Chiodo Corporation Operations Pty Ltd v Douglas Shire Council [2024] QCA 153 (2025) QPELR 633
SUPREME COURT OF QUEENSLAND
CITATION: Chiodo Corporation Operations Pty Ltd v Douglas Shire
Council [2024] QCA 153
PARTIES: CHIODO CORPORATION OPERATIONS PTY LTD
ACN 619 297 997
(applicant)
v
DOUGLAS SHIRE COUNCIL
(respondent)
FILE NO/S: Appeal No 16149 of 2023
P & E Appeal No 2827 of 2021
DIVISION: Court of Appeal
PROCEEDING: Application for Leave Planning and Environment Court Act
ORIGINATING
COURT:
Planning and Environment Court at Brisbane – [2023]
QPEC 44 (Kefford DCJ)
DELIVERED ON: 23 August 2024
DELIVERED AT: Brisbane
HEARING DATE: 29 May 2024
JUDGES: Flanagan JA and Brown AJA and Bradley J
ORDER: Application for leave to appeal dismissed with costs.
CATCHWORDS: APPEAL AND NEW TRIAL – APPEAL – PRACTICE AND
PROCEDURE – QUEENSLAND – WHEN APPEAL LIES –
BY LEAVE OF COURT – GENERALLY – where the
applicant seeks leave to appeal, pursuant to s 63 of the
Planning and Environment Court Act 2016 (Qld), against the
decision of the Planning and Environment Court dismissing an
appeal against the decision of the respondent council to refuse
a development application by the applicant – whether, as
contended by the applicant, the Planning and Environment
Court erred in exercising its discretion to refuse the
development application – whether the alleged errors
materially affected the decision of the Planning and
Environment Court – whether leave to appeal should be
granted
ENVIRONMENT AND PLANNING – PLANNING –
PLANNING CONTROLS – QUEENSLAND –
GENERALLY – LOCAL PLANNING INSTRUMENT –
where the applicant appeals from the decision of the Planning
and Environment Court, which dismissed an appeal against the
decision of the respondent council to refuse the applicant’s
development application – where the applicant contends that
the primary judge conflated her consideration of two relevant
-- 1 of 28 --
2
criteria in exercising their discretion – whether an analysis of
the primary judge’s reasons reveals that separate consideration
was given to both criteria – whether the alleged error was
material
COURTS AND TRIBUNALS WITH ENVIRONMENT
JURISDICTION – QUEENSLAND – PLANNING AND
ENVIRONMENT COURT AND ITS PREDECESSORS –
DUTY TO GIVE REASONS FOR DECISION – where the
applicant appeals from the decision of the Planning and
Environment Court, which dismissed an appeal against the
decision of the respondent council to refuse the applicant’s
development application – where the applicant contends that
the primary judge failed to refer to a line of authority about the
interpretation of planning schemes, which demonstrated
a failure to apply it in the reasoning – whether the line of
authority asserted by the applicant constitutes a discrete
principle of construction – whether the primary judge failed to
properly interpret the relevant planning scheme – whether the
alleged error was material
Planning Act 2016 (Qld), s 45, s 60(3)
Planning and Environment Court Act 2016 (Qld), s 63
Acland Pastoral Co Pty Ltd v Rosalie Shire Council [2008]
QPELR 342; [2007] QPEC 112, considered
Boral Resources (Qld) Pty Ltd v Gold Coast City Council
[2018] QPELR 982; [2018] QCA 75, considered
Glass House Mountains Advancement Network Incorporated
v Caloundra City Council & Excel Quarries [1997]
QPELR 438, cited
HA Bachrach Pty Ltd v Caboolture Shire Council (1992)
80 LGERA 230; [1992] QCA 384, cited
Jedfire Pty Ltd v Council of the City of Logan and White
[1995] QPLR 41; [1994] QPEC 47, considered
Lockyer Valley Regional Council v Westlink Pty Ltd (2011)
185 LGERA 63; [2011] QCA 358, considered
Zappala Family Co Pty Ltd v Brisbane City Council (2014)
201 LGERA 82; [2014] QCA 147, applied
COUNSEL: D R Gore KC, with J G Lyons, for the applicant
M J Batty and J E Bowness for the respondent
SOLICITORS: King & Wood Mallesons for the applicant
King & Company Solicitors for the respondent
[1] FLANAGAN JA: On 28 September 2021, the respondent (“Council”) refused an
application by the applicant (“Chiodo”) for a development permit for a material
change of use to facilitate the development of a luxury five-star resort complex on
vacant land at 71-85 Port Douglas Road, Port Douglas (“development application”).
-- 2 of 28 --
3
[2] On 14 November 2023, Chiodo’s appeal to the Planning and Environment Court of
Queensland (“P&E Court”) against the refusal was dismissed and the development
application was refused.1
[3] By application filed 20 December 2023, Chiodo applies to this Court for a grant of
leave to appeal the decision and orders of the P&E Court. The application is made
pursuant to s 63 of the Planning and Environment Court Act 2016 (Qld), which
provides:
“(1) A party to a P&E Court proceeding may appeal a decision in the
proceeding, but only on the ground of error or mistake in law or
jurisdictional error.
(2) However, the appeal may be made only with the leave of the
Court of Appeal”.
[4] For leave to be granted, Chiodo must not only demonstrate an arguable error or
mistake in law but must also establish that the error is material in that it could have
materially affected the decision of the P&E Court.2
[5] The P&E Court, pursuant to s 45 of the Planning Act 2016 (Qld), was required to
assess the development application as if it were the assessment manager. The
development application required impact assessment. While the P&E Court had
a broad discretion in determining the appeal, as the development application required
impact assessment, it was necessary that the exercise of the discretion be based on an
assessment carried out against the assessment benchmarks in the Planning Scheme to
the extent that they were relevant. Further, as identified by the learned primary judge,
it was only necessary to carry out an assessment against the assessment benchmarks
in the Planning Scheme to the extent that they were put in dispute by the parties.3
[6] The primary judge therefore had to assess the development application, relevantly,
by reference to the following instruments:
(a) Version 1.0 of the Douglas Shire Planning Scheme 2018
(“Planning Scheme”);4
(b) Strategic Framework;5
(c) Tourist Accommodation Zone Code;6
(d) Port Douglas/Craiglie Local Plan Code (“Local Plan Code”);7
(e) Access, Parking and Servicing Code;8 and
(f) Landscaping Code.9
1 Chiodo Corporation Operations Pty Ltd v Douglas Shire Council [2023] QPEC 44 (“Reasons”).
2 HA Bachrach Pty Ltd v Caboolture Shire Council (1992) 80 LGERA 230 at 237; Savage v Cairns
Regional Council (2016) 214 LGERA 192 at 195, [8].
3 Reasons [21], footnote 9.
4 RB, vol 5, page 870.
5 RB, vol 5, page 892.
6 RB, vol 5, page 1045.
7 RB, vol 5, page 1078.
8 RB, vol 6, page 1225.
9 RB, vol 6, page 1259.
-- 3 of 28 --
4
[7] If granted leave, Chiodo seeks to raise four grounds of appeal. The issue raised by
grounds 2 and 3 concern the Local Plan Code. The alleged error is that the primary
judge failed to give separate consideration to the issue of whether the development
complied with Performance Outcome 4 (“PO4”) of the Local Plan Code, but rather
conflated the consideration of PO4 with the consideration of the Overall Outcome in
s 7.2.4.3(3)(d) of the Local Plan Code. The significance of this error, according to
Chiodo, is that if PO4 were satisfied, that meant that the development complied with
the Local Plan Code as a whole (“the first alleged error”).
[8] As to ground 1, the error asserted by Chiodo is that the primary judge failed to apply
the correct legal test in the application of four provisions of the Planning Scheme,
being two provisions of the Strategic Framework, one provision of the Tourist
Accommodation Zone Code, and one provision of the Landscaping Code. Chiodo’s
complaint is that the primary judge failed to refer to a line of authority to the effect
that such provisions should not be construed “too strictly” but, instead, subject to the
qualification “to an acceptable degree”.10 That failure, according to Chiodo,
demonstrates that the primary judge failed to apply the correct test in construing these
four provisions (“the second alleged error”).11
[9] As to ground 4, the applicant’s complaint is that the primary judge failed to recognise
an inconsistency between a provision of the Tourist Accommodation Zone Code and
a provision of the Access, Parking and Servicing Code (“the third alleged error”).
[10] Chiodo accepts that the Court only needs to consider the third alleged error if the
applicant succeeds in relation to either or both of the first or second alleged errors.
This is because the issue of carparking raised by the third alleged error only arises if
the use is approved.12
[11] For the reasons which follow, Chiodo has failed to establish the first and second
alleged errors. Further, even if these errors had been established, Chiodo has failed
to demonstrate that the errors are material errors, as they could not materially have
affected the decision of the P&E Court.
[12] In order to place the first and second alleged errors into context, it is first necessary
to undertake an analysis of the Reasons.
The Reasons
[13] At [102]–[118] of the Reasons, her Honour gave a detailed description of the design
attributes of the proposed development. From the west, the building presents as
a building with five levels plus a rooftop terrace containing structures, and from the
east, it presents as four levels plus a rooftop terrace containing structures. The
distance between the proposed lower ground level and the top of the lift overrun is
approximately 20.8 metres. The building outline has a site coverage of approximately
11,253 square metres, which is about 54 per cent of the area of the subject land. The
proposal is to construct the building diagonally across the subject land from the front
south-east corner to the rear north-west corner. The overall building envelope
measures approximately 165 metres in length and 75 metres in width.
10 Applicant’s Amended Outline of Argument, paras 25–26.
11 Applicant’s Amended Reply, para 13.
12 Applicant’s Amended Outline of Argument, para 33.
-- 4 of 28 --
5
[14] The minimum setbacks for the building are seventeen metres from the eastern front
boundary, which fronts Port Douglas Road; seven metres from the northern side
boundary, which adjoins the Mirage Country Club; four metres from the western rear
boundary, which adjoins the Mirage Country Club golf course; and six metres from
the southern side boundary, which adjoins the Oaks Port Douglas Resort. As well as
containing a central multi-storey atrium, the proposed building provides external
private balconies for each unit on the upper ground floor and those floors above.
Almost all of the balconies terminate with prominent planters at their outer edge.
These landscape planters extend beyond the line of the balconies at each level and are
approximately 1.2 metres deep.
[15] Her Honour described the landscape and open space elements of the proposed
development as including:13
“(a) three communal pool areas, of which:
(i) one pool area is on the south-eastern corner with natural
ground;
(ii) one pool area is on the south-western corner; and
(iii) one pool area is on the rooftop;
(b) …
(c) balcony planters on each floor and on the roof terrace;
(d) a combination of deep planting and podium planting areas
around the building; and
(e) containerised planters on the roof terrace.”
[16] Her Honour summarised the combined effect of the various elements of the building
as follows:
“[116] Overall, considering the combined effect of the various
elements of the building, the proposed development conjures an
image reminiscent of the shape and structure of Uluru. It is
oblong and organic in shape. The curve in the building creates
a similar dome-like effect to that of Uluru. Visually, the
relativity of the building’s height to its length and width
reinforces a visual appearance reminiscent of Uluru. In addition,
like Uluru, the proposed development’s hill-like form stands out
as a distinctive element that is discordant with the surrounding
landscape character.
[117] Chiodo Corporation Operations Pty Ltd’s election to define its
proposed development by reference to a visual outcome that is
generally in accordance with photomontages suggests that it
accepts the evidence of Mr Butcher that, absent landscaping that
hides the built form from view, the proposed development
would be visually jarring.
[118] Having regard to the landscape plans and photomontages, it
seems to me that Chiodo Corporation Operations Pty Ltd
13 Reasons [113].
-- 5 of 28 --
6
proposes to disguise the building’s indomitable form by
shrouding it in vegetation and by incorporating other
landscaping on the subject land and in the Port Douglas Road
verge.”
[17] The photomontages referred to by her Honour at [117] show a five-storey building
with extensive and dense planter box landscaping on each balcony and the roof
terrace.14
[18] From the parties’ “Agreed list of issues”,15 her Honour distilled nine issues to be
determined; namely:
“1. Will the proposed development have an unacceptable impact on
the character and sense of place of Port Douglas and the local
area?
2. Will the proposed development result in an unacceptable visual
amenity impact?
3. Does the proposed development include appropriate landscape
works?
4. Is the scale of the proposed development appropriate given its
location?
5. Does the proposed development provide adequate car park
numbers and car park management?
6. What are the relevant matters relied on by the parties under
s 45(5)(b) of the Planning Act 2016?
7. Is there a need for the proposed development?
8. Are there other benefits provided by the proposed development
that lend weight to its approval?
9. Should the proposed development be approved in the exercise
of the planning discretion?”16
[19] Her Honour further noted that it was common ground between the parties that the
outcome of the case “is likely to be informed, in large measure, by my findings about
the appropriateness of the design and landscaping of the proposed development
having regard to its character and amenity impacts and the appropriateness of the
scale of the use proposed to be located on the subject land”.17
[20] As to the first issue concerning the unacceptable impact on the character and sense of
place of Port Douglas and the local area, her Honour commenced her analysis by first
identifying what were described as “uncontentious” provisions of the Strategic
Framework, the Local Plan Code, the Tourist Accommodation Zone Code and the
Landscaping Code, which together constituted the relevant assessment benchmarks.
In paragraph [32](b) of the Reasons, her Honour identified that these benchmarks
included the Overall Outcome in s 7.2.4.3(3)(d) and PO4 of the Local Plan Code.
14 RB, Book 4, pages 783–786.
15 RB, Book 4, pages 857–862.
16 Reasons [28].
17 Reasons [29].
-- 6 of 28 --
7
[21] Her Honour observed that the first assessment benchmark relied on by the Council to
found its allegation of unacceptable character impact was s 3.2.2.2(5) of the Strategic
Framework,18 which provides:
“Port Douglas will retain it (sic) lively tropical tourism ‘buzz’ as a
premier tourist destination. Development will be carefully planned to
achieve sensitive incremental change, rather than instant, over-scaled
development projects, that have little local context or character.”
[22] At Reasons [38] to [39], her Honour set out the Overall Outcome in s 7.2.4.3(3)(d)
and PO4. Section 7.2.4.3(3)(d) provides:
“(d) All forms of development will complement the tropical image
of the town through distinctive tropical vernacular, urban design
and landscaping.”
[23] PO4 provides:
“Landscaping of development sites complements the existing tropical
character of Port Douglas and Craiglie.”
[24] Having considered these and other provisions in the broader statutory context,19 her
Honour observed:
“[51] When the provisions on which the Council relies are read in the
context of the whole Planning Scheme, one readily discerns
a strong planning policy to maintain the distinctive sense of
place and character of Port Douglas and the various communities
within Port Douglas. Various assessment benchmarks align
with, and support achievement of, this policy.”
[25] In assessing the proposed development against the assessment benchmarks that the
Council had put in issue concerning the design of the built form and the landscaping,
and the character and amenity impact of it, her Honour identified four key factual
questions for determination:
“1. What is the character of Port Douglas?
2. What is the character of the local area surrounding the subject
land?
3. What are the design attributes of the proposed development?
4. Will the proposed development have an unacceptable impact on
the character and sense of place of Port Douglas and the local
area?”20
[26] Her Honour observed that the issue of whether the development appropriately
responded to the sense of place, character and identity of Port Douglas and the local
area within which the subject land was situated, required consideration of the
impression created by the aggregation of the built-form metrics, the use, and the
building’s design.21 The architecture expert called by Chiodo, Mr Curtis, opined that
18 Reasons [35]–[36].
19 Reasons [50].
20 Reasons [56].
21 Reasons [142].
-- 7 of 28 --
8
the proposed development was not over-scaled. Her Honour, however, noted
Mr Curtis’ evidence that the proposed development adopted a biophilic design
approach, such that “the proposed development resembles a low, rounded vegetated
hill rising from the ground amidst the landscape.”22 Her Honour noted that this
description:
“…is contrary to the geographic and topographic context of Port
Douglas where the physical references of Flagstaff Hill to the north
and the distant National Parks to the west are the natural landmarks.
There is no immediate reference to low rounded hills within the
surrounding context. Given that context, a biophilic design approach
that endeavours to impose, or manufacture, a man-made hill as a built
form response is contrived and an inappropriate response to the
established sense of place and identity of Port Douglas.”23
[27] At Reasons [154], her Honour considered the incorporation of landscape planters into
the built form:
“Further, although the building is proposed to incorporate landscape
planters to balcony edges and the roof area, from an architectural
perspective this manufactured landscape response does not contribute
to the tropical landscape character that is characteristic of Port
Douglas or the local area, being a series of smaller building envelopes
(either interconnected or stand-alone) that are located within and
around a landscape environment. Rather, the proposed development
will be perceived as a single large building envelope with landscape
planters applied to the edge.”
[28] Her Honour’s conclusion that the proposed development would have an unacceptable
impact on the character and sense of place (of Port Douglas and the local area) was
supported by the following detailed reasoning, which is set out in full:
“[160] Due to the combined effect of the height, setbacks, site cover,
the adoption of a single, enclosed building design, the flat roof
profile, and a design that fails to moderate its scale through the
adoption of a Queensland tropical vernacular architectural style,
the built form of the proposed development will be perceived as
a dominant, bulky structure. It will be perceived as one large
building form with minimal punctuation and modulation and no
separation into a pattern of smaller building envelopes. … [T]he
proposed development conjures an image reminiscent of the
shape and structure of Uluru. The proposed development’s hill-
like form stands out as a distinctive element that is discordant
with the built-form character of the area and the surrounding
landscape.
[161] The disparate character of the proposed development is
material. It is not a matter that can simply be attributed to the
adoption of a more modern design approach or the provision of
a standard of service expected of a luxury five-star resort.
Modernism can, no doubt, be achieved in a way that pays
22 Reasons [146].
23 Reasons [147].
-- 8 of 28 --
9
homage to the existing Queensland vernacular whilst remaining
responsive to the tropical climate. The proposed development is
not inappropriate because of a modern design, but because that
design is wildly discordant with the character of Port Douglas.
…
[163] Of itself, a design that incorporates landscaping into the design
of the building is not out of character for Port Douglas. There
are other examples of development that incorporate vegetation
into the building.
[164] The incorporation of vegetation into building design is a design
feature that is within contemplation when one reads
performance outcome PO2 of the Landscaping code together
with its associated acceptable outcomes. While acceptable
outcome AO2.1 says that no acceptable outcomes are specified,
acceptable outcome AO2.2 of the Landscaping code… provides
for tropical urbanism to be incorporated into building design.
The associated note explains that tropical urbanism includes
many things such as green walls, green roofs, podium planting
and vegetation incorporated into the design of a building. In
those circumstances, I am prepared to assume that the
incorporation of vegetation into the design of a building is not,
of itself, out of character for Port Douglas. Nevertheless, I am
not satisfied that the incorporation of vegetation into the
building design for the proposed development is consistent with
the landscape character of the area.
[165] The landscape character of Port Douglas is not simply
characterised by the dominance of vegetation over built form,
or by the incorporation of vegetation into building design, or by
a combination of those two attributes. As was identified by
Mr Butcher, it is the inter-relationship between the built form
and the surrounding landscape that meaningfully contributes to
the character, identity and sense of place of Port Douglas. That
interplay between built form and landscaping provides a sense
of visual, physical and environmental permeability within
a tropical landscape context.
[166] By virtue of the adoption of a single, large built form covered
in vegetation, rather than a decentralised resort layout with
a series of small buildings interspersed with landscaping at
ground level, the landscape character of the proposed
development is discordant with that which exists in the local
area. To adopt the words of Mr Curtis, “the proposed
development will resemble a low, rounded vegetated hill rising
form the ground”. It lacks permeability. I accept the opinion of
Dr McGowan that there is an obvious difference in visual effect
as between a vegetated hill or form emerging from the landscape
and more scaled-back building forms being dispersed amongst
densely planted landscaping. In this local area and region, the
dominance of tropical landscaping is provided by the
-- 9 of 28 --
10
landscaping forming lush, multi-layered planting that softens
and complements the built form, rather than hiding it. The
proposed development does not provide the interplay between
built form and landscaping that is characteristic of the
resort-style tourist accommodation development in the central
section of Port Douglas Road. The landscaping seeks to
disguise, not enhance.
[167] Overall, the character of the resort-style tourist accommodation
development in the central section of Port Douglas Road is one
of Queensland tropical vernacular architectural style buildings
with built form arranged in a pattern of smaller building
envelopes within a tropical landscape context that provides
a sense of visual, physical and environmental permeability. The
proposed development is discordant with this character. It is
inconsistent with the Douglas Shire and Port Douglas sense of
place and identity and will not offer a positive or meaningful
contribution to the character of the township or the local area
within which it sits.
[168] For the reasons provided above, I am satisfied that the proposed
development does not:
(a) achieve sensitive incremental change, rather it represents
an instant, overscaled development project that will have
little local context or character;
(b) complement the tropical image of the town through
distinctive tropical vernacular, urban design and
landscaping;
(c) complement the existing tropical character of Port
Douglas and Craiglie;
(d) have an appropriate scale and achieve an attractive built
form that incorporates the character and natural attributes
of the subject land and surrounding area as integral
features of the theme and design of the development;
(e) have proportions and a scale that is consistent with the
character of the area and local streetscape;
(f) achieve consistency with the prevailing landscape
character of its setting;
(g) incorporate external finishes that are compatible with the
landscape character;
(h) enhance the tropical, lush landscape character of the
region;
(i) provide landscaping that contributes to and creates a high
quality landscape character for the subject land, street and
local area by enhancing the appearance of the proposed
development from within and outside the development
and that makes a positive contribution to the streetscape;
and
-- 10 of 28 --
11
(j) have landscaping that contributes to a sense of place, is
functional to the surroundings, and enhances the
streetscape and visual appearance of the development.
[169] As such, an assessment of the development application against
s 3.2.2.2(5) of the Strategic framework; the overall outcome in
s 7.2.4.3(3)(d) and performance outcome PO4 of the Port
Douglas / Craiglie local plan code; the overall outcome in
s 6.2.14.2(3)(b) and performance outcome PO3 of the Tourist
accommodation zone code; the overall outcome in
s 8.2.6.2(2)(h) and performance outcome PO3(c) of the
Landscape values overlay code; and the overall outcome in
s 9.4.6.2(2)(a) and performance outcomes PO1(c) and PO2 of
the Landscaping code weighs in opposition to approval of the
development application.”
[29] Her Honour dealt with the second issue concerning unacceptable visual amenity
impact at Reasons [170] to [227]. Her Honour accepted that the visual amenity of the
proposed development would not be as extensive as that alleged by the Council, but
ultimately found that the development would have an unacceptable visual amenity
impact. Her Honour’s conclusion was arrived at by reference to the development
being assessed against a number of benchmarks, including the requirements of
s 3.5.5.1(1) and (2) of the Strategic Framework (which are two of the provisions
relevant to the second alleged error). Her Honour set out these two provisions at
Reasons [174]:
“(1) Development protects, maintains and enhances the region’s
Landscape values as shown on the Landscape values overlay
maps contained in Schedule 2.
(2) Major scenic routes and scenic outlooks, as shown on the
Landscape values overlay maps contained in Schedule 2, are
protected from both the detrimental visual impacts of
development and inappropriate vegetation clearing that may
detract from the scenic qualities of the scenic route, outlook or
ocean-side views.”
[30] In relation to s 3.5.5.1(1) of the Strategic Framework and the definition of “landscape
values” in the Planning Scheme, her Honour considered that the landscape character
along Port Douglas Road that contributed to the distinctive visual imagery of the
Douglas Shire:
“…is one of Queensland tropical vernacular architectural style
buildings with built form arranged in a pattern of smaller building
envelopes within a tropical landscape context that provides a sense of
visual, physical and environmental permeability.”24
Her Honour considered that the proposed development was discordant with this
character and was therefore inconsistent with s 3.5.5.1(1) of the Strategic Framework.
[31] Her Honour considered the application of s 3.5.5.1(2) of the Strategic Framework at
Reasons [198] to [220]. Her Honour concluded that the proposed development was
24 Reasons [223].
-- 11 of 28 --
12
inconsistent with this provision. Her Honour accepted that the loss of glimpses of the
vegetated hill to the west was not a consideration that weighed against approval.
Rather, her Honour’s conclusion was based on her finding that the proposed
development was discordant with the character along Port Douglas Road, being one
of “Queensland tropical vernacular architectural style buildings with built form
arranged in a pattern of smaller building envelopes within a tropical landscape context
that provides a sense of visual, physical and environmental permeability”.25
[32] In considering the ninth issue, namely whether the proposed development should be
approved in the exercise of the planning discretion, her Honour identified five matters
that lent weight to an approval of the proposed development. First, the Planning
Scheme made express provision for a town planning and community need for land in
Port Douglas, including the subject land, to be used for tourist accommodation
facilities. Secondly, there was no suggestion of any hard amenity impacts (such as
noise impacts) occasioned by the use. Thirdly, the evidence established that there
was an existing need for a further luxury resort complex in Port Douglas. Fourthly,
the proposed development would deliver economic benefits in terms of employment,
and flow-on benefits to the economy from such employment. Fifthly, the proposed
development would deliver cultural benefits.26
[33] Her Honour, however, did not consider that the collective weight of these matters,
which supported approval, provided a sound town planning basis to approve the
proposed development in the face of the identified non-compliances with the
assessment benchmarks in the Planning Scheme. Her Honour considered that these
non-compliances related “to a matter of significant town planning consequence,
namely the character and sense of place of Port Douglas”.27 Her Honour continued:
“[399] The planning context traversed in my reasons above
demonstrates an important planning strategy to protect the
character and sense of place of Port Douglas. Although the
Planning Scheme anticipates use of the subject land for a resort
complex, it is apparent that the support is conditional upon any
such development achieving consistency with the intended
character of the area.”
[34] By reference to ss 3.2.1.6, 3.2.1.7, 3.2.2.1(1), 3.2.2.2 and 3.7.4 of the Strategic
Framework, her Honour concluded as follows:
“[409] Reading those provisions with which the proposed development
is inconsistent in the broader context of the Strategic framework
referred to above, one can readily discern a strong planning
policy to maintain the distinctive sense of place and character
of Port Douglas, and of the various communities within Port
Douglas. The character and sense of place that is sought to be
achieved is not one that is ‘distinctive’ in terms of being
different to the design and character of built form present in the
local area. Rather, the built form is to integrate with established
urban qualities that distinguish the local area from other parts of
Queensland. The distinctive sense of place is one that is
25 Reasons [209]–[211].
26 Reasons [389]–[394].
27 Reasons [398].
-- 12 of 28 --
13
informed by the Shire’s natural and rural settings, its
unmistakeable Queensland tropical vernacular built form, and
its landscape setting. In combination, these attributes make
a vital contribution to the Shire’s identity that, in turn,
contributes to the everyday experiences of residents and visitors
alike. They are identified as critical to the tourism industry –
one of two principal determinants of economic activity and
employment in Douglas Shire.
[410] The proposed development is not, as I have outlined above,
without merit. Strong arguments have been made for its
approval. That said … the disparate character of the proposed
development is material. It is not a matter that can simply be
attributed to the adoption of a more modern design approach or
the provision of a standard of service expected of a luxury five-
star resort. Modernism can, no doubt, be achieved in a way that
pays homage to the existing Queensland vernacular whilst
remaining responsive to the tropical climate. The proposed
development is not inappropriate because of a modern design,
but because that design is wildly discordant with the character
of Port Douglas. It has the potential to diminish the experience
of those visiting Port Douglas by detracting from their
perception that the built form of Port Douglas is one
characterised by Queensland tropical vernacular architectural
style buildings with built form arranged in a pattern of smaller
building envelopes within a tropical landscape context that
provides a sense of visual, physical and environmental
permeability.
[411] What rings through with great finality is the importance of
protecting what is unique and special to Port Douglas’
character. The proposed development’s many merits do not
eclipse this essential consideration.”
The first alleged error
[35] As already observed, the first alleged error concerns the primary judge’s failure to
give separate consideration to whether the development complied with PO4 of the
Local Plan Code. Chiodo asserts that her Honour conflated her consideration of PO4
with her consideration of the Overall Outcome in s 7.2.4.3(3)(d) of the Local Plan
Code.
[36] Section 7.2.4.3(3)(d) and PO4 are set out at [22] and [23] above. Chiodo submits that
the structure of the Planning Scheme is such that, if PO4 were satisfied, then no
consideration needed to be given to the Overall Outcome. By reference to the
wording of PO4 and the Overall Outcome, Chiodo submits that PO4 is concerned
only with landscaping, and not with built form, whereas the Overall Outcome is
concerned with built form. By reference to Reasons [32](b), [38]–[39] and, in
particular, [56], [116], [160], [166], [167] and [169], which are all set out above,
Chiodo submits that her Honour impermissibly conflated the landscaping and built
form issues.28 This approach, according to Chiodo, involved three overlapping errors
of law:
28 Applicant’s Amended Outline of Argument, para 16.
-- 13 of 28 --
14
“First, the primary judge failed to identify and address the right
question, namely, whether, considered separately, there was
compliance with PO4. Secondly, the primary judge erred in principle,
in failing to apply the decision-making structure dictated by the
Planning Scheme. Thirdly, the approach taken by the primary judge
necessarily involved a misconstruction of the Planning Scheme.”29
[37] According to Chiodo, the structure of the Planning Scheme, which necessitates
separate consideration of PO4, arises from two provisions. The first provision falls
within Part 5 of the Planning Scheme which concerns tables of assessment.
Section 5.4 is headed “Additional matters about determining the assessment criteria”.
Section 5.4(1)(c)(iii) provides:
“(1) In addition to the above, the following rules apply in
determining assessment criteria for each level of assessment:
(a) …
(b) …
(c) Code assessable development.
(i) …
(ii) …
(iii) that complies with:
(A) the purpose and overall outcomes of the code
– complies with the code;
(B) the performance or the acceptable outcomes,
where prescribed – complies with the
purpose and overall outcomes of the code.”30
[38] The second provision is s 7.1(6)(e) which falls within Part 7 of the Planning Scheme
which concerns local plans. Section 7.1(6)(e) provides that each local plan code
identifies the performance outcomes that achieve the overall outcomes of the local
plan code.31 The effect of these provisions is that if a proposed development complies
with the performance outcomes of a code, it is taken to comply with the purpose and
overall outcomes of the code, which in turn means that the development complies
with the code as a whole.32
[39] Section 5.4(1)(c)(iii) operates so as to provide two distinct paths for a proposed
development to comply with the relevant code, in this case the Local Plan Code.
Pursuant to s 5.4(1)(c)(iii)(A), if a proposed development complies with the purpose
and overall outcomes of the Local Plan Code, then it is taken to have complied with
the code. The second path, established by s 5.4(1)(c)(iii)(B), is that if a proposed
development complies with the performance outcomes of the Local Plan Code, it is
taken to have complied with the purpose and overall outcomes of the Local Plan Code
and therefore, by operation of s 5.4(1)(c)(iii)(A), to have complied with the code.
29 Applicant’s Amended Outline of Argument, para 18.
30 RB, Book 5, page 939.
31 RB, Book 5, page 1050.
32 Applicant’s Amended Outline of Argument, para 11.
-- 14 of 28 --
15
[40] In the present case, although s 5.4(1)(c)(iii)(B) refers to the “performance …
outcomes”, it may be accepted that PO4 of the Local Plan Code was the only
performance outcome relevant to the issue of compliance.
[41] The essence of Chiodo’s submission is that the Reasons do not disclose any separate
consideration by her Honour of PO4, as PO4 is concerned only with landscaping, and
not with built form, whereas the Overall Outcome was concerned with built form.
This submission fails at the threshold as it proceeds on an incorrect premise; namely,
that in assessing the proposed development’s compliance with PO4, her Honour could
not have regard to the built form of the proposed development. Once it is accepted
that in considering PO4, her Honour was entitled to have regard to built form, a plain
reading of the Reasons does not establish that her Honour failed to give separate
consideration to PO4.
[42] PO4, in terms, requires a consideration of the “landscaping of development sites” for
the purposes of determining whether that landscaping “complements the existing
tropical character of Port Douglas and Craiglie”. In circumstances where a significant
aspect of the landscaping of the proposed development site is incorporated into the
built form, a commonsense approach to the interpretation of PO4 is that it is
appropriate in such circumstances to have regard to built form.33
[43] In the course of oral submissions, Mr Gore KC, who appeared with Mr J Lyons for
Chiodo, made the following two concessions:
(a) For the purposes of considering PO4, the P&E Court is permitted to take into
account the landscaping encompassed in the built form;34 and
(b) The application of PO4 requires some consideration of the interrelationship
between the built form as proposed and the landscaping.35
[44] In assessing whether her Honour gave separate consideration to PO4, the Reasons
should be read not only in light of these concessions, which reflect a commonsense
approach to the interpretation of PO4, but also by having regard to the issues
identified by the parties at first instance.
[45] The third issue identified in the agreed list of issues was whether the impacts of the
proposed development on the landscape values, sense of place and landscape
character were appropriate and acceptable, having regard to a number of provisions
of the Planning Scheme. The two provisions listed as relevant to the Local Plan Code
were the Overall Outcome in s 7.2.4.3(3)(d) and PO4. The agreed list of issues
therefore implicitly invited her Honour to consider both provisions. The fact that her
Honour considered both provisions does not, in itself, establish a failure on the part
of the primary judge to give separate consideration to PO4.
[46] In its written submissions at first instance, Chiodo made reference to the effect of
s 5.4(1)(c)(iii) of the Planning Scheme:
33 Zappala Family Co Pty Ltd v Brisbane City Council (2014) 201 LGERA 82 at [57] per Morrison JA
(with whom Margaret McMurdo P and Douglas J agreed).
34 Transcript of Proceedings, 29 May 2024, T1-18, lines 41–46.
35 Transcript of Proceedings, 29 May 2024, T1-22, lines 36–41. The second concession was consistent
with the evidence of Chiodo’s own visual amenity expert, Mr Butcher, which her Honour set out at
Reasons [165] set out at [28] above.
-- 15 of 28 --
16
“For the subject land, development that complies with those PO’s are
also to be taken to comply with the overall outcomes of the code.
There are no PO’s applicable to the subject land that relate to the built
form. The only PO of relevance is PO4 which relates to landscaping.
Notwithstanding, it is submitted that the proposed development
complements the tropical image of the town through distinctive
tropical vernacular, urban design and landscaping.”36
[47] While Chiodo’s written submissions below separately addressed the Overall
Outcome in s 7.2.4.3(3)(d) and PO4 of the Local Plan Code, overlapping
considerations were identified. For example, in relation to the Overall Outcome,
Chiodo submitted:
“The proposed development is designed to be responsive to local
landscape values and tropical character in a contemporary way by
adopting a biophilic design that incorporates landscape elements in
around the built form and by reinforcing the visual ‘dominance’ of that
vegetation over built form. The size and nature of the building,
otherwise, is not such as to affect the tropical image or character of the
township of Port Douglas or the local surrounding area.”37
[48] As to PO4, Chiodo submitted below:
“The on-site landscape consists of deep planting, podium planting and
on-building planters within the subject site. …
The Appellant otherwise repeats its submissions set out above in
relation to section 7.2.4.3(3)(d) above.”38
[49] In applying PO4 to the proposed development, the primary judge appreciated that
significant aspects of the landscaping of the development site were to be incorporated
into the built form.39 This included landscape planters which extended beyond the
line of the balconies at each level and were approximately 1.2 metres deep, as well as
a combination of deep planting and podium planting areas around the buildings and
containerised planters on the roof terrace. At Reasons [118] (which is set out in [16]
above), her Honour identified from the landscape plans and photomontages that
Chiodo proposed to disguise the building’s “indomitable form by shrouding it in
vegetation and by incorporating other landscaping on the subject land and in the Port
Douglas Road verge”.
[50] At Reasons [168](b)–(c), her Honour, by way of conclusion in relation to the issue of
whether the proposed development would have an unacceptable impact on character,
separately concluded that she was not satisfied that the proposed development either
complemented the tropical image of the town through distinctive tropical vernacular,
urban design and landscaping (the Overall Outcome), and that she was also not
satisfied that the proposed development complemented the existing tropical character
of Port Douglas and Craiglie (PO4).
[51] Chiodo submits that the separation of the issues at Reasons [168](b)–(c) does not
demonstrate that her Honour gave separate consideration to PO4. According to
36 RB, Book 6, page 1521, para 93.
37 RB, Book 6, page 1544, para 221.
38 RB, Book 6, page 1544–1545, paras 223 and 226.
39 See [15]–[16] above.
-- 16 of 28 --
17
Chiodo, what was required was for her Honour to expose reasoning which revealed
separate consideration.
[52] Upon a plain reading of the Reasons, these submissions cannot be accepted.
[53] As already observed, the application of PO4 required a consideration of whether the
landscaping of the development site complemented “the existing tropical character of
Port Douglas and Craiglie”. Her Honour at Reasons [154] specifically addressed the
issue of whether the “manufactured landscape response” contributed to “the tropical
landscape character that is characteristic of Port Douglas or the local area”.40 Her
Honour identified the tropical landscape character as being a series of smaller
building envelopes (either interconnected or stand-alone) that are located within and
around a landscape environment. Her Honour compared this to the proposed
development, which would “be perceived as a single large building envelope with
landscape planters applied to the edge”.41
[54] Further, at Reasons [166], her Honour accepted the opinion of Dr McGowan, the
Council’s visual amenity expert:
“I accept the opinion of Dr McGowan that there is an obvious
difference in visual effect as between a vegetated hill or form
emerging from the landscape and more scaled-back building forms
being dispersed amongst densely planted landscaping. In this local
area and region, the dominance of tropical landscaping is provided by
the landscaping forming lush, multi-layered planting that softens and
complements the built form, rather than hiding it. … The landscaping
seeks to disguise, not enhance.”
[55] By way of conclusion in relation to the issue of character at Reasons [169], her
Honour specifically listed PO4 and the Overall Outcome in s 7.2.4.3(3)(d) of the
Local Plan Code (as well as other provisions) in determining that these matters
weighed against the approval of the proposed development.
[56] Her Honour’s findings at Reasons [154] and [166] correlate, in terms, with a
consideration of whether the proposed development complied with PO4.
[57] Chiodo has therefore failed to establish the first alleged error.
[58] Even if the first alleged error had been established, such an error would not be
material, in the sense that it could not materially have affected the decision at first
instance.
[59] In considering the issue of materiality, it is necessary to consider the first alleged error
in context. The first contextual matter is that PO4 is a provision of the Local Plan
Code. As correctly submitted by Chiodo:
“(a) the [Local Plan Code] addresses matters at the local level, and
may be expected to provide more detailed planning for a site; 42
(b) the [Local Plan Code] is ‘tailor-made to suit local needs’;43
40 Reasons [154].
41 Reasons [154].
42 Planning Scheme, s 7.1(1); RB, Book 5, page 1050.
43 Planning Scheme, s 3.2.2.2(3); RB, Book 5, page 907.
-- 17 of 28 --
18
(c) the [Local Plan Code] identifies 5 precincts within the [Local
Plan Code] area,44 but the subject land is not within one of those
precincts (with the Planning Scheme provisions for those
precincts being more specific and comprehensive than the
provisions that apply to the subject land).”45
According to Chiodo, these matters are material, because they reinforce the
importance of giving separate consideration to PO4.46
[60] The second contextual matter is that Chiodo enjoyed reasonable success on a range
of disputed issues. As outlined at [32] above, her Honour identified five matters that
lent weight to an approval of the proposed development. Further, in relation to the
issue of the proposed development’s impact on character, her Honour made
determinations which either favoured an approval or were neutral including that the
height of the proposed development was not determinative,47 that the site coverage
exceedance was of little moment,48 that, at least viewed in isolation, the setbacks and
site coverage were generally acceptable,49 and that there were aspects of the proposed
development that provided a degree of consistency with the character of Port
Douglas.50
[61] As to the issue of visual amenity impact, her Honour also made findings that either
favoured an approval or were neutral. These included that the loss of glimpses of the
vegetated hills to the west did not weigh against approval,51 that the proposed
development would not interfere with views from the Captain Cook Highway,52 and
that the scenic outlook on Flagstaff Hill would not be detrimentally impacted to
a material extent.53
[62] Chiodo submits that if the first alleged error is established, it would have what is
described as a “domino effect”.54 Chiodo submits that if the primary judge had given
separate consideration to PO4 and found that the proposed development complied
with it, it would follow that the proposed development complied with the Local Plan
Code. Such compliance would amount to an expression of what constitutes the public
interest, which would then be the starting point for the exercise of the discretion under
s 60(3) of the Planning Act 2016.55
[63] There are a number of difficulties with Chiodo’s asserted “domino effect”. First, even
if it was thought that the primary judge failed to give separate consideration to PO4,
her Honour made a specific finding that the proposed development did not
complement the existing tropical character of Port Douglas and Craiglie as provided
in PO4. This finding was supported by her Honour’s reasoning at Reasons [154] and
44 Local Plan Code, s 7.2.4.3(4); RB, Book 5, page 1079.
45 Applicant’s Amended Outline of Argument, para 12.
46 Applicant’s Amended Outline of Argument, para 13.
47 Reasons [130].
48 Reasons [137].
49 Reasons [138].
50 Reasons [139]–[141]; Applicant’s Amended Outline of Argument, para 8.
51 Reasons [203]–[208].
52 Reasons [214].
53 Reasons [218]; Applicant’s Amended Outline of Argument, para 8.
54 Applicant’s Amended Outline of Argument, para 32.
55 Applicant’s Written Outline of Oral Argument, para 15 citing Abeleda v Brisbane City Council (2020)
6 QR 441 at 457, [42].
-- 18 of 28 --
19
[166], which are set out above. This reasoning included a finding that the proposed
development would resemble a low, rounded vegetated hill rising from the ground.
Further, her Honour specifically found that the proposed development did not provide
the interplay between built form and landscaping that is characteristic of the resort-
style tourist accommodation development in the central section of Port Douglas Road.
[64] Chiodo submits, however, that where the primary judge considered landscaping in
isolation, her Honour effectively acknowledged:
“…that the landscaping proposed would generally disguise the built
form, that the visibility of the built form would be quite limited, and
that the incorporation of vegetation into the design of the building was
not, of itself, out of character for Port Douglas.”56
[65] According to Chiodo, these are indicators that the decision of the primary judge in
relation to PO4 might have been different, if separate consideration had been given
to it. This submission cannot be accepted. Once it is accepted that in considering
PO4, her Honour was able to have regard to the landscaping encompassed in the built
form as well as the interrelationship between the built form and the landscaping, any
assertion that upon the matter being remitted, her Honour would make any different
finding as to compliance with PO4, is without substance.
[66] Secondly, any alleged failure on the part of the primary judge to separately consider
PO4 is comprehensively subsumed by her Honour’s ultimate findings in relation to
the proposed development having an unacceptable impact on character and visual
amenity. As observed by her Honour, it was common ground between the parties that
the outcome of the case was likely to be informed, in large measure, by her Honour’s
findings about the appropriateness of the design and landscaping of the proposed
development, having regard to its character and amenity impacts.57 Her Honour’s
conclusions in relation to the issues of character and visual amenity were informed
by numerous assessment benchmarks in the planning scheme, including s 3.2.2.2(5)
of the Strategic Framework. As set out at [34] above, her Honour by reference to
a number of provisions of the Strategic Framework concluded that the proposed
development was inconsistent in the broader context of the Strategic Framework. Her
Honour considered that the design was “wildly discordant” with the character of Port
Douglas,58 and that the proposed development’s “many merits do not eclipse” what
her Honour described as an essential consideration; namely, the importance of
protecting what is unique and special to Port Douglas’ character.59
The second alleged error
[67] This error concerns an alleged failure on the part of the primary judge to apply the
correct test in construing four provisions of the Planning Scheme. Chiodo asserts that
this test is established by a line of authority to which her Honour did not refer.60 The
first two provisions are ss 3.5.5.1(1) and (2) of the Strategic Framework. These
provisions constitute specific outcomes with respect to scenic amenity and were
relevant to issue two concerning whether the proposed development would result in
an unacceptable visual amenity impact. Section 3.5.5.1(1) provides:
56 Applicant’s Amended Outline of Argument, para 20.
57 Reasons [29].
58 Reasons [410].
59 Reasons [411].
60 RB, Book 5, page 919.
-- 19 of 28 --
20
“Development protects, maintains and enhances the region’s
Landscape values as shown on the Landscape values overlay maps
contained in Schedule 2.”
[68] Section 3.5.5.1(2) provides:
“Major scenic routes and scenic outlooks, as shown on the Landscape
values overlay maps contained in Schedule 2, are protected from both
the detrimental visual impacts of development and inappropriate
vegetation clearing that may detract from the scenic qualities of the
scenic route, outlook or ocean-side views.”
[69] The third provision is PO1(a) of the Tourist Accommodation Zone Code,61 which
deals with setbacks and provides:
“Buildings are set back to:
(a) Maintain the character and amenity of the area.”
[70] The fourth provision is the Overall Outcome in s 9.4.6.2(2)(a) of the Landscaping
Code,62 which provides:
“The tropical, lush landscape character of the region is retained,
promoted and enhanced through high quality landscape works.”
[71] The third and fourth provisions were relevant to the first issue concerning whether
the proposed development would have an unacceptable impact on the character and
sense of place of Port Douglas and the local area. As already observed, PO4 and the
Overall Outcome in s 7.2.4.3(d) of the Local Plan Code were also relevant to this
issue.
[72] The primary judge set out these provisions in full in the Reasons.63 Her Honour
concluded that the proposed development was inconsistent with both s 3.5.5.1(1) and
(2) of the Strategic Framework.64 As to PO1, the setback provision, her Honour
observed at Reasons [138]:
“Viewed in isolation, the setbacks and site coverage of the proposed
development are generally acceptable. However, this is not sufficient
to overcome the inappropriate character impacts occasioned by the
overall design nor to ensure that the built form is not bulky or visually
obtrusive. On balance, an assessment of the development application
against performance outcomes PO1 (Setbacks) and PO2 of the Tourist
accommodation zone code does not lend any meaningful weight to
either the case for refusal or the case for approval.”
[73] As to the Overall Outcome in s 9.4.6.2(2) of the Landscaping Code, her Honour
concluded that the proposed development did not enhance the tropical, lush landscape
character of the region.65 Her Honour further concluded that the Overall Outcome in
s 9.4.6.2(2)(a), together with other provisions of the Strategic Framework, the Local
61 RB, Book 5, page 1045.
62 RB, Book 6, page 1259.
63 Reasons [174], [43] and [48].
64 Reasons [225] and [220].
65 Reasons [168](h).
-- 20 of 28 --
21
Plan Code and the Tourist Accommodation Zone Code weighed against approval of
the development application.66
[74] By reference to the words emphasised in italics and underlining in each of the four
provisions set out above, Chiodo submits that there is a line of authority that such
provisions should not be applied “too strictly” but should be applied subject to the
qualification “to an acceptable degree”.67
[75] It may be accepted, and Chiodo does not assert otherwise, that a mere failure on the
part of the primary judge to refer to a particular line of authority does not constitute
an error of law. Chiodo submits, however, that such a failure demonstrates that the
primary judge failed to apply the correct test in construing and applying the four
provisions.
[76] The starting point for a consideration of the second alleged error is that Chiodo did
not bring the relevant line of authority to the attention of the primary judge. Nor did
Chiodo make any submissions at first instance, by reference to this line of authority,
as to how the four provisions should be construed or applied.
[77] By reference to Acland Pastoral Co Pty Ltd v Rosalie Shire Council,68 Chiodo did
make the following written submission before the primary judge:69
“This case turns largely on questions related to character and amenity.
In respect of character and amenity, it has been recognised by this
Court that proposed development will often affect existing amenity.
What the Court considered to be unacceptable, is a detrimental effect
to an unreasonable extent according to the reasonable expectation of
other land holders in the vicinity given the sorts of uses permitted
under current town planning controls, answered according to the
standards of comfort and enjoyment which are expected by ordinary
people of plain, sober and simple notion not effected by some special
sensitivity or eccentricity.” (emphasis in original)
[78] Her Honour, in her conclusion regarding visual amenity impact, which involved a
consideration of s 3.5.5.1(1) and (2) of the Strategic Framework, referred to Acland
Pastoral as follows:70
“It has long been recognised by this Court that new development will
often affect existing amenity. The real issue is whether a development
will have a detrimental effect to an unreasonable extent according to
the reasonable expectations of other landholders in the vicinity given
the requirements of the Planning Scheme. This is to be answered
according to the standards of comfort and enjoyment that are expected
by ordinary people of plain, sober and simple notion not effected by
some special sensitivity or eccentricity.”
[79] Chiodo submits that in the above passage the primary judge was not seeking to
construe the relevant provisions in accordance with the asserted test but was rather
66 Reasons [169].
67 Applicant’s Amended Outline of Argument, para 22.
68 [2008] QPELR 342 at 348–349, [40] (“Acland Pastoral”).
69 RB, Book 6, page 1503, para 18.
70 Reasons [226].
-- 21 of 28 --
22
only giving some general consideration to impacts on amenity.71 In oral submissions,
Mr Gore KC, while accepting that the point was a “relatively fine one”, sought to
draw a distinction between a construction issue and a discretion issue.72 The
distinction sought to be made is without substance. While it may be accepted that the
test in Acland Pastoral is concerned with the exercise of discretion rather than the
proper construction of planning instrument provisions, the test implicitly recognises
that, almost invariably, there are questions of degree in the application of planning
provisions because, as observed by the primary judge, “new development will often
affect existing amenity”.73
[80] Further, as recognised in Acland Pastoral by Dodds DCJ:
“Consideration of amenity in a town planning context is not in the
abstract. It is informed by the planning controls applying in the area
under consideration and the notion of reasonableness”.74
This notion of reasonableness in a consideration of amenity (and character) is
informed more generally by the principle of construction of planning provisions, that
they be read in a way that is practical and as intending to achieve balance between
outcomes. That is, courts will endeavour to adopt a commonsense approach. As
discussed below, the primary judge expressly had regard to these established
principles of construction.
[81] In considering issue one concerning character, which included a consideration of
PO1(a) of the Tourist Accommodation Zone Code and the Overall Outcome in
s 9.4.6.2(2)(a) of the Landscaping Code, her Honour recognised that such provisions
are to be read in their broader statutory context.75 Her Honour observed that such an
approach is:
“[c]onsistent with the principles and canons of statutory construction
that apply to the construction of planning documents and noting that
the Planning Scheme is to be read as a whole and as intending to
achieve balance between outcomes.”76
[82] In support of that proposition, her Honour cited a number of cases including Project
Blue Sky Inc v Australian Broadcasting Authority,77 AAD Design Pty Ltd v Brisbane
City Council,78 and Zappala Family Co Pty Ltd v Brisbane City Council.79
[83] In Zappala, Morrison JA set out the applicable principles relevant to the interpretation
of planning schemes. In essence, this is a repetition of the applicable principles of
statutory interpretation generally, with particular emphasis on the text of the provision
and the need to consider the provision in context. His Honour did, however, observe
that there may be some room to ensure planning schemes are read in a way which is
reasonable and balanced:
71 Applicant’s Amended Outline of Argument, para 30.
72 Transcript of Proceedings, 29 May 2024, T1-28 lines 40–44.
73 Reasons [226].
74 Acland Pastoral at 348, [40].
75 Reasons [50].
76 Reasons [50], footnote 32.
77 (1998) 194 CLR 355, 381–2, [69]–[71].
78 [2013] 1 Qd R 1.
79 (2014) 201 LGERA 82, 94–96, [52]–[58].
-- 22 of 28 --
23
“55 The correct approach to statutory interpretation must begin and
end with the text itself. At the same time it must be borne in
mind that the
‘modern approach to statutory interpretation … (a) insists
that the context be considered in the first instance, not
merely at some later stage when ambiguity might be
thought to arise, and (b) uses “context” in its widest sense
…’
56 The fact that planning documents are to be construed precisely
in the same way as statutes still allows for the expressed view
that such documents need to be read in a way which is practical,
and read as a whole and as intending to achieve balance between
outcomes.
57 As was said by Chesterman JA in AAD Design:
‘Planning schemes, and the definitions found in them,
often lack clarity, contain ambiguities and sometimes
appear contradictory. The attempt to make sense of them
gives rise, on occasions, to expressions of judicial
exasperation. Nevertheless, Mr Hinson submits that the
court should approach the task of construction in the
manner described by Thomas J … in ZW Pty Ltd v Peter
R Hughes and Partners Pty Ltd [1992] 1 Qd R 352 at 360:
“To arrive at the so-called proper construction of
such provisions involves a good deal of guess-
work. In the end courts endeavour to give some
meaning to such provisions and endeavour to adopt
a commonsense approach, or the approach which
seems to make the most sense out of provisions
which may be contradictory as well as
obscure…”.’
58 However, the essential approach must be the same, that is start
and end with the text, seen in its context in the way suggested
in Project Blue Sky and CIC.”
[84] The primary judge therefore appreciated the principles and canons of statutory
interpretation relevant to planning provisions. One of those principles is the adoption
of a commonsense approach which, at least implicitly, encompasses the asserted test
identified by Chiodo.
[85] Quite apart from Chiodo’s failure to bring this line of authority to her Honour’s
attention and the fact that her Honour appreciated the relevant principles and canons
of statutory construction applicable to planning provisions, there are two further
reasons why Chiodo has failed to establish the second alleged error. First, the line of
authority to which Chiodo refers does not, in my view, establish a discrete principle
of construction as asserted by Chiodo.
[86] Chiodo seeks to establish this test first by reference to Jedfire Pty Ltd v Council of
the City of Logan and White,80 where Skoien SJDC observed:
80 [1995] QPLR 41 at 43.
-- 23 of 28 --
24
“The raw words of the section have to be taken with a grain of salt.
Any rezoning for a proposed development might be said in some
degree to create or increase a traffic problem and to affect
detrimentally the efficiency of the roads if it creates any extra traffic,
which is what almost all developments will do. One must inject
a qualifying adverb such as ‘unreasonably’ or ‘intolerably’ into the
section. Traffic in modern urban settings is not assessed in Utopian
terms. In Utopia all cars, driven only by skilful, courteous drivers,
would carry the maximum number of passengers at reasonable speeds
on roads perfectly designed for safe swift travel. But the legislature
must be taken not to have been acting with Utopia in mind. So in this
case I consider that what I have to do is to decide whether the proposal
is for a reasonable or tolerable traffic arrangement in the context of
modern urban motor vehicle movement.”
[87] Chiodo submits that two decisions of this Court, Lockyer Valley Regional Council v
Westlink Pty Ltd81 and Boral Resources (Qld) Pty Ltd v Gold Coast City Council82
lend support to this test. A number of other cases are referred to by Chiodo as
containing similar views, including Glass House Mountains Advancement Network
Incorporated v Caloundra City Council & Excel Quarries.83
[88] In Lockyer Valley Regional Council, Fraser JA (with whom White JA and Douglas J
agreed) dealt with a submission by the council that the primary judge had erred in law
by overlooking a requirement in s 3.1(3)(e) of the Gatton Planning Scheme that
provided “that the rural character and landscape values of the Shire should be
enhanced”. In rejecting that submission, Fraser JA observed:
“It is apparent from my summary of the primary judge’s reasons that
his Honour did take into account the general provisions concerning
“rural character”. It is also clear that the primary judge did not
overlook the reference to “enhanced” in s 3.1(3)(e). His Honour
referred to Glasshouse Mountains Advancement Network Inc v
Caloundra City Council, where it was said that phrases such as
“maintain and preserve” and “preserve and enhance” must be read in
context and bearing in mind that when any development occurs some
amenity impairment will generally result. As the primary judge also
observed with reference to authority, planning schemes should be
construed broadly, rather than pedantically or narrowly, and with
a sensible, practical approach.”84
[89] In Boral Resources, Gotterson JA (with whom Holmes CJ and Morrison JA agreed)
considered a provision of a strategic framework which provided in s 3.5.5.1(10):
“In the non-committed areas at Reedy Creek … operations only
extend into the non-committed areas if it can be demonstrated that:
(a) the amenity of nearby residential land is maintained;
81 (2011) 185 LGERA 63 (“Lockyer Valley”).
82 [2018] QPELR 982 (“Boral Resources”).
83 [1997] QPELR 438 at 441.
84 Lockyer Valley at 73, [20].
-- 24 of 28 --
25
(b) critical corridors are accommodated and matters of
environmental significance are conserved, protected,
enhanced and managed; and
(c) the green backdrop provided by ridge lines is not
reduced when viewed from major roads and surrounding
residential land …” (emphasis in original)
[90] Gotterson JA observed:
“The construction issue, to which I have referred, related to Boral’s
contention that this section should be read as if each of the three limbs
in it contained modifying words such as ‘appropriately’ or ‘to an
acceptable level’. His Honour rejected that contention although he did
accept that each limb ought not be construed ‘too strictly’.”85
[91] Gotterson JA continued:86
“The learned primary judge regarded s 3.5.5.1(10) as a provision
which is not to be construed or applied too strictly. To similar effect,
in Newing v Silcock, Rackemann DCJ had observed that it should not
readily be inferred from the absence of an express qualification that
a provision of a planning scheme relevant to a change of use
application requires that the proposed use have no impact at all, no
matter how insubstantial, trivial or insignificant. A like observation
had earlier been made by Quirk DCJ in Glass House Mountains
Advancement Network Incorporated v Caloundra City Council &
Excel Quarries. Consistently with those observations, his Honour
rejected the Council’s submission that this provision should be
construed and applied strictly.
In Lockyer, decided in 2011, this Court noted that the primary judge,
Rackemann DCJ, had referred to Glass House Mountains
Advancement Network Inc. Fraser JA (with whom White JA and
Douglas J agreed), implicitly endorsed his Honour’s observation
made, with reference to authority, that planning schemes should be
construed broadly, rather than pedantically or narrowly, and with
a sensible, practical approach.”87
[92] In rejecting Boral’s submission, Gotterson JA concluded as follows:
“Consistency with the decision in Lockyer does not require the
interpolation of the words suggested by Boral in order for s 3.5.5.1(10)
to operate sensibly and practically. In my view, that is sufficiently
achieved by the not too strict manner in which the learned primary
judge considered it should be construed and applied. Moreover, to
interpolate those words would unjustifiably displace recognition of the
different standards that the express language of s 3.5.5.1(8) and
s 3.5.5.1(10) respectively indicate are to be applied to extractive
resource committed areas on the one hand, and to the Reedy Creek
extractive resource non-committed areas on the other.
85 Boral Resources at 61, [43].
86 Boral Resources at 65, [57].
87 Boral Resources at 65, [58].
-- 25 of 28 --
26
The contention that the learned primary judge allowed general
provisions relating to protection in situ to limit the meaning of
s 3.5.5.1(10) does not withstand scrutiny. For that to have occurred,
his Honour would have had to have construed and applied this specific
outcome with inflexible stricture.”88
[93] A consideration of these passages does not lend support to the proposition that the
test identified by Chiodo constitutes a discrete principle of construction additional to
established statutory interpretation principles. These principles establish that the
starting point is the text of each of the four provisions, which necessarily involves
a consideration of the emphasised words as set out at [67] to [70] above. The
provisions are to be read in context and a commonsense approach is to be adopted so
as to achieve a practical balancing between outcomes.
[94] Secondly, even if the asserted test constituted a discrete principle of construction, an
analysis of the Reasons does not reveal that her Honour applied these provisions “too
strictly” and without being subject to the qualification “to an acceptable degree”. As
to PO1, the setback provision, as observed at [72] above, her Honour considered that
the setbacks viewed in isolation were generally acceptable and did not lend any
meaningful weight to either the case for refusal or the case for approval. The setbacks
were not, however, “sufficient to overcome the inappropriate character impacts
occasioned by the overall design nor to ensure that the built form is not bulky or
visually obtrusive”.89
[95] Similarly, her Honour’s conclusion that the proposed development did not comply
with the Overall Outcome in s 9.4.6.2(2)(a) was primarily based on a finding that the
proposed development did not provide the interplay between built form and
landscaping that is characteristic of the resort-style tourist accommodation
development in the central section of Port Douglas Road. Her Honour identified that
in the local area and region, the dominance of tropical landscaping was provided by
the landscaping forming lush, multi-layered planting that softened and complimented
the built form, rather than hiding it.90 Her Honour’s application of PO1(a) and the
Overall Outcome in s 9.4.6.2(2) does not reveal any error in construing these
provisions.
[96] As to s 3.5.5.1(1) and (2) of the Strategic Framework, her Honour at Reasons [181]
identified five key factual questions in relation to the issue of whether the proposed
development resulted in an unacceptable visual amenity impact. Questions four and
five were as follows:
“4. Will the proposed development have a detrimental visual
impact on major scenic routes and scenic outlooks?
5. Does the proposed development protect, maintain and enhance
the region’s landscape values?”91
[97] Question 4 is referrable to s 3.5.5.2(2) and question 5 is referrable to s 3.5.5.1(1). At
Reasons [182], her Honour identified the material that was before her in relation to
determining these issues and observed:
88 Boral Resources at 65-66, [59]–[60].
89 Reasons [138].
90 Reasons [166].
91 Reasons [181].
-- 26 of 28 --
27
“As with the character issues, these issues call for value laden
judgments about which reasonable minds may differ. My findings
below reflect the aggregate impression that I have formed having
regard to the collective effect of that evidence, to the extent that it is
accepted by me.”92
[98] In considering s 3.5.5.1(2), her Honour identified a number of favourable or neutral
considerations. One of those considerations was that the term “buffer” in the
Landscape Values Overlap Map did not preclude the possibility of development
within a scenic route buffer-view corridor. Further, her Honour noted that the built
form of the proposed development was set back from the Port Douglas Road frontage
behind the landscaping. Her Honour acknowledged that although the proposed
development would partially obscure some limited views, that was reasonable “given
the nature of the existing approval that attaches to the subject land”.93 In relation to
the loss of glimpses, her Honour concluded it was not a consideration that weighed
against approval of the proposed development. Although the proposed development
would be visible from the Captain Cook Highway, it would be not be prominent to
persons travelling along the highway at speeds of 80 to 100 kilometres per hour.94
Her Honour was satisfied that, when viewed from the Captain Cook Highway, the
proposed development would not interfere with any identified scenic value on either
the Townscape plan map or the Landscape values map.95 Her Honour also noted that
a degree of visibility of buildings or structures on land within the Tourist
Accommodation zone was to be reasonably expected.96 Her Honour was also
satisfied that the scenic lookout on Flagstaff Hill would not be detrimentally impacted
to a material extent.
[99] The balancing of these considerations by her Honour does not reveal any error in
either the construction or application of s 3.5.5.1(2). Her Honour’s conclusion that
the proposed development was inconsistent with s 3.5.5.1(2) was primarily based on
a determination that the proposed development was discordant with the landscape
character along Port Douglas Road, given there was “an obvious difference in visual
effect between a vegetated hill or form emerging from the landscape and more
scaled-back building forms that are dispersed amongst densely planted
landscaping”.97 Her Honour’s conclusion that the proposed development was
inconsistent with s 3.5.5.1(1) was also based on this determination.98
[100] Even if the second alleged error had been established, such error would not be
material, in the sense that it could not materially have affected the decision at first
instance. For the reasons identified at [66] above, the second alleged error could not
have affected her Honour’s conclusions. The second alleged error, like the first
alleged error, is comprehensively subsumed by her Honour’s ultimate findings in
relation to the proposed development having an unacceptable impact on character and
visual amenity. A favourable finding that the proposed development complied with
each of the relevant four provisions, could not have materially affected the decision
of the P&E Court in light of these ultimate findings.
92 Reasons [183].
93 Reasons [204].
94 Reasons [213].
95 Reasons [214].
96 Reasons [216].
97 Reasons [210].
98 Reasons [223].
-- 27 of 28 --
28
Disposition
[101] The application for leave to appeal should be dismissed with costs.
[102] BROWN AJA: I agree with the reasons of Flanagan JA and the order proposed by
his Honour.
[103] BRADLEY J: I agree with the reasons of Flanagan JA and concur with the order
proposed by his Honour.
-- 28 of 28 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2024/153