal
considers appropriate.
(2) The tribunal’s decision under subsection (1)(a) or (b) for a reviewable
decision
-- 7 of 29 --
8
(a) is taken to be a decision of the decision-maker for the reviewable
decision except for the tribunal’s review jurisdiction or an appeal
under part 8; and
(b) subject to any contrary order of the tribunal, has effect from when
the reviewable decision takes or took effect.
Building Code of Australia 2009
[28] The 2009 BCA has been superseded, but is the code by reference to which the Meriton
tower was designed and certified.
[29] The BCA performance requirements require that a building have elements which will,
to the degree necessary, avoid the spread of fire to sole occupancy units and public
corridors. Avoidance of the spread of fire must be appropriate to:
(a) the use of the building;
(b) the potential fire intensity;
(c) the fire hazard;
(d) the number of storeys in the building;
(e) proximity of the building to other property;
(f) any active fire safety systems installed in the building;
(g) fire brigade intervention;
(h) the evacuation time.2
[30] There were three ways to comply with the performance requirements prescribed by
the 2009 BCA:
(a) compliance with deemed to satisfy provisions; or
(b) formulating an alternative solution which:
(i) complied with the performance requirements; or
(ii) was shown to be at least equivalent to the deemed to satisfy provisions; or
(c) a combination of (a) and (b).3
[31] Typically, the deemed to satisfy provisions prescribe quantitative standards and
alternative solutions require assessment by a competent person.
[32] Part C1.0 of the 2009 BCA addresses requirements for deemed to satisfy provisions.
Specification C1.1 contains requirements for the fire-resisting construction of
buildings. Section 2.4 deals with attachments to buildings. It allows use of a
combustible material in a sunscreen if:
(a) the material is exempted under C1.10 or complies with the fire hazard properties
prescribed in—
2 BCA 2009 Volume 1, Part CP2.
3 Ibid, Part A0.
-- 8 of 29 --
9
(i) Clause 2 of Specification C1.10; or
(ii) Clause 2 and 3 of Specification C1.10a; and
(b) it is not located near or directly above a required exit so as to make the exit
unusable in a fire; and
(c) it does not otherwise constitute an undue risk of fire spread via the facade of the
building.
[33] When applied to a material, the meaning of combustible is determined by AS 1530.1.
When applied to construction or part of a building, combustible means constructed
wholly or in part of combustible materials.4
[34] AS 1530.1 is the Australian Standard for methods of fire tests on building materials,
components and structure.5
Threshold issue
[35] As a threshold issue, the Commission submitted that, absent any application by the
Commission under section 72A(4) (none being made), the tribunal has no power to
direct rectification because more than six years and six months have elapsed since the
building work the subject of this application was completed. Counsel for the Body
Corporate submitted that the outcome contended for by the Commission was absurd.
[36] The Commission’s argument is based on a distinction which it says is to be drawn
between a decision to give (or not give) a direction to rectify, which is a reviewable
decision,6 and the subsequent giving of the direction to rectify,7 which is not a
reviewable decision. If the Commission’s argument is correct, it would leave the Body
Corporate without a remedy despite the fact that it made its complaint and filed its
application within six years and six months of completion of the building work the
subject of this application.
[37] For the reasons that follow I have decided that I have jurisdiction to consider this
review application filed on 2 September 2020, which is within six years and six
months of the completion of the building work on 15 April 2014, which enlivens the
power to substitute my decision for the Commission’s decision which was made on 5
August 2020. What follows will be a matter for the Commission.
Relevant cases
[38] The Commission submitted that I should adopt the reasoning of Member Lumb in
Clark v QBCC (Clark).8 In Clark Member Lumb addressed two questions: first, when
the building work had been completed, and second, whether the operative event for
the purpose of s 72A(4) was the making of the decision under review9 or the date of
filing the application to review the decision.10 He decided that the decision under
review had been made within six years and six months of completion of the building
4 Ibid, Part A1.
5 Exhibit 2.
6 86(1)(e).
7 QBCC Act s 72A(4).
8 [2024] QCAT 329.
9 In which case the decision was made on the last day of the six year six month period.
10 In which case the tribunal lacked jurisdiction to hear the application.
-- 9 of 29 --
10
work.11 In addressing the second question Member Lumb accepted the contractor’s
submission that the case was on all fours with the decision of the appeal tribunal in
Jorg v QBCC12 (Jorg).13
[39] In Jorg the decisions under review had been made within six years and six months of
completion of the building work (on 11 and 14 December 2018) but the consumers
had not filed their review application in the tribunal by 14 January 2019 (six years and
six months from completion of the building work). The appeal tribunal confirmed that
there could be no extension of time in cases in which the period provided by s 72A(4)
had elapsed before the review application had been filed unless the Commission
applied for, and was granted, an extension of time. The appeal tribunal rejected the
argument that section 24(2)(b) might confer jurisdiction, observing that section 24
relates to the powers given to the tribunal, not to its jurisdiction.14
[40] In Clark Member Lumb relied on the judgment of Dalton J (as her Honour then was)
in McNab Constructions Australia Pty Ltd v Queensland Building Services Authority
(McNab),15 to draw a distinction between the making of a decision to give a direction
to rectify, and the actual giving of the direction to rectify. The issue before Dalton J
was the validity of directions to rectify sent by the Commission to the contractor. Her
Honour found that the Commission had failed to provide the contractor with the
minimum time period to rectify as required by section 72(3) of the QBCC Act.
Accordingly, she declared the directions to rectify void.
[41] After finding the directions to rectify invalid, Dalton J went on to address the
arguments advanced by the parties regarding discretionary matters which might be
taken into account before making the declarations sought: the Commission arguing
that she should refuse to make the declaration as the hearing of the review application
was about to begin in the tribunal and the contractor arguing to the contrary. Her
Honour observed:
[18] From a review of the statutory provisions it should be plain that the
question before me is not the same as the question before QCAT. QCAT
has jurisdiction to review the decision of the [Commission] to direct
rectification. The decision to direct rectification is necessarily anterior to
the giving of a direction for rectification. My decision concerns only the
directions to rectify actually given, it does not touch upon the validity of
the decision of the [Commission] to direct rectification, or of course the
merits of that decision. My decision is only concerned with the notice of
that decision given to the [contractor], by way of direction pursuant to s
72(1) of the QBSA Act.
[19] For these reasons it seems to me that the existence of the impending
merits review in QCAT is no reason why I should not make the
declaration sought. Further, having regard to the limited statutory powers
of QCAT, I am of the view that QCAT does not have jurisdiction to
entertain the application for a declaration. As I say, I cannot see that there
is any overlap between the proceeding in the Court and the proceedings
in QCAT.
11 [2024] QCAT 329 at [28].
12 [2021] QCATA 134.
13 [2024] QCAT 329 at [32].
14 Ibid at [43].
15 [2013] QSC 57.
-- 10 of 29 --
11
[42] The Commission argues that Senior Member Traves in Agius v QBCC (Agius)16
confirmed the distinction between the making of a decision to give a direction to
rectify, and the actual giving of the direction to rectify. The issue before Senior
Member Traves was not whether the consumer had made his complaint or filed his
application within six years and six months of completion of the building work the
subject of his application. He had done both. Senior Member Traves’ decision deals
with quite a different factual situation which arose due to an error made by the
consumer in filing an application that stated that it was to review ‘Direction to Rectify
No 0106161 dated 28 May 2020’, whereas the Commission’s internal review decision
was a document dated 26 May 2020.
[43] Senior Member Traves took a practical and just approach in concluding that as a
decision to give a direction to rectify (or not) was a reviewable decision, the
application as filed should be treated as an application to review the decision to give
a direction, even if the application referred to the direction to rectify. She observed
that whilst the distinction between the decision to give a direction to rectify and the
actual notice was ‘entirely appropriate in the circumstances of [McNab]’ the judgment
of Dalton J did not ‘go so far as to establish that the giving of the direction was a
separate decision’. The Senior Member said17 that the decision to give a direction to
rectify was a reviewable decision. The actual giving of the direction was not a
reviewable decision but rather was ‘a consequential step’ which might be a separate
decision, but if it was (which the Senior Member did not decide) it would not be a
reviewable decision although possibly it would be reviewable under the Judicial
Review Act 1991 (Qld) or subject to declaratory relief in the Supreme Court.
[44] Counsel referred to a number of previous decisions of the tribunal:
(a) Tanna v QBCC (Tanna),18 where the application was not filed within six years
and six months of completion of the building work as the decision under review
had not been made within that period;
(b) Body Corporate for Parkside Bulimba CTS46539 v QBCC (Parkside)19 where
the time bar operated on 23 October 2021 but the application was not filed until
2 November 2021; and
(c) Jorg where the time bar operated on 14 January 2019 but the application was
not filed until after that date.
Consideration
[45] The Body Corporate’s right to make this application is created by section 87 of the
QBCC Act. It is common ground that the decision which is the subject of this
application was made on 5 August 2020. The six year six month period from the
completion of the building work expired on 15 October 2020. It is common ground
that the Body Corporate filed this application on 2 September 2020.
[46] This case is different from cases in which the tribunal had no jurisdiction because
more than six years and six months had passed between completion of the building
work and filing the relevant application, the Commission having decided not to apply
16 [2023] QCATA 145.
17 Ibid, at [21] and [25].
18 [2023] QCATA 81.
19 [2023] QCAT 139.
-- 11 of 29 --
12
for an extension of time under section 72A(4) of the QBCC Act, i.e., Jorg, Tanna and
Parkside. Each of those cases can be distinguished on the facts.
[47] I am not bound to follow Clark for reasons explained in TAJ (costs).20 Even if I were
bound to follow Clark, I am not bound to follow obiter dicta in Clark. In any case, as
the facts found in Clark are different from the facts in this case, I need not consider it
further.
[48] In this case the Body Corporate filed its application for a review of the decision of the
Commission within six years and six months of the completion of the building work.
Accordingly, the tribunal has jurisdiction. It follows that it has power to set aside the
decision and substitute its own decision and that decision is taken to be a decision of
the decision-maker for the reviewable decision having effect from when the
reviewable decision took effect in 2020 (5 August 2020).21
[49] My finding that the tribunal has jurisdiction to review the decision not to give a
direction to rectify in this case is in accordance with the statements of Senior Member
Traves in Agius. I respectfully agree with her comment that the judgment of Dalton J
in McNab did not ‘go so far as to establish that the giving of the direction was a
separate decision’. Whether the actual giving (or not giving) the direction following
the review, whether described as an anterior or consequential step, is a separate
decision, has not been decided.
[50] There is no argument in this case about the validity of a direction to rectify, none
having been given. Accordingly, the discretionary matters taken into account by
Dalton J in McNab before making the declarations sought do not go to the jurisdiction
of the tribunal to hear an application for a review of a procedurally valid decision of
the Commission filed within six years and six months of the completion of the
building work.
[51] What follows this review is a matter for the Commission. It is not my role to advise
the Commission as to the exercise of its discretion to make an application under s
72A(4) in circumstances in which an application for review has been made within six
years and six months of completion of the building work. However, it would seem
surprising that a statutory authority would make a pre-emptive decision not to take the
appropriate consequential step in circumstances in which, on review, a decision to
give a direction to rectify might be substituted for its decision not to give a direction
to rectify. The effect of making such a pre-emptive decision would be that a
consumer’s statutory right to apply for a review of the original decision within six
years and six months of the completion of the building work would be illusory.
Did affixing ACPs constitute an undue risk of fire spread via the facade of the
building?
The issue
[52] The overarching question is whether the building work is defective. The answer to
that question requires consideration of whether or not the use of the ACPs constituted
an undue risk of fire spread via the facade of the building. If the use of the ACPs
constituted an undue risk of fire spread via the facade of the building, the building
20 [2023] QCAT 133.
21 QCAT Act s 24.
-- 12 of 29 --
13
work is defective because it did not comply with 2009 BCA Specification C1.1,
Requirement 2.4(a)(iii).
[53] It is common ground that the question whether the building work is defective is not
determined by the opinion of a building certifier (either at the time or now) as to
whether it complied with the Building Code or any other relevant standard. Nor is it
determined by whether the use of ACPs would have been regarded as reasonable or
accepted industry practice at the time the building was designed or certified.
Relevant cases
[54] The only administrative review judgement directly on point cited is the judgment of
Henry J in Taylor Construction Group Pty Ltd v Strata Plan 92888 t/as The Owners
Strata Plan 92888 (Taylor).22 Those proceedings related to the use of Biowood, which
is a combustible material made of reconstituted timber and PVC, on two multi-storey
residential buildings.
[55] In considering the nature of Requirement 2.4(a)(iii) of the 2009 BCA, Her Honour
reasoned:
[140] The Appeal Panel found that the word “undue” in the context of cl
2.4(a)(iii) means, relevantly, “unwarranted or excessive”. Although the
Appellants’ submissions suggested that undue risk connoted “deliberate
and significant risk”, at the hearing they accepted that the words
“unwarranted and excessive” are not inapposite to describe the nature of
the risk as “undue” …. Thus, there is no real dispute that undue risk for
the purposes of cl 2.4(a)(iii) means risk of fire spread via the façade of
the Buildings that is unwarranted or excessive. The meaning given by the
Appeal Panel to “undue” accords with the ordinary English meaning of
the word and, in my view, correctly reflects that the word has no unusual
or technical meaning, unlike some other terms used in the BCA, such as
“Spread of Flame Index”. The Appeal Panel did not err by adopting that
meaning.
[141] The BCA does not specify the particular matters or precise parameters
for determining whether the use of combustible material as an attachment
constitutes a risk of fire spread via a building façade that is unwarranted
or excessive for the purposes of cl 2.4(a)(iii). In my view, the
determination as to whether the risk is undue (or unwarranted or
excessive) involves an evaluative task that requires consideration of the
circumstances and context in which the Biowood combustible cladding
is used as an attachment to the external walls of the Buildings. That
includes consideration of the objective of Section C of the BCA of
ensuring the safety of people from fire, the BCA requirement that
external walls in Type A buildings are to be constructed using non-
combustible material, the possibility of fire spread eventuating, and the
gravity of the risk from such use. Factors such as the ignitability of the
combustible material and the likely rate of fire spread, the location of the
material, and relevant safety features of the Buildings would also be
germane to consider.
22 [2021] NSWSC 1315.
-- 13 of 29 --
14
[142] To that extent, I accept the Appellants’ submission that the “test” or
approach to be applied in assessing whether risk is undue could be
described as a multifactorial one. …
[144] … the Appeal Panel’s approach clarifies that a material’s compliance
with Specification C1.10, such as by AS1530.3 and a low Spread of
Flame Index, is not determinative of whether use of that material
otherwise constitutes a risk of fire spread that is unwarranted or
excessive.
…
[153] The determination of whether a risk of fire spread is undue is not, in my
view, limited to a comparator of risk based on a quantitative assessment
of whether there is a high likelihood of fire spread or a low one. The
determination also takes into account a qualitative assessment of whether
the risk is warranted, in the sense of being acceptable or not, in the
circumstances. The evaluative exercise in assessing undue risk inevitably
requires the balancing of factors and judgment. The likelihood of fire
spread might be identified as low or not fully known based on the quality
of the material but the risk assessed as undue because of the gravity of
the consequences having regard to the location of the material and the
nature of the building.
[154] …The words undue risk do not only mean that which is an excessive,
great or high risk, but includes the concept of unwarranted, in the sense
that a risk may be inappropriate or unjustified in the circumstances even
if low.
[56] Black J considered whether cladding complied with the Building Code in Strata Plan
92450 v JKN Para 1 Pty Ltd (Strata Plan 92450),23 but in the context of civil
proceedings in which the claim was for damages for breach of statutory warranties.24
He was asked to determine separate questions based on an agreed statement of facts.
The parties agreed that the cladding did not comply with the deemed to satisfy
provisions of the BCA as it was combustible. Black J was not prepared to make
findings on the basis that the cladding was combustible absent proof of that as a fact
because such a finding would have significant implications for the developer, the
builder, the certifier, owners who had sold units and purchasers of those units and
existing owners, not all of whom were parties to the proceedings.
[57] An appeal against his judgement was allowed in Owners SP 92450 v JKN Para 1 Pty
Ltd.25 The appeal did not address the approach of Black J to the issue of combustibility
because the respondents conceded that there had been a breach of the statutory
warranty.
The evidence
[58] While it is common ground that the question whether the building work is defective
is not determined by the opinion of a building certifier as to whether it complied with
the Building Code or any other relevant standard, I include reference to the evidence
of the building certifier and of other building certifiers as that evidence provides some
23 [2022] NSWSC 958.
24 In the Home Building Act 1989 (NSW).
25 [2023] NSWCA 114.
-- 14 of 29 --
15
assistance in addressing factors to be taken into account when undertaking the
qualitative assessment of whether the risk was acceptable or not in the circumstances.
Hofstetter
[59] Mr Hofstetter provided an affidavit.26 He is a senior building certifier and the person
who certified the Meriton tower. He has been a building certifier since 1994. He was
not required for cross-examination.
[60] He decided that the sunscreens complied with the deemed to satisfy provisions of
Specification C1.1, clause 2.4. He listed the steps that he took under clause 2.4 to
conclude that the sunscreens did not impair fire resistance:
(a) regarding clause 2.4(a)(i), he did not believe that the panels were combustible
because they had a spread of flame index of 0;
(b) regarding clause 2.4(a)(ii), he was satisfied that the panels did not pose a risk of
making the exits unusable in a fire because the panels had a spread of flame
index of 0 and he believed that the panels did not burn;
(c) regarding clause 2.4(a)(iii), he thought that the use of aluminium composite
panels was acceptable because it was believed that they complied with deemed
to satisfy provisions as it was the thinking of the day that the panels did not
constitute an undue risk of fire spread via the facade of the building because the
test certificates showed they had a spread of flame index of 0.
Igoe
[61] Mr Igoe provided a report.27 He is a level 1 building certifier. He has 20 years of
experience as a private certifier of commercial buildings. He was cross-examined.
[62] He reviewed all the relevant documents and concluded:
There is no evidence to suggest external cladding… formed part of the Fire
Engineering analysis conducted at the time of the design and construction.
[63] He observed that prior to the advent of heightened awareness of the combustible
nature of cladding on high rise buildings, which he said occurred circa 2014 to 2016,
the consideration of external cladding products often did not occur until building
projects were significantly advanced which in the majority of cases was when the
project was well under construction.
[64] Mr Igoe observed that the Building Act requires a certifier to clearly and concisely
document and record their decision-making process, which can include relying on
certificates from appropriately qualified professionals. He endorsed the approach
taken by Mr Hofstetter. In Mr Igoe’s opinion Mr Hofstetter was entitled to rely on the
Form 15 and 16 certificates of the installation and design of the façade curtain wall
system provided by a registered professional engineer.
[65] In cross-examination Mr Igoe confirmed that the characteristics of ACPs have not
changed since the time Meriton tower was certified; the change is the state of
knowledge in the construction industry.
26 Hearing book tab 14.
27 Ibid, tab 10.
-- 15 of 29 --
16
[66] In cross-examination Mr Igoe said that he would not have regarded the sunscreens as
part of the building as they were not fixed to the external wall. A factor he would have
taken into account had he been undertaking a risk assessment in 2014 was the vertical
separation of approximately 2.5 to 3 metres.
[67] In re-examination Mr Igoe explained that he would not have taken the height of the
building into account if he had been performing a risk assessment focused on the
ACPs as the height of the building would already have been taken into account as part
of the assessment of the fire safety system for the tower.
Report from AED Fire Pty Ltd (signed by Clark and Halstead)
[68] Meriton Group commissioned AED Fire Pty Ltd (AED) to carry out a fire safety
analysis and assessment of the ACPs on the Meriton tower in 2019.28 The report was
not prepared for these proceedings. A purpose of the report was to agree a strategy to
reduce the undue spread of fire. The assessment is based on the 2016 amendment to
the BCA, not the version of the BCA which was applicable at the time the building
was certified.
[69] AED commissioned laboratory testing of samples of the ACP from Meriton tower.
That testing showed that ‘the curved horizontal sun screens are constructed from
Aluminium Composite Panel with a core material with 95% PE’.29 The report stated
that the sunscreens were constructed from combustible aluminium composite panels.
[70] AED carried out ad hoc drill testing of the vertical panels which showed that they
were constructed of solid aluminium and hence deemed to be non-combustible.
[71] The report identifies two options to address the risk of spread of fire:
(a) retain the sunscreens, leaving a medium risk of undue spread of fire;
alternatively
(b) install external drenchers to reduce the risk to low.
[72] Neither option is relevant to the question before me.
[73] The report identifies the following risk factors present in the building:
(a) occupants of a residential building of 79 storeys cannot be expected to be awake
or familiar with the building and exits;
(b) there is horizontal and vertical connectivity between the combustible cladding
elements on all elevations; and
(c) there are limited ignition sources near the combustible cladding.
[74] The report identifies the following items of particular importance in the fire safety of
the building:
(a) absence of balconies;
(b) the cladding does not extend to the ground;
28 Ibid, tab 12.
29 Ibid, tab 12, p 6.
-- 16 of 29 --
17
(c) the internal sprinkler system will limit the potential for fire spread from the
façade to the interior of the building and limit the potential of fire originating
within the building spreading to the façade through openings;
(d) the combustible sunscreens are not vertically continuous but occur at the edge
of each slab;
(e) the building has a smoke detection system and occupant warning system that
will detect a fire within the building and initiate evacuation;
(f) there are few ignition sources;
(g) there are no BBQ areas, space heaters or retail spaces close to the cladding.
[75] The author of the report had regard to a research paper published in April 2000 which
was produced to support the ongoing development of the Building Code of Australia.
The authors of the research paper noted that there were relatively few documented
cases of vertical fire spread involving combustible claddings, but that the sparse
historical record did not mean that there is no significant risk in the use of combustible
claddings. The authors of the research paper found no record of external vertical fire
spread from an external cladding fire in fully sprinklered buildings.
[76] Meriton tower is a fully sprinkler protected building. The author of the report opines
that sprinklers are a significant part of good fire safety design and their effectiveness
is very important. Drawing on a literature review, the author states that the reliability
of a sprinkler system is quoted in the range of 98-99%, but in reality, is more likely to
be 95-99%.
[77] The author of the report considered the four ignition and fire spread scenarios that had
been described by the authors of the research paper:
(a) flames projecting from broken windows in the room of fire origin, exposing the
façade and windows above, the upper windows break allowing fire to enter the
floors above;
(b) inadequate fire stopping of the gap between the edge of the floor slab and the
exterior walls;
(c) heat induced distortion causing fire stopping to be ineffective; and
(d) ignition of combustible cladding from an external source.
[78] They concluded:
(a) in the event of the successful operation of the sprinkler system, fire spread from
an internal fire to the ACPs is unlikely;
(b) the issue of fire stopping is not a concern;
(c) the issue of heat induced distortion is not a potential of fire spread vertically;
(d) ignition of combustible cladding from an external source is the most likely
source of substantial vertical fire spread.
-- 17 of 29 --
18
First Stratton Report
[79] Mr Blair Stratton, a fire engineer, who was called by the Body Corporate, provided a
number of reports, the first in September 2021.30
[80] Mr Stratton commissioned scientific analysis of 10 samples from the ACPs from
Meriton tower. The material in the core of the samples ranged between 87% to 92%
polyethylene + Ethylene Viny-acetate (sic) co-polymers.31
[81] In that report Mr Stratton made comments on, and criticisms of, the report from AED
with a particular focus on the accuracy of AED’s analysis of risks associated with the
combustible façade’. Relevantly, he criticised:
(a) failure to consider the possibility of horizontal fire spread between single
occupancy units;
(b) failure to consider the possibility of burning droplets or whole panels falling
from the building impeding safe evacuation and ability of fire fighters to access
the building and equipment;
(c) failure to consider the possibility of toxic smoke impacting the evacuation route;
(d) failure to consider that external fire brigade intervention is not possible for most
of the building; and
(e) use of the undefined term ‘medium risk’ in the absence of carrying out any risk
assessment.
[82] He observed that sprinkler systems are not 100% reliable. He also expressed concern
about placing reliance on data about the reliability of sprinkler systems collected in
the USA and data obtained from office buildings due to the differences in
circumstances between the USA and Australia.
[83] In cross-examination he acknowledged that he had not undertaken any analysis to
show that the design of the sprinkler system was in any way deficient. His point was
simply that there was a 5% chance that it would be unreliable which he thinks must
be taken into account in the risk assessment.
[84] He opines that risk is the product of both the likelihood of an event occurring and
consequences of the event. He is critical of AED’s failure to consider scenarios in
which fire would spread to the combustible façade and result in fire spread both
horizontally and vertically, blocked exits and difficult fire brigade intervention.
First Alexander Report
[85] Mr James Alexander, who was called by the contractor, is qualified in both fire safety
and building certification. He provided a number of reports, the first in March 2022.32
[86] Mr Alexander directed the comments in his report to the decision of the Commission’s
internal reviewer. When addressing the comment that testing should have been done
in line with AS 150301, 2, 3 and 4 he said:
30 Ibid, tab 4.
31 Ibid, tab 4, p 115.
32 Ibid, tab 13.
-- 18 of 29 --
19
The certifier is required to source test reports or test data to confirm compliance
with relevant provisions of the BCA. In this case, this requires that the installed
attachments or cladding comply with the fire hazard properties of Spec C1.10.
…
AS 15030.1-1994 is the test for combustibility. The certifier was aware that the
ACP was combustible and hence this is why the product was assessed under
Clause A2.4 of the Spec C1.1…
[87] Mr Alexander expressed doubt that if a fire managed to spread from within the
building, in what he thought to be a highly unlikely scenario of a sprinkler failure, that
it would cause an undue spread of fire up the façade of the building as the exposed
surface of the ACPs was aluminium with metallic flashings with no exposed PE edges
to enable ignition via the sheet edge. He said that in order to expose the combustible
core to flaming ignition it would be necessary to have a constant flame on the surface
of the aluminium sheet for a duration to cause delamination of the aluminium.
[88] He noted that the curved sunblinds on the northern façade are connected to the
protruding slab edge perimeter with a steel bracket arrangement. He noted that the
panels are 700 wide and that there is 2.4 metres above a panel to the base of the panel
on the slab above. He doubted whether, if a panel ignited, the flame height would be
sufficient to ignite a strip 2.4 metres above.
[89] In cross-examination he expressed the view that there is no undue risk of fire spread
due to the presence of the sunshades. He rejected the proposition that the height of
Meriton tower made the building sufficiently unusual given the difficulty it would
present in fighting a fire to justify taking a different approach to risk analysis. He
observed that the height of a building makes no difference to assessing risk because
people can die in a fire in a two-storey building.
Second Stratton Report
[90] Mr Stratton provided his second report in June 2022.33 Its purpose was to respond to
the First Alexander Report. His commentary included his opinion that during an
apartment fire where sprinklers fail to operate as designed, fire from one apartment
can break the glass and ignite the sunshades. Fire can spread horizontally along the
sunshades and break into one or more apartments, in a type of fire spread via the
façade. His opinion is that there is an undue risk of fire spread via the façade due to
the building being very tall and the resultant difficult evacuation and long complex
fire brigade intervention.
[91] He inspected the building on 6 May 2022 in order to determine the proximity of the
cladding to potential sources of ignition. While he criticised Mr Alexander for failing
to provide as built evidence to support his statement that ‘the sun blind arrangement
with metallic flashing have no exposed PE edges to enable ignition via the sheet’ he
did not record any instance in his observations that there were exposed PE edges.
[92] Mr Stratton observed that the curved profile of the sunshades means that in some
locations the sunshade is less than approximately 300mm from the external glazing of
the apartments.
33 Ibid, tab 5.
-- 19 of 29 --
20
The Joint Report
[93] Mr Stratton and Mr Alexander conferred on 4 April 2023 and provided a joint report.34
[94] The experts agree:
(a) that NCC BCA Volume 1: Class 2 to Class 9 Buildings, 2009 edition applies;
(b) that the sunblinds are aluminium panels containing a polyethylene core;
(c) that the sunblinds are attached to, but do not form part of the external wall;
(d) that BCA 2009 Specification C1.1 Clause 2.4 permitted combustible
attachments to external walls only if the requirements of Clause 2.4 were met.
[95] Mr Stratton says that the sunblinds constitute an undue risk of fire spread via the
facade of the building, due to:
(a) the polyethylene core of the ACPs being combustible;
(b) the sunblinds being installed near credible ignition sources including apartment
fires and air conditioning fires;
(c) the sunblinds spanning horizontally between groups of four or more sole-
occupancy units;
(d) the possibility fire spread between the sole-occupancy units via the sunblinds;
(e) fire spread between the sole-occupancy units being a risk to occupant life safety.
[96] Mr Alexander disagrees. In his opinion the only way a judgement can be made as to
whether or not the risk of fire spread via the facade of the building was undue, is to
examine the industry-wide practice at the time the building was approved by the
certifier. In his opinion the assessment must be made as at 2009 when the tower was
certified, putting aside the benefit of hindsight. With the benefit of hindsight, it is now
known:
(a) that there was a significant fire in the Lacrosse building in Melbourne in 2014;
(b) BCA 2009 Specification C1.1 Clause 2.4 was amended in 2016 by deleting
Clause 2.4(a)(iii), thus prohibiting the use of ACPs as attachments to external
walls;
(c) that there was a fire in the ACP cladding of the Grenfell Tower in London on
14 June 2017 which caused the deaths of 72 people;
(d) audits conducted after the Grenfell tragedy identified thousands of buildings
throughout Australia that were approved and constructed using ACPs before the
2016 amendment to the BCA.
[97] Mr Stratton and Mr Alexander disagree about the way a certifier would have gone
about assessing the risk posed by the sunblinds in 2011. Mr Stratton says a certifier
would have consulted a fire engineer who would have had to estimate the likelihood
of ignition and the consequence of fire spread. Mr Alexander says that there is no
point hypothesising as the ACPs were considered to comply with the deemed to satisfy
provisions of the BCA. Mr Stratton goes further and gives an opinion of what a
34 Ibid, tab 2.
-- 20 of 29 --
21
certifier might have done to address the risk, such as recommending the use of a non-
combustible material or recommending that the fire engineer prepare an alternative
solution. Mr Alexander disagrees. Perhaps, as submitted by counsel for the Body
Corporate they were at cross purposes due to the wording of the question put to them.
In any case, the question of what a certifier might, or might not, have done is not a
matter I need address.
[98] Mr Stratton set out issues that could have been addressed in assessing the risk posed
by the sunblinds:
(a) based on the design documents, such as credible sources of ignition near the
sunshades (air conditioning units and apartment fires) and the span of cladding
between multiple apartments;
(b) requests for fire test data from the manufacturer of the ACP system;
(c) difficulty of fire fighters accessing and controlling a facade fire anywhere in the
building due to the extreme height of the building;
(d) difficulty in evacuating occupants.
[99] In re-examination Mr Stratton said that when weighing the risk, he would have
addressed various scenarios to estimate possible outcomes in the event of a fire and
would have considered whether eliminating the hazard would have been a reasonable
course to adopt.
Testing undertaken by Ignis Labs
[100] In April and May 2023, at the request of Meriton, Ignis Labs Pty Ltd carried out large
scale tests to evaluate fire spread risk if an external sprinkler system (drenchers) were
to be installed on the Meriton tower. A copy of the report setting out the results of the
tests was provided to Mr Alexander who prepared a commentary on it.35 On 5 July
2023 the contractor was given leave to file the report.
[101] Ignis replicated the installation in a test assembly. Ignis carried out a bespoke test to
identify the risk of fire spread from one level to another including lateral spread. After
five minutes of testing by application of a 30MW sandbox burner under the ACP
material, the panel warped allowing flames to enter the internal part of the test system.
After 10 minutes the panel opened and exposed the core material to the fire. After
heating of the core material ignition occurred, contributing to the increase in flame
height. The increase in flaming did not reach a point to ignite the panel above. The
increased flaming lasted approximately three minutes before it decreased as the fuel
load was consumed. There was no lateral fire spread through the panel. Ignis
summarised the test result as indicating that when an uncontrolled fire event occurred
directly on the panel without automatic fire sprinklers, limited fire spread was likely
to occur.
[102] Mr Alexander considered that the result of the bespoke test simulating an external
ignition source debunked the view that an external fire source, such as a mis-fired
firework or external mechanical condenser unit, could cause undue fire spread, either
vertically or horizontally. Mr Alexander opined that the reasons the testing
demonstrated that undue fire spread did not occur included:
35 Ibid, tab 15.
-- 21 of 29 --
22
(a) that the edges of the sunblinds are enclosed by aluminium angles meaning that
the panel edge is not exposed to fire;
(b) that the arrangement with end caps and edge angles prevents fire from heating
both sides of the ACP;
(c) the height of the sunblinds restricts the fuel load thereby limiting the time at
which the flame projection is able to reach the panel above;
(d) that the fuel load was exhausted meaning that the panel effectively became non-
combustible, before fire spread occurred;
(e) the absence of the chimney effect because the panels are attached without a
cavity.
[103] Lateral fire spread did not occur as the fuel load was exhausted. He noted that in order
to carry out the test Ignis took steps that were unlikely to occur in reality such as
removing the bottom enclosing angle to expose the polyethylene core and bending the
sheet away from the frame in order to allow the panel to ignite quickly and applying
a heat source in excess of 600 degrees C directly below the panel for 10 minutes.
[104] In cross-examination Mr Alexander acknowledged that when polyethylene ignites it
drips, but opined that heat from below is needed for a fire to propagate on a building
facade. In the case of the Meriton tower (unlike Lacrosse and Grenfell) there is no
continuous source of heat due to the fact there is a gap of 2 metres to the slab above.
He also noted that the test results showed that the test sample passed the spread
classification and the debris flaming classification measurement.
Consideration
Nature of the evidence
[105] This is an administrative review of a decision of the Commission. The tribunal is not
bound by the rules of evidence but must observe the rules of natural justice. All parties
which might be affected by the outcome were joined to the proceedings and had an
opportunity to provide evidence and to cross-examine witnesses. If a party chose not
to test the evidence of a witness in cross-examination when it had the opportunity to
do so that is a matter for it. The weight to be given to unchallenged evidence is a
matter for me.
[106] It is common ground that the Body Corporate bears a practical burden of adducing
sufficient evidence to satisfy the tribunal that the relief sought should be granted. The
Commission and the contractor submitted that the Body Corporate failed to meet the
practical burden because Mr Stratton approached the matter as if it was for the
contractor or the Commission to satisfy him that the use of ACPs was satisfactory,
failing to appreciate that the obligation was on the Body Corporate to demonstrate that
it was unsatisfactory. The contractor submitted that the forensic approach adopted by
the Body Corporate, through Mr Stratton, in seeking to reverse the evidential onus,
created a lacuna that its evidence failed to fill.
[107] If these submissions were intended to suggest that Mr Stratton is the arbiter of fact,
they are obviously incorrect. While a party might have called an expert, every expert’s
role is to assist and advise the tribunal on issues in dispute within the expert’s area of
expertise. There is no lacuna in the evidence as I was assisted by evidence from each
expert called in the proceedings.
-- 22 of 29 --
23
[108] My task is to consider all the evidence to decide whether the decision of the
Commission should be confirmed or set aside. In a review application the tribunal
stands in the shoes of the Commission, but makes its decision de novo with the benefit
of all the evidence before it. I need not adopt one expert’s approach over another’s. I
can reach my conclusion on the basis of all the evidence before me. This requires
assessment of all the evidence in order to balance the likelihood of fire spread against
the gravity of the consequences of fire spread to decide whether the risk of retaining
the ACPs is undue.
Characteristics of Meriton tower
[109] Meriton tower:
(a) is a 79 storey (including basements) residential building occupied by people
who cannot be expected to be alert or familiar with the building and exits;
(b) has a smoke detection system and occupant warning system that will detect a
fire within the building and initiate evacuation;
(c) has a sprinkler system which will limit the potential for fire spread from the
façade to the interior of the building and limit the potential of fire originating
within the building spreading to the façade through openings;
(d) has no balconies;
(e) has no BBQ areas, space heaters or retail spaces close to the cladding;
(f) the cladding does not extend to the ground; and
(g) is located two blocks from the Roma Street fire station so fire brigade response
times will be relatively short.
[110] The sunshades on Meriton tower were intended to meet the performance requirements
prescribed by the 2009 BCA by complying with deemed to satisfy provisions.
Location of the material
[111] The sunshades do not form part of the external wall of the Meriton tower. They are
not cladding the building. They are attached to, but not part of the external wall.
[112] They are connected to each edge slab perimeter with a steel bracket arrangement.
There is an air gap between the sunshades and the external walls of the building. At
the closest point, the curved profile of the sunshades brings them less than
approximately 300mm from the external glazing of the apartments.
[113] The sunshades span horizontally between groups of four or more sole-occupancy
units.
[114] The sunshades are not vertically continuous. There is vertical separation of 2.4 metres
above a panel to the underside of the panel on the slab above.
[115] They are not located near BBQ areas, space heaters or retail spaces.
Are the ACPs combustible?
[116] I am satisfied that the ACPs are combustible for the reasons set out below.
[117] At the hearing no witness was challenged on their evidence regarding combustibility
of the ACPs. If the ACPs are not combustible they could not present any risk of fire
-- 23 of 29 --
24
spread. The ACPs would be no different to the vertical panels which are made of solid
aluminium which is not combustible.
[118] In its closing submissions on 25 October 2024 the contractor submitted that the Body
Corporate failed to adduce evidence that the ACPs satisfied the definition of ‘a
combustible material’ and that this was an evidential obstacle that could not be
overcome. This was a surprising submission considering the evidence provided by the
contractor and the 2009 BCA definition of combustible. Laboratory testing of samples
of the ACP from Meriton tower undertaken at the request of AED showed that the
core material of the ACPs was 95% polyethylene. Scientific analysis of 10 samples
from the ACPs from Meriton tower commissioned by Mr Stratton showed that the
material in the core of the samples ranged between 87% to 92% polyethylene +
Ethylene Vinyl-acetate co-polymers.
[119] When applied to part of a building, the BCA defines combustible to mean constructed
wholly, or in part, of combustible materials. The ACPs are part of a building. They
are constructed of non-combustible aluminium and combustible polyethylene.
[120] It was the evidence of Mr Alexander, the expert relied on by the contractor, that the
certifier was aware that the ACPs were combustible and that was the reason he
assessed the ACPs under Clause A2.4 of Spec C1 of 2009 BCA. It is also consistent
with Mr Stratton’s unchallenged opinion based on his experience as a fire engineer.
[121] If there was any doubt about the combustibility of the ACPs, it was dispelled by the
testing performed by Ignis, under instruction of Meriton, which replicated the
installation in a test assembly, which demonstrated the combustibility of the test
assembly, if not the actual panels on the Meriton tower.
[122] I note that the contractor did not seek to review the Commission’s direction to rectify
the cladding to the ground level fire isolated exits. That direction was given on the
basis that ‘the composite panels are flammable’.
[123] These proceedings are quite different from Strata Plan 92450. This is an
administrative review, not a civil proceeding. In these proceedings all affected parties
are represented and had the opportunity to make their case and challenge the
witnesses. The core of the ACPs has been tested and is 87% to 92% polyethylene +
Ethylene Vinyl-acetate co-polymers whereas the core of the cladding in the civil
proceedings was agreed to be between 35% and 40% polyethylene.
Fire safety features
[124] All the experts agree that the sprinkler system has a significant part to play in ensuring
safety of occupants of the building, regardless of the source of the fire. They also agree
that sprinkler systems are not 100% reliable. Even if the sprinkler systems were 100%
reliable it would not be possible to say that the safety of the occupants would be
assured in the event of a fire. The authors of the AED report estimate the reliability of
the sprinkler system between 95% and 99%. As Mr Stratton said, the chance that the
sprinkler system might not operate is a factor to be taken into account in any risk
assessment.
[125] I assume that the fact that the sprinkler system cannot ever be considered 100%
reliable was taken into account when the fire engineers certified the Meriton tower for
occupation.
-- 24 of 29 --
25
[126] The fact that the exposed surfaces of the ACPs are aluminium with metallic flashings
and that there is no exposed polyethylene is a feature that is relevant.
Possibility of fire spread
[127] There are two sources of potential fire spread to be considered: internal and external
ignition. I accept AED’s opinion that fire spread from an internal fire to the sunshades
is unlikely in the event of the successful operation of the sprinkler system and hence
that ignition from an external source is the most likely source of vertical fire spread.
However, I also accept Mr Stratton’s opinion that any risk assessment should include
the possibility of an internal fire breaking the glass and crossing the balcony to reach
the sunshades.
[128] I adopt Mr Alexander’s list of characteristics of the building that minimise the risk of
fire spread:
(a) the height of the ACPs limits the polyethylene fire load;
(b) the large open air gap between the ACPs prevents fire spread;
(c) the box section arrangement of the ACPs with enclosed edges limits the ability
to ignite an ACP; and
(d) the fact the ACPs are attachments, not cladding, means that a cavity is not
present to enable a chimney effect to occur.
[129] I also accept Mr Alexander’s opinion that the Ignis testing demonstrated no lateral fire
spread and no ignition of the panel above the test panel because:
(a) the edges of the sunblinds are enclosed by aluminium angles meaning that the
panel edge is not exposed to fire;
(b) the arrangement with end caps and edge angles prevented fire from heating both
sides of the ACP;
(c) the height of the sun blinds restricted the fuel load thereby limiting the time at
which the flame projection was able to reach the panel above;
(d) the fuel load was exhausted meaning that the panel effectively became non-
combustible, before fire spread occurred;
(e) the absence of the chimney effect because the panels are attached without a
cavity.
[130] I accept Mr Alexander’s opinion that fire is unlikely to spread from drips from above
as drips would not generate sufficient heat on the top of the panel below.
[131] Doing the best I can on the evidence before me, I have concluded that in order for an
internal fire to spread to a sunshade all the following would need to occur:
(a) the sprinkler system would have to fail (noting there is only a 5% chance this
would happen); and
(b) the glass would need to break; and
(c) the fire would have to cross the slab to a sunshade, (noting that the closest point
is 30cm); and
-- 25 of 29 --
26
(d) the aluminium angle or edge cap of the sunshade would have to have been
damaged with the consequence that the polyethylene core was no longer fully
encased by the aluminium; and
(e) the polyethylene core would need to ignite.
[132] In order for an external fire to ignite a sunshade the following would need to occur:
(a) there would have to be an external source of ignition; and
(b) the aluminium angle or edge cap of the sunshade would have to have been
damaged with the consequence that the polyethylene core was no longer fully
encased by the aluminium; and
(c) the polyethylene core would need to ignite.
[133] Whether the source of ignition was internal or external, the possibility of the fire
spreading horizontally or from one level to another is unlikely as demonstrated by the
Ignis testing which showed that the polyethylene fuel load will be consumed before
fire spread occurred.
[134] The possibility that a fire would spread is further reduced due to the location of the
sunshades at the slab edge, rather than as part of the external wall, which means there
will be no chimney effect.
An ‘undue risk’?
[135] The 2009 BCA does not define ‘undue risk’. There is no unusual or technical meaning
of the word ‘undue’. The 2009 BCA does not require that there be no risk. The 2009
BCA performance requirements require that a building have elements which will, to
the degree necessary, avoid the spread of fire to sole occupancy units and public
corridors. It goes without saying that some measure of risk must be acceptable.
[136] There is no evidence that it was common practice in the industry to undertake a
qualitative assessment of whether the attachment of ACPs as sunshades posed an
undue risk of fire spread via the facade of the building. It appears that the commonly
(but not universally) held industry view that ACPs complied with the deemed to
satisfy provisions of the BCA resulted in a common practice of not undertaking any
qualitative assessment of the risk.
[137] Industry-wide practice at the time the building was approved by the certifier has no
role to play in assessing the risk of fire spread via the facade of the building. It seems
that the certifier in this case adopted a common practice in the industry, certainly a
practice endorsed by Mr Igoe and Mr Alexander, of reliance on certificates provided
by suitably qualified professionals. It may be that Mr Hofstetter and others in the
industry did not consider the likely rate of fire spread, or the relevant safety features
of the Meriton tower, or the gravity of the consequences having regard to the nature
of the building because they believed that the panels would not burn.
[138] I note that Mr Stratton did not follow the practice of others in the industry. In his
opinion a qualitative assessment of the risk was required in order to comply with
General Requirement 2.4(iii) of the 2009 BCA. He is correct.
[139] Risk assessment requires a multifactorial approach. It is not based solely on likelihood
of fire spread, although that forms part of the consideration. The consequences of fire
-- 26 of 29 --
27
spread, in particular potential injury or loss of life of the occupants of the tower, must
be weighed in coming to a conclusion as to whether the risk is warranted.
[140] In considering whether there was an undue risk of fire spread I adopted the multi-
factorial test outlined by Henry J. I considered the circumstances and context in which
the ACPs were used. Factors considered included:
(a) the objective of Section C of the 2009 BCA to ensure safety of people from fire;
(b) location of the panels;
(c) fire safety features of the building;
(d) ignitability of the ACPs;
(e) the possibility of fire spread eventuating; and
(f) gravity of the risk.
[141] I am satisfied on the basis of the scenarios set out above that while it cannot be said
that there is no risk of fire spread, it can be said that the risk of fire spread via the
façade is not undue.
Gravity of the risk
[142] In reaching this conclusion I have not disregarded Mr Statton’s concerns about the
gravity of a fire in the Meriton tower. If there was a fire in the Meriton tower lives
might be lost. The fact that there are 70 storeys above ground occupied by many
residents in single occupancy units increases the number of potential casualties.
However, those are facts that pertain whether or not there are ACPs attached to the
building. I am not satisfied that the presence of the sunshades unduly increases the
risk otherwise facing the occupants of a very tall residential tower in the event of a
fire.
Would it be unfair to give the contractor a direction to rectify?
[143] If I am wrong and a direction to rectify should be given, I address the discretionary
considerations under section 72(5) of the QBCC Act; i.e. whether it would be unfair,
in the circumstances to give the contractor a direction to rectify.
Cost
[144] The Commission argues that the tribunal should give greater scrutiny than might
otherwise be the case to the exercise of the discretion given that the rectification costs
are substantial.
[145] I accept the contractor’s submission that the replacement of the sunshades over a
major proportion of the floors of this building will impose a substantial cost and,
undoubtedly, a far greater cost now than at the time the building was built. The only
evidence of the cost of rectification came from a cost estimate prepared by Sedgwick
Quantity Surveyors dated 17 August 2020 which estimated the cost of replacing the
cladding to be $3,787,167 plus GST.36 No doubt the cost would be even greater more
than four years after that estimate was given.
36 Ibid, tab 4, p 73.
-- 27 of 29 --
28
[146] While the examples of circumstances in which it would be unfair to give a direction
are just that, nonetheless cost of rectification is not one of the examples given in
section 72(5). There is no logical reason it would be. None of the parties referred to
any cases in which the cost of rectification was considered to be an indicium of
unfairness.
[147] Had drenchers been installed, as recommended by AED, it might have been unfair to
direct rectification. However, that is a moot point.
Prejudice to the contractor
[148] The contractor submits that it will suffer ‘enormous prejudice’ caused by the Body
Corporate’s dilatory conduct of this claim. It submits that it has effectively been
prevented from seeking contribution for the substantial costs of rectification from
other parties that were inevitably involved in the series of decisions giving rise to the
ACP’s being installed as sunshades on this building.
[149] The builder has always known that there were ACPs on the building. If it did not know
before it received the AED report in May 2019, it certainly knew then, that the ACPs
were combustible. The Body Corporate complained to the builder by letter dated 12
June 2019.37 Had the contractor wished to seek contribution from other parties it could
have filed proceedings in the Supreme Court making claims against the other parties
that it thought shared responsibility for the installation of the ACPs on the building.
The forensic choices made by the contractor are not a factor that should be taken into
account in considering whether it would be unfair, in the circumstances, to give the
contractor a direction to rectify.
Fairness generally
[150] I cannot accept the Commission’s submission that it would not be fair to give a
direction because when the work was carried out construction using ACP cladding
was common-place and considered acceptable. No matter how commonplace it might
have been, if the work did not comply with all the requirements of General
Requirement 2.4 of the 2009 BCA, not just some of them, the building work was
defective.
[151] As this is an administrative review, not a civil proceeding against the Registered
Professional Engineer Queensland who provided a Form 15 Compliance Certificate
for building design, or against the certifier, the fact that no allegation of negligence or
malfeasance was raised against either of them by the contractor is irrelevant.
[152] Changes made to the 2009 BCA in response to knowledge about the risk of ACP fire
following fires in Melbourne and London does not tend toward a conclusion that the
2009 BCA was insufficient and inadequate. General Requirement 2.4 was clear. It
included both objective and subjective considerations. Failure to consider the risk of
fire spread as required by General Requirement 2.4(iii) is not a reason to exercise the
discretion under section 72(5) of the QBCC Act.
Costs
[153] In this tribunal, unlike court proceedings, each party usually bears its own costs.38
Provision will be made in the orders for any party that considers the interests of justice
37 Ibid, tab 3, p 30.
38 QCAT Act s 100.
-- 28 of 29 --
29
require another party to pay all or a stated part of its costs to seek an order in that
regard.
[154] The recent judgment of the court of appeal in Health Ombudsman v du Toit39 provides
some guidance on the proper construction of ss 100 and 102 of the QCAT Act.
39 [2024] QCA 235.
-- 29 of 29 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2025/054