Chatfield v Burdon [2024] QCAT 607
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Chatfield v Burdon [2024] QCAT 607
PARTIES: KRISTY CHATFIELD
(applicant)
v
ZACK BURDON
(respondent)
APPLICATION NO/S: BDL270-23
MATTER TYPE: Building matters
DELIVERED ON: 6 December 2024
HEARING DATE: 6 July 2024
HEARD AT: Cairns
DECISION OF: Member Pearce
ORDERS: The respondent is to pay the applicant the amount
of $12,384.00 within 28 days of the date of this order.
CATCHWORDS: BUILDING MATTERS – Domestic building dispute – the
qualification rule that the rectification proposed be
reasonable.
Queensland Building and Construction Commission Act
1991 (Qld), s 77, s 79
APPEARANCES &
REPRESENTATION:
This matter was heard and determined on the papers
pursuant to s 32 of the Queensland Civil and Administrative
Tribunal Act 2009 (Qld)
REASONS FOR DECISION
Background
[1] On 12 September 2021 the applicant entered into a contract with the respondent for
building works to be carried out at her home at 14 Wright Court, Upper Coomera. The
works were in the nature of building a deck onto the applicants’ property. The works
commenced on 4 October 2021 and completed on 21 October 2021. The total costs
under the contract were $15,774.00 and the applicant paid these costs in full.
[2] The applicant alleges there are the following problems with the deck:
(a) Cement footing not mounded
(b) Incorrect screws used
(c) One section to close to the ground
(d) Stairs not secured
-- 1 of 3 --
2
(e) Rubber stripping joy tape missing
(f) Stars not secured to ground.
[3] The applicant states the respondent was to return to fix the issues however failed to
do so. The applicant is claiming $12,384.00 in order to reimburse the costs she has
outlaid to have the works rectified.
[4] The applicant lodged a complaint with the Queensland Building and Construction
Commission (‘QBCC’) and on 14 July 2023 received correspondence that there were
two substantiated findings against the respondent and a penalty infringement notice
for each was issued.
[5] The applicant made a claim to the Queensland Civil and Administrative Tribunal on
5 September 2023.
[6] A direction hearing was held on 11 December 2023 where directions were made that
the applicant was to supply further information and details regarding her claim. The
respondent was also directed to supply a response by 15 January 2024. The respondent
failed to do so. The directions state that should the applicant fail to comply with the
direction the applicant would be entitled to a final decision.
[7] A further directions hearing was held on 20 February 2024 seeking further
information from the applicant. The respondent had still not filed any materials.
[8] The applicant filed the requested material on 26 February 2024.
[9] The applicant states the respondent attended the site to meet with inspector and discuss
how to fix defects in the deck. The applicant states the respondent ignored emails and
text messages and failed to return.
[10] The applicant had an alternative builder complete the rectification works. The
applicant states she was also required to have plans drawn up which the respondent
failed to do, an engineer inspection, and lodgement with council incurring further fees.
[11] The applicant claims the amount of $12,384.00.
Jurisdiction
[12] QCAT has jurisdiction to hear domestic building disputes under the Queensland
Building and Construction Commission Act 1991 (‘QBCC Act’). Specifically, QCAT
can hear disputes involving:
Defective Building Work: Claims related to defective or incomplete building work.
Contractual Disputes: Issues arising from contracts for domestic building work,
including disputes over payment, delays, and variations.
Rectification Orders: Applications for orders requiring a builder to rectify defective
work.
[13] The relevant sections of the QBCC Act that outline QCAT's jurisdiction include:
Section 77: This section provides QCAT with the power to hear and decide building
disputes, including domestic building disputes.
Section 79: This section outlines the types of orders QCAT can make in relation to
building disputes, such as orders for rectification or completion of work.
-- 2 of 3 --
3
[14] In domestic building disputes, QCAT has the authority to make a variety of orders
under the QBCC Act. These orders can include:
(a) Rectification Orders: Directing a builder to rectify defective or incomplete
work.
(b) Completion Orders: Requiring a builder to complete unfinished work as per the
contract.
(c) Monetary Orders: Awarding compensation or damages to a party for losses
suffered due to defective or incomplete work.
(d) Contractual Orders: Modifying the terms of a contract, such as adjusting the
contract price or extending the time for completion.
(e) Specific Performance: Ordering a party to perform their contractual obligations.
(f) Rescission of Contract: Cancelling the contract and determining the rights and
obligations of the parties post-rescission.
[15] The respondent has failed to provide any information at all to assist the tribunal in its
decision. As such the applicant is entitled to final decision in the absence of any
materials.
[16] From the information provided, specifically the QBCC investigation it is the opinion
of the Tribunal that the work was both defective and incomplete.
[17] The applicant has provided information that confirms ample opportunity was provided
to the respondent to return to and rectify the workmanship. In fact, from text messages
supplied by the applicant it appears the respondent misled the applicant for quite some
time that he was willing to return to fix and complete the works and he was simply
awaiting the delivery of materials.
[18] The applicant has itemised the additional costs which include the works to bring the
deck into compliance with code, and extra associated plans, and applications. It would
appear in having this completed the applicant has acted reasonably and the costs
incurred are very normal and not excessive. The costs simply place the applicant in
the position they would have been had the works been carried out correctly in the first
place by the respondent.
[19] The applicant itemises her claim to include: works to complete deck $7,500.00, plans
$1320.00 and lodgement and certification $1584.00 totalling $12,384.00.
Orders
[20] The respondent is to pay the applicant the amount of $12,384.00 within 28 days of the
date of this order.
-- 3 of 3 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2024/607