Cai v Homecorp Constructions Pty Ltd [2025] QCAT 49
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Cai v Homecorp Constructions Pty Ltd [2025] QCAT 49
PARTIES: WENMIN CAI
(applicant)
v
HOMECORP CONSTRUCTIONS PTY LTD
(respondent)
APPLICATION NO: BDL286-23
MATTER TYPE: Building matters
DELIVERED ON: 29 January 2025
HEARING DATE: On the papers
DECISION OF: Member Taylor
ORDERS: The applicant’s Application for Domestic Building
Dispute filed 4 September 2023 is dismissed.
CATCHWORDS: CONTRACTS – BUILDING ENGINEERING AND
RELATED CONTRACTS – OTHER MATTERS – where
a home owner entered into a building contract to construct a
house on land which at the time of contract was not a
registered lot – where the owner had paid a deposit under
that building contract – where the building contractor went
into liquidation before construction of the house
commenced – where the owner subsequently entered into a
new building contractor with a second contractor – where
the second contractor did not require payment as deposit
under the second building contract of the amount the owner
had paid as a deposit under the first building contract - where
the land was subject of a contract of purchase with a sunset
date attached to it – where the lot was not registered by the
sunset date resulting in the land sale contract being
terminated – where the second building contract was
subsequently terminated – where the homeowner sought a
refund from the second building contractor of the deposit
paid under the first building contract – where the owner
relied on terms of the second building contract as the
premise for the refund claim – where the owner’s action was
a renunciation of the second building contract – where the
second contractor accepted that action and terminated the
contract – where in the alternative the parties mutually
discharged the contract - whether the second building
contractor is liable to the owner for the amount of the deposit
paid under the first building contract
-- 1 of 14 --
2
Koompahtoo Local Aboriginal Land Council v Sanpine Pty
Ltd (2007) 233 CLR 115
Shevill v Builders Licensing Board (1982) 149 CLR 620
APPEARANCES &
REPRESENTATION:
This matter was heard and determined on the papers
pursuant to s 32 of the Queensland Civil and Administrative
Tribunal Act 2009 (Qld)
REASONS FOR DECISION
[1] There are four proceedings in this Tribunal that ran together, each premised on similar
facts and circumstances. Whilst the applicants are different, they all involve the same
respondent. This is one of them. The others are BDL 287-23 – Chen v Homecorp;
BDL 291-23 – Zhang & Anor v Homecorp; and BDL 293-23 – Luo v Homecorp.
[2] The material filed for each of the applicants in the four matters was effectively
identical in its format and content save only for the unique references therein to names
of the applicants, the relevant property addresses, and dates and details of relevant
contract and corresponding events.1 Given such, I infer it was prepared by the same
advisor to the applicants, and as will be apparent on reading of these reasons I infer
that each of the applicants relied on at least one set of communications by one of the
applicants with Homecorp during the course of events which ultimately led to these
four separate proceedings.
[3] By a Consent Direction made 22 January 2024 by this Tribunal, such following a
single Compulsory Conference involving the parties in all four matters, it was directed
that:
(a) these four matters would travel, heard, and be decided together; and
(b) unless otherwise ordered, the applications were to be determined on the papers,
without an oral hearing, based on the written evidence and submissions of the
parties.
[4] By a Direction given 2 May 2024, the second of those directions was confirmed.
[5] It is against that background that these four matters came before me for determination
on the papers. Whilst each of the matters was considered and decided by me
simultaneously with the other three, for simplicity in drafting and ease of
understanding by each of the applicants of my reasons for the decision I reached, I
prepared a separate set of reasons with the detail therein pertaining solely to the
relevant facts and circumstances in their matter only. Given what I said earlier about
the format and content of the parties’ respective material being the same, my reasoning
in each is essentially identical with the outcome being the same in each.
1 There was one specific difference in this matter to the Chen and Zhang matters. Whilst all applicants
asserted that Homecorp issued two receipts for each of the deposits paid, in Cai’s material only one
receipt copy was included. This required some discussion in dealing with the absence of that receipt
that does not appear in the other matters. Notwithstanding that difference, ultimately nothing turns on
it as between each of the four matters.
-- 2 of 14 --
3
Overview
[6] The applicant (Cai) paid a deposit to Privium Pty Ltd t/as Impact Homes (Privium)
of $16,286.40 for construction of a house on land Cai purchased ‘off the plan’, then
subsequently entered into a contract for purchase of the relevant piece of land.
[7] The land sale contract was subject to a sunset date. It provided that if the subdivision
plan was not registered by that date, and so the parcel of land on which the house was
to be built not effectively created as a separate titled lot, the land sale contract was
subject to termination.
[8] After Cai had that deposit, Privium went into liquidation. Cai asserts that another
builder, the respondent (Homecorp), took over the responsibility for construction of
the house and, in doing so, the deposit. But the house was never built because the lot
was not registered by the sunset date and so the land sale never occurred.
[9] Cai sought recovery from Homecorp of the deposit paid to Privium. Homecorp
refused to repay it. It asserted it never received payment of that deposit. A subsequent
application by Cai to the Queensland Building and Construction Commission under
the Home Warranty Insurance Scheme was unsuccessful. Cai thus commenced this
proceeding in this Tribunal for recovery of the $16,286.40 paid, such expressed as a
claim for an amount owing under the contract with Homecorp.
[10] For the reasons given herein Cai fails in this proceeding. On the facts as they appeared
in the material before this Tribunal, whilst there is a contractual entitlement to a refund
of a deposit paid under the building contract with Homecorp, such being in
circumstances where the land sale contract did not proceed to completion, the conduct
of the parties, particularly that of Cai, was such that the entitlement was not enlivened.
Thus ultimately it did not matter whether the deposit paid to Privium was received or
not by Homecorp and whether or not Homecorp might have been said to be liable for
its refund following the house construction not proceeding. Accordingly an order was
made dismissing Cai’s application to this Tribunal.
Relevant Facts and Circumstances
[11] On 8 June 2021, Cai entered into a contract with Privium to construct a new house
for the fixed price of $325,728 (the First Building Contract) on land at Lot 22
Devries Road Subdivision, Pallara, Qld (the Land).2
[12] On 21 June 2021, Cai paid a deposit of $16,286.40 to Privium under that contract, it
being 5% of the contract price (the First Deposit).3
[13] On 10 August 2021, Cai entered into a contract to purchase the Land (the Land
Contract).4 That contract contained the following relevant terms:
(a) a ‘Sunset Date’, specified therein as being the date which is eighteen (18)
months from the date of formation of the Land Contract:
2 Cai’s submissions filed 5 March 2024 – para 4. A copy of what is said to be the original building
contract is annexed to the Deed of Novation which I refer to later in these reasons.
3 Ibid para 4. What is said to be a ‘receipt’ for payment of the Deposit is contained in Attachment 2.
4 Ibid para 3 – Attachment 1.
-- 3 of 14 --
4
(b) the contract was subject to the Seller completing the development and
registering the Plan of Survey, thus creating a separate title for the relevant Lot,
on or before 5:00 pm on the Sunset Date; and
(c) in the event such was not achieved, either party may by written notice to the
other terminate the contract.
[14] On 26 October 2021, a Xinjie Liu of Privium sent an e-mail to Ausproud Real Estate5
to which was attached a letter shown as being on Privium letterhead dated 22 October
2021 addressed ‘To our valued client’. In that letter which the following statements
appear:6
We are writing to advise that we are in the final stages of a collaboration with a
fellow building and development company, Homecorp Constructions.
…
Whilst this is a collaboration, the brand that we will now be working under is
the Homecorp brand. For this reason, there is a need to novate your contract to
Homecorp Construction to ensure that all the works under the Contract are
undertaken in a timely manner.
[15] On a date which is not specified nor otherwise shown on any of the material filed, Cai
signed a Deed of Novation. Therein it named Cai as the ‘Owner’, Privium as the
‘Outgoing Contractor’, and Homecorp as the ‘Incoming Contractor’, expressing the
following in its recitals (the Deed of Novation):7
The Outgoing Contractor and the Owner entered into a Build Contract to
construct a dwelling on the Property.
At the request of the Outgoing Contractor, the Incoming Contract has agreed to
assume all of the rights, interests and obligations of the Outgoing Contractor
under the Build Contract to construct a dwelling on the Property.
By this Deed the parties wish to novate the Build Contract on the terms and
conditions of this Deed.
[16] On 17 November 2021, Privium entered into voluntary administration.8
5 I infer that Ausproud Real Estate acted as the agent / representative for each of the applicants in each
of the four proceedings I have dealt with as discussed in paragraphs [1] and [2] herein. Elsewhere in
these reasons and in the parties’ respective material there are references to A&J Realty, which acted
as agent / representative. It is unclear to me as to whether these are separate entities or are the same,
although from the manner of presentation of the material I infer they are the same. However even if I
am wrong about that nothing turns on it. In all relevant instances the entity acted as agent for the
applicant.
6 Cai’s submissions filed 5 March 2024 para 6 – Attachment 4.
7 Ibid para 6 – Attachment 5. The ‘Build Contract’ is defined therein as the document annexed to the
Deed, which on my reading of that document it is the First Building Contract. There is nothing in the
material before me which informs me as to the source of this Deed, nor the means by which, nor the
date on which, Cai received it.
8 Ibid – see Attachment 3.
-- 4 of 14 --
5
[17] On or about 15 December 2021, what is shown to be between one of the parties to
the four matters before me that I referred to earlier herein, but not Cai, and a
representative of Homecorp, an exchange of e-mails occurred:9
(a) in response to the following ‘question’ posed about a second building contract:
How about the deposit paid previously to privium (sic). We signed the deed
of novation before and this should be transferred into Homecorp.
(b) Homecorp responded with the following statement:
There is no need to pay the deposit again, Homecorp will issue an (sic)
receipt to you as evidence of payment.
[18] On 22 December 2021, Privium entered into liquidation.10
[19] Whilst Cai signed the Deed of Novation, it was not signed for either Privium or
Homecorp.
[20] On 18 January 2022, Cai and Homecorp entered into a building contract under which
Homecorp would construct the house which was the subject of the First Building
Contract, on the Land, but for a price of $402,728 (the Second Building Contract).11
[21] By way of a Tax Invoice dated 20 December 2021 Homecorp issued to Cai a claim
for payment of what is said to be a ‘Deposit’ of $20,136.40 against a contract priced
at $402,728, which I thus infer was a reference to the Second Building Contract,
relative to the Land.12
[22] On 25 January 2022, Cai paid $3,850 to Homecorp, such being the difference
between the $20,136.40 deposit invoiced and the $16,286.40 paid as the First Deposit
(the Second Deposit).13
[23] Cai asserts that on 22 February 2022 Homecorp issued receipts for both the First
Deposit and the Second Deposit.14
[24] On 13 February 2023, the Land Contract was terminated.15
9 Ibid para 10 – Attachment 7. I infer that this query was raised in response to the provision of a draft
version of what I refer to shortly herein as the Second Building Contract. There is nothing in the
material before me to inform me as to when and to whom a draft version was provided.
10 Ibid para 5 – Attachment 3.
11 Ibid para’s 7 and 8 – Attachment 6.
12 A copy of this Tax Invoice is included within Cai’s submissions as part of Attachment 6, it showing
as having been signed via DocSign by Cai together with other documents evidencing the Second
Building Contract. There is nothing contained in the material to explain why it is dated 20 December
2021, thus predating the date on which Privium entered into liquidation.
13 Cai’s submissions filed 5 March 2024 - para 11.
14 Ibid para’s 13 and 14.
15 Ibid para 15. In Cai’s Submissions the termination date is said to be 21 February 2023. The reference
to this date is confusing because the submission also refers to and annexes e-mails of 13 and 16
February 2023 which I infer emanated from the developer’s solicitor confirming termination by Cai
and giving effect to refund of $16,950, being the amount stated as being the deposit under the Land
Contract. I also infer that the error has emanated from the fact that, as I discussed it earlier, four
separate matters seemingly were prepared by the same advisor. The asserted date as referenced in the
submissions prepared in the Chen matter is 21 February 2023
-- 5 of 14 --
6
[25] On 20 February 2023, Cai signed a document entitled ‘Termination Letter’ addressed
solely as being ‘To Whom It May Concern’ in which the following statement appears
(the Termination Letter):16
While the Contract of Sale of Lot 22 Devries Road Subdivision,
PALLARAQLD (sic) 4110 has been terminated, I believe that Homecorp
Constructions Pty Ltd is unable to proceed the building contract between us.
Therefore, I would like to terminate the building contract between us and please
return the deposit to me.
[26] I infer that Cai sent the Termination Letter to, and it was received by, Homecorp, such
being because it is referred to in paragraph 2 of Homecorp’s statement of response,
and a copy of it is found at Annexure B, both accompanying Homecorp’s Response
and/or Counterapplication filed in this proceeding.
[27] On 8 June 2023, Homecorp issued a letter to Cai in which the following statements
appear:17
We confirm that the land contract is at an end and therefore our build contract
with you is unable to complete and is therefore terminated.
Referring to your request for a refund of the deposit monies, we advise that
whilst we did issue a receipt acknowledging that we received the deposit, we
regret to inform you that following an investigation of our records this receipt
was issued in error.
As we did not receive the deposit monies, unfortunately we are unable to issue
any refund of those monies.
[28] Notwithstanding this response, Cai asserts that Homecorp did refund the Balance
Deposit of $3,850.00.18
[29] On 4 September 2023, Cai commenced this proceeding claiming payment from
Homecorp of $16,286.40, expressed as a claim for ‘payment of an amount owing’. It
did not include a claim for interest or costs.19
[30] On 29 September 2023, Homecorp filed its response to the application denying
liability.20
The Issues
[31] As Cai’s case is advanced, it is not a claim in restitution for money had and received
nor in some way advanced reliant on the doctrine of unjust enrichment, nor is it a
claim for damages such which could include damages for breach of contract. As
expressed, it is a claim for ‘payment of an amount’. In Cai’s submissions, the relief
sought is expressed as ‘full refund of deposit in the amount of $16,286.40’. Thus, in
the circumstances as presented by Cai to this Tribunal, the claim can only be an
amount owing under the Second Building Contract. Accordingly, the sole issue is
whether Homecorp bears liability for that amount ‘under the contract’. Cai submits
that it does so according to the terms of the contract, namely Special Condition 7A.21
16 Ibid para 18.
17 Ibid para 19.
18 Ibid para 18.
19 Application for Domestic Building Dispute filed 4 September 2023.
20 Response and/or Counterapplication filed 29 September 2023.
21 Cai’s submissions para 20.
-- 6 of 14 --
7
Relevant Law22
[32] Under clause 19.1(a) of the General Conditions of Contract, Cai was required to pay
to Homecorp the deposit as stated in Schedule 2 of the contract document upon signing
of the contract (the Deposit). Under Schedule 2, the Deposit is stated to be $20,136.40.
[33] The Second Building Contract also contained the following relevant terms as Special
Conditions:
7A Subject to Land Contract
7A.1 This Condition applies if the Owner is not the registered owner of
the Site as at the Contract Date and is required to purchase the Site.
7A.2 The Contract is subject to and conditional upon the Owner entering
into a Land Contract contemporaneously with this Contract and the
Owner subsequently effective (sic) of that Land Contract.
…
7A.4 If condition 7A.2 is not satisfied, then the Contractor may
terminate the Contract by giving written notice to the owner and
any Deposit paid by the Owner shall be refunded to the Owner,
less any costs referenced under condition 5.5 of the Contract.
7B Subject to registration
7B.1 This Condition applies if the Site is a lot in an unregistered plan as
at the Contract date.
7B.2 This contract is conditional upon a plan being approved by any
authorising authority to create the Lot and Plan Type and Plan No.
(“Plan”) referenced in Item 4 and that Plan registering with Titles
Queensland (“Registration”) within 12 months from the date of
Contract.
7B.3 If Registration does not occur within 12 months from the date of
the Contract, then the Contractor may elect to terminate the
Contract, by giving written notice to the Owner that the Contract
is at an end and any Deposit moneys (sic) paid by the Owner shall
be refunded to the Owner, less any costs referenced under
condition 5.5 of the Contract.
7C Sunset Date
7C.1 Notwithstanding any other condition contained within the
Contract, if the Works do not commence within 12 months from
the date of the Contract for any reasons whatsoever, then the
Contractor may elect to terminate the Contract, by giving written
notice to the Owner that the Contract is at an end and any Deposit
moneys paid by the Owner shall be refunded to the Owner, less
any costs referenced under condition 5.5 of the Contract.
22 As I read the material before me and considered the Issue, the contract terms was the only relevant law
that I needed to refer to. No statutory provision was engaged in the manner in which the issue arose on
the material before this Tribunal.
-- 7 of 14 --
8
[34] Under the contract, the ‘Site’ is defined as “Lot 22 Devries Road Subdivision,
PALLARA QLD 4110”; and the ‘Land Contract’ is defined as being “the contract,
where required, entered into the Owner and the original owner of the Site for the sale
of the Site.”
[35] There are no other express terms of the contract, general or special, that provide for
any dealings with the Deposit. Nor is there any provision of the contract that refers to
the First Deposit.
The Evidence & Findings of Fact
[36] On the material before me, as I have referred to the relevant facts and circumstances,
I find the following chronology of facts proven:
(a) 8 June 2021 - The formation of the First Building Contract;
(b) 21 June 2021 - The payment by Cai to Privium of the First Deposit;
(c) 10 August 2021 - The formation of the Land Contract;
(d) 22 December 2021 – The liquidation of Privium;
(e) 18 January 2022 – The formation of the Second Building Contract;
(f) 25 January 2022 – The payment by Cai to Homecorp of the Second Deposit;
(g) 10 January 2023 - The effective ‘sunset date’ under the Land Contract.23
(h) 13 February 2023 – The termination of the Land Contract.
(i) 20 February 2023 – Cai sent to Homecorp the Termination Letter.
(j) 8 June 2023 – Homecorp confirmed with Cai that the Second Building Contract
was at an end.
[37] There is however some uncertainty and confusion within the material as to the extent
it may properly be said that Homecorp issued a receipt for the First Deposit. Cai states
that two receipts were issued, namely:24
(a) the first being Receipt Number 154601-685240 being for payment of $3,850
stating the payment date of 27 January 2022; and
(b) the second being Receipt Number 154601-685323 being for payment of
$16,286.40 said to state the payment date of 21 February 2022.
[38] I accept that the payment of $3,850 was paid as part of the overall deposit required
under the Second Building Contract. The receipt given expressly references the
number of the Tax Invoice issued 20 December 2021. However I cannot as readily
accept that the second receipt was issued as confirmation by Homecorp as having
received the First Deposit. This is because, despite the submission referring to what
is said to be copies of ‘two receipts’ attached, there is only a copy of the first receipt.
A copy of the second receipt does not appear anywhere within Cai’s material filed in
this proceeding. Nor does Homecorp provide a copy or otherwise admit to its
existence. That being so, I am left to deal with the issue by way of inference to the
23 This is calculated as the date being 18 months from the date of the Land Contract, such being as per
the terms of the Land Contract as I noted it earlier herein.
24 Cai’s Submissions para 14.
-- 8 of 14 --
9
extent such may be possible. In that regard I note the following as it appears in the
material filed.
[39] Firstly, there is Cai’s reference to, and apparent reliance on, an exchange of e-mails
on 15 December 2021 in which it is said that Homecorp stated there was no need to
pay the deposit again, and that it would issue a receipt as evidence of payment.
[40] Secondly, in its Response filed in this proceeding, Homecorp states:25
The Deposit was paid to Privium. It was never received by the Respondent.
The Respondent was prepared to credit the Deposit to the Contract Price only if
the Contract proceeded and was preformed (sic) by both parties in full.
A receipt for the 5% Deposit was issued to the Applicant, however, it was issued
in error. The Deposit credit was only to apply if and when the Land Contract
settled and the builder commenced under the terms of the Contract.
[41] It also made this statement in its ‘Statement of Evidence’ filed 25 March 2024 in this
proceeding:
Homecorp purchased a range of assets from Privium through the Liquidation
process including vehicles, IP (house designs and plans) and a copy and the
right to use the Privium in-house designed CMS called iHub.
Homecorp did not novate contracts or receive any work in progress or deposit
payment from Privium or any related entities, or from the Administrator or
Liquidator. …
Homecorp offered many of Privium’s clients the opportunity to have their home
built by Homecorp now that Privium was in Administration, including waving
(sic) the full deposit or providing a discount to the value of the deposit should a
successful build occur. This was initially through a novation process that was
then replaced by a new build offer.
The applicant chose to enter into a new build contract with Homecorp. …
Homecorp received a notional deposit of circa 0.5% being $3,850 from the
Applicant, noting the Applicant had previously paid a 5% deposit to Privium …
Notwithstanding that Homecorp never received any deposit moneys from
Privium or its Administrators, in error, Homecorp issue a receipt for Privium's
5% deposit under the Contract. This was a clear clerical error, picked up in
reconciliation and probably due to Homecorp now using Privium's software.
[42] There is also an Affidavit of Mr Ryan Hammon sworn 18 January 2024 filed by
Homecorp wherein he states he is Homecorp’s Financial Controller and in that
position says that Homecorp did not at any time receive any deposit or progress
payments from Privium or its Administrators or Liquidators.
[43] Thirdly, Homecorp states in its material, as I just referred to it, that it effectively
waived the requirement for the full amount of the Deposit to the extent of the amount
of the First Deposit, or would provide a discount to the value of the First Deposit,
should a successful build occur. But this is a bare assertion. There is nothing contained
in any of the material before me, particularly that from Homecorp, to corroborate such
25 As I understand this statement, the ‘Contract’ to which Homecorp refers herein is the Second Building
Contract.
-- 9 of 14 --
10
a statement. It may very well have been something communicated at some time during
the changeover from Privium to Homecorp, such being a fact I do not make any
positive finding about because I need not do so. The relevant fact is that it was not a
term of the Second Building Contract, such being where it should have been expressed
to have had contractual effect and thus able to relied on by Homecorp.
[44] The exchange of e-mails on 15 December 2021 does not assist Cai. As it is contained
in Cai’s submissions, it is not one raised by or sent in response to Cai, but rather
appears to have been raised by other persons in the same circumstances as Cai was in,
namely a Xialoa Zhang and Pheng Zu in terms of Lot 11 Devries Road, such which is
the subject of proceeding BDL 291-23. But other than that, on the basis of the
remainder of the material to which I have referred I find as fact:
(a) Homecorp did issue a receipt to Cai for the amount of the First Deposit,
seemingly treating it as part satisfaction of the entire Deposit required to be paid
to it under the Second Building Contract, but in circumstances that it had not,
and did not ultimately receive the amount of the First Deposit; but
(b) at its highest, by its conduct Homecorp represented to Cai that: (the Homecorp
Representation)
(i) it did not require full payment of the Deposit under the Second Building
Contract to the extent Cai had already paid the First Deposit under the
First Building Contract; and
(ii) in conjunction with Cai’s payment of the Second Deposit it recognised
that payment of the full deposit under the Second Building Contract as
having been effected, the balance satisfied by the amount of the First
Deposit having been paid.
[45] Thus, the question that arises is the extent to which, if at all, Homecorp could be held
liable to Cai for refund of the amount of the First Deposit in the event the Second
Building Contract did not proceed, and in terms of the contractual burden to refund
the full amount of the Deposit under the Second Building Contract, such incorporating
the amount paid as the First Deposit, in circumstances where the Land Contract did
not complete.
Discussion of the Issue
[46] Before embarking on discussion of the material before me in addressing that question
to the extent necessary to explain the decision I have reached in this proceeding, for
completeness and the parties’ benefit I make this short observation about the Deed of
Novation. Whilst I can readily accept as a fact that the Deed was provided, and that
Cai signed it, ultimately it was not a concluded agreement and thus is irrelevant in this
proceeding. Given that which I have said at paragraphs [14] to [19] herein, I infer that
upon administration and then subsequent liquidation of Privium the step of novating
the First Building Contract was either abandoned by Homecorp or otherwise,
dependant on the relevant timeline, became impossible to implement. That being so,
the express legal relationship between Cai and Homecorp is that found in the Second
Building Contract and accordingly it was the terms of the Second Building Contract
that was the relevant material.
-- 10 of 14 --
11
[47] That being said, it seemed to me that the best place to start this discussion was with
the following statement by Homecorp:26
The Applicant had the right and opportunity to claim on the QLD (sic) Home
Warranty Scheme insurance within 3 months of the Privium contract
cancellation due to Privium being in voluntary administration. The final date
for this claim would have been circa 17 February 2022. This was the correct
avenue to claim the deposits (sic) and the Applicants (sic) chose not to claim
against these insurances. It was the Applicants (sic) responsibility or the
responsibility of their representative to seek the appropriate advice at that time
and to act.
[48] Whilst there is some error in the manner of expression of this statement, such as
cancellation of the Privium contract due to voluntary administration,27 the essence of
the statement is generally correct. Upon the termination of the First Building Contract
as a result of Privium’s liquidation, it was open for Cai to have claimed under the
Home Warranty Insurance Scheme for loss of the deposit paid to Privium. But that
step was not taken. The question is why ?
[49] Before answering that question, whilst not expressed by either party in the material
before this Tribunal, it may be observed that had Cai taken such a step and
successfully recovered the amount of the First Deposit it should be expected that
Homecorp would have required payment of the full amount of the Deposit under the
Second Building Contract such which would have resulted in Cai being required to
pay that amount to Homecorp in satisfaction of the requirement for the deposit
thereunder, and so upon termination of the Land Sale Contract in turn Cai being in the
same circumstances as have given rise to this proceeding. But such is merely
speculative discussion and there is no certainty that had that occurred Homecorp
might not have, or might have, refunded the full amount noting it readily refunded the
amount of the Second Deposit.28
[50] In my opinion, the answer to this question is found in the content of Cai’s application
to this Tribunal wherein the following statements appear:29
I signed a building contract with Privium Pty Ltd trading as Impact Homes on
8 June 2021, but on 22 December 2021, Privium was placed into liquidation. I
was then informed that my case would be taken over by Homecorp. Initially, I
received a Novation Deed to sign, but later, Homecorp didn’t sign that
document back (sic). Instead, they offered a new building contract with a higher
price, and asked me to sign if I agreed.
On 18 January 2022, I signed that contract and was instructed that there is no
need to pay the deposit again, Homecorp Pty Ltd will issue a receipt to me as
evidence of payment. I just needed to directly pay the difference in 5% deposits
26 Homecorp’s Statement of Evidence filed 25 March 2024 – para 6.
27 There is no premise upon which the First Building Contract could have been terminated upon Privium
entering voluntary administration. It is only at the time of liquidation that a right of termination arises
– see clause 27.1 of the General Conditions of Contract.
28 This is so even though Homecorp asserts it did so on an ex-gratia basis. See Homecorp’s Statement of
Evidence filed 25 March 2024 - para 17.
29 Application filed 4 September 2023, Part C Q2. It is not in issue that Homecorp refunded the amount
of the Second Deposit, thus what is pressed is solely the amount of the First Deposit as being the
‘amount owing’.
-- 11 of 14 --
12
between the building prices of Privium Pty Ltd trading as Impact Homes and
Homecorp Pty Ltd.
They assured us (sic) that they would provide a receipt for this 5% deposit
payment.
…
Throughout the entire process, I followed instructions from Homecorp Pty Ltd
and paid the deposits as required by them. They assured me that I didn’t need
to make additional deposit payments and that they would provide receipts.
Given these circumstances, I believe that they should refund the amount to me.
[51] Given what Cai stated in the Application, it seems to me that Cai relied on the
Homecorp Representation and so did not pursue recovery of the First Deposit under
the Home Warranty Scheme. It may be that such gives rise to some form of estoppel
which might have given some support to Cai’s efforts to recover the amount of the
First Deposit had such been a premise relied on by Cai in this proceeding.
[52] Alternatively it might be that it enlivens issues under the Australian Consumer Law
that might equally have given some support, once again had it been relied on by Cai.
[53] I do not express any opinion on whether either or both of these would be so, nor make
any findings about those legal concepts. This is because Cai did not advance either of
them as a premise for the relief sought in this proceeding. The relief pressed is for
payment of what is said to be an ‘amount owing’, which as I discussed earlier can
only be read as an amount owing under the Second Building Contract. To that end,
Cai pressed for relief reliant on Special Condition 7A of the Second Building Contract
terms as the basis for the asserted entitlement to the full deposit being refunded.30
[54] Special Condition 7A provides Cai, as the home owner under the contract, an
entitlement to refund of the Deposit only where the contract is terminated by
Homecorp. A similar entitlement is found in Special Conditions 7B and 7C. That
being so, the next relevant question is - did Homecorp terminate the Second Building
Contract ?
[55] As I noted it earlier herein, I found as fact that:
(a) on 20 February 2023, Cai sent to Homecorp the Termination Letter; and
(b) on 8 June 2023, Homecorp confirmed with Cai that the Second Building
Contract was at an end.
[56] Homecorp described the former as Cai having “asked to terminate the Homecorp
Contracts (sic)”.31 The manner in which Cai described it is a “contract termination”.32
[57] On the basis of these facts, and those short descriptions given to them by the parties
respectively, in my opinion it was Cai who sought to effectively terminate the Second
Building Contract, such which was accepted by Homecorp. In my opinion, whilst not
described as such by Homecorp, Cai’s action was a renunciation (which may also be
30 Cai’s Submissions para’s 16 and 20.
31 Homecorp’s Statement of Evidence filed 25 March 2024 – para 13.
32 Cai’s Submissions para 18.
-- 12 of 14 --
13
referred to as a repudiation) by Cai of the Second Building Contract.33 This is so given
the absence of:
(a) any express provision in the contract terms to enable such a termination by the
owner; and
(b) Homecorp not acting in any manner that could be said to have been a substantial
breach of the contract or otherwise a repudiation of it such as could have entitled
Cai to terminate the contract under common law.
[58] Accordingly, it was open to Homecorp to accept the renunciation and terminate the
contract, such being what it did by its conduct in sending the letter of 8 June 2023.
[59] Alternatively, if I am wrong in that conclusion on the meaning to be attributed to the
exchange of those communications between the parties, in my opinion these facts
demonstrate that the parties mutually discharged the Second Building Contract as a
result of it effectively being frustrated once the Land Contract had been terminated,
and as such the Site under the contract did not exist such as to permit the house to be
constructed.
[60] All that being said, it leads to the conclusions as I discuss them here.
Conclusions
[61] This is where Cai’s case has gone wrong.
[62] As I noted it in paragraph [51] herein, the circumstances as they appeared on the
material before me might give rise to issues in terms of an estoppel or an Australian
Consumer Law argument in which a liability might be shown to have arisen on
Homecorp for the loss Cai has undoubtedly suffered to the extent of the amount of the
First Deposit paid. But none of this forms part of Cai’s case in this proceeding. The
case can only be decided on the basis as advanced, that being what is said to be a claim
for an entitlement said to be found under the Second Building Contract. But no such
entitlement has been enlivened on the facts as they are presented to this Tribunal.
[63] For it to have arisen, it required Homecorp to have unilaterally terminated the contract.
Cai’s issuing of the ‘Termination Letter’ was something not provided for under the
Second Building Contract nor otherwise required. The express terms of the contract
did not provide any mechanism for the home owner to terminate the contract upon
expiry of the sunset date under the Land Contract, and then in turn become entitled to
refund of the deposit paid. The contract terms, and in particular Special Condition 7A,
it being the premise for Cai’s case and the relief pressed for in this Tribunal, but as
well as Special Conditions 7B and 7C, required Homecorp to have elected to terminate
the contract before the burden was cast upon it to refund the deposit. That is, it
provided for a unilateral action by Homecorp, not a bilateral action of mutual
discharge instigated by Cai.
[64] Such might be said to be an unfair, and to some degree an unworkable, arrangement.
The question that arises is – what if Homecorp never exercised the election open to it
to terminate the contract ? This would mean that the Second Building Contract simply
sat there but unable to be performed in terms of having a house constructed because
there was no ‘Site’ in existence unless the parties agreed by way of a variation to the
33 Shevill v Builders Licensing Board (1982) 149 CLR 620 at 625-626. See also Koompahtoo Local
Aboriginal Land Council v Sanpine Pty Ltd (2007) 233 CLR 115 at 135;[44].
-- 13 of 14 --
14
contract to change the Site, something not required by way of any express term and
so simply left to the parties, separate but coinciding action. The answer is that the
contract could thus only be treated as being legally frustrated, such meaning it could
never be performed the way in which it was intended. But neither the contract terms,
nor the common law, then provides for the owner to be entitled to a refund of the
deposit paid reliant solely on the doctrine of frustration.
[65] In all respects, it must be observed that the terms of the Second Building Contract
were not drafted favouring Cai or even balanced between the parties in that regard.
One might say that Cai had either failed to take advice about the contract before
signing it, or had been poorly to badly advised about it. It may also be observed that
Cai could have readily required a Special Condition to be inserted in the Second
Building Contract, or a redrafting of Special Conditions 7A, 7B, and 7C, to provide a
mechanism for either party to have terminated the contract. Such is the mechanism as
it appears in the Land Contract. But that was not provided for, and there is no basis
for such a term to be implied into the contract.34 Accordingly the express terms of the
contract must be the terms under which the issue is resolved.
[66] Given all I have discussed herein, there is no entitlement under the Second Building
Contract for Cai to be refunded the amount of the Deposit under the Second Building
Contract, and thus in any way become entitled to the amount paid as the First Deposit
as an amount owing under the Second Building Contract. Such is an unfortunate
outcome and one which has resulted solely from Cai’s own actions, possibly haven
arisen from poor or incorrect advice received. Accordingly, ultimately it does not
matter whether any such refund, if it was to have been made, should have included
the First Deposit amount. There is only one possible outcome in this proceeding, that
being the application must be dismissed. An order was made to that effect.
34 I pause here to observe that Cai did not seek, within this proceeding, to have such a term implied.
-- 14 of 14 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2025/049