Canadian Solar Construction (Australia) Pty Ltd v Re Oakey Pty Ltd [2024] QSC 27
SUPREME COURT OF QUEENSLAND
CITATION: Canadian Solar Construction (Australia) Pty Ltd v Re Oakey
Pty Ltd [2024] QSC 27
PARTIES: CANADIAN SOLAR CONSTRUCTION (AUSTRALIA0
PTY LTD (ACN 620 225 630)
(plaintiff)
v
RE OAKEY PTY LTD (ACN 160 581 626)
(defendant)
FILE NO/S: BS11591/23
DIVISION: Trial
PROCEEDING: Originating Application
ORIGINATING
COURT:
Supreme Court
DELIVERED ON: 5 March 2024
DELIVERED AT: Brisbane
HEARING DATE: On the papers
JUDGE: Freeburn J
ORDER: The defendant pay the plaintiff’s costs of the proceeding.
CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN STATE AND
TERRITORY COURTS – COSTS – OFFERS OF
COMPROMISE, PAYMENTS INTO COURT AND
COMPROMISE – INFORMAL OFFERS AND
CALDERBANK LETTERS – where plaintiff seeks costs
calculated on an indemnity basis, after the day of service of
an offer to settle – where plaintiff says offer was to settle
claim – where letter accompanying offer was sufficiently
detailed so as to allow plaintiff to pursue other claims against
defendant – where the defendant had its own counterclaims
against the plaintiff - whether plaintiff obtained order no less
favourable than the offer
PROCEDURE – CIVIL PROCEEDINGS IN STATE AND
TERRITORY COURTS – COSTS – TAXATION AND
OTHER FORMS OF ASSESSMENT – GST
CONSIDERATIONS – where plaintiff seeks costs with order
of GST under payment claim – whether defendant should pay
GST where absence of applications or supporting material
PROCEDURE – CIVIL PROCEEDINGS IN STATE AND
TERRITORY COURTS – COSTS – INTEREST ON COSTS
– where plaintiff contends it is entitled to compound interest
-- 1 of 7 --
2
and defendant contents it is to pay simple interest – whether s
67P of the Queensland Building and Construction
Commission Act 1991 requires the payment of compound
interest
COUNSEL: M Steele KC and BA Reading for the plaintiff
AC Stumer KC and AP McKinnon for the defendant
SOLICITORS: Norton Rose Fulbright Australia for the plaintiff
Thomson Geer for the defendant
REASONS
[1] There was a trial of this proceeding on 29 and 30 November 2023. On
15 December 2023 the court made two orders, namely:
1. Pursuant to section 78(2)(a) of the Building Industry Fairness (Security of
Payment) Act 2017, the defendant pay to the plaintiff the sum of $4,030,714.74
(excluding GST);
2. The defendant pay to the plaintiff interest on that sum of $4,030,714.74
calculated pursuant to section 67P of the Queensland Building and
Constructions Commission Act 1991 (Qld).
The parties were to be heard on costs. The orders and reasons are published at
Canadian Solar Construction (Australia) Pty Ltd v Re Oakey Pty Ltd.1
[2] The parties have subsequently filed written submissions on costs and on two other
issues.
Costs
[3] On 14 November 2023, that is about two weeks before the trial, the plaintiff’s
solicitors wrote to the defendant’s solicitors enclosing an offer to settle. The offer
was in these terms:
1. The Plaintiff offers to settle all the claims and counterclaims in
this proceeding on the conditions set out in this offer.
2. The Defendant pay the Plaintiff $3,085,000.00 (excluding GST)
within 28 days of acceptance of the offer.
3. The application filed 15 September 2023 be dismissed.
4. Each party bear its own costs.
[4] In an accompanying letter, the plaintiff’s solicitors explained their client’s offer in
this way:
1 [2023] QSC 288.
-- 2 of 7 --
3
2 We attach the Plaintiff’s Offer to Settle. The Plaintiff offers to
settle all the claims and counterclaims in the proceeding on the
conditions set out in the Offer to Settle.
3 The amount of $3,085,000.00 (excluding GST) comprises the
following amounts claim in Progress Claim No. 64 dated 26 June
2023:
(1) $635,000.00 (excluding GST) in relation to Milestone 4 (4
of 4) Project Management;
(2) $2,000,000.00 (excluding GST) in relation to Milestone 33
Substantial Completion; and
(3) $450,000.00 (excluding GST), being 50% of the amount
claimed for “Construction work carried out by the
Contractor and claimable pursuant to clause 24.7 and
clause 39.2(b) of the EPC Contract”.
4 If accepted, the Defendant [presumably this was a mistake and was
intended to refer to the Plaintiff] will withdraw Progress Claim
No. 64 insofar as it claims payment for:
(1) $57,766.42 (excluding GST) in relation to Variation No. 02
– ON Connection rev 2;
(2) $230,876.07 (excluding GST) in relation to Variation No. 05
– Rev 4 – Additional Harmonics Studies;
(3) $207,072.25 (excluding GST) in relation to Variation No. 07
– Additional GPS Modelling; and
(4) $450,000.00 (excluding GST), being 50% of the amount
claimed for “Construction work carried out by the
Contractor and claimable pursuant to clause 24.7 and
clause 39.2(b) of the EPC Contract”
(together, Remaining Claims).
5 For the avoidance of doubt, the Plaintiff reserves its right to claim
payment from the Defendant in relation to the Remaining Claims
pursuant to the Contract, but not pursuant to Progress Claim No.
64.
[5] The critical issue is the nature of the offer made by the plaintiff. Or, put another way,
if the offer was accepted, and the defendant paid $3,085,000 to the plaintiff, what
would be the effect of that acceptance and payment?
[6] Canadian Solar contends that Oakey’s non-acceptance of the offer engages rule 360
of the Uniform Civil Procedure Rules 1999 (Qld) (UCPR) because Canadian Solar’s
offer to accept $3,085,000 was, to use the language of rule 360, “no less favourable
than the offer”. In other words, the overall effect of the judgment is that the defendant
is required to pay $4,030,714 to the plaintiff as compared with the offer sum of
$3,085,000.
-- 3 of 7 --
4
[7] For that reason, Canadian Solar contends that the court should order the defendant to
pay the plaintiff’s costs on the standard basis up to the date of the offer and on an
indemnity basis from that date onwards. That general rule is the effect of rule 360,
unless the defendant shows that another order for costs is appropriate in the
circumstances.
[8] Canadian Solar points out that its offer was to settle only its claim in the proceeding.
However, that is not strictly accurate. The offer made was to settle “all the claims
and counterclaims in this proceeding”. Canadian Solar’s claim was for $4,030,714
pursuant to s 78(2) of the Building Industry Fairness (Security of Payment) Act 2017
(BIF Act). However, Oakey’s counterclaim was for:
(a) an injunction restraining Canadian Solar from enforcing payment of Payment
Claim 64 (PC64) in reliance on s 77 or 78 of the BIF Act;
(b) damages pursuant to s 236 of s 237 of the Australian Consumer Law (ACL) in
the amount of any liability it had to Canadian Solar in respect of PC64;
(c) damages pursuant to s 236 or s 237 of the ACL in the amount of the costs it has
incurred and is incurring in the present proceeding.
[9] And so, whilst it is true that Canadian Solar’s claim was confined to a claim under
s 78 of the BIF Act (and interest and costs) Oakey did not merely defend that case.
Oakey had its own counterclaims. And so, I reject the plaintiff’s contention that the
only dispute agitated was Canadian Solar’s claim for $4,030,714.
[10] The letter accompanying the offer explained the offer. As can be seen from paragraph
3 of the letter (quoted above), the offer of $3,085,000 was expressed to comprise three
components. Those components comprised two milestones and 50% of the amount
claim for amounts claim for “Construction work carried out by the Contractor and
claimable pursuant to clause 24.7 and clause 39.2(b) of the EPC Contract”.
[11] The letter also explained that, if the offer was accepted, Oakey was to withdraw PC64
in so far as it made four remaining claims, and Canadian Solar reserved its right to
pursue those four remaining claims – but it would not do so pursuant to PC64. Those
four remaining claims totalled roughly $945,000.
[12] It follows that what Canadian Solar proposed by means of its offer differs from the
orders made by the court. What the offer proposed was an adjustment of the parties’
rights under PC64. Under the court’s order Oakey was required to pay PC64 but
appreciating that any payment under s 78 of the BIF Act is in effect an interim
payment on account because of the effect of s 101 of the BIF Act. On the other hand,
under the offer, as explained by the covering letter, roughly $3m was to be paid for a
reduced PC64 and rights were reserved for a further $945,000.
[13] Of course, in some cases, the offer made is in effect a standalone offer and there is no
need to consider the accompanying letter. And, in some cases, the letter from a
solicitor accompanying an offer under the rules may merely explain the constituent
elements of the offer. But that is not this case. Here the letter accompanying the offer
went beyond merely explaining the offer. The letter specified that PC64 was to be
withdrawn in so far as it made the four remaining claims totalling $945,000, and that
Canadian Solar reserved its right to pursue those four remaining claims – but
explained that it would not do so pursuant to PC64.
-- 4 of 7 --
5
[14] In the circumstances the accompanying letter was designed to be read with the offer.
The letter should be considered, first, in making the comparison which rule 360
requires and, second, in deciding whether Oakey has shown whether another order
for costs is appropriate.
[15] As to the first aspect, the letter is clearly designed to explain the basis for the offer
and how the proposed altered rights of the parties under PC64 are to work. No
evidence explains why the court’s decision of an “interim” $4m gives a less
favourable result than the offer which prescribes adjusted rights under PC64, with a
payment of $3m now, and with a reservation of rights in relation to the balance.
[16] As to the second aspect, Oakey was entitled to read the letter with the offer. That was
what Canadian Solar’s solicitors intended. They intended, for example, that their
client’s rights to make the remaining claims be reserved.
[17] Canadian Solar contended that acceptance of the offer would not have determined the
parties’ underlying substantive dispute. That is true. The parties are presently
engaged in an arbitration. Their final, rather than interim, rights are yet to be
determined. However, the acceptance of the offer would have altered the parties’
interim rights. Instead of having a claim for $4,030,714 pursuant to PC64, Canadian
Solar would receive a payment of $3,085,000, and Oakey’s counterclaims would be
extinguished, and Canadian Solar would preserve its rights to claim a further
$945,000 for the remaining claims.
[18] It follows that the evidence does not establish, and I am not satisfied that the offer is
‘no less favourable’ than the court’s decision. This is certainly not a case where it is
appropriate to simply compare the offer of $3m against the judgment of $4m. The
comparison is more complex than that. The adjusted rights of the parties under the
offer may or may not be more favourable for Oakey. Much depends on future events,
namely, what was to happen with the remaining claims, and whether and when they
were prosecuted, and how they were to be resolved, the costs of resolving them.
[19] In any event, the letter and its reservation of rights, placed Oakey in a position where
it was comparing apples and oranges. On the one hand, Oakey could chance its arm
in the litigation which, if it lost, would result in an order that it pay $4m but subject
to a final adjustment of the parties’ rights. On the other hand, it could chance its arm
under the adjusted rights scheme proposed in the offer whereby it was required to pay
$3m, presumably also on an interim basis, but it may well have faced an uncertain
future with the four remaining claims totalling $945,000.
[20] Of course, one factor relevant here is whether there is evidence which establishes that
Oakey was acting unreasonably to chance its arm in the litigation. I do not think that
is the case. In my view, the uncertainty of the position under the offer means that
Oakey has shown whether another order for costs is appropriate, that is, the usual
order that costs follow the event.
[21] It follows that the plaintiff should have its costs on the standard basis.
GST
[22] The claim that Canadian Solar made was for “$4,030,714 (excluding GST)”. That is
the sum and the expression reflected in the judgment.
-- 5 of 7 --
6
[23] Canadian Solar, having obtained the order it sought, now seeks an order that Oakey
is liable to pay the GST claimed within PC64, being the total sum of $313,071.47.
[24] There are, as Oakey submits, two distinct issues. The first is whether the order made
by the court on 15 December 2023 requires the payment of GST. Plainly, the order
did not require the payment of GST. No such order was sought.
[25] Canadian Solar seeks to make submissions as what components of PC64 are subject
to GST. However, there is no application to amend the claim made in the proceeding,
and no application to re-open the evidence (so as to admit a further affidavit of Mr
Ruttledge), and no application to vary the orders made.
[26] In the absence of those applications, and material supporting the applications, I
decline to make the order requested.
[27] The second issue is whether Oakey is liable to pay GST on the amount stated in PC64.
That issue does not require resolution because of the absence of any of the
applications referred to above.
[28] Of course, the orders made by the court did not purport to restrict or alter or even
declare the parties’ rights under the GST legislation.
Interest
[29] The parties also disagree on the calculation of interest. Canadian Solar contends that
it is entitled to compound interest. Oakey disagrees and has paid simple interest.
[30] Pursuant to the judgment on 15 December 2023 (quoted above) interest is to be
calculated pursuant to s 67P of the Queensland Building and Construction
Commission Act 1991. That section provides:
(1) This section applies if—
(a) the contracting party for a building contract is required to
pay an amount (the progress amount) to the contracted party
for the building contract; and
(b) the progress amount is payable as the whole or a part of a
progress payment; and
(c) the time (the payment time) by which the progress amount
is required to be paid has passed, and the progress amount,
or a part of the progress amount, has not been paid.
(2) For the period for which the progress amount, or the part of
the progress amount, is still unpaid after the payment time, the
contracting party is also required to pay the contracted party
interest at the penalty rate, as applying from time to time, for
each day the amount is unpaid.
(3) In this section—
penalty rate means—
(a) the rate made up of the sum of the following—
-- 6 of 7 --
7
(i) 10% a year;
(ii) the rate comprising the annual rate, as published from
time to time by the Reserve Bank of Australia, for 90
day bills; or
(b) if the building contract provides for a higher rate of interest
than the rate worked out under paragraph (a)—the higher
rate.
[31] Canadian Solar distinguishes between the use of the words “progress amount” and
“the amount” in s 67P(2). However, in my view, the latter expression is merely
shorthand for the former. The section merely requires interest to be paid for each day
the sum is unpaid. I do not read s 67P(2) as requiring the payment of compound
interest.
[32] As Oakey points out, that view is consistent with the simple interest calculation in
Built Qld Pty Ltd v Pro-Invest Australian Hospitality Opportunity (ST) Pty Ltd
(No. 2)2 at [6]-[8].
[33] It follows that there is no need to make any further orders regarding interest.
2 [2021] QSC 301.
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2024/027