Allen & Anor v Queensland Building and Construction Commission [2024] QCA 24 (2024) 18 QR 79
SUPREME COURT OF QUEENSLAND
CITATION: Allen & Anor v Queensland Building and Construction
Commission [2024] QCA 24
PARTIES: REECE JUSTIN ALLEN
CHANTELL RENEE MARIA TAYLOR
(applicants)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(respondent)
FILE NO/S: Appeal No 8605 of 2023
QCATA No 91 of 2020
DIVISION: Court of Appeal
PROCEEDING: Application for Leave to Appeal – Queensland Civil and
Administrative Tribunal Act 2009 (Qld)
ORIGINATING
COURT:
Queensland Civil and Administrative Appeals Tribunal at
Brisbane – [2023] QCATA 66 (Judicial Member D J McGill SC)
DELIVERED ON: 1 March 2024
DELIVERED AT: Brisbane
HEARING DATE: 5 February 2024
JUDGES: Mullins P, Bond JA and Williams J
ORDER: The application for leave to appeal is refused, with
costs.
CATCHWORDS: ADMINISTRATIVE LAW – STATUTORY APPEALS
FROM ADMINISTRATIVE AUTHORITIES TO COURTS –
where the applicants terminated a construction contract for the
construction of their home – where the applicants advanced an
insurance claim against the respondent under the Home
Warranty Insurance Scheme established under Part 5 of the
Queensland Building and Construction Commission Act 1991
(Qld) – where the respondent rejected the claim on the basis
the applicants failed to demonstrate the contract had been
properly terminated – where the applicants contended they had
properly terminated pursuant to a contractual show cause
procedure, or alternatively at common law – where the
applicants sought review of the respondent’s decision pursuant
to s 20 of the Queensland Civil and Administrative Tribunal
Act 2009 (Qld) – where the Tribunal and subsequently the
Appeal Tribunal confirmed the respondent’s rejection of the
claim – where s 150(3)(a) of the Queensland Civil and
Administrative Tribunal Act 2009 (Qld) provides that an
appeal to the Court of Appeal from a final decisions of the
-- 1 of 26 --
2
Appeal Tribunal may be made “only on a question of law” and
only if leave is obtained – where principles guiding the
exercise of the discretion to grant leave discussed - where none
of the proposed grounds of appeal were appeals only on
questions of law
Queensland Building and Construction Commission Act 1991
(Qld), Schedule 1B
Queensland Civil and Administrative Tribunal Act 2009
(Qld), s 150
Chopra v Department of Education and Training (2019)
60 VR 505; [2019] VSCA 298, cited
Commissioner of Police v Antoniolli [2021] QCA 237,
considered
Crime and Corruption Commission v Andersen [2021]
QCA 222, considered
Dura (Australia) Constructions Pty Ltd v Hue Boutique
Living Pty Ltd (No 3) [2012] VSC 99, applied
FPM Constructions Pty Ltd v Council of the City of Blue
Mountains [2005] NSWCA 340, distinguished
Hayes v Federal Commissioner of Taxation (1956)
96 CLR 47; [1956] HCA 21, considered
Hometeam Constructions Pty Ltd v McCauley [2005]
NSWCA 303, cited
Koompahtoo Local Aboriginal Land Council v Sanpine Pty
Ltd (2007) 233 CLR 115; [ 2007] HCA 61, cited
Pivovarova v Michelsen (2019) 2 QR 508; [2019] QCA 256,
applied
Shepherd v Felt & Textiles of Australia Ltd (1931)
45 CLR 359; [1931] HCA 21, cited
COUNSEL: R J Allen, of Project Legal, on behalf of himself and the other
applicant
S E Seefeld for the respondent
SOLICITORS: R J Allen, of Project Legal, on behalf of himself and the other
applicant
Queensland Building and Construction Commission – Legal
for the respondent
[1] THE COURT: The appellants (who, for reasons which will appear, will be referred
to as the applicants) had sought to develop, design and construct a home in Brisbane.
They engaged a contractor to construct the house but ultimately terminated the
contract which they had with the contractor when the home was about 70% complete.
The contractor disputed the applicants’ entitlement to terminate, treated the
applicants’ conduct as itself repudiatory, and terminated the contract itself.
[2] The male applicant is a legal practitioner. He represented the applicants both in this
Court and below.
[3] After terminating the contract, the applicants advanced an insurance claim against the
respondent under the Home Warranty Insurance Scheme established under Part 5 of
-- 2 of 26 --
3
the Queensland Building and Construction Commission Act 1991 (Qld). That
insurance scheme would permit recovery for loss which the applicants suffered in the
event of the contractor failing to complete the contract, but only if they had “properly
terminated the contract with the contractor”. They would be regarded as having
“properly terminated” within the meaning of the insurance scheme if they could be
regarded as having “lawfully under the contract or otherwise at law” terminated upon
the contractor’s default, including but not limited to any breach of contract by the
contractor.
[4] The applicants claimed that they had properly terminated the contract, relying both
on having properly established a contractual right to terminate pursuant to
a contractual show cause procedure and on an alleged entitlement to terminate the
contract at common law.
[5] The respondent rejected the insurance claim on the basis that the applicants had failed
to demonstrate that the contract had been properly terminated. The respondent’s
opinion was that there had been insufficient basis for the applicants to have exercised
a contractual right to terminate pursuant to the contractual show cause notice
procedure. Furthermore, the respondent said that it had been unable to identify
evidence on which to show any appropriate basis for the contract to have been
terminated at common law.
[6] The applicants sought to review the respondent’s decision by a review conducted
under s 20 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (the
QCAT Act). Under such a review the Tribunal is required to produce the correct and
preferable decision by way of a fresh hearing on the merits. By a written judgment
published on 27 February 2020, the Tribunal, constituted by Member Oliver, decided
to confirm the respondent’s rejection of the applicants’ claim.1
[7] The applicants advanced an appeal to the QCAT Appeal Tribunal constituted by
Judicial Member McGill SC. Pursuant to s 142 of the QCAT Act insofar as the appeal
was on a question of fact, or a question of mixed law and fact, the applicants required
leave to appeal. Leave was not required for an appeal on a question of law. If leave
to appeal was granted on a question of fact, or on a question of mixed law and fact,
pursuant to s 147 of the QCAT Act the appeal would be by way of rehearing, albeit
with the power of the Appeal Tribunal to admit additional evidence.
[8] Before the Appeal Tribunal the applicants contended that the Tribunal had made
79 errors of law and 43 errors of fact.
[9] By a written judgment published on 15 June 2023, the Appeal Tribunal rejected the
applicants’ attempt to overturn the decision of the Tribunal and relevantly ordered:2
“1. So far as the appeal was on questions of law, the appeal is
dismissed.
2. Leave to appeal on questions of fact or mixed fact and law
granted, limited to the issues of whether the appellants were in
the circumstances entitled to terminate the building contract at
common law for repudiation, or for sufficiently serious breaches
of non-essential terms; otherwise leave to appeal refused.
1 See Allen & Taylor v Queensland Building and Construction Commission [2020] QCAT 63.
2 See Allen v Queensland Building and Construction Commission [2023] QCATA 66.
-- 3 of 26 --
4
3. Appeal by leave dismissed.”
[10] Section 150(3) of the QCAT Act provides:
“150 Party may appeal—decisions of appeal tribunal
(1) A person may appeal to the Court of Appeal against a decision
of the appeal tribunal to refuse an application for leave to appeal
to the appeal tribunal.
(2) A party to an appeal under division 1 may appeal to the Court
of Appeal against the following decisions of the appeal tribunal
in the appeal—
(a) a cost-amount decision;
(b) the final decision.
(3) However, an appeal under subsection (1) or (2) may be made—
(a) only on a question of law; and
(b) only if the party has obtained the court’s leave to appeal.”
[11] Pursuant to s 151 of the QCAT Act, any application for leave to appeal from the
decision of the Appeal Tribunal is required to be made by application under the
Uniform Civil Procedure Rules within 28 days of the applicants being given the
written reasons of the Appeal Tribunal.3 Such an application should be made using
form 69 “Application to Court of Appeal”.4 Use of that form requires applicants
specifically to identify reasons justifying a grant of leave. Appropriate material
should be set out in a supporting affidavit, which would in the normal course also
exhibit a proposed notice of appeal.
[12] On 12 July 2023 the applicants filed a notice of appeal which purported to institute
an appeal from the final decision of the Appeal Tribunal which had been delivered on
15 June 2023. However, the appeal to this Court had not been instituted properly
because the applicants had not obtained the Court’s leave to appeal. The applicants’
purported notice of appeal sought an order that leave to appeal be granted, but that
course was irregular.
[13] In order now to comply with the applicable procedural law, the applicants would be
required to file an application which sought the leave they needed and which also
sought an order extending the time within which the application was required to be
filed. Instead of taking that course, the applicants invited the Court to overlook their
procedural errors and to treat the notice of appeal as an application for leave to appeal
on the grounds identified in the notice of appeal. The respondent was content to take
that course. The parties invited the Court to hear argument on both the application
and on the merits of the appeal at the same time.
[14] For the reasons which follow, leave to appeal should be refused in relation to each of
the proposed grounds of appeal.
3 See s 151 of the QCAT Act.
4 See Uniform Civil Procedure Rules 1999, rr 778 and 779 and
https://www.courts.qld.gov.au/__data/assets/word_doc/0010/88417/ucpr-f-69-v4-070614.doc
-- 4 of 26 --
5
Legal principles governing the application
[15] Two important aspects of the law must be identified at the outset.
[16] First, leave to appeal may only be granted if the proposed appeal is “only on a
question of law”: s 150(3)(a). In Pivovarova v Michelsen5 and in a number of
subsequent decisions,6 this Court has determined that, on the proper construction of
the QCAT Act, appeals from the Appeal Tribunal pursuant to s 150 must be confined
to pure questions of law and only to such questions. This Court has no jurisdiction to
consider an appeal from a final decision of the Appeal Tribunal on a question of fact
or on a mixed question of fact and law.
[17] The applicants submitted in writing that this Court should overrule the Pivovarova
line of decisions by reference to High Court decisions in different contexts which
predated Pivovarova but which were not specifically adverted to in that case. In the
course of oral argument, the male applicant resiled from that position, but
immediately advanced an argument directly inconsistent with Pivovarova by
contending that an appeal on a question of mixed law and fact could be regarded as
an appeal on a question of law “if … appropriately framed.”7
[18] Whether it is couched as an attempt to overrule Pivovarova or as an attempt to
reinterpret it, the submission must be rejected. The reasons of Fraser JA specifically
considered and distinguished the earlier decision of the Full Court of the Federal
Court of Haritos v Commissioner of Taxation8 which itself had analysed many of the
cases on which the applicants now rely. Further, any contention that this Court should
depart from earlier decisions as to the proper construction of legislation must
persuade the Court to have a strong conviction that the earlier decisions are wrong.9
The applicants’ submission does not so persuade the Court. To the contrary, we agree
with the reasons advanced by Fraser JA in Pivovarova.
[19] The distinction between an appeal only on a question of law, on the one hand, and an
appeal on a question of fact or on a mixed question of fact and law, on the other hand,
is absolutely fundamental in the present context. It goes to the jurisdiction of this
Court to entertain an appeal from the Appeal Tribunal. An appeal which must be
“only on a question of law” is of a narrower ambit than an appeal in which a question
of law is merely “involved”10. In order to be an appeal which this Court has
jurisdiction to hear, the very subject matter of the appeal must be a question of law.
5 Pivovarova v Michelsen (2019) 2 QR 508 at [2] to [10] per Fraser JA, at [14] (Boddice J agreeing) and
at [37] per Crow J.
6 MKN v Laq [2020] QCA 4; Lee v Crime and Corruption Commission; Crime and Corruption
Commission v Lee [2020] QCA 201; Seirlis v Queensland Building and Construction Commission
[2020] QCA 283; State of Queensland v Tafao; Serco Australia Pty Ltd v Tafao [2021] QCA 56;
7 QR 474; Commissioner of State Revenue v Telgrove Pty Ltd [2022] QCA 132.
7 Transcript of proceedings, p 1-5, line 19-21.
8 Haritos v Commissioner of Taxation (2015) 233 FCR 315 (Allsop CJ, Kenny, Besanko, Robertson and
Mortimer JJ).
9 Lynch v Commissioner of Police [2022] QCA 166 per Beech AJA (with whom Morrison and Bond JJA
agreed) at [69] to [70]; Madden v Commissioner of Police [2023] QCA 31 per Mullins P, Bond JA and
Brown J at [26].
10 Maksymiuk v Savage [2015] QCA 177, [1], at [5] – [7] per North J (McMurdo P and Henry J agreeing)
applied in Lee v Crime and Corruption Commission; Crime and Corruption Commission v Lee [2020]
QCA 201 at [15] – [16] per Jackson J (with whom Sofronoff P and Morrison JA agreed).
-- 5 of 26 --
6
[20] Unfortunately, a failure to grapple with this limitation in accordance with the law
permeated the whole of the applicants’ written and oral argument. References were
made to many cases in different contexts but which were not relevant to the present
context. The applicants’ argument complained of errors below but without making
the distinction which the law requires between appeals only on a question of law, and
other appeals which allege factual error or error of mixed fact and law and in which
legal error might merely be somehow involved. In applications of this nature, it is
for the applicant and not this Court to formulate a ground of appeal which this Court
would have jurisdiction to consider. For the most part, the applicants failed in this
task.
[21] Second, even if a proposed appeal from a final decision of the Appeal Tribunal is only
on a question of law, an applicant still needs leave to appeal to this Court. In Crime
and Corruption Commission v Andersen this Court recently observed of the s 150
discretion to grant leave:11
“The identification that the proposed appeal raises a question of law is
not sufficient to warrant a grant of leave. An exercise of judicial
discretion is involved. The matters which authority has identified as
relevant to the exercise of that discretion include:
(a) whether there is a reasonable argument that there is an error of
law to be corrected; and
(b) whether leave is necessary to correct a substantial injustice, or
an important point of principle sufficient to warrant the grant of
leave has been identified.”
[22] Note should be taken of the use of the word “include” in the chapeau to the quote in
the previous passage. Cases in this Court which have addressed the analogous
statutory discretion to grant leave to appeal to a party dissatisfied with the judgment
of the District Court in its appellate jurisdiction pursuant to s 118(3) of the District
Court of Queensland Act 1967 (Qld), have counselled against reducing the discretion
to the application of hard and fast rules. In Commissioner of Police v Antoniolli12
after a consideration of relevant authorities, Bond JA summarised the position in
relation to the s 118(3) discretion in the following way:
“The discretion is unfettered, and exercisable according to the nature
of the case, but leave to appeal will not be granted lightly, given that
the applicant has already had the benefit of two judicial hearings.
It will usually be necessary – but not sufficient – that the Court be
persuaded that there is a reasonable argument that there is an error to
11 Crime and Corruption Commission v Andersen [2021] QCA 222 at [14] per Sofronoff P and Mullins
and Bond JJA, following Bown v Lee [2018] QCA 13 per Sofronoff P (with whom Gotterson and
McMurdo JJA agreed); Rintoul v State of Queensland [2018] QCA 20 at [10] per Applegarth J (with
whom Morrison and Philippides JJA agreed); Commissioner of State Revenue v Harrison [2019]
QCA 50 at [15] per Morrison JA, at [30] per Philippides JA and at [66] per Davis J; Seirlis v
Queensland Building and Construction Commission [2020] QCA 283 at [6] per Mullins JA (with
whom Philippides JA and Henry J agreed).
12 Commissioner of Police v Antoniolli [2021] QCA 237 at [105] - [115] per Bond JA (with whom
Flanagan J agreed), applied subsequently in Lynch v Commissioner of Police [2022] QCA 166;
11 QR 609 at [135] per Beech AJA (with whom Morrison and Bond JJA agreed); Woolston v
Commissioner of Police [2023] QCA 152; 105 MVR 13 at [9] per Boddice JA (with whom Bond and
Flanagan JJA agreed).
-- 6 of 26 --
7
be corrected, which, if corrected would justify the applicant’s claim
for relief.
Tests which provide useful guidance as to the nature of the additional
consideration over and above the existence of a reasonable argument
that there is an error to be corrected include:
(a) that leave is necessary to correct a substantial injustice;
(b) that the proposed appeal raises an important point of law or
principle; and
(c) that the proposed appeal raises a question of general or public
importance.”
[23] Having regard to the s 118(3) analogy and the position in Pivovarova outlined above,
a more complete summary of the principles guiding the s 150(3)(b) discretion in
relation to appeals from final decisions of the Appeal Tribunal may be essayed:
(a) Leave to appeal may only be granted if the proposed appeal is only on a
question of law in the sense discussed in Pivovarova.
(b) The discretion is otherwise unfettered, and exercisable according to the nature
of the case, but leave to appeal will not be granted lightly, given that the
applicants have already had the benefit of two hearings in QCAT.
(c) It will usually be necessary – but not sufficient – that the Court be persuaded
that there is a reasonable argument that there is an error of law to be corrected,
which, if corrected, would justify the applicant’s claim for relief.
(d) Tests which provide useful guidance as to the nature of the additional
consideration over and above the existence of a reasonable argument that there
is such an error of law to be corrected include –
(i) that leave is necessary to correct a substantial injustice; and
(ii) that the proposed appeal raises a question of law of general or public
importance.
[24] It will assist in understanding the gravamen of the proposed grounds of appeal if the
way in which the case was resolved at first instance by Member Oliver and on appeal
by Judicial Member McGill SC is first briefly described.
Factual background
[25] The contract between the applicants and their contractor was entered into by them on
17 February 2016. It provided for the construction of a residential dwelling for
a contract price of $1,896,000. The firm of architects who had assisted in the design
of the house were the nominated Superintendent under the contract.
[26] Work commenced in March 2016 and progressed thereafter but not without difficulty.
There were delays and the contractor had sought extensions of time under the
contract. There were also numerous occasions when the contractor needed
clarification of some aspects of the design drawings, resulting in requests for
information/clarification from the Superintendent to enable the project to proceed.
-- 7 of 26 --
8
[27] By 10 November 2017 the work was about 70% complete, but there was still
considerable finishing work to be carried out. However, the relationship between the
applicants and their contractor had deteriorated. The male applicant was concerned
about the standard of work, the progress of the works, the fact that practical
completion would not be reached within the time specified by the contract taking into
account agreed extensions of time, the need for further extensions of time and the fact
that the contractor had engaged some subcontractors without prior written approval
of the Superintendent.
[28] As a consequence of these concerns, the applicants issued a notice to show cause
under clause 39 of the contract. That clause relevantly provided:
“39.1 Preservation of other rights
If a party breaches (including repudiates) the Contract, nothing in this
clause shall prejudice the right of the other party to recover damages
or exercise any other right or remedy.
39.2 Contractor's default
If the Contractor commits a substantial breach of the Contract, the
Principal may, by hand or by certified post, give the Contractor
a written notice to show cause.
Substantial breaches include, but are not limited to:
a) failing to:
i. provide security;
ii. provide evidence of insurance;
iii. comply with a direction of the Superintendent pursuant to
sample clause 29.3; or
iv. use the materials or standards of work required by the
Contract;
b) wrongful suspension of work;
c) substantial departure from a construction programme without
reasonable cause or the Superintendent’s approval;
d) where there is no construction program, failing to proceed with
due expedition and without delay; and
e) in respect of [the clause dealing with payment of workers and
subcontractors], knowingly providing documentary containing
an untrue statement
39.3 Principal's notice to show cause
A notice under subclause 39.2 shall state:
a) that it is a notice under clause 39 of these General Conditions of
Contract;
b) the alleged substantial breach;
-- 8 of 26 --
9
c) that the Contractor is required to show cause in writing why
thePrincipal should not exercise a right referred to in
subclause 39.4:
d) the date and time by which the Contractor must show cause
(which shall not be less than 7 clear days after the notice is
received by the Contractor): and
e) the place at which cause must be shown.
39.4 Principal's rights
If the Contractor fails to show reasonable cause by the stated date and
time, the Principal may by written notice to the Contractor:
a) take out of the Contractor’s hands the whole or part of the work
remaining to be completed and suspend payment until it
becomes due and payable pursuant to subclause 39.6; or
b) terminate the Contract.”
[29] The contractor responded to the applicants’ notice to show cause by the due date.
However, the applicants considered that the response was not satisfactory and formed
the view that they were within their rights to elect to terminate under cl 39.4(b).
Accordingly on 21 November 2017 the applicants terminated the contract.
[30] On 1 December 2017 the contractor by its solicitors rejected the proposition that the
contractor was in substantial breach; asserted that the contractor had provided
a satisfactory response to the notice to show cause, treated the applicants’ termination
as a repudiation of the contract and elected to terminate the contract itself. The
contractor did not return to site or carry out any further building work.
[31] As previously mentioned, the applicants contended that they had properly terminated
the contract and advanced a claim on the respondent under the statutory insurance
scheme. The respondent rejected the claim on the basis that the contract had not been
properly terminated.
[32] Termination on the basis of an inadequate response to a notice to show cause was not
the only basis on which the applicants had sought to justify their termination. Before
the Tribunal the applicants also contended that after they took possession of the site
they found further evidence of defective building work which they said amounted to
substantial breaches of contract justifying their termination of the contract under the
general law. In this regard they relied on the preservation of their rights expressed in
cl 39.1 and on Shepherd v Felt & Textiles of Australia Ltd.13
[33] Member Oliver examined the operation of the statutory insurance scheme. He
identified that the policy would respond only if the insured had “properly terminated”
the contract with the contractor and noted that that phrase was defined in the policy
as “lawfully under the contract or otherwise at law, upon the contractor’s default
which extends to, but is not limited to … (d) any breach of the contract by the
contractor.”
13 Shepherd v Felt & Textile Industries of Australia (1931) 45 CLR 359.
-- 9 of 26 --
10
[34] Member Oliver then proceeded to consider whether the applicants had persuaded him
that they had properly terminated the contract in that sense.
[35] First, he proceeded to consider the validity of the applicants’ termination under
cl 39.4.
[36] He concluded that the Tribunal was required to determine on an objective assessment
of the conduct of the whether the contractor had been in substantial breach of contract
as alleged by the applicants. Although he accepted that a “substantial breach” within
the meaning of cl 39.2 did not have to be such a breach as would justify common law
determination, he found persuasive observations by Dixon J in Dura (Australia)
Constructions Pty Ltd v Hue Boutique Living Pty Ltd (No 3)14 and concluded that on
the proper construction of the contract the use of the adjective “substantial” provided
guidance. He concluded that that the breaches concerned should not be trivial or
inconsequential but should rather be of real or actual significance to the important
qualities of the bargain.
[37] He concluded that under cl 39 the principal did not merely have to establish that the
alleged breach was a substantial breach, but also that the response to the alleged
breach was not a reasonable response by the contractor. He thought that an objective
test applied to the question whether the response was a reasonable response. In this
regard he found that the factual circumstances giving rise to the issuing of the notice
may well be relevant to a consideration of whether the response to it was reasonable.
Further he concluded that in making the decision whether or not to terminate based
on an alleged unreasonable response by the contractor, the applicants were the subject
of an obligation to make that decision honestly and in good faith.
[38] Member Oliver then proceeded to address the circumstances attending each of the
alleged substantial breaches identified in the notice to show case and the nature of the
contractor’s response to the notice. As to this:
(a) He addressed ground 1, which had raised complaints concerning the contractor
having failed to use materials or standards of work as required by the
contractor. Specific issues had been raised concerning, the standard of
plasterwork, the size of door W3.09 and the visual characteristics of the rooftop
terrace concrete hobs.
(b) He addressed grounds 2, 3 and 6 which had raised complaints that the
contractor had failed to proceed with due expedition and without delay; had
failed to carry out the work with reasonable diligence and had failed to ensure
that the works reach practical completion by the agreed practical completion
date.
(c) He addressed ground 4 in which the applicants claimed that the contractor had
made a number of claims for payment to which it was not entitled.
(d) He addressed ground 5 which particularised two occasions in which the
contractor had engaged subcontractors without the specific approval of either
the applicants or the Superintendent.
(e) He summarised his analysis in this way:
(i) Insofar as breaches had been identified they were not substantial
breaches within the meaning of cl 39; and
14 Dura (Australia) Constructions Pty Ltd v Hue Boutique Living Pty Ltd (No 3) [2012] VSC 99.
-- 10 of 26 --
11
(ii) When looked at objectively, particularly when the works were 70%
complete with further work to do to bring the whole project together, the
contractor’s responses were reasonable in that they addressed the
applicants’ concerns and were not so inadequate that they gave rise to
a right to terminate the contract.
[39] Member Oliver then proceeded to address the applicants’ submission that if the
Tribunal was satisfied that the contractor had provided a satisfactory response to the
notice to show cause, then there still remained a right to terminate the contract at
common law. As to this:
(a) Member Oliver addressed a submission that the contractor’s behaviour over the
contract had evinced such a disregard of its contractual obligations as to amount
to repudiation on the basis that it would convey to a reasonable person standing
in the shoes of the applicants renunciation either of the contract as a whole or
of a fundamental obligation under it. He rejected the submission, finding that
it flew in the face of what actually occurred and indeed the nature of the
response which had been made to the show cause notice. He found that the
contractor had not acted in any way which would constitute repudiatory
conduct and therefore at the time the applicants issued the notice to show cause
and at the time of the contractor’s response, the contractor was ready, willing
and able to continue to perform its obligations under the contract.
(b) He then addressed a submission that the defects identified in the notice to show
cause and the defects later identified were so substantial as to justify
termination at common law. He considered on the one hand the evidence
contained in the statement of the male applicant and the expert engaged by him,
and, on the other, the evidence adduced from the contractor’s representative.
After addressing a multiplicity of specific issues he concluded:
“Having considered all of the grounds of termination put
forward by the applicants, I am not satisfied that individually or
collectively, they constitute a substantial breach that would give
rise to a right of termination. What is critical to a consideration
of each of those items is that the works were only 70% complete
and further work was to be done to bring the works to practical
completion. To go on site in a partially constructed building and
pick selective items which would normally be attended to
during completion of the works and contend that they are
substantial defects is particularly unfair to the contractor, where
in every case, there is an explanation as to why the works are in
the state that they are in, in particular the selected items
identified by the applicants, and also in circumstances where the
contractor was ready, willing and able to complete the building
project.”15
[40] Having conducted an analysis of all the ways in which the applicants sought to
persuade him that they had properly terminated the contract, and rejected them,
Member Oliver confirmed the decision which the respondent had made to reject the
insurance claim.
15 Allen & Taylor v Queensland Building and Construction Commission [2020] QCAT 63 at [148].
-- 11 of 26 --
12
[41] Despite the multiplicity of appeal grounds which the applicants sought to advance on
appeal to the Appeal Tribunal, Judicial Member McGill SC did not overturn any of
the findings of fact and law made below.16 He was persuaded to grant leave to appeal
only on the question of whether, taking into account the extent of an encroachment
over the side boundary of the concrete shown to have occurred by fresh evidence
admitted on appeal, the applicants were entitled to and did terminate the building
contract at common law, for either repudiation or sufficiently serious breaches of non-
essential terms.
[42] On the question of termination for repudiation, the Judicial Member said that a
previous decision in which various aspects of a builder’s conduct had justified the
conclusion of repudiation17 stood:
“… as a very marked contrast to the present case, where the only
significant defects were the encroachment onto the neighbouring land,
the absence of backblocking in parts of the plaster ceilings, and to
a lesser extent water penetration through inadequately sealed
windows. There were some additional minor matters, but on the whole
they do not show either a refusal, or an inability, to perform the
contract other than in a manner substantially inconsistent with its
terms. Applying the approach in the authorities referred to earlier, in
my opinion the behaviour of the builder in the present case has not
been shown to have amounted to repudiation of the contract, so as to
give rise to an entitlement to terminate on that basis at common law.”18
[43] On the question of termination for sufficiently serious breaches of non-essential
terms, the Judicial Member concluded:
“As for the alternative ground, on the basis of a collection of breaches
amounting to sufficiently serious breaches of non-essential terms, I do
not consider that the breaches of contract which have been
demonstrated, taken together, amount to a sufficiently serious set of
breaches of non-essential terms to entitle the appellants to terminate
on that basis at common law, since they did not deprive the appellants
of a substantial part of the benefit which they were entitled to under
the contract. I consider that damages were an adequate remedy for
such breaches as have been proved by the appellants. It follows that,
on this basis as well, the appellants were not entitled to terminate the
building contract at common law.”19
[44] Accordingly, the Judicial Member concluded that there was no reason to interfere
with the conclusion of the Member that the applicants had not validly terminated the
contract with the builder, and accordingly the decision of the respondent to reject their
claim under the insurance policy was correct.
[45] To the extent it is necessary to explain any further the approach taken to relevant
issues by the Appeal Tribunal, we will do so in relation to the relevant proposed
grounds of appeal below.
16 Allen v Queensland Building and Construction Commission [2023] QCATA 66 at [184] and [209].
17 Mousa v Vukobratich Enterprises Pty Ltd [2019] QSC 49.
18 Allen v Queensland Building and Construction Commission [2023] QCATA 66 at [248].
19 Allen v Queensland Building and Construction Commission [2023] QCATA 66 at [249].
-- 12 of 26 --
13
The proposed grounds of appeal
[46] Against the foregoing background it is necessary to address the question of leave to
appeal in relation to each of the proposed grounds of appeal. It is convenient to group
some of the proposed grounds of appeal together.
[47] We have explained that the applicants’ submissions failed to grapple properly with
the significance of the limitation that any appeal must be only on a question of law.
In the course of written and oral submissions premised on this wrong starting point,
many suggestions of error below were made. On the question of whether there should
be leave to appeal, we will limit our consideration to the grounds which were
formulated and for which, albeit irregularly, leave was sought. As it is not this Court’s
role to seek to formulate appeal grounds which might comply with the law, we will
not otherwise seek to deal with all the various contentions of error which were
mentioned.
Proposed ground 1
[48] The proposed ground of appeal was in these terms:
“1. The Appeal Tribunal erred in finding [the Contract] was not
"properly terminated" by the Applicants, as that term is defined
in Part 11 of Edition 8 of the Respondent's Insurance Policy
Conditions.”
[49] The applicants relied heavily on the observations by Fullagar J in Hayes v Federal
Commissioner of Taxation20 that “where all the material facts are fully found, and the
only question is whether the facts are such as to bring the case within the provisions
properly construed of some statutory enactment, the question is one of law only”.
[50] His Honour’s observation has itself been the subject of significant qualification and
explanation in other subsequent decisions.21 In the present context this Court22
recently referred with approval to the summary expressed by the Victorian Court of
Appeal in Chopra v Department of Education and Training:23
“The principles for distinguishing between questions of law, questions
of fact and mixed questions of law and fact are well established.
However, those principles are difficult to apply in practice. What is
the proper meaning, as a matter of construction, of a statutory
provision is usually a question of law. Ordinarily, whether facts fully
found fall within a statutory provision, properly construed, is
a question of law. However, where a statute uses words according to
their ordinary meaning and it is reasonably open to hold that the facts
20 Hayes v Federal Commissioner of Taxation (1956) 96 CLR 47 at 51.
21 As to which see, for example, Hope v Bathurst City Council (1980) 144 CLR 1 at 7 per Mason J with
whom Gibbs, Stephen, Murphy and Aickin JJ agreed; Collector of Customs v Pozzolanic (1993)
43 FCR 280 at 287 – 288; Collector of Customs v Agfa-Gevaert Ltd (1996) 186 CLR 389, 394–8;
Vetter v Lake Macquarie City Council (2001) 202 CLR 439 at [24] – [28] per Gleeson CJ, Gummow
and Callinan JJ; and Bell v Federal Commissioner of Taxation (2012) 88 ATR 923, 934–5 [36] – [41].
22 Crime and Corruption Commission v Andersen [2021] QCA 222 at [37] per Sofronoff P and Mullins
and Bond JJA.
23 Chopra v Department of Education and Training (2019) 60 VR 505 at 527 [88] per Tate, Whelan and
Kyrou JJA)
-- 13 of 26 --
14
as found fall within those words, the question whether they do or not
is one of fact.”
[51] It is unnecessary to explore the operation of the categorization because this is not a
case where the applicants accepted that all the material facts sounding on the question
were fully found below. In very many respects the applicants challenged the fact
finding below referable to the question whether the contract had been properly
terminated. Notably, in Robb v Tunio24 Jackson J (with whom Muir JA and Martin J
agreed) observed that findings on evidence and the determination of facts based upon
the totality of evidence before a tribunal, are not only questions of law and an appeal
from such a decision does not raise only a question of law.
[52] By the proposed appeal ground presently under consideration, the applicants seek to
have this Court make different findings on questions of fact and mixed fact and law
referable to the ultimate question whether the contract had been properly terminated.
Then having reached a different evaluation on those questions, the applicants would
invite this Court to reach a different conclusion on the ultimate question. The
applicants’ case on the first proposed ground of appeal could not be characterised as
an appeal only on a question of law.
[53] We would refuse leave to appeal on proposed ground 1.
Proposed ground 2a
[54] This proposed ground of appeal was in these terms:
“2. The Appeal Tribunal erred in finding the contract was not
lawfully terminated by the Appellants under the Contract upon
[the contractor’s] default for:
a. failing to use the materials or standards of work required
by the Contract (Clauses 29.125, 29.326, 39.2 a) iv) / ss. 22
and 23 of Schedule lB of the Queensland Building and
Construction Commission Act 1991 (Qld)) (Schedule 1B)
and Clause 11.127);”
[55] Leave to appeal on this ground must be refused for the reasons expressed in relation
to ground 1. The appeal ground is only slightly less general than that expressed in
relation to ground 1, focussing as it does on a particular category of breaches of
contract, but that does not avoid the existence of the same flaws.
[56] The observations just made are sufficient to justify refusal of leave. But additional
points can be made further explaining why it would be wrong to grant leave for this
proposed appeal ground.
[57] First, the applicants sought to persuade this Court to accept that on the proper
construction of cl 39.2 any single failure to use the materials or standard of work
24 Robb v Tunio [2014] QCA 127 at [22] – [23].
25 Clause 29.1 required the contractor to use suitable new materials and proper and tradesmanlike
workmanship.
26 Clause 29.3 required the contractor to rectify defective work if notified so to do by the Superintendent
27 Clause 11.1 required the contractor to satisfy all legislative requirements. Section 22 of Schedule lB
was one such requirement, namely a warranty by the contractor that the work would be carried out in
an appropriate and skilful way and with reasonable care and skill. Section 22 of Schedule 1B expressed
a warranty that work would be carried out in accordance with plans and specifications.
-- 14 of 26 --
15
required by the Contract, no matter how insignificant or readily remediated should be
regarded as a substantial breach of contract justifying engagement of the show cause
procedure and possible termination.
[58] But that construction of the clause is not reasonably arguable. We observe:
(a) The chapeau to cl 39.2 confers on the principal a conditional right to give a
notice to show cause.
(b) The condition is that described in the opening clause “If the Contractor
commits a substantial breach of the Contract”. Whether the condition is
satisfied is something which must be objectively assessed. Thus, if there is
a breach but that breach does not fall within the meaning of “substantial
breach”, then the condition is not satisfied, and the principal has no right to
give the notice.28
(c) “Substantial breach” is defined in an inclusive way. Member Oliver was
correct to conclude that the use of the adjective “substantial” provided
guidance.
(d) Here the applicants look to the definition of “a) failing to … use the materials
or standards of work required by the Contract.” But in that clause “failing” is
used as a present participle verb and should be taken to refer to a continuity of
failure. One trivial breach would not establish the requisite continuity of
failure.
(e) That is not to say that a single failure to use the required materials or standards
of work might not amount to a “substantial breach”, but, if it did, that would be
because it fell within the ordinary and natural meaning of that phrase and not
the extended definition.
[59] Second, any evaluation by the Tribunal or the Appeal Tribunal of the evidence of
breach on which the applicants relied to reach a conclusion on whether the breach
was or was not a substantial breach was a decision by them on a mixed question of
fact and law. The present appeal ground which invites this Court to reach a different
conclusion on that question cannot be regarded as an appeal only on a question of
law.
[60] Third, even if, contrary to our view, there was a reasonable argument that there was
an error of law to be corrected in the interpretation given to what was a “substantial
breach”, that error would go nowhere unless there was also a reasonable argument
that there was an error of law to be corrected in the approach take to the question
whether the contractor had shown reasonable cause in its response to the show cause
notice. As to this:
(a) The chapeau to cl 39.4 confers on the principal a conditional right to terminate.
(b) The condition is that described in the opening clause “If the Contractor fails to
show reasonable cause”. Those words assume the existence of a valid notice
and then would require an assessment of the contractor’s response.
28 A different view was reached in FPM Constructions Pty Ltd v Council of the City of Blue Mountains
[2005] NSWCA 340 but the clause in that case required, in addition to substantial breach, that the
Principal considered that damages may not be an adequate remedy and that influenced the construction
of the condition.
-- 15 of 26 --
16
(c) The applicants contended that the question whether the contractor had
succeeded to show reasonable cause was not something which must be
objectively assessed. Instead, they contended that the question was a matter
for them to decide subjectively and so long as they made that decision honestly
and in good faith, they would have the right to terminate.
(d) That argument is not reasonably open on the wording of this particular contract.
First, the chapeau to cl 39.4 does not say “if the Principal concludes that the
Contractor has failed to show reasonable cause” or anything like it. To the
contrary it is expressed in a way which invites the conclusion that it
contemplates an objective assessment as to whether the condition on the right
to terminate has been satisfied. But second, the applicants’ argument
transposes to the assessment of whether the condition to the right is established,
the law which governs whether the principal’s exercise of the right to terminate,
once established, is constrained in any particular way. There is no warrant in
the wording of the clause to take that course.
[61] Finally, any evaluation by the Tribunal or the Appeal Tribunal of the nature of the
contractor’s response to the show cause notice to reach a conclusion on whether the
response had showed reasonable cause was a decision by them on a mixed question
of fact and law. The present appeal ground which invites this Court to reach
a different conclusion on that question cannot be regarded as an appeal only on
a question of law.
[62] We would refuse leave to appeal on proposed ground 2a.
Proposed grounds 2b and 5
[63] These proposed grounds of appeal were in these terms:
“2. The Appeal Tribunal erred in finding the Contract was not
lawfully terminated by the Appellants under the Contract upon
[the contractor’s] default for:
b. failing to proceed with due expedition and without delay
and failing to carry out the work with reasonable
diligence (Clause 39 2) d) /, s. 25 of Schedule 1B and
Clause 11.129);
5. The Appeal Tribunal erred in:
a. the proper construction of the term failing to proceed with
due expedition and without delay including failing to
follow FPM Constructions v Council of the City of Blue
Mountains [2005] NSWCA 340;
b. finding that delay in the term failing to proceed with due
expedition and without delay means unreasonable delay;
and
c. equating the term due diligence with due expedition and
without delay and thereby following Hometeam
Constructions Pty Ltd v McCauley [2005] NSWCA 303.”
29 Section 25 of Schedule 1B expressed a warranty warrants the subject work will be carried out with
reasonable diligence.
-- 16 of 26 --
17
[64] The application for leave to appeal on grounds 2b shares similar problems to those
identified in relation to grounds 1 and 2a and should be refused for essentially the
same reasons.
[65] However unlike other proposed grounds considered thus far, each of the grounds
identified in proposed ground 5 does raise only a question of law. Accordingly on
the question of leave to appeal it is necessary to turn to address the remaining issues
of –
(a) whether there is a reasonable argument that there is an error of law to be
corrected, which, if corrected, would justify the applicant’s claim for relief; and
(b) relevant discretionary considerations.
[66] In our view, there were critical flaws in the legal arguments which the applicants
sought to present which meant that they failed to show they had a reasonable
argument that the alleged error of law had been made. Further, it was very evident
that any consideration of their arguments could only occur in the context of
determination of a mixed question of fact and law.
[67] First, the applicants sought to persuade this Court to accept that on the proper
construction of cl 39.2 any single delay in the progress of the works which was the
fault of the contractor, so long as it was not de minimis would have to be regarded as
a substantial breach of contract justifying engagement of the show cause procedure
and possible termination. The applicants get to that proposition by focussing on the
words “without delay” and saying that those words must be given their literal
meaning.
[68] But that construction of the clause is not reasonably arguable. We observe:
(a) We repeat the observations made at [58](a), [58](b) and [58](c) above.
(b) Here the applicants look to the definition of “d) where there is no construction
program, failing to proceed with due expedition and without delay.” (It was
accepted that there was no relevant construction program.)
(c) But again “failing” is used as a present participle verb and should be taken to
refer to a continuity of failure. Further “due expedition and without delay”
should be understood as a compendium phrase describing a required manner of
proceeding. It requires a characterisation of the manner by which the
contractor has in fact been proceeding.
(d) Support for that construction of the clause is also to be found in a comparison
between cl 39.2c) and cl 39.2d). Where there is a program, a substantial breach
requires an assessment whether the departure is substantial and whether it is
excused. It does not make any sense to have a different approach where there
is not a construction program.
(e) That is not to say that a single failure to proceed with due expedition and
without delay could not ever amount to a “substantial breach”, but if it did that
would be because it fell within the ordinary and natural meaning of that phrase
and would turn on an assessment of the particular significance of the delay
concerned.
-- 17 of 26 --
18
(f) That the question of characterisation required by the clause is a broad one finds
support in these observations made by Dixon J in Dura (Australia)
Constructions Pty Ltd v Hue Boutique Living Pty Ltd (No 3) [2012] VSC 99
(which observations may be applied here despite the fact that the contract there
considered is not on all fours with the present contract), namely:
“…. The meaning of [due expedition and without delay] and the
circumstances that will sufficiently demonstrate a substantial
breach of the obligation require careful consideration. The phrase
‘due expedition and without delay’ is uncertain in its precise
meaning. The ordinary meaning of due expedition, as revealed by
the Macquarie Dictionary, requires, affirmatively, adequate or
sufficient promptness or speed in accomplishing something. The
phrase cannot be construed in the abstract and obviously depends
on what is to be achieved, namely, progress with the works. The
second limb of the phrase addressed the negative in plain language
– the progress of the works should also be characterised as being
without delay. In context, the obligation qualifies how the
contractor ‘proceeds with the work under the contract’. What is
adequate or sufficient will be conditioned by other terms of the
bargain such as the agreed date for practical completion, the
agreed circumstances when, and procedure for, the date for
practical completion being varied and how the works are to be
staged or programmed. Such references, extraneous to the phrase,
introduce uncertainty in its precise meaning as they, in turn, may
depend on the interpretation of circumstances or events that have
occurred in the performance of the contract. Careful consideration
of the contractual context is required.”
(g) The result is that in order for the applicants to show this type of substantial
breach it would be necessary for them to prove that the proper characterisation
of the manner by which the contractor had been proceeding with the work was
that the contractor had been failing to proceed “with due expedition and without
delay”. One event of delay would not necessarily establish the requisite
characterisation.
(h) In any examination of the way in which the contractor had been proceeding in
order to determine whether it could be said that it had been failing to proceed
“with due expedition and without delay”, it would be necessary to bear in mind
the operation of all the central obligations in the contract governing the manner
of progress, namely:
(i) The central obligation in cl 34 is expressed as an obligation to ensure
that the work under the contract reaches practical completion by the date
for practical completion.
(ii) That obligation was qualified by the ability to obtain extensions of time
for that date for “qualifying causes of delay”. That phrase was defined
broadly to include, amongst other things, delays caused by the
Superintendent, the Principal and other contractors (not employed by the
contractor) and also causes “other than a breach of omission by the
contractor”.
-- 18 of 26 --
19
(iii) The warranty to proceed with reasonable diligence which flows from the
cl 11.1 promise to comply with legislative requirements.
(i) This strongly suggests that proceeding with due expedition and without delay
is the manner by which the contractor is required to proceed towards the goal
of reaching practical completion by the date for practical completion. And it
necessarily accepts that any entitlement to shift the timing of the end goal
(namely the date for practical completion) may well affect the characterisation
exercise.
[69] Putting to one side the misconceived argument that proof of any single delay would
necessarily establish that the contractor had been “failing to proceed with due
expedition and without delay”, the focus of the applicants’ argument was on alleged
error of law in the meaning which the Appeal Tribunal gave to that phrase. But the
Appeal Tribunal did not make the errors alleged of it. It treated “due expedition and
without delay” as a compendium phrase describing a required manner of proceeding.
It sought to consider the phrase in the entire contractual context, recognising the
significance of extensions of time which had been agreed, which had been sought and
might be disputed, and which might not yet have been sought. It was against that
background that its observations that “due expedition” means such expedition as it
was reasonable for the contractor to have exercised in all the circumstances and
“delay” in “without delay” must mean unreasonable delay on the part of the contractor
must be understood. FPM Constructions Pty Ltd v Council of the City of Blue
Mountains did not establish any principle which ought to have been applied to this
contract which was not applied. And to the extent that Hometeam Constructions Pty
Ltd v McCauley was referred to, the Appeal Tribunal did so only insofar as it thought
that there was relevant analogy in point of principle.
[70] Second, any evaluation by the Tribunal or the Appeal Tribunal of the evidence of
breach on which the applicants relied to reach a conclusion on whether the breach
was a substantial breach was a decision by them which was at best a decision on
a mixed question of fact and law. The question whether a contractor has proceeded
with due expedition and without delay is a question of fact. The present appeal
ground which invites this Court to reach a different conclusion on that question cannot
be regarded as an appeal only on a question of law.
[71] Third, even if, contrary to our view, there was a reasonable argument that there was
an error of law to be corrected in the interpretation given to what was a “substantial
breach”, that error would go nowhere unless there was also a reasonable argument
that there was an error of law to be corrected in the approach take to the question
whether the contractor had showed reasonable cause in its response to the show cause
notice. As to this, we repeat the observations made at [60] above.
[72] Finally, any evaluation by the Tribunal or the Appeal Tribunal of the nature of the
contractor’s response to the show cause notice to reach a conclusion on whether the
response had showed reasonable cause was a decision by them on a mixed question
of fact and law. The present appeal ground which invites this Court to reach
a different conclusion on that question cannot be regarded as an appeal only on
a question of law.
[73] We would refuse leave to appeal on proposed grounds 2b and 5.
-- 19 of 26 --
20
Proposed ground 2c
[74] This proposed ground of appeal was in these terms:
“2. The Appeal Tribunal erred in finding the Contract was not
lawfully terminated by the Appellants under the Contract upon
[the contractor’s] default for:
c. failure to ensure that the work under the Contract reaches
Practical Completion by the Date for Practical
Completion (Clause 34.1);”
[75] The application for leave to appeal on grounds 2c shares similar problems to those
identified in relation to ground 1 and the preceding parts of ground 2 and should be
refused for essentially the same reasons.
[76] We would refuse leave to appeal on proposed ground 2c.
Proposed grounds 2d, 3b and 6
[77] The proposed grounds of appeal were in these terms:
“2. The Appeal Tribunal erred in finding the Contract was not
lawfully terminated by the Appellants under the Contract upon
[the contractor’s] default for:
d. subcontracting part of the work under the Contract
without the Superintendent’s prior written approval
(Clause 9.2).
3. The Appeal Tribunal erred in finding the Contract was not
lawfully terminated by the Appellants otherwise at law upon
[the contractor’s] default:
b. on the basis of subcontracting part of the work under the
Contract without the Superintendent’s prior written
approval (Clause 9.2 and Special Condition 6), either as
an essential or an innominate term;
6. The Appeal Tribunal erred as to the proper construction of
Clause 9.2 and Item 17 of Annexure Part A of the Contract.”
[78] Clause 9.2 obliged the contractor not to subcontract or to allow a subcontractor to
subcontract without the Superintendent’s prior written approval (which should not be
unreasonably withheld). Item 17 specified that the obligation applied to all
subcontract work other than a specific exception. The exception was not said to be
relevant.
[79] There had been two occasions in which the contractor had engaged subcontractors
without the specific approval of either the applicants or the Superintendent.
[80] The Appeal Tribunal observed:
“The failure to obtain prior written approval was not a substantial
breach by definition, and the Member found that this did not amount
to a substantial breach for the purposes of Clause 39. He found that
-- 20 of 26 --
21
the superintendent did ultimately give approval for the plastering
subcontractor, and that the painting subcontractor was just a painter
employed to do some touch-up jobs, so that his involvement in the
project was not of significance.”30
[81] Proposed appeal ground 6 does raise only a question of law. It seems that the
applicants wish to argue that the promise not to subcontract without approval should
be regarded as a condition. In Koompahtoo Local Aboriginal Land Council v Sanpine
Pty Ltd31 the High Court instructed that “[i]t is the common intention of the parties,
expressed in the language of their contract, understood in the context of the
relationship established by that contract and (in a case such as the present) the
commercial purpose it served, that determines whether a term is “essential”, so that
any breach will justify termination.”
[82] The Appeal Tribunal rejected that argument in these terms:
“In any case, I do not regard Clause 9.2 as a condition. It is not said to
be one, and there is nothing in the contract to suggest that it was treated
that way by the parties. Breach of it was not made a substantial breach
by definition by Clause 39, nor did that clause give a right of summary
termination. In the context of the building industry, where
subcontracting is rife and it is commonplace for almost every person
who does any actual work on a building site to be a contractor rather
than an employee, it would not be a commercial construction of the
contract to treat Clause 9.2 as a condition.”32
[83] Apart from argument by assertion, reliance on a case which the Appeal Tribunal
correctly identified as involving materially different provisions33 and attempt to rely
on irrelevant extrinsic evidence, the applicants advanced no substantive argument as
to why the clause should be regarded as a condition. We do not think the proposition
is reasonably arguable. We would refuse leave to appeal on the construction ground.
[84] As to the other grounds, whether one is evaluating the significance of the breach
through the prism of substantial breach within the meaning of cl 39.2 or through the
prism of sufficiently serious breach of an innominate term for the purpose of
termination at common law, the question involves either a question of fact or a mixed
question of law and fact. The result is that the application for leave to appeal shares
similar problems to those identified in relation to ground 1 and the preceding parts of
ground 2 and should be refused for essentially the same reasons.
[85] We would refuse leave to appeal on proposed grounds 2d, 3b and 6.
Proposed ground 2e
[86] The proposed ground of appeal was in these terms:
“2. The Appeal Tribunal erred in finding the Contract was not
lawfully terminated by the Appellants under the Contract upon
[the contractor’s] default for:
30 Allen v Queensland Building and Construction Commission [2023] QCATA 66 at [153].
31 Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd (2007) 233 CLR 115; [2007] HCA 61
at [48] per Gleeson CJ, Gummow, Heydon and Crennan JJ.
32 Allen v Queensland Building and Construction Commission [2023] QCATA 66 at [156].
33 Advance National Services Pty Ltd v Daintree Contractors Pty Ltd [2019] NSWCA 270.
-- 21 of 26 --
22
e. failure to supply everything necessary for the proper
performance of the Contractor's obligations and discharge
of the Contractor's liabilities (Clause 28).”
[87] Clause 28 obliged the contractor to supply everything necessary for the proper
performance of the contractor’s obligations and the discharge of the contractor’s
liabilities. It appears that the applicants’ underlying complaint was the contractor had
consistently failed to supply all necessary resources including adequate labour to
perform the work with due expedition and without delay, with reasonable diligence
and failure to maintain progress.
[88] The application for leave to appeal on ground 2e shares similar problems to those
identified in relation to ground 1 and the preceding parts of ground 2 and should be
refused for essentially the same reasons.
[89] We would refuse leave to appeal on proposed ground 2e.
[90] For completeness, we also observe that the reasons we have given for refusing leave
to appeal after separate consideration of the subparagraphs of proposed ground 2 also
lead us to conclude that leave to appeal should be refused on proposed ground 2 upon
consideration of those subparagraphs in the aggregate.
Proposed ground 3a
[91] This proposed ground of appeal was in these terms:
“3. The Appeal Tribunal erred in finding the Contract was not
lawfully terminated by the Appellants otherwise at law upon
[the contractor’s] default:
a. on the basis of breaches of Special Condition 7 and
Clause 11.1 of the Contract and the implied term
contained in s 21 of Schedule lB of the Queensland
Building and Construction Commission Act 1991 (Qld),
either as essential or innominate terms;”
[92] Special condition 7 stated that each party agreed the statutory warranties applied to
the work under the contract. Cl 11.1 was the general promise to comply with
legislative requirements. Section 21 of Schedule 1B provided:
“The building contractor warrants the subject work will be carried out
in accordance with all relevant laws and legal requirements, including,
for example, the Building Act 1975”.
[93] The applicants suggested that this ground raised “illegality”. But it did not. It raised
first the question whether the clauses relied on should be regarded as conditions such
that any breach would justify termination at common law. Then it raised the
alternative argument that the nature of any breaches was such as should be regarded
as sufficiently serious a breach of an innominate term as to justify termination.
[94] As to the former argument, no proper argument was advanced that the promises
should be regarded as conditions. In our view there is no reasonable argument in
support of the proposition that such promises should be so regarded. We would refuse
leave to appeal on the construction ground.
-- 22 of 26 --
23
[95] The latter argument may be dismissed on the bases expressed at [84] above.
[96] We would refuse leave to appeal on proposed ground 3a.
Proposed ground 3c
[97] This proposed ground of appeal was in these terms:
“3. The Appeal Tribunal erred in finding the Contract was not
lawfully terminated by the Appellants otherwise at law upon
[the contractor’s] default:
c. on the basis of breaches of contract (Clause 1 Definition
of "Works", WUC (from work under the Contract),
Clauses 2.1, 29.1, 29.3, 39.2 a) iii) and iv), plans and
specifications included in the Contract, standards referred
to in the contract, Special Conditions 6.1 and 7, ss. 20, 21,
22 and 23 of Schedule 1B of the Queensland Building and
Construction Commission Act 1991 (Qld)) due to defects
in the work under the Contract, either as essential or an
innominate terms;”
[98] By this ground the applicants sought to have this Court grant leave to appeal to enable
it to advance error in relation to what they contended were “significant and
fundamental issues in regards to defective work”. For reasons expressed in relation
to other grounds, it is absolutely plain that the ground formulated is not an appeal
only on a question of law.
[99] We would refuse leave to appeal on proposed ground 3c.
Proposed ground 3d
[100] This proposed ground of appeal was in these terms:
“3. The Appeal Tribunal erred in finding the Contract was not
lawfully terminated by the Appellants otherwise at law upon
[the contractor’s] default:
d. on the basis of repudiation of the Contract by [the
contractor].”
[101] For reasons expressed in relation to other grounds, it is absolutely plain that the
ground formulated is not an appeal only on a question of law.
[102] We would refuse leave to appeal on proposed ground 3d.
[103] For completeness, we also observe that the reasons we have given for refusing leave
to appeal after separate consideration of the subparagraphs of proposed ground 3 also
lead us to conclude that leave to appeal should be refused on proposed ground 3 upon
consideration of those subparagraphs in the aggregate.
Proposed grounds 4 and 8
[104] These proposed grounds of appeal were in these terms:
-- 23 of 26 --
24
“4. The Appeal Tribunal erred as to the proper construction of
Clauses 39.2, 39.3 and 39.4 of the Contract.
8. The Appeal Tribunal erred in admitting and relying on evidence
after termination to permit [the contractor] to show cause twice
rather than limit its consideration to the evidence in [the
contractor’s] response to the notice to show cause.”
[105] The suggested errors in the proper construction of cl 39 have already been considered
in relation to earlier grounds. We have explained that on the proper construction of
this particular contract, an objective assessment is called for when considering
whether the conditions set out in the chapeaux of cll 39.2 and 39.4 have been satisfied.
No reasonable argument that there were errors of law to be corrected has been
identified in the appeal ground, let alone demonstrated.
[106] Proposed ground 8 does not raise only a question of law.34 We would refuse leave to
appeal on this ground.
Proposed ground 7
[107] This proposed ground of appeal was in these terms:
“7. The Appeal Tribunal erred as to the proper construction the
extension of time terms of the Contract, "qualifying cause of
delay" as defined in Clause 1.1, Clauses 34.3 and 34.5, Special
Condition 10, s. 42 of Schedule 1B of the Queensland Building
and Construction Commission Act 1991 (Qld).”
[108] The proposed ground is entirely opaque. At base it seems that the applicants complain
that the Appeal Tribunal should have overturned the findings made by the Tribunal
at first instance concerning whether the contractor should have been entitled to
extensions of time. Such an appeal could not possibly be regarded as an appeal only
on a question of law. We would refuse leave to appeal on proposed ground 7.
Proposed ground 9
[109] This proposed ground of appeal was in these terms:
“9. After deciding to grant leave to appeal on question of fact only
or a question of mixed law and fact, the Appeal Tribunal erred
in failing to decide the appeal by way of a rehearing as required
by s. 147(2) of [the QCAT Act].”
[110] An Appeal Tribunal could, in theory, err in law by failing to understand what were
the requirements of an appeal by way of a rehearing. In a particular case such an error
might be capable of being shown to have derived from an erroneous legal decision
such that an appeal ground which raised only a question of law might be framed and,
if resolved in favour of an applicant, justify a grant of leave and the remedy of
remission.
[111] The problem with this proposed ground of appeal is that the applicants did not
advance a reasonable argument that the Appeal Tribunal had erred in this way. Nor
did the appeal ground raise only a question of law.
34 Bagumya v Kakwano [2010] NSWSC 600 at [29] per Rothman J.
-- 24 of 26 --
25
[112] We agree with the respondent’s suggestion that the applicants’ contention seems to
be that, having granted leave to appeal, the Appeal Tribunal was then obliged to
rehear and make new findings in respect to the entirety of the evidence and all of the
contentions and submissions in the Tribunal. That contention is wrong because it
describes a process more akin to a hearing de novo.
[113] The Appeal Tribunal sufficiently encompassed the essential elements of a rehearing
when the Judicial Member observed:
“It is well established that, on an appeal by way of rehearing, the
Appeal Tribunal is required to conduct a real review of the hearing,
and the Member’s reasons, and make its own determination of relevant
facts in issue from the evidence, giving due deference and attaching
a good deal of weight to the Member’s view. Nevertheless, in order
to succeed on such an appeal, the appellants must establish some legal,
factual or discretionary error.”
[114] The formulation by the Appeal Tribunal can perhaps be mildly criticised as too brief
a description of the delineation between the circumstances in which an appellate
tribunal conducting an appeal by rehearing may give deference to the advantage held
by the tribunal of fact who actually heard the evidence, and those where an appellate
tribunal is in as good a position as the tribunal of fact.35 But that is not the point
which the applicants make. And even if it was, the nature of the inadequacy of the
description is not an error of law upon for which we would in the exercise of our
discretion grant leave to appeal.
[115] We would refuse leave to appeal on proposed ground 9.
Proposed ground 10
[116] This proposed ground of appeal was in these terms:
“10. The Appeal Tribunal denied the Appellants natural justice
because it erred in:
a. failing to give proper, genuine and realistic consideration
to all of relevant material, evidence and submissions
placed before it; and
b. failing to act fairly and according to the substantial merits
of the case as required by s 28(2) of [the QCAT Act].”
[117] It may be accepted that a denial of procedural fairness by an inferior tribunal will
generally involve an error of law. But as was explained at [19] above, an appeal
which must be “only on a question of law” is of a narrower ambit than an appeal in
which a question of law is merely “involved”. The very subject matter of the appeal
must be only on a question of law. The subject matter of the present appeal ground
could not be so regarded. To the contrary, it is a ground by which the applicants
invite this Court to analyse the facts of the proceeding; the entirety of the procedural
record of the conduct of the proceeding before the Appeal Tribunal; then to apply the
35 Compare Sutton v Hunter (2022) 102 MVR 343; [2022] QCA 208 at [48] to [50] per Bond JA (Crow
and Mellifont JJ agreeing) and Doerr v Gardiner [2023] QCA 160 at [65] to [70] per Morrison and
Bond JJA and Livesey AJA.
-- 25 of 26 --
26
legal standards required by the statutory prescriptions concerning proper process in
the conduct of proceeding; and to reach an evaluative judgment contrary to that
reached below. The questions being agitated would at least be mixed question of fact
and law.36
[118] We would refuse leave to appeal on this ground.
[119] For completeness, we should observe that our analysis of the limited nature of this
Court’s appellate jurisdiction pursuant to s 150 of the QCAT Act, does not mean that
there could be no remedy if there was a case in which a litigant before the Appeal
Tribunal truly had been denied procedural fairness because the Appeal Tribunal had
failed to comply with the obligations to do so expressed in s 28 of the QCAT Act.
[120] We do not exclude the possibility that such an outcome might in a particular case be
capable of being shown to have derived from an erroneous legal decision such that
an appeal ground which raised only a question of law might be framed and if resolved
in favour of an applicant, justify a grant of leave and the remedy of remission. But
even if it could not, such an error might amount to an error going to jurisdiction
thereby justifying an administrative law remedy under the Judicial Review Act37 or,
possibly, the exercise of the supervisory jurisdiction of the Supreme Court discussed
in Kirk v Industrial Court of NSW38 which jurisdiction is beyond the power of a State
legislature to exclude. It is notable that on other occasions this Court has made
declaratory orders in response to having been persuaded of the existence of such
jurisdictional error by the Appeal Tribunal.39
[121] None of these possible avenues avail the present applicants, first, because they have
not sought to engage them, and, second, because it was not reasonably arguable that
there had been any such denial by the Appeal Tribunal in this case.
[122] We would refuse leave to appeal on proposed ground 10.
Conclusion
[123] None of the proposed grounds of appeal should be the subject of leave to appeal.
Accordingly we would order that the applicants’ application for leave to appeal be
refused, with costs.
36 Bagumya v Kakwano [2010] NSWSC 600 at [44] per Rothman J.
37 The general exclusion of the application of parts 3 to 5 of the Judicial Review Act 1991 to a decision
or to the conduct of the tribunal which is expressed in s 156 of the QCAT Act is subject to the exception
“other than to the extent the decision or conduct is affected by jurisdictional error”.
38 Kirk v Industrial Court of NSW (2010) 239 CLR 531 and Citta Hobart Pty Ltd v Cawthorn (2022)
96 ALJR 476 at [20] per Kiefel CJ, Gageler, Keane, Gordon, Steward and Gleeson JJ, noting that
Owen v Menzies [2013] 2 Qd R 327 at 338 [20] per de Jersey CJ, 348 [61] per McMurdo P and 357
[103] per Muir JA found that QCAT is to be regarded as a Court of the State.
39 See, for example, Chandra v Queensland Building and Construction Commission [2014] QCA 335 at
[89] per Lyons J (with whom McMurdo P and North J agreed). Although the Court in that case also
had thought it was an appropriate case for the exercise of appellate jurisdiction, no argument to the
contrary had been presented to it: see at [87]. In our view it does not stand as authority to the contrary
of our conclusions on that question.
-- 26 of 26 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2024/024