Dixonbuild Pty Ltd v Queensland Building and Construction Commission [2025] QCATA 78
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Dixonbuild Pty Ltd v Queensland Building and
Construction Commission [2025] QCATA 78
PARTIES: DIXONBUILD PTY LTD
(applicant/appellant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(respondent)
APPLICATION NO/S: APL185-23
ORIGINATING
APPLICATION NO/S:
GAR136-21
MATTER TYPE: Appeals
DELIVERED ON: 29 August 2025
HEARING DATE: 1 May 2025
HEARD AT: Brisbane
DECISION OF: Senior Member Traves
ORDERS: The application for leave to appeal, insofar as leave
is required, is refused.
The appeal is otherwise dismissed.
CATCHWORDS: ADMINISTRATIVE LAW – ADMINISTRATIVE
TRIBUNALS – QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
APPEAL – GENERAL PRINCIPLES – RIGHT OF
APPEAL – WHEN APPEAL LIES – ERROR OF LAW
AND FACT
PROFESSIONS AND TRADES – BUILDERS –
STATUTORY POWER TO REQUIRE RECTIFICATION
OF DEFECTIVE OR INCOMPLETE BUILDING WORK
– where tribunal confirmed decision to issue a direction to
rectify in relation to a leaking shower – where multiple
grounds of appeal alleging errors of mixed law and fact –
whether leave to appeal should be given – if leave granted,
whether appeal should be allowed – if appeal allowed, what
orders should be made
Queensland Building and Construction Commission Act
1991 (Qld), s 71J, s 72
-- 1 of 17 --
2
Queensland Civil and Administrative Tribunal Act 2009
(Qld), s 28, s 142, s 147
Bitossi v Queensland Building and Construction
Commission [2021] QCAT 131
Harrison and Anor v Meehan [2016] QCATA 197
Stuart v Queensland Building and Construction
Commission [2016] QCATA 135
Young t/as LK & HM Young v Queensland Building and
Construction Commission [2021] QCAT 8
APPEARANCES &
REPRESENTATION:
Applicant: Mr CH Matthews, counsel, instructed by CDI Lawyers Pty
Ltd
Respondent: Ms AR Hewish, HWL Ebsworth
REASONS FOR DECISION
[1] This is an application for leave to appeal and, if granted, an appeal, of a decision
confirming a decision of the Queensland Building and Construction Commission
(‘QBCC’) to issue a direction to rectify to Dixonbuild Pty Ltd.
[2] The Direction to Rectify was in the following terms:
Water penetration is occurring from the main bathroom shower recess as the
water membrane has failed to the base, resulting in water penetration to the
adjacent bedroom wardrobe.
- Pertains to item 1 on the QBCC complaint form.
Leave to appeal
[3] The decision is appealed on grounds that errors of fact and law were made in the
decision. An appeal on a question of fact or a question of mixed law and fact may only
be made with leave of the appeal tribunal.1 If leave is obtained, the appeal must be
decided by way of rehearing.2
[4] The appeal tribunal in Harrison v Meehan3 set out the criteria to be applied in
determining whether leave should be granted:
The relevant principles to be applied in determining whether to grant leave to
appeal are well established: Is there a reasonably arguable case of error in the
primary decision; Is there a reasonable prospect that the applicant will obtain
substantive relief; Is leave necessary to correct a substantial injustice to the
applicant caused by some error; Is there a question of general importance upon
which further argument, and a decision of the appellate court or tribunal, would
be to the public advantage.4
1 Queensland Civil and Administrative Tribunal Act 2009 (Qld) , s 142(3)(b) (‘QCAT Act’).
2 QCAT Act, s 147(2).
3 [2016] QCATA 197.
4 Ibid, [8].
-- 2 of 17 --
3
[5] The applicant submits that leave should be granted for the following reasons:
(a) errors of fact and law were made in the decision;
(b) it would be manifestly unfair and a breach of the applicant’s natural justice to
allow a Direction to Rectify to remain on the applicant’s licence after the alleged
defect was remedied and the test undertaken to determine the alleged defect was
inappropriate;
(c) to correct a substantial injustice to the applicant caused by the decision; and
(d) if the decision is found to be wrong, substantial injustice would result if leave
were refused.
[6] The respondent submits that none of the grounds relied upon by the applicant
demonstrate error and that the appeal should be dismissed. Other than referencing the
principles to be applied in determining leave, the respondent did not specifically
address whether leave should be granted.
Background
[7] The main ground of appeal relates to whether the Member erred in properly
considering the unfairness in issuing the DTR to the builder. The factual context is
relevant to this ground. For that reason, it is appropriate to set out a brief chronology
of events:
(a) On 11 September 2020 the Owner’s property agent (Amanda Onderstal of
Sunshine Coast Real Estate Partners) emailed the Owner (Jon Meldon) a copy
of a Routine Inspection Report. Her cover email said:
Please see attached the latest routine report for your records
Ensure you read the body of the report for any maintenance that may have been
reported and needs to be address –
NOTE – MAIN SHOWER LEAKING INTO BEDROOM WALL/ROBE – I
have arranged a quote to repair this you may want to get onto your builder again
– last time it was the bath tub being an issue into the other room.
The attached report said, relevantly:
The only issue on the day reported is the main shower is leaking into the robe
in the back room – I have asked tenant to ensure they do not use this shower till
it is fixed and to use the en suite shower….There were no other maintenance
issues observed or reported on the day of the inspection.
(b) Mr Meldon sent that email and report to Dixon the same day.
(c) On 24 September 2020 Dixon maintenance undertook an inspection of the main
bathroom shower at which time Dixon’s worker ‘pulled massive clump of hair
+ debris from waste’, re-siliconed the body of the tap and pressure tested the
shower head. In relation to the shower base the report noted ‘filled base, water
did not drop, but carpet was wet.’5
5 Appeal Book, 481.
-- 3 of 17 --
4
(d) On 28 September 2020 Mr Meldon lodged a written Complaint with the QBCC
in these terms:
Complaint Item
List
Location Description Date first noticed
1 En suite water leaking
from ensuite
shower through
wall into walk in
robe damaging
carpet underlay,
wall sheeting and
house frame
11/09/2020
2 Bathroom water leaking
from bath drain,
possibly shower
11/09/2020
(e) On 29 September 2020 Dixon emailed the property agent to let her know Dixon
Maintenance (Johnathan) attended and performed a shower leak test but was
unable to find a leak and had advised ‘carpet in bedroom is only wet when
shower is running and that best for a plumber to attend for further assistance’
to which Dixon replied ‘their maintenance department has already done’.
(f) On 19 October 2020 the property manager emailed Dixon to follow up on the
job and asked if ‘it has been fixed’?
(g) On 20 October 2020 Dixon responded to the property manager saying:
our plumber has made multiple attempts to arrange access with the Tenant
but had no response. He has left voicemails, sent messages and even tried
showing up to the house but no one was present. To have this resolved as
soon as possible are you able to issue an entry notice and advise a date with
48 hours notice so we can book the plumber in?
(h) On 23 October 2020 the plumbing contractor (JLF Plumbing Queensland Pty
Ltd) attended the property to investigate the leak in the main bathroom shower
recess.
(i) On 27 October 2020 Mr Meldon emailed the property agent (copying in Dixon)
as follows:
Plumber attended last Friday, tests conducted and all clear. Tenant can use
the shower but keep an eye out for any further issues.
(j) On 19 November 2020 Dixon forwarded Mr Meldon’s email of 27 October 2020
to Dixon Maintenance.
(k) On 19 November 2020 JLF Plumbing emailed Dixon Maintenance to report that
on 23 October 2020 he put a new gauge on the shower outlet, conducted a
hydrostatic test for 10 minutes with no pressure loss and that no leak in the
plumbing had been found. He said that he then ‘ran the shower by itself to
stimulate a normal operation and found no leak. The Dixon Maintenance person
-- 4 of 17 --
5
was there earlier, and he seemed to have fixed the issue. From our assessment,
the plumbing is not the cause of the leak.’
(l) On 24 November 2020 Dixon emailed Mr Meldon saying she had tried calling
him again that morning to discuss his QBCC Complaint and asked him to return
her call as she has not had a response from him by phone or by email.
(m) On 24 November 2020 Dixon emailed the property agent (copying in Matthew
Buckner of QBCC and Mr Meldon) as follows:
Thank you for your time on the phone today. As discussed, please confirm
per your routine inspection dated 11/9/2020 there was no issue to be found
with the en suite shower (per attached inspection report).
Please also confirm that we have attended and completed repairs to the
leaking main bathroom shower & have not heard from Tenant/real
estate/owner of further issues
(n) On 24 November 2020 the property agent emailed Dixon and says:
As discussed I have another inspection coming up at the house on the
09/12/2020 – I will speak to the tenant and inspect the area that was effected
by the leak on this day and report to you and advise if there is no further
issues
(o) Almost immediately, Dixon emailed the property agent back (copying in the
QBCC and Mr Meldon) asking her to:
Please confirm per my email that there was no issue with the ensuite shower,
thanks
(p) The property agent replied the same day (copying in the QBCC and Mr Meldon)
and reports:
There was no issue with the ensuite shower, it was the main shower recently
and the bath tub leaking back in November 2019
(q) On 24 November 2020 Dixon emailed the QBCC (copying Mr Meldon) as
follows:
I have tried contacting the owner with no success, I have however spoken with
the real estate who confirms the ensuite did not have any issues, I have also
attached the real estate’s inspection report confirming this.
I have also attached the owner’s email dated 27/10/2020 confirming the
plumber also attended and tested the shower and advised the shower can now
be used, we have not heard from the tenant/owner/real estate of any further
issues. I have also attached the Plumbers report/confirmation email.
Please also find attached a phot of hair & debris found in the main bathroom
shower drain, this is part of homeowner/occupants maintenance and upkeep.
Please confirm this matter can now be closed.
(r) On 26 November 2020 the QBCC emailed Dixon:
The matter cannot be closed before our full assessment of the case is completed.
This includes my initial assessment (which has been completed) and the
technical assessment by a building inspector. The building inspector may also
decide to go to the property and inspect the complaint items.
-- 5 of 17 --
6
(s) On 9 December 2020 the property agent undertook an inspection of the
property.
(t) On 14 December 2020 the property agent emailed Dixon stating the inspection
(on 9/12/2020) went well, and ‘leak seems to be fixed as no further reports from
the tenant’.
(u) On 14 January 2021 the QBCC sent Dixon a formal Notice that inspection of
the work outlined in the attached complaint would be undertaken. The complaint
was the complaint initially lodged by Mr Meldon (see above at [7](d)].
(v) On 23 January JDK plumber attended the property.
(w) On 3 February 2021 Mr Hayes of the QBCC attended the property to inspect the
items of Complaint. Mr Meldon first took Mr Hayes to the first item of
complaint which, although referred to as the ensuite in the complaint form, was
actually the shower recess in the main bathroom. Mr Hayes said the tenant
confirmed they had been using the main bathroom shower since the trade
contractor had attended the property. Mr Hayes did a hydrostatic test which
showed water leaking to the adjoining bedroom. Mr Meldon recalled Mr
Reynolds from Dixon calling someone on his mobile and saying – ‘we’ve got
to fix this’.
The second item of the complaint was identified by the QBCC as having been
rectified.
(x) On 4 February 2021 Mr Hayes produced his Initial Inspection Report which
concluded that there was water penetration from the main bathroom shower
recess to the adjacent bedroom wardrobe caused by a failure of the waterproof
membrane to the base of the shower.
(y) On 4 February 2021 the QBCC caused a Direction to Rectify to be issued to
Dixon in respect of the main bathroom defect.
Grounds of appeal
[8] The applicant relies on the following grounds. I have taken into account the
comprehensive submissions of both parties which have been of considerable
assistance. I do not propose to set out those submissions in detail.
Ground One: The Member erred in fact in paragraphs 67, 71 and 72 of the Reasons
by concluding that it was not unfair to issue a DTR in the circumstances
[9] In summary, Dixon submits that it is unfair to issue a DTR because:
(a) On a proper interpretation of ss 71 J and 72 of the Queensland Building and
Construction Commission Act 1991 (Qld) (‘QBCC Act’), the QBCC cannot
issue a DTR in respect of work that has not first been the subject of written
complaint by an owner. If this were not the case, the builder would be denied
an opportunity to rectify the allegedly defective work prior to the issue of a
DTR.
(b) The incorrect naming of the bathroom on the QBCC complaint form misled the
applicant into believing there was no defect in the main bathroom shower until
it was disavowed of this on the day of the QBCC’s inspection. The DTR was
-- 6 of 17 --
7
issued the next day which gave Dixon no time to rectify the issue prior to the
issue of the DTR.
(c) The tenants at the property did not complain further about leaks after the main
bathroom shower waste was cleared and no water was allowed to pond.
[10] The QBCC submits:
(a) To the extent such a ‘finding’ was made by the Member they were supported by
the evidence put before the Tribunal, including:
(i) The evidence of Mr Meldon which was accepted by the Member;
(ii) The failure by the applicant to call an employee, who was there at the
relevant time, to give evidence that there was at any time any belief that
any shower other than the main bathroom shower was involved in the
leaking;
(iii) The evidence of Mr Bartholomaeus that a representative of the applicant
had attended the property around October 2020 and ‘removed hair and
debris from the drain of the main bathroom shower’;
(iv) The evidence that the applicant had been given previous opportunities to
repair the defect before the DTR was issued and had instructed it’s
employees or agents to remove tiles and re-waterproof the shower base;
(b) The applicant had an opportunity to lead evidence from an employee who was
present at the relevant inspection, but did not do so;
(c) The applicant did not correct Mr Bartholomaeus’ evidence at hearing, and
further Mr Bartholomaeus confirmed in cross-examination that the applicant
was made aware that there was a leak in the main bathroom shower on about 11
September 2020;6
(d) It would be inappropriate for the Appeal Tribunal to have regard to these matters
in circumstances where they were considered and determined by the Member
when the decision was made, and the applicant did not lead any evidence to
support its position.
Consideration: Ground One
[11] Section 71J(1) relevantly provides:
A consumer may ask the commission to give a direction to rectify building work
the consumer considers is defective or incomplete.
[12] Section 72 relevantly provides:
72 Power to require rectification of building work and remediation of
consequential damage
(1) This section applies if the commission is of the opinion that—
(a) building work is defective or incomplete; or
6 Transcript of the Hearing, 1-10, [35].
-- 7 of 17 --
8
(b) consequential damage has been caused by, or as a consequence of,
carrying out building work.
(2) The commission may direct the person who carried out the building work to
do the following within the period stated in the direction—
(a) for building work that is defective or incomplete—rectify the building
work;
(b) for consequential damage—remedy the damage.
…
(5) The commission is not required to give the direction if the commission is
satisfied that, in the circumstances, it would be unfair to the person to give
the direction.
Example for subsection (5)—
The commission might decide not to give a direction for the rectification of
building work because an owner refuses to allow a building contractor to
return to the owner’s home or because an owner’s failure to properly
maintain a home has exacerbated the extent of defective building work
carried out on the home.
(6) The commission may, before it considers whether building work is defective
or incomplete, require the consumer for the building work comply with a
process established by the commission to attempt to resolve the matter with
the person who carried out the work.
(7) In subsection (3), a reference to a contract for carrying out building work
includes a reference to a domestic building contract for managing the
carrying out of building work.
(8) To remove any doubt, it is declared that the commission may act under this
section in relation to consequential damage whether or not an owner or
occupier has made a request under section 71J .
[13] Section 72 falls within Part 6 of the QBCC Act. Part 6 deals with rectification of
building work. One of the objects of the QBCC Act is ‘to provide remedies for
defective building work’.7 Part 6 seeks to achieve this object by various means
including, for example, dispute resolution8 and the power to require rectification of
the building work.9 In seeking to achieve the object of providing remedies for
defective building work the purpose of Part 6 is consumer protection.10
[14] The power to give a direction to rectify is contained in s 72(2). The QBCC has a
discretion whether to give such a direction. Section 72(3) provides that in deciding
whether to give a direction the Commission may take into consideration all the
circumstances it considers are reasonably relevant. Section 72(5) provides that a
direction is not required to be given if the Commission, is satisfied that, in the
circumstances, it would be unfair to give the direction. Limitations on the power to
give a direction are contained in s 72A.
7 QBCC Act, s 3(b).
8 QBCC Act, s 72(6).
9 QBCC Act, s 72.
10 Barry v Queensland Building and Construction Commission [2015] QSC 50, [16] citing Lange v
Queensland Building Services Authority [2012] 2 Qd R 457, [30].
-- 8 of 17 --
9
[15] The applicant contends that, on a proper interpretation of s 71J and s 72, the
Commission cannot direct a builder to rectify work that has not been the subject of a
written complaint by an owner of residential property.11 I do not accept that
contention. The exercise of the discretion to issue a direction is conditioned only on
the Commission forming the opinion that the work is defective or incomplete.12 The
option for a consumer to request a direction be given, is not a condition to the exercise
of the power in s 72.13
[16] In arriving at that conclusion, I did not find the respondent’s reliance on Queensland
Building and Construction Commission v Groupline Constructions Pty Ltd14 at [79]
helpful. There, it was held, relying on s 72(8), that a direction to remedy consequential
damage (not to rectify defective work) may be given whether a request had been
given. Section 72(8) makes it clear that a request is not needed before a direction to
remedy consequential damage can be issued. It says nothing about directions to rectify
defective work.
[17] In saying that, I accept that in some circumstances the absence of a complaint or a
delay in making a complaint may be relevant to the issue of fairness.15 In this matter,
however, the applicant was aware from at least 11 September 2020 that the main
bathroom shower was leaking. This was confirmed in cross examination of Mr
Bartholomaeus, Managing Director of Dixonbuild Pty Ltd, in the hearing below.16
The applicant had ample opportunity between 11 September 2020 and 4 February
2021 (when the direction was given) to rectify the leak.
[18] Further, the learned Member at first instance made specific reference to the fact that
no evidence had been led to the effect that Dixon was at any time confused by the
naming of the wrong bathroom on the complaint form.17 I find no error of fact was
made in this respect. The real confusion surrounded whether that leak had been
rectified. It was the responsibility of the applicant to ascertain that the defect identified
in the main bathroom had been satisfactorily rectified. It cannot claim ‘unfairness’
because it assumed, wrongly as it turned out, that the leak had been fixed.
[19] For completeness, I add that I do not accept that the applicant was ‘never given
permission to attend to this aspect of the building’ (meaning the main bathroom). This
submission is inconsistent with the evidence adduced at the Hearing to the effect that
Dixon attended the property to test and try to fix the leak in the main bathroom on 23
October 2020.
[20] The applicant also submits that the power to issue a direction to rectify does not give
the QBCC inspector an unfettered discretion to determine that building work is
defective, in particular, as a matter of law, that it is unfair to issue a DTR where there
11 Amended Appeal Submissions filed on 30 April 2025, [35].
12 Barry v Queensland Building and Construction Commission [2015] QSC 50.
13 Interlink Developments Pty Ltd v Queensland Building and Construction Commission [2020] QCAT
480, [22] citing Urban Homes Pty Ltd v Queensland Building and Construction Commission [2016]
QCAT 131, [37]-[40].
14 [2020] QCA 245.
15 Christiansen & Anor v Queensland Building and Construction Commission [2020] QCAT 57;
Rosecove Pty Ltd v Queensland Building and Construction Commission (costs) [2024] QCAT 520,
[49].
16 Transcript 1-10, at 35.
17 Reasons, [66].
-- 9 of 17 --
10
are no building codes, standards, tolerances or guidelines which support a conclusion
that the relevant work was defective.
[21] The applicant argues the test conducted by the QBCC inspector which involved
‘ponding’ water was inconsistent with the QBCC Standards and Tolerances Guide
(section 14.3) which only deemed a shower to be defective if it leaked under ‘normal
usage’ (which did not include ponding water in the shower) and with the relevant
Australian Standard (AS3740-2020) which requires water to flow to the waste with
appropriate falls without leaving any standing water (except normal water tension).
[22] I do not accept that the Member erred in accepting the evidence of the QBCC inspector
as to the testing he conducted and what it revealed. The learned Member referred to
another tribunal decision where the use of a hydrostatic test had been accepted and
said:
I accept the evidence of Mr Hayes that the test which he conducted was an
industry standard, and appropriate, test.
I also accept the opinion of Mr Hayes that a shower has to be waterproof, and
that if it is not, it is a defect.
I consider that the expression ‘in normal usage’ in the QBCC tolerances guide
apprehends the use of a shower for its normal purpose of a person using the
shower for personal hygiene, and the need for a shower to be waterproof whilst
doing so it logical and unsurprising.18
[23] The Member also accepted the evidence of Mr Hayes as to how he conducted the test,
in particular, that the height of the water ponded for the purposes of the test was not
above the height of the waterproof membrane.
[24] There is no error by the Member in proceeding on this basis in circumstances where,
as the respondent submitted:
(a) the applicant did not adduce evidence from any of its employees or agents who
had actual knowledge of the inspection conducted and who had attended the
property;
(b) Mr Hayes gave evidence, which was accepted, that the hydrostatic test was an
industry standard test that he, as an experienced building inspector, had been
using for a long time;
(c) the applicant had not identified any specific test in any Australian Standard that
should have been applied or as to why the test conducted breached any
Australian Standard and did not adduce evidence to show that the testing
methodology applied by Mr Hayes was not reasonable;
(d) the evidence of Mr Hayes was accepted being that ‘the test which he conducted
was appropriate, and that it showed a leak issuing from the main bathroom
shower into the adjoining wardrobe, which would properly be classified as a
major defect’;19
(e) The applicant led no evidence to establish that ‘normal usage’ within the
meaning of s 14.3 of the Standards and Tolerances Guide, did not include water
18 Reasons, [59]-[61].
19 Reasons, [68].
-- 10 of 17 --
11
ponding in the shower. The evidence of Mr Hayes, which was confirmed in
cross-examination and not contested, was that ‘normal usage’ includes water
ponding because a shower should be able to hold water.
[25] In conclusion, there was no error in the construction of s 72. The learned Member has
not erred in his approach to the issue of unfairness in giving the direction and has not
erred in finding the relevant building work was defective on the evidence before him.
[26] In my view, this ground is not made out.
Ground Two: The Member erred in law at paragraph 59 of the Reasons in accepting
the evidence of Mr Hayes that the test he conducted was an industry standard, and
appropriate test.
[27] The applicant and respondent’s submissions are similar to those in respect of ground
one.
[28] Mr Hayes, the QBCC building inspector attended the property on 3 February 2021
and conducted testing of the main bathroom shower. It is Mr Hayes’ method of testing
that forms the basis of grounds two and three.
[29] In short, Mr Hayes’ method involved ‘ponding’ the shower recess to see whether the
water level receded. Mr Hayes did this by filling a plastic bag with water which is
then placed over the top of the drain to seal the waste.
[30] The applicant submits that the Member erred in law in concluding that the test
conducted by Mr Hayes was an industry standard test and appropriate test.20
[31] The applicant refers to section 14.3 of the QBCC Standards and Tolerances Guide
(the QBCC Guide). Section 14.3 of the QBCC Standards and Tolerances Guide (‘the
Guide’) provides:
14.3 Shower recess and components
Any shower component that allows a fully enclosed shower recess to leak
during normal usage is defective.
Within the first 12 months from completion of the work, shower recess and
components are defective if they crack or don’t perform as intended and cracks
in shower bases, screens and glass are defects if they are visible from normal
viewing position.
[32] The applicant contends that ‘normal usage’ contemplates the disbursement of water
in a non-concentrated manner with the majority of that water not pooling but rather
draining away through the waste fairly instantly. Accordingly, a test that permits water
to pond ‘cannot be said to compliment standard industry practice’.
[33] It is not in dispute that there is no particular test for shower waterproofing prescribed
in any Standard or in the QBCC Guide.
[34] In my view, it is not clear that ‘shower component’ in s 14.3 includes the
waterproofing membrane. Assuming for the purposes of the appeal that it does, the
learned Member accepted the evidence of Mr Hayes that ‘normal usage’ included
20 Reasons, [59].
-- 11 of 17 --
12
water ponding because a shower should be able to hold water.21 No evidence was led
by the applicant as to what ‘normal usage’ means in the context of s 14.3 of the Guide.
[35] The learned Member also accepted the evidence of Mr Hayes that the main bathroom
shower did not comply with the Building Code of Australia because water penetration
was occurring from the main bathroom shower to the adjacent bedroom.
[36] Finally, the learned Member accepted that the hydrostatic test conducted by Mr Hayes
was appropriately conducted, in circumstances where Mr Reynolds, the applicant’s
representative, was present during the testing, did not question the method of testing
or the height of the ponded water, and did not take any measurements of the water
level.22
[37] This ground is not made out.
Ground Three: The Member erred in law at paragraph 59 of the Reasons by accepting
the evidence of Mr Hayes that the test was an industry standard test, and appropriate
test because the test failed to adhere with AS3740
[38] The applicant submits that the test which involves ponding water in the shower, is not
in accordance with AS3740 which does not contemplate water being retained in the
recess of a shower for any given period because it requires falls in shower floors to be
sufficient to prevent ‘surface water from being retained on the shower floor (except
for residual water remaining due to surface tension)…’.23 The applicant submits, that
because the tribunal, in exercising its discretion to issue a DTR, will consider the
QBCC Defects policy, QBCC Standards and Tolerances Guide and relevant
prescribed Standards, the main bathroom shower could not be said to be defective.
[39] Further, the applicant says the Member’s reliance on Young t/as LK & HM Young v
Queensland Building and Construction Commission24 in support of the proposition
that the hydrostatic test (ie the ‘ponding method’) was accepted as an approved
methodology was incorrect where no issue was raised in the decision as to the manner
in which the hydrostatic test was conducted.
[40] The respondent submits no findings of law were made by the Member at [59] but
rather that the Member simply accepted the evidence of Mr Hayes that the test he
conducted was an industry standard and appropriate test and that the applicant by
ground three is merely trying to reargue its case which remains unsupported on the
evidence led by the applicant.
[41] I accept the respondent’s submissions. There is no error law at paragraph 59. The
Member preferred the evidence of Mr Hayes and accepted that the test he used
involving ponding of water is a standard industry practice. The Member also accepted
the opinion of Mr Hayes that a shower has to be waterproof and that if it is not, it is
defective.25 This finding was made in circumstances where the applicant did not lead
any evidence from any other person who was present at the time Mr Hayes conducted
the test. Mr Uppman, who gave evidence for the applicant, took issue with the test
conducted by Mr Hayes however, as the learned Member said, he did not personally
21 Transcript, 66, [10].
22 Statement of Danny Hayes dated 10 November 2021, [38].
23 Applicant’s written submissions dated 30 September 2022,[48], referring to AS3740-2010, s 3.4.
24 [2021] QCAT 8.
25 Reasons, [60].
-- 12 of 17 --
13
view the work at any time, and was not available to be cross-examined and,
consequently, that his evidence would be given no weight.26 Further, the Member did
not accept the evidence of Mr Bartholomaeus regarding ‘the validity of the recreation
and assumption’ as to the depth of ponded water used in the test, noting again that he
was not present when the test was undertaken.27
[42] Further, there is no error, in my view, in relying on the decision in Young. The
evidence given by Mr Hayes was to the effect that he did monitor the water level and,
in any event, that the ponded water did not exceed the height of the membrane.
[43] This ground is not made out.
Ground Four: The Member erred in fact in paragraph 66 of the Reasons by stating
there was no evidence that any party was confused by the misnaming of the shower
on the QBCC complaint form.
[44] The applicant submits that the learned Member was wrong when he concluded at [66]
that there was no evidence that any party was at any time confused by the misnaming
of the correct shower on the complaint form.
[45] The applicant says this was an error because the correspondence of 24 November 2020
between Dixon and the Mr Meldon shows Dixon was misled into believing there was
no defect in the main bathroom shower. The correspondence from Dixon asked Mr
Meldon to confirm there was no issue with the ensuite shower and that the main
bathroom had been rectified. Mr Meldon replied to say there was no issue with the
ensuite shower, the main shower had an issue recently and the bathtub was leaking
back in November 2019.
[46] The applicant submits that because the owner failed to identify any alleged defect
regarding the main bathroom shower, the applicant could not have been aware of any
alleged defect regarding the main bathroom shower. The applicant says this caused
confusion to the applicant by misleading it to believe that the items the subject of the
owners’ complaint had been rectified. On this basis, the applicant submits, the
Member erred in fact, by finding the Owner’s QBCC complaint did not cause the
applicant confusion.
[47] Although it is accepted an error was made on the complaint form, I do not accept the
Member erred in saying there was no evidence any party was at any time confused by
the error. In my view this was a reasonable conclusion on the evidence. Although
Dixon had been out to attempt to fix a leak in the main bathroom shower prior to the
owner lodging his complaint form (which only mentioned the ensuite) it was made
clear to Dixon that there was no issue with the ensuite and that the problem lay with
the main bathroom shower.
[48] I accept that the error on the complaint form led Dixon to seek clarification a number
of times that there was no issue with the ensuite. But at the same time, it was aware
there was an issue with the main bathroom and had sent a plumber out to fix the issue.
After the complaint form was lodged, Dixon had communications with the Owner and
property agent about the main bathroom shower. Dixon knew there was an issue with
it and thought, rightly or wrongly, the issue had been rectified.
26 Reasons at [57].
27 Reasons at [49].
-- 13 of 17 --
14
[49] In any event, even if I accept that Dixon was confused by the complaint form, the
confusion only meant that Dixon asked about the ensuite as well as the main
bathroom. The confusion did not mean that Dixon was denied the opportunity of
rectifying the issue with the main bathroom shower.
[50] I do not accept that Dixon believed the inspector and the QBCC were limited to
inspecting only the ensuite shower because that was the shower referred to in the
complaint form.
[51] The inspector was taken to the main bathroom shower and Dixon’s representative and
the property agent were with him. No one expressed any confusion about what was
being inspected or why. Further, the position reached by the Member was supported
by the evidence put before the Tribunal during the course of the hearing and it would
be inappropriate for the Appeal Tribunal to have regard to those matters in
circumstances where they were considered and determined by the learned Member
when the decision was made and where the applicant did not lead any evidence to
support its position.
[52] The Member has not erred in fact in making the statement at paragraph 66 of the
Reasons.
[53] Leave in relation to this ground is refused.
Ground Five: The Member erred in fact by finding that the main bathroom shower
was defective
[54] The applicant submits that the Member erred in finding the main bathroom shower
was defective by way of leakage essentially because the owner’s photos of a wall
containing a water ingress could not be identified as any specific wall in the house
and that the photos contradicted Mr Hayes’ testing which indicated a leak from the
floor in the main bathroom and not any wall.
[55] The respondent submits that the applicant does not point to any paragraph in the
Reasons to support the assertion that the Member erred. Further, that the Member’s
finding that the shower was defective was based on the unchallenged evidence of Mr
Hayes that the test he conducted showed a leak issuing from the main bathroom
shower into the adjoining wardrobe.
[56] The basis for this ground is not clear. The Member made clear he relied on the
evidence of Mr Hayes. That there may have been photos in existence which were
inconsistent with that evidence does not mean the Member has erred.
[57] There has been no error of fact in finding the main bathroom shower was defective.
[58] Leave to appeal on this ground is refused.
Ground Six: The applicant was not provided with the opportunity to resolve the matter
informally before the DTR was issued
[59] The applicant submits by ground six that the DTR was issued ‘against the principles
of procedural fairness’ on the basis they were not given an opportunity to rectify the
defective work. The applicant then refers to s 28(3) of the Queensland Civil and
Administrative Tribunal Act 2009 (Qld) (‘QCAT Act’) which provides that in
conducting a proceeding, the tribunal must observe the rules of natural justice.
-- 14 of 17 --
15
[60] The respondent submits that, notwithstanding the applicant has not articulated a basis
for ground six, that the Member found the builder had ample opportunity to remedy
the defect in the main bathroom shower. Further, that the QBCC Act does not require
that a builder be given an opportunity to resolve a matter informally before a DTR is
issued.
[61] Section 28(3) refers to the Tribunal’s obligation to afford natural justice, not to the
obligation of a party to the review proceeding. In any event, as the respondent has
outlined, the Member found on the evidence that the applicant was given an
opportunity to rectify the defective main bathroom shower. Further, as I have said
above, there is no statutory obligation on the part of the QBCC to afford a builder an
informal opportunity to rectify a defect prior to issuing a DTR.
[62] Ground six is not made out.
Ground Seven: The Member erred in fact by the contradictions between paragraphs
6 and 54 of the Reasons
[63] The applicant points to inconsistencies in the Member’s Reasons (between [6] and
[54]) as to whether the shower was in use between September 2020 and February
2021. The applicant says that if the shower was used this would support its position
that it would be unfair to issue a DTR because there would be a possibility of
intervening acts that could have contributed to the Owner’s Complaint.
[64] The respondent disputes there is any inconsistency in the identified paragraphs of the
Member’s Reasons and that the ground is merely an attempt by the applicant to
reargue its case.
[65] No evidence was led at the Hearing to the effect that the use of the shower contributed
to the leakage and, as a consequence, that it would be unfair to issue a DTR.
[66] Leave to appeal on this ground is refused.
Ground Eight: The Member failed to recognise the possibility that the leak identified
by Mr Hayes was caused by some other factor unrelated to the work carried out by
the applicant
[67] The applicant submits that the Member failed to recognise the possibility that the leak
was caused by some other factor unrelated to any work carried out by the applicant.
[68] This ground is similar to ground seven.
[69] Ground eight is also an attempt by the applicant to reargue its case. The applicant led
no evidence to support its argument that other causes, such as a plumbing leak, the
shower rose blowing out or the shower base overfilling, was a cause of the leaking.
[70] It was open for the applicant to adduce such evidence at the hearing at first instance.
That the opportunity was not taken is no ground for appeal.
[71] This ground is not made out.
Ground Nine: Mr Rodney Uppman’s evidence and statement must have been given
the appropriate weight and considered
[72] The applicant submits that Mr Uppman’s evidence and statement should have been
given the appropriate weight and considered. In support the applicant relies on [40] of
the Reasons where the Member re-states the respondent’s submission, in effect that
-- 15 of 17 --
16
the statement was ‘speculative’ and that an expert should be made available, but made
no finding in relation to the submission.
[73] The applicant submits that Mr Uppman provided a statement in his capacity as
installer of the waterproofing membrane and, accordingly, that the authority relied
upon by the respondent in support of the proposition that an expert should be
available,28 is distinguishable.
[74] The respondent submits that the applicant has not stated whether there has been an
error of fact or law and, accordingly, that the ground is baseless and cannot be properly
responded to by the respondent. Notwithstanding the applicant did not identify the
alleged error, the respondent refers to [57] of the Reasons where the Member states:
Mr Upmann took issue with the type of test conducted by Mr Hayes, saying that
it was not an accepted test, however Mr Upmann did not personally view the
work at any time, and was not available to be cross-examined. I do not place
any weight upon his evidence.
[75] The respondent submits that the finding made by the Member was based on Mr
Uppman not being present at the inspection and that this is not disputed.
[76] Whether or not Mr Upmann was an expert, he gave a statement in the proceeding and
the Member made no error in giving it no weight on the basis he was not available to
be cross-examined. It is not clear, in my view, whether the Member was referring to
Mr Upmann not having ever viewed the work the subject of the DTR or instead was
referring to him not being present at the time of the inspection and testing. In any
event, he was not present at the time of the testing and the Member would have been
justified in giving his evidence about the ponding testing undertaken, limited weight.
[77] This ground is not made out.
Ground Ten: The respondent relied upon case law not provided to the applicant
before the hearing
[78] The applicant submits by ground ten that the applicant was not afforded natural justice
in being taken by surprise by cases relied upon by the respondent in the hearing at first
instance.
[79] The applicant has not identified the relevant case law or explained what prejudice was
allegedly caused by the applicant. It is not sufficient to point to a denial of natural
justice without also demonstrating the prejudice which flows from such denial.29 In
any event, the applicant was legally represented, did not object to the case law being
raised at the time, and, if there were concerns, leave could have been sought to file
submissions responding to the case law to the extent that was considered necessary.
[80] There is no substance to ground ten.
Conclusion
[81] The applicant has not established any arguable error on the part of the Member.
[82] What seemed to be permeating much of the applicant’s application for leave, was the
notion that there was a disconnect between the Complaint which referred to the ensuite
28 Bitossi v Queensland Building and Construction Commission [2021] QCAT 131, [15].
29 Stuart v Queensland Building and Construction Commission [2016] QCATA 135, [46].
-- 16 of 17 --
17
bathroom, and the DTR which related to the main bathroom shower. There was no
demonstrable prejudice caused to the applicant by this and the evidence relied upon
by the Member showed this to be the case. The fact the applicant has issues with the
‘ponding’ method of testing is not a matter for appeal unless the Member has erred in
basing reliance on that testing. The applicant has not demonstrated this to be the case.
[83] Insofar as the applicant purports to argue that the Member did not consider other
possible causes of the leakage, that is also a matter that should have been raised at
first instance and relevant evidence adduced. It is simply too late to seek to reargue
the matter now.
[84] The application for leave to appeal insofar as leave is required, is refused.
[85] The appeal is otherwise dismissed.
-- 17 of 17 --