Chau’s & Sons Pty Ltd t/as Holiday Air Conditioning and Refrigeration Qld v Karam [2024] QCAT 476
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Chau’s & Sons Pty Ltd t/as Holiday Air Conditioning and
Refrigeration Qld v Karam [2024] QCAT 476
PARTIES: CHAU’S & SONS PTY LTD TRADING AS
HOLIDAY AIR CONDITIONING AND
REFRIGERATION QLD
(applicant) (respondent in counter-application)
v
ANTHONY KARAM
(respondent) (applicant in counter-application)
APPLICATION NO/S: BDL101-22
MATTER TYPE: Building matters
DELIVERED ON: 31 October 2024
HEARING DATE: 31 January 2024
HEARD AT: Brisbane
DECISION OF: Senior Member Brown
ORDERS: Proceeding dismissed.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – PERFORMANCE OF
WORK – where counter-applicant had retained services of
counter-respondent to undertake the supply and installation
of an air conditioning unit pursuant to an oral contract ––
questions as to standard of workmanship by the counter-
respondent – circumstances where counter-respondent
attributes incomplete items to be outside the scope of the
oral agreement – whether performance of works regulated
by the Queensland Building and Construction Commission
Act 1991 (Qld)
LIMITATION OF ACTIONS – CONTRACTS, TORTS
AND PERSONAL ACTIONS – where works the subject
of the dispute were undertaken more than 6 years before
the application was filed – where extension of limitation
period not asserted in reasons for application – whether
assertion required – whether proceedings maintainable
Civil Liability Act 2003 (Qld) s 4, s 9, sched 2
Limitation of Actions Act 1974 (Qld) s 10
Queensland Building and Construction Commission Act
1991 (Qld) s 77, sch 1B
-- 1 of 17 --
2
Queensland Civil and Administrative Tribunal 2009 (Qld)
s 28,
Blackman v M & DJ Bossie Pty Ltd [1968] WAR 97
Brookfield Multiplex v Owners Corporation Strata Plan No
61288 [2014] HCA 36
Bryan v Maloney [1995] HCA 17
Caltex Oil (Aust) Pty Ltd v The Dredge Willemstad (1976)
136 CLR 529
Cerda v Jacob [2020] QCATA 57
McSwan & Anor v Weaver [2023] QCAT 148
Mikita v Kontek Constructions Pty Ltd [2024] QCAT 315
Woolcock Street Investments Pty Ltd v CDG Pty Ltd [2004]
HCA 16
APPEARANCES &
REPRESENTATION:
Applicant: Self represented
Respondent: Self represented
REASONS FOR DECISION
[1] In 2013 Chau’s installed an air-conditioning system (the system) in Mr Karam’s
residence. Mr Karam says that the system is defective.
[2] Proceedings relating to the dispute were first commenced by Chau’s as a minor civil
dispute in 2018 (Chau’s proceeding). Chau’s claimed that Mr Karam had not paid the
balance of the contract price. An adjudicator ordered Mr Karam to pay Chau’s
$8,846.60.1
[3] Mr Karam appealed the decision.
[4] On 3 June 2020 Mr Karam commenced a minor civil dispute proceeding against
Chau’s claiming damages for breach of contract (Mr Karam’s proceeding). The
proceeding was commenced by Mr Karam before the determination of his appeal. In
2021 Mr Karam’s proceeding was transferred to the building list.
[5] In 2022 the QCAT Appeal Tribunal set aside the adjudicator’s decision and remitted
Chau’s proceeding to the QCAT building list.2
[6] Chau’s proceeding and Mr Karam’s proceedings were subsequently consolidated with
Chau’s proceeding as the application and Mr Karam’s proceeding as the counter-
application.
[7] On 5 August 2022 Chau’s proceeding was dismissed for non-compliance by Chau’s
with the requirements of s 77(2) of the Queensland Building and Construction
Commission Act 1991 (Qld). The remaining proceeding is Mr Karam’s counter-
application which now falls to be determined.
1 MCD 60618/18, 23 April 2020.
2 Anthony Karam v Chau’s & Son Pty Ltd t/as Holiday Air Conditioning and Refrigeration Engineering
Qld (unreported), APL169-20, 30 March 2022.
-- 2 of 17 --
3
Mr Karam’s claim
[8] In the minor civil dispute application Mr Karam claimed the amount of $18,104.45 to
repair the system and a further amount of $28,316.20 for the cost of repairing damage
to his residence as a result of water leakage from the system. As is often the case in
Tribunal proceedings, the legal basis for the claim is not particularised.
[9] Mr Karam’s position is clarified to some extent in his statement of evidence.3 Mr
Karam says that the parties entered into a contract for the supply and installation of
the system and that Chau’s breached the contract ‘by failing to provide services to the
standard expected under the contract, notwithstanding the manufacture’s (sic)
installation guidelines and specifications, The Australian Standards and the QBCC
(Best Practice) and Contractor Licence.’
[10] In his statement Mr Karam particularises his claim as:
(a) Repairs to air-conditioning system $18,104.45
(b) Repairs to dwelling caused by water leaking $27,951.00
(c) Emergency service costs $ 550.00
(d) Repairs to dwelling and insurance excess $ 3,590.91
[11] Mr Karam also claims costs in the amount of $1,265.00.
Jurisdiction
[12] I am satisfied that Mr Karam is a building owner and that Chau’s was, at the relevant
time, a building contractor.4 I am satisfied that the work undertaken by Chau’s was
domestic building work5 and that the dispute between the parties is a domestic
building dispute.6 I am satisfied that before commencing the proceeding, Mr Karam
satisfied the requirements of s 77(2) of the QBCC Act.
Was there a contract between the parties?
[13] It is first necessary to determine whether the parties entered into an enforceable
contract.
[14] The building work, the subject of the dispute, was domestic building work. As the
contract price was more than $3,300 and less than $20,000 any contract between the
parties would be a level 1 regulated contract. By s 13(2) of schedule 1B of the
Queensland Building and Construction Commission Act 1991 (Qld) (QBCC Act), a
level 1 regulated contract must be in writing, dated and signed by the parties. If the
contract does not meet these minimum requirements, the contract is of no effect with
the result that the contract cannot be enforced by either party.
3 Statement of Anthony Karam filed 29 November 2022.
4 QBCC Act, schedule 2; It is noted that Chau’s QBCC licence was cancelled on 6 October 2020.
5 Ibid, schedule 1B, s 4(6).
6 Ibid.
-- 3 of 17 --
4
[15] At the conclusion of the hearing, the parties were directed to file submissions
addressing whether a contract complying with the requirements of s 13(2) of schedule
1B had been entered into.
[16] Mr Karam says that the parties did not enter into a complying contract. Mr Chau
agrees.
[17] The parties were also directed to file submissions addressing the application of the
Electronic Transactions (Queensland) Act 2001 (Qld). Section 14 of the ET Act
provides:
14 Requirement for signature
(1) If, under a State law, a person’s signature is required, the requirement is
taken to have been met for an electronic communication if—
(a) a method is used to identify the person and to indicate the person’s
intention in relation to the information communicated; and
(b) the method used was either—
(i) as reliable as appropriate for the purposes for which the
electronic communication was generated or communicated,
having regard to all the circumstances, including any
relevant agreement; or
(ii) proven in fact to have fulfilled the functions described in
paragraph (a), by itself or together with further evidence;
and
(c) the person to whom the signature is required to be given consents
to the requirement being met by using the method mentioned in
paragraph (a).
(2) The reference in subsection (1) to a law that requires a signature includes
a reference to a law that provides consequences for the absence of a
signature.
[18] Mr Karam’s submissions do not address the application of the ET Act. Mr Chau says
that the parties did not consent to the use of electronic communications between the
parties satisfying the requirements for the contract to be signed by the parties
electronically.
[19] I find that on 21 December 2012 Mr Karam forwarded to Chau’s by email a copy of
a quote Mr Karam had obtained from another contractor for the installation of the air-
conditioning system. That quote, from Energy Air dated 19 December 2012, detailed
two options, the first at a cost of $15,600.00 and the second for $16,500.00 (both
inclusive of GST).
[20] I find that on 21 December 2012, Chau’s responded by email advising Mr Karam that
it could match the quote provided by Energy Air and would forward a quotation to Mr
Karam.
[21] I find that on 21 December 2012, Mr Karam emailed Chau’s and instructed Chau’s to
proceed to install the air-conditioning system. Although not entirely clear from the
evidence it seems both parties understood that the scope of works was to be in
accordance with option 2 set out in the Energy Air quote. I find that when Mr Karam
emailed Chau’s on 21 December 2012 instructing the respondent to proceed with the
-- 4 of 17 --
5
installation of the air-conditioning system, Chau’s had not formalised a written quote
reflecting the earlier communications between the parties. I find that on 27 December
2021 Chau’s forwarded to Mr Karam a written quote bearing the same date. The
written quote:
(a) Was for an amount of $16,000 inclusive of GST;
(b) Provided for the following scope of works:
Supply and install 1 x Daikin FDYQ250, 25kW ducted system, including 2
controllers and 2 zones touch pad; 12 outlets;
Constant zone: living/kitchen with 2 outlets
Zone 1: Bed 1 with 1 outlet
Zone 2: Bed 2, 3 and 4 with 3 outlets
Zone 3: Study with 1 outlet
Zone 4: Guest with 1 outlet
Zone 3: Kitchen, dining, living and meals with 4 outlets
Warranty as follows:
Equipment: 5 years parts and labour
Zone motor: 5 year
Refrigerant: half year
Labour: 1 year
Ducting and outlets: 1 year
Rest of parts: eg copper, cable, 1 year
[22] It is unclear from the evidence why Chau’s quote was for an amount less than option
2 in the Energy Air quote when Chau’s had earlier advised Mr Karam that it would
match, as opposed to better, the Energy Air quote. In the end result, it is unnecessary
to determine the issue. I find that Mr Karam did not, in electronic form, communicate
acceptance of the quote to Chau’s.
[23] It follows from the foregoing that there was no written, dated and signed contract
entered into by the parties satisfying s 13(2) of schedule 1B of the QBCC Act. The
consequence of this finding is that there are no warranties implied by operation of the
QBCC Act. That leaves the issue of whether Mr Karam has a claim in negligence
against Chau’s.
Does Mr Karam have a claim in negligence?
[24] A domestic building dispute means, inter alia, a claim or dispute arising between a
building owner and a building contractor relating to the performance of reviewable
domestic work or a contract for the performance of reviewable domestic work.7 A
domestic building dispute also means a claim or dispute in negligence, nuisance or
trespass related to the performance of reviewable domestic work other than a claim
for personal injuries.8 The definition of ‘domestic building dispute’ as meaning, inter
alia, a ‘claim or dispute arising between a building owner and a building contractor
relating to the performance of reviewable domestic work’ is couched in sufficiently
broad language to capture a claim in negligence by a building owner against a building
contractor who would, but for the operation of schedule 1B, have an enforceable
7 QBCC Act, schedule 2, definition of ‘domestic building dispute’.
8 Ibid.
-- 5 of 17 --
6
contractual relationship. And there is no doubt that such a claim is captured by ‘a
claim or dispute in negligence, nuisance or trespass related to the performance of
reviewable domestic work other than a claim for personal injuries.’
[25] The law of negligence in Australia as it relates to claims for pure economic loss arising
out of building work has developed over the past several decades since the decision
of the High Court in Bryan v Maloney.9 I do not propose to embark upon a detailed
exposition of the relevant authorities. Rather, I will confine consideration of the issue
principally to two recent decisions of the Tribunal: McSwan & Anor v Weaver10 and
Mikita v Kontek Constructions Pty Ltd.11 In each of these matters, the Tribunal
considered whether, in the absence of an enforceable building contract, a building
owner was entitled to bring a claim in negligence against a building contractor. In
both matters, the Tribunal undertook a detailed analysis of the development of the law
of negligence in the context of building disputes.
[26] Prior to the decisions in McSwan and Mikita, the Appeal Tribunal in Cerda v Jacob12
held that a homeowner was entitled to bring a claim in negligence against a building
contractor for damages for defective building work. The Appeal Tribunal did not
undertake a detailed consideration of the decisions of the High Court in Bryan v
Maloney13, Woolcock Street Investments Pty Ltd v CDG Pty Ltd14 and Brookfield
Multiplex v Owners Corporation Strata Plan No 6128815 and specifically whether the
homeowner was ‘vulnerable’, neither party having made submissions on the issue of
whether and to what extent the builder owed a duty of care to the homeowner.
McSwan & Anor v Weaver
[27] The McSwans engaged Mr Weaver to construct a carport at their residence. The
parties did not enter into a contract satisfying the requirements of schedule 1B of the
QBCC Act. The McSwans said that the colour of the as constructed carport roof was
incorrect. The carport was otherwise entirely free of defects.
[28] The tribunal stated:
As I understand it, the current state of the law is that a builder does not owe a
duty of care to an original owner of a building which the builder has constructed
for the owner. This is because the owner is not vulnerable to loss occasioned by
any wrong that might be committed in construction of that building in terms of
defective work. The reason being that the home owner is not vulnerable in the
sense of loss because the owner is able to protect itself from such loss by the
means of a building contract.16
[29] Central to the reasoning of the tribunal were the decisions of the High Court of
Australia in Woolcock Street Investments Pty Ltd v CDG Pty Ltd17 and Brookfield
Multiplex v Owners Corporation Strata Plan No 61288.18 In those decisions, the High
9 [1995] HCA 17 (‘Bryan’).
10 [2023] QCAT 148.
11 [2024] QCAT 315 (‘Mikita’).
12 [2020] QCATA 57.
13 n 9.
14 [2004] HCA 16 (‘Woolcock’).
15 [2014] HCA 36 (‘Brookfield’).
16 At [61].
17 Woolcock (n 14).
18 Brookfield (n 15).
-- 6 of 17 --
7
Court decided that proximity was no longer the guiding test for liability in cases where
a duty of care was alleged to have been breached in cases involving pure economic
loss arising out of the performance of building work. Rather, the question is whether
an individual is ‘vulnerable’ in the sense that an individual is unable to protect itself
from the consequences of a defendant’s want of reasonable care, either entirely or at
least in a way which would cast the consequences of loss on the defendant.19
[30] The tribunal found that the McSwans were able to protect themselves from the
consequences of Mr Weaver’s lack of care in undertaking the construction of the
carport by entering into a contract meeting the requirements of schedule 1B of the
QBCC Act. On this basis, reasoned the tribunal, the McSwans were not ‘vulnerable’
and were therefore not able to pursue a claim in negligence against Mr Weaver.
Mikita v Kontek Constructions Pty Ltd
[31] Kontek performed concreting work at Mr Mikita’s residence. Mr Mikita claimed that
the work was defective. The tribunal found that the requirements of schedule 1B of
the QBCC Act had not been met with the consequence that there was no enforceable
contract between the parties.
[32] The tribunal considered whether Mr Mikita was entitled to bring a claim in negligence
against Kontek and considered the various authorities referred to in McSwan. Contrary
to the determination in McSwan, the tribunal in Mikita found that a duty of care may,
in particular cases, arise between a building contractor and a homeowner despite a
failure to comply with the statutory requirements of a regulated contract.20
[33] The tribunal held:
(a) None of the relevant authorities relied upon by the tribunal in McSwan involved
a case where the parties were in a direct contractual relationship (or would have
been but for the restrictions imposed by statute);
(b) The law recognises concurrent duties in contract and in tort in circumstances
involving the performance of professional work and this would encompass a
professional builder or professional trade contractor;
(c) A duty of care may exist in the absence of a contractual relationship;
(d) The existence of an assumption of responsibility by a builder (or building
contractor) and known reliance or dependence by the homeowner is capable of
giving rise to a duty of care in tort, at least in cases involving a claim by an
owner of residential premises and the absence of a detailed building contract
between the parties governing the quality of work (including warranties);
(e) Relevant policy considerations included:
(i) The QBCC Act permits a claim in negligence in respect of both domestic
building disputes and commercial building disputes evidencing a
legislative intention that such claims are not confined to the exercise of
contractual rights;
19 Woolcock (n 14) at 530.
20 Mikita (n 11) at [26].
-- 7 of 17 --
8
(ii) While the QBCC Act imposes a penalty on a building contractor who fails
to comply with the relevant requirements before commencing work, no
such penalty is imposed on a building owner;
(iii) A regulated contract will only be denied effect by operation of the QBCC
Act in circumstances where the building contractor carries out domestic
building work in the absence of a compliant regulated contract;
(iv) While a regulated contract has effect only if it complies with the
requirements of schedule 1B of the QBCC Act, it is relevant if the contract
does not call for the commission of any illegality and the QBCC Act does
not prohibit a particular act essential for carrying out the contract.
[34] The tribunal considered that while the operation of s 14 of schedule 1B (and by
analogy for present purposes, s 13) was relevant to the issue of vulnerability, other
relevant matters were:
(a) The builder’s statutory obligations under s 30 of schedule 1B of the QBCC Act;
(b) Whether or not the homeowner was aware of the statutory requirements of s 14
(and, by analogy, s 13);
(c) Any evidence of an assumption of responsibility and reasonable reliance.
[35] The tribunal considered that a homeowner would be vulnerable in circumstances
where:
(a) the homeowner is unaware of the statutory requirements of s 14 (or s 13);
(b) the contractor assumes responsibility to perform the agreed work to the standard
expected of a reasonably competent professional building contractor
undertaking work of that kind; and
(c) the homeowner relies on the contractor’s skill or expertise.
Consideration
[36] The common law generally does not permit the recovery of damages for economic
loss that is not a consequence of injury to a claimant’s person or property.21 However
in certain cases a person may owe a duty to take reasonable case to avoid causing
purely economic loss.22
[37] The common law recognises that, generally speaking, the builder of premises has a
duty to take reasonable care to avoid injury, as a result of defects in premises, to those
persons or their property who may foreseeably suffer injury if care is not taken.23
[38] In Bryan v Maloney24 the High Court recognised the special relationship between a
building contractor and a building owner for whom building work is undertaken:
On the other hand, there are strong reasons for acknowledging the existence of
a relevant relationship of proximity between a builder such as Mr Bryan and a
first owner such as Mrs Manion with respect to the kind of economic loss
21 Caltex Oil (Aust) Pty Ltd v The Dredge Willemstad (1976) 136 CLR 529.
22 Caltex Oil (Aust) Pty Ltd v The Dredge Willemstad (1976) 136 CLR 529.
23 Blackman v M & DJ Bossie Pty Ltd [1968] WAR 97.
24 Bryan (n 9).
-- 8 of 17 --
9
sustained by Mrs Maloney. In particular, the ordinary relationship between a
builder of a house and the first owner with respect to that kind of economic loss
is characterized by the kind of assumption of responsibility on the one part (i.e.
the builder) and known reliance on the other (i.e. the building owner) which
commonly exists in the special categories of case in which a relationship of
proximity and a consequent duty of care exists in respect of pure economic loss.
There is nothing to suggest that the relationship between Mr Bryan and Mrs
Manion was not characterized by such an assumption of responsibility and such
reliance.25 (emphasis added)
[39] The Court in Bryan v Maloney recognised that, in the context of domestic building
work, the duty of care owed by a building contractor to the owner was concurrent in
contract and tort:
Mr Bryan and Mrs Manion were the parties to a contract in relation to the
building of the house. Whatever may have been the position in earlier times, the
existence of such a contractual relationship between builder and client did not
preclude the existence either of a relationship of proximity between them in
relation to that work or of a consequent duty of care under the ordinary law of
negligence.26
[40] While the High Court has, since Bryan v Maloney27, made clear that proximity is no
longer the guiding principle in determining the existence of a duty of care, the aspect
of the judgement dealing with the relationship between a building contractor and a
building owner for whom domestic building work has been undertaken has not been
overruled.
[41] If the particular circumstances of a case fall into one of the established categories of
duty of care it is unnecessary for an applicant to prove that the respondent owed a
duty.28 This is what the High Court was referring to in Bryan v Maloney and the
‘special categories of case’. Where however a novel set of circumstances arises, it is
necessary for an applicant to prove that the respondent owed a duty of care. In Caltex
Refineries (Qld) Pty Ltd v Stavar it was stated:
This rejection of any particular formula or methodology or test the
application of which will yield an answer to the question whether there exists
in any given circumstance a duty of care, and if so, its scope or content, has
been accompanied by the identification of an approach to be used to assist in
drawing the conclusion whether in novel circumstances the law imputes a duty
and, if so, in identifying its scope or content. If the circumstances fall within
an accepted category of duty, little or no difficulty arises. If, however, the
posited duty is a novel one, the proper approach is to undertake a close
analysis of the facts bearing on the relationship between the plaintiff and the
putative tortfeasor by references to the “salient features” or factors affecting
the appropriateness of imputing a legal duty to take reasonable care to avoid
harm or injury.29 (emphasis added)
25 Bryan (n 9) [9].
26 Bryan (n 9) [14].
27 Bryan (n 9).
28 Caltex Refineries (Qld) Pty Ltd v Stavar (2009) 75 NSWLR 649.
29 Ibid at 677.
-- 9 of 17 --
10
[42] The salient features approach to determining, in novel cases, whether a duty of care is
owed by a potential tortfeasor was referred to by the High Court in the recent decision
of Mallonland Pty Ltd v Advanta Seeds Pty Ltd 30:
In Sullivan v Moody, the Court observed that "[d]ifferent classes of case give
rise to different problems in determining the existence and nature or scope, of a
duty of care ... The relevant problem will then become the focus of attention in
a judicial evaluation of the factors which tend for or against a conclusion, to be
arrived at as a matter of principle." Since Sullivan v Moody, other than in cases
involving an assumption of responsibility, determining whether the relationship
between the parties gives rise to a duty of care to avoid causing pure economic
loss has been understood in Australia to involve such an evaluation. This
"salient features" approach, as it is now known, has attracted significant
academic and judicial criticism. (footnotes omitted)
[43] The ‘salient features’ approach referred to in Mallonland involves a consideration of
a range of matters in determining whether a duty of care arises. One of those matters
is vulnerability to harm. Where however the relationship between the relevant parties
is one involving an assumption of responsibility, the salient features approach to
determining the existence of a duty of care does not arise for consideration.
[44] In domestic building cases involving the original parties to the building work, as
recognised in Bryan v Maloney, there is an assumption of responsibility on the part of
the building contractor. Accordingly, consideration of the vulnerability of the building
owner in determining the existence of a duty of care is not required. This was
recognised by Edelmann J in Mallonland albeit in the context of a subsequent
purchaser:
It suffices to say that if there were truly an assumption of responsibility in Bryan
v Maloney, then any reference to "vulnerability" would be superfluous and
confusing at best.
[45] Edelemann J’s comment has direct application in circumstances where the building
contractor and the building owner are in a direct relationship.
Conclusion of duty of care
[46] The relationship between Chau’s and Mr Karam was characterized by an assumption
of responsibility by Chau’s and known reliance by Mr Karam. The relationship falls
within one of the special categories of cases in which a duty of care is owed. I find
that Chau’s owed to Mr Karam a duty to undertake the works in an appropriate and
skilful way, with reasonable care and skill and free from defects.
Did Chau’s breach the duty of care owed to Mr Karam?
[47] It is not contentious that by the time Mr Karam and his family moved into the house
on 23 December 2013, Chau’s had completed the installation of the air-conditioning
system but for the commissioning of the system which Chau’s did not undertake as
Mr Karam did not pay the balance of the monies owed to Chau’s.
[48] I accept Mr Karam’s evidence that on 25 December 2013 the system repeatedly
tripped the main power to the house and logging errors appeared on the system touch
30 [2024] HCA 25.
-- 10 of 17 --
11
panel and that Mr Karam attempted to contact Chau’s to address the issues without
success.
[49] I accept Mr Karam’s evidence that on 29 December 2013 an alternative contractor,
Air Smart Air Conditioning Pty Ltd, attended at the residence to investigate Mr
Karam’s complaints. There is no statement of evidence from a representative of Air
Smart Air Conditioning Pty Ltd nor was any person called to give evidence at the
hearing. I therefore approach with some caution Mr Karam’s evidence about what he
was told by the contractor. Mr Karam’s evidence was that on two subsequent
occasions, in January and February 2014, the contractor returned to the house to
investigate and address the issues raised by Mr Karam. I accept Mr Karam’s evidence
in this regard.
[50] Mr Karam says that in January 2014 he was told by Air Smart that the system had a
major air leak in the ceiling cavity and that the return air ducting was not connected
to the return air grill resulting in the indoor unit of the system drawing hot air from
the ceiling cavity rather than the air circulating in the house. The result of this, Mr
Karam says he was told, was that the system temperature gauge gave a false reading
causing the system to constantly operate. Mr Karam says that he was told by the
contractor that the installation of the return air grill was not compliant with the
manufacturer’s specification and required immediate replacement. Mr Karam’s
evidence about what he was told by the contractor is hearsay. The Tribunal is not
bound by the rules of evidence other than the extent to which the Tribunal adopts
those rules.31 In the present circumstances, the question is not of one admissibility but
rather of the weight to be given to the evidence of Mr Karam. Mr Karam’s evidence
in relation to the matters to which I have referred was not challenged at the hearing. I
found Mr Karam and Mr Chau to both be truthful witnesses who did their best to give
an accurate recounting of the relevant events albeit from their respective perspectives.
I accept the evidence of Mr Karam about what he was told by the contractor.
[51] Mr Karam’s evidence, which I accept, is that the manufacturer of the system attended
at the premises in February 2014 to investigate issues relating to what Mr Karam says
were outdoor unit error logs. Mr Karam says that this was found to be the result of
Chau’s not inputting the correct settings on the outdoor unit. It should be noted that
there is no evidence from the manufacturer to support Mr Karam’s assertion.
[52] Mr Karam says that in or about January or February 2014 Chau’s returned to the
residence to replace the return air ceiling mounting resulting in substantial damage to
the surrounding gyprock. Mr Karam says that he told Mr Chau that he was extremely
unhappy with the quality of Chau’s work.
[53] Following this, Mr Karam says that the system failed to adequately cool the house
with the issue remaining an ongoing one. I accept Mr Karam’s evidence in this regard.
I find that after February 2014 Mr Karam did not call upon Chau’s to investigate the
ongoing issues with the system.
[54] Mr Karam engaged an air conditioning specialist company, BNE Air Service Pty Ltd,
to investigate the issues with the system. BNE prepared a report.32 The report is
undated. The author of the report did not give evidence at the hearing although the
principal of BNE did. The report was filed by Mr Karam in the original minor civil
31 QCAT Act, s 28(3)(b).
32 Appendix 14 to exhibit 2.
-- 11 of 17 --
12
dispute proceeding brought by Chau’s. I am therefore satisfied that the report came
into existence some time in 2018.
[55] The salient findings contained in the report may be summarised as follows:
(a) Zone controller on the first floor of the residence not securely fastened;
(b) The condition of the piping system was compromised, with the liquid line not
being insulated within the ceiling space adjacent to the indoor unit. This resulted
in sweating on the pipework which dripped and marked the ceiling;
(c) It was not possible to inspect the full extent of the pipework which was
predominantly situated within finished ceiling areas, walls and in-slab;
(d) The condition of the ducting was compromised. Leakage apparent from air
readings indicated that the supply air ducting was either incorrectly joined,
damaged, cut and/or severely squashed;
(e) The leakage was likely present somewhere between the ground floor and the
upper floor however without some demolition work being undertaken this was
not able to be verified;
(f) The zone controllers and motorised dampers were operating as intended;
(g) The first floor airflow readings indicated an acceptable level of air leakage;
(h) The ground floor airflow readings indicated an excessive level of leakage;
(i) Supply air leakage results in higher volumes of non-air conditioned air being
drawn back through the indoor unit resulting in the system working harder to
condition the air which in turn results in the supply air not reaching the intended
zone in the residence, being wasted in the ceiling void and/or ceiling cavity
depending on the site of the leakage;
(j) The result of the above would be higher than usual power usage and the system
being unable to adequately cool the relevant parts of the residence;
[56] The report recommends the following further work:
(a) Fasten upper floor zone controller: cost of work $56.00;
(b) Insulate liquid line – recover system refrigerant, disconnect pipe, insulate,
reconnect pipe, vac out and test, recharge refrigerant: cost of work $807.00;
(c) Cut access to inspect the insultation of the remainder of the piping system and
the piping system in general, patch and repaint: cost of work $2,160.00 to
$3,160.00;
(d) Locate and repair air leakage in supply ductwork, remove ceilings and walls for
vertical sections of ductwork, locate leakage, repair or replace, re-balance
system once complete, patch and repaint: cost of work $5,200.00 to $11,720.00;
(e) In addition to the above costings, and allowance for overhead recovery and
profit of 15% should be added totalling $1,233.45 to $2,361.45.
[57] Mr Paul McTigue gave evidence at the hearing. Mr McTigue is the principal of BNE.
Mr McTigue did not inspect the works or prepare the report. His evidence was
therefore, at least in large part, a desktop evaluation of the report.
-- 12 of 17 --
13
[58] Mr McTigue’s evidence, which I accept, was that the costings contained in the BNE
report were inclusive of both work to be undertaken by an air-conditioning technician
and any required building work. Mr McTigue’s evidence, which I accept, was that
allowing for increases in costs since the report was prepared, the cost of the
recommended work would currently be 30% to 50% more than estimated in the report.
[59] It is appropriate to pause here to note that one of Mr Karam’s main complaints
regarding the work undertaken by Chau’s was that the unit installed in the ceiling
cavity of the house did not have a drip tray positioned beneath it. It was Chau’s
position that the agreement between the parties did not require it to install a drip tray.
[60] Mr McTigue’s evidence was that the installation of a drip tray was a safety feature to
catch condensate. Mr McTigue stated that if the unit could be installed without leakage
from the pipework and with a pipe effectively taking the moisture out of the ceiling
cavity the need for a drip tray would be obviated. Mr McTigue’s evidence was that if
cold air was not getting to areas it was supposed to get to the system was not doing its
job. He stated that the system was not capable of self diagnosis and that air flow
leakages would not appear as errors on the system control pads.
[61] I accept Mr McTigue’s evidence whose expertise as a licensed contractor engaged in
the design and installation of air conditioning units was not challenged. While Mr
McTigue did not inspect the works it was apparent that he had carefully reviewed the
contents of the BNE report and gave truthful and considered evidence.
[62] While Ms Chau, who appeared for Chau’s at the hearing, cross-examined Mr
McTigue at length, his opinions remained unchanged.
[63] The principal of Chau’s, Mr Chau, gave evidence at the hearing. Mr Chau’s evidence
was that, but for commissioning the system, the installation of the system had been
completed. Mr Chau’s evidence was that commissioning the system involved turning
on the system and running it and ensuring that the system was operating correctly.
[64] Mr Chau’s evidence at the hearing was that the pipes as installed were insulated. He
said the issues with condensation and water staining were the consequence of Mr
Karam’s failure to have the system regularly serviced. Mr Chau stated was unable to
say what the cause of the water damage in the residence was.
[65] A statement by Mr Chau was in evidence.33 Mr Chau stated that the system ‘was not
working at all time (sic) as it was not fully commissioned’. This evidence is not
consistent with Mr Chau’s oral evidence at the hearing that the physical installation
of the system had been fully completed and that the commissioning of the system
involved turning it on and monitoring it to ensure that the system was operating
correctly. Mr Chau says in his statement that ‘a reasonable person should not and
would not use an air conditioning units/system that is not completely installed and
should have known that it would not function properly.’ This evidence is, again,
inconsistent with the oral evidence given by Mr Chau at the hearing. Mr Chau goes
on to say in his statement that Mr Karam was ‘clearly aware that the air conditioning
was not completely installed and is not working. As a result (Mr Karam) contracted
… Air Smart to complete the installation of the air conditioning units.’ I do not accept
this evidence. I accept the evidence of Mr Karam that he only contacted Air Smart to
attend at the premises to investigate the system when he became aware of issues with
33 Exhibit 4.
-- 13 of 17 --
14
the operation of the system. On Mr Chau’s own evidence, this was after the system
had been fully installed by Chau’s save for the system being commissioned.
[66] As to the issues raised in the BNE report, Mr Chau attributes the air flow issues to the
system not having been fully installed and therefore ‘air balancing’ could not be
undertaken. No explanation is provided by Mr Chau as to what is meant by ‘air
balancing’ and, as I have found, the system had been fully installed but for the
commissioning. As to the cause of the air flow issues including leakage, I prefer the
evidence contained in the BNE report and the oral evidence of Mr McTeague to the
evidence of Mr Chau. Mr Chau also says that the issues associated with air balancing
and air leakage are attributable to the design of the building. Mr Chau says that the
defective design resulted in no available access to service the air conditioning duct
works. It is uncontroversial that Chau’s was responsible for the design of the air
conditioning system. And it is uncontroversial that at the time the system was designed
the residence had not been constructed. There is no evidence from Chau’s that it was
not provided with the relevant documentation including plans and specifications for
the residence at the time it designed the system. Nor is there any evidence from Chau’s
that the plans and/or specifications changed after it had designed the system.
Accordingly, any access issues as referred to in Mr Chau’s evidence should have been
identified by Chau’s at the time it designed the system and certainly before the system
was installed.
[67] In order to determine whether Chau’s breached the duty of care it owed to Mr Karam
it is necessary to turn to the provisions of the Civil Liability Act 2003 (Qld) (CLA).
The CLA applies to any civil claim for damages for harm.34 ‘Harm’ includes
economic loss.35
[68] A person does not breach a duty to take precautions against a risk of harm unless: the
risk was foreseeable (that is, it is a risk of which the person knew or ought reasonably
to have known); the risk was not insignificant; in the circumstances, a reasonable
person in the position of the person would have taken the precautions.36 In deciding
whether a reasonable person would have taken precautions against a risk of harm, the
Tribunal is to consider the following (among other relevant things): the probability
that the harm would occur if care were not taken; the likely seriousness of the harm;
the burden of taking precautions to avoid the risk of harm; the social utility of the
activity that creates the risk of harm.37
[69] In this case the relevant risk is that Mr Karam would suffer loss and damage if Chau’s
did not undertake the installation of the air-conditioning system in an appropriate and
skilful way and with reasonable care and skill, free from defects. Clearly the risk was
not insignificant.
[70] It is self evident that if Chau’s failed to take care in undertaking the installation of the
system, Mr Karam would suffer loss in being required to have the defects rectified at
his cost. Mr Karam was likely to incur significant expense in addressing the
consequences of Chau’s failure to exercise reasonable care and skill in installing the
system. There was no additional burden imposed upon Chau’s to take precautions to
avoid the risk of harm to Mr Karam. Chau’s as a competent and experienced building
34 CLA, s 4(1).
35 CLA, schedule 2.
36 CLA s 9(1).
37 CLA, s 9(2).
-- 14 of 17 --
15
contractor, was required to undertake the installation of the system appropriately and
without defects.
[71] As is apparent from these reasons, but for the breach of duty by Chau’s, the defects in
the system would not have been apparent and Mr Karam would not have suffered loss
in being required to expend monies in rectifying the defects.38 The defects were the
direct result of the way in which Chau’s undertook the installation of the system.39
[72] In making these findings I accept the evidence contained in the BNE report and the
evidence of Mr McTeague.
[73] I am therefore satisfied that Chau’s breached the duty of care it owed to Mr Karam in
undertaking the installation of the air-conditioning system.
The application of the Limitation of Actions Act 1974 (Qld)
[74] Chau’s has raised the application of the Limitation of Actions Act 1974 (Qld) (LAA)
as a defence to Mr Karam’s claim.
[75] I have found that there was no contract between the parties having effect. The
consequence of this is that there was no regulated contract between the parties and no
implied warranties and therefore Mr Karam has no claim for breach of contract nor
for breach of the statutory warranties.
[76] That leaves only the claim for breach of duty.
[77] By s 10(1)(a) of the LAA an action founded on tort (ie breach of duty) cannot be
brought after the expiration of 6 years from the date on which the cause of action
arose. The position in Queensland in relation to when the cause of action accrues in
cases involving claims for breach of duty resulting in pure economic loss is
summarised in the following passage from Melisavon v Springfield Land
Development Corporation Pty Limited:
Ordinarily, a cause of action for tortious negligence is complete when there is
any manifestation of damage which is ultimately found to be connected to the
alleged negligence. But it is at least arguable that this is a case of pure economic
loss where in Australia that principle has been modified. The incremental
development in Pullen of the legal principles established in Hawkins v Clayton
has been followed in a number of jurisdictions. Until the High Court says
otherwise, the cause of action in the present case was complete when the
respondent suffered economic loss, that is, when the respondent had actual
knowledge of the appellant's faulty engineering design or when the faulty design
itself became manifest or could be discovered by reasonable diligence.40
[78] It is apparent from the evidence that Mr Karam was aware of problems with the air-
conditioning system from the time he and his family moved into the residence in
December 2013. Unlike the various latent building defect cases including Melisavon
and the authorities referred to in that decision, it was known to Mr Karam from 23
December 2013 that the air-conditioning system was not operating as intended. By 9
January 2014 Mr Karam knew, as a result of investigations undertaken by Air Smart
Air Conditioning Pty Ltd, that the return air ducting had not been connected to the
return air grill and that the installation of the return air grill had not been undertaken
38 CLA, s 11(1)(a).
39 CLA, s 11(1)(b).
40 [2014] QCA 33 per McMurdo P with whom Ann Lyons J agreed.
-- 15 of 17 --
16
in accordance with the manufacturer’s specification and that the work undertaken by
Chau’s was ‘dangerous and poor workmanship of the highest order.’41 At this time
Mr Karam was also made aware by Air Smart of other leaks in the system including
substantial leaks in the ducting penetrations.42 Further, by 12 February 2014 Mr
Karam was advised by Air Smart that the copper piping in the system did not have
insulation and that major air leaks from the system remained in the ceiling and the
penetrations.
[79] Accordingly, I find that, at the latest, by 12 February 2014 Mr Karam was aware of
the defects in the air-conditioning system and knew, or ought to have known, that
these defects were attributable to the work undertaken by Chau’s. Alternatively, I am
satisfied that by 12 February 2014 Mr Karam could, by reasonable diligence, have
discovered the defective work undertaken by Chau’s. In light of the foregoing I find
that the Mr Karam’s cause of action against Chau’s for breach of duty had accrued by
12 February 2014. By operation of s 10(1)(a) of the LAA, proceedings by Mr Karam
against Chau’s for breach of duty should have been commenced by 12 February 2020.
Mr Karam commenced proceedings against Chau’s by Application for minor civil
dispute filed 3 June 2020. Accordingly the proceedings were not commenced within
the period of limitation and by operation of s 10(1)(a) of the LAA, the proceeding is
statute barred and must be dismissed.
Assessment of damages
[80] In case I am wrong in concluding that Mr Karam’s claim is barred by operation of the
LAA I make the following findings about Mr Karam’s claim for damages:
(a) I accept the evidence contained in the BNE report and the evidence of Mr
McTeague and find that the following rectification work is required to remediate
the defective work undertaken by Chau’s:
(i) Fasten upper floor zone controller: cost of work $56.00;
(ii) Insulate liquid line – recover system refrigerant, disconnect pipe, insulate,
reconnect pipe, vac out and test, recharge refrigerant: cost of work
$807.00;
(iii) Cut access to inspect the insultation of the remainder of the piping system
and the piping system in general, patch and repaint: cost of work
$2,160.00 to $3,160.00;
(iv) Locate and repair air leakage in supply ductwork, remove ceilings and
walls for vertical sections of ductwork, locate leakage, repair or replace,
re-balance system once complete, patch and repaint: cost of work
$5,200.00 to $11,720.00;
(v) In addition to the above costings, and allowance for overhead recovery
and profit of 15% should be added totalling $1,233.45 to $2,361.45.
(b) I accept the evidence of Mr McTeague that the cost estimates in the BNE report
should be increased by 30% to 50% to account for cost increases since the report
was prepared. I adopt a mid point of 40%;
41 Statement of evidence of Anthony Karam.
42 Ibid.
-- 16 of 17 --
17
(c) In respect of items (iii), (iv) and (v) above, I also adopt a mid point in the
estimates. There is no science to this approach, but rather an attempt to arrive at
a fair and equitable outcome in circumstances where a range of figures has been
provided.
[81] I assess damages as follows using the item numbers referred to above:
(i) $56.00
(ii) $807.00
(iii) $2,660.00
(iv) $8,460.00
$11,983.00
add 40% $16,776.20
(v) Add 15% $ 19,292.63
[82] The total assessment of damages is $19,292.63.
Conclusion
[83] The proceeding is dismissed.
-- 17 of 17 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2024/476