Cai v Chen [2024] QSC 148
SUPREME COURT OF QUEENSLAND
CITATION: Cai v Chen [2024] QSC 148
PARTIES: YINGJIE CAI
(first plaintiff)
XIAMEN AO ZHONG FORTUNE INVESTMENT LTD
(second plaintiff)
v
LIHUA CHEN
(defendant)
FILE NO/S: BS 10587 of 2022
DIVISION: Trial Division
PROCEEDING: Claim
ORIGINATING
COURT:
Supreme Court of Queensland
DELIVERED ON: Date of Orders: 9 July 2024
Date of Publication of Reasons: 25 July 2024
DELIVERED AT: Brisbane
HEARING DATE: 8 and 9 July 2024
JUDGE: Bradley J
ORDERS: THE JUDGMENT OF THE COURT IS THAT:
1. the Defendant pay to the Second Plaintiff the
amount of $330,276.50;
2. the Defendant pay the Plaintiffs’ costs of the
proceeding up to and including 1 April 2024; and
3. the Plaintiffs jointly and severally pay the
Defendant’s costs of the proceeding after 1 April
2024.
THE COURT ALSO ORDERS THAT:
4. the Defendant pay the Plaintiffs’ costs of the
application filed 5 December 2022 (CFI 2); and
5. the Plaintiffs jointly and severally pay the
Defendant’s costs of the applications filed 13 April
2023 (CFI 9 and CFI 10).
CATCHWORDS: INTERPRETATION – GENERAL RULES OF
CONSTRUCTION OF INSTRUMENTS – COMMERCIAL
AND BUSINESS TRANSACTIONS – GENERALLY –
where, by a property subscription agreement (PSA), the parties
agreed that the second plaintiff would transfer ownership of
certain land (the Property) to the defendant in exchange for an
-- 1 of 11 --
2
agreed amount – where, by the PSA, the parties also agreed
they would sign a contract for the construction of a house on
the Property – where, by a letter agreement (letter agreement),
the parties agreed that the house to be constructed on the
Property would be larger than originally intended and that the
construction cost would likely be higher – where the parties
later entered into a fixed price construction contract with a
third party valued at $924,447 (construction contract) – where,
by a later written agreement, the parties agreed to sell the
Property and equally split the net profits from its sale – whether
the construction costs to be deducted from the profit are those
calculated in accordance with the letter agreement or are the
difference between the value of the construction contract and
the PSA amount
COUNSEL: S J English for the plaintiffs
M E Clarke for the defendant
SOLICITORS: H&L Legal Group for the plaintiffs
Auslaw Partners for the defendant
[1] On 9 July 2024, at the conclusion of the trial, judgment was pronounced. The parties
then made short oral submissions on costs. Costs orders were then also pronounced.
The following is an edited version of the reasons for judgment and for the costs orders
given at that time.
[2] The present dispute is about the parties’ respective entitlements to the proceeds of the
sale of a residential property at Hope Island, following a series of dealings between
about June 2014 and February 2023.
[3] The first plaintiff (Mr Cai) was born in Xiamen, a port city in Fujian Province, China.
Over the relevant time, he lived on the Gold Coast. Mr Cai was the sole director of
the second plaintiff (XAZ), a company incorporated in China, with an address in
Xiamen. He was also the sole director of Harbour Garden G.C Real Estate Pty Ltd
ACN 602 676 326 (Harbour Garden), a company incorporated in Australia. Mr Cai
was involved in residential property development in Australia. In 2014, he had a
particular interest in land at Hope Island. His company, XAZ, was dealing with
Malpha Sanctuary Cove (Development) Pte Ltd (Malpha). Malpha was the owner
of several lots at Hope Island in which XAZ had an interest.
[4] The defendant (Ms Chen) lives in Xiamen. Ms Chen is now retired. In the relevant
period, she was involved in the business of design and renovation of properties in
China. There, she purchased residential apartments and commercial properties. At
that time, Ms Chen was unfamiliar with buying and selling property in Australia.
[5] Both Mr Cai and Ms Chen are citizens of the People’s Republic of China. Neither
reads English nor speaks it fluently. Each gave evidence at the trial in Mandarin.
Their answers were translated by an interpreter. Their communications and most of
the instruments they signed were in Mandarin. Agreed translations of these
documents were admitted into evidence for the trial.
-- 2 of 11 --
3
[6] In May 2014, Ms Chen travelled to Australia for a holiday, accompanied by her
daughter and two friends. They stayed with Mr Cai in his house at Sanctuary Cove.
Mr Cai was known to another of Ms Chen’s friends. This is how they became
acquainted.
[7] While they were staying with him, Mr Cai showed Ms Chen and her companions
several properties at Hope Island, including one at 1061 Edgecliff Drive (the
Property). The property was then vacant land.
[8] Between June 2014 and April 2016, the parties executed six instruments relating to
the Property. It is convenient to deal with each of these in turn.
The property subscription agreement
[9] On 4 June 2014, shortly after Ms Chen returned to China, Mr Cai visited her. There
Mr Cai, on behalf of XAZ, and Ms Chen signed the property subscription agreement
(the PSA). By the PSA, XAZ and Ms Chen agreed that XAZ would “withdraw from
control of” the Property, “terminate the relevant contract” with Malpha, and “handle
the land transfer contract” between Malpha and Ms Chen for a purchase price of
$865,000.
[10] By the PSA, XAZ and Ms Chen also agreed that XAZ (or a construction company it
controlled) and Ms Chen would “sign the house construction contract” for $867,000.
The parties agreed that the PSA “includes the land transfer contract and the house
construction contract, which are inseparable.”
[11] By the PSA, they also agreed that, on behalf of Ms Chen, XAZ would apply
“successively” for loans from Australian banks for the land transfer contract and the
house construction contract.
[12] In the PSA, the parties stated that Ms Chen had paid Chinese yuan renminbi (CNY)
150,000 to XAZ as a “deposit”. Ms Chen agreed she would pay the “full amount” by
a “mortgage payment method”. This method would require Ms Chen to pay:
(a) CNY 1,000,000 on or before 16 June 2014;
(b) CNY 1,000,000 on or before 16 January 2015;
(c) CNY 500,000 on or before 16 May 2015; and
(d) before “property settlement”, the “balance in a lump sum according to the total
contract price minus the payment, bank loan and deposit”.
[13] In the PSA, the parties also agreed that the construction of the house would be
“subject to the floor plan approved by both parties” and that after “completion of land
settlement” Ms Chen would be “allowed to modify the drawings.” They agreed that:
“Any additional expenses incurred shall be borne by [Ms Chen]. After
negotiation and confirmation by both parties, the drawings shall come
into force after signature. It will act as a supplement to this Contract.”
The land purchase contract
-- 3 of 11 --
4
[14] In July 2014, Ms Chen signed a contract with Malpha to purchase the Property for
$865,000. Mr Cai engaged solicitors to act for Ms Chen in the purchase. He also
assisted her in a loan application to Westpac Bank. Westpac approved a loan for part
of the purchase price. Ms Chen says it was up to $610,000.
[15] On 10 December 2014, Ms Chen settled the land purchase contract. By then Malpha’s
solicitors held the $86,500 deposit (about 150,000 CNY). The balance to be paid to
Malpha (or at its direction) was $778,543.34.1 These figures are drawn from
Malpha’s solicitors’ settlement statement.
[16] The trust statement from Ms Chen’s solicitors shows that $172,589.34 was paid from
their trust account to Malpha. I infer the balance of $605,954 was advanced by
Westpac.
[17] The trust statement shows four other payments associated with the settlement of the
land purchase contract. $31,959.33 was paid to the Commissioner of State Revenue
for transfer duty. $3,300 was paid to Ms Chen’s solicitors, I infer for their legal fees.
$38.50 was paid to a settlement agent. $10 was paid to the Commonwealth Bank for
a bank cheque fee. It follows that a total of $207,897.17 was paid out of the trust
account in respect of the settlement. There remained a balance of $532.83 in the
account.
[18] The funds in the trust account came from three sources. Malpha’s solicitors had
refunded $35, as an overpayment of the deposit. Ms Chen had deposited $142,590.
Mr Cai had deposited $65,805.
[19] Ms Chen says Mr Cai alerted her to the “shortfall” of $65,805 about three business
days before settlement. Both agreed that Mr Cai would cover the shortfall and that
Ms Chen would reimburse him. Ms Chen says the agreed amount of reimbursement
was CNY 330,000. Mr Cai accepted that this was about the equivalent of $65,000.
A translation of WeChat messages passing between Mr Cai and Ms Chen’s daughter
between 5 December 2014 and 4 January 2015 include acknowledgements by Mr Cai
that he received a total of CNY330,000 into his account, at his request, in two
tranches. Mr Cai says this was a repayment for the transfer duty on the purchase
contract. According to the trust statement, the transfer duty was about half the sum
Ms Chen’s daughter deposited into Mr Cai’s account. Both witnesses lack clear
recollections of the relevant events. In the circumstances, I prefer Ms Chen’s
recollection over Mr Cai’s because it accords with the contemporaneous documentary
evidence.
First supplementary agreement
[20] On 15 January 2015, XAZ sealed and Ms Chen signed a supplementary agreement
(the first supplementary agreement).
[21] In respect of Ms Chen, the first supplementary agreement varied the PSA by changing
the date for her to pay the second instalment (CNY 1,000,000) from 16 January 2015
(see [12](b) above) to 16 April 2015, and by setting CNY 80,000 as the agreed amount
of interest payable on that amount for the four month extension period. It also
provided for the parties to agree on a new start date for construction.
1 There was a rates adjustment, requiring Ms Chen to pay Malpha $43.34.
-- 4 of 11 --
5
[22] Ms Chen’s daughter Shuya Shao also executed the first supplementary agreement. It
appears she agreed to become the purchaser of neighbouring land (Lot No. 77) at
Hope Island. By the first supplementary agreement, XAZ agreed to defer a second
instalment of CNY 1,000,000 that was also due on Lot No. 77 on 16 January 2015.
XAZ, Ms Chen and Ms Shao agreed that as Lot No. 77 and the Property “are
connected”, the commencement of construction and the handover date adjustments
made for the Property “shall apply concurrently to both properties” and “Payment
methods will be synchronized”.
Second supplementary agreement
[23] On 17 October 2015, XAZ and Ms Chen executed another supplementary agreement
(the second supplementary agreement). This is the instrument upon which XAZ
relies to make its claim and on which Ms Chen relies to make her defence. It is
convenient to set out its terms in full:
“Party A: [XAZ] (hereinafter referred to as Party A)
Party B: [Ms Chen]
ID card No.: 350204195909174029 (hereinafter referred to as Party
B)
After negotiation, Parties A and B reached a supplementary agreement
as follows:
1. Shenxian Wan2 land lot No. 77 will be built at the fastest speed
in accordance with the original contract standards.
2. After the completion of the construction, the two parties will
jointly sell the [Property] as soon as possible. The net profit
above the main contract amount of $1.732 million will be split
50/50 between A and B.
3. In order to sell the [Property] at a higher price after building, the
original standard drawings may need to be changed to a larger
set, with the extra construction costs deducted from the profit,
referring to the standard drawings and quotations (Shaobao
Chen No. 67). The extension plan is an annex to this
agreement, which will take effect after both parties confirm it.
4. About 40% of the construction cost in the early stage will be
paid by [XAZ], and about 60% of the latter amount of the
construction cost still remains with [Ms Chen] applying for a
loan. From the date of the occurrence of the interest on the loan,
to the date of the sale of the property, the interest of the
construction loan shall be paid by [XAZ] (the interest of the land
loan is still paid by Part B in accordance with the original
contract). The final net profit will be split 50/50 between A and
B.
5. After the property is sold, the sales channel party can get a total
sales commission of $60,000.
2 I understood this to be a Mandarin expression for “Sanctuary Cove”, used to describe the land to be
purchased by Ms Shao (Ms Chen’s daughter). Nothing turns on this assumption.
-- 5 of 11 --
6
6. The final settlement net profit is spit within a week.”
[24] Ms Shao did not execute the second supplementary agreement. However, in it, XAZ
and Ms Chen referred to Lot No. 77, as well as to the Property. Its limited relevance
may be that Ms Shao’s property was to “be built at the fastest speed”. Nothing turns
on this.
The confirmation letter
[25] On 15 March 2016, Mr Cai signed a confirmation letter as company representative
of Harbour Garden. Ms Chen also signed on her own behalf. By it, they confirmed
that the “building area” for the house to be constructed on the Property “has been
redesigned” to be 191.97 square metres larger than the “original size”. Harbour
Garden and Ms Chen also confirmed that:
“The construction cost per square metre is calculated at a standard rate
of AUD 2,000, with a 15% discount applied, resulting in a price of
AUD 1,700 per square metre.”
The construction contract
[26] The last instrument was the Queensland New Homes Construction Contract (the
construction contract) made between Ms Chen and Allwood Contractors Pty Ltd
(Allwood). Ms Chen signed this as the owner. Mr Cai signed as a guarantor of Ms
Chen’s obligations under the construction contract.
[27] By the construction contract, Ms Chen, Allwood and Mr Cai agreed on a contract
price $924,447. This consisted entirely of fixed price components. Ms Chen agreed
to pay the contract price according to the progress payment schedule set out in Part A
of Schedule 2 of the construction contract:
Stage Percent Amount
Deposit 5.00% $46,222.35
Base 15.00% $138,667.05
Frame (See Special Conditions) 20.00% $184,889.40
Enclosed 25.00% $231,111.75
Fixing 20.00% $184,889.40
Practical Completion 15.00% $138,667.05
Total 100.00% $924,447.00
[28] The construction contract included a special condition as an “addendum”. By it, the
parties agreed that:
“The construction of the home is to proceed to frame stage only as
defined under schedule 2 of this contract under part A of the progress
payment schedule and schedule 4 under special conditions. The
-- 6 of 11 --
7
person nominated in schedule 1 under item 7 “Owner’s Guarantors”
and under the deed of guarantee on page 12 of this contract shall be
liable to make all payments to the builder until frame stage is reached.
When [finance] is confirmed to be available to the builder as per the
clauses of this contract to fund the enclosed, fixing and practical
completion stages as set out under part A of the progress payment
schedule the works shall then [proceed] to practical [completion] but
not before.”
[29] Ms Chen did not obtain a construction loan to finance the payments to Allwood under
the construction contract. Ms Chen paid none of the progress payments to Allwood.
XAZ or Mr Cai or an associated entity made all the payments.
Sale of the Property
[30] On 22 December 2022, Ms Chen executed a contract to sell the Property for
$2,500,000. In the settlement statement, the purchaser is noted only as “Chen”. The
sale price was later adjusted downward by $50,000 to $2,450,000.
[31] On 20 February 2023, Ms Chen settled the contract to sell the Property.
[32] The parties agree that XAZ is entitled to 50% of the “net profit” under cl 2 of the
second supplementary agreement. They also agree that “the extra construction costs”
are to be “deducted from the profit” under cl 3.
[33] When the PSA was executed, the land cost was $865,000 and the construction costs
were estimated to be $867,000. The sum of these figures is the $1,732,000 specified
in cl 2 of the second supplementary agreement.
[34] By the construction contract, the parties agreed with Allwood to fix the construction
costs at $924,447. On the morning of the first day of the trial, Ms Chen admitted
certain matters Mr Cai and XAZ had pleaded about “the total price of the Property
and construction of the Dwelling”. This included an admission that the “construction
(including agreed variations)” were $924,447. This accords with the construction
contract. This admission was the basis on which Ms Chen succeeded in excluding
much of the evidence in Mr Cai’s affidavit about the costs of construction, as it was
relevant only to matters no longer in issue.
[35] It follows that the construction costs were $57,447 more than the figure in the PSA.
Plainly, this amount represents “extra construction costs” to be deducted from the
profit.
[36] Ms Chen says more than this should be deducted. She submits that the estimated
additional construction costs that can be calculated by reference to the confirmation
letter should be deducted from the profit instead of the additional amount paid by
XAZ under the construction contract. Calculated in this way, her alternative “extra
construction costs” are about $386,500.
[37] I reject that submission for the following reasons.
[38] The confirmation letter records the additional costs Ms Chen and XAZ anticipated
would be incurred in constructing a larger house on the land. As events transpired,
-- 7 of 11 --
8
according to the evidence, the additional costs were not so high. The plain language
of the parties in the second supplementary agreement is “the extra construction costs”.
The parties’ agreement makes commercial sense using this ordinary meaning of the
words. I see no warrant to interpolate the word “anticipated” in a clause about what
the parties agree is to be done after the house has been constructed. Although Ms
Chen’s alternative interpretation would have given the parties greater certainty about
the notional cost base of the venture, it would have departed from the repeated terms
of the second supplementary agreement that the “net profit” be “split 50/50” and the
“final net profit will be split 50/50” between them. In this way, it would not be
consistent with the instrument as a whole.
[39] If Ms Chen’s submission were to be accepted, the agreement would be unlikely to
give effect to the “50/50 split”. Unless the actual construction costs were exactly as
estimated, there would be either additional funds available after the sale of the
Property or a shortfall. Where, as here, the actual construction costs were less than
anticipated, the second supplementary agreement is silent about what should occur.
If the actual costs were more than the anticipated costs, then the agreement would not
deal with who was to pay the shortfall. It would not make commercial sense. Some
other agreement would be required to deal with any surplus or any shortfall.
[40] I infer that by the second supplementary agreement, the parties intended to deal
completely with their commercial relationship.
[41] In addition to reaching this conclusion on the ordinary meaning of the instrument, its
consistency and its commercial sense, I am conscious that the parties’ actual written
agreement was made in another language. It has been translated into English. The
translation is agreed. These circumstances make it less appropriate to depart from the
parties’ actual words by more narrowly defining their expressions or by interpolating
additional words in the English translation.
[42] It follows that the net profit on the sale of the Property was $660,553. This is
$2,450,000 less $865,000 (being the purchase price for the land) and less $924,447
(being the construction costs). XAZ is entitled to 50% of this amount, which is
$330,276.50.
[43] By cl 5 of the second supplementary agreement, the parties made provision for a sales
commission of $60,000. As the seller, Ms Chen was uniquely placed to prove if any
sales commission was paid and, if so, the amount. Ms Chen led no evidence that any
sales commission was paid. The settlement statement exhibited to her affidavit noted
this amount was “TBA”. In the circumstances, no amount should be deducted for any
sales commission in the calculation of the net profit.
Other matters raised on the plaintiff’s pleadings
[44] XAZ does not pursue any claim to be reimbursed for any progress payments it made
to Allwood under the construction contract. It is not necessary to deal with that
matter. Nor does it claim any loss or damage for breach of any agreement by Ms
Chen. Although the prayer for relief includes other matters, it does not appear they
are pursued.
-- 8 of 11 --
9
Mesne rents
[45] In closing submissions, counsel for Ms Chen advanced a claim for mesne rents for
the use and occupation of the Property after XAZ ceased to rent it from Ms Chen.
There is no counterclaim for such relief. It seems to feature incidentally in Ms Chen’s
defence. In any event, such a claim must fail. Mr Cai gave evidence that neither he
nor XAZ occupied and used the Property after XAZ ceased to rent it from Ms Chen.
Ms Chen has no personal knowledge of any such use or occupation. Her assertion to
the contrary cannot rise above a suspicion.
[46] Counsel for Ms Chen relied on a company search of Harbour Garden made in August
2022. It specified the Property as the registered office and principal place of business
of Harbour Garden. It also listed the Property as the address of Mr Cai, in his capacity
as a director and shareholder of Harbour Garden.
[47] By the date of the company search, Ms Chen had changed the locks to the house on
the Property. Mr Cai did not have access to keys. Neither he nor any of the companies
with which he was associated could have occupied or used the Property at that time.
Plainly, the address noted in the company search was from an earlier time. Likely, it
was during the 10-12 month period before the COVID-19 pandemic, when Ms Chen
rented the Property to Harbour Garden.
Leave to add a counterclaim
[48] At the outset of the trial, Counsel for Ms Chen sought the Court’s leave to amend her
defence to add a claim for a “set off”. On further examination, this would be a
“counterclaim” against Mr Cai under s 130 of the Land Title Act 1994 (Qld). It was
described as a counterclaim for damages for lodging a caveat over the title to the
Property when, it would be alleged, Mr Cai did not have an interest that would support
the caveat.
[49] XAZ and Mr Cai opposed leave to amend. Mr English, who appeared for them, said
they were taken by surprise at Ms Chen’s application for leave.
[50] I refused to give Ms Chen leave to make this amendment. I did so for the following
reasons.
[51] In 2022, Ms Chen filed an application seeking the removal of the caveat. The
application was adjourned as part of an agreement that Mr Cai would withdraw the
caveat, Ms Chen would sell the property, and the sale proceeds would be held in a
solicitor’s trust account pending the outcome of this proceeding. In December 2022,
Mr Cai withdrew the caveat as agreed and Ms Chen contracted to sell the Property.
The application may have been abandoned. Ms Chen did not ask for it to be listed
for hearing together with the trial.
[52] The facts necessary to establish the proposed counterclaim have not been pleaded. There
is only an incidental reference to it in the present pleadings. No loss or damage is pleaded.
No proposed pleading has been produced.
[53] The proceeding has been on foot more than two years. Ms Chen’s solicitors averted
to the possibility of a claim in a letter in December 2022. No step to advance such a
claim was taken. The first notice of a set off or counterclaim appears in two
-- 9 of 11 --
10
paragraphs of an amended outline sent by Ms Chen’s solicitors to the plaintiffs’
solicitors at about 5pm on the last working day before the trial commenced. No
explanation was offered as to the lateness of the application to add the counterclaim.
[54] The application for leave to amend took Counsel for XAZ and Mr Cai by surprise.
[55] No evidence has been adduced in support of such a counterclaim. The principal witnesses
do not speak or read English. Their evidence in chief has been prepared in written form
and translated into Mandarin for them to affirm, well in advance of the trial. The trial
was expected to last only two days. Any new evidence could not be adduced conveniently
in that way. It would be necessary to adjourn the trial. All parties resisted that course.
Costs and form of order
[56] On 9 July 2024, I invited the parties to make any submissions on costs, based on a
draft of these reasons and to.
[57] Ms Chen placed evidence before the Court that the parties engaged in a mediation in
March 2024. On 1 April 2024, Ms Chen made an offer to resolve all claims in
accordance with the principles in Calderbank v Calderbank.3 This offer was made in
the form of a deed of settlement and release executed by Ms Chen. The settlement
amount payable by Ms Chen to the plaintiffs under the offer would be $750,000. This
offer to settle was not accepted by the plaintiffs.
[58] As indicated at paragraph [42] above, XAZ is entitled to the significantly lesser sum
of $330,276.50.
[59] The offer of settlement made by Ms Chen would have encompassed all the claims
that the parties may have against each other, including those litigated in this trial.
[60] Counsel for the plaintiffs, Mr English, submitted that the plaintiffs, or one of them,
still has a claim against Ms Chen to recover the 60% of construction costs payable by
her under the second supplementary agreement. It appears the plaintiffs, or their
associated entities, paid these costs to the builder. It also appears that Ms Chen did
not borrow any necessary funds to pay those construction costs.
[61] It is not possible to reach any definitive conclusion as to the merit of a claim by XAZ
to recover 60% of the construction costs from Ms Chen. It seems unlikely that such
a claim would succeed to that full extent.
[62] Under the second supplementary agreement, Ms Chen’s obligation was to apply for
a loan to cover 60% of the construction costs. The interest on that loan to the date of
the sale of the Property was to be paid by XAZ. The loan would then be repaid from
the proceeds of the sale of the Property. If, as it appears, Ms Chen failed to obtain a
loan to cover 60% of the construction costs, then the plaintiffs would likely have
incurred the cost of sourcing those funds. The cost is likely to have been close to the
interest that would have been payable by XAZ had Ms Chen obtained the loan.
[63] Any damage the plaintiffs might have suffered, because Ms Chen failed to obtain a
loan for 60% of the construction costs, is likely to be a relatively small sum. If the
plaintiffs have a more valuable claim, they have not advanced it.
3 [1975] 3 All ER 333.
-- 10 of 11 --
11
[64] Mr English also submitted that, if the plaintiffs had accepted Ms Chen’s offer, they
would have compromised any right to recover any reserved costs in respect of three
interlocutory applications mentioned below.
[65] Taking into account the $330,276.50 judgment sum, the potential damages claim and
the right to seek reserved costs, I am satisfied that the plaintiff’s failure to accept Ms
Chen’s offer was not reasonable in the circumstances.
[66] It follows that Ms Chen should pay the plaintiffs’ costs of the proceeding up to and
including 1 April 2024, and the plaintiffs should pay Ms Chen’s costs of the
proceeding after that date.
[67] The costs reserved from Ms Chen’s application filed 5 December 2022 to remove a
caveat over the Property, in my view, should follow the outcome of the proceeding.
As they were incurred before 1 April 2024, Ms Chen should pay the plaintiffs’ costs
of that application.
[68] In respect of the costs reserved from Ms Chen’s applications filed 13 April 2023 to
join XAZ to the proceeding, and to serve the proceedings on XAZ, the position is
slightly different. XAZ was a necessary party to this proceeding for the Court to
determine Ms Chen’s rights. Mr Cai declined to join XAZ. He unsuccessfully
resisted Ms Chen’s application to do so. So, the two applications became necessary.
The plaintiffs should pay Ms Chen’s costs of those applications.
[69] It follows that:
(a) the judgment of the Court will be that:
(i) Ms Chen pay XAZ the amount of $330,276.50;
(ii) Ms Chen pay the plaintiffs’ costs of the proceeding up to and including
1 April 2024;
(iii) the plaintiffs jointly and severally pay Ms Chen’s costs of the proceeding
after 1 April 2024;
(b) the Court will order that:
(i) Ms Chen pay the plaintiffs’ costs of the application filed 5 December
2022; and
(ii) the plaintiffs jointly and severally pay Ms Chen’s costs of the
applications filed 13 April 2023.
-- 11 of 11 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2024/148