Body Corporate for the Johnson CTS 49098 v Maxcon Constructions Pty Ltd [2024] QSC 65
SUPREME COURT OF QUEENSLAND
CITATION: Body Corporate for the Johnson CTS 49098 v Maxcon
Constructions Pty Ltd [2024] QSC 65
PARTIES: BODY CORPORATE FOR THE JOHNSON CTS 49098
(plaintiff)
v
MAXCON CONSTRUCTIONS PTY LTD
ACN 152 259 820
(defendant)
FILE NO: BS 10826 of 2022
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 20 May 2024
DELIVERED AT: Brisbane
HEARING DATE: 9 February 2024
JUDGE: Martin SJA
ORDER: The application is dismissed.
CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN STATE AND
TERRITORY COURTS – JOINDER OF CAUSES OF
ACTION AND OF PARTIES – PARTIES – GENERALLY –
where the plaintiff, a body corporate for a community title
scheme, alleges that the then owner of the land contracted
with the defendant to undertake design and construction
works – where the plaintiff alleges that it is subrogated to the
rights of the original owner under the contract – where the
plaintiff alleges both the design and construction works were
defective – where defendant’s defence pleads that the design
and construction agreement was a sham – where the
defendant pleads that the then owner, not the defendant,
engaged design consultants – where the plaintiff applies to
join a new defendant – where the plaintiff alleges, in the
alternative, that the proposed defendant undertook the design
work – where the proposed defendant argues there is no
evidence of a sham or of the proposed defendant’s
involvement – whether the proposed defendant should be
joined to the proceeding
PROCEDURE – CIVIL PROCEEDINGS IN STATE AND
TERRITORY COURTS – JOINDER OF CAUSES OF
ACTION AND OF PARTIES – MATTERS RELATING TO
-- 1 of 10 --
2
LIMITATION PERIOD – where proposed defendant argues
application to join brought outside limitation period –
whether application to join falls within provisions of r 69(2)
Uniform Civil Procedure Rules 1999 (Qld)
Limitation of Actions Act 1974 (Qld), s 38
Uniform Civil Procedure Rules 1999 (Qld), r 69(1), r 69(2), r
74
Allianz Australia Insurance Ltd v Haddad [2015] NSWCA
186, cited
Aqwell Pty Ltd v BJC Drilling Services Pty Ltd [2007] QSC
140, distinguished
Hutchinson v Equititour Pty Ltd [2011] 2 Qd R 99; [2010]
QCA 104, cited
IMDM (Townsville) Pty Ltd v City Pacific Ltd [2009] QSC
445, cited
Interline Hydrocarbon Inc v Brenzil Pty Ltd [2006] 2 Qd R
454; [2006] QSC 184, considered
Kestrel Coal Pty Ltd v Longwall Roof Supports Ltd [2003]
QSC 187, cited
Universal Music Australia Pty Ltd v Cooper [2004] FCA 78,
cited
COUNSEL: M C Long for the plaintiff
B W J Kidston for the defendant
B A Reading for Asian Pacific Building Corporation
SOLICITORS: Robinson Locke for the plaintiff
Diakou Faigen for the defendant
McCullough Robertson for Asian Pacific Building
Corporation
[1] The plaintiff (Johnson) applies to join Asian Pacific Building Corporation (AP
Building) as the second defendant in this proceeding and seeks leave to amend the
Claim and Statement of Claim. Questions concerning limitation periods arise and,
so, it is necessary to give some detail of the times at which certain events occurred.
A brief history of this matter
[2] In the middle of 2015 construction work began on the old Main Roads building in
Boundary Street, Spring Hill to convert it into a building which incorporated
commercial premises, residential units and hotel rooms. Johnson alleges that that
occurred by the then owner of the land – Asian Pacific Group Pty Ltd (AP Group) –
contracting with the defendant (Maxcon) to undertake the design and construction
work (the WUC).
[3] The work on the building was done and a certificate of classification was issued no
earlier than 9 September 2016. Three days later the building was converted into
separate strata titles with a number of separate bodies corporate. Johnson was the
Principal Body Corporate.
[4] Johnson is entitled to bring a claim like this because it is subrogated to the rights of
the original owner under the contract to the extent that the contract applies to work
-- 2 of 10 --
3
affecting scheme land that is common property - s 36(3)(a) of the Body Corporate
and Community Management Act 1997 (BCCM Act).
[5] On 8 September 2022 Johnson commenced proceedings against Maxcon. It alleged
that the design and construction work was subject to a series of “Design Defects”
and “Construction Defects”. The existence of those defects, the extent and cost of
any rectification, and Maxcon’s liability are all in issue.
Maxcon alleges that the Contract was a “sham”
[6] On 30 January 2022, Maxcon filed its Defence. For the purposes of this application,
the important part of Maxcon’s Defence is its assertion that the contract between AP
Group and Maxcon was a sham. It says that it agreed with AP Group that it would
build, but not design, the building. Maxcon does not identify in its pleadings who,
under the True Contract, was responsible for the design of the building.
[7] Maxcon pleads:
(a) the parties to the Contract (AP Group and Maxcon) did not intend to create a
legally enforceable agreement upon entering into the Contract;
(b) it was the intention of the parties that:
(i) the Contract would not form the terms upon which Maxcon would
carry out the building work; and
(ii) Maxcon would be engaged as builder in relation to the original land,
and perform the True WUC thereunder, pursuant to the terms of the
“True Contract” – the terms of the True Contract being partly oral
and partly by conduct;
(c) AP Group engaged the design consultants in respect of the True Contract;
(d) Maxcon did not engage the design consultants and the Design Consultant
Contracts were not novated to the defendant; and
(e) in the premises the Contract was not intended to be operated or completed in
accordance with its terms, it is unenforceable, and a sham.
[8] This assertion came as a surprise to Johnson.
[9] On 2 February 2023, particulars of the Defence and disclosure were sought.
[10] On 10 August 2023, Maxcon was ordered to provide further and better particulars of
the Defence and further disclosure including with respect to the alleged sham
contract.
[11] Maxcon gave disclosure on 19 September 2023. It filed the further and better
particulars on 16 October 2023.
[12] This application was filed on 5 December 2023.
The basis of Johnson’s application to join AP Building
[13] On the joinder application, Johnson relies on r 69(1) of the Uniform Civil Procedure
Rules 2001. It provides:
“The court may at any stage of a proceeding order that –
…
-- 3 of 10 --
4
(b) any of the following persons be included as a party –
…
(ii) a person whose presence before the court would be
desirable, just and convenient to enable the court to
adjudicate effectually and completely on all matters in
dispute connected with the proceeding.”
[14] If an order is made under r 69(1), then r 74 provides:
“(4) If an order is made including or substituting a person as a
defendant or respondent, the proceeding against the new
defendant or respondent starts on the filing of the amended
copy of the originating process.
(5) However, for a limitation period, a proceeding by or against a
new party is taken to have started when the original proceeding
started, unless the court orders otherwise.”
Have the provisions in r 69(1) been met?
[15] An applicant relying on this rule bears the onus of establishing that the presence of
the proposed party:
(a) would be desirable, just and convenient,
(b) to enable the court to adjudicate effectually and completely on all matters in
dispute.
[16] Johnson proposes that the “presence” of AP Building be effected by joining it as a
defendant to the proceedings. Its proposed Statement of Claim maintains the
allegations against Maxcon and pleads an alternative claim against AP Building
based upon the same alleged breaches.
[17] Johnson relies only on the pleading by the current defendant of a sham contract as
the basis for its application. It produces no evidence that the assertions have any
basis.
[18] An applicant under this rule must be able to identify a dispute with the party they
seek to join and show a prima facie case1 that it would be desirable, just and
convenient to join the proposed defendant.
[19] In assessing whether a case has been made the court should, as it is exercising a
discretion, consider the merits of the proposed case, at least where there are
significant doubts concerning its prospects of success.2 A slightly stricter expression
of the test was advanced by Tamberlin J in Universal Music Australia Pty Ltd v
Cooper3 namely, that regardless of what another party has pleaded against an
applicant for such relief, it is still necessary for that applicant to demonstrate the
existence of an arguable case, and one that is sufficient to resist the entry of
summary judgment by the party sought to be joined.
1 IMDM (Townsville) Pty Ltd v City Pacific Limited [2009] QSC 445; see also Tiu-Hsiao v Australian
Sharemarket Fund Pty Ltd (unreported, Beach J, Supreme Court of Victoria, 24 June 1994).
2 Kestrel Coal Pty Ltd v Longwall Roof Supports Ltd [2003] QSC 187.
3 [2004] FCA 78 at [6]-[7].
-- 4 of 10 --
5
[20] The words in r 69(1) direct attention to whether the joinder of the proposed part
would be “desirable, just and convenient”. There are decisions in which the mere
pleading of a case against a proposed defendant in a draft statement of claim has
been regarded as sufficient to justify joinder – see, e.g., Aqwell Pty Ltd v BJC
Drilling Services Pty Ltd4 – but that was a case in which the identity and
involvement of the proposed defendants were not in doubt.
Should AP Building be joined?
[21] This is not a case where the argument is about the existence of negligence or
damages but about the identity of the contracting party. This application is founded
upon Maxcon’s denial that it was a party to the true contract relied on for the design
and construction of the building. Given the requirements for the careful pleading of
such a defence then those allegations are sufficient to raise a doubt about whether
the proceeding was started in or against the name of the right person as a party. But
that is not enough. The merits of the proposed case must be considered and that
necessarily involves the identity of the proposed defendant.
[22] In answer to the question: “Why have you chosen this particular respondent, Asian
Pacific Building Corporation?”. Mr Long responded: “The answer to that is in the
further and better particulars of the defence that were provided …”. He directed me
to paragraphs 2 and 3 of those particulars. They were particulars of paragraph 40 of
the Defence. That paragraph concerns the allegation that the True Contract was
constituted in part by conduct and that the conduct was made up of the following:
(a) AP Group entering into the Design Consultant Contracts;
(b) Maxcon carrying out the True WUC;
(c) neither AP Group nor Maxcon requiring the Design Consultant Contracts to
be novated to Maxcon;
(d) AP Group giving directions to Maxcon in relation to the design of the
building;
(e) Maxcon issuing payment claims to AP Group in accordance with the True
Contract Construction Price; and
(f) AP Group paying Maxcon in accordance with the True Contract Construction
Price.
[23] The particulars given were:
(a) the variations and directions carried out by Maxcon comprising the True
WUC (in addition to the Design) are those set out in the documents contained
in the architect’s advice folders named “AA-001” to “AA-213”; and
(b) the date and substance of each alleged direction are those set out in the
documents contained in the architect’s advice folders named “AA-001” to
“AA-213”.
[24] The material which was said to identify AP Building as the architect of the project
was not exhibited. In Johnson’s written submissions it is contended that it is
4 [2007] QSC 140 where Helman J adopted the approach of McGill DCJ in Cooper v Dexter [2003]
QDC 31.
-- 5 of 10 --
6
Maxcon’s case that AP Building performed the design work. That cannot be drawn
from Maxcon’s pleading.
[25] In his submissions, Mr Long accepted that there was no evidence to suggest any
involvement by AP Building, but he contended that while the evidence was not
before the court, the proposed new defendant had not responded to any of the
allegations in the proposed Statement of Claim. That, he said, was the basis upon
which the case was brought.
[26] When the identity of a proposed defendant is in dispute, as it is in this case, an
applicant must show, at least, why it is just that the respondent be joined as a
defendant. That has not been done in this case. It is not sufficient to say that the
proposed Statement of Claim is based upon material (not seen by the court) and that
identifies the proper defendant.
[27] According to Mr Reading there is evidence which shows that the contract sued upon
was not a sham. He took me to documents which, on their face, show that Maxcon
had claimed payment during the project for numerous types of “design work”
performed by “design consultants” novated to it. So far as the proposed amended
pleading is concerned, there are five “design defects” pleaded against AP Building.
AP Building submits that the pleading does not identify any drawings said to be
created by it.
[28] The applicant has not established a prima facie case that AP Building was a party to
any contract let alone the “True Contract” alleged by Maxcon. With Johnson having
failed to establish that AP Building’s presence before the court would be desirable,
just, and convenient the application should be dismissed,
Have the conditions in r 69(2) been met?
[29] I will consider this point in case I have erred in my conclusion above and r 69(1)
has been satisfied.
[30] Johnson seeks damages for breach of contract and pleads that the building design
had the design defects “as at on or about 9 September 2016”. For the purposes of
the limitation period for a breach of contract, time begins to run from the date of
breach.5 Proof of damage is not an element of a claim for breach of contract. This
distinguishes a claim for breach of contract from a claim for negligence in, say, the
construction of a building. In that case, negligence is only actionable on proof of
damage and it is only on such a claim that issues of when the design defects became
manifest are relevant.
[31] Johnson argues that there is currently no pleading or evidence as to the extent to
which the design defects were latent, or manifest, and when.
[32] On the state of the proposed amended pleading, Johnson demonstrates that the
limitation period has passed.
[33] AP Building argues that, as the relevant limitation period has expired, it should not
be joined unless one of the criteria identified in r 69(2) is satisfied.
[34] Where a limitation period has expired, then r 69(2) confines the circumstances in
which the power to add a party can be exercised. Rule 69(2) provides grounds upon
5 Allianz Australia Insurance Ltd v Haddad [2015] NSWCA 186 at [21].
-- 6 of 10 --
7
which a party can be added after the end of the limitation period. In this case,
Johnson relies upon the following parts of that rule:
“(2) However, the court must not include or substitute a party after
the end of a limitation period unless 1 of the following
applies—
(a) the new party is a necessary party to the proceeding
because—
…
(iii) the proceeding was started in or against the name of
the wrong person as a party, and, if a person is to be
included or substituted as defendant or respondent,
the person is given notice of the court’s intention to
make the order; or
(iv) the court considers it doubtful the proceeding was
started in or against the name of the right person as
a party, and, if a person is to be included or
substituted as defendant or respondent, the person is
given notice of the court’s intention to make the
order;”
[35] The requirements of r 69(2) were considered by Muir J in Interline Hydrocarbon
Inc v Brenzil Pty Ltd.6 For these purposes, the following reflects Muir J’s
conclusions:
(1) Rules 69(2)(a)(iii) and 69(2)(a)(iv) are not limited in their application to cases
of misnomer.
(2) Rule 69(2)(a)(iv) might operate in circumstances in which there was (and
remained) a good cause of action against an initial defendant, who was to
remain a defendant in the proceeding.
(3) An explanation for a failure to join a party within time would always be
relevant, but was not a precondition of the power to order a joinder.
(4) That accordingly in circumstances in which it was arguable that only one of
two corporations potentially liable was sued and the corporation sued was the
other's agent or alter ego, an order for joinder of the other corporation would
be made under r 69(2)(a)(iv).
[36] If, contrary to my finding above, Johnson has shown that there was a reasonable
argument that AP Building was the entity which contracted with AP Group to
provide the design work, then that would satisfy r 69(2)(iv).
Was the commencement of the limitation period postponed?
[37] Johnson also sought to rely on s 38(1) of the Limitation of Actions Act 1974 (LAA).
It provides:
6 [2006] 2 Qd R 454. His Honour considered and applied the High Court’s decision in Bridge Shipping
Pty Ltd v Grand Shipping SA (1991) 173 CLR 231.
-- 7 of 10 --
8
“(1) Where in an action for which a period of limitation is
prescribed by this Act—
(a) the action is based upon the fraud of the defendant or the
defendant’s agent or of a person through whom he or she
claims or his or her agent; or
(b) the right of action is concealed by the fraud of a person
referred to in paragraph (a); or
(c) the action is for relief from the consequences of mistake;
the period of limitation shall not begin to run until the plaintiff has
discovered the fraud or, as the case may be, mistake or could with
reasonable diligence have discovered it.”
[38] That provision does not assist Johnson at this point. The onus of establishing the
facts necessary to come within s 38 LAA lies on Johnson – see Hutchinson v
Equititour.7 The basis for Johnson’s assertion on this point is the pleading by
Maxcon – nothing else was relied upon.
[39] Section 38(1)(b) requires that the right of action is concealed by the fraud of “the
defendant or the defendant’s agent or of a person through whom he or she claims or
his or her agent”. In this case, the contract was not executed by an agent of AP
Building. The evidence shows that there is a person who is a director of both one of
the parties who executed the contract and AP Building, but that does not establish
agency.
[40] Further, it is not suggested that AP Building or its agents represented to Johnson
that the “sham” contract was the actual document upon which the construction and
design work were based.
Are there discretionary grounds upon which relief should be refused?
[41] AP Building proposes a number of discretionary matters which would tell against
granting an order that it be joined.
There is no evidence to explain why Johnson could not have discovered the alleged
“sham” sooner.
[42] Mr Long submits that, before the Defence was filed, Johnson had no knowledge of
and no way of knowing about the “sham contract”. That, though, does not explain
the delay in commencing the action – one day before the limitation period expired.
[43] While delay is a matter to be taken into account, the more relevant factor is the
consequences of delay.
Passage of time and prejudice
[44] Mr Faigen is a solicitor and the Group Counsel and Development Director of the
Deague Group of Companies of which AP Building is a part. In his affidavit he
gives evidence of attempts to “obtain access to the books and records (both
electronic and hard copy) maintained by Asian Pacific Corporation from the period
at or about the time of the Project the subject of the D&C Contract.” He gives
evidence of contacting 5G Networks, a company contracted by Asian Pacific
7 [2011] 2 Qd R 99 at [27].
-- 8 of 10 --
9
Building as “an external information technology service provider.” While he could
not recall the name of the person he spoke to, he was informed that, “given the
passage of time since the Project was complete” “limited documentary records in
electronic form relating to the Project exist”, some documents may “not have been
retained in electronic form” and 5G Networks’ attempts to retrace the records were
still taking place at the time of making his affidavit.
[45] The evidence is equivocal. It does not go so far as to say that documents cannot be
obtained, only that it may be difficult to do so.
[46] It cannot go unnoticed that one of AP Building’s directors was involved with the
creation of the “sham” contract. There is nothing to suggest that he is unavailable or
unable to give instructions on these matters.
The pleading is deficient
[47] Mr Reading pointed to two aspects of the pleading as being deficient:
(a) first, schedule 1 of the Statement of Claim outlines the alleged defects and
labels a series of defects as both design and construction defects. He argued
that A P Building “can’t identify on the face of this what design of [AP
Building] is said to be defective or why” and further, that “there’s no
allegation here that references a drawing apparently authored by [AP
Building]”.
(b) secondly, schedules 3 to 5 provide tables of alleged rectification costs,
consultants’ costs, and scheme land damage and rectification costs,
respectively. Mr Reading submitted, with respect to sch 5, that “it’s
impossible, on the face of this schedule, to tell whether or not it’s alleged that
[AP Building’s] design caused this defect and how, if that’s what’s alleged, or
whether it’s a construction defect.”
[48] Both of those are reasonable criticisms but do not make the pleading irreparable
and, if AP Building is joined, can be cured by appropriate particulars.
[49] None of the matters advanced under this heading are of such a magnitude as to
require a refusal of the application.
Can Johnson be subrogated to the extent that it can sue on the design work?
[50] Johnson’s claim is contingent on its subrogation to the rights of Asian Pacific Group
held under the alleged “Design Contract”. That subrogation is pleaded to arise by
operation of s 36(3)(a) of the BCCM Act, which (broadly) provides that where “a
contract is entered into to have work carried out on land that becomes scheme
land… the body corporate is, on the establishment of the scheme, subrogated to the
right (if any) of the original owner” as relevant to scheme land that is common
property.
[51] AP Building argued that, even assuming the design contract existed as pleaded, it
was not performance of “work carried out on the land” but instead performance of
architectural services. Thus, it was argued, there could be no subrogation.
[52] Mr Long resisted the resolution of that question of construction on the interlocutory
application, given the factual analysis of the agreement which he submitted would
be required.
-- 9 of 10 --
10
[53] This is not a matter which can be decided at this point. Whether design work or
architectural services can be “work carried out on the land” will be mixed question
of fact and law and not suitable for decision at an interlocutory stage.
Orders
[54] The application is dismissed.
[55] I will hear the parties on costs.
-- 10 of 10 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2024/065